Sie sind auf Seite 1von 8

CENTRAL MARKS DEPARTMENT-II(LEGAL)

Our Ref.:CMD-II(L)/16:16098(Part 2) 13 01 2015

Subject : Grouping guidelines & STI for IS 16098(Part 2):2013

Grouping guidelines & STI for IS 16098 (Part 2):2013 (Structured Wall Plastics Piping
Systems For Non Pressure Drainage And Sewerage) approved by DDG(ERO) were
circulated to MSD, CED and all ROs/BOs vide mail dated 29 08 2014 for comments. Since
then, no comments have been received. The status was reviewed by Competent Authority and
it has been decided to treat the Grouping guidelines and STI approved by DDGE as final. A
copy of the Grouping guidelines and STI for IS 16098 (Part 2):2013 are enclosed for ready
reference.

( P S Yadav )
Sc.E

Circulated to : All ROs/BOs


DOC: STI/16098-2/ 1
May 2014

SCHEME OF TESTING AND INSPECTION


FOR CERTIFICATION OF STRUCTURED-WALL PLASTIC PIPING SYSTEMS
FOR NON-PRESSURE DRAINAGE AND SEWERAGE
Part 2 – Pipes and Fittings with non-smooth external surface, Type B
ACCORDING TO IS 16098 (Part 2): 2013

1. LABORATORY A laboratory shall be maintained, which shall be suitably


equipped and staffed where different tests given in the specification shall be carried out in
accordance with the methods given in the specification.

2. TEST RECORDS All records of tests, inspection and calibration shall be kept in
suitable forms approved by the Bureau.

2.1 All testing apparatus/measuring instruments shall be periodically checked and


calibrated and records of such checks / calibration shall be maintained.

2.2 Copies of any records and other connected papers that may be required by the Bureau
shall be made available at any time on request.

3. QUALITY CONTROL - It is recommended that, as far as possible, Statistical


Quality Control (SQC) methods may be used for controlling the quality of the product during
production as envisaged in this Scheme (See IS 397 (Part I):1972, IS 397(Part 2):1985 and IS
397 (Part 3) : 1980]

3.1 In addition, efforts should be made to gradually introduce a Quality Management


System in accordance with IS /ISO 9001 as appropriate to the activities of the organization.

4. STANDARD MARK The Pipe shall carry the standard mark as given in column1
of the first schedule of the licence in the form of a transfix label. The mark may also be
applied by engraving in such a manner that it does not impair the strength of the pipe in any
way. Marking may also be done by screen printing, inkjet printing, laser printing.

5. OTHER MARKING In addition the following information shall be clearly marked


in indelible ink / paint on either end of each straight length of pipe or hot embossed on white
at intervals of not more than three metres with the following.:

a) The manufacturer’s name and its recognized trade mark, if any:


b) Diameter series & Nominal size
c) Stiffness Class
d) Material ,
e) Lot no/ Batch number in code or otherwise which will enable to trace back the
date of production and the test records;
f) ISI Logo, IS Code no & License No………………(CM/L ………..) and
g) Made in India, if required.

1|Page
DOC: STI/16098-2/ 1
May 2014

5.0 LEVELS OF CONTROL - The tests, as indicated in Table 1 attached and at the levels
of control specified therein, shall be carried out on the whole production of the factory which
is covered by this scheme and appropriate records and charts maintained in accordance with
paragraph 2.0 above. All the production which conforms to the Indian Standards and covered
by the license shall be marked with certification mark of the Bureau.

5.1 CONTROL UNIT - A Control unit is defined as a continuous extrusion run of one size
and class of pipe from one extrusion compound up to a maximum of 48 (forty eight) hours
duration.

5.2 RAW MATERIAL - Only those additives shall be added which are needed to facilitate
the manufacture of the pipe and the production of sound and durable pipes of good surface
finish, mechanical strength. None of these additions shall produce toxic hazard or impair the
strength of the pipes. Manufacturers own rework material (Complying with IS 16098 (Part 2),
Cl. 5.2) is permissible. The quantity of rework material used is to be declared by the
manufacturer. No other rework material shall be used.

5.3 In case of failure in any of the tests twice the no. of samples should be tested for that
requirement. If a further failure occurs, the entire lot shall not be marked.

5.4 In respect of all other clauses of the specification and at all stages of production, the
factory shall maintain appropriate controls and checks to ensure that their product conforms
to various requirements of the specification.

6.0 REJECTIONS - A separate record shall be maintained giving information relating to


the rejection of the production not conforming to the requirements of the specification and the
method of its disposal. Such material shall in no circumstances he stored together with that
conforming to the specification.

7.0. SAMPLES - The licensee shall supply, free of charge, the samples required in
accordance with the Bureau of Indian Standards (Certification) Regulations, 1988, as
subsequently amended, from the, factory or godowns. The Bureau shall pay for the samples
taken by it from the open market if applicable.

8.0 REPLACEMENT - Whenever a complaint is received soon after the goods with
Standard Marks have been purchased and used, and if there is adequate evidence that the
goods have not been misused, defective goods or their components are to be replaced or
repaired free of cost by the licensee in case the complaint is proved to be genuine and the
warranty period (where applicable) has not expired. The final authority to judge the
conformity of the product to the Indian Standard shall be with the Bureau. The firm shall
have own complaint investigation system as per IS 15400.

8.1 In the event of any damages caused by the goods bearing the Standard Mark, or Claim
being filed by the Consumers against BIS Standard Mark and not “Conforming to” the
relevant Indian Standard, entire liability arising out of such non conforming product shall be
of licensee and BIS shall not in any way be responsible in such cases.

9.0 STOP MARKING- The marking of the product shall be stopped under intimation to
the Bureau if, at any time, there is some difficulty in maintaining the

2|Page
DOC: STI/16098-2/ 1
May 2014

conformity of their product to the specification, or the testing equipment goes out of order.
The marking may be resumed as soon as the defects are removed under intimation of Bureau.

9.1 The marking of the product shall be stopped immediately if directed to do so by


Bureau for any reason. The marking may then be resumed only after permission by the
Bureau. The information regarding resumption of markings shall also be sent to the Bureau.

10.0 PRODUCTION DATA The licensee shall send to BIS as per the enclosed
Proforma-1 to be authenticated by a Chartered Accountant, a statement of quantity produced,
marked and exported by him and the trade value thereof at the end of each operative year of
the license.

Table 1………

3|Page
DOC: STI/16098-2/ 1
May 2014
IS 16098 (Part 2): 2013
STRUCTURED-WALL PLASTIC PIPING SYSTEMS FOR NON-PRESSURE
DRAINAGE AND SEWERAGE – SPECIFICATION
Table 1: Levels of Control
(Clause 5 of the Scheme of Testing & Inspection)

Test Details Levels of Control


Cl. Requirement Test Methods No. of Frequency Remarks
No Samples
Table/ Serial
Clause No.
5.1 Material (PE) Table 1 i) One Each batch in a If a test certificate is
ii) consignment received for each
batch along with each
iii) One Once in 03 months consignment of raw
of each grade of material further
Raw material testing would not be
consignment necessary
5.1 Material in Solid Table 2 i) One Once in a year for
Pipe form (PE) ii) each variety
5.1 Material (PP) Table 3 i) One Each batch in a If a test certificate is
consignment received for each
batch along with each
ii) One Once in 03 months consignment of raw
of each grade of material further
Raw material testing would not be
consignment necessary
5.1 Material in Solid Table 4 i) One Once in a year for
Pipe form (PP) ii) each variety
6.3 Dimensions of Cl 6.3, - One Once in 4 Hrs -
Pipes and Fittings 7.1
7.1 , Visual Appearance Cl 7.1 , - Each Pipe Each Control unit
7.1.1 , finish & Colour 7.1.1
of Finished Pipes
7.2 Resistance to Table 6 i) One Each Control unit
Heating (PE)
7.2 Resistance to Table 7 i) One Each Control unit
Heating (PP)
7.3 Effect of Heating Table 8 i) One Each Control unit
(Only for PE
Injection moulded
components)

4|Page
DOC: STI/16098-2/ 1
May 2014
IS 16098 (Part 2) : 2013
STRUCTURED-WALL PLASTIC PIPING SYSTEMS FOR NON-PRESSURE
DRAINAGE AND SEWERAGE – SPECIFICATION
Table 1: Levels of Control
(Clause 5 of the Scheme of Testing & Inspection)

Test Details Levels of Control


Cl. Requirement Test Methods No. of Frequency Remarks
Samples
Table/ Serial
Clause No.
7.3 Effect of Heating Table 9 i) One Each Control unit
(Only for PP
Injection moulded
components)
8.1 Ring Stiffness Table i) One Each control unit Same for PE and PP
10 pipes
8.1 Impact Strength Table ii) One Each control unit Same for PE and PP
10 pipes
8.1 Ring Flexibility Table iii) One Each Control unit Same for PE and PP
10 pipes
8.2 Stiffness (Fittings) Table i) One Each Control unit Same for PE or PP
11 fittings
8.2 Impact Test Table ii) One Each Control unit Same for PE or PP
(Fittings) 11 fittings
8.2 Mechanical Table iii) One Each Control unit Same for PE or PP
Strength (Fittings) 11 fittings
8.1 Creep Ratio Table iv) One Once in a year for Same for PE and PP
10 each variety pipes
9 Tightness of Table i) One Once in a year for Same for PE and PP
elastomeric ring 12 each variety pipes
seal joint
9 Water Tightness Table ii) One Once in a year for Same for PE and PP
12 each variety pipes
9 Resistance to Table iii) One Once in a year for Same for PE and PP
combined 12 each variety pipes
temperature
cycling and
external loading

5|Page
DOC: STI/16098-2/ 1
May 2014

6|Page