Integration % of
Total No of Out Of New Unit Testing Ready for UAT Go
Entity Dev Completed Testing Complet
Interfaces Scope Addition Completed UAT Completed Live
Completed ion
SAP 27 7 3 11 10 10 10
BAAN 27 6 3 13 7 0 0
Remarks:
GIM interfaces - overall status is RED as final requirements have not been provided yet, even though they have early go live date.
PDW & GPM Interfaces - overall status is AMBER as requirements of most of the interfaces is closed.
• GIM Interface requirement is not • For SAP 7 & for BAAN 6 • We foresee a delay in GIM Go
yet started having direct impact interfaces are out of scope Live dates
on Go Live date • Direct impact on schedule
• BAAN Integration Testing is Slippage
getting delayed.
• Not much progress in status
since last week
• GPM Discussions to be arranged
Mitigation Plan:
• Need more dedicated time from all stake holders
Updates:
• UAT plan has been discussed. Next steps to be taken accordingly by each stake holder
• SAP Code has been transported to Quality Environment where as BAAN code movement is in progress.
• Master Data Interfaces UAT to be initiated first.
www.capgemini.com
This message contains information that may be privileged or confidential and is the property of the
Capgemini Group.
Copyright © 2017 Capgemini. All rights reserved. This message is intended only for the person to whom it is addressed. If you are not the intended recipient, you are not authorized to read, print, retain, copy,
disseminate, distribute, or use this message or any part thereof. If you receive this message in error, please notify the sender immediately and delete all copies of this
Rightshore® is a trademark belonging to Capgemini. message.