Beruflich Dokumente
Kultur Dokumente
net/publication/320960678
CITATIONS READS
0 9,837
1 author:
Mohamed Darwish
The American University in Cairo
44 PUBLICATIONS 59 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Mohamed Darwish on 09 November 2017.
Requests a detailed
proposal on how the work Request
will be accomplished,
who will do it, etc. for Proposal
(RFP)
sometimes called request for tender
Requests a
price quote
Requests one per item,
price to do all hour, etc.
the work
Invitation Request
for Bid For Quotation
(IFB) (RFQ)
The choice of which type of procurement document to use depends on
the form of scope of work and contract type selected. 2
1
3
2
Types of Costs
3
7
4
9
5
Direct labor Estimate
11
12
6
Facilities and Equipment Estimate
13
Engineering Estimate
14
7
Important Issues in Estimating
1- Estimating should be based on a WBS to improve
accuracy
2- Estimating should be done by the person doing the
work
3- Having historical records is a key element in improving
estimates
4- Costs(schedule, scope, resources) should be managed
to estimates
5-Costs(schedule, scope, resources) should be kept and
not changed
6-Plans should be revised, as necessary, during
completion of the work
7- Corrective action should be taken when cost problems
(schedule, scope, resources) occur. 15
(a)
1 2 3 4 5 6 7 8 9 101112
WBS Level 5 WBS Level 2
Rolling Wave
(b) or
(c)
(d) Moving
(e)
(f) Window 16