VOLTAGE DROP SPREADSHEET SINGLE OR THREE PHASE

PROJECT: DATE 3/29/94


UNION CREEK CAMPGROUND VOLTAGE DROP

ENTER DATA HERE CALCULATED


LOAD KVA PHASE Voltage Power Factor Length WIRE SIZE R X CURRENT VOLTS
1 OR 3 L-L KV 0.5-1.0 KFT AWG OHM/KFT OHM/KFT AMPS DROP

Generator to RV based
on 24A load @120VAC 5.52 1 0.23 0.90 0.15 #10 1.200 0.050 24.00 7.93

Generator to RV based
on 24A load @120VAC 5.52 1 0.23 0.90 0.15 #8 0.780 0.052 24.00 5.22

Generator to RV based
on 24A load @120VAC 5.52 1 0.23 0.90 0.15 #6 0.490 0.051 24.00 3.34
0.00 3 0.48 0.90 0.10 #8 0.000 0.000 0.00 0.00
0.00 3 0.48 0.90 0.10 #8 0.000 0.000 0.00 0.00
CULATED
%
VDROP

3.45%

2.27%

1.45%
0.00%
0.00%