AKS
17.02.2015
ZBR/90/W/--------CD/MS/004
Contract N. 210/2011/NR/ZU
Alstom Middle East, FZE, Dubai, UAE.
Vendor logo and business name Vendor Identification
002519-MS-Civil-SAS-AP-001
Order N. 210/2011/NR/ZU
SHAMS AL SABAH GENERAL CONTRACTING CO. LTD.
Facility Name Location Scale Sheet of
ZUBAIR-PERMANENT POWER GENERATION ONSHORE N.A. Sheets
1/6
Document Title Supersedes N.
REVISION HISTORY
This document is property of eni Iraq BV.
It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Logo & Doc. Number Company Logo & Doc. Originator Logo & Doc. AP Revision Index Sheet of
Number Number Rev. Sheets
No. Validity Rev.
Status No.
3/6
Alstom Middle East, FZE.
eni Iraq b.v.
C EX-CO 01
002519-MS-Civil-
ZBR/90/W/--------CD/MS/004 00251900DAST66716
SAS-AP-001
Table of Contents
7. REINFORCEMENT......................................................................................................................... 4
This document is property of eni Iraq BV.
It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Logo & Doc. Number Company Logo & Doc. Originator Logo & Doc. AP Revision Index Sheet of
Number Number Rev. Sheets
No. Validity Rev.
Status No.
4/6
Alstom Middle East, FZE.
eni Iraq b.v.
C EX-CO 01
002519-MS-Civil-
ZBR/90/W/--------CD/MS/004 00251900DAST66716
SAS-AP-001
1. OBJECTIVE
This document specifies method statement for the production, transporting and installing of
precast Concrete T-Walls for Zubair permanent Generation Unit.
2. SCOPE OF APPLICATION
To be applied on Zubair Permanent Power Generation Unit.
3. REFERENCE DOCUMENT
00251900DADB61003 - T-Wall – Section & reinforcement Details -PPG
5. CONCRETE WORKS
Grade of Concrete shall be as specified in the drawing of respective pre-cast elements. For
concrete mix proportion shall be an established mix proportion being used by T- wall supplier.
6. STEEL MOULD/FORMWORK
Mould shall be made from mild steel. Shape shall be as per construction drawing. The mould shall
be suitably laid on face for T-walls. Prior to pouring any concrete, the formwork must be
thoroughly cleaned and moistened with water. All inner surfaces of moulds shall be coated with
acid-free special oil for de-shuttering.
7. REINFORCEMENT
This document is property of eni Iraq BV.
It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Logo & Doc. Number Company Logo & Doc. Originator Logo & Doc. AP Revision Index Sheet of
Number Number Rev. Sheets
No. Validity Rev.
Status No.
5/6
Alstom Middle East, FZE.
eni Iraq b.v.
C EX-CO 01
002519-MS-Civil-
ZBR/90/W/--------CD/MS/004 00251900DAST66716
SAS-AP-001
8. CONCRETING
In general concrete placement and compaction will follow what is stipulated in document no.
00251900DAST66717 (Method Statement for Civil works –PPG). The concrete will be poured
starting from the wall toe by filling up the upstanding part of the mould first then to the other end.
The exposed surface shall be troweled to smooth finish.
Before pouring the concrete painted lifting hooks to be fixed in the right position as per
construction drawing.
9. CURING
Curing shall be as per document no. 00251900DAST66717 (Method Statement for Civil works –
PPG). Curing for T-Wall will be in 2 stages. Initial curing will be before shifting from the mould for
2 days, and then it will continue after shifting to the stock yard for next 5 days to ensure full curing. 01
Transportation shall be in two stages, first shall be from casting yard to stock yard and to be kept
there till complete curing is done. T-walls shall be stored on flat surface.
In both stages all safety measures shall be taken in consideration especially during lifting.
Quality checks for T-wall shall be performed according to Inspection & Test Plan for T-Wall – PPG
(document no. 00251900DASS75051). 01
12.1 Unloading of T-wall at site shall be done at designated areas using lifting devices and
method as identified in subsequent points.
12.2 Verify the T- wall as per the quality check list identified in item- 11.T-walls not matching
the quality check list requirement to be marked as ‘rejected’ on both the faces.
12.3 Prior to installation, all preparatory works must be completed including survey work for
setting out, preparation of ground surface.
12.4 Installation shall be directly from flat loader of second transporting by lifting the T wall and
placing it on the prepared surface.
12.5 Crane of minimum capacity of 30 tons shall be used for lifting operations.
This document is property of eni Iraq BV.
It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Logo & Doc. Number Company Logo & Doc. Originator Logo & Doc. AP Revision Index Sheet of
Number Number Rev. Sheets
No. Validity Rev.
Status No.
6/6
Alstom Middle East, FZE.
eni Iraq b.v.
C EX-CO 01
002519-MS-Civil-
ZBR/90/W/--------CD/MS/004 00251900DAST66716
SAS-AP-001
12.6 Lifting slings shall be of minimum 5 tons capacity and to be fixed at 45o to horizontal.
12.7 Appropriate safety measures shall be followed e.g. proper safety gears, certified crane &
crane operator and rigger as per permit to work.
12.8 Before installation, offset line using lime to be established to ensure the alignment and
straightness.
12.9 The installation shall be from one end of any T wall line, from somewhere halfway or
corner then subsequent installation can continue both sides concurrently.
12.10 Alignment will be checked after placing each piece of T-wall to ensure compliance with T-
wall layout plan 00251900DADB61002.
12.11 Site access road for the movement and parking of cranes shall be ensured at site before
starting erection.
12.12 All works shall comply with safety procedure as per the project safety plan.