1 x 650 TDS CHEMICAL RECOVERY BOILER - PRESSURE PARTS MANUFACURING DISCREPANCIES (TIRCHY)

Pressure parts Manufacturing discrepancies Corrective action Time Lapse Remarks


1 Furnace floor beam support beams area fins are welded - site has modfied 2 days

2 Total furnace ( water walls ) mock-up was not done which resulted in for trimming & rebeveling it
site has modfied 3 days
lot of msimatches & misalignment in water wall tube to tube fitup took more time

30% of the piping


3 Desuperheater link piping is sent in half finished condition Site has done fabrication fabrication is done at site
5 days
30% of the piping
4 Boiler bank & Screen downcomer pipngs are sent as loose items Site has done fabrication fabrication is done at site

5 Economiser mdoules inlet hedaer stubs are wrongly oreiented & site has modfied 3 days
welded
6 All the piping are sent with out 100% RT & SR Site has done the same 3 days 50% was done in site

7 No material is of proper quality ( improper bend orienations, weld


undercuts etc….. )
Note :
1 Because of all these discrepancies & delayed supplies overall shut duration has got extended to 31 days

2 As all the supplies have got delayed, all the preshut actvities were taken up in the shut which has incread the shut scope enormously & lead to
extended duration