Beruflich Dokumente
Kultur Dokumente
Head office : Business Class Kantorenpark Jan Olieslagerslaan 35 1800 Vilvoorde Belgium
Tel +32 (0)2 674 57 11 Fax +32 (0)2 674 59 60 pressure@vincotte.be www.vincotte.com
March 2009
Preface
Preface
This status report treats the surveillance of safety aspects when constructing
complex industrial installations and more specifically the surveillance of these aspects
when constructing LNG terminals.
First of all, we would like to thank our client, the inspection service of the VROM,
for assigning this mission to us, and the trust it puts in our company. Our gratitude is
more particularly extended to ir. Henk van der Veen and ing. Harrie Werkman for the
constructive meetings, the efficient cooperation, and many interesting discussions.
To clearly delineate the contents of this status report and to create a larger basis,
three meetings were organised (two in Breda, one in Vilvoorde), where, in addition to a
presentation on the topics treated in this status report, a forum was offered to discuss the
approach and contents of the report. We would therefore like to take this opportunity to
thank the participants to these meetings, namely Harrie Werkman, Rob Poelman and Henk
van der Veen of VROM-Inspectorate, Koos Bouwmeester of the province Groningen, Luc
Vijgen, Wim Been, Mahesh Soedesh and Marieke De Koning of DCMR, Edward Geus of the
RIVM, Guy Mariën of Gate terminal, Bert Wijker, Pieter Boerma, and Anton Tol of the
Minszw, Frank Lelieveld and Maarten Van Abeelen of the fire department Rotterdam-
Rijnmond, Danny De Baere and Frank Verschueren of the FOD WASO and last but not least
Herman Lens and Francis Leemans of Vinçotte Nederland, for the constructive and
interesting conversations and for the remarks sent in writing, which have made an
important and not to be underestimated contribution to this status report.
The contents of this report are based on the knowledge, competence, and
experience of our experts and engineers. Therefore, we would like to thank colleagues Fop
van der Bie, Kristof Van Bael, Guy Doms, Daniel Bruyland, Willy Wijns, André Weyn, Dirk
Wyffels, Patrick Zandbergen, Joseph Cremer, Ben Verhagen, Jan Liesmons, Raphaël
Termote, Bart Vanbever, Guy Jacques, Koen Chielens, Rudy Vanden Berghe, Tom
Cauwelier, Geert Boogaerts, Kristophe Van Immerseel and Jean Muls for the texts they
contributed and their presentations during the meetings. Writing these extensive and well-
supported texts within the time requirements made and parallel to our daily activities was
a task not to be underestimated. Our special thanks are therefore extended to Mrs. Livine
Dubois, who was capable of always efficiently managing the lay-out and the numerous
adaptations and corrections.
This report came to be within a limited amount of time and on a limited budget,
and was based on the experience and competence present within our company; therefore,
we are not averring that this report covers all conceivable aspects that may occur during
the construction of complex installations.
However, it is our hope that this document will constitute a significant addition to
augmenting safety of complex industrial installations and this by optimalizing surveillance
during construction of these installations. We are also convinced that by using our
experience and know-how, not only can adapted inspection plans be drafted, but the
quality of those inspections can be optimised.
We wish you much enjoyment reading this report. Remarks on it are, as ever,
most appreciated.
Table of Contents
Chapter 2 : Relevant Aspects for the Integrity and Safety of the Installations
2.0. Introduction
2.1. Risk Analyses
2.2. Design of Pressure-Retaining Parts
2.3. Materials for Pressure-Retaining Parts
2.4. Non-Destructive Testing on Pressure-Retaining Parts
2.5. Electrical Installations
2.6. Concrete Structures
2.7. Metal Structures
2.8. Coating and Isolation
2.9. Fire Safety Industrial Installations
2.10. Control and Safety Control Circuits
4.0. Introduction
4.1. Concerns
4.2. Start of an Inspection Program for Industrial Installations
Chapter 5 : Conclusions
Energy supply in Europe is mainly dependent on natural gas. This natural gas is
transported in gaseous condition via pipelines or in liquid condition in specially equipped
ships and then stored in LNG terminals. These terminals are buffers in case that, because
of conflicts (for example, the recent gas conflict between Russia and Ukraine), the gas
supplying is interrupted. Belgium has a lot of experience in storing liquid natural gas. The
first gas terminal in Zeebrugge dates from 1984, and recently there have also been a
number of important expansions.
Our company has actively, and in a number of domains, assisted in these projects as
expert, as External Service for Technical Control (EDTC), notified body and Authorized
Inspection Organization, with the mission of surveying the many aspects of constructing
this gas terminal.
In the Netherlands, gas terminals are also being built. The construction on the Gate
terminal has started in 2007 and it is hoped that the terminal is operational by 2011. It is
self-evident that in the Netherlands sufficient surveillance cannot be disposed with. The
VROM-Inspectorate, in cooperation with the other surveying bodies, investigates for this
reason how the surveillance during the construction of LNG-terminals in the Netherlands
has to be organised. In this investigation, attention needs to be devoted to the question
to what degree quality certificates of equipment, materials, and activities are to be tested
for correctness.
In this context, we were contacted by inspection services of the VROM to write a report
on the surveillance technique that has proven its usefulness in, among other projects,
the extension project of the LNG-terminal of Fluxys in Zeebrugge. The question of VROM
Inspection concerns in the first place the safety aspects that have to be checked during
the construction of such complex installations. Other aspects such as environment,
company security and worker health are treated where there is a relation to safety. Our
experience with controlling the construction of this type of installations teaches us that
the problems encountered are of an identical nature, independent of the specificity and
application area of the installations, which means that the extent of this study goes much
further than just solely LNG Terminals.
The legal requirements for building complex installations, such as LNG-Terminals, and
the inspection systems.
The most important topics relevant for the integrity and safety of the installations:
risk analysis, design of pressure-bearing parts, materials for pressure-bearing parts,
construction and non-destructive testing of pressure-bearing parts, electrical
installations, structures (concrete and metal), coating and isolation, control circuits
and safety control circuits.
A description of the approach and inspection philosophy in the context of the first
extension of the LNG Terminal in Zeebrugge.
The points meriting attention that we have established during our surveillance
activities such as: the (international) systematics of inspection certificates and the
explanation of ‘weaknesses’ in said systematics, the role and limitations of ISO 9001
certified quality systems in such projects, etc.
A start for a focused inspection plan, which could be a starting document for possible
inspections to be executed.
To treat this very broad domain, we called upon the age-old expertise of our employees.
For the subjects enumerated for this purpose, we asked our experts to mention, in
addition to the theoretical background, the most important points meriting attention,
based on our practical experience. You will find the names of the experts, who
participated actively on this report, in the preface. The finished texts were proofread by
our two coordinators, edited and grouped in a number of chapters. We will know give a
short survey of these chapters.
Chapter 2 takes a closer look at a number of technical aspects, and directs attention as
well to a number of shortcomings in surveillance and regulation. The following topics are
discussed in this order: risk analysis, design, materials, construction and inspection of
pressure-bearing parts, concrete and metal structures and their coating, electrical
installations, control and safety control circuits and, finally, fire safety.
The inspection philosophy our company used for the extension of the LNG terminal in
Zeebrugge is discussed in-depth in Chapter 3.
Finally, we have collected all the points meriting attention related to surveillance in
Chapter 4 and have also made a start with a proposal for an inspection plan.
In all this, it needs to be kept in mind that only topics were addressed for which our
company possessed sufficient experience and knowledge. Additionally, we certainly do
not claim completeness for the topics discussed, partially because of the fact that this
study had to be conducted within a limited time and with a limited budget.
1.0.0 Introduction
The purpose of this introductory part is to clarify the background and the purpose
of the European legislative acts underpinning the current regulations related to
the safety of workers and of industrial installations. Other important issues such
as the protection of the consumer or the protection of the environment are not
dealt with
This preliminary step is important because two different types of regulatory acts
do have a direct impact on the everyday life. A lot of time can be saved by
reducing the misunderstandings about the purpose and the interfaces of these
mandatory requirements.
Basically, we will identify two families of regulatory acts (European regulatory
acts are directives, decisions and regulations: the nature and the importance of
these documents is described in Appendix 1)
The regulatory acts based on article 95 of the Treaty (previously article 100A).
The idea is that "the Council shall […] adopt the measures for the approximation
of the provisions laid down by law, regulation or administrative action in Member
States which have as their object the establishment and functioning of the
internal market". Since the basic Idea is to promote the free movement of goods,
these directives are sometimes called "economic directives" (DG Enterprises at
Commission level). But most of these directives are also aimed at promoting the
health and safety of European workers and consumers.
Member States are responsible for ensuring the health and safety on their
territory of persons, in particular of workers and consumers and, where
appropriate, of domestic animals and goods, notably in relation to the risks
arising out of the use of machinery.
The vast majority of the published documents are based on the principles of the
"New Approach". Since there are still several operational questions on some
issues, we will illustrate the background and the recent evolutions
These regulatory acts are based on article 137 of the Treaty (previously article
118A). This is a result of the Single European Act (1987). It was the first time
health and safety at work had been dealt with in operational provisions of the EC
Treaty. The idea is i.e. that the Community shall support and complement the
activities of the Member States in the field of "improvement in particular of the
working environment to protect workers health and safety". For these reasons
the related set of directives is sometimes called "social directives" (DG
Employment and Social Affairs at Commission level). One should nevertheless not
forget that there is also an economical dimension: one of the purposes is to limit
the possibilities of Member States to make social dumping.
Whereas health and safety are, without doubt, key ingredients in employment
quality, represent one of the Union's most important social policy areas and
comprise a major economic dimension.
Regulatory acts adopted under article 95 and Article 137 are complementary.
Directives under article 95 are mainly intended to ensure the placing on the
market of safe products and under article 137 they are intended to ensure the
healthy and safe use of the products at the workplace.
Most of the directives are developed within the scope of the framework directive
89/391/EEC1 as amended by 2007/30/EC2. From now we want to indicate the
effects of the "Better regulation" as illustrated by directive 2007/30/EC. The
issue is quite simple: the Member States have to report on the practical
implementation of 17 particular directives referring to the framework directive.
For historical reasons, the provisions on reporting are sometimes inconsistent in
terms of both frequency and content. This situation is pure waste of time and
money for the Member States and in addition to that it makes exploitation of the
results much more difficult at Commission level. It might be seen as a detail but
in the regulatory world as in our individual lives, the devil is often in the details.
We will elaborate further on this issue in the section dealing with the Regulatory
Impact Analysis.
The very recent publication of the Package on Internal Market for goods (August
2008) is the culmination of a process where lessons were taken from the past in
order to improve the regulatory tools. As will be seen the main issues are related
to the improvement of the efficiency of the system as well as the clarification of
the role and duties of the different operators, including the public authorities.
The basics of the different steps will be highlighted hereafter. The trends of the
evolution are illustrated in figure 1.0.1.
Basically, it goes about a mutual learning process. Every regulation (or lack of
regulation) introduces specific incentives for the economic operators. Sometimes,
the foreseen effects do not happen. In the beginning of the eighties, when the
"New Approach" was designed, one of the fears was an excess of market
surveillance at national level. There were a lot of reasons to expect it, hidden
protectionism was not the less significant. Actually this did not happen and the
new idea is that market surveillance should not be "tolerated" but ""mandatory".
In the same context of surveillance of the market, another important issue is the
clear definition of the role and duties of the economic operators. The concepts of
"putting into service" or "putting on the market" was not legally defined. The
definitions of the importer and the identification of its duties are inconsistent
between the directives. As a result, it is possible for an operator to say to the
authorities that he fully agrees with the fact that the product X is dangerous but
that he cannot be held as responsible because the product was not yet sold (put
on the market) and/or because the manufacturer is somewhere in the world and
that it is up to the authorities to try to get in touch with him and to tell him that
he is accountable.
The many contacts with the different operators have taught us that it is of the
highest importance to know “why one does something” (does one have to do it?)
before one can know “how to do it”.
The structure of Europe has its very own logic. This logic is often different from
the logic that underlies our national customs. A first step is thus to gain insight in
the general framework, and integrate the European doctrine in our thought
pattern.
One of the main objects of this paragraph is therefore to stress the understanding
of the exact extent of new regulative concepts introduced into the European
Union. The implications of the CE-marking, the use of harmonized standards, the
role (and responsibility) of the Commission, the role (and responsibility) of the
Member States, the role of accreditation, … these are all themes that have to be
mastered.
Figure 1.0.1
The problem is that people often have the annoying tendency of only
remembering information that they like to hear. We have seen several involved
parties (including member states) defend with nail and tooth strategies that were
in fact disadvantageous to them. When one considers then that these parties
often turn to the wrong person, then what happens in the best case is a
considerable waste of money and time. The European industry, however, cannot
let opportunities pass by anymore.
To give an acceptable answer to the questions every one of us will ask ourselves,
it is important to create a guideline, to familiarize ourselves with a doctrine of
which all elements can be replaced in their context. One of the best means to
achieve this, is undoubtedly knowing how this doctrine has been conceived. It is
our intention to capture in a few words the success and the setbacks that have
made the European (Economic) Community to create the communal legislation
we are dealing with right now, even if we do not know it yet.
Program developed by the European Community for the build-up of the internal
market was certainly the most ambitious economic change planned in peacetime.
In fact, it was to be superseded later on by the opening of Eastern Europe in
1989/90.
In fact, Europe was out of options. The famous Cecchini-report, that was
published in 1988, is not named “The Advantages of Europe” but “The Costs of
Non-Europe”.
“We have to take our chances as they present themselves”, opportunists declare.
“We have to create the chances to succeed”, strategists say.
The opportunists are wrong.
H. Daems
As we have seen above, for the moment Europe is formed on the basis of a
doctrine that has strongly evolved since the signing of the Treaty in 1957. Five
steps can be distinguished. The first three correspond to a Council Resolution.
The fourth is a general philosophy (better regulation). The last and very
important step (August 2008) is based on a European regulation4 and a European
decision5.
Every one of these steps is a step ahead: always lessons are drawn from the
practical problems revealed during a previous step. Behind the technical terms we
see a thorough redistribution of responsibility and of regulatory obligations. After
describing each step we draft an operational balance: roles of the different
players, advantages and disadvantages of the existing structure.
3 Ch. D DE FOULOY - "Guide pratique des lobbyistes européens" - European study service – 1994.
4 REGULATION (EC) No 765/2008 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
of 9 July 2008 setting out the requirements for accreditation and market surveillance relating to the
marketing of products and repealing Regulation (EEC) No 339/93
5 DECISION No 768/2008/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
of 9 July 2008 on a common framework for the marketing of products, and repealing Council Decision
93/465/EEC
operators, whether they are the industry or the government or the accreditation-
institutions.
The Treaty of Rome gave an impulse to the internal market within the Community
by removing the two most constraining types of barriers of those days: customs’
rights and the import quota. Since then, a number of very founded concerns,
such as health protection, have pushed the Member States to impose a number of
technical requirements, that each constitute a technical limitation of free trade.
The community mechanisms dating from 1957 soon proved to be incapable of
handling with this evolution.
• But also, often hidden beneath the reasons mentioned above, there is the
will to protect the interests of the national manufacturers, or even a whole
industrial sector that is considered of strategic importance, despite the
European treaties.
The Players
Evaluation
Yet the decision structure is simple if we do not consider the marginal cases of
direct lobbying at political institutions. That structure can be found in the
schematic below. (Figure 1.0.2)
COMPETENT AUTHORITY
USER
Figure 1.0.2
Basic Idea
The Players
Evaluation
This first step of the harmonization is today called the “old approach”. It is the
conversion on the community level of the system hitherto applied to national
levels. We have to keep in mind that these directives have led to a first important
redistribution of roles.
Some of the directives applied, for example those related to toxic substances,
cosmetics, or additives for foodstuffs, are binding for everyone. Others, for
example in the automotive sector, were optional for the manufacturers, who
could choose to obey either national regulations or European directives. In the
second case, all national governments were forced to accept the European
certificates presented by the constructor.
This system works well, but has the major disadvantage that it is bulky, and thus
very slow.
These days, this old approach remains to be applicable for an economic sector of
the highest importance to the European industry: the car industry. Since 1992,
principles were slightly altered by some adaptations inspired by the rules of the
new approach: mandatory and no longer optional application; Monitoring of
conformity of production, …
Today, we see another type of evolution. The automotive market is not European
but worldwide and the applicable regulation becomes more and more
international (based on the Geneva Agreement (United Nations)). This is a basic
request from the big industry: they do not want to sell at European level but
worldwide. This can have positive results: due to scale effects, the higher level of
requirement set on safety and environment can be brought without increase of
the cost at consumer level.
Sidney Harris
Although the Council Resolution dealing with a new approach is already more
than twenty years old, it proposes a coherent whole of changes of which
economic operators do not always perceive the practical consequences. This topic
is important, and we go further into it in paragraph 1.0.4.
Basic Ideas
The harmonization of the technical regulations lead to a very bulky and thus very
slow and expensive approach, with very detailed technical attachments.
Furthermore, governments do not always have technical specialists at their
disposal. The two aspects of the technical regulation are thus kept apart.
CAVEAT
- Consultation is not a substitute for democracy
- Institutional balance must be respected
- Legislation must guarantee procedures
- Representation must be transparent
- Access to results must be guaranteed6
Evaluation
The new approach has added several dimensions to the simple decision structure
we showed in Figure 1.0.2. The rise in the number of intervening parties has
necessitated the creation of several coordination structures. These structures are
furthermore explicitly described in the texts of the new approach. The general
schematic can be presented as follows.
6 Enterprise Seminar 11 February 2003 – The future of the New Approach : Quo Vadis ?- Anne
Wilkinson - Brussels
Working Group
User
Figure 1.0.3
From Figure 1.0.3, it becomes quickly clear that this structure can lead to a
game of complex interaction between the different players. These interactions can
become even more complex as a consequence of the interaction between
different directives applicable to the same group of products.
Another difficulty comes from the implicit need for a consensus, due to diverging
positions taken for historical reasons, it appears to be almost impossible to reach
a common position on some critical questions.
+ use of standards
The “Global Approach” supplements and expands the principles of the “New
approach”.
Basic Ideas
The operators
We will not elaborate too much on this general issue but it is important to know
some of the background elements.
In 2005, the Commission wanted to reinforce its political ownership as well as the
overall coherence of the strategic political EU agenda. The Commisions then
launched a "better regulation project" with the aims to improve the quality of
new legislation, and update many existing rules to make them clearer. To that
end it is therefore:
• Withdrawing a number of pending legislative proposals. In fact, as
of March 2006, the Commission had withdrawn 67 legislative proposals
after screening 183 potential new laws that were pending ratification by
the Council and European Parliament.
1.0.4 The Internal Market Package for Goods : revamping the New
Approach
The set of Regulatory acts published in the OJEU of 13 August 2008 is the result
of four years of high level and intensive discussions between the Commission, the
stakeholders, the European Parliament and the Council.
The references of the regulatory acts are as follows (Regulation 764/2008 is quite
specific and will not be discussed later in this text)
- It sets out the requirements for accreditation and market surveillance relating
to the marketing of products.
One of the great challenges induced by the Regulation is the duty of surveillance
of the market by the Member States.
- Member States shall identify the responsible authorities
- Member States shall establish and make publicly available surveillance
programs.
- The Commission shall develop and maintain a general archiving and exchange
of information system.
The Decision is a tool for the Commission’s Better Regulation policy. The rationale
is to ensure more consistency of the legal environment and to establish a
common “culture” of legislating. The identified inconsistencies: (different
terminology, different logic behind obligations of economic operators, duplication
of procedures,..) make it difficult and more expensive for economic operators to
comply with the legal requirements. On the other hand it should be kept in mind
that European regulatory acts are well implemented and that the improvements
induced by harmonisation can be out weighted by the (administrative) cost
induced by the requested changes.
The directives “free circulation of goods” are but one of the aspects of the
growing Europe. The Single Act created new clear social responsibilities on a
European level.
Article 153 (previously article 137 and previously article 118A) gives the Council
the authority to adopt social directives. Apart from safety and health on the
workplace, those “social” directives mostly involve various aspects, from the free
circulation of workers to the equal treatment of men and women. Initially, the
tendency was to put the focus on safety and health in a narrow sense.8
Without further details, we point to the importance of the executive directive that
is aimed at the promotion of the amelioration of safety and health of workers.9
That framework directive is followed by several individual directives, of which we
have already introduced some.
Of particular interest here are the first three directives, with requirements for
workplaces, for the use of work equipment and for the personal protective
equipments.
That directive of 1989 was far from complete, and the Commission proposed an
amendment that introduced a significant number of changes.
- Make sure that the means of labour, the safety of which is dependent upon
installation conditions, are subject to a first inspection (after the installation
and before the first utilization) and an inspection after every installation on a
different location, to ensure that these work equipment have been correctly
installed and are working properly.
- Make sure that the work equipment that can cause dangerous situations when
damaged are subject to regular and exceptional inspections (after exceptional
events that might lead to dangerous situations).
The practical impact of this obligation to draft a plan for the inspection of the
work equipment is dependent upon its transposition to national law.
One of the new missions that the recognised bodies in Belgium have developed is
to help companies to put their machinery in order as determined in this directive.
Even more than before, everything will be a matter of accountability. In this the
employer will see the added value.
8 E. Vogel-Polsky en J. Vogel, "Het sociale Europa 1993: illusie, alibi of realiteit?", Uitgaven van
de Universiteit van Brussel, 1991
9 Council Directive 89/391/EEC of 12 June 1989 on the introduction of measures to encourage
improvements in the safety and health of workers at work O.J.. nr 183, 29-06-89
- Council Directive 89/654/EEC of 30 November 1989 concerning the minimum safety and health
requirements for the workplace
- Council Directive 89/655/EEC of 30 November 1989 concerning the minimum safety and health
requirements for the use of work equipment by workers at work
- Council Directive 89/656/EEC of 30 November 1989 concerning the minimum health and safety
requirements for the use by workers of personal protective equipment at the workplace
- Council Directive 90/269/EEC of 29 May 1990 concerning the minimum health and safety
requirements for the manual handling of loads where there is a risk particularly of back injury
to workers
- Council Directive 90/270/EEC of 29 May 1990 concerning the minimum safety and health
requirements for work with display screen equipment
- Council Directive 92/57/EEC of 24 June 1992 concerning the implementation of minimum safety
and temporary or mobile construction sites
- Council Directive 92/58/EEC of 24 June 1992 concerning the minimum requirements for the
provision of safety and/or health signs at work
- Council Directive 92/85/EEC of 19 October 1992 on the introduction of measures to encourage
improvements in the safety and health at work of pregnant workers and workers who have
recently given birth or are breastfeeding
- Council Directive 92/91/EEC of 3 November 1992 concerning the minimum requirements for
improving the safety and health protection of workers in the mineral-extracting industries
through drilling
- Council Directive 92/104/EEC of 3 December 1992 on the minimum requirements for improving
the safety and health protection of workers in surface and underground mineral-extracting
industries
- Council Directive 93/103/EC of 23 November 1993 concerning the minimum safety and health
requirements for work on board fishing vessels
- Council Directive 98/24/EC of 7 April 1998 concerning the protection of the health and safety of
workers from the risks related to chemical agents at work
- Directive 1999/92/EC of the European Parliament and of the Council of 16 December 1999 on
minimum requirements for improving the safety and health protection of workers potentially at
risk from explosive atmospheres
- Directive 2002/44/EC of the European Parliament and of the Council of 25 June 2002 on the
minimum health and safety requirements regarding the exposure of workers to the risks arising
from physical agents (vibration)
- Directive 2003/10/EC of the European Parliament and of the Council of 6 February 2003 on the
minimum health and safety requirements regarding the exposure of workers to the risks arising
from physical agents (noise)
- Directive 2004/40/EC of the European Parliament and of the Council of 29 April 2004 on the
minimum health and safety requirements regarding the exposure of workers to the risks arising
from physical agents (electromagnetic fields)
- Directive 2006/25/EC of the European Parliament and of the Council of 5 April 2006 on the
minimum health and safety requirements regarding the exposure of workers to risks arising from
physical agents (artificial optical radiation).
The “Pressure Equipment Directive”, henceforth called PED, is, together with the other
European Directives, a part of the unification process of Europe.
The PED is mandatory for vessels, pipes, steam generators, appendages, safety
appendages, and assemblies with a maximum operating pressure above 0.5 barg
that are put for the first time on the European market (one or more member states). The
directive is mandatory since May 29, 2002.
Despite many exceptions, more pressure equipment than ever before are subject to the
requirements of this directive
The most important exceptions are those subject to other European Directives or to other
national, regulations.
The PED is an economic Directive, founded on Art. 100 of the Treaty of Rome, in
opposition to the social directives founded on article 118 of the same Treaty of
Rome.
Economic Directives are addressed to manufacturers and applicable on products that
these manufacturers put on the European market for the first time.
Economic Directives introduce fundamental requirements of safety, health, and
environment.
Social Directives, on the other hand, are addressed to employers and owner/users of
installations and contain requirements concerning the safety and well-being of workers,
such as the Directive for work equipment 89/655/EEG.
In opposition to the economic directives, the social directives are not (yet) or not
completely transferred to the national legislations of the different member states.
This may give a strange feeling, as if “safety” is less important than economic interests.
Economic Directives have the purpose of guaranteeing the free circulation of goods
within the unified European market by eliminating all possible obstacles to this in the
process. For example, when the Directive for pressure equipment was implemented, the
member states were forced to withdraw their own national regulation related to pressure
equipment, so that, among other results, all national legal and regulatory obstacles were
removed in favour of the Directive.
The Directive thus guarantees the free circulation of goods within the unified European
market, independent of the origin of the equipment, and as far as the requirements of
the Directive are respected.
The first concepts that were adopted during the unification of the regulation for pressure
equipment, namely the fine-tuning of a European design and manufacturing standard
with very detailed technical contents, eventually led to nothing due to years of arguing
back and forth, an argument not at all devoid of chauvinism, between the member states
of that time. Because each one of these member states wanted to see its own vision on
safety and attendant regulation transposed to a European level.
These negative experiences, but also the rise of quality control and quality assurance
techniques and especially of the ISO 9000 and the EN 45000 standards, combined with
an ever stronger drive for unification, generated a new concept, one that was called the
“new and global approach”.
Thus, the European Directive for pressure equipment is a “new approach” Directive,
just like the Machinery Directive and the ATEX-Directive.
New approach Directives have some very specific characteristics, of which the most
important one are its essential health and safety requirements. These are crucial safety
requirements that mandatory have to be taken into account in the design and
manufacture of the pressure equipment insofar as the corresponding risk exist when the
equipment is used in reasonable conditions as expected by its manufacturer. To clarify
this, it is important to know that the Directives of the new approach are not only
concerned by safety, but also by health and environmental aspects of individuals, and
even of pets or goods.
The necessity for the manufacturer to care about “the reasonable conditions of use”
immediately introduces a second specific characteristic, one inherent to the Directives of
the new approach, namely the obligation to conduct a risk analysis to find out which
hazards exist on account of pressure.
He should than take into account the result of his analysis in the design and manufacture
of the equipment.
Thus, these directives are regularly called “risk-related directives”.
Conducting a risk analysis is not self-evident, certainly not for the classical equipment
manufacturers who have never gotten used to it. Furthermore, a manufacturer does not
always have all necessary data basic design information, or transients etc. of the
equipment at his disposal, and thus he will not always be able to cover all aspects.
The essential requirements are structured like most design and construction codes
and standards, and therefore start by stating generalities. Further on, aspects such as
design, materials, fabrication, inspection and tests are treated in independent
paragraphs. The essential requirements, however, do not give any technical
specifications for the design or manufacture of a pressure equipment.
They are expressed in very general terms that do not always facilitate their
understanding and application by manufacturers and other users.
And moreover:
- In case the hydrostatic pressure test is harmful or impossible, other tests with a
recognized value can be carried out. For other tests than the hydrostatic pressure
test, additional measures such as non-destructive tests s or other equivalent methods
have to be taken before these tests are carried out.
One could wonder on what basis the equivalent value of other tests will be assessed?
And what are suitable methods of non-destructive tests?
Is it possible to check the structural integrity of a pressure device without actually
putting it under pressure?
Furthermore:
- The following prescriptions normally apply. But when they are not applied, such as in
the case of materials not referred to individually and no harmonized standards were
used, the manufacturer has to be able to show that fitting measures have been taken
to achieve an equivalent level of general safety
The lack of more clarity and objective criteria leads to very different interpretations of
this requirement!
In the last example that should illustrate the lack of clarity in the essential requirements,
the term harmonized standards was used.
In the time period when the Directive was being drafted – something lasted some 15
years – the idea also grew to create European standards, i.e. technical specifications and
requirements necessary for designing, manufacturing, inspecting and testing of pressure
equipment, which should allow one to meet essential requirements as well. For this
purpose, the CEN (European Committee for Standardization) got a mandate from the
European Commission to prepare standards that should allow coverage of the whole
range of products of activities related to pressure equipment, taking into account the
applicable essential requirements.
In this manner, a manufacturer using a harmonized standard, will automatically gain a
presumption of conformity with the essential requirements.
A European standard acquires the status “harmonized” when the standard passes the so-
called “formal vote” and is published in the Official Journal of the European Union. The
different member states are then supposed to give the standard a national status and at
the same time to withdraw possible national standards that could contradict the contents
of the harmonized standard.
The story of the harmonized standards is not a complete success story.
Drafting and approving the thousands of required standards consumed too much time,
among other reasons because of the necessary consensus that had to be acquired from
the different member states, each one with their own safety philosophy and chauvinism.
It hardly needs to be said that some of those member states could exert a lot more
lobbying influence than other, smaller, member states.
Some member states, for example, opted for low safety margins (read: safety
coefficients) with a relatively high frequency and strictness of inspection and control,
while other member states rather chose high safety coefficients, which then result in over
dimensioning and for which a relatively low amount of inspections and controls is
required.
Furthermore, the use of harmonized standards is not mandatory.
A manufacturer can use national and international standards at all times insofar as he is
able to demonstrate that all applicable essential requirements are respected.
Due to their non-compulsory nature, many companies maintain their old trusted
standards. On the one hand this is due to their year-long experience with these
standards. Thus, for example, almost all petrochemical installations are designed and
built according to API, ASME, and/or ASTM standards and codes. On the other hand the
principle “unknown is unloved” is at play here.
A next characteristic of these Directives of the new approach and of the pressure
directive in particular is the division in risk categories.
This division is based on, as we might suspect on the basis of the degree of danger or
risk, which in this case of course the pressure in the equipment. The directive is talking
about PS the maximum allowable working pressure for which the equipment is designed.
This can be the design pressure, but the design pressure can be higher than the maximal
operational pressure for a whole host of reasons, such as standardisation. The maximal
working pressure is mostly the set pressure of the overpressure safety device of the
equipment or of the installation. Furthermore, the type of fluidum has to be taken into
account. Indeed, a distinction is made between gases, vapours, and fluids with a high
vapour pressure on the one hand, and liquids on the other hand.
For both categories, a further distinction is made between dangerous and non dangerous
substances, using the classical categorization for dangerous substances (see also EC
Directive 67/548) found in most national regulations, namely, substances that are
explosive, very lightly inflammable, light inflammable, inflammable (with a maximum
allowable temperature higher than the flashing point), very toxic, toxic or oxidating.
Furthermore, one additional parameter is taken into account, namely the potential stored
energy (under the form of pressure) in the equipment. Depending on the type of
equipment, this is expressed in volume (in liters) for all kinds of vessels, or in nominal
diameters (thus without dimension, but derived in millimeters) for pipes and all kinds of
appendages for which it is common to express these in diameters.
Relative to these parameters, all types of pressure equipment are divided into risk
categories, from category I, the lowest, up to category IV, the highest.
It needs to be remarked that for every configuration an area “Art. 3.3” is prescribed. The
specification Art 3.3 of course refers to the paragraph from the Directive that explains it.
What is involved in the case of complex industrial installations are equipment for which
the maximum working pressure certainly is more than 0.5 bars, but for which the
combination of a relatively low pressure with a relatively low volume (or small diameter)
does not constitute a veritable risk. For these equipment, the essential requirements
should not be applied, and thus these equipment may not bear the CE-marking.
To illustrate this, one of the nine configurations is presented below in Figure 1.1.1.1.
This refers to table 2 of annex II of the Directive. The table applies to vessels intended to
contain a non-hazardous gas (such as pressurized air, nitrogen, or steam).
Figure 1.1.1.1
After determining the risk category, we proceed to the next step, which constitutes an
other aspect of the Directives of the new approach, namely the choice of the procedure
of assessment of compliance with the essential requirements.
The Directive provides a number of assessment procedures in annex III from which the
manufacturer can choose depending on the risk category, and by which he demonstrates
that he respects the applicable essential requirements.
Thirteen assessment procedures are available (cf. Table 1.1.1.1) that can be used on
their own or in combination with others.
The impact of the risk category is thus limited to the degree of conservatism and the
strictness with which compliance with essential requirements is assessed.
Indeed, most of the essential requirements are expressed in very general terms, and
contain few qualitative requirements. The need to apply higher “safety requirements” for
higher risk categories, mostly due to higher pressure and other loads, is actually taken
into consideration by the design and construction standards.
The manufacturer can, within the possibilities provided within the limitations of the
directive, select the assessment procedure he wants to apply. His selection will be
determined by, among other factors, whether or not he has a quality system in place,
and also whether he plans a one-time or serial production.
The table below sums up the relations between risk categories and assessment
procedures that can be utilized. On its left side, procedures are represented based on
traditional inspection such as review and certification of design, review of other technical
documents, witnessing manufacture, inspection and testing activities.
It is worth noting that no intervention of a recognized notified body is required in
category I.
The intervention of a third party, called notified body, is also a characteristic of these
new approach directives.
In category II, this intervention is required but only in the construction phase and not in
the design phase, and only by sampling.
For categories III and IV, the assessment of design and construction is required at all
time.
The design review under the form of a pure and formal design approval under module
B1, or under the form of a type examination under module B. In addition to the pure
design, a type investigation will also assess the physical realisation based on one or more
prototypes for aspects such as manufacture, inspection and testing activities.
In some cases, the Directive allows to intervene by sampling, such as, for example,
under the modules A1 and C1, in category II, respectively in category III, in conjunction
with a type examination.
A constant in all this is the compilation, by the manufacturer, of the technical design and
construction file in which he gathers all elements that demonstrate that all applicable
essential requirements have been satisfied.
It is primarily the manufacturer who takes the responsibility of putting his devices in
conformity with the Directive, to evaluate them and to finally declare conformity with the
Directive, with or without the help and confirmation of a notified body.
From different legal cases in the framework of this Directive it appears that the
appropriate courts of law have the tendency to assert shared responsibility in the case of
the intervention of a notified body, as far as the latter is judged to be in error.
Therefore, it is important that the notified body take its responsibility, obviously
dependent on the selected assessment procedure, very seriously.
This message is even more important when dealing with certain procedures (B1, B, G
and the design review under H1) where the notified body is asked to support a formal
conformity with the Directive. We’d like remark here that the notified body is not a
designer, nor a pressure vessel manufacturer and that the means at its disposal to
conduct its evaluation, are per definition (as a third party) rather limited.
In the frame of other assessment procedures such as A1, C1, F, but also for other
procedures founded on quality system assessment, the situation is less clear-cut. What is
at stake here is more than merely formulating observation and objective self-evidences,
and it needs to be remarked that the reports published not necessarily conclude formal
conformity with the Directive, nor can they be seen as a certificate or attestation of
conformity.
In what preceded, it was mentioned a couple of times that from category II onwards, a
third party intervention, the notified body, is required for a number of configurations.
The notified bodies are designated by one of the member states on the basis of minimal
requirements imposed by the directives and further by the individual appraisal of each
member state.
The notified body conducts a number of assessments, ranging from simply attending the
final inspection by sampling, to the formal assessment and certification of the design and
manufacture of a category IV pressure equipment (module G) or the assessment of the
conformity of a quality system with respect to the requirements of the Directive.
Depending on the selected assessment procedure, the notified body delivers a report or a
certificate.
From that moment onwards, the manufacturer is allowed to attach a nameplate with a
CE marking to the equipment and also (obviously only from category II onward) the
identification number of the notified body that was involved in the manufacture
phase.
Both of these features constitute, together with the declaration of conformity drafted by
the manufacturer, a kind of passport for the free circulation of the pressure equipment on
the European market.
The declaration of conformity is truly a very important element in this context because it
implies the formal responsibility of the manufacturer or of his representative residing
within the European Community.
Theoretically considered, it is not required to deliver the declaration of conformity
together with the pressure equipment. The only requirement is that the manufacturer
files this declaration for ten years after putting the product on the market, and keeps it
at the disposition of the authorities whenever they may need it. Yet there does exist a
guideline 9/16 explaining this and “recommending” the delivery of the declaration of
conformity. “Guidelines” are official interpretations and clarifications of the Directive.
They are phrased and prepared by the forum of notified bodies on the requirement of all
possible users, and submitted for approval by the “Working Group Pressure” of the
European Commission. These guidelines are published on the official website of the
Commission.
(http://ec.europa.eu/enterprise/pressure_equipment/ped/directive/index_en.html).
However, when introducing the product on the market, the manufacturer will have to
deliver a user manual, which, as its name implies, explains to the user how the
equipment is to be used in a save manner, but that also needs to mention all residual
risks that could occur during the expected usage of the equipment.
For the sake of completeness, it is important to explore some further aspects, such as:
- The Technical Construction File
This is a file in which a manufacturer has to file all self-evident information that
demonstrates that all applicable requirements for the equipment in question have
been respected. This file, together with the declaration of conformity, is to be filed
and kept at the disposition of the authorities for ten years after the device is put on
the market.
A table of contents of such a technical file can be found in the Directive.
It also imposes obligations on the member states, such as the supervision of those actors
involved but also on the products.
We are not qualified and have not enough information to judge the efficiency of
supervision in Belgium and other member states.
On the other hand, we are regularly confronted with administrative anomalies (contents
and form of declarations of conformity, contents and form of material certificates) but
also with technical shortcomings (not reaching the prescribed material characteristics,
undetected deficiencies in material or welding joints …).
On the one hand, there is the factor of competition since neither the unity prices nor the
inspection or assessment programs are unambiguously set. Manufacturers of pressure
equipment (such as all economic players in any market) are tempted to work with the
cheapest “suppliers”.
Also, by opening up the European market (also for notified bodies), the monopoly
position of some national bodies was broken.
Another cause that can influence the cost of an intervention is for example the size and
means of the inspection company.
Bigger and more experienced inspection companies often have a staff of experts on non-
destructive analysis, in metallurgy, possibly a laboratory, tools and human resources for
design review and approval … It is self-evident that the possibility to call upon such
experts, internal as well as external, also affects unity prices. Young, small inspection
companies with a relatively small staff and limited action radius do not have to deal with
these costs to the same degree.
The total costs of an assessment by a notified body depends to an important extent to
the number and duration of the interventions.
Not rarely are we confronted with a trimmed intervention program.
Since the task is to observe and supervise, it is obvious that the effectiveness and
efficiency of the interventions are directly influenced by their duration and frequency.
All this results in non-conformities and all kinds of anomalies that can be divided into
three groups:
- Incomplete, incorrect basic materials
A conservative estimate, supported by objective evidences and research, is that
30% of the 3.1 certificates (which number above 200) was issued erroneously,
due to the fact that the products they are supposed to cover correspond
incompletely or absolutely not to the criteria required.
Fraud by material manufacturers and suppliers when certifying materials.
An investigation by the Belgian welding institute involving the brittle breaking
behaviour of flanges in SA 105 materials established that 50 to 60% of the
flanges acquired for testing corresponded incompletely or absolutely not with the
certificates that applied to them.
Incorrect execution of destructive testing (size testing bars, bending over a less
conservative calibre diameter, bending of 90° instead of 180°…).
“Foul play” by inspection agencies with 3.2 certification.
3.1 certificates are only countersigned and, if necessary, integrated in a document
with the heading of the inspection agency itself.
- Insufficient non-destructive analysis
The quality certificates of the operators are no guarantee that the non destructive
testing technique/parameters are sufficient to detect the expected
deficiencies/indications or flaws (especially when dealing with ultrasonic, eddy
current, but also with radiographic and even magnetic and dye check testing). A
qualification or validation of the method would not be advisable here.
The Directive does not require a formal approval of the non destructive testing
procedures by the notified body. On the other hand, many notified bodies do not
have sufficient competency to check or approve such procedures.
- Non-conform design
Use of erroneous allowable stresses or other design input data.
Incoherent data.
Use of configurations not accepted by the standard.
Lack of as built conformity assessment. It is common that during manufacture of a
pressure equipment, there is a deviation from the design approved in advance, for
different reasons. Not rarely, such deviations can have an impact on the stress
calculations. Without a final comparison between the situation “as designed” and
the situation “as built”, this cannot be called an acceptable situation.
A very specific deficiency, but one really generated by the Directive itself, are the
assemblies of equipment that are compiled under the responsibility of the exploiter on his
own site and are therefore called industrial installations and are as such not subject to an
assessment required by the Directive, due to the non-necessity of CE-marking and
intervention of a notified body.
The reasoning here is that in such cases there is no economical act being conducted.
However, the first part of guideline 3/1 is clear. When an exploiter/user assembles
himself with different parts (heads, flanges, nozzles …), this equipment does require an
assessment of conformity with the Directive. We have never understood the legislator
when he makes the distinction between assemblies and industrial installations, were it
not that thereby he provides the possibility of deviating from the Directive.
Assessing assemblies, as is specifically required by Article 10 § 2 of the Directive, is
indeed a logical step in checking the assembly for safety, as it applies for the individual
equipment.
Especially the third part of the global conformity assessment procedure and the
assessment of the safety provisions is for most assemblies a burdensome task and we
cannot grasp at all why users are trying to avoid third-party assessments here.
Because if we look further in the tangle of European laws and Directives, we then see
that there does exist something like a social Directive (cf. the beginning of this
paragraph). For example, the Social Directive for work equipment requires that a user
makes sure that all applicable Directives have been respected for all work equipment he
puts at the disposition of his workers, thus closing the circle in the end.
Indeed, assemblies (or industrial installations) can be as dangerous as individual
equipment, and furthermore we may think that it has never been the intention of the
authors of the Directive that assemblies were to be built that did not conform to the
safety requirements to which individual equipment are subjected.
Scope:
To gain an insight in the application of the machinery directive and the directive
on work equipment, it is important to take a closer look at the scope of the
machinery Directive.
Machine:
Safety component:
Simple machines:
The application of the Machinery Directive does not only depend on the definition,
but also on:
- When the risks are for example mainly of electrical origin, only the low
voltage directive applies (art. 1.5)
- When no risks are present, in other words if none of the essential
requirements apply, the directive will de facto not be applicable.
Manual shutters, storage tanks and pipelines, for example, are covered by this
and are thus excluded from the Directive.
Assembly of machines:
This means that an assembly of machines must also comply with the essential
requirements of the annex I of the machinery Directive.
For sizable complex installations, it is not always simple to determine whether we
are dealing with an assembly of machines or not.
Even if we assume that installations are not machines in the sense of the
Directive, it seems logical that this should not make any difference to the
requirements for an overall assessment of safety. The only difference is
administrative, namely the question whether the installation needs an additional
declaration of conformity and whether a CE-marking is to be attached.
In practice, a complex installation can be mostly subdivided in a number of
“machines” that work independently (for example an air treatment installation:
although the installation can be part of a larger whole, it can be considered stand-
alone in most cases).
These are equivalent to machines and the directive should be applied to safety
components that are put separately on the market.
- Pumps
A pump contains moving parts that imply mechanical risks. The directive usually
applies.
- (gas) shutter
A manual shutter (for example for a bypass) is not in the scope of the directive.
- Pressure controller
The amount of moving parts is limited here. The mechanical risks are thus limited
as well. We are of the opinion that the directive is not applicable if the risks are
limited.
- Compressor
A compressor contains moving parts which imply mechanical risks. The directive
normally applies.
Division in Risk-Categories
The Machinery Directive makes a distinction between machines that are included
in Annex 4 and machines that are not included in annex 4. Annex 4 covers 17
types of machines, for which a specific procedure applies (cf. infra).
The machines in annex 4 are mostly manually fed machines (with manual
intervention of the operator) and a number of very specific cases involving special
risks (for example hydraulic lifts for vehicles, lifting equipment for persons,
household refuse collecting vehicles, etc.).
Conformity Procedures
Before a machine can be placed on the market, or put into service, the
manufacturer must compile a technical file according to annex 5 § 3a. This
file must contain the following elements:
The file must kept available for the authorities (who can request it if there
is a sound reason for it) at the manufacturer for a period of ten years
(after the last produced machine of a certain type). As such, the file is not
delivered with the machine.
For all machinery that is placed on the market or put into service, the
manufacturer must deliver a declaration of conformity. This declaration
is a legal document that engages the responsibility of the
manufacturer.
Includes a general obligation to conduct a risk analysis and the taking of proper
measures, taking account of state of the art technology and techniques.
The employer shall take the measures necessary to ensure that the work
equipment made available to workers in the undertaking and/or establishment is
suitable for the work to be carried out or properly adapted for that purpose and
may be used by workers without impairment to their safety or health.
In selecting the work equipment which he proposes to use, the employer shall
pay attention to the specific working conditions and characteristics and to the
hazards which exist in the undertaking and/or establishment, in particular at the
workplace, for the safety and health of the workers, and/or any additional
hazards posed by the use of work equipment in question.
Where it is not possible fully so to ensure that work equipment can be used by
workers without risk to their safety or health, the employer shall take appropriate
measures to minimize the risks.
The general principle is that, to ensure health and safety for his employees,
the employer ensures that the work equipment he puts at his employees’
disposal is suited to perform the intended work or is sufficiently adapted to do
this,
- taking into account the labour circumstances and the foreseeable risks
- if not, the employer should take appropriate measures
This principle applies to all work equipment, not only to technical equipment
such as machines.
- the minimum requirements laid down in the Annex, to the extent that no other
Community directive is applicable or is so only partially;
Here the connection is made with the ‘economic’ directives. The user, too, has
an obligation to choose work equipment that has a CE-marking, as far as it
applies. If no directives are applicable (or if none exist), the user will have to
guarantee conformity with the work equipment directive.
a) Introduction
The ATEX-Directives describe on the one hand the technical requirements for
equipment that is used in a potentially explosive atmosphere, i.e. an atmosphere
that can become explosive because of local or operating conditions. On the other
hand, they describe requirements to exploit the workplace in the safest way
possible.
Important in all this is that this risk analysis becomes integrated in the general
process safety study, in order to conform to the requirements of the directive.
This only makes sense, however, if we are working in a process environment or
another complex environment regarding processes or substances. For process
installations, the ATEX-Directive plays on the overlap between individual safety
on the one hand, and process safety on the other.
ATmosphere EXplosible
Explosions are roughly divided into gas explosions and dust explosions. Dust
explosions are not treated any further in this context.
When gas or vapour is released, it mixes with air and will eventually dilute to a
such degree that the explosion danger disappears. Obviously this can only occur
when a good (natural) ventilation is present. Only where the proper gas/air
proportion (LEL) exists, there is a possibility of explosion in the case of ignition.
c) The Economic Part (ATEX 95 Directive, 94/9/EC) and the Social Part
(ATEX 137, 1999/92/EC)
Division of Equipment
The directive divides the equipment and protective systems, which involves more
than just electrical material, into groups and categories with different protection
levels.
Category 1: includes equipment and protective systems that have to ensure the
required safety level, even in case of an exceptional equipment failure.
Category 2: includes equipment and protective systems that have to ensure the
required safety level, even when dealing with frequent failures or predictable and
accountable deficiencies in the operation of the device.
Category 3: includes equipment and protective systems that ensure the required
safety level when operating normally.
The classification into zones takes no account of the consequences but is solely
based on the probability of an explosive atmosphere occurring. The directive
demands the prevention of the formation of explosive atmospheres; and if this is
impossible ignition should be avoided; if the nature of the activity does not allow
this, the detrimental effects of an explosion have to be mitigated so as to ensure
the health and safety of workers.
The idea behind zoning is the estimation of the likelihood that explosive
atmospheres occur. After an estimation of the probability, ignition sources should
be avoided so that the probability of an explosion becomes acceptable.
Classification into zones does not take consequences into account. When
classifying into zones, it is important that the product properties are known and
that danger sources are taken into account (for example where gas can be
released).
The ATEX 137 directive also applies to machines, via the explosion protection
document.
The relation between ATEX and the machinery directive (89/392/EEC) is different.
The ATEX-Directive is a specific directive in the sense of the machinery directive
and contains very specific and detailed requirements to prevent any risk caused
by a potentially explosive atmosphere. The machine directive only contains a
general determination of the explosion risk. For the risks caused by a potentially
explosive atmosphere, the ATEX-Directive takes priority and must be applied
supplementary.
a) Introduction
The name of the Seveso-Directive stems from the city of Seveso in Northern
Italy, where an accident occurred in the pharmaceutical manufacturing plant of
the Swiss group Hoffman-Laroche.
The main conclusions of the investigations of these accidents were that the
potential dangers associated with industrial activities were underestimated and
that legislation was no longer adapted. Because of the rising complexity, increase
in scale, and the high technological level of the industrial activities, the
government realized that it was hard to elaborate a detailed legislation that was
applicable at any given time. It was decided that legislation had to attempt to
achieve a self-regulation of the industry. The dangers had to be controlled by the
industry and everybody had to be informed of what could happen and what the
proper response should be.
b) Purpose
This goal is aimed for both for the protection of employees, the population and
the environment. The directive only concerns major accidents.
In the Seveso II directive, the stress is no longer on the risk of major accidents,
but on controlling the hazards here of. Furthermore, no distinction is made
anymore between different industrial activities, but “major accidents” are only
dependent on the presence or the potential presence of dangerous substances. It
does not matter whether production, storage or laboratory activities are involved.
The Seveso II directive has come into force in Flanders in the environmental
licenses policy (Vlarem I, Chapter IV) in 1999, and federally, in 2000, by means
of the Seveso “Cooperation Agreement” (Samenwerkingsakkoord in Dutch,
hereafter abbreviated to SWA).
On 31/12/2003, the Official Journal of the European Union published the directive
2003/105/EC that amends the Seveso II directive. (first amendment of the
Seveso II directive) This amendment of the Seveso II directive was transposed
via an adaptation of the Cooperation agreement (2006) that came into force on
06/05/2007.
Below, a short overview is given of the most important changes introduced by the
first amendment:
• Lowering the threshold values for the category “dangerous for the
environment”
• Separate addition rule for substances that are dangerous for the
environment (no longer in combination with the (very) toxic substances)
• Adaptation of the definition of an explosive substance
• Addition of the definitions of gas and liquid
• Extension of the list of carcinogenic substances
• Adding potassium nitrate to the list of the named substances
• Classification of ammonium nitrate in the list of named substances
• Classification and clarification of “Gasoline and other oil fractions” and the
lowering of threshold values
• Processing activities and the related storage of dangerous substances
related to exploitation of minerals are also within the area of application of
the directive
Environmental Legislation
Safety Legislation
In the Netherlands, the Decree Major Accidents (Risks) 1999 (BRZO 1999) and
the Hazards of Major Accidents Regulation are transpositions of the Seveso II
directive. All companies to which the BRZO 1999 applies have to do everything
necessary to prevent and limit the consequences of major accidents. BZRO 1999
applies to installations in which dangerous substances, according to the Wm
license, can be present or can be created in certain quantities as a result of
runaway reactions in an industrial chemical process.
Installations that fall under a BRZO 1999 have to have a Prevention Policy Major
Accidents (PBZO) and a Safety Management System (VBS) in any case.
Information duty also applies. In addition, companies from the high risk category
(VR-duty-bound) have to draft a safety report (veiligheidsrapport or VR), an
internal emergency plan, and an updated substance list. These duties are the
same in Flanders, except for some minor differences. In Flanders, a VR consists of
a SWA-VR and an OVR. An internal emergency plan is complusory in Flanders for
all (low and high threshold) installations, which differs from the situation in the
Netherlands. The Commission Prevention of Disasters by Dangerous Substances
(CPR) has published a number of reports in which the methods for QRA-
calculations have been included. These reports have been integrated in the
publication series “Dangerous Substances” (PGS). The Flemish legislation refers
to these publications and these methods have to be followed completely in some
cases.
When drafting a QRA to determine the external human risk, the “Manual Risk
Calculations Bevi” is consistently referred to, which is the replacement of the no
longer used Purple Book.
For some topics, Flanders refers to its own publications, such as the Handbook
Probability Rates.
Thus, it can be concluded that both Flanders and the Netherlands have the same
goal in mind, but that their practical ways of reaching it are slightly different.
There exist two regulations that apply to equipment and installations classified as
nuclear in Belgium:
On the one hand the regulation dealing with the danger of ionising radiation
for the workers and population.
On the other, the regulation dealing with the danger of losing structural
integrity of pressure equipment for the workers and population.
In the context of this overview, we will obviously limit ourselves to the second
part.
Due to the lack of any relevant legislation but also due to the lack of design and
construction requirements, Belgium pleaded, at the moment that it was decided
to build nuclear power plants, for the adoption of the American regulation of the
USAEC (United States Atomic Energy Commission) and the USNRC (United States
Nuclear Regulatory Commission), such as § 50-55a of the 10 CFR 50 (Code of
Federal Regulation) and the Regulatory Guide 1.26. These prescribe sections III
and VIII of the ‘ASME Boiler and Pressure Vessel’ code for nuclear ‘safety classes’
A, B, C en D.
In that period (1974), something like the ARAB (General Regulation for Labour
Protection) did exist in Belgium, a regulation that, among other things, provided
prescriptions for the design and construction of steam devices, but that certainly
was not sufficient for this new form of steam generation and power production.
After several evolutions of the Belgian national legislation for steam devices (the
earlier ARAB), a new all-inclusive ministerial decree was drawn up and approved
in 1993 (M.D. V4087 of 11/6/1993) for the seven Belgian plants in service at the
moment.
Due to the fact that the ministerial decree of deviation in favour of the ASME
codes is a deviation of the Belgian steam legislation, what precedes obviously
applies to ‘steam devices’.
For that reason, the amendment explicitly stated what is to be considered a
steam device.
In the context of the Belgian PWR-plants, these are the reactor vessel and the
primary loop with all devices and branch connections up until the second shutter
organ, and also the secondary side of the steam generators and the secondary
loop with all devices and branch connections up until the first shutter organ. This
whole is referred to as the ‘nuclear steam vessel’.
Furthermore, there are some individual devices that in themselves, due to their
design and operating conditions, are also subject to Belgian regulation.
Obviously such a PWR plant consists of a lot more than a nuclear steam vessel
and some devices…
Analogous to the ‘steam’ part, all other pressure-bearing devices, pipes and
installations, subject to ASME III or ASME VIII code are subject to supervision by
a Belgian authorized body, depending on their quality class (A, B, C, D or D+)
(there are some variants to this, but these are irrelevant to the current
discussion).
Design Review
Remark: the publication and conversion of the European Directive for pressure
equipment (EC 97/23) has up to this day brought about no change in the Belgian
legislation applying to equipment and installations classified as nuclear.
Steam legislation in Belgium had, for a long time, been set down in the ARAB (the
General Regulation for the protection of workers).
The ARAB regulated a lot more than just matters related to the surveillance and
inspection of new pressure equipment but also it regulated the putting into
operation and periodical inspections of steam equipment and installations.
In 1991, the regulation of steam applications was altered in a Royal and a
Ministerial Decree. The regulation of other applications than steam was also
arranged via Royal Decrees.
However, the transposition into the Belgian Law of the European Directive for
pressure equipment EC 97/23 abolished all paragraphs related to the
manufacture of new equipment in favour of this Directive. This was accomplished
via Royal Decree.
Certain chapters of the Vlarem (a regulation in Flanders) were abolished too.
In this manner Belgium has formally aligned itself with the European legislation,
namely that when implementing a Directive all national regulations dealing with
its substance must be abolished.
However, the prescriptions for putting into service and periodical inspection were
not abolished since the European Directive only applies to the introduction on the
market of new pressure equipment
The law of 12 April 1965, and the subsequent amendments to it, regulates
transport and transit of dangerous substances via pipelines and establishes a
number of requirements that apply to transportation companies and
transportation installations.
The products referred to are natural gas, oxygen, hydrogen, ethylene, propylene,
liquid or liquefied hydrocarbons, saline solutions, …
In view of the execution of the law, a number of Royal Decrees and ministerial
instructions were drafted and issued.
In addition, these Royal Decrees determine that the tests, inspections and trials
that they prescribe for the establishing, altering and repairing of transportation
These are pipes, fittings, flanges, pig traps, meters, filters, pressure vessels,
valves, hot bends, plates, … in short, all materials, accessories, and equipments
that will be exposed to pressure (excluding instrumentation).
d) Electrical Installations
Electricity
When we are discussing electrical safety, we can thereby mean different aspects,
such as:
- the safety aspects of the conception of the installations: a good selection of
materials and of the installation manners and a correct dimensioning in view
of the safe and efficient operation and safe use of the installations;
- safety when constructing the installation, with on the one hand the execution
of the installation work conforming to the design, and on the other the safety
of the individuals doing the construction work;
- the safe exploitation of the installation: drawing up and applying correct
procedures for safe operation and use, for finding and treating problems that
manifest themselves …;
- safety at maintenance, tracking failures, repairing, controlling, checking small
expansions or adaptations, and similar operations on installations in
operation, outside of the actual use of the installation.
Legislation Electricity
Figure 1.2.1.4.1
AREI
Figure 1.2.1.4.2
Protection Measures
A dangerous shocking current can run through the human body if the following
conditions are met:
1. the human body serves as conductor in a closed loop;
2. the active parts of electrical equipments, the masses or the alien conducting
parts are at different potentials;
3. the value of the current is sufficiently large or the duration of the passage of
the current in the human body is sufficiently long relative to the value of the
current to cause grave physiopathological consequences.
The protection measures against electrical shocks attempt to prevent at least on
of these three conditions. Active and passive measures can be distinguished,
whether or not they involve the cutting of the current.
The electrical protection against overcurrents must prevent that the electrical
material is traversed by currents that can harm the material as well as the
environment.
This protection must be provided by one or more devices that cut the current
before an accumulation of heat can take place that endangers the isolation, the
connections, the conductors and their environment.
Overcurrents in conductors can be of a threefold nature, which is:
1. overcurrents caused by an increase in the power contained in the user
equipment, one that rises above the normal capacity of the cable, for
example:
- as a consequence of blocking a appliance due to a mechanical overload;
- as a consequence of connecting additional appliances without enlarging the
diameter of the conductors;
- as a consequence of replacing certain appliances by appliances with more
power, without adjusting the cable accordingly;
2. impedance short circuit current in electrical material; the faults, that cause a
current with the character of an overcurrent, are caused by isolation gone
deficient;
3. short-circuiting currents.
The overcurrents caused by the non-adjustment of the electrical cable to the
terms of usage, have to be prevented by enlarging the power cables.
a) Introduction
Figure 1.2.1.5.1
Internal Affairs NL FR D
Public Health
Economy
Wallonia
Flanders
Brussels
Labour
construction
AREI, RL
materials
Hotels Environmental
Figure 1.2.1.5.2
Regions
The regions are responsible for the environmental regulations. In every region
(Flanders, Brussels, Wallonia), important chapters on fire safety have been
included in environmental legislation.
FOD Economy
The FOD Economy also has two regulations important for fire under its
responsibility, namely the Royal Decree of 19 August 1998 concerning products
intended for construction (conversion of European directive 89/106/EEC) and the
AREI (General Regulation of Electrical Installations).
In the ARAB (that is systematically being phased out in favour of the Codex),
Article 52 can be found that in addition to general principles gives an outdated
technical content that is particularly aimed at buildings. In other words, this text
gives little solid ground when dealing with industrial installations.
c) Construction Products
Fire safety is one of the main themes of this European directive in the context of
“free circulation of goods”. In this context, this means in practice that
components for, for example, sprinkler installations and detection systems are
construction materials.
To the degree that there already exist applicable harmonized standards (or
sometimes ETAs (European Technical Approval)), these materials should carry a
CE-marking with all the responsibilities that this implies.
In practice, however, it often happens that the specific equipment necessary for
or used for fire safety of industrial installations is often not available with CE-
marking, but is available with, for example, an approval of the NFPA framework
(National Fire Protection Association).
d) Other Prescriptions
Because of the European tendency to include less and less technical prescriptions
in regulations, and let the fleshing out of technical prescriptions happen more and
more via standards, we will here also have to call on standards to locate specific
prescriptions. In the chapter on European regulations, more information can be
found on this evolution.
1.2.2.0 Introduction
Before classified pressure equipment can be put into service in The Netherlands, a
so-called “Putting into Service Inspection” (KvI) needs to be conducted. This is
under national regulation.
This is different than with the directive pressure equipment 97/23/EC (PED –
Pressure Equipment Directive) that has a European reach.
An AKI is appointed by the Dutch government and can only perform inspection
activities within the Netherlands, in opposition to a Notified body in the directive
pressure equipment, which can operate anywhere in Europe.
Before the KvI became obligatory on January 1st, 2002, we had the so-called
“closer examination” in the Netherlands, as mentioned in the RToD page G 0301
paragraph 12. This was based on the old steam decree. This examination
consisted of two parts: the first included a schematics evaluation and took place
at the approval of the design, the second was conducted in the field. It is this
latter part that is the closest to the current KvI.
Both these topics are the reason why a KvI is very useful and often necessary in
practice to ensure safety. Safety is not only connected to “pressure” here.
On the first point it can be remarked that the hazards based on pressure should
be sufficiently covered by conforming to the pressure equipment directive.
Inspection
responsibility for
the User ( ARBO
decree)
Classification limits for the Putting into Service Inspection and Periodic Inspection for
pressure vessels intended for gases as classified in group I in Article 9 of PED as fas as they
are very toxic or explosive
Figure 1.2.2.1
The result is that, in such a case, the pressure equipment / assembly does not in
fact meet the requirements of the directive pressure equipment and the safety
level demanded by it.
According to the Wares law on Goods decree Pressure Equipment, the KvI has
four main objectives :
In The Netherlands, the focus of the inspection has been agreed upon and set
down in cooperation with the parties involved. This resulted in a checklist that,
because of its inclusion in a application guideline for pressure equipment (PRD), is
available to other parties than AKIs. The list has been shaped by practical
experience, and is therefore based on common sense instead of a theoretical
consideration.
Because the list is available for all parties, one would probably expect that on the
moment that the inspector of an AKI pays a visit to conduct the KvI, no remarks
can be made. Experience, however, presents a totally different picture. The
combined action of owner – EPC contractor – mechanical contractors and
subcontractors makes a KvI (still) essential.
During inspection, the inspector thus has to look at the installation from a
“helicopter view” and ask himself what, how, when and by whom is work
performed here and which interaction exists between the installation, persons and
installation parts. Does Murphy have a chance?
From its findings, the AKI draws up a Report Putting into Service Inspection
(RIK), and, after possible deficiencies have been remedied, a Declaration of
Putting into Service Inspection. Both documents are put at the disposal of the
owner of the pressure equipment.
Below, you will find a number of typical findings reported after the KvI:
Figure 1.2.2.2
On all four main objectives of the KvI, deficiencies are found. Verification using
technical documents is usually the most time-consuming.
Conclusion:
2.0. Introduction
In this chapter, a number of technical aspects will be examined in more detail and
attention will also be drawn to some shortcomings in surveillance and regulation.
The following topics are treated in this order: risk analyses, design, materials,
construction, and inspection of pressure-bearing parts, concrete and metal
structures and their coatings, electrical installations, control and safety control
circuits and, finally, fire protection. The main focus points, treated in these
paragraphs, are picked up again in table form in Chapter 4.
2.1.0 Introduction
In what follows, commonly known techniques of risk analysis are presented. First
of all, we would like to point out that risk assessment is a general term for risk
analysis and risk evaluation. Risk analysis is in its turn divided into hazard
identification and risk estimation. It is of the highest importance to clearly
distinguish these steps in every process. What we would also like to point out in
this context is that it is advisable to separate the analysis of risks from their
evaluation. Moving through all these steps motional at once leads to a loss of
quality and a waste of means as well. Because identifying hazards required for
the risk analysis requires different competencies than evaluating them, depending
on the context.
Also important to point out is the fact that the purpose of the risk analysis must
be clearly defined. The techniques of risk analysis and the depth of its execution
differ depending on the purpose of the analysis.
Examples of this difference are, among other things, risk assessment in the
context of the economical directives or risk assessment in the context of the
Seveso directives or the social directives involving explosion protection or safety
of individuals. Between process safety, safety of individuals, and external safety,
there are diverse differences and these require sufficient attention.
For danger identification, the DOW F&EI is an important instrument that allows a
possible (preliminary) hazard assessment. In the context of LNG, there is little
differentiation in the intrinsic hazards other then those based on mass,
temperature, and pressure. In other words, the intrinsic hazards of the product
are well known.
It is thus of high importance that the risk analysis focuses on the processes and
the gaps inside and around standards.
In what follows, we present some frequently used risk analysis techniques. Note
that some techniques are limited to hazard identification, and that others can
include complete analysis and evaluation. For the sake of completeness, we are
adding a checklist here as well, that, on the basis of past experience, is ideal and
supplementary from the point of view of risk analysis. The importance of well
drafted checklists should not be forgotten in this context.
• What if – method
• HAZOP – method
• FMEA – method
• Fault tree analysis
• Fact tree analysis
• LOPA – analysis
• Standard EN 1050
• Standard EN 954-1
We will not go deeper into the last two standards right now, since these will be
exhaustively and completely treated in the chapter machine safety. The big
difficulty there is defining what a process installation is and what a machine is.
Other important and necessary instruments are bow ties, cause and effect trees.
A useful instrument to document these is the PLANOP method, which was
developed by the FOD WASO, General Direction Surveillance on Well-Being at the
Workplace, Department Surveillance on Chemical Risks. PLANOP stands for
‘Progressive Loss of Containment’ and is a software-based methodology for
executing loss of containment analysis of process installations. More information
on this can be found on the website www.PLANOP.be.
Before treating the methods above in more detail, a classification of hazard and
risk-identification techniques is mentioned below, with their data requirements
and their output.
Then, it is investigated which data are required to apply the method. Seven
groups are distinguished:
• What if method:
To support brainstorming during a What-if analysis, checklists are often used. The
experience of the team is supplemented by the use of checklists. Sometimes, the
term SWIFT is used for this technique (Structured What-IF checklist).
• HAZOP method:
HAZOP is without any doubt the most widely used hazard identification technique
in the process industry. People work in a multidisciplinary team, and brainstorm
to detect dangers by looking for possible deviations of process conditions. The
team leader guides the team systematically through the piping and
instrumentation diagram (P&ID, also known as Process & Instrumentation
Diagram), using so-called ‘guide words’. These guide words are used at specific,
well-defined sections of the diagram to identify potential deviations of the process
parameters.
There are a number of factors that explain HAZOP’s success. First of all, the
method is applied to a well-defined study object, namely the piping and
instrumentation diagram. Furthermore, HAZOP is characterized by a very
systematic approach. The creative process, that risk analysis is after all, is
strongly supported by the actual questions that are generated by the HAZOP
method and this for every part of the installation to which the method is applied.
However, HAZOP is a verification technique, which limits its application
possibilities:
Yet this verification study has to be preceded by proper risk analyses in the
course of designing. Those preceding analyses should in principle expose most of
the scenarios, and on the basis of these analyses, a major part of the measures
will already have been determined.
Start
Select a process
or operating step
Yes
No
Deviation possible
No
Yes
Hazardous?
Yes
Yes
Cost adaptation
No Investigate other adaptations
acceptable?
Yes
All parameters
discussed?
Yes
All equipment of
installation discussed
Yes
Stop
The method has been included in IEC standard 61882 – “Hazard and Operability
Studies (HAZOP Studies) – Application Guide”.
• FMEA method
Also called FMEA, “Failure Modes and Effects Analysis”. This technique uses a
matrix wherein all separate system elements, their ways of failing, the effect of
each potential defect on the system itself, on the results of the system and on the
environment of the system, are inserted. The failure mode is a description of how
elements become defect. The effect of a defect is the system response or the
resulting accident.
Thus, FMEA identifies separate modes of failure that directly result in or are
important contributors to an accident. Human and operational errors are not
taken into account in an FMEA. The method is also not fit to detect combinations
of systematic defects that can lead to accidents. It is a qualitative technique,
whereby time and costs of methodologies are directly related to the number and
size of the systems investigated.
A variant is the FMECA – “Failure Modes and Effect Criticality Analysis”, which
estimates the probability of prevention for every malfunction and the graveness
for every effect. Thus, a risk number is acquired for every failure and
malfunctions can be ranked depending on their risk levels.
The method has been included in IEC standard 60812 – “Analysis techniques for
system reliability – Procedure for failure mode and effects analysis (FMEA)”.
• LOPA analysis:
These methods will be supplemented with a fault tree, event tree and MORT
analysis.
The use of risk analyses is obligatory and/or recommended by the diverse non-
prescriptive regulations, yet one has to realize the correct relationship and
estimate it in relation to existing and proven standards. Additionally, it is of high
importance that one describes its correct goals by risk analysis.
The use of internal and external information systems on major accidents are of
the highest importance in the process of risk analysis.
Important in the context of the Seveso regulations is, among other things, the
conducting of a QRA to translate the risks to the external framework, and to
calculate effects to delimit possible hazardous zones in the framework of external
interventions.
Problem areas in this matter are, among other things, the comparability of the
results in function of the included scenarios, the interpretation of risks and zones.
The same applies to the effect calculations preceding the QRA. In addition, the
usability has to be taken into account in relation to the emergency planning zones
in the context of the regulations referred to above.
2.1.3 Conclusions
The choice of the method to be applied is (often) free, and can be modified in
function of available data and the installations to be studied. However, it is more
than clear that risk analysis and management has become an essential tool in the
context of European Directives in general and the surveillance on safety of
installations in particular.
2.2.0 Introduction
In the lifecycle of a product, in this case pressure equipment, three phases can be
distinguished: design, manufacture, and utilization. To avoid major problems in
the last two phases, it is important to work accurately during the design phase.
By “design”, we hereby not only refer to dimensioning and determination of wall
thicknesses, but more generally to the specification of all parameters and
procedures that are supposed to guarantee a flawless manufacture and an
uncomplicated use in exploitation. More particularly, the design phase consists of:
- risk analysis
- selection of materials
- general dimensioning and wall thickness determination
- specification of important manufacture parameters (shape, connections, heat
treatments, etc.)
- program definition for destructive and non-destructive examinations
- definition of strength and leak tests
A number of considerations that are important for an efficient design process are
given below.
The design specification is the basic document that contains the requirements or
references to requirements that the pressure equipment has to fulfil. The absence
of a complete and clear design specification or an insufficient knowledge of its
contents by some parties (for example subcontractors) are often the fundamental
cause of problems occurring during manufacture or, later, utilization.
For important installations, the user is responsible for drawing up the design
specifications. Should he not have the capacities and/or capabilities to do this, he
has to designate a capable party himself.
A good design specification includes the following points:
scope of the design and construction
legal context
responsibilities of possible intervening parties
QA-requirements
classification of the components
specification of the construction code & standards (including the applicable
edition)
supplementary requirements in addition to the requirements of the
construction code (for example legal requirements and typical requirements
related to the application)
basic information for the dimensioning and wall thickness determination
- general dimensions
- design pressure
- design temperature (maximum and minimum)
- working pressure
- working temperature
- testing pressure
- weight
- weight fluid component
- transients
- number of cycles
- external loadings on the connections
- wind
- earthquakes
- dynamic loadings
- loading combinations and acceptance criteria to be considered
properties of the fluid
installation limits (assemblies)
supports
possible degradation mechanisms
prescriptions related to safety (such as overpressure protection)
prescriptions related to in-service inspection
To ensure that all parties take the design specification into account, the basic
documents (drawings, calculation note, material list, etc …) produced during a
project should refer to it.
The construction code chosen must be fit for the application, for example vessel,
pipe, tank, …
Once the construction code is defined, the requirements relating to the following
flow forth from it:
selection of materials
dimensioning & wall thicknesses determination
qualification of manufacturing processes & personnel
qualification of non-destructive examination methods & personnel
program and criteria for destructive and non-destructive examinations
strength and leak tests
QA/QC aspects
In the design phase it has to be verified that the material specifications, the
dimensioning, the determination of wall thickness, and the manufacturing and
inspection program meet the requirements of the construction code. In contrast
with what is often found, all requirements of a code must be respected and there
can be no mixture of requirements of different codes. The requirements of
a code constitute a coherent whole and it is this coherent whole that ensures that
what is constructed has an adequate level of safety. For purposes of illustration:
construction codes with less strict quality criteria for materials use a lower
allowable stress than construction codes with stricter quality criteria for materials;
thus it is not allowed, unless supplementary requirements are made, to apply
lower quality materials in the framework of a construction code with a higher
allowable stress.
The materials for the pressure-retaining parts have to be chosen from the list of
allowable materials included in the construction code. Furthermore, the specificity
of the application has to be taken into account: high/low temperature, sensitivity
to corrosion, capacity for welding, etc.
For many materials, supplementary requirements in addition to the requirements
of the material standard exist. They are specified in the construction code and/or
the design specification. The material certificates have to show that all
requirements are met.
If materials that were not included in the construction code are used, their fitness
should be checked, taking into account all requirements included in the
construction code for comparable materials. Often these are hardly taken into
account.
During the design phase, the dimensions of a pressure device are defined in the
design drawings. These shall take into account the geometrical limitations
prescribed in the construction code, such as:
central curvature radius in dished heads
knuckle radius in torispherical heads
welding details for mounting pipes, flanges, stiffeners, …
transition angles in the case of wall thickness variations
relative position of longitudinal welds in the case of adjacent cylindrical shells.
The calculation note has to show that the wall thicknesses mentioned on the
design drawings are acceptable according to the criteria of the construction code,
taking into account the loads specified in the design specification. To show the
validity of the calculation note for the application, the former needs to refer to the
design specification and the design drawings on which it is based. In addition, it
has to contain sufficient data to allow an independent review by a third party.
The as-built drawings take into account the deviations of the final product from
the design drawings. If these deviations are outside the tolerances the individual
responsible for design needs to verify whether the final condition still meets the
design criteria. More particularly, the calculation note needs to be reconciled with
the as-built drawing. This important verification is all too easily ignored.
2.2.7 Specifications
2.2.8 Conclusion
In order to avoid problems during the fabrication and the utilization of the
equipment, it is important to work accurately during the design phase. The
following points are important for an efficient and correct design process:
availability of a complete and comprehensible design specification
clear assignment of the responsibilities among the different parties
application of the construction code in a coherent way
consistency between the data in the different design documents
agreement between the calculation notes and the as-built drawings
2.3.0 Introduction
In the context of the design and fabrication of pressure-retaining parts, the basic
materials of the components are of fundamental importance.
Materials are primarily selected relative to the expected function of the pressure
equipment, this often consists of a combination of different parameters, such as:
The kind and type of certificate required is also important to mention in the order,
and may depend on different factors.
The different types of material certificates can be best illustrated by use of a
European standard. Other, non-European certificates can often be relatively easily
associated with this.
2.3.1 Certificates
1. A 2.1 certificate
A document wherein the manufacturer declares that the products supplied are
conforming to the requirements of the order without mention of possible
testing results.
2. A 2.2 certificate
A document wherein the manufacturer declares that the products supplied are
conforming to the requirements of the order and wherein he presents testing
results from non-specific tests.
This means that the products supplied are not necessarily those inspected or
tested , and that these inspections and tests are carried out according to the
manufacturer’s procedures and not necessarily those determined in the
product specification.
3. A 3.1 certificate
A document drafted by the manufacturer wherein he declares that the
products supplied are conforming to the requirements of the order and
wherein he presents testing results.
The tests to be carried out are those determined in the product specification,
in official regulation and the associated requirements and/or in the order.
The document is validated by an authorized representative of the inspection
service of the manufacturer, one who is independent from the production.
4. A 3.2 certificate
A document drafted by two parties, on the one hand by an authorized
representative of the inspection service of the manufacturer, one who is
independent from the production, and on the other by an authorized
inspection representative appointed by the customer, or an inspector
appointed by official and applicable regulations. In this document they declare
that the products have been delivered conforming to the requirements of the
order. This document also contains testing results.
Type 2.1 and 2.2 certificates are often used for less important (read: less risky)
applications (for example in the European Directive for Pressure Equipment
97/23/EC for category I equipment or for other than the main pressure-retaining
parts in category II, III and IV equipment).
Type 3.1 and 3.2 certificates are actually identical content-wise, except that in
the case of a 3.2 certificate a third party is involved who has to ensure conformity
of the order together with the material manufacturer.
The involvement of a third party obviously has its implications. On the one hand
these interventions always come at a cost, and on the other a specific reception
and inspection is at stake here, something that can impact the tests to be carried
out and the delivery time.
To partly deal with these issues, sometimes an upgrade of the material delivered
with a 3.1 certificate is carried out. Here, the 3.1 certificate is, by sampling or
not, confirmed in the presence of the third party. In case the results of the
inspections and/or testing are confirmed, an equivalent 3.2 certificate is drafted.
This procedure is convenient for bars, plates, pipes, … but is more problematic
when cast or forged pieces are involved.
Due to the production processes of such materials, more attention needs to be
given to aspects such as the traceability of heat numbers or lots of heat
treatments.
The 3.2 procedure with intervention of a independent (and neutral) third party
does not only give more guarantees of intrinsic quality (read: conforming to
material specifications), but also gives an additional guarantee as to traceability
and origin of the material.
However, as we will see later on, a 3.2 certification, for different reasons, does
not always offer the guarantees expected of it.
Certain certification institutions have eagerly used this to make money. Thus,
many European, but especially non-European, material manufacturers got an
offer to check and certify their quality system, specifically for use within the
European Pressure Equipment Directive 97/23/EC. When the assessment was
positive, they became holder of a certificate of recognition as a material
manufacturer within the scope of this Directive. From our market experience, it
appears that many, especially non-European material manufacturers were duped
by this. Due to their lack of experience and knowledge of the Directive, especially
in the beginning of its application, they gladly made use of the “help” offered.
Fact is that such a certification is not required at all, and what appears from the
practical examples given later is that many of these certificate holders, especially
those in India and Southeast Asia, even have no idea of the value of such a
certificate.
In other cases the type of certificate is set in the construction standard. Thus,
section III of the ASME code requires that materials for pressure-retaining parts
are delivered with a CMTR. CMTR is an abbreviation for Certified Material Test
Report, and is actually a type of 3.2 certificate where a third party, appointed by
the customer, functions as an “authorized inspector”, a qualified and recognized
third party specifically in the scope of this application.
Materials are not always bought straight from the material manufacturer. Too
small amounts of too many different kinds of materials could cause unacceptable
and unreal times of delivery and prices.
In these cases suppliers that buy and store important stocks of materials to sell
them later to the final users, are called upon. Needless to say that, particularly as
traceability is concerned, it is of exceptional importance that such suppliers are
very careful in handling the identification of materials and with the appended
certificates.
- Upgrade of pipes, diameter 3/8”, sch 160 in ASME SA 182 316L for a nuclear
application.
Description of the problem:
Due to the relatively small quantity needed, material with a 3.1 certificate was
purchased. Due to the necessity of guarantees on the quality of the material,
it was decided to run all tests and inspections required by the material
specification and by the order on every pipe length (of 6m).
The pipes were all supposed (and certified) to belong to the same heat
number and the same lot of heat treatment. On review, it was seen that for a
number of pipes the intergranular corrosion test was insufficient. In view of
the homogeneity of the lot this was theoretically impossible.
Cause:
At the degreasing after fabrication (this is accomplished by submerging the
tubes with a basket in a bath) it was shown that, at regular times, tubes were
not entirely flat in the basket, which was why one of their extremities was not
degreased. The carbon in the oils and fats used in the fabrication were left
unneutralized on those loci and diffunded between the granular borders of the
steel during the following heat treatment, which caused a number of tubes
showing an unacceptable structure.
to proceed to 3.2 certification. See annexes 3.2 and 3.3. As is apparent from
the reports and conclusions, it is not evident for these organisations to
demonstrate sufficient competence and trust, despite every possible ISO
9001s and other certifications.
- Upgrades of pipes, fittings and flanges with a 3.1 certificate in the context of
the Belgian gas regulations.
Of the 96 different heat numbers tested, 21 had to finally be declared
unacceptable because the mechanical test results were insufficient, 2 had to
be declared unacceptable because of defects in the material, and 1 had to be
declared unacceptable because of dimensional shortcomings. More than
twenty percent of the materials were thus rejected because the testing results
of the 3.1 certificate were not conforming to reality.
As an illustration the annex 3.5 contains some remarkable results:
• Item 2, heat number 180RZ: both the results of the tensile test as those of
the impact tests were insufficient.
• Item 5, heat number 201RV: the results of the impact tests are insufficient
• Item 71, heat number 106781: anomalies in the chemical analysis
- Edited certificates.
In annex 3.7 a 3.1 certificate is included that dates from May 6, 1996 and yet
refers to the European Pressure Equipment Directive 97/23/EC (only effective
from November 29, 1999 onwards). The composer of the certificate is even
presumptuous enough to mention that his organisation was certified by a well-
known qualified organisation for supplying materials conforming to this
Directive. It is a pity that the certificate also cannot be withheld for other
reasons because this kind of material can only be used for structural purposes
and not for pressure-retaining equipment.
- Copied certificates.
In annex 3.9 two 3.1 certificates are included of different manufacturers for
material with the same heat number. The results are simply copied from one
certificate to the other, yet in this process, the temperature of the impact
tests suddenly changes.
- 3.2 certificates
Annex 3.4 features a 3.2 certificate of a third party, drafted on the basis of a
3.1 certificate distributed by the manufacturer. One notices that the third
party has simply copied the results of the mechanical tests and the chemical
analysis to its own document. Furthermore, there is no mention of the
different heat numbers included in the 3.1 certificate and a mistake occurred
during the copying of the dimensions. (For item 1, a wall thickness of 2.87mm
and a pipe length of 9m is indicated, where the 3.1 certificate indicates a wall
thickness of 3.91mm and a pipe length of maximally 6m.)
Additionally it was established that on the same day, the same inspector
drafted more and different 3.2 certificates for materials produced in different
locations.
From the explanation of this internationally active third party (and Recognized
and notified Body), it seems that, in February 2006, they do not yet apply the
2004 edition of the EN 10204 standard. This explanation is supposed to be
part of a justification why this organisation, in a 3.2 certification, did not
witness the sampling nor attended any tests, being content to just copy the
information of the 3.1 certificate to a 3.2 certificate.
However, their arguments do not make sense, because the previous 3.1.C (an
outdated name for 3.2) certificate in the previous edition of the standard was
identical.
The 3.2 certification which was supposed to offer additional guarantees
therefore has absolutely no added value in this case, but is on the contrary
misleading, thus producing the opposite of the effect desired.
2.3.3 Conclusions
Despite the importance to be able to have materials that are in compliance with
the specifications while the mechanical characteristics are taken into account in
the design, we have seen here that, in practice, they are sometimes handled
carelessly and irresponsibly.
ISO 9001 certificates or other approvals based on a general evaluation of the
quality system of the manufacturer does not really offer an added value here and
do not provide a final guarantee of the quality and conformity of the materials.
The most important reasons why things go wrong are carelessness and partly
also incompetence or ignorance of the manufacturer. But, we also see that third
parties are not always innocent and sometimes adopt, as a way of profiling
themselves or because of market pressure, methods that certainly not have
positive effects.
In practice, there is no watertight solution, or the whole fabrication process
should, from the preparation of the steel up to delivery, be under supervision of
an independent and reliable third party, something not only utopic, but also
unpractical and unaffordable.
It remains clear, however, that 3.2 certification still offers more guarantees than
3.1 certification. Fact is that in such cases only sufficient supervision and
assistance in key operations has any chance of identifying deficiencies.
Of course, more (external) quality control affects costs and times of delivery,
which both are primordial parameters in the contemporary, liberalized market.
Yet a consensus will have to be reached to ameliorate the current situation. Only
then can situations as those presented in the annexes be avoided.
2.4.1 Impact
The codes utilized identify and define the deficiencies established for different
kinds of products, mainly for welds.
These are divided in groups and are mentioned, for example, in ISO 5817
(EN 25817).
These deficiencies must be detected, interpreted, and finally evaluated.
Depending on the functionality of the products, a threshold level is defined that
determines acceptance or rejection.
a) Visual Investigation
The first investigation with which the department Quality Control (QC) is charged,
is the visual investigation of the equipment and of possible welds.
No measure or analysis equipment is necessary, except possible extra lighting,
instruments allowing a better vision, and/or accessories to determine the
dimensions of the deficiencies.
The conformity with drawings and the dimensions of the welds have to be
checked.
b) Surface Investigation
Then the surface investigations begin: dye penetrant and/or magnetic particle
testing.
The dye penetrant testing works according to the principle of the capillary
attraction in the holes of the surface whereby these are filled with a penetrating
fluid. After removing the superfluous penetrating fluid remaining on the surface, a
second product (the developing product) is applied. This extracts the penetrating
fluid out of the holes and makes it more visible by creating an effect of contrast
(coloured penetrating fluid on a white background) or fluorescence (fluorescent
penetrating fluid activated by UV-rays).
c) Volumetric examinations
Radiographic examination
Adaption.
Method and technique must be selected taking into account the product to be
controlled and the deficiencies to be investigated. A device in rust-free steel
cannot be controlled for surface cracks by means of a magnetic analysis, because
this kind of steel is not ferromagnetic and the investigation will therefore reveal
nothing.
Reliability.
If all steps of the preparation and execution of the examination are executed by
meticulous employees trained for this purpose (adapted training that is regularly
refreshed) and who are experienced (with the product and the method), the
usage of an apt method and technique must lead to reliable results. The vision
and experience of the operator are of decisive importance, because half of the
analyses conducted stand or fall with human interpretation and evaluation.
Reproducibility.
An examination conducted on a moment M1 by operator O1 and supported by
report R1 must be executed again on a moment M2 by another operator O2 and
must be supportable by a report R2 that must be completely identical to R1. The
qualification of the operators and the procedure for applying the technique are
absolutely necessary for reproducibility. Essential variables are defined and
calibration blocks exist for all available techniques to guarantee and control
reproducibility.
Examinations must always begin with visual examination before surface and/or
volumetric examination. If no specific surface and/or volumetric examination is
requested, the visual one should be unavoidable.
One does not begin an investigation for a weld when this one is too small or
incomplete, or one of which the welding slag have been insufficiently removed; a
magnetic examination cannot be performed on non-magnetic rust-free material; a
welding too thick for the requirements of the code must be ground off before
radiographic examination is conducted; an ultrasonic examination is impossible
without a review of the drawings to take the geometrical features of the zones to
be investigated into account.
Dye penetrant testing has the advantage that it require not much material and no
external power, but temperatures under 10° centigrade or humid circumstances
can impair the testing or even render it inexecutable. Products packaged with
aerosols and solvents damage health and environment and also create an
explosion hazard.
For the magnetic particle testing an electrical power source is always needed
(permanent magnets excepted: however, this is a rarely used technique about
Examinations with roentgen and gamma beams are conducted with material that
weights tens of kilos and involves generation of very intense and strongly
penetrating electromagnetic beams for the industrial application. Its safety aspect
(ionising radiation!) is without doubt its most disadvantageous element, but this
type of examination produces good results in tracking three-dimensional
deficiencies if application limits are respected (materials, thickness of the material
relative to the type of radiation and the type of radioactive isotopes, freezing of
not desirable beams, sharpness of the granule on the film or the resolution of the
digital equipment …).
Flat deficiencies such as lack of fusion on the bevel or between layers are more
often found by coincidence because the detection of them depends on the
deviation angle between the direction of the beam striking the film and the plane
on which the deficiency is located: the closer the angle is to zero, the better the
deficiency’s visibility.
As to documentation and inspection, radiographic examination has the advantage
that an image of the deficiencies can be saved and consulted after the execution
of the analysis and even during the lifetime of the equipment.
For documentation and inspection, AUT examinations have the advantage that an
image of the deficiencies can be saved and consulted after the execution of the
analysis and even during operation of the equipment.
With the development of more recent AUT methods such as Phased Array,
multiple ultrasonic techniques can be combined. TOFD, for example, is an ideal
technique to detect and measure deficiencies in the volume of the weld, but is
relatively weak on the internal and external surfaces. A combined TOFD / Pulse
Echo analysis uses TOFD for volume and Pulse Echo for surface, making it
possible to acquire the best analysis results.
The operators need to have the required experience on the levels of knowledge of
materials and production methods, welding processes and general and specific
deficiencies caused by this. This experience is required to utilize the most apt
techniques for detecting deficiencies.
The costs tied to the examination cannot influence the price of the inspected
products negatively, but have to be judged on their proper value. Sometimes
they are ridiculously low relative to the possible costs on products that are
damaged by a lack of investigation or tampering with the examination.
One also cannot attempt to reduce training, competence of operators, quality of
products and of used materials to minimize construction costs.
As was mentioned succinctly earlier in this text, every method has its area of
application and its limits and incompatibilities.
Below are listed some examples of flagrant or more concealed deficiencies that
are often found:
Penetrant Testing
Radiographic examination
Ultrasonic examination
2.4.6 Conclusion
• The documents not conform to the “as built” situation (for example drawings,
cable calculations, …)
• Zoning file not drafted in advance, but only after construction of the
installation.
The points mentioned above are mostly due to a lack of communication and
absence of pre-existing agreements.
2.5.2 Inspection
• Inspections are required for partial installations. In view of the size of the
installation, it is not always evident to keep track of what has been inspected
and what has not. In addition to this, the inspected installation can be altered,
making the inspection report no longer conform with reality. It is of great
importance that the EDTC (External Service for Technical Inspection) keeps
good track of the work performed and that after the work is done, inspection
can commence immediately. Also important for the inspections is to call upon
a limited amount of people who have been continually present on the
construction site to better keep track of the work done. If the inspector only
comes by afterwards and half of the construction is already invisible, it
becomes very difficult to perform a (good) inspection. Therefore we strongly
advise the constructor to let the EDTC (External Service for Technical
Inspection) follow the construction closely from the beginning.
2.5.3 Organisation
The EDTC (External Service for Technical Inspection) can be appointed by both
the contractor as the subcontractor.
If the EDTC is appointed by the subcontractor, conflict might occur because in
this case commercial interest may prevail. Because of this, the EDTC (External
Service for Technical Inspection) is better appointed by the contractor to
guarantee an independent surveillance.
2.5.4 Conclusions
From the above, it clearly appears that, for a good tracking of electrical
installations, which have an important contribution to the safety of the complete
installations, a number of preconditions have to be met:
- The EDTC (External Service for Technical Inspection) is best appointed by the
contractor to guarantee its independent surveillance.
- The inspectors involved have to be present on the construction site almost
permanently.
- It is very important to have good agreements in advance and to communicate
these agreements to all people involved.
Recent experience teaches that hidden deficiencies can occur with major projects
in The Netherlands. From a census taken from bridge experts, for example, it is
clear that these hidden deficiencies often had negative consequences for
structural safety, utility, and durability of the bridge construction.
In Belgium, a so-called insurance contract with ten-year liability is usually
concluded when dealing with major projects. To acquire this insurance, an
independent technical inspection is required and at the delivery of the work a
statement of approval is drafted that allows the work to be insured. But also if no
insurance is concluded after the works, a technical inspection can offer added
value.
All deficiencies in the structural parts of the work that are due to errors in design
or competency or materials that were unknown during the statement of approval
and the delivery of the work. This term also refers to deficiencies caused by
defect or malfunctioning water tightness of both structural and non-structural
parts of the work.
For the construction of an LNG terminal, where the architectural constructions are
important and subject to very different loads such as those described in the EN
1473, a TIS can also be useful.
Beyond the scope of the TIS are the works that have to be performed by or in the
name of the client in the context of design and realisation of the construction
project, such as making the design products, contractual management,
realisation of the work, representation of the client or (other technical)
surveillance within the framework of the execution. These works are performed
by other contractors.
When performing the TIS, the following basic assumptions are used:
The TIS works objectively and independently
The TIS indicates to the building contractor during the phase of (contract)
execution which drawings and documents are needed for the execution of its
duties and which period is needed for the appraisal or inspection.
The TIS hereby takes into account the planning of the project and the nature and
extent of the work.
The inspections of the execution of the work are conducted in conformation with
the planning of the contractor. For this purpose, the TIS has the planning –
including the execution planning – of the contractor at its disposition;
The TIS gets access to all locations (construction yards, workplaces).
The works the TIS conducts for the delivery of the statement of approval can be
divided into two phases.
The first part of the works involves the design of tender documents. The tender
phase can be based on a complete design by architects or design offices or on a
design-and-build procedure. On the basis of an analysis of the question
specification and a risk scan on the designs or the initial design, a sufficient
quality level of structural safety, usability and durability of the initial design is
aimed for.
A question specification is the input in the tendering procedure with which the
work is put on the market. The TIS reviews a number of relevant contract pieces
for possible limitations vis-à-vis the delivery of the statement of approval.
In case of a complete design, the TIS is conducted from the beginning of design
activities. During the different phases of the design, the TIS will judge whether
the design conforms with applicable standards (Dutch, European …) and
directives (CUR-reports …).
In the case of a question specification and the possible consequence of the tender
procedure with a competitive dialogue that is often divided into a number of
phases, the TIS conducts a risk scan and appraisal of submitted designs in every
phase.
After the appraisal of the submitted materials is complete and the economically
most advantageous submission has been found, a clarification round will take
place to establish the “durability” of this submission. Here, the TIS will indicate on
which points it sees a increased risk in relation to the possibility of acquiring a
statement of approval. It will indicate this on the basis of a risk scan of the
submitted design belonging to the economically most advantageous submission.
After every phase of either design or procedure with question specification, the
TIS will draft an analysis report to allow the designers to adapt either the design
or the submission documents. This report usually contains the following
elements:
- short project description or technical description of the part of the work
the report is about
- overview of the documents involved in the analysis
- overview of the checks conducted on the design
- overview of the review of the calculation designs employed by the
designer, basic assumptions, load assumptions and method
- risk of hidden deficiencies
- potential exclusions of the statement of approval
- synthesis and advice on design and execution risks related to the
statement of approval
The second part of the work is aimed towards the (contractual) execution phase
of the design.
These works are performed to establish whether the statement of approval can be
truly acquired, which means that the work has been designed and built in such a
way that the risk of possible hidden deficiencies related to constructive safety,
usability and durability of the work has been reduced to an acceptable level.
The inspection involves the risk on hidden deficiencies and includes at least:
- checks of the design’s basic assumptions;
- checks of the construction in relation to the applicable standards and
directives, legislations and regulations;
- checks of the calculation models employed by the designer, basic
assumptions and load assumptions (including standards);
- checks of environmental factors that can directly influence the risk of
hidden deficiencies in the work;
- the inspection must take into account the computer programs used and
analyse the applicability of these computer programs
Just like in the design phase, reports are made of the phased risk-oriented
inspection of the design documents.
The appraisal of the risks of execution documents takes place by means of risk-
oriented inspections of the execution documents.
The purpose of inspecting and appraising risks of the execution of the work is the
timely identification of inadequacies in the work that can lead to possible hidden
deficiencies in the context of the statement of approval.
Inspections of the work are conducted in conformation with the applicable Arbo
legislations and regulations.
Inspections take place on the construction yard or on other locations where parts
of the work are produced.
Inspections are conducted in such a way that the risk of possible hidden
deficiencies is minimalized.
Inspections are conducted regularly.
The number of inspections, their frequency and time is determined on the basis
of:
- the nature and extent of the work;
- the risk scan
- a self-performed risk analysis of the work
- the research reports, design and execution documents;
- inspections already carried out.
At certain times, the TIS imposes stops. At these points, the contractor may only
continue working when the inspection is completed on location. This is particularly
important for the inspection of placement of important reinforcement or pre-
tension cables before the pouring of concrete is commenced. The same applies for
placement isolation or vapour-limiting isolations before grouting or the like are
applied for the construction of tank walls or floor plates.
Inspections include all risk-related aspects of the work.
A report that indicates which parts of the work were inspected and whether any
remarks were made related to the execution is drafted after every inspection.
When deficiencies are serious, the client is informed as soon as possible.
a) Foundations
b) Structures
2.6.5 Conclusion
From the above the important role of independent technical inspections during
the different phases of the construction of concrete structures becomes clear. The
quality of these inspections can be the determining factor for the reliability and
safety of the installations.
Coupled with these loads there are the possible ways steel structures can fail:
There is often not one unambiguous cause why steel constructions will fail. Most
of the times, it is a consequence of a piling up of blunders, deficiencies or
coincidents. The most frequently occurring deficiencies judging from our
experience are:
a) Design Errors
- Often changes are made to the concept during the design process and even
during the execution. Frequent changes in the concept lead to a heightened
chance of design- or detailing errors.
- The calculation and drawing of steel constructions has been outsourced to
external design offices for ages. These dispose of sophisticated software
packages that can perform all calculations conform to a certain standard.
These days, we are able to calculate constructions that are made just strong
enough. In the past possibilities were less extensive, and larger safety
margins were employed during calculations. Reducing the safety margins
implies that less room is left for small errors or deficiencies during the
execution or montage phases.
- The software packages mentioned above are in fact a “black box”. A large
number of parameters can be inputted and an abundance of results comes
rolling from the computer mere seconds later. These results are often
considered absolute and are not questioned afterwards. Yet a change in
certain basic hypotheses often leads to totally different results. By using this
software, the calculator loses his “feeling” with the construction. The use of
complex software packages can never replace a solid know-how, common
sense, and experience. The usage of calculation software can thus create
dangerous situations.
b) Execution Errors
During execution too, all kinds of errors can happen that afterwards lead to
annoying and dangerous situations. One has to try to trace these errors as
quickly as possible and to correct them to minimalize repair costs. Here also, an
independent party can be useful by conducting inspections in the workplace and
during montage.
- Reviewing whether the last revision of the design drawings is available in the
workplace
- Inspection of the conformity of the execution with the drawings. (dimensions)
- Inspection of the material certificates
- Inspection of the welding preparations
- Inspection of the weldings (possible NDO for critical weldings)
- Correct execution of the connection details, correct placement of stiffeners.
- Inspection of tightening torque of high-resistance bolts
- Geometrical inspections: inspection of flatness and perpendicularity,
alignment of certain parts
- Are montage tolerances met?
- Inspection of certain ergonomic and safety aspects for later users:
- Height and resistance of guard-rails
- Minimum proportions of manholes
- Safe access to machinery
- Correct placement and montage of anchoring points for safety lines
c) Fatigue
In the long term, fatigue is one of the most important causes of the failure of a
steel structure. Fatigue occurs when an element is exposed to a great number of
variable loads. Structures sensitive to fatigue are for example production
machinery, lifting devices, rolling bridges, masts and chimneys. Fatigue cracks
can happen on those places in a steel structure where there are great tension
concentrations. The propagation of these cracks can lead to a rapid degeneration
of the resistance of the affected element and may possibly lead to breakage with
possibly major consequences. These cracks rarely appear in the basic material
and almost always in the vicinity of weldings or connection elements. Especially
weldings are sensitive to fatigue.
Controlling the risks of fatigue demands a specific type of study and a certain
execution of the connections. The basis is a correct definition of the predicted
loads, their frequency, their amplitude and their variations in time; specialists
refer to the load spectrum. The minimal lifespan of the structure can be defined
by the final user as well. On the basis of all this data, the designer can then select
a certain type of connection, taking into account the technical and economical
feasibility of the whole.
The welders are to execute these connections, carefully taking into account the
correct welding procedures to reach the desired stress concentration class.
There is much information on these problems: results of tests in the lab,
university studies, catalogues supplying specific resistances of certain weldings
and finishing details. More specifically this involves Wöhler curves, stress
concentration factors, classification of weldings according to their type and
finishing.
Strain gages are also available to measure stresses in a steel structure near
weldings.
A strain gage is really a small electrical resistance that is bonded to the steel
structure. By the appearance of mechanical stresses, the electrical resistance of
the strain gage will be altered. By measuring and registering these resistance
alterations, dynamical loads that are hard to determine can be very exactly
defined.
This technique allows a comparison between the behaviour of the structure and
the design hypothesis and thus to make an accurate judgement on the expected
lifespan of the structure.
d) Corrosion
a) Specifications
This standard treats all aspects related to the conservation of steel objects, such
as:
- determining the three categories of lifespans;
- classifying the different environments in function of their aggressiveness;
- concept and corrosion-friendly designs;
- description of different types of soil and their pre-treatment
- description of different types of paint systems and their layer thickness
structure in function of the expected lifespan and the aggressiveness to
which the object will be exposed;
- the manner in which the different systems should be applied,
climatological circumstances, possible labtests to be carried out, how to
track and inspect the work activities, etc…;
- drafting specifications for new buildings and maintenance systems.
- choice from the selected painting systems, taking the different possible
manners of surface preparation into account (ISO 12944-4);
- minimizing the damage to the environment and all risks connected to
safety and hygiene (ISO 12944-1, ISO 12944-8);
- drawing up a work program and selecting an applicable method (ISO
12944-7);
- drawing up a control program during and after the work activities (ISO
12944-7, ISO 12944-8);
- drafting a maintenance program for the entire lifespan of the conservation
system.
b) Vendors
Once good and workable specifications are available, these are added to the order
to all vendors. They are requested to conserve according to these specifications
and possibly present their own coating procedure with selected painting system
for approval.
It is here that a second problem emerges: rarely do we get a vendor specification
that is completely in conformity.
Not all existing standard (housing) specifications of manufacturers of valves,
tanks, coolers, pipes, prefabs, equipment etc… are already in conformity with the
standard mentioned above. Some keep on working as of old, with non-adapted
standard procedures and using painting products from the manufacturer round
the corner.
The consequence of this is that many vendors ask for variations on the
specification; a time-consuming activity for he/she that has to qualitatively assess
these deviations to the directives of the existing specification.
Luckily, more and more constructors that have their objects conserved are
adapting their methods and systems to the ISO 12944.
The standard ISO 12944 is only partially applicable to the conservation of isolated
objects. All specific aspects related to the isolation itself, such as for example the
design and choice of painting system in function to design temperature, are not
described there.
That is why we will go deeper into the matter here.
In fact, combating corrosion, also under isolation, starts on the design desk.
a) Designing Critically
During the design phase, it is to be taken into account that painting and isolation
have to happen on the spot.
Difficultly accessible locations are therefore to be avoided as much as possible.
Supports to benefit isolation of pipes and devices should, in cooperation with
designers and isolation specialists, be installed beforehand and not during
construction.
Sufficient space has to be provided to allow for a good installation of isolation and
plating.
Valves have to be placed in vertical pipes as much as possible. Then, they can be
isolated by water draining. In case that a valve has to be placed in a horizontal
pipe, the spindle should whenever possible be placed horizontally instead of
vertically. Furthermore, valves should always be controllable from steps or
ladders; this prevents walking on the isolation.
No flat steel rings should be used for an isolation welded directly against a pipe or
device. These rings can then work as collecting places for moisture etc. and thus
cause serious corrosion. It is better to apply clips or loose, circular rings.
Especially for stiffening rings connected to devices working in a vacuum, a good
detailing of the isolation has to be provided because these places are very
sensitive to corrosion.
Cold bridges are to be avoided. It is also wise to have as much equipment as
possible painted and/or isolated by the manufacturer of said equipment, since the
quality obtained will almost always be superior then conservation systems and
isolations applied on location.
All the points mentioned above point in one direction, which is: an isolation or
painting system, too, requires design, either in combination or separately.
Further focal points related to applying the isolation are: apply as many
prefabricated isolation materials as possible; this is faster, cheaper, and the
material lasts longer.
Isolation material for cold application needs to be prefabricated in the workplace
as much as possible and needs to be finished through use of a tape or foil, to limit
vapours. Only montage seams need to be finished on the spot.
It is valid at all times that as much work as possible should be completed in the
workplace, especially in winter!
Conserving under isolation is a “must”. But what is, exactly, a good painting
system under isolation?
All big producers of painting products for industrial applications have their own
specific formulations. Multiple factors have to be taken into account to make a
well-founded selection from the painting products.
The isolated environment can become very aggressive (certainly on the seaside),
just consider accumulation of salts, namely chlorides during the becoming wet
and drying of the isolation. Furthermore, salt traces are hygroscopic and thus
retain humidity longer, therefore exacerbating the corrosion.
When dealing with rust-free steel from the AISI 300 series, for example, the risk
of stress corrosion, a crack-forming corrosion influenced by mechanical pulling
stresses, needs to be taken into account. Two things can be done here: painting
or aluminium foil wrapping; Aluminium has the advantage vis-à-vis rust-free steel
in that it has a cathodic operation, just like zinc with steel. If one chooses to
paint, this is to be done with a “zinc-free” product.
For example, for highly alloyed steel objects with carbon steel parts (supports or
flanges), use one system both for carbon steel and for highly alloyed steel, this to
prevent mistakes. For this purpose, select a painting system that is chosen for
the highly alloyed steel.
Despite all well-selected materials for isolation and paint, things can go wrong in
practice. What is the cause of this? The durability of a painting system in the
construction phase is completely dependent on a good surface preparation.
External circumstances such as the weather, time pressure, etc. should be
prevented from affecting the execution of the work. When the whole system is
applied as prescribed in a single time, this prevents many problems.
One painting system will almost never fail because of the paint itself, but almost
always because of other circumstances such as insufficient surface preparation,
environmental temperature, relative humidity and product selection in relation to
(natural) environment, object temperature, nature of the object material, and
method of application.
Experience teaches that isolation systems, when inexpertly applied, can cause
corrosion damage. All isolation materials for industrial applications available on
the market have their specific good features. Use these during the application of
the materials.
For example, for warmth isolation a soft material needs to be used, such as wool
types. For cold isolation, hard materials such as extruded or foamed construction
elements are preferable.
So when is hard isolation to be applied, and when soft?
As soon as the operating temperature of a system is constantly lower than the
environmental temperature on the location, a hard isolation material with a
vapour-limiting finish, is to be applied.
Should the operating temperature of a system be constantly higher than the
environmental temperature and require isolation, then a soft isolation material is
to be selected. This must then be finished using (non-vapour-limiting) plating, to
prevent water percolation.
When dealing with varying temperatures, the best option is a hard isolation
material that can also handle high temperatures; the lowest temperature is the
most determining in this case.
The system or object to be isolated must be dry, free of dirt, rust etc. and it has
to be painted. The isolation to be applied must also be clean and dry. When
dealing with multiple layers, the isolation must be executed in half-brick skin and
should be applied tightly using a wire or hand (of rust-free steel).
Instead of using kit to render the plating watertight, the preference should
strongly be to design water-draining structures.
When applying the plating, finishing the isolation with plating material,
precautions can be made to avoid corrosion problems. Here, a so-called roof tile
construction can be achieved by making the plates overlap in a correct manner,
an effective aid. Furthermore, much attention needs to be devoted to tops of high
towers and vessels; a segment top might be pretty, but a pointed top is simpler
and has less seams.
When finishing tank roofs or tops of high towers and vessels, synthetic fibre, such
as a laminated fibreglass-reinforced synthetic fibre that renders a completely
seamless finish, can also be used instead of metal plating.
On places where the isolation still has to be stepped upon, an isolation material
with a higher load density can be applied, finished with, for example, aluminized
steel plates.
Before repairing plating, the paint system has to be checked for corrosion.
Possible corrosion needs to be treated. Not repairing established rust damage
under plating is obviously not an option.
Figure 2.8.1
Comparison of two rust degrees
The location of the blasting and painting halls on-site has to be as strategically
possible to avoid unnecessary displacements during the conservation process. But
oftentimes these halls are makeshift “cabins” that in no way contribute to the
quality of the blasting and painting work.
A decently conditioned hall is certainly no luxury.
b) Climatological Circumstances
The period for conducting painting work is fixed in principle. A painting season
starts in March and ends in September. The ideal is that the construction is
planned in such a way that the finishing can be done in summer. But experience
teaches that this is not always possible because of several factors. Once
September comes closer, we find that the “paintable hours” are reduced
drastically due to condensation, rain, etc.
Should one still desire to conserve in this period, this is only possible by
sufficiently protecting zones to be painted. Every professional, self-respecting
team thus has to dispose of the necessary measurement and registration
equipment to anticipate climatological circumstances.
c) Blasting Work
f) Working Heights
During the preparatory phase, certain painting systems have been set by the
constructor. Often, the type of paint is named after the binding means such as,
for example, a two component high build micaceous iron oxide. Since there are
different paint manufacturers offering these products or their alternatives on the
marketplace, it is recommended to choose only one of them. If not, a mix of
systems is acquired that cannot guarantee compatibility among each other. Some
form of guarantee and responsibility is impossible in this case. If this is not
feasible for the entire project, one can choose to divide the construction yard into
zones with each its own paint manufacturer.
Conservation and isolation are often the last to be discussed, sometimes a few
days before the completion date.
It is necessary to choose an
adapted painting system.
Mill scale.
Stagnation of water.
Reference List
This chapter offers an overview of the focus points and inspection approach
concerning the most important aspects of fire safety.
In short: the guidelines for the planned organisation have to be set during the
design phase together with the technical guidelines.
A1) Prevention
--- beginning of quotation from the “Law of August 4, 1996 Concerning The
Well-Being at Work” ---
Art. 5.- § 1. The employer takes the necessary steps for the promotion of the
well-being of employees in the execution of their work.
A2) Repression
Examples:
- “sufficient” distance between different installations on a single industrial
terrain to limit the spreading of a fire and explosion from one installation
to the other, cf. the division in “companies”: every “company” is far
removed from other “companies”, and in that way not only is possible
spreading limited but the spacious intervention paths between the
companies remain available;
- distance in itself is not always enough or feasible, and additional “passive”
measures can be: designing constructions in a way that they can resist a
certain external explosion pressure, building of walls or the construction of
embankments to protect certain parts of the installations, etc.;
- offices, social premises (coat room, showers, dining room,…), and control
rooms are built at a safe distance from the industrial installations and are
where required combined with a design that allows sufficient resistance to
a fire or explosion to render a safe evacuation possible (the catastrophe at
BP in Houston, for example, caused a number of victims by the presence
of contractor-offices between the industrial installations);
- banks around the storage tanks is a form of compartmentalization as well.
Detection
Important aspects:
- In industrial installations the detection of the release of inflammable
products is highly important. It allows for action to be taken before a fire
or explosion occurs.
- The fire detection technology has to be adapted to the operating
circumstances (resistant to weather and wind and the influence of the
installations and used products) and to the phenomenon to be detected
(smoke, heat, …). The EN-54–series is at this point in time especially
aimed at detection in buildings and is less fit for open-air detection, in
other words in industrial installations (see list of EN-54 standards in
appendix).
- Especially for detection technology for which no standards exist yet, such
as fire detection through video cameras, it is important to have practical
agreements in advance on the inspection method and criteria.
- Detection systems are used as a trigger for a series of signals and controls
that should render a fast and efficient intervention possible. In addition to
testing the detection itself, the testing of these signals and controls is thus
crucial (cf. below, integration and scenarios).
Automatic Extinguishers
As far as sprinkler systems (foam or not) for industrial installations are
concerned, European standards fall short as well. The NFPA-directives (or the
FM global directives grafted upon it) describe more concretely how industrial
risks can be limited with automatic extinguisher systems. In addition to design
and execution guidelines, the NFPA directives also provide clear maintenance
and testing procedures.
Another focus point are those parts of the scenarios that are embedded in the
installations via hard- and software.
Important here are the protocols between the different systems (are they
compatible?) and the reliability of their operation.
f) Inspection
Some examples:
- Points in the directives that are open to interpretation, are better cleared
out in advance. Last-minute changes because of different interpretations
of inspector and designer can cause huge problems: extra costs,
slowdowns, changes impacting other parts of the installation, etc.
- Practical tests on location: agree in advance when these will take place, by
what means, what criteria, etc. Keep these things in mind, for example:
o testing detection systems with “a test fire” without any preparation or
planning and safety measures before testing are often not executable
o the same goes for testing extinguisher systems, for example deluge
systems, foam extinguisher installations, etc.
o it often happens that fire safety systems are only inspected in the last
phase or are tested in conditions that disallow certain practical tests
(for example because certain parts of the installation are already
operational), rendering a possible modification of the installation
problematic
o testing of inbuilt scenarios such as disabling certain parts of the
installation after detection can no longer take place, for example, when
production is ongoing while it is clear that testing these scenarios is of
The given examples are not based on our practical experiences during the
construction of LNG terminals but are based on the construction of other similar
complex industrial installations and discussions with safety engineers and
managers of e.g. LNG terminals.
Some of the most relevant examples:
- Distances between the storage tanks differ to a high degree if one compares
different LNG terminals. On the basis of NFPA directives, the mutual distance
is at least half a tank diameter. The EN standards (see EN 1473 – Annex A)
describe the mutual distances by calculating the radiation heat, for example.
From shared experience it is clear that multiple calculation methods are used
that render strongly differing results.
From the outset of the project, it is thus necessary not only to enforce respect
for a certain standard, but also to describe more narrowly how it will be
applied. For example, which mathematical model to use, which design
parameters, etc. This prevents discussion afterwards and simplifies inspection
on the correct observation of the distance requirements.
- At some terminals, not only is there a bank around the storage tanks, but also
below the pipes and certainly below critical points such as the flanges. In
addition, these areas have been equipped with an automatic fire extinguishing
system using foam. The automatic foaming system is controlled by fire
detection, namely IR-detection. Through a “voting system” between multiple
detectors, the fire extinguish system is rendered operational.
With execution, multiple problems come to the surface, namely:
o In some cases the general contractor that was familiar with things such as
piping and controls of industrial installations, designed and built large
parts of the active fire security himself. Apparently the tender allowed for
this, with as a consequence the application of components and calculation
methods unusual (read: not compliant) for fire safety.
o A number of additional remarks were recorded on various sites:
A normal PLC (later replaced by a safety-PLC) for the detection system
and the control of the extinguishers, while approved systems for this
application exist.
A foaming extinguisher installation that was unsatisfactory in practice,
for example because of self-designed foam spray muzzles and a
wrongly proportioned pipe network.
NFPA 11 (foam extinguisher systems) requires, for example, that the
number of minutes for the completion of the foam coverage, has to be
set in advance. If the NFPA 11 is just imposed without further
clarification of which design parameters are desirable, then the
contractor is left at great liberty in building his installation.
In other words, the inspection of an installation by a third party
produces in that case a number of founded remarks with consequently
important (expensive) adaptations.
To sum up, the following recommendations can be derived from the above:
- When drafting guidelines it’s advisable to take into account the following
remarks :
o Compile the technical guidelines with care and attention to detail.
o Make sure that specialized companies install fire safety installations,
according to agreed-upon guidelines and this both for possible calculations
and for components and execution on location.
o Provide a good management of design modifications during the project.
(management of change)
- For the inspections:
o Involve the Controlling Bodies as much as possible in the project.
o For example, let the guidelines be validated by qualified controlling bodies
for the aspects that are relevant to them. Ask what the inspection
procedure will be, so that it can be taken into account.
o Let the design (and its possible modification) of actual installations be
approved by the qualified Controlling Bodies (in other words, don’t wait for
an inspection of a completed installation).
Reference List
2.10.0 Introduction
Control and safety control circuits are an essential part of the functioning and
security of complex industrial installations. In what follows, we are first going to
situate control circuits and then explore safety control circuits to a larger extent.
These will be illustrated by means of the onion model (Figure 2.10.1) that was
already presented earlier on in Chapter 2.1
In process safety, safety control circuits are located in layers four and seven (see
the onion model in Figure 2.10.1). The purpose of a safety control circuit is to
detect a deviation in the process in relation to normal process conditions on the
one hand and steer the process towards a safe condition on the other. Exceptions
are, among others, manual emergency shut downs (ESD’s).
In the process industry, active measures are divided into control circuits and
safety control circuits.
Here, the following remarks can be made on the development of ESD systems:
SIL Determination:
Moreover, the possibility exists to carry out the determination of the SIL levels,
based on IEC 61511, annex F, in which is referred to the so-called LOPA study
(Layers Of Protection Analysis). In this case, one person can apply the
determination method on the basis of a quantitative approach.
SIL Verification:
On the basis of standards, a device has been developed, explicitly for electrical,
electronic and programmable electronic applications, that allows us, in a relatively
simple manner, to assess and subsequently test, the architecture and failure
probability of a safety control circuit and whether or not it complies to the
assumed expectations (SIL determination).
3.0. Introduction
At the end of the seventies, the interministerial task group “Safety Aspects LNG
Terminal” was founded in view of the construction of the LNG Terminal in Zeebrugge
(Figure 3.1). The purpose of this task group was not only to take care of the license
modalities, but also to establish the safety standards against which the LNG Terminal
would be measured.
Thus, the advice of the interministerial task force was included in the final license,
granted by the Royal Decree of August 7, 1981.
In addition to the advice of the interministerial task group, said license also referred
to the Belgian regulation for the transport of dangerous products by means of
pipelines (in short: the Gaslaw) and required the involvement of an Authorised
Inspection Organization to survey the tests, inspections and trials.
For the extension of the LNG Terminal (2004–2008), the advice of the
interministerial task group was asked again. In their report it was stressed that for
the extension the same security principles were to be applied, unless a more
optimalized solution guaranteeing an equivalent level of safety were to be possible.
This time, the advice of the interministerial task group was included in the Ministerial
Decree of September 29, 2004, to supplement and amend the existing transport
license.
Apart from the safety standards on a local level, different European directives were
also taken into account for the extension of the LNG Terminal, such as the Pressure
Equipment Directive 97/23/EC.
3.1. EPC-contract
No longer is an installation for the storage and/or transportation of natural gas solely
an affair of public utility. Indeed, because of purely economic motivations, oftentimes
a group of investors decides to build an installation collectively.
Since the partners in such a project do not always possess the necessary technical
know-how and experience and/or in view of the fact that financial costs and planning
related to the investment are primordial parameters, such projects are often
outsourced via an EPC-contract.
The abbreviation EPC here stands for Engineering, Procurement, and
Construction.
For the extension of the LNG Terminal in Zeebrugge too, an EPC-contractor was hired.
Yet it is to be noted that Fluxys LNG, because of their technical know-how and
experience as owner and exploiter of the existing installation, did not give the EPC
contractor total independence. Thus, a whole series of project specifications were
construed above all the legal requirements and obligations, sometimes leading to
far-reaching additional safety requirements. In addition, Fluxys LNG, together with
their engineering service have conducted a great number of additional quality and
conformity checks.
Quality and quality control are two concepts that are inconceivable to do without in
our contemporary world.
Most companies now have a quality system within which their own quality and
inspection services function. Furthermore, the intervention of an independent
company or third party is possible for the carrying out of certain inspections.
To clarify who exactly fulfills which task, the following will for simplicity’s sake talk
about “internal” and “external” quality control.
a) Actors
Primarily, this is the quality service of the manufacturer or the contractor that
surveys the quality of the work done. In addition, the customer can, if he should
wish so, conduct additional inspections and check the quality delivered.
is, in theory, in his best interest to ensure that these materials fulfill the
requirements made.
Apart from this, the owner or exploiter of the installation can obviously conduct
additional inspections as final customer. All this is schematically represented by the
schematic below. (Figure 3.2).
Engineering
General Design
Specifications Procurement
Design
Fabrication
QC EPC-contractor
Construction
QC Manufacturer
Reception Materials
QC Contractor
Construction
Testing
Figure 3.2
Both for the quality services of the manufacturer or the contractor, as for the
inspection service of the EPC-contractor or the owner, there is a risk that other
elements beside quality and safety influence the final appraisal.
b) Remarks
In contrast with the internal quality control, the external quality control is provided
by an independent institution or third party, both of whom are supposed to have
neither a direct nor an indirect interest in the final results.
When the specific case of quality control of mechanical and pressure-retaining parts
is analyzed, three groups can, in the context of the extension of the LNG Terminal in
Zeebrugge, be distinguished (Figure 3.3):
General Design
Specifications Procurement
Design
Manufacture
Notified Body
Final inspection
Reception materials
Possible intervention
Required intervention
Figure 3.3
The intervention of the Authorised Inspection Organization involved both the storage
tank and the piping.
For the mechanical and pressure-retaining parts, the following elements were
considered:
Storage tank:
• Roof penetrations
• Filling lines
• Pump columns
• Overpressure relieving devices
Piping:
a) Design
General design:
Procurement specifications:
Design:
Manufacture:
Final inspection:
c) Construction
Reception of materials:
• Identification of materials
• Spot visual examination
Construction:
Testing:
3.2.5 In Practice
a) Quality Control
In the context of the extension of the LNG Terminal in Zeebrugge, it was attempted
to perform the task of the Authorised Inspection Organization not only as primary
inspector (by directly attending and controlling certain activities) but, due to the
intervention of different Third Parties and Notified Bodies, also as a general surveyor
with the purpose of increasing the effectiveness of the intervention as Authorised
Inspection Organization and lowering the number of double checks and reinspections.
Practically, this amounted to the fact that the intervention points of the Authorised
Inspection Organization were not merely defined on the basis of legal requirements
and/or the possible additional requirements of the customer, but that the
intervention points of the Third Parties and/or the Notified Bodies were also taken
into account.
Initially, it was, for example, prescribed that the design of the piping would only be
checked after the approval of the Notified Body. For the review of the documentation
of the different manufacturers too, it was predetermined that these would already
have been checked and approved by the EPC-contractor, the Third Party and/or the
Notified Body before these would be presented to the owner and the Authorised
Inspection Organization.
The idea behind this method was to make the parties involved (specifically the EPC-
contractor) take their responsibility.
Practice, however, has shown that different documents that were presented were not
(first) checked by the EPC-contractor, the Third Party and/or the Notified Body, or
that remarks only reached the final manufacturer when it was sometimes already too
late.
The initial intent of basing a number of controls on the intervention points marked by
the Third Parties and/or the Notified Body also proved too optimistic very soon.
Indeed, at the moment when these intervention points were clearly perceived, again
fabrication had often already begun or been completed.
Not only in the extension project of the LNG Terminal in Zeebrugge, but also in
several other projects, a very strict planning is maintained these days, something
that naturally influences the time of delivery of materials. In this case therefore,
insufficient or no room was sometimes allotted for the quality control of these
materials.
Not only time pressure, but also the inexperience and egotism of some persons or
institutions responsible for quality control, are reasons for the fact that these cases
are sometimes approached from a theoretical viewpoint.
On the level of organization, for example, it was asked on multiple occasions to
check calculation notes without the corresponding construction drawings being
available, to check welding procedure specifications without the supporting procedure
qualification records being available, etc.
On a technical level, one easily hides behind clauses that may or may not be literally
included in the applicable directive, standard or specification. The most striking
example of this is perhaps EN 10204, which in the context of the 3.2 certification
does not literally specify that the tests (be they through sampling or not) should be
attended by the Third Party.
All this, combined with the eventual establishing of different lacks and shortcomings,
necessitated a correction of the prescribed inspection approach and an eventual need
for more inspection visits than was initially provided for.
b) Quality Assurance
4.0. Introduction
This chapter contains a number of points meriting attention for the most
important topics, which were extensively discussed in the previous chapters
(mainly chapters 2 and 3). These are found in the first part, and can have an
impact on the safety and quality of industrial installations during the construction
phase. In the second part, a start is made with drafting an inspection plan.
4.1. Concerns
The points meriting attention found below are not based on coincidences. They
are a representation of the most important shortcoming regularly found during
inspections in the context of the construction of industrial installations. The
attention points mentioned most often have already been discussed in more
detail, mainly in Chapter 2 and 3 of this status report.
The attention of the reader is directed to the fact that it was never the intention
to draft a complete list, and that this list is not an inspection program. The
purpose of it is to direct attention to a number of critical points that regularly
cause trouble.
In the tables that follow, you will find the relevant attention points arranged per
topic (equipment and installations under pressure, concrete structures, coating
and isolation and fire safety) and per phase (generalities, design, materials,
manufacturing, inspection and quality assurance). In a number of case, certain
chapters and paragraphs are referred to for more explanation.
1. Design
1.1. Cf Chapter 2.2. In many cases, it is unclear for which medium or The drafting of a design specification should
temperature an equipment or installation under pressure has happen in a very early stage. Its
to be designed, or whether fatigue or external influences prescriptions have to be made known to the
such as wind loads should be taken into account. authorized inspection organization, the
notified body and/or third party.
Therefore, a design specification should be compiled that
contains the prescriptions, or references to these, to which
the pressure equipment and/or installation have to conform.
The lack of a complete and clear design specification, or the
insufficient familiarity with its contents by some parties (for
example subcontractors) are often the fundamental cause of
problems surfacing during manufacture or during later
exploitation.
1.2. Cf Chapter 2.2. Independent of the requirements of the applicable regulation, With the extension of the LNG Terminal in
it is necessary that a construction code be selected. All Zeebrugge, the construction code for the
prescription of this construction code have to be respected tank, piping, and pressure equipment was
(this applies to design aspects as well as materials, imposed in the license.
construction, inspection, …) and there should be no mingling This is not the case, however, in for example
of prescriptions from different codes. the European pressure equipment directive,
Indeed, the prescription of a code constitute a coherent where only a series of essential safety
whole, and it is this coherent whole that ensures that the requirements are imposed.
construction is sufficiently safe.
The notified body is responsible to check
whether or not the essential requirements of
the directive have been met. The verification
of the coherent application of a construction
code is not necessarily part of its mission.
1.3. Cf Chapter 2.2. The pressure equipment or the installation regularly deviates This important exercise is often forgotten, as
in the final condition from the design drawings. If the is the formal confirmation of compatibility
deviations should be outside the prescribed tolerances, or if, between the calculation note and the as-built
for example, other materials were applied, the design officer drawings.
should verify whether or not the final condition is in
conformity with the design criteria. In particular, the This review should be conducted by the
calculation note should be brought into conformity again with contractor, the design office, and the notified
the as-built drawings (checks of compatibility). body.
2. Materials
2.1. Cf Chapter 2.3. The selected material should be included in the construction In the context of the European directive for
code. Some manufacturers sometimes erroneously select the pressure equipment, a separate material
application of a (cheaper) construction steel (for example EN evaluation should be drafted for materials not
10210 S355J2H) instead of a steel fit for pressure-bearing included in a harmonized standard.
parts (for example EN 10216 P355NL1).
Experience teaches that the manufacturers
and/or notified bodies do not always take into
account intrinsic qualities and application
areas of the materials and often limit
themselves to a review of the mechanical
characteristics (strength and tenacity).
2.2. Cf Chapter 2.3. From experience it can be said that, for more than 20% of The European pressure equipment directive
the materials delivered with a EN 10204 3.1 certificate puts the choice of the type of certificate in
(pipes, plates, castings, forgings, …), deviations exist function of the statute of the material
between the values included in the certificate and the manufacturer.
veritable characteristics of the materials involved. For material manufacturers whose quality
A EN 10204 3.2 certificate offers more guarantees system has been approved by a body
(conformity with materials specifications & traceability) than competent for this and established in the
a EN 10204 3.1 certificate, on condition that there has been European Community, it suffices that
sufficient surveillance and assistance during key operations materials are delivered with a EN 10204 3.1
to identify deficiencies. certificate.
Those deficiencies can be of very different natures:
- erroneous chemical composition In the context of the extension of the LNG
- erroneous mechanical characteristics (strength, Terminal in Zeebrugge, all cryogenic
tenacity, …) materials and all materials intended for the
- copied certificates transportation of gas under high pressure (>
- falsified certificates 14,7 bars – see Belgian Gaslaw) were
3. Manufacture
3.1. All ‘special processes’ (welding, soldering, bending,…) should Where the European pressure equipment
be executed in conformity with qualified procedures and by directive applies, the welding activities should
qualified staff. Nevertheless, deviations are regularly be checked in a sampling manner by the
established that can have implications on the structural notified body, if the manufacturer has
integrity of materials, pressure equipment, or installations. selected a module with actual inspections
(modules C1, F, G).
This in particular for welding activities: However, because of market pressures, it is
- insufficient preheating so that even in those cases, the notified
- wrong intermediate temperature bodies have to limit their surveillance on the
- wrong application of postheating or cooldown welding activities to a minimum.
- wrong filler metal or problem of traceability of the
filler metal In the context of the extension of the LNG
- unqualified welders Terminal in Zeebrugge, the welding activities
- … on the process piping and the tank (both in
prefab and on the yard) were conducted
under permanent surveillance of the
authorized inspection organization.
4. Inspection
4.1. Cf Chapter 2.4. The methods and techniques for the non-destructive testing Only for module G, it is required in the
of materials and welds have to be selected by the framework of the European pressure
manufacturer in function of the product to be controlled and equipment directive to approve the NDT
of the deficiencies that should be detected. It is also procedures formally by the notified body. In
important to check that the applied method and technique practice, no or little attention is again
are able to detect the expected indications, that all NDT devoted to this.
procedures are formally approved by a level 3 operator and
that, where needed, the procedures are qualified In the context of the extension of the LNG
(demonstration of detection degree). Terminal in Zeebrugge, the NDT procedures
were checked by a specialist of the
authorized inspection organization.
4.2. Cf Chapter 2.4. When performing non-destructive testing, even when Where the European pressure equipment
qualified procedures were used, deviations can regularly be directive applies, the non destructive testing
detected that can compromise the structural integrity of the activities should be checked in a sampling
construction: manner by the notified body, if the
- when only a percentage of the welds is to be checked, manufacturer has selected a module with
the manufacturer often chooses to have the most actual inspections (modules C1, F, G).
accessible or most ‘favourable’ welds inspected; it is In this case however, surveillance is often
sometimes even asked to mention the faulty welds in limited to reviewing the films (even this does
a separate report (which is not included in the official not always happen) and reviewing the NDT
file) to limit the number of faulty welds and thus to reports.
prevent an augmentation in the number of welds to be
inspected In the context of the extension of the LNG
- the approved procedures are not applied correctly Terminal in Zeebrugge, non-destructive
(radiation time, type of probe, …) testing (in prefab, on the yard, and when
- inspections of repairs not being conducted in the inspecting the materials) was conducted
correct location under surveillance of the authorized
- wrong interpretation of results inspection organization. For the most critical
- wrong criteria applied when interpreting results inspections, the expertise of a level 3
- … operator was called upon.
5. Quality
Assurance
5.1. Cf Chapter 1.1.1 Lack of sufficient experience and knowledge of the auditor,
and lack of coherence between the quality system of an
organisation and the activities that were supposed to be
controlled by this system, lead to an inefficient use of this
tool.
1. Design
1.1. Cf chapter 2.6. Often many changes are made to the concept during the design It is the task of the technical inspection
phase without taking into account the implications these bureau to conduct risk-oriented checks in
alterations have on the final stability and durability of the every phase of the construction project with
construction. particular attention for the final durability of
the construction.
1.2. Cf chapter 2.6. The calculations and the drawing of constructions have been The software package mentioned on the left
done by the designer or an external design office for a very long are very much like ‘black boxes’: a great
time. These parties dispose of sophisticated software packages number of parameters is inputted and an
that can do all calculation conforming to particular standard. abundance of results comes rolling out of
Before, possibilities were less ample, and higher safety margins the computer. These results are all too
were used in calculations. Decreasing safety margins allows less often considered absolutely true, and are
space for mistakes or deviations. not questioned anymore. We see that
through the use of software, a designer
looses his feel with the construction and
with reality. A technical controlling bureau
often provides a new way of approach or
questions things that are no longer noticed
by someone involved in the project for a
very long time (and cannot see the wood
because of the trees).
2. Execution
2.1. Cf chapter 2.6. Also during the execution of construction activities, all kinds of If no independent body should be present
(unpredictable) things can happen that can endanger the quality on the construction yard that conducts an
of execution: umbrella inspection (inspection during
- unfavourable weather circumstances that endanger design and execution), then who will point
planning: since planning has to be met at all costs (by out the effect of some decisions on quality?
designers, constructor), often it is quickly conceded to
alter agreed-upon execution methods (for example:
imposed phases, length pouring phases, …) to make the
deadline anyway.
- Being behind on planning due to too late delivery of
execution plans, too many changes in the project in a too
late stage, decisions not being made,…
2. Execution
2.1. Cf chapter 2.8. An evaluation of the painting companies before the start of
activities is advisable to test a number of aspects, such as, for
example, the application procedure, the competence of the
painters,…
2.2. Cf chapter 2.8. The materials delivered should be inspected. Often non-
conformities are found in the nature and quality of the systems
applied.
2.3. Cf chapter 2.8. All activities should be executed conforming to the approved Because of unadapted scaffolds, often
procedures. Nevertheless, very often deviations are found that can certain zones remain unreachable or hard to
have an implication on the quality: reach, with the consequence that these
- climatological circumstances are to be followed from close zones are incorrectly coated or isolated.
by; all too often painting happens at, for example, a too
high air humidity
- during application of the first layer, often ‘mistakes’ happen
with the type of primer
- if the different painting layers are not different in colour, it
is impossible to check the number of applied layers
- the roughness profile should be checked; this is necessary
to guarantee a good stickiness (critical when dealing with
stainless steel)
- insufficient protection of stainless steel, with welding sparks
or dust as a consequence; extra manipulation is then
necessary before passivation.
- when painting flanges, all bolt connections should remain
free of paint
- …
2. Execution &
Inspection
2.1. Cf chapter 2.9. Practical tests on the terrain: agree in advance when these are For example, think of:
planned, with which means, criteria, etc. It often occurs that fire • testing detection systems with “fire
safety systems are only inspected or tested in the very last phase, types” without preparation in
which prevents certain practical tests from being conducted planning and safety measures before
anymore (for example, because parts of the installation are the test itself, often do not happen
already in service) and because of which a possible adaptation of • the same goes for testing
the installation in response to the inspection becomes extinguishing systems, for example,
problematical; testing the built-in scenarios such as the shutdown deluge-systems, foam extinguishing
of certain parts of the installation after detection cannot, for installations, etc.
example, be conducted when the production is already operational,
while it is clear that testing these scenarios is of crucial
importance; it often happens that individual safety systems
operate correctly but that the interaction between systems has
been incorrectly configured.
• The intention of these inspections is the concern for safety, health and
environment, but they can also be expanded toward company security.
• The approach is the safety analysis has been conducted and has led to
determining design, construction, and inspection rules, and that these are
set in the design specification. As concerns the safety analysis, it is
important that the seriousness of a danger and the probability of it are
taken into account.
• The origins of this approach are twofold, on the one hand the result of
safety analysis of the installation and of the combined individual
components, on the other the result of our practical field experience.
• It is the intention that the future user of this tool makes his/her own
selection from the series of attention points that are identified in function
of the SRC (safety related category), depending upon the gradation in
categories that applies to him/her.
4.2.1 Approach
4.2.2 Remarks
PRESSURE
Aspect and Subaspects SRC Check Inspection Activity Time of
by x inspection
Preliminary
Safety Analysis Verifies availability During design
Test the completeness and clarity
Design Specification Verifies availability During design
Test completeness
Evaluate the conformity with the safety analysis
Buyer specification Verifies availability for all materials and components At the
Evaluate conformity with the design specification beginning of
Evaluate conformity with technical purchase phase
standards/specifications
Test completeness
Manufacturing specification Verifies availability for all relevant manufacturing During
processes (welding, forming, heat treatment,…) purchase phase
Evaluate conformity with the design specification (for individual
Evaluate conformity with technical components) or
standards/specifications during
Test completeness montage
Inspection specification Verifies availability for all components to be inspected During the
Evaluate conformity with design specifications purchase phase
Evaluate conformity with technical (for individual
standards/specifications components) or
Evaluate competence to identify sought-for indications during
Verifies the qualification of the technique/procedure montage
Test specification Evaluate conformity with design specifications During the
Evaluate conformity with technical purchase phase
standards/specifications (for individual
components) or
during
montage
Design
Design calculations Evaluate conformity of input data with design During design
specifications
Evaluate whether the correct calculation parameters such
as allowable stress, 0.2% or 1% strain,…, were used, or
correct hypotheses were made and whether all load cases
were accounted for
Evaluate whether the design takes all design data into
account, such as fluids to be pumped away, erosion,
ageing, fatigue, transients, number of cycli, wind, earth
quakes, dynamical loads, supports,…
Check whether only one design code was used
Evaluate whether the calculation note contains sufficient
information for an independent review
Drawings Evaluate whether welding configurations and other During design
fabrications details are in conformity with what the
design code provides for and allows for
Evaluate whether the construction/design allows for the
required non-destructive investigations in the different
phases (manufacture, exploitation)
Evaluate whether the impact on calculation notes of the Before putting
differences between the ‘as designed’ and the ‘as built’ into operation
situation were checked
Inspection (non-destructive and Verify that all NDT procedures are formally approved by a
destructive) level III operator
Check whether for certain non-destructive investigations,
the procedure should be qualified (demonstration of the
doability of the procedure) …
Evaluate whether the applied method is able to detect
the expected indications
Check whether the operators are formally qualified for
the specific technique and possible subtechnique (for
example, US on austenitic casting parts)
Check the NDT reports for completeness and correctness
Confirm the results of the investigation for X % (of the
component, of the number of components, of the length
of the welds, of the number of welds …)
Evaluate whether the program of production test coupons
was realized
Evaluate whether the results of the tests on the
production test coupons are acceptable
Testing – Strength and Tightness Evaluate whether the correct testing pressure is applied
Tests (taking into account the different design pressures,
heigth differences, …)
Evaluate the correctness of the pressure test procedure
(sequence of pressurizing and depressurizing, venting,
draining, position of valves and other appendages,
durations, …)
Evaluate whether a correct testing medium is used
Evaluate the instrumentation (manometers) that are
being used, for example, scale, capacity, calibration, …
Evaluate the objective results (pressure drop,
deformations, leaks, …)
Verify that a distinction has been made with the tightness
test if required
Data book Evaluate the contents set down in the design code and/or
regulations
Evaluate the efficiency of the use of the data book for the
future exploiter (repairs, spare parts, replacements,
alternative methods of inspection, …)
Evaluate the traceability between soft and hardware
(which document belongs to which component)
Design
Audit Painting Company Not considering an ongoing QS with the intervening Start of
parties, an independent assessment of the painting purchase phase
company can be envisaged (quality audit based upon
ISO 9001, evaluation of a recently completed
construction yard, general theoretical and technical
professional knowledge)
Vendors Evaluate the application procedure and the selected Start of
materials purchase phase
Paint manufacturers Evaluate / analyse the quality of the proposed products Start of
purchase
Execution
Inspection during application at Vendors’ Purchasing of steel for paintability During
workshops Evaluate the preparation of the substrate production
Analyze the chlorine ions on the substrate and in the
blasting means
Evaluate the application of the different layers
Evaluate the execution and/or results of the qualitative
tests
Measure the layer thickness in a sampling manner
Inspection of the supplied materials Verify the painting systems used and their conformity At delivery
with the applicable specifications
Check the applied layers
Measure the layer thickness in a sampling manner
Conduct tensile tests
CIVIL WORKS
Aspect and Subaspects SRC Check Inspection Activity Time of
by x Inspection
Basic Specifications Evaluate the availability and correct usage of soil At the start of
analyses the design
Evaluate the seismic risks
Evaluate the influence of the environment (sea…)
Evaluate the usage of a correct standard frame for design
calculations
CHAPTER 5 : CONCLUSIONS
After thoroughly reading through this report, its reader will realize that there are
really numerous aspects that can endanger the quality and safety of an
equipment or installation when approached erroneously.
In addition, the freeing of the European market leads to a situation where the
economic players, who experience the consequences of this globalization in a very
concrete manner, are less and less controlled. More and more, they are
considered the sole entities responsible for their products (materials, equipments,
installations, …). That is generally what they like best, as the secretary-general of
Orgalime put it recently: “Test houses very often play an essential role in helping
manufacturers in the design and testing of their products. But this should be as
far as possible a B2B relationship and we do not like obligatory 3d party
certification (…).”
We therefore hope that they have been a useful source of inspiration and
information for the Dutch government. The Belgian governments, of which some
services were also involved in this study, will also have been very interested in
certain Dutch particularities, such as inspections before putting into operation of
industrial installations (a mandate nonexistent in Belgium in the conventional
sectors, especially for pressure risks, steam installations excluded) and the
importance of a regular communication between inspection bodies and the
authorities.
To conclude this study, we would like to stress a number of aspects that from our
point of view as an inspection body and on the basis of our experience,
indisputably contribute to a higher safety level of an industrial installation:
The inspections and checks by the different project actors (manufacturers,…) are
particularly important. The economical realities and especially the pressures of
polyvalent nature that they cause make it even more essential that inspection
activities are conducted by independent inspection bodies (so-called third party
inspections).
An inspection by an independent body will only provide extra value if this body
disposes of competent and experienced staff. It is therefore proper that the
number of bodies that is designated by the government, is limited,
allowing them to gain and transmit expertise.
The problems related to quality and safety of equipments and installations can
often only be discovered via inspection activities. The individuals charged with
these inspections, have to dispose of a broad mandate, allowing them to
regularly check the different construction phases.
An efficient government control over the market and its different actors
remains essential. In this way, deviations can be discovered, and measures can
be taken to remedy them.
This study can be no endpoint, but, if and where deemed necessary, it can be a
start for further exploration (for example, by further developing an inspection
plan), for training and adapted coaching of the surveying personnel and for a
restructuring and optimisation of the surveillance structure.
We hope that this status report can modestly contribute to the amelioration and
reinforcement of the rules that guarantee the quality and safety when building
industrial installations. Without forgetting that quality is above all a mentality, a
philosophy that all levels of human organization should use as a guiding thread.
“We are convinced that the management practices overseeing the Space Shuttle
Program were as much a cause of the accident as the foam that struck the left
wing.”
and
“It is our view that complex systems always fail in complex ways, and we believe
it would be wrong to reduce the complexities and weaknesses associated with
these systems to some simple explanation. Too often, accident investigations
blame a failure only on the last step in a complex process, when a more
comprehensive understanding of that process could reveal that earlier steps
might be equally or even more culpable.”
Abbreviation Explanation
AISI American Iron and Steel Institute
AK Anforderungs Klasse
AKI Aangewezen Keuringsinstantie (Nederland) / Authorized Inspection
Organisation, The Netherlands
ARAB Algemeen Reglement op de Arbeidsbescherming (België) / General
Health and Safety Regulation (Belgium)
ARBO Arbeidsomstandigheden (Nederland) / Labour Conditions, Law on
(The Netherlands)
AREI Algemeen Reglement op de Elektrische Installaties (België) / General
Electrical Installations Regulation (Belgium)
ATEX Atmosphère Explosible / Explosive atmospheres
AUT Automatisch Ultrasoon Onderzoek / Automatic ultrasonic testing
AVG Abstand - Verstärkung - Grosse/Distance-Amplification-Size
BC Besturingscategorie / Control category
Bevi Besluit externe veiligheid inrichtingen (Nederland) / External Safety
of Installations, Decree on (The Netherlands)
BPCS Basic Process Control System
BRZO Besluit Risico op Zware Ongevallen (Nederland) / Control of major-
accident hazards involving dangerous substances, decree on (The
Netherlands)
BWR Boiling Water reactor
CEN Comité Européen de Normalisation / European Standardisation
Committee
CENELEC Comité Européen de Normalisation Électrotechnique / European
Electrotechnical Standardisation Committee
CFK Chloorfluorkoolstofverbinding / carbonfluorinechlorine compound
COP Conformity of Production
CPR Commissie voor Preventie van Rampen (Nederland) / Commission for
Prevention of Disasters (The Netherlands)
CUR Centrum Uitvoering Research en Regelgeving (Nederland) / Centre
for Execution of Research and Legislation (The Netherlands)
DAC Distance Amplitude Connection
DCMR Dienst Centraal Milieubeheer Rijnmond (Nederland) / Public Service
Department Environmental Control Rijnmond (The Netherlands)
DIN Deutsches Institut für Normung
DOC Declaration of conformity
DOW F&EI Dow Fire and Explosion Index
EC Europese commissie / European Commission
EDTC Externe Dienst voor Technische Controle (België) / External Service
for Technical Inspection (Belgium)
EMC Electromagnetic compatibility
EN Europese norm / European Standard
EPC Engineering, Procurement, Construction
ESD Emergency Shut Downs
ETA European Technical Approval (see European Construction Products
Directives)
ETSI European Telecommunications Standards Institute
FM Factory Mutual
FMEA Failure Modes and Effect Analysis
Annex 3 :
Materials - Examples
January 9, 2008
Thomas Eun
Folks,
Please find attached photos of a pressure vessel that recently failed whilst under hydrotest during post
fabrication testing. This vessel was manufactured by a vessel vendor in China and the plate was of
Chinese mill origin. Unfortunately this is another example of serious equipment/material failures with
equipment being sourced out of the rapidly developing economies such as China, Eastern Bloc and
others. These examples are becoming almost a weekly occurrence now and are exhibiting failure modes
not seen in the mature manufacturing economies since the 1930's. Again we need to ensure vigilance in
the acceptance of manufacturers and once more I stress the need to know where the base materials are
sourced from.
Apparently this pressure vessel had reached fifty percent of the required test pressure when the shell
ruptured. A metallurgical failure report is not available however from the photographs a number of
observations could be made regarding the quality of the material and the welding.
Lesson learned
(1) All base metal requirements shall be specified in P.O Requisition per project/Industry Code
requirements.
(2) Consult specialists (i.e., Materials and Corrosion Engineers) whenever you doubt.
(3) All inspection (from base materials to final products) should be performed per the codes, specs &
standards.
(4) Especially when you selected the manufacturers in China, the above (1), (2) & (3) will be a very
important message.
1
2
3
4
5
6
7