Project: Construction of 40 footer HC Container customized

Location: ICE International Technologies Inc., Philexcel Clark Freeport Zone.

Duration: 14 days Calendar days.

Scope of work:

The scope of is to supply of labour, transportation and equipment for completion of the project.

1. Set up and layout of equipments and frames.


2. Application o f primer paint.
3. Assembly of frames and support, this includes all fit in and fixing works.
4. Assembly of wall panels and roofing’s.
5. Housekeeping and clearing after the completion of works.

Attached are the shop drawings for container assembly.

All works shall carry under this SOW and shall be implemented accordingly.

The submitted a quote an amount of 32,000 pesos only for supply of labor, transportation and
equipment for complete assembly of the latter SOW stated.

Project Issuer and approval by:

Mark Roger Huberit II


Operation manager

Accepted by:

Teodoro Torres
Contractor