DAILY REPORT PT.

TEKINDO ENERGI
Tuesday, January 02, 2018

SUMMARY OF DAILY REPORT


1. Pre Mining Operation
No Activities Unit Support Progress Next day Plan
Preparation of Road 1 PC 300 TE 08 - Limestone boulder - Boulder stockpiling from
1 service on Weight 6 DT KAK stockpiling from KM 8 to Smelter area to weight bridge
bridge. Weight bridge area. area.
Road service on 1 PC 200 TE 03 - Armco bridge KM 13; - Continuing Armco bridge road
Armco bridges and 1 PC 200 TE 11 Quarrying from KM 17 service at KM 13 and KM 16
2
Log bridges 6 DT KAK Quarry loading from KM 17 such as Quarrying , loading
Set log on road foundation quarry
Preparation for 1 PC 200 TE 09 - Pull out Logs from forest area - Pull out Logs from forest area
Installation Log 1 BD 03 SKM to main road KM 23, as many to main road KM 23, as many
bridges KM 18, 1 DT Camc TE as 15 logs. as 15 logs.
3 KM 13, KM 7, KM - Hauling logs from KM 23 to - Hauling logs from KM 23 to
17 & KM 20 KM 17 and KM 13 KM 17 and KM 13
- Loading logs to DT Camc - Loading logs to DT Camc
- Installation brigde KM 17
4 Hauling road 1 Motor grader No activities no operator - Grading KM 12 to KM 18
Maintenance 1 Compactor No activities unit breakdown - Compacting KM 12 - 18

2. Mining Operation
a. SKM Mining activity
Mining activity at pit did not progress from dec 23, 2017 until dec 28, 2017 cause all of SKM’s heavy
equipment unit used for barging activity and waiting for diesel fuel supplying.
Continuing mining activity that begin again from dec 29, 2017 such as stripping over bourden, OB
removal, ore getting and ETO area extension activity until minimum more than 50.000 WMT. Support
loading ore at ETO KM2A for ore hauling activity to EFO have finished this day.

Production progress (WMT)


No Date Ore Remarks
ETO Production
Grade This day Previous Total
1 Dec 29, 2017 ETO23/NURI/MG 34 HGO 558 30.420 30.978
2 Dec 30, 2017 ETO23/NURI/HG 10 WA 738 30.978 31.716 Waiting Assay
3 Dec 31, 2017 ETO23/NURI/HG 11 WA 900 31.176 32.616 Waiting Assay
4 Dec 31, 2017 ETO23/NURI/HG 12 WA 792 32.616 33.408 Waiting Assay
5 Jan 02, 2018 ETO23/NURI/MG 35 WA 828 33.408 34.236 Waiting Assay

b. KAK Ore Hauling activity


Ore hauling activity still have done on sunny day only. Hauling road condition still can not passing yet for
night activity, Safety factor become our principal opinion.

Hauling ore
No Date Ore Remarks
ETO pile id
Grade Trip Tonase Total
1 Dec 31, 2017 ETO2A/SQ01 – SQ02 LGO 119 2.261 2.261 Ni 1.64% & 1.53%
2 Jan 2, 2018 ETO2A/SQ03 LGO 113 2.147 4.408 Ni 1.69%
DAILY REPORT PT. TEKINDO ENERGI
Tuesday, January 02, 2018

3. Production, Engineering and Geology


 Mobiliation of drilling unit have been arriving in Ternate at January 02, 2018 and will be continue
mob to mess Tekindo, estimation arrive at site night January 3, 2018. Commissiong plan will be
doing at January 04, 2018 and continue Mob to first drill hole at Sagentel prospect.
 This week SKM planning will start mining activity in Maleo PIT.
 Continuing ETO area extension till minimum more than 50.000 WMT according to the work
contract.
4. Issues
 Lim mining team need to clarity of job contract that have given to contractor company to know
their job responsibility clearly.
 Bridge of KM 17 have broken and collapsed yesterday, heavy equipment can’t pass it, so need to
sevice as soon as possible. Still waiting excavator unit support PC 300 from SKM.
 Ore hauling activity from ETO 17 and ETO 18 will be continuing this week after service brigde
KM 17 that have collapsed with safety ramdor.
 Pull out and logs material hauling, start continuing this week for Log bridges KM 18, KM 20, KM
17 and KM 8 with support unit from SK and TE such as Bulldozer and Loboy.
 Unit supporting for road service and maintenance often breakdown so it’s disturbing road service
activity.

Pic 1. Road service activity in KM 13, date January 02, 2018


DAILY REPORT PT. TEKINDO ENERGI
Tuesday, January 02, 2018

Pic 2. Log bridge KM 17 collapse, waiting unit support to service it, date January 02, 2018

Pic 3. Road Servicing at bridge KM 13 have done and still continue progress, date January 02, 2018