FACILITY LAYOUT & WAITING LINE ANALYSIS (QUEUING THEORY):

Question 1

Every 5 Minutes your customers will arrive to your outlet. Your system can serve 4 minutes per
customer. By using Single-Server (M/M/1), solve these problems:
i. Ls
ii. Lq
iii. Wq
iv. Ws
v.  (the system is full/ the system is fully utilise)
vi. 0 (the system is empty/no customer in the system)

Question 2

Using the assembly-line balancing procedure, what is the theoretical minimum number of
workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5
minutes, and the cycle time is 10 minutes?

Question 3

You have just determined the actual number of workstations that will be used on an assembly
line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes,
and the sum of all that tasks required on the line is 25 minutes. What is the correct value for the
resulting line's efficiency?

Question 4

Using the assembly-line balancing procedure, what is the required cycle time in minutes per unit
if the daily production time is 480 minutes and the required daily output is 50 units?