DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated
soils including laying jointing testing of pipe line including
cost of materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm
Thickness in mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm 14 mm ### 14 mm 14 mm 14 mm
Pressure rating (m)

1 Wt of pipe 32.455 39.360 47.991 56.623 73.886 91.149 108.412 125.675 142.938 160.201 ### 211.990 246.516 281.042
2 Wastage (5%) 1.62 1.97 2.40 2.83 3.69 4.56 5.42 6.28 7.15 8.01 8.87 10.60 12.33 14.05
Total weight 34.07 41.33 50.39 59.45 77.58 95.71 113.83 131.96 150.09 168.21 186.33 222.59 258.85 295.09

A) Materials component
1 Cost of pipe per RMT 1396.87 1694.53 2065.99 2437.45 3180.78 3924.11 4667.03 5410.36 6153.69 6896.61 ### 9126.19 ### ###

2 Cost of specials (1.50% of 20.95 25.42 30.99 36.56 47.71 58.86 70.01 81.16 92.31 103.45 114.59 136.89 159.19 181.48
basic cost)
3 Transportation charges, 23.92 29.02 35.38 41.75 54.48 67.21 79.93 92.66 105.39 118.12 130.84 156.30 181.76 207.21
loading, unloading and
stacking
1441.70 1749.00 2132.40 2515.80 ### 4050.20 ### 5584.20 ### ### ### ### ### ###

B) Labour component
4 fabrication 374.77 454.63 554.29 653.95 853.38 1052.81 1252.13 1451.56 1650.99 1850.31 ### 2448.49 2847.35 3245.99
5 Epoxy paint Out side 63.20 76.64 93.45 110.26 143.87 177.49 211.10 244.72 278.33 311.95 345.56 412.79 480.02 547.25

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84

8 Jointing of pipes (Rs:10.34 / k 352.28 427.35 521.03 614.71 802.18 989.64 1177.00 1364.47 1551.93 1739.29 802.00 987.00 1246.00 1475.00

844.00 1025.80 1252.80 1479.70 ### 2388.00 ### 3296.00 ### ### ### ### ### ###
Total 2285.70 2774.80 3385.20 3995.50 ### 6438.20 ### 8880.20 ### ### ### ### ### ###
311.20 377.79 460.89 543.99 710.27 876.56 ### 1209.04 ### ### ### ### ### ###
2596.90 3152.59 3846.09 4539.49 5927.07 7314.76 8701.66 10089.24 ### ### ### ### ### ###
AS PER COMMON SSR

1.50 x 2.0m

900 mm 1000 mm 1100 mm 1200 mm


14 mm 14 mm 14 mm 14 mm

315.569 350.095 384.621 419.147


15.78 17.50 19.23 20.96
331.35 367.59 403.85 440.11

### ### ### ###

203.78 226.07 248.37 270.67

232.67 258.12 283.58 309.05

### ### ### ###

3644.85 4043.49 4442.35 4841.21


614.48 681.71 748.94 816.17

605.07 672.30 739.53 806.76

1788.00 2002.00 2069.00 2138.00

### ### ### ###


### ### ### ###
### ### ### ###
### ### ### ###
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm 1800 mm
Thickness in mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 12 mm 25 mm
Pressure rating (m)

1 Wt of pipe 27.226 33.145 40.544 47.942 62.739 77.536 92.333 107.130 121.926 136.723 151.520 181.114 210.708 240.302 269.895 299.489 329.083 358.677 388.271 417.864 447.458 477.052 536.240 1125.181
2 Wastage (5%) 1.36 1.66 2.03 2.40 3.14 3.88 4.62 5.36 6.10 6.84 7.58 9.06 10.54 12.02 13.49 14.97 16.45 17.93 19.41 20.89 22.37 23.85 26.81 56.26
Total weight 28.59 34.81 42.57 50.34 65.88 81.42 96.95 112.49 128.03 143.56 159.10 190.17 221.25 252.32 283.39 314.46 345.53 376.61 407.68 438.75 469.83 500.90 563.05 1181.44

A) Materials component
1 Cost of pipe per RMT 1172.19 1427.21 1745.37 2063.94 2701.08 3338.22 3974.95 4612.09 5249.23 5885.96 6523.10 7796.97 9071.25 10345.12 11618.99 12892.86 14166.73 15441.01 16714.88 17988.75 19263.03 20536.90 23085.05 48439.04

2 Cost of specials (1.50% of basic cost) 17.58 21.41 26.18 30.96 40.52 50.07 59.62 69.18 78.74 88.29 97.85 116.95 136.07 155.18 174.28 193.39 212.50 231.62 250.72 269.83 288.95 308.05 346.28 726.59

3 Transportation charges, loading, 20.08 24.44 29.89 35.35 46.26 57.17 68.08 78.99 89.90 100.81 111.72 133.54 155.36 177.18 199.00 220.81 242.63 264.46 286.27 308.09 329.91 351.73 395.37 829.61
unloading and stacking
1209.80 1473.10 1801.40 2130.20 2787.90 3445.50 4102.60 4760.30 5417.90 6075.10 6732.70 8047.50 9362.70 ### ### ### 14621.90 15937.10 ### 18566.70 19881.90 21196.70 23826.70 49995.20

B) Labour component
4 fabrication 314.49 382.91 468.27 553.74 724.68 895.62 1066.45 1237.39 1408.33 1579.16 1750.10 2091.87 2433.75 2775.52 3117.29 3459.06 3800.83 4142.71 4484.48 4826.25 5168.13 5509.90 6193.55 12995.84

5 Epoxy paint Out side 61.85 75.30 92.11 108.91 142.53 176.14 209.76 243.37 276.99 310.60 344.22 411.45 478.68 545.91 613.14 680.37 747.60 814.83 882.06 949.29 1016.52 1083.75 1218.21 1226.95

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 295.62 359.94 440.17 520.52 681.20 841.88 1002.46 1163.15 1323.83 1484.41 802.00 987.00 1246.00 1475.00 1788.00 1976.00 2041.00 2106.00 2177.00 2390.00 2450.00 2511.00 2846.00 3449.00

725.70 885.30 1084.50 1284.00 1682.80 2081.70 2480.30 2879.20 3278.00 3676.70 3232.40 3893.70 4629.00 5334.20 6123.50 6787.70 7328.90 7870.30 8417.50 9106.70 9643.10 10180.30 11467.90 18881.90
Total 1935.50 2358.40 2885.90 3414.20 4470.70 5527.20 6582.90 7639.50 8695.90 9751.80 9965.10 ### ### ### ### ### 21950.80 23807.40 ### 27673.40 29525.00 31377.00 35294.60 68877.10
263.52 321.10 392.92 464.84 608.69 752.53 896.26 1040.12 1183.95 1327.71 1356.75 1625.79 1904.97 2179.99 2466.47 2735.91 2988.60 3241.38 3494.89 3767.73 4019.83 4271.98 4805.36 9377.62
2199.02 2679.50 3278.82 3879.04 5079.39 6279.73 7479.16 8679.62 9879.85 11079.51 11321.85 13566.99 15896.67 18191.69 20582.27 22830.71 24939.40 27048.78 29164.29 31441.13 33544.83 35648.98 40099.96 78254.72
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm
Thickness in mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm 10 mm
Pressure rating (m)

1 Wt of pipe 22.195 27.128 33.293 39.458 51.789 64.120 76.451 88.781 101.112 113.443 125.774 150.435 175.097 199.758 224.420 249.081 273.743 298.404 323.066 347.727 372.389 397.050 446.373
2 Wastage (5%) 1.11 1.36 1.66 1.97 2.59 3.21 3.82 4.44 5.06 5.67 6.29 7.52 8.75 9.99 11.22 12.45 13.69 14.92 16.15 17.39 18.62 19.85 22.32
Total weight 23.31 28.49 34.95 41.43 54.38 67.33 80.27 93.22 106.17 119.11 132.06 157.96 183.85 209.75 235.64 261.53 287.43 313.32 339.22 365.12 391.01 416.90 468.69

A) Materials component
1 Cost of pipe per RMT 955.71 1168.09 1432.95 1698.63 2229.58 2760.53 3291.07 3822.02 4352.97 4883.51 5414.46 6476.36 7537.85 8599.75 9661.24 10722.73 11784.63 12846.12 13908.02 14969.92 16031.41 17092.90 19216.29

2 Cost of specials (1.50% of basic cost) 14.34 17.52 21.49 25.48 33.44 41.41 49.37 57.33 65.29 73.25 81.22 97.15 113.07 129.00 144.92 160.84 176.77 192.69 208.62 224.55 240.47 256.39 288.24

3 Transportation charges, loading, 16.37 20.01 24.54 29.09 38.19 47.28 56.37 65.46 74.55 83.64 92.73 110.92 129.10 147.29 165.47 183.65 201.83 220.01 238.20 256.39 274.57 292.75 329.11
unloading and stacking
986.40 1205.60 1479.00 1753.20 2301.20 2849.20 3396.80 3944.80 4492.80 5040.40 5588.40 6684.40 7780.00 8876.00 9971.60 ### 12163.20 13258.80 ### 15450.90 16546.40 17642.00 19833.60

B) Labour component
4 fabrication 256.41 313.39 384.45 455.73 598.18 740.63 882.97 1025.42 1167.87 1310.21 1452.66 1737.56 2022.35 2307.25 2592.04 2876.83 3161.73 3446.52 3731.42 4016.32 4301.11 4585.90 5155.59

5 Epoxy paint Out side 60.51 73.95 90.76 107.57 141.18 174.80 208.41 242.03 275.64 309.26 342.87 410.10 477.33 544.56 611.79 679.02 746.25 813.48 880.71 947.94 1015.17 1082.40 1216.86

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 241.03 294.59 361.38 428.39 562.29 696.19 829.99 963.89 1097.80 1231.60 802.00 987.00 1246.00 1433.00 1737.00 1921.00 1982.00 2044.00 2107.00 2316.00 2371.00 2427.00 2752.00

611.70 749.10 920.60 1092.50 1436.10 1779.70 2123.00 2466.60 2810.20 3153.60 2933.60 3538.00 4216.20 4822.60 5545.90 6149.10 6629.50 7110.70 7593.10 8221.40 8695.70 9170.90 10334.50
Total 1598.10 1954.70 2399.60 2845.70 3737.30 4628.90 5519.80 6411.40 7303.00 8194.00 8522.00 ### ### ### ### ### 18792.70 20369.50 ### 23672.30 25242.10 26812.90 30168.10
217.58 266.13 326.71 387.44 508.83 630.22 751.52 872.91 994.30 1115.61 1160.27 1391.78 1633.28 1865.06 2112.71 2344.00 2558.63 2773.31 2988.21 3222.98 3436.71 3650.58 4107.39
1815.68 2220.83 2726.31 3233.14 4246.13 5259.12 6271.32 7284.31 8297.30 9309.61 9682.27 11614.18 13629.48 15563.66 17630.21 19560.30 21351.33 23142.81 24936.11 26895.28 28678.81 30463.48 34275.49
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m 1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm 700 mm 800 mm 900 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm
Thickness in mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm 8 mm
Pressure rating (m)

1 Wt of pipe 17.362 21.308 26.240 31.172 41.037 50.901 60.766 70.631 80.495 90.360 100.224 119.954 139.683 159.412 179.141 198.870 218.600 238.329 258.058 277.787 297.516 317.246 356.704
2 Wastage (5%) 0.87 1.07 1.31 1.56 2.05 2.55 3.04 3.53 4.02 4.52 5.01 6.00 6.98 7.97 8.96 9.94 10.93 11.92 12.90 13.89 14.88 15.86 17.84
Total weight 18.23 22.38 27.55 32.73 43.09 53.45 63.81 74.16 84.52 94.88 105.23 125.95 146.66 167.38 188.10 208.81 229.53 250.25 270.96 291.68 312.40 333.11 374.54

A) Materials component
1 Cost of pipe per RMT 747.43 917.58 1129.55 1341.93 1766.69 2191.45 2616.21 3040.56 3465.32 3890.08 4314.43 5163.95 6013.06 6862.58 7712.10 8561.21 9410.73 10260.25 11109.36 11958.88 12808.40 13657.51 15356.14

2 Cost of specials (1.50% of basic cost) 11.21 13.76 16.94 20.13 26.50 32.87 39.24 45.61 51.98 58.35 64.72 77.46 90.20 102.94 115.68 128.42 141.16 153.90 166.64 179.38 192.13 204.86 230.34

3 Transportation charges, loading, 12.80 15.72 19.35 22.98 30.26 37.53 44.81 52.08 59.35 66.62 73.89 88.44 102.98 117.53 132.08 146.63 161.18 175.73 190.27 204.82 219.37 233.91 263.00
unloading and stacking
771.40 947.10 1165.80 1385.00 1823.40 2261.90 2700.30 3138.20 3576.60 4015.10 4453.00 5329.90 6206.20 7083.10 7959.90 8836.30 9713.10 10589.90 ### 12343.10 13219.90 14096.30 15849.50

B) Labour component
4 fabrication 200.53 246.18 303.05 360.03 473.99 587.95 701.91 815.76 929.72 1043.68 1157.53 1385.45 1613.26 1841.18 2069.10 2296.91 2524.83 2752.75 2980.56 3208.48 3436.40 3664.21 4119.94

5 Epoxy paint Out side 59.16 72.61 89.42 106.22 139.84 173.45 207.07 240.68 274.30 307.91 341.53 408.76 475.99 543.22 610.45 677.68 744.91 812.14 879.37 946.60 1013.83 1081.06 1215.52

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38 470.61 537.84 605.07 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14

8 Jointing of pipes (Rs:10.34 / kg) 188.50 231.41 284.87 338.43 445.55 552.67 659.80 766.81 873.94 981.06 783.00 967.00 1221.00 1406.00 1707.00 1889.00 1889.00 1661.00 1909.00 2197.00 2197.00 2197.00 3872.74

501.90 617.40 761.30 905.50 1193.80 1482.10 1770.40 2058.50 2346.80 2635.10 2618.20 3164.50 3780.80 4328.20 4991.60 5535.80 5898.20 6032.60 6642.90 7293.30 7655.60 8017.90 10418.30
Total 1273.30 1564.50 1927.10 2290.50 3017.20 3744.00 4470.70 5196.70 5923.40 6650.20 7071.20 8494.40 9987.00 ### ### ### 15611.30 16622.50 ### 19636.40 20875.50 22114.20 26267.80
173.36 213.01 262.37 311.85 410.79 509.75 608.69 707.53 806.47 905.42 962.74 1156.51 1359.73 1553.65 1763.35 1956.76 2125.48 2263.15 2465.57 2673.50 2842.20 3010.85 3576.36
1446.66 1777.51 2189.47 2602.35 3427.99 4253.75 5079.39 5904.23 6729.87 7555.62 8033.94 9650.91 11346.73 12964.95 14714.85 16328.86 17736.78 18885.65 20574.77 22309.90 23717.70 25125.05 29844.16
DATA BASED ON 2015-16 AS PER COMMON SSR

1 Earth work excavation in all soils upto SDR except hard rock
requiring blasting for 'MS 'pipes and refilling with excavated soils
including laying jointing testing of pipe line including cost of
materialsm CED and other taxes, etc complete

Cost of steel plate per MT Rs: ### including all taxes 33300 feb
a Fabrication charges Rs: 11.00 /kg as per SSR 2015-16
b Rate of Apoxy paint Rs: 1070.00 /10 sqm 33300
c Rate for Jointing of pipes Rs: 10.34 /kg
d Transportation charges Rs: 702.20 /MT

Trench size 0.90 x 1.20 m 0.90 x 1.30 m 1.00 x 1.40 m 1.1 x 1.6m 1.2 x 1.7m

Pipe dia in mm = 80 mm 100 mm 125 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm 600 mm
Thickness in mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm
Pressure rating (m)

1 Wt of pipe 12.725 15.685 19.384 23.083 30.482 37.880 45.279 52.677 60.075 67.474 74.872 89.669
2 Wastage (5%) 0.64 0.78 0.97 1.15 1.52 1.89 2.26 2.63 3.00 3.37 3.74 4.48
Total weight 13.37 16.46 20.35 24.23 32.00 39.77 47.54 55.31 63.08 70.84 78.61 94.15

A) Materials component
1 Cost of pipe per RMT 548.17 674.86 834.35 993.43 1312.00 1630.57 1949.14 2267.71 2586.28 2904.44 3223.01 3860.15

2 Cost of specials (1.50% of basic cost) 8.22 10.12 12.52 14.90 19.68 24.46 29.24 34.02 38.79 43.57 48.35 57.90

3 Transportation charges, loading, 9.39 11.56 14.29 17.01 22.47 27.93 33.38 38.84 44.29 49.74 55.20 66.11
unloading and stacking
565.80 696.50 861.20 1025.30 1354.20 1683.00 2011.80 2340.60 2669.40 2997.80 3326.60 3984.20

B) Labour component
4 fabrication 147.07 181.06 223.85 266.53 352.00 437.47 522.94 608.41 693.88 779.24 864.71 1035.65
5 Epoxy paint Out side 57.82 71.26 88.07 104.88 138.49 172.11 205.72 239.34 272.95 306.57 340.18 407.41

6 Epoxy paint Inside 53.78 67.23 84.04 100.85 134.46 168.08 201.69 235.31 268.92 302.54 336.15 403.38

8 Jointing of pipes (Rs:10.34 / kg) 138.25 170.20 210.42 250.54 330.88 411.22 491.56 571.91 652.25 732.49 812.83 973.51

396.90 489.70 606.30 722.80 955.80 1188.80 1421.90 1654.90 1888.00 2120.80 2353.80 2819.90
Total 962.70 1186.20 1467.50 1748.10 2310.00 2871.80 3433.70 3995.50 4557.40 5118.60 5680.40 6804.10
Add Contractor
131.07 161.50 199.80 238.00 314.51 391.00 467.50 543.99 620.49 696.90 773.39 926.38
Profit@13.615%
Total Cost 1093.77 1347.70 1667.30 1986.10 2624.51 3262.80 3901.20 4539.49 5177.89 5815.50 6453.79 7730.48
1.3 x 1.8m 1.4 x 1.9m 1.50 x 2.0m 1.6 x 2.1m

700 mm 800 mm 900 mm 1000 mm 1000 mm 1100 mm 1200 mm 1300 mm 1400 mm 1500 mm 1600 mm 1800 mm 1800 mm
6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm 6 mm

104.466 119.263 134.060 148.857 148.857 163.654 178.451 193.248 208.044 222.841 237.638 267.232 267.232
5.22 5.96 6.70 7.44 7.44 8.18 8.92 9.66 10.40 11.14 11.88 13.36 13.36
109.69 125.22 140.76 156.30 156.30 171.83 187.37 202.91 218.44 233.98 249.52 280.59 280.59

4497.29 5134.02 5771.16 6408.30 6408.30 7045.03 7682.17 8319.31 8956.04 9593.18 10230.32 11504.19 11504.19

67.46 77.01 86.57 96.12 96.12 105.68 115.23 124.79 134.34 143.90 153.45 172.56 172.56

77.02 87.93 98.84 109.75 109.75 120.66 131.57 142.48 153.39 164.30 175.21 197.03 197.03

4641.80 5299.00 5956.60 6614.20 6614.20 7271.40 7929.00 8586.60 9243.80 9901.40 10559.00 11873.80 11873.80

1206.59 1377.42 1548.36 1719.30 1719.30 1890.13 2061.07 2232.01 2402.84 2573.78 2744.72 3086.49 3086.49
474.64 541.87 609.10 676.33 676.33 743.56 810.79 878.02 945.25 1012.49 1079.72 1214.18 1214.18

470.61 537.84 605.07 672.30 672.30 739.53 806.76 873.99 941.22 1008.45 1075.68 1210.14 1210.14

1134.19 1294.77 1455.46 1616.14 1616.14 1776.72 1937.41 2098.09 2258.67 2419.35 2580.04 2901.30 2901.30

3286.00 3751.90 4217.90 4684.00 4684.00 5149.90 5616.00 6082.10 6547.90 7014.00 7480.10 8412.10 8412.10
7927.80 9050.90 ### ### 11298.20 ### 13545.00 ### ### ### 18039.10 20285.90 20285.90

1079.37 1232.28 1385.26 1538.25 1538.25 1691.16 1844.15 1997.14 2150.04 2303.03 2456.02 2761.93 2761.93

9007.17 10283.18 11559.76 12836.45 12836.45 14112.46 15389.15 16665.84 17941.74 19218.43 20495.12 23047.83 23047.83