Brief Summary
Length of Line : S/C (22.7 + 21.09 km) and D/C (7.6 + 7.6 km)
Signing of
Contract Agreement : 14-12-2017
Page No. 1
Lot-I (ADB-108-2017):
1. Construction/Site Progress
Tower No./
Sr. Till Date Percentage Percentage Physical
Activity Description Locations/
No. Progress Progress Weightage Achieved
km
1 No. of Bore Holes 18 18 100% 10% 10%
Tower stacking /
released for
70 70 100% 3% 3%
Foundation
2 Construction
Tower Foundations
19+51 19+51 100% 44% 44%
Concrete + Piling
Pile Cap 51 51 100% 6% 6%
3 Tower Erection 70 68 97.14% 15% 14.57%
Stringing of
21.27 87.46% 13% 11.37%
Conductor
Pulling of
4 24.32 19.27 79.24% 4% 3.17%
OPGW
Pulling of
18.39 75.62% 3% 2.27%
Shield Wire
Testing &
5 - 2% 0%
Commissioning
Total To date Progress in % 100% 94.38%
Page No. 2
Lot-II (i) (ADB-108-2017):
2. Construction/Site Progress
Tower No./
Sr. Till Date Percentage Percentage Physical
Activity Description Locations/
No. Progress Progress Weightage Achieved
km
1 No. of Bore Holes 21 21 100% 10% 10%
Tower stacking /
released for
62 62 100% 3% 3%
Foundation
2 Construction
Tower Foundations
44+18 44+18 100% 44% 44%
Concrete + Piling
Pile Cap 18 18 100% 6% 6%
3 Tower Erection 62 61 98.39% 15% 14.75%
Stringing of
19.78 93.79% 13% 12.19%
Conductor
Pulling of
4 21.09 17.19 81.51% 4% 3.26%
OPGW
Pulling of
16.23 76.96% 3% 2.31%
Shield Wire
Testing &
5 - 2% 0%
Commissioning
Total To date Progress in % 100% 95.51%
Page No. 3
Lot-II (ii) (ADB-108-2017):
3. Construction/Site Progress
Tower No./
Sr. Till Date Percentage Percentage Physical
Activity Description Locations/
No. Progress Progress Weightage Achieved
km
1 No. of Bore Holes 8 8 100% 10% 10%
Tower stacking / released
27 27 100% 3% 3%
for Foundation Construction
2 Tower Foundations
20+7 20+7 100% 44% 44%
Concrete + Piling
Pile Cap 7 7 100% 6% 6%
3 Tower Erection 27 27 100% 15% 15%
Page No. 4
(ADB-108-2017):
4. Construction/Site Progress
Cumulative Progress
Tower No./
Sr. Till Date Percentage Percentage Physical
Activity Description Locations/
No. Progress Progress Weight age Achieved
km
1 No. of Bore Holes 47 47 100% 10% 10%
Tower stacking / released
159 159 100% 3% 3%
for Foundation Construction
2 Tower Foundations
83+76 83+76 100% 44% 44%
Concrete + Piling
Pile Cap 76 76 100% 6% 6%
3 Tower Erection 159 156 98.11% 15% 14.72%
Stringing of Conductor 47.67 88.50% 13% 11.51%
Pulling of 53.87
4 40.70 75.56% 4% 3.02%
OPGW
Pulling of
45.41 34.62 76.24% 3% 2.29%
Shield Wire
5 Testing & Commissioning - 2% 0%
Page No. 5
Page No. 6