Beruflich Dokumente
Kultur Dokumente
The products manufactured at heavy machine shop are Hitachi suspension tube (conventional
loco spare), Loco Roof (Three phase), Traction bar, Traction motor stator welding and
machining, assembly of wheel set with traction motor, head stock, central under frame items.
The HMS has 8 sections according to their respective works.
We will discuss all the products we have seen in HMS from where they are supplied to HMS
and then where they dispatched.
1. First the chalking will be done on the entire surface of raw suspension tube came from
steel foundry of cast iron. Then marking and punching to be done on them
subsequently according to their dimensions.
2. Then the both end of suspension tube is undergoes milling operation.
3. Then the bottom pad milling is done.
4. Then the side pad milling is done.
5. Then the inside gap between two base of suspension tube is undergoes the milling
operations.
6. Then the joint face (TM joint) raw milling is done.
7. Then the joint face finish milling is done with very high accuracy.
8. Then the relief cutting operation is done.
9. Then the joint face drilling and tapping is done subsequently.
10. Then rough boring is done in finish B hole on the joint face.
11. Then finish boring is done thereafter.
12. Then marking is done for end drilling and tapping.
13. Then overall dressing and cleaning is done.
14. Then the final inspection is done according to standards and dimensions.
15. If there is any deviation work is needed, then it will be done.
16. At last painting is done.
17. Then it will be given to consumer shop (mainly WS-09).
The Stator is received from TM-21 shop then in HMS-08 it is given to Universal machining
Centre (MAG IAS Gmbh GERMANY) , then it is given to welding section for final welding.
1. Clean Pinion, Gear, Suspension tube, Ring etc. properly fit ‘O’ ring on motor and
complete motor wheel assembly.
2. Check back lash with lead wire (Limit 0.290-0.490mm).
3. Take the motor-wheel assembly on running stand for stage-II trial run without
gear case and trial run for 30 minutes. Get it cleared by Works inspector.
4. Clean properly the both halves of gear case and fit in position. Use locktite
sealant as and when required.
5. Tighten all the sub-assemblies with torque wrench with various torque values as:-
1. This is manufactured with the help of thick plates. The thick plates are of 32 mm, 16
mm and 25 mm.
2. The long beam is usually manufactured in SHOP no-17(Long beam Section).
3. The Main long beam structures are central seal and side beams.
4. These are later became part of under frame.
5. The fabrication of long beam generally done by MIG welding process.
6. After the welding the grinding is done all over the welding zones.
7. After the inspection these beams are ready for fabricate the under frame.
UNDERFRAME STRUCTURE
1. The main parts of under frames are central seal, central under frame, bolster,
headstocks and side beams.
2. In this stage long beams (two in number) were placed on the jig in the under frame
BIB structure.
3. Under frames are manufactured here with help of box type transverse member,
channel plates, Z-plates and L-plates were welded here for the formation of the
transformer opening which is known as the SL-42 opening.
4. This type of opening is provided at the both end structure thus it is made and sends
to the next stage.
In this stage all kind of channels, angles etc. are fitted for mounting tools for electrical
equipments. Name of the components which are fabricated in this stage are given below.
1. SHELL MARKING
2. INFILL PLATE ASSEMBLY
3. SPRING POCKET COVERING PLATE
4. FLOOR VENTILATION
5. DRILLING ON OIL COOLING BASE UNIT
6. DRILLING ON FRONT SHEET (FOR STRIKER CASTING).
MANIPULATOR
The manipulator is a wheel like structure with two parts of semicircle. By the help of
manipulator the under frame is changes it’s stage from RWU to USD (upside down).For this
operation the shaft of manipulator the vital part. Under frame structure comes to manipulator
RWU-1 and all types of welding of under frame are carried out here and completed.
USD (UPSIDE DOWN)
1. CENTRAL PIVO
2. COMPRESSOR LEG
3. BATTERY BOX LEG
4. HOLDING ITEMS (PIPE LINE HOLDING ITEMS)
5. DIN RAIL (UNISTUD)
6. LUMING BAR
7. SOCKET
8. DRILLING ON DRAFT GEAR BOX
9. CONDUIT PIPE
10. JUNCTION BOX(06 Nos)
11. CONNECTING BOX
12. SAFETY SHEILING ( COMPRESSOR)
13. PITCH STOPPER(08 Nos)
14. SECUIRITY LOCK (02 Nos)
15. DRILLING AND TAPPING FOR AIR BELLOW ASSEMBLY(DRILL 8mm, TAP
10mm)
16. REFERENCE 38
17. SPRING POCKET PLATE(08 Nos)
18. CENTRAL PIVOT HOUSING ASSEMBLY(ALKATHIN RUBBER RING USED
AS A BUSH)
INSPECTION
1. Ultra Sonography Tests (UTS): This test is used for testing of headstock-bolster
plate joints and bolster plate-central seal joints.
2. Dye Penetrate Test (DPT): This test is used to find out the welding defects present
in pivot joint.
RWU-II (RIGHT WAY UP)
In this stage, we use the jigs, fixture and side walls (as a reference)for following item
fitment:-
SHELL
DISPATCH
At this stage after the fitting of CBC (centre Buffer Coupling) and cattle guard assembly are
done. Then the complete Shell is under goes the inspection and dispatched to the ELS-16 for further
assembly works. The dispatch is done by the help of dummy bogies.