Beruflich Dokumente
Kultur Dokumente
Issue 11
Date 2017-01-20
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Website: http://e.huawei.com
Intended Audience
This document describes hardware features of the AC and provides basic installation methods.
This document is intended for:
l Network planning engineers
l Hardware installation engineers
l Commissioning engineers
l Onsite maintenance engineers
l System maintenance engineers
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol Description
Symbol Description
Change History
Changes between document issues are cumulative. The latest document issue contains all
changes made in previous issues.
Issue 11 (2017-01-20)
This version has the following updates:
Issue 10 (2015-07-15)
This version has the following updates:
The section 4.1 Logging In to the AC Through the Console Port is optimized.
Issue 09 (2015-05-18)
This version has the following updates:
Issue 08 (2014-12-05)
This version has the following updates:
AC6005's 2.1.5 Ordering Information and AC6605's 2.2.6 Ordering Information are
added.
Issue 07 (2014-01-15)
This version has the following updates:
Issue 06 (2013-09-30)
This version has the following updates:
Issue 05 (2013-06-30)
This version has the following modified:
The figure of 2.2.2.3 500 W AC PoE Power Supply is replaced.
Issue 04 (2013-05-30)
This version has the following updates:
A warning is added in 3.4.1 Scenario 1: Installing a Device in a Cabinet/Rack.
Issue 03 (2013-05-15)
This version has the following updates:
The following information is modified:
4 Logging in to the Device
Issue 02 (2012-07-30)
This version has the following updates:
The full name of AC6605 is provided.
Issue 01 (2012-05-30)
Initial commercial release.
Contents
3 Device Installation...................................................................................................................... 36
3.1 Installation Procedure................................................................................................................................................... 37
3.2 Preparing for Installation.............................................................................................................................................. 37
3.2.1 Reading Carefully the Safety Cautions..................................................................................................................... 37
3.2.2 Checking the Installation Site....................................................................................................................................39
3.2.3 Checking the Cabinet/Rack....................................................................................................................................... 40
3.2.4 Checking the Power Supply System..........................................................................................................................40
3.2.5 Preparing Installation Tools and Accessories............................................................................................................ 40
3.3 Unpacking a Device......................................................................................................................................................43
3.4 Installing the Device..................................................................................................................................................... 44
3.4.1 Scenario 1: Installing a Device in a Cabinet/Rack.................................................................................................... 44
3.4.2 Scenario 2: Installing a Device on a Desk................................................................................................................. 49
3.4.3 Scenario 3: Installing the Device on a Wall...............................................................................................................51
5 Hardware Failures....................................................................................................................... 76
5.1 Power Supply Failures..................................................................................................................................................77
5.1.1 A device Fails to Be Powered On..............................................................................................................................77
5.1.2 The PWR Indicator Is Steady On.............................................................................................................................. 77
5.2 Memory Failures...........................................................................................................................................................78
5.2.1 Failed to Write Data to the SD Card or USB Flash Drive.........................................................................................78
5.3 Interface Faults............................................................................................................................................................. 78
5.3.1 An Optical Interface Cannot Turn Up....................................................................................................................... 78
6 Appendix....................................................................................................................................... 81
6.1 On-site Cable Assembly and Installation..................................................................................................................... 82
6.1.1 Cable Assembly Precautions..................................................................................................................................... 82
6.1.2 Assembling Power Cables......................................................................................................................................... 83
6.1.2.1 Assembling a DC 2-Pin Round Connector (A)...................................................................................................... 83
6.1.2.2 Assembling a DC 2-Pin Round Connector (B)...................................................................................................... 87
6.1.2.3 Assembling the OT Terminal and Power Cable..................................................................................................... 93
6.1.2.4 Assembling the JG Terminal and Power Cable...................................................................................................... 97
6.1.2.5 Assembling the Cord End Terminal and the Power Cable..................................................................................... 99
6.1.3 Assembling Ethernet Cables....................................................................................................................................102
6.1.3.1 Assembling the Shielded RJ45 Connector and Ethernet Cable............................................................................102
6.1.3.2 Assembling an Optimized Shielded RJ45 Connector and SFTP Network Cables...............................................108
6.1.3.3 Assembling an Integrated Shielded RJ45 Connector and SFTP Network Cables................................................112
6.1.3.4 Assembling a Shielded RJ45 Connector and an FTP Network Cable..................................................................116
6.1.3.5 Assembling an Unshielded RJ45 Connector and Ethernet Cable.........................................................................121
6.1.3.6 Checking the Appearance of Contact Strips.........................................................................................................123
6.1.3.7 Testing the Connection of Assembled Cables...................................................................................................... 126
6.1.3.8 Common Network Cable Faults and Preventive Measures.................................................................................. 129
6.1.4 Assembling Feeders.................................................................................................................................................130
6.1.4.1 Assembling the Straight Male Coaxial N Connector and the 1/2'' Feeder........................................................... 130
6.1.4.2 Assembling a Straight Male Coaxial N Connector and an RG8U Feeder............................................................134
6.1.5 Installing Cable Accessories....................................................................................................................................140
6.1.5.1 Precautions for Installing Cable Accessories....................................................................................................... 140
6.1.5.2 Installing Power Adapters.................................................................................................................................... 141
6.1.5.2.1 Installing the OT Terminal.................................................................................................................................141
6.1.5.2.2 Installing the Cord End Terminal...................................................................................................................... 144
6.1.5.2.3 Installing a 2-Pin Round Connector and a DC Power Cable.............................................................................145
6.1.5.3 Installing Ethernet Adapters................................................................................................................................. 148
6.1.5.3.1 Installing a Shielded Ethernet Connector.......................................................................................................... 149
6.1.5.3.2 Installing an Unshielded Ethernet Connector.................................................................................................... 150
6.1.5.4 Installing Fiber Connectors.................................................................................................................................. 152
6.1.5.4.1 Cleaning Fiber Connectors................................................................................................................................ 152
6.1.5.4.2 Installing an FC Fiber Connector...................................................................................................................... 152
6.1.5.4.3 Installing an LC Fiber Connector...................................................................................................................... 154
6.1.5.4.4 Installing the SC Fiber Connector..................................................................................................................... 156
6.1.5.4.5 Installing an MPO Connector............................................................................................................................ 157
6.1.6 Replacing the Mold of the Crimping Tool...............................................................................................................159
6.2 Environmental Requirements for Device Operation.................................................................................................. 162
6.2.1 Environmental Requirements for an Equipment Room.......................................................................................... 162
6.2.1.1 Requirements for Selecting a Site for an Equipment Room.................................................................................162
6.2.1.2 Equipment Room Layout......................................................................................................................................163
6.2.1.3 Construction Requirements for the Equipment Room......................................................................................... 164
6.2.1.4 Equipment Room Environment............................................................................................................................ 165
6.2.1.5 Requirements for Corrosive Gases....................................................................................................................... 166
6.2.1.6 Requirements for ESD Prevention....................................................................................................................... 167
6.2.1.7 Electromagnetism Requirements for the Equipment Room................................................................................. 167
6.2.1.8 Requirements for Lightning Proof Grounding..................................................................................................... 167
6.2.2 Requirements for Power Supply..............................................................................................................................170
6.2.2.1 Requirements for AC Power Supply.................................................................................................................... 170
6.2.2.2 Recommendations for AC Power Supply.............................................................................................................171
6.2.2.3 Requirements for DC Power Supply.................................................................................................................... 172
6.2.2.4 Recommendations for DC Power Supply.............................................................................................................172
6.3 Equipment Grounding Specifications.........................................................................................................................173
6.3.1 General Grounding Specifications...........................................................................................................................173
6.3.2 Grounding Specifications for an Equipment Room................................................................................................ 173
6.3.3 Grounding Specifications for Devices.....................................................................................................................173
6.3.4 Grounding Specifications for Communications Power Supply...............................................................................174
6.3.5 Grounding Specifications for Signal Cables........................................................................................................... 175
6.3.6 Specifications for Laying Out Grounding Cables................................................................................................... 175
6.4 Engineering Labels for Cables................................................................................................................................... 176
6.4.1 Introduction to Labels..............................................................................................................................................176
Before starting service deployment for a WLAN project, use WLAN network planning tools
to plan for the network. Lack of proper network planning may cause the following problems:
l Coverage holes exist in the WLAN network. STAs cannot receive radio signals in the
coverage holes and therefore cannot connect to the network.
l WLAN devices provide strong signal coverage but severely interfere with each other. As
a result, STAs can receive radio signals but fail to connect to the WLAN network or
encounter severe packet loss. This results in a poor user experience.
l The WLAN network is unstable, which severely affects network services.
To ensure normal operations of the WLAN network, you must follow instructions in this
section to plan for AP locations and configuration data of the entire network. Huawei offers
comprehensive network planning tools. You can use these tools to conduct site survey and
network planning by following the instruction videos. First install a single AP to check
whether the network performance is consistent with the network plan you have made.
l WLAN Overview
l WLAN Planning and
Optimization Overview
l Clarifying Customer
Requirements
l WLAN Data Planning
l WLAN Architecture Design
l Indoor WLAN Design
Guide
l WLAN Outdoor Coverage
l WLAN Roaming Planning
l WLAN Network Planning in
Typical Scenarios
l WLAN WDS Mesh Log in to Huawei enterprise technical
WLAN Planning support website and search for
Training
l WLAN Network Design WLAN Training.
Overview
l WLAN Design for Small-
and Medium-scale
Enterprises
l WLAN Design for Large-
scale Enterprises
l WLAN Optimization
Overview
l WLAN Interference
Optimization
l Introduction to WLAN
Tester
l WLAN Optimization in
Different Industries
Describes the AP
WLAN Pre-
models and
sales Network Log in to Huawei enterprise technical support
installation
Planning & website and search for WLAN Pre-sales Network
recommendations
Installation Planning & Installation Notice.
for different
Notice
scenarios.
Describes the AP
parameters,
AP Hardware installation methods, Log in to Huawei enterprise technical support
Installation and how to log in to an website and search for Hardware Installation
Maintenance AP, precautions for and Maintenance Guide of the desired AP
Guide AP installation, and models.
methods to rectify
AP hardware faults.
Describes antenna
parameters,
Antenna Quick Log in to Huawei enterprise technical support
installation methods,
Start website and search for Antenna Quick Start.
and precautions for
antenna installation.
Networki Set names for APs according to the network plan to facilitate network
1
ng design maintenance.
Networki Use different VLANs as the service VLAN and management VLAN of
2
ng design an AP to prevent WLAN services from being affected by other services.
N Categor
Recommendation
o. y
Network Manually specify appropriate channels for APs or enable automatic radio
planning calibration.
5 and In V200R006 and later versions, the automatic radio calibration is
optimizat enabled by default. The default radio calibration interval is 1440
ion minutes.
Network
planning
Configure proper transmit power for APs. Too strong signals will cause
6 and
interference, whereas too weak signals will reduce the coverage area.
optimizat
ion
Some STAs cannot roam to APs with higher signal strength when the
Network RSSI values of their home APs drop. Forcible disconnect such STAs
planning from the home APs to enable them to associate with APs with better
7 and signal quality.
optimizat In V200R006 and later versions, it is recommended that smart roaming
ion be configured to enable STAs to associate with APs with better signal
quality.
Version
8 Upgrade WLAN devices to latest versions to obtain better performance.
upgrade
When upgrading an AP, ensure that the file name and size of the software
Version package loaded to the AP are the same as those of the software package
9
upgrade saved on the file server. It is recommended that digital verification be
performed on the software package.
When configuring the WDS service, properly set the parameters related
Service to coverage distance to ensure good link quality; configure leaf AP
11 configura whitelist to control APs' connection to the network; configure AP
tion interfaces to allow service VLANs to enable communication between
leaf and root APs.
Service
In V200R005 and earlier versions, to use 802.1x authentication, enable
12 configura
802.1x authentication globally.
tion
Service
In V200R005 and earlier versions, configure a default domain and a
13 configura
forcible domain when 802.1x authentication is used.
tion
Service
When configuring Portal authentication, configure an authentication-free
14 configura
rule to allow access to the DNS server before authentication.
tion
N Categor
Recommendation
o. y
Service
When configuring Portal authentication, set the security policy to non-
15 configura
authentication and non-encryption.
tion
Service
When configuring Portal authentication, set the same authentication port
16 configura
on the Portal server and AC.
tion
Service
When configuring Portal authentication, ensure network connectivity
17 configura
between STAs and the authentication server.
tion
Service
The encryption key configured on the AC must be the same as that on
18 configura
the RADIUS or Portal server.
tion
Service Reduce the number of retransmissions after a packet sending failure and
21 configura remove low rates from the basic rate set to mitigate non-Wi-Fi
tion interference.
Service You are advised to configure smart roaming on the device to ensure
22 configura network experience of STAs with low roaming aggressiveness and
tion enable them to connect to APs with better signals.
Service
When a large number of users connect to the network, configure user
24 configura
isolation and port isolation.
tion
Service When a large number of 2.4G terminals exist on the network, enable the
25 configura band steering function to enable 5G-capabile terminals to preferentially
tion connect to the 5G radio and reduce the burden on the 2.4 GHz radio.
Service
In multi-user scenarios, enable airtime fair scheduling to ensure that
26 configura
wireless channel resources are allocated to users fairly.
tion
N Categor
Recommendation
o. y
If multiple SSIDs are bound to an AP, set a larger interval for sending
Beacon frames.
Service
In most cases, set the interval to the half of the number of bounded
27 configura
SSIDs multiplied by 100. For example, if four SSIDs are bound to an AP,
tion
set the interval for sending Beacon frames to 200 ms (4/2 x 100).
It is recommended that the interval be set from 100 ms to 500 ms.
N Categor
Recommendation
o. y
In a scenario where rooms are on both sides of the corridor, you are
advised to deploy indoor distributed APs or wall plate APs in the rooms
Networki to implement indoor coverage. Alternatively, you can deploy indoor
32 settled APs in the rooms in W-shaped mode.
ng design
Do not deploy indoor settled APs in a corridor, nor in two rooms facing
each other on both sides of the corridor.
For outdoor equipment, all feeders, power cables, network cables, and
fiber connectors must be waterproofed.
l Feeder connectors and power cable connectors must be completely
Networki wrapped using one layer of PVC insulation tape, three layers of
33
ng design waterproof tape, and three layers of PVC insulation tape. Each layer
of tape should be wrapped tightly and bundled securely with binding
straps.
l Network cables and optical fibers use waterproof PG connectors.
N Categor
Recommendation
o. y
Surge protection measures are mandatory for deploying outdoor APs and
Networki antennas to prevent device damage and service interruption due to
34
ng design lightning. Deploy outdoor AP within the 45-degree protection area of the
lightning rod and connect the APs to the nearest ground points.
2 Device Overview
2.1 AC6005
2.2 AC6605
2.1 AC6005
Table 2-1 and Table 2-2 show the appearance of the AC6005.
Model Appearance
AC6005-8 1 2 3 3 4 5
HUAWEI 1 2 3 4 5 6 7 8
PWR
SYS
STAT
SPED
7 8
CONSOLE
MODE
AC6005-8
AC6005-8- 1 2 3 3 4 5
PWR
HUAWEI 1 2 3 4 5 6 7 8
PWR
SYS
STAT
SPED
7 8
PoE CONSOLE
MODE
AC6005-8-PWR
Model Appearance
AC6005-8 6 7
~100-240V;50/60Hz;2A
AC6005-8- 6 7
PWR
~100-240V;50/60Hz;2A
No. Description
4 Console port.
5 USB port.
6 Ground point.
7 AC power jack.
Attribute Description
Connector RJ45
Network protocol IP
Combo Port
A pair of combo port consists of an optical Ethernet port and an electrical Ethernet port on the
panel. Each combo port matches only one internal forwarding port. A combo port is a
multiplexing port, and you can use either the optical port or electrical port at one time. When
one of the Ethernet ports is used, the other port is disabled.
NOTE
You can configure a combo port as an electrical or optical port using the combo-port command. By
default, a combo port works in auto mode, in which the port type is determined as follows:
l If the optical port has no optical module installed and the electrical port has no network cable
connected, the port type depends on which port is connected first. If the electrical port is connected
by a network cable first, the electrical port is used for data switching. If the optical port has an
optical module installed first, the optical port is used for data switching.
l If the electrical port has a network cable connected and is in Up state, the electrical port is still
used for data switching even when the optical port has an optical module installed.
l If the optical port, no matter in Up or Down state, has an optical module installed, the optical port
is still used for data switching even when the electrical port has a network cable connected.
l If the optical port has an optical module installed and the electrical port has a network cable
connected, the optical port is used for data switching after the switch restarts.
Console Port
The console port is connected to an operation terminal for on-site configuration. The port
must use a console cable. To configure the device after the first power-on, log in to the device
through the console port. Table 2-4 lists attributes of a console port.
Connector RJ45
Standard RS-232
compliance
USB Port
The USB port is used to connect USB disks for configuration file transfer and file upgrade.
The USB flash drive used on AC6005 must comply with USB 2.0 and support the Linux
operating system.
NOTE
To ensure compatibility between USB flash drives and devices, use Huawei-certified USB flash drives (listed
in the following table) to configure the Huawei devices.
SanDisk Cruzer Blade Huawei does not offer this USB flash
drive, and you need to buy it from other
vendors.
HUAWEI 1 2 3 4 5
1 PWR
2 SYS
STAT
SPED
PoE
345 MODE
AC6005-8-PWR
7 7
HUAWEI 1 2 3 4 5 6 7 8
PWR
SYS
STAT
SPED
7 8
PoE CONSOLE
MODE
AC6005-8-PWR
NOTE
6 Mode - AC6005-8-PWR:
switching l When you press the button once, the
button: SPED indicator turns green and the
MODE service port indicators indicate the speed
of the ports.
l When you press the button for a second
time, the PoE indicator turns green and
the service port indicators indicate the
PoE status of the ports.
l When you press the button for a third
time, the STAT indicator turns green.
AC6005-8:
l When you press the button once, the
SPED indicator turns green and the
service port indicators indicate the speed
of the ports.
l When you press the button for a second
time, the STAT indicator turns green.
If you do not press the button within 45
seconds, the indicators restore to the default
mode. That is, the STAT indicator turns
green, and the SPED and PoE indicators are
off.
2.2 AC6605
Currently, the AC6605 only has one model AC6605-26-PWR (AC6605 for short).
Figure 2-2 and Figure 2-3 show the appearance of the AC6605.
PoE
MODE
AC6605-26-PWR 1 4
No. Description
No. Description
6 Console port.
8 Ground point.
9 Filler panel.
10 Two slots for the power supplies. The AC6605 supports three types of power
supplies:
l 2.2.2.1 150 W DC Power Supply
l 2.2.2.2 150 W AC Power Supply
l 2.2.2.3 500 W AC PoE Power Supply
NOTE
The built-in USB interface of the AC6605 is unavailable for use. No operation regarding the USB circuit
is defined on software. There is no plan for using the interface function on the product model.
NOTICE
l Only the AC6605 supports power modules.
l Power off the AC6605 before removing the power supplies. Do not operate the power
supplies when the device is running.
l Before powering off the AC6605, shut down all its power supplies.
Function
The 150 W DC power supply provides +12 V DC power. It has the following functions:
l Various alarms, for example, the alarm triggered when there is no power input, the alarm
for the circuit breaker status, the alarm for ineffective surge protection, and the alarm for
undervoltage input.
ON
RTN(+)
STATUS OFF
NEG(-)
PWR150D -48 -60V;6A
Technical Specifications
Table 2-10 describes the technical specifications of the 150 W DC power supply.
Weight 0.84 kg
Function
The 150 W AC power supply provides the EMC filtering function and protects the device
against:
l Output overcurrent
l Output overvoltage
l Output undervoltage
l Input overvoltage
l Input undervoltage
l Overtemperature
l Short circuit
l Surge
ON
STATUS OFF
~100-240V;
PWR150A 50/60 Hz;3A
Table 2-11 describes the meanings of the 150 W AC power supply indicators.
Technical Specifications
Table 2-12 describes the technical specifications of the 150 W AC power supply.
Item Value
Weight 0.84 kg
Item Value
Function
Power over Ethernet (PoE) refers to power supply over a 10Base-T, 100Base-TX, or
1000Base-T twisted pair cable.
PoE provides power for terminals such as IP phones, APs, portable device chargers, point-of-
sale (POS) machines, cameras, and data collectors. These terminals are powered when they
access the network, so the indoor power supply systems are not required. Complying with
IEEE 802.3af and IEEE 802.3at, the PoE is able to remotely provide power for the devices of
different vendors. IEEE 802.3af supports a maximum of 15.4 W power and IEEE 802.3at
supports a maximum of 30 W power.
The PoE function transmits power together with data to terminals over cables or transmits
power without data over idle lines. The AC6605 can transmit power together with data at a
rate of up to 1000 Mbit/s.
Technical Specifications
Table 2-14 describes the technical specifications of the AC PoE power supply.
Weight 1 kg
Item Value
NOTE
A PoE power supply provides 12 V voltage for the entire device and -53.5 V voltage for PDs.
Attribute Description
Connector RJ45
Network protocol IP
Combo Port
A pair of combo port consists of an optical Ethernet port and an electrical Ethernet port on the
panel. Each combo port matches only one internal forwarding port. A combo port is a
multiplexing port, and you can use either the optical port or electrical port at one time. When
one of the Ethernet ports is used, the other port is disabled.
NOTE
You can configure a combo port as an electrical or optical port using the combo-port command. By
default, a combo port works in auto mode, in which the port type is determined as follows:
l If the optical port has no optical module installed and the electrical port has no network cable
connected, the port type depends on which port is connected first. If the electrical port is connected
by a network cable first, the electrical port is used for data switching. If the optical port has an
optical module installed first, the optical port is used for data switching.
l If the electrical port has a network cable connected and is in Up state, the electrical port is still
used for data switching even when the optical port has an optical module installed.
l If the optical port, no matter in Up or Down state, has an optical module installed, the optical port
is still used for data switching even when the electrical port has a network cable connected.
l If the optical port has an optical module installed and the electrical port has a network cable
connected, the optical port is used for data switching after the switch restarts.
Attribute Description
Standards IEEE802.3
compliance
Console Port
The console port is connected to an operation terminal for on-site configuration. The port
must use a console cable. To configure the device after the first power-on, log in to the device
through the console port. Table 2-17 lists attributes of a console port.
Attribute Description
Connector RJ45
Attribute Description
Standard RS-232
compliance
Standards IEEE802.3ae
compliance
Network protocol IP
10
9 11
32 1
HUAWEI 1 2 3 4 5 ETH CONSOLE
PWR1
PWR2
SYS
STAT
SPED
PoE
456 MODE
AC6605-26-PWR 1 2
7
8
PoE
MODE
AC6605-26-PWR 1 2
10 Mini USB Green l Off: The Mini USB port is not active,
indicator and the console port is active.
l Steady on: The Mini USB port is
active.
When this indicator is on, the console
port indicator is off.
3 Device Installation
Start
Prepare for
installation
Install modules
End
Installation and maintenance personnel must be trained to perform operations correctly and
safely.
DANGER
In case of fire, immediately leave the building or equipment deployment site and press the fire
alarm button or call the fire department. Never enter the building on fire again in any
situation.
CAUTION
l Before performing any operation on a device, wear ESD clothing and ESD gloves or an
ESD wrist strap. Remove conductive objects like jewelry and watches.
l After installing the device on the cabinet/rack, connect the ground cable to the chassis
before any operations on the chassis and remove the ground cable only after you remove
all the other components and cables from the chassis.
Environmental Safety
DANGER
Do not place or operate the device in an environment with flammable or explosive gases or
smoke.
CAUTION
l Keep the device away from water or damp to prevent damages to circuits.
l The device heats during operation. The installation site must be well ventilated to ensure
normal operation of the device.
Electric Safety
DANGER
l Direct contact with a high-voltage power source or indirect contact through damp objects
can be fatal. Misoperations on high-voltage facilities may result in fire, electric shock, or
other accident.
l Never install or remove the device or power cables while the power is on. The electric arc
or spark generated between a power cable and conductor may cause fire or eye damage.
l To protect personal and equipment safety, ground the device before powering it on.
Laser Safety
CAUTION
l Invisible laser beams will cause eye damage. Do not look into open optical ports without
eye protection.
l After unplugging an optical fiber, cover the fiber connectors with dust caps.
Mechanical Safety
CAUTION
l Wear gloves to protect your hands from sharp edges when you are moving the chassis.
l Before carrying a heavy object, use appropriate tools to protect yourself from bruise or
sprain.
l Before pulling the chassis out of the cabinet, check whether there are any unstable or
heavy objects on the cabinet. Be careful not to make the objects fall, which may cause
body injuries.
l Do not drill holes on a cabinet without permission. Unqualified holes on a cabinet affect
the electromagnetic filter performance of the cabinet and cause damages to the cables in
the cabinet. In addition, metal scraps may fall into the cabinet when you are drilling holes,
causing short circuit on printed circuit boards (PCBs).
The devices are used indoors. The requirements for the installation site are as follows:
l The devices must be installed in a clean, dry, well ventilated site with stable temperature.
The installation site must be free from leaking or dripping water, heavy dew, and
humidity.
l Dustproof measures must be taken in the site. Dust will cause static charges on the
chassis and affect connections of metal connectors and joints. This shortens service life
of the device and may cause failures of the device.
l The temperature and humidity in the site must be within acceptable ranges. For the
operating temperature and relative humidity ranges required by the devices, see Physical
Parameters in Device Structure. If the relative humidity exceeds 70%, use dehumidifiers
or air conditioners with dehumidification features.
l There are no acidic, alkaline, or other corrosive gases in the installation site.
l There should be sufficient space around the device for heat dissipation. Leave at least 50
mm clearance at two sides and rear of the device.
Table 3-1 shows the tools required for installing the series devices.
ESD Prevent
gloves electrostatic
charges.
ESD Prevents
wrist electrostatic
strap charges. Wear the
strap on your
wrist and insert
the other end into
the ESD jack on
the cabinet.
Measurin Measures
g tape distances.
Marker Marks
component
installation
positions and
draws lines.
Flat-head Fastens or
screwdri loosens small-
ver sized screws and
(M4/M6) bolts. It is seldom
used to fasten
nuts.
Phillips Fastens or
screwdri loosens small-
ver sized screws and
(M4/M6) bolts. It is seldom
used to fasten
nuts.
Table 3-2 shows the installation accessories required for installing the series devices.
Context
NOTE
If you find the package of a device is damaged, stop unpacking and contact the supplier. If all packages
are intact and the number of packages is correct, unpack the packages to check the equipment and
components.
l Take ESD protection measures to protect the equipment from electrostatic charges.
l It is recommended that you move the carton of a device near the installation position
before unpacking (if space is sufficient). Moving an unpacked device over a long
distance may cause damages to the device.
l If a device is found eroded or damped, stop unpacking, check for the reason, and contact
the supplier.
l Wear gloves or take other protection measures to prevent hand injuries when unpacking a
carton.
l When cutting the adhesive tape on a carton, do not insert the utility knife too deep;
otherwise, the utility knife may cut the components in the carton.
l Keep the cartons safe for future transpiration of the devices.
Tools
The following tools are used:
l ESD gloves
l Utility knife
Procedure
Step 1 View the label on the carton to confirm the device model and learn about precautions to take.
Step 2 Use a utility knife to cut the pressure-sensitive adhesive tape around the cover of the carton.
Step 3 Open the carton and take out the package of installation accessories.
Step 4 Remove the foam materials and take out the device.
Step 5 Take the device out of the plastic bag and check whether the nameplate on the chassis is
consistent with the label on the carton.
----End
NOTICE
l The AC series products are class A products. Customers should take preventative
measures as the operating devices may cause radio interference.
l Before the installation, take ESD protection measures, for example, wear ESD gloves or
an ESD wrist strap.
l There should be sufficient space around the device for heat dissipation. Leave at least 50
mm clearance at two sides and rear of the device.
l When fixing the chassis onto a cabinet/rack with mounting brackets, ensure that the
mounting brackets are kept in a horizontal line in the mounting holes on the left and right
mounting rails. If the mounting brackets are not in a horizontal line, do not install the
chassis with force. Or the chassis may be distorted.
Procedure
Step 1 Install the AC6005.
1. Install front mounting ears. Install the front mounting ears on two sides of the panel with
ports.
NOTE
The AC6005 requires only front mounting ears which are delivered with the chassis.
M4
1.2N•m
NOTICE
The distance between two chassis must be at least 1 U.
>=1U M6
M6
3N•m
4. Connect the M4 connector of the PGND cable to the chassis and the M6 connector to a
ground point. The PGND cable is in yellow and green.
M4
1.2N•m
1. Install two front and two rear mounting ears on the AC6605. Install the front mounting
ears near the front panel with interfaces and the rear mounting ears near the rear panel
with power supplies.
M4
M4
1.2N•m
Floating nut
mounting bar
M6
When installing a device in a cabinet/rack, install guide rails for rear mounting ears
depending on the distance between front and rear mounting rails. For details, see Table
3-3.
375 mm to
454 mm
507 mm to
566 mm
4. Align the rear mounting ears with guide rails and insert the chassis in the the cabinet or
rack among the guide rails.
5. Hold the chassis while secure the front mounting ears to the supports using a
screwdriver. Then fix the rear mounting rears to the guide rails.
----End
NOTICE
l Before the installation, take ESD protection measures, for example, wear ESD gloves or
an ESD wrist strap.
l Ensure that the desk is flat and properly grounded.
l There should be sufficient space around the device for heat dissipation. Leave at least 50
mm clearance at two sides and rear of the device.
l Do not place other objects on the device.
Procedure
Step 1 Wear an ESD wrist strap or ESD gloves.
Ensure that the ESD wrist strap is grounded and in a close contact with your wrist.
Step 2 Attach the rubber pads to the bottom of the device.
Slowly turn the device upside down, and then attach four rubber pads in the imprinted round
areas at the bottom of the chassis. See a in Figure 3-2.
Step 3 Place the device on the desk.
Turn the chassis over and gently place the chassis on the desk. See b in Figure 3-2.
a
b
----End
NOTICE
l Only the AC6005 series products support wall mounting installation.
l Take ESD protection measures before the installation, for example, wear ESD gloves or an
ESD wrist strap.
l Ensure that the equipment room is dry, well-ventilated, and has good heat dissipation.
l When installing multiple fan-free or intelligent-heat-dissipation devices in a cabinet or
rack, leave at least 1 U distance between each two.
l Leave at least 50 mm clearance at two sides and rear of each chassis for heat dissipation.
l A wall for installing the device needs to meet the following requirements:
l The wall can bear the weight of four times the total weight of the device and
mounting bracket without damage.
l When the tightening torx of a screw reaches 1.5 N•m, the screw still properly works,
without crack or damage on the wall.
l Phillips screwdriver
l Flat-head screwdriver
l Marker
l Hammer drill
l M4 screws
l Expansion screws
l Mounting brackets
Procedure
Step 1 Fix mounting ears to both sides of the panel with ports using M4 screws.
M4
1.2N•m
Step 2 Use a marker to mark the positions of mounting holes according to the size of the chassis and
positions of the mounting ears. You are advised to install the device at a position that is 1700
mm higher above the floor but lower than 2500 mm to facilitate maintenance and observation
of indicators.
1700mm ≤ h ≤ 2500mm
φ8 drill bit
90°
2. Insert expansion bolts into the holes and screw the nuts to fasten the expansion bolts.
5N•m
----End
Context
Grounding is a key step in device installation. The ground cable of a device must be correctly
connected to protect the device from lightning, electromagnetic interference, and electrostatic
charges.
The ground cable can be connected to a ground point on the cabinet/rack or a ground bar,
depending on the situations in the installation site. The following procedure connects the
ground cable to a ground point on the cabinet/rack.
NOTE
If a cabinet or rack has anti-rust coating, scrape off the paint around the ground point to ensure reliable
grounding.
Procedure
Step 1 Wear an ESD wrist strap or ESD gloves.
Ensure that the ESD wrist strap is grounded and in a close contact with your wrist.
Step 2 Remove the M4 screw from the ground point on the device.
Loosen the M4 screw counterclockwise with the Phillips screwdriver, as shown in Figure 3-3.
Keep the M4 screw for later use.
Step 3 Connect the ground cable to the ground point on the device.
Fix the M4 lug (with a smaller hole) of the ground cable to the ground point on the device
with the M4 screw you removed in step 2, and use the Phillips screwdriver to fasten the M4
screw clockwise. See Figure 3-4.
Figure 3-4 Connecting the ground cable to the ground point on the device
Figure 3-5 Connecting the ground cable to a ground point on the cabinet
----End
Context
The power modules must be installed onsite. They are hot swappable. The procedure for
installing a DC power module is the same as that for installing a AC power module. The
following provides installation of a AC power module.
NOTICE
l Only the AC6605 supports power modules.
l When installing a battery, battery charger module, or power module, slowly push it into
the slot. If you feel resistance or find the module inclined, pull the module out and push it
into the slot again. Do not push the module with force; otherwise, the connectors on the
module and backplane may be damaged.
l If the battery slot is empty, install a filler panel to ensure efficient heat dissipation.
l The batteries and power modules for the device are hot swappable. Before removing the
battery or power module from a device, ensure that the internal power supply unit of the
device is working normally. Otherwise, services on the device will be interrupted due to a
power failure after the battery or power module is removed.
l Do not put your fingers into the battery slot when installing or removing a battery or
power module.
Procedure
Step 1 Wear an ESD wrist strap or ESD gloves.
Ensure that the ESD wrist strap is grounded and in a close contact with your wrist.
Step 2 Take out a power module from the box.
Verify that the delivered power module is the model you need.
Step 3 Remove the filler panel from the battery slot at the rear of the device, as shown in Figure 3-6.
1. Use the Phillips screwdriver to loosen the captive screw on the filler panel
counterclockwise.
2. Pill the filler panel out by the handle.
Keep the filler panel for future use.
Figure 3-6 Removing the filler panel from the battery slot
Step 4 Install the power module in the battery slot, as shown in Figure 3-7.
1. Hold the handle on the power module with one hand and support the bottom of the
power module with the other hand. Horizontally push the power module into the slot
until it is completely in the slot.
2. Use the Phillips screwdriver to fasten the captive screw on the power module clockwise.
----End
Context
NOTICE
l Before the installation, take ESD protection measures, for example, wear ESD gloves or
an ESD wrist strap.
l When installing the optical module, do not touch the gold finger of the optical module
without wearing gloves.
l Do not insert the optical module with optical fibers directly into the optical interface. You
need to install the optical module first and then the optical fibers.
l Cover idle optical interfaces with dust plugs.
Procedure
Step 1 Ensure that the ESD wrist strap is grounded and in a close contact with your wrist.
Step 2 Take out an optical module from the ESD bag and verify that the optical module is the model
you need.
Step 3 Install the optical module on the optical interface.
Insert the optical module into the optical interface smoothly until you hear a crack sound.
NOTICE
If an optical module cannot be completely inserted into an optical interface, do not push it
with force. Turn the optical module over and try again.
----End
Context
NOTICE
l Before the installation, take ESD protection measures, for example, wear ESD gloves or
an ESD wrist strap.
l Power cables must be buried underground or routed indoors and cannot be led into the
equipment room aerially.
l Do not install power cables while the power is on.
l Do not power on a device before you finish installing the device and connecting cables.
l Each device has an AC power cable delivered as an accessory. The AC power cable can
only be used on the device in the same package and cannot be used on any other device.
Procedure
Step 1 Wear an ESD wrist strap or ESD gloves.
Ensure that the ESD wrist strap is grounded and in a close contact with your wrist.
Step 2 Turn off the external power supply system.
c. Connect the other end of the AC power cable to the external power supply system.
l If a DC power module is used, perform the following steps to connect the DC power
cables.
a. Use the Phillips screwdriver to loosen the screw on the protection cover of the DC
terminals and remove the protection cover.
b. Use the Phillips screwdriver to remove the screws on the two DC terminals.
c. Attach the DC power cables to the DC power module and use the screws you just
removed to secure the power cables. The black cable is the -48 V return ground
cable and must be connected to the RTN(+) terminal on the DC power module. The
blue cable is the -48 V power cable and must be connected to the NEG(-) terminal
of the DC power module.
d. Cover the DC terminals with the protection cover and fasten the screw on the
protection cover with the Phillips screwdriver.
----End
Follow-up Procedure
Complete post-installation check before powering on the device. For the post-installation
checklist, see 3.8 Checking the Device After Installation. For the procedure for powering on
the device, see 3.9 Powering on a Device for the First Time.
Context
CAUTION
Invisible laser beams will cause eye damage. Do not look into open optical ports without eye
protection.
NOTICE
l Before the installation, take ESD protection measures, for example, wear ESD gloves or
an ESD wrist strap.
l Keep signal cables more than 10 cm away from power cables.
l To prevent damages to wires in cables or fibers, do not over bend cables or optical fibers.
l Optical fibers routed in a cabinet must be protected by a corrugated pipe. The bend radius
of an optical fiber must be 20 times larger than its diameter. Generally, the bend radius of
optical fibers should be no less than 40 mm.
l Before connecting an optical fiber, check whether its connector is contaminated. If so, use
an air-laid cotton or a fiber cleaner to clean the fiber connector.
Operation Suggestions
Pay attention to the following points when binding cables or optical fibers:
l Cables or optical fiber must be bundled at equal intervals. Bundle cables or optical fibers
in a cabinet at less than 250 mm intervals.
l Do not bundle cables especially optical fibers too tight.
l Cover idle fiber connectors with dust caps and cover idle optical ports with dust plugs.
l Wrap redundant optical fibers, power cables, and network cables neatly so that you can
find required cables easily during maintenance.
l Cable connectors made onsite must be securely attached, reliable, neat, and comply with
related regulations.
When a large number of cables need to be connected, arrange the cables in the cabinet, and
then install cable connectors. Figure 3-9 shows connected cables and optical fibers.
NOTE
This figure is only for reference. The actual layout of cables and optical fibers in a cabinet depends on
the installation scenario and interfaces used in the device.
9 Each signal cable has labels attached at both ends, with View
clear text facing the same direction.
10 The power cables and ground cable are all copper wires, View
and are not spliced or damaged. The cables are reliably
connected in compliance with regulations.
13 The power cables and ground cable are separated from View
the signal cables.
14 The power cables and ground cable are routed straightly View
and bundled neatly. Leave sufficient slack at the bent
part of the cables.
18 No signal cables are near the heat vents on the cabinet. View
19 Cables in the cabinet are not crossed and cables outside View
the cabinet are bundled.
Procedure
Step 1 Check the device before powering it on.
1. Check that the external power supply system connected to the device and the power
module or battery installed on the device are both turned off.
2. Check that the power cables are correctly connected.
3. Use a multimeter to check that there is no short-circuit condition between the phase wire
(also called the live wire), ground cable, and neutral wire.
4. Use the multimeter to check that the input voltage provided by the external power supply
system is within the operating voltage range for the device. For the operating voltage
range required by the series devices, see Physical Parameters in Device Structure.
MODE
S5700-28P-LI-BAT 1G/STACK-5G
RJ-45
DB-9
NOTE
You can connect the device to the maintenance terminal using the console cable. For details, see 4.1
Logging In to the AC Through the Console Port. When the device is starting, you can choose whether
to enter the BIOS menu. The BIOS menu and the procedure for entering the BIOS menu vary according
to software versions. For details about the BIOS menu, see BIOS Menu.
l Whether the sound of fans can be heard and air is exhausted from the air vent.
l Whether the indicators on the device and power module are in normal state. Normally,
the PWR indicator on the device and the STATUS indicator on the power module are
steady green.
NOTE
l To check whether the device is running properly after it is powered on, check the STATUS indicator
on the power module and the PWR and SYS indicators on the device.
l For the indicator states and meaning of each state, see Indicator Description in Device Structure.
l After the device is powered on and completes the startup, the command line interface (CLI) is
displayed.
----End
Follow-up Procedure
To power off the device, perform the following steps:
NOTICE
Powering off the device will interrupt all the services on the device. Exercise caution when
you perform this operation.
Procedure
Step 1 Connect the console port of the wireless controller to the COM port of a PC through console
cables.
Step 3 Set Connection type to Serial, enter COM1 or COM2 in Serial line based on the serial port
of the PC, and retain default settings for the other parameters.
After the connection is complete, enter the login password and press Enter, and you can enter
commands to configure or manage the device. On the first login, you have to reset the
password.
NOTE
The password value is a string of case-sensitive characters. It must contain at least two types of
characters, including upper-case and lower-case letters, digits, and special characters. For details, see the
information printed in the screen.
----End
l Ensuring that the IP address 169.254.1.1 and subnet mask 255.255.0.0 have been configured on
MEth0/0/1 of the AC6605 before the delivery.
l Ensuring that the IP address 169.254.1.1 and subnet mask 255.255.0.0 have been configured on VLANIF
1 of the AC6005 before the delivery, and interfaces GE0/0/1 to GE0/0/8 have been added to VLAN 1 by
default.
l Before the device is delivered, the STelnet service has been configured on the device. The STelnet
interface number is 22, and the default user name and password are respectively admin and
admin@huawei.com.
Use the SSH client software to log in to the device through STelnet from a terminal. The
third-party software PuTTY is used as an example here.
1. After the device is powered on, connect the PC's network interface to GE0/0/1 of the
device using network cables.
NOTE
3. Click Open. Enter the user name and password at the prompt, and press Enter. You have
logged in to the device. (The following information is only for reference.)
login as: admin
admin@169.254.1.1's password:
<Huawei>
NOTE
It is recommended that you change the initial user name and password after login.
NOTE
l In V200R005C00 and later versions, upon factory delivery, the Telnet server is disabled. Before
connecting to the device through Telnet from a user terminal, make sure that the Telnet service is
enabled on the device by the STelnet service.
l The Telnet protocol poses a security risk, and therefore the STelnet V2 protocol is recommended.
administrator
VLANIF 200
192.168.1.1/24 PC
SwitchB
RS-232 serial port
Ethernet Console cable
Console port
GE0/0/2 GE0/0/1
SwitchA
GE0/0/3 AC
GE0/0/1
VLANIF 100
192.168.0.1/24
AC6005:GE0/0/8
VLANIF 1
AP
192.168.0.2/24
AC6605:MEth 0/0/1
192.168.0.2/24
Configuration Roadmap
1. Log in to the AC through the console port to configure Telnet.
2. Configure a default route for the AC so that the PC and AC can communicate, meeting
the basic requirement for login using Telnet.
3. Set basic Telnet parameters so that the administrator can log in to the AC using Telnet.
1. Log in to the wired side of the AC6605 through the console port. For the method of login
through the console port, see Logging In to the AC Through the Console Port.
2. Set the device name.
<Quidway> system-view
[Quidway] sysname LSW
5. Set the level of login users 0 to 4 to 15 and set the authentication mode to AAA.
[LSW] user-interface vty 0 4
[LSW-ui-vty0-4] user privilege level 15
[LSW-ui-vty0-4] authentication-mode aaa
[LSW-ui-vty0-4] quit
[LSW] aaa
[LSW-aaa] local-user huawei password cipher huawei123
[LSW-aaa] local-user huawei privilege level 15
[LSW-aaa] local-user huawei service-type telnet
5. Set the level of login users 0 to 4 to 15 and set the authentication mode to AAA.
[AC] user-interface vty 0 4
[AC-ui-vty0-4] user privilege level 15
[AC-ui-vty0-4] authentication-mode aaa
[AC-ui-vty0-4] quit
[AC] aaa
[AC-aaa] local-user huawei password cipher huawei123
[AC-aaa] local-user huawei privilege level 15
[AC-aaa] local-user huawei service-type telnet
[AC-aaa] quit
l The IP address 169.254.1.1 and subnet mask 255.255.0.0 have been configured on VLANIF 1 of the
AC before the delivery, and GE interfaces have been added to VLAN 1 by default.
l The Telnet service is enabled on the AC before delivery, with a port 23. A default user account is
provided for Telnet login, with the user name admin and password admin@huawei.com. You are
advised to change the user name and password on your first login.
l Assign your PC an IP address on the same network segment as the default IP address of VLANIF 1,
and directly connect the PC to the AC. Then log in to the AC through the console port and configure
the Telnet service for the administrator.
1. Log in to the AC through the console port. For the method of login through the console
port, see Logging In to the AC Through the Console Port.
2. Set the device name.
<AC6605> system-view
[AC6605] sysname AC
ii. Set the type of the interface that connects AC and SwitchA to trunk. Add the
interface to the management VLAN in trunk mode.
[AC] interface Gigabitethernet 0/0/8
[AC-GigabitEthernet0/0/8] port link-type trunk
[AC-GigabitEthernet0/0/8] port trunk allow-pass vlan 1
[AC-GigabitEthernet0/0/8] quit
5. Set the level of login users 0 to 4 to 15 and set the authentication mode to AAA.
[AC] user-interface vty 0 4
[AC-ui-vty0-4] user privilege level 15
[AC-ui-vty0-4] authentication-mode aaa
[AC-ui-vty0-4] quit
[AC] aaa
[AC-aaa] local-user huawei password irreversible-cipher huawei123
[AC-aaa] local-user huawei privilege level 15
[AC-aaa] local-user huawei service-type telnet
NOTE
In V200R003C00 and later versions, The web management system is enabled on the AC before delivery.
The default IP address of the web management system is 169.254.1.1 and the mask is 255.255.0.0. The
web management system provides a default user account, with the user name admin and password
admin@huawei.com. You are advised to change the user name and password on your first login.
Assign your PC an IP address on the same network segment as the default IP address of the web
management system, and connect the PC to any one of GE interfaces. Start the web browser on the PC
and visit http://169.254.1.1 to log in to the web management system.
Procedure
Step 1 Open a web browser on a PC, and enter the management address in the format of http://
169.254.1.1 in the address bar. Ensure that the PC and AC can communicate with each other.
Then press Enter. Set the language, user name, and password. The HTTPS login URL is
displayed in the address box indicating that the system has gone to the HTTPS login page.
NOTE
You can also enter https://IP address in the address box to log in to the AC using HTTPS. HTTPS
ensures security of login information during login and security of data exchanged during subsequent
operations.
Step 2 Click Login or press Enter. The web system home page is displayed. You can manage and
maintain the . For details, see the Web-based Configuration.
----End
5 Hardware Failures
This section describes common methods for troubleshooting typical hardware faults.
5.1 Power Supply Failures
5.2 Memory Failures
5.3 Interface Faults
Fault Description
The SYS and PWR indicators of an device are both off.
Possible Causes
l The device is powered off.
l The power switch on the device is turned off.
l The power cable is not securely connected to the device.
l The power supply unit has failed.
– If the device uses a pluggable power supply, the pluggable power supply may fail.
– If the device connects to an external power source, its power adapter may fail.
– If the device has a built-in power supply, the device itself may be faulty.
Troubleshooting Procedure
1. Check whether the device is powered off.
2. Check that the power switch is on.
3. Check that the power cable is securely connected to the device.
4. Check whether the power supply is normal.
– If the device uses a pluggable power supply, replace the pluggable power supply
with a normal one. If the device is powered on, the original pluggable power supply
is faulty. Contact technical support personnel or Huawei agent and ask them to
replace the pluggable power supply.
– If the device uses a power adapter, replace the power adapter with a normal one. If
the device is powered on, the original power adapter is faulty. Contact technical
support personnel or Huawei agent and ask them to replace the power adapter.
5. If the device still cannot be powered on, the device itself is faulty. Contact technical
support personnel or Huawei agent and ask them to replace the device.
Fault Description
The PWR indicator is steady on.
Possible Causes
l The power module of the device is not properly installed.
l The pluggable power supply module on the device becomes faulty.
l The external power supply module of the device becomes faulty.
Troubleshooting Procedure
1. Install the power module properly.
2. Replace the faulty pluggable power supply module.
3. Replace the external power supply module.
Possible Causes
l The SD card or USB flash drive is not securely installed.
l The SD card or USB flash drive is corrupted.
Troubleshooting Procedure
1. Reinstall the SD card or USB flash drive.
2. Replace the SD card or USB flash drive.
NOTICE
Use a Huawei-certified SD card or USB flash drive.
If the system still fails to write data to the Huawei-certified SD card or USB flash drive,
contact technical support personnel.
Possible Causes
l The optical fiber is faulty.
l The optical module on the optical interface cannot meet the requirements.
l The optical attenuator used cannot meet the requirements.
l A combo interface is used but the interface type is not set to optical interface.
NOTE
l There are four combo interfaces GE0/0/21, GE0/0/22, GE0/0/23 and GE0/0/24 on the main
control board of the AC6605, and the four interfaces function independently.
l There are two combo interfaces GE0/0/7 and GE0/0/8 on the main control board of the AC6005,
and the two interfaces function independently.
Troubleshooting Procedure
1. Replace the optical fiber and optical module and check whether the optical interface can
turn Up. Ensure that the optical module meets the following requirements.
2. Determine optical module attributes.
– The optical module has passed Huawei certification.
– The transmission speed of the optical module is the same as the interface speed.
– Check whether the wavelength of the optical module is the same as that of the
remote optical module.
– The transmission distance of the optical module is suitable for the actual distance
between the two devices.
NOTE
If the combo interface type is electrical interface, run the combo-port auto or combo-
port fiber command to configure it as auto or optical interface.
NOTE
If the interface type is set to auto, check that the electrical interface is not Up. If the electrical interface
is Up, remove the network cables and then install the optical module.
<AC6605>system-view
Enter system view, return user view with Ctrl+Z
[AC6605]interface GigabitEthernet 0/0/24
[AC6605-GigabitEthernet0/0/24]combo-port fiber
4. Run the display transceiver command to check whether any alarms about the optical
module have been generated. If such alarms are displayed, handle the problem according
to the alarms. For example, if an alarm shows that the receive signal strength is too high,
use an optical attenuator between the remote optical module and the optical fiber.
NOTE
The attenuation coefficients of single-mode fibers with 1310 nm and 1550 nm wavelengths are 0.4
dB/km and 0.25 dB/km respectively.
5. If the interface remains Down, contact technical support personnel.
6 Appendix
The connectors, cables, and tools provided by different vendors may be different. The figures in this
document are for your reference only.
Context
Figure 6-1 shows the components of DC 2-PIN round connector A.
Procedure
Step 1 Bind a cable tie, separate the socket and nut, and install them on the cable, as shown in Figure
6-2.
Step 3 Open the clip and correctly insert the core wires to the negative and positive holes, as shown
in Figure 6-4.
Step 4 Use a Phillips screwdriver to tighten the crimping screw in "+" hole, rotate the connector by
180 degree, and tighten the crimping screw in "-" hole, as shown in Figure 6-5.
Step 5 Close the clip and tighten the screw to compact the shield layer, as shown in Figure 6-6.
Step 6 Pre-tighten the socket and enclosure and use the Phillips screwdriver to tighten the socket
with the tightening torque no less than 1.2 N•m, as shown in Figure 6-7.
Step 7 Pre-tighten the socket and nut and use the Phillips screwdriver to tighten the nut with the
tightening torque no less than 1.2 N•m, as shown in Figure 6-8.
Step 8 Use a multimeter to check the connectivity of the 2-pin round connector's cable components,
as shown in Figure 6-9.
Step 9 If devices are installed outdoor, wrap three layers of PVC insulation tape around the
connector for protection, as shown in Figure 6-10.
NOTICE
Ensure that proper quantity of the PVC insulation tape is used for wrapping the connector,
facilitating the connector uninstallation in later maintenance.
----End
Context
Table 6-1 lists power cables connected to the active antenna unit (AAU).
NOTE
The color and appearance of cables in this topic are for reference only. The cable color and appearance
vary depending on countries and regions.
Procedure
Step 1 Determine the diameter of the cable to be installed. If the diameter is larger than 14 mm,
replace the clamping jaw, as shown in Figure 6-12. During the replacement, connect the
clamping jaw boss to the groove inside the socket and ensure that the clamping jaw is
completely installed in the socket, as shown in Figure 6-13.
NOTE
1. Groove 2. Boss
Step 2 Reserve the cable length at the assembly end, bind the plastic cable tie, install the nut,
clamping jaw, and socket on the cable and pre-tighten them, as shown in Figure 6-14.
Step 3 Use the stripping ruler card to measure required lengths, strip the outer jacket (48 mm) on the
head of the cable to be connected and the outer jacket (17 mm) of each core wire, twist the
shield layers into one strand, as shown in Figure 6-15.
NOTICE
l The stripping ruler card is delivered with the components of the connector.
l Cut the padding using diagonal pliers.
l Gently strip the insulation sheath to avoid damage to the conductor metal.
l Ensure that the edge of core wires is not split.
1. Shield layer
Step 4 Connect the cable NEG (-) (gray in Britain and blue in other countries) to - end of the
connector and cable RTN (+) (blue in Britain and black/brown in other countries) to + end of
the connector. Tighten two crimping screws using the Phillips screwdriver and compact the
cable with tightening torque 1.4 N•m, as shown in Figure 6-16.
Step 5 After the cables are assembled, pull the cables slightly to check whether the connections are
secure. If the cable slides outward or the wire of the cable is exposed outside the hole for the
cable, remove the cable, cut the split wires, and then strip the jacket and install the cable
again.
Step 6 Twist the shield layers into one strand and insert it into the shield slot, tighten the tail screw,
and fasten the shielded layer with tightening torque 1.4 N•m, as shown in Figure 6-17.
1. Shield layer
NOTE
Step 7 Tighten the socket and enclosure until the red line on the socket is invisible, as shown in
Figure 6-18.
Step 8 Pre-tighten the nut and socket and further tighten the nut using a torque wrench (opening
width: 28 mm), as shown in Figure 6-19.
Step 9 Use a multimeter to check the reliability of cable components, as shown in Figure 6-20.
NOTICE
l Ensure that the short circuit does not occur between the positive and negative holes of
the connector.
l Ensure that the short circuit does not occur between the metal enclosure and connector's
positive and negative holes.
Step 10 If devices are installed outdoor, wrap three layers of PVC insulation tape around the
connector for protection, as shown in Figure 6-21.
NOTICE
Ensure that proper quantity of the PVC insulation tape is used for wrapping the connector,
facilitating the connector uninstallation in later maintenance.
----End
Context
Figure 6-22 shows the components of an OT terminal and a power cable.
Procedure
Step 1 Based on the cross-sectional area of the cable conductor, strip a length of insulation coating C
to expose the conductor D of length L1, as shown in Figure 6-23. The recommended values
of L1 are listed in Table 6-2.
NOTICE
l When you strip a power cable, do not damage the conductor of the cable.
l If the bare crimping terminal is not provided by Huawei, the value of L1 is 1 mm (0.04 in.)
to 2 mm (0.08 in.) greater than the value of L.
Table 6-2 Mapping between the cross-sectional area of the conductor and the value of L1
NOTE
If you are proficient in assembling OT terminals and power cables, you can obtain the value of L1 by
comparing the part to be crimped with the power cable.
Step 2 Put the heat-shrinkable (A) tubing onto the bare crimping terminal, as shown in Figure 6-24.
Figure 6-24 Putting the heat shrink tubing onto the bare crimping terminal
Step 3 Put the OT terminal B onto the exposed conductor, and ensure that the OT terminal is in good
contact with the insulation coating C, as shown in Figure 6-24.
NOTICE
After the conductor is fed into the OT terminal, the protruding part of the conductor, or L2 in
Figure 6-24, must not be longer than 2 mm (0.08 in.).
Step 4 Crimp the joint parts of the bare crimping terminal and the conductor, as shown in Figure
6-25.
NOTE
The shapes of crimped parts may vary with the crimping dies.
Figure 6-25 Crimping the joint parts of the bare crimping terminal and the conductor (OT
terminal)
Step 5 Push the heat shrink tubing (A) toward the connector until the tube covers the crimped part,
and then use a heat gun to heat the tube, as shown in Figure 6-26.
NOTICE
Stop heating the shrink tubing when the connector is securely locked in the shrink tubing. Do
not heat the shrink tubing too long as this may damage the insulation coating.
----End
Context
Figure 6-27 shows the components of a JG terminal and a power cable.
Procedure
Step 1 Strip a part of the insulation to expose the cable conductor with a length of L, as shown in
Figure 6-28. The recommended values of L are listed in Table 6-3.
NOTICE
l When you strip a power cable, do not damage the conductor of the cable.
l If the bare crimping terminal is not provided by Huawei, you can adjust the value of L as
required.
Table 6-3 Mapping between the cross-sectional area of the conductor and the value of L
Cross-Sectional Area of Conductor Value of L (mm(in.))
(mm2(in.2))
16 (0.025) 13 (0.51)
25 (0.039) 14 (0.55)
35 (0.054) 16 (0.63)
50 (0.077) 16 (0.63)
Step 2 Put the heat shrink tubing onto the bare crimping terminal, as shown in Figure 6-29.
Figure 6-29 Putting the heat shrink tubing onto the bare crimping terminal
Step 3 Put the bare crimping terminal onto the exposed conductor, and ensure that the bare crimping
terminal is in good contact with the insulation of the power cable, as shown in Figure 6-29.
Step 4 Crimp the joint parts of the bare crimping terminal and the conductor, as shown in Figure
6-30.
Figure 6-30 Crimping the joint parts of the bare crimping terminal and the conductor (JG
terminal)
Step 5 Push the heat shrink tubing toward the connector until the tube covers the crimped part, and
then use a heat gun to heat the tube, as shown in Figure 6-31.
----End
6.1.2.5 Assembling the Cord End Terminal and the Power Cable
Context
Figure 6-32 shows the components of a cord end terminal and a power cable.
A. Cord end terminal B. Insulation layer of a power cable C. Conductor of a power cable
Procedure
Step 1 Strip a part of the insulation to expose the cable conductor with a length of L1, as shown in
Figure 6-33. The recommended values of L1 are listed in Table 6-4.
NOTICE
When you strip a power cable, do not damage the conductor of the cable.
Table 6-4 Mapping between the cross-sectional area of the conductor and the value of L1
Step 2 Put the cord end terminal onto the conductor, and ensure that the conductor is aligned with the
edge of the cord end terminal, as shown in Figure 6-34.
NOTICE
After the conductor is fed into the cord end terminal, the protruding part of the conductor
must not be longer than 1 mm (0.04 in.).
Figure 6-34 Putting the cord end terminal onto the conductor
Step 3 Crimp the joint parts of the cord end terminal and the conductor, as shown in Figure 6-35.
Figure 6-35 Crimping the cord end terminal and the conductor
Step 4 Check the maximum width of the tubular crimped terminal. The maximum width of a tubular
crimped terminal is listed in Table 6-5.
6 (0.009) 4 (0.16)
16 (0.025) 6 (0.24)
35 (0.054) 10 (0.39)
----End
Context
Figure 6-36 shows the components of an RJ45 connector and a shielded Ethernet cable.
Procedure
Step 1 Fit the jacket of the connector onto the Ethernet cable, as shown in Figure 6-37.
Figure 6-37 Fitting the jacket of the connector onto the Ethernet cable
Step 2 Remove a 30 mm (1.18 in.) long section of the jacket, cut off the nylon twine inside the
jacket, and cut a no more than 5 mm (0.20 in.) cleft in the jacket, as shown in Figure 6-38.
NOTICE
l When you remove a section of the jacket, do not damage the shield layer of the twisted-
pair cable.
l When you remove the shield layer, do not damage the insulation of the twisted-pair cable.
Step 3 Fit the metal shell onto the twisted-pair cable. The shield layer is covered by the metal shell,
as shown in Figure 6-39.
Figure 6-39 Fitting the metal shell onto the twisted-pair cable
Step 4 Fit the metal shell onto the twisted-pair cable until the shield layer is covered completely.
Along the edge of the metal shell, cut off the aluminum foil shield layer and ensure that there
is no surplus copper wire. The exposed twisted-pair cable is about 20 mm (0.79 in.) long, as
shown in Figure 6-40.
Figure 6-40 Removing the shield layer of a twisted-pair cable (unit: mm (in.))
Step 5 Lead the four pairs of twisted-pair wires through the wire holder, as shown in Figure 6-41 and
Figure 6-42. Ensure that the colored wires are in the correct location in the cable.
G C
White-Orange
Orange
White-Green Blue
Green White-Blue
White-Brown
Brown
Step 6 Align the four pairs of cables in the holder, as shown in Figure 6-43. The connections
between the wires and the pins are shown in Figure 6-44 and listed in Table 6-6.
Pin 8
Pin 1
Table 6-6 Connections between wires and pins (using a straight-through cable as an example)
Matching Pins of Wires Wire Color
1 White-Orange
2 Orange
3 White-Green
4 Blue
5 White-Blue
6 Green
7 White-Brown
8 Brown
Step 7 Cut off the surplus cables along the lower edge of the wire holder, as shown in Figure 6-45.
Step 8 Put the connector body onto the wire holder and turn the metal shell by 90°, as shown in
Figure 6-46.
NOTE
Ensure that the wire holder is in good contact with the connector body.
Figure 6-46 Putting the connector body onto the wire holder
Step 9 Push the metal shell toward the connector body until the wire holder and the connector body
are engaged completely. Crimp the connector, as shown in Figure 6-47.
Step 10 Push the jacket towards the metal shell until the metal shell is covered. This completes the
assembly of one end of the cable, as shown in Figure 6-48.
Step 11 To complete the assembly of the other end, repeat steps 1 to 10.
----End
Context
This topic describes how to assemble an optimized shielded RJ45 connector with a Secure
File Transfer Protocol (SFTP) straight-through network cable as an example. The connector
has a cable support rack but does not have a metal jacket. Such a connector can be used for
crimping CAT. 6 network cables.
Figure 6-49 shows the shielded RJ45 connector.
1: Core 2: Aluminum foil 3: Braid 4: Outer 5: RJ45 6: Load bar 7: Cable support
wires shield jacket connector rack
Procedure
Step 1 Strip 20 mm outer jacket off the network cable, peel off the braid shield backward, and cut off
the aluminum foil and protection band, as shown in Figure 6-50.
NOTICE
Ensure that the shielded layer is intact when stripping outer jackets off the network cable.
Keep the cable insulation intact when stripping the shielded layer.
Step 2 Arrange core wires in the order of colors shown in Figure 6-51 and fix the cable support rack
to the bottom of the core wires.
Step 3 Hold the arranged core wires and route them through the load bar, as shown in Figure 6-52.
Table 6-7 shows the mapping between the core wires and pins of the connector.
Figure 6-52 Routing the core wires through the load bar
1 White-orange
2 Orange
3 White-green
4 Blue
5 White-blue
6 Green
7 White-brown
8 Brown
Step 4 After routing core wires through the load bar, move the load bar to the bottom to connect to
the cable support rack, and neatly cut the edge cables, as shown in Figure 6-53.
Step 5 Insert the load bar into the RJ45 connector, as shown in Figure 6-54.
Figure 6-54 Inserting the load bar into the RJ45 connector
NOTICE
Cables must be inserted into the bottom of the connector, which can be checked on the side or
front end face of the connector.
Step 6 Use the crimping tool to crimp the connector, as shown in Figure 6-55. Use cutting pliers to
neatly cut braid shields exposed out of the connector along the load bar, as shown in Figure
6-56.
Step 7 Repeat Step 1 through Step 6 to assemble the optimized shielded RJ45 connector on the other
end of the network cable.
----End
Context
This topic describes how to assemble an integrated shielded RJ45 connector with a Secure
File Transfer Protocol (SFTP) straight-through network cable as an example. The connector
does not have a cable support rack or metal jacket.
Figure 6-57 shows the integrated shielded RJ45 connector.
1: Core wires 2: Aluminum foil 3: Braid shield 4: Outer jacket 5: RJ45 connector
Procedure
Step 1 Strip 20 mm outer jacket off the network cable, peel off the braid shield backward, and cut off
the aluminum foil and protection band, as shown in Figure 6-58.
NOTICE
Ensure that the shielded layer is intact when stripping outer jackets off the network cable.
Keep the cable insulation intact when stripping the shielded layer.
Step 2 Arrange the twisted pair wires in the order of colors shown in Table 6-8 and cut the wire ends
neatly with 12 mm core wires left, as shown in Figure 6-59.
1 White-orange
2 Orange
3 White-green
4 Blue
5 White-blue
6 Green
7 White-brown
8 Brown
Step 3 Route the arranged core wires through the RJ45 connector, as shown in Figure 6-60.
Step 4 Use the crimping tool to crimp the connector, as shown in Figure 6-61.
Step 5 Neatly cut braid shields exposed out of the connector along the load bar, as shown in Figure
6-62.
Step 6 Repeat Step 1 through Step 5 to assemble the integrated shielded RJ45 connector on the other
end of the network cable.
----End
Context
This topic describes how to assemble a shielded RJ45 connector and File Transfer Protocol
(FTP) network cable and related notes.
A: Connector B: Connector C: Core wires of the D: Aluminum foil used as the E: Network cable
jacket twisted pair network cable shield jacket
Procedure
Step 1 Route the network cable through the connector jacket, as shown in Figure 6-66.
Figure 6-66 Routing the network cable through the connector jacket
Step 2 Strip 20 mm outer jacket off the cable and cut off the nylon layer inside the jacket, as shown
in Figure 6-67.
NOTICE
Ensure that the aluminum foil used as a shielded layer is intact when stripping outer jackets
off the twisted pair cable.
Step 3 Pull outward the shielded aluminum foil and cut off the PET membrane and ground cables
along the end face of the outer jacket, as shown in Figure 6-68.
Figure 6-68 Cutting off the PET membrane and ground cables
Step 4 Arrange the twisted core wires according to color order shown in Figure 6-69. Use cutting
pliers to neatly cut the front end of the twisted pair, as shown in Figure 6-70. Figure 6-71
shows pin arrangement of each contact of the connector.
Pin8
Pin1
Step 5 Insert the arranged four twisted pair cables into the connector, as shown in Figure 6-72.
NOTICE
l Cables must be inserted into the bottom.
l The aluminum foil must keep intact after cables are inserted into the connector.
Step 6 Use the crimping tool dedicated for FTP network cables to crimp the connector and neatly cut
the aluminum foil along the end face of the connector, as shown in Figure 6-73.
Step 7 Move the connector jacket to the connector body to wrap the connector shell, as shown in
Figure 6-74.
Step 8 Repeat Step 1 through Step 7 to assemble the shielded RJ45 connector on the other end of the
network cable.
----End
Context
Figure 6-75 shows the components of an unshielded RJ45 connector and cable.
Procedure
Step 1 Remove a 16-mm (0.63 in.) long section of the jacket, as shown in Figure 6-76.
NOTICE
When you remove the shield layer, do not damage the insulation of the twisted-pair cable.
Step 2 Align the four pairs of wires and cut the ends neatly, as shown in Figure 6-77. The
connections between the wires and the pins are listed in Table 6-9.
Table 6-9 Connections between wires and pins (using a straight-through cable as an example)
Matching Pins of Wires Wire Color
1 White-Orange
2 Orange
3 White-Green
4 Blue
5 White-Blue
6 Green
7 White-Brown
8 Brown
Step 3 Feed the cable into the plug, and crimp the connector, as shown in Figure 6-78.
NOTE
When inserting the cable, check from the side or bore of the plug to ensure that the cable is completely
seated in the plug.
----End
Context
l To ensure proper contact between the crimped wires and the wire conductors, the heights
and sizes of the contact strips must be standard and the same.
l The contact strips must be parallel to each other, with an offset of less than ± 5°. The top
margin of a strip must be parallel to the axis of the connector, with an offset of less than
± 10°.
l To ensure conductivity, the surface of the contact strips must be clean.
l The contact strips must be in good contact with the RJ45 socket. The plastic separators
must remain intact and be aligned.
l The contact strip blade must extend beyond the ends of the wires. The ends of the wires
must be in contact with the edge of the RJ45. The distance between them must be less
than 0.5 mm (0.02 in.).
Procedure
Step 1 Hold the crimped connector, with the front side facing you, and check whether the contact
strips are of the same height. The height should be 6.02 ± 0.13 mm (0.237 ± 0.005). If a
measuring tool is not available, you can compare the connector with a standard connector.
Figure 6-79 shows an unqualified piece, and Figure 6-80 shows a qualified piece.
NOTE
Step 2 Hold an RJ45 connector and turn it 45°. Observe the top edges of the metal contact strips.
Figure 6-81 shows an unqualified piece.
Step 3 Check whether the contact strips are clean. If they are not clean and the dirt cannot be
removed, replace it with a new RJ45 connector. Figure 6-82 shows an unqualified piece.
Step 4 Check whether the contact strips and the plastic separators are well aligned and intact. If a
separator is skewed and cannot be fixed, replace it with a new RJ45 connector. Figure 6-83
shows an unqualified piece.
Step 5 Hold the connector with the side facing towards you, and check whether you can see the
cross-sections of the wires. Ensure that the ends of the wires are in good contact with the edge
of the RJ45, and that the contact strip blade extends beyond the ends of the wires and is
crimped with the wires. If not, replace the connector. Figure 6-84 shows an unqualified piece.
Figure 6-84 Wires not in good contact with the edge of the RJ45
----End
Context
Huawei provides two types of Ethernet cables: straight-through cables and crossover cables.
l Straight-through cables are connected in a one-to-one manner. They are used to connect
terminals such as a computer or switch to network devices. Table 6-10 lists the
connections of core wires in a straight-through cable.
2 2 Orange Twisted
1 1 Orange-White
6 6 Green Twisted
3 3 Green-White
4 4 Blue Twisted
5 5 Blue-White
8 8 Brown Twisted
7 7 Brown-White
l Crossover cables are connected in a crossover manner. They are used to connect
terminals such as two computers or switches. Table 6-11 lists the connections of core
wires in a crossover cable.
6 2 Orange Twisted
3 1 Orange-White
2 6 Green Twisted
1 3 Green-White
4 4 Blue Twisted
5 5 Blue-White
8 8 Brown Twisted
7 7 Brown-White
Pin8
Pin1
Procedure
Step 1 Feed both connectors of the cable into the ports of the cable tester.
Step 2 After the connectors are properly inserted, turn on the tester. If the indicators from 1 to G turn
on simultaneously, you can infer that the pins work normally and the wires are correctly
connected.
NOTE
Turn the switch to the S position to slow down lighting of the indicators so that you can see the
indicators more clearly, as shown in Figure 6-86.
Step 3 Gently shake the connector and repeat Step 2 to check whether the metal contact strips are in
good contact with the core wires and Ethernet ports, as shown in Figure 6-87.
The procedure for testing a crossover cable is the same as that for testing a straight-through
cable except for the sequence in which the indicators turn on, which depends on the wire
connections of a crossover cable.
The Ethernet cable is qualified if the indicators turn on in the following sequence:
At the master (left) section of the tester, the indicators turn on in the sequence of 1-8-G. At the
slave (right) section of the tester, the indicators turn on in the sequence of 3-6-1-4-5-2-7-8-G.
If the indicators do not come on in this sequence, the Ethernet cable is unqualified.
NOTE
If a tester is not available, you can use a multimeter to perform a simple test, as shown in Figure 6-88.
----End
Table 6-12 lists common network cable faults and preventive measures.
l The device cannot be A network cable has high Before using network cables
powered using PoE. resistance or is too long. purchased from other
l The device restarts suppliers, use a multimeter
frequently. or other tools to measure
cable resistance. Replace the
l A large number of error network cables if their
packets exist on the resistance does not conform
device or services are to PoE standard
interrupted. requirements for network
cable quality.
The following methods are often used to test network cable resistance, and the test criteria are
listed in Table 6-13:
l Use a network cable tester (high-end cable tester of Fluke) to measure network cable
resistance.
l Connect multimeter probes to two ends of each wire in a network cable and check the
resistance value on the multimeter.
l Connect a network cable to an AP. Use a multimeter to test the resistance between pins 1
and 2 (or between pins 3 and 6, 4 and 5, or 7 and 8) on the other end of the cable. The
cable's DC resistance approximately equals a half of the displayed value.
802.3af ≤ 20 ohms
6.1.4.1 Assembling the Straight Male Coaxial N Connector and the 1/2'' Feeder
Context
Figure 6-89 shows the components of an N coaxial connector and a 1/2" feeder cable.
Procedure
Step 1 Cut the feeder cable, as shown in Figure 6-90.
NOTICE
l Ensure that the feeder cable is cut with reference to the guide in the package box of the
connector.
l After you cut the feeder cable, ensure that the cross-section of the outer conductor is
smooth, intact, and round.
l Ensure that the feeder cable is cut at the wave crest of the outer conductor.
l The inner conductor must be beveled, as shown in Figure 6-90.
Step 2 Use a brush to remove the dirt on the cross-section of the feeder cable.
Step 3 Feed the feeder cable into the heat-shrink tubing, and cover the outer conductor of the feeder
cable with the O-ring seal, as shown in Figure 6-91.
Figure 6-91 Installing the heat-shrink tubing and the O-ring seal
Step 4 Put the back shell of the connector onto the feeder cable. Tighten the back shell to the end of
the feeder cable, as shown in Figure 6-92.
Figure 6-92 Putting the back shell of the connector onto the feeder cable
Step 5 Mount the body of the connector onto the feeder cable so that the inner conductors of the
connector and feeder cable are connected. Use a spanner (27 N•m to 30 N•m torque
recommended) to fasten the body and back shell, as shown in Figure 6-93.
Step 6 Push the heat-shrink tubing towards the connector, as shown in Figure 6-94. Then, heat the
tube.
Step 7 After the components are assembled, install the connector, as shown in Figure 6-95.
----End
Context
Figure 6-96 shows the coaxial N connector and RG8U feeder.
E: Cable jacket F: Shielded layer of the G: Aluminum foil of the H: Insulation medium of
feeder feeder the feeder
Procedure
Step 1 Strip the feeder with the length shown in Figure 6-97.
NOTICE
Ensure that the shielded layer F is intact after the stripping.
Step 2 Route the Cable jacket (E) through the nut (D), as shown in Figure 6-98.
Step 3 Install the clip (C) on the Cable jacket (E) and move the clip until the clip is close to the Cable
jacket, as shown in Figure 6-99.
Step 4 Peel off the shielded layer (F) to the direction of the clip (C) so that the aluminum foil (G) is
exposed, as shown in Figure 6-100.
Step 5 Install the lining (B) on the feeder and tightly crimp the shielded layer (F) of the feeder, as
shown in Figure 6-101.
Step 6 Cut off the aluminum foil (G) and insulation medium (H) along the end face of the lining (B).
Ensure that the length of the conducting line inside the feeder is 4.5 mm, as shown in Figure
6-102.
Figure 6-102 Cutting off the aluminum foil and insulation medium of the feeder
Step 7 Use the file to taper the internal conductor (I) of the feeder, as shown in Figure 6-103.
Step 8 Use a brush to remove impurities from the cross section of the feeder, as shown in Figure
6-104.
Step 9 Insert the half-finished part into the main body of the connector (A) and rotate the nut (D) and
the connector's main body until you cannot rotate further, as shown in Figure 6-105.
Step 10 Use a wrench to fix the nut (D) to connector's main body (A) with recommended tightening
torque 15 N•m, as shown in Figure 6-106.
Step 11 Figure 6-107 shows the effect drawing after the assembling is complete.
----End
Tools
NOTE
The illustrations in this document may differ from actual situations, but the installation methods are the
same. For example, in this document, the adapters of cable connectors have separate interfaces. In the
actual situation, the adapters may have interfaces fixed on equipment.
Use dedicated tools provided or specified by Huawei and follow the installation procedure
described here.
Bending Radius
Unless otherwise specified, bending radius (R) of cables or fibers must meet the requirements
listed in Table 6-14.
NOTE
Procedure
l Install an OT terminal.
a. Align the hole of the OT terminal (conductor upward) with a connecting hole, as
shown in Figure 6-108.
NOTE
When you install an OT terminal, the crimping sleeve is installed as shown in Figure 6-109,
where A is correct and B is incorrect.
b. Place the spring washer and flat washer in turn, mount a matching screw, and fasten
it clockwise, as shown in Figure 6-110.
NOTICE
Ensure that the OT terminal is not in contact with other terminals or metal
components.
c. Move the cable slightly and ensure that it is securely connected, as shown in Figure
6-111.
NOTICE
If the two terminals are different sizes, place the smaller one above the bigger one. A
maximum of two terminals can be installed on a post.
Procedure
Step 1 Hold a cord end terminal upright and place it on a terminal jack, as shown in Figure 6-114. To
ensure bump contact and dense connection, place the plain side of the terminal outwards.
Step 2 Insert the terminal into the jack vertically, and turn the screw clockwise to fasten the terminal,
as shown in Figure 6-115.
NOTICE
l Ensure that the exposed section of the terminal is less than 2 mm (0.079 in.) in length.
l Do not press the insulation of the terminal.
l Insert only one terminal into one jack.
Step 3 Move the cable slightly and ensure that it is securely connected.
Step 4 Before you remove a cord end terminal, loosen the screw counterclockwise.
----End
Context
Figure 6-116 shows the 2-pin round connector with a DC power cable.
Procedure
Step 1 Waterproof cables to be connected.
1. Wrap a layer of PVC tape, as shown in Figure 6-117.
3. Wrap three layers of the PVC tape around the waterproof insulation tape, as shown in
Figure 6-120.
4. Tightly bind the PVC tape at the ends of the wrapping section, as shown in Figure
6-121.
Step 2 Fix the DC power cable connector to the PWR port, as shown in Figure 6-122. Ensure that
positive and negative polarities are correct during the installation.
NOTICE
Use the outdoor binding strap to bind cables under the DC power cable connector for weight
bearing, preventing the DC power cable connector from being pulled. Reserve the proper
cable length between the binding point and the PWR port.
----End
Procedure
Step 1 Hold the male and female connectors, with the male connector facing the female connector, as
shown in Figure 6-123.
Step 2 Insert the male connector into the female connector, as shown in Figure 6-124.
Figure 6-124 Feeding the male shielded connector into the female shielded connector
Step 3 When you hear a click, the cable connector is completely inserted in the port. (The clip on the
cable connector pops up to fix the connector in the port.) Pull the connector slightly and
ensure that it is securely connected, as shown in Figure 6-125.
Step 4 To remove an Ethernet connector, press the locking key and pull out the connector, as shown
in Figure 6-126.
----End
Procedure
Step 1 Hold the male and female connectors, with the male connector facing the female connector, as
shown in Figure 6-127.
Step 2 Feed the male connector into the female connector, as shown in Figure 6-128.
Figure 6-128 Feeding the male connector into the female unshielded connector
Step 3 A crisp click indicates that the connector is locked by the locking key. Pull the connector
slightly and ensure that it is securely connected. Figure 6-129 shows an installed Ethernet
connector.
Step 4 To remove an Ethernet connector, press the locking key and pull out the connector, as shown
in Figure 6-130.
----End
Context
NOTICE
l After you remove the dustproof cap, ensure that the fiber pins are clean and install them as
soon as possible.
l When you disassemble fiber connectors, you must use a dedicated tool if the connectors
are densely installed.
Procedure
Step 1 Clean the pins of a fiber connector by using lint-free cotton and alcohol.
Step 2 Clean the pins again by using dust-free cotton. If necessary, clean the pins by using an air gun.
Ensure that the pins are free from any fiber or debris.
----End
Procedure
Step 1 Remove the dustproof cap of the FC connector and store it for future use.
Step 2 Align the core pin of the male connector with that of the female connector, as shown in
Figure 6-131.
Figure 6-131 Aligning the male connector with the female connector
Step 3 Align the male connector with the female connector and gently push the male connector until
it is completely seated in the female connector, as shown in Figure 6-132.
Figure 6-132 Feeding the male connector into the female connector
Step 4 Fasten the locking nut clockwise and ensure that the connector is securely installed, as shown
in Figure 6-133.
Step 5 To disassemble an FC fiber connector, loosen the locking nut counterclockwise, and gently
pull the male connector, as shown in Figure 6-134.
----End
Procedure
Step 1 Remove the dustproof cap of the LC fiber connector and store it for future use.
Step 2 Align the core pin of the male connector with that of the female connector, as shown in
Figure 6-135.
Figure 6-135 Aligning the male connector with the female connector
Step 3 Align the male connector with the fiber adapter and gently push the male connector until it is
completely seated in the fiber connector, as shown in Figure 6-136.
Figure 6-136 Feeding the male connector into the female connector
Step 4 A clicking sound indicates that the male connector is locked, as shown in Figure 6-137.
Step 5 To disassemble an LC fiber connector, press the locking nut to release the locking clips from
the bore, and gently pull the male connector, as shown in Figure 6-138.
----End
Procedure
Step 1 Remove the dustproof cap of the SC fiber connector and store it for future use.
Step 2 Align the core pin of the male connector with that of the female connector, as shown in
Figure 6-139.
Figure 6-139 Aligning the male connector with the female connector
Step 3 Feed the fiber connector into the female connector, with your fingers holding the shell of the
fiber connector (not the pigtail). When you hear a click, the fiber connector is secured by the
clips (internal parts, not illustrated in the figure). Pull the fiber connector gently. If the
connector does not loosen, the installation is complete. See Figure 6-140.
Step 4 To disassemble an SC fiber connector, hold the shell of the connector (do not hold the fiber)
and gently pull the connector in the direction vertical to the adapter. Unlock the male
connector, and then separate it from the shell, as shown in Figure 6-141.
----End
Procedure
Step 1 Remove the dustproof cap of the MPO fiber connector and store it for future use.
Step 2 Align the core pin of the male connector with that of the female connector, as shown in
Figure 6-142.
Figure 6-142 Aligning the male connector with the female connector
Step 3 Hold the shell labeled "PUSH" and feed the male connector into the female connector until
you hear a clicking sound. The male and female connectors are securely installed, as shown in
Figure 6-143.
Step 4 To disassemble an MPO fiber connector, hold the shell labeled "PULL" and remove the male
connector, as shown in Figure 6-144.
----End
Procedure
Step 1 Hold the handles of a pair of COAX crimping tools. Loosen the two fastening screws
counterclockwise, as shown in Figure 6-145.
Step 2 Hold the handles of the COAX crimping tools to open the self-locking mechanism. The jaw
of the COAX crimping tools opens automatically, as shown in Figure 6-146.
Step 3 Remove the mold from the COAX crimping tools, as shown in Figure 6-147.
Figure 6-147 Removing the mold from the COAX crimping tools
Step 4 Place the mold to be installed into the jaw of the COAX crimping tools and align the screw
holes, as shown in Figure 6-148.
NOTICE
Keep the short side of the mold inwards and the long side outwards, with the teeth of the mold
aligning from the larger size to the smaller size.
Step 5 Hold the handles of the COAX crimping tools tightly to match the mold and the jaw
completely. Align the screw holes, as shown in Figure 6-149.
Step 6 Hold the handles of the COAX crimping tools with one hand. Tighten the two fastening
screws clockwise. Figure 6-150 and Figure 6-151shows the mold installed in the COAX
crimping tool.
----End
Construction, structure, heating and ventilation, power supply, lighting and fire-proof
construction of the equipment room should be designed by specialized construction designers
to suit the environmental requirements of devices. The equipment room should also follow
local regulations concerning the industrial construction, environmental protection, fire safety,
and civil air defense. Construction must conform to government standards, regulations, and
other requirements.
The equipment room should be located in a place free from high temperature, dust, toxic
gases, explosive materials, or unstable voltage. Keep the equipment room away from
significant vibrations or loud noises, as well as power transformer stations.
The specific requirements for selecting a site for an equipment room are as follows:
l The room should be located at a distance of at least 5 km (3.11 mi.) from heavy pollution
sources such as smelting and coal mines. It should be located at a distance of at least 3.7
km (2.30 mi.) from moderate pollution sources such as chemical, rubber, and
galvanization factories. It should be located at a distance of at least 2 km (1.24 mi.) from
light pollution sources such as packinghouses and tanyards. If these pollution sources
cannot be avoided, ensure that the equipment room is upwind of the pollution sources. In
addition, use a high-quality equipment room or protection products.
l The room should be located away from livestock farms, or be upwind of the livestock
farms. Do not use an old livestock room or fertilizer warehouse as the equipment room.
l The equipment room must be far away from residential areas. An equipment room that is
not far away from residential areas must comply with equipment room construction
standards to avoid noise pollution.
l The room should be located far away from industrial and heating boilers.
l The room should be at least 3.7 km (2.30 mi.) away from the seaside or salt lake.
Otherwise, the equipment room should be airtight with cooling facilities. In addition,
alkalized soil cannot be used as the construction material. Otherwise, equipment suitable
for wet conditions must be used.
l The doors and windows of the equipment room must be kept closed to maintain an
airtight room.
l Using steel doors to ensure sound insulation is recommended.
l No cracks or openings are allowed on the walls or floors. The outlet holes on the walls or
windows must be sealed. Walls must be constructed such that they are smooth, wear-
resistant, dustproof, flame retardant, sound insulated, heat absorptive, and have
electromagnetic shielding.
l The air vent of the room should be far from the exhaust of city waste pipes, big cesspools
and sewage treatment tanks. The room should be in the positive pressure state to prevent
corrosive gases from entering the equipment room and corroding components and circuit
boards.
l It is recommended that the room be on or above the second floor. If this requirement
cannot be met, the ground for equipment installation in the room should be at least 600
mm (23.62 in,) above the maximum flood level.
l The equipment room should be strong enough to resist winds and downpours.
l The room should be located away from dusty roads or sand. If this is unavoidable, the
doors and windows of the equipment room must not face pollution sources.
l Do not place air conditioning vents near the equipment so that they blow directly on the
equipment because condensation may be blown into the equipment.
l Do not use decorative materials that contain sulfur in the equipment room.
Substation room
Item Requirements
Area The smallest area of the equipment room can accommodate the
equipment with the largest capacity.
Net height The minimum height of the equipment room should not be less than 3 m
(9.84 ft). The minimum height of the equipment room is the net height
below overhead beams or ventilation pipes.
Load-bearing The floor must bear loads larger than 150 kg/m2 (0.21 bf/in.2).
capacity
Item Requirements
Door and The door of the equipment room should be 2 m (6.56 ft) high and 1 m
windows (3.28 ft) wide. One door is enough. Seal the doors and windows with
dustproof plastic tape. Use double-pane glass in the windows and seal
them tightly.
Wall surface Paste wallpaper on the wall or apply flat paint. Do not use pulverized
treatment paint.
Cable trays Use cable trays to arrange cables. The inner faces of the cable trays must
be smooth. The reserved length and width of the cable trays, and the
number, position and dimensions of the holes must comply with the
requirements of device arrangement.
Water pipe Do not pass service pipes, drainpipes, and storm sewers through the
equipment room. Do not place a fire hydrant in the equipment room, but
place it in the corridor or near the staircase.
Internal Separate the area where the equipment is installed from the equipment
partition wall room door. The partition wall can block some outside dust.
Installation Install air conditioner vents so that the air does not blow directly on
position of the equipment.
air conditioner
Other Avoid the proliferation of mildew, and keep out rodents (like mice).
requirements
The equipment room must be free from explosive, conductive, magnetically-permeable, and
corrosive dust. Table 6-16 lists the requirement for dust concentration in the equipment room.
Description
l Dust particle diameter ≥ 5 µm
l Suspending dust diameter ≤ 75 µm
l 75 µm ≤ precipitable dust diameter ≤ 150 µm
l Avoid constructing the room near a place where the corrosive gas concentration is high,
such as a chemical plant.
l Ensure the air intake vent of the room is in the prevailing upwind direction from any
pollution source.
l Place batteries in different rooms.
l A professional service should monitor the corrosive gas conditions regularly.
Item Requirements
Power cables l After the low-voltage power cables are led into the room, install the
leading in the surge protector for the power cables in the AC voltage stabilizer and
equipment room the AC power distribution panel (box). Correctly ground the surge
need to be protector nearby.
equipped with a l For an equipment room in urban area, install a power supply surge
surge protector protector with the nominal discharge current of no less than 20 kA.
For an equipment room that is built in a suburb and subject to
lightning strikes, install a power supply surge protector with the
nominal discharge current of more than 60 kA. For an equipment
room that is built in a mountain area and subject to frequent
lightning strikes, or in a separate high-rise building in a city, install a
power supply surge protector with the nominal discharge current of
more than 100 kA.
l The ground cable of the surge protector should be no longer than 1
m (3.28 ft).
Grounding for l Connect the DC working ground (positive pole of the -48 V DC
DC power power supply or the negative pole of the 24 V DC power supply)
distribution with the indoor collective ground cable nearby. The total ground
cable should meet the maximum load of the equipment.
l The power equipment must have a DC working ground cable, which
can connect the power equipment to the collective ground cable of
the telecommunication site (or the protective ground bar of the
equipment room).
Equipotential l Properly ground the devices and auxiliary devices in the room such
connection as mobile base station, transmission, switching equipment, power
supply equipment, and cable distribution frame. Connect all PGND
cables to the collective protective ground bar. Connect all PGND
cables in one equipment room to one protective ground bar.
l Apply joint grounding to the working ground and protective ground
of devices, which means the two share one grounding network.
l The cable tray, rack or shell, metal ventilation pipe, metal door or
window of the equipment should be grounded for protection.
General l Do not connect the neutral line of the AC power cable with the
requirements for protective ground of any telecom equipment in the equipment room.
grounding l Do not install a fuse or switch on the ground cable.
l All ground cables should be as short as possible, and arranged in a
straight line.
Item Requirements
Routing of l Do not arrange the signal cables overhead in the equipment room.
signal cable All signal cables must be led into the site underground.
l Use the cables with a metal jacket or place them into a metal pipe if
they come out/in the equipment room.
l Ground the idle lines inside the cable in the equipment room.
l Signal cables should be deployed on internal walls. Do not deploy
outdoor aerial cables.
l Keep signal cables away from power cables and surge protection
devices.
Collective l Use a ground ring or ground bar for the collective ground cable.
ground cable l Do not use aluminum cables as ground cables. Adopt measures to
prevent electrification corrosion when connecting different metal
parts together.
l Use a copper busbar as the collective ground cable with a cross-
sectional area of no less than 120 mm2 (0.19 in.2), or use the
galvanized flat steel of the same resistance. Insulate the collective
ground cable from the reinforcing steel bars of the building.
Grounding lead- The grounding lead-in should be a maximum of 30 m (98.42 ft) long.
in Use the galvanized flat steel with cross-sectional area of 40 mm x 4
mm (1.58 in. x 0.158 in.) or 50 mm x 5 mm (1.97 in. x 0.197 in.).
Item Requirements
Grounding of the l All the devices including the surge protection device in the cabinet
cabinet must be connected in an equipotential manner. The ground cables
can be aggregated to the ground bar or surge protector socket first,
and then the ground bar or surge protector socket can be connected
to the ground.
l The resistance between the device ground terminals and ground bar
cannot exceed 0.1 ohm.
l The cabinet can be grounded using the protecting earthing (PE) wire
of the electrical network in the building, zinc-coated angle steel, or
the main steel bar of the building.
l If the cabinet is grounded using the PE wire of the electrical
network, use a multimeter to test the grounding status. If the voltage
between the PE wire and neutral wire is lower than 5 V and the
voltage between the PE wire and live wire is about 220 V, the PE
wire is grounded well. If the tested AC voltages are not within the
ranges, the cabinet must be grounded in other ways.
l The yellow-green ground cable contains multiple copper wires. The
cross-sectional area of the ground cable must be no less than 6 mm2
(0.0093 in.2) and the length cannot exceed 3 m (9.84 ft.).
l Ground cables cannot be twisted with signal cables.
l Antirust and anticorrosion measures must be taken on the ground
terminals.
l The fiber reinforcing rib can be directly connected to the ground bar
of the cabinet. Before wrapping the reinforcing rib with insulation
tape, cut a 0.5 m (1.64 ft.) segment from the reinforcing rib. Wrap
the reinforcing rib with at least five layers of insulation tape. Keep
the reinforcing rib at least 5 cm (1.969 in.) from the cabinet surface.
protect independent devices. Configure the current-carrying capacity of the protection switch
of the equipment room for more than that of the devices.
Table 6-19 lists the voltage range of the AC power supply for the devices.
The automated electric generator must have a standard interface that supports
telecommunication protocols, remote telecommunication, monitoring, and control.
l A large-scale enterprise can deploy an independent power supply system on each floor to
supply power to the telecommunications equipment room on the respective floor.
l A medium-scale enterprise can use a power room and a battery room for centralized
power supply or use distributed power supply systems.
l A small-scale enterprise can deploy an integrated power supply system in its equipment
room but must take measures to prevent corrosive gases released from batteries from
eroding circuit boards of telecommunications equipment.
Item Requirements
Regulated If the AC input voltage is in the range of 85% to 110% of the rated
voltage precision value, and the load current is in the range of 5% to 100% of the rated
value, the output voltage of the rectifier ranges from -46.0 V to -56.4 V,
with the regulated voltage precision less than or equal to 1%.
Dynamic The recovery time is less than 200 ms. The overshoot is in the range of
response the integral value of the DC output voltage ±5%.
l The total capacity of the high-frequency switching rectifier must satisfy the power of the
communication loading and battery charging. If there are 10 or fewer active rectifier
modules, configure one backup module. If there are more than 10 active modules,
configure one backup module for every 10 active modules.
l Install storage batteries in two or more groups. The capacity is determined by the
duration for which the storage batteries must supply power. For most offices, the
batteries should be able to supply power for at least one hour.
1 The working ground and protective ground, including the shielded ground and the
lightning-proof ground of the cable distribution frame should share the same
grounding conductor.
2 The cable trays, shells, metal ventilation pipes, metal doors and windows in the
equipment room should be grounded for protection.
3 The metal parts of the equipment which are electrically floating in normal
conditions should be grounded for protection.
4 The ground cable must be connected securely to the protective ground bar of the
equipment room.
5 Do not use other equipment as part of the ground cable or electrical connection.
1 All communication devices and auxiliary devices (such as mobile base stations,
transmission and switching devices, power supply devices) in the equipment room
should be grounded for protection. Connect all protective ground for various
devices jointly to a general ground bar, and then to the same protective ground bar
in the room together with the protective ground (PGND) of the device.
2 The PGND of the equipment is shorted to the copper ground bar provided by the
customer. The short-circuiting cable used should be a yellow-green plastic
insulated cable with a copper core and a cross-sectional area greater than 25 sq.
mm (0.039 sq. in.).
3 There are grounding terminals and grounding lugs at the lower part of the front
door, rear door and side panel of the cabinet, connected to the grounding terminals
of the cabinet framework through connection cables with cross-sectional area of no
less than 1.6 sq. mm (0.002 sq. in.).
4 Ensure that all metal components of the cabinet conduct well. No insulating
coating should be sprayed on the connection part of the metal components.
5 Connect the cabinets in the same row by fastening captive screws and gaskets on
the top of the cabinets. Do not spray any coating into a rectangular area measuring
30 mm x 50 mm (1.18 in. x 1.97 in.) around the connection hole for a captive bolt.
Measures to prevent rust and corrosion must be taken for this area. Zinc
electroplating with iridescent yellow chromate conversion coating should be
applied to the gasket and nut to ensure good electrical contact.
6 When combining cabinets of the same type, short-circuiting cables are required to
connect the ground busbars (if any) of the cabinets. The cross-sectional area of the
short-circuiting cable is 6 sq. mm (0.009 sq. in.) and is no more than 300 mm (11.8
in.) long. Connect the two ends of the short-circuiting cable to the ground busbar
terminals of neighboring cabinets and fix them firmly.
Table 6-23 shows the grounding specifications for communication power supplies.
1 The inlet for the AC power cable at the equipment room should be equipped with a
surge protection device (C-level) with a nominal discharge current no less than 20
kA.
2 The protective ground for the power supply and that for communication equipment
share the same grounding conductor. If the power supply and the equipment are in
the same equipment room, use the same protective ground bar for them if possible.
No. Description
4 The positive of the -48 V DC power supply or negative pole of the 24 V DC power
supply should be grounded at the output of the DC power supply.
5 The working ground and protective ground of the DC power supply equipment
should use the same grounding conductor with the protective ground of the
switching equipment. If the power supply and equipment are in the same
equipment room, use the same protection ground bar for them if possible.
No. Description
1 Equip the cable outdoors with a metal jacket, well grounded at both ends, or
connect the ends of the metal jacket to the protective ground bar of the equipment
room. For cables inside the equipment room, install surge protection devices at the
interface to the equipment. The PGND cable for the surge protection devices
should be as short as possible.
2 The incoming and outgoing signal cables to and from the office and unused wires
inside the cable should be grounded for protection.
3 The Tone & Data Access (TDA) cable must pass through the Main Distribution
Frame (MDF) with surge protective device (SPD) when going out of the office.
The cable's shield layer should be connected to the protective ground of the MDF.
The MDF should use the same grounding conductor as the cabinet.
No. Description
1 The grounding wire should not run parallel to or twist around the signal cable.
No. Description
2 Bury ground underground or arrange them indoors. Do not route ground cables
overhead.
3 Do not connect two cables together to extend the PGND cable, or add any switches
or fuses.
4 The PGND cable should be an alternating yellow and green plastic insulated one
with a copper core.
5 The neutral line of the AC power cable cannot be connected to the protective
ground of transmission and communication equipment in the equipment room.
NOTE
Fill in labels according to specified requirements to keep consistency of labels in the equipment room.
Make a relevant statement in the self-check report.
To specify more clearly the position of a cable, use the dividing lines on the label. For
example, there is a dividing line between the cabinet number and the chassis number, and
another one between the chassis number and the slot number. Each dividing line is light blue
(Pantone 656c) and 1.5 mm x 0.6 mm (0.06 in. x 0.02 in.).
The cut dotted line helps to fold the label when affixed to the cable, and its size is 1 mm x 2
mm (0.04 in. x 0.08 in.).
The word "TO:" (upside down in the figure) at the lower right corner of the label is used to
identify the opposite end of the cable on which the label is affixed.
l If many characters need to be filled in, decrease the font size, but make sure that the
printouts are clear and legible.
If the warning prompt as shown in Figure 6-156 appears before printing, click Ignore to continue
the printing.
After the page setup has been made correctly, save it for future use. This page setup is only
necessary the first time you use the template to print the labels.
Writing Tools
To make sure the printouts are clear and legible, use black markers instead of ball-point pens
to write the labels.
If no marker is available, black ball-point pens are allowed, although not recommended.
Compared with ball-point pens, waterproof markers are better. When writing with a ball-point
pen, do not leave the oil on the label, which may contaminate the label and blur the words.
NOTE
The delivered marker has two nibs. Use the smaller nib to write the labels.
Font
For the sake of legibility, use standard block letters and numbers as shown in Table 6-26
(Times New Roman).
0 1 2 3 4 5 6 7 8
9 A B C D E F G H
I J K L M N O P Q
R S T U V W X Y Z
Determine the size of characters based on the number of letters or digits and ensure that the
characters are distinct and tidy.
Cable
TO:
B03
TO:
B03 -48V2
-48V2
Cable
Seen from the cabling end of the equipment, the text part of the label is on the right side of the
cable. The side with "TO:" that is facing outside carries the location information of the
opposite end; and the other side carries the location information of the local end.
In other words, the information in Area 1 at one end is the same as the information in Area 2
at the other end of the cable.
These labels are affixed to the optical fibers that connect the optical interfaces on the boards
in a chassis, or on the device boxes. There are two types of labels for optical cables:
l One is for the fiber that connects the optical interfaces on two devices.
l The other is for the fiber that connects the device and the ODF.
Table 6-27 Information on labels affixed to the fibers between two devices
MN-B-C-D- MN: cabinet M: The cabinet rows from front to back are numbered
R/T number from A to Z.
N: The cabinet columns from left to right are numbered
from 01 to 99.
For example, A01 is the cabinet in row A and column
01.
R: Receiving -
interface
T: optical
transmitting
interface
A01 01 05 01 R
T 01 01 01 G01
TO:
6.4.2.2 Labels for the Optical Fibers Connecting the Device and an ODF
Table 6-28 Information on labels affixed to a fiber between a device and an ODF
Content Meaning Example
R: Optical -
receiving
interface
T: optical
transmitting
interface
ODF-MN-B- MN: row M: The cabinet rows from front to back are numbered
C-R/T number and from A to Z.
column number N: The cabinet columns from left to right are
of an ODF numbered from 01 to 99.
For example, G01 is the ODF of row G and column
01.
C: column
number of the
terminal device
R: Optical -
receiving
interface
T: optical
transmitting
interface
Figure 6-163 Sample label on an optical fiber between the device and the ODF
ODF G01 01 01 R
R 01 05 01 A01
TO:
Applicable Ranges
The labels can be applied to Ethernet cables.
Label Content
Table 6-29 shows the information on both sides of the labels affixed to Ethernet cables.
You can also decide the label content based on the actual environment. If the device is not
installed in the cabinet, for example, you can remove the cabinet number.
MN-B-C-D MN: cabinet For example, A01 is the first cabinet in row A.
number
MN-Z MN: cabinet For example, B02 is the second cabinet in row B.
number
The contents of the labels for network cables connecting hubs and devices or agents and the
network cables for other purposes should be specified according to actual connections. The
details are as follows:
l For a network cable connecting a hub and device, the label on the hub end should
indicate the numbers of the chassis and cabinet where the hub resides, and the serial
number on the hub. The label on the device end should indicate the number of the
chassis and cabinet where the device is located. If the device is a standalone device,
provide the specific position of the device.
l For a network cable connecting a hub and an agent or terminal, the label on the agent or
terminal end should contain the serial number of the network interface. The definitions
of the cabinet number and chassis number are the same as those described in Table 6-29.
l If the hub is a standalone device without a cabinet or chassis, the label should contain
specific location information that identifies the hub.
The serial number on the hub, the network interface number of the agent or terminal, and the
location of the standalone device should be specified according to actual connections.
Label Example
Figure 6-164 shows a sample label on an Ethernet cable.
A01 03 01 01
01 03 B02
TO:
Attach labels to both ends of a user cable to indicate the locations of the cable on the device
and main distribution frame (MDF).
MN-B-C-D MN: cabinet For example, A01 is the first cabinet in row A.
number
MDF-MN-B-C MN: row number M: The rows of cabinets from front to back are
and column numbered from A to Z. N: The columns of cabinets
number of the from left to right are numbered from 01 to 99. For
MDF example, G01 is the MDF of Row G and Column
01.
C: column number
of the terminal
device
A01 03 01 01
01 01 MDF G01
TO:
The label only carries location information about the destination direction of the power cable
whereas information about the local end is unnecessary. That is, the label only carries location
information about the opposite equipment, the control cabinet, or the distribution box. Table
6-31 lists the information on two -48 V power supplies on the label. The information on other
DC voltages, such as 24 V and 60 V should be given in similar methods.
Make sure that labels are affixed in the correct direction. That is, after the cable ties are
bundled onto the cable, the identification plates with the labels should face up, and the text on
the labels in the same cabinet should be in the same direction. For details, see Figure 6-166.
NOTE
In the power distribution box or the first power cabinet of a row in a transmission equipment room,
every terminal block on the -48 V connector bar has a numeric identification. For example, in the above
label of "A01/B08--48V2", "08" (or sometimes "8") is the numeric identification of the terminal block.
PGND and BGND are two copper bars, on which the terminal blocks are short-circuited.
Therefore, it makes no difference which terminal is connected to them. It is only necessary to
give the row and column of the power distribution box, instead of giving the specific serial
number of the terminal block on the copper bar. For example, if the label on the loaded
cabinet side is "A01-BGND", it means that the power cable is a BGND that connects BGND
copper bar in the power distribution box in row A, column 01 in the machine room.
Information on the labels for PGND cables should be given in a similar way.
The labels for AC power cables are affixed to one side of the identification plates on cable
ties. For details, see Table 6-32.
Content Meaning
MN-(B)-ACn MN: serial number of the cabinet or the socket where the power is led
in
B: chassis number, numbered in bottom-up order with two digits, for
example, 01.
n: power port number, numbered as 1 to 3 in bottom-up and left-to-right
order.
Serial number of the socket where the power is led in: the location of
the socket is marked according to the actual situation. If the sockets can
be identified by row numbers and column numbers, they can be
numbered following the same rule for the cabinets. If the sockets
cannot be identified by rows and columns, specify the detailed
locations to avoid confusion with other sockets.
The label only carries location information about the opposite equipment and the power
socket; information about the local end is unnecessary.
Make sure that labels are affixed in the correct direction. That is, after the cable ties are
bundled onto the cable, the identification plates with the labels should face up, and the text on
the labels in the same cabinet should be in the same direction, as shown in Figure 6-167.
Label on the loaded cabinet side Label on the distribution box side
(indicating the position of the cable (indicating the position of the cable
on the power distribution box) on the loaded cabinet side)
The system may fail to obtain information about non-Huawei-certified optical modules or obtain incorrect
information. You are advised to use Huawei-certified optical modules. Obtain the electronic label of the
optical module and contact technical support personnel to confirm whether it is a Huawei-certified optical
module.
1. An optical module is not completely installed in position.
If the optical module is not completely installed in position and the latch boss is not
secured, the device cannot identify the optical module. After the optical module works
for a long time, it will be ejected under external stress.
2. The optical receptacle on an optical module is contaminated.
If an optical module is not cleaned or protected properly, contaminants may accumulate
on the fiber pin in the optical module. As a result, the coupling efficiency is reduced,
optical signals are cut off, or even worse, the surface of the fiber pin is damaged
permanently.
3. An optical module is burnt.
If high-power optical signals (caused by an optical time domain reflectometer or self-
loop test) are transmitted through an optical module that is used for long-distance
transmission but no optical attenuator is used, the optical power will exceed the overload
power of the avalanche photodiode (APD). Then the optical module is burnt.
The preceding faults lead to temporary or long-term cut-off of optical signals; or even cause
permanent damages to the optical module, affecting communication services.
NOTE
Place at least three cleaning tissues on the work bench. As shown in Figure 6-169, wipe the end of
an optical connector from left to right or from right to left on a cleaning tissue, and then move the
connector end to the unused part of the cleaning tissue to continue.
2. Cover an unused optical module with a protective cap to prevent dust, as shown in
Figure 6-170.
If no protective cap is available, use fibers to protect the optical module, as shown in
Figure 6-171.
3. Cover unused optical connectors with protective caps, as shown in Figure 6-172, and
then lay out fibers on the fiber rack or coil them in a fiber management tray to prevent
fibers from being squeezed.
4. If a receptacle or an optical connector has not been used for a long time and is not
covered with a protective cap, you need to clean it before using it. Clean a receptacle
with a cotton swab, as shown in Figure 6-173. Clean an optical connector with cleaning
tissues.
NOTICE
When cleaning a receptacle, insert the cotton swab and turn it slowly in the receptacle.
Do not use too much strength because the receptacle may be damaged.
5. If optical signals are lost during the operation of a device, use the preceding method to
clean the receptacle or the optical connector. In this manner, the possibility of
contamination can be excluded.
Precautions
1. The optical connector should be vertically inserted in the receptacle to avoid damages to
the receptacle.
2. Fibers must be inserted into optical modules of the corresponding type. That is,
multimode fibers must be inserted into multimode optical modules, and single mode
fibers must be inserted into single mode optical modules. If a fiber is inserted into an
optical module of a different mode, faults may occur. For example, optical signals will
be lost.
Address:
Contact person:
Tel.: Fax:
Fault Description
BOM Product Bar Occurring of the Fault Category Software
Code Description Code* Date* Phenomena* No.* Version*
Note:
l For optical interface cards returned, the optical interfaces should be covered with
protection caps.
l In general, the analysis card will not be returned to you. If you have any special
requirements, please contact Huawei.
l One Fault Tag should be adapted in one return category, such as RMA/Return/Analysis.
l The items marked with "*" are the mandatory fields that you must fill in.
AC Indepen The air vent of the device is free from blockage to ensure
1
dent AC normal heat dissipation.
Com Applic
pone No. able Check Item
nt Scope
Indepen The power modules are securely installed with their captive
2
dent AC screws tightly fixed.
5 General The PoE switch is correctly grounded with the ground cable.
Com Applic
pone No. able Check Item
nt Scope
Indoor APs are placed far away from windows and in dry
Indoor environments with little dust and good ventilation. There
6
AP should be no inflammable materials in rooms. The indoor
temperature and humidity must be within acceptable ranges.
When two or more APs are installed in the same area, they
Outdoor
8 must be installed in the same vertical or horizontal line with
AP
certain spacing greater than 15 mm.
Com Applic
pone No. able Check Item
nt Scope
Outdoor
16 Unused radio ports should be installed with 50 Ω RF loads.
AP
Com Applic
pone No. able Check Item
nt Scope
Indoor The optical, power, network, and feeder cables are bundled
6
AP using straps (one strap every 0.5 m) and securely fastened.
Keep the signal cables away from heat sources and use heat
insulation materials to insulate the cables from the heat
8 General sources. Do not place signal cables on the air vents of the
cabinet to avoid affecting subrack heat dissipation or cable
lifetime.
Com Applic
pone No. able Check Item
nt Scope
Outdoor
17 Do not deploy cables overhead between two buildings.
AP
Com Applic
pone No. able Check Item
nt Scope
Com Applic
pone No. able Check Item
nt Scope
Power cables and ground cable are separated from the signal
5 General
cables.
The lugs for the power cables and ground cables are soldered
8 General
or crimped securely.
The lugs and bare wires of power cables and ground cables
are tightly wrapped with tubes or insulation tape without any
9 General
exposed copper wire. Flat washers and spring washers are
installed correctly.
Com Applic
pone No. able Check Item
nt Scope
NOTE
l When a device is installed in a harsh environment or its ports face upward, follow outdoor
waterproof standards to lay out indoor cables. For details, see "Cable Connection" in the
AP6510DN&AP6610DN Hardware Installation and Maintenance Guide.
l The network cable directions in the description below are relative to an AP.
l If a cable is downward, no drip loop is required.
ǹ
Ķ
≤100mm
≥50mm
ǹ
≥50mm
≤100mm
Ķ
Horizontal Port, Upward Cable
ǹ
≥50mm
≤100mm
Ķ
Bending Radius Requirements
l The bending radius of a 7/8'' feeder must be more than 250 mm, and that of a 5/4'' feeder
must be more than 380 mm.
l The bending radius of a 1/4" jumper, 1/2" super-flexible jumper, and 1/2" common
jumper must be greater than 35 mm, 50 mm, and 127 mm, respectively.
l The bending radius of a ground cable must be greater than or equal to five times the
cable diameter.
l The bending radius of a network cable must be greater than or equal to five times the
cable diameter (that is, 50 mm).