Beruflich Dokumente
Kultur Dokumente
Black Start/Emergency DG
Unit 3 Startup
Unit 4 Startup
Coordination with Smelter
Annexure: Black Start DG start-up & Synchronisation with Grid
600
390
240
50
1
0 1.5
0 2
0 2.5 3 3.5 4 4.5 5
1 2 3 4 5 6 7 8 9
Load(MW) 0 0 0 50 240 390 600 750 750
Time (Hrs) 1 1.5 2 2.5 3 3.5 4 4.5 5
Responsibility- PKS/Jyoti/Abinash
Step1: Operator will select screen “CPP-3 Panel Line Diagram” under “LINE
DIAGRAM” from SCADA Screen. “CPP AREA -3” will appear on SCADA
Screen.
Step2: Operator will give “CLOSE” command through SCADA button to 2B DG
Incomer breaker (Q1). Breaker will close on Dead Bus & DG will take the load
of the bus.
Step3: (Optional for 2A Switchgear operation) Operator will ensure the following
condition on CPP Area-3 SCADA screen
a. Breaker Q3 (2A Traformer Incomer) – OFF
b. Bus of 2A Section is OFF (i.e. Green colour).
Step4: (Optional for 2A Switchgear operation) Operator will give “CLOSE” command
through SCADA button to Q4 Breaker (New 2B Tie Feeder to 2A), Else Local
Closing may be done.
Step5: (Optional for 2A Switchgear operation) Operator will give “CLOSE” command
through SCADA button to Q5 Breaker (New 2A Tie Feeder to 2B), Else Local
Closing may be done.
Responsibility-Electrical SIC/PKS/BKP/Ramakanta/Jyoti
Step1: Operator will select screen “CPP-4 Panel Line Diagram” under “LINE
DIAGRAM” from SCADA Screen. “CPP AREA -4” will appear on SCADA
Screen.
Step2: Operator will give “CLOSE” command through SCADA button to 3B DG
Incomer breaker (Q6). Breaker will close on Dead Bus & DG will take the load
of the bus.
Step3: (Optional for 3A Switchgear operation) Operator will ensure the following
condition on CPP Area-4 SCADA screen
a. Breaker Q8 (3A Traformer Incomer) – OFF
b. Bus of 3A Section is OFF (i.e. Green colour).
Step4: (Optional for 3A Switchgear operation) Operator will give “CLOSE” command
through SCADA button to Q9 Breaker (New 3B Tie Feeder to 3A)
Step5: (Optional for 3A Switchgear operation) Operator will give “CLOSE” command
through SCADA button to Q10 Breaker (New 3A Tie Feeder to 3B)
Responsibility-Electrical SIC/PKS/BKP/Ramakanta/Jyoti
Responsibility-Electrical SIC/PKS/SP/BKP/Ramakanta/Jyoti
Responsibility-Electrical SIC/PKS/SP/BKP/Ramakanta/Jyoti
Responsibility-Electrical SIC/PKS/SP/BKP/Ramakanta/Jyoti