Site

-short discussion
Tempfacil
-water connection
-lighting – temporary connection from Meralco
-sewer line – cannot be connected immediately, how?
-site layout plan – use colors/ numbers/ arrows (just for presentation)
Schedule
-start with general schedule
-then go to detailed sched
-discuss milestones
-use 2 levels
-use pictures for PPE
-add equipment (including non-heavy, for every process)
-one safety officer is enough
-emergency procedure
-sequence explanation
-avoid 1 liner slides
-approval needed for everything architectural
Methodology
-discuss equipment
-send an addendum
-concrete
-How are you going to compact? (walker?..)
-do 7 day – 28 day testing?
-3 to 4 days curing time
-3 hrs setting time
-include pulley
-roof truss
Mill tested, welders are certified
-welding rods and anchor bolts types, discuss or mention
-a lot of talk should be done in structural, especially structural materials
-add content
-shop drawing of pre-fab materials needed at least a week before placement
-samples
-include details of railings (how are you going to put it)
-also for gate, fence, and stairs. Provide addendum for stairs
-where will you get fixtures? Mention if reputable
-say how are you going to repair, e.g. cracks
-how are you going to protect finishes
-how are you going to protect door from paint
-discuss unique stuff
-no need for rebar testing if with certificate
-kitchen system
-state that drawings will be given (???)
-check for critical areas
-ribbing, fascia
For approval: elec wires, cables, conduits, panelboards
-state brand, provide sample
Termination of ceiling into wall
Tile: indicate brand of adhesive, when are you going to install tiles?
Tile pattern: seruho etc for approval
What type of mariwasa?
Details of the finish?

QA organization – state who are visiting : owner? PM?


MEPFS – E and P only
PM and foreman only usually for a house project

-mechanical is not necessary


-make an impression that there will be no problems