Beruflich Dokumente
Kultur Dokumente
Discussion Question are set too high, the repeated failure to achieve them
will tend to reduce the motivation for attainment. The
1) Standard costs are the predetermined costs of converse is also true. Standards that are too loose
manufacturing products during a specific period represent an invitation to relax. (c) The participant
under current or anticipated operating conditions. should have a voice or influence in the establishment
Standards aid in planning and controlling operations. of standards and resulting performance measures.
A few uses of standard costs are: (a) establishing Involvement in the formulation of standards gives the
budgets (b) controlling costs by motivating participant a greater sense of understanding and
employees and measuring efficiencies (c) simplifying commitment.
costing procedures and expediting cost reports (d) 7) (a) The role of the accounting department in the
assigning costs to materials, work in process, and establishment of standards is to determine their
finished goods inventories (e) forming the basis for ability to be quantified and to provide dollar values
establishing contract bids and for setting sales prices. for specific unit standards. (b) In the establishment of
2) standards, the role of the department in which the
3) To set sales prices, executives need cost performance is being measured is to provide
information furnished by the accounting department. information for realistic standards, and to allow for
Since standard costs represent the cost that should be subsequent performance evaluation for the purpose of
attained in a well managed plant operated at normal detecting problems and improving performance. (c)
capacity, they are ideally suited for furnishing The role of the industrial engineering department in
information that will enable the sales department to the establishment of standards is to provide reliable
price products. Budgets are used for planning and measures of physical activities related to the
coordinating future activities and for controlling standards of performance, and to verify the
current activities. When budget figures are based on consistency of the performance between departments.
standard costs, the accuracy of the resulting budget is 8) After variances have been determined,
strongly influenced by the reliability of the standard management should: (a) decide whether each
costs. With standards available, production figures variance is sufficiently significant to require
can be translated into the manufacturing costs. investigation and explanation (b) investigate and
4) Standards are an integral part of job order and obtain, from the responsible department head,
process cost accumulation, but do not comprise a explanations of significant variances (c) take
system that could be utilized in lieu of one of the corrective action and recognize and reward desirable
accumulation methods. Costs may be accumulated performance, where appropriate (d) revise standards
with or without the use of standards. if needed.
5) Criteria to be used when selecting the operational 9) (a) Features of tolerance limits include: (1) A
activities for which standards are to be set include the standard cost control system is established,
following: (a) The activity should be repetitive in specifying expected performance levels. (2) An
nature, with the repetition occurring in relatively information system is designed to highlight the area’s
short cycles. (b) The input and output (product or most in need of investigation and possible corrective
service) of the activity should be measurable and action. (3) Variance ranges for areas and items are
uniform. computed. Management does not spend time on parts
(c) The elements of cost, such as direct materials, of the operations that produce satisfactory
direct labor, and factory overhead, must be defined performance levels within these ranges. (4)
clearly at the unit level of activity. Management’s attention and efforts are concentrated
6) Behavioral issues that need to be considered when on significant variances from expected results, which
selecting the level of performance to be incorporated signal the presence of unplanned conditions needing
into standards include the following: (a) The investigation. (b) Tolerance limits have potential
standards must be legitimate. The standards need not benefits because they may result in more effective
reflect the actual cost of a single item or cycle. use of management time. The manager’s time is not
However, they ideally will represent the cost that wasted on the process of identifying important
should be incurred in the production of a given problems or in working on unimportant ones. The
product or the performance of a given operation. (b) manager should be able to concentrate efforts on
The standards must be attainable. When the standards important problems, because the technique highlights
them. (c) It may be difficult to determine which which exceed the range. Subordinate morale may
variances are significant. Also, by focusing on suffer because of the lack of positive reinforcement
variances above a certain level, other useful for work well done. Using tolerance limits may also
information, such as trends, may not be noticed at an affect supervisory employees in an unsatisfactory
early stage. If the evaluation system is in any way manner. Supervisors may feel that they are not
directly tied to the variances, subordinates may be getting a complete review of operations because they
tempted to cover up negative exceptions or not report are always keying on problems. In addition,
them at all. In addition, subordinates may not receive supervisors may think that they are excessively
reinforcement for the reduction and maintenance of critical of their subordinates. A negative impact on
cost levels, but only reprimands for those items supervisory morale may result.
Exercises
E-1
Given
Standard cost per unit = $ 13.50 / pound
Material purchased = 4,500 pounds
Purchase price/cost = $ 60,975
Actual unit cost = 60,975/4,500 = $ 13.55/pound
Material used = 3,900 pounds
Standard quantity allowed for use = 3,800 pounds
Solutions:
Req. (1) purchase price variance
Quantity (pounds) x $ unit cost = $ Amount
Actual Quantity purchased at actual cost 4,500 x 13.55 = 60,975
Actual Quantity purchased at standard cost 4,500 x 13.50 = 60,750
_______ _______
unfavorable $ 0.05 $ 225
Solutions:
Unfavorable 50 500
E-3 (1) Given ????
Solutions:
Unfavorable (0.1) 31
Favorable 30 (360)
Estimated F.O.H
Fixed $96,000
$150,000
Overall/total variance
Unfavorable $28,500
Estimated F.O.H
Fixed $ 96,000
Unfavorable $20,500
Unfavorable $8000
Estimated F.O.H
Fixed $64,000
$166,400
E-5 Solutions:
Overall/total variance
Favorable ($2,120)
Estimated F.O.H
Fixed $ 64,000
Favorable ($3,000)
(2) Capacity Variance
Unfavorable $4000
Favorable ($3,120)
Estimated F.O.H
Fixed $85,500
$111,600
Overall/total variance
Unfavorable $16,840
Estimated F.O.H
Fixed $ 85,500
Unfavorable $8,820
Estimated F.O.H
Fixed $ 85,500
Unfavorable $5,700
Unfavorable $2,320
Estimated F.O.H
Fixed $7,000
Variable $3,000
$10,000
E-7 Solutions:
Overall/total variance
Favorable ($500)
Estimated F.O.H
Fixed $ 7,000
Favorable ($100)
(2) Variable Efficiency Variance
Favorable ($225)
Favorable ($525)
Unfavorable $350
Estimated F.O.H
$720,000
Overall/total variance
Unfavorable $16,000
(1) Spending Variance
Estimated F.O.H
Fixed $ 480,000
Favorable ($236,000)
Unfavorable $,252000
Reconciliation of variances:
Actual factory overhead $19,272
Standard factory overhead chargeable
to work in process 16,830
Overall factory overhead variance $ 2,442 unfav.
Controllable variance $ 282 unfav.
Volume variance 2,160 unfav.
Overall factory overhead variance $ 2,442 unfav.
E-10
per unit
Per unit
Less:
Less:
(390,000 x $0.525)
Variance
Cost per
$(39,895) $38,075
E-12
Allowed variance
II 7 500 3,500
I 5 500 2,500
1,500 $10,000
Labor class
II (650 x 7) = 4,550
Normal capacity direct labor hours (2,400) × Fixed factory overhead rate per direct labor
hour ($10 ÷ 4) = 2,400 × $2.50 = $6,000 fixed factory overhead based on normal
monthly capacity.
*The spending variance includes the difference between actual and budgeted fixed cost,
$200 ($8,200 – $8,000). This portion could be separately labeled as a fixed spending
variance, leaving a balance of $2,300 as the variable spending variance.
P-3
P-4
Raw material:
Gallons × Unit Cost = Amount
Actual quantity purchased 600,000 $1.917 actual $1,150,000
Actual quantity purchased 600,000 2.000 standard 1,200,000
Materials purchase price variance 600,000 $(.083) $(50,000) fav.
Drums:
Drums × Unit Cost = Amount
Actual quantity purchased 85,000 $1 actual $85,000
Actual quantity purchased 85,000 1 standard 85,000
Materials purchase price variance 85,000 0 0
Direct labor:
Hours × Rate = Amount
Actual hours worked 65,000 $7.231 actual $470,000
Actual hours worked 65,000 7.000 standard 455,000
Labor rate variance 65,000 $ .231 $15,000 unfav.