Sie sind auf Seite 1von 20

Road Planning Process

Road Planning
Process

2 | Road Planning Process


Road Planning
Process
The following is a summary of the highway ments, or the negative impacts caused by traffic
(i.e. state road) planning process – what are its cannot be reduced enough.
phases and what can be done to achieve the best
result? Reasons to improve existing highways and con-
struct new ones include the following:
Why Highways Are Improved and
Constructed • Increased mobility/travel due to residential,
Improving an existing highway is preferred to the work place and service developments.
constructing a new one. Highways are improved • Requirements better serve the transport needs
to meet general traffic needs, to eliminate or of industrial and commercial activities.
reduce negative impacts caused by traffic or when • Increasing mobility during working hours and
changes in land use so require. A new highway free time and growth of the car fleet.
shall be constructed when the existing highway • Need to make highways safer and reduce negative
network no longer meets the requirements of impacts on the environment caused by traffic.
traffic or land use, and these requirements cannot • Aim to improve pedestrian and bicycle traffic
be satisfactorily met or eliminated through road conditions, and the use of public transport.
improvements or other transport system develop- • Aim to improve traffic mobility.

Highways are
improved and built
to increase traffic
safety, among
other things.

Road Planning Process | 3


Co-operation is
necessary between
the different
parties involved in
planning.

Who Plans and Constructs Highways? for traffic, land use and areas are all integrated.
Highway planning is based on the Highway Act Co-operation is therefore necessary between the
and Decree, and other legislation concerning land different parties involved in planning.
use planning. Road maintaining and planning involves
The state is responsible for maintaining planning of maintenance, upkeep and develop-
and planning highways. The Finnish Transport ment of the highway network. It is based on
Agency acts as the responsible organisation at goals set by the Ministry of Transport and Com-
state level. The Centres for Economic Develop- munications, resulting in plans and programmes
ment, Transport and the Environment (EDTE to achieve these goals. These in turn direct
Centres) are regional-level authorities. The EDTE actions within different segments, such as the
Centre commissions the planning, construction planning of road projects.
and maintenance of highways from companies Road management programmes are
offering such services. drawn up in co-operation with the other parties
In addition to highways maintained by the involved in community planning. There are pro-
state, there are streets in urban areas, construct- grammes with three time scales: long-term plan
ed and maintained by the municipalities. In addi- (LTP, 10 to 30 years), operational and financial
tion, many private roads exist, especially in rural plan (OFP, 4 years) and an annual implementa-
areas, which are the responsibility of shareholders tion plan based on the state budget.
or the owner of the real estate in question. Major road network development projects
are drawn up in a centralised manner, with
Road Planning as Part of Road Network Parliament making implementation decisions
Management during budget debates. Other road projects are
Road planning is part of community planning. drawn up in the regional Centres for Economic
It is part of a planning system in which plans Development, Transport and the Environment.

4 | Road Planning Process


Transport system Land use planning
planning

Feasibility studies

Decision to start
planning

EIA
Preliminary engineering planning Impact
assessment
Approval decision

Final engineering planning

Approval decision

Implementation stage
Construction planning and construction

Commissioning

Impact
Maintenance and upkeep monitoring

Henkilö­liikenteestä
93 prosenttia ja
Road planning is part of
tavaraliikenteestä
community planning.
68 prosenttia
kulkee teillä.

Road Planning Process | 5


The Phases of
Road Planning

6 | Road Planning Process


The Phases of
Road Planning
The planning of road projects is a process becom- • Preliminary engineering planning corre-
ing more detailed stage by stage. At each stage, sponds to land use planning on the level of a
the level of planning accuracy and decision- local master plan or a local detailed plan. A
making is adapted in accordance with land use preliminary engineering plan determines the
planning. approximate location and space requirement
The planning process has four stages: of the road and its relation to the surrounding
feasibility study, preliminary engineering plan- environment.
ning, final engineering planning and construction • Final engineering planning is planning at the
planning. In minor road projects with limited same level of detail as local land use plans.
impacts, planning and decision-making stages • Construction planning is related to the imple-
can be combined. mentation of a road project and is performed
When a new highway or the improvement before and during construction.
of an existing highway is planned, the planning
must be based on a land use plan meeting the In different phases of the planning process, alter-
requirements of the Land Use and Building Act. natives are reduced as road planning becomes
Road planning phases are connected to land use more accurate. As the process progresses, plan-
planning as follows: ning can be more and more focused.
For the public and other parties to the plan-
• At the feasibility study phase, the necessity ning process, it is important to participate in the
and timing of road projects are studied at the planning at the right time. Planning can also be
same approximate planning level as the re- interrupted, if sufficient reasons no longer exist to
gional land use plan and the local master plan. continue the planning process.

A road project is given its form and Dividing project-specific planning into
details during a planning process which phases makes specifying the order and
becomes more and more detailed in time of road project implementation
phases, adjusted to correspond to land easier.
use planning.

Road Planning Process | 7


TRANSPORT SYSTEM PLANNING
Transport system planning, road network planning,
development planning, location study
Road planning

Dialog with PRELIMINARY FINAL ENGINEERING


interest groups ENGINEERING Dialog with involved
Extensive dialog parties

CONSTRUCTION
PLANNING

Goals for further Approval of the plan Approval of the plan Construction
planning
Land use planning

REGIONAL GENERAL PLANNING TOWN PLANNING Construction


PLANNING Compiled and Compiled and
Compiled and approved by the approved by the
approved by the municipality. municipality.
regional council. Road location is
Ratified by the approved in the plan.
Ministry of
Environment.

For the public and other parties


to the planning process, it is
important to participate in the
planning at the right time.

8 | Road Planning Process


Feasibility Study
Planning a transport system involves interactive The outcome of the feasibility study is a project
planning of land use and traffic. Thus, a frame- or several projects for which preliminary examina-
work is created for the arrangement of different tions have been conducted of possible alternative
traffic modes and land use. Planning gener- actions, including the related impacts and costs.
ates traffic policy objectives and goals, network During the feasibility study, the need for interac-
plans for different traffic modes, implementation tion varies according to the nature of the project.
strategies for the system and assessments of the Participation by municipalities and regional coun-
impacts. More detailed plans for pedestrian and cils are usually emphasised during co-operation.
bicycle traffic, public transport, parking etc. are The decision to begin planning can be made
made when needed. based on the feasibility study. Such a decision
Transport system plans have been drawn consists of the road authority’s statements con-
up for many urban areas and some provinces. In cerning the necessity, timing and further planning
smaller urban areas, the planning emphasis is of development actions. Actions deemed neces-
usually on traffic network planning. sary proceed for further development and imple-
For various purposes, feasibility studies mentation. The related timetables are determined
can have different names and content. The most according to the funding available.
common project-specific feasibility studies are
the development study, needs assessment and
development/action plan.
The starting points of a feasibility study are Outcomes of feasibility studies:
existing land use and current road and traffic con- • goals
ditions. Societal development causes changes in • alternatives
travel needs and traffic conditions. These changes • approximate actions
are examined during the feasibility study phase • preliminary impact assessments
and the actions required to meet the goals set for • cost forecasts
the development of traffic conditions are planned.

Uusi jk+pp
Uusi suojatie
Nopeusrajoituksen alentaminen
Nykyinen jk+pp
Nykyinen linja-autopysäkki
Nykyinen suojatie

Road Planning Process | 9


Preliminary Engineering Plan
Preliminary engineering planning determines the other construction activities and impose an obli-
approximate location of the road, the road’s con- gation on the road authority to expropriate areas.
nections to the existing and future road network In general, principles approved in the preliminary
and land use, basic technical and traffic solutions engineering plan are usually no longer discussed
and the principles underlying the prevention of in the final engineering planning phase. Custom-
negative impacts to the environment. Planning is arily, when the final engineering plan is eventu-
performed at a level of detail which ensures that ally submitted for processing, solutions already
the plan is technically, financially and environ- approved in principle are no longer subject to
mentally feasible. When legislation requires an change through objections or appeals.
environmental impact assessment (EIA), the
road project’s environmental impact is assessed
according to the Act on Environmental Impact
Assessment Procedure during the preliminary Outcomes of preliminary
engineering planning phase. engineering planning:
The approval decision is made on the • approximate location of the road
preliminary engineering plan. The project can • basic traffic and road engineering
then be included in near-future implementation solutions
programmes (the Finnish Transport Agency’s • principles underlying the landscaping
operating and financial plan, the programmes of of the road side and the handling
the Centres for Economic Development, Transport of green areas
and the Environment). • principles underlying the prevention of
Because the location and quality of the high- negative impacts on the environment
way and the highway’s impacts on people’s living • impact assessment
conditions and the environment are determined in • cost estimate
the preliminary engineering plan, this phase has • target timetable and stages of
the most important effect on the road project. An construction
approved preliminary engineering plan may limit

10 | Road Planning Process


Impacts of the Road Project
The impacts of the road project are assessed in all planning phases when alternatives are
being decided upon, compared and chosen. Such assessments are considered in the final pre-
liminary engineering plan and when making decisions on further planning.
Impact assessment requires many-sided co-operation between road planners, munici-
palities and environmental authorities, and experts in various fields.
The Act on Environmental Impact Assessment Procedure is always applied in motorway
and semi-motorway construction projects, and when a project entails the construction of
a continuous road over 10 km in length and with four or more traffic lanes (also applies to
realignment and widening projects). The Act is also applied in individual cases when the EIA
coordinating authority so separately decides in the case of road projects which are likely to
cause a negative environmental impact of a significant level and extent.

Final Engineering Construction Plan


Plan Construction planning belongs to the road
Final engineering planning determines the pre- construction phase and covers the drafting of
cise location of the highway, areas required for the the documents required for construction. In
highway, intersections of highways and private many cases, the contractor is often responsible
roads and solutions for other road connections, for drawing up the construction plan. Within
solutions for pedestrian and bicycle traffic and limits of the final engineering plan, interaction
public transport, and other detailed solutions between road constructors and landowners and
such as measures necessary to the prevention of other concerned parties continues throughout the
negative traffic impacts. Because the final engi- entire planning and construction phase. In minor
neering plan settles all issues directly affecting projects, the final engineering and construction
land owners and other parties concerned, interac- planning phases can be combined.
tion is focused on issues to be agreed with them. Compensation is paid for any damage caused
The approval decision is made on the final to external property during final engineering or
engineering plan, allowing the road authority the construction planning and construction.
right to take possession of the area required for the
highway. It is sometimes necessary to make a revi-
sion plan to an approved final engineering plan. This
process is similar to the original plan, unless the im-
pact of the change is so minor that agreement with
real-estate owners is sufficient. Once financing has
been ensured, highway construction can be started.

Outcomes of final engineering Outcome of construction


planning: planning:
• precise road area • documents required in construction
• detailed solutions
• cost estimate and possible division of costs

Road Planning Process | 11


Road Planning
Terminology

Public Road Survey


Compensation is paid for any losses, impediments and damage caused by the implementation of the
road project. Voluntary agreements are preferred on the expropriation of residential buildings and build-
ings essential for business.
Compensation for the land area required for road construction, detours or other impediments caused
by the road, and any damage, are settled in the public road survey carried out by the National Land Sur-
vey of Finland.
A separate brochure on land expropriation and compensation issues describing the survey proce-
dure, compensation and payment in more detail is available from Centres for Economic Development,
Transport and the Environment and District Survey Offices.

12 | Road Planning Process


Road Planning Terminology

Highways Level of service


Roads maintained and planned by the State A description of the road’s traffic conditions
Motorways Horizontal alignment
Highways with dual carriageways for motorised The location of the road (route) on a map or in the
traffic terrain
Semi-motorways Vertical alignment
Highways with a single carriageway for motorised The road’s height relative to the ground surface
traffic (longitudinal section in the plans)
Main roads I class Alignment
Roads belonging to the main national road Horizontal and vertical alignment together
network
Curve radius
Main roads II class Half of the diameter (radius) of the circle forming
Roads complementing the main road network a curve in the road
Regional roads Channelised intersection
Roads connecting municipal centres The driving directions in the intersection are
Connecting roads separated by road markings and/or raised traffic
Roads collecting traffic from rural areas islands

Pedestrian and bicycle ways Roundabout (traffic circle)


Roads or road areas for pedestrian and bicycle Turning only to the right
traffic Interchange
AADT A traffic connection between roads intersecting at
Annual average daily traffic different levels via a ramp

SADT Noise impact area


Average daily traffic during the summer The average traffic noise exceeds a certain limit
(June-August) value (e.g. 55 dB) in this area

Roundabout

Underbridge
Lateral clearance area

Drainage ditch
Ramp

Channelizing Drainage
Lateral
island ditch
clearance area
iNoise bank
Pedestrian Noise barrier Road area: right to expropriate the area
and bicycle Shoulder Traffic Traffic Turning
way lane lane lane Buffer zone: no new buildings
Lateral clearance area: no barriers which
Road way
pose a hazard to road safety

Road Planning Process | 13


Interaction
Interaction
Road planning is interactive co-operation in all This interaction allows stakeholders, parties
phases of planning. The parties, scope and con- concerned and citizens to participate in and affect
tent of interaction depend on the planning phase planning, while interaction also serves as a means
and the nature of the project: to obtain information required for planning. The
goal of interaction is to find solutions which are
• At the feasibility study phase, the main focus acceptable to all parties involved in planning. The
is on co-operation between organisations earlier the interaction begins during the planning
• During the preliminary engineering plan- phase , the better the results achieved. In this
ning phase, the co-operating parties include way, it is easier to consider various proposals and
municipalities, regional councils, environmental viewpoints.
authorities and other planning organisations, Information on the planning of road projects
land owners, local residents, entrepreneurs and is also available on the websites of the Finnish
various civic organisations. Extensive interac- Transport Agency and Centres for Economic
tion is especially important during preliminary Development, Transport and the Environment
engineering planning in particular, since the www.fta.fi and www.ely-keskus.fi.
most important basic project solutions are
decided in this phase.
• During the final engineering planning phase,
the interaction mostly deals with details and,
in addition to the municipalities, the parties
include the land owners, residents and entre-
preneurs in the vicinity of the road.

Extensive interaction
is especially important
during preliminary
engineering planning.

Road Planning Process | 15


The Administrative Processing
of Road Plans
Statements and opinions are requested from The Finnish Transport Agency approves prelimi-
various parties on the solutions identified during nary and final engineering plans. For particular
planning and on the proposed plan, to form the reasons, the Finnish Transport Agency may trans-
basis for decision-making during the administra- fer the plans for approval by the Ministry of Trans-
tive processing of the plans. The procedures in port and Communications, which also approves
different planning phases are as follows: plans concerning the discontinuation of a road.
The plan formed during the planning and the
• Feasibility studies: statements are acquired, administrative process does not always satisfy
if the estimated impacts are significant and/or everyone. For this reason, it is possible to appeal
wide-scale. For many road projects, information against a decision to approve a preliminary or final
is distributed on only the basic solutions and engineering plan, to an administrative court and/
the decisions made. or the supreme administrative court.
• Preliminary and final engineering plans: the
administrative processing follows the procedure
stipulated in the Road Act and Decree. This
includes public notifications in the specified
format, keeping the plan available for public
viewing, providing an opportunity to lodge
objections and requesting statements.

Henkilö­liikenteestä
The administrative
93 prosenttia
processing ja
follows the
tavaraliikenteestä
procedure stipulated in
68
theprosenttia
Road Act and Decree.
kulkee teillä.

16 | Road Planning Process


ECONOMIC DEVELOPMENT, Requests for statements
TRANSPORT AND THE
ENVIRONMENT CENTRE
• Preliminary or final NATIONAL BOARD OF
MUNICIPALITY: plan for public
engineering plan ANTIQUES
viewing, objections to the plan
OTHER AUTHORITIES
REGIONAL COUNCIL
OTHER ORGANISATIONS
ECONOMIC DEVELOPMENT,
TRANSPORT AND THE Statements
ENVIRONMENT CENTRE Objections (Statement if necessary)
• Processing of statements and
objections
• Plan revisions
• Proposal for approval MUNICIPALITY: decision for public viewing
STATEMENT DELIVERERS
Decision OBJECTORS
OTHER AUTHORITIES
FINNISH TRANSPORT
AGENCY • Parties concerned have the right
• Approval decision, or transfer to appeal against the decision
to the Ministry of Transport
and Communications
MINISTRY OF TRANSPORT Appeal against Appeal
AND COMMUNICATIONS the decision against
made by the the decision
Transport made by
Agency the Ministry
No appeals
ADMINISTRATIVE COURT
Plan is legally valid (not
appealed against / decision Decision
by administrative court / Further appeal
supreme administrative
court), or the plan needs THE SUPREME
revising Decision ADMINISTRATIVE COURT

Road Planning Process | 17


Co-operation
Is Important
Co-operation
Is Important
The starting point of road improvement and con- ning. In many cases, information on larger road
struction is to promote the possibilities for travel planning projects can also be found in newspaper
and transportation, while increasing traffic safety articles and the websites of the Finnish Transport
and making the travel environment more pleas- Agency and the Centre for Economic Develop-
ant. The pros and cons of the road project are ment, Transport and the Environment.
weighed up during the various planning phases,
in order to identify solutions which allow the goals You can affect planning through the following:
to be achieved as economically as possible. • Personal discussion with the planners.
You can participate in achieving a good result • Contacting municipality officials and decision-
by bringing up important issues during plan- makers (usually members of the co-operation
ning. The announcement of the planning phase is groups).
usually publicly notified in newspapers, including • Active participation in associations, organisa-
information on the subject of the planning, as well tions etc. representing your interests.
as the parties and persons responsible for plan-

The pros and cons of


the road project are
weighed up during
the various planning
phases.

Road Planning Process | 19


www.fta.fi
www.ely-keskus.fi

October 2010

Das könnte Ihnen auch gefallen