Drill Scenario
Some scaffolders were in process of scaffold installation/modification at level 3 module ESS-300.
At approximately 13.30 hrs, one of scaffolders lost his footing and fell down out side module. He was
hanging with body harness and in conscious condition. (IP-hanging was performed by dummy)
His co-worker shouted out for help, and another co-worker sought for their foreman/supervisor to
inform the incident.
Once after received the information the foreman/supervisor notified the incident to EAS/ Project HSE
Lead (by radio) then proceeded to the scene and found IP was hanging in conscious condition.
Project HSE Lead/Emergency Active Support (EAS) notified the incident to Site Incident
Controller (SIC)/ FIRST Coordinator by radio.
SIC instructed EAS to activate all ERT team (FIRST).
EAS notified Emergency Situation and instructed all ERT team/ FIRST to switch radio to channel-
1, then EAS activated FIRST (including rescue team, paramedic team, ambulance, security
personnel, etc).
EAS performed coordination of ERT mobilization.
EAS notified the incident to PT. SMOE-HSE Dept and to Siemen’s HSE Coordinator. (by
radio/phone).
First aiders, safety personnel on site arrived at the scene then secured the area, and continued
communicating with IP to keep IP conscious.
Security-Crowd Control arrived at the scene, and performed crowd-control and trafic .
Rescue team arrived and proceeded to the scene and performed rescue (using tripod to lower
down IP to ground).
Ambulance and paramedic team arrived and proceeded to the scene (at ground area).
First Aiders caught the IP after landed on the ground, and paramedic team performed medical
examination and treatment.(After dummy landed on the ground, IP was performed by a
worker)
Paramedic team notified to EAS that IP should be evacuated to Medical Center for further medical
treatment. First aider and paramedic team evacuated IP to ambulance.
Ambulance left the scene.
Ambulance arrived at Clinic.
Doctor reported IP condition to EAS.
EAS notified to SIC that IP had successfully been evacuated to Clinic and had got medical
treatment by doctor. (emergency situation was over).
SIC instructed to EA to give ‘clear signal’ and deactivate the ERT team.
EAS gave clear signal and deactivated the whole ERT team..
End of the drill
Actions by Crowd:
Dispatched immediately to the scene of the incident.
Understood the type of emergency and what immediate Actions was required.
Controled vehicle movement around the scene of the incident (especially for the ambulance).
Performed crowd control, including traffic control.