The major inputs like pig iron, cast iron, sponge iron are manufactured at the most modern composite iron and steel
plant of Electrotherm situated in the same campus as the plant for manufacture of DI Pipes. The composite iron and
steel plant of Electrotherm.
INDUCTION FURNACE
Melting done from solid charge for hot metal. Weighed, known charge is put to the furnace. Analysis of metal bath is
done. Final adjustment of chemical composition is achieved by additives and chemical analysis done by spectrometer
for trace and
Fixed quantity of liquid metal is tapped from furnace to open ladle at about 1550 deg (± 50) C already containing
required quantity of FeSiMg lumps covered with metallic covering. Qty. of FeSiMg is governed by opening S % and
liquid metal quantity
ANNEALING FURNACE
ZINC COATING
External surface coating is done by arc paint process. Melted zinc is deposited as fog by compressed air. Coating mass
per meter square as per QAP.
FETTLING
Each and every pipe is hydrotested at specified pressure to ensure leak proof pipes as per QAP.
CEMENT LINING
STEAM CURING
BITUMEN COATING
External surface coating is done by spraying of bitumen. Coating mass per square meter as per QAP.
MARKING
STOCK YARD