ATASAMENT

1. BETON
a. FUNDATIE
i. FUNDATIE 1
Lfundatie1 = 12.23m
Afundatie1 = 1.10m * 3.00m = 3.30mp
Vfundatie1 = 12.23m * 3.30mp = 40.36mc
ii. FUNDATIE 2
Lfundatie2 = 1.13m
Afundatie2 = 1.10m * 1.60m = 1.76mp
Vfundatie2 = 1.13m * 1.76mp = 1.99mc
b. ELEVATIE
Lelevatie = 13.55m
Aelevatie = (0.50m + 1.20m) / 2.00 * 1.95m = 1.6575mp
Velevatie = 13.55m * 1.6575mp = 22.46mc
Vbeton, total = 40.36mc + 1.99mc + 22.46mc = 64.81mc ≈ 64.80mc
Transport beton: 64.80mc * 2.40 to/mc = 155.52 to
2. ARMATURA
M1 (Φ14): 12(buc/m) * 8.10(m/buc) * 12.23(m) = 1188.76m
M2 (Φ14): 12(buc/m) * 3.70(m/buc) * 13.36(m) = 593.18m
M3 (Φ14): 12(buc/m) * 1.90(m/buc) * 13.55(m) = 308.94m
M4 (Φ14): 12(buc/m) * 5.30(m/buc) * 1.13(m) = 71.87m
M5 (Φ14): 12(buc/m) * 1.10(m/buc) * 13.55(m) = 178.86m
Rep (Φ8): 35(buc/m) * 1.00(m/buc) * 12.23 (m) = 428.05m
Rep (Φ8): 22(buc/m) * 1.00(m/buc) * 1.13 (m) = 24.86m
Rep (Φ8): 16(buc/m) * 1.00(m/buc) * 13.55 (m) = 216.80m
Total Φ14mm = 1188.76 + 593.18 + 308.94 + 71.87 + 178.86 = 2341.61 ml
2341.61ml * 1.21 kg/ml = 2833.35 kg
Total Φ8mm = 428.05 + 26.86 + 216.80 = 669.71 ml
669.71ml * 0.395kg/ml = 264.53 kg
Total Otel beton tip PC52: 2833.35kg + 264.53kg = 3097.88kg

pag. 1
ATASAMENT
3. Cofraje

Lelevatie = 13.55m

H elevatie = 1.95m

Aelevatie = 1.66mp

Cofraj = 13.55m * 1.95m * 2.00 + 1.66mp + 0.50mp = 52.84mp + 1.66mp + 0.50mp = 55.00mp

4. Zidarie uscata

L = 12.42m

H = 1.00m

B1 = 1.20m

B2 = 1.38m

A = 1.00 * (1.2 + 1.38) / 2 = 1.29mp

V = 12.42m * 1.29mp = 16.02mc ≈ 16.00mc

5. Material granular

L = 12.43m

H = 0.70m

B1 = 1.38m

B2 = 3.00m

A = 0.70 * (1.38 + 3.00) / 2 = 1.533mp

V = 12.43m * 1.533mp =19.06 ≈ 19.00mc

pag. 2