PRESUPUESTO DE OBRA

PROYECTO

ETAPA 1.0 : IE. "SAN JOSE" PAUCAMARCA


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE ICHOCAN
UBICACION : DPTO:CAJAMARCA PROV.:SAN MARCOS DIST.:GREGORIO PITA
FECHA PROYECTO : 15/04/2019
Item Descripción Unid. Cant. Precio Parcial Sub Total
1 IE. "SAN JOSE" PAUCAMARCA 6695448.57
1.1 ESTRUCTURAS 3956122.99
1.1.1 OBRAS PROVISIONALES 41046.42
1.1.1.1 ALMACÉN, OFICINAS Y CASETA DE GUARDIANÍA glb 1.00 17800.00 17800.00
1.1.1.2 CARTEL DE OBRA DE 3.60 mx7.20m pza 1.00 1889.42 1889.42
1.1.1.3 CERCO PROVISIONAL DE TRIPLAY ml 216.78 30.51 21357.00
1.1.2 TRABAJOS PRELIMINARES 730020.89
1.1.2.1 TRABAJOS PRELIMINARES 30437.55
1.1.2.1.1 LIMPIEZA DE TERRENO MANUAL m2 2100.00 0.74 383.37
1.1.2.1.2 TRANSPORTE DE EQUIPOS Y MAQUINARIA glb 1.00 30000.00 30000.00
1.1.2.1.3 TRAZO Y REPLANTEO PRELIMINAR m2 500.00 2.00 54.18
1.1.2.2 DEMOLICIÓN DE ESTRUCTURA ACTUAL 97581.22
1.1.2.2.1 DEMOLICION DE ESTRUCTURA EXISTENTE m3 3874.83 55.45 86630.64
CORTE DE MATERIAL PARA NIVELACIÓN DEL TERRENO CON
1.1.2.2.2 m3 640.00 7.74 1969.83
MAQUINARIA

1.1.2.2.3 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 330.85 23.59 7804.75

1.1.2.2.4 NIVELACION DE TERRENO MANUAL m2 840.00 1.40 1176.00


1.1.2.3 SEGURIDAD Y SALUD 602002.12
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL
1.1.2.3.1 glb 1.00 25663.88 25663.88
PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO
1.1.2.3.2 EQUIPOS DE PROTECCION INDIVIDUAL und 100.00 5335.00 533500.00
1.1.2.3.3 EQUIPO DE PROTECCION COLECTIVA glb 1.00 6500.00 6500.00
1.1.2.3.4 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 15000.00 15000.00
1.1.2.3.5 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 18000.00 18000.00
RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN
1.1.2.3.6 glb 1.00 3338.24 3338.24
SEGURIDAD Y SALUD EN EL TRABAJO
1.1.3 MOVIMIENTO DE TIERRAS 334607.25
1.1.3.1 EXCAVACION DE ZANJAS Y ZAPATAS RT<2KG/CM2 m3 661.59 39.34 6356.95
1.1.3.2 EXCAVACION MASIVA C/MAQUINA m3 650.37 17.82 43665.59
1.1.3.3 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO m3 516.79 26.16 21367.23
ESCARIFICADO Y COMPACTACION CON PLANCHA
1.1.3.4 m2 406.83 3.95 4371.98
COMPACTADORA
ACARREO INTERNO MATERIAL PROCEDENTE DE
1.1.3.5 m3 185.48 17.21 54822.11
EXCAVACIONES

1.1.3.6 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 335.84 23.59 132949.47

1.1.3.7 AFIRMADO COMPACTADO E=4" EN PISOS Y VEREDAS m2 566.83 12.38 13702.56

1.1.3.8 AFIRMADO COMPACTADO E=8" EN PATIOS Y LOSA DEPORTIVA m2 331.67 17.22 57371.36

1.1.4 OBRAS DE CONCRETO SIMPLE 272900.87


SOLADO PARA ZAPATAS DE 2" MEZCLA 1:12 CEMENTO-
1.1.4.1 m2 284.01 45.06 68779.58
HORMIGON
1.1.4.2 CIMIENTOS CORRIDOS 1:10 + 30 % P.G. f'c >=100Kg/cm2 m3 12.93 214.20 54353.25
1.1.4.3 CIMIENTOS CORRIDOS ENCOFRADO Y DESENCOFRADO m2 1691.66 48.98 82857.51
1.1.4.4 SOBRECIMIENTO, CONCRETO f'c >=100Kg/cm2 +25% P.M. m3 7.33 312.48 15858.36
1.1.4.5 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m2 22.04 39.87 13489.22
1.1.5 OBRAS DE CONCRETO ARMADO 2577547.56
1.1.5.1 ZAPATAS 199188.59
1.1.5.1.1 ZAPATAS - CONCRETO f'c=210 kg/cm2 m3 397.49 344.79 55714.62
1.1.5.1.2 ZAPATAS - ENCOFRADO Y DESENCOFRADO m2 223.11 65.58 45879.77
1.1.5.1.3 ZAPATAS.- ACERO Fy=4200 Kg/cm2 kg 12048.54 5.58 97594.20
1.1.5.2 VIGAS DE CIMENTACION 163042.99
1.1.5.2.1 VIGA DE CIMENTACION - CONCRETO FC=210 Kg/cm2 m3 45.01 365.48 41734.16
1.1.5.2.2 VIGA DE CIMENTACION - ENCOFRADO Y DESENCOFRADO m2 119.05 61.54 23423.35
1.1.5.2.3 VIGA DE CIMENTACION - ACERO Fy=4200KG/CM2. kg 3319.70 5.58 97885.48
1.1.5.3 COLUMNAS 525756.11
1.1.5.3.2 COLUMNAS - CONCRETO fc= 210Kg/cm2 m3 25.05 496.48 88914.60
1.1.5.3.3 COLUMNAS - ENCOFRADO Y DESENCOFRADO m2 257.82 64.45 141278.27
1.1.5.3.4 COLUMNAS - ACERO fy=4200 Kg/cm2 kg 6358.40 5.58 287118.68
1.1.5.3.5 COLUMNAS - ACERO LAMINADO TUBISA CUADRADO 150X4 kg 14659.97 5.58 287118.68
1.1.5.3.6 COLUMNAS - ACERO LAMINADO TUBISA CUADRADO (3"X3) kg 2089.32 5.58 287118.68
1.1.5.4 VIGAS 1012613.10
1.1.5.4.2 VIGAS - CONCRETO 210Kg/cm2 m3 103.52 379.25 100808.44
1.1.5.4.3 VIGAS.- ENCOFRADO Y DESENCOFRADO m2 397.83 74.68 397429.04
1.1.5.4.4 VIGAS.- ACERO fy=4200 Kg/cm2 kg 16146.43 5.58 509915.41
1.1.5.5 LOSAS ALIGERADAS 615789.36
1.1.5.5.1 LOSA ALIGERADA - CONCRETO 210 kg/cm2 m3 47.75 386.68 225902.32
1.1.5.5.2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO m2 521.21 46.16 45924.58
1.1.5.5.3 LOSA ALIGERADA - ACERO fy=4200 Kg/cm2 kg 2558.80 5.58 152211.35
1.1.5.5.4 LOSA ALIGERADA - LADRILLO HUECO 15X30X30 und 8691.00 3.51 112148.22
1.1.5.5.5 LOSA ALIGERADA - CONCRETO 175 kg/cm2 m3 60.80 3.51 112148.22
1.1.5.5.6 LOSA ALIGERADA - eNCOFRADO Y DESENCOFRADO m4 60.80 3.51 112148.22
1.1.5.5.7 COBERTURA CON TEJA ANDINA m2 470.10 46.58 79602.89
1.1.5.6 ESCALERAS 9299.48
1.1.5.6.1 ESCALERAS - CONCRETO fc=210 kg/cm2 m3 22.56 493.83 2449.40
1.1.5.6.2 ESCALERAS - ENCOFRADO Y DESENCOFRADO m2 45.60 98.20 3196.41
1.1.5.6.3 ESCALERAS - ACERO fy=4200 kg/cm2 kg 5395.40 5.58 3653.67
1.1.5.9 GRADERIAS PARA COLISEO Y PISCINA 1238.83
1.1.5.9.1 GRADAS EN PISO, CONCRETO F'C=175KG/CM2 m3 38.30 362.03 905.08
1.1.5.9.2 GRADAS EN PISO - ENCOFRADO Y DESENCOFRADO m2 439.60 80.81 333.75
1,1,5,10 POLICARBONATO m2 938.60
1.2 ARQUITECTURA 1340846.87
1.3 INSTALACIONES SANITARIAS 176648.52
1.4 INSTALACIONES ELECTRICAS 767608.25
1.6 MITIGACIÓN DE IMPACTO AMBIENTAL 750.00
1.7 FLETE TERRESTRE 60000.00
1.5 EQUIPAMIENTO Y MOBILIARIO 393471.94

Costo Directo 6695448.57


Gastos Generales 9.9990374% 669480.41
Utilidad 5.00% 334772.43
I.G.V. 18% 1385946.25
Parcial 9085647.66
Elaboración de Expediente Técnico 4.00% 363425.91
Supervisión 4.00% 363425.91
TOTAL : 9812499.48

[Son: nueve millones ochocientos doce mil cuatrocientos noventa y nueve Nuevos Soles con cuarenta y ocho céntimos]
Sub Total
6695448.57
3956122.99
41046.42

730020.89
30437.55

97581.22

602002.12

334607.25

272900.87

2577547.56
199188.59

163042.99

525756.11
1012613.10

615789.36

9299.48

1238.83

1340846.87
176648.52
767608.25
750.00
60000.00
393471.94

6695448.57
669480.41
334772.43
1385946.25
9085647.66
363425.91
363425.91
9812499.48

céntimos]