Sie sind auf Seite 1von 104

CONTENT

TABLE OF CONTENT

CHAPTER TITLE
NO.
1. SYNOPSIS

2. ACKNOWLEDGEMENT

3. LIST OF SYMBOLS

4. INTRODUCTION

5. SPECIFICATION REPORT

6. PROJECT AT A GLANCE

7. STRUCTURE DESIGN

 DESIGN OF ROOF SLAB

 DESIGN OF FLOOR SLAB

 DESIGN OF BEAM

 DESIGN OF SUN SHADE

 DESIGN OF COLUMN

 DESIGN OF FOOTING

8. RATE ANALYSIS
9. LEAD STATEMENTS

10. DATA PREPARATION

11. DETAILED ESTIMATE

12. ABSTRACT ESTIMATE

13. BARBENDING SCHEDULE

14. CONCLUTION

15. BIBLIOGRAPHY
CONTENTS

 SYNOPSIS

 ACKNOWLEDGEMENT

 LIST OF SYMBOLS

 INTRODUCTION

 SPECIFICATION REPORT

 PROJECT AT A GLANCE

 STRUCTURE DESIGN

 LEAD STATEMENT

 DATA PREPARATION

 DETAILED ESTIMATE

 ABSTRACT ESTIMATE

 DRAWINGS

 CONCLUTION

 BIBLIOGRAPHY
CHAPTER-1
SYNOPSIS
SYNOPSIS OF THE PROJECT

The project presents the functional planning, structural design and Estimate of
“VAO OFFICE” is proposed to be constructed at nagapadi, tiruvannamalai
District.

Dental care is not available in that place, so planned to construct the dental care at
,nagapadi, tiruvannamalai District.

The plinth area of the proposed building 302m2

The plinth area rate is Rs.7648 / m2

The approximate cost of the building is Rs25 Lakh

The building consists of

Store room, File Room,

Hall room
CHAPTER-2

ACKNOWLEDGEMENT
ACKNOWLEDGEMENT
We here by acknowledgement our regards and gratitude to our
Mrs.J.MEGALA.M.E,M.I.S.T.E., Principal of Government
polytechnic college for her encouragement & guidance to this project
work.

We wish to acknowledge ours sincere thanks and gratitude to


our head of the department Mrs.N.SIVAKAMI.M.E.PGDCA, has
activated and encourage to do this project.

We wish to acknowledge ours sincere thanks and gratitude to our


guide Mr.S.RAMESH.B.E., for his untiring efforts in completing our
project work.

We extended our thanks to our department faculties


Mr.R.KUMARESAN.M.E.,DTSA.,
Mr.M.RAMESH KUMAR.B.E.,
Mr.S.PANDIDURAI.B.E.,
Mr.M.SIVASANKARAN.B.E.,
To their valuable encouraging for the successful completion of
project work.
Batch Members
G.RAGU

C.RAJESH

M.POONGAN

N.SARAVANAN

R.SILAMBARASAN

E.SURYA
CHAPTER-3

LIST OF SYMBOLS

LIST OF SYMBOLS

A - Area

b - Breath of footing or shorter dimension of rectangular column.

d - Effective depth

D - Over all depth

DL - Dead load

LL - Live load
W - Total load

Fd - Factored load

Leff - Effective length

L - Length of the column

fck - Characteristic strength of concrete

Fy - Characteristic strength of steel

Ag - Cross sectional area of the concrete

DF - Depth of foundation

Mu - Bending moment

Ast - Area of steel in tension

- shear force

Zv - Normal shear stress

Zc - Permissible shear stress

SPWt - Specific weight

- Limiting volume

Ast - Total cross section area of stirrup legs (or) bent up bars with in
a distance.

Sv - spacing of the stirrup or bent up bars along the length of the


member.
X - Depth of the neutral axis

C/c - Center to center

# - Fe 415 (R.T.S)

- Mild steel

Z - Lever arm

CHAPTER-4,5
1. INTRODUCTION
1.1. SCOPE AND OBJECTIVE
 To finalize the plan of VAO office.
 To design a slab, beam, column, footing and sunshade manually
 The future extension design has been carried out.
1.2. SPECIFICATIONS
The specifications are provided for the construction “DESIGN OF VAO
OFFICE”. The provision is made in the specifications are as follows.

1.2.1. SUB SOIL DATA:-


The sub soil is of course grade and compacted sand. The plate load test was
conducted by the P.W.D authorizes to determine the SBC value.
1.2.2. ORIENTATION:-
The Design of VILLAGE proposed to be constructed at deanery. This
proposed land is owned by the private it faces south.
1.2.3. BRICK MASONARY:-
The most and widely used material for construction of building is brick. It
has the following advantages.
i) Raw materials required are ordinary earth which is available is
abundance.
ii) Kill burning bricks are used
iii) Locally available brick size 19 x 9 x 9 cm
All the works will be in brick masonry in cement mortar 1:6 using above
maintained bricks. The height of wall from floor level to roof level is 3.5m this
brick are obtained from Tiruvannamalai town.

1.2.4. CONCRETE:-
Concrete is a material obtained by combining together interest material like
sand gravel and broken stone. This R.C.C is weak in tension and strong in
compression so steel reinforcement is used to take up the tensile stress in this
project the R.C.C for the ratio of 1:2:4 using 20mm nominal metals are obtained
from Vellore. All the R.C.C works are going to be done by volume batching.
1.2.5. ROOFING:-
The roofing will be of R.C.C M20 grade with 150 mm thick and it is designed
as two way slab.

1.2.6. COLUMN AND FOOTING:-


The column is of the size 0.30X 0.30 .1m center. The footings are the size of
1.5 X 1.5 with 0.3m wide.
1.2.7. FLOORING:-
This will be of R.C.C 1:2:4 150 mm thick using 40mm nominal size HBG
metal over the wall compacted river sand cushion which is 150 mm thick the top of
the floor is finished with mosaic slabs polished.
1.2.8. DAMP PROOF COURSE:-
The damp proofing of a building is achieved by using a suitable material this
should satisfy the following requirement.
i) It should be imperious to moisture
ii) It should be stable in loaded and unloaded condition.
iii) It should not be distributed by the effect of dead load coming over the
surface
iv) Damp proofing properly should remain constant with lapse of time in
this project the CM of 3 cm is used as DPC.

1.2.9. DOORS AND WINDOWS:-


The primary purpose of doors is serving as a means of communication from
one room to another room. Secondly in combination with windows provides
circular ventilators.
1.2.10. PLASTERING:-
Plastering for the ceiling is in CM 1:3, plastering for walls if 1:5 with 5mm
curing is done locally available portable water.

1.2.11. WHITE WASHING:-


White washing is done by using white cement over the plastered surface of
internal walls to improve its appearance.
1.2.12. WEATHERING COURSE:-
This will be in brick jelly works with lime of 40% and over which that tiles
are laid in oiled mortar required slope may be maintained.
1.2.13. COLOUR WASHING:-
The color wash is applied in one or the more coats over the first coat of
white wash 5% of gum is added to the solution. The application is similar.
1.2.14. STEEL:-
This steel used in the design of the R.C.C member is Fe 415.
CHAPTER-6
2.PROJECT AT GLANCE

1. Name of project : Design of VAO OFFICE

2. Type of construction : Framed structure

3. Type of foundation : square footing

4. Roofing : R.C.C. with 1:1.5: 3

5. Plinth area : 302m2

6. Built up covered area : 400 m2

7. Plinth area rate : 7648 / m2

8. Approximate cost : 25 Lakh of building

9. Design code : IS 456-2000

10.Grade of concrete : M20

11.Grade of steel : Fe 415

12.Cost of construction :2302086/-


CHAPTER-7

STRUCTURAL DESIGN
3.1. DESIGN OF SLAB

3.1.1. Design of Two way slab

Step-1:

SIZE of the room = 3.0m x 3.5m

Lx =3.0m

Ly =3.5m

=3.0/3.5

=1.66< 2
3.5m File room

“ Hence the slab is a Two Way Slab”

Step-2: Effective Depth


3.0m

d=

d =3000/(40x0.8)

d 62.5 100 mm

Provide clear cover =15mm

Diameter of bars =10mm

Over all depth (D) =d+ clear cover+ diameter of bars/2

Over all depth (D) =100+15+10/2


D =120mm

Step- 3: Load calculation

Consider 1m width of a slab

1. self-weight of slab = Unit Weight × D x b

=0.12×25 × 1

=3.0KN/m

2. weathering crouse = 1 KN/m


3. Impose load = 1.5 KN/m
4. Total load = 5.5 KN/m

Total design load = 5.5×1.5

=8.25 KN/m

Step - 4: Calculate the eff span

Lx shooter span (i) 3000+100 =3100

=3.1m

(ii) 3000+300 = 3300

=3.30m

Lx = 3.10m

Lylenger span

(i) 3500+100 =3600


=3.6m
(ii) 3500+300 = 3800
= 3.80mm
Ly = 3.60m

Step-5: bending moment Co-efficient

Two adjacent Edges discontinuous

Ratio ly/lx = 3.60/ 3.10

= 1.161

-αx =0.056

+αx = 0.042

-αy =0.047

+αy =0.035

Step-6: Calculate the design bending moments shorter span

Positive moment at mid span + mx = αx ×wu× lx2

= 0.047 × 8.25 × 3.102

mx =3.369 KNm

Negative moment at support longer span = - Mx = 0.0565× 8.25× 3.102

= - Mx =4.479 KNm

LONGER SPAN

Positeve moment of mid span = +My = 0.035 × 8.25 × 3.102

= 2.774 KNm
Negative moment of mid span = -My = 0.047 × 8.25 × 3.102

= 3.726 KNm

Step-7: Effcive depth “d” from maximum

2.76 bd2 = 4.479 × 106

d =√

= 40.729mm

Effective depth dpro 100mm > 40.729mm

“ Hence ok ”

Step - 8: Calculate the area of main steel

Shorter span width mid strip =3/4 3.60

= 2.70 m

Longer span width mid strip =3/4 x 3.10

=2.325m

Min area of steel = 0.12/100 1000 120

= 144 mm2

Ast mid span steel along shorter span

+ Mx = 0.87 Fy Ast [ d – Fy Ast / Fck b]

3.369 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +3.369 106 =0


Ast = 95.120 mm2

Ast mid span steel along longer span

+ My = 0.87 Fy Ast [ d – Fy Ast / Fck b]

2.774 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +2.774 106 =0

Ast = 78.049 mm2

steel reinforcement at support

Ast at support along shorter span

- Mx = 0.87 Fy Ast [ d – Fy Ast / Fck b]

4.479 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +4.479 106 =0

Ast = 127.295 mm2

Ast at support along longer span

- My = 0.87 Fy Ast [ d – Fy Ast / Fck b]

3.726 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +3.726 106 =0

Ast = 105.421 mm2

Astmin =144mm2

Ast =127.295mm2
Astrqu=144mm2

Ast =150mm2

Spacing limit

(1) 3d=3x120=360mm
(2) 300mm
Max permitted spacing = 300mm,spacing providing 10mm ϕ bars

At middle of shorter span =1000x78.54/95.120

=825.69mm

At support of shorter span =1000x78.54/127.295

=616.99mm

At middle of longer span =1000x78.54/78.049

=1006.2mm

At middle of shorter span =1000x78.54/105.421

=745.012mm

(Max spacing restricted to 300mm c/c)

Step 9: calculate the edge srip reinforcement

Width of edge strip on either side shorter span =1/8x3.6=0.45

Width of edge strip on either side longer span =1/8x3.1=0.38

Area of steel in edge strip=min area of steel=150mm2

Providing 8mm ϕ spacing s=1000x50.27/150


=335.133mm

Say =300mm c/c

Spacing limit

The spacing should not exceed following

5d(or) 450mm

Say spacing s =300mm c/c

S=300mm<5d<450mm

Hence ok

Step :10 calculate the torsion reinforcement

„at the corner where the slab is discontinuous 2 edges. provided 100%.
Torsion steel

Size of reinforcement = 0.2.lex

=0.2x3.10

0.62 1m

Area of steel required middle at shorter span =120mm2

Area of steel required at per layer of torsion reinforcement =3/4x95.120x1

=75mm2

No of 8mm ϕ bars in each for a length 1m=75/50.27x3.10 4.62 5 nos

Torsion reinforcement need not be provide at the corner having both the
edge continuous
Step:11 Curtailment

Alternate bass are curtailment at 0.1 le from the face of support the full
length bass are taken to top and extended from face of the support for
discontinuous of 0.1 le to taken negative BM

Step:12 Check for shear

Nominal shear force vu=wuxle/2

=8.25x3.10/2

vu =12.787 KN

Nominal shear stress τv = vu/bxd

=12.787/1x100

τv =0.127N/mm2

Permissible shear stress maximum shear = τc=0.72N/mm2

τc> τv

Hence ok

Step:13 check for deflection

Ast=127mm2

Pt=0.16%

dstiff =40.67mm

Hence ok
Step:14 Result

Total depth of slab, D=120mm.

Reinforcement along

Shorter span –Middle strip -10mm ϕ @ 300mm c/c

-edge strip -8mm ϕ @300mm c/c

-at support -10mm ϕ @300mm c/c

Longer span-middle strip -10mm ϕ @300mm c/c

-edge strip -8mm ϕ @300mm c/c

-at support -10mm ϕ @ 300mm c/c


3.1.2. Design of Two way slab

Step-1:

Size of the room = 3.0m x 4.5m

Lx =3.0m Hall
4.5m
Ly =4.5m

=3.0/4.5
3.0m
=1.5< 2

“ Hence the slab is a Two Way Slab”

Step-2: Effective Depth

d=

d =3000/(40x0.8)

d 62.5 100 mm

Provide clear cover =15mm

Diameter of bars =10mm


Over all depth (D) =d+ clear cover+ diameter of bars/2

Over all depth (D) =100+15+10/2

D =120mm

Step- 3: Load calculation

self-weight of slab = Unit Weight × D ×b

=0.12×25 × 1

=3.0KN/m

weathering crouse = 1 KN/m

Impose load = 1.5 KN/m

Total load = 5.5 KN/m

Total design load = 5.5×1.5

=8.625 KN/m

Step - 4: Calculate the eff span

Lx shooter span (i) 3000+100 =3100

=3.1m

(ii) 3000+300 = 3300

=3.30m

Lx = 3.10m

Lylenger span
(iii) 4500+100 =4600
=4.6m
(iv) 4500+300 = 4800
= 4.80mm
Ly = 4.60m

Step-5: Calculate the bending moment Co-efficient

(for one longer edge is discontinuous)

Ratio ly/lx = 4.60/ 3.10

= 1.483

-αx =0.0662

+αx = 0.050

-αy =0.028

+αy =0.037

Step-6: Calculate the design bending moments shorter span

Positive moment at mid span + mx = αx ×wu× lx2

= 0.050 × 8.625 × 3.102

mx =4.010 KNm

Negative moment at support longer span = - Mx = 0.662× 8.625× 3.102

- Mx =5.522 KNm
Longer span

Positeve moment of mid span = +My = 0.028 × 8.625 × 3.102

= 2.335 KNm

Negative moment of mid span = -My = 0.037 × 8.625 × 3.102

= 3.086 KNm

Step-7: Effcive depth “d” from maximum

2.76 bd2 = 5.22 × 106

d =√

= 43.489 mm

Effective depth dpro 100mm > 43.489mm

“ Hence ok ”

Step - 8: Calculate the area of main steel

Shorter span width mid strip =3/4 4.60

= 3.457 m

Longer span width mid strip =3/4 x 3.10

=2.232m

Min area of steel = 0.12/100 1000 120

= 144 mm2

Ast mid span steel along shorter span


+ Mx = 0.87 Fy Ast [ d – Fy Ast / Fck b]

4.171 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +4.171 106 =0

Ast = 118.324 mm2

Ast mid span steel along longer span

+ My = 0.87 Fy Ast [ d – Fy Ast / Fck b]

2.335 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +2.335 106 =0

Ast = 65.531 mm2

steel reinforcement at support

Ast at support along shorter span

- Mx = 0.87 Fy Ast [ d – Fy Ast / Fck b]

5.22 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]

7.49 Ast2- 36105Ast +5.22 106 =0

Ast = 149.019 mm2

Ast at support along longer span

- My = 0.87 Fy Ast [ d – Fy Ast / Fck b]

3.086 106 = 0.87 415 Ast [ 100 – 415 Ast / 20 1000 ]


7.49 Ast2- 36105Ast +3.086 106 =0

Ast = 86.986 mm2

Astmin =150mm2

Ast =149.019mm2

Spacing limit

(1) 3d=3x120=360mm

(2) 300mm
Max permitted spacing = 300mm,spacing providing 10mm ϕ bars

At middle of shorter span =1000x78.54/118.324

=663.770mm

At support of shorter span =1000x78.54/65.531

=1198.5mm

At middle of longer span =1000x78.54/149.019

=527.046mm

At middle of shorter span =1000x78.54/86.986

=902.903mm

(Max spacing restricted to 300mm c/c)

Step 9: calculate the edge srip reinforcement

Width of edge strip on either side shorter span =1/8x3.6=0.45


Width of edge strip on either side longer span =1/8x3.1=0.38

Area of steel in edge strip=min area of steel=150mm2

Providing 8mm ϕ spacing s=1000x50.27/150

=335.133mm

Say =300mm c/c

Spacing limit

The spacing should not exceed following

5d(or) 450mm

Say spacing s =300mm c/c

S=300mm<5d<450mm

Hence ok

Step :10 calculate the torsion reinforcement

„at the corner where the slab is discontinuous 2 edges. provided 100%.
Torsion steel

Size of reinforcement = 0.2.lex

=0.2x3.10

0.62 1m

Area of steel required middle at shorter span =120mm2

Area of steel required at per layer of torsion reinforcement =3/4x118.29x1


=88.695mm2

No of 8mm ϕ bars in each for a length 1m=88.295/50.27x3.10 5.46 6 nos

Provide 4 layer two at and at bottom of 6 nos of 8 mm ϕ bars a length of 1m


at the corner having one edges discontinuous 4 layer (50% torsion)

Torsion reinforcement need not be provide at the corner having one edge
discontinuous

Step:11 Curtailment

Alternate bass are curtailment at 0.1 le from the face of support the full
length bass are taken to top and extended from face of the support for
discontinuous of 0.1 le to taken negative BM

Step:12 Check for shear

Nominal shear force vu=wuxle/2

=8.625x3.10/2

vu =12.787KN

Nominal shear stress τv = vu/bxd

=12.787/1x100

τv =0.127N/mm2

Permissible shear stress maximum shear = τc=0.72N/mm2

τc> τv

Hence ok
Step:14 Result

Total depth of slab, D=120mm.

Reinforcement along

Shorter span –Middle strip -10mm ϕ @ 300mm c/c

-edge strip -8mm ϕ @300mm c/c

-at support -10mm ϕ @300mm c/c

Longer span-middle strip -10mm ϕ @300mm c/c

-edge strip -8mm ϕ @300mm c/c

-at support -10mm ϕ @ 300mm c/c


3.2. DESIGN OF BEAM

3.2.1. Design of doubly reinforced beam


Step – 1: Data

Fck =20N/mm2

Fy=415N/mm2

L =3000mm

Mulimi=2.76bd2

Xumax=0.48d

Step – 2: Size of beam

d = L/12

d = 3000/12
d = 250 mm
Over all depth (D) = d + effective cover + dia/2

=250 + 25+20/2

D=283mm

Say=300mm

d=300-25-20/2

=265mm

bw=2/3d

bw=2/3 x 265

bw=2178mm say 230mm

Step – 3: Load calculation


For slab, consider 1m

Live load = 1.5 KN/m

Weathering course = 1KN/m

Slab weight =10.5KN/m

Self-weight of Beam = l x b x D x unit weight

=0.3 x 0.23 x 1 x 25

=1.725KN/m

Total Load =14.725KN/m

Factored Load =1.5 x 14.725

Wu=22.087KN/m

Step – 4: Bending moment

Mu = Wu x (Le) 2/24

=22.087 x (3.267)2/24

Mu =9.822KN/m

Step – 5: Effective span

1) c/c support =3000+300+3.3m


2) Clear span eff depth =3000+265=3.265

Step – 6: Calculate the limiting moment ,Mu

Mulimi=2.76bd2
Mu1= Mulimi =2.76x230x2672

Mu1=45.254x106N.mm

Step – 7: calculate the execs moment Mux

Mu2=Mu-Mulimi

=45.254x106-9.822x106

Mu2=35.432x106 N.mm

Step – 8: Calculate the area of tension steel (Ast)

Ast= Ast1+ Ast2

Area of steel required to resist Mulim,Ast= Mulim/0.87.fy.(d-0.42 Xumax)

Xumax =0.48d

=0.48x267

=128.16mm

Ast1=45.254x106/0.87x415(267-0.42x128.16)

=587.97mm2

d'=25+20/2=33mm 40mm

Area of steel required to resist Mulimi Ast2=Mux/0.87.fy(d-d')

=35.432x106/0.87x415(267-40)

Ast2=432.31mm2

Area tension steel Ast= Ast1+ Ast2


=587.97+432.31

=1020.29mm2

Assuming 20mm ϕ bars

No of bars =1020.29/ π /4x202

=3.24nos 4nos

Provide 4nos of 20mm ϕ bars

Step – 9: Calculate the area of compression steel

fsc=[0.0035[(xumax-d')/ xumax]] 2x105

xumax=128.6mm

d'=33mm

fsc=519.4N/mm2

Area of compression steel,Asc=Mux/ fsc(d-d')

=35.432x106/519.49(267-40)

=300.6461mm2

Assuming 16mm ϕ bars

o of bars 1.909nos 2nos

Step – 10: Check for shear

τv=vu /b×d [to refer Pg.no:72- IS456:2000]

=33.130 x103/300 x 230


τv =0.480N/mm2

Percentage of Ast = 100×Ast/bd

= (100×784.820) / (300×230)

τc=0.62N/mm2

τc>τv

So Shear Reinforcement is provided

Shear reinforcement

Balance shear Vus = Vu - τcbd [to refer Pg.no:73- IS456:2000]

= 33.13×106 – (0.62×300×230)

=9.65 KN

Use 10mm ϕ, 2Legged vertical stirrups

Asv (π×102)/ 4

= 78.53mm2

Sv=

=764.744mm
RESULT:

Effective depth d =265 mm

Overall depth D = 300mm

Size of beam =230x300mm

Ast provide 4no`s of 20mm ϕ of bar

Asc provide 2no`s of 16mm ϕ of bar


3.2.2. Design of doubly reinforce beam

Step – 1: Data

Fck =20N/mm2

Fy=415N/mm2

L =4500mm

Mulimi=2.76bd2

Xumax=0.48d

Step – 2: Size of beam

d = L/12

d = 4500/12
d = 375 mm
Over all depth (D) = d + effective cover + dia/2

=375 + 25+20/2

D=410mm

Say=300mm

d=300-25-20/2

=265mm

bw=2/3d

bw=2/3 x 265

bw=178mm say 230mm


Step – 3: Load calculation

For slab, consider 1m

Live load = 1.5 KN/m

Weathering course = 1KN/m

Slab weight =15.186KN/m

Self-weight of Beam = l x b x D x unit weight

=0.3 x 0.23 x 1 x 25

=1.725KN/m

Total Load =19.411KN/m

Factored Load =1.5 x 19.411

Wu=29.11KN/m

Step – 4: Bending moment

Mu = Wu x (Le) 2/24

=29.11 x (4.767)2/24

Mu =24.563KN/m

Step – 5: Effective span

1) c/c support =4500+300=4.8m


2) Clear span eff depth =4500+265=4.265

Step – 6: Calculate the limiting moment ,Mu


Mulimi=2.76bd2

Mu1= Mulimi =2.76x230x2672

Mu1=45.25x106N.mm

Step – 7: calculate the execs moment Mux

Mu2=Mu1-Mulimi

=45.25x106-24.563x106

Mu2=20.687x106 N.mm

Step – 8: Calculate the area of tension steel (Ast)

Ast= Ast1+ Ast2

Area of steel required to resist Mulim,Ast= Mulim/0.87.fy.(d-0.42 Xumax)

Xumax =0.48d

=0.48x267

=128.16mm

Ast1=45.25x106/0.87x415(230-0.42x128.16)

=711.397mm2

d'=25+20/2=33mm 40mm

Area of steel required to resist Mulimi Ast2=Mu2/0.87.fy(d-d')

=20.687x106/0.87x415(267-40)

Ast2=252.40mm2
Area tension steel Ast= Ast1+ Ast2

=711.397+252.40

=963.797mm2

Assuming 20mm ϕ bars

No of bars =963.797/ π /4x202

=3.07nos 4nos

Provide 4nos of 20mm ϕ bars

Step – 8: Calculate the area of compression steel

fsc=[0.0035[(xumax-d')/ xumax]] 2x105

xumax=128.6mm

d'=33mm 40mm

fsc=519.756N/mm2

Area of compression steel,Asc=Mu2/ fsc(d-d')

=20.687x106/519.49(267-40)

=175.42mm2

Assuming 16mm ϕ bars

No of bars=175.42/л/4x162

=1.08nos 2nos
Step – 9: Check for shear

τv=vu /b×d [to refer Pg.no:72- IS456:2000]

=33.130 x103/300 x 230

τv =0.480N/mm2

Percentage of Ast = 100×Ast/bd

= (100×784.820) / (300×230)

τc=0.62N/mm2

τc>τv

So Shear Reinforcement is provided

Shear reinforcement

Balance shear Vus = Vu - τcbd [to refer Pg.no:73- IS456:2000]

= 33.13×106 – (0.62×300×230)

=9.65 KN

Use 10mm ϕ, 2Legged vertical stirrups

Asv (π×102)/ 4

= 78.53mm2

Sv=

=764.744mm
RESULT:

Effective depth d =265 mm

Overall depth D = 300mm

Size of beam =230x300mm

Ast provide 4no`s of 20mm ϕ of bar

Asc provide 2no`s of 16mm ϕ of bar


3.2.3.DESIGN OF SUNSHADE

1. DATA:

Assume projection of sunshade = 600 mm

Assume an uniform thickness of sunshade = 100 mm

Effective Depth = 80 mm

2. LOAD CALCULATION:

Consider 1m length of sunshade

Self weight of sunshade = D X B X L x 25

= 0.1 x 0.6 x 1 x 25

= 1.5 KN/m

Total design load, Wu = 1.5 x 1.5

= 2.25 KN/m

3. DESIGN BENDING MOMENT:

Bending moment, Mu =

= 0.405 KNm

4. AREA OF TENSION STEEL:

Mu = 0.87 x fy x Ast x d x [ ]

0.405 x 106 = 0.87 x 415Ast x 80 x [ ]

Ast = 14.07 mm2

Ast min = 0.12% x b x D


= 0.0012 x 1000 x 100

= 120 mm2

5.SPACING:

Spacing of 6 mm dia. bars

Sv = x 1000

= x 1000

= 235.62 say 230 mm

Maximum permitted spacing is the least of:

(i) 3d = 3 x 80 = 240 mm

(ii) 300 mm

PROVIDE:

Main Reinforcement = 8 mm dia. @ 230 mm c/c distance.

Distributors = 6 mm dia. @ 230 mm c/c distance.

RESULT:

1.Over all depth of sunshade = 100 mm

2.Effective depth of sunshade = 80 mm

3.Main Reinforcement = 8 mm dia. @ 230 mm c/c distance.

4.Distributors = 6 mm dia. @ 230 mm c/c distance.


3.4. DESIGN OF COLUMN

3.4.1. DESIGN OF SQUARE COLUMN

Step 1: Data

load = (beam load× (distance/ 2))

= (14.725 × (3.25/2))

load =23.925KN

Factor load = 1.5 × Axial load

=1.5×23.925

=35.892KN

Area = 300mm x 300mm

Step 2:Caculate the slenderness ratio ,λ

λ =3250/300=10.833<12

It is a short column

Step 3: To Calculate the eccentricity :

1) emin=L/500+D/30
=3250/500+300/30
=16.5mm< emin=20mm
2) e=0.05xD=0.05x300

=15mm<20mm

Load is assumed as axial


Step 4:To Calculate Actual Asc:

PU =0.4 x fck Ac+ 0.67 x fy x Asc [to refer Pg.no:71- IS456:2000]

Ag=300x300

=90000mm2

Ac=Ag-Asc

=90000-Asc

35.892x103=0.4x20(90000-Asc)+(0.67x415xAsc)

35.892x103=720000-8 Asc+278.05 Asc

Asc=684108/270.05

Asc =2533.26mm2

Assuming 20mm ϕ bars

No of bars= Asc/(π/4x202)

8.06nos 8nos

Are to be Provided 8nos of 20mm ϕ bars

Step 5: Check for Asc :

Actual Asc=8x πx202/4

=2827.43mm2

% Asc=100(2827.43/300x300)=3.14%
3.14<Amax=4%

3.14>Amin=0.8%

Hence ok

Step 6: lateral ties [to refer Pg.no:45- IS456:2000]

(i) diameter
1) 6mm
2) 1/4x larger longitudinal bar dia=1/4x20=5mm Say 8mmϕ
(ii) Pitch
Pitch is least of the following
(i) LLD = 300mm
(ii) 16 x smallest longitudinal bar=16 x 20=320mm
(iii) 300mm

Is to be Provide 8mm diameter of bar at 300mm c/c

RESULT:

Size of column = 300mm x 300mm

Are to be Provided 8no`s of 20mm dia of bars

Is to be Provide 8mm lateral ties @300mm c/c


3.5. DESIGN OF FOOTING

3.5.1. DESIGN OF COLUMN BASE (FOOTING)

Step 1: Data

Column total load =23.925KN/m

Column size =300 x 300mm

M20, Fe415 grade

Safe bearing capacity of soil =100KN/m2 (fine sand & silt)

Step 2: Load calculation:

Area of footing = W+W1/ Safe bearing capacity

Axial load = column load × no of floors

= 23.925× 1

W =23.925KN/m

Self-weight of footing (W1) =45% of w

W1=45/100 x 23.925

=10.766KN

Total load =23.925+ 10.766

=34.691KN

Design Load =34.69×1.5

=52.035 KN
Size of Footing:

Area of footing = w+w1/ Safe bearing capacity

=34.691/100

=0.345m2

A =B x L

L =B

0.345 =B2

B=1.5m

L =1 x 1.5

L =1.5m

Size of footing =1.5m x 1.5m

Step 3: To calculate Design Net Upward Pressure:

q =Pu/A=Column load/footing area

= 1.5x34.691/1.5

q =23.12KN/m2

Projection of Longer direction= (1500-300)/2

=600mm

Projection of shorter direction= (1500-300)/2

=600mm
Step4: To calculate the Bending Moment:

Mu1 =q x area of hatched portion x distance of C.G „a‟

=23.12 x (0.6 x 1.5) x (0.6/2)

Mu1 =6.243KNm

Mu2=6.243KNm

Step 5: To calculate Effective Depth:

d =√

d =√

=86.83mm ~100mm

Provide an overall depth = 100+50+16/2+16

=174mm ~200mm

Assuming 50mm cover &16mm ϕ bars

Eff depth at column face = 200-50-16-16/2 =126mm

To be safe in shear depth on overall depth

D = 2x200=400mm

Eff depth of top layer,d=400-50-16-16/2=326mm

D = 400mm

D = 326mm
Step 6 : To calculate the Main Reinforcement

In Longer Span:

Mu=0.87 x fyxAst x (d-(fyxAst)/fck x b)

6.243x106 =0.87 x 415 x Ast(126-(415 x Ast)/20 x 300)

Ast=149.50mm2

Assume 12mm diameter of bar

No of bar = Ast/ast

= (149.50/ (π/4 x122))

o of bar 4 no‟s ~6 no‟s

Is to be Provide 6no‟s of 12mm dia of bar @ 200 mm spacing

In Shorter Span:

Mu=0.87 x fyxAst x (d-(fyxAst)/fck x b)

6.243x106=0.87 x 415 x Ast(200- ((415 x Ast)/ (20 x 300)))

Ast= 149.50mm2

No of bar = Ast/ast

= (4149.50/ (π/4 x 122))

o of bar 4no‟s ~ 6 no‟s

Provide 6no‟s of 12mm dia of bar @ 300mm spacing

%Ast = 100x4x113.04/300x126
=1.19%

Development length:

Ld= [ reference Pg.no:42- IS456:2000]

= (0.87×415×12)/ (4×1.2x1.6)

=564.14mm

Longer direction=600-50

=550mm

Shorter direction=600-50

=550mm

Step 7: Check for Shear:

Critical section „bb‟ lies at a distance d 126mm

Distance of section from edge of footing=600-126=474mm

Breadth of column footing at this seelian =1500-2x474=652mm

Shear force across section „bb‟ Vb=(1.5+0.652/2) x0.42x23.12

Vb=4.748KN

ominal shear ,τv =V/bd

=4.748x103/326x652

τv =0.022N/mm2

%Ast=1.19
τc = 0.62+(0.67-0.62/2) x(1.19-1.00)

τc =0.624N/mm

τv<τc

Hence Safe

Step 8: Calculation & Check ins For Punching Shear Stress:

d/2=126/2

=63mm

Distance of section „ccc‟ from edge of footing 600-63=537mm

Breadth of section = 1500-2x537

=426mm depth of this section

Punching shear force,

Vc= qx(1.52-0.426)

=23.12x(1.52-0.426)

Vc =42.17KN

ominal shear stress,τvc =Vu/bd

τvc= (42.17× 103)/ (426 ×126)

=0.78N/mm2

Design shear stress in concrete in two way shear=Ks. τc

Ks=1m for square column


τc = 0.25√

=0.25√

=1.118N/mm2

Design shear stress in concrete Ks. τc =1x1.118

=1.118N/mm2

τv < τc

Hence safe in punching shear stress

Step 9: Check for Bearing stress:

Actual bearing stress = design load on column /Top area of column

= 1.5x23.925x103/300x300

= 0.40 N/mm2


Permissible bearing stress = 0.45xfckx

A1=bottom area of rustum of pyramid = [300+(4x400)]x[300+(4x400)]

A1 = 1.9x1.9=3.61m2

But restricted to A1=1.5x1.5=2.25m2

Loaded area at the column base = 0.3x0.3= 0.09m2


=√2.25/0.09= 5 restricted to 2

Permissible bearing stress =0.30xfckx2


=0.3x20x2= 12N/mm2

Actual bearing stress < permissible bearing stress

Hence safe

Step 10:check for bearing capacity of soil

Column load = 23.925 KN

Self weight footing = 1.5x1.5x0.2x25 = 11.25 KN

Total load on the soil = 23.925+11.25=35.175 KN

Pressure on the soil = 35.175/1.5x1.5

= 15.63 KN/m2 < 100 KN/m2

Hence safe

Conclusion for footing:

Effective depth d =100mm

Overall depth D = 200mm

Size of footing L =1.5m x 1.5m

Is to be Provide 6no‟s of 12mm dia of bar @ 300mm spacing


CHAPTER-8

PWD SCHEDULE OF RATE 2016-2017


COST OF LABOUR

1. Mason 1 class - 496.00 / each / day

2. Mason 2 class - 444.00 / each / day

3. Mazdoor grade 1 - 310.00 / each / day

4. Mazdoor grade 2 - 280.00 / each / day

5. Painter 1 class - 397.00 / each / day

6. Centering charges - 300.00 m2

7. Steel fabrication - 8.00/kg

8. Mixing charge - 110 / m3

9. Grinding charges - 184/ m3

10. Labour for Curing, Centering - 45.00/ m3

11. Labour for Plastering, curing - 80.00/ m2

12. Labour for earthwork excavation - 40.00/ m3


CHAPTER-9
COST OF MATERIAL AT SITE

1.Cement - 7000 / tone

2. Sand - 1800 / m3

3. Lime - 1200 / m3

4. Steel - 49150 / tone

5.Binding work - 60 / kg

6. Brick (190x90x90 mm) - 5000 / 1000 Nos

7. Broken stone (20 mm) - 1350 / m3

8. Broken stone (40 mm) - 1000 / m3

9. Crude oil - 50 / kg

10. Paint prime coat - 120 / liter

11. Linseed oil - 50 / liter

12. Ready mix paint - 180 / liter

13. Cum, Conjee , water, etc(L.S) - 80/100 m2

14. Sundries - 75/ m2


CHAPTER-10
PREPARATION OF DATA
CEMENT MORTER 1:3 FOR 1m3 :
QTY DESCRIPTION RATE UNIT AMOUNT
1440/3=480kg Cement 7000.00 Tone 3360.00
3 3
1m Sand 1800.00 1m 1800.00
3 3
1m Mixing charge 110.00 1m 110.00
3
Rate for 1m = Rs . 5270.00 /-
CEMENT MORTER 1:4 FOR 1m3:
QTY DESCRIPTION RATE UNIT AMOUNT
1440/4=360kg Cement 7000.00 Tone 2520.00
3 3
1m Sand 1800.00 1m 1800.00
3 3
1m Mixing charge 110.00 1m 110.00
3
Rate for 1m = Rs . 4430.00 /-
CEMENT MORTER 1:5 FOR -1m3
QTY DESCRIPTION RATE UNIT AMOUNT
1440/5=288kg Cement 7000.00 Tone 2016.00
3 3
1m Sand 1800.00 1m 1800.00
3 3
1m Mixing charge 110.00 1m 110.00
3
Rate for 1m = Rs . 3926.00 /-
CEMENT MORTER 1:2 FOR- 1m3
QTY DESCRIPTION RATE UNIT AMOUNT
3 3
0.5m Lime 1200.00 1m 600.00
3 3
1m Sand 1800.00 1m 1800.00
3 3
1m grinding charge 184.00 1m 184.00
3
Rate for 1m = Rs . 2584.00 /-
EARTH WORK EXCAVATION IN FOUNDATION -1m3
QTY DESCRIPTION UNIT AMOUNT
RATE
3
1m Earthwork 40.0 1m3 40.0
excavation
Rate for 1m3 = Rs.40.0/-
PLAIN CEMENT CONCRETE 1:4:8-10m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
5m Broken stone 1000.00 m3 5000.00
(40mm)
3
2.75m Cement mortar 1:4 4430.00 m3 12182.5
1.8Nos Mason 2 class 444.00 Each 799.2
8Nos Mazdoor grade 1 310.00 Each 2480.00
10Nos Mazdoor grade 2 280.00 Each 2800.00
Rate for 1m3 = Rs.23261.7/-
CEMENT CONCRETE 1:5:10 – 10m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
5.0m Broken stone 1000.00 m3 5000.00
(40mm)
3
2.75m Cement mortar 1:5 3926.00 m3 12182.5
1.80Nos Mason 2 class 444.00 Each 799.2
5Nos Mazdoor grade 1 310.00 Each 1550.00
10 Nos Mazdoor grade 2 280.00 Each 2800.00
3
Rate for 1m = Rs.223317.17/-

FLOORING WITH C.C 1:5:10 , 130mm tk AND PLASTERED OVER WITH


C.M 1:3,20 mm tk
QTY DESCRIPTION RATE UNIT AMOUNT
3
1.3m Cement concrete 1:5:10 3839.27 m3 4991.05
3 3
0.2m Cement mortar 1:5 3926.70 m 785.2
L.s Labour for 80.00 _ 80.00
plastering,curing…etc
Rate for 1m3 =Rs.585.62/-
BRICK WORK IN CM 1:5 USING GRADE 7.5 BRICKS – 10m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
5.0m Bricks (190x90x90mm) 5000.00 Nos 25000.00
3 3
2.2m Cement mortar 1:5 3926.00 m 5424.54
3.0Nos Mason 1 class 496.00 Each 1488.00
8 Nos Mason 2 class 444.00 Each 3552.00
5.0Nos Mazdoor grade 1 310.00 Each 1550.00
10 Nos Mazdoor grade 2 280.00 Each 2800.00
3
Rate for 1m = Rs.39814.54/-
CONCRETE BROKEN STONE IN LIME MORTAR 1:2:5 -10m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
5m Broken stone (40mm) 1000.00 m3 5000.00
3 3
3.8m lime mortar 1:2 1000.00 m 3800.00
1.80Nos Mason 2 class 444.00 Each 799.20
5Nos Mazdoor grade 1 310.00 Each 1550.00
10Nos Mazdoor grade 2 280.00 Each 2800.00
3
Rate for 1m = Rs.13949.2/-
FIOORING WITH LIME CONCRETE, 75mm THICK IN LIME MORTER
1:2 & RENDERTED SMOOTH WITH CEMENT– 10m2
QTY DESCRIPTION RATE UNIT AMOUNT
3
5.0m Concrete broken stone in LM 2429.4 m3 23103.59
1:2
9kg Cement 7000.0 1ton 63.00
0.25Nos Mason 1 class 496.00 Each 124.00
2Nos Mason 2 class 444.00 Each 888.00
3
Rate for 1m = Rs.823.00/-
PLASTERING WITH CM 1:5,15mm THICK FOR
SUPER STRUCTURE-10m2
QTY DESCRIPTION RATE UNIT AMOUNT
3
0.18m cement mortar 1:5 3926.00 m3 706.68
1.5Nos Mason 1 class 496.00 Each 744.00
0.5Nos Mazdoor grade 1 310.00 Each 155.00
2Nos Mazdoor grade 2 280.00 Each 560.00
2
Rate for 1m = Rs.2165.68/-
PLASTERING WITH CM 1:3,10mm THICK FOR
CEILING PLASTERING-10m2
QTY DESCRIPTION RATE UNIT AMOUNT
3
0.1m cement mortar 1:3 5270.00 m3 527.00
1.1Nos Mason 1 class 496.00 Each 545.60
1.1Nos Mazdoor grade 1 310.00 Each 341.00
1.1Nos Mazdoor grade 2 280.00 Each 308.00
2
Rate for 10m = 1721.6/-
PAINTING THE NEW WOOD WORK PRIME COAT-10m2
QTY DESCRIPTION RATE UNIT AMOUNT
0.61 lit Prime coat 120.00 Litre 73.20
0.61 lit Linseed oil twice boiled 50.00 Litre 30.50
0.7Nos Painter I class 397.00 Each 277.90
L.s Sundries _ _ 75.00
2
Rate for 10m = Rs.456.61/-
Rate for 1m2 = Rs.45.661/-
PAINTING 2 COATS WITH READY MIXED PAINT-10m2
QTY DESCRIPTION RATE UNIT AMOUNT
2.55 lit Ready mixed paint 180.00 Litre 459.00
1.2 Nos Paint 1 class 397.00 Each 476.4.00
2
Rate for 10m = Rs.935.4/-
Rate for 1m2 = Rs.93.54/-

PAINTING THE NEW WOOD WORK TWO COATS


OVER PRIME COAT-10m2
QTY DESCRIPTION RATE UNIT AMOUNT
2
8m Prime coat 120.00 8m2 120.00
8m2 Painting 2 coats 100.00 8m2 800.00
Rate for 10m2 = Rs.920.00/-
Rate for 10m2 = Rs.92.00/-

WHITE WASHING WALLS AND CEILING WITH LIME


TWO COATS – 10m2
QTY DESCRIPTION RATE UNIT AMOUNT
3
0.07m Shell lime fine screened 1200.00 m3 84.00
L.s Cum, conjee, water…etc 80 80m2 80.00
L.s Sundries _ 75m2 75.00
1.6Nos Mason II class 444.00 Each 710.40
0.5 Nos Mazdoor grade I 310.00 Each 155.00
2.7Nos Mazdoor grade II 280.00 Each 756.00
2
Rate for 10m = Rs.1860.00/-
Rate for 1m2 = Rs.186.00/-

DPC IN CM 1:3 20mm THICK USING 5% CRUDE OIL– 10m2


QTY DESCRIPTION RATE UNIT AMOUNT
3
0.21m Cement mortar 1:5 3926.00 m3 824.46
1.1Nos Mason 1 class 496.00 Each 545.60
1.1Nos Mason 2 class 444.00 Each 488.40
2.2Nos Mazdoor grade 1 310.00 Each 682.00
1.1Nos Mazdoor grade 2 280.00 Each 308.00
5kg Crude oil 50.00 Kg 250.00
2
Rate for 1m = Rs.3098.46/-
Rate for 10m2 = Rs.309.846/-

SAND FILLING– 1m3


QTY DESCRIPTION RATE UNIT AMOUNT
3
1m Sand 1800 m3 1800
1.1Nos Mason 1 class 496.00 m3 545.6
Rate for 1m3 = Rs.2345,60/-
CEMENT CONCRETE 1:1.5:3 – 10m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
4.56m Broken stone (20mm) 1350.00 m3 6156.00
4.228m3 Sand 1800.00 m3 7596.00
3110.5kg Cement 7000.00 Tone 217735.50
3.5Nos Mason 2 class 444.00 Each 1554.00
17Nos Mazdoor grade 1 310.00 Each 5270.00
22Nos Mazdoor grade 2 280.00 Each 6160.00
3
Rate for 10m = Rs.244471.5/-
Rate for 1m3 = Rs.2444.715/-

PCC 1:4:8 FOR COLUMN BASE– 1m3


QTY DESCRIPTION RATE UNIT AMOUNT
3
1m Pcc 1:4:8 4031.66 m3 4031..66
1.1Nos Labour for curing centering 45.00 _ 45.00
3
Rate for 1m = Rs.4081.16/-
RCC 1:11/2:3 IN COLUMN FOOTING-1m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
1m Cement concrete 1:1.5:3 4168.21 m3 4168.21
40 kg Steel bar 49150.00 Tone 1966.00
0.4kg Binding wire 60.00 Kg 24.00
2 2
1.82m Centering charges 300.00 m 546.00
40kg Steel fabrication 8.00 Kg 320.00
3
Rate for 1m = Rs.7024.21/-
RCC 1:11/2:3 IN 300x270mm SIZE BEAM-1m3
QTY DESCRIPTION RATE UNIT AMOUNT
3 3
1m Cement concrete 1:1.5:3 4168.21 m 4168.21
120kg Steel bar 49150.0 Tone 5898.00
1.2kg Binding wire 60.00 Kg 72.00
2 2
8.89m Centering charges 300.00 m 2667.00
120kg Steel fabrication 8.00 Kg 960.00
3
Rate for 1m = Rs.13765.21/-
COLOUR WASHING 2 COATS FOR WALLS AND CEILING– 1m2
QTY DESCRIPTION RATE UNIT AMOUNT
2
1m Rate as per white wash 11.85 m2 11.85
2
1.1Nos Add 50% extra 11.85 m 5.93
Rate for 1m3 = Rs.17.78/-
RCC 1:11/2:3 IN 300mmx150mm SIZE LINTEL-1m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
1m Cement concrete 1:1.5:3 5324.90 m3 5324.9
120 kg Steel bar 49150.00 Tone 5898.00
1.2kg Binding wire 60.00 Kg 72.00
2
13.33m Centering charges 300.00 m2 3999.00
120kg Steel fabrication 8.00 Kg 960.00
3
Rate for 1m = Rs.16253.9/-

RCC 1:11/2:3 IN 100mm THICK SUNSHADE-1m3


QTY DESCRIPTION RATE UNIT AMOUNT
3
1m Cement concrete 1:1.5:3 5324.9 m3 5324.9
80 kg Steel bar 49150 Tone 3932.00
0.8kg Binding wire 60.00 Kg 48.00
2
10.00m Centering charges 300.00 m2 3000.00
80kg Steel fabrication 8.00 Kg 640.00
3
Rate for 1m = Rs.40221.29/-
RCC 1:11/2:3 IN 130mm THICK FLOOR SLAB-1m3
QTY DESCRIPTION RATE UNIT AMOUNT
3
1m Cement concrete 1:1.5:3 5324.9 m3 5324.9
80 kg Steel bar 49150 Tone 3932.00
0.8kg Binding wire 60.00 Kg 48.00
2
7.14m Centering charges 300.00 m2 2142.00
80kg Steel fabrication 8.00 Kg 640.00
3
Rate for 1m = Rs.39401.54/-
CHAPTER-11
DETAILED ESTIMATE
Sl.No DESCRIPTION No’s L(m) B(m) D(m) Qty Remarks
1 Earthwork excavation
(a) (b) Column 9 1.5 1.5 1.8 36.45

Plinth Beam
Wall around 1 30 0.23 0.3 2.07

C/W file,store room 2 3.0 0.23 0.3 0.207

C/W Hall room 1 6.2 0.23 0.3 0.427

TOTAL=39.154m3
2 P.C.C 1:4:8 for
foundation
(a) (b) Column 9 1.5 1.5 0.2 4.05
TOTAL=4.05m3
3 R.C.C 1:2:4 for columns,
beams, lintels, roof
Column
Level base 9 1.5 1.5 0.2 4.05
Tripizontal A1= (1.5×1.5)
A1=2.25
= h/3 (A1+A2+√A1+A2) A2= (0.23×0.23)
A1= (1.5×1.5) A2=0.09
A1=2.25
A2=0.09
0.580 5.22
= 0.45/3[ (2.25+0.09)+√
9
2.25×0.09]

=0.15 (3.869)
=0.580 m2

Column below

9 0.3 0.3 0.2 0.162

Plinth beam
Wall around 1 30 0.23 0.3 2.07
C/W file,store room 1 3 0.23 0.3 0.207

C/W hall 1 6.2 0.23 0.3 0.427

Roof slab 1 6.8 8.8 0.13 7.77

Roof beam
1 30 0.23 0.35 2.415

C/W file&store 1 3 0.23 0.35 0.241

C/W hall 1 6.2 0.23 0.35 0.499

Lintel
windows 7 1.5 0.2 0.15 0.15

TOTAL=23.211 m3

Brick work in CM 1:5 for


4 Super structure

Wall around 1 30 0.3 3.57 12.57


C/W file& store 2 3.0 0.3 3.9 7.02
c/w hall 1 6.2 0.3 6.9 12.83

(b)Steps 1st 2 1.0 0.9 0.15 0.27


2nd 2 1.0 0.6 0.15 0.18
3rd 2 1.0 0.3 0.15 0.09
TOTAL=32.96m3
Deduction for
Column 9 0.3 0.3 4.17 3.37
Windows (W) 7 1.5 0.2 1.5 3.15

TOTAL=6.52m3
Total Brick Work=26.44m3
5 Earth Filling inside the
basement
Inside the hall 1 6.2 4.5 0.45 12.55
Inside the file 1 3.0 3.5 0.45 4.725
Inside the store 1 3.0 3.5 0.45 4.725

TOTAL 22 m3
6 Ceiling Plastering with
CM 1:3
` Inside the hall 1 6.2 4.5 29.9
Inside the store 1 3.0 3.5 - 10.5
Inside the file 1 3.0 3.5 - 10.5

Sunshade(top & bottom) 1x 2 31.2 0.6 - 37.44


TOTAL=88.34m2
7 Wall Plastering with CM
1:5 12mm thick

Outside Wall around 1 31.2 6.8 212.16


Inside the hall 1 21.4 2.97 63.558
Inside the sotre 1 13 - 2.97 38.61
Inside the file room 1 13 - 2.97 38.61

Steps(rise portion)
1st 2 0.9 0.15 0.27
2nd 2 0.6 0.15 0.18
3rd 2 0.3 0.15 0.09
Tread portion 6 1.0 0.3 1.8
Parapet wall at top 1 30 0.3 9.0
Inside 1 31.2 0.6 18.72
TOTAL=382.99m2
Deduction for
Window(w) 7 1.5 1.5 15.75
Door(M.D) 1 1.0 2.1 2.1
Door(D) 2 0.9 - 2.1 3.78
TOTAL=21.6 m2
Total Plastering=361.36m2
8 Floor Finishing with CM
1:4 20mm thick

Inside the hall 1 6.2 4.5 27.9


Inside the store 1 3.0 3.5 - 10.5
Inside the file 1 3.0 3.5 - 10.5

TOTAL 48.9m2
10 Supply and fixing of
windows
Windows (W) 7 7 no‟s
Weathering course
11
Floor slab 1 8 6.2 49.6
TOTAL=49.6m2
12 White washing 2 coats ─ ─ ─ ─ 449.7m2
over the plastered area
13 Color washing 2 coats ─ ─ ─ ─ 361.36m2
13 Painting two coats with
good emulsion paint over
priming coat
Windows (W) 7 1.5 1.5 15.75
Door (M.D) 1 1.0 2.1 2.12
Doors(D) 2 0.9 - 2.1 3.78
TOTAL=21.63m2
14 Providing electrification ─ ─ ─ ─ L.S

15 Providing plumbing ─ ─ ─ ─ L.S


works
16 Providing drainage works ─ ─ ─ ─ L.S
17 Rainwater Harvesting ─ ─ ─ ─ L.S
system
18 Pelly works & ─ ─ ─ ─ L.S
supervision
19 Thermo plasting ─ ─ ─ ─ L.S
20 Interior ─ ─ ─ ─ L.S
CHAPTER-12
ABSTRACT ESTIMATE
S.N QTY DESCRIPTION RATE UNIT AMOUNT
3
1 39.154 m Earth work excavation 300.0 m3 19591
2 4.05m3 P.C.C 1:4:8 in foundation 2345.92 m3 65686
3 180.30 m3 R.C.C 1:1.5:3 in column footing 6700.21 m3 1208048
4 47.34 m3 R.C.C 1:1.5:3 in column 1703.9 m3 80663
5 5.859 m3 R.C.C 1:1.5:3 in Plinth beam & 12450.21 m3 105700
Roof beam
6 20m2 D.P.C in C.M 1:3,20 mm TK 125.38 m² 2508
3
7 26.44 m B.W in C.M 1:5 413.66 m3 30271
8 22 m3 Sand filling 106.93 m3 7860

9 48.9m2 Flooring with C.C1:5:10 417.92 m² 61434


3
10 7.77m R.C.C 1:1.5:3 in floor slab 400.4 m3 18079
11 6.59m3 R.C.C 1:1.5:3 in lintels 598.8 m3 3946
12 33.84m3 R.C.C 1:1.5:3 in sun shade 487.6 m3 16298
13 49.6m2 W.C with lime concrete 75 mm 83.00 m² 23825
14 361.36m2 Plastering with C.M 1:5 in S.S 151.43 m² 120259
15 mm TK
15 88.34m2 White washing 2 coats 14.2 m² 6751

16 361.36m2 Color washing 17.78 m² 14650

17 16 m2 Iron rolling shutter 1000 m² 16000


18 21.63m2 Painting door 100.12 m² 2894
19 48.9 m2 Flooring tiles finish with 20 mm 626.65 m² 92117
thick
20 100.8m2 Glass works 2000 m² 201600
21 6000Nos Pressed tiles 6.0 Nos 36000
22 7 Glazed window 1900 Nos 19000
23 4 Ventilator 1500 m² 6000
24 18 Glazed door 2100 Nos 37800

Total cost of building=2196980 /-

25 L.S Water supplying, electric fittings 25000 L.S 25000


,…… etc.
26 L.S 1 % of architectural works 1% L.S 21972
27 L.S Thermo plasting 5% 43852
28 L.S Septic tank 10000 L.S 10000
29 L.S Rain water harvesting 10000 L.S 10000
Total cost of building =2302086/-
Cost of per 1 m2 plinth area =7648 /-

CHAPTER-13
BAR BENDING SCHEDULE FOR SLAB-1

Sl. Dia Remark Shape Length No‟s Weight Total


No (m) (n/m) Weight in N

1. 10# Main Rft. 215

170
3.73 4 6.1 91.01

3345

2. 10# Main Rft. 215


170 3.73 4 6.1 91.01
3345

3. 10# Distributor 3470 3.47 4 6.1 84.66


s

Total = 266.68N

Add 5 % extra for wastages in cutting, overlapping etc. =13.33

Total quantity of steel required =280.01N

TOTAL QUANTITY OF STEEL REQUIRED

size of slab = 3.5 m x 3.5 m

No of slab = 12

Total weight of reinforcement =12x 280.01

= 3360.12 N
BAR BENDING SCHEDULE FOR SLAB-2

Sl. Dia Remark Shape Length No‟s Weight Total


No (m) (n/m) Weight in N
1. 10# Main Rft. 215 7.23 4 6.1 176.41

170

6845

2. 10# Main Rft. 7.23 4 6.1 176.41


215
170
6845

3. 10# Distributor 6970 6.97 4 6.1 170.06


s

Total = 522.88N

Add 5 % extra for wastages in cutting, overlapping etc. = 26.14

Total quantity of steel required = 549.02N

TOTAL QUANTITY OF STEEL REQUIRED

size of slab = 7 m x 3.5 m

No of slab = 6

Total weight of reinforcement =6x 549.02

=3294.12 N
BENDING SCHEDULE OF STRUCTURAL BEAM-1

Sl.No Position Dia Shape Length No`s Weight in Total


of in (m) (N/m) weight in
bar (N)
1 Tension 16# 3.65 3 15.7 171.915

2 Compression 16# 3.65 2 15.7 114,61

5 Stirrups 8# 1.04 12 3.9 48.67


250

350

Total = 335.19N

Add 5% extra for wastage in cutting over lapping, etc. = 16.75 N

Total quantity of steel required = 351.94N

TOTAL QUANTITY OF STEEL REQUIRED


Span = 3.35 m

No of beams = 37

Total weight of reinforcement =37 x 351.94

= 13021.78N
BENDING SCHEDULE OF STRUCTURAL BEAM-2

Sl.No Position Dia Shape Length No`s Weight in Total


of in (m) (N/m) weight in
bar (N)
1 Tension 16# 7.15 3 15.7 336.76

2 Compression 16# 7.15 2 15.7 224.51

5 Stirrups 8# 350
1.64 21 3.9 134.3
550

Total =695.57N

Add 5% extra for wastage in cutting over lapping, etc. = 34.77N

Total quantity of steel required = 730.34N

TOTAL QUANTITY OF STEEL REQUIRED


Span = 7 m

No of beams = 6

Total weight of reinforcement = 6x730.34

= 4382.04N
BAR BENDING SCHEDULE FOR COLUMN & FOOTING

Sl. Remark Shape Dia Length No‟s Weight Total


No (m) (n/m) Weight in N
1. Footing
(i) Shorter side 16# 1.90 10 15.7 298.3

(ii) Longer side

22# 2.90 6 29.8 518.5

2. column
(i) Reinforcement

22# 1.45 6 29.8 259.3

(ii) Stirrups 250

350
8# 1.04 5 3.9 20.3

Total = 1096.4 N

Add 5 % extra for wastages in cutting, overlapping etc. = 54.82

Total quantity of steel required =1151.22 N

TOTAL QUANTITY OF STEEL REQUIRED

o‟ 30
Total weight of reinforcement = 30 x 1151.22

= 34536.6N

CHAPTER-14
CONCLUSION

By doing this project we the students of our batch draw and prepare for a
“VAO OFFICE” we also now have a rough idea about the various books
available in design of R.C.C members.

The design was done by the following the provisions of IS 456:2000, IS 875:
PART-III; SP-16.

The necessary drawing for reinforcement details was prepared using


AutoCAD software.
CHAPTER-15
BIBLIOGRAPHY:

IS : 456-2000 Code of practice for RCC -Work

Design aids for reinforced concrete to IS:456-2000&IS :800-2007

IS:456-2000 & IS :800-2007 of proactive for loads

Schedule of rates for tiruvannamalai district by TAMIL NADU, P.W.D for the
year 2016-2017

Standard data book by TAMIL NADU ,P.W.D

Text book of estimating & costing by .

Das könnte Ihnen auch gefallen