Beruflich Dokumente
Kultur Dokumente
COLLEGE OF ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
TE 41 – CONCRETE TECHNOLOGY
CHAPTER 13
CONCRETE REPAIRS
BSCE – 4C
GAN, ABEGAIL C.
RAMOS, LIEZL ANN P.
SAFLOR, JOMINA D.
May 7, 2019
1
1. Introduction
Though concrete is a relatively durable building material, it may suffer damage or distress
during its life period due to a number of reasons. Because of the varying conditions under which
it is produced at various locations, the quality of concrete suffers occasionally either during
production or during service conditions resulting in distress.
Concrete structures will show the degree of deterioration in the form of cracking, spalling
and disintegration. Each one of these is clearly distinguishable. The reasons for their
development may be poor materials, poor design, poor construction practice, poor supervision or
a combination. Crack formation in concrete is most interesting because sometimes the same
causes produce a different cracking pattern, and sometimes the same cracking pattern is
produced by different causes.
Sometimes concrete cracks in a location where no cause can be found out, and in other
places it does not crack where there is every reason for cracks to occur. However, fifty percent of
the cases are straightforward. Cracks in themselves are seldom indicative of structural danger;
accordingly, repair usually does not involve strengthening. So their repairs are basically intended
to seal the cracks against an objectionable flow of water or to improve the appearance of the
construction. In the repair of a structure showing spalling and disintegration, it is usual to find
that there have been substantial losses of section and/or pronounced corrosion of the
reinforcement. Both are matters of concern from a structural viewpoint, and repair generally
involves some urgency and some requirement for restoration
of lost strength.
2
2. Reasons Why Concrete Cracks
The first reason among others is excess water in the mix. Concrete does not require much
water to achieve maximum strength. But a wide majority of concrete used in residential work has
too much water added to the concrete on the job site. This water is added to make the concrete
easier to install. This excess water also greatly reduces the strength of the concrete. Shrinkage is
a main cause of cracking. As concrete hardens and dries it shrinks. This is due to the evaporation
of excess mixing water. The wetter or soupier the concrete mix, the greater the shrinkage will be.
Concrete slabs can shrink as much as 1/2 inch per 100 feet. This shrinkage causes forces in the
concrete which literally pull the slab apart. Cracks are the end result of these forces.
The bottom line is a low water to cement ratio is the number one issue affecting concrete
quality- and excess water reduces this ratio. What you can do about it is know the allowable
water for the mix the contractor is pouring- or be very sure you have chosen a reputable
contractor who will make sure the proper mix is poured. It is more expensive to do it right- it
simply takes more manpower to pour stiffer mixes.
Another reason is rapid drying of the concrete. Rapid drying of the slab will significantly
increase the possibility of cracking. The chemical reaction, which causes concrete to go from the
liquid or plastic state to a solid state, requires water. This chemical reaction, or hydration,
continues to occur for days and weeks after you pour the concrete. You can make sure that the
necessary water is available for this reaction by adequately curing the slab. The solution to this is
proper curing.
Another reason is improper strength concrete poured on the job. Concrete is available in many
different strengths. Verify what strength the concrete you are pouring should be poured at. You
can know all about the concrete if you talk to the ready mix supplier.
Another reason is lack of control joints. Control joints are planned cracks which allow for
movements caused by temperature changes and drying shrinkage. In other words, if the concrete
does crack-you want to have an active role in deciding where it will crack and that it will crack
in a straight line instead of randomly. Control joints help concrete crack where you want it to.
The joints should be of the depth of the slab and no more than 2-3 times (in feet) of the thickness
of the concrete (in inches). So 4"concrete should have joints 8-12' apart.
A thing to remember is to never pour concrete on frozen ground. The ground upon which the
concrete will be placed must be compacted
3
Fig. 2(a) Cement Slurry Fig. 2(b) Cement Mortar
b. Cement Mortar
Mortar is a workable paste used to bind building blocks such as stones,
bricks, and concrete masonry units together,
c. Epoxy Resin
Epoxy resin is more commonly known as a type of glue that is fast-acting
and bonds to nearly any surface. Epoxy resin is also nearly impossible to remove
from an item so once you use it you can be certain it will not come apart. Epoxy
resin can also be found in many other useful products. Epoxy resin is very
inexpensive to purchase but its effects can last for several years depending on its
use.
4
i. More extensive cement cure. Cement/concrete strength depends
on proper curing, a chemical reaction (hydration) between water and
cement that causes crystals to grow and wrap around the mix
components. During the early stages of cure (roughly the first five to
seven days), there must be enough water to maintain the hydration
process or the cement/concrete will not harden properly.
5
Toughness test of modified and unmodified
mortar patches. Mortar Patches are feathered
down to blend in with original substrate.
Adhesion is a key property in mortar patches
over existing concrete. Without polymer
modification (left), the patch flashes off very
quickly and breaks like a potato chip. Notice
the residual mortar on the concrete substrate.
The 10% polymer-modified patch (right)
could not be moved. Notice the scallop marks
near the bottom where removal was attempted.
6
face so that the water or other aggressive agents cannot penetrate the interior of
the concrete and cause side effects such as swelling, chemical attack, or
corrosion of the reinforcement. The sealant may be any of the several materials,
depending on how tight or permanent seal is desired. This is a method where
thorough water tightness of the joint is not required and where appearance is not
important
VIDEO LINK : https://www.youtube.com/watch?v=hjOzk-IbCy0&t=207s
c. Stitching
Stitching involves drilling holes on both sides of the crack and grouting
in U-shaped metal units with short legs (staples or stitching dogs) that span the
crack as shown in the figure. Stitching may be used when tensile strength must be
re-established across major cracks. The stitching procedure consists of drilling
holes on both sides of the crack, cleaning the holes, and anchoring the legs of the
7
staples in the holes, with either a non shrink grout or an epoxy resin-based
bonding system.
Drill holes at an angle so that they intersect the longitudinal crack or joint at about mid-
depth. (It is important to start drilling the hole at a consistent distance from the crack or
joint, in order to consistently cross at mid-depth.)
8
Select a drill that minimizes damage to the concrete surface, such as a hydraulic powered
drill; Select a drill diameter no more than 0.375 inches larger than the tie bar diameter.
Choose a gangmounted drill if higher productivity is needed for larger jobs.
Inject epoxy into the hole, leaving some volume for the bar to occupy the hole. (Pouring
the epoxy is acceptable for small quantities.)
9
Fig. 4.5 Removing excess epoxy
• Cut slots approximately perpendicular to the longitudinal joint or crack using a slot
cutting machine or walk-behind saw. Unlike dowel bar retrofit, precision alignment is not
critical since deformed bars will hold the joint tightly together preventing the slabs from
separating.
• Prepare the slots by removing the concrete and cleaning the slot. If the slabs have
separated, consider using a joint reformer and caulking the joint or crack to prevent
backfill materials from flowing into the area between the slabs.
• Place deformed bars into the slot.
• Place backfill material into the slot and vibrate it so it thoroughly encases the bar. Select
a backfill material that has very low shrinkage characteristic.
• Finish flush with the surface and cure
10
Fig. 4.5 Slot Stitching Diagram
Conventional reinforcement
Applications and limitations. Cracked reinforced concrete bridge girders have been
successfully repaired by use of additional conventional reinforcement (Stratton,
Alexander, and Nolting 1982). Posttensioning is often the desirable solution when a
major portion of a member must be strengthened or when the cracks that have formed
must be closed. For the posttensioning method, some form of abutment is needed for
anchorage, such as a strongback bolted to the face of the concrete, or the tendons can
be passed through and anchored in connecting framing.
Procedure.
1. This technique consists of sealing the crack, drilling holes 19 mm (3/4 in.) in
diam at 90 deg to the crack plane, cleaning the hole of dust, filling the hole and
crack plane with an adhesive (typically epoxy) pumped under low pressure 344 to
552 KPa (50 to 80 psi), and placing a reinforcing bar into the drilled hole.
Typically, No. 4 or 5 bars are used, extending at least 0.5 m (1.6 ft) on each side
of the crack. The adhesive Figure 6-1. Crack repair using conventional
reinforcement with drillholes 90 deg to the crack plane bonds the bar to the walls
11
of the hole, fills the crack plane, bonds the cracked concrete surfaces together in
one monolithic form, and thus reinforces the section.
2. A temporary elastic crack sealant is required for a successful repair. Gel-type
epoxy crack sealants work very well within their elastic limits. Silicone or
elastomeric sealants work well and are especially attractive in cold weather or
when time is limited. The sealant should be applied in a uniform layer
approximately 1.6 to 2.4 mm (1/16 to 3/32 in.) thick and should span the crack by
at least 19 mm (3/4 in.) on each side.
3. Epoxy adhesives used to rebond the crack should conform to ASTM C 881, Type
I, low-viscosity grade.
4. The reinforcing bars can be spaced to suit the needs of the repair. They can be
placed in any desired pattern, depending on the design criteria and the location of
the in-place reinforcement.
5. Concrete elements may also be reinforced externally by placement of
longitudinal reinforcing bars and stirrups or ties around the members and then
encasing the reinforcement with shotcrete or cast-in-place concrete. Also, girders
and slabs have been reinforced by addition of external tendons, rods, or bolts
which are prestressed. The exterior posttensioning is performed with the same
equipment and design criteria of any posttensioning project. If desirable for
durability or for esthetics, the exposed posttensioning strands may be covered by
concrete.
12
Applications and limitations. This technique is applicable only where cracks run in
reasonably straight lines and are accessible at one end. This method is most often
used to repair vertical cracks in walls.
Procedure.
f. External Stressing
Development of cracking in concrete is due to tensile stress and can be
arrested by removing these stresses. Further, the cracks can be closed by inducing
a compressive force, sufficient to overcome the tension and to provide a residual
compression. This compressive force is applied by use of the usual prestressing
wires and rods. The principle is very similar to stitching, except that the stitches
are tensioned; rather than plain bar dogs which apply no closing force to the crack
and which may in fact have to permit the crack to open up a bit before they begin
13
to take the load. All the points noted regarding stitching must be considered. An
additional problem is that of providing an anchorage for the prestressing wires or
rods. Some form of abutment is needed for this purpose. The effect of the
tensioning force on the stress conditions in the structure should be analyzed.
g. Drypack
Drypacking is the hand placement of a very dry mortar and the subsequent
tamping of the mortar into place, producing an intimate contact between the new
and existing works. Because of the low water-cement ratio of the material, there is
little shrinkage, and the patch remains tight. So it will be of good quality with
respect to durability, strength and water tightness. Drypacking is used for filling
small, relatively deep holes, such as those resulting from the removal of form ties,
and narrow slot cut for repair of cracks. The usual mortar mix is 1:2:5 to 1:3.
14
Fig. 4 (g) Drypacking
h. Surface Coating
Fine surface cracks in structural slabs and pavements may be repaired
using either a bonded overlay or surface treatment if there will not be further
significant movement across the cracks. Unbounded overlays may be used to
cover, but not necessarily repair a slab. Overlays and surface treatments can be
appropriate for cracks caused by one-time occurrences and which do not
completely penetrate the slab.
h.2. Overlays
15
Overlays may be used to seal the cracks and they are very useful
and desirable where there are large numbers of cracks and treatment of
each individual defect would be too expensive. Sealing of an active crack
by use of an overlay requires that the overlay be extensible and not
flexible alone. The occurrence of prolongation of a crack automatically
means that there has been elongation of the surface fibers of concrete.
Accordingly, an overlay which is flexible but not extensible, ie. Can be
bent but cannot be stretched, will not seal a crack that is active.
REFERENCES:
http://www.cement.org/learn/concrete-technology/concrete-construction/contraction-control-
joints-in-concrete-flatwork
http://www.cipremier.com/e107_files/downloads/Papers/100/26/100026073.pdf
https://www.concretenetwork.com/concrete/concrete_cracks/preventing_concrete_cracks.htm
16
http://www.concreteconstruction.net/how-to/polymer-modified-mortars_o
https://www.youtube.com/watch?v=hjOzk-IbCy0&t=207s
https://www.youtube.com/watch?v=7_diXmKZp_8
17