Site Visit Report Conducted on 22.04.

2019 of Dediyapada Hostel at Navsari

Date of Visit:- 22.04.2019


Name of work:- Dediyapada Boys Hostel
Report Submitted to:- M/s Eco Architecture
Site Visited by:- Mr Harsh Kankadia (M.Tech Str)

This report was conducted after visiting site as mention above and remarks
of the same are listed below in table, column and foundation wise.

Column No. as per Status At Site While Visit on


Sr. No.
Structure Drawing 22.04.2019
1 C1 Foundation & Column casting completed upto Ground level with soil filling.

2 C2 Foundation & Column casting completed upto Ground level with soil filling.

3 C3 Foundation & Column casting completed upto Ground level with soil filling.

4 C4 Foundation & Column casting completed upto Ground level with soil filling.

5 C5 Foundation & Column casting completed upto Ground level with soil filling.

6 C6 Foundation & Column casting completed upto Ground level with soil filling.

7 C7 Foundation & Column casting completed upto Ground level with soil filling.

8 C8 Foundation & Column casting completed upto Ground level with soil filling.

9 C9 Foundation & Column casting completed upto Ground level with soil filling.

10 C10 Foundation & Column casting completed upto Ground level with soil filling.

11 C11 Foundation & Column casting completed upto Ground level with soil filling.

12 C12 Foundation & Column casting completed upto Ground level with soil filling.

13 C13 Foundation & Column casting completed upto Ground level with soil filling.

14 C14 Foundation & Column casting completed upto Ground level with soil filling.

15 C15 Foundation & Column casting completed upto Ground level with soil filling.

16 C16 Foundation & Column casting completed upto Ground level with soil filling.

17 C17 Foundation & Column casting completed upto Ground level with soil filling.

18 C18 Foundation & Column casting completed upto Ground level with soil filling.

19 C19 Foundation & Column casting completed upto Ground level with soil filling.

20 C20 Foundation & Column casting completed upto Ground level with soil filling.

21 C21 Foundation & Column casting completed upto Ground level with soil filling.

22 C22 Foundation & Column casting completed upto Ground level with soil filling.

23 C23 Foundation & Column casting completed upto Ground level with soil filling.

24 C24 Foundation & Column casting completed upto Ground level with soil filling.

25 C25 Foundation & Column casting completed upto Ground level with soil filling.

26 C26 Foundation & Column casting completed upto Ground level with soil filling.
27 C27 Foundation & Column casting completed upto Ground level with soil filling.

28 C28 Foundation & Column casting completed upto Ground level with soil filling.

29 C29 Foundation & Column casting completed upto Ground level with soil filling.

30 C30 Foundation & Column casting completed upto Ground level with soil filling.

31 C31 Foundation & Column casting completed upto Ground level with soil filling.

32 C32 Foundation & Column casting completed upto Ground level with soil filling.

33 C33 Foundation & Column casting completed upto Ground level with soil filling.

34 C34 Foundation & Column casting completed upto Ground level with soil filling.

35 C35 Foundation & Column casting completed upto Ground level with soil filling.

36 C36 Foundation & Column casting completed upto Ground level with soil filling.

37 C37 Foundation & Column casting completed upto Ground level with soil filling.

38 C38 Foundation & Column casting completed upto Ground level with soil filling.

39 C39 Foundation & Column casting completed upto Ground level with soil filling.

40 C40 Foundation & Column casting completed upto Ground level with soil filling.

41 C41 Foundation & Column casting completed upto Ground level with soil filling.

42 C42 Foundation & Column casting completed upto Ground level with soil filling.

43 C43 Foundation & Column casting completed upto Ground level with soil filling.

44 C44 Foundation & Column casting completed upto Ground level with soil filling.

45 C45 Foundation & Column casting completed upto Ground level with soil filling.

46 C46 Foundation & Column casting completed upto Ground level with soil filling.

47 C47 Foundation & Column casting completed upto Ground level with soil filling.

48 C48 Foundation & Column casting completed upto Ground level with soil filling.

49 C49 Foundation & Column casting completed upto Ground level with soil filling.

50 C50 Foundation & Column casting completed upto Ground level with soil filling.

51 C51 Foundation & Column casting completed upto Ground level with soil filling.

52 C52 Foundation & Column casting completed upto Ground level with soil filling.

53 C53 Foundation & Column casting completed upto Ground level with soil filling.

54 C54 Foundation & Column casting completed upto Ground level with soil filling.

55 C55 Foundation & Column casting completed upto Ground level with soil filling.

56 C56 Foundation & Column casting completed upto Ground level with soil filling.

57 C57 Reinf. Placing has been checked

58 C58 Reinf. Placing has been checked

59 C59 Reinf. Placing has been checked

60 C60 Reinf. Placing has been checked

61 C61 Reinf. Placing has been checked

62 C62 Reinf. Placing has been checked


63 C63 Foundation & Column casting completed upto Ground level with soil filling.

64 C64 Foundation & Column casting completed upto Ground level with soil filling.

65 C65 Foundation & Column casting completed upto Ground level with soil filling.

66 C66 Foundation & Column casting completed upto Ground level with soil filling.

67 C67 Foundation & Column casting completed upto Ground level with soil filling.

68 C68 Foundation & Column casting completed upto Ground level with soil filling.

69 C69 Foundation & Column casting completed upto Ground level with soil filling.

70 C70 Foundation & Column casting completed upto Ground level with soil filling.

71 C71 Foundation & Column casting completed upto Ground level with soil filling.

72 C72 Exacavtaion Pending

73 C73 Exacavtaion Pending

74 C74 Excavation done for fdn activity

75 C75 Excavation done for fdn activity

76 C76 Excavation done for fdn activity

77 C77 Excavation done for fdn activity

78 C78 Excavation done for fdn activity

79 C79 Excavation done for fdn activity

80 C80 Excavation done for fdn activity

81 C81 Excavation done for fdn activity

82 C82 Excavation done for fdn activity

83 C83 Exacavtaion Pending

84 C84 Exacavtaion Pending

85 C85 Exacavtaion Pending

86 C86 Exacavtaion Pending

87 C87 Exacavtaion Pending

88 C88 Exacavtaion Pending

89 C89 Exacavtaion Pending

90 C90 Exacavtaion Pending

91 Water tank Exacavtaion Pending


Important Notes:-
1) Stirrups for Column (C-1 to C-71) were not bend at 135º (Refer attached photo).Necessary
rectification to be done for stirrups.
2) Columns,Foundations exposed to environment should be properly cured.Additional care should be
taken due to high temperature and may use wet gunny bags to over lap the exposed column surface.
3) Concrete quality for some of the columns (C-1,C-4,C-20,C-27,C-33,C-34,C-37,C-39,C-61,C-62)
surface were found minor honey combing.Site incharge to take care of vibration during pouring of
concrete.
4) Site incharge to execute all details as per approved structure drawings and if any discrepancy
observed, its should be notified to structure engineer or in case should followed relevant Indian
Standards.
5) Contractor to take care of Founding levels of column and water tank and proper compaction below
foundation to be ensured.

Additional Notes:-
Engineer in charge (NAU) is to ensure maintaining grade of Concrete as specified in Structure
Drawing.