Beruflich Dokumente
Kultur Dokumente
2
DMAIC
4
Define Measure Analyze Improve Control
ct
C
oje
PO
Pr
SI
C
VO
1
ms
DEFI NE gra
Dia
5
Importance of This Project
Today’s definition
of failure
Equipment F
Condition
Equipment
Broken
Time
“Normal state”
Design
Potential Failure
Intended
Function
Failure
Project Assumptions
What is meant by Critical Equipment?
An Equipment is considered critical where either it does not have any
standby or it’s non-availability would greatly affect plant throughput and
it’s failure will have potential threat to safety & environment.
What is Maintenance interruption?
An event or condition in which the equipment is taken out of service or
stopped for attending an abnormal state or part by maintenance however
small may the condition be is termed as an interruption.
What is MTBF and its interpretation?
Mean Time Between Failure is an average uptime available for an
equipment. In other words it is the average time an asset will function
before it fails.
In Refinery the MTBF is considered for equipments overhauled at
Machine Shop only.
8
Define Measure Analyze Improve Control
Project Assumptions
9
Define Measure Analyze Improve Control
Project Assumptions
Why Rotary Reco (SAP Type M6) alone is considered for analysis?
• Data in type M6 is highly authenticated, precise and created by a trained
professional.
• Data in type M2 majority of times incomplete and sometimes duplicate in
nature created by working level person.
• Type M2 notification data is more of descriptive in nature, while M6 data
comprises measurable data.
• While generating notification through M6 analysis would be conducted
based on condition monitoring of the equipment by the in charge.
• Also, data shows over 90% of cases bearing failures were captured in
M6 Data
10
Define Measure Analyze Improve Control
700 80
600
Frequency
60
Percent
500
400
40
300
200 20
100
0 0
Equipment Pumps Motors Comp/ Fans
Frequency 596 254 34
Percent 67.4 28.7 3.8
Cum % 67.4 96.2 100.0
500
80
400
Per cent
60
C2
300
40
200
100 20
0 0
C1 s s r
ng ng P ie ite he
s si ssi RM li it f s Ot
oc
e
oc
e Ut Of
Pr Pr
y ry
ar da
im on
Pr c
Se
C2 168 161 154 79 24 9
Percent 28.2 27.1 25.9 13.3 4.0 1.5
Cum % 28.2 55.3 81.2 94.5 98.5 100.0
• As per above Pareto diagram more recurring failures are observed in Primary,
Secondary Processing and RMP units.
• It is evident process units cover more than 80% of failure list. 12
Define Measure Analyze Improve Control
Project Charter
In the 36 month period under study (April 2007-March 2010), 103 out of 594 pumps in plant areas
Problem Statement have been taken out of service more than twice for maintenance purposes, leading to reliability and
availability issues in plant operation. Such repeated maintenance activities would lead to lower
MTBF values( the present benchmark of 5.2 years) and will be a potential threat to plant uptimes.
Project Charter
Top 3 critical tags for different failure modes out of identified list will be taken up for
Expected Tangible root cause analysis. Such process of avoiding repeat failures would not only result in
Benefits lower maintenance cost but also help maintain optimum plant through put.
One day shutdown of CCU on account of non-availability of critical bottom pump would
result in loss of over Rs.2.1 Cr direct cost (CCU Value addition Rs 7000 per MT Waxy
processing), can be avoided.
Expected Intangible With higher equipment availability, Process can have flexible operation. Once time
spent on repeat jobs reduced, better focus can be given to other reliability
Benefits improvement initiatives. Also improvement plans can be extended to other parts of the
refinery.
Team members KK Nanduri, John Bosco, Neelesh Bhagwat & RC Agarwal ( BB for guidance)
Support Required
Rotary Cell, Operations and Technology
Environmental conditions and operating at Turn down due to non availability of plant
Risks/ Constraints through put can greatly affect MTBF of rotary equipments.
15
CTQ Drill Down
Define Measure Analyze Improve Control
Tree
Enhance Availability of
Critical Equipment for Ops
C O P I S
1. WHO are your 2. WHAT does the 3. What STEPS are 4. What is 5. Who
primary customer Included in the Process provided to PROVIDES
customers? receive? (Think today? (high level) START the the input?
(From Step A) of their CTQ’s) process?
Customer Output Process Input Supplier
(Who) (Nouns) (Verbs) (Nouns) (Who)
Notification Closure
Follow up reading
Route /
Plant Call
Reading
YES acceptable NO
?
Close Start
18
Define Measure Analyze Improve Control
Stakeholder Analysis
Strongly Strongly
Stakeholder ARMI* Opposed Neutral Supportive
Opposed Supportive
Ops PP R X/O
Ops SP R X/O
Ops RMP R X/O
Rotary Cell X/O
R
Technology I X/O
* When Populating the Stakeholder, consider the ARMI: X = Where this Stakeholder IS TODAY on the Project
• A= Approver of team decisions O = Where this Stakeholder NEEDS TO BE on the Project
• R= Resource or subject matter expert (ad hoc)
• M= Member of team
• I= Interested Party who will need to be kept informed 19
Define Measure Analyze Improve Control
Communication Plan
Top Management Project Progress Report As per Project Road Steering Committee
Map Review Meeting
Project Sponsor / Project Progress, Issues, End of Each Phase Project Review Meeting.
Champion. Milestones Achieved, Next
DGM (Maint.) Steps.
Operators / Technicians Project Needs, Issues, Need based As and When required
Barriers, Progress Done, discussion at site
Changes Done, Next Steps
DMAIC
Define Measure Analyze Improve Control
DEFINE
Data
Pat
ter
ns
ANALYZE
Ca
p ab
ilit
y
21
Define Measure Analyze Improve Control
Identification Process
for Top 3 Critical Pumps for Study
List Reduced
segregated Actions yet list based Top 3
Total Repeat List of Over
based on to be on source of
Failures two Failures
criticality initiated severity failures
index index
594 103 23 16 8 3
Define Measure Analyze Improve Control
Number of defect
opportunities per unit
(Failure Modes) O 3
Number Of Units
(Notifications for pumps
under study) N 16
DMAIC
Define Measure Analyze Improve Control
DEFINE
2
IMPROVE MEASURE
MASURE
ANALYZE
FM
Regression
EA
E
DO
Define Measure Analyze Improve Control
Mechanical
Seal Failure
Improper bearing CW system
Incorrect support / piping installation
Pump Failure out of improper pump assembly
Incorrect lube oil level - brg guard/ leveler
Misalignment in Hot condition
Frequent Pump Change over -No defined policy
Improper Seal Flushing - NA to checklist
Improper Seal Flushing - Orientation of piping
Improper Seal Flushing - Chocking of piping
Incorrect Seal Design
Lower flow operation - lower plant throughput
Lower flow operation - ignorance about P-Q
Cavitation - process upset
Dirt/Moisture in housing
Bearing
Improper bearing CW system
Failure
External Corrosion
Excessive Load on the pump Distorted casing
Deviation from design conditions
Incorrect Bearing Design
Absence of Lubrication Bent Shaft / Run Out
Improper Lubrication
Improper Pump Installation
Improper Brg Installation Un Balance - Pump
Misalignment
Lower flow operation
Misalignment 1. Alignment does not take process conditions 1. Improper skill or knowledge on Hot
2. Excessive piping strain service
3. Erratic instrument reading 2. Improper piping / support installation
3. Absence of Instrument Calibration
Wrong Mechanical Seal 1. Improper personnel skill 1. Lack of awareness or focused training
assembly 2. Use of Non-Standard Materials 2. Not adhering to Standard Procedure /
spare parts
Damage to bearings during 1. Improper use of tools and tackles 1. Not adhering to Standard Procedure
installation 2. Use of defective bearing 2. Use of Non-Inspected (by SKF) bearing
Bearing Failure while in 1. Improper Lube oil Level 1. Defective bearing isolator / leveler
operation 2. Improper Lube Oil Quality 2. Use of contaminated oil / Handling issue
3. Excessive Cooling or Heating of housing 3. Improper cooling system / Choice of
lubricant / defective oil ring or splasher
Suction Pressure variations 1. Operation outside acceptable range 1. Absence of suction surge vessel
/ Low flow / Pump 2. Operation much lesser than design point 2. Pump too big to handle lower throughput
Cavitations
3. Deviation in operating parameter/ 3. Process upset
Cavitations
Improper flushing of seal 1. Connected piping is chocked 1. Not adhering to procedure / checklist
2. Improper piping orientation 2. Ignorance or insufficient knowledge
Frequent change over of 1. Plant follow 15 day cycle it is too frequent to 1. No defined practice available
the pump adopt.
Define Measure Analyze Improve Control
Cause Prioritization
(Mechanical Seal Failure)
Cause Validation
(Mechanical Seal Failure)
Cause
Cyclone Replaced by
Separator Strainer
Original Seal Flushing Plan API Present Seal Flushing Plan API
31 12
Define Measure Analyze Improve Control
Major Causes
Define Measure Analyze Improve Control
Misalignment 1. Alignment does not take process conditions 1. Improper skill or knowledge on Hot service
2. Excessive piping strain 2. Improper piping / support installation
3. Erratic instrument reading 3. Absence of Instrument Calibration
Oil Contamination 1. Improper personnel skill 1. Lack of awareness or focused training
2. Non-Standard Methods / Oil Handling 2. Not adhering to Standard Procedure / tools
Damage to bearings during 1. Improper use of tools and tackles 1. Not adhering to Standard Procedure
installation shop 2. Use of defective bearing 2. Use of Non-Inspected (by SKF) bearing
Suction pressure variations / 1. Operation outside acceptable range 1. Absence of suction surge vessel
Low flow or Cavitation 2. Operation much lesser than design point 2. Pump too big to handle lower throughput
3. Deviation in operating parameter/ Cavitation 3. Process upset
Overloading 1. Casing distortion 1. Improper pump nozzle load design
2. Improper piping orientation 2. Ignorance or insufficient knowledge
Frequent change over of the 1. Plant follow 15 day cycle it is too frequent to 1. No defined practice available
pump adopt.
Define Measure Analyze Improve Control
Cause Prioritization
(Bearing Failure)
Cause Validation
(Bearing Failure)
Cause
CDU - 001G11**
001G11** -P1H Pump Inboard Horizontal
7
Route Spectrum
09-Apr-10 11:47:31
6 OVERALL= 10.23 V-DG
M
M
RP
RP PK = 10.13
LOAD = 100.0
M
1X
RP
5 3X
PK Velocity in mm/Sec
0
Freq: 2887.5
0 10000 20000 30000 40000 50000 Ordr: .979
Frequency in CPM Spec: 3.385
Improper Lubrication
(132P266B of LOBS)
Define Measure Analyze Improve Control
Improper Lubrication
(Bearing Failure)
• Under - Lubrication
• Poor lube oil circulation
• Improper bearing cooling
• Improper level or overheating
2-3 mm above
• Oil blackening
Oil Level
• Premature bearing failure
DMAIC
Define Measure Analyze Improve Control
DEFINE
FM E A –
Pilot So
l’n. 2
IMPROVE MEASU
MASURERE
. Ana.
Cost benefit
. ANALYZE
roi
l. P
So
R
PE
AM
SC
Define Measure Analyze Improve Control
Replace Strainer with Change over with 3 With OIL RING with Replace the pump
Substitute
Cyclone separator month period as pilot splasher disc with lower capacity
Combine
Replace pump with heavy Change over with 3 Replace the pump
Substitute With splasher ring
duty API 610(8th) month period as pilot with lower capacity
Solution Prioritization
Matrix
Pumps in Train III / LOBS
Easy to Easy to
Sr. No Solution Generation COST Total
Implement Control
1 Install a suction surge vessel to re-arrange all streams 1.8 10.8 5.4 18
2 Replace existing pumps with sturdier API design pumps 0.4 10.8 5.4 16.6
3 Modify (Trim / balancing hole size etc) / Replace impeller 1.8 10.8 5.4 18
Replace existing lube oil ring with Splasher Disc and use
4 1.8 10.8 5.4 18
filtered lube oil.
Modify existing seal flushing plan from API Plan 11 to API Plan
7 1.8 10.8 5.4 18
32 (external flushing)
Solution Prioritization
Matrix
Pump in CDU Complex
Easy to Easy to
Sr. No Solution Generation COST Total
Implement Control
Replace existing strainer on seal flushing line with cyclone
1 1.8 10.8 5.4 18
separator.
Modify existing seal flushing plan from API Plan 12 to API Plan
2 0.4 10.8 5.4 16.6
21 (with energy efficient cooler) or Double seal
3 Always use filtered and quality lube oil 1.8 10.8 5.4 18
4 Replace existing lube oil ring with Splasher Disc 1.8 10.8 5.4 18
Solution Implementation
Action Plan
SR DESCRIPTION OF SUPPORT
ACTION POINTS BY WHOM BY WHEN
NO SOLUTION REQD
1. Stock Proposal
1. Codification and Stock Completed.
Installation of Cyclone Proposal 2. Procurement action
Separators in place of 2. Procurement and Binning of Rotary Cell / P&CS / initiated.
1
existing strainers – CDU items Area Maintenance 3. Material expected in 6
PUMPS 3. Installation at site weeks.
4. On Job Training on Seals 4. Area wise Training
Jun 2010 – Nov 2010
1. Study to be completed
1. Study tag wise effect for pump
Adopt 3 month pump by 20.09.2010
change over Rotary Cell / LOBS
5 change over policy on pilot 2. Implementation by
2. Change present process Ops
project 01. 10.2010
3. Implement as a pilot
Define Measure Analyze Improve Control
Replace Plan 12
Replace ring
Modify existing with Plan 31(CDU) Carry out RUN
Modify impeller with splash
pump change / Replace Plan 11 alignment after
SOLUTION Replace pump disc /
over procedure with API Plan 10 min pump
Install filtration
on pilot project 32(RMP) and On run
unit
Job Training
Define Measure Analyze Improve Control
Effort Benefit
Analysis
DMAIC
Define Measure Analyze Improve Control
FM
CO
EA
N
PL TR
AN OL
DEFINE
2
IMPROVE MEASURE
MASURE
ANALYZE
61
Define Measure Analyze Improve Control
Process Management
Temp below
X1: Flushing of Maint Officer / Clean
Temp / Seal Temp / Pressure 160 deg C /
Mechanical Operator / Ops Trend flushing
Pressure once every day Pressure below
Seal Officer circuit
14 Kg/cm2
63
End of Presentation
Thank You
Define Measure Analyze Improve Control
Back to Definitions
Solution Tree – Bearing / Seal
Failures
Back 2 Imp
Solution Tree – Bearing / Seal
Failures
Modified to API Plan 32
Back 2 Imp
PRESSURE STRAINER
GAUGE
EXTERNAL FLUSH
TO SEAL
ORIFICE