Beruflich Dokumente
Kultur Dokumente
Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 1 of 53
PROJECT/CONTRACT REF.:
This plan has been developed specifically for Dana-Kusma 220 kV Transmission line
and Associated Substations Safety Management objectives and practices that are to
be implemented, to manage the Safety, Health and Environment issues of the Project,
for Jv of TPL & CHINT, its employees and subcontractors. It is the private property of
Jv of TPL & CHINT and without their consent must not be shown or given to any third
party or used by the recipient for purposes other than those for which they are issued.
Recipients are responsible for destroying all superseded documents in their
possession.
Sunil Choudhary/Amit
Checked by: Saurav Sharma Prepared by: Kumar
Signed: Signed:
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Abbreviations:
GM General Manager
IS Indian Standard
SO Safety Officer
SE Site Engineer
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
SLI Safe Load Indicator
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
TBT Tool Box Talks Issued: 20.01.2017
Page Page 3 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 4 of 53
Table of Contents
1.0 SCOPE OF WORK ............................................................................ 6
1.1 Objectives ........................................................................................................................ 7
2.0 Reference………………………………………………………………………………. 7
3.0 COMMITMENTS .............................................................................. 8
3.1 Health, Safety & Environment Policy .......................................................................... 8
3.2 Vision, Mission, Values................................................................................................ 8
4.0 ACCOUNTABILITY FOR SAFETY .................................................... 9
4.1 Management Responsibilities ....................................................................................... 9
4.2 Responsibilities of site management .......................................................................... 10
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 6 of 53
SCOPE OF WORK
Outline scope of work covers for the execution of “220 kV Dana- Kusma Transmission Line
Project and associated 220 kV Substation” under Nepal Electricity Authority in Nepal.
These include:
Substations:-
Scope for Construction of new 220 kV/132kv /33kV Substation at DANA & Construction of
new 220 kV/132kV Substation at KUSMA
As per the Contract Agreement no. PMD- KGTCP-071/72-03, Volume-II (Part-B (I),
Substation) OF III under Chapter 1 (Project Specification requirement) and clause no.
2.2.1(A) Construction of a new 220/132/33 kV substation at Dana, Nepal &
As per the Contract Agreement no. PMD- KGTCP-071/72-03, Volume-II (Part-B (I),
Substation) OF III under Chapter 1 (Project Specification requirement) and clause no.
2.2.1(B) Construction of a new 220/132/ kV substation at Kusma, Nepal.
There are specific phases of the project for which individual Job Hazard Analysis /Risk
Assessment and Method Statements will be prepared, addressing issues of Health and Safety and
Environment. This Job Hazard Analysis/Risk Assessment shall be in accordance to Jv of TPL &
CHINT procedure HSE MANUAL TSF-011 Hazard Identification & Analysis Procedure
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 7 of 53
1.1 Objectives
To ensure compliance with applicable legal requirements and other requirements related to
environmental aspects of its operations.
To meet JV of TPL & CHINT, and Nepal Electricity Authority expectations and to
conduct all activities consistent with Jv of TPL & CHINT applicable HSE Policies.
To prevent injury to anyone and to safeguard human lives, property and the environment.
To promote and establish the highest standards of safety to benefit both Nepal Electricity
Authoturiy and Jv of TPL & CHINT through prevention of accidents and thereby
promote increased productivity, reduced schedule disruptions and mitigate the effects of
any accidents/ incidents.
To increase safety consciousness and awareness among Jv of TPL & CHINT employees
and subcontractors by uplifting the safety standards and setting the trend in safety
excellence through established goals and objectives, training programs, audits and
motivations.
Jv of TPL & CHINT shall ensure that all of its personnel and subcontractors engaged in
these works commit to these same Quality & HSE principles and shall establish and utilize
programs that ensure the requirements are achieved.
2.0 REFERENCES
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 8 of 53
3.0 COMMITMENTS
Jv of TPL & CHINT Management considers the health and safety of our employees, visitors,
guests and neighbours together with protection of the environment as fundamental to achieving
business excellence.
This policy is communicated to all employees and is made available to all interested parties.
We realise that our most valued assets are the employees and their health and safety is of utmost
importance to our business.
Both the management and employees consider themselves as a team and are responsible for working
together to accomplish the common goal of Safe, Healthy and Environmentally compliant
workplace.
Jv of Tata
To be India’s premier ProjectsProcurement
Engineering, Limited andandCHINT Electric Co. Ltd
Construction
Company and “Be Ahead” of expectations of all its stakeholders
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 9 of 53
MISSION:
To make or clients successful, while creating stake holder value, with uncompromising
quality and safety standards.
To create a culture that excites our people in pursuit of excellence through innovation,
differentiation and continued learning.
To uphold TATA Group’s cherished value of contributing to the society to improve the
quality of life.
VALUES:
Good Corporate Citizenship
Humility and willingness to learn
Concern for all stakeholders
Business with ethics
Passion for excellence
Teamwork
Safety is a fundamental to the operations of Jv of TPL & CHINT and its primary objective is to
have an accident free project execution. It is everyone’s responsibility to understand the
requirements for working safely and protecting themselves and others. To achieve this goal the
following accountabilities are expressed, to assist all personnel in understanding their more
specific responsibilities.
BU– HEADS / HODs: BU Heads/ HOD’s are members of the company EHS
Management Committee and are responsible for review and implementation of HS
management in the respective areas under their control and provide necessary resources.
PROJECT MANAGER: Project Manager is overall responsible for the EHS
Management related to persons working in the project sites with
him. Jv of Tata Projects Limited and CHINT Electric Co. Ltd
o PM with the help of REHS Coordinator prepares project
specific safety instructions taking into consideration the local applicable legal
Ref:TPL/EHSMP/DKSS/001
Safety, Health
requirements, & Environment
in addition Management
to the relevant Plan of safety instructions
portions Rev: 00
of the
company. Issued: 20.01.2017
o PM will ensure that a site specific EHS committee is formed by Page projectPage 10 of 53
Manager
within 15 days of job starting.
EHS COORDINATOR:
EHS- COORDINATOR ensures EHS system requirements are implemented and
maintained in the organization including sites.
Safety Officer visits worksite daily and maintain a diary in which his observations
with respect to EHS performance will be entered, including the instructions given
by him at the site.
Safety Officer inspects the condition of PPE prior to issue and after usage at
regular intervals.
Safety Officer ensures that sufficient awareness is created by display of safety
posters, slogans etc.
Safety Officer conducts safety audits along with workmen representative at least
once in a month and his observations will be recorded and a copy will be given to
RCM for necessary action.
Safety Officer conducts investigation / enquiry into the accidents dangerous
occurrences.
Safety Officer sends weekly/monthly/near miss/accident reports to the REHS
Coordinator and the management
Jv of TPL & CHINT HSE personnel will participate in Hazard Identification/Risk
Assessment to ensure all precautions are being taken to ensure the Safety and well-
being of employees is protected and to eliminate personnel injury and damage to
property, and encourage the participation of labour force representatives
Toolbox Talks will be conducted at all work locations prior to commencement of
any work. A separate Toolbox Talk will be conducted before start up of any
specific works.
SITE ENGINEER: Site Engineers are directly responsible for the implementation of the
safety norms at site and to ensure all their personnel understand and comply with HSE
procedures that relate to their job activities.
Directly responsible for maintaining safe working conditions, utilization of safe
practices, the safety of personnel under their control and the safety of others
affected by the activities of their personnel.
To ensure that safety induction has been given to the site personnel working under
them on first day by the Safety Officer.
Jv of
To TataSafety
inform Projects Limited
Officer and CHINT
regarding Electric
any new activityCo. Ltd
being
started in their area and to ensure that Toolbox Talks prior to
the start of the particular work has been conducted by the Safety Officer.
Ref:TPL/EHSMP/DKSS/001
Safety,
Participate in Health & Environment
the investigation of allManagement Plan
near miss incidences and accidents,
Rev: 00 to ensure
timely action may be taken to prevent recurrence. Issued: 20.01.2017
All contractors shall ensure that Jv of TPL & CHINT HSE standards & procedures along with
Nepal Electricity Authority requirements shall be strictly adhered.
Subcontractor Management is expected to actively and adequately promote safe working
performance on the part of their employees.
Subcontractors must ensure that their employees are competent and qualified to carry out their
specific tasks. Necessary documents pertaining to the qualifications and certification must be
submitted for evaluation and approval from Jv of TPL & CHINT HSE Departments.
All necessary PPE’s as enlisted in Appendix-5 shall be provided by the contractor. All such
items should comply with JV OF TPL & CHINT specifications.
All contractors should ensure that their workers have been given safety Induction by JV OF
TPL & CHINT Safety officer.
All subcontractors should ensure that the non-conformities found during the monthly audits by
the SO are closed within the stipulated period.
Subcontractor should arrange for all site facilities of their workers viz.First Aid, drinking
water, toilets, waste bins on suitable location at the site.
Subcontractor should deploy a qualified/experienced safety supervisor at site who will work in
close co-ordination with JV OF TPL & CHINT Safety Officer and will be responsible for
implementation of safety norms at site. The credentials of the safety supervisors must be
submitted to the Jv of TPL & CHINT HSE department for approval.
Subcontractors should ensure that all the equipment’s and tools and tackles (Crane, Hydra,
slings, shackles etc.) being used at site is duly certified by competent authorities. A copy of
these certificates should be submitted to Jv of TPL & CHINT HSE Dept. for verification,
approval and rec.
All subcontractors will be issued a copy of OCP’s. All works should be carried out in
compliance to them.
All penalties (Weather worker or subcontractor) will be deducted from the bills of the
subcontractor.
All subcontractors
Jv of Tata Projects Limited
are advised and
to follow anyCHINT Electric given
other guidelines Co. Ltd
by
Jv of TPL & CHINT SO as per site specific requirements.
Jv of TPL & CHINT HSE Department shall ensure that all new recruits & subcontractors attend
the mandatory HSE induction at Jv of TPL & CHINT Safety Department prior to their deployment
at worksite
Jv of TPL & CHINT HSE MANAGER shall then ensure that Jv of TPL & CHINT employees &
Subcontractor personnel attend site Induction training.
All Jv of TPL & CHINT personnel shall attend mandatory trainings/briefing on OHSE, Fire &
Environmental Awareness prior to enter/work at Nepal Electricity Authority site.
Jv of TPL & CHINT shall ensure that appropriate HSE Trainings/Awareness applicable to Project
be provided/given to Jv of TPL & CHINT employees & subcontractor personnel for skill
enhancement. Training Matrix will be maintained
Jv of TPL & CHINT shall ensure that certificates for training have been obtained prior to work on
site.
Jv of TPL & CHINT shall provide a competent person as translator when needed and evaluate
comprehension through a series of questions and answers
Retribution clauses
To enforce workforce regarding implementation of HSE norms at site retribution clause will be
applicable. This shall be managed by Jv of TPL & CHINT’s RCM &
Jv of Tata
HSE Manager Projects
on whose Limited
decision it shalland CHINT Electric Co. Ltd
be binding.
Following may be included in “Tool Box Talks” as and when applicable (not exhaustive):
Emergency Procedures
Muster points/ alarms
PPE
Site Safety Regulations
Housekeeping
Fire Prevention
Safe Working Practices
Employees Safety Responsibility
Eye Protection
Tools
Short Cuts
Confined Space Safety
Near Miss
Cylinders
Scaffolding
Preventing Accidents
Deep Excavations
Restricted Areas Working
Permit To Work (PTW)
Lifting
Rigging
Manual Material Handling
Pressure tests
Electrical Safety
HSE Organisation Chart- Appendix A
Jv of TPL & CHINT HO will conduct an internal system audit at least once in a year. A detailed
program for the same will be sent to all sites prior to the audit.
Jv of TPL & CHINT Safety Officer shall conduct a periodic HSE Audit Programme/HSE Performance
Site Monitoring in accordance with Jv of TPL & CHINT standards. The findings shall be forwarded to
the Jv of TPL & CHINT HO and RCM. Jv of TPL & CHINT Project SO & RCM shall follow-up all
outstanding items. Corrective actions shall be implemented. Copy of HSE Audit/HSE Performance
Site Monitoring Report shall be retained by the Jv of TPL & CHINT HSE Department.
Findings of the daily HSE Supervisors inspections are logged in individual field books and daily
inspection sheets. HSE Supervisors check daily and ensure that all deficiencies that have been noted
are corrected / rectified promptly. HSE Manager shall ensure likewise that appropriate rectification is
religiously done in coordination with the Project Management Team.
Periodic HSE Inspection /Walk Around shall be organized by Jv of TPL & CHINT HSE Department
along with Nepal Electricity Authority, HSE Department personnel. Deficiency notices are utilized
and issued per group/ discipline to ensure rectifications are made. Concerned personnel are notified of
any deviation with corresponding recommended corrective actions. HSE Department shall follow up to
ensure safe continuation of the construction activities.
Jv of TPL & CHINT HSE Manager shall carry-out a regular site visit in which spot inspection/walk
around may be carried-out. Findings will be documented & issued to Project HSE Department &
Project Manager for rectification.
5.1.7 DOCUMENTATION
Jv of TPL & CHINT shall evolve a comprehensive, planned and documented system for implementation
and monitoring of the HSE requirements. This shall be submitted to Client for approval. The monitoring
for implementation shall be done by regular inspections and compliance to the observations thereof. Jv of
TPL & CHINT Contractor shall get similar HSE requirements implemented at his sub-contractor(s) work
site / office. However, compliance of HSE requirements shall be the responsibility of the Jv of TPL &
CHINT. Any review / Client shall not absolve contractor of his responsibility / liability in relation to all
HSE requirements.
Jv of TPL & CHINT shall be fully responsible for planning, reporting, implementing and monitoring all
HSE requirements and compliance of all laws and statutory requirements. The Contractor shall also ensure
that the HSE requirements are clearly understood and faithfully implemented at all levels at site.
5.1.9 AWARENESS
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Jv of TPL & CHINT shall promote and develop consciousness about Health,
Safety and Environment among all personnel working for the Contractor. Regular awareness programmes
Ref:TPL/EHSMP/DKSS/001
Safety,
and fabrication shop / work siteHealth & Environment
meetings Management
shall be arranged Plan
on HSE activities to cover hazards
Rev:
involved in
00
various operations during construction. Issued: 20.01.2017
Page Page 16 of 53
5.1.10 INTOXICATING & DRUGS
Jv of TPL & CHINT shall ensure that his staff members & workers (permanent as well casual) shall not be
in a state of intoxicating during working hours and shall abide by any law relating to consumption &
possession of intoxicating drinks or drugs in force. Awareness about local laws on this issue shall form
part of the Induction Training.
5.2 HOUSEKEEPING
Jv of TPL & CHINT shall ensure that a high degree of house keeping is maintained and shall
ensure interalia; the followings:
All surplus earth and debris are removed / disposed off from the working areas to designated
location(s).
Unused / surplus cables, steel items and steel scrap lying scattered at different places within the
working areas are removed to identify location(s).
All wooden scrap, empty wooden cable drums and other combustible packing material, shall be
removed from work place to identified location(s).
Roads shall be kept clear and materials like pipes, steel, sand, boulders, concrete, chips and bricks
etc., shall not be allowed on the roads to obstruct free movement of men and machineries.
Fabricated steel structural, pipes and piping materials shall be stacked properly for erection.
Water logging on roads shall not be allowed.
No parking of trucks / trolleys, cranes and trailors etc. shall be allowed on roads, which may
obstruct the traffic movement.
Utmost care shall be taken to ensure over all cleanliness and proper upkeep of the working areas.
Trucks carrying sand, earth and pulverized materials etc. shall be covered while moving within the
plant area / or these materials shall be transported with top surface wet.
The contractor shall ensure that the atmosphere in plant area and on roads is free from particulate
matter like dust, sand, etc. by keeping the top surface wet for case in breathing.
At least two exists for any unit area shall be assured at all times
Jv of Tata
When materials Projects
are stored, theyLimited
shall be and CHINT
segregated as Electric Co. and
to kind, size, Ltd
length such that they are safe against falling. Piles higher than one meter
shall be stepped properly and they shall be arranged such that they allow a passage way at least
one meter wide.Safety, Ref:TPL/EHSMP/DKSS/001
Healthway
All passage & Environment Management
shall be kept clear Plan
at all times.
Rev: 00
Issued: 20.01.2017
If the material storage yard is near a public place, it shall be fenced and shall have
Pagesuitable waning
Page 17 of 53
sings.
In any case, stair ways, gangways and passages shall not be obstructed by the materials.
All flammable liquids like petrol, thinners, etc, shall be stored in conformity with the relevant
regulations.
A first aid facility shall be maintained during execution of all types of construction and erection
work.
An appropriate first aid facility, including an adequate number of stretchers, shall be maintained at
all construction sites.
The Contractors shall make arrange for a medical attended who is at least a Para- medical
health worker to examine and advice on workers’ health regularly once a month.
Adequate fire fighting equipment shall be provided on building construction, erection and
stringing site. The Composition and number of pieces of such equipment shall be determined by
the Engineer.
All electric power lines shall be disconnected or isolated before commencing any construction
activities.
Housekeeping should be maintained by utmost importance.
The type and the design of the foundation adopted shall be such as to allow safe construction
practices and the protection of neighbouring properties.
The method of construction of a foundation construction activity such as pile-driving, the required
measures for reinforcing the adjoining properties safety during each activity shall be undertaken.
While works are undertaken in deep excavations, adequate measures shall be taken against
collapse of the walls of the excavation.
When the slope of the roof is more than 30 degrees to the horizontal, workers shall be provided
with catch- ropes and belts.
When roofs are to be covered with corrugated iron sheet or asbestos cement sheet, or similar each
joist shall be fixed securely so as to prevent slippage during construction.
Workers shall no tbe allowed to wal directly on asbestos cement sheet.
Loose tiles shall not be kept on a roof during the tile-laying operation. All loose tiles shall be kept
on the scaffolding.
During the wet season , the Engineer or his representative shall inspect a sloping roof and satisfy
himself as to its safety before allowing any workers to go on to it.
Jvconstruction
During the of Tata Projects Limited
of reinforced androofs,
concrete CHINT Electric
workers shallCo. Ltd
not be
allowed to walk over the reinforcement. A waling platform shall be
provided where necessary.
Railing or otherSafety, Health
protective & Environment
guarding Management
shall be provided Planedges to preventRef:TPL/EHSMP/DKSS/001
on all roof workmen
Rev: 00
falling.
Issued: 20.01.2017
Page Page 19 of 53
Bare wires shall not be used for any type of electrical connection.
All Electric wires laid over a floor during construction shall be covered to protect them from
moving machinery and workmen.
Overhead wires shall be so installed that they leave minimum 4.50 cm headroom over the
construction site.
All electrical circuits other than those required for work or illumination of the works at night shall
be switched off after the day’s work.
No loose material, clothing or other combustible substance shall be placed or kept over the electric
switch off after the day’s work.
One 4.5 kg CO2 extinguisher ro noe 5 kg dry powder extinguisher as a minimum shall at all times
be kept near the switch board.
All permanent electrical lines and all other wiring shall be installed by a competent and qualified
electrician under the strict supervision of the Engineer. When construction is being undertaken
close to exposed high or low tension lines, all such cables shall be covered with insulation
materials so as to avoid possibility of electrocution of workers.
No cables or electrical equipment shall be placed over wet floor.
Temporary works shall be designed to take at least one and half times their expected load. They
shall be approved by the Engineer or his representative.
All false work and formwork shall be securely tied to the permanent structure.
All ladders shall be secured at both ends.
The height or length of a ladder shall be at least one meter than the height it is intended to serve.
A guard-or hand-rail shall be provided at the side of the ladder.
Traffic Management
Cautionary boards
Mandatory Boards
Informationary boards.
Speed Limit
Speed limits for vehicles shall be maintained in site premises as well as on road. All drivers shall follows
speed limit as given below.
At Construction site (inside site premises) - 15 km/Hr
Near Village - 30 km/Hr
Highway - 60 km/Hr.
All road accident / incidents shall be reported and thoroughly investigated and reported in designated
format to Client as per their requirements.
Machines, equipment’s and vehicles are potential source of the air pollution. The main Pollutants, which
will come out from different construction activities would be Suspended Particulate Matter (SPM). The
main sources of air pollution are:-
Exhaust coming out from different equipment’s.
Dust generated as the result of different construction activities.
Dust and suspended particles during transportation of material.
All engaged workforce at construction sites shall wear the reflective jacket for high visibility..
Sanitation & Hygiene in conformance to Jv of TPL & CHINT procedure At Site Housekeeping, Sanitation
& Hygiene.
General Requirements
Clear access shall be maintained to emergency exits at all times.
Clear access shall be maintained to fire fighting equipment, alarm points, confined spaces,
entrance, exit and first aid clinic.
When not in use, materials, tools, equipment shall be properly stored.
Rubbish shall be removed from the work site at the end of every day
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Suitable bins will be provided for general site debris. Disposal of these
wastes from the work site will be determined by the amount of waste accumulated. Storage of
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
waste with in the plant site shall be minimized and of minimal duration.
Issued: 20.01.2017
Foreman, Charge Hand or Supervisors shall conduct daily inspections on their Page
respectivePage 21 of 53
areas and
see that they complying with good rules of house keeping. Verification of clean work location
prior to commencement of work activities shall be done at each shift.
All boards shall be promptly de-nailed upon removal and nails shall be collected and disposed of in proper
containers.
6.0 NEAR MISS/ACCIDENT/ INCIDENT REPORTING
Reporting shall be in accordance with Jv of TPL & CHINT procedure TSF- 001.
All accidents/incidents & near misses shall be recorded, reported to Nepal Electricity Authority
immediately and investigated. Generated reports must be submitted within 24 hrs
For the purpose of accident reporting and investigation, TSF-001 & TSF-002 should be used.
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 22 of 53
Jv of TPL & CHINT shall follow & respond in any unlikely emergency event in compliance to the
Principals Evacuation Procedure. Jv of TPL & CHINT shall develop and implement emergency
procedures. Jv of TPL & CHINT shall ensure that all its staff and personnel are fully familiar with the use
and location of the essential emergency equipment such as fire extinguishes, fire exits, muster points and
plant alarms. The typical contents of such procedure are:
This Procedure will be clearly emphasized & cascaded from top Management down to the workers during
Site Induction Training:
Contact Details, Location of First Centre and Location of fire extinguishers as per TSF-005,006 & 007
shall be displayed on prominent places at the site and should be informed to all workers in the tool Box
Talks.
The Emergency Preparedness procedure shall be reviewed by PM/SO at least every six months.
An onsite emergency response team may be established. External emergency services will be utilized to
support the emergency response team, as their responsibility will be to stabilize the emergency until
external assistance arrives.
FIRE EXPLOSION
In Case you notice a fire does the following:
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Rush to the spot and take charge of the rescue and control work.
Be concerned about your own safety and that of others Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Shout, “Fire Fire”, raise an alarm and call for help from colleagues
Issued: 20.01.2017
If the fire is small, attempt it to extinguish by using the nearest fire Page
extinguishers Page 24 of 53
available,
without undue personal risk
At the same time, inform fire station, main gate and PM/SO. While reporting state:
Your name
What happened?
Location of Incident
Instruct security staff to cordon off the affected area and guide the fire brigade personnel to the
exact location of the fire and render all possible assistance to them.
Keep all spectators and non – essential employees away from fire.
If required, switch off the electrical supply, taking adequate care
Try to remove flammable / dangerous materials lying in the vicinity without endangering yourself.
If explosive type materials are involved immediately evacuate all personnel
Count number of people involved and organize rescue of any trapped personnel with the help of
the fire brigade.
Make no comments. Refer all inquiries to the company Project Manage.
EARTHQUAKE
If you are inside the office building when an earthquake occurs:
Stay under until the shaking stops.
Stay away from windows, large panels of glass, ceiling tiles, file cabinets, book cases, heavy
furniture, electrical equipment and appliances.
Crawl under a desk or sturdy table and hold onto it. If it moves, move with it.
Move to a clear area from unbalanced/ unsupported / partly erected structure / equipment’s /
buildings and electrical wires and poles that may fall.
Stay clear of falling objects and find a place duck, cover and hold on.
Stay near an interior wall and protect your head with your arm.
GAS/TOXIC RELEASE
JvTry
oftoTata Projects
identify Limited
the source of leak,and CHINT Electric Co. Ltd
if possible.
Wind directions
Warn people in the vicinity/neighbouring environment.
Inform seniors
Inform fire station. Instruct main gate to blow emergency siren.
Take charge of the site and direct efforts to contain and control the leak
by getting isolating valve closed, specific machinery is switched off. If leak
Isolation is not possible; arrange transfer of materials into another tank of low level
and pressure.
Get the movement of vehicles away from the source and cordon off the
area.
Use a wet cloth to cover your nose in case of breathing difficulty and move away
from the source of toxic release.
Contagious Diseases
Bar all entry to visitors
Inform Medical Regulatory bodies about the incident immediately
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Isolate the area from Personnel Movement except those related to Medical
Relief Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Declare Emergency Situation if required Issued: 20.01.2017
Control Mob / onlookers Page Page 27 of 53
Mobilize Medical teams, Medical Supplies, Movement Vehicles, Associated Hospitals / Labs
Ensure Electricity supply and Communication
Ensure Essential supply of Medical Team
Inform Relatives of the affected people and arrange their travel as required
Check for communication to interested parties including neighbours and statutory and
regulatory bodies
Open Helpline at affected site
Upon deciding shifting affected persons to identified hospitals, shift the personnel
Deploy assistance teams at the hospitals as required
OHS coordinator shall report formally both internally and to statutory and regulatory bodies about
the incident
Handle Media and External communication as per policies
Prepare Report of the situation
Electric Shocks
Isolate the affected circuit from electric supply
Provide first-aid to the injured for
Shock
Burns
Temporary breathlessness
Declare Emergency Situation if required
Control Mob / onlookers
Depending on the nature of injury, decide to shift the patient to the Medical assistance or request
Medical assistance on-site through ambulance
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Install sign boards on the affected circuits
Repair, Rectify and Restore the healthiness of the circuit involved Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
If required, informed statutory and regulatory bodies for any checks and validations before using
Issued: 20.01.2017
the affected facility. Page Page 28 of 53
Update records for further analysis for corrective and preventive action
Fall from Height
Provide First-Aid to the injured personnel
Isolate area from operations
Declare Emergency Situation if required
Control Mob / onlookers
Mobilize support and shift injured to medical room
Arrange for taking injured home after Out-patient treatment
If necessary, admit injured to the hospital. Coordinate patient / Hospital Needs
Inform statutory and regulatory bodies as needed
Rectify and check for healthiness of the area
Restore site condition to safe normal situation
Prepare Report of the situation
Handle Media and External communication as per policies
Update records for further analysis for corrective and preventive action
Hit by Moving Vehicles
Provide First-Aid to the injured personnel
Isolate area\vehicle from operations
Control Mob / onlookers
Mobilize support and shift injured to medical room/Hospital
Arrange for taking injured home after Out-patient treatment
If necessary, admit injured to the hospital. Coordinate patient / Hospital Needs
7.3 Jv ofFacilities:
First Aid Tata Projects Limited and CHINT Electric Co. Ltd
Jv of TPL & CHINT shall provide First Aid Boxes at every site equipped with
– H for Details) Ref:TPL/EHSMP/DKSS/001
Safety,
basic First Aid Medicines Health
(Refer & Environment
Appendix Management Planits employees and
on site for
Rev:
workmen. This
First Aid shall be manned by a qualified First Aider as required. Inventory of Medicines shall00 be carried
Issued: 20.01.2017
out on a monthly basis and a register will be maintained. Page Page 29 of 53
Refer Appendix – A
Appendix – A HSE Organization Chart
BU HEAD
HEAD OPERATIONS
REHS
COORDINATOR
PROJECT
DIRECTOR
PROJECT
COORDINATOR
RESIDENT
CONSTRUCTION
MANAGER (RCM)
SAFETY STORE
STEWARD (SS) ASSISTANTS
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 30 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 31 of 53
APPENDIX – C
CONSTRUCTION HAZARDS, THEIR EFFECTS & PREVENTIVE MEASURES
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
(A) Failing into Personal Provide guard rails / barricade with
EXCAVATION pit Injury warning signal
Provide at least two entries /exists
Provide escape ladders
Pit Excavation up Earth Suffocation Provide suitable size of shoring and
to 3.0 M Collapse Breathlessness strutting, if required.
Buried Keep soil heaps away from the edge
equivalent to 1.5m or depth of pit
whichever is more.
Don’t allow vehicles to operate too close
to excavated areas. Maintain at least 2m
distance from edge of cut.
Maintain sufficient angle of repose.
Provide suitable and stable slope as per
the condition of Soil.
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 32 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 33 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 34 of 53
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Falling of May prove Use helmets
material from fatal Do not throw any material, tools or
height equipment from the height. Tool- kit bag
to be used.
Transportation Protruded rods Use red flags / lights at the ends
of rods by may hit the Do not protrude the rods in front of or by
trucks / persons the side of driver’s cabin.
trailers Do not extend the rods 1/3rd of deck
length or 1.5m whichever is less.
(D) WELDING Welding Radiation can Use specified shielding devices and other
AND GAS radiates damage eyes PPE of correct specifications.
CUTTING invisible and skin Avoid throated tungsten electrodes for
ultraviolet and GTAW( Gas Tungsten Arc Welding)
infrared rays
Improper Explosion may Move out any leaking cylinder
placement of occur Keep cylinders in vertical position
oxygen and Use trolley for transportation of cylinders
acetylene and chain them
cylinders Use flashback arrestors.
Leakage / cuts May cause fire Purge regulators immediately and then
in hoses turn off.
Never use grease or oil on oxygen line
connections and copper fittings on
acetylene lines.
Inspect regularly gas carrying hoses.
Always use red hose for acetylene and
other fuel gases and black for oxygen.
Opening up of Cylinder may Always stand back from the regulator
cylinder burst while opening the cylinder.
Turn valve slowly to avoid bursting.
Cover the lug terminals to prevent short
circuiting.
Welding of Explosion may Empty & purge them before welding
tanks, occur Never attach the ground cable to tanks,
container or container or pipe storing flammable
pipes storing liquids
flammable Never use LPG for gas cutting.
liquids
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 35 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 36 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 37 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 38 of 53
May hit the Keep the work place neat and clean
scrap / material Remove the scrap immediately.
stacked at the
ground or in
between.
Material can fall May hit the Same as above plus
down workers Do not throw or drop materials or
working at equipment from height. i.e., do not
lower levels bomb materials
and prove fatal All tools to be carried in a tool-kit
Bag.
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 39 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 40 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 41 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 42 of 53
(K) Personal Can cause injury Do not take rest inside rooms built
STRUCTURAL negligence and or casualty for welding machines or electrical
WORKS danger of fall distribution system.
Avoid walking on beams at height.
Wear helmet with chin strap and
full body harness while working at
height.
Use hand gloves and goggles during
grinding operations.
Cover or mark the sharp and
projected edges.
Do not stand within the operating
radius of cranes.
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 43 of 53
Appendix – D
TATA PROJECTS LTD
LIST OF OPERATIONAL CONTROL PROCEDURE
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 44 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 45 of 53
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 46 of 53
Electrical fires
G G e e E
G : NOT TO BE USED
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 47 of 53
APPENDIX – G
B. For establishments in which the number of contract labour exceeds fifty, each first aid box
shall contain the following equipment:
i. 12 small sterilized dressings.
ii. 6 medium size sterilized dressings.
iii. 6 large size sterilized dressings.
iv. 6 large size burn dressings.
v. 6 (15 gms) packets sterilized cotton wool.
vi. 1 (60 ml) bottle containing a two percent alcoholic solution of iodine.
vii. 1 (60 ml) bottle containing savelatile having the dose and mode of administration indicated
on the label.
viii. 1 roll of adhesive plaster.
ix. A snake bite lancet
X 1 (30 gms) bottle of potassium permanganate crystals.
xi. 1 pair scissors.
xii. 1 copy of the first aid leaflet issued by the Director General, Factory Advise Service and
Labour Institute, Government of India.
xiii Ointment for burns.
xiv. A bottle of suitable surgical antiseptic solution.
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 48 of 53
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 49 of 53
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 50 of 53
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 51 of 53
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 52 of 53
Jv of Tata Projects Limited and CHINT Electric Co. Ltd
Ref:TPL/EHSMP/DKSS/001
Safety, Health & Environment Management Plan Rev: 00
Issued: 20.01.2017
Page Page 53 of 53