CHAPTER 4

TECHNICAL STUDY

Objectives of the Study

Technical aspect tackles how important to know the technicalities that will be run in MiRcube
Manufacturing Corp.

1. To have an actual plant layout and design of the company that will help the machines

and the workers to have an efficient production.

2. To have a more efficient methods and process for a well productive firm.

3. To find materials that meets the quality of the product.

4. To create disciplined waste disposal

5. To state the name of a corporation for partnership/where to get the materials

needed.

Product name: Coffee Fusion Tumbler

Description of the product


Coffee Fusion tumbler is a combination of two products to become one, a Boiler and a Stirrer. It

can cater the needs

Features of Coffee Fusion Tumbler

Spinner/Stirrer - Can stir liquid contents inside the tumbler

LowerLeft Switch – Use to charge the coffee fusion tumbler

Push Button Switch – To activate the stirrer

Lower Right Switch – To make boil the liquid content

Specifications

 The diameter of the Tumbler is 83 degrees

 The height of the tumbler is 9 inches


 Weight approximately is less than 1kg

 Easy to bring because of the Handle

Use of the Product

The coffee fusion tumbler is an innovative product with a combination of a Stirrer and a Boiler.

o To make the coffee hot

o To make the liquid / coffee stir


10pieces 1,195.00 11950.00 Ofix

Philippines

Multi-purpose Chair

2 pieces 19,995.00 39990.00 Ofix

Philippines

Lounge Sofa set

4 pieces 7,495.00 29, 980.00 Ofix

Philippines

Filing Cabinet

3 pieces 7,295.00 21,885.00 Ofix

Philippines

Round Table
1 piece 14,999.00 14,999.00 All Home

Furniture

Conference Table

2 pieces 24,995.00 49,990.00 Ofix

Philippines

Executive Table

5 pieces 1,695.00 8,475.00 Ofix

Philippines

Office Chair

5 pieces 3,499.00 17,495.00 Ofix

Philippines
Office Table

1 piece 999.00 999.00 Lazada

Shredder

1 piece 7,500.00 7,500.00 Megakarte

Smartcard

Corporation

Biometrics

2 piece 4,999.00 9,998.00 Aerovent

Fans and

Blowers

Manufacturi

ng

Industrial Fan
2 piece 4,999.00 9,998.00 Whirlpool

Water Dispenser

2 piece 24,999.00 49,998.00 Matrix MX

Aircondition
2 pieces 4,499.00 9,998.00 Ofix

Philippines

Printer

2 pieces 999.00 1,998.00 Matrix MX

Exhaust Fan

5 pieces

Computer
Table 4.2

Office and Production Supplies

Office Supplies Quantity Price Total Supplier


( PHP) Price
(PHP)
10 pieces 84.75 840.75 Office

Warehouse.

Inc

Correction Pen

10 pieces 90.00 900 Office

Warehouse.

Inc

Cash Register Roll

5 pieces 259.75 1298.75 Office

Warehouse.

Inc
Copy Paper - Letter

5 pieces 81.50 407.50 Office

Warehouse.

Inc

Check Voucher

15 pieces 185.00 2775.00 Office

Warehouse.

Inc

Ring Binder

10 pieces 18.75 180.75 Office

Warehouse.

Inc

Clear Tape
15 pieces 5.00 150.00 Office

Warehouse.

Inc

Folder

1 piece 715.00/pack 715.00 Office

Warehouse.

Inc

Carbon Paper

10 pieces 39.75 390.75 Office

Warehouse.

Inc

Packaging Tape

3 pieces 79.00 Office

Warehouse.

Inc

Tape Dispenser
10 pieces 145.00 1450.00 Office

Warehouse.

Inc

Magfile

10 pieces 7.00 70 Office

Warehouse.

Inc

Cutter

10 pieces 264.00 2640.00 Office

Warehouse.

Inc

Storage Box

10 pieces 42.50 42.50 Office

Warehouse.

Inc
White Board Marker

5 box 84.75 423.75 Office

Warehouse.

Inc

Pencil

10 pieces 76.25 760.25 Office

Warehouse.

Inc

Alcohol

5 pieces 94.75 473.75 Office

Warehouse.

Inc

Log Book
10 pieces 67.75 670.75 Office

Warehouse.

Inc

Double sided Tape

10 pieces 56.75 560.75 Office

Warehouse.

Inc
Post it Note

5 pieces 556.50 2782.5 Office

Warehouse.

Inc

Corkboard
Table 4.2

Safety and Security Equipment and Tools

Equipment Quantity Price Total Price Supplier

1 piece 772.00 772.00 Apollo Fire


Alarm

Fire Alarm

10 pairs 250.00 2,500.00 3M Personal


Protective
Equipment

Safety

Shoes

10 pieces 230.00 2,300.00 3M Personal


Protective
Equipment

Hard

Hat
10 pairs 10.00 100.00 3M Personal
Protective
Equipment

Gloves

2 boxes 659.00 1,318.00 Lazada

First Aid

10 pieces 15.00 150.00 3M Personal


Protective
Equipment

Goggles

5 pieces 999.00 4,995.00 Qube FullHD

CCTV Phil

CCTV
2 pieces 435.00 870.00 Akari

Emergency Light
Table 4.3

Program Evaluation and Review Techniques

Opti
mistic Most Likely Pessimistic Estimated Time
Activities Description Predecessor
Time Time (M) Time (P) (O+4(M)+P)/6
(O)

Material - 15 18 20 18
A Preparation
Metal
Fabrication A 46 58 70 58
B Assembly

Wiring for B 20 24 27 24
C Dynamo Spinner

Attaching of C 25 28 30 28
D Nichrome Wire
Connecting of
Wires to the D 15 17 20 17
E Battery

Inserting of E 20 24 28 24
F On/Off Switch
Inserting of
Outlet for F 15 19 23 19
G Charging

G 5 8 11 8
H Final Inspection

H 3 6 9 6
I Packaging
Table 4.4

Production Schedule

Prede Optimistic Most Likely Pessimisti Estimated Time Slack


Activities Description
cessor Time (O) Time (M) c Time (P) (O+4(M)+P)/6 Time
Material - 15 18 20 18 -
A Preparation

A 10 12 14 12 4
B Cutting

B 5 7 9 7 4
C Drilling

C 3 6 9 6 6
D Screw

D 20 22 24 22 4
E Welding

E 8 11 14 11 6
F Polishing
Wiring for
Dynamo F 20 24 27 24 7
G Spinner
Attaching of
Nichrome G 25 28 30 28 5
H Wire
Connecting of
Wires to the H 15 17 20 17 5
I Battery
Inserting of I 20 24 28 24 8
J On/Off Switch
Inserting of
Outlet for J 15 19 23 19 8
K Charging
Final K 5 8 11 8 6
L Inspection

L 3 6 9 6 6
M Packaging

Table 4.5

Raw Materials and Supply

Raw Materials Supplier

Cup Ohms Electronic Shop Landayan S.P.L.

Dynamo Ohms Electronic Shop Landayan S.P.L.

Mica Ohms Electronic Shop Landayan S.P.L.

Nichrome wire Ohms Electronic Shop Landayan S.P.L.

Battery Ohms Electronic Shop Landayan S.P.L.

Charger Ohms Electronic Shop Landayan S.P.L.

Wire Ohms Electronic Shop Landayan S.P.L.

Jack Ohms Electronic Shop Landayan S.P.L.

Connector Ohms Electronic Shop Landayan S.P.L.

Stirrer Ohms Electronic Shop Landayan S.P.L.

Push Button Switch Ohms Electronic Shop Landayan S.P.L.


On/Off Switch Ohms Electronic Shop Landayan S.P.L.

Silicon Ohms Electronic Shop Landayan S.P.L.

Screws Ohms Electronic Shop Landayan S.P.L.

Direct Labor Requirements

Hiring the right people to the right job is very essential. The qualifications must be meeting by the

people applying for the job specification.

Plant Lay-out
Executive Q.C Office
Office Sales and
Marketing
Marketing

Waste Disposal Management

Having a proper waste disposal for company is a very important aspect that a company must have

because not everything the company been make is a finished product. Some product will be rejected ,

rework and others will become waste. So therefore we consider recycling and waste management

system as a resource management system. Also to Ensure that consumers and nearby neighbors and

employees will not be harmed by the wastes of the company. Some of the wastes of company could be

stainless steel, metal, batteries, wires and etc. This materials can cause serious injury when not isolated

properly or been put to its own proper waste disposal. Having this kind of Management system will not

only focus on the consumers and nearby neighbor and employees but also to reduce the over all system

cost of product that needed to be recycled or rework.

Utilities

The company electric power supply will be coming from MERALCO and Prime water district to cater the

needs and requirements for employee usages and cleaning purposes that will be supplied by the Prime
Water district in San Pedro City, Laguna. Other miscellaneous things like Internet, Wifi, Internet lines for

Executive use, Administrative purposes, Purchases and other purposes will come directly from PLDT.

These primarily services provide the needs for the operation of the company

Das könnte Ihnen auch gefallen