Beruflich Dokumente
Kultur Dokumente
TABLE OF CONTENT
CHAPTER TITLE
NO.
1. SYNOPSIS
2. ACKNOWLEDGEMENT
3. LIST OF SYMBOLS
4. INTRODUCTION
5. SPECIFICATION REPORT
6. PROJECT AT A GLANCE
7. STRUCTURE DESIGN
DESIGN OF BEAM
DESIGN OF COLUMN
DESIGN OF FOOTING
8. RATE ANALYSIS
9. LEAD STATEMENTS
14. CONCLUTION
15. BIBLIOGRAPHY
CONTENTS
SYNOPSIS
ACKNOWLEDGEMENT
LIST OF SYMBOLS
INTRODUCTION
SPECIFICATION REPORT
PROJECT AT A GLANCE
STRUCTURE DESIGN
LEAD STATEMENT
DATA PREPARATION
DETAILED ESTIMATE
ABSTRACT ESTIMATE
DRAWINGS
CONCLUTION
BIBLIOGRAPHY
CHAPTER-1
SYNOPSIS
SYNOPSIS OF THE PROJECT
The project presents the functional planning, structural design and Estimate of
“VAO OFFICE” is proposed to be constructed at nagapadi, tiruvannamalai
District.
Dental care is not available in that place, so planned to construct the dental care at
,nagapadi, tiruvannamalai District.
Hall room
CHAPTER-2
ACKNOWLEDGEMENT
ACKNOWLEDGEMENT
We here by acknowledgement our regards and gratitude to our
Mrs.J.MEGALA.M.E,M.I.S.T.E., Principal of Government
polytechnic college for her encouragement & guidance to this project
work.
C.RAJESH
M.POONGAN
N.SARAVANAN
R.SILAMBARASAN
E.SURYA
CHAPTER-3
LIST OF SYMBOLS
LIST OF SYMBOLS
A - Area
d - Effective depth
DL - Dead load
LL - Live load
W - Total load
Fd - Factored load
DF - Depth of foundation
Mu - Bending moment
- shear force
- Limiting volume
Ast - Total cross section area of stirrup legs (or) bent up bars with in
a distance.
# - Fe 415 (R.T.S)
- Mild steel
Z - Lever arm
CHAPTER-4,5
1. INTRODUCTION
1.1. SCOPE AND OBJECTIVE
To finalize the plan of VAO office.
To design a slab, beam, column, footing and sunshade manually
The future extension design has been carried out.
1.2. SPECIFICATIONS
The specifications are provided for the construction “DESIGN OF VAO
OFFICE”. The provision is made in the specifications are as follows.
1.2.4. CONCRETE:-
Concrete is a material obtained by combining together interest material like
sand gravel and broken stone. This R.C.C is weak in tension and strong in
compression so steel reinforcement is used to take up the tensile stress in this
project the R.C.C for the ratio of 1:2:4 using 20mm nominal metals are obtained
from Vellore. All the R.C.C works are going to be done by volume batching.
1.2.5. ROOFING:-
The roofing will be of R.C.C M20 grade with 150 mm thick and it is designed
as two way slab.
STRUCTURAL DESIGN
3.1. DESIGN OF SLAB
Step-1:
Lx =3.0m
Ly =3.5m
=3.0/3.5
=1.66< 2
3.5m File room
d=
d =3000/(40x0.8)
d 62.5 100 mm
=0.12×25 × 1
=3.0KN/m
=8.25 KN/m
=3.1m
=3.30m
Lx = 3.10m
Lylenger span
= 1.161
-αx =0.056
+αx = 0.042
-αy =0.047
+αy =0.035
mx =3.369 KNm
= - Mx =4.479 KNm
LONGER SPAN
= 2.774 KNm
Negative moment of mid span = -My = 0.047 × 8.25 × 3.102
= 3.726 KNm
d =√
= 40.729mm
“ Hence ok ”
= 2.70 m
=2.325m
= 144 mm2
Astmin =144mm2
Ast =127.295mm2
Astrqu=144mm2
Ast =150mm2
Spacing limit
(1) 3d=3x120=360mm
(2) 300mm
Max permitted spacing = 300mm,spacing providing 10mm ϕ bars
=825.69mm
=616.99mm
=1006.2mm
=745.012mm
Spacing limit
5d(or) 450mm
S=300mm<5d<450mm
Hence ok
„at the corner where the slab is discontinuous 2 edges. provided 100%.
Torsion steel
=0.2x3.10
0.62 1m
=75mm2
Torsion reinforcement need not be provide at the corner having both the
edge continuous
Step:11 Curtailment
Alternate bass are curtailment at 0.1 le from the face of support the full
length bass are taken to top and extended from face of the support for
discontinuous of 0.1 le to taken negative BM
=8.25x3.10/2
vu =12.787 KN
=12.787/1x100
τv =0.127N/mm2
τc> τv
Hence ok
Ast=127mm2
Pt=0.16%
dstiff =40.67mm
Hence ok
Step:14 Result
Reinforcement along
Step-1:
Lx =3.0m Hall
4.5m
Ly =4.5m
=3.0/4.5
3.0m
=1.5< 2
d=
d =3000/(40x0.8)
d 62.5 100 mm
D =120mm
=0.12×25 × 1
=3.0KN/m
=8.625 KN/m
=3.1m
=3.30m
Lx = 3.10m
Lylenger span
(iii) 4500+100 =4600
=4.6m
(iv) 4500+300 = 4800
= 4.80mm
Ly = 4.60m
= 1.483
-αx =0.0662
+αx = 0.050
-αy =0.028
+αy =0.037
mx =4.010 KNm
- Mx =5.522 KNm
Longer span
= 2.335 KNm
= 3.086 KNm
d =√
= 43.489 mm
“ Hence ok ”
= 3.457 m
=2.232m
= 144 mm2
Astmin =150mm2
Ast =149.019mm2
Spacing limit
(1) 3d=3x120=360mm
(2) 300mm
Max permitted spacing = 300mm,spacing providing 10mm ϕ bars
=663.770mm
=1198.5mm
=527.046mm
=902.903mm
=335.133mm
Spacing limit
5d(or) 450mm
S=300mm<5d<450mm
Hence ok
„at the corner where the slab is discontinuous 2 edges. provided 100%.
Torsion steel
=0.2x3.10
0.62 1m
Torsion reinforcement need not be provide at the corner having one edge
discontinuous
Step:11 Curtailment
Alternate bass are curtailment at 0.1 le from the face of support the full
length bass are taken to top and extended from face of the support for
discontinuous of 0.1 le to taken negative BM
=8.625x3.10/2
vu =12.787KN
=12.787/1x100
τv =0.127N/mm2
τc> τv
Hence ok
Step:14 Result
Reinforcement along
Fck =20N/mm2
Fy=415N/mm2
L =3000mm
Mulimi=2.76bd2
Xumax=0.48d
d = L/12
d = 3000/12
d = 250 mm
Over all depth (D) = d + effective cover + dia/2
=250 + 25+20/2
D=283mm
Say=300mm
d=300-25-20/2
=265mm
bw=2/3d
bw=2/3 x 265
=0.3 x 0.23 x 1 x 25
=1.725KN/m
Wu=22.087KN/m
Mu = Wu x (Le) 2/24
=22.087 x (3.267)2/24
Mu =9.822KN/m
Mulimi=2.76bd2
Mu1= Mulimi =2.76x230x2672
Mu1=45.254x106N.mm
Mu2=Mu-Mulimi
=45.254x106-9.822x106
Mu2=35.432x106 N.mm
Xumax =0.48d
=0.48x267
=128.16mm
Ast1=45.254x106/0.87x415(267-0.42x128.16)
=587.97mm2
d'=25+20/2=33mm 40mm
=35.432x106/0.87x415(267-40)
Ast2=432.31mm2
=1020.29mm2
=3.24nos 4nos
xumax=128.6mm
d'=33mm
fsc=519.4N/mm2
=35.432x106/519.49(267-40)
=300.6461mm2
= (100×784.820) / (300×230)
τc=0.62N/mm2
τc>τv
Shear reinforcement
= 33.13×106 – (0.62×300×230)
=9.65 KN
Asv (π×102)/ 4
= 78.53mm2
Sv=
=764.744mm
RESULT:
Step – 1: Data
Fck =20N/mm2
Fy=415N/mm2
L =4500mm
Mulimi=2.76bd2
Xumax=0.48d
d = L/12
d = 4500/12
d = 375 mm
Over all depth (D) = d + effective cover + dia/2
=375 + 25+20/2
D=410mm
Say=300mm
d=300-25-20/2
=265mm
bw=2/3d
bw=2/3 x 265
=0.3 x 0.23 x 1 x 25
=1.725KN/m
Wu=29.11KN/m
Mu = Wu x (Le) 2/24
=29.11 x (4.767)2/24
Mu =24.563KN/m
Mu1=45.25x106N.mm
Mu2=Mu1-Mulimi
=45.25x106-24.563x106
Mu2=20.687x106 N.mm
Xumax =0.48d
=0.48x267
=128.16mm
Ast1=45.25x106/0.87x415(230-0.42x128.16)
=711.397mm2
d'=25+20/2=33mm 40mm
=20.687x106/0.87x415(267-40)
Ast2=252.40mm2
Area tension steel Ast= Ast1+ Ast2
=711.397+252.40
=963.797mm2
=3.07nos 4nos
xumax=128.6mm
d'=33mm 40mm
fsc=519.756N/mm2
=20.687x106/519.49(267-40)
=175.42mm2
No of bars=175.42/л/4x162
=1.08nos 2nos
Step – 9: Check for shear
τv =0.480N/mm2
= (100×784.820) / (300×230)
τc=0.62N/mm2
τc>τv
Shear reinforcement
= 33.13×106 – (0.62×300×230)
=9.65 KN
Asv (π×102)/ 4
= 78.53mm2
Sv=
=764.744mm
RESULT:
1. DATA:
Effective Depth = 80 mm
2. LOAD CALCULATION:
= 0.1 x 0.6 x 1 x 25
= 1.5 KN/m
= 2.25 KN/m
Bending moment, Mu =
= 0.405 KNm
Mu = 0.87 x fy x Ast x d x [ ]
= 120 mm2
5.SPACING:
Sv = x 1000
= x 1000
(i) 3d = 3 x 80 = 240 mm
(ii) 300 mm
PROVIDE:
RESULT:
Step 1: Data
= (14.725 × (3.25/2))
load =23.925KN
=1.5×23.925
=35.892KN
λ =3250/300=10.833<12
It is a short column
1) emin=L/500+D/30
=3250/500+300/30
=16.5mm< emin=20mm
2) e=0.05xD=0.05x300
=15mm<20mm
Ag=300x300
=90000mm2
Ac=Ag-Asc
=90000-Asc
35.892x103=0.4x20(90000-Asc)+(0.67x415xAsc)
Asc=684108/270.05
Asc =2533.26mm2
No of bars= Asc/(π/4x202)
8.06nos 8nos
=2827.43mm2
% Asc=100(2827.43/300x300)=3.14%
3.14<Amax=4%
3.14>Amin=0.8%
Hence ok
(i) diameter
1) 6mm
2) 1/4x larger longitudinal bar dia=1/4x20=5mm Say 8mmϕ
(ii) Pitch
Pitch is least of the following
(i) LLD = 300mm
(ii) 16 x smallest longitudinal bar=16 x 20=320mm
(iii) 300mm
RESULT:
Step 1: Data
= 23.925× 1
W =23.925KN/m
W1=45/100 x 23.925
=10.766KN
=34.691KN
=52.035 KN
Size of Footing:
=34.691/100
=0.345m2
A =B x L
L =B
0.345 =B2
B=1.5m
L =1 x 1.5
L =1.5m
= 1.5x34.691/1.5
q =23.12KN/m2
=600mm
=600mm
Step4: To calculate the Bending Moment:
Mu1 =6.243KNm
Mu2=6.243KNm
d =√
d =√
=86.83mm ~100mm
=174mm ~200mm
D = 2x200=400mm
D = 400mm
D = 326mm
Step 6 : To calculate the Main Reinforcement
In Longer Span:
Ast=149.50mm2
No of bar = Ast/ast
In Shorter Span:
Ast= 149.50mm2
No of bar = Ast/ast
%Ast = 100x4x113.04/300x126
=1.19%
Development length:
= (0.87×415×12)/ (4×1.2x1.6)
=564.14mm
Longer direction=600-50
=550mm
Shorter direction=600-50
=550mm
Vb=4.748KN
=4.748x103/326x652
τv =0.022N/mm2
%Ast=1.19
τc = 0.62+(0.67-0.62/2) x(1.19-1.00)
τc =0.624N/mm
τv<τc
Hence Safe
d/2=126/2
=63mm
Vc= qx(1.52-0.426)
=23.12x(1.52-0.426)
Vc =42.17KN
=0.78N/mm2
=0.25√
=1.118N/mm2
=1.118N/mm2
τv < τc
= 1.5x23.925x103/300x300
= 0.40 N/mm2
√
Permissible bearing stress = 0.45xfckx
A1 = 1.9x1.9=3.61m2
√
=√2.25/0.09= 5 restricted to 2
Hence safe
Hence safe
2. Sand - 1800 / m3
3. Lime - 1200 / m3
5.Binding work - 60 / kg
9. Crude oil - 50 / kg
Plinth Beam
Wall around 1 30 0.23 0.3 2.07
TOTAL=39.154m3
2 P.C.C 1:4:8 for
foundation
(a) (b) Column 9 1.5 1.5 0.2 4.05
TOTAL=4.05m3
3 R.C.C 1:2:4 for columns,
beams, lintels, roof
Column
Level base 9 1.5 1.5 0.2 4.05
Tripizontal A1= (1.5×1.5)
A1=2.25
= h/3 (A1+A2+√A1+A2) A2= (0.23×0.23)
A1= (1.5×1.5) A2=0.09
A1=2.25
A2=0.09
0.580 5.22
= 0.45/3[ (2.25+0.09)+√
9
2.25×0.09]
=0.15 (3.869)
=0.580 m2
Column below
Plinth beam
Wall around 1 30 0.23 0.3 2.07
C/W file,store room 1 3 0.23 0.3 0.207
Roof beam
1 30 0.23 0.35 2.415
Lintel
windows 7 1.5 0.2 0.15 0.15
TOTAL=23.211 m3
TOTAL=6.52m3
Total Brick Work=26.44m3
5 Earth Filling inside the
basement
Inside the hall 1 6.2 4.5 0.45 12.55
Inside the file 1 3.0 3.5 0.45 4.725
Inside the store 1 3.0 3.5 0.45 4.725
TOTAL 22 m3
6 Ceiling Plastering with
CM 1:3
` Inside the hall 1 6.2 4.5 29.9
Inside the store 1 3.0 3.5 - 10.5
Inside the file 1 3.0 3.5 - 10.5
Steps(rise portion)
1st 2 0.9 0.15 0.27
2nd 2 0.6 0.15 0.18
3rd 2 0.3 0.15 0.09
Tread portion 6 1.0 0.3 1.8
Parapet wall at top 1 30 0.3 9.0
Inside 1 31.2 0.6 18.72
TOTAL=382.99m2
Deduction for
Window(w) 7 1.5 1.5 15.75
Door(M.D) 1 1.0 2.1 2.1
Door(D) 2 0.9 - 2.1 3.78
TOTAL=21.6 m2
Total Plastering=361.36m2
8 Floor Finishing with CM
1:4 20mm thick
TOTAL 48.9m2
10 Supply and fixing of
windows
Windows (W) 7 7 no‟s
Weathering course
11
Floor slab 1 8 6.2 49.6
TOTAL=49.6m2
12 White washing 2 coats ─ ─ ─ ─ 449.7m2
over the plastered area
13 Color washing 2 coats ─ ─ ─ ─ 361.36m2
13 Painting two coats with
good emulsion paint over
priming coat
Windows (W) 7 1.5 1.5 15.75
Door (M.D) 1 1.0 2.1 2.12
Doors(D) 2 0.9 - 2.1 3.78
TOTAL=21.63m2
14 Providing electrification ─ ─ ─ ─ L.S
CHAPTER-13
BAR BENDING SCHEDULE FOR SLAB-1
170
3.73 4 6.1 91.01
3345
Total = 266.68N
No of slab = 12
= 3360.12 N
BAR BENDING SCHEDULE FOR SLAB-2
170
6845
Total = 522.88N
No of slab = 6
=3294.12 N
BENDING SCHEDULE OF STRUCTURAL BEAM-1
350
Total = 335.19N
No of beams = 37
= 13021.78N
BENDING SCHEDULE OF STRUCTURAL BEAM-2
5 Stirrups 8# 350
1.64 21 3.9 134.3
550
Total =695.57N
No of beams = 6
= 4382.04N
BAR BENDING SCHEDULE FOR COLUMN & FOOTING
2. column
(i) Reinforcement
350
8# 1.04 5 3.9 20.3
Total = 1096.4 N
o‟ 30
Total weight of reinforcement = 30 x 1151.22
= 34536.6N
CHAPTER-14
CONCLUSION
By doing this project we the students of our batch draw and prepare for a
“VAO OFFICE” we also now have a rough idea about the various books
available in design of R.C.C members.
The design was done by the following the provisions of IS 456:2000, IS 875:
PART-III; SP-16.
Schedule of rates for tiruvannamalai district by TAMIL NADU, P.W.D for the
year 2016-2017