Beruflich Dokumente
Kultur Dokumente
One of the projects handled by respondent Lirag, the Assuming for the sake of argument that an oral
Bureau of Post project, amounting to P100,000,000.00 consultancy agreement has been perfected between the
was awarded to the Marubeni-Sanritsu parties, respondent Lirag could not still claim fees on the
tandem.[8] Despite respondents repeated formal verbal project that has not been awarded to Marubeni.
demands for payment of the agreed consultancy fee, If respondents contentions were to be taken as truth, he
petitioners did not pay. In response to the first demand would be entitled to 6% consulting fee based on the
letter, petitioners promised to reply within fifteen (15) total cost of the projects obtained,[26] or on success
days, but they did not do so. basis.[27]
Pursuant to the consultancy agreement, respondent
claimed a commission of six percent (6%) of the total However, even respondent admitted that the Bureau of
contract price, or a total of P6,000,000.00, or in the Post project was not awarded to Marubeni, but to
Sanritsu.[28] Marubeni did not even join the bidding for duties, which contemplates the use of personal influence
the Bureau of Post project. and solicitation rather than an appeal to the judgment of
Respondent could not claim from Sanritsu because of the official on the merits of the object sought is contrary
the absence of any agreement between him and the to public policy.[39] Consequently, the agreement,
latter. When asked to clarify whether he has an existing assuming that the parties agreed to the consultancy, is
consultancy agreement with Sanritsu, respondent null and void as against public policy.[40] Therefore, it is
answered in the negative. unenforceable before a court of justice.[41]
Contrary to the trial courts finding that petitioners led In light of the foregoing, we rule that the preponderance
respondent to believe that they hired respondents of evidence established no consultancy agreement
services as consultant, the evidence proved between petitioners and respondent from which the
otherwise. Petitioner Shoichi One, one of the officers of latter could anchor his claim for a six percent (6%)
Marubeni Phils., testified that at the onset, Marubeni consultancy fee on a project that was not awarded to
Phils. informed respondent that it had no authority to petitioners.
commit to anything, as it all depended on the decision of
the principal headquarters in Tokyo, Japan.However, Prudential Bank vs Rapanot, GR 191636, January 16,
respondent Lirag insisted on providing assistance to 2017
Marubeni to get coveted government contracts because
Marubeni might encounter difficulties due to Facts
discrimination from the government.[32]Despite such Golden Dragon is the developer of Wack-Wack Twin
knowledge, respondent said that its alright with him as Towers Condominium, located in Mandaluyong City. On
he believes Marubeni was an old time friend so he May 9, 1995, Rapanot paid Golden Dragon the amount
wanted to work for those projects.[33] Hence, how could ofP453,329.64 as reservation fee for a 41.1050-square
petitioners be guilty of misleading respondent on the meter unit in said condominium, particularly designated
acceptance of the latters offer of consultancy service? as Unit 2308-B2,6 and covered by Condominium
Certificate of Title (CCT) No. 2383 in the name of Golden
With regard to the Court of Appeals ratiocination that Dragon.7
petitioner Tanakas response dated October 13, 1988 to
the demand letter of September 26, 1988, amounted to On September 13, 1995, the Bank extended a loan to
an implied admission of the consultancy agreement, the Golden Dragon amounting to P50,000,000.008 to be
records showed that, to the contrary, this fact utilized by the latter as additional working capital.9 To
strengthened petitioners allegation that Marubeni Phils. secure the loan, Golden Dragon executed a Mortgage
lacked the requisite authority to enter into any binding Agreement in favor of the Bank, which had the effect of
agreement. constituting a real estate mortgage over several
As explained by petitioner Shoichi One, Marubeni Phils. condominium units owned and registered under Golden
could enter into a consultancy agreement only after Dragon's name. Among the units subject of the
submitting a recommendation to the principal Mortgage Agreement was Unit 2308-B2.10 The mortgage
headquarters in Tokyo, Japan. If the office in Tokyo, was annotated on CCT No. 2383 on September 13,
Japan agrees to hire consultants, it would then give a 1995.11
power of attorney to its general manager in Manila
authorizing the latter to enter into such agreement. On May 21, 1996, Rapanot and Golden Dragon entered
into a Contract to Sell covering Unit 2308-B2. On April
In the instant case, the parties did not reach the second 23, 1997, Rapanot completed payment of the full
stage as the headquarters in Tokyo, Japan did not see it purchase price of said unit amounting to
fit to hire a consultant as they decided not to participate P1,511,098.97.12 Golden Dragon executed a Deed of
in the bidding. Hence, no consultancy agreement was Absolute Sale in favor of Rapanot of the same
perfected, whether oral or written. There was no date.13 Thereafter, Rapanot made several verbal
absolute acceptance of respondents offer of consultancy demands for the delivery of Unit 2308-B2.14
services.
Assuming arguendo that the petitioner accepted Prompted by Rapanot's verbal demands, Golden Dragon
respondents offer of consultancy services, we could not sent a letter to the Bank dated March 17, 1998,
give legal imprimatur to the agreement. The service requesting for a substitution of collateral for the purpose
rendered by respondent contemplated the exploitation of replacing Unit 2308-B2 with another unit with the
of personal influence and solicitation on a public officer. same area. However, the Bank denied Golden Dragon's
request due to the latter's unpaid accounts.15Because of
Respondent said that petitioners sought out his services this, Golden Dragon failed to comply with Rapanot's
because they needed somebody who can help them verbal demands.
penetrate and establish goodwill with the
government.[34] Petitioners found it difficult to arrange a Thereafter, Rapanot, through his counsel, sent several
meeting with Postmaster General Angelito Banayo demand letters to Golden Dragon and the Bank, formally
because of petitioners reputation of engaging in demanding the delivery of Unit 2308-B2 and its
questionable transactions.[35] Suddenly, through the corresponding CCT No. 2383, free from all liens and
intervention of respondent, the postmaster general encumbrances.16 Neither Golden Dragon nor the Bank
became accessible to petitioners. This became possible complied with Rapanot's written demands.
because of respondents close personal relationship with
the postmaster general, his trusted and long-time friend. Ruling
The Mortgage Agreement is null and void as against
Any agreement entered into because of the actual or Rapanot, and thus cannot be enforced against him.
supposed influence which the party has, engaging him to
influence executive officials in the discharge of their The Court finds the Bank's assertions indefensible.
Administration.6 Acting Secretary Domingo signed a
First of all, under Presidential Decree No. 957 (PD 957), marginal note on the letter-proposal, which read, "OK,
no mortgage on any condominium unit may be proceed!"7 Guillermo and AV Manila allegedly worked on
constituted by a developer without prior written "Joyride" on a tight schedule and submitted the finished
approval of the National Housing Authority, now product on April 4, 2010.8 "Joyride" was aired on NBN-
HLURB.57PD 957 further requires developers to notify Channel 4 on April 5, 2010.9
buyers of the loan value of their corresponding
mortgaged properties before the proceeds of the Guillermo and AV Manila further claimed that
secured loan are released. communications and meetings on the Campaign and
"Joyride" ensued between them and various government
In Far East Bank & Trust Co. v. Marquez,58 the Court agencies.10 These covered instructions from government
clarified the legal effect of a mortgage constituted in agencies, emphasis on the proprietary nature of
violation of the foregoing provision, thus: "Joyride," and discussions on the terms of reference,
deliverables, and submissions.11
The lot was mortgaged in violation of Section 18 of PD
957. Respondent, who was the buyer of the property, Among the government agencies alleged by Guillermo
was not notified of the mortgage before the release of and AV Manila to have been involved in the
the loan proceeds by petitioner. Acts executed against communications and meetings were: the National
the provisions of mandatory or prohibitory laws shall be Economic and Development Authority and National
void. Hence, the mortgage over the lot is null and void Anti-Poverty Commission,12 Former Cabinet Secretary
insofar as private respondent is concerned. Corazon K. Imperial,13 Department of Public Works and
thus, the Mortgage Agreement cannot have the effect of Highways Senior Undersecretary Manuel M.
curtailing Rapanot's right as buyer of Unit 2308-B2, Bonoan,14 the Pro Performance System-Steering
precisely because of the Bank's failure to comply with PD Committee (PPS-SC),15 and respondent Philippine
957. Information Agency.16
Moreover, contrary to the Bank's assertions, it cannot be Petitioners alleged that under the foregoing exchanges,
considered a mortgagee in good faith. The Bank failed to they, working with the Department of Public Works and
ascertain whether Golden Dragon secured HLURB's prior Highways' production team, committed to the following
written approval as required by PD 957 before it deliverables: (a) reproduction and distribution of a
accepted Golden Dragon's properties as collateral. It also revised, expanded, and more comprehensive "Joyride"
failed to ascertain whether any of the properties offered documentary, for distribution to the Department of
as collateral already had corresponding buyers at the Foreign Affairs, the Department of Transportation and
time the Mortgage Agreement was executed. Communication, Philippine consulates and embassies,
and for showing to various transport sectors, as well as
The Bank cannot harp on the fact that the Mortgage to the audience of the Independence Day rites on June
Agreement was executed before the Contract to Sell and 12, 2010 at the Quirino Grandstand in Rizal Park; 17 (b)
Deed of Absolute Sale between Rapanot and Golden production and distribution of a "Joyride" coffee table
Dragon were executed, such that no amount of book;18 (c) production of "Joyride" comics;19 (d)
verification could have revealed Rapanot's right over production of a "Joyride" infomercial entitled "Sa Totoo
Unit 2308-B2.62 The Court particularly notes that Lang!" in the form of a 45-second advertisement, which
Rapanot made his initial payment for Unit 2308-B2 as captured the essence of the full length film;20 and (e)
early as May 9, 1995, four (4) months prior to the production of a "Joyride" infomercial entitled "Sa Totoo
execution of the Mortgage Agreement. Surely, the Bank Lang-GFX", which was a representation of improved
could have easily verified such fact if it had simply government services, presented in a 45-second
requested Golden Dragon to confirm if Unit 2308-B2 advertisement.21 On April 20, 2010, petitioners
already had a buyer, given that the nature of the latter's submitted samples and storyboards of the foregoing to
business inherently involves the sale of condominium respondent Department of Public Works and Highways.
units on a commercial scale.
Petitioners further alleged that Acting Secretary
Guillermo et al vs PIA, GR 223751, March 15, 2017 Domingo informed them that the total consideration of
₱25,000,000.00 for their services and deliverable items
Facts was acceptable and approved.24 A Memorandum dated
Guillermo and AV Manila alleged that in the last few May 6, 201025 addressed to Former President Gloria
months of the Administration of Former President Gloria Macapagal-Arroyo pertaining to the "Joyride" materials
Macapagal-Arroyo (Arroyo was issued by Acting Secretary Domingo.26
Administration), then Acting Secretary of the
Department of Public Works and Highways Victor It stated that petitioners were asked to produce the
Domingo (Acting Secretary Domingo), consulted and "Joyride" materials. A Memorandum of Agreement
discussed with Guillermo and AV Manila the urgent need dated April 30, 201027 was entered into by the Road
for an advocacy campaign (Campaign).4 The purpose of Board and respondent Philippine Information Agency. In
the Campaign was to counteract the public's negative the agreement, the Road Board was to provide
perception of the performance of the outgoing Arroyo ₱l5,000,000.00 to be released to the Philippine
Administration.5 Information Agency for the "Joyride" materials, and AV
Manila was the preferred production agency.28
After meetings with Acting Secretary Domingo and
some preliminary work, Guillermo and AV Manila Thereafter, Joan Marzan, Philippine Information
formally submitted in a letter-proposal dated February Agency's representative to PPS-SC, and Executive
26, 2010 the concept of "Joyride," a documentary film Assistant of Philippine Information Agency Secretary
showcasing milestones of the Arroyo Conrado Limcauco, advised that, in light of the
foregoing agreement, a separate written contract was accounting official and auditor that funds have been
no longer necessary.29 Thus, the Philippine Information appropriated by law and such funds are available. Failure
Agency instructed Guillermo to send billings directly to to comply with any of these two requirements renders
the Philippine Information Agency.30 the contract void.
In several cases, the Court had the occasion to apply
Ruling these provisions of the Administrative Code of 1987 and
The Complaint attempts to establish a contract that the Government Auditing Code of the Philippines. In
involves expenditure of public funds. As pointed out by these cases, the Court clearly ruled that the two
respondents, contracts involving the expenditure of requirements-the existence of appropriation and the
public funds have additional requisites to be valid. attachment of the certification-are "conditions sine qua
Sections 46, 47, and 48 of Book V, Title I, Subtitle B, non for the execution of government contracts."
Chapter 8 of the Administrative Code provides for
essential requisites for the validity of contracts: In COMELEC v. Quijano-Padilla, we stated:
It is quite evident from the tenor of the language of the
SECTION 46. Appropriation Before Entering into law that the existence of appropriations and the
Contract. - (1) No contract involving the expenditure of availability of funds are indispensable pre-requisites to or
public funds shall be entered into unless there is an conditions sine qua non for the execution of government
appropriation therefor, the unexpended balance of contracts. The obvious intent is to impose such
which, free of other obligations, is sufficient to cover the conditions as a priori requisites to the validity of the
proposed expenditure; and proposed contract.
(2) Notwithstanding this provision, contracts for the The law expressly declares void a contract that fails to
procurement of supplies and materials to be carried in comply with the two requirements, namely, an
stock may be entered into under regulations of the appropriation law funding the contract and a
Commission provided that when issued, the supplies and certification of appropriation and fund availability. The
materials shall be charged to the proper appropriations clear purpose of these requirements is to insure that
account. government contracts are never signed unless supported
by the corresponding appropriation law and fund
SECTION 47. Certificate Showing Appropriation to Meet availability.
Contract. - Except in the case of a contract for personal
service, for supplies for current consumption or to be The three contracts between PNR and Kanlaon do not
carried in stock not exceeding the estimated comply with the requirement of a certification of
consumption for three (3) months, or banking appropriation and fund availability.1âwphi1 Even if a
transactions of government-owned or controlled banks, certification of appropriation is not applicable to PNR if
no contract involving the expenditure of public funds by the funds used are internally generated, still a certificate
any government agency shall be entered into or of fund availability is required. Thus, the three contracts
authorized unless the proper accounting official of the between PNR and Kanlaon are void for violation of
agency concerned shall have certified to the officer Sections 46, 4 7, and 48, Chapter 8, Subtitle B, Title I,
entering into the obligation that funds have been duly Book V of the Administrative Code of 1987, as well as
appropriated for the purpose and that the amount Sections 85, 86, and 87 of the Government Auditing
necessary to cover the proposed contract for the current Code of the Philippines.
calendar year is available for expenditure on account
thereof, subject to verification by the auditor concerned. However, Kanlaon is not left without recourse. The law
The certificate signed by the proper accounting official itself affords it the remedy. Section 48 of the
and the auditor who verified it, shall be attached to and Administrative Code of 1987 provides that "the officer or
become an integral part of the proposed contract, and officers entering into the contract shall be liable to the
the sum so certified shall not thereafter be available for Government or other contracting party for any
expenditure for any other purpose until the obligation of consequent damage to the same extent as if the
the government agency concerned under the contract is transaction had been wholly between private parties."
fully extinguished. Kanlaon could go after the officers who signed the
contract and hold them personally liable.
SECTION 48. Void Contract and Liability of Officer. - Any
contract entered into contrary to the requirements of The Complaint, however, completely ignored the
the two (2) immediately preceding sections shall be void, foregoing requisites for the validity of contracts
and the officer or officers entering into the contract shall involving expenditure of public funds. Thus, the Regional
be liable to the Government or other contracting party Trial Court could not order the enforcement of the
for any consequent damage to the same extent as if the alleged contract on the basis of the Complaint, and the
transaction had been wholly between private parties. Complaint was properly dismissed for failure to state a
cause of action.
In Philippine National Railways v. Kanlaon Construction
Enterprises Co., lnc.,82 this Court has held that contracts Finally, petitioners' invocation of the principle
that do not comply with the foregoing requirements are of quantum meruit could not save the Complaint from
void: dismissal. A careful reading reveals that the Complaint
does not mention the principle of quantum meruit, or any
Thus, the Administrative Code of 1987 expressly facts showing that the public has derived any benefit
prohibits the entering into contracts involving the from the "Joyride" project. Even assuming that basis
expenditure of public funds unless two prior exists to reimburse petitioners under the principle
requirements are satisfied. First, there of quantum meruit, no factual basis for its application
must be an appropriation law authorizing the was laid down in the Complaint. Its belated invocation
expenditure required in the contract. Second, there must does not retroactively make the Complaint sufficient.
be attached to the contract a certification by the proper
However, as in Philippine National Railways, petitioners agreed to sell the property under the second deed for
are not without recourse. P2,000,000.00, provided that payment be immediately
effected. Severino said that he wanted to use the money
Under the Administrative Code, officers who enter into to invest in another property located in Alabang and told
contracts contrary to Sections 46 and 47 of Book V, Title Henry that if payment was made at a later date, the price
I, Subtitle B, Chapter 8 of the Administrative Code are would be the current market value at the time of
liable to the government or to the other contracting payment.
party for damages:
Henry then gave Severino P300,000.00 as "earnest
SECTION 48. Void Contract and Liability of Officer. - Any money", purportedly with the understanding that the
contract entered into contrary to the requirements of former was to pay the balance within 60 days.
the two (2) immediately preceding sections shall be void, Otherwise, said amount would be forfeited in favor of
and the officer or officers entering into the contract shall Severino. 8 The latter also maintained that he signed the
be liable to the Government or other contracting party second deed only for the purpose of facilitating Henry’s
for any consequent damage to the same extent as if the acquisition of a bank loan to finance payment of the
transaction had been wholly between private parties. balance of the purchase price 9 and added that
execution of the second deed was necessary to enable
Thus, assuming petitioners are able to prove a contract Henry to file a court action for ejectment of the tenant.
was entered into, they may go after the officers who 10
entered into said contract and hold them personally
liable. After execution of the second deed, Henry filed a loan
application with the Philippine American Life Insurance
Penalosa vs Santos , GR 133749, August 23, 2001 Company (Philam Life) for the amount of P2,500,000.00.
11 According to Henry, he had agreed with Severino
Facts during the signing of the second deed, that the balance
Respondents Severino C. Santos (deceased) and Adela of P1,700,000.00 would be paid by means of a loan, with
Mendez Santos are registered owners of a residential the property itself given as collateral. 12
house and lot located at No. 113 Scout Rallos Street,
Quezon City under TCT No. PT-23458 (54434). 1 In 1988, Meanwhile, on the strength of the first deed and as new
Severino and Adela decided to sell their property and for "owner" of the property, Henry wrote a letter 13 dated
this purpose, negotiated with petitioner Hernando (or August 8, 1988 to the lessee, Eleuterio Perez,
Henry) Peñalosa. The property was then occupied by a demanding that the latter vacate the premises within 10
lessee, Eleuterio Perez, who was given preference to buy days. Failing in this effort, Henry brought a complaint for
it under the same terms offered by the buyer. 2 Perez ejectment 14 against Perez before the Office of the
proposed less favorable terms 3 and expectedly, Barangay Captain.
Severino rejected his offer.
On September 1, 1988, a Certification To File Action 15
On August 1, 1988, petitioner Henry Peñalosa and was issued by the barangay lupon. This led to the
respondent Severino Santos attempted to enter into an subsequent filing of a Civil Case
agreement whereby the latter, for a consideration of
P1,800.000.00, would sell to the former the property Issue: whether or not the second deed is valid and
subject of the instant case. The deed of absolute sale 4 constitutes evidence of the final agreement between the
(first deed) evidencing this transaction was signed by parties regarding the sale transaction entered into by
Henry but not by Severino, because according to the them.
latter, Henry "took time to decide" on the matter. 5
Ruling
On August 15, 1988, Henry signed a document 6 stating The basic characteristic of an absolutely simulated or
that the first deed was executed between him and fictitious contract is that the apparent contract is not
Severino, for the sole purpose of helping the latter eject really desired or intended to produce legal effects or
Perez, the occupant of the property. Henry alter the juridical situation of the parties in any way. 30
acknowledged in said document that although Severino However, in this case, the parties already undertook
had agreed to sell the property to him, he had not paid certain acts which were directed towards fulfillment of
the consideration stated in the first deed.chanrobles their respective covenants under the second deed,
virtual law library indicating that they intended to give effect to their
agreement.chanrob1es virtua1 1aw 1ibrary
Thereafter, Henry and Severino executed another deed
of absolute sale 7 (second deed) for a higher In particular, as early as August 8, 1988, after execution
consideration of P2,000,000.00. Although the second of the first deed, Severino authorized petitioner to bring
deed was originally dated "August 1988", superimposed an action for ejectment against the overstaying tenant
upon the same was the date "September 12, 1988." This and allowed petitioner to pursue the ejectment case to
second deed was signed by both parties and duly its final conclusion, presumably to secure possession of
notarized. It states that Severino sells and transfers the the property in petitioner’s favor. Petitioner also applied
house and lot to Henry, who had paid the full price of for a loan, which was approved by Philam Life, to
P2,000,000.00 therefor. complete payment of the stipulated price. After making
extensive repairs with the knowledge of Severino,
Severino explained that his initial asking price for the petitioner moved into the premises and actually
property was only P1,800,000.00 as shown in the first occupied the same for three years before this action was
deed. But he later asked for a higher price because Henry brought. Moreover, simultaneous with the execution of
could not give the money as soon as expected. However, the second deed, petitioner gave Severino P300,000.00
Severino claimed that he made it clear to Henry that he in earnest money, which under Article 1482 31 of the
New Civil Code, is part of the purchase price and proof of that form, once the contract has been perfected. 35 This
perfection of the contract. is consistent with the basic principle that contracts are
obligatory in whatever form they may have been entered
What may have led the lower courts into incorrectly into, provided all essential requisites are present. 36
believing that the second deed was simulated is Exhibit
D — a document in which petitioner declared that the Spouses Abella vs Spouses Abella, GR 195166, July 8,
deed was executed only for the purpose of helping 2015
Severino eject the tenant. However, a perusal of this
document reveals that it made reference to the first Facts
deed and not the second deed, which was executed only petitioners alleged that respondents obtained a loan
after Exhibit D. So that while the first deed was qualified from them in the amount of P500,000.00. The loan was
by stipulations contained in Exhibit D, the same cannot evidenced by an acknowledgment receipt dated March
be said of the second deed which was signed by both 22, 1999 and was payable within one (1) year. Petitioners
parties.chanrob1es virtua1 1aw 1ibrary added that respondents were able to pay a total of
P200,000.00—P100,000.00 paid on two separate
Further, the fact that Severino executed the two deeds occasions—leaving an unpaid balance of
in question, primarily so that petitioner could eject the P300,000.00.7redarclaw
tenant and enter into a loan/mortgage contract with
Philam Life, is to our mind, a strong indication that he In their Answer8 (with counterclaim and motion to
intended to transfer ownership of the property to dismiss), respondents alleged that the amount involved
petitioner. For why else would he authorize the latter to did not pertain to a loan they obtained from petitioners
sue the tenant for ejectment under a claim of ownership, but was part of the capital for a joint venture involving
if he truly did not intend to sell the property to petitioner the lending of money.9redarclaw
in the first place? Needless to state, it does not make
sense for Severino to allow petitioner to pursue the Specifically, respondents claimed that they were
ejectment case, in petitioner’s own name, with approached by petitioners, who proposed that if
petitioner arguing that he had bought the property from respondents were to "undertake the management of
Severino and thus entitled to possession thereof, if whatever money [petitioners] would give them,
petitioner did not have any right to the [petitioners] would get 2.5% a month with a 2.5% service
property.chanrob1es virtua1 1aw 1ibrary fee to [respondents]."10 The 2.5% that each party would
be receiving represented their sharing of the 5% interest
Also worth noting is the fact that in the case filed by that the joint venture was supposedly going to charge
Severino’s tenant against Severino and petitioner in against its debtors. Respondents further alleged that the
1989, assailing the validity of the sale made to one year averred by petitioners was not a deadline for
petitioner, Severino explicitly asserted in his sworn payment but the term within which they were to return
answer to the complaint that the sale was a legitimate the money placed by petitioners should the joint venture
transaction. He further alleged that the ejectment case prove to be not lucrative. Moreover, they claimed that
filed by petitioner against the tenant was a legitimate the entire amount of P500,000.00 was disposed of in
action by an owner against one who refuses to turn over accordance with their agreed terms and conditions and
possession of his property. 32 that petitioners terminated the joint venture, prompting
them to collect from the joint venture's borrowers. They
Our attention is also drawn to the fact that the were, however, able to collect only to the extent of
genuineness and due execution of the second deed was P200,000.00; hence, the P300,000.00 balance remained
not denied by Severino. Except to allege that he was not unpaid.11redarclaw
physically present when the second deed was notarized
before the notary public, Severino did not assail the truth In the Decision12 dated December 28, 2005, the Regional
of its contents nor deny that he ever signed the same. As Trial Court ruled in favor of petitioners.
a matter of fact, he even admitted that he affixed his
signature on the second deed to help petitioner acquire a Ruling
loan. This can only signify that he consented to the Thus, it remains that where interest was stipulated in
manner proposed by petitioner for payment of the writing by the debtor and creditor in a simple loan or
balance and that he accepted the stipulated price of mutuum, but no exact interest rate was mentioned, the
P2,000,000.00 as consideration for the sale. legal rate of interest shall apply. At present, this is 6%
per annum, subject to Nacar's qualification on
Since the genuineness and due execution of the second prospective application.
deed was not seriously put in issue, it should be upheld
as the best evidence of the intent and true agreement of Applying this, the loan obtained by respondents from
the parties. Oral testimony, depending as it does petitioners is deemed subjected to conventional interest at
exclusively on human memory, is not as reliable as the rate of 12% per annum, the legal rate of interest at
written or documentary evidence. 33 the time the parties executed their agreement.
It should be emphasized that the non-appearance of the Moreover, should conventional interest still be due as of
parties before the notary public who notarized the deed July 1, 2013, the rate of 12% per annum shall persist as the
does not necessarily nullify nor render the parties’ rate of conventional interest.
transaction void ab initio. We have held previously that
the provision of Article 1358 34 of the New Civil Code on This is so because interest in this respect is used as a
the necessity of a public document is only for surrogate for the parties' intent, as expressed as of the
convenience, not for validity or enforceability. Failure to time of the execution of their contract. In this sense, the
follow the proper form does not invalidate a contract. legal rate of interest is an affirmation of the contracting
Where a contract is not in the form prescribed by law, parties' intent; that is, by their contract's silence on a
the parties can merely compel each other to observe specific rate, the then prevailing legal rate of interest
shall be the cost of borrowing money. This rate, which by unconscionable. As emphasized in Castro v. Tan,50 the
their contract the parties have settled on, is deemed to willingness of the parties to enter into a relation
persist regardless of shifts in the legal rate of interest. involving an unconscionable interest rate is
Stated otherwise, the legal rate of interest, when applied inconsequential to the validity of the stipulated rate:
as conventional interest, shall always be the legal rate at The imposition of an unconscionable rate of interest on a
the time the agreement was executed and shall not be money debt, even if knowingly and voluntarily assumed,
susceptible to shifts in rate. is immoral and unjust. It is tantamount to a repugnant
spoliation and an iniquitous deprivation of property,
Petitioners, however, insist on conventional interest at repulsive to the common sense of man. It has no support
the rate of 2.5% per month or 30% per annum. They in law, in principles of justice, or in the human conscience
argue that the acknowledgment receipt fails to show the nor is there any reason whatsoever which may justify
complete and accurate intention of the contracting such imposition as righteous and as one that may be
parties. They rely on Article 1371 of the Civil Code, which sustained within the sphere of public or private morals.51
provides that the contemporaneous and subsequent acts The imposition of an unconscionable interest rate is void
of the contracting parties shall be considered should ab initio for being "contrary to morals, and the
there be a need to ascertain their intent.44 In addition, law."52redarclaw
they claim that this case falls under the exceptions to the
Parol Evidence Rule, as spelled out in Rule 130, Section 9 In determining whether the rate of interest is
of the Revised Rules on Evidence.45redarclaw unconscionable, the mechanical application of pre-
established floors would be wanting. The lowest rates
It is a basic precept in legal interpretation and that have previously been considered unconscionable
construction that a rule or provision that treats a subject need not be an impenetrable minimum. What is more
with specificity prevails over a rule or provision that crucial is a consideration of the parties' contexts.
treats a subject in general terms.46redarclaw Moreover, interest rates must be appreciated in light of
the fundamental nature of interest as compensation to
The rule spelled out in Security Bank and Spouses the creditor for money lent to another, which he or she
Toring is anchored on Article 1956 of the Civil Code and could otherwise have used for his or her own purposes at
specifically governs simple loans or mutuum. Mutuum is the time it was lent. It is not the default vehicle for
a type of nominate contract that is specifically predatory gain. As such, interest need only be
recognized by the Civil Code and for which the Civil Code reasonable. It ought not be a supine mechanism for the
provides a specific set of governing rules: Articles 1953 to creditor's unjust enrichment at the expense of another.
1961. In contrast, Article 11371 is among the Civil Code
provisions generally dealing with contracts. As this case Petitioners here insist upon the imposition of 2.5%
particularly involves a simple loan, the specific rule monthly or 30% annual interest. Compounded at this
spelled out in Security Bank and Spouses Toring finds rate, respondents' obligation would have more than
preferential application as against Article 1371. doubled—increased to 219.7% of the principal—by the
end of the third year after which the loan was contracted
Contrary to petitioners' assertions, there is no room for if the entire principal remained unpaid. By the end of the
entertaining extraneous (or parol) evidence. In Spouses ninth year, it would have multiplied more than tenfold
Bonifacio and Lucia Paras v. Kimwa Construction and (or increased to 1,060.45%). In 2015, this would have
Development Corporation,47 we spelled out the requisites multiplied by more than 66 times (or increased to
for the admission of parol evidence: 6,654.17%). Thus, from an initial loan of only
In sum, two (2) things must be established for parol P500,000.00, respondents would be obliged to pay more
evidence to be admitted: first, that the existence of any than P33 million. This is grossly unfair, especially since up
of the four (4) exceptions has been put in issue in a to the fourth year from when the loan was obtained,
party's pleading or has not been objected to by the respondents had been assiduously delivering payment.
adverse party; and second, that the parol evidence This reduces their best efforts to satisfy their obligation
sought to be presented serves to form the basis of the into a protracted servicing of a rapacious loan.
conclusion proposed by the presenting party.48
The issue of admitting parol evidence is a matter that is The legal rate of interest is the presumptive reasonable
proper to the trial, not the appellate, stage of a case. compensation for borrowed money. While parties are
Petitioners raised the issue of applying the exceptions to free to deviate from this, any deviation must be
the Parol Evidence Rule only in the Reply they filed reasonable and fair. Any deviation that is far-removed is
before this court. This is the last pleading that either of suspect. Thus, in cases where stipulated interest is more
the parties has filed in the entire string of proceedings than twice the prevailing legal rate of interest, it is for
culminating in this Decision. It is, therefore, too late for the creditor to prove that this rate is required by
petitioners to harp on this rule. In any case, what is at prevailing market conditions. Here, petitioners have
issue is not admission of evidence per se, but the articulated no such justification.
appreciation given to the evidence adduced by the
parties. In the Petition they filed before this court, In sum, Article 1956 of the Civil Code, read in light of
petitioners themselves acknowledged that checks established jurisprudence, prevents the application of
supposedly attesting to payment of monthly interest at any interest rate other than that specifically provided for
the rate of 2.5% were admitted by the trial court (and by the parties in their loan document or, in lieu of it, the
marked as Exhibits "2," "3," "4," "5," "6," "7," and legal rate. Here, as the contracting parties failed to make
"8").49 What petitioners have an issue with is not the a specific stipulation, the legal rate must apply.
admission of these pieces of evidence but how these Moreover, the rate that petitioners adverted to is
have not been appreciated in a manner consistent with unconscionable. The conventional interest due on the
the conclusions they advance. principal amount loaned by respondents from
Even if it can be shown that the parties have agreed to petitioners is held to be 12% per annum.
monthly interest at the rate of 2.5%, this is
Spouses Mallari vs Prudential Bank, GR 197861, June interest rates were 7% and 5% a month, which are
5, 2013 equivalent to 84% and 60% p.a., respectively, we had
reduced the same to 1% per month or 12% p.a. We said
Facts that we need not unsettle the principle we had affirmed
On December 11, 1984, petitioner Florentino T. Mallari in a plethora of cases that stipulated interest rates of 3%
(Florentino) obtained from respondent Prudential Bank- per month and higher are excessive, unconscionable and
Tarlac Branch (respondent bank), a loan in the amount of exorbitant, hence, the stipulation was void for being
₱300,000.00 as evidenced by Promissory Note (PN) No. contrary to morals.24
BD 84-055.3 Under the promissory note, the loan was
subject to an interest rate of 21% per annum (p.a.), In this case, the interest rate agreed upon by the parties
attorney's fees equivalent to 15% of the total amount was only 23% p.a., or less than 2% per month, which are
due but not less than ₱200.00 and, in case of default, a much lower than those interest rates agreed upon by the
penalty and collection charges of 12% p.a. of the total parties in the above-mentioned cases. Thus, there is no
amount due. The loan had a maturity date of January 10, similarity of factual milieu for the application of those
1985, but was renewed up to February 17, 1985. cases.
Petitioner Florentino executed a Deed of
Assignment4 wherein he authorized the respondent We do not consider the interest rate of 23% p.a. agreed
bank to pay his loan with his time deposit with the latter upon by petitioners and respondent bank to be
in the amount of ₱300,000.00. unconscionable.
In Villanueva v. Court of Appeals,25 where the issue
On December 22, 1989, petitioners spouses Florentino raised was whether the 24% p.a. stipulated interest rate
and Aurea Mallari (petitioners) obtained again from is unreasonable under the circumstances, we answered
respondent bank another loan of ₱1.7 million as in the negative and held:
evidenced by PN No. BDS 606-895 with a maturity date
of March 22, 1990. They stipulated that the loan will bear In Spouses Zacarias Bacolor and Catherine Bacolor v.
23% interest p.a., attorney's fees equivalent to 15% p.a. Banco Filipino Savings and Mortgage Bank, Dagupan
of the total amount due, but not less than ₱200.00, and City Branch, this Court held that the interest rate of 24%
penalty and collection charges of 12% p.a. Petitioners per annum on a loan of ₱244,000.00, agreed upon by the
executed a Deed of Real Estate Mortgage6 in favor of parties, may not be considered as unconscionable and
respondent bank covering petitioners' property under excessive. As such, the Court ruled that the borrowers
Transfer Certificate of Title (TCT) No. T-215175 of the cannot renege on their obligation to comply with what is
Register of Deeds of Tarlac to answer for the said loan. incumbent upon them under the contract of loan as the
said contract is the law between the parties and they are
Petitioners failed to settle their loan obligations with bound by its stipulations.
respondent bank, thus, the latter, through its lawyer,
sent a demand letter to the former for them to pay their Also, in Garcia v. Court of Appeals, this Court sustained
obligations, which when computed up to January 31, the agreement of the parties to a 24% per annum
1992, amounted to ₱571,218.54 for PN No. BD 84-055 interest on an ₱8,649,250.00 loan finding the same to be
and ₱2,991,294.82 for PN No. BDS 606-89. reasonable and clearly evidenced by the amended credit
line agreement entered into by the parties as well as two
On February 25, 1992, respondent bank filed with the promissory notes executed by the borrower in favor of
Regional Trial Court (RTC) of Tarlac, a petition for the the lender.
extrajudicial foreclosure of petitioners' mortgaged
property for the satisfaction of the latter's obligation of Based on the above jurisprudence, the Court finds that
₱1,700,000.00 secured by such mortgage, thus, the the 24% per annum interest rate, provided for in the
auction sale was set by the Provincial Sheriff on April 23, subject mortgage contracts for a loan of ₱225,000.00,
1992.7 may not be considered unconscionable. Moreover,
considering that the mortgage agreement was freely
On April 10, 1992, respondent bank's Assistant Manager entered into by both parties, the same is the law
sent petitioners two (2) separate Statements of Account between them and they are bound to comply with the
as of April 23, 1992, i.e., the loan of ₱300,000.00 was provisions contained therein.26
increased to ₱594,043.54, while the ₱1,700,000.00 loan Clearly, jurisprudence establish that the 24% p.a.
was already ₱3,171,836.18. stipulated interest rate was not considered
On April 20, 1992, petitioners filed a complaint for unconscionable, thus, the 23% p.a. interest rate imposed
annulment of mortgage, deeds, injunction, preliminary on petitioners' loan in this case can by no means be
injunction, temporary restraining order and damages considered excessive or unconscionable.
Delos Santos et al vs Abejon, GR 215820, March 20, On the other hand, respondents, as Teresita's
2017 successors-in-interest, are entitled to the refund of the
additional PS0,000.00 consideration she paid for such
Facts sale. However, it should be clarified that the liability for
The complaint alleged that Erlinda and her late husband the said amount will not fall on all petitioners, but only
Pedro Delos Santos (Pedro) borrowed the amount of on Erlinda, as she was the only one among the
₱l00,000.00 from the former's sister, Teresita, as petitioners who was involved in the said sale. Pursuant
evidenced by a Promissory Note dated April 8, 1998. As to Nacar v. Gallery Frames,29 the amount of PS0,000.00
security for the loan, Erlinda and Pedro mortgaged their shall be subjected to legal interest of six percent (6%) per
property consisting of 43.50 square meters situated at annum from the finality of this Decision until fully paid.
2986 Gen. Del Pilar Street, Bangkal, Makati City covered
by Transfer Certificate of Title (TCT) No. 131753 (subject In this case, it bears stressing that the execution of the
land) which mortgage was annotated on the title. Deed of Sale involving the subject land was done in
1992. However, and as keenly pointed out by Justice
After Pedro died, Erlinda ended up being unable to pay Alfredo Benjamin S. Caguioa during the deliberations of
the loan, and as such, agreed to sell the subject land to this case, Teresita was apprised of Pedro's death as early
Teresita for ₱l50,000.00, or for the amount of the loan as 1990 when she went on a vacation in the
plus an additional ₱50,000.00. On July 8, 1992, they Philippines.35 As such, she knew all along that the
executed a Deed of Sale and a Release of Mortgage, and aforesaid Deed of Sale - which contained a signature
purportedly belonging to Pedro, who died in 1989, or Abuse of this privilege by the grantees thereof cannot be
three (3) years prior to its execution - was void and would countenanced. The "kabit system" has been Identified as
not have operated to transfer any rights over the subject one of the root causes of the prevalence of graft and
land to her name. Despite such awareness of the defect corruption in the government transportation offices. In
in their title to the subject land, respondents still the words of Chief Justice Makalintal, 1 "this is a
proceeded in constructing a three (3)-storey building pernicious system that cannot be too severely
thereon. Indubitably, they should be deemed as builders condemned. It constitutes an imposition upon the goo
in bad faith. faith of the government.
Lita Enterprises vs IAC, GR L-64693, April 27, 1984 Although not outrightly penalized as a criminal offense,
the "kabit system" is invariably recognized as being
Facts contrary to public policy and, therefore, void and
The spouses Nicasio M. Ocampo and Francisca Garcia, inexistent under Article 1409 of the Civil Code, It is a
herein private respondents, purchased in installment fundamental principle that the court will not aid either
from the Delta Motor Sales Corporation five (5) Toyota party to enforce an illegal contract, but will leave them
Corona Standard cars to be used as taxicabs. Since they both where it finds them. Upon this premise, it was
had no franchise to operate taxicabs, they contracted flagrant error on the part of both the trial and appellate
with petitioner Lita Enterprises, Inc., through its courts to have accorded the parties relief from their
representative, Manuel Concordia, for the use of the predicament. Article 1412 of the Civil Code denies them
latter's certificate of public convenience in consideration such aid. It provides:
of an initial payment of P1,000.00 and a monthly rental
of P200.00 per taxicab unit. ART. 1412. if the act in which the unlawful or forbidden
cause consists does not constitute a criminal offense, the
To effectuate Id agreement, the aforesaid cars were following rules shall be observed;
registered in the name of petitioner Lita Enterprises, Inc, (1) when the fault, is on the part of both contracting
Possession, however, remained with tile spouses parties, neither may recover what he has given by virtue
Ocampo who operated and maintained the same under of the contract, or demand the performance of the
the name Acme Taxi, petitioner's trade name. other's undertaking.
About a year later, on March 18, 1967, one of said
taxicabs driven by their employee, Emeterio Martin, The defect of inexistence of a contract is permanent and
collided with a motorcycle whose driver, one Florante incurable, and cannot be cured by ratification or by
Galvez, died from the head injuries sustained therefrom. prescription. As this Court said in Eugenio v.
Perdido, 2 "the mere lapse of time cannot give efficacy to
A criminal case was eventually filed against the driver contracts that are null void."
Emeterio Martin, while a civil case for damages was
instituted by Rosita Sebastian Vda. de Galvez, heir of the The principle of in pari delicto is well known not only in
victim, against Lita Enterprises, Inc., as registered owner this jurisdiction but also in the United States where
of the taxicab in the latter case, Civil Case No. 72067 of common law prevails. Under American jurisdiction, the
the Court of First Instance of Manila, petitioner Lita doctrine is stated thus: "The proposition is universal that
Enterprises, Inc. was adjudged liable for damages in the no action arises, in equity or at law, from an illegal
amount of P25,000.00 and P7,000.00 for attorney's fees. contract; no suit can be maintained for its specific
performance, or to recover the property agreed to be
This decision having become final, a writ of execution sold or delivered, or damages for its property agreed to
was issued. One of the vehicles of respondent spouses be sold or delivered, or damages for its violation. The
with Engine No. 2R-914472 was levied upon and sold at rule has sometimes been laid down as though it was
public auction for 12,150.00 to one Sonnie Cortez, the equally universal, that where the parties are in pari
highest bidder. Another car with Engine No. 2R-915036 delicto, no affirmative relief of any kind will be given to
was likewise levied upon and sold at public auction for one against the other." 3 Although certain exceptions to
P8,000.00 to a certain Mr. Lopez. the rule are provided by law, We see no cogent reason
why the full force of the rule should not be applied in the
Thereafter, in March 1973, respondent Nicasio Ocampo instant case.
decided to register his taxicabs in his name. He
requested the manager of petitioner Lita Enterprises, Jose vs Chelda Enterprises, GR L-25704, April 24, 1968
Inc. to turn over the registration papers to him, but the
latter allegedly refused. Hence, he and his wife filed a Facts
complaint against Lita Enterprises, Inc., Rosita Sebastian Plaintiff corporation filed suit in the Court of First
Vda. de Galvez, Visayan Surety & Insurance Co. and the Instance of Manila on May 29, 1964 against the
Sheriff of Manila for reconveyance of motor vehicles partnership Chelda Enterprises and David Syjueco, its
with damages, docketed as Civil Case No. 90988 of the capitalist partner, for recovery of alleged unpaid loans in
Court of First Instance of Manila. the total amount of P20,880.00, with legal interest from
the filing of the complaint, plus attorney’s fees of
Ruling P5,000.00. Alleging that post dated checks issued by
Unquestionably, the parties herein operated under an defendants to pay said account were dishonored, that
arrangement, comonly known as the "kabit system", defendants’ industrial partner, Chellaram I. Mohinani,
whereby a person who has been granted a certificate of had left the country, and that defendants have removed
convenience allows another person who owns motors or disposed of their property, or are about to do so, with
vehicles to operate under such franchise for a fee. A intent to defraud their creditors, preliminary attachment
certificate of public convenience is a special privilege was also sought.
conferred by the government .
Answering, defendants averred that they obtained four
loans from plaintiff in the total amount of P26,500.00, of provide for the recovery of the interest paid in excess of
which P5,620.00 had been paid, leaving a balance of that allowed by law, which the Usury law already
P20,880.00; that plaintiff charged and deducted from provided for, but to add that the same can be recovered
the loan usurious interest thereon, at rates of 2% and "with interest thereon from the date of payment."cralaw
2.5% per month, and, consequently, plaintiff has no virtua1aw library
cause of action against defendants and should not be
permitted to recover under the law. A counterclaim for The foregoing interpretation is reached with the
P2,000.00 attorney’s fees was interposed. philosophy of usury legislation in mind; to discourage
stipulations on usurious interest, said stipulations are
Ruling treated as wholly void, so that the loan becomes one
Article 1411 of the New Civil Code is not new; it is the without stipulation as to payment of interest. It should
same as Article 1305 of the Old Civil Code. Therefore, not, however, be interpreted to mean forfeiture even of
said provision is no warrant for departing from previous the principal, for this would unjustly enrich the borrower
interpretation that, as provided in the Usury Law (Act at the expense of the lender. Furthermore, penal
No. 2655, as amended), a loan with usurious interest is sanctions are available against a usurious lender, as a
not totally void but void only as to the interest. further deterrence to usury.
True, as stated in Article 1411 of the New Civil Code, the The principal debt remaining without stipulation for
rule of pari delicto applies where a contract’s nullity payment of interest can thus be recovered by judicial
proceeds from illegality of the cause or object of said action. And in case of such demand, and the debtor
contract. incurs in delay, the debt earns interest from the date of
the demand (in this case from the filing of the
However, appellants fail to consider that a contract of complaint). Such interest is not due to stipulation, for
loan with usurious interest consists of principal and there was none, the same being void. Rather, it is due to
accessory stipulations; the principal one is to pay the the general provision of law that in obligations to pay
debt; the accessory stipulation is to pay interest thereon. money, where the debtor incurs in delay, he has to pay
2 interest by way of damages (Art. 2209, Civil Code). The
court a quo therefore, did not err in ordering defendants
And said two stipulations are divisible in the sense that to pay the principal debt with interest thereon at the
the former can still stand without the latter. Article 1273, legal rate, from the date of filing of the complaint.
Civil Code, attests to this: "The renunciation of the
principal debt shall extinguish the accessory obligations; Spouses De Guzman vs CA, GR 185757, March 2, 2016
but the waiver of the latter shall leave the former in
force."cralaw virtua1aw library Facts
The property subject of this case (property) is a 480-
The question therefore to resolve is whether the illegal square meter lot that formed part of Lot No. 532 located
terms as to payment of interest likewise renders a nullity at North Poblacion, Medina, Misamis Oriental. Lot No.
the legal terms as to payments of the principal debt. 532, which has a total area of 25,178 square meters, was
Article 1420 of the New Civil Code provides in this acquired by Lamberto Bajao's (respondent) parent,
regard: "In case of a divisible contract, if the illegal terms Leoncio Bajao,6 through Free Patent No. 4000877 issued
can be separated from the legal ones, the latter may be on May 28, 1968.8
enforced."cralaw virtua1aw library
Petitioners acquired the property in two transactions. On
In simple loan with stipulation of usurious interest, the May 24, 1969, Spouses Bajao sold 200 square meters of
prestation of the debtor to pay the principal debt, which Lot No. 532 to them for P1,000.9 On June 18, 1970,
is the cause of the contract (Article 1350, Civil Code), is Spouses Bajao sold another 280 square meters of Lot
not illegal. The illegality lies only as to the prestation to No. 532 to petitioners for P1,400.10 Both transactions
pay the stipulated interest; hence, being separable, the were evidenced by separate Deeds of Absolute
latter only should be deemed void, since it is the only Sale.11 Spouses Bajao allegedly promised to segregate
one that is illegal. the property from the remaining area of Lot No.
53212 and to deliver a separate title to petitioners
Neither is there a conflict between the New Civil Code covering it.13 However, because the promise was not
and the Usury Law. Under the latter, in Sec. 6, any forthcoming, petitioner Lydia S. de Guzman executed an
person who for a loan shall have paid a higher rate or Affidavit of Adverse Claim14 on April 21, 1980 covering
greater sum or value than is allowed in said law, may the property. This was annotated on the title covering
recover the whole interest paid. The New Civil Code, in Lot No. 532, Original Certificate of Title (OCT) No. P-
Article 1413 states: "Interest paid in excess of the interest 6903, on April 25, 1980.15
allowed by the usury laws may be recovered by the
debtor, with interest thereon from the date of payment." On May 29, 1980, petitioners initiated the segregation of
Article 1413, in speaking of "interest paid in excess of the the property from Lot No. 532 through a survey.16 As a
interest allowed by the usury laws" means the whole result of the survey, petitioners acquired Lot 2-A, Psd-
usurious interest; that is, in a loan of P1,000, with 10-002692.17 They allegedly acquired possession over
interest of 20% per annum or P200 for one year, if the the land immediately, fenced the area, introduced
borrower pays said P200, the whole P200 is the usurious improvements, and planted it with fruit-bearing trees.18
interest, not just that part thereof in excess of the
interest allowed by law. It is in this case that the law does On September 26, 1980,19 or after the death of Leoncio
not allow division. The whole stipulation as to interest is Bajao on February 1, 1972,20 respondent and Anastacia
void, since payment of said interest is the cause or object Bajao executed an Extrajudicial Settlement Among
and said interest is illegal. The only change effected, Heirs21 (Extrajudicial Settlement), which subdivided Lot
therefore, by Article 1413, New Civil Code, is not to No. 532 into three parts.22 The property was included in
Lot No. 532-C, which was adjudicated in favor of amended. We applied the rule that upon annulment of
respondent.23 The Extrajudicial Settlement was the sale, the purchaser's claim is reduced to the purchase
registered on December 10, 1980.24 price and its interest.
On December 16, 1980, respondent caused the Olea vs CA, GR 109696, August 14, 1995
cancellation of petitioners' annotated adverse claim over
the property and later obtained Transfer Certificate of Facts
Title (TCT) No. T-7133 on February 13 and October 2, On 27 January 1947 spouses Filoteo Pacardo and Severa
1981.25 Petitioners thereafter requested respondent to de Pacardo executed a deed of Sale Con Pacto de Retro
deliver TCT No. T-7133 so they could present it to the over Lot No. 767 of the Passi Cadastre covered by
Register of Deeds, together with the two Deeds of Transfer Certificate of Title No. 26424 in their name for a
Absolute Sale, for proper annotation.26Respondent, consideration of P950.00 in favor of Maura Palabrica,
however, refused to heed their request.27cralawred predecessor in interest of petitioner, subject to the
condition that —
Thus, on January 21, 2000, petitioners filed a Complaint
for Reconveyance with Writ of Preliminary Mandatory . . . if we, the said spouses, Filoteo Pacardo and Severa
Injunction and Damages. de Pacardo, our heirs, assigns, successors-in-interest,
executors and administrators shall and will truly
Ruling repurchase the above-described parcel of land from the
Under Section 124 of the Public Land Act, any said Maura Palabrica, her heirs, assigns, successors-in-
acquisition, conveyance, alienation, transfer, or other interest after THREE YEARS counting from the date of
contract made or executed in violation of Sections 118 to the execution of this instrument, to wit, on January 27,
123 of the Public Land Act shall be unlawful and null and 1950 in cash payment in the sum of Five Hundred Pesos,
void from its execution. The violation shall also produce Philippine currency, plus Four Hundred and Fifty Pesos
the effect of annulling and cancelling the grant, title, (P450), also lawful currency, in cash or eighteen (18)
patent or permit originally issued, recognized or cavans of palay (Provincial Measurement) at our option,
confirmed actually or presumptively. The violation shall then this sale shall become null and void and of no force
also cause the reversion of the property and its and effect whatsoever. On the contrary, the same will
improvements to the State. The contract executed in become irrevocable, definite and final and will vest
violation of these sections being void, it is not complete and absolute title on the vendee upon the
susceptible of ratification, and the action for the premises. 1
declaration of the absolute nullity of such a contract is
imprescriptible.73 The contract of sale with right to repurchase was
acknowledged by the vendors before Notary Public
In this case, portions of Lot No. 532 were conveyed to Victorio Tagamolila on the same day the contract was
petitioners by virtue of two Deeds of Absolute Sale executed in the Municipality of Passi, Province of Iloilo.
executed on May 24, 1969 and June 18, 1970, or after the The vendors also delivered to the vendee their owner’s
grant and issuance of Free Patent No. 40008774 on May copy of the title.
28, 1968. Both Deeds of Absolute Sale were executed
within the prohibited period of five years. Consequently, After the execution of the sale, the Pacardo spouses as
following Section 124, these Deeds are null and void and vendors remained in possession of the land and
produce no effect. They did not convey any right from continued the cultivation thereof. Since the sale on 27
Spouses Bajao to petitioners on the property. January 1947 up to August 1987, or for a period of about
40 years, the spouses delivered annually one-third (1/3)
The rule of pari delicto will not apply here in view of the of the produce of the land to Maura Palabrica and kept
nullity of the contracts of sale between the parties.79 To for themselves the remaining two-thirds (2/3).
have it otherwise would go against the public policy of
preserving the grantee's right to the land under the On 27 January 1950, despite the lapse of three (3) years,
homestead law.80 In Binayug v. Ugaddan,81 we returned the Pacardo spouses did not repurchase the land but
the properties which were acquired through a grant of a faithfully continued to give 1/3 of the produce to Maura
homestead patent to the heirs of the original owner after Palabrica. When the spouses died, their son Filoteo Jr.,
it was proven that the properties were alienated within took over the possession and assumed the cultivation of
the five-year prohibition period under Section 118 of the the land and, like his parents, gave 1/3 of the produce to
Public Land Act. Maura Palabrica and later to her daughter, petitioner
herein, who would eventually buy from her the lot
Jurisprudence, therefore, supports the return of the subject of the litigation.
subject properties to respondents as Gerardo's heirs
following the declaration that the Absolute Deed of Sale On 22 September 1966 Maura Palabrica caused the
dated July 10, 1951 between Gorardo and Juan is void for registration of the Sale Con Pacto de Retro with the
being in violation of Section 118 of the Public Land Act, Register of Deeds of Iloilo and its annotation on Transfer
as amended. That the subject properties should revert to Certificate of Title No. 26424 covering the subject lot.
the Slate under Section 124 of the Public Land Act, as
amended, is a non-issue, the State not even being a On 10 May 1978 Maura Palabrica sold Lot No. 767 for
party herein. P40,000.00 to one of her daughters, petitioner Thelma
Olea. From then on it was petitioner who received the
With respect to the purchase price of P2,400 which one-third (1/3) share of the annual produce of the land
petitioners paid for the land, respondent should return it from Filoteo Pacardo, Jr., until he died in August 1987.
with interest.84 We similarly ruled in the recent case His widow Elena Vda. de Pacardo however refused to
of Tingalan v. Spouses Melliza85 which also involved the give to petitioner the one-third (1/3) share of the
void sale of land covered by the Public Land Act, as produce. After Elena transferred residence to another
barangay the spouses Jesus and Elizabeth Palencia took
over the possession and cultivation of the property.
Elizabeth Palencia is a sister of Filoteo Jr., and is one of
the children of spouses Filoteo and Severina Pacardo.
The Palencias delivered the share of the produce not to
petitioner but to respondent Elena Pacardo.
Ruling
The rule is settled that where in a contract of sale with
pacto de retro the vendor remains in physical possession
of the land sold as lessee or otherwise, the contract
should be considered an equitable mortgage. 9 The
same presumption applies when the vendee was given
the right to appropriate the fruits thereof in lieu of
receiving interest on the loan. 10