Beruflich Dokumente
Kultur Dokumente
Approx. Duration: 1-2 weeks Approx. Duration: 1-2 months Approx. Duration: 1-2 months Approx. Duration: 1-2 weeks Approx. Duration: 2-3 weeks
1. Application Submission 1. Preliminary Design 1. Pre-Construction Meeting 1. Blue Stake 1. Cutovers and Power Kills
• Customer submits application • The design reflects details • A TEP design team member will meet • TEP will request that • If needed, service panel
online at tep.com/construction discussed at the site meeting. with you or your representative to underground utilities are marked cutovers or temporary power
review the project design and schedule. before the project begins. kills will be scheduled in
2. Site Meeting 2. Customer Review advance.
• A discussion of project specifics • You can approve the 2. Billing/Contract Fulfillment 2. Dig
and a determination of overall preliminary design or • You may need to obtain easements, • TEP will conduct any necessary 2. Line and Meter Installation
electrical needs, system request changes. execute contract and/or submit excavation for a pole and/or • Connection of your service
requirements and whether TEP payment, if applicable anchor. is established and meter is
equipment will be installed 3. Approved Final Design Packet installed. A line extension may
overhead or underground. • This packet may include an 3. Customer Civil Construction 3. Haul be scheduled separately from
easement request and/or • You or your contractor will complete any • TEP will deliver a pole or other meter installation.
billing/contract, if applicable. necessary civil construction work and necessary equipment to the
schedule access to TEP’s facilities. work site.
5. TEP Inspections
• At your request, a TEP design team
member will determine if your property
satisfies all requirements for connecting
to TEP’s system.
6. Project Release
• You must obtain approval from your
local government (city or county) to
use your electric service panel. A copy
of the document granting jurisdictional
clearance must be provided to TEP.
Definitions and commonly used terms FAQ’S
• Easement – The legal right to use • Line Extension – The addition Q. How much will it cost to Q. Who is responsible for civil
the real property of another party of TEP lines and equipment establish a new electric construction?
for a specific purpose, such as necessary to deliver electric service connection?
A. The customer is ultimately
installation of an electric line. service to a customer.
A. Qualified applicants may be responsible for completing
eligible for line extensions the civil construction work as
• Jurisdictional Clearance – • Service Entrance/Panel – The
up to 500 feet at no cost. outlined by TEP’s design team
Approval by the local governing connection point where TEP’s
Qualifications will be member. The extent of civil
agency that declares that all work electric facilities connect to your
determined by your TEP design construction will be determined
specified in the building permit is electrical system. This is where
team member. Billing may be by the type of service - either
in accordance with the agency’s TEP’s meter will be installed.
on a per foot or actual cost overhead or underground – and
standards and requirements.
basis, some of which may be other factors.
• TEP Equipment Access
refundable.
• Power Kill – A task performed Appointment – A scheduled
Q. What if I have additional
by TEP to de-energize an electric appointment with a TEP crew
Q. How long will it take to develop questions not addressed in
service panel. member to gain access to
a new line extension? this guide?
an energized piece of TEP
• Civil Construction – Work equipment. A. It typically takes 4 to 5 months, A. Scan the QR code below or visit
including but not limited to depending on project scope. tep.com/construction to find
trenching, backfilling, grading • Cutover – A transfer of electric more helpful resources.
and material installation in service from an existing service Q. Will my service connection
preparation for utility work. panel to a new panel. be developed overhead or
underground?
A. That determination depends
on several factors that will be
discussed during your initial
meeting with a TEP design
team member.
tep.com
SC - 11/16