Project Report

2019 TI+ GT 1.1 PLTGU GRATI


8 Maret 2019 s/d 11 Mei 2019
Author : Fauzan Fauziansyah

DAY : 53

CUACA : CERAH
PROJECT PROGRESS

REALISASI PEKERJAAN HARI INI

MAN POWER
PROGRESS
PEKERJAAN
(%)
TEKNISI HELPER

BIDANG MEKANIK TURBIN

PM INSTALL ATOMIZING AIR HEADER, FUEL OIL & GAS PIPE 100 4

PM INSTALL BLEED & ROTOR COOLING PIPE (COMPRESSOR & TURBINE) 100 1 4

PM BORESCOPE COOLING AIR PIPE & COMBUSTOR CHAMBER 100 3

PM JOINT INSPECTION COMBUSTOR AREA 100


PL (1)
TEKNISI (1)
PM JOINT INSPECTION IGV AREA 100
QC (2)
START UP (1)
PM JOINT INSPECTION EXHAUST DUCT AREA 100

PM INSTALL COMBUSTOR MANHOLE 100 3

PM INSTALL MANHOLE IGV 100 1 3

PM INSTALL MANHOLE EXHAUST DUCT 100 3

PM INSTALL INSULATION 50 MITRA

BIDANG MEKANIK AUXILIARY

PM AUXILIARY GEAR, RUN OUT CHECK JACK SHAFT & INSTALL UPPER COVER 20 1 10
PL (1)
TEKNISI (1)
PM JOINT INSPECTION INLET DUCT 100
QC (2)
START UP (1)
BIDANG LISTRIK

GENERATOR

INSTALL EXCITER 100


1 6
PM PEMASANGAN BRUSH HOLDER DAN BRUSH CARIER 100

MOTOR
PM INSTALL IGNITOR ASSY 75 4

PM LOAD TEST MOTOR AC TURNING 100 1 2

PM LOAD TEST MOTOR DC TURNING 100 2

BIDANG KONTROL INSTRUMEN

GT FIELD AREA

PM PEMASANGAN KEYPHASOR 100


1 2
PM PEMASANGAN DAN ADJUSTMENT VIBRASI PICK UP BEARING # 2 100

PM PEMASANGAN DAN ADJUSTMENT VIBRASI PICK UP BEARING # 3 100


1 3
PM PEMASANGAN THERMOCOUPLE BLADE PATH 1 - 18 100

RENCANA PEKERJAAN BESOK

MAN POWER
PEKERJAAN
TEKNISI HELPER

START UP & COMMISIONING GAS TURBIN

PM SIMULASI INTERLOCK START UP (4)

BIDANG MEKANIK TURBIN

PM INSTALL INSULATION (LANJUTAN) MITRA

PM INSTALL CROSS LADDER 1 5

PM INSTALL TURBINE ENCLOSURE 1 10

BIDANG MEKANIK AUXILIARY

PM AUXILIARY GEAR, RUN OUT CHECK JACK SHAFT & INSTALL UPPER COVER (LANJUTAN) 1 10

BIDANG LISTRIK

GENERATOR

PM FINAL INSPECTION IPB (LANJUTAN) 1 4

MOTOR

INDIVIDUAL TEST STARTING MOTOR 2


1
PM INSTALL IGNITOR ASSY (LANJUTAN) 4

RELAY PROTEKSI

PM PERSIAPAN INTERLOCK TEST 1 4

BIDANG KONTROL INSTRUMEN

GT FIELD AREA

PM PEMASANGAN THERMOCOUPLE DISCAVITY 1 2

PM SIMULASI INTERLOCK 2 3
DOKUMENTASI PEKERJAAN HARI INI

PM JOINT INSPECTION IGV AREA PM AUXILIARY GEAR, RUN OUT CHECK JACK SHAFT

PM PEMASANGAN DAN ADJUSTMENT VIBRASI PICK UP


INSTALL EXCITER
BEARING # 2