(PHASE –I)
VOLUME-II
TECHNICAL BID
2. DESIGN CRITERIA
PROVIDING PURE DRINKING WATER SUPPLY TO HOSADURGA TOWN AND 346 HABITATIONS OF
HOSADURGA TALUK IN CHITRADURGA DISTRICT AND RAW WATER TO 113 HABITATIONS OF TARIKERE
TALUK, CHIKKAMAGALURU DISTRICT, KARNATAKA STATE, INDIA. Under DBOT
(i) Traditionally, the projects for water supply are tendered in terms of what is known as “Item Rate”
tender. In other words, the Detailed Scheme Report (DSR) and detailed design and technical
estimate of the work are drawn-up in advance by the agency calling the tender. The bidders, in
such a case, execute the already designed water supply scheme and bidding is basically on the
cost of execution of a known design and DSR.
(ii) In the present case the tender is for (i) Design (ii) Build (iii) Operate & (iv) Transfer. This
methodology of tender has been selected for the following reasons –
a. Providing Water Supply to Hosadurga Town and Other 346 Habitations of Hosadurga
Taluk Chitradurga District, & Enroute Uncovered Habitations Tarikere Taluk water supply
project is a “Greenfield” water-supply project. Therefore, there are viable multiple
alternatives in terms of design and technology (within the overall standards as laid down
by CPHEEO & Other relevent Guidelines/Standards).
b. Further, the size of the project is large and major part of rural area of Hosadurga Taluka,
Hosadurga town of Chitradurga District will get drinking water-supply over a geographical
area spread over about 1416.4 sqkm. This means the design options are multiple.
c. The Tamil Nadu Water Supply & Drainage Board (TWADB) has executed DBOT projects
on similar scale and experience has shown that the approach of DBOT can give more
optimal solutions in terms of design and cost and also reduce execution time of the large
water-supply projects.
d. KUIDFC has also used DBOT method to execute “Davangere Town Sewerage
Treatment Plant”.
e. In the same lines, Gadag district entire rural habitations covering water supply scheme
has been awarded and work implementation has started.
f. In this context the Cabinet approval has been accorded for implementation of this project
on DBOT based tender in Phases.
(iii) The (a) source of water, (b) population to be catered and their location (the water requirement at
destination villages/habitations) shall be made available to the DBOT bidders as input data (c)
as for as possible suitable Government land available for the components of the scheme be
selected and bidder should get permission from the concerned departments wherever it is
inevitable to locate any component in private lands, bidder has to make his own arrangements
to procure required land.
(iv) It is expected that bidders shall propose and prepare an optimal design to meet the drinking
water supply requirement and actually prepare a Scheme Report as accurate as possible which
will be the basis of contract. This Scheme Report shall be submitted as part of the Technical Bid
4
and same shall be evaluated by a Committee of Technical Experts. A bid which proposes a
Scheme Report that is technically not sound, is perfunctory /superficial, and does not conform to
actual field facts/reality and CPHEEO Standards & Guidelines shall be rejected at the stage of
Technical Evaluation itself.
5
GENERAL
District Profile
CHITRADURGA Located at a distance of 202 kms Northwest of Bangalore, in the heart of the Deccan
Plateau, Chitradurga is recognized as the land of valour and chivalry. The district headquarters town,
Chitradurga owes its name to “Chitrakaladurga,” or “Picturesque castle”. This is a massive fortress on
top of granite hills that rises dramatically from the ground. Archaeological remains found in the area,
trace its history to the 3nd millennium B.C.
A rock cut edict of Emperor Ashoka, near Bharamagiri reveals that Chitradurga was part of the Mauryan
Empire dating to the 3rd century B.C. After the fall of the Mauryans, this land was under the rule of royal
dynasties like the Rashtrakutas, Chalukyas and Hoysalas. But it really achieved eminence, as a
feudatory state of the Vijayanagar Empire, under the dynastic rule of the Nayakas or “Paleyars”, known
for their heroic exploits. The most eminent of the feudatory chieftains, was Madakari Nayaka, who after
the fall of the Vijayanagar Empire, declared his suzerainty and consolidated his power. This hill fortress
built by the Nayakas during the Vijayanagar era, became their stronghold later. In 1779, the fort was
captured by Haider Ali, who along with his son Tipu Sultan, was responsible for its expansion and
strengthening. After Tipu Sultan’s defeat by the British, the fort came under the rule of the Royal
Mysore family.
Chitradurga features bold rock hills and picturesque valleys, huge towering boulders in unimaginable
shapes. It is known as the "stone fortress" (Kallina Kote). The landscape looks much like a mischievous
giant's playground, with boulders thrown around, forming silhouettes against the sky. According to a
story in the Epic Mahabharatha, a man-eating gaint named Hidimbasura lived on the Chitradurga hill
and was a source of terror to everyone around. When the Pandavas came with their mother Kunti in the
course of their exile, Bhima had a duel with Hidimba. Hidimba was slain by Bhima and peace returned
to the area. Legend has it the boulders were part of the arsenal used during that duel. In fact, the
boulders on which major part of the city rests belong to the oldest rock formation in the country.
Timmana Nayaka a chieften under the Vijayanagar empire rose to the rank of governor of Chitradurga
as a reward for his excellence in military achievements, from the Vijayanagara ruler. This was the
beginning of the rule of the Nayakas of Chitradurga. His son Obana Nayaka is known by the name
Madakari Nayaka 1588 CE. Madakari Nayaka's son Kasturi Rangappa 1602 succeeded him and
consolidated the kingdom to rule peacefully. As he had no heirs to succeed him, his adopted son, the
apparent heir was enthroned but was killed in few months by the Dalavayis.
Chikkanna Nayaka1676 the brother of Madakari Nayaka II sat on the throne, and his brother succeeded
him with the title Madakari Nayaka III in 1686. The unwillingness of Dalawayis to accept Madakari
Nayaka III's rule gave an opportunity to one of their distant relatives, Bharamappa Nayaka to ascend
the throne in 1689. He is known as dthe greatest of the Nayaka rulers. Somehow, the subjects of
Chitradurga did not experience a good reign of the successive rulers as they ruled on the throne for
very brief periods. The Hiri Madakari Nayaka IV 1721, Kasturi Rangappa Nayaka II 1748, Madakari
Nayaka V 1758 ruled this area but there is not much to mention of their rule.
Taluk Profile
Hosadurga Taluk is in Chitradurga District around 200km from Bangalore. Agriculture is the main
activity of this region. According to Dr. D M Nanjundappa Committee Report, Hosadurga Taluk is
classified as Most Backward Taluk. The villages of the Taluka are having drinking water supply
schemes with bore wells as source.
Tarikere Taluka:
6
Ground Water Scenario
The bore wells were drilled from a minimum depth of 64 mbgl to a maximum of 200.1mbgl. Depth of
weathered zone ranges from 6.0mbgl to 27.0 mbgl. Yield ranges from 0.64 to 5.5 lps. Transmissivity
ranges from 0.5m2/day to 75.88 m2/day. Storativity ranges from 0.07 to 0.21. Seasonal water- level
fluctuation varies from 2.65 m to 3.37m. In Hosadurga Taluk, except the western part which falls under
critical category, the rest of the taluk is safe. 22% of the taluk falls under over exploited category.
Because of over exploitation the yield from bore wells dwindles down during summer and the water
supply is affected and the villages face scarcity of drinking water.
The present coverage is about 0-25 is 252 habitations, 25-50 is 33 habitations, 50-75 is 17 habitations,
75-100 is 44 habitations. In some cases the bore well water is contaminated with Alkalinity, Nitrates,
Chloride, TDS, Fluoride, Iron and pH and other harmful chemicals. The Alkalinity contamination varies
from 604.00mg/l to 2026.00mg/l of 42 Samples, Nitrates contamination varies from 98.00mg/l to
138.00mg/l of 16, Chloride contamination varies from 1005.00mg/l to 1330.00mg/l of 9 Samples, TDS
contamination varies from 2166.00mg/l to 2400.00mg/l of 10 Samples, Fluoride contamination varies
from 1.51 mg/l to 4.40 mg/l of 54 Samples, Iron contamination varies from 0.50 mg/l to 5.00 mg/l of 16
Samples, pH contamination varies from 8.53 to 9.00 of 18 Samples out of 920 samples.
Because of water quality issue and coverage the Elected Representatives of the taluk have requested
the Government to provide potable and dependable water supply to the taluk. So it is necessary to
provide safe and dependable water supply scheme to the villages and Town. The source of supply has
to be dependable and water should be potable and free from harmful chemicals. This is possible if
surface water (River or Tank) is taken as source with Water Treatment Plant.
Rural Drinking Water and Sanitation Department of Govt. of Karnataka is the agency responsible for
planning and execution of water supply and sanitation projects in rural areas of Karnataka State.
7
RDW&SD has formulated a project for supplying potable water to all the habitations in the project area
of Hosadurga Taluk from a sustainable surface source as a step towards solving the problem
permanently. RDW&SD has prepared a Preliminary Report for the above multi village drinking water
supply scheme for a general understanding and for broad guidelines.
The source of supply should be dependable and water should be potable and free from harmful
chemicals. This is possible if surface water (River or Tank) is taken as source with Water Treatment
Plant. Since demand of each village will be usually small we should go in for Multi Village Water Supply
Scheme with common source and Water Treatment Plant. Then clear water should be transmitted to
the service reservoirs/storage stand posts in the Habitations to be covered through Master Balancing
Reservoir or Tanks and network of gravity mains, looking in to the topography of the area. In some
cases where the village is located at higher elevation, intermediate sump with pumping arrangement
will have to be provided for supplying water to such village.
8
3.0 SELECTION OF SURFACE SOURCE FOR THE PROJECT:
After experiencing short falls in ground water sources, other natural sources such as surface source
were investigated. River Vedavathi flows through the taluk to get bridged at Mari Kanive dam. The River
is one of the main source for drinking water for the town and villages of Hosadurga Taluk.
Vani Vilasa Sagar Dam located across Vedavathi river near Marikanive. The distance is around
40.0kms from source to Hosadurga Town. Using this as source other water supply schemes have been
taken up and the requirement for this scheme will not satisfy because of total allocation for this dam is
only 8.20 TMC. And River Vedavati is not sustainable or dependable since it is not perennial.
Bhadra Reservoir located nearby Lakkavalli village of Tarikere Taluk Chickamagular District across
Tungabhadra River. The distance is around 80.0kms from source to Hosadurga Town. From this source
water supply scheme can be taken up as it has more dead storage capacity and also the static head
and distance are relatively less.
Tungabhadra Reservoir located nearby Mallapur village of Hospet Taluk Bellary District across
Tungabhadra River. The distance is around 210.0kms from source to Hosadurga Town. Taking up
water supply scheme from this source works out to be uneconomical the source is distance from the
proposed area and the static head are high. Hence Bhadra Reservoir very is considered as source. A
Multi Village Water Supply Scheme with Bhadra Reservoir as source is proposed for covering 346
Habitations of Hosadurga Taluk, Chitradurga District and covering 113 Habitations of Tarikere Taluk.
It is found that tapping water from Bhadra Reservoir the water requirements of Hosadurga taluk
including all habitations and town are fulfilled. Also, the source is perennial and the static head is less
when compared with the other source.
The water allocation for this scheme required about 0.873 TMC to cater the needs of Hosadurga taluk
including all habitations and town and Enroute Uncovered Habitation Tarikere taluk. The Permission
from the Government sanctioned through Letter No: WRD58MMB2013 Dated 22 / 07 / 2014 of 1.00
TMC.
Phase – I
Phase – II
The tentative locations identified by RDW&SD, subject to final feasibility/ acceptance by bidder with the
flexibility to choose his own alternative sites with minimum land acquisition at his own cost.
Sl
Components Tentative Locations Identified by RWS&SD
No
11
7.0 TECHNICAL COMMITTEE
The Review and Evaluation Committee (Technical Expert Committee) to review and evaluate the
technical proposal/PSR/Evaluation shall be formed with Chief Engineer RDW&S Dept and other expert
members of credibility and independent standing – including experts from Premier
Institutions/Organizations. The recommendations of this committee regarding the technical bid shall be
final and binding.
a) However, for the above package the firm has to provide 01 Nos of AC Car/ Jeep with
Drivers, Consumables, Insurance tax etc till Completion of the project. And handover
the vehicle to the designated officers of the Department after completion of the Project.
b) The firm has to provide standard PC, and its Consumables with Internet facility to the
designated officers of the Board for project purpose at no extra cost till defect liability
period.
12
ANNEXURE 1
PROJECTED POPULATION AND WATER DEMAND FOR PROJECT TOWN IN PROJECT AREA FOR DESIGN
1 Hosdurga Town (TMC) 60,213 96,377 135 1,01,60,947 10.160 1,62,63,621 16.263
PROJECTED POPULATION AND WATER DEMAND FOR PROJECT VILLAGES / HABITATIONS IN PROJECT AREA
FOR DESIGN OF HOSADURGA RURAL 346 HABITATIONS
Requirement at Requirement at
Projected
Supply tapping point tapping point
Sl. population
Name of Village / Habitation ZBT'S Rate (2035) (2050)
No.
(LPCD)
2035 2050 Litres MLD Litres MLD
Phase - I
1 ALADAHALLY 1 1461 1740 85 155231 0.155 184875 0.185
13
17 NERAGUNDHA GOLLARAHATTI 1 324 386 85 34425 0.034 41013 0.041
14
53 BALEKERE 3 1177 1402 85 125056 0.125 148963 0.149
15
89 KRISHNAPURA 4 457 545 85 48556 0.049 57906 0.058
Phase – II
Requirement at Requirement at
Projected Supply
Sl. tapping point tapping point
Name of Village / Habitation ZBT'S population Rate
No. (2035) (2050)
(LPCD)
2035 2050 Litres MLD Litres MLD
16
118 GULIHATTI 5 1654 1970 85 175738 0.176 209313 0.209
136 HUNAVINADU JANATHA COLONY 6 197 235 85 20931 0.021 24969 0.025
158 BANTANAGAVI A.K. HATTY 7 403 480 85 42819 0.043 51000 0.051
18
190 BALLALASAMUDRA 8 1902 2265 85 202088 0.202 240656 0.241
218 HARIYANAHALLI LAMBANI HATTI 9 179 214 85 19019 0.019 22738 0.023
259 RAMDAS NAIKA THANDA 11 427 509 85 45369 0.045 54081 0.054
20
262 (S) BOVIHATTY 11 301 359 85 31981 0.032 38144 0.038
21
298 BARAMANPALYA 12 178 212 85 18913 0.019 22525 0.023
312 KAGGALAKATTE BOVI HATTI 13 302 360 85 32088 0.032 38250 0.038
321 KELAGAHATTI LAMBANI HATTY 13 195 233 85 20719 0.021 24756 0.025
22
334 SIDDHAPURA 14 229 273 85 24331 0.024 29006 0.029
PROJECTED POPULATION AND RAW WATER DEMAND FOR ENROUTE UNCOVERED HABITATIONS OF
TARIKERE TALUK
Requirement at
Projected Requirement at
Supply tapping point
Sl. population tapping point (2035)
Name of Village / Habitation Rate (2050)
No.
(LPCD)
2035 2050 Litres MLD Litres MLD
24
53 Doddabokikere 696 766 85 73950 0.074 81388 0.081
25
89 Gondedahalli 396 436 85 42075 0.042 46325 0.046
26
SYSTEM DESIGN CRITERIA FOR PROVIDING WATER SUPPLY TO HOSADURGA TOWN AND OTHER 346
HABITATIONS OF HOSADURGA TALUK CHITRADURGA DISTRICT, & ENROUTE UNCOVERED
HABITATIONS TARIKERE TALUK.
The system design criteria to be followed for the proposed water supply scheme for supplying treated
water to villages in Hosadurga Taluk shall be as given below;
27
S. Description Design Criteria
No
structure toprevent silt entry and is to be designed for twice the
design flow with entrance velocity of Max 1.50 m/sec.
9. Design guidelines for piped Piped Intake Well and Connecting Pipes or Intake Channel
intake well and Connecting with forebay and unitise sump:
pipes with inspection chamber Material of connecting pipe: RCC NP4 class with pipe and
control arrangement for flow.
Hours of raw water drawl per day : 22 hours
Design flow for inlet to pipe inlet : 2.0 times ultimate design
flow
Design entrance velocity in inlet gratings: Max. 8 m / min
Design velocity in each connecting pipe : 1.50 m / sec
Access opening : Min. 750 x 750 heavy duty CI manhole with
cover
Access ladder: MS caged ladder with epoxy coating both
inside and outside.
Cleaning chambers : RCC inspection chambers / cleaning
chambers shall be provided for connecting pipes at spacing’s
not greater than 50 m.
10 Intake structure and pumping Type of structure : Lower suction chamber, Pump delivery
.
station at Cauvery River bank chamber and motor floor chamber with electrical room in RCC
Bhadra Reservoir framed construction
Design flow for intake structure : Ultimate design flow
Hours of raw water pumping per day : 22 hours
Sump model analysis to be carried out before finalizes the
detail design.
Type of raw water pumps: Vertical Turbine (VT) pumps with
hollow shaft and external oil lubricated. The life span of
pumping machinery shall be designed as per norms of
CPHEEO Manual
Design flow for pumps : Intermediate design flow
Number of pumps: Min. 3 Nos. (2 working + 1 standby) or any
number with minimum 50% standby
Pump setting level: 1.0m above the invert level of jack well.
Invert level of connecting pipes at intake structure : same as
invert level of lowest grating / piped inlet
Invert level of intake structure : Min. 2.00 m below invert level
28
S. Description Design Criteria
No
connecting pipes
CI sluice vavles to be provided for the lowest inlet of piped
intake well if intake well and connecting pipes are proposed
Foundation level : As per design based on geotechnical
investigation
Floor level of pump delivery chamber : Min. 1.50 m above HFL
Height of pump delivery chamber : Min. 2.50 m clear up to
soffit of roof beams
Height of motor floor : Min. 6.00 m or adequate height clear up
to EOT crane hook
Height of electrical panel room / control room : Min. 5.00 m
clear up to soffit of roof beams
Piping and fittings : DI / MS with epoxy coating
Capacity of EOT crane : Min. 5.0 Ton or 1.50 times heaviest
equipment to be lifted whichever is higher
DG capacity: One pump working (Minimum 50% pumping
capacity) + other loads. DG with acoustic enclosure as per
CPCB norms
Surge protection system : As per surge analysis with all the
accessories with best latest technology viz. Air vessel /
Bladder vessel / Surge Tank etc.,
Access opening : Adequate size opening
Access ladder : MS caged ladder with epoxy coating with
intermediate RCC landings
Exhaust fans : To meet Min. 10 air changes
Min. 3.75 m wide asphalted approach road to be provided
excluding shoulders from nearest existing road
Associated rooms / facilities : electrical panel room, LT room,
battery / UPS room, SCADA / control room, operator rest
room, water filtration unit for domestic use, toilets with waste
disposal facility, compound wall etc.
Floor area of rooms : As per equipment / machinery layout as
per IEE rules and approved by Client
11 Raw water rising main Pipe material : MS of design thickness with internal food grade
.
epoxy lining of required thickness with two coats of primer and
external guniting confirming to IS: 3589
29
S. Description Design Criteria
No
Hours of working per day : 22 hours
Design flow : Ultimate design flow
Hazen William's constant "C" to be considered with aging Max.
120
Minor losses : Min 10% of friction loss
Design velocity in pipeline : Max 1.50 m / sec (based on the
principle of techno-economic feasibility and financial viability
with due consideration to number of factors/parameters)
Pipe bedding: CNS layer as per soil analysis
12 Water treatment plant General
.
Treatment Units: Cascade Aerator, Parshall Flume, Flash
Mixer, Clariflocculator, Rapid Sand Filter, Disinfection, Sludge
Thickener, Sludge Drying Beds, Filter backwash recovery tank
etc.
Associated Buildings / Rooms: Chemical building, air blower
room, office, electrical panel room, control room, laboratory,
disinfection room, toilet, twin block staff quarters, waste
disposal facility etc.
Type of construction : RCC
Hours of operation per day : 22 hours
Raw water quality : To be assessed by bidder during floods
and in lean periods.
The design of WTP shall meet requirements as given in
CPHEEO manual on Water Supply and Treatment with latest
edition
Coagulant : PAC / Aluminiumsulphate / any suitable
Sludge treatment : Sludge thickening, drying and disposal
Filter appurtenances: Rate setters, Filter rate controllers, filter
flow gauges, loss of head indicators, wash water controllers
and indicators, float chambers, under-drainage system,
calibrated notch for flow measurement etc.
Piping and Fittings: DI as per design with epoxy inner lining.
Wash water tank capacity : Two filter washing + one day
storage for daily service water requirement
Wash water recovery: Sedimentation of filter back wash water
to be provided for returning supernatant to inlet of WTP after
30
S. Description Design Criteria
No
pre-chlorination. The sludge shall be thickened, dried and
disposed.
Chemical storage area: Sufficient to store minimum one month
chemical requirementas per manual.
Disinfection
Disinfection system shall be as per CPHEEO / WHO
guidelines through latest proven technologyat clear water
Balancing reservoir / and at village OHTs / GLSRs just before
water is supplied to first consumer.
Other facilities
Min. 3.75 m wide asphalted plant roads excluding shoulders to
be provided connecting all the treatment units / buildings
Min. 3.75 m wide asphalted approach road to be provided
excluding shoulders from nearest existing road
Minimum floor area of rooms :
Admin and SCADA building: In two floor min.100 sqm each
Office Room - Min. 25 m2
Laboratory - Min. 20 m2
Twin block staff quarters - Each block Min. 60 m2 with central
staircase for accessing the roof
Compound wall
Other rooms - As per equipment / machinery layout approved
by Client
Treated water quality
"Acceptable" limits as listed in Table - 2.2 and Table - 2.3 of
CPHEEO Manual on Water Supply and Treatment. or IS-
10500 2012
13 Contact Tank / Clear Water Contact Tank / Treated Water Storage Tank
.
Storage Tank and Clear Water Design flow: Ultimate design flow
Pumping Station at WTP Type of structure : RCC covered tank
premises and at intermediate Hours of flow per day : 22 hours
pumping stations Capacity : To store Min. one hours flow (or decide by Mass
Balancing analysis)
Number of compartments: 2 Nos.
Level : Shall provide positive suction for pumps
Clear Water sump at Pumping Station
31
S. Description Design Criteria
No
Type of structure : RCC framed construction
Design flow for pumping station : Ultimate design flow
Hours of clear water pumping per day : 22 hours
Type of clear water pumps: Centrifugal pumps. The life span of
pumping machinery shall be designed as per norms of
CPHEEO Manual
Design flow for pumps : Intermediate design flow
Number of pumps: Min. 3 Nos. (2 working + 1 standby) or any
number with minimum 50% standby
Height of pump floor : Min. 5.00 m clear up to EOT crane hook
Height of electrical panel room / control room : Min. 4.00 m
clear up to soffit of roof beams
Piping and fittings : DI / MS with epoxy coating
Capacity of EOT crane : Min. 5.0 Ton or 1.50 times heaviest
equipment to be lifted whichever is higher
DG capacity: One pump working (Minimum 50% pumping
capacity) + other loads. DG with acoustic enclosure as per
CPCB norms
Exhaust fans : To meet Min. 10 air changes
Surge protection system : As per surge analysis with all the
accessories with best latest technology viz. Air vessel /
Bladder vessel / Surge Tank etc.,
Associated rooms / facilities: electrical panel room, LT room,
battery / UPS room, SCADA / control room, compound wall
etc.
Floor area of rooms : As per equipment / machinery layout
approved by Client
14 Clear water rising mains / Pipe material : Ductile Iron (DI) K9 Class confirming to IS:
.
Gravity mains / Bulk 8329 for diameters up to 450 mm with internal factory CM
transmission mains up to Clear lining and MS of design thickness with internal food
Water Sumps / Master gradeepoxy of design thickness and external guniting
Balancing Reservoirs / Tanks confirming to IS: 3589 for diameters above 500 mm
(MBRs / ZBTs) Hours of working per day : 22 hours
Design flow : Ultimate design flow
Hazen William's constant "C" to be considered with aging Max.
120
32
S. Description Design Criteria
No
Minor losses : Min 10% of friction loss
Design velocity in pipeline : Max 1.50 m / sec (based on
theprinciple of techno-economic feasibility and financial
viability with due consideration to number of
factors/parameters)
Pipe bedding: CNS layer as per soil analysis
15 Break Pressure Tanks (BPTs) if Design flow: Ultimate design flow
.
proposed as per design Type of structure : RCC tank
Hours of pumped flow per day : 22 hours
Capacity : To store Min. two hour flow (or Based on Mass
Balancing of inflow and outflow analysis)
Compound wall
16 Intermediate Pumping Sumps Intermediate Sumps (If Required)
.
and Lifting Stations Design flow: ultimate design flow
Type of structure : RCC covered tank
Hours of flow per day : 22 hours
Capacity : To store Min. one hour flow (or decide by Mass
Balancing analysis)
Number of compartments : One or Two depending on capacity
Level : Shall provide positive suction for pumps
Intermediate Pumping Station (If Required)
Type of structure : RCC framed construction
Design flow for pumping station : Ultimate design flow
Hours of pumping per day : 22 hours
Type of booster pumps: Centrifugal pumps. The life span of
pumping machinery shall be designed as per norms of
CPHEEO Manual
Design flow for pumps : Intermediate design flow
Number of pumps: Min. 3 Nos. (2 working + 1 standby) or any
number with minimum 50% standby
Number of pumps for small lift stations less than 50 HP: Min. 2
Nos. (1 working + 1 standby)
Height of pump floor : Min. 5.00 m clear up to EOT crane hook
Height of electrical panel room / control room : Min. 4.00 m
clear up to soffit of roof beams
Piping and fittings : DI / MS with epoxy coating
33
S. Description Design Criteria
No
Capacity of EOT crane : Min. 2.0 times heaviest equipment to
be lifted
Lifting arrangement for small lift stations : Min. 2.0 Ton or 1.50
times heaviest equipment to be lifted capacity whichever is
higher chain pulley block
DG capacity: One pump working (Minimum 50% pumping
capacity) + other loads. DG with acoustic enclosure as per
CPCB norms
Exhaust fans : To meet Min. 10 air changes
Surge protection system : As per surge analysis with all the
accessories with best latest technology viz. Air vessel /
Bladder vessel / Surge Tank etc.,
Associated rooms / facilities: electrical panel room, LT room,
battery / UPS room, SCADA / control room, compound wall
etc.
Floor area of rooms : As per equipment / machinery layout
approved by Client
17 Master Balancing Reservoirs Design flow: Ultimate design flow
.
(MBRs) /Tanks / Zonal Type of structure : RCC ELSR / GLSR as per hydraulic design
Balancing Reservoirs/Tanks and ground level
serving cluster of villages Hours of pumped inflow per day : 22 hours
Hours of gravity outflow per day : 22 hours
Capacity : To store Min. two hours inflow(or decide by Mass
Balancing analysis)
Outlet RL of reservoir : As per hydraulic design to feed OHTs
in villages / habitations in respective cluster by gravity for
residual head of 7m at nodes.
Approach road and compound wall shall be provided for MBRs
/ ZBTs /ZBTs
Staff rest room with toilet and waste disposal facility shall be
provided at MBRs / ZBTs/ZBTs
Disinfection to be provided to have 0.5mg/lt residual chlorineat
village OHT entry.
18 Clear water gravity feeder mains Pipe material: Up to 250 mm HDPE pipe /DI and pipe size
.
from MBRs / ZBRs / ZBTs to above 250mm shall beDuctile Iron (DI) K7 Class or K9 as
OHTs in each village / habitation perpressure requirement.
34
S. Description Design Criteria
No
Hours of working per day : 22 hours
Design flow : Ultimate design flow
Hazen William's constant "C" to be considered with aging Max.
120
Minor losses : Min 10% of friction loss
Design velocity in pipeline : Max 1.50 m / sec (based on
theprinciple of techno-economic feasibility and financial
viability with due consideration to number of
factors/parameters)
Pipe bedding: CNS layer as per soil analysis
Bulk water meters for rate of recorders and Flow meters shall
be provided at all the village / habitation OHTs to measure
water supplied to each village / habitation for water audit and
to control flow into reservoir.
The flow meters shall be connected to operation management
system.
19 Supply point at each village / Treated water shall be fed to existing / proposed OHTs /GLSR
.
habitation in each village / habitation through gravity feeder mains as
bulk supply.
Further Distribution is not in the scope of his contract.
If existing OHT is not available in any of the projectvillage, one
new OHT of capacity to meet 50% daily ultimateyear demand
or 10000 lt capacity whichever is higher with7.5m or
appropriate staging shall be constructed and connected
The design minimum residual head above full supply level of
existing / proposed OHTs in each village / habitation shall be
3.00 m.
20 Electrical works at head works, The design criteria for electrical works shall be as given below;
.
WTP, treated water pumping
station, IPS etc.
Power Supply The power shall be derived from the Electricity Board supply via the
provision of dedicated 33 kV feeders for Jack well, WTP, IPSs and
11kV for lifting stations
Electricity Board supply (a) Voltage : 33 kV / 11 kV as above
system (b) Frequency : 50Hz
(c) Voltage tolerance : plus or minus 10%
(d) Frequency tolerance : plus or minus 5%
35
S. Description Design Criteria
No
(e) Neutral earthing : Direct
(f) Three phase maximum fault level: Based on actual tapping
conditions
Design Standards Electrical design shall be based on the standard practice with
relevance to IEE / NBC / ISS standards
Transformer Sizing The transformer sizing shall be to supply on a continuous basis for
the total maximum working load at the site concerned including
internal and external lighting plus an additional allowance of 20% of
total load requirement as contingency.
Redundant Transformer shall be provided for each pumping station
Efficiency and power factor of LV shall be considered for sizing.
Drive Motors Drive motors shall be TEFC all-weather proof.
Up to 5 HP the drive controls shall be with DOL starters, from 7.5
HP to 25 HP shall be through star / delta starters and further
beyond 25 HP rated motors shall be with soft starters. The PLC
and its software shall interface controls flawlessly the drives to the
intended program with the process technology and stream route
sequence and other requirements during the complete process.
Power Factor Correction For maintaining the energy efficiency, the power system shall be
assisted by static capacitor banks in each load centre with auto
controls so that the power factor is always maintained above 0.95
P.F and optimum energy efficiency is achieved. The capacitor
banks shall be located on the LT side of the electrical distribution
system
Lightning Protection System Lightning protection shall be provided for the buildings and tall
structures as per IS: 2309
Earthing System Double earthing system shall be adopted for providing better
equipment safety using GI strips for more than 7.5 HP drives and
8G GI wire for lesser rated drives. The earth stations proposed shall
be of conventional type with 50 mm GI pipe as per IS 3043-1987.
Copper Plate type Earthing shall be provided for Transformer
Neutral earthing.
21 Operation and maintenance of The system shall include Integrated District Management System
.
entire water supply scheme (IDMS), Water Management Districts (WMDs), Air Management
through "Integrated Water System (AMS), Reservoir Management System (RMS) etc. to
Management System" operate the entire water supply system from source up to service
OHTs in each village / habitation through SCADA, automation etc.
36
(This technical bid sheet shall be evaluated by “Expert Technical Committee” and in each module the bidder must
score the minimum prescribed marks and overall 70% marks must be scored to technically qualify)
In order to prove that the technical proposal of the bidder with respect to the Goods offered shall
be of acceptable quality and standard, the bidders shall furnish in the technical bid the details about the
Goods he is going to offer as to number of years they have been in production and similar capacity have
been sold, as indicated in the table below. This shall form part of technical bid and evaluated as part of
the technical bid.
The bidder/his representative shall visit the project locations and photograph at least 25 geo-
stamped and time-stamped photographs as a proof of the visit to the project location. These 25-
Geo&Time Stamped photographs shall be included as part of the data-sheets/technical bid
submission.
ITEM -1:(50 marks & must score minimum 40 marks to technically qualify)
Manufacturer's Experience
Manufacturer's Actual Details
Criteria
Name
Minimum No. & Minimum
of years other No. of years
Item Goods preceding the details preceding Minimum
Minimum
due date of of the the due date average
average units
tender the Propo of tender the units sold
sold per year
goods offered sed goods per year
are in Manuf offered are
production acture in production
r
Pumps, Electrical &
1
Mechanical equipment's :
1.1 Pumps :
Vertical Turbine
10 5 Units
Above 250HP
Centrifugal Pump
10 10 Units
Above 200HP
Submersible Pump
5 10 Units
Above 10HP
1.2 Electrical Transformer :
Above 750 KVA 5 Two
Valves :
2 From minimum size of 50mm
to maximum size of 600mm
50-200 5 100 Units
250-400 5 75 Units
450-600 5 40 Units
Enders Hanser
Electromagnetic / Ultrasonic
/ Siemens /
Flow Meter, Electronic and
ABB / Krohne–
3 ICA Equipment / Bulk water 5
Marshall or
meter max 800cum/hr and
equivalent to
below up to 1cum/hr
ISI
800-500 5 5 Units
450-200 5 10 Units
150-50 5 25 Units
37
50-1 5 100 Units
4 Pipes :
MS Pipes: 610-219mm 5 30 KM Length
DI K-9 Pipes:300-150mm 5 30 KM Length
HDPE Pipes:450-50mm 5 50 KM Length
ITEM – 5: CONTACT TANK / CLEAR WATER STORAGE RESERVOIR AND PUMPING STATION:
(50 marks & must score minimum 30 marks to technically qualify)
Sl. Details to be filled by Bidder
Description
No. (attach PSR sheets to explain)
a) Contact Tank / Clear Water Storage Reservoir
1 Design capacity (MLD)
2 Design flow with 22 hours operation (m3/ hour)
3 Number of compartments (Nos.)
4 Capacity of each compartment (m3)
5 Size of each compartment and FB (m x m x
m)
42
17 Details of surge protection system
18 Size of below rooms:
- LT room (m x m x m)
- Battery / UPS room (m x m x m)
- SCADA / control room (m x m x m)
19 Details of flow meter and bulk meter
20 Details of exhaust fans
21 Details of Yard Lighting
22 Drainage System in WTP
ITEM – 6:
CLEAR WATER BULK TRANSMISSION MAINS UP TO ZBTs:
(50 marks & must score minimum 30 marks to technically qualify)
Sl. Details to be filled by Bidder
Description
No. (attach PSR sheets to explain)
1 Diameter wise length of pipeline
................ mm ................m
................ mm ................m
................ mm ................m
................ mm ................m
................ mm ................m
2 Number of hours of flow considered (hours)
3 Velocity range at design capacity (m / sec)
4 Pipe material and class of pipe
Whether air valves, scour valves, line valves etc.
with Tamper proof enclosure system with
5
vandalized alert system considered as per
specifications?
Provision pipe bridges, pipe support structures,
6 ducts, and concrete encasing, trenchless at SH,
NH, railway crossings etc.
ITEM – 7:
INTERMEDIATE PUMPING STATIONS:
(50 marks & must score minimum 30 marks to technically qualify)
Sl. Details to be filled by Bidder
Description
No. (attach PSR sheets to explain)
a) Intermediate Sumps
1 Location
2 Design capacity (MLD)
3 Design flow with 22 hours operation (m3 / hour)
4 Number of compartments (Nos.)
5 Capacity of each compartment (m3)
6 Size of each compartment and FB (m x m x m)
b) Intermediate Pumping Station
1 Design capacity (MLD)
2 Size of pump room (m x m)
3 Clear height of pump room (m)
4 Size of electrical panel room (m x m x m)
5 Number of pumps W + S (Nos.)
43
6 Type of pumps
Discharge capacity of each pump with 20
7
hours operation (m3 / hour)
8 Design head for each pump (m)
9 Efficiency of pump (%)
10 Pump BKW and motor capacity (KW / HP)
11 Material for piping and fittings
12 Number and size of valves
a) Actuator operated butterfly valves on suction
(Nos. /mm)
b) Non return valves (Nos. / mm)
c) Actuator operated butterfly valves on delivery
(Nos. /mm)
d) Automatic air valves (Nos. / mm)
e) Expansion joint / bellow (Nos. / mm)
f) Pump Control Valve
Capacity of EOT crane / Chain pulley block
13
(Ton)
14 Source and distance of electricity supply with KV
15 Transformer capacity (KVA)
16 DG capacity (KVA)
17 Details of surge protection system
18 Size of rooms:
- LT room (m x m x m)
- Battery / UPS room (m x m x m)
- SCADA / control room (m x m x m)
19 Details of flow meter and bulk meter
20 Details of exhaust fans
21 Approach road considered.
1. M.S. PIPES
1. M/s. Steel Authority of India Ltd., No.8, VISL Building, J.C. Road, Bangalore – 560002.
2. M/s. Welspun, Trade World, `B' Wing, 9th Floor, Kamala Mills Compound, Senapati Bapat
Marg, Lower Parel, Mumbai- 400013
3. M/s. PSL Holdings, 22, Vaijavoor Village, Malai Vaiyavoor P.O., Mahuranthakam Taluk,
Kancheepuram Dist- 603308.
4. M/s Tata Steel Limited, Tata Steel tubes Division, PO Burmamines, Jamshedpur-831 007,
Jharkhand.\
5. M/s Asean pipes Ahamedabad.
2. D.I Pipes
1. M/s. Electrosteel Casting Ltd., 30, B.T. Road, Kharda, P.O. Sukhchar, Dist. 24,
Paraganas(N)- 700 115 – WestBengal
2. M/s.Jindal Saw Ltd., Samaghogha Village, Mundra Taluk, Dist. Kutch, Gujarat-392415
3. M/s.Lanco Industries Ltd., Rachagunneri-517 641 Sri Kalahasti, Chittor,A.P.
4. Tata Metallics DI PipesLtd.
5. M/s Electrotherm India ltd-Plot no 206-207,Shop no-1, Kunal-II, sector-21 Nerul ( E) Navi
Mumbai-400706 (Maharashtra)
3. H.D.P.E. PIPES
1. M/s. Jain Irrigation Systems Ltd., Jain Plastic Park, P.O. Box: 72, N.H. No. 6, Bambhori,
Jalagaon- 425 001
2. M/s. Duraline India Pvt. Ltd., Plot No. L-24, 25, Phase II A, Verna Electronic City, Verna,
Salcete, Goa- 403722
3. M/s. Pioneer Polyfab, Plot No. 12, Site IV, Industrial Area, Sahibabad Dist.,Ghaziabad.
4. M/s. Pennwalt Agro Plastics Ltd., Plot No. 272/A, Savli GIDC Village, Manjusar- 391 775.
Gujarat.
5. M/s. Reliance Industries, Surath, Hazira Manufacturing Fa Village, Botha Taluq, Surath,
Gujarat.
6. M/s Rishi Polymach Pvt. Ltd., 16-A belagola indutrial area metagalli,K.R. Road, Mysore– 570
017
7. M/s.Supreme Industries Ltd., 612, Raheja Chambers, Nariman Point, Mumbai- 400021.
8. M/s Time technoplast Ltd -C-Wing, 2nd Floor, Opp - HDFC Bank, Off. Saki Naka, Chandivali
Road, Andheri - (E)- Mumbai –400072
1. M/s.The Mysore Stoneware pipe & Potteries Ltd., Soladevanahalli Chickbanavar P.O.,
Bangalore-90
1. M/s Indian Hume pipe Co. Ltd., Venkatala Village, Yelahanka Pos,Bangalore – 560064
2. M/s Aradhya Concrete Products, No. 301, Hebbal Industrial Area, Mysore-570016
46
6. G.I. PIPES FOR PLUMBING WORKS
1. M/s. Tata Iron & Steel Co. Ltd., No.45, Jubilee Building, II Floor `A' Wing, Museum Road,
Bangalore- 560001
2. M/s Surya Roshni Limited, Prakash Nagar, Delhi-Rohtak Road, Bahadurgarh-124
507, Haryana
3. M/s Jindal Pipes Ltd- Plot no 30, Institutional sector-44 Gurgoan-122002-Haryana
4. M/s Jindal Industries ltd -Delhi Road, Model Town,Hisar
7. CI D/F PIPES
1. M/s. NECO Castings Ltd., 65/2, Nildoh/Digdoh, MIDC Industrial area, Nagpur- 440016
2. M/s. Upadhaya Valves Mfg, Pvt Ltd., NH-6, VIII, Jangalpur, Andul Mogri Road,Howrah
3. M/s Electrosteel Casting Ltd., 30, B.T. Road, Kharda, P.O. Sukhchar, Dist. 24,
Paraganas(N)- 700 115 – WestBengal
8. DI SPECIALS
1. M/s. Kiswok Industries Pvt. Ltd, Bipranna Para, Via-Begri, Domjur, Howrah-711411
2. M/s. Electrosteel Casting Ltd., 30, B.T. Road, Kharda, P.O. Sukhchar, Dist. 24,
Paraganas(N)- 700 115 – WestBengal
3. M/s. Kejriwal Castings, P-200, Benaras Road, Netajigarh, Howrah – 711108
4. M/s Jindal Saw Ltd-Jindal Centre, 12 Bhikaiji Cama Place-New Delhi110066
9. CI SPECIALS
1. M/s. Indian Valves Pvt Ltd., H.O.- 53, Industrial Estate, Satpur, Nashik- 422 007
18. SLUICE GATES
1. M/s Indian Valves Pvt Ltd., H.O.- 53, Industrial Estate, Satpur, Nashik- 422007
2. M/s.JashEngg.Ltd.,31,Sector`C‟,IndustrialArea,SanwerRoad,Indore-452015
48
19. FOOT VALVES
20. CEMENT
1. M/s.Vasavadatta, Cement, Prop.Kesoram Industries Ltd., Post Sedam- 585 222, Gulbarga,
Karnataka
2. M/s.Penna Cement Industries Ltd., Talaricheruvu Village, Tadpatri Mandal, Ananthapur Dist.
A.P.
3. M/s.Madras Cement, Flat No.100-100/1, M-Floor, Eden Park, No.20, Vittal Mallya Road,
Bangalore- 560001
4. Birla Cement
5. Ultratech
6. ACC
7. Zuari Cement
8. Ambuja Cement, Elegant Business Park, MIDC Cross Road „B‟ Off Andheri-Kurla Road,
Andheri (E) Mumbai400059
9. Chettinad Cement, House of chettinad “Rani Seethai Hall” 5th Floor # 603, Anna Salai,
Chennai 600006 PNo. 044 –28292727
10. Ramco Cement , The Ramco Cements Limited (Formerly Madras Cements Ltd), Auras
Corporate Centre, 98-A Dr.Radhakrishnan Salai Mylapore, Chennai - 600 004, PNo.044
- 28478666
11. Coromandal Cement, Coromandel Towers, 93, Santhome High Road,Karpagam Avenue,
R.A.Puram,Chennai600028.
1. M/s. Krohne Marshell, A34/35, MIDC Estate, H block, Pimpri, Pune- 411018
2. M/s Endress Hauser Flowtec (India) Pvt. Ltd., M-174/175 MIDC Waluj, Aurangabad–
431 436.
3. M/s. Siemens, 130, Pandurang Budhkar marg, worli, Mumbai400018
4. M/s. Krohne Marshell, A34/35, MIDC Estate, H block, Pimpri, Pune- 411018.
5. M/s Endress Hauser Flowtec (India) Pvt. Ltd., M-174/175 MIDC Waluj, Aurangabad– 431
436.
6. M/s ABB, Prestige Palladium Bayan, Greams Ln, Thousand Lights West, Thousand
Lights, Chennai, Tamil Nadu600006.
7. M/s Yokogawa, 115, Mahatama Gandhi road, 2nd floor, Kothari, buildings,
Nugambakkam, Chennai, Tamilnadu, India,600034.
1. M/s.Durable Polymer Products Pvt Ltd., Boai, 2nd Lane, P.O.Jugberia, Kolkata- 700110
2. M/s. Prabhat Elastomers Pvt. Ltd., A1/413-415, GIDC Road, No. 4, Sarigam Gujarat- 396155
3. M/s.Amalgamated Synthetic Moulders,44/14, K.B.Sarani(Mall Road),Kolkatta- 700080
4. M/s. J.D.Rubber Industries, Survey No. 580/A, Ghatkesar (M) R.R. Dist(A.P.)
5. M/s Andhra Polymers Pvt. Ltd., Plot No.2, Phase – 5, IDA, Jeedimetla, Hyderabad – 560055
1. M/s. K.G.M. Exports, Plot No. 1 & 2, Sector 59, H.S.I.D.C. Indl. Estate,Faridabad
2. M/s. TV Plastics Ltd., 488, Kamakshipalya New Extension, Bangalore- 560079
3. M/s. Rajvaibhav Enterprises Pvt Ltd., No. 18, KIADB, Industrial Area, Chintamani Road,
Hosakote- 14,Bangalore
1. M/s. STP Ltd., Mirgadih, Dimna Road, P.O. MGM Medical College, Jamshedpur- 831 018,
Jharkhand
2. M/s Shalimar Tar products- 404,Lloyds Chamber,Block no-2, Mangalwar Peth-Pune-411011
3. M/s MP Tar Products- Plot No 69 and 70 Light Industrial area Bhilai dist- Durg(C.G)
4. M/s A.R. Laminators -497/2, G.I.D.C-Makarpura, Vadodara-390 010-Gujarat,India
5. M/s IWL India ltd-W360, North Main Road-Anna Nagar West-Chennai -600 101-Tamilnadu
1. M/s.JashEngineeringLtd.,31,Sector`C‟,IndustrialArea,SanwerRoad,Indore-452015
2. M/s. Indian Valves Pvt Ltd., H.O.- 53, Industrial Estate, Satpur, Nashik- 422007
1. M/s. Fair Banks Morse, 28 A, Site IV, Industrial Area, Sahibabad, Ghaziabad(U.P)
2. M/s. Kirloskar Brothers, Stategic Business Unit-1, Kirloskar Brothers, Kirloskar Wadi, Pune –
416 308
3. M/s. Jyothi Ltd., Nanubai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
4. M/s. Worthington Pvt. India Ltd., (WPIL), 22, Ferry Fund Road, Panihati-743 176, 24,
Parganas(N), WestBengal.
5. M/s. Worthington Pvt. India Ltd., (WPIL), Macneill & Major Industrial Estate, A-5, Section
XXII, Meerut Road, Ghaziabad- 201 002, UttaraPradesh.
6. M/s. Mather & Platt Pumps Ltd., P.O. Box No.7, Pune-Mumbai Road, Chinchwad, Pune- 411
019.
7. M/s. Voltas Ltd., Pumps & Projects, Business Dvn. 2nd Pokran Road, Thane-400601.
8. M/s.Flowmore Pvt. Ltd., 9th Mile Stone, G.T.Road, P.O. Mohan Nagar, Ghaziabad,U.P.
9. M/s Grundfoss Pumps India Pvt Ltd., 118, Old Mahabalipuram Road, Thorappakkam,
Chennai-60009
50
29. CENTRIFUGAL PUMPSETS
1. M/s.Kirloskar Brothers Ltd., Ujjain Road, Opp. Railway Station, Dewas(MP)- 455001
2. M/s.Beacon Weir Ltd., 28, Industrial Estate (North), Ambattur, Chennai- 600098.
3. M/s. Kirloskar Brothers, Stategic Business Unit-1, Kirloskar Brothers, Kirloskar Wadi, Pune
416308
4. M/s. Flowmore Pvt.Limited, A-292, Mahipalpur Extn., N.H- 8, New Delhi-110037
5. M/s. Jyothi Ltd., Nanubai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
6. M/s. Worthington Pvt. India Ltd., (WPIL), Macneill & Major Industrial Estate, A-5, Section
XXII, Meerat Road, Ghaziabad- 201 002(U.P.)
7. M/s. Mather & Platt Pumps Ltd., P.B. No.7, Mumbai–Pune Road, Chinchwad, Pune– 411019
8. M/s Grundfoss Pumps India Pvt Ltd., 118, Old Mahabalipuram Road, Thorappakkam,
Chennai-600 097(including boosterpump)
1. M/s. Kirloskar Brothers Ltd., Ujjain Road, Opp. Railway Station, Dewas (MP)- 455001
2. M/s. KSB Pumps Ltd., Mumbai – Pune Road, Pimpri, Pune – 411018.
3. M/s. Grundfoss Pumps India Pvt Ltd., 118, Old Mahabalipuram Road, Thorappakkam,
Chennai-600097
4. M/s Aqua pumps and Machinersi pvtltd
5. M/s. Kishore Pumps Pvt. ltd., Enviro Pumps Dvn., 675/2, Pune-Nasik Highway, Kuruli
(Chakan), Pune- 410501.
6. M/s. M.B.H. Pumps Pvt. Ltd., Plot No. 14, GIDC Naroda Industrial Estate,Ahmedabad-
7. M/s Xylem Water Solutions India Pvt ltd--Ground & First Floor,- Vishnu Shivam Mall-Thakur
Village, Kandivali (E)- Mumbai – 400101
1. M/s. M.B.H. Pumps Pvt. Ltd., Plot No. 14, GIDC Naroda Industrial Estate, Ahmedabad- 382
330
2. M/s. Arihant Pumps Pvt. ltd., Nr. Ladbhi Nala, Deesa Highway, Palanpur, Banaskantha- 385
001
3. M/s. Jyothi Ltd., Nambai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
4. M/s. Unnati Industrial Corporation, Near Uttar Gujrat Industrial Estate, Opp. Forge & Blower,
Naroda Road, Ahmedabad- 380025
5. M/s Cheran Industries,Coimbatore
6. M/s Waterman Industries Pvt Ltd., 407, Opp New Intas Pharma, Sarkhej Baavla Highweay,
Moraiya, Changodar, Ahmedabad-382213
7. M/s. Mather & Platt Pumps Ltd., P.B. No.7, Mumbai–Pune Road, Chinchwad, Pune– 411019
33. MOTOR
51
1. M/s. Jyothi Ltd., Nanubai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
2. M/s.Crompton Greaves Ltd., Pumps Division, Plot No.A/28, MIDC, Ahmednagar-414111.
3. M/s. SIEMENS Ltd., Thane Belapur Road, Kalwa, Thane- 400601.
DESCRIPTION MAKES
HT SIDE:
COMPACT SUB-STATON ABB / SCHIENDER
RING MAIN UNITS ABB / SCHIENDER / SIEMENS
PLCs ABB / SIEMENS / ALLEN BRADLEY / HONEYWELL
VCB ABB / SCHIENDER / SIEMENS
HT PANELS ABB / SIEMENS / LOTUS POWER GEAR
11kV HT XLPE CABLES UNISTAR / POLYCAB / CCI / KEI
HT CABLE TERMINATION KIT RAYCHEM / BIRLA-3M
OIL FILLED TRANSFORMER UNIVERSAL/ KIRLOSKAR/ VOLT AMP
DRY TYPE TRANSFORMER ABB / VOLT AMP
CHANGE OVER SWITCH ABB / HPL / C&S /INDOASIAN
CURRENT TRANSFORMER KAPPA / AE / PRAGATHI
VOLTAGE TRANSFORMER KAPPA / AE / PRAGATHI
LT SIDE:
BUS DUCT ( AIR INSULATED TYPE) ZETA / ANITA ELECTRICALS / TRICOLITE
BUS DUCT ( SANDWITCHED
CONSTRUCTION) SCHNEIDER ELECTRIC / GODREJ / EMFORM
ACB / MCCB ABB / SCHNEIDER / SIEMENS / L&T
PRAGATHI CONTROLS / LOTUS POWER GEAR /
LT PANELS / AMF POWER CONTROL EQUIPMENTS/ LOAD
CONTROLS
DG SETS CUMMINS / CATERPILLAR
BATTERIES EXIDE / AMCO / AMARON
UPS DELTA / LIEBERT / EMERSON
1.1kV LT CABLES POLYCAB / CCI / SBEE
CABLE GLANDS USHA / CROMPTON / COMET
CABLE LUGS DOWELL/3D
LT CABLE TERMINATION KIT RAYCHEM / SAFE KIT
MCB / MCCB - DBs FOR LIGHTING /
ABB / MDS LEXIC / SCHNEIDER
POWER / EMERGENCY / UPS
BELUK (GERMANY) / ENERCON SYS. PVT.LTD /
APFCR (NUMERIC TYPE)
ALSTOM
CABLE TRAYS PROFAB / INDIANA / OBO BUTTERMAN
RACE WAYS / CABLE MANAGEMENT
SCHNEIDER / LEGRAND / OBO BUTTERMAN
SYSTEM
TELEPHONE CABLE ( INDOOR) DOORAVANI / DELTON / FINOLEX
TELEPHONE CABLE OUTDOOR (JELLY
FINOLEX / KARNATAKA TELECABLES / VINDHYA
FILLED)
TELEVISION CABLE RR KABELS/FINOLEX
INDUSTRIAL TYPE PLUG & TOP
SOCKETS & WEATHER PROOF HENSEL/ LEGRAND
ENCLOSURES
52
DESCRIPTION MAKES
ADVANCED LIGHTNING PROTECTION
ERICO / INDELEC / OBO BUTTERMAN
SYSTEM
METERS / SWITCHES / RELAYS:
STARTERS ABB / SIEMENS / TELEMECHANIC/L&T
TIMERS ABB / LEGRAND / TELEMECHANIC
CAPACITORS UNIVERSAL / MEHER / EPCOS
SELECTOR SWITCHES SIEMENS / L&T / KAYCEE
INDICATING METERS CONZERV
ENERGY METER CONZERV / AE / SECURE
PUSH BUTTONS SIEMENS / L&T / TEKNIC
INDICATING LAMPS SIEMENS / ALSTOM / VAISHNO / BINAY
PROTECTIVE RELAYS ABB / SIEMENS / ALSTOM / EASUN
LIGHT FIXTURES / CONDUITS
LIGHT FIXTURES PHILIPS / HAVELS / BAJAJ
STREET LIGHT POLES SHUBHAM / PIPE CORPORATION / KESELEC
CEILING / EXHAUST FANS GE / KHAITAN / ANCHOR/CG
FRLS PVC CONDUITS VIP / PRECISION / UNIVERSAL
METAL CONDUITS TATA / BHARATH / GB
FRLS WIRES-1100V GRADE RR KABELS / ANCHOR / FINOLEX
LIGHT SWITCHES ANCHOR ROMA / ABB / LEGRAND
1. M/s. Hitech Systems and Services, White House, 119, Park Street, Kolkata- 700016
2. M/s. Nivo Controls Pvt Ltd., 104-115, Electronic Complex, Indore- 452010.
3. M/s. Gujarat Electronics and Controls, (Water level controllers & Water level guards) 7,
Adavani Market, Out side Delhi Gate, Ahamedabad- 380004.
4. M/s. Pune Techtrol, S-18, MIDC Bhosari, Pune - 411026(INDIA).
5. M/s. SBEM, 39, Electronic Co-Operative Estate, Pune Satara Road, Pune – 411009(India).
1. M/s Al Aziz Plastics Pvt Ltd., No. Plot No.5-14, Achhad Industrial Estate, Achhad,
Tal:Talasari, Dist: Thane(Maharastra)-401606
2. M/s.Glynwed Pipe Systems India Private Ltd., A-208, Kailash Complex, Park Site, Vikhroli-
Hiranandani Link Road, Vikhroli (W), Mumbai -400079.
3. M/s.George Fischer Piping System, Plot No.9-B, 1st Floor, Kopri Village, Above China
Valley, Powai, Mumbai- 400076.
1. M/s.Sujana Metal Products Ltd., Survey No.296/7/9, IDA Bollaram, Jinnaram Mandal, Medak
Dist., A.P. India (TMTBars)
2. M/s.SRMB Srijan Ltd., SRMB House, 7 Khetra Das Lane, Kolkata- 700 002. India (TMTBars)
3. M/s.Shyam Steel Industries, Shyam Towers, EN-32, Sector V, Salt Lake, Kolkata- 700 091
(TMT re-bars, CRS TMRre-bars)
4. SAIL, Steel Authority of India limited, Ispat Bhawan, Lodi Road, New Delhi – 110003 PNo.
011 -24300100
5. TATA, Tata Steel Limited Registered Office Bombay House, 24, Homi Mody Street, Mumbai
- 400 001Ph: 91 02266658282
6. Rashtriya Ispat Nigam Limited, Visakhapatnam Steel Plant, Visakhapatnam,AP.
53
38. Ultrasonic Level transmitter & Pressure Transmitter
1. M/s ABB, Prestige Palladium Bayan, Greams Ln, Thousand Lights West, Thousand
Lights, Chennai, Tamil Nadu600006.
2. M/s Siemens, 130, Pandurang Budhkar marg, worli, Mumbai400018.
3. M/s E&H, M-174/175 MIDC Waluj, Aurangabad– 431436.
4. M/s Yokogawa, 115, Mahatama Gandhi road, 2nd floor, Kothari, buildings,
Nugambakkam, Chennai, Tamilnadu, India,600034.
5. M/s Honey well, Mohamadpur Pace City-2, Sector-36, Gurgaon Ho, Gurgaon –122001.
2. M/s Schneider - Schneider Electric India Pvt. Ltd., 9th Floor, DLF Building
No. 10, Tower C,DLF Cyber City,Phase II,Gurgaon-122002.Haryana,India
54
PART - A :GENERAL SPECIFICATION
1.1 General
(d) Contact tank / treated water storage tank and clear water pumping station;
(e) Treated water pumping mains / bulk water transmission mains from WTP up to MBRs
/ ZBTs;
(h) Treated water feeder mains from MBRs / ZBTs to existing / proposed OHTs at all the
Habitations /habitations;
(j) All other works as detailed in Concept Note and Design Criteria;
(k) Operation and maintenance the whole of the entire Works for a period of 60 months.
c) Royalties:
The Employer shall deduct Royalties on materials used in the works from progress payments to
the Contractor at the rates specified in the “Karnataka Minor Minerals Concession Rules 2007” as
published by the Commerce and Industries Department (Mines) and as amended from time to time
till the date of submission of tenders. It shall be responsibility of the Tenderer to ascertain the
applicable rates as on the date of submission of tenders.
d) Rates quoted by the contractor / firm is inclusive of all taxes and duties.
e) The contractor / firm should mandatorily pay by themselves the necessary Entry Tax &
other applicable taxes without fail.
1.2 Scope
The Contractor shall design, manufacture, construct, install, test and commission the
works described in items (a) to (j) above in "Construction Period" under the Contract. The
Employer will take-over the Works after the Contractor has satisfactorily completed this stage
and will subsequently handover the whole Works to the Contractor to conduct 60 months of
operation and maintenance, in "Operation and Maintenance Period". "Operation and
Maintenance Period", the whole Works will be under the possession of the Contractor.
Therefore, the obligation of the Contractor shall have no difference to “the Contractor” as
mentioned in the Conditions of Contract. The Contractor shall be responsible for all
insurances, where the cost of providing that shall be entered in the Schedule of Prices. After
the Contractor has satisfactorily completed the 60 months operation and maintenance works
in "Operation and Maintenance Period", the Employer will take over the whole Works. Both
"Construction Period" and "Operation and Maintenance Period" of the Works contain a 12
months Defects Notification Period. During the Defects Notification Period at "Construction
Period", the Contractor has to rectify all defects and complete all minor outstanding works
that are agreed by the Contractor and the Engineer after the Test on Completion of
"Construction Period". The scope of the tests to be done in the aforesaid Test on Completion
is detailed elsewhere in this General Specification. Prior to handover the whole Works to the
Employer, the Contractor has to conduct and satisfactorily complete the Test on
Completionof "Operation and Maintenance Period". The scope of the tests to be done in this
Test on Completion is detailed elsewhere in this General Specification.
1.3 Design
The Contractor shall take design responsibility for the Works, not withstanding the level
of detail provided in any of the drawings or other items comprising the Employer’s
Requirements.
The raw water supply shall be derived from reservoir source as detailed in Concept Note
and Design Criteria. The raw water shall be conveyed to the Water Treatment Works via
pipeline.
1.5 Capacity
The design capacity of proposed water supply scheme including WTP shall be as
specified in Design Criteria. During Trial Operation at the Test on Completion for
"Construction Period" of the Works, the Contractor has to demonstrate the above
requirement can be attained, with the output treated water conforming to the treated water
standard stipulated in the Specification.
During "Operation and Maintenance Period" of the Works, the Employer intends to
operate the Water Treatment Plant to produce an output as specified by running all the
pumping stations (raw water and treated water). This treated water quantity per day should
have been used by the Contractor to price the chemical consumption, power consumption,
spare to use, consumables to use, operation and maintenance resources to use etc. in
"Operation and Maintenance Period" of the Works. The Employer has the right to instruct the
Contractor, during "Operation and Maintenance Period", to vary the running hours of the
whole Works in order to produce treated water output lower or higher than the specified.
Used filter wash water shall be recycled to the works inlet as specified.
The raw water supply for the treatment works shall be derived from the reservoir at site
as finalized in consultations with Client. The Contractor shall obtain their own raw water
quality data by carrying out water quality analysis during different periods of the year.
When operated in accordance with the Contractor's instruction at flows up to the required
maximum throughput, the water treatment works treating raw water from the reservoir shall
be capable of producing a reliable and continuous supply of potable water free of waterborne
pathogenic organisms. The water quality from the works sampled after treatment at the
treated water reservoir outlet or as otherwise stated shall comply with the "Acceptable" limits
as listed in Table - 2.2 and Table - 2.3 of CPHEEO Manual on Water Supply and Treatment.
The sequence of treatment processes proposed for the treatment works is summarized
below. Where aluminium sulphate is mentioned as a coagulant the Contractor may use
polyaluminium chloride (PAC) instead at his sole responsibility subject to the approval of the
Engineer.
particulate matter.
Filtration
Thickening of clarifier sludge and sludge Reduction of volume of sludge for further
from used filter washwater treatment
Overall control and monitoring of the head works, intake structure, raw water pumping
station, the water treatment works, the treated water pumping station, the booster pumping
stations, MBRs / ZBTs, OHTs in Habitations / habitations, etc shall be directed from the
central control room / control center. Operation of plant and treatment processes shall
normally be from local control centres in various buildings associated with the process units
and chemical and disinfection buildings. Instruments shall be used to monitor critical plant
states and alarm plant faults, failures and abnormal operations on local panels. Information
essential to the overall running of the treatment works shall be presented in the central
control room at WTP.
The treatment works shall be arranged for manual operation with the following exceptions;
The treatment processes are required to deal effectively and efficiently with the variations in
raw water quality and in the through put which are likely to occur, due both to seasonal
changes in the water quality and consumer demands.
1.12 Hydraulics
The hydraulic loss through the Treatment Works for the maximum flow from the normal
TWL at the Parshall flume to the TWL in the treated water reservoir shall not exceed 5.0m.
The height of cascade aerator shall be as per design.
The unit processes for treatment plant shall be as specified in design criteria. The design
of water treatment plant shall be in accordance with CPHEEO manual on Water Supply and
Treatment and as approved by client.
1.14 Electricity distribution system
(a) General
The power shall be derived from local Electricity Board supply via the provision of
dedicated 33kV feeders at each pumping station such as Intake structures, Water Treatment
plant, Clear Water Pumping Station and Intermediate Booster Pumping Stations etc. the
Contractor shall provide a 33kV sub-station which shall house the 33kV switch board to be
provided as part of this Contract. Local pumping stations with total load less than 50 HP may
be fed from lower voltage feeders.
The 33kV supplies from KPTCL to the pumping stations of Intake Structure, Water
Treatment plant, Clear Water Pumping Station and Intermediate Booster Pumping Stations
will be via overhead lines. Outdoor switch gear shall be for connection to overhead cables.
The 33kV switch boards provided shall be fed from the KPTCL 33kV outdoor switch gears by
underground cables. The Contractor shall be responsible for the supply and installation of
these underground cables. At each of the sites of this Contract, as described above, the
Contractor has to provide a 33kV outdoor switchgear yard with fencing and a metering
house for use by KPTCL. Electricity supplies to the process plant and site infra-structure
shall be as detailed within this Specification.
High voltage switchgear equipped with vacuum circuit breakers shall be provided as
detailed herein.
(c) Transformers
Transformers shall be of the oil filled and naturally air-cooled type with primary and
secondary cable boxes as detailed in the Standard Specifications. Transformers of rating
below 500kVA located indoor shall be dry-type encapsulated winding cast resin
transformers. Redundant Transformer shall be provided for each pumping station.
Switch boards and motor control centres shall be the multi-compartment type
incorporating circuit-breaker or switch dis-connector incomer units, circuit-breaker or fuse-
switch type outgoing units and motor starters as appropriate.
The power factor shall be corrected at each load centre by means of individual or
automatically controlled multistage capacitor banks.
(f) Cables
33/11/6.6/3.3kV and 415V cables shall be of the cross-linked polyethylene insulated, single
wire armoured and polyvinyl chloride over-sheathed type of appropriate voltage grade.
Conductors shall be copper.
(g) Earthing
The 1600kVA and above rated Transformer winding neutral shall be earthed through
resistance. The selected value of resistance should restrict the earth fault current below the
full load current of the largest drive/motor in the system. Time rating of neutral earthing
resistor shall be 10sec. Necessary provisions in the protection systems shall be made to
avoid adverse impact on sensitivity of protection relays. The works high and low voltage
earthing systems shall be inter connected.
On simultaneous mains power failure on both the independent dedicated feeders, the
works shall shut-down to a safe-mode. On failure of one supply, the second supply shall
automatically supply the complete Works.
2.1 Scope
This part of the specification covers certain duties of the Contractor in connection with
the administration of the Contract; it includes also some of the general responsibilities of the
Contractor in carrying out work under the Contract, which are in addition to or in furtherance
of the requirements of the Conditions of Contract. The requirements of any clauses of this
specification herein, or compliance with the requirements of the Engineer, shall not limit any
of the Contractor's obligations or liabilities under the Contract.
Except where stated to the contrary, references herein to Clauses are reference to
Clauses numbered in the Specification.
The Contractor will be supplied with one copy of the Contact Documents for his own use.
The term materials shall mean all materials, goods and articles of every kind whether
raw, processed or manufactured and equipment and plant of every kind to be supplied by
the Contractor for incorporation in the Works. Except as may be otherwise specified for
particular parts of the Works in other volumes of the specification, the provision of the
standard specifications shall apply to materials general requirements for any part of the
Works. All materials shall be new and of the kinds and qualities described in the Contract
and shall be at least equal to approved samples. The Contractor shall as far as possible use
materials available in India for the completion of the Works, subject to compliance with the
specification. Materials shall be transported, handled and stored so as to prevent
deterioration, damage or contamination.
The Contractor shall procure pipes from reputed manufacturers with at least 3 years of
manufacturing experience and the respective ISI Certification. For pumps, mechanical and
electrical equipments, at least 10 years of manufacturing experience is required with the
respective ISI Certificate. Experience of collaborators, if any, for satisfying these criteria will
be acceptable, subject to documentary evidence.
2.5 Substances and products
Substances and products used in the Works which may be applied to or introduced into
water which is to be supplied for drinking, washing or cooking shall not contain any matter
which could impart taste, odour, colour or toxicity to the water or otherwise be objectionable
on health grounds. Only substances and products which have been approved by a national
or international regulatory body shall be used. After award of Contract, from time to time, the
Contractor shall submit for the approval of the Engineer a schedule of substances and
products he proposes to use in the Works giving the following information as applicable:
Item of plant;
Substance/product in contact with water;
Manufacturer of plant/substance/product;
Point of use in the Works;
Name of the regulatory body, which has approved the substance/product;
Date of approval (for use on water quality and on health grounds);
Approval (with respect to water quality and health) reference number.
For all other products and substances to be used in the Works in such situations, the
Contractor shall at his own expense obtain the necessary approval and follow the procedure
set above and obtain the approval of the Engineer before use.
The Contractor shall ensure that the Plant is safe in use, and that any safety regulations
imposed by law or by any authorized body empowered to make such regulations are
complied with.
"Design life" means the period for which an item is designed to operate at full design
output without major overhaul involving extensive dismantling, serious corrosion or necessity
for substantial renewal of any anti corrosion system, reduction of efficiency in excess of 5%,
or replacement of major components essential to the functioning of the item etc except for
consumables and for any limited-life components explicitly agreed at the time of the Contract
award.
1
All items and systems shall be designed to allow replacement or major overhaul at the end
of the design life without requiring major work or dismantling of other items and systems
which interrupt operation of independent items and systems.
3.0 STANDARDS:
The Works shall be carried out in accordance with the relevant quality standards, test
procedures or codes of practice, collectively referred to as Reference Standards, listed in the
relevant Part of the Specification. In many places, British Standards or other International
Standards are stipulated. During the submission of that works for the approval of the
Engineer, the Contractor shall also provide one copy of such Standard that the works is
conforming to for the use of the Engineer. The Contractor shall familiarise himself fully with
the requirements of such standards. Applicable Indian Standards may be offered. If no
standard is indicated then the relevant Indian or British Standard or, in the absence of such
standard, internationally recognised standard shall apply. Other national standards may be
considered provided that they are, in the opinion of the Engineer, no less exacting than the
corresponding standard quoted in the Specification. The Contractor shall demonstrate to the
Engineer that the alternative standard is suitable and equivalent to the specified standard,
and shall provide proof of previous successful use. The Engineer will decide whether or not
the use of such alternative will be permitted as a Reference Standard. When an alternative
standard is proposed, the Contractor shall supply the Engineer with a copy of that alternative
standard that the equipment is conforming to and also a copy of the standard as required to
be complied by the equipment in the specification, as part of that equipment submission for
the Engineer's approval.
The applicable issue of any Reference Standard shall, unless otherwise stated in the
specification, be the issue current at the date three months preceding the date for
submission of the tenders for the Contract.
The following abbreviations where used in the Specification refer to standards, codes
of practice and other publications published by the organisations listed:
For the purposes of this Contract the term “Project Manager” shall be used instead of
the term "Contractor’s Representative". The Contractor shall submit to the Engineer a
diagram showing the structure of the organisation for his administration of the Contract. This
structure shall include a project managing organisation which may be part of the Contractor's
organisation, or an outside body which shall be named by the Contractor.
2
The Project Manager and an assistant capable of deputising for the Project Manager,
both belonging to the Project Managing organisation shall be appointed.
The duties of the Project Manager shall include responsibility for programming, progressing
and co-coordinating:
The Project Manager shall also be responsible for ensuring that all codes, standards
and any other technical requirements of the Contract are complied with by all sub
contractors. All correspondence and communication between the Engineer and the
Contractor shall be directed through the Project Manager. The structure diagram shall state
the names of the firms to be employed to carry out the following portions of the Works.
• Process plant;
• Mechanical plant;
• Electrical plant;
• Instrumentation, control and automation systems;
• IDMS, WMDs, AMS, RMS etc.
• Civil works;
The specialist firms and the specific engineers to perform the design of the process
plant, mechanical plant, electrical plant, the civil works and the instrumentation, control and
automation systems, IDMS, WMDs, AMS, RMS etc. shall possess, as a minimum, 10 years
of relevant experience in his specialist field for projects similar to the degree and nature of
work as this Contract. The Contractor has to submit relevant details of this specialist firms
and the specific engineers to the Engineer for approval prior to the commencement of any
design work.
Designs, drawings and documents that are required to be submitted to the Engineer for
approval shall be considered as bona fide by the Engineer only if they have been submitted
by the Project Manager. Prior to submission to the Engineer, the Project Manager shall have
reviewed the design, drawing or document. Each item submitted shall be stamped "checked
by Project Manager", dated, and shall be clearly identified as to its final location and
function.
Each month the Contractor shall submit to the Engineer three copies of a written detailed
progress report showing the stage reached in the execution of the Works. The report shall
show progress to the end of the preceding month with respect to the approved Contract
programme. The reports shall be accompanied by such additional information in approved
form as may be required by the Engineer.
The reports shall be forwarded promptly so that on receipt the content is not more than
seven days out of date. The report shall show all activities required by the Contract such as
design, drawings, procurement, manufacture, works tests, delivery, erection, testing and
commissioning, operation and maintenance of all items of plant. Delays shall be detailed by
the Contractor, with the proposed action to overcome it. The Engineer/Employer may call
3
Meetings in his office, at the Contractor's office, or at the Site, to review the progress
of the Contract. The Contractor's Project Manager shall attend all such meetings.
In addition to the above, the Employer shall convene periodical meetings with Contractor /
Engineer for reviewing progress and for necessary co-ordination among Contractor(s) for
smooth construction implementation and maintain the time schedule.
The Contractor shall prepare and submit to the Engineer detailed method statements for
aspects of his work which may affect the operations of the Employer, the activities of others
outside the site, the work of other contractors on the Site or other potentially hazardous
activities. The method statements shall be submitted for review by the Engineer at least 21
days before the work covered by the method statement is programmed to start. Aspects of
work for which method statements are required include:
Each method statement shall comprise a step-by-step schedule of specific operations and
activities with descriptions, dates, times and durations for each step. It shall highlight specific
points in the programme, and include contingency plans for emergency reinstatement of
plant including "point of no return" and "earliest start time" of modified or new plant. The
statement shall clearly state who and what organization will carry out work and precisely
when and what support or provisions are to be made by others outside the Contract. The
statement shall include all supportive detail to enable a clear understanding of the method
and significance of each step of the safely and in accordance with the specification.
Upon the successful completion of the prescribed off-Site testing and inspection and
prior to dispatch from the place of manufacture, all items of plant shall be thoroughly
protected against corrosion and incidental damage from any cause. Packaging shall be
carried out to BS 1133 / relevant IS. Items intended to be painted shall receive the treatment
specified and all unpainted parts liable to corrosion (with the exception of the electrical
equipment) shall be thoroughly coated with high melting point grease or other approved
protective substance, which is easily removable. Electrical equipment shall be suitably
protected against corrosion and incidental damage to the satisfaction of the Engineer.
Temporary leads shall be fitted to electrical equipment to enable anti-condensation heaters to
be energised when the plant is in store. The heaters shall be energised by the Contractor
when conditions require. Items shall be packed to withstand rough handling in transit.
Packages shall be suitable for exposure to the atmosphere and storage in the open. The
Contractor shall be responsible for items reaching the destination undamaged. The
Contractor shall provide all necessary packing, cases and crates, properly strengthened.
Packages containing dangerous or breakable goods shall be packed and marked in
accordance with any statutory rules and orders applicable. Crates and packages shall be
correctly and adequately marked as follows;
• Employer's name;
• Title of scheme;
• Title of contract;
• Contractor's name;
• Designation site and item number matching approved schedules;
• Commercial markings;
The Contractor shall keep the Engineer informed of the state of deliveries. The
Contractor shall send copies of all shipping documents to the Employer and to the Engineer.
Shipping documents shall be accompanied by copies of test certificates as required.
4.4.2 Delivery
The Contractor shall be responsible for the safe delivery of items to the Site. Delivery
of items shall comprise any of the following, which may be necessary but not be limited to;
• Obtaining the necessary permits for all plant and equipment from relevant
Authorities;
• Loading and transporting items by whatever means, including insurances;
• Taking charge of items at the port of entry or rail or air terminal in India, including
payment of all handling charges, off-loading at terminal points, reloading and
transporting to the Site;
• Taking delivery of items at the Site, off-loading and temporarily storing in store
buildings or under cover until they are required for installation in the Works.
The Contractor shall examine items to the extent possible at the port or air or rail
terminal, and more thoroughly whilst taking delivery at the Site. If the Contractor discovers
that any item of Plant has been damaged in transit, he shall forthwith inform the Engineer
who will inspect and may give instructions for its disposal. Any item condemned by the
Engineer shall be immediately removed and replaced by the Contractor. Items with short
shelf-life shall be delivered in the shortest possible time before use with the Plant.
4.4.3 Storage
The Contractor shall provide all facilities for the safe storage of Plant as recommended
by the manufacturer. Stored items shall be laid out by the Contractor to facilitate their
retrieval as required. Stacked items shall be protected from damage. No metalwork shall be
stacked directly on the ground. Small items shall be held in suitable storage and shall be
clearly labeled. Items shall be handled and stored so that they are not subjected to
excessive stresses and their protective coatings are not damaged. The Contractor shall
comply with manufacturers' recommendations concerning the use of lifting arrangements.
4.5.1 General
The Contractor's site personnel shall include at least one approved skilled supervising
erector to supervise the erection of the Plant and enough skilled, semi-skilled and unskilled
labour to ensure completion of the Works in the time required. The Contractor shall not
remove any supervisory staff or skilled labour from the Site without the Engineer's approval.
The supervising erector shall mean the engineer in charge responsible to the Contractor for
completion of the erection, installation, setting to work, commissioning, operation
orMaintenance of the Works. Where different engineers are in charge of separate stages or
sections of work, the Contractor shall state their names and responsibilities to the Engineer
in writing.
Plant shall be erected in a neat and workman like manner on the foundations shown
on the approved drawings. The Contractor shall be responsible for setting-up and erecting
Plant to the line and level required and shall ensure that all equipment is securely held and
remains in correct alignment during grouting-in. This responsibility shall not be passed to any
other contractor. Where the Works are associated with are in physical contact with plant
supplied under a separate contract, the Contractor shall satisfy himself that the work carried
out by the other contractor is consistent with the correct operation of the plant. If the
Contractor considers any work being done, or any work completed, to be detrimental to the
plant, he shall report the matter at once to the Engineer. The Contractor shall make all holes
and openings in building structures required for fixing small plant items and shall provide any
associated supports. If any other openings or holes or additional loads applied to the
structures are found to be required, after approval of the drawings prepared by the
Contractor, their locations and sizes and method of cutting shall be submitted by the
Contractor to the Engineer for approval. Approval will be dependent on an assessment by
the Engineer on whether the structural integrity of the building will be compromised and
whether they will be detrimental to the appearance of the finished Works. If the Engineer
refuses permission for these reasons, the Contractor shall make fresh proposals, and shall
have no claim for delay. All additional holes or openings shall be cut by the Contractor at his
own expense.
4.5.2 Foundations
Foundations shall comply with the details shown on the approved drawings. Where
floors and plinths require to be cut away and prepared to accept foundation bolts or
mounting frames and plates, the approval of the Engineer shall be obtained before any work
begins.
The Contractor shall supply all anchor bolts, holding down bolts, fixing bolts, washers,
nuts, straps, supports, brackets, spacers and fixtures, which are needed for the satisfactory
installation of the Plant. All fixing anchors, nuts and washer shall be made of stainless steel.
No holes in concrete, brick, timber or structural steel work for fixing devices shall be
drilled without the prior approval of the Engineer. Holes shall preferably be made with a
rotary drill of the non-percussion type. A single-shot cartridge tool may be used only at the
discretion of the Engineer. Any damage caused by the Contractor to any surface during
erection shall be made good by the Contractor at his own expense to the satisfaction of the
Engineer. The Contractor shall be responsible for the provision of any scaffolding required
and the cost shall be deemed to be included in the Contract Price.
Plant shall be adequately protected during and after installation against damage to
finished surfaces and fitted components and against ingress of dust, moisture and the
effects of humidity. Structural finishing operations may have to be done near installed plant
before it is taken-over and the Contractor shall take this into consideration in complying with
the requirements of this Clause. The cost of all protection shall be included in the Contract
Price.
The Contractor shall apply the protective coatings for the Plant at Site in accordance
with the protective treatment system approved by the Engineer. The first in-situ coat shall be
applied immediately the items of Plant have been erected and built-in. Painting of Plant shall
be completed not later than one month after the satisfaction completion of the trial operation
and prior to proceed to Operation and Maintenance period. Before the end of the Operation
and Maintenance period of the Works all damaged paintwork shall be touched up and the
cost of this shall be deemed to be included in the Contract Price. Where touching up is done,
the result shall be uniform in colour with the original paint. If uniformity of colour is not
achieved after touching up, to the Engineer’s satisfaction, then the entire item shall be re-
painted so that uniformity of colour is achieved. The cost of this work shall be deemed to be
included in the Contract Price.
The Contractor shall check all items of electrical plant for correct phasing and
insulation resistance. Motors shall be dried out in accordance with the manufacturer's
instructions and checks on the insulation resistance shall be made at regular intervals.
Drying out shall continue until the insulation resistance reaches a steady value as
recommended by the manufacturer. After all drying out and checking of insulation resistance
is complete the Contractor shall check that all electrical connections to the plant are correct
and any errors shall be brought immediately to the notice of the Engineer. Electric power
shall only be applied to any plant item after the individual tests specified for the plant have
been done to the satisfaction of the Engineer.
The Contractor shall comply with the relevant requirements of all local and the
national health, safety and welfare acts and regulations issued by the Ministry of Labour
(MOL). Compliance with the requirements of acts and regulations by the Contractor shall not
relieve the Contractor from responsibility for the safety of his workers and employees and
those of his sub contractors.
In the event that the Contractor fails to comply with the requirements of the regulations
or with the Specification in respect of safe working conditions or practices on the Site, the
Engineer will have the authority to instruct the Contractor to stop work in any particular
location until the unsafe conditions or practices have been rectified to the satisfaction of the
Engineer. The Engineer will issue safety violation notices to the Contractor, informing him
that he is working unsafely and describing the nature of the unsafe working practice, the time
and date and the location. In this event, the Contractor shall be responsible for all costs and
delays resulting from complying with such instruction by the Engineer and for the actual
costs incurred on rectification of the unsafe conditions or practices.
The Contractor shall appoint a qualified and experienced HSWS officer for the
duration of the Contract. The full time duty of the officer will be to implement the site
implementation plan, to prevent accidents and enforce the requirements of legislation in
force. The name and qualifications of the officer so designated shall be submitted to the
Engineer by the Contractor for approval within two weeks of the commencement of the
Contract. The officer shall attend full time on site during normal working hours and whenever
work is in progress during out of hours working, public and national holidays approved by the
Engineer and available by phone and mobile during nonworking hours. The Contractor shall
engage senior site engineers and foremen that are properly trained in the application of
correct Health and Safety practices. These individuals shall liaise closely with the HSWS to
maintain safety on site at all times. The Contractor shall submit the details of the Health and
Safety qualifications of all such site personnel. The HSWS officer will be responsible for
ensuring all relevant information and posters are displayed at locations throughout the site in
accordance with the site implementation plan.
The HSWS officer will be responsible for keeping a site accident book to record all site
incidents or any major site rescue events. The book will be available for inspection by the
Engineer or any MOL authorised person. Record keeping must also be maintained to comply
with any other legal or regulatory requirements. The HSWS officer will be responsible for
ensuring that every site worker and regular visitor is given site HSWS procedure training
when they first enter the site and refresher training at an appropriate frequency agreed by
the Engineer. All occasional visitors will be trained on arrival and be provided with the
appropriate personal, protective equipment. Records of the training will be kept and available
for inspection by the Engineer.
The Contractor shall set up a safety committee comprising her full-time HSWS officer,
project manager, site engineers and foremen for the Contract. The committee shall meet
weekly and minutes shall be recorded and a copy shall be submitted to the Engineer. The
Engineer shall be invited to be present at the meetings. The purpose of the meetings will be
to discuss and resolve health, safety, welfare and security aspects of various parts of the
work, including possible areas of conflict or difficulty. Where different contractors are working
in the same area or adjacent areas, or where the work of one may impinge upon the work of
another, the meetings will consider what action needs to be taken to ensure that each
contractor is aware of the safety requirements of others.
The Employer may oversee the health, safety, welfare and security arrangements of
the various contractors working on the Site, to liaise with the Engineer and to draw his
attention to any breaches of Contract requirements or the approved safety plans of the
Contractor.
5.7 First aid facilities
The Contractor shall provide a complete approved first aid kit in his site office. The kit
shall be in the charge of either the Contractor's HSWS Officer or some other responsible
person who will also be on the site during all working hours to ensure that the first aid kit is
available without delay. The Contractor shall also provide a first aid kit in the office for the
Engineer. Kits shall also be provided at all remote sites. The HSWS Officer and adequate
numbers of other senior members of the Contractor's staff shall be trained in occupational
site first aid duties including resuscitation to take account of numbers of site workers located
on the permanent site and mobile site operations.
The Contractor will make arrangements with the emergency and rescue services to
provide adequate support where on site first aid assistance is inadequate to meet the
welfare requirements of all site workers.
The Contractor shall comply fully with all rules and regulations from time to time
issued and orders given by the Health Service of the Government or the local medical or
sanitary authorities.
Every excavation or underground space into or through which a person may fall shall
be covered by a temporary cover fixed securely in position or guarded by an effective barrier
to prevent falls except where free access is required by work actually in progress. In such a
case where work is in progress, the barrier shall be maintained in position to the extent
possible, and suitable warning signs shall be erected.
Where the work involves filling tanks with water leaving an open surface, the
Contractor shall provide at all times and at suitable locations equipment for promptly
rescuing persons from the water and resuscitating rescued persons. The Contractor shall
take all necessary steps to prevent any such accidents occurring by providing adequate
guarding.
The Contractor shall not suffer or permit an employee to use a passage way, or a
scaffold, platform or other elevated working surface which is in a slippery condition. Oil,
grease, water and other substances causing slippery footing shall be removed, sanded or
covered to provide safe footing.
All passageways, platforms and other places of work shall be kept free from
accumulations of dirt and debris and from other obstructions that may cause tripping. Sharp
projections shall be removed or covered.
5.13 Access to workplace
All alkalis, acids, gases and other hazardous and corrosive substances shall be so
stored and used so as not to endanger employees in accordance with national and state
regulations. Suitable protective equipment for the use of such substances shall be provided.
Clean water supply shall be readily available for washing off any spillage of any corrosive
substance on the employees.
Suitable eye protection equipment shall be provided for and shall be used by
employees while engaged in welding or cutting operations or in chipping, cutting or grinding
any material from which particles may fly, or while engaged in any other operation which
may endanger the eyes. The Contractor shall ensure that fully equipped eye washing
facilities are available on permanent and mobile site locations. Ear protectors shall be made
available for employees when operating noisy machinery.
All personnel working in such conditions shall be provided with escape sets. The
Contractor shall provide a "top-man" who shall be stationed immediately outside the
entrance to the confined space, and who shall maintain communication with personnel
working inside the confined space. In the event of a tranverse entry, this may require
additional personnel to be used to facilitate a reliable line of communication if evacuation has
to take place. The top man shall have the means to raise the alarm in case of any
emergency inside the confined space. The Contractor shall provide adequate ventilation for
workers carrying out work inside a confined space, pipeline or chamber or other enclosed
areas by using blowers or other suitable means.
Every site worker and visitor shall be provided with a full set of personal protective
equipment for use at all times including a luminous vest, helmet of a type tested and
approved by the MOL, steel toe-capped boots, gloves and other specific work related
clothing offering ear and eye protection. All site workers and visitors shall be required to
wear PPE while working on the Site, except in the Engineer’s and Contractor's office. The
Contractor shall display a notice on the access to the site stating that entry is for authorised
personnel only, and that PPE is to be worn at all times. Every employee required to work in
water, wet concrete or other wet footing shall be provided with suitable safety, waterproof
boots. Every employee required to use or handle alkaline, acid or other corrosive substances
shall be provided with appropriate PPE.
The Contractor shall not suffer or permit an employee to work in such proximity to any part of
an electric power circuit that he may contact the same in the course of his work unless the
employee is protected against electric shock by de-energising the circuit and earthing it or by
guarding it, by effective insulation or other means acceptable to the Engineer. The location
of underground power lines that encroach on the Works shall be confirmed using cable
detectors, the path of the cable shall be clearly marked. If such cables are adjacent to
excavations, the cable location shall be confirmed by finding the cable using carefully
controlled hand-dig methods under the supervision of a senior member of the Contractor’s
staff. No live cables shall be retained within working trenches or other excavations. Any such
cables shall be diverted prior to excavation commencing. The Contractor shall at all times
liaise with the local electricity supplier with regard to the locating and diverting of any
supplies.
5.21 Power driven saws, abrasive wheels and grinders
All portable power-driven hand operated saws, abrasive wheels and grinders shall be
equipped with guards above the base plate which completely protects the operator from
contact with the saw blade when in motion and with self-adjusting guards below the base
plate which completely covers the saw to the depth of the teeth when the saw is removed
from the cut.
Whenever any work is being performed over, on, or in proximity to a highway or any
other place where public vehicular traffic may cause danger to men at work, the working
area shall be so barricaded as to direct traffic away from it or the traffic shall be specially
controlled by persons designated for that purpose.
All vehicles used at the worksite must be roadworthy and registered with the
appropriate authority. No person shall drive a vehicle at the worksite unless they are a holder
of the appropriate driving license or certificate. A site internal access management system
including all appropriate road signs will be submitted by the Contractor to the Engineer for
approval at the commencement of the Contract.
No section of the plant or other structure or part of a structure shall be left unguarded in
such condition that it may fall, collapse or be weakened due to wind pressure or vibration.
All materials shall be stored or stacked in a safe and orderly manner so as not to obstruct
any passageway or place of work. Material piles shall be stored or stacked in such a manner
as to ensure stability. Hazardous materials shall be stored in secure areas and the HSWS
shall maintain an up-to-date list of the persons with a key to those areas.
Debris shall be handled and disposed of by a method which will not endanger
persons. Debris shall not be allowed to accumulate so as to constitute hazard.
5.27 Excavations
Excavated material and other superimposed loads shall be placed at least 1 m back
from the edge of open excavations and trenches and shall be so shored or retained that no
part Thereof can fall into the excavation, or cause the banks to slip or cause the upheaval of
the excavation bed. Banks shall be stripped of loose rock or other materials which may slide,
roll or fall upon persons below. Open sides of excavations where a person may fall more
than1.5 m shall be guarded by adequate barricades, and suitable warning signs shall be put
up at conspicuous positions. No employee shall be allowed to work where he may be struck
or endangered by an excavating machine with which his activity is not directly related.
Every ladder, step-ladder and access platform shall be of good construction, sound material
and adequate strength for the purpose of which it is used. Ladders, stepladders and access
platforms shall not stand on loose bricks or other loose packing, but shall have a levelled
and firm footing. Ladders of over 2m in height shall be securely tied to the structure it is
propped against. Free-standing, portable ladders over 4m in height shall not be used.
All site workers who work at height shall be provided with appropriate PPE to prevent an
accident by slipping or falling.
Fixed and mobile cranes shall be so constructed, positioned and operated as to be stable.
No crane shall be loaded beyond the safe working load except by an approved person or an
inspector for the purpose of testing such machine. Every crane including all blocks, shackles,
sheaves, wire ropes and the various devices on the mast and jib shall be thoroughly
inspected by an approved person at intervals not exceeding 12 months. Cranes shall be
inspected before being first erected or operated on each job or after any major repair.
Inspection and repair of crane jib shall be made only when the jib is lowered and adequately
supported. Outriggers and counter-weights shall be provided and used as specified by the
manufacturer of the crane or by an approved person. Counter-weights shall be properly
placed and secured. Leveling jacks or other suitable means shall be provided and used with
outriggers of truck-mounted mobile cranes.
Firm and uniform footing shall be provided for cranes. When such a footing is not otherwise
supplied it shall be provided by substantial timber, or other structural members sufficient to
distribute the load so as not to exceed the safe bearing capacity of the underlying material.
Every power-operated crane shall be provided with efficient brake or brakes or other locking
devices which will prevent the fall of the load when suspended and by which the load can be
effectively controlled whilst being lowered. Hand or foot-operated bakes shall be provided
with a substantial locking device to lock the brake in engagement.
No load-bearing part of any crane shall be replaced by another part, and no such machine
shall be modified by the addition thereto or removal there from of any load bearing part,
unless the replacement or modification shall be certified by either the manufacturer or the
approved person who tested the crane. A capacity chart shall be provided for every crane.
Such chart shall be posted and maintained in a place clearly visible to the operator and shall
set forth the safe loads for various lengths of jib at various jib angles and radial distances.
Where outriggers are provided such loads shall be set forth with and without the use
ofOutriggers. Unless furnished by the manufacturer or builder of the crane, a capacity chart
shall be prepared and certified by an approved person. Cranes shall have audible overload
warning alarms. A crane shall not lift any load that exceeds the corresponding safe working
load specified by its capacity chart. Every crane having a jib shall be provided with an
accurate indicator which shows, clearly to the operator, the radius of the jib and the safe
working load corresponding to that radius at all times and gives warning signal when the
radius is unsafe. Before hoisting any load at a new job site, the jib shall be operated to its
maximum height.
Crane cabs shall be locked when the operator is not present and no unauthorised
person shall enter the cab or remain immediately adjacent to any crane in operation. If
locking of a crane cab is impracticable, the operating mechanism shall be locked as to
prevent the crane from being operated by an unauthorised person. No crane shall be
operated in such a location that any part of the crane or of its load in any position of jib or
swing may come within 3 meters of live power line. All the lifting equipment used at site shall
be registered with the appropriate GOI Ministry and shall have a valid certificate at the time
of usage. All crane operatives should be authorised to operate the particular type of fixed or
mobile crane. Valid certificates will be available for inspection by the Engineer. All banks
men will be formally trained to undertake their duties and refresher training will be given at
an appropriate frequency agreed by the Engineer.
Where a sling is employed to hoist long-length material, a lifting beam shall be used to
space the sling legs for proper balance. When load is suspended at two or more points with
slings, the eyes of the lifting legs of the slings shall be shackled together and this shackle or
the eyes of the lifting legs may be shackled directly on the hoisting block or balance beam.
The eyes may be placed on the lifting hook without shackles if the hook is of the safety type.
Each container or receptacle used for raising or lowering filter media or other loose material
of any kind shall be so enclosed, constructed or designed as to prevent the accidental fall of
such material. Crane loads shall be raised vertically so as to avoid swinging during hoisting.
No crane shall travel with a suspended load except upon a safe runway. During travel
without loads, crane’s falls shall be secured or placed so as to prevent accident or damage
by swinging.
If the Contractor's work will cause unavoidable interference with access to adjoining
property the Contractor shall first give seven days notice in writing to the occupier of such
property and shall provide temporary means of access for vehicles, animals and
pedestrians. In carrying out the Works due regard shall be paid to the amenities of adjacent
property and to the interests of owners, tenants and occupiers. The Contractor shall take
adequate steps to prevent trespass by his employees and shall be wholly responsible for
making good any loss or damage caused by such trespass. The Contractor shall take all
necessary steps to ensure that the activities of his employees (and those of his
subcontractors) do not have any detrimental effect on the surrounding environment.
Any claim received by the Employer in respect of matters in which the Contractor is
required under the Contract to indemnify the Employer will be passed to the Contractor who
shall likewise inform the Employer of any such claim which is submitted directly to him by a
claimant. The Contractor shall do everything necessary, including notifying the insurers of
claims received, to ensure that all claims are settled properly and expeditiously and shall
keep the Employer informed as to the progress made towards settlement, failing which
theEmployer shall be entitled to make direct payment to claimants of all outstanding
amounts due to them in the Employer's opinion and without prejudice to any other method of
recovery to deduct by way of set-off the amounts so paid from sums due or which become
due from the Employer to the Contractor. If the Contractor receives a claim which he
considers to be in respect of matters for which he is to be indemnified by the Employer under
the Contract he shall immediately pass such claim to the Employer. All information as
aforesaid shall be given in writing and shall be copied to the Engineer's Representative.
5.35 Advertisements
The Contractor shall not except with the written authority of the Engineer exhibit or
permit to be exhibited on the Site any advertisement board. Any such advertisement may
also be subject to the approval of the local planning authority before it is put up and it shall
be removed if the Engineer so demands. Site sign boards shall be erected, typically of 3m x
2m, to bear the logos and text as specified by the Engineer. Costs shall be deemed to be
included in the site establishment items in the Price Schedules.
5.36.1 Sanitation
The Contractor shall maintain the Site and all working areas in a hygienic condition
and in all matters of health and sanitation shall comply with the requirements of the local
requirements. The Contractor shall be responsible for providing all sanitary services
necessary to keep all offices and stores in a clean, neat and hygienic condition.
The Contractor shall provide all proper temporary sanitary facilities for the Contractor’s
employees and sub-contractor’s. The sanitary facilities provided within the Site shall be of
the portable type. The Contractor shall provide septic tanks as necessary for the disposal of
sewage. Waste water and septic-tank effluent shall discharge into properly designed French
drains. Where the construction of septic tanks or water-borne sewerage is not feasible, the
Contractor shall construct conservancy tanks and arrange for the removal and disposal of
sewage. All such arrangements shall meet all the requirements as stipulated by the relevant
local Health Authority and the Contractor's proposals shall be submitted to and approved by
the Engineer. In particular, the Contractor shall ensure that his employees (and those of his
subcontractors) only use the toilet facilities provided by him as part of his site establishment.
Any person found urinating or defecating elsewhere on the Site shall be removed from the
Site immediately, and shall not be re-employed on the Site.
The Contractor shall also provide for the removal and legal disposal off the Site of all
rubbish and solid waste from offices and other areas of the Site, with collections being made
at least twice weekly.
Before commencing work on the Site, the Contractor shall ensure that all his
employees are instructed about the necessity for the prevention of pollution. The Contractor
shall immediately dismiss and remove from the Site any of his employees or representatives
who have been polluting or fouling the Site or any of the water supply installations and shall
take appropriate remedial measures to prevent a repetition of the occurrence and to disinfect
the areas concerned all to the satisfaction of the Engineer.During commissioning and
subsequent operations the Contractor shall not employ upon the Site, or on periodic visits
thereto, persons who are known to have any disease which could be water-borne or who is
suffering from an illness associated with looseness of thebowelsor who are carriers of
typhoid bacillus or other potential pathogenic organisms or who are otherwise unsuited on
medical grounds to be employed in or around water supply installations.
The Contractor shall if and when required to do so, arrange for his employees to be
examined and tested in the manner approved by the local medical officer.
The Contractor shall immediately remove from the Site any such employees who as a
result of such examination and testing may in the opinion of the medical officer or the
Engineer constitute a danger to water supplies or who refuse to undergo an examination.
In preparing the programme required to be furnished the Contractor shall take into
account any restrictions on possession of the Site or of Temporary Working Areas imposed
by the Contract. The Contractor shall also take account of the availability dates for the
different portions of the site.
The programme shall be in the form of a Critical Path Network, together with bar charts.
Particulars to be shown on the programme shall include:
• Submission of designs, drawings and documents
• Engineer's approval procedures/review procedures
• Re-submission of drawings etc as necessary and review
• Civil construction of each major structure
• Placing of orders for Plant
• Plant manufacture
• Plant tests at place of manufacture
• Plant deliveries to Site
• Plant erection
• Plant tests at Site
• Final commissioning tests
• Trial operation
• Plant operation and maintenance for 60 months
The programme shall make reasonable allowance for any work to be carried out by
other contractors employed by the Employer. The Time for Completion of the Works and
Sections thereof shall correspond to the periods prescribed in the Contract. Approval of the
Contractor's programme by the Engineer shall not relieve the Contractor of his duties and
responsibilities under the Contract.
The programme shall be updated monthly and when requested by the Engineer to
show actual progress and any revisions necessary to achieve completion.
All work to be done and goods and services to be provided by the Contractor under
the Contract and other general obligations of the Contractor shall be valued for payment as
per Schedule of Prices. The cost of any work, goods, services and general obligations as
aforesaid which are not so itemized shall be deemed to be included in the rates and prices
for other items in the Schedule of Prices.
Designs and documents submitted by the Contractor to the Engineer for approval
shall comprise generally;
• Contents list;
• Scope (description of the contents and purpose of the submission);
• Conclusions and recommendations;
• References, Specification requirements, codes, manuals and supporting documents
used, drawing numbers, and titles of drawings which are based on the design;
• Description of design approach;
• Criteria, parameters and methods used;
• Test procedures, analyses and results;
• Calculations and schedules;
• Qualitative description and comments on results;
• Any other relevant information;
• Appendix.
Designs and documents shall be presented on A4 size paper with every page
numbered and bound in order between covers formed of a transparent front and stiff back.
The title of the submission shall be given on the front sheet beneath the transparent cover
together with a reference number, Employer's name, title of scheme, title of Contract,
Contractor's name, Consultant's name title of works location, author's reference, date,
Contractor's signature, revision box and space for Engineer's markings as for drawings and
any other relevantinformation. Drawings submitted as part of the design or document shall
be folded into pockets at the back.
The Engineer may withdraw or modify his approval to an "Approved" design drawing
or document as a result of subsequent submissions. In this circumstance, he will inform the
Contractor in writing of the withdrawal or modification and, upon receipt of such information,
the Contractor shall immediately take the necessary action in regard to the Works and
confirm this to the Engineer in writing. Where appropriate and as agreed between the
Engineer and the Contractor drawings may be submitted in stages of development so as to
allow certain milestones to be achieved or certain elements of the work to be started; the
following stages are quoted by way of example and not as requirements to be met:
Stage1: Sufficient to allow preparation of foundations (floor slab and beams thickness
and levels agreed);
Stage2: Structural outlines shown (sufficient to permit ordering of materials and detail
up planning for building dates);
Stage 3: Structural outlines and details shown (sufficient to accommodate and fix all
plant and to allow building to proceed).The programme for submission of
designs, drawings and documents shall be based on the following general
order, which may need to be adjusted to fit particular circumstances;
Drawings submitted for approval shall be submitted as four A1 paper copies, two A3
paper copies, and in electronic format. The Engineer may agree with the Contractor to waive
the requirement for A1 copies for certain submissions, for example where drawings are low
in detail.
In respect of returning drawings, the following shall apply: One A1 and one A3 original
shall be stamped accordingly, signed off and returned, balance A1 original and A3 original
shall be stamped as above, signed off, and retained by the Engineer.
The Contractor shall submit to the Engineer for approval four copies of all other
submissions. Only one copy generally will be returned to the Contractor.
After approval, the Contractor shall submit to the Engineer two A1 copies, and two A3
copies, of all "Approved" drawings with the date of approval marked on the reproducible
against a new revision/issue of the document. The drawing shall also bear an electronic
watermark, or stamp, with the words “AS APPROVED”.
Four copies of all "Approved" designs and documents shall also be submitted.
In the context of time for approval by the Engineer of submissions by the Contractor,
and for no other, "working days" shall mean Monday to Saturday in each week, and shall
exclude any public holidays in Karnataka. The number of working days shall be counted
from the next working day following the day of delivery to the office of the Engineer until the
day before the day of dispatch from the office of the Engineer to the Contractor.
Hydraulic profile drawings for the treatment works shall show top water levels for all
water retaining structures, chambers and channels from the inlet works to the treated water
storage tank for normal and peak inputs. The drawing shall be supported by detailed
calculations.
Hydraulic calculations shall also be produced for used wash water and clarifier sludge
treatment streams and the overflow system. All formulae and coefficients used with source
references and assumptions made in the calculations shall be detailed. The design shall be
in accordance with CPHEEO manual guidelines.
Detailed hydraulic calculations, drawings and hydraulic profiles shall be submitted for
intake well / channel, connecting pipes, intake structure cum pumping station, raw water /
Treated water transmission mains, intermediate sumps and pumping stations, gravity feeder
main network, MBRs / ZBTs etc.
The hydraulic profile and calculations shall be the first design submission to be made
by the Contractor for the Engineer's approval. Until the Engineer has given the approval to
the hydraulic profile, the Contractor shall not commence any construction work on the site.
Drawings for all items of plant constituting an operating system shall be submitted to
the Engineer concurrently and shall include diagrams showing circuit functioning and details
for erection.
Plant working drawings prepared by subcontractors and manufacturers employed by
the Contractor shall be checked by the Contractor for accuracy and compliance with the
Contract as specified, before being forwarded to the Engineer. Working drawings, not so
checked and noted, will be rejected and returned to the Contractor without further
examination.
The Contractor shall submit the operation and maintenance manuals for approval by
the Engineer. Submission to, and approval, subject to comments, by the Engineer of the
operation and maintenance manuals shall be a mandatory necessary condition precedent to
the allowance of the Contractor to proceed to "Operation and Maintenance Period", even the
Contractor has satisfactory completed the final commissioning tests and trial operation. Draft
operation and maintenance manuals shall be available for the Engineer’s use prior to the
start of the final commissioning tests.
The operation and maintenance manuals shall cover the setting to work,
commissioning, testing, operation and maintenance of the Works. The greatest importance is
attached to completeness and clarity of presentation. Its shall be` users friendly bearing in
mind theTraining and abilities of the Contractor’s and Employer’s personnel responsible for
operating and maintaining the Works at "Operation and Maintenance Period" and the time
there after respectively.
The preparation of the manuals shall be carried out by personnel who are trained and
experienced in the operation and maintenance of the Plant described and are skilled as
technical writers to the extent required to communicate essential data and are competent to
prepare the required drawings and documentation.
The manuals shall be in English, shall be securely bound, and pages shall be of A4
size to ISO 216 or folded to that size in a loose-leaf hardcover binder, using not more than
70% of the binder capacity.
The format of the manuals shall be white paper for typed pages with neatly typewritten
text except for manufacturers' printed data. Drawings shall be provided with a punched
reinforced binder tab for binding into the text. Drawings shall be so sized that they may be
folded to the size of the text pages.
All pages shall be clear, legible and permanent. Offset printing or multi lith is
preferable, but electrostatic or photocopies will be acceptable if clear and permanent.
Each volume of the manual shall be identified both on the front cover and on the
spine, with the typed or printed title "OPERATION AND MAINTENANCE INSTRUCTIONS",
the title of the project, including the Contract reference number, and the identity of the
general subject matter covered in the manual. The text and drawings shall be placed in
commercial 4-ring binders with durable and cleanable plastic covers. When multiple binders
are used, the instructions shall be correlated into related consistent groupings.
The front cover and spine of each volume, shall also bear the Employer’s logo, details
of which will be provided by the Engineer. The background colour for the cover shall be
proposed by the Contractor and agreed with the Engineer.
Each O&M manual volume shall contain a neatly typewritten table of contents
arranged in a systematic order giving: name of Contractor, address and telephone number, a
list of each item of Plant included, an index to the contents of the volume and a list of each
plant item with the name, address and telephone number of any sub-contractor or installer.
Only the manufacturer's printed data which is pertinent to the specific Plant shall be
included. Each sheet of manufacturers' instructions shall be annotated to identify clearly the
specific item or part installed and the instructions applicable to that item or part of the Plant.
All inapplicable information shall be deleted. Plant data shall be supplemented with drawings
as necessary to illustrate clearly component parts of equipment and systems, control
diagrams, flow diagrams, and test procedures covered in the manual. Written text shall be as
required to supplement the Plant data for that particular installation. Written text shall be
organised into a consistent format under separate headings for different procedures and in
a manner to provide a logical sequence of instructions for each procedure.
The operation and maintenance manuals shall describe the installation as a whole
and shall give a step-by-step procedure with assembly drawings for any operation likely to
be carried out during the life of each item of plant, including its erection,
commissioning, testing,Operation, maintenance, dismantling and repair. Manuals shall
identify and cover aspects liable to affect other installations and shall include all health and
safety precautions to be taken.
A separate section of the manuals shall be devoted to each size and type of
equipment and to each item of Plant. It shall contain a detailed description of its construction
and operation and shall include all relevant pamphlets, and a list of parts with the procedure
for ordering spares.
The detailed sections of the manual, if necessary, shall contain further maintenance
instructions and fault location charts. Subject to the foregoing, the manual shall generally
comply with the recommendations of BS 4884 parts 1 and 2.(Technical Manuals - Content
and Presentation) / relevant IS.
The Contractor's attention is drawn to the need to ensure that the following items are
included in the operation and maintenance manuals;
• All health and safety instructions for chemicals and any precautionary measures
necessary for ensuring health and safety and avoidance of misuse;
• General description of the scope, purpose and manner of working of each system or
apparatus forming part of the Works, and the final functional design specification
(FDS);
• Maintenance procedures for the flushing of chemical tanks, pumps and dosing lines
and procedures for dealing with leakages and spillages including neutralisation;
• Schedule of spare parts with ordering reference numbers and parts identified on
equipment drawings;
• Schedule of tools;
• General arrangement and circuit diagrams for switchboards and control panels "as
installed";
• Operating procedures including step by step instructions for pre-start, starting up,
including start up following emergency shutdown, normal operation and normal and
emergency shutting down of the Plant;
• "Do's" and "Don’ts" in plant operation with attention drawn to all operations
considered to be hazardous to personnel or likely to damage plant;
• Data on general setting of controls associated with controlling design conditions,
monitoring instruments and switchgear, together with the details of initial settings of
all adjustable items;
• Test certificates for works and site tests carried out on plant, for site tests carried out
on pipe work, electrical and instrumentation installations and other items where
appropriate;
• Typical log sheets for recording plant operating information for each process and
chemical plant with instructions for identifying departures for normal behavior;
• Typical log sheets on which operating staff can record their service/maintenance
checks on essential equipment and at periods recommended by the Contractor;
• Description of the plant control philosophy (a layman's guide for operator assistants)
including plant trips and interlocks;
• Data sheets for process and chemical plant giving design parameters;
All drawings incorporated in the manuals shall be presented in such a way that they
can be easily referred to whilst reading the associated description in the text.
The Contractor shall submit for the Engineer's approval, not less than one month in
advance of the time at which any item of Plant is delivered to Site, two copies of instructions
appropriate to the erecting, testing, operation and running maintenance of that item of Plant.
These instructions shall form a draft of the relevant parts of the operation and maintenance
manual.
Two complete draft copies of the manual for the Works shall be submitted to the
Engineer at least one month before the commencement of the final commissioning tests.
These copies may be the same copies as those submitted in sections in accordance with the
previous paragraph. In this case the Contractor shall check and certify that these two copies
are complete before the commencement of the trial operation.
The trial operation shall not be started if the complete draft manual has not been
submitted to the Engineer.
All copies of the manual shall be amended as necessary by the Contractor during the
period of testing, commissioning and setting to work of the Plant. Following this updating, the
Contractor shall check and certify that the copies of the amended manual are the final draft
of the manual.
The Engineer will review the final draft manual and advise the Contractor of any
changes required. This review will be completed by the Engineer within 35 working days of
the certification by the Contractor that the final draft manual is complete.
Final copies of the manual shall be submitted not later than three months after the
commencement of "Operation and Maintenance Period". The text of the manual shall also be
submitted on CD ROM disc.
If any further revisions are necessary as a result of operational experience during the
"Operation and Maintenance Period", all copies shall be revised by the Contractor within a
period of thirty days of the need for revision becoming apparent.
A third copy of the draft manual shall also be provided by the Contractor for use by the
operating staff during the period between the commencement of "Operation and
Maintenance Period" and receipt of the final manual. The manual shall be clearly marked
"draft". This copy shall also be amended as for the copies provided for the Engineer, and
may, after checking and certification of its correctness by the Contractor, form one of the
sets to be provided to the Board under the Contract.
Upon approval of the Draft O&M manuals, the Contractor shall submit six sets of the
final O&M manuals, two sets of CD ROM discs and pdf/html format to be loaded onto the
Workstations of the SCADA system.
6.10 Hazard and operability study
The Contractor shall carry out a hazard and operability study (HAZOP) in accordance
with the recommendations of Chapter 2 of "HAZOP and HAZAN, Notes on the Identification
and Assessment of Hazards" by Trevor A. Kletz, published by the UK Institution of Chemical
Engineers / Relevant Indian Standards. The study shall be applied to the process and
instrumentation diagrams produced under the Contract prior to the submission of the same
for approval.
The HAZOP study sessions shall be held at the Contractor's site office and shall be
attended by his Project Manager and the persons responsible for the design of the subject
matter. The Contractor shall appoint one of his team to act as secretary responsible for
recording, typing and issuing copies of the minutes to each person present at the meeting. A
representative of the Engineer will act as chairman.
Unless otherwise specified, the timing for submittal of certificates shall be as follows:
(a) Manufacturer's and supplier's test certificates shall be submitted as soon as the tests
have been completed and in any case not less than seven calendar days prior to the time
that the materials represented by such certificates are needed for incorporation into the
Permanent Works.
(b) Certificates of tests carried out during the installation of plant and equipment or on
completion of parts of the Permanent Works shall be submitted within 7 days of the
completion of the test.
7.1.1 General
The Contractor shall offer all items of Plant for inspection by the Engineer at all stages
of manufacture and shall include for the testing of all Plant as required by the Specification.
The Engineer/Employer/Third Party Inspection Agency may witness any test, at his sole
discretion.
The Contract Price shall include for the costs of all inspection and off-Site tests
including temporary assembly and subsequent dismantling, labour, materials,
instrumentation, chemicals and consumable items, provision of test certificates, certified
records and curves.
The off-Site tests shall normally be carried out at the manufacturer's works but if the
tests are beyond the resources of the manufacturer, the Contractor shall make
arrangements for tests to be carried out elsewhere. The off-site testing may be witnessed by
the Engineer or by inspectors appointed by the Employer. All travel and out of pocket
expenses, e.g. airTickets, accommodation, allowances, professional charges, etc. incurred
by the inspectors in attending any test will be paid by the Contractor and be reimbursed
under an item in the PROVISIONAL SUM. Details of Inspection Agency and the details of
agreement between Third Party Inspection Agency and the Employer will be notified to the
Contractor.
No Plant or materials for inclusion in the Works shall be dispatched from any
manufacturer's works without the written permission of the Engineer. Any Plant or materials
dispatched without permission shall be returned and tested in accordance with the
Specification at the Contractor's expense.
If during off-site testing, any Plant or materials fails to meet the requirements of the
Specification, the defects shall be rectified forthwith. The rectified item shall be offered for re-
inspection and witness testing, and all resulting additional costs incurred shall be borne by
the Contractor.
The Contractor shall carry out all applicable tests required by the Specification and the
Reference Standard, together with such tests as are necessary, in the opinion of the
Engineer to demonstrate that the Plant or materials comply with the Specification.
When the Contractor is ready to carry out any off-Site test, he shall submit a detailed
test procedure to the Engineer. The proposals shall give values, such as test parameters
and make reference to Reference Standards, any other standards and manufacturer's
literature. The proposed format for the test sheets shall be submitted at the same time. The
testing shall not start until the Contractor's proposals and test sheets have been approved by
the Engineer. After receiving approval, the Contractor shall notify the Engineer of the place
and time of the proposed tests giving not less than fifteen working days notice.
The Contractor shall carry out every off-Site test at the time and place notified. If the
Engineer does not attend any test, then the Contractor shall carry out the test in the absence
of the Engineer and the certified copies of the test results shall be deemed to be a correct
record. The Contractor shall provide the Engineer with three certified copies of the test
results within two weeks of completing the tests. Enough information, including the Contract
number and title, shall be given on each test certificate to enable the Engineer to check for
compliance with the Specification.
Where items of Plant are of identical size and duty the Engineer may elect not to
witness all tests, but the Contractor shall assume that the performance tests on all items will
be done prior to offering any Plant for witnessed testing.
All instruments used for testing purposes shall have been calibrated by an
independent accredited testing authority and shall have a valid calibration certificate.
The calibration validity period shall not be longer than 12 months. Instruments used
for tests at site shall have been calibrated not more than 3 months before the start of testing.
The Contractor shall provide the Engineer with three copies of calibration certificates
and correction graphs etc at the time of testing.
The procedure and requirements for all tests off-Site on all Plant or materials shall be
in accordance with the requirements of the Specification and shall in addition be in
accordance with the requirements of the Reference Standards applicable to the item being
tested.
The figures entered in the Schedule of Technical Particulars or stated in the Contract
for performance and efficiency shall be guaranteed by the Contractor in respect of the Plant
offered at the duties specified. These figures will be binding and may not be varied except
with the written approval of the Employer. No tolerances are permitted on these figures.
Testing to the relevant standards and to prove guarantees given will be required for all Plant
and materials and the complete Works.
For any test required by the Contract, the Contractor shall produce a written record, in
a form approved by the Engineer, certifying that the test has been completed. The
Contractor's representative at the test shall sign the test record. The tests witnessed by the
Engineer's Representative shall be certified by the Engineer's Representative on the same
test record.
7.1.6 Certificates
Certificates of test in triplicate shall be provided by the Contractor for all off-Site tests.
These shall incorporate all test results, calculations, performance graphs and curves and
shall be signed by representatives of the manufacturer, Contractor and Inspector. These
certificates shall be provided within two weeks after completing the test. Copies of all test
certificates shall be included in the operating and maintenance manual.
7.1.7 Notification
Following any inspection or testing of Plant or materials, the Engineer shall notify the
Contractor in writing either that:
• The item has not met guaranteed performance or efficiency requirements not in
compliance with the Specification.
The Engineer shall state the grounds on which the decision is based.
7.2.1 Inspection
During erection of the Plant the Engineer will inspect the installation from time to time
in the presence of the Contractor to establish conformity with the Specification. Any
deviations found shall be corrected forthwith to the satisfaction of the Engineer.
As soon as the Engineer is satisfied that the erection of the Plant in an installation has
been completed and the Plant found to be in good working order and that the associated civil
works have been substantially completed to an extent permitting the proper operation of the
plant, the Contractor shall start testing at Site.
• Individual tests (also called pre-commissioning tests) which shall be at the first
opportunity after installation of the Plant;
• Trial operation.
Before any testing involving water entering supply, disinfection of all Plant items in
contact with water to be supplied shall be undertaken by the Contractor. The disinfection of
structure and pipe work shall be generally in accordance with relevant clause and subject to
the approval of the Engineer.
When water is discharged to waste, the Contractor may, subject to such conditions as
the Engineer and Employer may lay down, operate and adjust the Plant as necessary in
order to test the operation of the Plant. No water shall be put into supply except with the prior
authorisation of the Engineer and Employer and under such conditions as they may lay
down.
No part of the Plant shall be set to work until it has been inspected and accepted by the
Engineer.
The Contractor shall submit to the Engineer for his approval a programme for testing
up to the commencement of the trial operation, at least 28 days in advance of the proposed
start of testing and shall agree the timing with the Engineer and Employer not less than one
week before the start of testing.
The programme shall show the quantities of raw water, chemicals and power required.
Details of the proposed test procedures shall be submitted by the Contractor, including the
manner and order in which each item of Plant and process will be tested. Associated flow
rates and durations shall be submitted, and log sheets shall be prepared for recording plant
information and other operating, water quality parameters, and presentation and
interpretation of test data.
The programme shall be subject to approval by the Engineer and shall take into
consideration the extent of progress on other contracts, the availability of water, chemicals
and power, and the Employer's requirements for disinfection and discharges either to supply
or to waste.
The Contractor and any specialist sub-contractor shall be available to attend meetings
at the Site to discuss the testing programme, the test details and the test results.
7.2.4 Labour, materials, water, electricity and chemicals for tests
For individual tests, final commissioning tests and trial operation, the Contractor shall
provide all necessary labour, materials, chemicals, electricity, water, fuel, stores, apparatus,
instruments and indicators necessary to carry out the tests. If it is permitted by the Employer,
the Contractor may be allowed to use the permanent electricity supply registered under the
name of the Employer. However, the Employer has the final discretion to decide whether
such permission will be given. If the Employer permits the Contractor to do so, all electricity
tariff expense that is to incur to the Employer has to be reimbursed by the Contractor.
Electricity used for the tests shall be recorded on suitable meters provided by the Contractor,
which shall be read by the Engineer in the presence of the Contractor at appropriate times.
Electricity consumed as a result of testing activities shall be paid for by the Contractor. The
Engineer will from time to time deduct the cost of supplying electricity to the Contractor from
the Contractor’s monthly progress claims. The Contractor has to make arrangement for
water for carrying out all necessary tests.
During testing and trial operation of the Plant, until completion of the Works being
taken over by the Employer, the Contractor shall be responsible for all work, plant and costs
in connection with the commissioning and the trial operation of the Works.
All measuring instruments used for testing purposes shall comply with relevant clauses.
The Contractor shall prepare test record sheets for recording of all test results for the
approval of the Engineer at least one month before the programmed date for the tests. Three
copies of each approved sheet shall be provided to the Engineer not less than one week
before the start of testing.
Individual tests shall be in the presence of the Engineer and shall include the following;
Leakage tests shall be carried out on all pipe work. Where pipe work is to be built in,
these tests shall be carried out after erection and before concreting. The Contractor shall
ensure that the pipe work is suitably anchored and supported to sustain the pressure in the
not-built- in condition.
Pipelines and valves shall be pressure tested to one and a half times working
pressure unless otherwise specified.
Pipe work and valves through which oil or gas is to be conveyed shall be thoroughly
inspected then tested with the oil with which they are to be used or an inert gas and the
whole checked for leakage. Hydraulic tests using water shall NOT be applied to this pipe
work.
Tests on all items of Plant and materials in accordance with the requirements of the
Specification shall also be in accordance with the requirements of the Reference Standard
applicable to the item being tested.
All individual tests on items of plant or equipment making up a complete system shall
be completed to the satisfaction of the Engineer, before starting the final commissioning
tests on that system.
The Contractor shall carry out such tests and retests on complete systems as are
required to demonstrate to the satisfaction of the Engineer that substantial portions of the
Works are ready to undergo the trial operation with a minimum of interruption in regular
operation.
The final commissioning tests shall demonstrate satisfactory performance of the items
of Plant under normal operation and their response to abnormal and emergency conditions.
Each process system shall be set to work under manual control and final
commissioning tests shall be carried out for such time as is agreed by the Engineer as being
appropriate. Subsequently the automatic control equipment shall be set to work and further
final commissioning tests shall be done.
The tests shall include simulation of the full ranges of alarm conditions over the full
ranges of operation and include tests of emergency shutdown procedures including
electricity power failure.
The period of final commissioning tests shall finish after the Plant has been
satisfactorily operated by the Contractor, as certified by the Engineer, for a continuous
period of fourteen days or for such extended period in excess of 14 days as may be required
by the Engineer to make up for interruptions in operation. However, the Contractor will not
be required to run the Plant under the provisions of this clause more than once for one
continuous fourteen day period.
The Contractor shall use the 14 day period to optimise the water treatment process.
During the 14 day period or after the trial operation as decided by the Engineer, the
Contractor shall demonstrate the hydraulic capacity of the works and overflows at the
maximum works through put with:
During the hydraulic capacity tests, the Contractor shall measure water levels at various
points corresponding to the points where levels are identified on the approved hydraulic
profile drawing and shall also measure the free board at these points and at overflow points.
7.4.1 General
The Contractor shall start the trial operation when the following conditions have all been
completed:
Trial operation shall be carried out on Sections of the Works and on the Works as a whole,
as appropriate.
The trial operation shall demonstrate that the Works can fulfill all the mechanical,
electrical, instrumentation, control and automation and process requirements of the
Specification in the ambient conditions prevailing, using the raw water available at the time.
The Works shall be tested for performance for a continuous period of 30 days, of
which at least the last 15 days shall be uninterrupted by other tests. During the 30 days tests
the Works shall be operated at the maximum output for at least 15 days as instructed by the
Engineer. The object of the tests shall be to obtain a comprehensive set of data to show that
treatment performance meets the Specification and performance guarantees specified over
a range of flows within the design capacity limits. Following each flow change and after a
period of plant stabilisation all process and water quality parameters shall be measured and
recorded for comparison against the Specification and performance guarantees relating to;
• Works output;
• Clarified water quality;
• Filtered water quality;
• Treated water quality;
• Filter run duration;
• Clarifier sludge discharge;
• Filter wash water consumption;
• Thickener supernatant turbidity;
• Any other parameter.
During the 30 day performance trial period, the Contractor shall collect samples and
carry out analyses for the parameters listed in accordance with the sampling schedule at the
end of this section of the Specification.
Every sample taken shall be divided into three equal portions; one portion shall be
used for analysis by the Contractor's chemist, in accordance with the schedule. This analysis
shall be witnessed by the Employer's chemist. The second portion may be used by the
Employer for analysis at the discretion of the Employer. The third portion shall be retained as
a check sample. The sample volume shall be at least 3 liters.The Employer may, at its own
discretion, carry out additional sampling and tests at its own laboratories or accredited
laboratories as it deems necessary.
The methods to be used to analyse the listed parameters shall be as given in Standard
Methods for the Examination of Water and Wastewater; APHA-AWWA-WPCF, latest edition,
as follows;
These tests shall require provision of facilities and man-power, organisation and a
high degree of co-operation between the Contractor and the Employer and it shall be
deemed that this has been taken into account in the rates and sums entered in the
Schedules.
The Contractor shall be responsible for collecting and collating all data and test results
and shall carry out all necessary calculations to confirm compliance with the Specification
and Performance guarantees. A report comprising test data, results, calculations and
conclusions shall be submitted within one week of the date of completion of the tests, or set
of tests.
The test procedures to be used for the trial operation during the specified periods shall
be as follows:
The Works output shall be the difference between the clarified water flow and the filter
wash water flow. Clarified water flow shall be measured at the common clarifier outlet using
the flow meter in the pipe connecting the clarifiers and the filters totalised during the period
when the works is operated at the maximum flow. Filter wash water flow shall be measured
in the wash water outlet pipe from the wash water holding tank totalised during the period
when the works is operated at maximum flow.
Samples of clarified water, filtered water and treated water shall be taken at the specified
frequencies and tested by the methods listed in the Specification. Sampling at clarified water
and filtered water shall be separated by about two hours and that between filtered water and
treated water by about one hour to ensure that the same parcel of water is sampled in one
sampling event. The failure of one or more of water quality parameters in filtered water and
treated water shall be deemed to be a failure of the water quality test.
(c) Clarifier sludge discharge
Works input shall be monitored at the inlet flow meter to the works and shall be totalised
throughout the test. Losses due to clarifier Desludging shall be the works input less the
clarified water flow as defined above.
The total quantity of wash water used during the test period measured at the wash water
flow meter divided by the total quantity of the Works input as defined above for the same
period, multiplied by 100 shall be not greater than the filter wash water consumption as
stated in the Schedule of Guarantees.
The chemical consumption on the plant to achieve the specified water quality guarantees
during the test period shall be not greater than the chemical consumptions stated in the
Schedule of Guarantees.
The electrical energy consumption of the Works comprising raw water pumping plant,
treatment plant, treated water pumping plant and intermediate booster pumping stations over
the test period shall be evaluated on the basis of maximum demand and units used and shall
be divided by the volume of raw water treated over the same period. The electrical energy
consumption of the Works shall not be greater than the electrical energy consumption stated
in the Schedule of Guarantees.
If the performance during the tests of the Works (or any parts thereof) fails to comply
with the Specification or with the Contractor's performance guarantees, the Contractor shall
submit his proposals for meeting the requirement of the Specification and the guarantees to
the Engineer for his approval and shall carry out at his own expense, whichever measures
may be necessary to achieve the specified requirements. Such measures may include
improvements, alterations or additions to the plant and/or civil works and the Contractor shall
bear the whole cost of such modification including any changes to the civil, electrical,
instrumentation or mechanical works. The tests shall be completely repeated and shall be
continued until the Engineer is satisfied that the requirements of the Specification and the
guarantees have been met. Failure of any item of equipment or part of the Works which is
tested for performance as a separate exercise during the final commissioning tests will
require the Contractor to repeat the complete final commissioning test, as specified. Failure
of any one or more of the tests which forms part of the overall Works trial operation will
require the Contractor to repeat the complete trial operation. The duration of repeat trial
operation shall be not less than 15days.
In case of repeated failure of the trial operation, the Contractor shall continue to make
adjustments to the Plant and repeat the tests until full compliance is reached, or until the
Employer, at its sole discretion, decides to accept the Plant, despite the failure of the final
commissioning tests or the trial operation. In this event the Contractor shall pay liquidated
damages as a result of failure to achieve the guaranteed values of chemical consumption
and electrical energy consumption and delay damages to the Employer, in the amount as
guaranteed by the Contractor in the Schedule of Technical Particulars.
Sampling Schedule
The greatest care shall be taken to ensure that all process unit tanks are kept free from
contamination.
In addition the following structures shall be sterilised in accordance with the procedure
set out below;
• Pipes, channels and mixers from filter outlets to treated water reservoir;
• Contact tank and treated water reservoir;
• Pipe feed to treated water pumping station;
• Treated water pumping station pipe work;
• Treated water surge vessels (where applicable);
• Treated water pumping main connecting to MBRs /ZBTs;
• MBRs /ZBTs;
• Pipe main connecting the MBRs / ZBTs to OHTs;
• Existing / proposed OHTs in each village /habitation;The Contractor shall subject all
workmen who will be engaged in sterilising structures to a medical examination by a doctor
Approved by the Employer. Only workmen considered fit by the examining doctor shall be
permitted to enter the structure for carrying out any work associated with the sterilisation
procedure. The Contractor shall keep a separate register of all such labour and shall forward
a copy to the Engineer prior to commencing such work. The Contractor shall maintain strict
supervision over all workmen entering the tanks. The Contractor shall provide rubber boots
and means for the workmen to wash their boots clean and sterilise them before entering the
structure.
The Contractor's sterilisation procedure shall strictly adhere to as set out in relevant IS /
International Standards. The Employer will carry out the necessary sampling in the
presence of the Contractor, and the subsequent physical and bacteriological analysis. The
Engineer will advise the Contractor of the results. Should the tests fail the procedure shall be
repeated as many times as may be necessary to achieve satisfactory results.
The Contractor shall make all arrangements necessary for conveying the water from the
source to the point of filling and such arrangements shall be subject to the approval of the
Engineer. The Contractor shall provide all hoses, pumps and other equipment necessary to
carry out the tests. The Contractor shall also provide all water and chemicals necessary to
sterilise structures, which shall be of a type and from a source Approved by the Engineer.
The Contractor shall note that these structures are Confined Spaces as defined in the
Specification and that during the sterilisation process the levels of chemical in the
atmosphere may exceed acceptable occupational exposure limits. The work shall be subject
to the specified requirements for entry and working in Confined Spaces, and the Contractor
shall provide all necessary trained personnel and equipment as specified.
8.1 General
8.2 Pumps, valves and pipe work and general purpose machinery
(a) Pumps
Pumps shall be individually tested in accordance with relevant IS standards and the tests
shall be with clean water. Site conditions shall be simulated as nearby as possible including
the NPSH condition. Pumps shall be tested with their own prime movers. Where it is
impracticable to include the full length of the connecting shaft, the Contractor shall state the
allowances to be made for the losses incurred by its omission and shall demonstrate the
accuracy of the allowances to the satisfaction of the Engineer.
Pumps shall be tested at the guaranteed duty point and over the full working range from the
closed valve condition to 20 percent in excess of the quantity when a single pump runs alone
at minimum head. The tests shall provide information for performance curves to be drawn for
head/quantity, efficiency/quantity, power absorbed/quantity and net positive suction head /
quantity. Readings shall be taken at a minimum of seven points in addition to shut-off
condition. Each pump shall also be run at its duty point for at least 30 minutes.
Positive displacement pumps shall be tested in accordance with relevant IS.
For eccentric helical rotor pumps the tests shall provide information for performance
curves to be drawn for pump speed/flow, input power absorbed/flow differential
pressure/flow and pump efficiency/flow.
Pump casings shall be subject to a pressure test at 1.5 times the pressure obtained
with the delivery valve closed. The positive suction head when installed shall be taken into
account in determining this pressure. During the test, the casing and joints shall show no
signs of leakage, distortion or defect.
In addition to confirming the specified hydraulic performance of the pump set, the test
shall demonstrate that vibration is within the specified limits, the mechanical performance is
satisfactory and the noise level is within the specified limit.
Additionally chemical dosing pumps shall be tested in accordance with API standard 675
and the specified flow linearity, steady state accuracy and flow rate shall be demonstrated.
Valves and penstocks specified as operated by actuators shall be tested with their own
actuator. For valves and penstocks fitted with power operated mechanisms, the test shall be
carried out to demonstrate correct manual and power operation.
Gate valves shall be tested in accordance with BS EN 1171 or BS 5163 and BS 6755 Part 1
as relevant / relevant IS. Whichever applies, valve seat tests shall be made under open-end
conditions, the test pressure being applied to each face of the valve in turn.
Butterfly valves shall be tested in accordance with BS EN 593 and BS 6755 Part 1 / relevant
IS. The seat test shall be for tight shut-off and low leakage. Valves shall be tested under
maximum unbalanced water test pressure in either direction.
Air valves shall be water tested for drop-tightness at all pressures from 0.2 bars in steps of 2
bars up to the specified pressure. The valve body shall be water tested at 1.5 times the
specified pressure, at which pressure no damage or permanent deformation of the valve
body, ball or seat shall occur.
Two valves of each type and size incorporating large orifices shall be tested for exhaust of
air at a differential pressure up to 1 bar in steps of 0.1 bar and for inflow of air at a differential
pressure up to 0.5 bars in steps of 0.1 bar. During the tests the air flow rates shall be
measured by orifice plates in accordance with BS 1042 / relevant IS. Pressures (positive or
vacuum) shall be measured by Bourdon tube gauges or by mercury-in-glass manometers.
The temperature of the flowing air shall be measured in accordance with relevant parts of BS
1041 / relevant IS. The barometric pressure shall also be measured.
If the manufacturer provides results of independently witnessed air flow tests similar to
those specified and these are accepted by the Engineer, the specified airflow tests shall be
deemed to be completed.
(f) Check valves
Check valves shall be tested in accordance with the requirements of BS EN 12334 and
BS 6755 Part 1 / relevant IS.
Body strength: closed-end test, valve open, test pressure 1.5 times working pressure;
Valve element strength: open-end test, valve closed, test pressure of 1.5 times working
pressure applied to each end;
Leak tightness: open-end test, valve closed, test pressure of the working pressure applied to
inlet end, no visible leakage permitted.
Ball float valves shall be tested hydrostatically in the closed position and a pressure of
1.5 times the working pressure applied to the inlet end.
Plug valves shall be subject to hydrostatic shell and seat tests in accordance with BS
5158 and BS 6755 Part 1 / relevant IS.
Diaphragm valves shall be tested in accordance with BS EN 13397 and BS 6755 Part 1 /
relevant IS.
Ball valves shall be tested in accordance with BS 5159 and BS 6755 Part 1 / relevant IS.
Globe valves shall be tested in accordance with BS EN 13789 and BS 6755 Part 1 / relevant
IS.
Seating shall be tested hydrostatically at 2400 kN/m2 and the valve shall be tested for 1500
kN/m2 working pressure.
(m) Penstocks
Penstocks shall be operated from fully closed to fully open positions to verify correct
operation.
Penstocks shall be tested in accordance with BS 7775 and AWWA C501 as relevant /
relevant IS.
(n) Electric actuators
Compliance with the specified functional and performance criteria shall be demonstrated.
Compliance with the specified functional and performance criteria shall be demonstrated.
Pipe work shall be tested in accordance with the appropriate Reference Standards.
(q) Castings
Castings shall be tested hydrostatically to 1.5 times the maximum working pressure for a
minimum period of 1 hour.
(s) Cranes
Cranes shall be completely assembled and tested for all operations in accordance with
BS 466 / relevant IS. All slings, ropes, shackles and other lifting equipment shall be tested at
1.25 x their Safe Working Load.
(t) Weighers
All weighing equipment shall be tested for accuracy with standard weights and shall be load
tested at 1.25 times the safe working load.
Automatic in-line strainers shall be tested in accordance with the Reference Standards and
with manufacturer's own requirements.
Tests shall be carried out on all items of plant, vessels, pipe work and valves to
demonstrate compliance with the criteria specified and with relevant standards. Unless
otherwise specified the tests shall be in accordance with the Reference Standards including
BS 6754 for dryers, BS 6759 Part 2 for safety valves, BS 1123 Part 1 for fusible plugs, BS
3274 for after coolers, BS 5169 for air receivers, BS 1571 for compressors and BS 5500 for
pressure vessels and the manufacturer's own procedures / relevant IS.
Noise level of all the compressors and blowers shall be tested and shall not exceed the
specified limit.
For package units.functional tests of the fully assembled system shall be carried out to
demonstrate correct operation with respect to sequence and pressure.
8.2.2 Individual tests
The following Site inspections and tests shall be carried out as appropriate:
(a) Inspection to check the assembly of the Plant and conformity with the Specification
and consented drawings;
(b) Rotational checking of all electric motors;
(c) Hydrostatic testing of all gravity flow pipe work systems and penstocks at the
maximum head or differential head that can occur in service. Leakage from
penstocks shall be measured and recorded but shall not exceed the maximum value
stated in the AWWA C501 or BS 7775 or otherwise required for safe operation /
relevant IS;
(d) Hydrostatic testing of all pressurised pipe work systems at 1.5 x maximum working
pressure for a period of at least one hour; during this time the pressure shall not
change;
(e) Functional testing of each pump, compressor and blower to prove correct operation,
absence of fluid leaks, correct bearing temperatures and absence of undue vibration
and noise for a period of not less than four hours;
(f) Functional testing of auxiliary items including automatic in-line strainers and valve
actuators;
(g) Functional testing of valves to demonstrate correct orientation and operation;
(h) Overhead cranes and slings, ropes, shackles and other lifting equipment shall be
tested with a load of 1.25 x Safe Working Load and results recorded in accordance
with the Reference Standards. Additionally each complete system shall be tested for
all functions including overload safety device;
(i) All weighers shall be tested with standard weights for accuracy and shall be load
tested at 1.25 x the Safe Working Load;
(j) The following tests shall be carried out on the installed air supply systems:
• The air pipe work system shall be tested for 1 hour at 1.5 x maximum working
pressure using dry air or nitrogen;
• Pressure safety valve operation shall be demonstrated;
• Performance tests shall be carried out on all machinery, coolers and dryers
for a minimum period of 48 hours with air demand simulated by purging at
measured rates downstream of all plant subject to testing; the purging rates
shall correspond to zero demand, maximum demand and at least one
intermediate value.
• The tests shall prove correct operation, absence of fluid leaks, correct
operating pressures, temperatures and dew point and absence of excessive
vibration and noise with due regard to any containment and attenuation
provisions.
The complete mixer, flocculator and scraper system shall be checked for accuracy of
dimensions against construction drawings and all welds inspected.
The following Site inspections and tests shall be carried out as appropriate:
(a) Inspection to check the assembly of the plant and conformity with the Specification
and approved drawings;
(b) Rotational checking of all electric motors;
(c) Tip speed and flight speed, as applicable;
(d) Rotation speed;
(e) Functional testing of the mixers, flocculators and scrapers;
(f) Scraper torque overload protection device;
(g) Head loss across static mixers at maximum works throughput.
The performance of the static mixers shall be tested for compliance over a 30 minutes
period by dosing the chemical corresponding to each mixer at the specified doses and
concentrations. Alternatively a solution of sodium chloride shall be injected continuously at a
fixed dose in the range 10 to 20 mg/l or a fluoride solution at 1.0 mg/l as F. The injection
velocity shall not be greater than that applicable to the specified chemical dosing. The mixer
performance shall be determined by measuring either the conductivity or the chloride or the
fluoride ion concentration. The background conductivity value or chloride or fluoride ion
concentration shall be monitored during the test. The water shall be sampled continuously at
the prescribed sampling points from at least four different positions along a diameter of the
pipe using a sampling system specially designed for the purpose.
8.4 Filters
Upon preliminary approval of sources of filter material supply and within two months of
the award of Contract, the Contractor shall submit to the Engineer a 10 kg of representative
sample of each filter material for testing and approval as specified.
Filter material (sand and gravel) shall be tested by the Contractor before dispatch from
source in accordance with the following schedule. Certificates for all tests shall be delivered
to the Engineer for approval or rejection before the material is dispatched.
(a) For a volume equivalent to the volume in each filter Grading curve, effective size and
uniformity coefficient.
(b) Additionally for a volume equivalent to the volume in 2 filters Specific gravity and
losses of weight on acid washing and ignition.
(c) Additionally every 500 m3 or every batch, whichever is the smaller Loss due to
abrasion.
The following Site inspections and tests shall be carried out as appropriate:
(a) On delivery to Site, one kg of filter material shall be taken from a selection of bags
until 12 kg is obtained. The samples shall then be mixed and quartered before testing
as follows;
(i) Gravel: a sample shall be taken from each delivery to Site as described
above and graded. Samples shall be examined to ensure they are similar to
the initial 10kg sample.
(ii) Sand: samples shall be taken from each delivery to Site as described above.
Tests shall include a sieve analysis and preparation of grading curves, and shall give
effective size, uniformity coefficient and specific gravity. A visual inspection shall also
be carried out to ensure it is similar to the initial 10 kg sample.
In addition to the above tests, certificates for each load equal to one filter volume
shall include tests to determine loss on acid washing and ignition as applicable to the
filter material.
(b) Inspection to check the assembly of plant and conformity with the Specification and
approved drawings;
(d) Functional testing of each air blower for correct operations, absence of fluid leaks,
correct bearing and gearbox temperature and absence of undue noise and vibration;
(e) Relief valve operation and blower unloading device shall be demonstrated.
Filters shall be tested as follows before any filter material is placed and additionally, in the
case of pipes lateral system before placing concrete on the pipes;
The empty filter bed shall be filled with water to a level 150mm above the top of the nozzles.
Air shall then be passed into the under drain system at such a rate that the system can be
seen to pass air thorough the nozzles over the whole filter area. Any discrepancies in
distribution shall be rectified and the test repeated.
All the nozzle outlets shall be plugged. The filter under drain system shall then be filled with
water and a pressure of (a-b+c) applied to the underside of the filter floor or to the piped
lateral system as applicable where:
a = twice the normal peak pressure during a combined air and water filter wash, or separate
air and water filter wash as applicable to the design, measured under the filter floor or in the
filter laterals;
b = the downwards pressure on the floor due to the weight of media and water which would
be present during air scouring;
c = the pressure due to any water present in the filter above the floor during the test.
Any pressure relief pipe on the wash water supply pipe work shall be blanked off during this
test. The test pressure shall be maintained for one hour. Any leaks detected shall be
corrected and the test repeated.
After placing the material in the filters and backwashing to remove fines the Contractor
shall take samples of the material from each filter and carry out sieve analysis and the
results along with grading curves shall be submitted to the Engineer for approval. Only when
the Engineer has given approval to the samples, shall the Contractor bring the filters into
service.
The sampling of sand in the individual filters shall be repeated in the twelfth month of the
Defects Notification Period for compliance with the Specification. The results shall be
submitted to the Engineer for approval.
Tests shall be carried out on all items of plant, vessels, pipe work and valves to
demonstrate compliance with the criteria specified and with relevant standards and tests
specified. Unless otherwise specified, the tests shall be in accordance with the Reference
Standards and the manufacturers' own procedures.
The following Site inspections and tests shall be carried out as appropriate;
• Inspection to check the assembly of the plant and conformity with the Specification
and approved drawings;
• Rotational checking of all electric motors;
• Functional testing of all auxiliary items including mixers;
• All tanks shall be filled to overflow level and inspected for absence of leaks;
• Hydrostatic testing of all pipe work systems at 1.5 x maximum working pressure for a
period of at least one hour; during this time the pressure shall not change;
• Relief valve operating pressure shall be demonstrated;
• Functional testing of each pump to prove correct operation, absence of fluid leaks,
correct gearing and gearbox temperatures and absence of undue vibration and
noise.
Tests shall be carried out on all items of plant to demonstrate compliance with the criteria
specified, with relevant standards and tests specified.
Unless otherwise specified, the tests shall be in accordance with the Reference Standards
and manufacturers own procedures.
• Inspection to check the assembly of the plant and conformity with the Specification
and approved drawings;
• Rotational checking of all electric motors;
• Functional testing of all ancillary items including mixers;
• The slurry tanks and saturators shall be filled with water to overflow level and
inspected for absence of leakage;
• Water and slurry pipe work and all components up to the point of application shall be
tested hydrostatically for one hour at 1.5 x maximum working pressure;
• Relief valve operating pressure shall be demonstrated;
• Functional testing of each pump to prove correct operation, absence of fluid leaks,
correct beaming and gearbox temperatures and absence of undue vibration and
noise.
Tests shall be carried out on all items of plant to demonstrate compliance with relevant
standards. Pumps shall be tested as specified.
Unless otherwise specified, the tests shall be in accordance with the Reference Standards,
the manufacturers' own tests where applicable.
• Inspection to check the assembly of the Plant and conformity with the Specification
and approved drawings;
• Sample water pipe work and components shall be tested hydrostatically for 1 hour at
1.5 x maximum working pressure or 5 bar whichever is greater. During the test the
pressure shall not change;
• Drain pipe work shall be flushed and inspected visually for absence of leaks;
• Water quality monitoring instruments shall be tested as specified.
Tests shall be carried out on all items of plant to demonstrate compliance with the criteria
specified, with relevant standards and tests specified.
Unless otherwise specified, the tests shall be in accordance with the Reference Standards
and manufacturers own tests where applicable.
The following Site inspection and tests shall be carried out as appropriate;
• Inspection to check the assembly of the Plant and conformity with the Specification
and approved drawings;
• Rotational checking of all electric motors;
• Hydrostatic testing of all pipe work systems at 1.5 x maximum working pressure for a
period of at least one hour during which the pressure shall not change;
• Service water storage tank shall be filled to overflow level and inspected for absence
of leaks;
• Testing of safety showers and eye baths for correct operation.
8.9.1 General
Miscellaneous tests shall include tests for hydraulic pallet trucks, safety equipment, and
contact tank and access equipment.
8.9.2 Off-site inspection and testing
Tests shall be carried out on all items of plant to demonstrate compliance with the criteria
specified, with relevant standards and tests specified.
Unless otherwise specified the tests shall be in accordance with the Reference Standards
and the manufacturer's own procedures.
Tests shall be carried out to demonstrate compliance with the Reference Standards
and the specified functional and performance criteria.
Unless otherwise specified, the tests shall be Routine Tests in accordance with the
Reference Standards and the following additional tests as appropriate to demonstrate;
(i) High Voltage & Meggar test of busbars with circuit breaker connected;
(ii) The interchangeability of withdraw able equipment;
(iii) The correct operation of electrical and mechanical interlocks;
(iv) The correct and accurate functioning of current and voltage operated
protection relays by primary and secondary current injection and voltage
application;
(v) The correct polarity between current and voltage elements of power operated
protective devices, instruments and metering;
(vi) Meters do not creep with the removal of either the current or voltage supply.
(vii) The correct operation of control circuits, indications and alarms;
(viii) Where necessary a suitable test panel shall be provided for simulation of
external controls and signals during such tests;
(ix) The calibration of ammeters Voltmeter, KW meter, PF meter, Hz meter etc at
0.25, 0.5 and full scale deflection by secondary current injection;
(x) The calibration of transducers;
(xi) Type and special tests shall be carried out when specified.
(i) Power frequency high voltage pressure test with all breakers racked in and
closed, between phases and from phase to earth;
(ii) Pressure test on secondary small wiring circuits;
(iii) Milli-volt drop tests - Milli-volt drop (Ductor) test across circuit breaker
contacts and between extreme terminals on individual panels, (for
comparison purposes, the manufacturer shall state design values for each
size and rating of equipment);
(iv) Operational closing tests - These tests are to ensure the operation of closing
coil or spring release coil and satisfactory closing of the circuit-breaker with
the voltage on the coil down to 80% of its rated voltage and to ensure that
mal-operation does not occur, with a voltage at the coil of 120% of its rated
voltage;
(v) Operational opening tests - These tests are to ensure the satisfactory
operation of the shunt trip circuit, and the tripping of the circuit-breaker at no
load conditions with the trip coil energised at 50% of its rated voltage;
(vi) Mechanical tests - All mechanical interlocks on the switchgear panels shall be
thoroughly tested to ensure their correct operation, together with mechanical
tripping, opening and isolating devices;
(vii) Interchangeability – With drawable circuit-breaker panels of identically
equipped units shall be capable of inter-changing of circuit-breaker trucks.
This facility shall be proved. A check shall also be carried out to ensure that
the inter- changeability shall not be possible between incoming and outgoing
feeder circuit-breaker trucks;
(viii) Heat run tests - Heat run tests will not be required on panels manufactured
under this Contract provided type test figures for heat runs carried out on
identical panel types are made available for inspection by the Engineer;
(ix) General operation tests;
(x) In addition to the tests given above, tests shall be conducted, where
applicable, for the following purposes;
• to ensure satisfactory tripping of the circuit-breakers with the closing
coil energised;
• to prove satisfactory mechanical behaviour of the circuit-breaker when
the closing coil is energised with the tripping coil also energised;
• to prove that the operation of the power closing device when the
circuit-breaker is already closed causes neither damage to the circuit-
breaker nor danger to the operator;
• Protection and control circuits;
• For all forms of current transformer protection, the following
information shall be made available to the Engineer prior to the time of
inspection;
• Current transformer magnetising curve;
• Recommended relay setting;
• Calculated primary operating current at this setting;
• Calculated through fault stability values, where applicable;
• Values of any stabilising and setting resistors employed in the
scheme.
(xi) As far as possible, based on the completeness of the circuits in the final
manufactured form within the manufacturer's premises, the satisfactory
operation of associated control and protection circuits shall be proved by the
following tests;
• to ensure the correct operation of all current operated protection relays and
direct acting coils at the recommended setting by current injection;
• to ensure the correct polarity between current and voltage elements of power
relays, meters and instruments;
• to ensure the correct operation of control circuits at normal operating voltage
by operation of local control switches and simulation of operation from remote
control positions.
Note: The checking of the operation of all protection relays and control circuits is to be
carried out with all closing and tripping circuits energised at their normal rated
voltage.
• Indicating ammeters shall be checked for calibration at 0.25, 0.5, 0.75 and full
scale deflection by primary current injection testing;
• Indicating voltmeters shall be checked for normal voltage readings by voltage
application;
• Frequency, power factor and kilowatt meters shall be tested for accuracy of
indication;
• Integrating kWh meters shall be tested for correct rotation. Creep tests shall
be carried out to ensure that the meter is inoperative with voltage alone, if the
secondaries of current transformers are left connected with the primary
current interrupted;
• All transducers shall be tested for at least 5 different points in the complete
working range of each unit.
The following Site inspections and tests shall be carried out as appropriate;
(i) Insulation resistance of main connections and secondary wiring using an approved
insulation tester. The test shall be carried out between phases and phase to earth. All
circuit-breakers, switches and contactors shall be in circuit and closed;
(ii) The correct operation of electrical and mechanical interlocks shall be demonstrated;
(iii) The correct and accurate operation of current and voltage operated protection relays
shall be demonstrated by primary and secondary current injection and voltage
application. At least two points shall be demonstrated for each relays. Simulation test
on the operation of thermal overload relay for motor shall not be acceptable. Actual
test on thermal overload relay for motor shall be carried out;
(iv) The stability of unit protection systems shall be demonstrated by primary current
injection;
(v) The correct operation of control circuits, indications and alarms shall be
demonstrated;
(vi) The continuity of all protective conductors shall be checked;
(vii) The correct operation of inter tripping circuits shall be demonstrated;
(viii) Demonstration of accurate operation at 50% and 10% of working range on all
measuring devices, meters and transducers;
(ix) Any tests required by the electricity supply company.
(i) Pressure testing - Power frequency pressure test shall be carried out on equipment for
use on systems above 1000 volts. For systems up to 1000 volts the insulation resistance of
the equipment shall be tested with a 500 volt Megger hand generator. These tests shall be
carried out with all circuit phases and phase to earth. All secondary small wiring circuits shall
be similarly tested;
(ii) Mechanical tests - All mechanical tests specified and carried out at Manufacturer's
premises are to be re-checked to ensure satisfactory operation of the Works in the final
erected state;
(iv) Protection and control circuits - The satisfactory operation of all current operated
protection circuits over their whole operating range and correct connection of CT wiring shall
be tested by primary current injection;
(v) The checking of the operation of all protection relays and control circuits shall be carried
out with all tripping circuits energised;
(vii) The satisfactory operation of control circuits shall be tested from local and from remote
positions;
(viii) Indicating ammeters - Indicating ammeters shall be checked for calibration at 0.25, 0.5,
0.75 And full scale deflection by primary current injection testing;
(ix) Indicating voltmeters - Indicating voltmeters shall be checked for normal voltage reading
by voltage application;
(x) Integrating kWh meters - Where possible kWh meters shall be tested for correct rotation.
Creep tests shall be carried out to ensure that the meter is in-operative with voltage alone, if
the secondaries of current transformers are left connected with the primary current
interrupted;
(xi) Other indicating meters - Other indicating meters including frequency, power factor and
kilowatt meters shall be tested for accuracy of indication;
(xii) Transducers - All transducers shall be tested for at least 5 different points in the
complete working range for each unit;
(xiii) Current transformers - Current transformers shall be tested for the following;
(xiv) For all forms of current transformer protection the following information shall be made
available to the Engineer prior to the time of testing;
(xv) Voltage transformers - Voltage transformers shall be tested for the following;
(xvi) Operational sequence tests - Tests shall be carried out on all starter panels to test
operational sequence and operation of protection devices. Sequential tests for pump- motor
shall be able to carry out when putting the VCB at “Test” position without required to modify
any control circuit;
(xvii) Continuity of earth conductors - Continuity tests shall be carried out on the earth
conductor of the switchboard, such tests being by current injection;
(xviii) This does not include the earth resistance test of the station earthing system which
shall be tested as detailed elsewhere in the Specification.
Motors shall be inspected and tested to show that they are compliant with the
Specification and approved drawings.
Tests shall be in accordance with BS 4999: Part 143 / relevant IS. For low voltage
standard production motors for general use, the tests shall be routine checks. For high
voltage and low voltage motors for main drive application, the tests shall be duplicate.
If the test to determine the locked rotor current of cage induction motors is carried out
at reduced voltage, allowance shall be made for the effect of saturation when adjusting for
rated voltage. The estimated value of locked rotor current at rated voltage shall be stated on
the test certificate.
A Polarisation Index test shall be carried out for high voltage motors.
The requirement for "basic" or "special" tests shall be as specified.
Unless otherwise specified the following tests shall be carried out on each motor before
energising;
8.12 Transformers
Transformers shall be inspected and tested to show that they are fully compliant with the
Specification and approved drawings and shall include the following tests as a minimum;
• Routine tests;
• Measurement on winding resistance;
• Ratio, polarity and phase relationship;
• Impedance voltage;
• Load loss;
• No-load loss and current;
• Insulation resistance;
• Induced over voltage withstand;
• Separate source voltage withstand;
• Magnetic circuit voltage withstand
• Transformer tank oil leakage test (1 kg/cm2 for 24hours);
• Transformer noise level measured in accordance with methods and procedures
detailed in IEC 551 -Noise level shall not exceed 65dBA;
• Tap changer switching, mechanical and electrical tests according to BS4571 /
relevant IS;
• Zero sequence impedance measurement;
• Type tests;
• Impulse voltage withstand test;
• Temperature rise test;
• On load tap changer panels;
• Operational tests;
• Sequence tests.
Unless otherwise stated by the Engineer at the time of placing the order, evidence of
records of satisfactory type test carried out on identical transformers to those ordered will be
accepted in lieu of actual tests on transformers manufactured under this Contract for impulse
voltage withstand test. Temperature rise test shall be carried out on one transformer of each
size and type. The guaranteed no-load and load losses of each transformer shall be verified
at the manufacturer's works. The positive tolerances stipulated in BS 171 / relevant IS shall
not be accepted. The Board reserves the right to reject any transformer which does not
achieve its declared guaranteed values.
Samples of insulating oil shall be taken and subjected to dielectric strength tests. If the
insulating oil fails the site test, the Contractor shall carry out the drying of oil to remove the
moisture content or replace the oil and then carry out the oil tests again to comply with BS
148 / relevant IS.
The correct operation of the charger in the float and boost modes and the alarm functions
shall be checked.
Unless otherwise specified cables shall be subject to Routine Tests in accordance with the
Reference Standards.
The following inspection and tests shall be carried out on the completed cable installation as
appropriate;
• Insulation resistance between cores and core to earth using an approved insulation
tester compatible with the voltage grade of the cable under test. For high voltage
cables, the test shall be carried out at the highest voltage compatible with the voltage
grade of the cable under test. Where cables are jointed, the test shall be repeated
after each joint has been completed;
• For multicore and multipair cables, continuity of each core and correct identification
and ferruling;
• Supports and cleating arrangements are fitted;
• For power cables, correct phasing and phase colouring;
• Correct bonding and earthing of cable metallic sheaths, core screens and armouring;
• Sealing of cable entries against water and vermin ingress;
• Mechanical glands have been correctly fitted;
• For high voltage cables pressure tests shall be carried out in accordance with the
Reference Standards using high voltage d.c. Wherever possible cables shall be
energised after the satisfactory completion of the pressure test;
• For high voltage cables, additional checks and tests to the manufacturers' specific
instructions shall be carried out;
• For low voltage cables, additional tests as required by the Reference Standard;
• Loop resistance test for each pair of conductors in multipair instrumentation and
telephone distribution cables;
• Attenuation test for each pair of conductors in telephone distribution cables;
• Measurement of cross talk across pairs of conductors in telephone distribution cables
over a minimum frequency band of 0.5 to 20kHz. The conductors connected to a
resistive load equal to that of their characteristic impedance. The injected signal shall
have a sinusoidal waveform at a level equivalent to the intended operating level of
the modems to be connected (-3dBm).
8.15 Earthing
On completion of the earthing installation tests shall be carried out in accordance with the
Reference Standards and the following requirement;
The building services installations shall be inspected and tested in accordance with the
Reference Standards.
The lightning protection installation shall be inspected and tested in accordance with the
Reference Standards and the following requirement;
9.0 TRAINING
Training shall be provided on site and at the Employer’s premises as applicable, and
shall commence at such time as directed by the Engineer/Employer. Training of the
Employer’s personnel shall aim at achieving optimum operation of the Works including
maximum efficiency of plant, optimum use of chemicals, minimum loss of water, and
minimum numbers of operating staff. The Employer’s personnel shall be trained in all
aspects involved including management, operation of plant, water quality tests, laboratory
procedures, control of chemicals, routine and periodic maintenance of every item of
equipment and plant, health and safety at work, security and in all other subjects as may be
required for satisfactory operation and maintenance of the Works.
During the period of classroom and practical training, the Employer will make available
selected staff for the Contractor to train in the safe and efficient operation and maintenance
of the installed plant. The Contractor shall allow for comprehensive training in at least two
separate sessions for each of the following disciplines and designed to accommodate the
Works shift (24 hour, 3 shift) pattern.
• Staff discipline;
• Management staff;
• Operational staff including Works chemist and laboratory personnel;
• Electrical and ICA maintenance staff;
• Mechanical maintenance staff.
The exact number of personnel attending the training sessions will be finalized prior to
the training. During the last 12 months hands-on training period, the Contractor shall remain
fully
responsible for the operation and maintenance of the Works, but shall utilize the Employer's
staff to the fullest extent possible, commensurate with their proficiency at the time, with a
view to providing a smooth transition of responsibility for operation and routine maintenance
from the Contractor to the Employer. During installation of the Plant, the Contractor shall
produce videos (CD ROM format) where necessary illustrating all essential aspects of plant
installation and testing for use during training of the Employer's personnel.
The Contractor shall provide an experienced training manager (with a minimum of ten years
training experience and five years experience in a similar capacity) to organize and
supervise the training programme. He shall be based on site and shall remain on site from
the commencement of the training programme until the completion of the first 12 months of
"Operation and Maintenance Period".
The Contractor shall ensure that, training on individual items of plant, equipment or
systems such as chemical facilities, instrumentation, control and automation systems (ICA)
and similar shall be carried out by the manufacturer or specialist sub-contractor. Provision
shall be made for both classroom and hands-on-training in this respect. The Contractor shall
be responsible for ensuring that such training is properly co-ordinate into the overall
programme, and that the quality of the training is of the type, quality and standard specified.
The Contractor shall submit details of the number of training specialists he shall assign to
each phase of training together with details of their duties, qualifications, capabilities and
experience to the Engineer for approval.
The Contractor shall maintain a register of attendance at training sessions and the
subjects covered and shall carry out assessments jointly with the Engineer and the
Employer’s representative to monitor the effectiveness of training. Based on the
assessments, the Contractor shall offer technical advice, organize and conduct special
tutorial sessions for any personnel who have jointly been assessed and needing them and
ensure that they carry out operations and procedures correctly. Training shall be based on
the relevant approved operating and maintenance manuals and record drawings including
P&I Diagrams and flow sheets, which shall be available before training commences.
Training shall be provided for management, operating and maintenance staff and shall
cover in detail the areas listed below. At least six months prior to the start of training the
Contractor shall provide a draft syllabus of the proposed training and shall then develop in
liaison with the Engineer and the Employer an approved syllabus, training programme and
training methodology. The approval syllabus programme and methodology shall be
submitted to the Engineer at least one month prior to the agreed start date for training. The
syllabus to be provided by the Contractor shall be based upon, but not limited to, the
following;
(i) Health and safety procedures, with particular respect to toxic and hazardous gas
areas, chemical handling, electrical plant use, maintenance, entry/working in
confined spaces and similar;
(ii) General plant description:
The method of delivery shall be structured to include theory, group discussion and part
practical elements supported by audio-visual aids, hand outs, demonstrations and
appropriate assessments. Hand outs shall include extracts from operating and maintenance
manuals supplemented by specially prepared material and shall be prepared so as to be
collated to form a set of course notes for use by attendees for future reference. Audio-visual
aids shall include relevant video presentations prepared by plant and equipment
manufacturers, as well as those prepared during plant installation and testing.
Classroom Training shall start at an appropriate time during the erection of plant and
shall be completed before the commencement of the trial operation of the Works. “Hands-
on” training as specified elsewhere shall start prior to the commencement of any final
commissioning test of the equipments and shall be completed before the commencement of
the trial operation of the Works. During "Operation and Maintenance Period", the Contractor
shall provide "hands- on" training, as specified, and full direction and supervision of the
Employer's staff, so that by the last twelve months period of operation and maintenance by
the Contractor during "Operation and Maintenance Period", the Employer’s personnel are
sufficiently proficient so as to take over the operation and maintenance of the Works with
minimal supervision by the Contractor. The extent/length of training provided shall also take
into account the numbers of Employer’s personnel involved, shift patterns and scope of
training or the like. As a minimum requirement the following number of 8 hour, day shifts
shall be allowed for each course in the scope of training (excluding the “hands on” training
to be given during the erection and pre-commissioning testing):
Subject Days
Process chemistry 2
Operation of all plant including safety aspects of chemical and
10
other plant
Electrical maintenance 4
Mechanical maintenance 4
ICA maintenance 5
The number of trainees per theory and group discussion class shall not exceed ten and the
number of trainees per practical and/or “hands on” training session shall not exceed five.
The training shall be monitored continuously by the Contractor jointly with the
Engineer and / or the Employer’s representative and each trainee will be required to
demonstrate their understanding of the instruction received. In order to achieve an
acceptable standard of competence, the Contractor shall build into the training, a two-step
assessment monitoring programme as set out below or a comparable assessment method
approved by the Engineer:
(a) Each session shall include small groups of trainees being given a task/scenario, which
will require them to use the knowledge learnt during the session to feed back and
demonstrate understanding in such a manner as to promote trainee participation without
putting individuals under pressure. This type of assessment shall be adopted for both
theoretical and practical sessions and time shall be built into the course programme for this
purpose.
(b) Each trainee shall be issued with a training task book which will include sections for
recording attendance at individual classroom, practical and "hands-on" training sessions.
Each section of the task book shall relate to a session undertaken during the training and will
be signed off by the Contractor, Engineer and the Employer on completion of the training
session.
The training material shall be in a user-friendly style and shall cover in general terms the
main technical procedures and activities associated with the Plant. The documents shall be
in a format suitable for use in future training of Employer’s personnel up to operating shift
supervisor level. Training documents shall be securely bound in such a manner that
individual pages can be added or replaced so that the documents can be kept up to date. On
completion of the training programme, the training manual and other documentation,
Updated to take account of changes during the performance of the programme, shall be
submitted to the Engineer in CD ROM format (IBM PC compatible).
The Contractor shall provide an outline training programme indicating target dates for the
following associated activities:
(a) Submission of draft training plan, draft training manual, training task book and draft
functional task book;
(b) Submission/agreement with the Engineer and the Employer of detailed training plan
and syllabus. This shall include agreement of the assessment structure for trainees,
training manual, training task books and functional task books;
(c) Submission/agreement with the Engineer and the Employer of training development
programme. This will include aspects such as duration of training courses, dates,
training venue/arrangements, training content, training materials, confirmation of
numbers involved;
(d) Training review updates;
(e) Two week “familiarisation” programme;
(f) Number, dates and duration of courses/sessions within overall training programme;
(g) Relative dates for start of plant tests;
(h) Date for availability of draft operating and maintenance manuals.
The Contractor shall make available suitable personnel to carry out training updates
and assessments at six months from the start of the "Operation and Maintenance Period"
and at six months prior to the end of the "Operation and Maintenance Period".
The Contractor shall attend to all requests for advice and assistance, both oral and
written, made by the Employer’s personnel and shall keep a written record of these requests
with a copy submitted to the Engineer monthly.
Any advice or technical support given by the Contractor to the Employer’s personnel,
as a result of requests from them, and the action taken by them as a result of such technical
support shall be recorded by the Contractor and copies shall be submitted to the Engineer
monthly.
The Contractor shall keep a complete record of Plant formal training carried out in the
classroom and on the plant on DVD (MPEG2 format) and at the end of the training period
shall submit to the Engineer four copies on DVD disks (MPEG2 format).
10.0 SPECIAL TOOLS, SPARE PARTS, TOOLS AND TEST EQUIPMENT
As well as the workshop tools specified, the Contractor shall provide special tools or
appliances which he considers necessary for erection, dismantling or testing, operation and
maintenance for any part of the Works during the life of the Works. Special tools provided
shall not be used for the erection of the Plant unless the Engineer instructs the Contractor to
demonstrate the effectiveness of any special tool. The special tools shall be handed over to
the Employer in a new and unused condition. Should the Contractor require any special tools
at Site for erection, he shall provide his own. Tools for each different type of equipment shall
be contained in a suitable box clearly marked or labeled with its description. Each tool shall
be identified and a list of tools shall be fixed to the inside of the box lid. Each set of tools
shall be supplied with the equipment it serves.
The Contractor shall submit a complete list of spares recommended for continuous
operation of all items of Plant and the Works for "Operation and Maintenance Period", in
Schedule of Technical Particulars. The list shall be based on average servicing requirements
and prevention of breakdown for continuous operation of the Plant. Following detailed design
of the Plant, the list submitted at the time of tender shall be updated. The list shall contain a
description of the spare parts, ordering reference numbers, with parts identified on
equipment drawings, quantities, unit price and the total price. The prices entered in this list
shall be the prices quoted, except where the items listed at that time have been superseded
by the requirements of detail design of the Works. The list shall be re-submitted in a single
submission for the approval of the Engineer before any items are ordered.
The sum included in the Contract for provision of those spare parts listed in the Price
Schedules is provisional, and the Employer reserves the right to order spares in accordance
with the recommendations of the Contractor, or to vary the list and quantity of items to be
ordered, or not to order spare parts through the Contract. Should additional quantities be
ordered from the Employer, the Contractor shall be obliged to supply based on the unit rates
being entered in the Schedules of Technical Particulars.
Any spares that are specified elsewhere as part of any plant item shall be provided
and the cost shall be deemed to be included in the lump sum for the plant item. The final
approved spare parts schedule shall be submitted in hard copy and CD ROM format. It shall
show part numbers, ordering references and equipment drawings showing the spare parts.
Spare parts shall be new original manufacturers' spares. They shall be packed separately
from the main Plant in packages or containers designed to preserve the spares from the
effects of long term storage under the ambient conditions at the Site. Any items which
cannot be packed in this shall be protected from corrosion by applying temporary protective
coatings and shielded from mechanical damage. All items shall be clearly labeled with brief
descriptions and part numbers, and shall be cross referenced to the approved spare parts
list.
Spare parts shall be delivered to the Site prior to the commencement of "Operation
and Maintenance Period". Spare parts being ordered additionally by the Employer for their
use after they take over the operation and maintenance of the Works shall be delivered to
the Employer 6 months prior to the completion of "Operation and Maintenance Period".
Whether the Contractor can achieve this requirement can be a prerequisite condition for the
Employer to issue the Taking-Over Certificate of "Operation and Maintenance Period".
The Contractor shall not use any of the spare parts for construction, commissioning or
rectification of defects without written permission from the Engineer. Parts so used shall be
Replaced free of charge by the Contractor prior to the commencement of "Operation and
Maintenance Period". The Contractor shall not use any of the spare parts additional ordered
by the Employer for them to carry out future operation and maintenance of the Works without
written permission from the Employer or the Engineer. Parts so used shall be replaced free
of charge by the Contractor prior to the issue of the Taking-Over Certificate of "Operation
and Maintenance Period". All packages may be opened for such examination as the
Engineer may require and packing’s shall be designed to facilitate opening and thereafter
repacking.
The Contractor shall supply two sets of all the standard workshop hand tools
necessary for the dismantling and repair of the Plant.
Tools and test equipment for each different type of equipment shall be contained in a
suitable hardwood, floor mounted cabinet clearly marked or labeled with its description.
Each item test equipment and tools shall be identified and a list shall be affixed to the inside
of the cabinet door.
Each set of tools and items of test equipment shall be supplied with the equipment it serves.
11.1 General
Following the Engineer to accept the Contractor has satisfactorily completed the
individual tests, final commissioning tests and trial operation of the Works, the Engineer shall
issue a “minor outstanding works and defect list”. This “minor outstanding works and defect
list” is to provide the details of the defects to be rectified and works that are still outstanding
which the Employer can accept the Contractor to finish those works after the Employer has
taken-over the Works completed. The Contractor shall acknowledge to complete these minor
outstanding works and rectifies the identified defects within the Defects Notification Period of
"Construction Period". Under this pre-requisite condition and other necessary conditions
specified elsewhere in the Contract, e.g. to receive from the Contractor the Performance
Security for "Operation and Maintenance Period", the Engineer will issue the Taking-Over
Certificate for "Construction Period" and a letter to the Contractor to permit "Operation and
Maintenance Period “to commence. The Defects Notification Period of "Construction Period",
which is of 12 months duration, shall commence on the same day.
The Employer and the Engineer will arrange handover of the whole Works to the
Contractor, for them to commence the operation and maintenance of the whole Plant. The
duration of "Operation and Maintenance Period" will be 60 months.
During the first twelve months of "Operation and Maintenance Period", which is also
the Defects Notification Period of "Construction Period", the Contractor shall be responsible
for the following;
(a) Operation and routine maintenance for the whole of the Works, including the
provision of all necessary skilled supervisory staff and unskilled workers necessary
for full operation and maintenance of the works. The Contractor shall provide at least
five persons per shift. In addition, the day shift shall include a supervisor for the
whole of the plant, intake structure, pumping stations, booster stations and water
treatment plant, a process chemist, ICA system subcontractors, and a maintenance
supervisor. The additional day shift staff shall be available on a "call out" basis to
deal with any problems, which may arise outside the specified day shift period.
During this twelve month period the Contractor shall provide `hands-on' training to
the Employer's operating and maintenance personnel, who will be trained to carry out
their future duties under the direction and supervision of the Contractor. The
Contractor shall be responsible for the work of the Employer’s personnel during this
period;
(b) Rectifying defects in accordance with the requirements entered in the “minor
outstanding works and defect list” issued by the Engineer for "Construction Period",
including the provision of all supervision, labor, parts and materials including
chemicals, fuel and lubricants excluding electricity power charges. All defects of the
Works in "Construction Period" shall be rectified by the Contractor in this Defects
Notification Period and the Contractor shall prove to the Engineer or Employer of
that;
(c) The supply of all spare parts required for maintenance of plant as specified
elsewhere in the Contract; and
(d) Carrying out amendments to the operating and maintenance manuals based on
experience gained in the Employer operating the plant.
11.3 Contractor's obligations after the first twelve months and before the last twelve
months of "Operation and Maintenance Period"
(a) Same scope of work as (a) above, except that formal “hands-on” training is not
required in this period. In this period, the Contractor shall provide advice to the
operation and maintenance staff of the Employer at the Works for the queries they
raise, based on the experience the Contractor obtained during the course of their
operation and maintenance work;
(c) Provision of all materials including chemicals, fuel and lubricants excluding electricity
power charges for the operation of the Works.
11.4 Contractor's obligations during the last twelve months of "Operation and
Maintenance Period"
After satisfactory operation of the Works during the first four years of "Operation and
Maintenance Period", the Contractor shall be responsible for the following:
100
(a) Advising on operation of the whole of the Works to the Employer's personnel for the
remainder of the "Operation and Maintenance Period", who will be conducting
operation and maintenance of the Works under the direction and supervision of the
Contractor. The Contractor shall provide all necessary skilled advisory staff and
providing necessary training. The staff shall be provided on a day shift basis on
weekdays only and shall number at least three, including the overall plant supervisor,
ICA sub-contractor's supervisor and a maintenance engineer. The staff shall also be
available on a "call out" basis to deal with problems arising outside the specified day
shift period. The Contractor shall be responsible for the work of the Employer’s
personnel during this period;
(b) During this twelve month period the Contractor shall provide `hands-on' training to
the Employer's operating and maintenance personnel, who will be currently carrying
out operation and maintenance of the Works under the direction and supervision of
the Contractor. The Contractor shall supplement the “hands-on” training material
being used in the training mentioned above by those experience the Contractor
gained in operation and maintenance of the Works in the first four years of
"Operation and Maintenance Period";
(d) The supply of all spare parts required for maintenance of plant as specified
elsewhere in the Contract;
(e) Carrying out amendments to the operating and maintenance manuals based on
experience gained in the Employer operating the plant.
(f) Provision of all materials including chemicals, fuel and lubricants excluding electricity
power charges for the operation of the Works.
During the "Operation and Maintenance Period", the Employer will provide and be
responsible for the following in respect of the operation of the Works;
(a) All manpower to be trained to operate and maintain the Works under the direction of
the Contractor;
(b) Electric power;
(c) All manpower to operate and maintain the Works in the last twelve months of
"Operation and Maintenance Period", under the direction and supervision of the
Contractor.
The installation shall be visited during the eleventh month, twenty-third month, thirty
fifth month, forty-seventh month and fifty-ninth month of "Operation and Maintenance Period"
by a competent engineer or other specialist representative and training manager of the
Contractor. He shall inspect all Plant provided under the Contract, ensure that servicing,
adjustments and recalibrations as necessary are being carried out on all those items
requiring attention and assess the competence of the Employer's personnel. The Contractor
shall obtain the Engineer's or the Employer’s approval at 14 days prior to each visits and
shall supply a full service report within 14 days after each visit.
101
12.0 TEST ON COMPLETION FOR OPERATION AND MAINTENANCE PERIOD OF
THEWORKS
Test on Completion at the end of "Operation and Maintenance Period" shall be carried
out to show that the Works are in complete and satisfactory working order. The tests shall be
agreed in detail with the Employer and be carried out to an agreed programme which shall
be submitted to the Employer at least 28 days prior to the start of the tests.
The tests will include functionality, leakage and any structural tests necessary to prove
that the Works are in full and compliant order, and are fit for purpose.
The Test on Completion shall be similar to those set down for Trial Operation for
"Construction Period" as in above clause. The continuous period the Works, to be tested on
handover, shall be 7 days. The tests shall be designed to prove that the Works and
treatment performance meets the Specifications and Performance Guarantees entered in
the Schedule of Technical Particulars. Additionally, the following specifications and
Performance Guarantee aspects shall also be included:
• Works Output
• Classified Water Quality
• Treated Water Quality
• Filter run duration
• Clarifier Sludge discharge
• Filter Wash water Consumption
• Thickener supernatant turbidity
• Any other Parameters
The procedures to be used for the Test on Completion during the specified period
shall be as listed in items (a) to (f) inclusive of relevant above clause. All Mechanical Plant
and Pumping equipment shall be inspected during operation, and tested for functionality and
performance. The contractor shall prove to the Employer that plant as installed and operated
complies fully with specified performance.
All those defects and outstanding works identified in the Tests on Completion, that the
Employer considers shall be completed prior to allowing the Defects Notification Period for
"Operation and Maintenance Period" to commence, the Contractor shall carry out the
rectifications works promptly. Repeated tests shall then be conducted.
After all the critical defects and outstanding works be completed and the necessary
repeated tests be satisfactorily completed, the Employer will furnish to the Contractor a
"defects and minor outstanding work list". The Contractor shall rectify all those defects and
complete all the minor outstanding works in the list during the Defects Notification Period of
"Operation and Maintenance Period".
102
PART - B: PARTICULAR SPECIFICATION
1 CAPACITY OF THEWORKS:
Each of the above pumping stations and mechanical plant shall include all necessary
systems, plant, equipment, structures and protections allowing safe and undisrupted
operation and maintenance. These systems and plant may not be expressively mentioned
in the specifications but it shall be Contractor’s responsibility to undertake relevant study
and analyses and propose systems suitable for stipulated conditions and requirements.
2.3 Drawings
The Contractor shall prepare all relevant drawings as specified elsewhere for execution
of the works. The Contractor shall prepare the drawings duly considering available space,
location of site and based on detailed site survey. The equipment / machinery layout shall
be prepared duly considering sizes of proposed plant and equipment, hydraulic
calculations, etc. The submissions shall include detailed designs, drawings, procedures
and method statements required for construction of the pumping stations, all associated
systems and mechanical plants.
2.4 Works, systems and equipment common to all pumping stations
Valves and pipe work – general requirements
Pump, valves, pipe work, and their supports shall be designed to withstand the
maximum stresses imposed by any operating condition, including the shock resulting from
pump starting when the advancing inrush of water strikes the closed non-return valve.
The design maximum velocity through the valves and pump branch pipe work shall
not exceed 2.0 m/s.
The design pressure rating of valves and pipe work shall be 1.5 times the pump shut
valve pressure or 16 bar, whichever is greater.
2.4.1.1 Valves
Each pump shall be provided with a delivery non-return valve, a delivery isolating valve,
and an automatic air inlet / release valve. The air valve shall be fitted to the delivery pipe
work near to the discharge bend and upstream of the non-return valve.
A main suction isolating valves shall be provided. The valve shall be of the same nominal
size as the suction manifold. Valve shall be resilient-seated butterfly valves, fitted with
electric actuators. Air valves shall be made of ductile iron and all other valves shall be
made of cast steel. Valve operation when manual shall be by hand wheel through integral
reduction gearing. Valve operation when manual shall be by hand wheel at the level of
valve installation or from the platform / walkway at higher level (usually ground level) by
headstock. The position to operate the valve manually shall provide the highest operation
convenience to the future operators. The Contractor shall submit their proposal for the
approval by the Engineer.
Pump suction isolating valve shall be resilient-seated butterfly valves, fitted with electric
actuators. Valve operation when manual shall be by hand wheel through integral reduction
gearing.
Pump delivery isolating valves shall be resilient-seated butterfly valves, fitted with electric
actuators. Valve operation when manual shall be by hand wheel through integral reduction
gearing.
Non-return valves shall be of the swing-check type, designed for rapid closing as soon as
forward flow stops. If any closure-rate control is needed, full details shall be as provided in
the Technical Schedules at the time of Tender.
A main isolating valve shall be provided. The valve shall be the same nominal size as the
delivery manifold.
The valve shall be butterfly type with resilient seating, and manually operated by a hand
wheel through integral reduction gearing.
The valve shall be the same pressure rating as the delivery manifold.
All valves size DN250 and above, installed in the chambers within pumping station
compound shall be fitted with electric actuator. Valve operation when manual shall be by
hand wheel through integral reduction gearing in the chamber and by T key from the
chamber cover.
2.4.1.2 Pipe work
Pump suction and delivery pipe work shall be fabricated steel, with flanged connections.
Pressure ratings shall match those for valves as given above.
Dismantling joints shall be incorporated wherever needed to facilitate the removal of
pumps and valves.
Pipe work shall be protected from corrosion as detailed for exposed steel pipes
elsewhere in the Specification
2.4.1.3 Pump common delivery manifold
The pump deliveries shall be joined to a fabricated-steel delivery manifold, with flanged
connections. The manifold shall be of nominal diameter as per design. The term pipe work
shall include all necessary supports, saddles, slings, fixing bolts and foundation bolts
required to support the pipes and its associated equipment.
The pipe work shall be laid out and designed so as to facilitate the erection, painting in-
situ, dismantling of any section for maintenance and to give a constant and uniform flow of
working fluid with a minimum head loss. Positions of flanges shall take in to account any
necessary steel and concrete pipe supports or thrust blocks.
Flexible joints shall be provided where necessary to allow for differential settlement of
building structure. Wherever practical, flexible joints shall be provided with tie bolts or other
means to transfer longitudinal thrust along the pipe work as a whole. Wherever possible
standard fittings shall be used in preference to fabricated or special fittings. Facilities shall
be provided for draining the pipe system and releasing air. The drainage fluid shall be
piped into the building drainage system and the period of time for drainage shall not exceed
30minutes.
The pipe work layout within pump stations shall have the approval of the pump
manufacturer. Wherever the pipe enters and leaves the building through walls, a pipe
sleeve should be used and proper sealing to be done to make it fully water tight.
Valves, strainers and other devices mounted in the pipe work shall be supported
independently of the pipes to which they are connected.
The manifold design pressure rating shall be 1.5 times the pump shut valve pressure or
16 bar, whichever is greater. Protection shall be as specified for pump delivery pipe work.
The reducers on inlet and delivery branches shall suit the pump branch sizes and
corresponding inlet and delivery pipe branch sizes shown. Inlet reducers shall be eccentric
with flat tops.
2.4.2 Electric overhead travelling crane (EOT)
An electric overhead travelling crane shall be provided in each of pumping stations and
shall be designed to serve the pumps and all the plant installed in the motor hall, and for
water intake pumping station to lift and lower the skips provided for de-silting the pump
wells. Enough hoisting cable shall be incorporated to lower skips to the bottom of the pump
well. EOT crane shall be provided for clear water pumping stations and booster stations
also as specified in Design Criteria.
The Contractor shall determine the Safe Working Load required for the crane and capacity
shall be as specified in specifications. The pendant control shall be designed for operation
from the motor hall floor.
Crane operating speeds shall be as follows:
2.4.2.1 Long travel: Not more than 40 m /min
2.4.2.2 Cross travel: Not more than 25 m /min
2.4.2.3 Hoisting and lowering: Not more than 10 m /min
A fixed ladder with safety hand railing shall be provided for access to the crane for
servicing, and to access the maintenance platform for use when servicing high-level
lighting and ventilation units mounted in thereof.
The Contractor shall carry out comprehensive steady state hydraulic analysis and
pressure (transient) surge analysis on the complete pumping system at all the pumping
stations and along the pipelines under all operating conditions. The surge analysis shall be
undertaken by independent specialist Subcontractor using a proven computer programme.
The surge analysis shall identify the most adverse transient operational conditions. The
analyses shall include but not be limited to the following conditions:
- Complete power failure to the pumping stations with all duty pumps running at
maximum capacity.
- Start up of the pumps under the specified control system
- Shut down of the pumps under the specified control system
In addition to the delivery pipeline the surge analysis shall include consideration of the
length of pipeline(s) between the pumping stations and the pressure vessel(s), and the
suction condition(s).
The objective of the surge analysis is to recommend surge protection equipment which
ensures maximum and minimum pressures under all conditions within the allowable surge
rating of the pipelines as indicated below:
- Maximum pressures shall not exceed the capabilities of the pipes and fittings on
the system.
- Minimum pressures in the system shall not fall below atmospheric pressure and
subsequently rise above atmospheric pressures again during the same transient
event. Pressures below atmospheric pressure will only be permitted as the
systems drain down through supply connections during extended periods of
pump shutdown.
The recommended solutions should include sensitivity checks to show that it is still valid
with possible variations in system parameters such as wave speed, friction factor and
system demands.
The solution should include but not be limited to the following recommendations:
- Size and details for delivery air pressure vessel (Surge Vessel)
- Details for controlling the air volume in the above vessels
- Details and alarms for monitoring the air volume in the above vessel.
- Recommendations for controlling “slam” on the pump delivery non-return valve
that may adversely affect the lifetime or operation of the valve and the system
The Contractor shall determine the required air pressure vessel capacity as per detailed
engineering, according to the transient surge analysis.
In addition to surge vessels of total capacity as arrived by calculations, the Contractor shall
install at least one standby surge vessel (for each pumping station) of the same type and
size as the proposed ones. Such surge vessel shall provide stand by capacity in a case of
releasing one of duty vessel for maintenance.
The Contractor shall furnish the surge analysis report to Engineer for approval. The report
shall include computer printouts and graphs showing maximum and minimum pressure
envelopes. The report shall also include time-flow and time pressure plots at critical points.
Surge protection may be by pressure vessel or feed tank, but flywheels to add to the pump
rotating inertia shall not be used.
Surge Vessels shall be compressed air type, designed, constructed, installed and tested as
detailed elsewhere in the Specification.
Surge vessel(s) shall be installed near, as practically possible, to the pumping stations.
2.4.4 Provision of safe access
Steel access platforms and ladders shall be provided wherever needed. The
arrangements shall ensure that all parts of the plant are made readily accessible in safety
for operation and maintenance.
2.4.5 Ventilation system
Each of the pumping stations shall be provided with a ventilation system designed to limit
the air temperature rise to not more than 5 deg. C, above the ambient, when the plant is
operating. The system shall be designed to provide uniform ventilation throughout the
pumping station to promote plant cooling and eliminate pockets of stagnant air.
The system shall be sized based on the maximum number of motors operating together,
with all the lights switched on, and with three operating personnel present, but the design
maximum air extraction rate shall be not less than ten air changes hourly for the complete
pump hall.
The system shall comprise a number of roof-mounted air extraction fans and manually
operated air inlet louvers. The fans shall be fitted with non-corrodible protective cowls and
all other protective measures needed to make them weatherproof in the climatic conditions
at the Site, including monsoon winds combined with heavy rainfall. Louvers shall be
manually operated and comprise as a minimum of removable anti-insects stainless steel
mesh and sand trap.
The air extraction units shall be designed so that routine servicing can be from the
maintenance platform on the crane and access from the roof is not needed.
Fans shall be controlled from wall-mounted contactors, accessible from pumping station
floor level.
2.4.6 Sump Pump and Discharge Pipe work
Each pumping station shall be equipped with a minimum two submersible sump pumps
(one duty and one stand by) pumping water from the sump to the location approved by the
Engineer. The sump pump shall have an integral vertical level switch and all principal
components and shall be fabricated from Grade 304 stainless steel. Pump shall be capable
of pumping solids up to 10 mm diameter.
The sump pump shall be supplied with all mechanical, electrical, I & C components,
ancillaries and materials required for installation and normal operation.
Capacity of each of the sump pumps shall be minimum 100 l/min. The pump head
shall be as per hydraulic design.
Sump pump control and electric systems shall be designed in such a way that allows both
pumps operation at the same time in a case of emergency.
Sump pump discharge pipe work within the pumping station and above ground shall be
of galvanized carbon steel and incorporate a check valve and isolation valve (as minimum)
to prevent back syphonage. Below ground, pipe work shall be made of rigid material.
2.5 RAW WATER PUMPINGSTATION
2.5.1 General
The Contractor shall design the plant to be installed in the raw water pumping station. The
arrangement shall be as per specifications.
2.5.2 Sump Model Study
To improve the performance of pumps, the Contractor shall perform sump model tests
with various pumping combinations. The sump model study shall have to be taken up and
completed before the finalization of sump design. The tests shall be conducted considering
the design parameters.
2.5.3 Mechanical plant included
Mechanical plant to be installed at the intake structure and the raw water pumping station
shall include but not be limited to the following;
2.5.3.1 inlet gratings for intake well (in case of intake well and connecting pipes)
2.5.3.2 intake screens / trash racks constructed in two levels (in case of intake channel);
2.5.3.3 set of stop logs and lifting beams;
2.5.3.4 manually operated overhead crane for intake screens and stop logs;
2.5.3.5 penstocks;
2.5.3.6 raw-water pumps;
2.5.3.7 pump delivery valves and pipe work, including delivery manifold with isolating
valves;
2.5.3.8 delivery pipe work with isolation and throttling / control valve, flow meter, and flow
meter bypass;
2.5.3.9 electric overhead travelling crane for the pump hall;
2.5.3.10 two submersible drainage pumps with flexible hose;
2.5.3.11 two sump pumps;
2.5.3.12 de silting plant and tools;
2.5.3.13 pump well ventilation system;
2.5.3.14 pump hall ventilation system
2.5.3.15 pump hall fire fighting system and other auxiliary systems,
2.5.3.16 surge protection system including surge vessels, air compressors (duty and
standby):
2.5.3.17 provision for safe access
2.5.4 Intake screens / trash racks and stop logs (in case of intake channel)
Bar screens shall be provided to protect each inlet. Screens shall be designed for easy
cleaning by manual raking. The screen free area provided shall be not less than five times
the area of the inlet which is protected.
Bars shall be spaced not more than 25 mm apart, and the screens shall be sized so that
themaximumheadlossshallnotexceed50mm.Screenbarsshallbeprovidedwithstiffeners for
reinforcement and the stiffeners shall be designed and installed to avoid impeding raking.
Rakes shall be provided, each designed for use by one man. Rake handles shall be of
non- corrodible lightweight tubular alloy. Rake tines shall fit the screen apertures and shall
be of softer material than the screen bars to ensure bars are undamaged by raking.
Raking containers shall be provided, designed for ease of handling and lifting. They shall
be free draining, with mesh apertures not larger than 25 mm square. They shall be fitted
with lifting handles designed for use by hand or with the hoist.
Stop log slots to be provided in structures and shall be fitted with channel-section inserts,
built-in to the structure during construction. Materials used for the inserts shall be corrosion
resistant and designed for long life in installed conditions at site. The slot inserts shall be
designed to ensure effective sealing with stop logs.
Manually operated overhead travelling crane shall be provided to raise the containers to
the structure top level for safe disposal as well as for lifting stop logs. The hoist shall be
fitted with a suitable hook, designed for quick attachment and release, and shall be
designed for operation by one-man.
2.5.5 Penstocks (Sluice Gate) for isolating the inlets
Manually-operated penstocks shall be installed inside the pumping station pump well to
shut off each of inlets. Each penstock shall be provided with a headstock, mounted at the
floor level, complete with extension shaft and couplings.
Penstocks and their frames shall be cast iron, and the frames shall be provided with cast
iron mounting spigots (thimbles), for building-in the frame to the structure. Penstocks shall
be the off-seating type, with rising spindles.
Apertures shall be rectangular, sized to provide a clear opening to match the inlet port
size. Penstocks shall be designed for the maximum pressure to which they could be
subjected in service.
2.5.6 2.5.6 Raw water pumps
As per requirements and specifications as specified elsewhere
2.5.7 2.5.7 De-silting plant and tools
The plant and tools to be provided for de-silting shall include:
2.5.7.1 4 No. long-handled shovels;
2.5.7.2 4 No. handpicks;
2.5.7.3 4 No. skips for loading with recovered silt.
Tools shall be of first-class commercial quality, designed for rough handling and frequent
use. Shovel blades and pick heads shall be steel, and handles of best quality ash or
hickory wood.
Skips shall be robustly built of fabricated steel, designed for hard ware and protected from
corrosion by painting. They shall be designed for emptying by tipping. They shall be
provided with handles suitable for hand carrying and for safe lifting without tipping when
using the station crane.
The total weight of each skip when fully loaded with silt shall not exceed 50 kg.
particulate matter.
Rapid gravity filtration
Filtration through sand media. Removal of flocculated particulate matter
carried over from clarifiers.
Disinfection Disinfection system proposed shall be as
per WHO standards for drinking water
Treated water storage
Hydraulic mixing with the addition of lime. Final pH correction to give a positive
Langelier Index
Storage in treated water reservoir. Balancing treated water inflow to treated
water pumped outflow
Used wash water recovery
Sedimentation of used filter wash water. Separation of supernatant for return to inlet
works and sludge discharged for further
treatment.
Sludge thickeners
Thickening of clarifier sludge and sludge Reduction of volume of sludge for further
from used filter wash water Treatment
Sludge drying beds
Removal of excess water. Increase in dried solids concentration to
facilitate handling for removal from site.
Plant Road and drains All units shall be provided with access road
for vehicular movement, hard stand area.
Proper drainage system for effective
drainage of storm water shall be provided.
At the maximum overflow rate, the head over any overflow weir shall not be greater
than 250 mm and at the maximum design treatment flow, taking into account conditions
when the specified number of process units are not in service, the upstream overflow level
shall be at least 100 mm below the crests of the overflow weirs. Each overflow shall be
served by a level probe arranged to initiate an alarm state when the water level rises to
within 20 mm of the overflow weir level.
The hydraulic profile of the works shall be such that overflow occurs at the point in
the process stream immediately upstream of the condition causing the overflow, so that
water does not back up to other upstream overflow locations and so that no more than one
overflow occurs in the water treatment process at any time. The tanks, chambers and
channels shall be designed to accommodate the head necessary to evacuate the
maximum flow at overflows with a freeboard of at least 200mm.
The sludge balance tank overflow shall be discharged to the sludge drying beds. All
other overflows shall be discharged to the site drain.
3.4.3 Drainage
All water retaining structures and interconnecting channels and pipes shall be provided
with facilities for complete dewatering. Where practicable, provisions shall be made to allow
draining of individual process units, compartments, sections of channels and lengths of
pipes without interrupting the operation of the treatment works.
Dewatering shall be either by gravity (direct or via a sump) or using pumps or by both.
Where pumped drainage is proposed adequately sized pump sumps with portable pumps
of the submersible type shall be provided as specified
A site drainage system discharging to an approved nallah off the site of the water
treatment works shall be provided. All drainage not discharging to a specified location shall
be directed to the site drainage systems.
3.5 Inlet works
3.5.1 General
Raw water shall be delivered by pipeline from the intake pumping station through a MS /
DI pipe to the treatment works, terminating at an upturned bell mouth at the cascade
aerator. The raw water shall flow over steps of cascade aerator and shall be conveyed
through inlet channel. The inlet works shall consist of an inlet channel, a Parshall flume and
a clarifier flow division chamber unless flow division is incorporated in the clarifier block.
3.5.2 Mixing Tank
A flash mixing tank shall be provided with mechanical mixer for the dosing of aluminium
sulphate or poly aluminium chloride and oxidising agent.
3.5.3 Clarifier flow division chamber
A clarifier flow distribution chamber shall be provided unless provision for the uniform
distribution of flow from the clarifier inlet channel to individual clarifiers is incorporated in
the clarifier block.
The clarifier flow distribution chamber shall distribute flow to the clarifiers using a system
of free-fall weirs. The design of the system shall ensure that equal division of flow is
effected between the clarifiers in service at all flows up to the hydraulic capacity of the
clarifiers.
Weir penstocks (also called weir gates) on the flow division weirs shall be provided for
isolating the individual clarifiers at the flow division chamber or other equivalent
arrangements shall be incorporated in the clarifier inlet channel. The flow division weirs
could be provided in sections to enable weir penstocks to be accommodated. The
arrangements for isolation shall be provided with access.
3.5.4 Access and drainage
All structures of the inlet works including the flume and clarifier flow division chamber shall
be provided with stair access and platforms complete with hand railing for operation and
maintenance of the plant. Where structures are connected by channel, a walkway complete
with hand railing shall be provided along the side of the channel.
The clarifier flow division chamber shall also be provided with access from the top of the
clarifier.
At least one hydrant point and a high pressure hose of 20 m length complete with
hose reel, hose connector and nozzle shall be provided central to the clarifier flow division
chamber for washing and cleaning purposes.
The inlet works shall be provided with facilities for completely dewatering the pipelines,
conduits, chambers and where applicable individual compartments independently.
3.6 Mixing of chemicals
3.6.1 Location of dosing points
The points of application of chemicals shall be as specified.
3.6.2 Mixing -general
Mixing of chemicals at all dosing points shall be by high speed impellor. Hydraulic energy
for mixing at the relevant points of chemical application shall be derived from a device
which produces a head loss adequate for mixing.
Mixing of chemicals at each point shall produce the most uniform dispersion of the
chemical into the body of the water as quickly as possible. Chemical solutions shall be
diluted with an adequate amount of carrier water before dosing into the point of greatest
turbulence at the mixer.
3.6.3 Design criteria
Design requirement for each mixing point shall be as specified in CPHEEO manual.
All free-fall weirs shall be ventilated below the nappe to prevent a depressed or clinging
nappe and shall have a downstream freeboard of not less than 50 mm under the maximum
flow condition.
3.6.4 Mixing chambers
Mixing chambers at the contact tank and treated water reservoir inlets shall be fully
covered and ventilated and access to dosing facilities shall be sealed with removable
water-tight covers. All mixing chambers shall be provided with facilities for completely
draining of all water and sludge. Drainage shall be by either gravity or pumped to the site
drainage system and for gravity drainage each chamber shall be supplied with a 150 mm
diameter outlet valve and pipe work. Valves shall be provided with extension spindles and
supporting brackets and shall be operated by hand wheel.
Where gravity drainage is not feasible, facilities shall be provided for pumped drainage and
shall consist of pump sumps within the chamber.
3.6.5 Chemical dosing at mixers
Aluminum sulphate shall be dosed by an injection pipe / coagulant distributor terminating
close below the eye of the impellor. Dosing of lime shall be by perforated distributor
channel.
All distributors shall be designed to minimize clogging and provide uniform distribution.
The coagulant distributor shall be provided with removable end caps to give access for
cleaning. Two flexible wire brushes shall be supplied to serve the pipe distributors.
A hydrant and a hose complete with hose reel, hose connector and nozzle shall be
provided at mixing points for cleaning and washing down purposes.
Means of access shall be provided at the mixing points for operation of valves, flushing and
cleaning of distributors and for maintenance purposes.
All chemical injection devices at each point of application shall be provided in duplicate (1
duty, 1 standby) to allow one to be taken out of service for cleaning, without interrupting
chemical dosing.
3.6.6 Protection against chemical attack at dosing points
At locations where aluminum sulphate and other chemicals are distributed the concrete
surfaces within 0.5 m upstream and 2.5 m downstream of the dosing point, both above and
below the water surface shall be protected against chemical attack by a suitable protective
coating.
3.7 Clariflocculator
Clariflocculator design shall be as given in CPHEEO manual.
3.8 Filtration
3.8.1 General
The treatment works shall be provided with minimum number of filter units as specified in
design criteria. The filters shall be of the duplex type comprising two equal size beds
separated by a central used wash water collection channel and operating at constant rate
on the principle of influent flow division and constant water level. The under drain system
shall comprise nozzles set in a plenum concrete floor.
The filters shall be arranged in two banks located on either side of a covered central
gallery containing a walkway and filter wash consoles at high level and filter pipe gallery
and filtered water channel complete with walkway at low level.
The banks of filters shall be served by an adjoining filter building which shall house the air
scour blowers, compressors and any other equipment required for the operation of the
filters. The filter building shall also accommodate administration facilities for the works,
which shall include offices, the control room, laboratory, toilets and mess facilities. Air
blower and compressor rooms shall be sound proofed to reduce the sound level in offices
on the floor above to less than 65 dB(A).
3.8.2 Layout and design considerations
Layout and design of the filters shall comply with the following;
3.8.2.1 All filters shall be identical in dimensions and designed for combined air and water
washing using filtered and disinfected water.
3.8.2.2 Filtration shall be through sand media with depth of bed and effective size as per
manual.
3.8.2.3 Filter media shall be supported by a layer of gravel of specified depth and which
shall be placed in graded layers so as to be stable under the simultaneous
application of air and water wash unless the filter nozzle system is specifically
designed to operate with a lesser depth of gravel under the simultaneous
application of air and water wash.
3.8.2.4 The depth of water in the filter above the top of the media shall be as specified.
3.8.2.5 The design shall minimize any tendency to develop negative head in the filters;
filter outlet shall be arranged to discharge filtered water over a weir into the
filtered water channel with weir crest set at about the top level of the sand layer.
3.8.2.6 Filter run length shall be not less than 24hours.
3.8.2.7 The design shall minimize any tendency to scour the media, particularly during
filling or surface flush and to carry-over of media particularly at the start of the air
scour.
3.8.2.8 Filters shall be arranged for slow start by opening the outlet in a step wise manner
over 30 minute period.
The filter works shall be designed to facilitate sections being taken out of service for
inspection, cleaning of filters and channels and maintenance, without total loss of supply.
Stop logs shall be provided at the inlet channel to each bank of filters for isolation.
The filter design shall have been proved in service in existing installations in the tropics for
a minimum period of five years in at least three drinking water treatment works.
3.8.3 Filter media
The loss of media in the first year of operation shall be not be greater than 1% of the total
media in the filters.
Spare media shall be provided to replace that lost in the first 5 years of operation following
issue of the Performance Certificate.
The minimum quantity supplied shall be 50 m3 and shall be packed in bags and stored on
2 - way entry close boarded pallets in a location to be advised by the Engineer. Pallets
shall be shrink wrapped and shall be stacked two high.
3.8.4 Filter flow control
The filter control shall be of the equal inlet flow division, constant water level type.
The inflow to the filters shall be divided equally between filters using the pre-set overflow
weirs in the inlet to each filter. The control system shall be arranged to maintain the level of
water in each filter constant irrespective of the inflow and the head loss by modulating the
filter outlet flow control valve as necessary.
The filtration rate shall be as uniform as possible between filters any variation shall be
limited to plus or minus 5%. The water level variation in the filter shall be limited to 50 mm
during the complete filtration cycle.
3.8.5 Filter inlet and flow division
The inlet flow division weir to each filter shall be provided with a stainless steel weir plate
set in stainless steel frame with an adjustable height of at least 150 mm and an
pneumatically actuated penstock / valve for filter isolation and shall be arranged to feed the
filter by way of a central washout channel. A flow stabilising baffle shall be provided at the
inlet to each weir.
3.8.6 Filter outlet valve
The outlet pipe of each filter shall be provided with a flow control valve of the butterfly type
with a pneumatic actuator and shall be arranged to discharge into the filtered water channel
via a chamber containing an outlet weir.
3.8.7 Filter level
Each filter shall be provided with a level electrode system for terminating the drain down of
a filter and for the execution of any other operations during the wash and for initiating any
level alarms.
3.8.8 Loss of head indicators
Each filter shall be provided with a loss of head transmitter and local indicator. The unit
shall be designed and installed to eliminate air entrainment and sand ingress. The
transmitter signal shall be utilized to initiate remote indication and alarm annunciation.
In addition, each filter shall be provided with piezometer tappings to monitor head loss
across the media and outlet valve. The system shall be provided complete with all
necessary puddle pipes, strainers, manometer tubes (diameter 50 mm) and floats,
mounting boards, scales calibrated in 0.10 m minor divisions and 1 m major divisions to
show water levels, interconnecting pipes, valves and fittings.
3.8.9 Filter washing
The method of cleaning filters shall be by simultaneous application of air and water
followed by a water rinse.
Filter washing shall be automatic following manual initiation. Filter valves and
penstocks which require to be operated as part of the wash sequence shall be fitted with
pneumatic actuators of the double acting type. Except where specified the time to
open/close penstocks/valves shall be less than one minute.
It is an essential requirement of the Contract that only proven wash systems, materials and
procedures be used. Particular care shall be exercised in ensuring equality of pressure and
flow to the nozzle floor system bearing in mind the high velocities of air and water. The
Design shall incorporate such devices as may be necessary for converting velocity head to
pressure head.
Wash rates proposed shall be those of the Contractor's own proven design, but in any case
shall meet the requirements as given in CPHEEO manual.
Air supply for air scour shall be provided by Root type rotary air blowers. One or two
duty blowers and at least one standby blower of equal capacity to one duty blower shall be
provided. Air blowers shall be provided with acoustic enclosures.
Each filter shall be provided with an air release if the Contractor considers it is
necessary to remove any residual air from the plenum floor.
Disinfected water shall be used for washing filters and shall be drawn under gravity
from an elevated storage tank.
The scour air and wash water pipes shall be laid in a ring main.
The wash water supply to the filters shall be provided with a flow meter of the
magnetic type. The rate of wash water flow shall be controlled by a butterfly valve located
downstream of the flow measuring element. Operation of the valve shall be manual by
hand wheel unless the Contractor requires it to be automated for applying two different
rates for combined air-water wash and the water only rinse. The valve shall be provided
with a position indicator and a locking device where applicable. The maximum velocity
through the control valve shall not exceed 5 m/s. The valve shall be provided with access
for operation and maintenance.
The rate of flow shall be indicated local to the control valve.
Wash water shall be removed from above the media by a side weir arrangement. The
system shall be designed to:
- Remove wash water evenly from the filter and as rapidly out of the filter as
possible.
- Prevent the loss of filter media, particularly at the start of the air scour.
- Incorporate means for removal of residual solids at the end of the rinse phase.
- Be free draining on completion of the backwash.
Suspended troughs over the media surface for wash water removal will not be accepted.
Surface flush (also known as cross-wash) using clarified water may be provided and
the manner in which it is introduced onto the filter shall be such that scouring of the filter
media at the points of entry is avoided. The quantity of surface flush water used shall be
included in the computation of the wash water consumption.
It shall be possible to drain a filter, in emergencies, to waste via the wash water outlet
valve instead of draining it to supply. This is defined as a `dump' and will amount to the
volume of water formed by the full depth of water over the sand media down to the washout
weir sill. Used wash water including `dump' water shall gravitate to the used wash water
holding tanks. Dump water is not required to be included in the computation of the wash
water consumption.
3.8.10Filter sampling
Each filter shall be provided with facilities for taking a filtrate sample, which shall be
brought to an accessible point in the lower walkway gallery. Each sampling point shall be
provided with a sink complete with a drain.
3.8.11Filter performance
When operated in accordance with the Contractor's instructions at the rated throughput
using all filters less one out of service for maintenance and one washing individual filters
working together with clarifiers shall perform to the standards as specified elsewhere.
Filters shall achieve the filtrate quality specified with a minimum length of filter run of 24
hours.
Water used in washing filters (i.e. wash water and surface flush water) averaged over a 24
hour period shall not exceed 2.5% of the works input averaged over the same 24 hour
period.
3.8.12 Drainage
The filter building shall be provided with a drain sump to collect and evacuate drainage in
the filter pipe gallery.
If drainage by gravity is not practicable the sump shall be provided with two drain pumps
arranged to operate on automatic level control as duty and `duty assist'.
Pumps shall be fitted with quick release couplings and lifting chain and shall be supplied
complete with delivery and non-return valves and pipe work.
All filter plant drainage shall be discharged to the used wash water channel or to the site
drainage system.
3.8.13 Access
Access shall be provided on top of the filters as follows:
- Along filter inlet channels
- Between pairs of filters leading to the upper filter gallery
- Covered walkway between the two banks of filters.
Access shall also be provided from the filter building to the lower and upper filter galleries
and also to the opposite end of the upper filter gallery. Lower filter gallery shall be provided
with stair access from the upper filter gallery from the opposite ends. Filter wash control
panels shall be located opposite each filter in the upper filter gallery. Upper filter gallery
shall be provided with glass panels to observe the filters from the central walkway.
All access ways where necessary shall be provided with hand railing.
3.9 Used wash water disposal plant
3.9.1 General
Filter wash water after use shall be discharged to a filter wash water recovery tank from
which supernatant will be returned to the treatment works inlet at a rate not greater than
5% of the rated throughput.
3.9.2 Used wash water recovery tank
One used wash water holding tank shall be provided. The tank shall be provided with two
equal sized compartments interconnected by a penstock, to allow one to be taken out of
Service for settling of the used wash water or for maintenance, whilst the other remains
available to receive used wash water. Each compartment shall be rectangular in plan with
the floor laid to a fall and terminating in a pump sump. The capacity of each compartment
of the tank shall be adequate to store as a minimum, the wash water from two consecutive
filter washes. In sizing the tank and the draw-off systems the Contractor shall assume that
all filters will be washed consecutively spaced at 30 minutes apart.
The used wash water shall flow into an inlet channel and then through penstocks into
the compartment in use.
The inlet channel to the tank shall be provided with an overflow discharging to the
site drainage system.
Each compartment shall have a floating draw-off arm which shall be design to
remove settled water from the upper part of the tank. The floating arm shall be connected
to the draw-off connection by an articulated pipe or suitable arrangement. A restraint
system shall be provided to prevent excess movement of the floating draw-off arm and
articulated pipe during filling and when the compartment is fully emptied.
Each compartment shall have a sludge draw-off connection with a downward facing
bell mouth in the sump.
Each compartment of the used wash water recovery tank shall be provided with level
monitoring equipment for filter wash inhibit and pump control.
The Contractor shall include sufficient pedestrian access-ways in reinforced concrete,
which shall be fitted with hand railing and kick-plates on both sides of the tank and on the
common wall throughout their full length, to enable the operational staff to have ready
access around each compartment and to the inlet channel.
Means of access shall be provided into each compartment of the wash water recovery
tank.
3.9.3 Used wash water return
After a period of settling the supernatant shall be returned to the works inlet from the used
wash water recovery tank at a rate not exceeding 5% of the raw water inflow to the
treatment plant. The water remaining shall be pumped to the sludge balancing tank.
The supernatant discharge pipe at the works inlet water tank shall terminate in a
nozzle to give an exit velocity of not less than 2.5 m/s to promote mixing of the water with
the raw water. The flow in the pipe shall be measured.
The wash water recovery pump house shall be arranged as a dry basement having a
common wall with the wash water recovery tank.
Separate pumps (one duty, one standby) shall be provided for supernatant and for
sludge. Pumps shall be located below the minimum sludge level in the wet wells to ensure
that they are fully primed and operate under positive suction head at all times. Drive from
the motor to pump shall be direct and motors shall be mounted at a suitable level to avoid
the risk of flooding.
Pumps shall be of the vertical spindle, volute type arranged to draw supernatant or
sludge directly from the tank. Pump volute casing shall have integral suction and delivery
branches
And shall be constructed to permit the removal of the rotating assembly without disturbing
the branch connections.
The suction connections form each compartment shall be interconnected so that the
duty and standby pumps can draw from either compartment. The pump delivery
connections shall be manifold to a single delivery main in each case.
Operation of the pumps shall be controlled by level probes in each compartment of
the used wash water recovery tank. Pumps shall be arranged for automatic changeover
from duty to standby on the failure of the duty pump.
The sludge pumps shall be installed to minimise ingress of sand originating from the
filters. Pump design and materials shall be selected to minimize damage to the pump due
to sand in the sludge.
The installation shall be provided with all pipe work, valves, fittings, level detectors and
penstocks. Sludge pipe work shall be arranged with easily detachable joints and isolating
valves to allow any blockages to be easily cleaned.
3.9.4 Tank cleaning
At least two hydrant points shall be provided near the used wash water recovery tank for
washing down purposes. The Contractor shall provide a high pressure hose of length 20 m
complete with hose reel, connector and nozzle to serve the two hydrant points.
3.10 Sludge treatment
3.10.1General
Sludge from the clarifiers and from the used wash water recovery tank shall be thickened
before disposal to the drying beds.
Sludge works shall include the following treatment stages and plant;
3.10.1.1 Sludge balance tanks.
3.10.1.2 Thickener feed pumps.
3.10.1.3 Sludge thickeners.
3.10.1.4 Thickened sludge tank.
3.10.1.5 Supernatant and thickened sludge discharge system.
3.10.1.6 Sludge drying beds.
If separate buildings are to be provided then the requirements shall be the same except
that the buildings shall be specifically for aluminium sulphate or hydrated lime.
A separate building shall be provided for disinfection system.
3.11.3Chemical building - storage and reception
Aluminium sulphate and lime will be manually unloaded from delivery vehicles on to
pallets for conveying to storage.
The basis for sizing storage space for bags of lime shall be that they will be stacked on
pallets to a height not more than 1.5 m. Aluminium sulphate shall be stored loose on the
floor in bunkers of width about 3 m to an average height of about 1 m. Transfer of bags and
blocks from delivery vehicle to storage area shall be by pallet truck. Movement of bags and
blocks in the storage area and to slurry/solution preparation area shall be by pallet truck.
The storage space for aluminium sulphate and lime shall be estimated on the basis of
average dose x maximum throughput x 30 days.
The aluminium sulphate storage area floor and the walls up to the storage height shall be
protected by a 5 mm thick trowel applied epoxy mortar.
3.11.4Chemical building -drainage
Slurry/solution preparation and stock tanks shall be located in the basement of the
chemical building. Floor drains shall be provided to collect overflow, spillage leakage and
drainage from the tanks and discharge by gravity to a chemical waste holding tank in the
basement of the chemical building. The drains shall be provided with open mesh flooring of
GRP construction.
The contents of the chemical waste holding tank shall be pumped to the clarifier sludge
balance tanks. There shall be two pumps arranged to operate on level control as duty and
duty „assist'. The pumps shall be arranged for control on level in the tank using a system of
level electrodes.
The basement floor, plinths, drains and waste holding tank and the walls up to 300 mm
shall be protected by a 5 mm thick trowel applied epoxy mortar.
3.11.5 Chemical handling
Equipment provided for handling chemicals shall include the following;
3.11.5.1 Hand powered hydraulic pallet trucks each with a lifting capacity of not less than
1500 kg and 10 Nos 4-way entry open deck reversible pallets of approximate size
1200 x 1200 mm for transfer of lime and aluminium sulphate.
3.11.5.2 2 - Way entry closed deck non-reversible type pallets for lime bag storage, each
of timber construction and approximate size 1200 x 1200mm.
3.11.6Chemical plant safety
The following safety equipment shall be provided to serve the chemical building:-
3.11.6.1 One safety shower (complete with eyebath)
3.11.6.2 20 Face masks each containing disposable dust masks for lime handling area.
3.11.6.3 Protective clothing as specified.
3.11.6.4 Goggles.
3.11.6.5 First aid boxes.
Each sample point shall be provided with means of extracting the sample at a rate not less
than 2.5 l/minute, a sample pump (where necessary) of the centrifugal type and pipeline of
nylon or flexible reinforced PVC construction for conveying the sample to the laboratory. All
sample lines shall be laid in trenches provided with covers and protected from the sun light.
Pumps shall where possible be located under cover in the nearest building. Where this is
not possible the pumps shall be located in a weather-proofed kiosk. A standby sample
pumps are not required. One spare pump common to all installed pumps shall be provided
and kept in store.
A sink shall be provided in the laboratory dedicated for receiving the samples. Each
sample tap shall be appropriately labeled.
Treated water quality at (e) above shall be continuously monitored for pH and turbidity. The
instruments shall be mounted on a backboard and shall be located in the laboratory. Each
Instrument shall be provided with local indicators. The Contractor is at liberty to derive the
sample to the instruments from the sample delivered to the laboratory, provided the sample
flow to the instruments is not influenced by the sample flow to the laboratory.
3.15 Treatment works water supply system
3.15.1General
A treated water supply shall be provided to serve the treatment works service water supply
requirements include the following:
3.15.1.1 Process water for the preparation of chemical solutions /slurries.
3.15.1.2 Motive water
3.15.1.3 Safety showers.
3.15.1.4 Water for flushing chemical and sludge pipelines.
3.15.1.5 Water for washing down purposes.
3.15.1.6 Domestic potable water for all buildings and the laboratory.
3.15.1.7 Irrigation water.
Sufficient pressure shall be maintained in the system at all times for all service conditions
by means of an elevated storage tank, but if necessary also by pumps or hydro pneumatic
booster system. The elevated storage tank specified for storage of filter wash water shall
be used to store the site service water requirements specified above.
3.15.2Elevated water storage tank
A fully covered storage tank of concrete construction shall be provided. The tank shall
have two interconnected compartments of equal capacity with isolating facilities to enable
one compartment to be taken out of service for cleaning and maintenance.
The capacity of the tank shall be adequate to provide water for two consecutive filter
washes, all continuous water requirements and the simultaneous use of one flushing point,
two washing down points and two safety showers.
The supply to each compartment shall be provided with an isolating valve. Each
compartment shall be provided with a level transmitter and level switches for monitoring /
measurement. The two compartments shall be provided with overflows and valved drains.
Each compartment shall be provided with separate outlets for filter washing and site water
supply.
The tank shall be located independently supported on RCC framed structure. The
elevation of tank shall be adequate for the requirements of backwashing.
Access shall be provided to the tank, around the tank in particular to the level monitoring
equipment, drains and isolating valves.
3.15.3Works water supply pumps
Two pumps of the horizontal radial flow type (one duty, one standby) shall be installed in
the treated water pump station, arranged to draw treated water from the treated water
reservoir.
The capacity of each pump shall be sized on the assumption that all the filters will be
washed consecutively spaced at 30 minutes apart and shall not be less than 5% of the
maximum works input.
The operation of the pumps shall be automatic, controlled on level using a system of level
probes in the storage tank.
The pumps shall be provided with all necessary suction and delivery pipe work, isolating
and non return valves, pressure gauges and instrumentation and control system.
3.15.4Works water supply boosting system
Water for flushing and hosing down duties shall if necessary be boosted by using either
booster pumps (one duty, one standby) or a hydro-pneumatic type boosting system.
The hydro-pneumatic system shall consist of two booster pumps (one duty, one standby)
drawing water from the works water supply system and operating in conjunction with a
precharged diaphragm pressured air/water vessel of suitable capability.
The boosting system shall be designed to satisfy conditions of maximum water demand as
would occur in the event of simultaneous flushing of all duty dosing/feeder/transfer pumps
and the operation of at least four hosing down points. The start/stop operation of the
booster pumps shall be on pressure in the air/water vessel, controlled by a pressure switch
in the supply water line.
The system shall be supplied as a package unit, complete with all necessary valves,
pressure gauges, control switches, starters, fuses and other associated electrical
equipment, all contained in a composite control panel; volt free contacts shall be provided
to indicate unit in operation and unit failure alarm on a remote panel.
The high pressure system if provided shall be separated from the low pressure process
water system.
3.15.5Loop system
The main supply system shall be in the form of a loop or loops, with arrangements made to
ensure continuity of supply in case of a break or interruption at any point. Pipe diameters
shall be amply sized to permit maximum flows under service conditions.
3.15.6Pipe work
All pipes shall be laid underground with 1 m minimum cover. Valves and air valves shall
be provided in drained chambers where required. Valve wash water branches with effluent
drain systems shall be provided at low points in the main system to permit sections of the
loop to be emptied when necessary.
Service connections shall be provided from the main system to all buildings and points of
individual demand or likely demand, and where required for washing down, e.g. chemical
building, clarifiers and filters, and for general purposes. Branch lines shall be connected to
points of demand by properly designed assemblies, with backflow and excess pressure
protection and by-pass draining. The number of washing-down points to serve a particular
area shall be determined on the basis of a maximum hose length of 20 m. Washing-down
points for each area shall be provided with the required number of hoses complete with
hose reels, connectors and nozzles all suitably mounted and shaded from sunlight.
3.16 Laboratory equipment
3.16.1General
The works shall be provided with a laboratory equipped for routine monitoring of
parameters necessary for process control including setting of chemical doses as follows:
3.16.1.1 pH value;
3.16.1.2 Turbidity(NTU);
3.16.1.3 Colour (true);
3.16.1.4 Total alkalinity
3.16.1.5 Aluminium concentration
3.16.1.6 Jar testing.
3.16.1.7 Specific gravity of chemical solutions
3.16.1.8 Bacteriological quality
3.16.2Laboratory equipment
The following equipment shall be provided:
• 1 No. Laboratory pH meter with combination electrode and temperature
compensation;
• 1 No. Spare combination electrode for the pH meter above;
• 1 No. Laboratory turbid meter to cover the range 0.1 to 1000 NTU including six
o sample cells and standards (Hach 2100N or equivalent);
• 1 No. Laboratory Spectrophotometer to cover wavelength range of at least 330
to 900 nm, with facility to accept cells from 10 to 100 mm. Single beam
instrument with microprocessor control. To include spare tungsten-halogen
lamp, cell holders as appropriate for 10 and 40 mm cells and 2 pairs of each of
10 mm and 40 mm cells. (Hach DR/4000 or similar)
• 1 No. Lovibond type Nessleriser with integral comparator including six sample
tubes (50 ml) and disc for colour (0 to 70 Haze units);
• 2 Nos. Comparator (Lovibond type) with twenty sample cells for analysis by
DPD method, discs for the range 0.1 to 1.0 mg/l and 0.1 to 4.0 mg/l residual
chlorine;
• 3 Nos.Hydrometers calibrated in specific gravity units with the range1.000 to
1.200 for measuring lime slurry of concentration at 50 g/l;
• 1 No conductivity meter complete with a graph of conductivity against
concentration at 30oC to measure saturated limewater concentration;
• 3 Nos Hydrometers calibrated in specific gravity units with the range1.000 to
1.400 for measuring saturated aluminum sulphate concentration;
• 3 Nos Hydrometers calibrated in specific gravity units with the range1.000 to
1.200 for measuring diluted aluminum sulphate of concentration 100 g/l;
• 1 No. Jar tests apparatus of the 4 jar unit type with adjustable speed control,
illumination and timer including 10 No. 1 litre jars;
• 1 No. Water deionization unit of capacity 10litres/hour;
• 1 No. Aspirator, heavy duty high density polyethylene (HDPE) construction, with
screw in tap; 50 litre capacity;
• 1 No. Aspirator, heavy duty HDPE construction, with screw in tap; 10 liter
capacity;
• 10 Nos. Plastic sample bottles with screw caps of capacity 500m;
• 10 Nos. Plastic sample bottles with screw caps of capacity 1000ml;
• 4 Nos. Plastic buckets of capacity 10litres;
• Beakers, Pyrex, low form with spout (10 Nos. capacity 100 ml., 5 Nos. capacity
250 ml. and 5 Nos. capacity 1000ml);
• 5 Nos. Wash bottles capacity 600ml;
• Filter Papers (Whatsmann) 15 cm diameter (10 Nos. boxes No. 1 Grade and 10
No. boxes No. 42Grade);
• 10 Nos. Funnels, plain glass, conical, 75 mm diameter;
• Beakers, low form with spout; (5 Nos. 100 ml; 5 No. 250 ml; 5 Nos. 600 ml; 4
Nos. 1000 ml; 2 Nos. 2000ml)
• Burette, schellbach, Class B, with interchangeable PTFE key (2 Nos. 50ml)
• Retort stand base, stainless steel, 210 x 130 x 8 mm; with threaded retort rod,
750 x 12.5 mm. (2 Nos. of each).
• Retort stand boss and clamp (5 Nos. of each)
• Measuring cylinders, polypropylene with spout (5 Nos. 25 ml., 5 Nos. 50 ml., 5
Nos. 100 ml. and 2 Nos. 1000ml.);
• Volumetric flasks BS 1792 Class B type, with poly stop (5 Nos. 100 ml., 5 Nos.
250 ml., 5 Nos. 500 ml. and 5 Nos. 1000ml.);
• Erlenmeyer flask, DIN 12387 (5 Nos. 200ml)
• Pipettes, straight sided BS 700, Class B, graduated to deliver fast flow (10 Nos..
1 ml., 10 Nos.. 2 ml., 10 Nos. 5 ml. and 10 Nos. 10ml.);
• Pipettes, bulb, Class B, BS 1583 (2 Nos. 10 ml; 2 Nos. 25ml.)
• 2 Nos. pipette fillers;
• Nessler tubes (20 pairs 50 ml. and 5 pairs 100ml.);
• Racks for Nessler tubes (5 Nos. 50 ml. and 2 Nos. 100ml.);
• Bacteriological test equipment;
Chemical Reagents
• Aluminum standard solution; 1000 mg/l 2 x 500ml
• Ammonia 35% solution 4 x 1000ml
• DPD tablets No 1 (comparator) 2000No.
• DPD tablets No.3 (comparator) 2000No.
• Hexamine 4 x 500g
• Hydrochloric acid (2N) 6 x 1000ml
• Hydroxyl ammonium chloride 2 x 500g
• Indicator solution, BDH 4.5 2 x 500ml
• 1, 10 Phenanthroline hydrochloride 6 x 5g
• Pyrocatechol violet 2 x 5g
• Sulphuric acid, 0.02 N (0.01 M), CONVOL 3 carton x 6ampoules
The electrical plant, cabling and earthing installations shall comply with Standard
Specifications and the following clauses herein. Where the Drawings, Standard
Specification and Particular Specification differ, the latter shall take precedence.
4.2 General electrical requirements
4.2.1 Design considerations
The Contractor shall design the electrical installation taking into consideration the following;
4.2.1.1 Location and maximum power demand of all loads;
4.2.1.2 Availability and reliability of supply;
4.2.1.3 Prospective short-circuit current;
4.2.1.4 Environment in which electrical plant is located;
4.2.1.5 Ambient temperature, humidity and its effect on the rating of switchgear,
transformers, cables and generating plant;
4.2.1.6 Method of cable installation;
4.2.1.7 Cable transient and steady state volt-drop on motor starting;
4.2.1.8 Transient volt-drop on motor starting at point of supply;
4.2.1.9 Electrical protection discrimination;
4.2.1.10 Ground earth resistivity;
4.2.1.11 Overall system power factor shall be minimum0.95;
4.2.1.12 Total harmonic distortion;
4.2.1.13 Effective operation, control and monitoring of plants;
4.2.1.14 Easiness and effectiveness of maintenance.
4.2.2 Environmental conditions
All Plant shall be designed and manufactured for continuous operation under the specified
climatic and environmental conditions as detailed elsewhere within the Specification.
4.2.3 Estimated power requirements
The Tenderer shall submit estimated installed and running loads and distribution
schematic diagram with rating of major equipment for each site and calculate the estimated
available load required as part of his Tender submission.
Load computations for sizing all equipment/cables shall consider present load, future
expansion and 20% design margin on the total value.
The Contractor shall update the preliminary load schedule during the detailed design stage,
finalize plant ratings and submit all calculations to the Engineer for approval.
4.2.4 Electrical distribution system
The electrical distribution systems shall be designed to provide;
4.2.4.1 Redundant transformer shall be provided for supplying switchboards and MCCs
for each pumping station. Each transformer of a transformer pair shall have the
capacity to support the maximum connected duty load. The connected loads shall
be shared evenly by the transformer pair during normal operation.
4.2.4.2 Switchboards and MCCs shall be provided with a bus coupler to enable change
over in case any one of the transformer failed.
4.2.4.3 Operational flexibility.
4.2.4.4 Ease of maintenance with minimum operational disruption to the operation of the
works.
The Contractor shall determine the equipment quantity, equipment rating, equipment
location, and suitable distribution network and protection scheme.
The configuration of the main distribution system and sub distribution system shall be
determined by the Contractor.
4.2.5 Electricity supply
`The high voltage electricity supply to each pumping station, booster station and water
treatment works shall be drawn by dedicated feeders from local Electricity Boards via 33/11
kV overhead lines as detailed herein.
The Electricity Board contract interface shall be the 33/11kV metering panels incoming
cable boxes or termination chambers at the switchgear of Electricity Board. The cables
connecting to the switchgear of Electricity Board from the incomer switchgear of the
Electrical Works of this Contract shall be provided by the Contractor.
All liaison works for the procurement of the Electricity Board supplies shall be included
within the Contract Price.
4.2.6 Electricity Board supply system data
a) Voltage: 33/11/6.6kV
b) Frequency: 50Hz
c) Voltage tolerance: plus or minus10%
d) Frequency tolerance: plus or minus5%
e) Neutral earthing: direct
f) Three phase maximum fault level: Based on Actual tapping conditions.
Liaison with the Electricity Board shall be by the Contractor through the Engineer.
4.2.8 Liaison with Electrical Inspectorate
The Contractor shall be responsible for all the works required for obtaining all design
approvals necessary from the local Electrical Inspectorates / Chief Officer as well as
obtaining a sanction for energizing the new supplies. All liaison with the Electrical
Inspectorate shall be by the Contractor through the Engineer.
4.2.9 Electricity Board Metering Requirements
The Contractor shall be responsible for coordinating all designs with Electricity Board.
The Contractor shall provide metering CTs, electricity maximum demand watt meter and
testing terminals in accordance with the requirements of Electricity Board as detailed
below. Meter shall conform to standards IEC 1107, IEC 1000-4, IEC 255, IEC 60687 in
concurrence with IS 13779 and IS 14697. All metering equipment including VTs and CTs
shall be housed in HV metering panels which shall be fully sealed and self-contained to
ensure Electricity Board metering seals can be installed. Prior to procurement of any
equipment, the Contractor shall submit full technical details of the proposed plant to
Electricity Board.
(a) Metering Voltage Transformer (VTs)
VTs shall be provided for the main switchboard. Tappings from each VT compartment shall
be used to provide a supply to the separate Electricity Board metering compartment.
(b) Metering Current Transformer (CTs)
Separate metering summation CTs shall be provided. The CTs shall have an accuracy
class of better than 0.5. In any case total metering error shall be less than 1%.
(c) Electricity Maximum Demand Wattmeter
The Contractor shall provide electricity maximum demand watt meter located within the
metering panel. The meter shall be programmed in accordance with Electricity Board
requirements. Prior to procurement of the meter the Contractor shall confirm latest
requirements of Electricity Board.
4.2.10 Utilisation voltages
(a) High voltage 33kV, 11kV, 6.6kV or 3.3kV three phase to suit plant
rating. 33kV incomer for capacity demand above
5MVA in accordance with the Distribution Code of
Electricity Board.
(b) Low voltage 415V three phase
(c) Control Low Voltage - AC, 415, 3phase, 4 wires, 50Hz.
Lighting & space heating - AC, 230V, 3phase, 4
wires, 50Hz.
AC Control - 240V single phase for anti-
condensation heater, instrumentation and LV motor
starter control, motor starter control and indication
lamps. .
UPS Supply - AC, 110V(filed Instruments and PLC
system)
DC Supply -110V for high voltage switchboard
control, protection, circuit breaker motor charging
(b) Transient
During motor starting periods the following criteria shall apply:-
- Under minimum supply voltage conditions specified earlier, the voltage at the
motor terminals shall not be lower than 85% of the motor rated voltage;
- The voltage drop at the point of supply shall not be greater than 10% of the
rated voltage.
Motors provided with variable speed drive or soft starter shall be provided with the following
additional facilities:
- Drive Fault Indicator;
- Motor Speed Indicator;
- Variable Speed Controller (door-mounted).
- Cooling facility shall be provided for dissipating heat generated by the variable
speed drive or soft starter in accordance with the manufacturer’s
recommendations.
Main transformers shall be provided with an on-load tap changing (OLTC) facility as
shown on single line diagram. All other auxiliary transformers shall be provided with offload
tap changing facilities. On load tap changer panels shall provide automatic adjustment of
voltage level with facility of manual operation.
The transformers shall be fitted with a removable link to connect the low voltage
winding neutral point to earth. The link shall be accommodated in the low voltage cable box
and shall be fitted with a label inscribed LV WINDING NEUTRAL EARTH LINK.
Transformers using open type bushings shall not be accepted.
Each transformer shall be provided with an emergency trip push button in the secondary
voltage switch room or as agreed with the Engineer.
Remote control unit for OLTC
The OLTC control equipment shall be housed in an indoor sheet steel cubicle located in the
adjacent HV switch room. It shall conform to degree of enclosure protection IP 54 or better
and shall comprise the following but not be limited to:
• Control switch: Raise / off / Lower (spring return to normal type)/automatic or
independent pushbuttons.
• Tap position indicator.
• Facia type alarm annunciators with “accept”, “lamp test” facilities and hooter /
buzzer for alarms.
• Necessary auxiliary relays.
• Lamp indications for tap change in progress, lower limit reached, upper limit
reached etc.
• 240 V rated panel space heater with thermostat.
• Fluorescent type interior lighting fixture with lamp and door switch.
• Voltage sensing and voltage regulating devices
• Line drop compensator with adjustable R and X elements.
• Timer 5-25 seconds for delaying the operation of the tap changer in the first step
for every tap change operation.
• Adjustable dead band for voltage variation.
• Volt free contacts for alarms for a. c. supply failure drive motor auto tripped and
other protective purpose considered essential by the Contractor shall be wired
to a common terminal rail. The Contractor shall cable the outputs to the ICA
compartment of the adjacent switchboard/motor control centre.
Transformer Compounds
The transformers shall be housed in a compound surrounded by 2.4 m high chain
link fencing or similar approved. Each transformer shall be provided with a double leaf gate
not less than 2.4 m wide. The transformers shall be shaded from direct sunlight.
A minimum clearance of 1500 mm shall be provided to all sides of the transformer.
Transformers shall stand on reinforced concrete plinths surrounded by an oil retaining
sump. The sump shall be filled with suitable single size (nominally 40 mm) rounded stones.
The capacity of the sump when filled with stones shall be suitable to hold the total oil
content of the transformer plus 15%. The sumps shall be connected to a separate chamber
to permit the removal of standing water and oil.
Trenches and ducts entering the oil-retention area shall be sealed after the cable
installation.
The compound shall be provided with a name plate identifying the transformer number
and rating. The name plate shall be plastic laminate or other material approved by the
Engineer
And the size of characters and numerals shall be not less than 50 mm. The name plate
shall be fixed to the access gate using stainless steel fixings.
Each transformer compound shall be provided with adequate portable firefighting
equipment accordingly to Statutory Requirements.
4.5 415V switchboard and motor control centre
The Contractor shall design the low voltage power distribution to meet the requirements
of the proposed plant. The Contractor shall generally provide motor control centres at each
process area including the chemical house, clarifier works, individual pumping station, the
filter building, the sludge treatment plant and the chlorine plant. The motor control centre’s
shall be supplied from the main works switchboard which shall then feed the sub
distribution switchboards/ motor control centre’s. The Contractors design should not derive
feeders from one sub-distribution switchboard to another sub-distribution switchboard.
The 415V switchboard/motor control centre’s shall be of Form 4 construction, floor
mounting metal-clad cubicle type equipped with ACBs, MCCBs, fuse-switches and motor
starters as appropriate. Cable entry may be top or bottom with panel access to the front to
suit the requirements of the site layout drawings.
Cable openings in the base of switchboards and motor control centres shall be fitted with
plates to prevent the entry of vermin.
Provision shall be made on switchboards and motor control centres for supplying building
and external electrical & mechanical services.
Supplies to process plant and instrumentation shall be derived from a separate process/
instrumentation services distribution board and not derived from building services
distribution boards.
Switchboards and motor control centres shall be extensible to cater for the future designed
development. The Contractor shall take this requirement into account when designing
switch and control rooms.
Rubber insulation floor mat of 9mm thickness shall be provided at the front of each
switchboard and motor control centre. The mat shall extend over the full depth of
switchboards and motor control centre plus 800 mm minimum at each end.
Test plugs and tools shall be provided to facilitate switchboard testing.
(a) Technical requirements
Motors provided with variable speed drive units shall be provided with the following
additional facilities:
- Drive Fault Indicator;
- Motor Speed Indicator;
- Variable Speed Controller (door-mounted).
Cooling facility shall be provided for dissipating heat generated by the variable speed drive
or soft starter in accordance with the manufacturer’s recommendations.
(d) Control and operation
Control and operational requirements for motor starters shall be as specified herein. All
control and instrumentation equipment shall be located within the ICA section of each
switchboard/motor control centre.
(e) Interlocking
The main switchboards/motor control centres with incomers derived from two
transformers shall have ACBs for the two incomers and bus-coupler. The switchboard shall
be provided with an electrical interlocking scheme to allow only two out of three circuit
breakers to be closed at any one time. The normal operation of the switchboard will have
the two incomers closed and the bus-coupler open, with the load equally distributed
between the two incomers. On power failure of one incomer, the bus-coupler will be closed
automatically and the complete plant operating from one supply as shown in SLD.
Main switchboards/motor control centers with incomers derived from a generator and
transformer shall be provided with two incomers electrically interlocked to prevent the
paralleling of the incoming supplies or an automatic (with manual over-ride) changeover
switch.
(f) Feeder units
Feeder units shall be provided as required on each switchboard and motor control centre.
(g) Lamp test
Each switchboard and motor control centre compartment shall be provided with a lamp test
facility when fitted with indicating lamps.
(h) Anti condensation heaters
Anti condensation heaters shall be provided for each panel.
(i) Auxiliary contacts
Voltage-free changeover type contacts shall be provided for remote status and alarm
indications as follows:-
- Each incomer(mains/generator)
o Circuit-breaker/switch open;
o Circuit-breaker/switch closed;
o Circuit-breaker tripped on fault;
o Supply healthy;
- Each bus-coupler
o Circuit-breaker/switch open;
o Circuit-breaker/switch closed;
- Each motor starter
o Motor available
o Motor running
o Motor fault(common)
o Individual fault signal
The contacts shall be wired to a common marshalling terminal in the associated ICA
section of the switchboard/motor control centre.
(j) Socket outlet
A 240V 5A single phase socket outlet shall be provided within the ICA compartment of
each switchboard and motor control centre.
(k) Location
The switchboards and motor control centres shall be located as per approved Drawings.
(l) Switch room design considerations
Switch room floor flatness shall be finished to the requirements of switchboard
manufacturer. Switchboards and motor control centres shall be extensible to cater for the
future designed development. The Contractor shall take this requirement into account when
designing switch and control rooms. Front clearance shall be not less than 1500mm.
For switchboards and motor control centres designed for rear access, a clear space of
not less than 800 mm shall be provided at the rear of the panel. For front access
switchboards a nominal 150 mm clear space shall be provided at the rear of the panel.
Where floor trenches for cabling is provided it shall extend over the full depth of
switchboards and motor control centres plus 800mm minimum at each end. Trench depth
shall be not less than 1000 mm. For switchboards and motor control centres designed for
front cable access the trench shall extend not less than 600mm from the front face. A
galvanized steel supporting framework shall be provided for switchboards and motor
control centres.
Galvanised steel or aluminium chequer plate cable trench covers shall be provided.
Doorways shall be dimensioned to permit the entry of the largest section of switchboards
and motor control centres in its upright position.
An identification label shall be fitted to the outside of the building adjacent to the access
door. The label shall identify voltage and substation location. The label material shall be
plastic laminate or other material approved by the Engineer and the size of characters and
numerals shall be not less than 50mm. The label description shall be subject to the
approval of the Engineer. The label shall be fixed to the building using non-ferrous screws.
Mechanical ventilation shall be provided for the switch room. Ventilation fan sizing
calculation taking into account of equipment heat dissipation rate shall be provided for
Engineer’s approval. The minimum air change rate for switch room shall be 10 air changes
per hour.
4.6 Electrical ancillary equipment
4.6.1 Power factor correction
The power factor at each load centre shall be corrected to no less than 0.95 lagging. The
correction may be by means of capacitors connected to individual items of plant or by
automatically controlled multistage capacitors connected to each busbar section.
For multistage power factor correction, capacitor ratings shall be selected to ensure that
motors are not subjected to leading power factor conditions or abnormal operating
conditions due to the effect of self-excitation when switched off.
Multistage capacitors shall be controlled by contactors via an automatic capacitor
controller with target power factor setting adjustment and manual override facilities. The
contactors shall be de-rated to compensate for zero power factor switching duty, the
permitted capacitor positive tolerance and the presence of harmonic currents.
Capacitors shall incorporate a discharge circuit and shall not contain polychlorinated
biphenols.
Each of the HV main pump motors shall be provided with an individual power factor
correction unit to the highest value obtainable without the self-excitation of the motor.
Power factor correction units shall comprise one or more three phase capacitor banks and
a set of three fuses, housed in an enclosure and connected through fuse gear and an
isolating link by cable to the motor starter such that it is permanently connected across the
motor windings. A manually operated mechanical key interlock system shall be provided to
ensure that the enclosure cannot be opened until the associated motor starter breaker is
open and in the "earthed “position.
Calculations corroborating capacitor kVAr ratings shall be submitted to the Engineer for
approval.
4.6.2 Switchgear battery units
(a) 110V Battery and battery charger
The Contractor shall provide battery charger units with adequately sized batteries and
battery chargers for the HV switchboard and motor control centre. Each battery supply unit
shall incorporate two float and boost chargers with auto changeover facility in case of
failure of one.
The batteries shall have adequate capacity to operate HV switchboard control and relay
system, monitoring devices, circuit breaker charging, OLTC etc. The sizing calculations
shall be submitted to the Engineer for approval.
(b) Battery and battery charger for 415Vswitchboard
Battery units of the appropriate voltage and capacity shall be provided for 415V
switchboard circuit-breaker tripping, control, indication and alarm supplies.
Battery capacity calculations shall be submitted to the Engineer for approval.
4.6.3 Uninterruptible power supplies
An uninterruptible power supply (UPS) unit or units shall be provided where it is necessary
to maintain a no-break supply to instrumentation, control, PLCs, servers, computer
workstations, telecommunication systems, network systems and alarm systems as detailed
in the ICA section of the site works specifications.
The UPS system with fully charged batteries shall, on loss of mains supply, be capable of
supplying the connected loads for a minimum period of 2 hour.
Battery capacity calculations shall be submitted to the Engineer for approval.
4.6.4 Emergency stop push-buttons
An emergency stop push-button shall be installed adjacent to all motors.
4.6.5 Local Control Units (LCU)
Each motor shall be capable of being manually operated from a local operating position.
Where motor starters are provided at remote locations, the Contractor shall provide a local
control unit (LCU) in a safe and accessible operating position adjacent to the motor. Each
LCU shall be of robust construction suitable for the environmental conditions. The LCU
shall be provided with a start/stop or open/close pushbutton.
Local control units installed externally shall be protected from the sun with sun covers and
constructed with an IP rating of IP65
The Contractor shall submit drawings identifying the locations of the LCUs for the
Engineer’s approval.
4.7 Cabling
(a) General
The Contractor shall provide a complete cabling installation comprising power, control,
instrumentation, communications and telephone cables and all accessories including cable
glands, terminations, cable markers, support systems, clips, fittings and fixtures to:-
- Interconnect all Plant provided under the Contract;
- Interconnect Plant provided under the Contract to the Electricity Board point of
supply;
- Interconnect ICA signals to the regional telemetry outstation; and
- Interconnect existing plant with the Plant provided under the Contract.
All calculations to corroborate current carrying capacity and compliance with the volt-drop
criteria specified herein shall be submitted to the Engineer for approval.
The power, control and instrumentation cabling shall interconnect the entire Plant including
but not limited to:
- Valves actuators, pump sets ,etc;
- Switchgear and distribution boards;
- Motor control centers;
- Local control panels, PLCs, intelligent outstations;
- Regional telemetry outstation;
- Local control units; and
- Measuring instruments and sensors.
This volume contains the Particular Specification for the civil engineering works. The
Particular Specification contains a description of the civil works to be designed and
constructed including any applicable design criteria that have to be met. The general civil
Specification is contained separately, and includes the standards to be met in the design
and construction of the works. Civil works shall comply with all other relevant provisions
elsewhere in the Specification.
5.1 Scope
5.1.1 This section describes the civil works to be designed and constructed under
the Contract. This includes intake well / channel, connecting pipes, intake
structure cum pumping station, WTP, intermediate booster sumps and pumping
stations, MBRs / ZBTs etc.
5.1.2 The principal units include: intake well / channel, intake structure cum pumping
station, intermediate booster sumps and pumping stations, MBRs / ZBTs,
treatment plant units / buildings and other works necessary for the completion
of the Contract. The civil works include associated structures and buildings,
water supply system, overflows, drainage, roads, compound wall, staff housing,
plant compound walls, landscaping, pipe bridge and other associated works
necessary for the Contract.
5.1.3 Mechanical plants shall be provided as per the Mechanical Specification of the
Particular Specification. Electrical plants shall be provided as per the Electrical
Specification of the Particular Specification. Lighting and small power shall be
provided as per the Building Services Specification of the Particular
Specification. Instrumentation, Control and Automation plants shall be provided
as per the ICA Specification of the Particular Specification.
5.1.4 The Contractor shall prepare and submit all the necessary designs and
drawings for each of the works. Civil works shall comply with all the basic
criteria given in this Particular Specifications and the Standard Specification as
given elsewhere.
5.1.5 The Contractor shall provide all the civil works necessary for the Works under
the Contract notwithstanding any omission in the Particular Specification.
5.1.6 The civil works shall be sufficient to provide for all the requirements of the
plant specifications.
All structural design shall be conducted by the Contractor and all design calculation shall be
submitted to the Engineer for approval. The structural design shall confirm to all relevant
Indian Standard. The grade of concrete for all water retaining structure shall beM30.
5.2.1 The structures shall be designed to take account of all possible load
combinations. Part of the structures that may be submerged shall be designed
to withstand the most onerous combination of uplift, differential head across the
structure, wave action, wind and seismic forces. Design shall include an
analysis of the vibration cause by the mechanical plant and appropriate
mitigation.
Supports shall be well founded on solid strata using piles and anchors as
necessary. Principal load bearing members shall be of reinforced concrete. All
engineering metalwork for ladders, handrails and platforms shall be of
aluminium alloy. Water retaining structures shall be reinforced concrete with
sloped or screeded floors at not less than 0.5% to drainage channels and
sumps. As far as possible drainage shall be by gravity, otherwise sumps for
submersible pumps shall be provided.
Other structures may have reinforced concrete frames and brick infill for non-
load bearing walls.
All roofs shall be flat with a minimum fall of 1 in 250. On no account shall water
retaining structures be formed of concrete with a cement render (plaster) finish.
5.2.2 The plan area and shape of pump well shall be in accordance with approved
codes of practice. The Contractor shall design the wells in collaboration with the
pump supplier to ensure that the flow conditions approaching the pumps under
all operating conditions are smooth and uniform and that the angle of the swirl
entering any pump inlet does not exceed 5 degrees or such value as is deemed
acceptable by the pump supplier in order that the guarantees he has provided
with respect to efficiency and maintenance are met. In addition the sump design
must ensure that no air, entrained by flow plunging into the sump or by other
features of the proposed design, is carried through to pump inlets. The
Contractor shall demonstrate the appropriateness of the design to meet these
requirements using physical modeling or other means that may be agreed with
the Engineer.
5.2.3 The pump well shall have a cover slab and safe, easy access via a manhole
cover and staged ladders. The Contractor shall provide a cradle for lowering
operatives into the well via this manhole. The cradle shall be sized to fit through
the manhole opening and carry two operatives in safety to the bottom of the well.
The cradle shall be stable even when unevenly loaded, have safety rails and
safe, secure means of access. The cradle shall be capable of carrying at least
300 kg and shall bear a plate stating the safe working load.
5.2.4 The Contractor shall provide skips and other accessories, as mentioned for silt
removal. The system shall be appropriate for handling manually and with the
overhead crane. The skips shall be designed to be moved, lowered and raised
using the overhead crane.
5.2.5 Manhole covers shall be raised at least 50 mm above floor level. The raised area
shall be profiled smoothly down to the floor to avoid making trip hazards.
5.2.6 The plan area and shape of the motor hall should generally follow standards.
Enough space shall be provided between adjacent motors and between a motor
and the wall such that the maintenance staff can have sufficient room to perform
the dismantling and subsequent reassembly work of the pumps, motors, valves,
pipe work etc. Sufficient space shall be provided to enable the dismantled
pumps, motors, valves, pipe work etc to be moved into the loading bay using the
overhead travelling crane. The structure shall have enough head clearance to
accommodate an overhead travelling crane that can lift the largest piece of plant
with at least 0.5 m clearance from any obstruction. The motor hall shall be a
clean, well lit, well ventilated, rainproof structure with adequate access to all
items of the Plant. Raised platform of removable floorings shall be provided
above the pipe work to provide clear, easy access to valve actuators, penstock
actuators and pump motors, should the operating actuators/hand wheels of
these valves, penstocks and any parts of the motors that required operation and
maintenance are not conveniently accessible with operators standing at the floor
of the motor hall. These raised platforms shall be provided with access ladders,
hand railings and the like. The structure shall be provided with external
navigation lights.
5.2.7 The building shall incorporate a loading bay in the motor hall. The overhead
travelling crane shall be designed to travel into the loading bay and place the
largest piece of plant directly onto the back of a suitable vehicle. The loading bay
shall have a roller shutter door and be sized to accommodate a suitable
vehiclethatwouldbeusedtotransportthelargestpieceofPlant, withatleast 1.0m
clearance on either side and to the end of the roller shutter when it is completely
opened.
5.2.8 A high-voltage switchgear room shall be provided near intake well, large enough
to house the switchgear and allow easy access for removal and maintenance.
The general arrangement of the room shall make provision for incoming and
outgoing power and control cabling, by either placing the switchgear on raised
flooring or providing cable trenches.
The room shall have adequate provision of space for removal of switchgear. It
shall be possible to remove any panel from the room or install additional panel
with the same size as the installed panels into the room through the door of the
room, without the need to temporarily shifting the installed panels.
5.2.9 A separate low voltage switchgear room shall be provided for the equipment
other than the pump motors, including small power, lighting, ventilation etc. The
room shall have enough space to house the switchgear and allow easy access
for maintenance and removal of the panels, in a way same as that mentioned
above.
5.2.10 The structure shall be provided with adequate facilities for rainwater drainage
and wastewater removal. The structure shall have a flat roof falling to gutters that
shall empty the collected rainwater to the reservoir via downpipes. Wastewater
shall be connected to a septic tank inside the Plant area.
5.2.11 An outdoor intake electrical sub-station and a metering house shall be provided
for the HV metering panels and HV switchgear of KPTCL. Outdoor transformer
bays shall be provided for transformers, ancillary plants and associated control
systems. Those structures that are to be used by the KPTCL and the cable
ducts/draw pits/cable trenches for KPTCL's incoming cable shall be constructed
to conform to their requirement. Individual transformer bays and HV switch
rooms shall comply with Electrical Specification.
5.2.12 Staff housing shall be provided for the operators, helpers and watchers as
specified.
5.2.13 The works and the outdoor electrical sub-station shall be fenced off from the
exterior by compound walling of, not less than, 2 m height. A double leaf access
door, the main gate, for vehicles and a single leaf access door, the side gate, for
operation personnel shall be provided at the compound wall. The main gate and
the side gate shall be positioned adjacently. The distance in between the gate
and the roller shutter of the pumping station shall be enough for the vehicle to
transport the largest piece of the Plant to turn freely after it enters the Plant with
the main gate closed behind.
5.2.15 Landscaping of the final site shall be provided including tilling and seeding soil
and planting suitable species of trees and shrubs as agreed with the Engineer.
All grassed areas shall be irrigated.
5.2.16 All land around the compound walling disturbed by the works shall be reinstated
upon completion of the civil works by tilling the topsoil and seeding with grass
mix as per the Specification.
5.3.1 The civil works for the transmission mains shall include provision, laying, jointing,
backfilling and reinstatement.
5.3.3 The pipeline route and exact locations of fittings and chambers shall be agreed
on site between the Contractor and the Engineer following a preliminary survey
to be done by the Contractor. The Contractor shall provide the design for all pipe
supports, anchor blocks, pipe bridges etc. The main shall have a washouts at the
lowest points.
5.3.4 The pipelines diameter and wall thickness shall be in accordance with the
Specifications.
5.3.6 The Contractor has to conduct all trench excavation and all other necessary
work, as specified in Specification.
5.4.1 The civil works for the treatment works shall include all earthworks to form the
site area to appropriate levels, and all the structures necessary. All structures
shall be reinforced concrete unless otherwise stated.
5.4.2 The Contractor shall provide all the earthworks and any associated structures
such as retaining walls needed to establish the formation levels.
5.4.3 Structures for the treatment processes shall be designed to meet the
requirements given in the water treatment works specification. Water retaining
structures shall be reinforced concrete with sloped or screeded floors at not less
than 0.5% to drainage channels and sumps.
5.4.4 Water retaining structures shall be designed to resist water loading due to
external water level at ground level. Uplift forces on reservoirs, tanks and pipes
shall be calculated assuming that they are empty and the factor of safety against
flotation in this condition shall be not less than1.1.
5.4.5 All open tanks shall be provided with handrail protected access walkways all
around at the top level of the tank walls. Ladders shall only be provided within
chambers. Steps shall be provided to all external access platforms unless it can
be demonstrated that steps are impracticable and ladders are absolutely the only
alternative. All engineering metalwork for ladders, handrails and platforms shall
be of aluminium alloy.
5.4.6 All covered tanks shall be provided with approved ventilation cowls. All chambers
shall be provided with manholes and approved hinged covers. Manhole
openings shall be 750 x 750 mm minimum. Chambers and tanks shall be
provided with aluminium ladders. Ladders over 3 m long shall have cages.
5.4.7 Where a standard Drawing is provided for an item, such as handrails, ladders
etc, that item shall comply with that standard detail unless the Contractor
submits an alternative detail that is subsequently approved by the Engineer.
5.4.8 All pipe work shall be laid in trenches complying with the standard details
provided in the Drawings. All valves on buried pipelines shall be in chambers
unless otherwise stated. All stop valves shall be butterfly valves unless otherwise
stated.
5.4.9 The inlet work design shall suit the requirement of Water Treatment Plant
Specification of the Particular Specification. It shall, as a minimum, consists of a
Cascade Aerator, Raw Water Channel, Parshall flume channel for measuring the
inlet flow to the treatment plant, mixing chambers and the flow diversion
chambers to the clarifiers.
5.4.10 The flow division chamber shall have weirs dividing the flow. The weirs shall
discharge into separate chambers feeding separate clarifiers.
5.4.12 Rapid gravity filters shall be provided. The filters shall be of the duplex type
comprising two equal size beds. Space shall be left for adding additional units in
the future to meet ultimate year requirement. The filters shall have a covered
central gallery accommodating filter wash consoles, pipe work and filtered water
channel. The filter walls shall be tiled, tiles to be approved by the Engineer.
5.4.13 A two storey filter building shall be provided to house air scour blowers, air
compressors, electrical switchgear, store room and separate ladies. And men’s
toilet / washrooms at ground level.
The filter building shall be provided with a covered area for the transformers
adjacent to the electrical switchgear rooms. The air blower and compressor
room shall be adequately soundproofed. The building shall have a flat roof
accommodating an elevated water storage tank. The upper floor shall have a
floor area sufficient to accommodate office and laboratory. The layout shall be
as approved by the Engineer. The Contractor shall provide all the necessary
furniture, which shall include but not be limited to:
5.4.14 Offices shall have at least one window on each exterior wall, of individual area
not less than 2 m2. Rooms shall be painted to a colour scheme approved by the
Engineer and windows shall have curtains to match the colour scheme. Floors of
rooms and corridors shall be tiled with polished stone tiles, type and colour to be
approved by the Engineer. A first aid station shall be placed in the mess room
with posters giving basic first aid guidance.
5.4.15 A works water supply pump house shall be provided for works water supply
pumps located adjacent to the filters and contact tank. The motors and
switchgear shall be at a suitable level to avoid flooding.
5.4.16 A contact tank / treated water storage tank shall be provided adjacent to the
filters. The design of the same shall comply with stated standards. The tank shall
be divided in half lengthwise by a central wall.
5.4.17 Flow shall discharge to the treated water reservoir via weirs with adjustable weir
plates. The roofs shall be coated internally with approved epoxy paint. The roof
surface shall have a waterproof membrane and shall be covered with a 150 mm
layer of 10 mm clean gravel chippings.
5.4.18 A sludge balancing tank shall be provided to receive sludge from the clarifiers.
The design of the sludge balancing tank shall comply relevant Clause. One tank
with two equal compartments of combined capacity adequate to balance sludge
discharges shall be provided.
5.4.19 A sludge pump house shall be provided for sludge thickener feed pumps. The
pump house shall have a common wall to the sludge balancing tank. Motors and
switchgear shall be at a suitable level to avoid flooding. The design of the sludge
pump house shall comply with relevant Clause.
5.4.20 Circular sludge thickening tanks shall be provided. Each shall have an inwardly
sloping floor to a central well, and a peripheral launder. Tanks shall be provided
with rotating mechanical scrapers. The design of the sludge thickening tanks
shall comply with relevant Clause.
5.4.21 A rectangular tank shall be provided for used filter wash water. The design of the
used filter wash water tank shall comply with the requirements entered in
relevant Clause. It shall have two interconnected compartments, being isolated
by a penstock with low level aperture no less than 0.3 m x 0.3 m with isolating
gate and external operating mechanism. The capacity of each compartment of
the tank shall be adequate to store as a minimum, the wash water from two
consecutive filter washes.
5.4.23 The elevated water storage tank shall be provided for filter backwash and service
water. It shall be fully covered and have two interconnected compartments of
equal capacity with isolating facilities to enable one compartment to be taken out
of service for cleaning and maintenance. Each compartment shall have a high
level inlet and low level outlet. The tank shall have an overflow.
The roofs shall be coated internally with approved epoxy paint. Access to the
inside shall be provided via a manhole with inclined aluminium ladder 2.4 m
long, to a reinforced concrete platform with aluminium hand railing. Reinforced
concrete steps shall be provided down to the floor. Platform and steps shall
have approved non-slip surface finishes.
5.4.24 Number of sludge drying beds shall be provided as per design and shall be used
in rotation each being in various stages of filling, dewatering and emptying. The
design of the drying beds shall comply with relevant Clause.
5.4.25 The sludge drying beds shall be constructed to the levels as per approved
design and drawings.
5.4.26 Site drainage, drainage from water retaining structures, overflows, basements
and under drains shall be discharged to the point specified outside the site
boundaries. A septic tank shall be provided for domestic wastewater.
5.4.27 The site shall have access roads of minimum width as specified to connect all
the units. Provision shall be made for safe turning for delivery vehicles. Road
areas shall contain space for manoeuvring large vehicles. Covered parking shall
be provided adjacent to buildings for vehicles. Roads and parking areas shall be
surfaced with bituminous macadam.
5.4.28 Under drains shall be provided below reservoir floors and other water retaining
structures as necessary. Outlets from under drains shall be designed so that
leakage can be easily identified.
Flows from under drains shall be collected in sumps and pumped to drainage
or overflow system.
5.4.29 Buildings shall have all necessary provisions for services such as trenches,
ducts, cable trays, racks etc. External service trenches shall be provided for
cables and chemical dosing and sampling lines, which shall be neatly arranged
on racks to be visible and easily accessible. Where several services run in
parallel they shall normally be grouped in a common trench with provision for
man access, except that chemical lines shall not be run in the same trench as
cables. Trenches in roads shall be provided with continuous removable covers
designed to withstand vehicle loading. Trenches shall be clearly identifiable and
shall not be covered with road surfacing.
5.4.30 The Contractor shall provide permanent signboards for all the works including
treatment works. The signboards shall bear text and logos as defined by the
Engineer. The signboard shall typically be 2.5m wide by 2m deep. The sign shall
be corrosion resistant, weatherproof and mounted on painted steel posts set in
concrete. The design shall be approved by the Engineer.
5.4.31 An outdoor electrical sub-station and a metering house shall be provided for the
HV metering panels and HV switchgear. Outdoor transformer bays shall be
provided for transformers ancillary plants and associated control systems. Those
structures that are to be used by the KPTCL and the cable ducts/draw pits/cable
trenches for KPTCL incoming cable shall be constructed to conform to their
requirement. Individual transformer bays and HV switch rooms shall comply with
Electrical Specification.
5.4.32 Staff housing shall be provided for the operators, helpers and watchers.
5.4.33 All the structures of the Treatment Plant as mentioned including the outdoor
electrical sub-stations and also the Treated Water Pumping Station shall be
fenced off from the exterior by compound walling of, not less than, 2 m height. A
double leaf access door, the main gate, for vehicles and a single leaf access
door, the side gate, for operation personnel shall be provided at the compound
wall. The main gate and the side gate shall be positioned adjacently and the
main gate shall be positioned to at a location as agreed with the Engineer.
Compound walling shall be rendered brickwork with painted finish in accordance
with the standard. The main and side gates shall be anti-intruder painted steel
gates.
5.4.34 Landscaping of the final site shall be provided including tilling and seeding soil
and planting suitable species of trees and shrubs as agreed with the Engineer.
All grassed areas shall be irrigated
PARTICULAR CIVIL & STRUCTURAL REQUIREMENTS
The design considerations described hereunder establish the minimum basic requirements
of plain and reinforced concrete structures, masonry structures and structural steel works.
However, any particular structure shall be designed for the satisfactory performance of the
functions for which the same is being constructed. The Contractor shall also take care to
check the stability of partly completed structures.
5.6 Design Standards
All the designs shall be based on the latest Bureau of Indian Standard (BIS) Specifications
or Codes of Practice. The design standards adopted shall follow the best modern
engineering practice in the field based on any other International Standard or specialist
literature subject to such standard reference or extract of such literature in the English
language being supplied to and approved by the Engineer. In case of any variation or
contradiction between the provisions of the BIS Standards or Codes and the specifications
given along with the tender document, the provision given in this Specification shall be
followed.
166
All Reinforced Concrete structural design/details shall conform to the following recently
published publications of the Indian Standards Institution:
All Structural steel design shall conform to the following recently published publications of
the Indian Standards Institution:
167
(i) Weight of water : 10kN/m 3
Weight of soil (irrespective of strata
available at site and type of soil used for
(ii) filling etc).However, for checking stability : 20.00kN/m3
against uplift, actual weight of soil as
determined by field test shall be
considered
(iii) Weight of concrete : 24.00kN/m3
(iv) Weight of reinforced concrete : 25.00kN/m3
20.00N/m2per mm thickness of
(v) Weight of Brickwork(exclusive of plaster) :
Brickwork
Weight of Solid Concrete Block 24.00N/m2per mm thickness of
(vi) : block work
work (exclusive of plaster)
(vii) Weight of plaster to masonry surface : 18.00N/m2per mm thickness
Weight of granolithic terrazzo finish
(viii) : 24.00N/m2per mm thickness
or rendering screed, etc.
(ix) Weight of MS chequered plates : 78.5N/m2per mm thickness of
plates
Live Load
Live Load (LL) shall include the superimposed loads due to the use/occupancy of
the structure/building not including dead, wind or earthquake load. Live loads shall be in
general as per I.S. 875 Part (II). However, the following minimum live loads shall be
considered in the design of structures:
In the absence of any suitable provisions for live loads in BIS Codes or as given
above for any particular type of floor or structure, assumptions made must receive the
approval of the Engineer prior to starting the design work. Apart from the specified live
loads or any other load due to material stored, any other equipment load or possible
overloading during maintenance or erection/construction shall be considered and shall be
partial or full whichever causes the most critical condition.
Wind Load
Wind loads shall be as per I.S. 875 Part (III).
168
Earthquake Load
Seismic forces shall be as per I.S. 1893.
Dynamic Load
Dynamic loads due to working of plant items such as pumps, blowers, compressors, switch
gears, travelling cranes, etc. shall be considered in the design of structures.
5.9 Joints
Movement joints such as expansion joints, complete contraction joints, partial contraction
joints and sliding joints shall be designed to suit the structure. However, contraction joints
shall be provided at specified locations spaced not more than 7.5 m in both right angle
directions for walls and rafts.
Expansion joints of suitable gap at suitable intervals not more than 30 m shall be provided
in walls, floors and roof slabs of liquid retaining structures.
Construction joints shall be provided at right angles to the general direction of the member.
The locations of construction joints shall be decided on convenience of construction. To
avoid segregation of concrete in walls, horizontal construction joints are normally to be
provided at every 2 m height. PVC water stops of 150 mm width shall be used for walls and
230 mm width for base slabs.
169
5.10.7 Walls shall be designed under operating conditions to resist earthquake
forces from earth pressure mobilization and dynamic water loads (Hydrodynamic
Impulsive Pressure);
5.10.8 For general retaining walls and large sized tanks where the walls are
designed as retaining walls, sliding check shall also be performed along with over
turning checks. Overturning: The stability of a structure as a whole against
overturning shall be ensured so that the restoring moment shall be not less than the
sum of 1.2 times the maximum overturning moment due to the characteristic dead
load and 1.4 times the maximum overturning moment due to the characteristic
imposed loads. In cases where dead load provides the restoring moment, only 0.9
times the characteristic dead load shall be considered. Restoring moment due to
imposed loads shall be ignored.
5.10.9 Sliding: The structure shall have a factor against sliding of not less than 1.4
under the most adverse combination of the applied characteristic forces. In this case
only 0.9 times the characteristic dead load shall be taken into account.
5.10.10 All the liquid retaining structures shall be designed for maximum design crack
widths of 0.1mm for direct tension and flexure.
5.10.11 In case of Large and Deep Underground Tanks such as Wet Wells, the
analysis can be carried by Finite Element Method using STAAD.Pro or any other
equivalent software predominantly used and accepted in the industry.
5.11 Foundations
5.11.1 The minimum depth of foundations for all structures, equipments, buildings
and frame foundations and load bearing walls shall be as per IS 1904 but in any
case this shall not be less than 1.0 meter in the original soil.
5.11.2 Maximum safe bearing capacity of soil strata shall be taken as determined by
the Contractor through his own independent investigations. Geotechnical reports of
proposed STP sites covered under the contract are provided with the Bid
Documents. It may be used by Contractor as part of, in addition to, or in lieu of such
investigations at his own risk.
5.11.3 Care shall be taken to avoid the foundations of adjacent buildings or structure
foundations, either existing or not within the scope of this Contract. Suitable
adjustments in depth, location and sizes may have to be made depending on site
conditions. No extra claims for such adjustments shall be accepted by the Employer.
5.11.4 Special attention is drawn to danger of uplift being caused by the ground
water table. All underground structural slabs shall be designed for uplift forces due to
ground water pressure.
5.11.5 EGL (Existing ground level) and FGL (Finished ground level) shall be marked
on all drawings showing foundation/sub-structure details and related design
documents.
5.11.6 Machine / static equipment foundations shall be separated from adjoining
parts of buildings, other foundations and floor/pavement slabs. Joints at
floor/pavement slabs shall be suitably sealed.
5.11.7 Foundations and structures for machines subject to vibrations shall be so
proportioned that the amplitude and frequency of the foundation/structure are within
the permissible limits as per relevant BIS codes (or as required by the machine
170
vendor).
5.11.8 Machine foundations shall be designed and detailed as per IS: 2974. All
appendages to such foundations shall be reinforced suitably to ensure integral
action.
5.11.9 Pile Foundations - Design, Testing and Execution of piles shall be considered
as per provision of relevant codes (conforming to latest version of IS: 2911), and in
compliance with the Geotechnical report recommendations as applicable.
5.11.10 Foundations for plant structures in Swampy/Waterlogged areas, for lightly &
medium loaded structures and relevant Ground Improvements shall be considered in
compliance with the relevant Geotechnical Investigation Report recommendations as
applicable. Also to enlist the services of an experienced & specialized agency for all
related design aspects considerations, equipment specifications, and implementation
methodology, etc., as an advice for the same.
c) The reinforced concrete for all structures shall have a minimum cement
content of 360kg/m3 with a maximum 20mm size aggregate for liquid
retaining structures and 320kg/m 3 for non liquid retaining structures.
Reinforced concrete shall have maximum slump of 100mm with maximum
water cement ratio of0.45.
e) The minimum cover to the main reinforcing bars for different members for:
1. Non-liquid retaining structures shall be as follows unless stated
otherwise:
Slab (Floor, Roof, Canopy, Chajjas and Staircase)
25m
m Beams (Sides, Bottom& Top)
40m
m
Lintels (all-around) 30mm
171
Columns
i) For columnwidth200 40mm
ii) For column width 230&above
iii) 50m
m Pedestals (in contact with earth)
50mmBasementwall, retaining walls
i) Face in contact with earth 50mm
ii) Interior face 40mm
Foundations (Top, Bottom and sides) 50mm
g) The minimum amount of reinforcement in each of the two direction sat right
angles within each surface zone should be provided as per clause 8.1 of
IS3370 (Part2): 2009. Definition of surface zones is clearly shown in Figure-1
and Figure-2 of IS3370 (Part2): 2009. For slabs, minimum of 10 mm dia bars
shall be used to avoid any deformation of lesser diameter bars under loads
prior to construction.
h) All buildings shall have a minimum 1meter wide, 100mm thick plinth protection
pavinginM15gradeconcreteorstoneslabs/tiles.Allplinthprotectionshallbe
supported on well compacted strata.
i) All pipes and ducts lay below the structural plinth and roadwork’s shall be
surroundedwithconcreteofgradeM15havingminimum150mmthickconcrete or
172
D/4(D=outer dia of pipe) thickness whichever is more.
j) Use of pressure relief valves to reduce uplift pressure due to ground water
table shall not be allowed.
l) Sliding layer or slip layer shall be provided between sub base and structural
slab (Raft). Polythene sheets of 500 microns shall be provided as sliding layer
as per IS specification.
Reinforcement bars and structural steel to be procured only from Primary steel
producers / Integrated Steel Plants such as TATA/SAIL/RINL/JSW/SHYAM
STEEL using iron ore as the basic raw material and having in-house iron
making facilities. No Re-rolled material / secondary steel will be accepted or
allowed for any structural works.
The steel manufacturing company should have latest ISO accreditation for
Quality Management System.
173
o) The minimum amount of reinforcement in each of the two direction straight
angles within each surface zone should be provided as per clause 8.1 of IS
3370 (Part-2): 2009. Definition of surface zones is clearly shown in Figure-
1and Figure-2 of IS 3370 (Part2):2009. For slabs, minimum of 10mm dia bars
shall be used to avoid any deformation of lesser dia meter bars under loads
prior to construction.
p) All buildings shall have a minimum1meter wide, 100mm thick plinth protection
paving in M15 grade concrete or stone slabs/tiles .All plinth protection shall be
supported on well compacted strata.
q) All pipes and ducts laid below the structural plinth and road works shall be
surrounded with concrete of grade M15 having minimum 150mm thick
concrete or D/4(D=outer dia. Of pipe) thickness whichever is more.
r) Use of pressure relief valves to reduce up lift pressure due to ground water
table shall not be allowed.
t) Sliding layer or slip layer shall be provided between sub base and structural
slab (Raft). Polythene sheets of 500 microns shall be provided as sliding layer
as per IS specification.
Water tightness testing of water retaining structures shall be done in accordance with IS:
3370, (Part-I)-2009. It is described in Clause5.26 of this document. The depth of water
for testing shall be up to the soffit of the covering slab.
The following minimum thicknesses shall be used for different reinforced concrete members,
irrespective of design requirements:
174
(xii) Launder Vertical Wall, Baffle Wall, Gutter Slab : 150 mm
(xiii) Grade Slabs : 150 m
5.15 Standards
Materials and workmanship shall comply with the relevant Indian Standards (with
amendments) current on the date of submission of the tender.
Where the relevant standard provides for the furnishing of a certificate to the Engineer, at his
request, stating that the materials supplied comply in all respects with the standard, the
175
Contractor shall obtain the certificate and forward it to the Engineer.
The specifications, standards and codes listed below are considered to be part of this
specification. All standards, specifications, codes of practices referred to herein shall be the
latest editions including all applicable official amendments and revisions.
In case of discrepancy between the Specification and the Standards referred to herein, the
Specification shall govern.
a) Materials
IS:269 - Specification for 33 grade ordinary Portland cement
IS:278 - Specification for Galvanized Steel Barbed wire &Fencing
IS:383 - Specification for coarse and fine aggregates from natural
sources for concrete
IS: 428 - Specification for distemper, oil emulsion, coloras required
IS: 432 - Specification for mild steel and medium tensile steel bars and
hard drawn steel wire for concrete reinforcement (Parts1&2)
IS: 455 - Specification for Portland slag cement
IS: 458 - Specification for precast concrete pipes (with and without
reinforcement)
IS:650 - Specification for standards and for testing of cement
IS:651 - Specification for salt glazed stone ware pipe sand fittings
IS:808 - Specification for dimensions for hot rolled steel beam, column
channel and angle sections
IS:814 - Specification for covered electrodes for manual metal arc
welding of Carbon and Carbon Manganese steel
IS:1003 - Specification for timber paneled and glazed shutters(Parts1&2)
IS:1038 - Specification for steel doors, windows and ventilators
IS:1077 - Specification for common burnt clay building bricks
IS:1398 - Specification for packing paper, water proof, and bitumen
laminated.
IS:1489 - Specification for Portland pozzolana cement(Parts1&2)
IS:1566 - Specification for hard drawn steel wire fabric for concrete
reinforcement.
IS:1580 - Specification for bituminous compounds for waterproofing and
caulking purposes
IS:1786 - Specification for high strength deformed steel bars and wires for
concrete reinforcement
IS:1852 - Specification for rolling and cutting tolerances for hot rolled
steel products
IS:1948 - Specification for aluminum doors ,windows and ventilators
IS:1977 - Specification for Low Tensile structural steel (Ordinaryquality)
IS:2062 - Specification for steel for general structural purposes(Hot
176
Rolled Low, Medium and High Tensile Structural Steel).
IS:2185 - Specification for concrete masonry units(Parts1,2&3)
IS:2202 - Specification for wooden flush door shutters(Parts1&2)
IS: 2645 - Specification for integral cement water proofing compounds IS:
2721 - Specification for Galvanized Steel Chain Link Fence Fabric IS: 2750
- Specification for steel scaffoldings
IS:2835 - Specification for flat transparent sheet glass
IS:3384 - Specification for bitumen primer for use in water proofing and
damp proofing
IS:3502 - Specification for steel chequered plates
IS: 4021 - Specification for timber door, window and ventilator frames IS:
4350 - Specification for concrete porous pipes for under drainage IS:
4351 - Specification for steel door frames
IS:4990 - Specification for plywood for concrete shuttering work
IS:8112 - Specification for 43 grade ordinary Portland cement
IS:9862 - Ready mixed paint, brushing, bituminous, and black, lead
free, acid, alkali, water and chlorine resisting
IS:10262- Recommended guidelines for concrete mix design
IS:12269- Specification for 53 grade ordinary Portland cement
IS:12330- Specification for sulphate resisting Portland cement
IS:12709- Glass fiber reinforced plastics (GRP) pipes, joints and fittings for
use for potable water supply
b) Tests
IS:516 - Method of test for strength of concrete
IS: 1182 - Recommended practice for radiographic examination of fusion-
Joints in steel plates
IS: 1199 - Methods of sampling and analysis of concrete
IS: 2386 - Methods of test for aggregates for concrete (Parts1to8)
IS: 2720 - Methods of test for soils (Parts1 to 39)
IS: 2911 - Code of Practice for design and construction of Pile foundations
IS:3025 - Methods for sampling and test(physical and chemical) for water
Wastewater (Parts1to56)
177
IS:7318 - Approval tests for welders when welding procedure approval is
not required (Parts1and2)
IS: 13311 - Methods of Non-destructive testing of Concrete - (Part1 & Part2)
178
IS:2911- Code of practice for design and construction of Pile foundations
IS:2974- Code of practice for design and construction of machine
foundations (Parts1to4)
IS:3114- Code of practice for laying of Cast Iron pipes
IS:3370- Code of practice for concrete structures for the storage of
liquids(Parts1to4)
IS:3414- Code of practice for design and installation of joints in buildings
IS:3558- Code of practice for use of immersion vibrators for consolidating
concrete
IS:3658- Code of practice for liquid penetrate flaw detection
IS:3935- Code of practice for composite construction
IS:4000- Code of practice for High strength bolts in steel structures
IS:4014- Code of practice for steel tubular scaffolding(Parts1&2)
IS:4111- Code of practice for ancillary structures in sewerage system
(Parts1to5)
IS:4127- Code of practice for laying of glazed stoneware pipes
IS:4326- Code of practice for Earthquake Resistant Design and
Construction of Buildings
IS:4353- Recommendations for submerged arc welding of mild steel and low
alloy steels
IS:5329- Code of practice for sanitary pipe work above ground for
buildings
179
5.16 General Arrangement of Plant
The following general guidelines shall be followed in the preparation of general arrangement
of Plant:
- Sufficient room shall be allowed between items of plant and adjacent Plant or fixed
structures to permit safe and convenient access for operation and maintenance;
- An area adjacent to all mechanical Plant shall be provided as maintenance lay down
area;
- fixed runways, lifting eyes or other means shall be provided to permit the removal of
Plant that may be required to be removed during the course of its normal operational
life for maintenance or any other purpose;
- areas where leakage is likely to occur whether in normal use or during maintenance
shall be provided with covered drainage channels which shall direct spillage either to
a suitable plant drain or to a sump from where it can be pumped to plant drain;
5.17 Orientation
The works shall be laid out within the confines of the Site in order to interface to the existing
infrastructure of roadways and inlet and outlet pipe work. Underground services requiring to
be relocated in order to accommodate the proposed site layout shall, with the approval of the
Engineer, be relocated by the Contractor.
5.18 Buildings and Structures
All the building and structure works shall generally comply with the following
Employer’s Requirements unless otherwise specified elsewhere:
1. All building works shall be of reinforced concrete framework (Concrete Grade of M25 as
aminimum).
2. All external walls shall be in solid cement concrete blocks of concrete grade M15 and
shall be provided as per IS: 2185 (Latest Revision) and shall be 200 mm thick.
3. All internal partition walls shall be in solid cement concrete blocks of concrete grade
M15 and shall be provided as per IS: 2185 (Latest Revision). All internal walls shall be
200mm thick except for toilets. Toilet partition walls shall be in 100 mm thick solid
concrete block.
4. (a) Finishes to concrete liquid retaining structures shall
be: F1 - External surfaces, buried
F2 - External surfaces exposed and up to 300 mm below ground level
F2 - Internal surfaces
(b) Finishes to other concrete structures shall
be: F1 - Buried
F1 - Exposed, where plastering is specified
F2 - Exposed
5. All internal masonry and ceiling surfaces finish shall have 12 mm thick plain faced
cement plaster in cement mortar (1:4) with neat cement finish on top. Over this, one
coat of primer and two coats of plastic emulsion paint of approved quality and shade
shall be provided.
6. All external masonry and concrete with rough board finish shall have 20 mm thick
sand faced cement plaster in two coats, base coat 12 mm thick in cement mortar 1:4
and finishing coat 8 mm thick in cement mortar 1:4. Waterproofing compound of
180
approved make and quality shall be added to the cement mortar in proportions as
specified by the manufacturer.
7. All external surfaces above ground level shall have one coat of primer and two coats
of waterproof cement based paint of approved quality and shade. A coat of silicone
water repellent paint shall also be applied thereon.
8. Toilet areas, walls and ceilings, shall have one coat of primer and two coats of plastic
emulsion paint.
9. Toilet floor slab shall be filled with brick bat coba (broken bricks in lime) and provided
with waterproofing as per the specifications of an approved specialist waterproofing
company.
10. The finished floor level in toilet areas shall be 25 mm below general finished floor level
elsewhere in the building.
11. The flooring in all areas except toilets, staircases, pumping stations, chlorination
building, centrifuge building, workshop, D.G.Room shall be in 250 mm x 250 mm x 20
mm thick marble mosaic tiles of approved make unless otherwise specified, shade
and pattern and placed in cement mortar 1:4 to give overall thickness of 50 mm. Half
tile skirting shall also be provided in these areas.
12. The flooring in the pumping stations, chlorination building, centrifuge building,
workshop, D.G.Room shall be 60mm thick cement flooring with Metallic concrete
hardener topping, under layer of 42mm thick cement concrete 1:2:4 (1 cement :
2coarse : 4 graded stone aggregate 16mm thick nominal size) and top layer of 18mm
thick metallic concrete hardener consisting of mix 1:2 (1 cement : 2 stone aggregate
6mm nominal size) by volume & mixed with metallic hardening compound of approved
quality @ 3 kg/m2. Including cement slurry and rounding off edges.
13. The flooring in operator’s room, loading/unloading bay, MCC cum Panel room shall be
in 25mm thick Kota stone slab of approved shade and pattern and placed over 20 mm
thick base of cement mortar 1:4 to give overall thickness of 45 mm. Half tile skirting
shall also be provided in these areas.
14. Toilet areas shall have 450 mm x 450 mm x 25 mm thick polished Kota stone tiles
placed in cement mortar 1:4 to give an overall thickness of 50 mm. 2100 mm high
dado, in 150 mm x 150 mm x 6 mm thick glazed tiles (approved make, shade and
pattern) placed in cement mortar 1:3 shall also be provided in these areas.
15. The flooring along with skirting in administration cum laboratory building shall be 20
mm thick mirror polished, machine cut granite slab of approved shade and pattern
placed in cement mortar (1:4). 150mm high skirting shall be provided in these areas.
Granite stone shall be provided for laboratory platforms fixed over double sandwiched
cudapa support as directed and the edges of granite is to be embedded into the wall.
16. The toilet facilities shall include at least:
(i) 2 Nos. Water closets with white porcelain Orissa pan minimum 580 mm long with
low level flushing cistern of 10 litres capacity.
(ii) 2 Nos. Urinals of sizes 600 mm x 400 mm x 300 mm flat back type in white
porcelain separated by a marble partition of size 680 mm x 300mm.
(iii) 2 Nos. wash basins of size 510 mm x 400 mm in white porcelain with inlet, outlet
and over flow arrangements.
(iv) 2 Nos. mirror of size 400 mm x 600 mm wall mounted type fitted over washbasins.
181
(v) 2 Nos. plastic liquid soap bottles
(vi) 2 Nos. chromium plated brass towel rails minimum 750 mm long.
(vii) All stopcocks, valves and pillar cocks shall be heavy duty chromium plated brass.
(viii) All fittings such as ’P’ or ‘S’ traps ,floor traps ,pipes, down take pipes etc.
(ix) The sewage from toilet blocks shall be led to the wet well of terminal sewage
pumping station if present or included under this contract or to the closest gravity
sewer.
17. All staircases shall have 25 mm thick chequered mosaic tiles for treads and 25 mm
thick plain mosaic tiles for risers of approved make and shade and half tile skirting set
in cement mortar in 1:4 to give an overall thickness of 50 mm. All concrete stairs shall
have aluminium nosing over 2 mm thick rubber strip of width same as nosing for the
full length of the tread. Nosing shall be fixed with countersunk screws.
18. Stairways shall be provided to permit access between different levels within buildings.
Staircase shall be minimum 1000mm wide, minimum Tread = 250 mm, maximum
Riser
= 175 mm and maximum 15 number of steps per flight unless specified otherwise.
Staircases in general shall not be steeper than 40°. Staircases having space constraints
may be steeper than400. The maximum vertical run for a single flight of stairs shall be
3.0 M.
19. All roof tops and overhead tanks shall be made accessible with ladder provision.
Vertical step ladders fitted with landing point extensions will be permitted where
considered appropriate by the Engineer to access areas not frequently visited.
Steel staircases shall be constructed of standard channel stringers with M.S. grating
treads 25mm thick with non skid nosing. Steel Ladders shall be minimum 600mm
wide and shall not exceed 6m of straight run. The ladders shall be painted with epoxy
paint.
20. All hand railing shall be provided with 6063-T6 Aluminium Alloy with an ultimate
tensile strength of at least 207 MPa and yield strength of at least 172 MPa. The
minimum height of hand railing shall be 1m and maximum spacing of verticals shall be
1.5 m. Number of horizontal rails shall be 3 (1 top, 1 intermediate and 1 bottom) OR 2
rails ( 1 top, 1 intermediate) with a 100 x 6 toe plate at the bottom.
21. The reinforced concrete roofs shall be made waterproof by application of an approved
roof polythene / bitumen membrane / brick bat coba. The finished roof surface shall
have adequate slope to drain quickly the rain water to R.W down take inlet points.
22. All roof floors shall have minimum 750 mm height solid concrete block parapet wall
where accessible is provided and shall have minimum 300 mm height solid concrete
block parapet wall where accessible is not provided
23. For roofing drainage, cast iron or uPVC rainwater down takes with C.I. bell mouth or
uPVC bend and C.I. or uPVC grating at top shall be provided. For roof areas up to 40
sq m minimum two nos. 100 mm diameter down take pipes shall be provided. For
every additional area of 40 sq m or part thereof, at least one no. 100 mm dia. down
take pipe shall be provided.
24. Top surfaces of chajjas and canopies shall be made waterproof by providing a screed
layer of adequate slope or application of an approved roof membrane and sloped to
drain the rainwater.
182
25. Building plinth shall be minimum 450 mm above average finished ground level around
building or high flood level whichever is more.
26. All doors, windows, rolling shutters shall have lintels above. Chajja protection to lintels
on external walls shall be such as to prevent the rain water splashing into the building.
Chajja projection of minimum 750 mm for rolling shutters, 600 mm for doors and
windows shall be provided to prevent the rain water splashing into the building. Chajja
shall be projected 150 mm on either sides from size of doors/windows/rolling shutters.
27. All windows and ventilators shall have 25 mm thick Kota stone sills bedded in cement
mortar(1:3).
28. All doors and windows shall be painted with two coats of synthetic enamel paint over
a priming coat (ready mixed Zinc Chromate Yellow primer of approved brand and
manufacturer confirming to I.S.: 127-106, 341 and340).
29. All doors, windows and ventilators shall be made of aluminium confirming to latest
version of IS: 1948. All fixtures for doors, windows and ventilators shall also be of
aluminium. Aluminium grills shall be provided in all the windows. Doors shall be in two
panel and both panels shall be glazed/unglazed. Minimum weight of aluminium doors
& windows shall be as follows
183
IV. Aluminium Door
Outer Frame : Weight 2.508kg/Rmt
Shutter Frame : Weight 2.508kg/Rmt
Bottom Stile :
Weight2.508kg/Rmt
Glazing shall be 5.5 mm thickness.
30. Openings of the windows & ventilators shall be minimum 25% of the external wall area.
31. Ventilator shall be provided where height of floor is more than3m.
32. All windows and ventilators shall have wire mesh. Frame of doors, windows and
ventilators shall be of aluminium of standard rolled section. Doors, Windows and
Ventilators shall be of size as per schedule to be submitted by the Contractor for
approval of Engineer. The minimum size shall be as per below:
Door of opening size 1.2m x 2.1m
Door of opening size 0.75m x 2.1m for
toilets Glazed windows of minimum size
1.2m x 1.2m Ventilators of minimum size
0.6m x 0.6m
33. Rolling shutters shall be made of 80 x 1.25 mm MS laths. Rolling shutter shall be of
minimum size 3m wide x 3.0m high. Rolling shutter shall be provided in MCC cum
panel room, chlorine tonner shed, at entry and exit of the pump house for access to
pumps, motors, valves, panels and as wherever required.
34. All concrete channels and ducts used for conveying liquid shall have inside finish of
type F2. The width of concrete channels shall not be less than 500 mm. All open
channels shall be provided with Aluminium hand railings (3-rail) or concrete walls to a
minimum height of 1 m from the access surface elevation. All concrete surfaces of
structures conveying raw sewage or primary effluent upstream of the aeration tanks
shall be protected from corrosion with an approved internal lining as specified in
Clause 5.25of this document.
35. Kerbs to be provided below the hand railing on the catwalks/pathways should be as
per relevant sections of Factory Act. It shall not be less than150mm.
36. All exposed surfaces of inserts embedded in concrete shall be painted with two coats
of enamel paint over one coat of red oxide zinc chrome primer. Surfaces in contact
with concrete shall not be painted.
37. All structural steel members shall be painted with two coats of enamel paint over one
shop and one field coat of red oxide zinc chrome primer.
38. All rooms in the treatment plant buildings shall be provided with appropriate sign
boards indicating the function of the rooms involved written in Kannada and English
Languages.
39. The design of buildings shall reflect the climatic conditions existing on site. Process
buildings shall as far as is possible permit the entry of natural light , and the use of
glazed paneling shall be kept to a minimum and preference given to wall openings
protected by weather canopies.
40. Emergency exit doorways shall be provided from all buildings in order to comply with
184
local and international regulations .Stairways and paved areas shall be provided at the
exit points.
41. Toilet blocks in process buildings and control blocks shall be provided with a sink with
two drinking water taps of 20 mm size with adequate inlet and outlet connections.
42. All the walkways shall have minimum 1 m width and shall be covered with mosaic
tiles. Walkways to be provided with 6063-T6 Aluminium Alloy hand railings.
43. Anaerobic Sludge Digesters and Sludge Tank with Gas Holders shall be built in RCC.
A top dome of digesters and Gas Holders shall be made of Steel with full Epoxy
Coating as per the specification given in Clause 5.25of this Part-10 and top surface
Ring Beam and top 2m wall of the digester shall also be coated with Epoxy Coating.
Contractor may submit his proposal for the alternative materials which can be used for
digester dome and gas holder along with all technical details. Employer will approve
the type of material which shall be used for the construction of gas holders and
digester domes depending upon the durability, corrosion resistivity, strength, ease in
operation, functional requirements, economy, etc.(if included in this contract)
44. All concrete structures in contact with sewage and/or sludge upstream of the Aeration
Basins shall be provided with full interior corrosion protection linings and/or coatings of
appropriate material and thickness to be approved by client. This also applies to all
concrete structures in contact with any type of sewage sludge anywhere in the plant.
For Aeration Basins, interior lining shall extend from the top of wall down to 1.0 meter
below the lowest operating water level.
45. For structures containing water or process liquid, the top of the wall shall be at least
0.5m higher than the maximum water surface level calculated at high flood level and
peak plant flow. The top level of internal plant roads and approaches shall be at least
0.5m above the site High Flood Level.
46. If the High flood level is more than Ground Level then road shall be constructed on the
Earthen Embankments/Engineered Embankment. Earthen Embankments/ Engineered
Embankment shall be constructed with side slope of at least 2 horizontal to 1 vertical.
Stone pitching shall be provided at both sides of the embankment as per IS: 8237.
Top width of embankment shall be taken as 6.0m. Top level of embankment shall be
0.5m above high flood level. Good quality of filling materials can be used for
embankment construction as approved by Engineer/as suggested in relevant
Geotechnical Investigation Report recommendations as applicable.
47. Engineered Embankments for plant structures in Swampy/Water logged areas shall
be considered in compliance with relevant Geotechnical Investigation Report
recommendations as applicable.
48. All requirements for Engineered Embankments and all other associated works
connected to this system (i.e. like, all controlled filling requirements, Type & suitability
of materials, Methodologies, Testing, Protective systems, Aprons, Proper slopes,
Stability, Specifications, Quality control, and all other requirements pertaining to this
system of works, etc.,) shall be considered in compliance with relevant Geotechnical
Investigation Report recommendations as applicable. Also to enlist the services of an
experienced & specialized agency for all related design aspects considerations,
equipment specifications, and implementation methodology, etc., as an advice for the
same (Refer to 46 &47).
49. Suitable River flow training systems/Flow diversion to be adopted at required
locations/places in compliance with relevant Geotechnical Investigation Report
recommendations as applicable.
185
5.19 Roadways, Pathways & Hard standings
A comprehensive network of roadways shall be provided around the treatment plant to
link in with the existing road network and permit access to the plant for necessary
maintenance, delivery of consumables and personnel access. All roads shall be of
asphalt macadam having minimum 5.5 metres wide. Vehicular access shall be
provided for all Plant structures and buildings. All roads shall be provided with
drainage and shall be constructed to prevent standing water.
Paved pedestrian access ways shall be constructed to provide a network of logical
routes interlinking plant areas. Damage to any existing roads on account of their use
by the Contractor shall be made good to the satisfaction of the Engineer.
Hard standing areas with shading facility shall be provided to permit the parking of
vehicles involved in the delivery of consumables from blocking site roadways during
unloading or loading. The road system shall be designed such that vehicles involved
in the delivery of consumables can follow a continuous route through the works and
out again.
188
6 PARTICULAR SPECIFICATIONS – BUILDING SERVICESWORKS
BUILDING SERVICES
6.1 Scope
The Contractor shall design, supply, delivery to Site, off-loading, storage, erection, testing
and commissioning the complete building services installations at all the works including but
not limited to;
(a) Internal main and emergency lighting;
(b) External lighting and floodlighting;
(c) Roadway lighting;
(d) Small power;
(e) Ventilation and ceiling fans;
(f) Telephone lines and handsets;
(g) Plumbing and drainage.
The building services installation shall comply with Standard Specification and the following
clauses herein and local Codes and Regulations. Where the drawings, standard
specification and particular specification differ, the latter shall take precedence.
6.2 Lighting
6.2.1 Internal main lighting
Internal lighting shall be designed to provide the following minimum service luminance,
measured at floor level:-
6.2.1.1 Process plant/pump hall areas : 200lux
6.2.1.2 Chemical and disinfection areas : 300lux
6.2.1.3 Switch rooms : 200lux
6.2.1.4 Control room : 350lux
6.2.1.5 Workshop areas : 300lux
6.2.1.6 Laboratory : 350lux
6.2.1.7 Offices : 300lux
6.2.1.8 Staff rooms : 150lux
6.2.1.9 Toilets, washrooms, mess rooms, corridors and staircases : 100lux
LED type Luminaries shall be provided and fixed directly to, or suspended from the
underside of roof slabs, ceilings or fixed to walls as appropriate.
Pump halls areas shall be provided with LED high or low bay energy efficient lighting. The
Contractor shall provide all necessary equipment to ensure lighting maintenance can be
performed in a safe and efficient manner. Where special provision would have to be made
for accessing luminaries supported from the underside of the roof slab for maintenance,
luminaries shall be wall mounted.
LED type Luminaries for the control room and offices shall be designed to minimize glare
and shall be suitable for VDUs.
Light switches shall be located adjacent to doorways. Multi-way switching shall be provided
for rooms and areas with more than one point of access. For large area light switching or
high/low bay lighting, contactors shall be provided to switch lighting in blocks from each entry
point.
189
Luminaries and associated electrical accessories installed in chemical plant rooms shall be
protected to IP 65 minimum.
6.2.2 Internal emergency lighting
Emergency lighting shall be provided and shall comprise exit and escape route luminaries to
facilitate safe movement of personnel in or from any building or major dry structure in the
event of a mains supply failure. Exit luminaries shall be provided above all doors leading to
or accessible to an outdoor area.
Emergency lighting shall be provided in areas where essential operations may be required
during a mains supply failure, for example, switch room and control rooms. Exit luminaries of
emergency lighting shall be powered by integral battery units.
6.2.3 External walkway areas
LED type Luminaries shall be provided to illuminate all external personnel walkway areas
around buildings and structures. The lighting shall be designed to provide an even minimum
service illuminance measured at ground level of 15 lux.
Lighting shall be switched at personnel access doors. Multi-way switching shall be provided
where there is more than one point of access.
Luminaries and associated electrical accessories installed in outdoors shall be protected to
IP 65 minimum.
6.2.4 Flood lighting
LED type Floodlighting shall be provided for the entrance to the sites all site pumping
stations and loading / unloading areas. Floodlighting shall also be provided at all locations
requiring inspection.
Floodlights shall be mounted on galvanised steel poles or on structure walls as appropriate.
Floodlighting shall provide a minimum service illuminance of 50 lux measured at the working
plane.
Floodlighting shall be locally switched. Luminaries and associated electrical accessories
installed in outdoors shall be protected to IP 65 minimum.
6.2.5 Lighting for Booster Stations & MBRs / ZBTs site and general roadway
lighting
Lighting for Booster Stations & MBRs / ZBTs site and general roadway lighting at all plants in
this Contract shall comprise tubular steel columns with semi cut-off high pressure sodium
type luminaries complete with control gear, which shall in general conform to the Standard
Drawing. The lighting shall provide a minimum illuminance at ground level of 25 lux.
Concrete mass base and skirting, in conceptual design as per design shall be installed. Each
lamp pole shall be structurally sound to withstand, as a minimum, 160 knots without causing
any damage. The height of the lamp pole for general roadway lighting shall be not less than
4.5 m and that for MBRs / ZBTs shall be not less than 8 m. Lamp poles of mild steel
construction shall be hot dip galvanized to BS 729. The poles shall be finished overall with at
least two coats of primer and two coats of finishing paint after erection. The colour of the
finishing paint shall be as directed by the Engineer.
Minimum of 4c x 6sq mm, 1.1 kV, Cu., PVC, Armoured cables shall be used for power
supply from distribution board up to the individual junction boxes of each street light pole.
From the junction boxes up to the luminaries 2.5sq mm Cu flexible wire shall be used.
190
External Roadway lighting control shall be integrated with timer control and DB for the same
shall be kept in security cabin / control room.
Luminaries and associated electrical accessories installed in outdoors shall be protected to
IP 65 minimum.
6.3 Small power
Industrial switched type 240Vac socket outlets with residual current devices for the
connection of electric tools shall be installed in convenient places in all plant and workshop
areas.
Suitable rated 415Vac/240Vac socket outlets with residual current device shall be provided
for all water retaining structures for the water treatment works, intake structure and raw
water pumping station. The socket outlets shall be located in an IP65 weatherproof
enclosure fixed to the structure wall.
For process plant areas, industrial type socket outlets shall be so spaced so that any
location within the area is no greater than 20m from an outlet. A minimum of two socket
outlets shall be provided in each area.
Commercial type 240V 16A and 6A socket outlets shall be installed throughout all
administrative office areas including the associated corridor areas. A minimum of two socket
outlets shall be provided in each room to allow each desk to be serviced with a power supply
without the need for extension leads. Additional socket outlets to suit the particular
requirements of the main control room and the laboratory shall be provided.
6.4 Local area network
The Contractor shall provide a local area network for all offices including control room and
laboratory within the filter building in accordance with the standard specification. As a
minimum two RJ45 connections shall be provided in each office, laboratory and control
room. The Contractor shall submit details of the proposed network for the Engineer’s
approval.
6.5 Ventilation
Ventilation system shall be as specified elsewhere in the document.
6.6 Ceiling fans
All administrative areas such as the control room, all offices and building entrance areas at
the water treatment works and each water pumping station shall be provided with ceiling
fans to provide 4 ACH. The fans shall be provided with local speed controllers and switches
adjacent to each individual unit.
6.7 Distribution boards
Each individual building or facility shall be provided with suitably sized distribution board
dedicated for building services. The distribution board shall provide distribution to lighting,
socket outlets, heating, ventilation and air conditioning. Circuits shall be arranged to provide
a balanced load on each phase of the supply. Each distribution board shall be provided with
20% spare ways.
191
6.8 Wiring
Internal wiring on concrete and block work surfaces shall be carried out using single core
PVC insulated non-sheathed cables installed in surface mounted heavy duty galvanised
steel conduit and / or trunking. Wiring in plastered and tiled areas shall be installed in
concealed steel conduit.
External wiring shall be carried out using single core PVC insulated non-sheathed cables
installed in heavy duty galvanised steel conduit or PVC covered mineral insulated copper
sheathed cables.
Wiring associated with lighting and ventilation fans in the chemical buildings shall be carried
out using heavy duty PVC or GRP conduits / trunking and/or cable tray/ ladder as necessary.
192
7 PARTICULAR SPECIFICATIONS – INSTRUMENTATIONWORKS
7.1 General
All pumping stations and water treatment plant shall be designed for automatic operation
with programmable logic controller (PLC) and HMI / SCADA with facility to operate each
process unit manually if need arises.
The control system shall be designed to recover the plant fully to the normal operational
mode on the restoration of power (either from utility supplier or the generator) within the
predefined (programmable) time of power recovery without any manual intervention. If
power outage is for more than the above predefined time, then the same shall be treated as
fresh start and the system shall follow the fresh starting sequence selected by operator and
the timing shall be logged with real time data in the report format.
Local manual controls shall be located adjacent to equipments wherever required for manual
operation. The system envisaged shall be compatible for continuous operation of the plant.
The entire electrical control systems and instrumentation systems of the plant shall be
interfaced. The automation system proposed shall not be limited to only process / equipment
control but shall also cater to the energy monitoring system of all the areas including
substation and generator. All data shall be logged on real time basis including hours of
generator operation, total power produced and supplied to the plant etc. Data shall also be
logged for the power used from Electricity Board.
7.2 Control System
The control system hardware to be located in control room and near each plant areas, MCC,
pump / power, distribution areas shall consist of;
7.2.1 Plant Control Panel(PLC)
7.2.2 Local 10.4” TFT Colour Screen HMI
7.2.3 Power Supplies
7.2.4 PC based MMI / SCADA System (2 Nos.) at Central Control Room(CCR)
The Central Control Room shall also have screen printed dynamic MIMIC with transparent
acrylic cover showing the plant flow diagrams and dynamic status using multi coloured LED
lamps and digital meters for flow, level etc. MIMIC shall also have buzzer along with alarm
display, window type or message display unit type. All PLC panel and instrument / PC
supply shall be provided through UPS with at least one hour backup time.
The field instrumentation process forms an integral part of control system. Hardwired
interlocking shall be provided for safety circuits such as motor protection, dry run protection,
emergency stop circuitry and rotation monitor.
193
7.3 Process Instrumentation
The process instrumentation includes instruments for Control, Operation and Monitoring.
The contractor shall list all the process instruments proposed in the scheme.
Ultrasonic signal shall be interfaced with PLC for SCADA and control functions and float type
switches signal shall be as a backup to transmitter signal for protection of dry run or over
flow condition.
7.4 Process Units Control
7.4.1 General
The WTP shall be divided into sections depending on the operational requirements. A
hierarchical structure shall be adopted throughout the plant for fault annunciation.
The highest alarm level shall be at the central point MMI which shall annunciate general
alarms like disinfection fault, mixing fault, sludge dewatering fault, chemical dosing fault,
backwashing fault, and other specific alarms related to the plant. However, information shall
be made available up to the lowest level fault by selecting the drive details on SCADA
screen.
The next lowest level shall be the alarms matrix associated with each area. This shall
indicate non drive specific alarms on MIMIC panel.
The next lowest level shall be the alarm annunciated on each drive starter module. This will
annunciate every alarm associated with that drive. The same information shall be made
available on SCADA and also on the popup screen of particular drive.
Thus the operator noting the fault at the Central MIMIC panel shall go to the specific alarm
matrix to determine the correct nature of fault, in case of SCADA not operational.
7.4.2 Motor Control Centers
The MCC shall be provided with Local Remote Selector Switches and Auto Manual Selector
Switches for operation of the motors from various locations.
Auto Mode
Motors shall be operated from the PLC when the selected mode is Auto of Auto
Manual Selector Switch.
Manual Mode
Motors shall be operated from the Motor Control Centre when the mode selected in
the MCC is “Manual” from Auto / Manual Selector Switch and “Local” from Local /
Remote Selector Switch.
Remote Mode
Motors shall be operated from the Local Push Button Stations of the corresponding
motor kept near the motor.
Local Mode
194
7.4.2.1 Main Substation
Higher load feeders shall be provided (in the MLTP) with energy meter for each of those
feeder with pulse output to interface with PLC. Detailed single line diagrams shall be
furnished with the proposal. Also typical detailed feeder single line diagram shall be
submitted. These provisions shall be for the feeders above 15 HP.
7.4.2.2 Local Man Machine Interface
Local HMI shall be provided in all PLC panels for controlling and monitoring of the status of
all the pumps, mixers, air blowers etc.
Typically with local HMI the operator shall be able to do;
7.4.2.2.1 Start and Stop control
7.4.2.2.2 Auto Manual Selector Switches
7.4.2.2.3 Pump - Motor start - stop pushbuttons
7.4.2.2.4 Discrete Controls to provide selection of duty pumps
7.4.2.2.5 Indicating lamps
The start, stop and trip alarms of all associated motors MCCs shall be indicated in the HMI.
The Contractor to include all the alarms as necessary for the satisfactory operation of the
pumping stations and WTP in his proposal. The list shall also indicate parameters of offered
MCC feeders of each area.
In order to make PLC function properly and accurately, the point of power and control shall
be from one point. Junction boxes shall be provided at approximate locations on signal
concentration to avoid multiple cables.
7.4.2.3 Central Man Machine Interface (SCADA)
The MMI / SCADA at the central control shall have the following facilities:
7.4.2.3.1 Auto - manual selector switches
7.4.2.3.2 Pump motor start stop pushbuttons
7.4.2.3.3 Indicating Lamps
7.4.2.3.4 Alarm annunciators
7.4.2.3.5 HMI of PLC Panel (for selecting sequence of duty – standby pumps)
7.4.2.3.6 MIMIC
The Central MIMIC including annunciator panel shall be provided to meet the requirements
of entire pumping station and WTP. The MIMIC which shall be approximately 2 m x 1 m
shall comprise of following:
7.4.2.3.7 A MIMIC providing a colour representation of the Plant Flow Diagram WTP
dynamic status.
7.4.2.3.8 Physical displays of measured values of levels, flows, totalized flows etc.
7.4.2.3.9 An alarm matrix for displaying general fault alarms.
All the alarms shall be provided in alarm annunciation in the identified windows of area of
fault.
7.5 Instrumentation and Control System
7.5.1 Instrumentation System
The offered system shall provide all the necessary protection devices to protect electrical
equipments. The scraper mechanism, turbine mixers etc. shall be provided with electronic
type torque overload devices to trip the drive to ensure safety of the equipment. The
195
Arrangement shall include necessary electronic speed monitoring equipment for monitoring
the movement of equipment and shall give alarm in the event of stoppage.
All the tanks level shall be measured using ultrasonic level sensors / transmitters. As
detailed in process description necessary flow monitoring instruments shall be provided and
all these transmitters to be integrated with PLC for monitoring and interlocking.
Contractor shall provide a list of equipments / instruments proposed for approval giving
details of instrument / equipment, numbers, location etc. in a format as indicated in Table - 1
below.
TABLE - 1
SAMPLE FORMAT FOR INSTRUMENT LIST
Sl. Type of Instrument Area of Plant Location Quantity
No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
…..
196
However in PLC mode of operation status of all the drives and instrumentation system shall
be available in PLC and SCADA.
SCADA shall be capable of generating the shift report for Production, Inputs, and Power
Consumed etc. in each of those feeders provided with KWH meters. The system shall
include required tools for routine maintenance.
The instrumentation system proposed shall be state of the art type and shall give full
information on;
1. The level switches with back up switch and both these switch status shall be compared
and faulty switch indication shall be provided for maintenance purpose.
2. All the flow transmitter indications shall be made available on MIMIC panel as well as
on PLC.
3. All the pumping station sumps shall have level measurement instruments to monitor
the level of water. All pumps shall be controlled based on liquid levels in the sumps.
The hardwired protection shall be provided for all pumps against dry run based on Low
Level switch.
4. Monitoring systems shall be provided at critical locations to detect flow stoppages etc.
The stoppages if any shall raise alarms indicating the same.
The entire field I/O from field instruments shall be interfaced with PLC for control / monitoring
functions. Typical I/O per device as a minimum shall be 6 inputs and 4 outputs or as required
if it is more than the minimum specified above.
7.6 PLC Data Sheet
The configuration and specifications for PLC shall be as detailed in Table - 2 below.
TABLE – 2
197
Sl. Description Required
No.
6. Isolation Optical
7. Isolation voltage 1500 V AC for 1 minute
C) Digital Output Module
1. No. of Channels / Module 16 /32 / 64
2. Interrogation voltage 24 V DC
3. Output rating for each channel 2 Amps. (if not
interphasing relays to be
4. Response Time 1.2 m sec.
5. Built in protection
Against over voltage
Against overload and short circuits Yes
Against Polarity Reversal
6. Isolation Optical
7. Isolation Voltage 1500 V – AC for 1 sec.
D) Analog Input
1. Number of channels / Module 8 / 16
2. Operating range 4 - 20 m Amp.
3. Isolation Optical
4. Analog / Digital conversion 12 bits
5. Real time Fast scan 3 x (No. of channels + 1)
6. Isolation voltage 1000 V rms
7. Maximum over voltage / over current 30 V Voltage
30 m Amps
8. Standard IE C 1131
E) Analog Output
1. No. of channels / Module 8
2. Operating range Multi-usage 4 - 20 m Amp
3. Conversion time 5 m sec.
4. Isolation voltage 1000 V rms
5. Type of protection Short circuit and overload
6. Standard IE C 1131
201
7.7.1.7 all analogue displays shall be of the digital type with no moving parts utilizing back lit
liquid crystal diode LCD / LED technology
7.7.1.8 Instrumentation shall utilize solid state electronic technology and avoid the use where
practical of any moving parts;
7.7.1.9 Instruments shall have minimum maintenance requirements
7.7.1.10 Instrumentation shall resume operation automatically on the application of power
following a power failure
7.7.1.11 Air conditioned room shall be provided for all PLC panels.
Analogue instrumentation systems shall be provided to monitor the parameters and digital
systems shall be provided as necessary for the efficient and safe operation of WTP
Instrumentation sensors shall be suitable for the environment in which they are expected to
work. Sensor located in hazardous (flammable) or potentially hazardous atmospheres shall
be certified for use in these areas.
Instrumentation converter units shall where practical be located in the associated MCC
common control panel well away from any injurious effects of the process.
202
PART C - PLANT MATERIALS AND WORKMANSHIP
1.1 Introduction
This part of the Specification sets out the minimum standards of materials, workmanship and
design to be used by the Contractor and reference to any specific material or equipment
does not necessarily imply that such material or equipment is included in the Works. All
component parts of the Works shall, unless otherwise specified, comply with the provisions
of this Chapter or be subject to the approval of the Engineer.
Except where otherwise specified all materials and workmanship shall comply with the
current national standards of the country of manufacture provided that these standards are
not less stringent than the equivalent specified Bureau of Indian Standards IS), British
Standards or Codes of Practice or that they comply with the requirements of the International
Standards Organization (ISO) or the International Electro technical Commission (IEC) as
appropriate. The Contractor may be asked to make copies of relevant standards available to
the Engineer or the Engineer‘s Representative, together with, if necessary, English
translations. He shall provide these as requested for prior assessment and for use during
inspection and testing. Reference is made in this section to the Standards listed below.
The Works as a whole shall be new, of sound workmanship and robustly designed for a
long, reliable operating life and shall be capable of continuous operation for prolonged
periods in the climatic and working conditions prevailing at the Site, with the minimum of
maintenance. The design shall take account of temperature changes, the stability of paint
finish for high temperatures, the rating of engines, electrical machinery, thermal-overload
services, cooling systems and the choice of lubricants for possible high and prolonged
operating temperatures. The Contractor shall be called upon to demonstrate this for any
component part, either by service records or evidence of similar equipment already installed
elsewhere or relevant type tests.
The Plant shall be designed to provide protection against damage by the entry of vermin and
dust, and to minimise fire risk and consequent fire damage. It shall be protected against
damage due to dampness and condensation. Plant shall operate without undue vibration,
and parts shall be designed to withstand the maximum stresses under the most severe
conditions of service. Materials shall have a high resistance to change in their properties due
to the passage of time or any cause which may have a detrimental effect upon the
performance or life of the Works.
The Plant shall be designed to have a high resistance to change in its operating
characteristics due to passage of time or any other which may affect the performance or life
of the Works. The Contractor may be called upon to demonstrate this for any component
part either by service records of similar equipment, or by the records of extensive type tests.
Materialsshallbeselectedtakingintoconsiderationtheirlocationandduty.ForPlantin
203
Contact with water, the risk of electrolytic reaction between differing materials of construction
and to the effects of corrosion and erosion shall be taken into account.
The plant shall be designed to provide easy access for replacement of component parts
which are subject to wear, without the need to replace whole units. Except for consumable
items requiring frequent replacement, no part subject to wear shall have a life from new to
replacement or repair of less than five years. Where major dismantling is unavoidable to
replace a part, the life shall not be less than ten years.
Substances and products used in the Works which may be in contact with water which is to
be supplied for drinking, washing or cooking shall not contain any matter which could impart
taste, odour, colour or toxicity to the water or otherwise be objectionable on health grounds.
All substances and products so used shall meet the requirements of Regulation 25 of the
Water Supply (Water Quality) Regulations 1989 or the Water Supply (Water Quality)
(Scotland) Regulations 1990 or other equivalent body as applicable / relevant IS standards.
1.5 Workmanship
Workmanship and the general finish of plant installations shall be of first-class commercial
quality and in accordance with the best workshop practice, and shall be performed by
persons skilled in their respective trades.
Pipe work, fittings, cables, cable trays and the like shall be fitted in a neat, straight and
symmetrical manner so as to present a pleasing appearance. Indicating gauges fitted to
machine assemblies or control panels shall generally be of similar style and grouped
together.
External welds and flame cuts shall be finished smoothly by grinding. Chequer plate
coverings shall be fixed squarely in their frames with their patterns properly aligned. Hand
railings shall be free from burrs.
1.6 Welding
Where welds may be highly stressed, the Contractor shall supply to the Engineer before
welding starts detailed drawings of all weld preparations and procedures proposed. No
welding shall be carried out before the Engineer has approved the procedures. No alteration
shall be made to any previously-approved procedures without prior approval of the Engineer.
The use of organic materials shall be avoided as far as possible but where these have to be
used they shall be treated to make them fire resistant and non-flame propagating.
Fabrics, cork, paper and similar materials which are not subsequently to be protected by
impregnation shall be treated with a fungicide. Sleeving and fabrics treated with linseed oil
varnish are not acceptable.
The use of wood shall be avoided as far as possible. If used, woodwork shall be thoroughly
seasoned teak or similar hardwood which is resistant to fungal decay and other blemishes.
All woodwork shall be treated to protect it against damage by any cause. All joints in
woodwork shall be dovetailed or tongued and pinned. Metal fittings on wood shall be non-
ferrous Adhesives shall be impervious to moisture and fungus growth. Only synthetic resin
cement shall be used for joining wood.
204
1.8 Gaskets and joint rings
1.9 Vibration
All rotating elements shall be dynamically balanced so that the level of vibration at any point
on any Plant item when operating at Site, either singly or with other Plant, and at any speed
throughout the operating range, shall be within the limits of Class IV, grade B, as defined in
ISO 10816-1:1995 / relevant IS codes.
Pipe work, valves and other connected equipment, or forming part of the operating system,
shall be provided with adequate supports, brackets and fixtures, as necessary, to restrict any
induced vibration to a minimum, under any operating condition.
Vibration measurements shall be taken on site by the Contractor at various points on each
complete machine as defined above.
Measurements shall also be taken on connecting plant. If any item is found to be vibrating
beyond the level considered by the Engineer to be a reasonable minimum, the Contractor
shall reduce the vibrations to the required level.
The Contractor shall provide adequate access to all Plant items to which access is
necessary for routine maintenance and operation. The principal ladders, platforms, covers
and handrails to be supplied and fixed shall be as per approved drawings.
Any small areas of chequer plating or other covering needed to cover gaps between items of
Plant and the surrounding structure, and any access ladders, platforms and handrails that
must be attached to items of Plant to facilitate operation, inspection or maintenance, shall be
supplied and erected by the Contractor.
Handrails shall consist of double ball forged steel standards with tubular rails, hot-dip
galvanized in accordance with BS EN 729-1:1995 / relevant IS codes. Chequer plating shall
be of ‘Durbar‘ or other non-lip pattern, not less than 4.5mm thick (exclusive of pattern) and
hot-dip galvanized after fabrication in accordance with BS EN 729-1:1995 / relevant IS
codes.
Diamond type pattern chequer plate shall not be used. Open-type or solid-type chequer plate
flooring shall be used as appropriate for the location, taking into account ease of cleaning,
precautions against slipping and areas below walkways.
205
1.11 Machinery, lifting and dismantling
Machinery bedplate design, packing and fixing shall minimise distortion and vibration.
Aligned machinery shall be mounted on bed or sole plates, permitting removal and
reinstatement without a requirement to re-grout. Bedplates shall incorporate fine adjustment
of the vertical and horizontal alignment between driver and driven Plant. All machinery shall
be fitted with lifting facilities. Large structures shall be provided with jacking points. For Plant
subject to frequent dismantling, tapped holes or other provision shall be made in all main
castings, for the insertion of jacking screws or the fixing of drawing gear. Bolts or studs shall
be used in preference to setscrews.
1.12 Bearings
The Contractor shall select the most appropriate type of bearing for the Plant being supplied.
Single journal plain bearings shall be phosphor bronze or synthetic lubrication impregnated
bushes with carbon or stainless steel journals respectively. Synthetic bearings shall be used
only where bearing condition can be inspected readily.
Plain-type bearings shall be self-lubricating either by grease, forced oil or impregnation. Ball
and roller type bearings shall be adequately lubricated by oil or grease and sealed to prevent
leakage of lubricant along the shaft. The dismantling of bearings shall be simple and free
from risk of damage. Bearings fitted to gearboxes shall have a minimum design life of 100
000 hours at maximum loading.
1.13 Gearboxes
Gearboxes shall have a life of 100 000 hours, be selected in accordance with American
Gearbox Manufacturers ‘Association recommendation / relevant IS codes for horsepower
and service factor application. They shall employ a standard reduction ratio. Gearboxes
which have to be angle-mounted shall have a rating, choice of bearings, seals and
lubrication system designed for such mounting. Dependence on splash lubrication alone is
not acceptable but it may be used in conjunction with a forced-feed method to reach all
bearings and gears.
2 PAINTING ANDPROTECTION
2.1 Scope
Protective coatings shall comply with BS 5493:1977 ‘Code of practice for the protective
coating of iron and steel against corrosion’ / relevant IS codes except as otherwise specified.
For coatings designed to BS 5493:1977 exterior conditions shall be assumed to be ‘polluted
inland‘ conditions and the interiors of buildings shall be assumed to be ‘frequently damp or
wet‘ except for control rooms. The thickness of coatings stated in this section of the
specification is the minimum allowable thickness as defined in Clause 19 of BS 5493:1977 /
relevant IS codes. Where the paints that are available do not provide dry-film thickness as
specified, additional coatings shall be applied. Protective coatings for surfaces of tanks and
other plant in contact with chemicals or otherwise in conditions not foreseen in this section of
the specification or in BS 5493:1977 / relevant ARE codes shall be suitable for those
conditions. They shall be the subject of design submissions supported by evidence proving
satisfactory experience of the proposals elsewhere. Where dissimilar metals are in contact,
the Contractor shall provide insulation to prevent electrochemical corrosion.
2.2 General
The protective coating system shall have a minimum 10-year life to first maintenance.
206
A five year minimum performance warranty shall be given in respect of the paint as applied.
All coatings applied to any part of the plant in contact with water to be used for drinking,
washing or cooking shall be non-toxic, non-carcinogenic, shall not impart taste, odour, colour
or turbidity to the water or foster microbial growth and shall be approved in the same manner
as substances and products in relevant Clause 1.4. No manufacturer‘s name-plate
identification, vented filler plugs in gearboxes or grease nipples shall be painted over.
All machined, polished or bright surfaces shall be given suitable protection against corrosion,
damage and deterioration.
The Contractor shall ensure that, before dispatch from the manufacturer‘s works and after
completion of erection, all plant has received suitable preparation followed by the protection
system listed in tables A and B attached.
The Contractor shall liaise closely with the plant manufacturer who shall provide full facilities
for him to inspect and check the preparation and painting during all stages. The Contractor
shall report on his inspections to the Engineer.
All paint materials shall be stored and applied strictly in accordance with manufacturers
‘instructions.
Paint shall not be applied under adverse conditions. Air temperatures shall be above 5°C
and relative humidity less than 55% or as otherwise specified by the paint manufacturer.
The Contractor shall ensure that, for the materials specified, application conditions are in
accordance with the specification and manufacturer‘s instructions. Paint shall be applied only
to surfaces that have been cleaned and prepared in accordance with these instructions.
Where local climatic conditions make the specified requirements difficult to achieve, the
Contractor shall provide temporary protection during painting.
The dry paint-film thickness shall be measured by Elcometer or other approved method. All
manufacturing processes shall be complete prior to galvanizing with all erection markings
clearly legible afterwards. Surfaces shall be adequately degreased before the application of
any coating, pre-treated with a brush application of etches primer or T wash.
Steel subject to hydrogen embrittlement through galvanizing shall not be used. All iron and
steelwork to be painted shall be blast cleaned to all parts of BS 7079 Second Quality /
relevant IS codes to achieve a surface profile with a minimum amplitude of 0.025 mm and a
maximum of 0.100 mm.
Following blast cleaning, steel surfaces shall be zinc metal sprayed where specified.
Aluminium structures and fittings shall need not be painted.
All fabricated steel pipe work and other Plant where specified, shall have a lining and
coating, not less than 250 microns thick, of 100% solids, thermosetting fusion-bonded, dry
power epoxy coating.
207
All grit and dust shall be removed and coating shall be started before formation of visible
oxidation of the surface. The metal shall be pre-heated to a temperature recommended by
the manufacturer and the epoxy powder applied by immersion in a fluidized bed, after which
excess powder shall be removed. The powder shall be allowed to flow out completely before
curing. The thickness of the coating, including any repaired areas, shall be checked with a
calibrated tester. Spark testing, for pinholes, voids, contamination, cracks and damaged
areas, shall use a high-voltage spark generator.
Enclosures shall be given protective coating at the place of manufacture and before
installation of any electrical fittings. Electrical panels, including switchboards, control panels
and instrument panels, installed within buildings shall be prepared as follows:
(i) Thoroughly clean surfaces to remove rust, scale, dirt, loose paint and the like and
degrease by the use of solvents which are compatible with the paint finish to be applied. If
rust-proof steel has not been used in the construction, the surfaces shall be treated with a
passivating agent such as phosphoric acid.
(ii) Internal surfaces shall have a minimum of three coats of paint of which the first shall be
an approved priming coat. The final coat shall be opaque gloss white enamel.
(iii) External surfaces shall have a minimum of five coats of paint of which the first shall be
an approved priming coat, the second and third a suitable undercoat, all of which shall be
rubbed smooth when dry before application of the next coat. The colour of undercoat paints
shall be different from priming and finishing coats.
(iv) The final coats shall be of stove enamel paint to a finish and colour as specified in Table
C. The dry-film thickness shall be not less than 100 microns. Electrical panels which are to
be installed in exposed positions or in damp conditions shall receive a surface preparation
containing zinc prior to application of the primer undercoat and finishing coats. A 500 ml tin
of matching touch-up paint shall be supplied with each panel.
2.5 Defects
The Contractor shall ensure that all coatings are free from defects and adequate in all
respects for the purpose intended.
(a) after painting, damage has been caused by handling, impact, abrasion or welding;
(b) any portion of the paint film separates from any other or the parent metal;
(c) After painting the total dry-film thickness is less than that specified.
208
Failure shall not include:
Unless otherwise specified, colour coding for plant, equipment and pipe work shall be as
given in tables C to G. Steel pipes shall be painted and hoses and thermoplastic pipes shall
be colour banded in accordance with BS1710 / relevant IS codes. When using colour bands
on thermoplastic pipes the Contractor shall ensure that the adhesives used on colour bands
do not contain agents which will cause deterioration of the pipes. Colour bands shall be
applied on straight lengths of pipes at no more than 3 m spacing. Bands shall be applied, at
all junctions, both sides of valves, Plant, fittings and wall penetrations.
Finishing coats shall be applied as specified in the colour schedule in accordance with the
requirements of BS 1710:1984, BS 4800:1989, BS 5252:1976 and BS 5499-5:2002 /
Relevant IS codes. Pipeline contents shall be identified by name and the direction of flow by
arrows. Where two or more pipes in a duct or gallery convey the same fluids, each pipe shall
display a separate number, with contents named at each point of entry or outlet.
TABLE A
REQUIRED COATING SYSTEMS AND MINIMUM COATING THICKNESSES FOR PLANT AND EQUIPMENT
Applied prior to delivery and erection Applied
following
Pre treat Second installation
Substrate First coat Third coat
ment coat
ABOVE
WATER Etch
Steel Zinc
LEVEL: prime High-build High-build
(galvanized) phosphate
Machinery & or T wash chlorinated chlorinated
CR
steelwork not in rubber rubber
alkyd primer
contact with paint paint
Steel zinc undercoat
sewage, sludge Etch (0.075mm) (0.075mm)
sprayed (0.050mm)
or water to be used prime
for drinking, (0.070mm)
washing or Zinc Zinc
cooking Blast phosphate phosphate High-build
Steel,
clean CR CR chlorinated
cast iron,
BS7079 alkyd blast alkyd blast rubber
ductile iron nd
2 quality primer primer (0.075mm)
(0.050mm) (0.050mm)
BELOW
WATER Etch
Steel
LEVEL: prime
(galvanized)
Machinery and or T wash
Epoxy Epoxy Epoxy
steelwork in primer primer primer
contact with Steel,
cast iron, high-build high-build high-build
water to be used (0.125mm) (0.050mm) (0.075mm)
ductile iron Etch
for drinking,
zinc prime
washing or
cooking sprayed
(0.070mm)
Pipe work Steel As specified elsewhere
Switchboard
shells, frames Steel As specified elsewhere
and back
209
TABLE B
REQUIRED HEAT – RESISTANT COATING SYSTEMS FOR STEELWORK
Working A1: Surface
First coat Second coat Third coat
temperature treatment
Polyvinyl Butyral Aluminium heat Aluminium heat
Blast clean BS (0.025mm) resistant resistant
50°C to 175°C 7079 Zinc chromate @ 200°C @ 200°C
second quality Primer (0.012mm – (0.025mm) (0.025mm)
15mm)
175°C to 500°C Aluminium
Aluminium
Blast clean BS pigmented
pigmented silicone
7079 silicone
heat-resistant
second quality heat-
(0.025mm)
resistant
NB A minimum temperature of 350°C within a short time after application is required
TABLE C
COLOUR CODING FOR PLANT AND EQUIPMENT
BS 4800 shade
Equipment Colour finish
number
Above water Green --- 12–D–45
Pumps and
level: Machinery
machinery --- Saxe blue 18–C–39
and steelwork
not in contact with Dry-well motors Tangerine Tangerine 06–E–51
sewage, Gearboxes Saxe Blue Saxe blue 18–C–39
sludge or potable Compressors &
Blue Blue 24–E–51
water or specified blowers
as Lifting gantries Gorse Gorse 08–E–51
requiring Valves & pipe work Green --- 12–D–45
identification above FFL --- Pale grey 00–A–05
as table D Pipe work below
below Black Black 00–E–53
FFL
Below water level: Machinery and
steelwork (including pumps, penstocks, Black Black 00–E–53
pipe work and the like)
Switchboard shells Light semi grey Light semi grey
18–B–17
gloss gloss
Switchboard supporting frames 00–E–53
Black semi gloss Black semi gloss
Switchboard internal equipment mounting 00–E–55
White semi gloss White semi gloss
plates
Control and instrument panels -external Light semi grey Light semi grey
18–B–17
gloss gloss
Control and instrument panels -internal White gloss White gloss 00–E–55
GRP covers (pigmented) Spruce Spruce 14–C–39
TABLE D
IDENTIFICATION COLOURS FOR PIPES
All pipes are to be identified in accordance with BS 1710
Basic identification Colour BS 4800 shade no.
Drinking water Green
Steam Silver grey
Mineral, vegetable and animal oils combustible liquids Brown
Diesel fuel Brown
Gases in either gaseous or liquid defined condition (except air) Yellow ochre
Acid and alkalis Violet
Air Blue
Other liquids Black
Electrical services such as conduits & trunkings Tangerine
210
TABLE E
IDENTIFICATION COLOURS FOR PIPES – HYDRATED LIME
Steel pipe work carrying hydrated lime slurry shall be painted black, colour code 00E53 with
banding. Pipe work conveying hydrated lime slurry shall be banded with vinyl laminated
identification tape to enable individual lines to be identified throughout their length. The
banding shall conform to BS 1710 to indicate the fluid conveyed and shall have flow direction
arrows, lettering and codings as described below.
(a) Lettering
Duty Lettering Colour
Slurry "LIME" White
Service Water Not applicable -
Waste Water "DRAIN" White
(b) Banding
Duty Coded
Slurry violet -da
Service water green Waste
water black
Individual bands shall be 50mm wide. Bands for slurry lines shall incorporate danger warning
markers (black/yellow diagonal stripes) 50mm wide giving a composite width of 150mm.
TABLE F
IDENTIFICATION COLOURS FOR PIPES – ALUMINUM SULPHATE
Pipeline shall be banded with vinyl laminated identification tape to enable individual lines to
be identified throughout their length. The banding shall conform to BS1710 to indicate the
fluid conveyed and shall have flow direction arrows, lettering and codings as described
below:
(a) Lettering
Duty Lettering
Aluminium sulphate "ALUM"
Dilution water not applicable
Wastewater "DRAIN"
(b) Banding
Duty C
Aluminium sulphate V
Dilution water G
Wastewater B
211
Danger markers shall consist of black/yellow diagonal stripes overall width of individual or
composite bands shall be 150mm.
Colour Code
Violet 22C37
Green 12D45
Blue (auxiliary) 18E53
Yellow 08E51
Black 00E53
White 00E55
TABLE G
IDENTIFICATION COLOURS FOR PIPES – MISCELLANEOUS
Sample lines:
Pipe work conveying sample water shall be banded with vinyl laminated identification tape to
enable individual lines to be identified throughout their length. The banding shall conform to
BS 1710 to indicate the fluid conveyed and shall have flow direction arrows, lettering and
codings as described below.
(a) Lettering
Duty Lettering
Sample "SAMPLE
Wastewater "DRAIN
Note that the approved sample designation for each line is to be substituted for
"XXX".
(b) Banding
Duty C
Sample G
Wastewater B
Colour C
Green 12
White 00
Black 00
Pipe work conveying air shall be identified throughout its length in accordance with BS1710 /
relevant IS codes. For steel pipe work, the finish colour of the protective coating system
generally shall be the basic identification colour, blue 2O-E-51 to BS4800. Where this is
precluded by use of high temperature paint finishes and/or the application of thermal
insulation and cladding, then banding shall be applied in appropriate materials. The banding
shall be 150 mm wide and in the same basic identification colour. For non-steel pipe work
such as instrument air supply branches, identification shall be by means of banding
generally as above except that the width of banding shall be limited to 50mm.
212
PART D - PIPELINE WORKS STANDARD SPECIFICATION
SCOPE
This specification covers the general requirements for supply, fabrication, delivery at site
laying, jointing, testing and commissioning of all welded M.S pipeline, appurtenances,
specials etc. above/below ground, including Civil works required for the same.
The following specifications, standards and codes are made a part of the specification. All
standards, tentative specifications, specifications, codes of practice referred to herein shall
be the latest editions including all applicable official amendments and revisions. In case of
discrepancy between this specification and those referred to herein, this specification shall
govern.
213
24. IS : 1182 Recommended practice for Radiographic examination of Fusion - Welded
Butt Joints in steel plants
25. IS: 2595 Code of Practice for Radiographic Testing.
26. IS : 3658 Code of Practice for Liquid Penetrate Flaw Detection
27. IS: 5334 Code of practice for Magnetic Particle Flaw Detection of welds.
28. ASTM E 94 Guide for Radiographic Testing
29. ASTM E 709 Guide for Magnetic Particle Examination.
30. ASTM E 165 Test Method for Liquid Penetrate Examination.
31. IS : 3600 Methods of Testing Fusion Welded Joints and weld metal in steel(Parts 1 to
9)
32. IS: 4853 Recommended Practice for Radiographic Inspection of Fusion Welded Butt
Joints in Steel Pipes.
33. IS : 3589 Seamless or Electrically welded steel pipes for Water Gas and Sewage
(168.3 to 2032 Outside Diameter)
34. IS : 6631 Steel pipes for Hydraulic Purposes
35. IS : 7343 Code of practice for ultrasonic Testing of Ferrous Welded Pipes and
Tubular Products
36. IS : 2598 Safety Code for Industrial Radiographic Practice
37. IS : 5822 Code of Practice for Laying of Electrically Welded steel pipes for water
supply
38. IS: 1608 Mechanical testing of Metals.
39. IS: 9595 Metal Arc welding of Carbon and Carbon-Manganese Steels.
40. IS : 2825 Code of unfired Pressure Vessels
41. IS:5504& IS:3589 Code for SW PIPES
42. IS: 10748 Requirement for Wieldable Hot Rolled Carbon Steel Strip uncoils.
43. IS 10234: Recommendation for radiography for general pipeline welding.
44. API-1104 Welding of pipeline & related facilities
1.3 MATERIALS
Steel Coils - The steel Coils for pipes, fittings, specials and stiffeners shall be of mild
steel conforming to IS: 10748 grade III and shall bear ISI mark
Welding Consumables - such as electrodes, filler rods and wires shall conform to IS:
814,IS 3613, IS : 6419 and IS :7280
Before fabrication of pipes and specials/fittings is commenced, the copies of the mill sheets
and the manufacturer's test certificates for Coils and other materials required forth
fabrication, shall be submitted by the Contractor to the Engineer for his approval.
When requested by the Engineer, the Contractor shall supply free of charge to the
Employer, for testing suitable samples of the materials to be used/used in the Works.
The cost of such tests shall be borne by the Contractor and shall be included in his quoted
rates.
1.4 INSPECTION
1.4.1 All works and material under specification will be rigidly inspected during all phases of
manufacture and testing and such inspection shall not relieve the Contractor of his
responsibility to furnish materials and performed work in accordance with this
specification.
1.4.2 The Contractor shall notify the Engineer, in advance of the production of materials
and fabrication thereof, in order that the Employer may arrange for mill and shop
inspection.
214
1.4.3 The Engineer may reject any or all materials or works that do not meet with any of the
requirements of this specification. The Contractor shall rectify or replace such
rejected material/performed work at his own cost, to the satisfaction of the Engineer.
1.4.4 The Engineer shall have free access to those parts of all plants or any other premise
sand sites that are concerned with the furnishing of materials or the performance of
work under this specification.
1.4.5 The Contractor shall furnish to the Employer's inspector reasonable facilities and
space without charge for inspection, testing and obtaining of any information he
desires in respect of the character of material used and the progress and manner of
the work.
1.4.6 The Contractor shall supply free of cost required specimen of materials for testing by
the Owner at any time during the progress of work and shall bear the cost of all such
tests or retests to the satisfaction of Engineer.
1.4.7 The Contractor shall provide 2 (two) sets of accurate `Go' and `No Go' ring gauges to
measure the diameter of pipes specials and fitting for the use of the Engineer at no
extra cost.
1.5.1General
1.5.1.1 All pipes and specials shall be manufactured as per IS: 3589 out of new mild steel
HR Coils (IS: 10748 grade-III) which shall be free from any cracks, surface flaws,
laminations, excessive fittings or any other defects. The pipes shall be truly
cylindrical, and straight in axis. The ends shall be accurately cut and prepared for
field welding.
The external circumference of the pipe pieces which are to be fixed adjacent to flange
adapter with fixed outer diameter shall not deviate from theoretical one by more than
1mm.To obtain this accuracy the pipe shall be rolled several times, if necessary, as pipe
pieces should be truly cylindrical. The external longitudinal welding of this pipe shall be
ground smooth flush with surface to the satisfaction of the Engineer, for a length of 200mm.
No extra cost shall be charged by the Contractor for this grinding work. However, the pipe
shall be manufactured as per tender specification.
The permissible stress in the pipe shell shall be related to yield stress (fy) of pipe material
making due allowance for weld efficiency of the joint.
i) Working stress for combined bending and direct tensile stress shall not exceed 60%of
yield stress of the material making due allowance for efficiency of welded joint (as per
IWWAM-1).
ii) Working stress for combined bending and direct compressive stress shall not exceed 50%
of yield stress making due allowance for weld efficiency (as perIWWAM-1).
215
iii) It is also necessary to check the shell thickness for adequate factor of safety against
failure by buckling (as per IWWAM-11).
For field welded joint, efficiency factor of 80% is generally adopted, while for shop welding
joint 90% efficiency is allowed (as per IS 5822 ).
1.5.2 Fabrication
1.5.2.1 The Contractor shall get the fabrication work done in a duly valid licensed factory of
his own or that of an approved nominated sub-contractor. This factory meant for
fabrication of pipes, specials etc. shall also be involved with testing etc., machining
as well as painting. For completing the work under the present contract within the
contract period, the factory shall be equipped with adequate number of various
equipment and plant such as:
1.5.2.2 The factory shall have adequate area, and shall also have stacking yard for the
stacking of Coils, structural, fabricated pipes etc. and the scrap.
1.5.2.3 The Bidder may establish pipe fabrication factory within the project site for
minimizing the transportation of pipes after fabrication to bring the pipes to the
trench where pipes are to be laid. Contractor shall furnish with his bid the details of
the factory where he intends to get the fabrication done, such as its location within
the project site and the equipment, plant and other facilities available in the factory
for the manufacture of M.S.Pipes and special required under this contract.
1.5.3 Cutting Coils or from Coils rolled as coil to the required sizes.
1.5.3.1 The Coils shall be indented in such length as to have minimum wastage and so as
to make the pipe as far as possible.
1.5.3.2 Before cutting, all the edges of the Coils shall be cleaned by brushing/grinding on
both the sides.
1.5.3.3 After the Coils are cut, the edges shall be made smooth and even by polishing with
an electrical or pneumatic grinder to remove all inequalities. Care shall be taken to
see that the cut edges of the plate are perfectly straight. Jigs to be used for this
purpose shall depend upon the types of cutting machine used. The Coils cut to the
required shape shall be checked for correctness before they are rolled into pipe
drums. If any corrections are required, the Contractor shall do the same by re-
cutting, if necessary.
216
1.5.3.4 Rolling of Coils
1.5.3.5 The Coils prepared as mentioned above are cut to the exact size shall be put into
rolling machine to form a pipe of the required diameter as under:
The Contractor shall adjust the rolling machine so as to give a uniform curvature to the
pipe throughout its circumference.
The curvature obtained shall be checked by the Contractor's foreman during the process
of rolling and if proper curvature is not obtained at any place including the ends, the rolling
operation shall be repeated at this stage
Heating of Coils to obtain the desired curvature shall not be permitted.
1.5.4Welding
1.5.4.1 All components of a standard shell, either straight or bent etc. shall be welded,
wherever possible by use of automatic arc welding machine by Submerged Arc
welding process with alternating current. Generally hand welding shall not be
permitted except specific cases, where it is absolutely necessary. This should be
done in consent with clients representative. Hand welding shall also not be
permitted except for sealing runs and such other minor works at the discretion of
the Engineer-in-charge. The strength of the joint shall be at least equal to that of
the parent material.
1.5.4.2The Contractor shall use electrodes of client approved make and size, the size
depending on the thickness of coil and the type of joint. It shall also be used with
standard current and arc voltage required for the machine in use with such
modifications as may be found necessary after experimental welding. For this
purpose, samples of welded joints shall be prepared and tested in the presence of
the Engineer. The values once determined shall be maintained throughout the work
and if any modifications are to be made, a written permission of the Engineer shall
be obtained. In the case of thin sheets, electric arc welding may not give
satisfactory results and gas welding shall be resorted to. Gas welding shall be
subject to the same specifications and tests as those for electric welds. Welding
should be carried out inside as well as outside.
1.5.4.3All the shop and field joints shall be welded, all welding shall conform to the
requirements of IS 9595 and IS4353.
1.5.4.4 All circumferential joints shall be double welded butt joints. Field joints shall be from
outside, with a sealing weld from inside. End preparation for such welding shall
conform to IS: 2825.
1.5.4.5 All circumferential welds involving Coils of unequal thickness shall be so kept that
the inside surfaces of Coils match to provide stream lined joints without alteration in
the internal diameter. As far as practicable, welding of dissimilar thickness of shells
shall be carried out in the shops.
1.5.4.6 The welding shall be of the best workmanship free from flaws, burns, etc. and the
Contractor shall provide for his own electrodes and equipments, ovens to keep the
electrodes at the desired temperatures and dry. In order to maintain a good
standard in welding, welders shall be tested by the Contractor with prior intimation
to the client before they are entrusted with the job. Qualification standard for
welding procedures, welders and welding operation shall conform to the
requirements of IS: 7307 and IS: 7310 (latest). Periodical tests as regards their
efficiency shall also be taken at intervals of about 6 months and those found
inefficient shall be removed from the job. Only those who pass the test shall be
posted on the job. If an incompetent welder has already welded some pipes, all
217
welding done by him previously shall be fully checked by X-ray in addition to
the regularX-ray inspections. The defects if any shall be set right to the satisfaction
of the Engineer. All such check tests and rectification of defects shall be entirely at
the cost of the Contractor. No pipes or steel sections shall be erected unless the
work of the welder concerned has been proved to be satisfactory. Specially
selected welders shall do site welds.
1.5.4.7 A record shall be maintained showing the names of welders and operators who
have worked on each individual joint. Hand-welding shall preferably be carried out
by a pair of welders (parallel welding putting two welders at a time both will be
working in diametrically opposite side of the curvature. Welding shall be divided
into 4 quadrants shall be welded simultaneously, so that by observing proper
sequence, distortion can be avoided. A joint entrusted to a particular individual or a
pair shall be as far as possible, completed by them in all respects, including sealing
run. No helper or other unauthorized person shall be permitted to do any welding
whatsoever. In case of infringement of above, the persons shall be punished as
directed by the Engineer.
1.5.4.8 The welded joint after welding should not become brittle or sensitive to blows and
there should be no loss of toughness due to welding or heat treatment. The
material after welding and heat treatment is to be tougher than the base metal and
is to retain its original ductility. No allowance will be made for thinning of weld and
the weld should in no point be less than the nominal thickness of plate.
1.5.4.9 Upon receipt of the order and prior to the start of fabrication, the Contractor shall
submit to the Engineer for his approval the ``welding procedure'' he intends to use
in the shopworn. Similarly, prior to the start of the field welding, procedure for the
field welding must be submitted to the Engineer for his approval. Manual welding
shall be adopted only when machine welding is not possible.
1.5.5.1 For the mild steel pipes manufactured in site factory/workshop, fabricated from mild
steel Coils, 100 % of the each welded joints shall be subjected to ultrasonic test
and15% of the each welded joints shall be subjected to radiography test.
1.5.5.2In case of field joints 15% of the each welded joints shall be subjected to Ultrasonic
and radiography test. In case of failure of joints the contractor shall be required to
carry out radiography of thrice the number of field joints failing during the Ultrasonic
and radiography test. Even after such radiography testing, if any one of the joint
fails, the contractor shall be required to carry out Ultrasonic and radiography of
joints on all field welded joints i.e. 100 % basis. All these testing’s shall be carried
out by the contractor at his own risk and cost.
1.5.5.3 The weld ripples or weld surface irregularities, on both inside and outside shall be
removed by any suitable mechanical process to a degree such that resulting
radiographic contact due to any remaining irregularities cannot mark or be
confused with that of objectionable defect. The radiograph shall be made in strict
accordance with the latest requirements and as per the latest and most efficient
technique either with X-ray or gamma ray equipment.
1.5.5.4 The photographs are to be marked in such a way that the corresponding portion of
the welded seam can be readily identified. All radiographs will be reviewed by the
Engineer to identify the defect and determine those which must be removed.
Defects that are not acceptable shall be removed by chipping, machining or flame
gouging to sound metal and the resulting cavities shall be welded. After
rectification, the joint is tube radiographed again to prove the quality of the repair.
218
The Engineer based on the latest standards prescribed by Indian Standard
specification will judge the radiographs as acceptable or unacceptable.
1.5.5.5All X-ray shall be made with equipment and by personnel furnished by the
Contractor. Films shall be developed within 24 hours of exposure and be readily
accessible at all times for inspection by the Engineer. The Contractor shall provide
for the use of the Engineer suitable X-ray viewing equipment. X-ray films shall be
properly maintained byte Contractor and shall be handed over to the department
on completion of the Contract. All films shall be identified by the No. and chart
prepared indicating location of the joint each X-ray photo represents. In the event
of additional radiographic inspections required of any work associated with the pipe
erection, the Radiographer at the discretion of the Engineer shall perform such
inspection.
1.5.6.1 General
1.5.6.1.1 The Engineer shall assure himself that the welding procedure employed in the
construction of pipes has been qualified. The Contractor shall submit evidence
to the Engineer that the requirements have been met. The Contractor shall
certify that the welding of pipes has been done only by qualified welders and
welding operators and the Engineer shall ensure himself that only qualified
welders and welding operators have been used.
1.5.6.1.2 The Contractor shall make available to the Engineer a certified copy of the
records of the qualification tests of each welder and welding operator. The
Engineer shall have the right at any time to call for and witness tests of
welding procedure or of the ability of any welder and welding operator.
1.5.6.1.4 The reinforcement on each side of all butt welded joints shall not exceed 1.5
mm complete set of radiographs and records as described in IS: 2595 for each
job shall be retained by the Contractor and kept on file for a period of at least
five years.
1.5.6.1.6 Final acceptance of radiographs shall be based on the ability to see the
prescribed penetrometer image and the specified hole.
1.5.6.1.7 The acceptance criteria for radiography of the joint shall be as per IS-10234 or
as per API -1104standard.
219
1.5.7Thermal Stress Relieving Not applicable.
1.5.8Tolerance
1.5.8.1 The shell in the completed work shall be substantially rounded. The difference
between maximum and minimum inside diameters at any cross section shall not
exceed 1% of the nominal diameter of the cross section under consideration
subject to a maximum of10mm.
1.5.8.3 Straight pipes shall have their faces perpendicular to the axis of the section with a
maximum deviation of 2 mm on either side of the plane. Pipe ends shall be beveled
as per IS: 3589. The pipes shall be supplied in length of 10.5 metres to 12.5metres.
1.5.9.1After fabrication, but before application of protective coatings all pipes and specials
shall be subjected to a shop hydraulic test (100%). Standard lengths of pipes shall
be directly subjected to test and non-standard pipe and elbows can be tested as
standard pipe before being cut to size.
1.5.9.3 The Pipeline after laying at site shall be subjected to 100% Hydro testing. The test
pressure shall be 1.5 times working pressure or 6 kg/cm2 whichever is higher. The
pressure shall be maintained for a period of 24 hours. The length of pipe for hydro
testing shall be generally 5 km as directed by Engineer-In-Charge.
1.5.9.4Each pipe shall be filled with water and the pressure slowly and uniformly increased
until the required test pressure is reached.
1.5.9.5 The pipe to be tested shall be given a serial no. which shall be painted on its inside
together with details such as pipe No. Shell thickness, diameter, length etc. as
directed. It shall be entered in the register to be maintained by the Contractor.
1.5.9.6Prior to testing, the pipe shall be inspected thoroughly and all the apparent defects
in welding such as jumps, porosity etc. shall be repaired by gouge and re-welding.
1.5.9.7 The hydraulic test shall be carried out under cover at the fabrication shop, in the
presence of and to the satisfaction of the Engineer or the inspection agency
appointed by the Employer.
1.5.9.8For indicating the pressure inside the pipe an accurate pressure gauge of approved
make duly tested and calibrated for the accuracy of readings shall be mounted on
one of the closures which close the pipe ends.
1.5.9.10The pipe shall withstand the test without showing any sign of weakness, leakage,
oozing or sweating. If any leak or sweating is observed in the welded joints, the
same shall be repaired by gouging and re-welding after dewatering the pipe. The
repaired pipe shall be re-tested to conform to the specified pressure.
220
1.5.9.11 If any leak or sweating is observed in pipe shell the pipe under test shall be
rejected temporarily. The Contractor shall stack such rejected pipes separately in
his yard. The Engineer shall inspect the same and after taking cuts if necessary,
shall determine the nature of repairs to be carried out thereon and shall then
decide as to how and where they shall be used. No payment shall be made for
handling or carrying out repairs, but, payment for the fabrication and hydraulic
testing of the pipe shall be released only after acceptance of the pipe with
necessary repairs and subsequent testing etc. are carried out by the Contractor to
the satisfaction of the Engineer. The Engineer shall be supplied with two copies of
the results of all the tests carried out. The Mechanical Tests for Pipe material at
Manufacturers work shall be carried as per approved Quality Assurance Plan(
QAP) and tests shall be as perIS:3589
(i) The welded joints at site shall be tested for Tensile test, Bend test & Tre-panned plug in
accordance with procedure laid down in as per the latest edition of IS No.3600 “code of
procedure for testing of fusion welded joints and weld metals in steel”.
(ii) Test pieces shall be taken by the contractors from the welded joints at the position on
fabricated pipes pointed out by the Engineer in-charge.
(iii) The sample so taken shall then be cut to the exact shape and dimensions and machined
as described below and handed over to the Engineer-in-charge for testing. All the work up to
and including machining and arranging for test shall be done by the contractors.
1.5.10.1 The Contractor shall submit to the Engineer a daily progress report in the pro
forma approved by the Engineer, wherein all the details of the work carried out in
the factory shall be fully recorded. Similarly, works done in the various units in the
factory shall be separately mentioned. The Contractor shall maintain a register of
all the finished materials giving dates of carrying out important operations such as
testing, transport, etc. The register shall be presented at least once a week to the
Engineer who shall initial the entries after verification.
MS pipe shall be lined inside with food grade epoxy as per the provisions of IS: 3589
Annexure B.
1.6.1 General
The inside surface of all pipes shall be provided with 12.5 mm thick cement mortar lining in
proportion of 1 : 1.5 by weight, applied by centrifugal spinning method at factory. The lining
shall be in conformity with AWWA C 205. At each ends minimum 6 Nos. of MS rings of 6 mm
diameter shall be welded before lining.
1.6.2 Material
1.6.2.1 Cement
Portland cement shall confirm to the requirements of IS: 269, IS: 1489, IS: 8112. Cement
containing lumps shall be rejected and shall immediately be removed from the lining site.
1.6.2.2 Sand
221
Sand shall consist of inert granular material having hard, strong, durable uncoated grains
confirming to the requirements of IS: 2116. The sand shall be well graded and 100% of the sand
shall pass a US standard sieve number No. 4.
1.6.2.3 Admixtures
A water reducing, set-controlling admixtures confirming to ASTM C 494 may be used to improve
the workability, density, and strength of the mortar. No admixture shall contain injurious amounts
of chlorides. The ratio of admixture to cement shall not exceed that used in the qualification
tests of ASTM C 494. No admixtures shall be used that would have a deleterious effect on
potable water flowing through the pipe line.
1.6.2.4 Water
Water shall be clean, colorless, and free from injurious quantities of organic matter, salt, alkali,
orother impurities that might reduce the strength, durability, or other desirable qualities of the
mortar.
Cement mortar shall be composed of cement, sand and water, well mixed and of proper
consistency to obtain a dense, homogenous lining that shall adhere firmly to the pipe surfaces.
Mortar proportion shall be with 1.5 parts of sand and 1 part of cement by weight. The soluble
chloride-ion (Cl) content of the cement mortar mix shall not exceed 0.15 percent, expressed
as percentage of cement weight. Maximum water / cement ratio shall not exceed 0.45:1.
1.6.4 Mixing
The mortar shall be mixed in batches. The amount of cement and sand entering into each batch
shall be measured by weight. The quantity of water entering the mixer shall be measured
automatically by an adjustable device, or it shall be otherwise measured to ensure that the
correct quantity of water is being added. The mortar shall be mixed long enough to obtain
maximum plasticity and shall be used before initial set.
1.6.5 Equipment
Straight sections of pipe shall be lined by using a spinning machine specifically designed and
built for the purpose of rotating the pipe section and centrifugally applying cement mortar
lining to the interior of steel pipe or by method known to provide equivalent results.
Thickness of inside lining shall be uniform throughout except at joints and other
discontinuities in the pipe wall. Ends of lining shall be left squareand uniform with regard to the
longitudinal axis of the pipe. The lining shall be terminated at 10 to 15 cm at the end of pipe for
joint welding. The lining thickness requirements shall be maintained by mechanical end
retaining rings and verified by physical measurements. Positive tolerance of 3 mm in
thickness is permissible; however, no negative tolerance is allowed.
222
1.6.7 Surface preparation
Before application of the lining, the internal surface shall be cleaned thoroughly. The pipe
interior surface shall be free of oil and grease etc. Loose mill scale, dirt, rust, shall be removed
from the interior surface, so that the surface is thoroughly clean and dry to receive the lining.
When required to prevent distortion or vibration during the spinning, each section of pipe shall be
suitably braced with external or internal supports, appropriate to the equipment to maintain
thecircular shape of pipes. Contractor may provide adjustable steel struts of approved design
for this purpose before application of lining. Minimum two struts at ends shall be provided for
each pipe. The struts shall not be removed till the pipes are laid and jointed. The cost of
providing struts with material and labour required is covered under the item of pipeline and
hence shall not be payable extra.
1.6.8.2 Placement
In application of lining by spinning machine, the entire quantity of mortar required for completion
of the lining of the section of pipe shall be placed without interruption.
The application of lining to MS specials such as bends, reducers, tees, tapers etc, the shape of
which precludes application by the spinning process, shall be done by mechanical / pneumatic
placement or hand application and finished to produce a smooth, dense surface.
Cement mortar for hand application shall be in 1.5 parts of sand and 1 part of cement by weight
and plaster sand confirming to ASTM C 35 shall be used in place of sand confirming to ASTM
C 33. Areas shall be cleaned to remove loose or other foreign matter that would interfere with
the adherence of cement mortar and, if necessary, shall be moistened with water just before the
placing of the cement mortar.
Material and mortar proportion for application of lining at field joints shall be 1 part of cement and
2 parts of sand by weight. The cement and sand shall be dry mixed and moistened with
sufficientwater to permit placing and troweling without crumbling. Inside joints of mortar lined pipe
shall be filled with cement mortar and finished off smooth flush with the inside surface of the
pipe by troweling or by equivalent means. Before placing the cement mortar against the surfaces
of the lining, the surfaces shall be carefully cleaned, have all soap removed, and then be wetted
to ensure a good bond between the lining and the joint cement mortar.
1.6.10Defective lining
All defects in cement mortar lining including, but are not limited to, sand pockets, voids, over
sanded areas, blisters, and cracking as a result of impacts, shall be cutout, and replaced by
hand or pneumatic placement.
223
1.6.11Repairs of defective lining
Small defective areas shall be repaired by manual removal of the defective lining and
reapplication of mortar lining by hand. Defective areas encompassing the full diameterof the
pipe shall be replaced by machine application wherever possible.
1.6.12Lining cracks
Temperature and shrinkage cracks in the mortar lining less than 1.5 mm in width need not
be repaired. Cracks wider than 1.5 mm need not be repaired if it can be demonstrated to the
satisfaction of the BIL that the cracks shall heal autogenously under continuous soaking in water.
The autogenously healing process may be demonstrated by any procedure that keeps the lining
of the pipe continuously wet or moist.
Compression test cylinders or centrifugal test cylinders shall be prepared for testing. A set of at
least two standard test cylinders, 150 mm in diameter and 300 mm in length, shall be made
each day from the cement mortar lining for each shift. Samples may be prepared by omitting
sufficient water from the production mix to obtain a 25 to 75 mm slump. Test cylinders from this
mix shall be made in conformance with ASTM C 31.
Centrifugal spun test cylinders may be substituted for cement mortar test cylinders, at the option
of the manufacturer. The test cylinders shall be spun about their longitudinal axis in 150
mmdiameter by 300 mm long steel moulds at a speed that shall simulate the compaction of
mortar in the lining to produce a spun cylinder wall thickness of approximately 40 mm. The net
cross sectional area of hollow cylinder shall be used to determine its compressive strength.
Damaged cylinders shall not be used.
All cement mortar test cylinders shall be cured with the pipe at the same temperature and for the
same length of time, and shall be tested in accordance with ASTM C 39 in an approved testing
laboratory unless the manufacturer has approved testing facilities at the work site.
Cement mortar test cylinders shall attain a minimum compressive strength of 31 MPa in 28 days
or at the time of dispatch to work site, if less than 28 days.
The average of any 10 successive strength tests of cylinders representing each cement
mortar mix shall be equal to or greater than the specified strength, and not more than 20% of
the strength tests shall have values less than the specified strength. No cylinder test result
shall be less than 80% of the specified strength.
1.7.1 General
The outside surface of the MS pipes and specials shall be provided with reinforced cement
mortar (1:3) coating of 25 mm thickness, applied by mechanical / pneumatic placement at shop /
factory.
224
1.7.2 Material
1.7.2.1 Reinforcement
1.7.2.2 Cement
Portland cement shall confirm to IS: 269 / IS: 8041 / IS: 1489 and IS: 8112.
1.7.2.3 Sand
Sand shall consist of inert materials having hard, strong, durable uncoated grains confirming to
the requirements of IS: 2116.
1.7.2.4 Water
The water used for guniting shall be clean, colorless, and free from injurious quantities of
organic matter, alkali and salt. The maximum water cement ratio shall not exceed 0.45: 1.
The mortar applied by mechanical or pneumatic process shall consist 3 parts of sand and 1 part
of cement by weight. The water in the mixture shall be carefully controlled so that the mortar
shall not run, sag or segregate. The soluble chloride-ion (Cl) content of the cement mortar mix
shall not exceed 0.15 percent, expressed as a percentage of cement weight. Rebound not
exceeding one fourth of the total mix weight may be used as replacement material for fine
aggregate only. Rebound not used within 1 hour shall be discarded.
The outer surface shall be cleaned for oil grease etc. The dust shall be removed by
compressedair or vacuum cleaner before placement of reinforcement. The BRC fabric
reinforcement shall then be placed with required cover on the pipe surface.
1.7.5 Application
The pipe shall be supported on wooden logs at the ends to keep bottom clearance and to
facilitate easy rotation while applying the coating. The mortar coating shall be applied in one or
more continuous applications for achieving required thickness. If applied in more than one
course, the interval between the first and last course shall not be more than 2 hours. The mortar
shall be projected at high velocity against the exterior surfaces of the pipe with a pressure of 2.1
to 2.8 kg / cm2 to produce a hard, tight adhering coating of specified thickness. The coating
shall not be applied on ends of pipes for 100 mm length. Ends of coating shall be uniform and
square to the longitudinal axis of the pipe. The rebound material unused shall be disposed
off within a lead of50m.
The temperature of the cement mortar mix shall not be less than 4° C, nor shall the surface
temperature of the MS pipe be greater than 35° C at the time of placement.
225
1.7.7 Curing
After the initial set of the cement mortar coating has taken place, the mortar coating shall be
cured by the moist curing method. The coating shall be kept continuously moist by intermittent
orcontinuous spraying of water for a period of at least 7days.
If any sand pockets or porous spots occur, they shall be completely cut out and replaced by
mechanical / pneumatic placement or hand application of mortar in proportion of 2 parts of sand
and 1 part of cement, by weight.
Care shall be taken to minimize the occurrence of cracks in the mortar coating. However,
hairline cracks need not be repaired. The cracks, if developed, shall be repaired by brushing
orwiping of neat cement in to the cracks, or painting of the cracks with epoxy coating or a
combination of these methods shall be adopted.
Handling of the mortar coated pipes while transporting those from shop / factory, for laying and
jointing purpose, shall be done very carefully to avoid any damage or development of cracks to
the mortar coating. Any damaged portion shall be cut out and replaced. The pipes shall be laid
in the trenches as early as possible after the curing period is over to avoid hair cracks in the
coating due to temperature variations.
After the welding and testing of the welded joints of MS pipeline, the BRC fabric reinforcement
shall be provided over the joint. Cement mortar used for the joints shall be composed of one
part of cement to not more than two parts of sand, by weight, thoroughly mixed with water to the
consistency of thick cream. Sand shall be graded confirming to the requirements of ASTM C
33, except that 100% shall pass a US standard sieve number16.
Outside field joints shall be coated with cement mortar, retained by suitable water-
impermeable bands or diapers to bridge the joint and retain the cement mortar without
leakage. Before filling, the cement mortar space shall be flushed with water so that the surface
of the joint shall be in contact with the cement mortar shall be moistened when the cement
mortar is poured. The joint shall be filled with cement mortar by pouring from one side only
until the cement mortar reaches at least the pipe spring line on the opposite side, and shall be
rodded with a wire or other flexible rod, or vibrated so that the cement mortar completely fills the
joint recess by moving down one side of the pipe, around the bottom of the pipe, and up the
opposite side. Pouring and rodding the cement mortar shall be continued to allow completion of
the filling of the entire joint recess in one operation. Care shall be taken to leave no unfilled
space. The exposed portion of the grout at the top of the pipe shall be coated with a sealing
compound or covered with burlap or moist earth for curing.
1.7.12Inspection
The tests performed shall be inspected by the Engineer-in-Charge. If any sample fails to meet
the requirements, the Contractor shall be notified immediately. Material affected by the test results
shall be set aside pending final disposition.
226
1.8 EXTERNAL EPOXY PAINTING FOR EXPANSIONJOINTS
1.8.1 General
Unless otherwise specified, the expansion joints shall be epoxy painted externally. The shop
applied painting is to be stopped 150 mm short at each end of pipe to facilitate field welding
and then made up on site following testing of the joint.
The expansion joints shall be painted externally with zinc rich epoxy primer and epoxy paint.
Both in factory and site application is to be done by airless spray equipment. Paints of
reputed make and approved by Engineer-in-Charge shall be used. Thinning or heating of
paints will not be permitted except with specific approval from Engineer-in-Charge and in
accordance with manufacturer’s instructions.
Each lot of primer and paint used by Contractor shall be accompanied by certified copies of
the test results on hardness, impact and heat resistance and resistance to corrosion carried
out by manufacturers in accordance with relevant Indian or International standards.
The priming coat shall be uniform in thickness and free from floods, runs, sags, drips, and
bare spots. Any bare spots or defects shall be recoated with an additional application of the
primer. All defects shall be rectified as per the instructions of the Engineer-in-Charge.
Though the priming coats become touch dry in 10 to 15 minutes, the finishing coats with
epoxy paints shall be applied after allowing the film to cure at least for 48 hours. The final dry
film thickness shall be a minimum of 300 microns. This may be achieved by applying in 2 to
4coats.
On completion of the work, the contractor shall remove any oil stains or paint spots, leaving
the pipe in a clean and acceptable condition.
The entire procedure of applying the paint as specified will be rigidly inspected right from the
cleaning stage to the application of the final coat by the Engineer-in-Charge. If, at any time, it
is found that the procedure of applying the paint or defects noticed, all such painting work
done shall be rectified or redone by the Contractor at his own cost, as directed by the
Engineer-in-Charge.
Samples of the paint brought by the Contractor shall be sent to the testing laboratory for
testing, as directed by the Engineer-in-Charge. If any sample is found to be not conforming
to the specifications, the entire consignment to which the sample may pertain shall be
rejected. Samples shall be taken at intervals at the option of the Engineer-in-Charge. The
entire cost incidental to such testing shall be deemed to be included in the rates quoted by
the Contractor.
227
1.9 TRANSPORTATION AND HANDLING
All pipes and specials manufactured at factory and internally cement mortar lined and
externally gunited in the yard and temporarily stacked in the factory shall be transported
carefully to the work site for laying and jointing.
Any vehicles on which pipes are transported shall have a body of such length that the pipes
do not overhang. Large pipes shall be placed on cradles and the loads properly secured
during transit.
The pipes and specials shall be handled in such a manner as not to distort their circularity or
cause any damage to their coating. Wide non-abrasive or other approved slings shall be
used and hooks and other metal devices shall be well padded. Hooks engaged on the comer
wall surface at pipe ends shall not be used. Steadying ropes shall be employed. The
positions of lifting slings shall ensure that stresses and tendency towards deformation in the
pipes are kept to a minimum.
Pipe handling equipment shall be maintained in good condition and any equipment which in
the opinion of the Engineer-in-Charge may cause damage to the pipes shall be discarded.
Under no circumstances shall pipes be dropped, be allowed to strike one another, be rolled
freely or dragged along the ground. No valves shall be lifted by the spindle.
Fabricated materials such as man-hole covers, appurtenances, bolts, nuts, flanges, saddles,
collars, bypass arrangements etc., shall be transported to the site of laying from the
fabrication yard according to needs of the laying operations only.
3.1 General
Laying / erection of factory made internal lined and external gunited pipes shall be carried
out by the Contractor who shall equip himself, at his cost, with all necessary tools,
machinery, labour etc., required for the purpose. The pipeline shall be constructed in lengths
with a separate full time gang working on each length.
The Contractor shall submit a detailed bar chart for manufacturing and laying of the pipeline,
which shall be subject to the Engineer-in-Charge’s approval. In preparing this bar chart, the
Contractor shall plan his activities such that the laying of pipes shall closely follow the
manufacturing schedule and no pipes shall remain stacked in factory or at site for a period
more than 15 days.
Together with the chart he shall submit a methodology describing how he will carry out this
work within the contractual period and the required resources in terms of construction
equipment and other facilities that he shall utilize to complete the works.
228
3.3 Buried Pipelines
3.3.1 Trenching
Unless otherwise specified, all buried pipes and fittings, specials shall have minimum
cushion of 1.20 m above the top surface of external pipe guniting.
Trenching includes all excavation which is carried out either by hand or by machine and shall
be carried out in accordance with all general requirements as specified elsewhere. In
addition to those general requirements, the following requirements shall apply to pipelines.
The width of the trench shall be kept to a minimum consistent with the working space
required and having regard to the safety of the trench, the method of laying and jointing the
pipe and the need to avoid damage to pipe coating and so as to provide the minimum
horizon as stated in the table below. The bottom of the trench shall be properly trimmed to
permit even bedding of the pipeline.
The portion of the trench which extends from the formation level to not less than 300 mm
above the crown of the pipe when laid in its correct position, shall, unless otherwise specified
or ordered by the Engineer-in-Charge, be formed with vertical sides. The clearance between
the sides and bottom of the trench and the barrel of the pipe shall be kept minimum.
The clearance at joints may be increased to allow the joints to be made and inspected; any
proposed increase shall be approved by the Engineer-in-Charge.
All trenches deeper shall have the trench walls battered or supported to ensure the safety of
all persons working in the trench if required. The Contractor is to provide details of these
arrangements for approval by the Engineer-in-Charge prior to any work being undertaken in
such a trench.
No excavations with battered sides shall be made in roads, footpaths, private gardens, or
within 10 m of any buildings or other structures.
The Contractor shall erect temporary fencing around all open excavations and post warning
signs in English and the local language. A fencing shall be at least 1.0 m tall, rigid in nature
and strong enough to prevent people falling into the trench. The Contractor shall also take all
other necessary measures to ensure the safety of the public and others.
The maximum length of excavation which may be left open in any length is 500 m. The
opening of two lengths within 500 m of each other shall require the approval of the Engineer-
in-Charge.
The excavation shall be kept free of water to allow placing of bedding, laying of pipes,
welding of pipes, inspection and testing of joints, coating of joints, placing of backfill and
other activities within the pipe trench, to be carried out in a satisfactory manner.
3.3.2 Bedding
The depth and type of bedding shall be as per approved drawing certified by BIL. Based on
the site conditions, the Contractor shall submit detailed drawings with bedding details for
BIL’s approval. Where rock or boulders are encountered, the trench shall be trimmed to a
depth of at least 300 mm below the level at which the bottom of the barrel of the pipe is to be
laid and filled to a like depth with sand as shown in the approved drawings.
229
Class of bed and surround Brief description of bedding material
Class A Mass Concrete
Class N Well Graded Sand
Class S Granular material
Class S bed and surround shall be used on all pipes unless otherwise specified or shown on
the drawings.
The concrete to be used for Class A bedding and surround shall be M: 15 type. Class A
bedding shall be used at all road / drain crossings under the road / drain and for a distance
of 5 m back from the back edge of road / drain or footpath.
Class N bed material shall only be used where the pipe trench is founded in hard rock or
otherwise as directed by the Engineer-in-Charge. The sand shall be clean and well graded
and free from topsoil, clay or vegetable matter and to the approval of the Engineer-in-
Charge. If the sand supplied is unclean it shall be washed. In no case shall sand containing
more than 3.5% by dry volume or 5% by wet volume of clay, loam or silt be accepted. Tests
specified for determining silt in sand and organic impurities as described in IS: 383 shall
apply.
The graded granular bed material for use in Class S bedding and surround shall consist of
durable gravel, crushed stone or disintegrated rock. Selected material excavated from the
pipe trench may be used, provided it contains no topsoil, clay or vegetable matter and is to
the approval of the Engineer-in-Charge. Any imported bed and surround materials shall be to
the approval of the Engineer-in-Charge and shall be supplied with certification which gives
details of its content, source and grading. In all cases the soluble sulphate and chloride
content of the granular material shall not exceed 0.5 % and 0.06 % by weight respectively.
Graded Material
The Contractor's method of grading the excavated material shall be to the approval of the
Engineer-in-Charge. All Class S graded material shall pass though test sieves to IS: A60
(Part 1) in the following proportions by mass:
Class A bed and surround shall be constructed as indicated in the approved drawings by
BIL.
Before placing concrete the pipes shall be supported near each joint with a padding of
compressive material on a precast concrete block. Concrete shall not be placed until the
pipes have been jointed, inspected and tested. The concrete shall be placed to ensure full
contact with the pipe barrel throughout its length.
230
The concrete shall be made discontinuous at flexible pipe joints by a diaphragm of fiber
board or other compressible material of at least 20 mm thickness extending for the full area
of the surround.
No concrete shall be placed around joints of a welded steel pipe until that length of pipe has
passed a sectional hydraulic test.
Class S pipe bed and surround shall be constructed as indicated in the approved drawings.
The granular material shall be evenly spread over the full width of the formation and lightly
compacted to a level slightly higher than level corresponding to the underside of the pipe
barrel to allow for settlement of the pipe to the correct level.
Following placement and jointing of the pipe further granular material shall be placed in the
trench, special care being taken to fill under the sides of the pipes to ensure full contact with
the barrel of the pipe.
Field joints which have not been tested shall be left exposed for a minimum length of 150
mm each side of the joint. The granular material shall then be placed and compacted evenly
on both sides of the pipe to a depth of 300 mm above crown of the pipe.
Trench supports shall be withdrawn gradually in accordance with the progress of the fill with
the provision that such withdrawal shall not prejudice the safety of the works.
The contractor shall ensure that the material to the sides of the pipe is adequately
compacted in layers having a maximum thickness of 150 mm and that the method of
compaction used shall achieve not less than 95% of the maximum dry density as determined
from IS: 2720: Part - 7.
After each section of the pipeline has passed the hydraulic test, the exposed joints shall be
backfilled and compacted to the above specification. .
The laying of the pipes shall be in accordance with IS: 5822 unless otherwise specified. The
pipeline shall be constructed in lengths with a separate full time gang working on each
length. No metal tools or heavy objects shall be permitted to come into contact with the pipes
or fittings. External gunited pipe shall be handled at all times with wide non-abrasive canvas,
rubber or leather straps or other equipment to prevent damage to the guniting. The use of
chains, wire slings, or any other handling equipment found to be injurious to the guniting
shall not be permitted. The timber or skids used to support the gunited pipe prior to lowering
into the trench shall be properly padded with sufficient bags stuffed with sand or straw for the
purpose of protecting the guniting. Alternatively, the pipe may be supported alongside the
trench on mounds of sand. Any injury to the protective guniting from any cause must be
repaired before the pipes or fittings placed in the trench. During laying operations, no debris,
tools cloth or other material shall be placed in the pipe. Pipes and fittings shall be lowered
into the trench with equipment suitable for the weight of the pipes and fittings, and they shall
be carefully cleaned before jointing.
Pipes shall be laid accurately to the lines and levels shown on the drawings, within a
tolerance of ± 10 mm.
231
Pipe alignments shall be straight between bends or curves. Length laid to curves shall only
be allowed where shown on drawings or in accordance with detailed proposals approved by
the Engineer-in-Charge.
Properly painted sight rails shall be supplied and erected, with boning rods of predetermined
measurement for the boning of individual pipes to the correct gradient. The sight-rails shall
be situated vertically above the line of the pipe or immediately adjacent thereto, and there
shall at no time be less than three sight rails in position on each length of pipeline under
construction to anyone gradient.
The Contractor may submit to the Engineer for his approval an alternative method of the
control of pipe laying to the correct levels and alignment.
The joining of pipes shall be made in accordance with the requirements of this specification.
The Contractor shall obtain from manufacturers all special information regarding the
handling of the pipes, joints and other fittings and he will be deemed to have made himself
thoroughly conversant with all phases of pipe laying before commencing the works.
A "badger" or "bung" about 10 mm smaller than the internal diameter of the pipe shall be
kept in the pipe at all times, pulled forward as the work progresses. When pipe laying is not
in progress, including overnight, the open ends of the pipeline shall be blanked off with a
temporary watertight fitting approved by the Engineer-in-Charge. The pipe shall be suitably
held down so that the pipe does not become buoyant in the event of the trench becoming
flooded.
To restrict the flow of rain runoff along the trench, the Contractor shall plug the trench with
backfill material at distances not exceeding 250 m until the pipeline can be filled in. The
plugs shall be removed when trench filling is taking place. In granular bedding areas the
plugs shall be of clay and shall be left in.
The criterion for the level to which transmission main shall be laid such that the cover above
the crown of the pipe to ground level shall be as specified in the drawings but in no case
shall be less than 1200 mm unless otherwise directed by Engineer-in-Charge.
Where pipes are to be laid to curves, the deflection at each joint shall not exceed one
degree. For sharper curves specifically made bends shall be provided.
The pipe shall be lowered into the trenches such that no part of any shoring is disturbed or
damaged and, if necessary, additional temporary struts may be fixed during the lowering
operations. Care shall be taken to ensure that the longitudinal joints of two consecutive pipes
at each circumferential joint are staggered by 90°. While assembling the pipes, the ends
shall have to be brought close enough to leave a uniform gap not exceeding 4 mm. There
shall be no lateral displacement between the pipe faces to be joined. If necessary, spiders
from inside and tightening rings from outside or other suitable equipment shall be used to
bring the two ends in perfect contact and alignment. In no case shall hammering or
longitudinal slitting be permitted. Jacking may be permitted for this purpose in particular
circumstances as approval by the Engineer-in-Charge, when the pipe is properly assembled
232
firmly supported on wooden beams and wedges or by other approved means it shall be
checked for correct line and level.
On completion of the pipe jointing the external portion of MS pipes shall be coated with M:
15 concrete and the trench and the welding pits shall be cleaned. The pipe jointing pit for all
the pipe materials shall be filled with approved bedding material and compacted in 150mm
layers.
3.3.9 Floatation
The Contractor shall take proper precautions against the risks of floatation and of flooding of
the excavated works and shall make due allowance in his programme for any closure he
considers necessary on account of monsoon.
Should any section of the pipeline be affected by floatation in the course of works the entire
work shall be removed and then reinstalled to the satisfaction of Engineer-in-Charge. The
entire cost of laying it again to the correct line and level shall be to account of the Contractor.
For mild steel pipes in order to effectively provide cement mortar lining to the inside of the
pipes and to avoid difficulties during the work, it is necessary that the roundness of the pipes
is maintained circular till the lining work is taken up. To achieve the same, steel adjustable
screw type props or similar approved type consisting of minimum six legs (three props) shall
be fixed inside the pipe and the diameter correctly set.
The design and drawings of the props that the Contractor intends to use should be approved
by the Engineer-in-Charge before starting the work. These props shall be fixed vertically at
intervals as directed by the Engineer-in-Charge. The props should be kept in position at least
for three days after the encasing of the pipe in that section is completed or until refilling is
done to the full height of fill over the pipe in case the pipes are not encased. The props shall
be removed only after obtaining permission from the Engineer-in-Charge.
3.3.11 Backfilling
On completion of the pipe laying operations in any section, for a length of about 100 m and
while further work is still in progress, refilling of trenches shall be started by the Contractor
with a view of restricting the length of open trenches. Pipe laying shall closely follow the
progress of trench excavation and the Contractor shall not permit unreasonably excessive
lengths of trench excavation to remain open while awaiting testing of the pipeline. If the
Engineer-in-Charge considers that the Contractor is not complying with any of the foregoing
requirements, he may prohibit further trench excavation until he is satisfied with the progress
of laying and testing of pipes and refilling of trenches. Filling to a level of 300 mm above the
crown of the pipe shall be done in accordance with the requirements of the clause on
bedding. Care shall be taken during backfilling, not to injure or disturb the pipes, joints or
guniting. Filling shall be carried out simultaneously on both sides of the pipes so that
unequal pressure does not occur. Walking or working on the completed pipeline shall not be
permitted unless the trench has been filled with the instructed bedding and surround material
up to height of at least 300 mm over the top of the pipe except as may be necessary for
tamping etc., during backfilling work.
The remaining portion of the trench shall be filled in with selected excavated material free
from and topsoil, vegetation or boulders and clods of earth larger than 75 mm in size. Filling
shall be done in layers not exceeding 150 mm in thickness accompanied by adequate
watering, ramming etc., so as to be compacted to 95% of the maximum dry density as per
233
Part 7 of IS: 2720. The water contents of the soil shall be kept near to optimum moisture
content as possible. The trench shall be refilled so as to build up to the original ground level,
keeping due allowance for subsequent settlement likely to take place. The surface of the
refilled excavations shall be left slightly higher than the adjacent ground and be maintained
by the Contractor to a smooth even slope.
The Engineer-in-Charge shall, at all times, have powers to decide which portion of the
excavated materials shall be used for filling and in which portion of the site and in what
manner it shall be so used.
If suitable material for refilling is not available from already excavated material the Contractor
shall import material of approved quality as directed by the Engineer-in-Charge.
Regular measurement of the field dry density shall be taken by the Contractor at various
levels in the backfilling as required by the Engineer-in-Charge.
No mechanical plant other than approved compacting equipment shall run over or operate
within the trench until backfilling has reached its final level or the approval for the Engineer-
in-Charge has been obtained.
Should any subsidence take place either in the filling of the trenches or near about it during
the works the Contractor shall make good the same at his own cost.
Surplus excavated material shall be used to fill in any low spots above the pipeline which are
identified on the drawings or are instructed by the Engineer-in-Charge. Such material shall
be evenly placed and compacted in layers not exceeding 200 mm thick after compaction.
The method of compaction employed shall achieve not less than 90% maximum dry density
as determined from IS: 2720, Part 7. Unless approved of by the Engineer-in-Charge, the
width of areas to be filled shall not exceed 20m.
3.3.12.1 General
The procedure for handling the pipes, lowering and assembling specified in previous clauses
shall be followed for lifting and laying pipes on supports. The pipeline should be laid on
saddle and ring girder supports as specified in approved drawings by BIL and as directed by
Engineer-in-Charge. No material shall be erected unless they have been previously
approved by the Engineer-in-Charge.
Erection of fabricated pipes shall be carried out by the Contractor who shall equip himself, at
his cost, with all necessary tools, machinery, labour etc., required for the purpose. The
pipeline shall be constructed in lengths with a separate full time gang working on each
length.
Unless specified otherwise in the BIL approved drawings, ring girders are to be used to
support pipe work on all pipe bridges. They shall be fabricated from IS: 2062 Grade B steel
and supported by pipe bridge piers. Ring girders are usually installed 1.0 m behind each
welded joint. Pipes are supported on ring girders placed at 13.5 m c/c directly over bridge
piers. Ring girders shall be fabricated as per approved drawings. All pipes and fittings on
pipe bridges shall be epoxy painted as specified. Any damage to the painting shall be made
good.
234
3.3.12.3 Expansion Joints
Expansion joints are designed to allow for thermal induced movement of pipelines laid above
ground. Contractor shall submit detailed design and drawings for the expansion joints as per
the standard specifications.
If any defects are noticed after its erection at site, the Contractor shall carry out necessary
repairs either at site or at their works as directed by the Engineer-in-Charge. All expenses in
this connection including its removal, transporting and refixing shall be borne by the
Contractor. The responsibility as regards the defects noticed shall be determined by the
Engineer-in-Charge and his decision shall be final and binding on the Contractor.
The Contractor shall provide suitable pipe supports or pedestals as per detailed working
drawings. Pipe laying shall generally start from the fixity points on either side, the expansion
joints being provided last.
Anchor blocks shall be constructed in stages. The anchorages shall be made from concrete
and constructed as per designed dimensions.
As per approved drawings the concrete pedestals shall be cast at least 3 weeks before the
pipeline is laid on them. In case of any errors in casting the pedestals, corrections shall be
applied as directed by the Engineer-in-Charge. The method of joining the pipes and erecting
them on the previously cast pedestals shall be determined by the Contractor in consultation
with the Engineer-in-Charge.
The pipe shall be assembled in position on the pedestal by the equipment approved by the
Engineer-in-Charge.
235
3.4 Puddle and Thrust Flanges
The puddle flange and weld between the flange and pipe work shall be sufficient to take care
of designed total shear force. Puddle flanges on steel pipe work over 1000 mm Dia. shall be
a minimum thickness of 60 mm. and height of 150 mm.
3.5 Gaskets
All gaskets shall be manufactured from SBR rubber in accordance with IS: 5382. Gaskets for
spigot and socket pipes shall comply with ARE: 12820. The dimensions of flange gaskets
shall comply with BS: 4865.
Contractor shall provide anchor blocks at horizontal bends, vertical bends at intervals on
pipelines with gradients in excess of 1 in 6. The anchorages shall be made from RCC M: 25
concrete or grade as specified elsewhere only and constructed to the dimensions as per the
approved drawings. Anchor blocks shall also be provided at line valves to counteract
unbalanced forces developed in lines and valves. Anchorage shall also be provided to
counteracting buoyancy forces acting on the pipelines when empty. Anchor blocks designed
as (i) gravity anchors, where pipelines are encased in concrete block for the entire length or
in sections to give adequate counteracting weight and (ii) ground anchor, where pipeline is
passing through areas subjected to high water tables or in marshy land. The buoyancy force
is resisted by buoyant weight of block and soil / rock supported by the anchor. Adequate
factor of safety shall be considered.
Where faces of anchor blocks are bear against undisturbed ground, the Contractor shall take
all necessary measures to ensure that such bearing is given over the full dimensions shown.
When pipe work is in a Class A bed and surround or surrounded in concrete at thrust and
anchor blocks etc, the pipes shall be given the normal external guniting and shall be
wrapped with at least two layers of 0.30 mm thickness waterproof polythene securely fixed in
place with waterproof tape.
Pipelines entering and leaving certain structures shall include two flexible joints, at distances
from the face of structure as per the design and as identified by the Engineer-in-Charge.
A pipe line laid in the alignment having deviation points, be they underground or above
ground, due to internal pressures unbalanced forces develops, which causes development
of stress in the pipe shell. To counteract these forces RCC thrust blocks shall be provided.
The thrust block size is governed by following criteria:
The resultants of vertical forces due to weight of block, pipe and water and horizontal
forces due to thrust and component of longitudinal forces wherever acting shall fall
within middle third of base width.
Frictional forces at the base shall have adequate factory of safety against sliding.
236
Ground pressure developed at the base shall not exceed safe bearing capacity of
foundation strata.
Also following two cases are considered for different conditions of side supports.
First case shall be, design of block neglecting support of soil and soil pressure and second
one is design of block where support of surrounding soil is considered.
Wherever there is a transition between above ground and buried pipelines. Vertical thrust
blocks shall be provided. Vertical thrust blocks shall have flexible joints at either end to allow
for small amounts of settlement to occur. The Contractor shall undertake the construction of
the thrust blocks as early in the programme of work as is practical, in order to reduce the risk
of settlement of imposing additional loads on the pipeline supports.
Where possible the base of the thrust block shall be cast against solid rock in order to
prevent any settlement. Any material overlying the rock shall be excavated and replaced with
class M: 15 grade mass concrete. In the event of no rock being encountered the base of the
thrust block shall be cast against undisturbed ground. Any ground which in the Engineer-in-
Charge’s opinion is unsuitable shall be excavated and replaced with class M: 15 grade mass
concrete.
The Contractor shall programme the works to reduce disruption to road traffic to a minimum,
and before any work commences in existing roads shall:
i. Obtain the permission and approval of all authorities concerned serving notices of
intent to start work as may be necessary and observing all the local Laws and
Regulations.
ii. Submit details of his proposals, and obtain approval from the Engineer-in-Charge and
local highway authority.
The pipelines crossing roads shall be provided with RCC ducts in M: 25 concrete as per the
approved design and drawings by BIL.
Pipelines which are laid along a road shall be laid in trench. The bed and surround shall be
previously specified but above this the trench shall be backfilled with crushed rock up to the
underside of the road sub-base. Not more than 20% of the crushed rock shall pass through a
IS test sieve with 4.75 mm apertures and all material shall pass through a IS test sieve
having an aperture of 40 mm. The backfill shall be compacted in layers having a maximum
thickness of 200 mm and the method of compaction used shall achieve not less than 95%
maximum dry density as determined from IS 2720: Part7.
The replacement of road structures shall be carried out as soon as practicable after
backfilling has been completed. Suitable excavated road pavement which complies with the
requirements of the Engineer-in-Charge may be used at the sub-base levels. Compaction
shall be carried out with approved mechanical compacting equipment. The depth and type
of reinstatement shall consist of the following:
237
ii. laying and compacting a 150 mm thick layer of Water Bound Macadam
iii. laying and compacting a 150 mm thick of Built Up Spray Grout
iv. where the carriage way surface adjoining the trench is of rolled asphalt the
Contractor shall lay a wearing course of 40 mm thick rolled asphalt
The edges of the trench shall be cut to form a uniform line consistent with the varying width
of the trench and the agreed trimming allowances. Any part of the structure of the road which
has been damaged beyond the width of trench must be cut out and made good. Prior
approval for such additional work must be obtained from Engineer-in-Charge.
A vertical joint shall be formed between the new work and the existing road surface and shall
be painted with hot bitumen or as approved by the Engineer-in-Charge. The joint between
the base course and wearing course shall be stepped 75mm.
The finished levels of the completed reinstatement shall conform with adjoining carriageway
surface.
Reinstatement of wearing courses shall match as nearly as practicable the colour or other
characteristics of the existing surface.
Pipelines shall be cleaned of all dirt, debris, dust or other deposits by repeated hosing of
copious quantities of water on the pipe surface and simultaneously rubbing the surface with
gunny cloth to the satisfaction of Engineer-in-Charge. Cleaning with metal cleaning solution,
acid, wire brushes, scrappers or sand paper shall not be permitted.
The section of the pipeline once cleaned shall not be entered into for any purpose later.
Sufficient precaution shall be taken to prevent the ingress of any dirt, debris, or dust inside
the section. Failing this the section shall be cleaned again at the discretion of the Engineer-
in-Charge.
In the case of above ground pipeline, the length of the section to be taken up for cleaning
shall be decided in consultation with the Engineer-in-Charge from the point of view of
ventilation etc.
In case of buried pipeline a section, shall be taken up for cleaning after the work of back
filling around and over the pipeline is completed and the spiders have been removed from
inside with approval of Engineer-in-Charge.
During the pipe laying operation in the adjoining section, the Contractor shall take all
precautions to prevent ingress of water, debris, dirt, etc. in the cleaned section, failing which
the section shall be cleaned again at the discretion of the Engineer-in-Charge. When
deemed necessary by the Engineer-in-Charge suitable closures shall be provided at the
open end or the ends of the cleaned sections.
Pipelines and fittings shall be subjected to hydraulic pressure tests in the presence of the
Engineer-in-Charge which shall comply with relevant IS specifications.
The Contractor shall equip with all plant, equipment, fittings and water necessary for the
hydraulic tests. The Contractor shall submit to the Engineer-in-Charge, well in advance of
the time of tests, details of his proposals.
238
Test gauges shall be of approved manufacture having dials at least 200 mm diameter,
graduated such that the test pressure is at least 75% of the full scale reading shall be used.
As directed by the Engineer-in-Charge different gauges shall be supplied for different
pipeline sections. Two gauges shall be provided for the sole use of the Engineer-in-Charge
and shall remain in the Engineer-in-Charge possession for the duration of the Contract. All
gauges shall be dead weight tested and calibrated at the commencement of work and at
regular intervals as required by the Engineer-in-Charge.
The Contractor's arrangements for testing shall include a suitable means of quick installation
and removal of the Engineer-in-Charge’s gauges during testing.
The Sectional Hydraulic Test shall be carried out, after the pipeline section which has been
laid, joined and backfilled to a depth sufficient, to prevent floatation, but leaving the joints
exposed which have not been tested. The sections to be tested shall be to the approval of
the Engineer-in-Charge and shall be not longer than 20000 in or 500 m when either the
pipeline is laid adjacent to or underneath the carriageway or when section includes an air
valve chamber. The joints between each tested section shall be left until the pipeline has
passed the Test on Completion.
In addition to the above requirements the Contractor shall perform a hydraulic test on the
first 200 m length of pipeline to be laid under the Contract. This test shall be undertaken
within one month of the Contractor commencing the laying of pipes. Should the pipeline fail
the test or the Contractor fail to undertake the test, all laying and welding work shall come to
a halt until that section of pipeline passes a hydraulic test.
Each length of the pipeline to be tested shall be capped or blanked off at each end and
securely strutted or restrained to withstand the forces which will be exerted when the test
pressure is applied. Testing against closed valves will not be permitted. Washout valves
shall be fitted with blank flanges and these together with in-line valves shall be left open. Air
valves already fitted shall be permitted to function during the test.
Proposals for testing where thrusts on structures are involved, even where thrust flanges on
the piping are installed, shall be submitted, with the calculations of the forces to be carried,
to the Engineer-in-Charge for approval.
The method of filling the pipeline with water shall be approved by the Engineer-in-Charge.
The length under test shall be filled making certain that all air is displaced through an air
valve installed at the top of the blank flange situated at the high end of the line. The length
shall then remain under constant moderate pressure, 10 to 20 m head of water, for a period
of several hours until the pressure can be maintained without additional pumping.
The pressure shall then by slowly increased at a maximum rate of 1 bar per minute to the full
test pressure and pumping discontinued for 3 hours or until the pressure has dropped by 10
m, whichever occurs earlier. Thereafter pumping shall be resumed and continued until the
test pressure has been restored. The quantity of water pumped to restore the pressure shall
be the measure of leakage from discontinuation of pumping until its resumption.
The pipe length shall pass the test if the leakage is not more than 0.33 litres per mm
diameter per kilometre per 24 hours for each 100 m head of pressure applied.
Notwithstanding the satisfactory completion of the hydraulic test, if there is any discernible
leakage of water from any pipe or joint the Contractor shall, at his own cost, replace the pipe,
repair the pipe or re-make the joint and repeat the hydraulic test.
239
No pipeline shall be accepted until the leakage on any length is not more than the rate of
leakage specified above and all sources of leakage have been rectified.
Pipelines shall be tested as above except where the Engineer-in-Charge issues such
instructions as are necessary for testing parts of the works that have been designed for
stresses limited by considerations other than those applying to the pipeline systems.
Test pressures are to be measured in bars or in Kg/ cm 2 at the centre of the blank flange
situated at the lowest end of the pipeline under test. Pipeline test pressure shall be as per
specified below;
The field test pressure to be imposed should not be less than the maximum of the following:
Sum of the maximum sustained operating pressure and the maximum surge
pressure
Sum of the maximum pipeline static pressure and the maximum surge pressure
However minimum test pressure for all the reaches shall be 6.0Kg/cm2.
With above criteria’s and as per approved design Contractor shall calculate the required field
hydraulic test pressure. On the approval of the same field hydraulic tests shall be carried out.
Upon completion of a newly laid pipeline, the pipeline shall be cleaned, disinfected and
dewatered as directed by the Engineer.
The internal surfaces of pipeline, specials and appurtenances shall be disinfected using
chlorine solution in accordance with procedure specified in IS: 5822. Alternative methods
may be adopted with the approval of the Engineer-in-Charge. The chlorinated water shall
stand in pipeline for a minimum period of 24 hours and all valves in the system shall be
operated twice during this period.
The chlorinated water shall be neutralized and disposed off as directed by Engineer-in-
Charge.
After final flushing and before the pipeline is placed into service, water samples shall be
collected and tested for bacteriological quality and shall not indicate the presence of Coli
forms. If the initial disinfection fails to produce satisfactory results, disinfection shall be
repeated until satisfactory samples are obtained.
3.17 Markings
Details like valve type, size, and number shall be painted on all valve chambers as directed
by the Engineer.
240
In case of the pipeline laid above ground, details such as chain age, invert levels of pipe,
pedestal / saddle number, culvert number, anchor / thrust block number etc., shall be
suitably painted either on pipeline or the supporting structure in distinct colour.
4.1 General
In particular, the following standards, specified herein shall be referred. In all cases, the
latest revision of the codes shall be referred to. If requirements of specifications conflict with
the requirements of the codes and standards, this specification shall govern.
IS: 8329 Specification for Centrifugally Cast (spun) Ductile Iron pressure pipes for water, gas
and sewage specification.
materials.
IS: 9523 Ductile Iron fittings for pressure pipes for water, gas and sewage.
IS: 12820 Dimensional requirements. of rubber gaskets for mechanical Joints and push on
joints for use with cast Iron pipes and fittings for carrying water, gas and sewage.
ISO: 4179 Ductile iron pipes for pressure and no pressure- Centrifugal cement mortar lining -
General requirements.
ISO: 2531 Ductile iron pipes, fitting and accessories for pressure pipe lines.
IS: 12288 - Code of practice for use & laying of Ductile iron pipes.
4.2 Manufacturing:
4.2.1 General
b) Owner / Engineer shall at all reasonable times have free access to the place where
the pipes are manufactured for the purpose of examining and testing the pipes and
for witnessing the test and manufacturing.
c) All tests specified either in this specification or in the relevant Indian Standards shall
be performed by the supplier/contractor at his own cost and in presence of
Owner/Engineer if desired. For this, sufficient notice before testing of the pipes shall
be given to Owner/Engineer.
d) If the test is found unsatisfactory, Owner/Engineer may reject any or all pipes of that
lot. The decision of Owner/Engineer in this matter shall be final and binding of the
contractor and not subject to any arbitration or appeal.
4.2.2 Materials
The general requirements relating to the supply of material shall be as per IS: 1387.
241
4.2.3 Dimensions:
The internal diameter, thickness and length of barrel, dimensions of pipes shall be as per the
relevant tables of IS.8329/IS: 9523 for different class of pipes. The tolerances for pipes
regarding dimensions and deviations from straight line shall be as per relevant IS codes. The
standard weight of uncoated pipes and the permissible tolerances shall be per relevant IS
codes.
3.2.4 Testing
Mechanical Tests
Mechanical tests shall be carried out during manufacture of pipes as specified in relevant IS
codes. The results so obtained shall be considered to represent all the pipes and fittings of
different sizes manufactured during that period and the same shall be submitted to
Owner/Engineer. The method for tensile tests and the minimum tensile strength requirement
for pipes shall be as per relevant IS codes.
3.2.5 Coating
All DI pipes shall be delivered with internal lining and external coating. Coating shall not be
applied to any pipe unless its surface is clean dry and free from rust. All DI pipes shall be
mortar lined on internal surface as specified in ISO: 4179 and externally coated with
bituminous paint as specified in IS: 8329.
3.2.6 Marking
All pipes manufactured in the factory and temporarily stacked in the Contractor's yard shall
be transported to the site of laying after cleaning them internally etc. The item of transport
covers the cost of loading in the factory, transporting to the site of laying or to stacking yard
selected byte Engineer in its vicinity and unloading and stacking them carefully in such a
manner that the material so kept is not easily disturbed or rolled away from the place of
stacking.
The loading in the factory shall be carried out by means of either a crane, gantry or shear
legs, so as not to cause any damage to the finished material. Similarly, while unloading and
stacking, great care shall be taken to ensure that the material is not damaged or dented. The
contrivances to be used for unloading will be different in different situations and in each case
the one approved byte Engineer shall be adopted.
The material stacked at site shall be jointly inspected by the Engineer and the Contractor
and defect or damage noticed shall be repaired to the satisfaction of the Engineer before
payment is admitted. The stacking ground, both in the Contractor's yard and at the site of
laying shall be selected in such a way as not to get waterlogged during monsoon. If this
cannot be done, the pipes shall be supported on sleepers to avoid contact with wet earth. As
explained in earlier paragraphs, materials such as pipes, tapers, etc. may be transported to
the site of laying as soon as the material is finished in all respects with the permission of the
Engineer.
242
3.3 Laying of Ductile Iron Pipes and Fittings /Specials
3.3.1 Scope
Pipes and fittings/specials shall be transported from the factory to the work sites at places
along the alignment of pipeline as directed by Owner/Engineer and as specified by
manufacturer. Contractor shall be responsible for the safety of pipes and fittings/specials in
transit, loading/unloading. Every care shall be exercised in handling pipes and
fittings/specials to avoid damage. While unloading, the pipes and fittings/specials shall not
be thrown down from the truck on to hard surfaces. They should be unloaded on timber
skids with steadying ropes for by any other approved means. Padding shall be provided
between coated pipes, fittings/specials and timber skids to avoid damage to the coating.
Suitable gaps between pipes should be left at intervals in order to permit access from one
side to the other. In case of spigot socket pipes, care should be taken regarding orientation
of pipes while unloading. As far as possible pipes shall be unloaded on one side of the
trench only. All pipes shall be checked for any visible damage (such as broken edges,
cracking or spilling of pipe) while unloading and shall be sorted out for recantation. Any pipe
which shows sufficient damage to preclude it from being used shall be discarded. Dragging
of pipes and fitting/specials along concrete and similar pavement with hard surfaces shall be
prohibited.
3.3.3 Storage
Each stack of pipes shall contain only pipes of same class and size, with consignment or
batch number marked on it with particulars of suppliers wherever possible. Storage shall be
done on firm level and clean ground and wedges shall be provided at the bottom layer to
keep the stack stable. The stack shall be in pyramid shape or the pipes laid lengthwise and
crosswise in alternate layers. The pyramid stack shall be made for smaller diameter pipes for
conserving space in storing them. The height of the stock shall not exceed 1.5 m.
fittings/specials, shall be stacked under cover and separated from pipes. Rubber rings shall
be stored in a clean, cool store away from windows, boiler, electrical equipment and petrol,
oils or other chemicals. Particularly in the field where the rubber rings are being used it is
desirable that they are not left out on the ground in the sun or overnight under heavy frost or
snow conditions.
3.3.4 Laying
Excavation
Before excavating trench the alignment of pipeline shall be approved by Engineer. The
excavation shall be carried out in accordance with the relevant Standards. To protect
persons from injury and to avoid damage to property, adequate barricades, construction
signs, red lanterns and guards as required shall be placed and maintained during the
progress of the construction work and until it is safe for the traffic to use the roadways.
The relevant Indian standards and the rules and regulations of local authorities in regards to
safety provisions shall be observed. Suitable fencing shall be provided along the sides of
trenches and pits. The posts of fencing shall be of timber securely fixed in the ground not
more than 3 in apart and they shall not be less than 75 mm in diameter or less than 1.2 m
above surface of the ground. There shall be two rails, one near the top of the post and the
243
Other about 450 mm above the ground and each shall be from 50 mm to 70 mm in diameter
and sufficiently long to run from post to post to which they shall be bound with strong rope.
The method of projecting rails beyond the post and tying them together where they meet will
not be allowed on any account. All along the edges of the excavation trenches a bank of
earth about 1.2m high shall be formed where required by Owner/Engineer for further
protection. The road metal and also the rubble packing shall first be stripped off for the whole
width of the trench/pit and separately deposited in such place or places as may be
determined by Owner/Engineer. During excavation, large stones and rubble shall be
separated and removed from the excavated soil and stacked separately.
The material from excavation shall be deposited on either side of the trench leaving
adequate clear distance from the edges of the trench and pit, or as may be necessary to
prevent the sides of the trench pit to slip or fall, or at such a distance and in such manner as
to avoid covering fire hydrants, sluice valves, manholes covers etc. and so as to avoid
abutting the wall or structure or causing inconvenience to the public and other service
organizations or otherwise as Owner/Engineer may direct.
Contractor shall take into account additional excavation if any as Owner/Engineer may
require in order locating the position of water pipes, drains, sewers etc. or any other works
which may be met with, in or about the excavation of trenches/pits while quoting the rates for
excavation of trenches/pits while quoting the rates for excavation. Such service lines if met
with during excavation shall be properly maintained by Contractor, by means of shoring,
strutting, planking over, padding or otherwise as Owner/Engineer may direct, and shall be
protected by the Contractor from damage during the progress of the work.
All precautions shall be taken during excavation and laying operations to guard against
possible damage to any existing structure/pipe line of water, gas, sewage etc. If the work for
which the excavation has been made is not completed by the expected date of the setting of
monsoon or the setting in of rain whichever is earlier, or before the day fixed by
Owner/Engineer for filling in any excavation on account of any festival or special occasion,
Contractor shall backfill such excavation and consolidate the filling. Utmost care shall be
taken to see that the width of the trench up to ground level is not more than as per required
standards.
If any extra width is provided in the pipe zone, the Contractor shall have to provide remedial
measures in the form of lime concrete or rubble masonry otherwise at the discretion and to
the satisfaction of Owner/Engineer. If rock is met with, it shall be removed to 15 cm below
the bottom of pipes and fittings/specials and the space resulting shall be refilled with
granular materials and properly consolidated. Bottom of trenches/pits shall be saturated with
water well rammed wherever Owner/Engineer may consider if necessary to do so.
Wherever a socket or collar of pipe or fitting/special occurs, a grip is to be cut in the bottom
of the trench or concrete bed to a depth of at least 75 mm below the bed of the pipe so that
the pipe may have a fair bearing on its shaft and does not rest upon its socket. Such grip
shall be of sufficient size in every respect to admit the hand all around the socket in order to
make the joint and the grip shall be maintained clear until the joint has been approved by
Owner/Engineer.
When welding is to be carried out with the pipes and specials in the trench, additional
excavation of not more than 60 cm in depth and 90 cm in length shall be made at joints in
order to facilitate welding.
244
The excess excavated material shall be carried away from site of works to a place up to a
distance as directed by Owner/Engineer. This shall be done immediately so as not to cause
any inconvenience to the public or traffic. If the instructions from Engineer are not
implemented within seven days from the date of instructions to cart the materials and to
clear the site, the same shall be carried out by Owner/Engineer and any claim or dispute
shall not be entertained in this respect. The contractor shall make proper provision for
protecting the work by fencing, watch and ward lighting at right on in another manner as may
be directed by Engineer.
De-watering
During the excavation, if subsoil water is met with Contractor shall have to provide
necessary equipment and laborers for dewatering the trenches/pits by bailing out water or
water mixed with clay if pumping out subsoil water is found to be necessary; Contractor shall
provide sufficient number of pumps for the same. In both the above cases the excavation
shall be done to the required level and the pipes shall be laid to proper alignment and
gradient.
Contractor shall also make necessary arrangement for the disposal of drained water to
nearby storm water drain or in a pit if allowed by Owner/Engineer. In no case the water shall
be allowed to spread over the adjoining area. Before discharging this water into public
sewer/drain, Contractor shall take necessary permission from the local authorities.
Where the bottom of the trench and sub grade is found to consist of material which is
unstable touch a degree that in the opinion of Owner/Engineer, it cannot be removed and
replaced with an approved material thoroughly compacted in place to support the pipe
properly, a suitable foundation for the pipes, consisting of piling, limbers or other materials, in
accordance with Relevant drawings and as instructed by Owner/Engineer shall be
constructed.
The mortar lining is strongly bonded with the pipe wall at all places. However, near the spigot
end due to rough handling of pipes or on account of incidental shock loads the mortar lining
may get damaged over a small area. Such damages if taken place shall be immediately
identified and repaired before installation. When repairing damaged cement-mortar-lining,
the following shall be adhered to:
I. Materials required
The damaged lining shall be removed with hammer and chisel, with due care without
disturbing the surrounding lining. Contractor shall supply protective spectacles for workmen
to prevent penetration of cement fragments into their eyes.
245
III. Composition of repair mortar
V. Emulsions:
One part of acrylic emulsion, four parts of potable water Firstly the dry sand and the dry
cement shall be mixed separately. The acrylic emulsion shall be added to the water stirring
constantly(The container for acrylic emulsion should be resealed at once after use and
stored in a cool place) Small quantities of the treated water shall be gradually added to the
cement and sand mixture mixed thoroughly. Care shall be taken not to prepare too large
quantity of cement to avoid premature hardening.
Any loose sand from the areas to be repaired shall be brushed off. Moisten the areas under
repair and surrounding areas with water but avoid water accumulations. Mortar is to be
applied to cleaned areas and the lining surface is to be smoothened.
In order to ensure faultless hardening of cement it is recommended that the repaired area to
be covered temporarily with plastic sheet. In the case of diameters exceeding DN 300 it is
possible that after cutting off a piece the new spigot end has become out of round. On
account of the elastic and plastic properties of ductile iron, it is possible to re-round these
pipe ends. This shall be done on site by means of a hydraulic or mechanical jack, acting
from inside and pressing outwards or by using press acting from outside the pipe and
pressing inwards by the contractor.
In order to avoid damage to the cement mortar lining it is recommended that hardwood ads
of shape to match the pipes internal diameter be used. The re-rounding device should
remain in place during assembly. If necessary the manufacture may consulted for
resounding.
Thrust blocks shall be provided, to counteract hydraulic thrust, at places wherever directed
by Engineer in charge
3.3.7 Jointing
Jointing for pipes and fittings/specials shall be done in accordance with the relevant
specifications for DI pipes and DI fittings and as recommended by manufacturer. The
recommended bolting torque to be followed for assembling flanges as specified in
manufacturer instructions.
Testing and commissioning of pipes shall be done in accordance with the relevant
specification.
246
3.3.9 Backfilling
Trenches shall be backfilled with approved selected excavated material only after the
successful testing of the pipeline as directed by engineer. The tamping around the pipe shall
be done by hand or other hand-operated mechanical means. The water content of the soil
shall be as near the optimum moisture content as possible. Filling of the trench shall be
carried out simultaneously on both side of the pipe in such a manner that unequal pressure
does not occur.
Backfilling shall be done in layers not exceeding 30 cm. Each layer shall be consolidated by
watering, ramming, care being taken to avoid damage to the pipeline. Where timbers are
placed under the pipeline to aid alignment, these timbers shall be removed before backfilling.
Applicable Codes
The manufacturing, testing, supplying, laying, jointing and testing at worksites of HDPE
pipes shall comply with IS: 4984-1995 all currently applicable statutes, regulations,
standards and amendments and others as follows;
Colour
Materials
The material used for the manufacture of pipes should not constitute toxicity hazard, should
not support microbial growth, should not give rise to unpleasant taste or odour, cloudiness or
discoloration of water. Pipe manufacturers shall obtain a certificate to this effect from the
manufacturers of raw material by any internationally reputed organization as per the
satisfaction of the Engineer-in-Charge in charge.
247
Raw Material
(a) Resin used to manufacture the HDPE pipes shall be 100% virgin PE Black pre
compounded confirming to IS: 4984, IS: 7328 and ISO: 4427-2007 (latest
version).The resin proposed to be used for manufacturing of the pipes should also
comply with the following norms as per ISO 9080-2003 (latest version).
(b) The resin should also have been certified by an independent laboratory of
international repute like Bodycote / Slevan / Advantica for having passed 10,000
hour-long term hydrostatic strength (LTHS) test extrapolated to 50 years to show that
the resin has a minimum MRS of over 10MPa. There should not be any brittle knee
at80OC before 5000 hours. Internal certificate of any resin manufacturer will not be
acceptable.
(c) Certificate from reputed organization or Raw material supplier for having passed the
full scale rapid crack propagation test as per ISO 13478. High IS 9845 Method of
analysis for the determination of specific and/or overall migration of constituents of
plastics material and articles intended to come into contact with foodstuffs IS
10141Positive list of constituents of polyethylene in contact with food stuffs,
pharmaceuticals and drinking water. IS 10146 Polyethylene for its safe use in contact
with foodstuff, Pharmaceuticals and drinking water. Density Polyethylene (HDPE)
used for the manufacture of pipes shall conform to designation PEEWA-50-T- 003 of
IS 7328. HDPE conforming to designation PEEWA-50- T-003 of IS: 7328 may also
be used with the exception that melt flow rate (MFR) shall not exceed 1.10 g/10
min.In addition the material shall also conform to clause 5.6.2 ofIS:7328.
(d) The specified base density shall be between 940 kg/ m³ and 958 kg/ m³ (both
inclusive) when determined at 27°C according to procedure prescribed in IS 7328
The value of the density shall also not differ from the nominal value by more
than3kg/m³asper5.2.1.1ofIS7328.TheMFRofthematerialshallbebetween
0.20 and 1.10(both inclusive) when tested at 190°C with nominal load of 5 kgf as
determined by method prescribed in IS 2530. The MFR of the material shall also be
within ± 20percent of the value declared by the manufacturer.
(e) The resin shall be compounded with carbon black. The carbon black content in the
material shall be within 2.5 ±0.5% and the dispersion of carbon black shall be
satisfactory when tested as per IS: 2530.
Anti-oxidant
The percentage of anti-oxidant used shall not be more than 0.3 percent by mass of finished
resin. The anti-oxidant used shall be physiologically harming less and shall be selected from
the list given in IS: 10141
Reworked Material
No addition of Reworked/ Recycled Material from the manufacturer’s own rework material
resulting from the manufacture of pipes is permissible and the vendor is required to use only
100% virgin resin compound.
The outside diameter of pipes, tolerance on the same and ovality of pipe shall be as given in
table 2 of IS 4984. Ovality shall be measured as the difference between maximum outside
diameter and minimum outside diameter measured at the same cross section of the pipe,
at
248
300 mm away from the cut end. For pipes to be coiled the ovality shall be measured prior to
coiling. For coiled pipes, however, re-rounding of pipes shall be carried out prior to the
measurement of ovality.
Detectability
HDPE Pipes shall be detectable when buried underground, by providing an insulated copper
wire having minimum diameter of 1.20 mm, firmly attached along the entire length of pipe.
To avoid theft or dislocation during handling / laying or earth refilling in trench, the insulated
Copper wire shall be firmly fixed on the outer surface of HDPE pipe at Pipe manufacturer’s
works through external adhesion or co-extrusion or any other appropriate method.
The length of straight pipe used shall be more than 6 m or as agreed by Engineer-in-Charge
in charge. Short lengths of 3 meter (minimum) up to a maximum of 10% of the total supply
may be permitted.
Coiling
The pipes supplied in coils shall be coiled on drums of minimum diameter of 25 times the
nominal diameter of the pipe ensuring that kinking of pipe is prevented. Pipe beyond 110mm
dia shall be supplied in straight length not less than 6m.
Workmanship / Appearance
Pipes shall be free from all defect including indentations, delaminating, bubbles, pinholes,
cracks, pits, blisters, foreign inclusions that due to their nature degree or extent detrimentally
affect the strength and serviceability of the pipe. The pipe shall be as uniform as
commercially practicable in colour opacity, density and other physical properties as per
relevant IS Code or equivalent International Code. The inside surface of each pipe shall be
free of scouring, cavities, bulges, dents, ridges and other defects that result in a variation of
inside diameter from that obtained on adjacent unaffected portions of the surface. The pipe
ends shall be cut clearly and square to the axis of the pipe. IS 4984:1995 will be followed for
visual appearance.
During handling, transportation, storage and lowering, all sections shall be handled by such
means and in such a manner that no distortion or damage is done to the section or to the
pipes as a whole. The following procedures should be followed so as to eliminate potential
damage to pipes and fittings and to maintain maximum safety during unloading, lifting and
lowering.
• Pipes must not be stored or transported where they are exposed to heat sources
likely to exceed60oC.
• Pipes shall be stored such that they are not in contact with direct sunlight, lubricating
or hydraulic oils, petrol, solvents and other aggressive materials.• Scores or
scratches to a depth of greater than 10% or more of wall thickness are not
permissible; any pipes having such defects should be strictly rejected.
• PE pipes should not be subjected to rough handling during loading and unloading
operations. Rollers shall be used to move, drag the pipes across any surface.
249
• Only polyester webbing slings should be used to lift heavy PE (>315mm) pipes by
crane. Under no circumstances, chains, wire ropes and hooks are used on PE pipes.
• Pipes shall not be dropped to avoid impact or bump. If any time during handling or
during installation, any damage, such as gouge, crack or fracture occurs, the pipe
shall be repaired if so permitted by the competent authority before installation.
• During coiling care should be taken to maintain the coil diameter at or above the
specified minimum to prevent kinks. Coiling shall be done when the pipe attains the
ambient temperature from the extruder. In uncoiling or recoiling care should be taken
that sharp objects do not scour the pipe.
• When releasing coils, it must be remembered that the coil is under tension and must
be released in a controlled manner. The end of the coil should be retained at all
times, then the straps released steadily, one at a time. If the coil has bands at
different layers of the coil, then they should be released sequentially starting from the
outer layers. The amount of the energy locked up in the coil will depend on the size
of the pipe, the SDR of the pipe, and the size of the coil.
• Pipes manufactured at factory are to be carried to the site of work directly or stacked
suitably and neatly along the alignment/road side/elsewhere near by the work site or
as directed by the Engineer-in-Charge.
• Damages during transit, handling, storage will be to the Contractor’s account and
replacement for such pipes has to be made by the Contractor without any extra cost
as directed by the Engineer-in-Charge.
• Each pipe shall be thoroughly checked for any damages before laying and only the
pipes which are approved by the Engineer-in-Charge shall be laid.
• While installing the pipes in trenches, the bed of the trench should be level and free
from sharp edged stones. In most cases, the bedding is not required, as long as the
sharp and protruding stones are removed, by sieving the dug earth, before using the
same a backfill material. While laying in rocky areas suitable bed of sand or gravel
should be provided. The fill to about 10 to 15 cm above the pipe should be fine sand
or screened excavated material. Where hard rock is met with, bed concrete M15,
15cm or 20cm thick sand bed as approved by the Engineer-in-Charge may be
provided
• As PE pipes are flexible, long lengths of fusion-jointed pipes having joints made
above ground can be rolled or snaked into narrow trenches. Such trenches can be
excavated by narrow buckets.
250
• During the pipe laying of continuous fusion jointed systems, due care and allowance
should be made for the movements likely to occur due to the thermal
expansion/contraction of the material. This effect is most pronounced at end
connections to fixed positions (such as valves etc) and at branch connections. Care
should be taken in fixing by finishing the connections at a time the length of the pipe
is minimal (lower temperature times of the day.)
• For summer time installations with two fixed connection points, a slightly longer
length of PE pipe may be required to compensate for contraction of the pipe in the
cooler trench bottom.
• The final tie-in connections should be deferred until the thermal stability of the
pipeline is achieved.
• The flexibility of polyethylene pipes allows the pipe to be cold bend. The fusion
jointed PE pipe is also flexible as the plain Pipe. Thus the total system enables
directional changes within the trench without recourse to the provision of special
bends or anchor blocks. However, the pipe should not be cold bend to a radius less
than 25 times the OD of the pipe.
• Provision should be made at all heavy fittings installation points for supports (such as
anchoring of the flange in the soil) for the flange joint to avoid the transfer of valve
wheel turning torque on to the PE flange joint.
• PE pipe is lighter than water. Hence care should be taken for normal installations
where there could be a possibility of flooding of the trench thus the trench shall be
kept free of water till the jointing has been properly done
• When flooded, some soils may lose cohesiveness, which may allow the PE pipe to
float out of the ground. Several design checks are necessary to see if groundwater
flotation may be a concern. Obviously, if the pipeline typically runs full or nearly full of
liquid, or if groundwater is always below the pipe, flotation may not be a significant
concern.
• However, weights by way of concrete blocks (anchors) are to be provided so that the
PE pipe does not float when suddenly the trench is flooded and the soil surrounding
the pipe is washed away. Thus site conditions study is necessary to ensure the
avoidance of flotation.
Jointing of Pipes
The pipe shall have Electro-fusion jointing system that shall provide for fluid tightness for the
intended service conditions.
251
Bedding, Backfilling and Compaction
Bedding
In case of sandy strata no separate bedding is required. However the bottom face /trench
bed where pipe shall be placed shall be compacted to provide a minimum compaction
corresponding to 95% of maximum dry density. The pipe bedding should be placed so as to
give complete contact between the bottom of the trench and the pipe. The minimum cover
over buried pipe should be 1 m.
Back Filling
Backfilling should be placed in layers not exceeding 15cm thickness per layer, and should be
compacted to a minimum of 95% maximum dry density. The refilling should be done on both
sides of pipe together & height difference in earth fill on each side should not be more to
cause lateral movement of pipe. Most coarse grained soil are acceptable. This may
comprise of gravel or sand. However silty sand, clayey sand, silty and clayey gravel shall not
be used unless proposed to be used in conjunction with gravel or cleans and.
It is very important that the pipe zone backfill material does not wash away or migrate in to
the native soil. Likewise, potential migration of the native soil in to the pipe zone backfill must
also be prevented.
Heavy earth moving equipment used for backfilling should not be brought until the minimum
cover over the pipe is 90 cm in the case of wide tracked bulldozers or 120cm in the case of
wheeled roaders or roller compactors.
Compaction
Vibratory methods should be used for compaction. Compaction within distances of 15cm to
45 cm from the pipe should be usually done with hand tempers. The backfill material should
be compacted not less than 95% of maximum dry density.
Restoration
All excavated roads/streets are to be restored to its original condition by making the same as
previous.
Thrust Block
RCC thrust block should be suitably designed & provided at bends and at places of
reduction in cross section to take care of thrust
All HDPE fittings/ specials shall be of minimum PN 6.0 or above Pressure Class unless
specified otherwise, fabricated in accordance with IS: 8360 (Part I& III). PE Injection molded
fittings shall be as per IS: 8008 (Part I to IX). All fittings/specials shall be fabricated or
molded at factory only. No fabrication or molding will be allowed at site, unless specifically
permitted by the Engineer-in-Charge. Fittings will be welded on to the pipes or other fittings
by use of Electrofusion process.
252
Bends
HDPE bends shall be plain square ended conforming to IS: 8360 Part I & III Specifications.
Bends shall be molded.
Tees
HDPE Tees shall be plain square ended conforming to IS: 8360 Part I & II Specifications.
Tees may be equal tees or reduced take off tees. Tees shall be molded.
Reducers
HDPE Reducers shall be plain square ended conforming to IS: 8008 Part I & VII
Specifications. Reducer must be molded.
HDPE Stub ends shall be square ended conforming to IS: 8008 Part I & VI Specifications.
Stub ends will be welded on the pipe. Flange will be of slip on flange type as described
below.
Slip-On Flanges
Slip-on flanges shall be metallic flanges covered by epoxy coating or plastic powder coating.
Slip-on-flanges shall be conforming to standard mating relevant flange of valves, pipes etc.
Nominal pressure rating of flanges will be PN10.
Electro Fusion Tapping Saddle, Branch Saddle & Electro Fusion fittings:
a. All the Electro fusion fittings should be manufactured with top quality virgin
precompounded PE 100 resin which should be compatible with the distribution
mains.
b. The products shall comply with the requirements of EN 12201-3, EN 1555-3 or ISO
8085-3.
d. The fittings shall have the approval from any three Agencies like KIWA, DVGW, and
WRC-NSF, U.K. CIPET etc.
e. All the products shall be manufactured by injection molding using virgin compounded
PE 100 polymer having a melt flow rate between 0.2- 1.4 grams/10minutes and shall
be compatible for fusing on PE 100 distribution mains manufactured according to the
relevant national or international standards. The polymer used should comply with
the requirements of EN 12201-1.
h. The heating coils contained in each individual saddle should be so designed that only
one complete process cycle is necessary to fully electro fuse the fitting to the
adjoining pipe or pipeline component as applicable. The heating coils shall be
terminated at terminal pins of4.0 or 4.7 millimeter diameter.
253
i. No heating element shall be exposed and all coils are to be integral part of the body
of the fitting.
j. The EF tapping / branch saddles should be fixed by fixation device and shall be
achieved by external or integral clamping device.
k. The cutter should be designed in such a way that the cut coupon is not allowed to fall
into the pipeline and is retained inside the body of the cutter.
l. A limited path style fusion indicator acting for each fusion zone as visual recognition
of completed fusion cycle should be incorporated into the body of each fitting near
the terminals. The fusion indicators should not allow the escape of the molten
polymer through them during or after the fusion process.
m. All the sockets in the electro fusion fittings should include a method of tapping
controlling the pipe penetration (pipe positioner/stopper).
n. All the electro fusion products should be individually packed in transparent protective
bags to allow easy identification without opening the bag and must clearly indicate its
contents
o. The brand name, size, raw material grade, SDR rating and batch identification arête
be embedded as part of the injection molding process. Each fitting should also be
supplied with a Data Card or stickers with appropriate barcode as well as manual
setting information for data transfer purpose.
The fusion jointing process is to be carried out is as per the procedure outlined in
theDVS2202 standard, if not available equivalent standards acceptable to employer.
A protocol for each fusion joint to be printed to ensure the joint process carried out is
error free. The electro fusion machine shall have the facility to record & make print for
each joint.
The related pipe jointing accessories such as rotary pipe cutter, Universal clamping
tools, Pipe cleaners, Pipe peelers supplied by the same electro fusion fitting/machine
supplier shall be used to ensure perfect jointing. The usage of tapping tools such as
taping keys, supplied by the same electro fusion fitting /machine supplier must be
used to ensure perfect tapping of mainlines.
The piping system will be tested as per the guidelines given by ISO standard. The
guideline shall be furnished by the supplier of electro fusion fittings, tools and
machines.
254
Hydraulic Testing
Pipes shall be given different hydraulic tests for ensuring quality of manufacture as per
clauses of Standard Specification.
Two or more PE specials coming at one place (like PE Tee, Reducer, Flanged etc,) shall be
jointed at contractor’s workshop and transported to the site of works for final installation with
proposed PE pipelines. In no case, jointing of three or more welds in one place, at site will
bellowed.
Manuals
Flanges
All flanges employed in the project must be compatible whatever material used.
Marking
The pipes should be preferably transported by road from the factory and stored as per the
manufacturer specifications to protect damage.
Length:
i. For diameter 90 mm and 110 mm :100 meter (If pipe is supplied in length less than
100 m than cost of extra joints will be borne by the contractor)
ii. For diameter more than 110 mm: minimum 6 meter.
(Tolerance as per IS4984)
255
9. Special Test : Notch hydraulic Test for the HDPE pipe made from PE-100 grade raw
material as per ASTM 1474 OR ISO 13479 at manufacturers laboratory or independent
laboratory and should pass the Hydraulic test as per IS:4984:1995 for a minimum 165
Hours. The test reports shall not be more than three months old. Pipe shall convey water
under variable temperature conditions ranging from 4 degree centigrade to 45 degree
centigrade.
11. Quality Assurance: Quality Assurance Plan shall be got approved from the
employer before production start.
BIS specifications.
Inspection &Testing:
The inspection and testing of the sample pipes shall be carried out as per relevant IS and/or
ISO standards (latest version) by the CEIL (Certification Engineers International Ltd.) or
CIPET (Central Institute of Plastic engineering & Technology) or any other agency approved
by the Concerned department/ Third party in the manufacture’s works before dispatch and /
or picking random samples of pipe from the worksite.
Sectional tests
After laying and jointing the pipeline shall be tested for tightness of barrels and joints, and
stability of thrust blocks in sections approved by the Engineering- Charge in Charge. The
length of the sections depends on the topographical conditions. Preferably the pipeline
stretches to be tested shall be between two chambers (air valve, scour valve, bifurcation,
other chamber).At the beginning, the Contractor shall test stretches not exceeding 1 km.
After successful organization and execution of tests the length may be extended to more
than 1 km after approval of the Engineer-in-Charge in Charge. The hydraulic testing shall
have to be commenced immediately after laying and jointing of 1 km reach is completed.
The water required for testing shall be arranged by the contractor himself. The Contractor
shall fill the pipe and compensate the leakage during testing. The Contractor shall provide
and maintain all requisite facilities, instruments, etc. for the field testing of the pipelines. The
testing of the pipelines generally consists in three phases: preparation, pre-test/saturation
and test, immediately following the pre-test. Generally, the following steps are required which
shall be monitored and recorded in a test protocol.
256
• If the pressure gauge cannot be installed at the lowest point of the pipeline, an
allowance in the test pressure to be read at the position of the gauge has to be made
accordingly
• Slowly filling the pipe from the lowest point(s).
• the water for this purpose shall be reasonably clear and free of solids and suspended
matter
• Complete removal of air through air valves along the line.
• Closing all air valves and scour valves.
• Slowly raising the pressure to the test pressure while inspecting the thrust blocks and
the temporary anchoring.
• Keeping the pipeline under pressure for the duration of the pre-test / saturation of the
lining by adding make-up water to maintain the pressure at the desired test level.
Make up water to be arranged by Contractor himself at his own cost.
• Start the test by maintaining the test pressure at the desired level by adding more
make-up water; record the water added carefully and the pressure in intervals of
15minutes at the beginning and 30 minutes at the end of the test period. The pipeline
stretch will pass the test if the water added during the test period is not exceeding the
admissible limits. No section of the pipe work shall be accepted by the Engineer-in-
Charge in Charge until all requirements of the test have been obtained.
Back filling
Back filling of pipeline should be placed in layers not exceeding 15 cm thickness per layer,
and should be compacted to a minimum of 95% maximum dry density. The refilling should
be done on both sides of pipe together& height difference in earth fill on each side should
not be more to cause lateral movement of pipe completed. Water used for testing should not
be carelessly disposed off on land which would ultimately find its way to trenches on
completion of a satisfactory test any temporary anchor blocks shall be broken out and stop
ends removed. Backfilling of the pipeline shall be completed.
After testing and commissioning the contractor shall flush the pipes with a velocity not less
than 1 m/s or as approved by the Engineer-in-Charge in Charge. Disinfection of drinking
water pipelines should be done by Contractor.
257
PART E - MECHANICAL STANDARD SPECIFICATION
1.1 General
Pumps shall be vertical and shaft-driven by vertical-shaft motors. Impellers shall be of the
mixed or axial-flow multi-stage type, driven at a maximum speed of 1450 rpm unless
otherwise specified.
Operation of pumps shall be automatic with working and standby pumps operated in rotation
such that no pump shall be operated continuously for longer duration.
The minimum clearance between adjacent pumps and between pump and wall shall be as
per Hydraulic Institute Standards.
For all the pumps the selected model shall be such that the operating point shall lie nearest
to maximum efficiency point but towards the left of the maximum efficiency point.
The impeller diameter selected shall be such that there shall be a minimum of one diameter
higher and one diameter lower size impeller is available for all the pumps.
The pump installation shall include MS galvanized suction strainer, suction bell mouth,
suitable length column pipe, discharge head, motor stool, lower stool, all the accessories, etc
complete.
The total suspension length shall be from suction point at bell mouth up to delivery point at
common header as per design. The vertical column shall be suitably supported and
anchored to prevent vibrations /movement.
The pumps shall confirm to IS: 1710 and IS: 5120. The pumps shall be capable of handling
raw water from a reservoir with expected turbidity of more than 5000 PPM.
Vertical-shaft driving motors shall be mounted on the discharge head above the discharge
bend. Unless otherwise specified or approved, they shall be of the hollow shaft type, fitted
with an axially-adjustable thrust bearing designed to carry the combined weight of pump and
motor rotating parts, the drive shaft with couplings, and hydraulic loadings.
Support bearings shall be provided between each impeller stage. The impeller shaft shall be
corrosion-resistive low-alloy steel, designed for low stress and long life.
The drive-shaft couplings shall be designed to preserve true shaft alignment in all operating
conditions, and shall be close to bearings. Coupling design shall provide for accurate
assembly and re-assembly within the limits of the permissible end-float of the shaft.
The drive shaft and couplings shall be designed to withstand the maximum accelerating
torque of the motor, with a factor of safety of at least two. When required, the Contractor
shall provide his design calculations to demonstrate that the shaft size chosen meets the
requirement for safety factor given in the paragraph above.
258
That accumulated air shall not be passed to the delivery pipe work on starting. If draining the
column pipe on pump stopping could result in reverse rotation of the pump, means shall be
incorporated to ensure that the pump cannot be restarted before reverse rotation stops.
The design, manufacture and performance of the pumps shall comply with all currently
applicable statutes, regulations and safety codes in the locality where the equipment will be
installed. The equipment shall also conform to the latest applicable Indian or equivalent
international standard. Some of the relevant standards are:
The hydraulic design of the pump should meet the requirements of high efficiency, low
submergence, high reliability, optimum system design.
The shut off head shall be at least 110% of the total head and maximum of 130 % of total
head.
The first critical speed for the pump rotor shall be at least 30% above the operating speed.
Pumps shall run smooth without undue noise and vibrations. The velocity of vibrations and
the noise level shall be as per latest IS code. To detect excessive vibrations exceeding
design limits as per standards, three axis vibration monitors shall be installed on the motor at
top. The motor shall stop automatically when the vibration exceeds the limits.
The power rating of the pump motor shall be higher of the following:
115% of the power input to the pump at duty point at a speed corresponding to given
frequency.
Maximum power input while operating single pump corresponding to the speed of 50
Hz.
The pumps of a particular category shall be identical. Components of identical pumps shall
be interchangeable.
All pumps shall be provided with suitable protections including protection against overload,
bearing failure, increase in bearing temperature etc.
All accessories required for proper and safe operation shall be furnished with the pumps.
259
1.4 Material of Construction
Note: Material test certificated shall be provided for all the components.
The discharge-head shaft seal shall be selected for long life with minimum maintenance, and
may be of the mechanical or packed-gland type. Packed glands shall have an intermediate
lantern ring, supplied with filtered water. The pressure limit of mechanical seals shall be at
least 50% greater than the pump closed-valve delivery pressure. Provision shall be made to
return to the pump well any water leaking past the head seal.
Bearings shall be spaced at the intervals needed to ensure vibration less running at all
possible pump operating speeds, with a maximum distance of 2.5m apart. Guide bearings
shall be of resilient synthetic rubber, mounted in spider bearing-retaining assemblies.
260
Transmission shafts shall be of forged steel, with ground finish. The shaft sections shall be
connected by mild-steel couplings and shall have machined left-hand or right-hand threads,
depending on the direction of rotation of the pump, to tighten during pump operation. Shaft
sections shall be in lengths chosen to be the same as the guide-bearing spacing. The butting
faces of each section shall be machined square to the axis of the shaft. Means shall be
provided to supply filtered water to each bearing.
a) that filters used are duplex type so that one filter can be cleaned while the second
remains in-service;
b) that if required by the bearing design, a filtered water supply is provided to each
bearing before the shaft begins to rotate.
c) that if the installed arrangement makes any reverse rotation possible on pump
stopping, if required by the bearing design a filtered water supply is provided to each
bearing until reverse rotation stops.
Column pipe shall be steel, coated internally and externally with an epoxy bituminous
solution or other approved protective coating. The column pipe shall comprise a number of
flanged sections, designed to suit the installation requirements. The sections shall be
connected by welded-on flanges. The butting flange faces of the riser pipe shall be
machined square to the axis of the pipe. The column pipe shall be provided with a long-
radius flanged discharge bend at the top end. The bend shall incorporate the shaft sealing
arrangement.
1.8 Testing
The pumps shall be subjected to inspection by PRED / Third Party. The performance of all
the pumps shall be demonstrated during factory testing as per curves submitted during
tendering. The tolerance on efficiency shall be with zero negative tolerance and not 5% as
indicated in IS: 5120. The pumps shall be tested over the entire range covering from shut off
head to maximum flow. The duration of test shall be minimum one hour. Minimum 5 readings
approximately equidistant shall be taken for plotting the performance curve.
In addition factory testing a dry run test shall also be carried out at site after installation of
pumps to test the vibration characteristics, bearing performance etc. and to determine if the
pumps have been properly erected. A vent test also be conducted to verify the operating
characteristics, water tightness of the system etc. as per relevant IS codes.
1.9 Rejection
If on shop testing, the guaranteed efficiency considering the zero percent negative tolerance
is not met, the pump shall stand rejected.
The Tenderer’s to include a detailed technical data sheet with their technical proposal giving
all the details of pumps.
261
2.0 INDUCTION MOTORS FORPUMPS:
2.1 General
The motors for all the pumps shall be of suitable HP, 1450 RPM synchronous speed, TEFC,
IP: 55 protection, squirrel cage induction motors continuous rated with “F” class insulation
conforming to IS: 325 with latest amendments. The motors shall be suitable for operation on
3 Phase 50 Hz AC supply indoor application with variations as listed and shall be suitable for
installation at an altitude as per site condition and 50o C design temperature.
Motors for VT pumps shall be of hollow shaft type vertically mounted so as to have direct
coupling of pump shaft to the motor shaft. The total load of rotating parts shall be on top
thrust bearing placed on top of the motors.
The design, manufacture and performance of the motor shall comply with all currently
applicable statutes, regulations and safety codes in the area where the motors will be
installed.
Unless otherwise specified the motors shall conform to the latest applicable Indian
Standards as below:
IS: 900 Code of practice for installation and maintenance of induction motors.
2.3 Performance
The motors shall be suitable for neutral connected FCMA soft starter. All six terminals shall
be brought for this purpose. A separate terminal box shall be provided for the starter. Motor
shall also be suitable for direct on line staring and the staring current shall be limited to 5xIr.
Terminal shall be suitable for 25 KA fault level. Pull out torque of motor shall not be less than
2.1 times the rated torque. Starting torque shall be more than 0.80 times the rated torque.
The starting equipment offered shall be of proven design and shall be robust and can
withstand number of starts in day. All the control equipment for selection of pumps to be
started, and all interlock, indication and alarm and annunciation circuits shall be included in
the scope of supply. All the protection and control circuits of starting equipment shall be
incorporated in the system.
The motors shall be designed to allow the required number of consecutive starts.
The details to be furnished shall include efficiency and P.F. at no load, 50%, 75% and full
load.
262
Motors shall be capable of giving rated output without reduction in the expected life span
when operated continuously under either of the following cases of supply conditions.
Motors shall be capable of starting and accelerating the load with the applicable method of
starting without exceeding acceptable winding temperature when the supply voltage is 85%
of the rated voltage.
The locked rotor current of squirrel cage motors shall not exceed 600% rated current.
Terminal box shall be suitable for top and bottom entry of cables. Further it shall be capable
of being turned through 360o in steps of 90o.
Motors shall have grease lubricated ball or roller bearings. Bearings shall be adequate to
absorb axial thrust from the driven load together with any thrust produced by the motor itself.
Bearings shall be capable of grease injection from outside without removal of covers with
motor in running condition. The bearing boxes shall be provided with labyrinth seal to
prevent loss of grease or entry of dust.
Two earth terminals shall be provided for each motor. These shall be located outside the
terminal box. These terminals shall preferably be on diametrically opposite points. A
separate earth terminal shall be provided inside the terminal box.
The motor shall be provided with roller bearings at bottom and 2 Nos. of angular contact
bearing at top to take care of the thrust due to self weight of the rotor and provided with
labyrinth ring seal in the bearing housing to prevent the entry of dust or water as per IS:
4691 standards. The rotor shall be dynamically balanced.
2.5 Testing:
2.7 Protections
The motors shall be provided with suitable protections including protection against reverse
rotation, dry run protection, phase sequence change indicators, single phase preventor,
RTD’s, temperature rise protections etc.
263
2.8 Painting:
External parts shall be finished and painted to produce a neat and durable surface, which
will prevent rusting and corrosion. The surface shall be degreased and all rust, sharp edges,
scales be removed and treated with two coats of primer and finished with two coats of epoxy
based final paint. Unless otherwise agreed the motors shall be painted with shade 631 of IS:
5.
3.1 General
The pumps proposed shall be suitable for installation at site whose altitude is as per site
level and shall work under maximum ambient temperature of 50oC. The pump and motor
shall be capable of providing the required output when working under above conditions.
The design, manufacture and performance of the pumps shall comply with all currently
applicable statutes, regulations and safety codes in the area where the pumps will be
installed and shall confirm to IS: 1520. The performance of pumps shall be guaranteed as
per IS: 5120 and IS: 9137 with zero negative tolerance. The pump set shall be coupled to 3
Phase, TEFC horizontal mounted induction motor. The synchronous speed of pump shall not
be more than 1500RPM.
i. Operation of pumps shall be automatic with working and standby pumps operated in
rotation such that no pump shall be operated continuously for longer duration.
ii. The minimum clearance between adjacent pumps and between pump and wall shall
be as per Hydraulic Institute Standards.
iii. For all the pumps the selected model shall be such that the operating point shall lie
nearest to maximum efficiency point but towards the left of the maximum efficiency
point.
iv. The impeller diameter selected shall be such that there shall be a minimum of one
diameter higher and one diameter lower size impeller is available for all the pumps.
v. The Impeller shall be enclosed type, securely keyed to the shaft. Means shall be
provided to prevent losing operation including rotation in reverse direction.
vi. The pump shall be provided with renewable type casing ring.
vii. The first critical speed for the pump rotor shall be at least 30% above the operating
speed.
viii. Replaceable shaft sleeves shall be provided to protect the shaft where it passes
through stuffing boxes.
ix. Stuffing boxes shall be of such design that they can be repacked by removing the
gland and lantern ring.
264
x. Pump shall be furnished complete with flexible coupling. Coupling guard made of
expanded metal bolted to the base plate shall be furnished.
xi. The base plate for pump and motor shall be common. Suitable holes shall be
provided in the foundations for fixing of bolts and grouting. Foundation bolts shall be
complete with nuts and washers.
xii. The gland and cooling water shall be collected and led by suitable pipeline up to the
sump pit.
xv. The pumps of a particular category shall be identical. Components of identical pumps
shall be interchangeable.
xvi. The pump shall be capable of developing the required total head at rated capacity for
continuous operation. The pumps shall operate satisfactorily at any point on the H-Q
characteristic curve over a range of 50% to 130%capacity.
xvii. The NPSH required shall be at least 1.0 m less than the NPSH available under all
operating conditions.
xviii. The shut off head shall be at least 110% of total head and maximum of130%.
xix. Pumps shall run smooth without undue noise and vibrations. The velocity of
vibrations and the noise level shall be as per latest IS code. To detect excessive
vibrations exceeding design limits as per standards, three axis vibration monitors
shall be installed. The motor shall stop automatically when the vibration exceeds the
limits.
xx. The pumps shall be with zero negative tolerance (and not 5% as indicated in IS -
5120).
xxi. The total head capacity curve shall be continuously rising towards the shut-off point
with the highest head at shut-off.
xxii. The pump that works at the best efficient point for specified duty conditions would
only be selected. However the pump should have a very good efficiency when it
works at lower heads due to higher level in the sump.
xxiii. Tappings at suction and discharge nozzles shall be provided for pressure gauge
connection. Casing drain connection with stainless steel collared plug shall be
provided.
265
The power rating of the pump motor shall be higher of the following:
115% of the power input to the pump at duty point at a speed corresponding to given
frequency.
Maximum power input while operating single pump corresponding to the speed of 50
Hz.
3.5 Testing
The pumps shall be subjected to inspection by PRED / Third Party. The performance of all
the pumps shall be demonstrated during factory testing as per curves submitted during
tendering. The pump efficiency shall be demonstrated with zero negative tolerance (and not
5% as indicated in IS: 5120). The pumps shall be tested over the range covering from shut
off head to maximum flow. The duration of test shall be minimum one hour. Minimum 5
readings approximately equidistant shall be taken for plotting the performance curve.
In addition to above, dry run test after installation shall be carried out to test the vibration
characteristics, bearing performance etc. and to determine if the pumps have been properly
erected. A vent test also be conducted to verify the operating characteristics, water tightness
of the system etc. as per latest IS codes.
3.6 Rejection
If on shop testing, the guaranteed efficiency considering the zero percent negative tolerance
is not met, the pump shall stand rejected.
The Tenderer’s to include a detailed technical data sheet with their technical proposal giving
all the details of pumps.
266
4.0 SUBMERSIBLE SUMP DRAINAGE PUMPS
Sump pumps over 1.5kW shall be controlled and started from the supply point. Control shall
be by means of adjustable float level switches mounted near the pump.
Pumps shall be supplied with all necessary pipe work to discharge to surface drainage. Each
pump shall be provided with delivery reflux and isolating valves, and suitable lifting gear for
lowering and lifting the pump from the sump. Pumps weighing 40kg or more shall be lowered
into the sump on guide rails and be located to their respective discharge pipe work with an
angle flange connection and self-locating clamps. Pump impellers shall be designed to pass
solids of the sizes which pass through the inlet ports of the pump and shall be capable of
pumping solids of up to 50mm diameter.
The total head capacity curve shall be continuously rising towards the shutoff with the
highest at the shutoff.
The pump shall run without undue noise and vibration. The power rating of the pump motor
shall not be less than the power required from zero discharge to zero head.
The pump shall be dry pit type with double mechanical seals. The motors shall be provided
with Class F insulation with temperature rise limited to that of Class B insulation. The
degree of protection shall be IP: 55.
The pump shall be suitable to handle turbid water. Both pump and motor shall be provided
with a common shaft.
Delivery pipe of drainage pumps shall be of size 40 NB and shall be as per IS: 1239, heavy
class. The pumping main shall be common for two pumps.
Level switch to start and stop the pump automatically shall be supplied with the pump.
The pump shall be provided with necessary medium duty GI piping, valves, specials etc.
complete so as to discharge the spillages and leakages to nearby natural drain as directed
by Engineer-in-Charge.
The material of construction for different components of the pumps shall be as specified
below;
267
6.0 BUTTERFLY VALVES
Butterfly valves shall be metal seated type and shall confirm to IS: 13095 / BS 5155. Valve
shall be suitable for mounting in any position.
The valve seat shall be of integrally cast or replaceable design. When the valve is fully
closed, the seal shall seat firmly so as to prevent leakage. The seat surfaces shall be
machined smooth to provide a long life for the seal.
All fasteners shall be set flush so as to offer the least resistance possible to the flow through
the valve.
All valve, spindles and hand wheels shall be positioned to give good access for operational
personnel.
The time from fully open to fully closed position and vice versa shall be limited to about 5
minutes. The valve shall be suitable for controlling flows by throttling.
Valves shall be provided with enclosed gear arrangement for ease of operation. The
operation gear shall be such that they can be opened and closed by one man against an
unbalanced head 15% in excess of the maximum specified rating. Valve and any gearing
shall be such as to permit manual operation in a reasonable time and not exceed a required
nm pull of 400 N.
All hand wheels shall be arranged to turn in a clockwise direction to close the valve, the
direction of rotation for opening and closing being indicated on the hand wheels. Hand
wheels shall be provided with an integral locking device to prevent operation by
unauthorised persons.
Suitably designed RCC / CC or structural steel supports shall be provided underneath the
valves.
The Tenderer’s shall submit complete technical data sheets and drawings for the valves.
All butterfly valves including valves on common header and bypass line shall be provided
with electrical actuators for valve operation.
Materials of Construction:
The material of construction for different components of Butterfly valve shall be as below.
Sl.
Component Material
No.
1. Pressure Class Minimum PN : 16 or as per design
2. Body Cast Steel (Conforming to ASTM A216 Gr WCB)
3. Disc Cast Steel (Conforming to ASTM A216 Gr WCB)
4. Seat Ring Stainless Steel: SS ASTM A 743 CF8
5. Shaft Stainless Steel: SS ASTM A 276
6. Seat Stainless Steel: SS ASTM A 276
7. Bearings Teflon
8. Fasteners, Anchors bolts, Stainless Steel : 316
Foundation Bolts etc. both in wet
and dry areas
268
The contractor shall provide test certificates for materials; strength and leakage shall be in
accordance with BS: 5155 or relevant international standards.
Non Return Valves shall confirm to API 600 standards with latest amendments. The valves
shall be suitable for mounting on horizontal pipeline. The internal parts shall be easily
accessible for inspection through inspection hole. Hydraulic passages and doors shall be
designed to avoid cavitation.
The valve flange shall be parallel to each other and flange face should be at right angle to
the valve centerline. Backside of the valve flanges shall be machined or spot faced for
proper seating of bolt head and nut.
Valves shall be of swing type, quick closing and shall be with non-slam characteristics. The
non-slam characteristics shall be achieved by providing suitable combination of door and
hydraulic passages without any external lever / damping arrangement.
Direction of the flow shall be clearly embossed on the valve body. Maximum pressure drop
across the valves shall be 0.4 mwc. Maximum allowable leakage rate shall be 7 cc / hr / mm
diameter.
Suitably designed RCC / CC or structural steel supports shall be provided underneath the
valves.
The Tenderer’s shall submit complete technical data sheets and drawings for the valves.
Material of Construction:
The material of construction for different components of Non Return Valve shall be as below.
Sluice valves on scour lines shall conform to IS: 14846, 2000 or relevant internationally
recognized standards.
They shall be of non-rising spindle type. The valves shall be furnished with a bushing
arrangement for replacement of packing without leakage. They shall also have renewable
channel and shoe linings. The gap between the shoe and channel shall be limited to 1.5 mm.
269
The gate face rings shall be screwed into the gate or alternatively securely pegged over the
full circumference.
All valves, spindles and hand wheels shall be positioned to give good access for operational
personnel.
All hand wheels shall be arranged to turn in a clockwise direction to close the valve, the
direction of rotation for opening and closing being indicated on the hand wheels.
Materials of Construction:
The material of construction for different components of Sluice Valve shall be as below.
The air valves shall be of Ductile Iron material and minimum PN: 10 Class unless specified
otherwise. The valve shall be Single Chamber Triple Function Tamper Proof (Both the
Orifices to be housed in the single chamber) Air Valves with body and cover in Ductile Iron of
Grade GGG50.
All internal parts such as float, shell etc., all cover bolts of austenitic alloy steel, float shall be
of HOSTAFLON and Gaskets and seals of EPDM. Epoxy powder coating (EP-P) shall be
provided inside and outside with colour blue RAL 5005. The valve should be designed for all
the three functions i.e. 1. Large orifice for venting of large air volumes on start up. 2. Large
orifice for intake of large air volumes. 3. Small orifice for discharge of pressurized air during
operation.
The valves should be capable of venting at high velocities up to sound velocity by stabilized
float. For isolation, isolation valve shall be provided resilient seated soft sealing approved
make sluice valve with body, bonnet of Ductile Iron of grade GGG40, wedge fully rubber
lined with EPDM and seals of NBR and the valves should be of vaccum tight and 100% leak
proof with face dimensions as per BS 5163-89/ IS 14846-2000/DIN 3202F4\F5.
The stem sealing should be with torodial sealing rings (Minimum 2 O-rings). All the valves
should be with electrostatic powder coating with inside and outside with pocket less body
passage. The valves shall be supplied with suitable size galvanized bolts and nuts of
required numbers of GKW/KITO/NEXO/TECHMAN or any other equivalent approved brand.
The contractor shall provide test certificates for materials and properties shall be in
accordance with relevant standards.
270
10.0 EOT CRANE
10.1 General:
The intake pumping station, treated water pumping station and booster pumping
stations shall be provided with suitable capacity electrically operated transverse
crane for the required span, height and long travel length including all the
accessories, electrically operated hoist, travelling trolley, lifting chain, hook etc.
complete for electrically hoisting and lowering of pumps, motors and other
equipments etc.
The scope of work includes designing, providing, erecting and commissioning the
crane suitable for electrically operation of designed capacity traversing gantry crane
as specified.
The design, manufacture and performance of the crane and its allied equipment and
material shall comply with all currently applicable statutes regulations and safety
codes in the locality where the crane will be installed.
The equipment shall also conform to IS: 3177 and IS: 807 and relevant international
standards.
The crane shall be of best quality equipped with given capacity standard travelling
trolley, chain pulley block etc.
The chain pulley block shall be of machine cut gears, tested for 50 % over load
capacity and shall have sturdy forged hooks, special alloy load chains, chain for hand
operation all for smooth working without any shocks, all complete.
A traversing cross trolley shall be designed and assembled using standard size RS
girders adequate to withstand to travel in any direction on load with all mechanism
complete. It shall be provided with wheels and trade over two girders. There shall be
adequate room dimensions.
The gantry girders shall be designed and manufactured with two girders frame,
travelling wheel on both ends of the span and shall have an arrangement to operate
with sprocket wheel and chain, suitable for operations from ground level of the pump
house. The steel used for the same shall conform to IS 2062.
271
These girders are to be fitted over corbels using MS plates of adequate capacity and
shall be rigidly fixed in corbels. Girders are to be welded to MS plates. Expansion
allowance for lengthwise girders shall be kept.
Welding quality for the entire unit shall be maintained using standard make welding
rods for duty purpose. All lengthwise girders and frame used for traversing shall be
designed for 150% of the design load, considering the spans, in both direction,
lengthwise and width wise where the crane is to be operated.
On the entire length of girder, both sides, adequate size MS square or standard rail
section shall be designed and used. It shall be welded on both sides of the section to
have homogeneous section. Welding shall be carried out using standard welding
rods for the purpose and it shall be carried out by experienced trained welder having
sufficient experience of this type of work. All excessive welding shall be removed and
then to be ground to requirements.
The entire structure shall have good stability with or without load.
Suitable arrangements at both the ends shall be provided to restrict the travel of the
crane beyond decided limits.
10.4 Performance
The unit shall be capable of satisfactory operation and shall be available for duty as
required in the pump house for maintenance and repairs of pumping machinery,
motor and allied equipment provided in the pump house for functioning as a pumping
station.
10.5 Painting
All the parts of the unit shall have good and smooth finish. It shall be painted to
produce a neat and durable surface which will prevent rusting and corrosion. The
equipment shall be degreased cleared of all rust, sharp edges, scales to be removed
before painting. The Crane structure shall be painted with two coats of red-oxide
metal primer and two coats of enamel paint of approved colour. The electric hoist
and LT - drive units shall be painted with enamel paint approved by Engineer-in-
Charge.
10.6 Tests
All routine tests shall be conducted in manufacture's works and test certificates shall
be produced.
The unit shall be tested for 150% of designed load as per latest IS codes.
Load chain certificate, forged load hook certificate shall be provided along with the
test certificate of chain pulley block provided on the unit.
10.7 Documents
As a part of proposal, the Tenderer’s shall furnish relevant descriptive and illustrative
literature on the components proposed to be provided for the gantry arrangement.
General arrangement drawing showing details of all parts and accessories of EOT
crane.
272
Detailed methodology and note for erection and testing.
10.8 Bearing
Plain or roller type bearings shall be used. Roller bearing shall conform to IS: 5669.
Plain bearing shall be of cast iron or bronze.
10.9 Frame
The frame shall be designed for proper strength and it shall maintain alignment under
all service conditions. The material shall be high tensile, weldable structural steel.
10.10 Lubrication
The block shall be provided with adequate facility for lubrication unless materials with
inherent lubricating properties are used.
10.11 Anchorages
The load chain anchorages associated fittings and framework at the slack end shall
be at least equal in strength to 2.5 times the maximum tension in the load chain when
working load is being lifted.
10.12 Gears
Gears shall be provided for proper strength and for surface durability such as to
afford efficient operation during the guarantee period and thereafter. Material of
construction shall be carbon steel of conforming to IS 1875 and 4367, or equivalent
international Standard.
Chain pulley block shall be provided with an automatic mechanical load brake which
will prevent self lowering of the load. It will arrest and sustain the load in any position
within the working limit. Brake should allow smooth lowering of the load.
10.14 Inspection
The representative of employer shall have access to the works of the manufacturer
for inspecting the material, tests etc.
Test certificate shall be produced for design test, which should be carried on tensile
testing machine to at least 4 times the working load limit without any distortion.
273
10.16 Operational Proof Tests
Each chain pulley block shall be subjected by the manufacturer to a proof load of
1.5 times the working load limit through a length of lift which will ensure that every
part of the block mechanism and each tools of gear comes under load.
Inline magnetic inductive flow meters factory assembled and factory calibrated on a
precision calibration rig only are accepted. Alternate forms of measuring devices like
insertion flow meters, clamp on flow meters, turbine or PD flow meters are not
acceptable
The process connection shall be flanged end connections to ANSI B 16.5 Class 150
lbs up to 600 mm size and above 600 mm and up to 1000 mm flanged to AWWA
Class D (10 bar) pressure rating. Above 1000 mm up to 2000 mm flanges to AWWA
Class B (6 bar) pressure rating.
Electrode Design: Flat elliptical electrodes, solidly fitted and surface polished
Materials of Construction :
Signal Convertor :
Local Display: 2 - line High contrast LCD for actual flow rate, forward, reverse and sum
totalisers (7 - digits), display engg. Units programmable to use defined
unit.
Meter flow range: Fully programmable from front facia of instrument without opening the
cover
Cables: The special cable for signal and the coil supply cable both are
required to be supplied (Refer Note 3)
Sealing : Flow meters shall have protective devices which can be sealed in such a
way that after sealing, both before and after the flow meter has been correctly
installed, there is no possibility of dismantling or altering the flow meter or its
adjustment device without damaging the protective devices.
Meter markings
Flow rate: Minimum, Maximum and transition flow shall be as per relevant standards.
Notes:
If the flow meter size works out to be smaller than the pipeline size, suitable reducers
and expanders shall be provided. The reducers / expanders shall be of MS, smaller
dia end flanged to suit the flow meter flanges and the larger dia end finished for
welding to the pipe. The conical angle of reduction should not exceed 10 Deg. The
bidder should guarantee that installation of such reducers and expanders
immediately before and after the flow meter will not affect the accuracy stated above 275
for the flow meter.
The accuracy of calibration of flow meters at the factory shall be better by a factor of 3 times
better than the guaranteed accuracy as per ISO 9104. This higher accuracy should be
reflected in the calibration certificate of the flow meter
Bidder shall include cable for required length.
All flow meters shall be housed in chamber / room as per approved design.
Power supply to electro-magnetic flow meter - Battery operated with 2 internal batteries
having a life span of 5 years.
Data Loggers
Input: Current (4-20Ma)
Totaliser: Inbuilt
Display: LED display, 5 digit for flow rate & 8 digits totaliser
Logging Time: Programmable Accuracy:0.25% of Full
Scale Datalogging: Memory capacity 512 KB
Communication Port for SCADA ; RS485(Modbus)
Parallel port : For Dot-matrix Printing Conditions:
The offered flow meter should be calibrated at the factory on calibration rigs having an
accuracy at least ten times better than the flow meter accuracy guaranteed. Further the
calibration rig accuracy should be traceable to National / International standards. The
calibration facility should be accredited/certified by an independent authority of
International reputation. This accreditation certificate for the calibration facility should be
furnished along with the offers.
The flow meters shall have arrangements for servicing / repairing without resorting to dismantling the
flanged joints or removing entire unit.
276
12.0 CAST IRON SLUICE GATES /PENSTOCKS:
12.1 General
The construction of sluice gate shall be in accordance with the specification and shall be
generally confirming to IS: 13349. All sluice gates shall be of rising spindle type. The frame
shall be of the flange back type and shall be machined on the rear face to bolt directly to the
machined face of the wall thimble.
Seating faces shall be made of full width, solid section and dovetail strips of stainless steel.
They shall be secured firmly by means of counter sunk fixings in finished dovetail grooves in
the frame and slide faces in such a way as to ensure that they will remain permanently in
place, free from distortion and loosening during the life of the sluice gate.
Sluice gates shall be equipped with adjustable side, top and bottom wedging devices as
required, to provide contact between the slide and frame facing when the gate is in closed
position. The gate shall be operated through suitable lifting mechanism which shall
incorporate suitable gearing if required to keep the torque requirement within 7.0 Kg.m.
Lifting mechanism shall incorporate a strong locking device suitable for use with a padlock or
padlock and chain. The mechanism shall be provided with a suitable position indicator to
show the position of the gate at all times.
The cross section of the thimble shall have the shape of the letter “F”. Lifting lugs shall be
provided for all gates. When sluice gates are provided with flush bottom seals, the wedging
device and facing along the bottom edge of the slide and frame shall be omitted.
A solid square cornered, resilient rubber seal shall be provided on the bottom facing of slide.
The seal shall be securely fastened to the bottom face of the slide by a retainer bar and
stainless steel fasteners. The top surface of the bottom facing of frame shall be flush with
invert of the gate opening. Bottom facing of the slide shall be accurately machined to make
contact with the seal when the slide is closed.
- Surface preparation shall include hand tool cleaning as per IS: 1477, Part 1 and is
6005
- Primer: two packs of zinc phosphate epoxy with DFT of each coat 50μ.
- Undercoat: two packs of titanium dioxide epoxy with DFT of each coat 50μ.
- Finish: two packs of silicate extender epoxy with DFT of each coat 100μ.
All sluice gates shall be provided with electrical actuators for operation.
277
12.2 Material of Construction
The material of construction for different components of the sluice gate shall be as below.
The mixer shall be capable of providing a required velocity gradient to get a uniform blend of
chemical / polyelectrolyte solution. The impeller shall be hydrofoil type and shall have a
minimum of three number of blades. The mixer shall have worm type gear box with axial
type oil lubricated bearings. The mixer shall be driven by an electric motor with IP: 55
enclosure, Class F insulation and temperature rise limited to Class B. Motor shaft and rotor
shall be dynamically balanced.
The pumps for pumping chemical solution / polyelectrolyte solution shall be metering type.
The pump shall be with adjustable dosing rate. The normal design dosing rate shall fall well
below the maximum dosing rate of the pump. The pumps shall have inbuilt pressure relief
valves. Bearings shall be heavy duty antifriction type ball bearings and shall be with splash
lubrication. The pumps shall run smooth without undue noise and vibration. Dosing rate
control shall be through stroke adjustment and dosing rate range shall vary from 0 to 100%.
The pumps shall have flexible couplings and shall be dynamically and statically balanced.
The surfaces shall be sand blasted and given protective coating as detailed.
The motor shall be with IP: 55 enclosure, Class F insulation and temperature rise limited to
Class B.
278
The painting specification for pumps shall be as detailed below;
- Surface preparation shall include hand tool cleaning as per IS: 1477, Part 1 and is
6005
- Primer: two packs of zinc phosphate epoxy with DFT of each coat 50μ.
- Finish: two packs of polyamide cured high build epoxy with DFT of each coat 125 μ.
The pumps for pumping sludge from thickeners to sludge drying beds shall be of positive
displacement progressive cavity screw type. The pumps shall have single helical screw and
shall be driven by suitable capacity motor and inbuilt gear box. Bearings shall be heavy duty
antifriction type ball bearings and shall be oil lubricated. The pumps shall run smooth without
undue noise and vibration. The noise level at 1.0 m distance shall be less than 85 dB. The
pumps shall have an inspection / cleaning window with bolted cover on the suction casing.
The pumps shall have flexible couplings and shall be dynamically and statically balanced.
The surfaces shall be sand blasted and given protective coatings as detailed.
The motor shall be with IP: 55 enclosure, Class F insulation and temperature rise limited to
Class B.
- Surface preparation shall include hand tool cleaning as per IS: 1477, Part 1 and is
6005
- Primer: two packs of zinc phosphate epoxy with DFT of each coat 50μ.
- Finish: two packs of polyamide cured high build epoxy with DFT of each coat 125μ.
279
Sl. Component Material
No.
5. Fasteners, Anchors bolts, Foundation Bolts etc. Stainless Steel : 316
6. Base Plate MS epoxy coated
The air blowers shall be positive displacement twin lobe type compressors i.e. root type.
The blower shall be complete with suction filter, suction silencer, acoustic hood, safety
valves, pressure gauges with snubbers, non return valves, discharge silencers, after cooler
and all other accessories as necessary. The blower shall be driven by an induction motor
connected to blower pulley through a “V” belt covered with a belt guard. The blowers shall be
placed on a firm foundation and the support structure shall be provided with heavy duty type
anti-vibration pads. All the moving parts shall be dynamically balanced. The bearings shall
be of heavy duty type with cylindrical / spherical rollers and shall be oil lubricated.
The safety valve shall be dead weight type and shall operate automatically when the
pressure reaches a preset high value. The blowers shall be provided with acoustic hood to
minimize the noise level. The noise level at 1.5 m distance shall not be more than 85 dB.
Also the blower room including walls, roof, doors, windows, ventilators etc, shall be
acoustically treated to keep the noise level inside the building less than permissible
standards. After coolers shall be of standard make and shall be designed to reduce the
discharge air temperature to less than 50 oC. The air suction for the blower shall be through
air ducts drawing air from outside the building.
The motor shall be squirrel cage type with TEFC IP: 55 enclosure, Class F insulation and
temperature rise limited to Class B.
The material of construction for different components of air blower shall be as below.
The valves shall meet requirements of MSS SP 81. The body shall be devoid of any wedge/
dead pockets to avoid settling of suspended particles and solids in the service fluid. The gate
/ plate shall be precision buffed and the edge contoured to a knife edge. The gate shall move
along / be guided by the seat ring to ensure that it scrapes any deposit / scale, enabling
smooth uninterrupted movement.
Seat shall be so designed that there is no recess / relieved groove to harbour deposition that
could build up and swamp the valve. The design to also incorporate bosses that guide the
gate and avoid deflection, ensuring positive shut-off. The stem shall have double start
threads cut in order to ensure smooth and speedy operation. Gland packing shall offer
280
minimal frictional resistance and precludes external lubrication. As positive sealing element,
the packing shall also include a resilient rubber ring. The knife edge and seat face in flow
path shall be hard faced to a hardness of 400 to 450 BHN to counter erosion. In such cases,
provision shall also be made to ensure the fluid contact with the seat ring is minimal.
The pressure gauges shall be of dial type, stainless steel material and glycerin filled suitable
for connecting to suction / delivery pipes of each pump and shall include nipple, stop cock
and three way cock for cleaning and necessary length of stainless steel tubing. The
pressure gauges shall be connected to the suction / delivery pipes by nipple. The tapping
shall be provided with 15 NB isolating valve and shall include required fittings.
The manually operated hoist shall be suitable for operating on the lower flange of a monorail
(I - Beam). The load chain shall be of alloy steel as per IS: 3109 and shall be heat treated to
give ductility and toughness so that it will stretch before breaking. The chain shall be of
welded construction with a factor of safety not less than 5. The hand chains for the hoisting
and traverse mechanism shall hang well clear of the hook and both the chains shall be on
the same side. Hand chain wheel shall be made from pressed sheet steel and shall be
provided with roller type guarding to prevent snagging and fouling of the chain.
The gearing shall be totally encased and proper lubricating arrangements shall be provided
for bearings and pinions. Gears shall be cut from forged steel blanks and shall confirm to IS:
4460 and pinions shall be of heat treated alloy steel. The trolley track wheels shall be rim
toughened, heat treated carbon steel or low alloy steel or CI and shall be single flanged and
shall have antifriction ball bearings. The wheels shall be machined on their treads to match
the flanges of the track joints.
The travelling trolley frame shall be made of rolled steel confirming to IS: 2062. The side
plates of trolley shall extend beyond wheel flanges, thus providing bumper protection for the
wheels. The two side plates shall be connected by means of an equalizing pin. Axles and
shafts shall be made of carbon steel and shall be accurately machined and properly
supported.
The lifting hooks shall be of forged, heat treated alloy or carbon steel of rugged construction.
They shall be of single hook type provided with a standard depress type safety latch. They
shall swivel and operate on antifriction bearings with hardness races. Locks to prevent
281
hooks from swiveling shall be provided. Hook shall be as per IS: 3815. The brake for the
lifting gear shall be automatic and always in action. It shall be screw and friction disc type
self actuating load pressure brake. The brakes shall offer no resistance during hoisting.
Pneumatic actuators of the double or single acting type, with or without spring closing, shall
be provided as specified. Cylinders shall provide satisfactory operation using dry, oil-free air
at 5.5 bar g pressure and shall be factory tested for pressure retaining integrity at 16.5 bar g.
The valve actuator mechanism shall be totally enclosed. The cylinder shall be rigidly secured
to the mechanism housing and shall not pivot, rotate, or swing during operation. The piston
rod shall be enclosed in the housing and shall not be exposed to view.
Pneumatic actuations shall be fitted with a local valve-position indicator and hand wheel-
operated manual override. If pneumatic actuators are used on fail-close valves, means shall
be provided for automatic closing on supply air failure. A 4-port solenoid valve shall be
provided to control the operation of double-acting actuators and a 2–port solenoid valve shall
be provided for single acting actuators. Each solenoid valve shall be heavy-duty, single 24 V
dc coil, two-position type, rated for a differential operating-air pressure of 8.5 bar g, with
manual override facility. In general the solenoid valves shall comply with the Specification for
solenoid operated valves.
Actuators shall be designed to eliminate any risk of contact between the actuator lubricant
and the fluid conveyed.
Pneumatic actuators of the double or single acting type with or without spring closing shall
be provided as specified. Actuators shall provide satisfactory operation using dry, oil-free air
at 5.5 bar g pressure and shall be factory tested for pressure-retaining integrity at 16.5 bar g.
The actuator shall be rigidly secured to the mechanism housing and shall not pivot, rotate, or
swing during operation. The actuator shaft shall be enclosed in the mechanism housing and
shall not be exposed to view.
Pneumatic actuators shall be fitted with a local valve-position indicator and hand wheel-
operated manual override. If pneumatic actuators are used on fail-close valves, means shall
be provided for automatic closing on supply air failure.
Otherwise, actuators shall be provided with the appropriate fail safe devices.
• An electronic or digital positioner which can accept 4-20 mA input signal and position
the valve accordingly.
282
• An electronic position transmitter to provide 4-20 mA feed back of the valve position.
• Air sets in the supply and signal airlines.
• Pressure gauges of appropriate ranges in the supply and signal airlines.
• Limit switches to indicate fully open and fully closed positions.
Electric actuators shall operate valves and penstocks at opening and closing rates that will
not impose unacceptable surge pressures on the pipe work. Actuators shall be rated at not
less than 20 percent in excess of the power required to operate the valve or penstock under
maximum working conditions. Actuator enclosures shall have a minimum protection IPW 67
to BS EN 60529. Actuator electric motors shall comply with BS 4999. For non-modulating
type actuators, the motor short-time rating (STR) shall allow the successive full travel
operation of the travel from open to closed and vice versa but shall be not less than 15
minutes.
For modulating type actuators the motor shall have a duty-type rating (DTR) to meet the
varying cyclic load requirements of the valve. Electric motors shall be provided with built-in
thermal protection complying with BS 4999: Part 111.
(a) An alternative system for manual hand wheel and reduction gear operation which
shall be lockable.
(b) An interlock, to prevent engagement of the hand wheel whilst the actuator is being
power driven and to disengage the manual drive positively when the power drive is
started.
(c) Reversing type motor starter complete with isolating switch.
(d) Local and remote control selector switch when specified, which shall be lockable.
(e) Open, stop and close push-buttons.
(f) Potentiometer for remote valve position indication when remote control is specified.
(g) Torque switches for mechanical disengagement of the drive at the extremes of valve
operation to limit excess torque.
(h) Supply failure and remote control available monitoring relays. The supply failure relay
shall operate under single phasing and phase reversal conditions.
(i) Auxiliary and interposing relays as necessary.
(j) Voltage-free changeover type contacts for the remote indication of:
-Motor tripped on overload
-Fully open
-Fully closed
-Operating
-Supply failed
283
-Remote control available
The rating of volt-free contacts shall be not less than 15 A at 240V AC. and 2 A at 50V DC
unless otherwise specified. The contacts shall be suitable for inductive load switching.
Separate or segregated terminal boxes shall be provided for the connection motor, heater
and control cables.
284
PART F - ELECTRICAL STANDARD SPECIFICATION
A) GENERAL
These are general technical specifications. The contractor shall read this in conjunction with
SLD and other drawings.
The installation shall conform in all respects to Indian Standard code of practice for electrical
wiring installation IS: 732 (1963) and IS: 2274 (1963). It shall also be in conformity with the
current Indian Electricity Rules and Regulations and the requirements of the local electric
supply authority in so far as these become applicable to the installation. Wherever this
specification calls for higher standard materials and / or workmanship than those required by
any of the above regulations, this specification shall take precedence over the said
regulations and standards. In general the materials, equipment and workmanship not
covered by the above shall conform to the latest relevant Indian Standards unless otherwise
called for.
On completion of the work the Contractor shall obtain and deliver to the PRED the
certificates and approval by the Electrical Inspectorate of local administration. Necessary
drawings for submission to the electrical inspectorate shall be prepared by the Contractor.
The PRED representative shall have access to the manufacturer’s premises for inspection of
any item of the tender.
3.0 Sub-Contractor
The works shall be carried out by a licensed electrical Sub-Contractor possessing a valid
Electrical Contractor`s license of required category in the state, employing licensed
supervisors and skilled workers having valid permits as per the regulations of Indian
Electricity Rules and local Electrical Inspector’s requirements.
B) HT SWITCHGEAR
The switchboards and the mounted equipment shall confirm to following standards;
285
j) IS:3427 - Degree of protection provided for metal enclosed switchgear and control
gear
k) IS:4710 - switches and switch isolators above 1.0 KV but not exceeding 11KV
l) IS:5082 - Material for data for aluminum busbars
m) IS:5578 - Guide for marking of insulated conductors
n) IS:6005 - Code of practice for phosphating of iron and steel
o) IS:6875 - Control switches and pushbuttons
p) IS: 13118 - Specification for high voltage alternating current Circuit breakers
Equipment shall be furnished in strict accordance with the rating and requirements for
continuous operation at ratings as per design.
Temperature rise of the various switchgear components shall be limited to the permissible
values stipulated in the relevant standards and in this specification.
The switchgear and components shall be capable of withstanding the mechanical forces and
thermal stresses of the system, short circuit current without any damage, distortion and / or
deterioration of material.
Circuit breaker shall not produce any harmful over-voltage during switching off induction
motors. Surge protective devices to limit over voltage shall be included in the scope of
supply for all motor feeders.
4.1.1 Construction
The switchgear shall be outdoor / indoor, metal-clad, floor mounted, draw-out type. Design
and construction shall be such as to allow extension at either end.
The switchgear enclosure shall confirm to the degree of protection IP: 54 for out-door and IP:
42 for indoor application. The minimum thickness of sheet steel used shall be 2 mm.
Switchgear cubicle shall be so sized as to permit closing of the front access door when the
breaker is pulled out to test position. The working zone shall be restricted within 750 mm to
1800 mm from floor level.
All relays, meters, switches and lamps shall be flush mounted on the respective cubicle door
or on a control cabinet built on the front of the cubicle.
The main buses and connections shall be of high conductivity aluminium / aluminium alloy,
sized for specific current ratings with maximum temperature limited to 85 C (i.e. 35 C rise
over 50 C ambient).
286
All bus connections shall be silver plated. Adequate contact pressure shall be ensured by
means of two bolts connection with plain and spring washers and lock nuts.
Busbars and connection shall be fully insulated for working voltage with adequate phase /
ground clearances. Insulating sleeves for busbars and cast-resin shrouds for joints shall be
provided.
All buses and connection shall be supported and braced to withstand stresses due to
maximum short circuit current and also to take care of any thermal expansion.
Busbars shall be colour coded for easy identification and so located that the sequence R-Y-
B shall be from left to right, top to bottom or front to rear, when viewed from front of the
switchgear assembly.
The busbar chamber shall be provided with inter panel barrier with epoxy case seal-off
bushings which the buses will pass through so as to prevent fire from one panel to another.
Current transformers shall generally conform to IS: 2705. The CTs shall be mounted on the
switchgear stationary parts. The CTs shall be of cast resin, bar-primary type and of Class E
or better insulation.
All secondary connections shall be brought out to terminal blocks where Y or delta
connection will be made.
Core balance CT and associated relay combination shall be such as to ensure a pick up
sensitivity of 10A primary ground fault current.
Facilities for easy shorting and grounding the terminals shall be provided at the terminal
block.
Voltage transformer shall generally conform to IS: 3156. Voltage transformer shall be cast-
resin, draw-out type and shall have an accuracy Class of 1.0. Voltage Transformer mounted
on breaker carriage is not acceptable.
High voltage fuses, sized to prevent overload, shall be installed in all ungrounded secondary
leads. Fuses shall be suitably located to permit easy replacement while the switchgear is
energized.
Low voltage fuses, sized to prevent overload, shall be installed in all ungrounded secondary
leads. Fuses shall be suitably located to permit easy replacement while the switchgear is
energized.
287
Fuse failure relay shall be provided on the secondary side of all voltage transformers to
monitor failure of HV or LV fuses. The relay shall initiate alarm and block the tripping etc.
which will operate in case of VT fuse failure.
4.1.5 Relays
Relays shall be of draw-out design and built-in testing facilities. Small auxiliary relays may be
in non-draw-out execution and mounted within the cubicle with pluggin.
The Contractor shall furnish, install and co-ordinate all relays to suit the requirements of
protection, interlock. Auto / Manual change over schemes shall be provided for Unit and
Station switchgears.
All control switches shall be rotary type having a cam operated contact mechanism.
Phosphor bronze contacts shall be used on the control switches. Unless otherwise stated,
circuit breaker control switches shall be 3 - position spring return to “neutral” from both close
and trip positions. They shall have “Pistol Grip” handle.
Ammeter selector switches shall have make before break feature on its contacts. The
selector switch shall generally have four positions, three for reading three phase currents
and the fourth as off position. The voltmeter selector shall measure phase to phase voltages.
The contacts shall be of silver plated, air break type. The continuous current and breaking
capacity of the contacts shall be adequate for the duty involved.
4.1.7 Meters
Indicating instruments (96 x 96 mm) shall be switchboard type, with 240 C, anti-glare glass
and accuracy class of 2% full scale. Each meter shall have zero adjuster on the front.
Motor ammeter shall have extended suppressed end-scale range to indicate starting current
(6 - 8 times full load).
Watt-hour meter shall be provided in draw out cases with built-in test facilities. Alternatively,
they may have test block to facilitate testing of meter without disturbing CT or VT secondary
connections.
The switchgear shall be fully wired at the factory to ensure proper functioning of control,
protection, transfer and inter locking schemes.
Fuse and links shall be provided to permit individual circuit isolation from bus wires without
disturbing other circuits. All spare contacts of relays, switches and other devices shall be
wired up to terminal blocks.
Wiring shall be done with flexible, 650V grade, PVC insulated switchboard wires with
stranded copper conductors of 2.5 mm2 for current circuits and 1.5 mm2 for voltage circuits.
288
Each wire shall be identified, at both ends, with permanent markers bearing wire numbers as
per Contractor’s wiring Diagrams.
Wire termination shall be made with crimp in type connectors with insulating sleeves. Wires
shall not be spliced between terminals.
All external cable terminations shall be accessible while the breaker is in service position.
Terminal blocks shall be 660V grade box-clamp type with marking strips ELMEX - 10mm 2 or
equal. Terminals for CT secondary leads shall have provision for shorting.
Not more than two wires shall be connected to any terminal. Spare terminals equal in
number to 20% active terminals shall be furnished.
Terminal blocks shall be located to allow easy access. Wiring shall be so arranged that
individual wires of and external cable can be connected to consecutive terminals.
Switchgear shall be designed for cable entry from the bottom. Sufficient space shall be
provided for ease of termination and connection.
All provision and accessories shall be furnished for termination and connection of cables
including removable gland plates, cables supports, crimp type tinned copper / aluminium
lugs, brass compression glands with tapered washer (power cables only) and terminal
blocks.
The gland plates shall be minimum 4 mm thick. The gland plate and supporting arrangement
for I / C Power cables shall be such as to minimise flow of eddy current.
Sufficient space shall be provided between the power cable termination (end-boxes) and
gland plate. Core balance CTs wherever specified, shall be accommodated within the space.
A ground bus, rated to carry maximum fault current, shall extend full length of the
switchgear.
The ground bus shall be provided with two-bolt drilling with G.I bolts and nuts at each end to
receive 50 X 6 mm G.I. flat.
Each stationary unit shall be connected directly to the ground bus. The frame of each circuit
breaker and draw-out VT unit shall be grounded through heavy multiple contacts at all times
except when the primary disconnecting devices are separated by a safe distance.
Wherever a definite ground is provided at the switchgear, a single wire for each circuit thus
grounded shall be ran independently to the ground bus and connected thereto.
CT and PT secondary neutrals shall be earthed through removable links so that earth of one
circuit may be removed without disturbing other.
289
4.1.12 Name plates
Name plates of approved design shall be furnished at each cubicle and at each instruments
and device mounted on or inside the cubicle.
The material shall be lamicoid or approved equal, 3 mm thick with white letter on the black
back ground.
The material shall be held by self-tapping screws. Nameplate size shall be minimum 20 X 75
mm for instrument, device and 40 X 150 mm for panels.
Caution notice of suitable metal plate shall be affixed at the back of each vertical panel.
Each cubicle shall be provided with thermostat controlled space heaters suitable for
operation from 240 V, single phase AC supply and 5A, 3 pin plug socket. The space heater
shall be located at the bottom of each switchgear compartment.
In addition, motor feeder cubicle shall be wired-up for feeding the motor space heater
through suitable rated breaker auxiliary NC contact and / or contactor.
Cubicle heater, motor heater, plug / socket circuits shall have individual switch fuse units.
The following power supplies shall be made available to each switchgear: panel:
Isolating switch fuse units of adequate rating shall be provided at each switchgear for the
incoming supplies, 4-pole, single throw for AC and 2 pole double throw for DC.
4.1.15 Accessories
290
5.0 Protections
Transformer Protection
The protection consists of a three inverse time O / C relays (51) with high set instantaneous
units (50) for phase faults and one instantaneous over current relay (50 N) for earth faults.
Buch-holz relay for gas.
The inside and outside of the equipment shall be thoroughly cleaned of all foreign matter,
excessive oxide, weld spatter and flux. All fabricating scars and rough edges shall be
repaired by welding and / or grinding.
No paint of filler shall be applied until all repairs, hydrostatic tests and final shop inspection
are completed, but shall be applied prior to shipment.
All surfaces shall be sand blasted, pickled and ground as required to produce a smooth,
clean surface free of scale, grease and rust.
After cleaning, the surface shall be given zinc chromate coating (yellow) followed by two
coats of high quality primer and stoved after each coat.
The switchgear shall be finished in two coats of synthetic enamel paint of shade 631 of IS: 5.
Shop Test
Ten (10) copies of test certificates shall be submitted for approval prior to dispatch of
equipment from works.
Only type tested equipment shall be acceptable. Type test certificates for all items shall be
furnished along with the Tender. In case identical design of similar or higher rated equipment
as offered has not been type tested for all the tests, this shall be clearly indicated in the
Tender. All such type tests which have not been conducted so far shall be conducted during
the tenure of contract by the Contractor without any cost and time implications.
Oscillographic test results for closing and tripping timings of breaker shall be furnished.
C) POWER DISTRIBUTIONTRANSFORMER
1.0 Scope
This specification is for design, manufacture, inspection and testing at vendor’s works and
erection and commissioning of oil filled power / distribution transformer, along with
necessary accessories.
291
2.0 Codes and Standards
The design, manufacture, testing and performance of transformer and all accessories shall
comply in all respects with the currently applicable IS specifications and codes of practice
and other statutory regulations prevailing in the region where the equipment is intended to
be installed.
All material used shall be of best quality and of the class most suitable for working under the
conditions specified and shall withstand the variations of temperature and atmospheric
conditions without distortion or deterioration.
Pipes and pipe fittings, screws, studs, nuts and bolts used for external connections shall be
as per the relevant standards. Steel bolts and nuts exposed to atmosphere shall be
galvanized.
Exposed parts shall not leave pockets where water can collect. Tank covers shall be sloped
so as not to retain rain water.
Materials in contact with oil shall be such as not to contribute to the formation of acid in oil.
Surface in contact with oil shall not be galvanized or cadmium plated.
Labels, indelibly marked, shall be provided for all identifiable accessories like terminals, WTI,
OTI, thermometer pocket, etc. All label plates, name plates and diagram plate shall be of
non-corrodible material.
Painting
The interior of transformer tank and other oil filled chambers and internal structural steel
work shall be cleaned of all scale and dust by shot-blasting. These surfaces shall be painted
with not less than two coats of heat resistant, oil insoluble and insulating varnish.
Steel surfaces exposed to the weather shall be thoroughly cleaned and have a priming coat
of zinc chromate applied. The second coat shall be of an oil and weather resistant nature.
The final coat shall be of a glossy oil and weather resisting non fading paint of specified
shade.
Transformer shall operate without injurious heating at the rated KVA at any voltage
within plus / minus 10% of the rated voltage of that particular tap.
Transformer shall be capable of delivering the rated current at a voltage equal to 105
percent of the rated voltage without exceeding the limiting temperature rise.
292
Overloads shall be allowed within the conditions defined in the loading guide of the
applicable standard. Under these conditions, no limitations by terminal bushings, tap
changers or other auxiliary equipment shall apply.
Transformers, complete with bushings / cable boxes, shall be designed and constructed to
withstand without damage, the effects of external short circuits as per the specified
standards. Account shall be taken of the different forms of system faults that can arise in
service, such as line to earth faults and line to line faults associated with the relevant system
and transformer earthing conditions.
The neutral terminal of winding with star connection shall be designed for the highest over-
current that can flow through this winding.
Every care shall be taken to ensure that the design and manufacture of transformer shall be
such as to reduce noise and vibration to the level obtained in good modern practice.
5.0 Core
The magnetic circuit shall be constructed from high grade cold rolled non-ageing grain
oriented silicon steel laminations.
The laminations shall be free of all burrs and sharp projections. Each sheet shall have an
insulating coating resistant to the action of hot oil.
The insulation structure for the core to bolts and core to clamp plates shall be such as to
withstand a voltage of 2000V for one minute.
The core and coils assembly with all the clamping structures shall be free from deformation,
shall not vibrate during operation and shall be so fixed in the tank that shifting will not occur
during transport or short circuits.
The core clamping structure shall be designed to minimise eddy current loss.
The core shall be provided with lugs suitable for lifting the complete core and coil assembly
during maintenance.
6.0 Windings
The completed core and coil assembly shall be dried in vacuum and shall be immediately
impregnated with oil after the drying process to ensure elimination of air and moisture within
the insulation.
Windings shall not contain sharp bends which might damage the insulation or produce high
dielectric stress.
Materials used in the insulation shall be insoluble and chemically inactive in hot transformer
oil.
Terminals of all windings shall be brought out of the tank through bushings for external
connections.
293
7.0 Tank
Tank shall be made from good commercial grade low carbon steel and shall be of welded
construction.
Tank shall be designed for lifting by crane or jacks of the complete transformer assembly
filled with oil. Suitable lugs and bosses shall be provided for this purpose.
Tank together with radiators, coolers, conservator, bushings, vessel and other fittings shall
be designed to withstand without permanent distortion the following conditions;
(a) Full vacuum of 760 mm of Hg. for filling with oil by vacuum.
(b) Internal gas pressure of 0.35 Kg/ Sq.cm. with oil at operating level.
The transformer top shall be provided with a detachable tank cover with a bolted flanged
gasket joint. Lifting lugs shall be provided for removing the cover. The surface of the cover
shall be suitably sloped so that it does not retain rain water.
Pulling eyes shall be provided at the base for moving the transformer in either direction.
8.0 Valves
Valves shall be provided with an indicator to show the open and closed positions. There
shall be no oil leakage when the valves are in closed position.
9.0 Undercarriage
The under-carriage of the transformer shall be provided with detachable flat rollers. Wheels
shall be provided with suitable bearings which will resist rust and corrosion. It shall be
possible to swivel the wheels in two directions.
10.0 Radiators
Radiators shall be designed to withstand the vacuum and pressure conditions specified for
the tank. They shall be so designed as to avoid pockets in which moisture may collect, to
completely drain oil into the tank and to prevent formation of gas pockets when the tank is
being filled.
The clearance between all pipe work and live parts shall be more than the clearance for live
parts to earth.
11.0 Tappings
Off circuit taps as specified shall be provided on the high voltage winding.
294
The transformer shall be capable of delivering its rated output at any tap position.
The winding including tapping arrangement shall be designed to preserve the
electromagnetic balance between HV and LV winding at all voltage ratios.
In addition to the requirements given in the foregoing clauses, the following fittings shall be
provided on each transformer as standard accessories;
The following routine tests shall be conducted on each transformer at the manufacturer’s
works. Test records shall be submitted at the time of delivery.
The manufacturer should have got their transformer of similar capacity successfully type
tested at CPRI or any other recognized testing laboratories. The Contractors shall
specifically confirm this in their Tender. Copies of type test reports shall be furnished at the
time of delivery. Following are the type tests;
15.0 Rejection
PRED reject the transformer during factory testing or during performance period, if any of the
following conditions arise;
295
(a) Transformer fails in any of the routine tests.
(b) No load loss / load loss exceeds the guaranteed value by20%.
(c) Impedance value differs the specified value by plus or minus10%.
(d) Oil or winding temperature rise exceeds the specified value by 5oC.
(e) Transformer is proved to have been manufactured not in accordance with the agreed
specification.
1.0 Scope
Switchgear assembly and its accessories shall conform to latest applicable Indian Standard
specifications / Codes of Practice and in particular, with;
The switchboard shall be vertical, free standing, floor mounted type, compartmentalized,
modular type and suitable for indoor installation. It shall be dust and vermin proof and the
enclosure shall provide a degree of protection of not less than IP: 52.
296
Switchboard shall be easily extendable on either side by the addition of vertical sections,
when required.
The design shall ensure maximum safety during operations, inspection, connection of
cables, relocation of outgoing cables and maintenance (with the busbar system energized)
and without taking any special precautions. It shall provide means to prevent shorting of any
power due to accidental dropping of tools, etc. Checking and removal of component shall be
possible without disturbing adjacent feeders.
All the similar parts / components shall be fully interchangeable without need for structural
modifications.
The frame shall be fabricated using structural steel sections. The frames shall be enclosed
by minimum 14 / 16 SWG cold rolled sheet steel. Doors shall be provided with stiffeners
wherever required. Alternatively, panels can be fabricated out of CRCA folded steel sheets,
with suitable reinforcements.
All openings, covers and doors shall be provided with neoprene gaskets. Suitable eye
hooks shall be provided for shipping / easy lifting of panels.
Panels shall have base frame of 3 mm thick sheet steel with facility for directly bolting using
foundation bolts. The design shall ensure that weight of the components is adequately
supported.
The maximum height of the panels shall generally be restricted to 2200 mm and the
maximum length of a shipping section to 2500 mm. The max.and min. operating height of
the switch handles / push buttons shall be 1800 mm and 400 mm respectively.
Metal sheets shall be provided between two adjacent vertical panels running to full depth
and height.
Panels shall be in single front execution unless specified as double front. Circuit breakers
shall be in single front execution.
All auxiliary devices for control, indication, measurement and protection such as push
buttons, control and selector switches, indicating lamps, ammeters, voltmeters etc. shall be
mounted on front side of respective compartment.
Suitable cable and busbar alleys shall be provided for extra safety of working personnel.
Cable alleys and busbar alleys shall be provided with hinged doors. Adequate number of
slotted angle cable supports shall be provided in cable alleys.
All doors shall be provided with concealed type hinges. Rear doors wherever appropriate,
shall also be of hinged openable type.
The switches / MCCB shall be interlocked with compartment door to prevent opening of door
when switch / MCCB is ON.
4.0 Busbars
Busbars shall be of high conductivity aluminium conforming to grade of E91E of IS: 5082
supported on insulators of non hygroscopic type epoxy / SMC / DMC / FRP with high
creepage surface (preferably epoxy materials). The main phase busbars shall be of uniform
current rating throughout their length. The current rating of neutral shall be half that of phase
busbars.
297
Maximum current density employed for aluminium busbar dimension calculations shall not
be more than 1 ampere per sq.mm. A suitable section of earthing busbar shall be provided
throughout the length of the switchboard.
The thermal design of busbar enclosure shall be based on installation of panel in poor
ventilated condition. The cooling air volume shall take into account the busbar enclosure
only. The maximum operating temperature of busbar shall be 85 oC in normal conditions and
200 oC for short circuit conditions.
The busbar and its supports shall be capable of withstanding dynamic and thermal stresses
created due to short circuit conditions. Busbar shall be provided with heat shrinkable
insulating sleeves of high di-electric strength which is also non-inflammable and self
extinguishing type.
All the busbars shall be colour coded throughout its length. Minimum clearance between
phase to ground shall be 20 mm, phase to phase shall be 25 mm and phase to neutral shall
be 25 mm.
Interconnections and vertical busbars shall be compartmentalised and fully shrouded.
All busbar joints and connections shall be made by galvanised zinc passivated or cadmium
plated, high tensile strength steel bolts with a spring washer and a plain washer on either
sides of the busbars.
Interconnections between the main busbars and individual units shall be made by using Cu
or Al busbar strips of adequate rating. These interconnections and terminals shall be fully
shrouded.
For outgoing feeders above 100 A, provision shall be made by suitable bus link from
switchgear terminals so that required number cables could be connected to these links.
Circuit breaker (CB) compartment shall be fully draw out type. Suitable guides shall be
provided to facilitate easy withdrawal of trolley. It shall be possible to withdraw the trolley
without having to unbolt / unscrew any connections. Spring actuated and gravity operated
shutters shall be provided for covering the busbars and other live parts when the CB is
completely withdrawn.
There shall be three positions for the draw out trolley as below;
Service Position: In this position both power and control circuits shall be connected
and this is normal operating position of the CB.
Test Position: The power contacts shall be disconnected, but control connections
shall not be disturbed. It shall be possible to trip / close the CB in this position.
Fully Draw out Position: The power and control circuits shall be disconnected. It shall
be possible to close the cubicle door in this position.
Compartment door shall be interlocked against opening of door in ON condition. It shall not
be possible to either push in or withdraw the trolley when the breaker is in closed condition.
298
CB shall be of air break, draw out type and shall be provided with series trip for overload and
shunt trip for various other protections. It shall have mechanical tripping device on front part
of the panel.
CB’s open / close position should also be indicated mechanically. Such indication shall also
be available with manual operating mechanism.
Operating mechanism shall be quick make, quick break and trip free type. It shall not be
possible to close the breaker under short circuit condition.
The ON, OFF and TRIP positions of the MCCB shall be clear and visible to the operator
when mounted as in service. Front of board operating handle shall be provided.
MCCBs shall be provided with inverse-time-current tripping characteristic for sustained over
load and instantaneous tripping characteristic for short circuit conditions. These shall be
microprocessor type built in facility.
Under voltage release and any other features shall be provided when called for. Maximum
tripping time under short circuit conditions shall be 20 milli seconds.
8.0 Switches
All switches shall be of heavy duty, air break type with quick make / break manual operating
mechanisms. The operating handles shall be mounted on door of compartment having
the switch. Switches should be rated to carry the designed load without overheating.
Barriers shall be provided to prevent inter-phasing arcing and live terminals shrouded to
avoid accidental contact.
The contactors shall be air break type, equipped with three main contacts and minimum 2
NO + 2 NC auxiliary contacts. The main contacts shall be rated for AC 23 operations. The
auxiliary contacts shall be rated for 5A at 240VAC.
The coil of contactor shall be suitable for operation on 240V AC. The drop off voltage of
contactor coil shall be between 15% to 65% of rated coil voltage.
Auxiliary relays / contactors shall be used for interlocking and multiplying the signals. Their
ratings must not be less than 5A for 240V AC at PF of 0.8 to 1.0.
299
Thermal overload relays shall be of three elements, positive acting, ambient temperature
compensated with adjustable range. Relays shall be of manually reset type. Relays shall be
provided with minimum 1 NO + 1 NC contracts having a rating of 5A at 240V AC.
Door mounted over load relays / earth fault relays shall be of back connected, draw out type,
suitable for flush mounting and fitted with dust tight covers. The relay cases shall have
provision for inserting of test plug at the front for testing and calibration. It shall be possible
to test relays without connection of wirings. It should be provided with hand reset type built in
flag indicators to reset the flag without opening the relay case.
In case single phasing preventor is used, it shall be of current operated type and shall
operate on the principle of sensing negative sequence component of current. SPP used shall
be suitable for protection of non-reversing and reversing motors. The relay operation shall be
independent of loading and RPM of the motor prior to occurance of single phasing.
Timers used for star delta starters shall be of electronic type and shall have adjusting time of
0 - 60 Secs.
CT for instruments shall have accuracy of Class 1.0 and accuracy limit factor 5.0. CT shall
be capable of withstanding peak short circuit for 1.0 second. The neutral side of CT shall be
earthed. CT shall generally be of cast resin type.
Primary of PT shall be provided with fuse and secondary of it shall be provided with MCB. It
shall be of Class 1 at 0.8 PF lag. Primary of VT shall be 415V and secondary 110 V.
All measuring instruments shall be of size 96 sq.mm for MCC and 144 sq.mm for PCC and
shall be of flush mounting type.
All AC ammeters, voltmeters, KW meters shall be of moving iron type for AC and permanent
magnet type for DC. Accuracy Class shall be 1.0 for KW / KWH meter and 1.5 for ammeter
and voltmeter. KW / KWH meters shall be suitable to measure unbalanced loads on a 3
phase 4 wire system.
Selector switches shall have 3 Indication position for reading phase units and 4 th
position for off position.
The wiring for power, control, instrument, etc. shall be of PVC insulated flexible copper
conductors of grade 1.1 KV. All wirings shall be neatly bunched.
Control wiring shall be of 2.5 sq.mm and power wiring shall be of 4 sq.mm size, minimum.
Each wire shall be identified at both ends by ferrules and shall be terminated by using lugs.
300
Terminal blocks shall be of reputed make. Insulated barriers shall be provided between
adjacent terminals. Minimum 10% spare terminals shall be provided on each terminal
blocks.
13.0 Earthing
All vertical panels shall be connected to a common earth busbar. All doors and movable
parts shall be connected to the earth bus with flexible copper connections. Switchboards
shall have 2 Nos. of 3/8” Dia bolts with nuts and washers at each end to connect earthing
bus to plant earth grid. The earth busbar shall be painted green.
14.0 Labels
All incoming and outgoing feeders shall be provided with name plates on doors of each
compartment, indicating the service and the rating. Danger plates shall be provided as per
statutory requirements. Inside the panel, permanent stickers shall be provided for all
components and terminal blocks giving identification, number and feeder details as per
detailed wiring diagram.
Labels shall be of anodized AL, with white engraving on black background. They shall be
properly secured with fasteners.
15.0 Painting
All metal surfaces shall be thoroughly cleaned and degreased. Fabricated structures pickled
and rinsed. The under surface shall be applied a coat of phosphate paint and a coat of zinc
chromate primer. The under surface shall be made free from all undulations and
imperfections before undertaking the finishing coat.
After preparation of under surface, the panel shall be painted with two coats of enamel paint.
Colour shade shall be light grey unless specified otherwise.
In case of epoxy painting, surface shall be thoroughly cleaned, epoxy primer and epoxy paint
applied, baked in oven up to 120 oC and cured.
The panel finish shall be free from any imperfections like pin holes, orange peels, run off
paint, etc.
Panels shall be tested after completion of assembly, busbar interconnections, wiring and
internal checks. All switchboards shall be tested extensively and as per IS: 8623
specification. Works shall be well equipped with the necessary testing equipment. The
following tests shall be conducted.
i) Routine Tests:
a) HV Test: To test high voltage withstand capacity of the current carrying parts.
b) Megger Test: To check the insulation resistance.
c) Phase Sequence: To check the phases configuration
d) Functional Tests
e) Coat meter: To check the painting thickness of the sheet steel fabrication.
f) Gauge meter: To check the gauge of the fabricated steel.
g) Heat run test kit: To check the adequacy of size of current carrying conductors.
301
h) Secondary injection Test set: To check the protection relay for its correctness.
i) Millivolt test Equipment: To check millivolt drop at any point of joint.
a) Short circuit withstand capacity from Central Power Research Institute, Bangalore.
b) Dust / vermin / weather - proof test (i.e. IP: 54, IP: 55 etc. as per IS: 2147) from
Central Power Research Institute, Bangalore.
1.0 Scope
Distribution boards shall be of totally enclosed type. The enclosure shall be made of best
quality sheet steel of not less than 16 gauge thickness. The sheet steel shall be treated with
a rigorous rust inhibition process before fabrication. The distribution boards shall have switch
fuse unit, miniature circuit breaker or isolator as incoming and required number of circuit
breakers or HRC fuses as out-goings. The rating shall be as per design.
3.0 Bus-Bars
Suitable bus bars made of high conductivity copper and mounted on non-hydroscopic
insulating supports shall be provided. Separate bus bars for neutral and earth connections
shall be provided.
Miniature circuit breakers shall be of approved design and make. Circuit breakers shall be
equipped with individually insulated, braced and protected connectors. The front face of all
the breakers shall be in line. The fault level of the MCBs shall be minimum 9KA.
HRC fuses shall conform to IS: 2208 and fuse bases to IS: 1300. They shall be made out of
best grade phenolic mouldings. They shall be non inflammable and non-hydroscopic, with
hard glass finish. HRC fuses shall have non-deteriorating type characteristic. It shall be link
type and shall conform to IS: 2208. Fuses shall be capable of clearing 20KA fault level.
All the live parts shall be shrouded such that accidental contact with live parts are totally
avoided. The distribution boards interior assembly shall be dead front with the front cover
removed. Main lugs shall be shrouded. Suitable insulating phase barrier made of arc
resistant materials shall be provided. Ends of bus structures shall also be shrouded.
302
7.0 Cabinet Design
The distribution boards cabinet shall be totally enclosed type with dust and vermin proof
construction. The cabinet shall be stove enameled. The interior surface shall be finished to
off white shade. The interior components shall be mounted on a separate sheet steel DIN
rail which is mounted and locked on to the studs provided inside the cabinet. The insulators
used shall be heat resistant and non- tracking. Live parts shall be shrouded to prevent
accidental contact. The cabinet shall be equipped with a front door having a spring latch and
a vault lock or screwed cover as specified. Cabinets shall have detachable gland plates at
both top and bottom.
8.0 Directory
Distribution board shall be provided with a directory the load served by each circuit, rating of
breaker / HRC fuses, size of the conductor etc. The directory shall be mounted in metal
holder with a clear Perspex sheet on the inside of the front door.
9.0 Installation
Distribution boards shall be surface mounted or recess mounted. The boards shall be fixed
with suitable angle iron clamps and bolts. All cables / conduits shall be terminated using
glands / grips / check nuts etc. Wiring shall be terminated properly using crimping lugs /
sockets and PVC identification ferrules. No bare conductor shall be inside the board.
Distribution boards shall be bonded to earth at least at 2 points using brass bolts and lugs.
Suitable name plate and danger plate indicating the voltage shall be fixed to the front cover.
10.0 Testing
Distribution boards shall be tested at the factory as per IS and shall be tested for insulation
resistance after erection.
F) DIESEL GENERATOR
1.0 Scope
The scope of work shall include design, manufacture, fabrication, packing, supply, delivery at
site, storage, erection, testing and commissioning of diesel generator sets of capacity as per
design at site conditions with associated plant and equipment.
The scope of work shall include but not be limited to:
- Diesel engine with all engine mounted equipment such as governors, lube oil pumps,
C.W. pumps, injectors, turning gears, control and instruments.
- Fuel system suitable for High Speed Diesel including filtration, day tanks, piping
work, fuel transfer equipment from day tanks to engine with controls.
- Lubrication oil system including clean and dirty storage tanks with transfer pumps,
coolers, filtration, centrifuge and preheating if required, automatic engine oil reservoir
top up system.
- Combustion air system with inlet filtration, turbo charging and cooling system.
- Exhaust system including ducting, silencer, expansion provision and chimney as per
statutory requirements
303
- Cooling water system for engine jacket, oil cooler, charge air cooling including heat
exchanger, piping, valves, pump, strainer and controls
- Fabricated steel base plate for each engine generator unit with anti-vibration
mountings.
- Local and remote controls and instruments for start, stop control and protection of all
equipment.
- Auxiliary 415 V switch board for auxiliaries, battery charger, electrical station services.
- All pipe work, cabling, wiring, integral with, forming part of and linking the plant
specified, including supports, support steel work, cable trays and ladders and
conduits.
- Outlet of the exhaust system outside the building including chimney as per KSPCB
norms.
- Commissioning spares.
- Obtaining all necessary statutory clearances for operation of the DG set including
consent from KSPCB.
304
2.0 Design Climate
The diesel engine shall be suitable for installation at the proposed site with climatic
conditions as specified elsewhere in the document.
Each engine shall be four-stroke turbo charged, water cooled type, capable of driving the
generator at the specified load under all climatic conditions. Each engine shall be directly
coupled to alternator, all mounted on a common base frame.
Standard sized plant shall be provided with a continuous power rating at generator terminals
as defined in BS: 5514 or IS: 3046 (e) as a minimum, at 0.8 power factor for each set under
the following conditions.
Under the above condition, D.G. Set should be capable of operating with a 10% over load for
one hour...
- Crank case removal access doors on each side and at each crank throw to camshaft
drive and oil pump.
- Bearing shall be capable of removal without removing crankshaft.
- Exhaust valve: mounted in removable cages which obviate need to remove cylinder
heads.
Engine governing shall be in accordance with BS: 5514 / ISO: 3046 Part 4 Class A1, over
speed protection shall also be included. Motor operated speeder gear shall be provided to
allow the speed to be varied over the fuel output range. Local manual speed adjustment
shall also be provided. The governor shall be adjustable for both drop and load limit to allow
load sharing with other units.
305
4.4 Lubricating Oil System
The system shall be such that there is adequate oil circulation through all lubricated moving
parts prior to starting and after stopping. Oil filters shall be duplex type so that one element
can be cleaned while the engine is still operating. The filter shall have cleaning capability of
15 micron maximum.
The inlet air for the engines shall be taken within the D.G. station building. The degree of
filtration shall be as per BS: 1701.
A separate exhaust system shall be provided for each D.G. set. The system shall
accommodate expansion movements and shall be arranged so that vibration from the
engine is not transmitted to building or support structures. Condensation of flue gases when
the engine is operating under any load and under any ambient conditions (down to 13.4 °C)
should not take place to avoid corrosion in the system. The ducting system shall be slopped
and equipped with drains at low points and at the base of chimneys. Connection shall be
provided for flue gas sampling. A silencer shall be provided within the air exhaust system for
each engine.
Chimneys to be supplied shall conform to IS: 6533. The chimney shall be arranged in such
a way to prevent rain water entry as for as practicable.
Thermal insulation shall be provided on exhaust ducting. This shall be extended further
downstream to the stack, if necessary, to avoid condensation of the flue gases under
condition mentioned above.
A separate enclosed engine jacket cooling system shall be provided for each engine. An
expansion tank shall be provided for system to compensate for volume changes in the
cooling water system and to provide sufficient system pressure, to prevent pump cavitation.
The tank volume shall be at least 10% of the system volume and at least 100 litres. Soft
water shall be used for engine jacket cooling system.
Maximum level of sound at 1.0 meter from sound generating source shall be maintained at
70dB (A). Suitable acoustic enclosure / insulation shall be provided for maintaining the
above sound level.
1.0 General
This shall be applicable for 3 ph, 4 wire, 415V, 50 Hz, AC supply and 240V, single phase, 2
wire, 50 Hz, AC supply. The installation, testing and commissioning of complete lighting
system and power receptacles shall be carried out according to this specification. The
installation shall be carried out as per below listed standards.
306
2.0 Standards
3.0 Scope
The work shall include supply and fixing of all the equipments associated with lighting and
power receptacles, routing and laying of conduits, wiring, termination, testing, commissioning
and all other works necessary for completing the job. Supply and fixing of all mounting
accessories, earthing wires, hardware and consumables like saddles, spacer plates, junction
boxes, conduits, required fittings for fixing suspension points, joint boxes, connectors,
jointing ferrules, fixing brackets ball and socket, screws etc.
5 Conduit System
All conduits including bends, unions, junction boxes etc. shall be cleaned and painted with
bituminous paint before they are fixed in position. Conduits which are to be taken in the
ceiling slab shall be laid on the prepared shuttering work before the concrete is poured. The
conduits shall be properly threaded and screwed into the sockets, bends, junction boxes,
outlet boxes and shall be made water tight by using bituminous yarn at the screwed ends.
The conduit in ceiling slab shall be straight as far as possible. Before, the conduits controls
junction boxes shall be set out clearly so as to minimize off-sets and bends.
Conduits concealed in the wall shall be secured rigidly by means of steel hooks / staples at
800 mm intervals. Before conduit is concealed in the walls, all chases, grooves shall be
neatly made to proper dimensions to accommodate required number of circuits. The outlet
boxes, point control boxes, inspection and draw boxes shall be fixed as and when conduits
are being fixed. The recessing of conduits in walls shall be so arranged as to allow at least
12 mm plaster cover on the same. All grooves, chases etc. shall be refilled with cement
mortar and finished up to wall surface before plastering of wall is taken up.
Where conduits pass through expansion joints in the buildings, adequate expansion fittings
or other approved devices shall be used to take care of the relative movement. Whenever
the conduits terminate into control boxes, distribution boards etc. conduits shall be rigidly
connected to the boxes / boards with check nuts on either side of the entry to ensure
electrical continuity. After conduits, junction boxes, outlet boxes etc. are fixed in position their
outlets shall be properly plugged with PVC stoppers or any other suitable materials, so that
water, motor vermin or any other foreign materials do not enter into conduit system.
All conduits end terminating into an outlet shall be provided with bushes or PVC or rubber
after the conduit ends are properly filed to remove bur and sharp edges.
307
Necessary GI pull wires shall be inserted into the conduits for drawing wires and earth wires
shall be run throughout the length of the conduit with the earth wire being efficiently fastened
to the conduits by means of special clamps.
Wherever specifically called for, surface conduit system shall be adopted. Conduits shall be
run in square and symmetrical lines. Before the conduits are installed, the exact route shall
be marked at site and approval of PRED’s Representative shall be obtained. Conduits shall
be fixed by heavy gauge GI saddles, secured by suitable expansion plugs, at an interval of
not more than 1.0 meter. Wherever couplers, bends or similar fittings are used, saddles
shall be provided at either side at a distance of 300 mm from the centre of such fittings.
Conduits shall be joined by means of screwed couplers and screwed accessories only. In
long distance straight runs of conduit, inspection type couplers / junction boxes shall be
provided. Threading shall be long enough to accommodate pipe to the full threaded portion
of the couplers and accessories. Cut ends of conduits shall have no sharp edges or any
burrs left to avoid damage to insulation of wires.
Bends in conduit runs shall be done by using pipe bending machine. Sharp bends shall be
accomplished by introducing solid bends, inspection bends or cast iron inspection boxes.
Radius of solid bends shall not be less than 75 mm. Not more than three 90 Deg. bends
shall be used in a conduit run from outlet to outlet.
All conduit opening shall be properly plugged with PVC stoppers / bushes. Conduits shall be
adequately protected against rust by applying two coats of approved synthetic enamel paint
after the installation is completed.
Wherever conduits terminate into control boxes, outlet boxes, distribution boards etc. it shall
be rigidly connected to the box with check nuts on either side of the entry. The entire
conduit system shall be bonded to the earth.
For outdoor lighting such as street lights, flood lights, the Contractor shall erect the poles /
tower including foundation work, install the terminal boxes, and assembled fittings and the
necessary wiring to the fitting and earthing.
5.0 Wiring
Wiring shall be colour coded to enable easy identification of phase and neutral conductors.
The wiring throughout the installation shall be such that there is no break in neutral wire in
the form of a switch or fuse units.
Enclosure for electrical accessories such as switches, receptacles, fan regulators etc. shall
be of cast iron or mild steel. Wall thickness of CI enclosures shall not be less than 2 mm
and that of M.S. boxes shall not be less than 1.6 mm. The enclosure boxes shall be provided
with a minimum of four fixing lugs located at the corners for fixing the covers. All fixing lugs
shall have tapped holes to take machine brass screws. Sufficient number of knock outs
shall be provided for conduit entries. Provision shall be made for bonding the enclosures to
earth. The enclosure shall be protected against rust and corrosion inside and outside with
red oxide primer followed by two coats of synthetic enamel paint. The enclosures shall be
provided with 5 mm thick Perspex sheet cover with rounded corners and
308
leveled edges for mounting switches and receptacles. Wherever different phase conductors
are brought into the same enclosure, phase barriers shall be used.
All receptacles and switches unless specified otherwise shall be flush mounted in the wall.
The conductors shall not be drawn into the conduits until all the works of any nature that
may cause damage to wires are completed. Proper care shall be taken in pulling wires to
see that no damage occurs to the insulation of the wires. Ends of wiring conductors shall be
terminated by using fork / pin / eye lugs. Lugs shall be crimped to the conductor. Bimetallic
connectors shall be used wherever aluminium conductors are tapped from copper mains or
vice versa. Sub-main wiring shall be either in 3 ph, 4 wire or 1 ph, 2 wire system. Each sub-
main circuit shall also have its own earth wire. Circuit wiring shall be in single phase system.
However, a maximum of three single phase circuits of same phase could be installed in the
same conduit. Neutral circuit shall not be looped between circuits. Each circuit wiring shall
be provided with suitable earth conductor.
Light control switches shall be rated 5A for controlling up to four light points and 15A for
more than four light points. Light control switches shall be piano key type design suitable for
flush mounting for general lighting, wherever specifically called for, tumbler switches shall be
used.
All receptacles of 5A and 15A rating shall be flush mounting type with control switches piano
key type of the same rating as that of the receptacle. All receptacles shall be of 3 pin type.
The base of receptacle shall be high quality porcelain with pins made of brass alloy and
plated with noble metal. All receptacles shall be provided with plug tops of approved quality.
Industrial type receptacle shall be provided wherever specifically called for. Industrial
receptacles shall be totally metal clad with porcelain base incorporating the pin. Sockets
shall have three pins for single phase application and four pins and scraping earth for three
phase applications. The receptacle shall be provided with suitable metal clad plug top with
provision for cable entry. Receptacle shall have a spring loaded cover or metal covers with a
chain. It shall have a suitably interlocked switch. Receptacle shall be mounted in a cast
aluminium enclosure or sheet steel enclosure with receptacle mounted flush with the cover
of the housing.
Accessories for light outlets such as lamp holders, ceiling roses etc.shall be in conformity
with requirements of relevant IS specifications. Only approved make of accessories shall be
used.
All switches shall be wired on phases. Connections shall be made only after testing the
wires for continuity, cross phase etc., with the help of megger. The arrangement of switches
and sockets shall be neat and systematic. Outlets for fans shall be terminated into a ceiling
rose or into a connector if concealed fan hooks are used.
309
5.0 Ceiling Fans
Ceiling fans shall conform to IS: 374 in all respects. The motor shall be of capacitor type
and motor body shall be high conductivity aluminium die cast type. The motor and blades
shall be statically and dynamically balanced. The fans shall be provided with ball bearing
and bush bearing, which shall be accessible for lubrication, rubber shackle and downs shall
be of suitable length. Length of the down rod shall be co-ordinate with down drops of light
fittings so that no shadow will fall on the working plane. A regulator for five speed operation
and stop shall be provided with every fan.
Propeller type exhaust fans shall conform to IS: 2312 in all respects. The motor shall be of
die cast aluminium case. Fan motor shall be of squirrel cage induction design. Single phase
motors shall be designed to withstand the effects of moisture under normal conditions of
use. Exhaust fans shall be complete with mounting rings, ring arms and a resilient
suspension. The motor and blades shall be statically and dynamically balanced. Exhaust
fan shall be connected to the electrical point by means of flexible chord.
1.0 Standards
The light fittings and their associated accessories such as lamps, reflectors, housings,
ballasts etc shall comply with the latest applicable standards, more specifically the following:
Fittings shall be designed for continuous trouble free operation under atmospheric conditions
without reduction in lamp life or without deterioration of materials and internal wiring.
Outdoor fittings shall be weatherproof and rain proof. Fittings shall be so designed as to
facilitate easy maintenance including cleaning, replacement of lamps / starters etc.
All fittings shall be supplied complete with lamps. All Metal halide fittings shall be complete
with accessories like ballasts, power factor improvement capacitors, starters, etc. Outdoor
type fittings shall be provided with weather proof boxes.
Fluorescent lamp fittings shall be complete with all accessories like low loss electronic
ballasts PF improving capacitors, starters capacitors for correction of stroboscopic effect.
310
Each fitting shall have a terminal block suitable for loop-in loop-out connection by 1100V
PVC insulated copper conductor wires up to 4sq.mm. The internal wiring should be
completed by the manufacturer by means of multi-stranded copper wire and terminated on
the terminal block. All hardwares used in the fitting shall be suitably plated or anodized and
passivated for use in industrial plants.
Earthing
Each lighting fitting shall be provided with an earthing terminal. All metal or metal enclosed
parts of the housing shall be bonded and connected to the earthing terminal so as to ensure
satisfactory earthing continuity throughout the fixture.
Painting / Finish
All surfaces shall be stove-enameled or anodized as required. The surface shall be scratch
resistant and shall show no sign of cracking or flaking when bent through 90 Deg. over 12
mm Dia.mandrel.
Decorative fluorescent fittings shall be provided with mounting / housing channel cum
reflectors of CRCA sheet steel, stove enameled. Diffusers or louvers shall be translucent
white polystyrene / aluminium as specified.
The reflectors shall be made of CRCA sheet steel / aluminium / silvered glass / chromium
plated sheet copper as required. The thickness of reflectors shall be as per relevant
standards. Reflectors made of steel shall have stove enameled / vitreous enameled / epoxy
coating finish. Aluminium used for reflectors shall be anodized / epoxy stove enameled /
mirror polished. The finish for the reflector shall be as specified.
The reflectors shall be free from scratches blisters and shall have a smooth and glossy
surface having an optimum light reflecting coefficient. Reflectors shall be readily removable
from the housing for cleaning and maintenance without use of tools.
Lamp holders shall have low contact resistance, shall be resistant to wear. They shall hold
lamps in position under normal conditions of shock and vibration prevalent in an industrial
atmosphere. Lamp holders for fluorescent lamps shall be of spring loaded bipin rotating
type. Live parts of the lamp holder shall not be exposed during insertion or removal of the
lamp or after the lamp has been taken out. Lamp holders for incandescent and mercury
vapor lamps shall be bayonet type up to 100W and Edison screw type for higher wattage.
Starter holders for fluorescent lamps shall be so designed that they are mechanically robust
and shall be capable of withstanding shocks during transit, installation and use.
6.0 Ballasts
The ballasts shall be designed for long life and low power loss. They shall be mounted using
self locking, anti vibration fixtures and shall be easy to remove without demounting the
fittings. The enclosures shall be dust tight and non combustible.
Ballasts shall be inductive, heavy duty type, filled with thermosetting, insulating, moisture
repellent polyester compound, filled under pressure or vaccum. Ballasts shall be provided
311
with tapes to set the voltage. The ballast wiring shall be of copper. They shall be free from
separate ballast shall be provided in case of multi-lamp fittings, except in case of 2 x 20 W
fittings. For all DFL and TFL fittings the ballasts shall be electronic type.
7.0 Starters
Starters shall have bi-metal electrodes and high mechanical strength. Starters shall be
replaceable without disturbing the reflector of lamps and without use of any tool. Starters
shall have brass contacts and radio interference capacitor.
8.0 Capacitors
The capacitors shall have a constant value of capacitance and shall be connected across
the supply of individual lamp circuits. The capacitor shall have a value of capacitance so as
to correct the power factor of its corresponding lamp circuit to 0.95 lag or better. Capacitors
shall be hermetically sealed, preferably in a metal enclosure to prevent seepage of
impregnation and ingress of moisture.
9.0 Lamps
Incandescent lamps shall be clear type unless otherwise specified. Fluorescent lamps shall
be "day-light colour" type unless otherwise specified and shall be provided with features to
avoid blackening of lamp ends. Mercury vapor lamps shall be of high pressure, colour
corrected type.
The installation work shall include unloading, sorting, laying fixing, joining / termination,
testing, commissioning and any other work items necessary for completing the job.
The cable shall be laid in built up trenches, directly buried in ground on cable trays, vertical
raceways, clamped on structures / walls / ceiling, pulled through pipes and conduits as
specified elsewhere in the document. The scope of cable laying shall include laying, pulling
cables as above, proper dressing of cables and supply and fixing of saddles, spacers and
nylon chord for tying as required.
The scope of termination at each end shall include dressing and connection of each core of
cables. The following shall be included in the scope of work. Making the required holes in
gland plate for cable boxes / glands, fixing the cables boxes / gland, terminating the
cables in the glands / cable boxes, earthing of cable armour, crimping of cable lug on each
core, neatly clamping the cables inside switch gear / cables alleys / wiring through etc.
Cable identifying lugs shall be supplied and installed. All cable termination shall be solder-
less crimping type. Proper crimping tool shall be used by the Contractor.
312
3.0 Cables Directly Buried in Ground:
The depth of burial shall not be less than 750 mm from the finished ground level. Minimum
width of the trench shall be 350 mm an axial distance of one diameter of the cable between
cables. The trenches shall be cut square with vertical side walls and with uniform depth.
Suitable shoring and propping may be done to avoid caving in of trench walls. The floor of
the trench shall be rammed level.
The cable drum shall be rolled in the direction indicated. Minimum bending radius of cables
shall not be less than 12 times the diameter of the cable. After the cable is laid and
straightened, it shall be covered with 80 mm thick layer of sand. Cable shall be lifted and
placed over this sand cushion. The cable shall then be covered by 80 mm thick sand
cushion. Over this a layer of cable protection tiles or burnt bricks shall be provided so as to
cover the cables by 50 mm on either side. The trench shall be backfilled with selected earth
and consolidated. Cables shall be laid in hume pipes at road crossing and foundation entry
points. Cable markers of cast iron / concrete indicating the voltage, number of cables and
the direction of run of the cables shall be installed at intervals of 25meters.
Suitable clamps, hooks and saddles shall be used for securing the cables in position.
Spacing between the cables shall be 25 mm wherever specified. The trench shall be filled
up with fine sand. Necessary trench covers shall be provided as per standards.
Testing of electrical installations shall be as per IS: 732. The insulation resistance shall be
measured between earth and whole system of conductors or any selection thereof with all
fuses in place and all switches closed, all lamps in position, or both poles of the installation
otherwise electrically connected together, by applying a direct current pressure of not less
than twice the working pressure provided it need not exceed 500V for medium voltage
circuits. Where the supply is derived from three wire or a polyphase system, the neutral of
which is connected to earth either direct or through added resistance, the working pressure
shall deemed to be that which is maintained between the outer or phase conductor and
neutral.
The insulation resistance so measured shall not be less than 50 megohms divided by
number of points or the circuits provided that the whole installation shall be required to have
an insulation resistance of more than one megohm. The insulation resistance shall also be
measured between all conductors connected to one pole or phase conductor of the supply
and all the conductors connected to the middle wire or neutral or to other pole or phase
conductors of the supply and its value shall be less than specified above. The test voltage of
the meggar shall be500VDC
The earth continuity conductor including metal conduits and metallic envelope in all cases
shall be tested for electric continuity and the electrical resistance of the same along with the
earthing lead, but excluding any added resistance or leakage circuit breaker measured from
the connection with the earth electrodes to any point in earth continuity conductor in the
completed installation shall not exceed one milliohm
313
Testing of polarity of non linked single pole switches
In a two wire installation, a test shall be made to verify that all non linked single pole
switches have been fitted in the same conductor throughout and such conductor shall be
labeled or marked for connection to an outer or phase conductor or the non earthed
conductor of the supply. In three wire or four wire installation, test shall be made to verify that
every non linked single switch is fitted on a conductor which is labeled or marked for
connection to one of the outer phase conductor of the supply.
314
PART G - CIVIL STANDARD SPECIFICATION
CIVIL SPECIFICATIONS - 1
GENERAL
1.0 PREAMBLE
These specifications cover the items of work in structural and non-structural parts of
the works coming under purview of this document. All work shall be carried out in
conformation with relevant specifications. In general, provisions of Indian Standards,
Indian Roads Congress Codes and other national standards have been followed.
These specifications are not intended to cover the minute details. The work shall be
executed in accordance with best modern practices. All codes and standards referred
to in these specifications shall be the latest thereof.
2.0 INCLUSIVEDOCUMENTS:
The provisions of special conditions of contract, those specified on the tender as well
as execution drawings and notes or other specifications issued in writing by the
Engineer-in-Charge shall form part of these specifications.
3.0 The attention of the contractor is drawn to those clauses of IS codes which require either
specification by the Engineer-in-Charge or the mutual agreement between the
supplier and purchaser. In such cases it is the responsibility of the contractor to seek
clarification on any uncertainty and obtain previous approval of Engineer-in-Charge
before taking up the supply /construction.
4.0 Contractor should furnish the mix. design for all grades of concrete works required for
the work.
5.0 The surfaces of all steel works excluding reinforcement shall be painted with two
coats of zinc phosphate primer (one coat at shop and the second coat at site before
commencement of painting) unless otherwise specified.
6.0 Samples of all approved makes shall be submitted to the Engineer-in-Charge and got
approved well before the intended supply.
7.0 All the concrete works shall be supplied from approved RMC plant. The Tenderer
has to get prior approval from the Engineer-in-Charge before finalizing the agency.
8.0 The necessary grooves, recesses, champhers, rounding edges shall be provided in
concrete / masonry surfaces either it requires for architectural or functional purposes.
9.0 All the machinery foundations and packets for the bolts shall be grouted with non- shrink
grout GP2 of FOSROC.
10.0 All defective works are liable to be demolished, rebuilt and defective materials replaced
by the Contractor at his own cost. In event of such works being accepted by carrying
out repairs etc. as specified by the Engineer-in-Charge, the cost of repairs will be
borne by the Contractor.
315
CIVIL SPECIFICATIONS - 2
1.0 SCOPE:
This part of the specification deals with general requirements for earthwork in
excavation in different materials, site grading, filling in areas shown in drawings,
filling back with approved borrowed earth around foundations, plinths and approach
ramps, conveyance and disposal of excess excavated soil or stacking them properly
as shown on the drawings or as directed by the Engineer-in-Charge and all
operations covered within the intent and purpose of the specifications. The
excavation in rock by blasting etc. shall be as per relevant specifications.
2.0 APPLICABLECODES:
The provisions of the latest Indian Standards listed below, but not restricted to, form
part of these specifications:
IS: 1200 Method of measurement of building and (Part I) civil engineering works
- Part I Earth work.
IS: 4081 Safety Code for blasting and related drilling operations
Any soil which generally yields to the application of picks and shovels, phawras,
rakes or any such ordinary excavating implements or organic soil, gravel, silt, sand,
turf loam, clay, peat etc. fall under this category.
Any soil which generally requires the close application of picks, or jumpers or
scarifies to loosen it. Stiff clay gravel and cobble stone etc. fall under this category.
316
(Note: Cobble stone is the rock fragment usually rounded or semi-rounded having
maximum diameter in any one direction between 80 & 300 mm)
Mud:
Mud is a mixture of ordinary soft soil and water in fluid or weak solid state.
This shall include the type of rock and boulders, which may be quarried or split with
crow-bars. Laterite, hard conglomerate and amygdaloidal basalts also come under
this category.
This shall include the type of rock or boulder, which for quarrying or splitting requires
the use of mechanical plant or blasting.
Under this category shall fall hard rocks, which though normally requires blasting for
their removal but blasting is prohibited and excavation has to be done by chiselling,
wedging or other suitable method.
4.0 GENERAL:
4.1The contractor shall furnish all tools, plant, instruments, qualified supervisory
staff, labour, materials, any temporary works, consumable and everything
necessary, whether or not such items are specifically stated herein, for completion
of the job in accordance with the specification requirements.
4.2 The contractor shall carry out the surveys of the site before excavation and set
out properly all lines and establish levels for various works such as earth work in
excavation for grading, foundations, plinth filling, road drains, cable trenches, pipe
lines, culverts, retaining walls etc. Such surveys shall be carried out taking
accurate cross sections of the area perpendicular to the grid lines at intervals
determined by the Engineer-in-Charge, depending on the ground profiles. These
will be checked by the Engineer-in-Charge or his representative and thereafter
properly recorded.
5.3 The excavation shall be done to correct lines and levels. This shall include where
required, proper shoring to maintain excavation and also the furnishing, erection
and maintaining of substantial barricades around excavations and warning lamps
at night for safety purposes.
5.4 The work shall include dumping of excavated material in regular heaps, bunds,
and rip rap with regular slopes as directed by the Engineer-in-Charge within the
lead specified and leveling the same so as to provide natural drainage. Rock /
soil excavation shall be properly stacked as directed by the Engineer-in-Charge.
As a ruleallsoftermaterialsshallbelaidalongthecentreoftheheaps,theharderand
317
more resistant materials, forming the casting on the sides and the top. Rock shall be
stacked separately.
5.0 CLEARING:
The area to be excavated / filled shall be cleared of all fences, trees, plant logs,
stumps, bush, vegetation, rubbish, slush etc. and other objectionable matter. If any
roots or stumps of trees are met during excavation, they shall be removed. The
material so removed shall be disposed off as directed by the Engineer-in-Charge.
Where earth fill is intended, the area shall be cleared of all loose or soft patches, top
soil containing objectionable matter / materials before filling commences. No
separate payment shall be made for such clearing works.
All gold, silver, oil, minerals, archaeological and other findings of importance or other
materials of any description and all precious stones, coins, treasures trove, relics,
antiquities and similar things which may be found in or upon the site shall be property
of the owner and the contractor shall duly preserve the same to the satisfaction of the
Engineer-in-Charge and from time to time deliver the same to him.
7.1 Description:
Excavation for structures shall consist of removal of materials for the construction of
the foundations, retaining walls, pipe trenches, tunnels and other similar structures in
accordance with the requirements of this specification and the lines and dimensions
shown on the drawings or as indicated by the Engineer-in-Charge. The work shall
include construction of shoring, bracing, draining, dewatering and pumping; the
removal of all logs, stumps, grubs and other deleterious matter and obstruction
necessary for placing the foundations, trimming bottoms of excavation; backfilling
with approved material brought from outside or brought from approved borrow pits
cleaning up the site and disposal of all surplus materials.
After the site has been cleared as per clause 4 above, the limits of excavation shall
be set out true to lines, curves, slopes, grades and sections as shown on the
drawings or as directed by the Engineer-in-Charge. The contractor shall provide all
labour, survey instruments and materials such as string, pegs, nails, bamboo, stones,
lime, mortar, concrete etc. required in connection with the setting out of works and
establishment of bench marks. The contractor shall be responsible for the
maintenance of bench marks and other marks and stakes as long as they are
required for the work in the opinion of the Engineer-in-Charge.
7.3 Excavation:
Excavation shall be taken to the width of the lowest step of footing or the pile caps
and the sides shall be left plumb where the nature of the soil allows it. Where the
nature of the soil or the depth excavated trench / pit does not permit vertical sides,
the contractor at his own expense shall put up the necessary shoring, strutting and
planking or sheet piling or cut slopes to a safe angle or all with due regard to the
safety of personnel and the works and to the satisfaction of the Engineer-in-Charge.
318
The depth to which the excavation is to be carried out shall be as shown on the
drawings unless the type of material encountered is such as to require changes, in
which case the depth shall be as ordered by the Engineer-in-Charge.
Where water is met within excavation due to stream flow, seepage, springs, rain or
other reasons, the contractor shall take adequate measures such as bailing,
pumping, construction of diversion channels, drainage channels, bunds and other
necessary works to keep the foundation trenches / pits dry when so required and to
keep the green concrete / masonry against damage by erosion or sudden rise of
water level. The method to be adopted in this regard and other details thereof shall
be left to the choice of the contractor but subject to the approval of the Engineer-in-
Charge. Approval of the Engineer-in-Charge shall, however, not relieve the contractor
of his responsibility for the adequacy of dewatering and protection arrangements and
the safety of the works. Pumping from inside of any foundation enclosure shall be
done in such a manner as to preclude the possibility for the movement of water
through any freshly placed concrete. No pumping shall be permitted during the
placing of concrete or for any period of at least 24 hours thereafter, unless it is done
from a suitable sump separated from the concrete work by a water tight wall or
similar means. At the discretion of the contractor and at his cost, cement grouting or
other approved methods may be used to prevent or reduce seepage and to protect
the excavation area. The contractor shall take all precautions in diverting channels
and in discharging the drained water so as not to cause damage to the works or to
adjoining property.
The bottom of the foundation shall be leveled both longitudinally and transversally or
stepped as directed by the Engineer-in-Charge. Before the footing is laid, the surface
shall be slightly watered and rammed. In the event of the excavation having been
made deeper than that shown on the drawing or as otherwise ordered by the
Engineer-in-Charge, the extra depth shall be made up with concrete of the foundation
grade at the cost of the contractor. Ordinary filling shall not be used for the purpose
to bring the foundation to level.
When rock or other hard strata is encountered, it shall be freed of all loose and soft
materials, cleaned and cut to a firm surface either level, stepped, or serrated as
directed by the Engineer-in-Charge. All seams shall be cleaned out and filled with
cement mortar or grout to the satisfaction of the Engineer-in-Charge.
If there are any slips or blows in the excavation, these shall be removed by the
contractor at his own cost.
7.7 Backfilling:
Fill material shall be free from clods, salts, sulphates, organic or other foreign
materials. All clods of earth shall be broken or removed. Where excavated material
is mostly rock, the boulders shall be broken into pieces not larger than 150 mm size
mixed with properly graded fine materials consisting of murrum or earth to fill up the
voids and the mixture used for filling.
319
Selected fill material is required to be borrowed, the contractor shall make
arrangement for bringing the material from outside borrow pits. The material sources
shall be subject to the prior approval of the Engineer-in-Charge. The contractor shall
make necessary access roads to such borrow areas at his own cost, if such access
roads do not exist.
Backfilling of the foundation / pits shall be done as soon as the foundation work has
been completed to the satisfaction of the Engineer-in-Charge but not earlier than the
full setting of the concrete or masonry of the foundation. Backfilling shall be carried
out in such a manner as to not cause undue thrust on any part of the structure.
Backfilling shall be done in space around the foundations after clearing it of all debris
and in layers of 150 mm loose thickness, watered and compacted to the satisfaction
of the Engineer-in-Charge and to the original surface.
All the excavated material shall be the property of PRED. Where the excavated
material is directed to be used in the construction of the works for general grading,
plinth filling or embankments, the operations shall be arranged in such a manner that
the capacity for cutting, haulage and compaction are nearly the same.
All hard materials such as hard murrum, rubble etc. not intended for filling in
foundations, plinth or embankments shall be stacked neatly for future use as directed
by the Engineer-in-Charge. Unsuitable or surplus materials not intended for use in
part of the works or for reuse shall be disposed off outside the colony complex as
directed by the Engineer-in-Charge.
7.9.4 Forming (or leaving) "Deadmen" or "Tell Tales" and their removal after
measurement.
7.9.5 Bailing / pumping out water in excavation from rains, sub-soil water etc.
7.9.7 Forming (or leaving) steps in sides of deep trenches and their removal:
7.9.9 Fencing and / or other suitable measures for protection against risk of
accidents as approved by the Engineer-in-Charge
7.9.10 Excavation for insertion of planking and strutting where required and
7.9.11 Backfilling the trenches with approved selected material etc complete.
320
CIVIL SPECIFICATIONS - 3
1.0 GENERAL
1.01 The Contractor shall obtain license from the District Authorities for undertaking
blasting work as well as for obtaining and storing the explosives as per explosives
Rules 1940, corrected up to date. The Contractor shall purchase the explosives, fuses;
detonators etc only from licensed dealer and shall be responsible for the safe custody
and proper accounting of the explosive materials. The Engineer-in-Charge or his
authorized representative shall have the access to check the contractor’s store of
explosives and his accounts.
1.02 It is the full responsibility of the contractor to transport the explosives as and
when required for work in safe manner to the work spot.
1.03 The Contractor shall acquaint himself with all the applicable laws and
regulations concerning storing, handling and the use of explosives. All such laws,
regulations and rules etc as were current from time to time shall be binding upon
the contractor.
1.04 The provisions detailed in this are supplementary to the above laws, rules and
regulations etc. and are applicable except where they conflict with the afore
mentioned laws etc., from time to time. Further, the Engineer-in-Charge may
issue modifications, alterations and new instructions from time to time. The
contractor shall comply with the same without these being made a cause for any
claim.
1.05 Materials
All materials such as explosives, detonators, fuses tamping materials etc that are
proposed to be used in the blasting operations shall have the prior approval of the
Engineer-in-Charge.
1.08 Before use the fuse shall be inspected and moist, damaged or broken ones
shall be discarded. The rate of burning of fuses, when they have been in stock for
long period shall be tested before use.
1.09 The detonators used shall be capable of giving an effective blasting of the
explosives, moist and damage detonators shall be discarded.
1.10 Personnel:
321
1.11 All supervisors and workmen in-charge of makeup, handling, storage and
blasting work shall be adequately insured by the contractor.
1.12 The storage shall be in the charge of a very reliable person, approved by the
Engineer-in-Charge, who may if necessary cause police enquiries being made as
to his reliability, antecedents etc. the contractor shall have to produce a security
for the person in charge of the explosives, if and as required by the Engineer-in-
Charge or the civil authorities of the district.
1.13 The contractor shall make sure that his supervisors and workmen and fully
conversant with all the rules to be observed in storing, handling and use of the
explosives. It shall be assured that the supervisor in-charge is thoroughly
acquainted with all the details of the handling and the blasting operations.
1.14 The explosives, detonators and fuses shall each be separately stored.
1.15 A careful and day to day account of the use of the explosives shall be kept by
the contractor in an approved register and in an approved manner. The register
shall be produced by the contractor for the inspection of the Engineer-in-Charge
when so required by the later. The Engineer-in-Charge may also pay surprise
visits to the storage magazine. In case of any unaccountable shortage of the
explosives or if the account is not found to have been maintained in a manner
prescribed by the Engineer-in-Charge, the contractor shall be liable to be
penalized in which case he shall not be entitled to any compensation for the
losses etc. The action taken under this clause shall be in addition to that which
might be taken by the competent civil authorities in a court of law. There is no
departmental magazine at site of work. For the storage of blasting materials the
contractor has to make his own arrangements by providing a portable magazine
at site for day to day requirement. For bulk storage the nearest available
magazine can be made use by obtaining necessary permission from them.
Licenses required for the portable magazine are to be obtained by the contractor
himself.
1.17 No un-authorized person shall at any time be admitted inside the magazine.
1.18 The magazine shall, when not in use by authorized persons be kept well and
securely locked.
1.20 Magazine shoes without nails shall at all times be kept in the magazines, and a
wooden tub or cement tub about one foot high and eighteen inches in diameter,
filled with water shall be fixed near the door of the magazine.
Persons entering the magazine must put on the magazine shoes which shall be
provided at the magazine for this purpose and should be careful.
1.20.1 Not to put their feet on the clean floor unless they have the magazine
shoes on.
1.20.2 Not to allow the magazine shoes to touch the ground outside the clean floor.
322
1.20.3 Not to allow any dirt or grit to fall on the clean floor.
1.21 Persons with bare foot, shall before entering the magazine dip their foot in
water and then step direct from the tub over the barrier (if there be one) on to the
clean floor.
1.22 A brush broom shall be kept in the lobby of the magazine for cleaning out the
magazine, on each occasion if it is opened for the receipt, delivery or inspection of
explosives.
1.24 No person having article of steel or iron on him shall be allowed to enter the
magazine.
1.25 Oily cotton, rag waste and articles liable to spontaneous ignition shall not be
allowed inside the magazine.
1.26 Workmen shall be examined before they enter the magazine to see that they
have none of the prohibited articles on their person.
1.27 No tools or implements other than those of copper, brass, gunmetal or wood
shall be allowed inside the magazine. All tools shall be handled and used with
extreme care and gentleness
1.28 Boxes of explosives shall not be thrown down or dragged along the floor, and
shall be stacked on wooden trestles. Where there is presence of white ants, the
legs of the trestles shall rest in shallow copper, lead or brass bowls containing
water. Open boxes of dynamite shall never be exposed to the direct rays of the sun.
1.29 Empty boxes of loose packing material shall not be kept inside the magazine.
1.30 The magazine shall have lightning conductor, which should be got tested at
least once, by an officer authorized by the Engineer-in-Charge, the testing fee
shall be a charge on the contractor. The contractor shall within 10 days comply
with all the recommendations made by the officer testing the lightning conductor
failing which the Engineer-in-Charge shall be entitled to comply with the same at
the contractor’s expense. This shall not be open to any question or the Engineer-
in-Charge may consider any action that be may consider fit.
1.31 A notice shall be kept hung near the store, prohibiting entrance of
unauthorized people inside the magazine.
1.32 The following shall be kept hung in the lobby of the magazine:
1.32.1 A copy of rules both in English and in the languages which the
workers concerned are familiar with.
1.32.2 A Statement showing the stock in the magazine at that particular time.
1.33 The magazine shall be inspected at least once in two weeks by an officer
authorized bytheEngineer-in-
Chargewhowillseethatalltherulesarestrictlycompliedwith.
323
He will notify all omissions etc. to the contractor, who shall rectify the defects
immediately from the date of receipt of the notice. Failing which the Engineer-in-
Charge may take whatever action he considers suitable.
For the transport of the explosives and detonators between the store and the site,
closed and strong containers made of soft material such as timber, zinc, copper,
leather and the like shall only be used.
1.35 Explosives and detonators shall be carried in separate boxes. For the
conveyance of primers, special containers shall be used.
1.36 The boxes with half contents used shall be kept closed.
1.37 Explosives shall be stored and used chronologically to assure the ones,
received earlier, are being used first.
1.38 A make up house shall be provided at each working place in which cartridges
will be made up by experienced men as required for the work. The make-up
house shall be separated from other buildings. Only electric storage battery lamps
shall be used in this house.
1.39 No smoking shall be allowed in the make-up house or generally while dealing
with explosives.
1.44 Only wooden tamping rods, without any kind of metal on them shall be allowed
to be used. The tamping rods shall have cylindrical ends.
1.45 Bore holes must be of such size that the cartridges can easily pass down
them, they shall not however be too big.
324
1.46 Only one cartridge shall be inserted at a time and gently pressed with the
tamping rod. The sane, clay or other tamping material used for filling the hole
completely shall not be tamped too hard.
1.47 Blasting shall be carried out during fixed hours of the day. Which shall have
the approval of the Engineer-in-Charge; the hours once fixed shall not be altered
without prior written approval of the Engineer-in-Charge.
1.48 The site of blasting operations shall be prominently demarcated by red danger
flags. The order to fire shall be given only after giving the warning signal three
times, so as to enable all labour, watchmen etc., to reach safe shelters.
1.49 A bugle with a distinctive note shall be used to give the warning signals. This
bugle shall be made acquainted with the sound of the bungle and shall be strictly
warned to leave their work immediately at the first warning signal and to make for
safe shelter, and not to leave the shelters until, all clear signal has been given.
1.50 All the roads and footpaths leading to the blasting area shall be watched.
1.52 For lighting the fuses, a lamp with a strong flame such as carbide lamp shall be used.
1.53 The supervisor shall watch the time required for the firing of the fuses and shall
see that all the workmen are under safe shelters in goodtime.
Only the Supervisor in-charge shall possess key of the firing apparatus and he shall
kept it always with himself.
1.55 Special apparatus shall be used as a source of current for the blasting
operations. Power lines shall not be tapped for the purpose.
1.57 For blasts in series only detonators of the same manufacture and of the same
group of electrical resistance shall be used.
1.58 Such of the electrical lines and could constitute danger for work of charging,
shall be removed from the site. The firing cable shall be with proper insulating
cover so as to avoid short-circuiting due to contact with water, metallic parts of
rock.
1.59 The firing cable shall be connected to the source of current only when nobody
is in the area of b l a s t i n g .
1.60 The use of the earth as a return line shall not be permitted.
325
1.62 After firing, whether with or without an actual blast, the contact between the
firing cable and the source of current shall be cut off before any people are
allowed to leave the shelters.
1.63 During storms, charging with electrical detonators shall be suspended. The
charges already placed in the holes shall be blasted as quickly as possible, but
taking all the safety precautions and giving necessary warning signals. If this is
not possible, the site shall be abandoned till the storm has passed.
After the blasting the supervisors must carefully inspect the work and satisfy himself
that all the charges have exploded.
1.65 After the blast takes place in underground works, the workmen shall not be
allowed to go to the place till all the toxic gases are evacuated from the place.
1.66 Mis-Fires
If it is suspected that part of the blast has failed to fire or is delayed; sufficient time
shall be allowed to elapse before entering the danger zone.
1.67 None of the drillers are to work near this hole until one of the two following
operations have been carried out by the supervisor.
1.68 Before leaving his work, the supervisor shall inform the supervisor of the
relieving shift of any case of mis-fires and shall point out the position with a red
cross denoting the same, also stating what action, if any, he has taken in the
matter. A register of mis-fires and their location and how they are dealt with shall
be maintained.
1.69 The supervisor shall also at once report at the contractor’s office all cases of
mis- fires, the cause of the same and what steps were taken in connection
therewith.
1.70 The names of the day and night shift supervisors shall be noted daily in the
Contractor “office.
326
CIVIL SPECIFICATIONS - 4
1.0 GENERAL
The provisions of the latest revisions of the following I.S Codes shall form a part of
this specification to the extent they are relevant.
IS - 280 Specification for mild steel wire for general engineering purpose
IS - 432 (All Parts) - Specifications for mild steel and medium tensile
steel bars and hard-drawn steel wire for concrete reinforcement.
IS - 456 Code of practice for plain and reinforced concrete for general
building construction
IS -1139 Hot rolled mild steel, medium tensile steel and HYSD bars for
concrete reinforcement
327
IS -1542 Sand for plaster
IS -1732 Dimensions for round & square steel bars for structural
& general engineering purposes.
IS -1785 Plain hard drawn steel wire for PRESTRESSED concrete (Part I) Cold
drawn stress-relieved wire.
IS -1786 Specification for high strength deformed steel bars &wires for
concrete reinforcement
IS -2502 Code of practice for bending and fixing of bars for concrete
reinforcement.
IS -2722 Specification for portable swing weigh batcher (single and double
bucket type)
IS -3558 Code of practice for the use of immersion vibrators for consolidating
concrete.
328
IS - 6461 Cement concrete: glossary of terms
Other IS codes pertaining to the items of cement concrete work in structural work and
not listed above shall also be deemed to come under the purview of this clause. All
Indian Roads Congress Standards, specifications and codes of practice also come
under this purview.
2 GRADE OF CONCRETE
For controlled concrete, design of the mix shall be arrived at after preliminary tests
and in its production all necessary precautions shall be taken to ensure that the
required works cube strength is attained and maintained. The controlled concrete
shall be in nine grades designated as M:10, M:15, M:20, M:25, M:30, M:35, M:40,
M:45 and M:50.
Where Ordinary Portland Cement conforming to IS: 269, IS: 8112, IS: 12269 or
Portland Blast Furnace Cement conforming to IS: 456 is used, the compressive
strength requirements for various grades of concrete controlled as well as ordinary
shall be as given in Table - 1. Where rapid hardening Portland cement is used, the
28 days compressive strength requirements specified in Table - 1 shall be met at 7
days.
For controlled concrete, the mix shall be so designed as to attain in preliminary tests
strength at least 33 per cent higher than that required on work tests, for concrete up
to and including M:25 and 25 per cent higher for higher strengths.
329
TABLE – 1
Grade of Concrete Compressive Works test strength in N/sq.
mm on 150mm cubes after testing
Conducted in accordance with IS: 516
Min at 7 days. Min at 28 days.
M10 7 10
M15 10 15
M20 13.5 20
M25 17 25
M30 20 30
M35 23.5 35
M40 27 40
M45 30 45
M50 33.5 50
Note: In all cases, the 28 days compressive strength specified in Table - 1 shall
alone be the criterion for acceptance or rejection of the concrete.
Where the strength of a concrete mix, as indicated by tests, lies in between the
strength for any two grades specified in Table - 1, such concrete shall be classified
for all purposes as a concrete belonging to the lower of the two grades between
which its strength lies.
MATERIALS
4.1 Cement
All types and brands of cement shall be subject to the approval of the Engineer-in-
Charge.
Fine aggregates shall consist of natural sand conforming to IS: 383. The grading
zone of sand proposed for use shall be supplied by the contractor and got approved
by the Engineer-in-Charge.
The sand shall be of siliceous material, sharp, hard, strong and durable and shall be
free from adherent coatings, clay, dust, alkali, organic material, deleterious matter,
lumps, etc.
Natural sand shall be washed, unless specific written authority is given by the
Engineer-in-Charge to use sand that meets specifications and standards of
cleanliness without washing. The cost of screening and washing must be borne by
the contractor. The fine aggregate shall be taken from a source approved by the
Engineer-in-Charge.
330
4.3 Coarse Aggregates
Coarse aggregates shall consist of hard, strong, durable particles of crushed stone
and shall be free from thin elongated soft pieces, organic or other deleterious matter.
It shall not have adherent coatings. It shall be from a source approved by the
Engineer-in-Charge.
Coarse aggregate shall be washed if necessary to remove all vegetable and other
perishable substances and objectionable amounts of other foreign matter, the cost of
washing and screening being borne by the contractor.
Following shall be the maximum nominal size of coarse aggregate for the different
items of work:
For heavily reinforced concrete members as in the case of ribs of main beams, the
nominal maximum size of aggregate shall usually be restricted to 5 mm less than the
minimum lateral clear distance between the main bars, or 5 mm less than the
minimum cover to the reinforcement, whichever is smaller. However, if required
under special circumstances, the Engineer-in-Charge may permit nominal maximum
aggregate size of 25% more than these critical spacing / cover, provided that proper
vibrating is ensured.
Steel for reinforcement shall be high yield strength deformed TMT bars. The steel
shall be either TISCON - of Grade Fe 415 / Fe 500 or SAIL‟s Grade Fe 415 / Fe 500
or VIZAG Steel’s A1 - Rebars of Grade Fe 415 / Fe 500 and shall have mechanical
properties as per IS: 1786.
331
The reinforcement supplied shall have the following Chemical Properties:
i. Manufacturer’s Tests
Based on the results of tests carried out as mentioned above, the Engineer-in-Charge
will decide the acceptance of the batch under test for use in RCC structures, and his
decision shall be final and binding on the Contractor.
The charge for all the tests shall be borne by the Contractor and are deemed to have
been included in the quoted price. It shall be clearly understood by the Contractor that
the confirmatory test stipulated above is mandatory and the time required for such
testing shall be catered for in the construction period.
Reinforcing steel shall be clean and free from loose mill scales, dust, loose rust and
coats of paints, oil, grease or other coatings which may impair or reduce bond.
Mild steel and medium tensile steel bars and hard drawn steel wire shall conform to
the latest edition of IS: 432.
Structural steel sections and plates shall conform IS: 226 and IS : 2062.
4.6 Water
Water used for mixing and curing shall be free from injurious amounts of deleterious
materials. Potable waters are generally considered satisfactory for mixing and curing
concrete.
4.7 Admixtures
No materials other than the essential ingredients, i.e., cement, aggregates and water,
shall ordinarily be used in the manufacture of concrete or mortar. But the Engineer-
in-Charge may permit the use of approved admixtures conforming to IS: 6925 for
imparting special characteristics to the concrete, on satisfactory evidence that its use
does not in any way adversely affect the properties of concrete particularly its
strength, volume changes, durability and has no deleterious effect on the
332
reinforcement. Admixtures where allowed will generally be conforming to relevant
ASTM standards and IS: 9103.
The use of epoxy for bonding fresh concrete used for repairs will be permitted on
written approval of the Engineer-in-Charge. Epoxies shall be applied in accordance
with the instructions of the Manufacturer. The cost of such repair when approved by
the Engineer-in-Charge shall be borne by the contractor.
i. Cement
ii. Aggregates
Reinforcing steel shall not be stored directly on the ground. These shall be
stored under cover and shall be protected from rusting, oil, grease and
distortions as directed by the Engineer-in-Charge.
333
5.0 PROPORTIONING CONCRETE
Concrete mix shall be designed on the basis of preliminary tests. The proportions for
ingredients chosen shall be such that concrete has adequate workability for
conditions prevailing on the work in question and can be properly compacted with the
means available.
It is most important to keep the specified water-cement ratio constant and at its
correct value. To this end, the moisture content in both fine and coarse aggregates
shall be determined by the Engineer-in-Charge according to the weather conditions.
The amount of mixing water shall then be adjusted to compensate for variations in
the moisture content. For the determination of moisture content in the aggregates,
IS: 2386 (Part III) shall be referred to. Suitable adjustments shall also be made in the
weights of aggregates to allow for the variation in weights of aggregates due to
variation in their moisture content.
The reinforced concrete for liquid retaining structures shall have a minimum cement
content of 360 Kg/m3 and all other reinforced cement concrete structure shall have a
minimum cement content of 320 Kg/m3. The maximum free water cement ratio shall
not exceed 0.40 for liquid retaining structure and 0.45 for all other reinforced concrete
structures.
For all works concrete shall be mixed in approved RMC plant only. A mechanical
mixer with weigh batcher along with other accessories may be allowed for mixing
only under exceptional conditions. The Contractor must take the permission of the
Engineer-in-Charge in advance. Mixing shall be continued till materials are uniformly
distributed and a uniform colour of the entire mass is obtained and each individual
particle of the coarse aggregate shows a complete coating of mortar containing its
proportionate amount of cement. In no case shall the mixing be done for less than 2
minutes after all ingredients have been put into the mixer. Mixers which have been
out of use for more than 30 minutes shall be thoroughly cleaned before putting in a
new batch. Unless otherwise agreed to by the Engineer-in-Charge, the first batch of
concrete from the mixer shall contain only two thirds of the normal quantity of coarse
334
aggregate. The mixing plant shall be thoroughly cleaned before changing from one
type of cement to another.
The method of transporting and placing concrete shall be approved by the Engineer-
in-Charge. Concrete shall be transported and placed such that no contamination,
segregation or loss of its constituent materials takes place.
All formwork and reinforcement contained in it shall be cleaned and made free from
standing water or dust, immediately before placing of concrete.
No concrete shall be placed in any part of the structure until the approval of the
Engineer-in-Charge has been obtained in writing.
If concreting is not started within 24 hours of the approval being given, it shall have to
be obtained again from the Engineer-in-Charge. Concreting shall then proceed
continuously over the area between construction joints. Fresh concrete shall not be
placed against concrete which has been in position for more than 30 minutes unless
a proper construction joint is formed.
Concrete when deposited shall have a temperature of not less than 4.5 deg. C and
not more than 38 deg. C unless otherwise specified. It shall be compacted in its final
position within 30 minutes of its discharge from the mixer unless carried on properly
designed agitators, operating continuously, in which case this time shall be within 2
hours of the addition of cement to the mix and within 30 minutes of its discharge from
the agitator.
When concrete is conveyed by chute, the plant shall be of such size and design as to
ensure practically continuous flow. Slope of the chute shall be so adjusted that the
concrete flows without the use of an excessive quantity of water and without any
segregation of its ingredients. The delivery end of the chute shall be as close as
possible to the point of deposit. The chute shall be thoroughly flushed with water
before and after each working period and the water used for this purpose shall be
discharged outside the formwork.
Where concrete has not fully hardened, all laitance shall be removed by scrubbing
the wet surface with wire or bristle brushes, care being taken to avoid dislodgement
of any particles of coarse aggregate. The surface shall then be thoroughly wetted, all
free water removed, and then coated with neat cement grout. The first layer of
concrete to be placed on this surface shall not exceed 150 mm in thickness, and
shall be well rammed against old work, particular attention being given to corners and
close spots.
335
All concrete shall be compacted to produce a dense homogeneous mass with the
assistance of vibrators. For exceptional cases, where vibrators cannot be used an
alternate scheme of compaction shall be approved by the Engineer-in-Charge.
Sufficient vibrators, in serviceable condition, shall be kept at site so that spare
equipment is always available in the event of breakdowns.
8 CONCRETING UNDERWATER:
Concrete shall not be placed in water having temperature below 4.5 Deg.C. The
temperature of the concrete, when deposited, shall be not less than 16 Deg.C., nor
more than 38 Deg.C.
Concrete shall contain 10 per cent more cement than that required for the same mix
placed in the dry. The materials shall be so proportioned as to produce a concrete
having a slump of not less than 100 mm. and not more than 180 mm. The slump
shall be tested as per IS:516.
Concrete shall be deposited continuously until it has been brought to the required
height. While depositing, the top surface shall always be kept as nearly level as
possible and formation of seams avoided. For depositing concrete any one of the
following methods may be used:
336
the tremie in order to allow a uniform flow of concrete, but it shall not be emptied
so that water enters above the concrete in the pipe. At all times after the placing
of concrete is started and until all the required quantity has been placed, the
lower end of the tremie pipe shall be kept below the top surface of the plastic
concrete. This will cause the concrete to build up from below instead of flowing
out over the surface, and thus avoid formation of layers of laitance. If the charge
in the tremie is lost while depositing, the tremie shall be raised above the
concrete surface, and unless sealed by a check valve it shall be re-plugged at
the top end, as at the beginning, before refilling for depositing further concrete.
b.Drop Bottom Bucket: The top of the bucket shall be closed. The bottom doors
shall move freely downward and outward when tripped. The bucket shall be
filled completely and lowered slowly to avoid backwash. It shall not be
dumped until it rests on the surface upon which the concrete is to be
deposited and when discharged shall be withdrawn slowly until well above the
concrete.
To minimize the formation of laitance, great care shall be exercised not to disturb the
concrete as far as possible while it is being deposited.
9 CURING OF CONCRETE
Where retarders are used, the waiting period before application of the steam shall be
increased from four to six hours. The steam shall be at 100 % relative humidity to
prevent loss of moisture and to provide excess moisture for proper hydration of the
cement. The application of steam shall not be directly on the concrete, and the
ambient air temperature shall increase at a rate not exceeding 5 deg. cent. Per hour
until a maximum temperature of 60 deg. cent.to 70 deg. cent. is reached. The
maximum temperature shall be maintained until the concrete has reached the
desired strength.
When steam curing is discontinued the ambient air temperature shall not drop at a
rate exceeding 5 deg. cent per hour until a temperature of about 10 deg. cent. Above
the temperature of the air to which the concrete will be exposed, has been reached.
337
10.0 WORKING IN EXTREME WEATHER
When depositing concrete in very hot weather, precautions shall be taken so that the
temperature of wet concrete does not exceed 38 deg. C while placing. This shall be
achieved by stacking aggregate under sheds and keeping it moist using cold water or
crushed or flaked ice if specified and permitted by the Engineer-in-Charge, reducing
the time between mixing and placing to the minimum, cooling formwork by sprinkling
water on the exterior, starting curing before the concrete dries out and restricting
concreting, as far as possible, to mornings and evenings.
During hot weather and rains the concrete shall be covered with tarpaulin and
transported and placed in the forms and consolidated to final state in as short a time
as possible.
Commencement of concrete pours shall be avoided during heavy rains, storms and
high winds.
11.0 FINISHING
11.1 General
Immediately after the removal of forms, all exposed bars or bolts passing through the
reinforced cement concrete member and used for shuttering or any other purpose
shall be cut inside the reinforced cement concrete member to a depth of at least 25
mm below the surface of the concrete and the resulting holes be closed by cement
mortar. All fins caused by form joints shall be broken. All cavities produced by the
removal of form ties, all holes and depressions, honey-comb spots, broken edges or
corners and all other defects shall be thoroughly cleaned, saturated with water and
carefully pointed and rendered true with mortar of cement and fine aggregate mixed
in the proportions used in the grade of concrete that is being finished and of as dry a
consistency as is possible to use. Considerable pressure shall be applied in filling
and pointing to ensure thorough filling in all voids. Surfaces which have been filled /
pointed shall be kept moist for a period of twenty-four hours. Any repair and
rectification of defective work is to be undertaken and carried out as directed by the
Engineer-in-Charge and the cost is to be borne by the Contractor.
All construction and expansion joints in the completed work shall be left carefully
tooled and free from any mortar and concrete. Expansion joint filler shall be left
exposed for its full length with clean and true edges.
The surface finish for formed and unformed surfaces are classified and defined as
below. Surface irregularities permitted for the various classes of finishes are termed
either "abrupt" or "gradual". Fins or offsets caused by displaced or misplaced form
sheeting, lining or form sections, by loose knots in form timber or by otherwise
defective form timber are considered abrupt irregularities. All other cases are
338
described as gradual irregularities. Gradual irregularities will be measured with a
template consisting of a straight edge for plane surfaces or its equivalent for curved
surfaces. The length of template for testing gradual irregularities on formed surfaces
shall be 1.5 m in length, the permissible gradual irregularities being measured over
this length of the template.
Special surfaces, finishes and treatments falling outside the classes described here
but defined elsewhere by the Engineer-in-Charge shall also form part of these
specifications.
Class F1 Finish
This class of finish shall apply to all formed surfaces for which class F2 or F3 is not
specified. It shall generally be formed by sawn timber formwork so constructed that
there shall be no loss of material from the concrete during placement and
compaction. After hardening, the concrete shall be in the position required and shall
have the shape and dimensions called for in the drawings. Any abrupt irregularities
shall not exceed 8 mm and gradual irregularities shall not exceed 16 mm. All fins
and drifts in excess of the above limits shall be made good by chipping and grinding
if required by the Engineer-in-Charge. Small blemishes caused by entrapped air or
water may be expected but the surface shall be free from voids, honeycombing or
other large blemishes.
Class F2 Finish
Class F2 finish shall be obtained by the use of properly designed forms, either close
jointed wrought timber forms or with forms having plywood or steel sheet lining. The
abrupt irregularities shall not exceed 5 mm and gradual irregularities shall be less
than 8mm. Small blemishes caused by entrapped air or water may be permitted but
the surface shall be generally free from honeycombing, voids and large blemishes.
Surface irregularities in excess of those stipulated shall be removed by chipping or
rubbing with abrasive stone.
Class F3 Finish
Class F3 finish shall be formed by specially designed close jointed rigid forms having
lining of high quality form plastic coated / laminated plywood. The surface
irregularities shall be limited to nil for abrupt irregularities and 3 mm for gradual
irregularities. Unless otherwise specified the surface finish shall be understood to be
Class F3 finish. If steel forms are used they shall be subject to Engineer-in-Charge's
approval.
In addition, finish F3 shall include filling air holes with mortar and treatment of the
entire surface with sack rubbed finish. It shall also include clean up of loose and
adhering debris. For a sack rubbed finish, the surface shall be prepared within two
days after of removal of the forms. The surface shall be wetted and allowed to dry
slightly before mortar is applied by sack rubbing. The mortar used shall consist of
one part cement to one and one half parts by volume of fine (I.S. No. 16 mesh) sand.
Only sufficient mixing water to give the mortar a workable consistency shall be used.
The mortar shall then be rubbed over the surface with a fine burlap or linen cloth so
339
as to fill all the surface voids. The mortar in the voids shall be allowed to stiffen and
solidify after which the whole surface shall be wiped clean with clean burlap such
that all air holes etc. are filled and the entire surface presents a uniform appearance
without air holes, irregularities etc.
Class U1 Finish
This is the screened finish used on surfaces over which other finishes such as
wearing coats etc. are to be placed. It is also the first step in the formation of U2 and
U3 finishes. The finishing operation consists of levelling and screeding the concrete
to produce an even and uniform surface so that the gradual irregularities are not
greater than 6 mm. Surplus concrete should be removed immediately after
consolidation by striking it off with a sawing motion of a straight edge or template
across a wooden or metal strip that has been set as guide. Unless the drawings
specify a horizontal surface or show the slope required, the tops of narrow surfaces,
such as stair treads, walls, curbs and parapets shall be sloped approximately 10 mm
per 300 mm width. Surfaces to be covered with concrete topping, terrazzo, and
similar surfaces shall be smooth screeded and levelled to produce even surfaces,
irregularities not exceeding6mm.
Class U2 Finish
This is a floated finish used on all outdoor unformed surfaces not prominently
exposed to view such as tops of piers etc. The floating may be done by hand or
power driven equipment. It should not however be started until some stiffening has
taken place in the surface concrete and the moisture film or "shine" has disappeared.
The floating should work the concrete no more than is necessary to produce a
surface that is free from screed marks. All joints and edges should be finished with
edging tools. It shall include the repair of gradual irregularities exceeding 6 mm. All
abrupt irregularities shall also be repaired unless a roughened texture is specified.
Class U3 Finish
This is a trovelled finish used on all surfaces exposed to view at close quarters such
as tops of parapets and kerbs etc. Steel trovelling should not be started after the
moisture film and "shine" have completely disappeared from the floated surface and
the concrete has hardened enough to prevent an excess of fine material and water
from being worked to the surface. Excessive trovelling, especially if started too soon,
tends to produce crazing and lack of durability. Too long a delay will result in a
surface too hard for proper finishing. Steel trovelling should be performed with a firm
pressure that will flatten and smooth the sandy surface left by floating. Trovelling
should produce a dense, uniform surface free of blemishes, ripples and trovel marks.
It shall include the repair of all abrupt irregularities and the repair of gradual
irregularities exceeding 6 mm. It shall also include finishing the joints and the edges
of concrete with edging tools.
12.0 CONSTRUCTIONJOINTS
Concreting shall be carried out continuously up to the construction joints, the position
and details of which shall be as shown on approved drawings or as directed by the
Engineer-in-Charge. Such joints shall, however, be kept to the minimum.
For a vertical construction joint, a stopping board shall be fixed previously at the pre-
determined position and shall be properly stayed for sufficient lateral rigidity to
340
prevent its displacement or bulging when concrete is compacted against it.
Concreting shall be continued right up to the board. The board shall not be removed
before the expiry of the specified period for removal of vertical forms. Before
resuming work at a construction joint where the concrete has not yet fully hardened,
all laitance shall be removed thoroughly, care being taken to avoid dislodgement of
coarse aggregates. When work has to be resumed on a surface which has
hardened, the surface shall be thoroughly hacked, swept clean, wetted. The first
batch of concrete shall be rammed against the old work to avoid formation of any
stone pockets, particular attention being paid to corners and close spots.
In all cases, the position and detailed arrangement of all construction joints shall be
predetermined and got approved by the Engineer-in-Charge
For controlled concrete preliminary tests referred to in Paras 2.1 & 3.0 shall consist of
three sets of separate tests, and in each set, tests shall be conducted on six
specimens. Not more than one set of six specimens shall be made on any particular
day. Of the six specimens in each set, three shall be tested at seven days and the
remaining three at 28 days. The preliminary tests of 7 days are intended only to
indicate the strength likely to be attained at 28 days.
Works strength tests shall be made in accordance with IS: 516. Each test shall be
conducted on ten specimens, five of which shall be tested at seven days and the
remaining five at 28 days. However, if in each grade concreting done in a day, the
minimum 6 number of cubes shall be taken.
Similar works tests shall be carried out whenever the quality and grading of materials
is changed irrespective of the quantity of concrete poured. The number of
specimens may be suitably increased as deemed necessary by the Engineer-in-
Charge, when procedure of tests given above reveals a poor quality of concrete and
in other special cases.
All work shall be carried out under the supervision of a qualified and a competent
Engineer who will supervise proportioning, placing and compacting of concrete at all
stages.
All necessary labour, materials, equipment, etc. for sampling, preparing test cubes,
curing, etc., shall be provided by the Contractor. Testing of the materials and
concrete may be done in the presence of Engineer-in-Charge authorized
representative in the laboratory established at site.
The average strength of the group of cubes cast for each day shall not be less than
the specified works cube strength. 20 percent of the cubes cast for each day may
have values less than the specified strength, provided the lowest value is not less
than 85 per cent of specified strength.
341
13.4 Manufacturer's Certification: Testing Resulted.
For all materials required for concrete construction including cement, aggregate,
water, reinforcing and prestressing steel the original copies of test certificates, test
results etc. either carried out by the manufacturer or any other agency, the mix
design recommendations etc. shall be submitted to the Engineer-in-Charge for his
approval and record. It shall remain the property of the PRED.
Since the chloride contents of the constituent materials of the concrete would be
additive, it is desirable to keep a check on the overall chloride content of the concrete
to keep it minimal. Specially, for prestressed concrete, the total chloride content of
the concrete when manufactured according to the requirements of workability and
strength shall not exceed 500 ppm by weight of cement. The costs of testing for the
chloride content of the ingredients of concrete and of undertaking remedial measures
if the chloride content is more than the permissible limit shall be borne by the
contractor.
14.0 REPAIRWORK
Repairing leakage in liquid retaining structures which become apparent during leak-
testing will also have to be repaired by the contractor at his own cost following
methods & specifications as directed by the Engineer-in-Charge.
For repair of the concrete works, the contractor may use epoxy as a bonding agent
prior to placing fresh concrete. The use or otherwise of epoxy for the repair work will
be at the discretion of the Engineer-in-Charge. Epoxies shall be applied in strict
accordance with the instructions of the manufacturer.
Epoxy is a two packed or three packed system containing base and hardner/s. The
shelf life of the unmixed cans is about one year or more when stored in a place
where ambient temperature does not increase beyond 75 deg. F. The base and
hardner/s shall be mixed in the correct proportions recommended by the
manufacturer. The blend, after mixing intimately, shall have a pot life of one hour and
the material shall be applied over the old concrete to form a thin film. Fresh concrete
shall be deposited immediately prior to the film drying up so as to ensure proper
bonding between both concrete.
Where the dry pack method is used, holes shall be sharp and square at the surface
edges, but corners within holes shall be rounded. The perimeter of the hole shall be
under-cut in several places. Holes for dry pack shall have a minimum depth of 25
mm. The holes to be repaired shall be scrupulously clean and slightly wet with no
free water on the surface. The surface shall then be dusted lightly with cement by
342
means of dry brush. Under no conditions shall the holes be painted with neat cement
grout.
The dry pack mix shall be proportioned by weight: 1 part cement to 2.5 parts of sand
that will pass a No.16 screen. Only enough water shall be used to produce a mortar
which will stick together when moulded into a ball by a slight pressure of the hands
and will not extrude water but will leave the hands just damp.
Dry pack material shall be placed and packed in layers having a compacted
thickness of about 10mm. Each layer shall be solidly compacted over its entire
surface by use of hardwood stick and hammer. The stick is normally about 300 mm
to 460 mm long and not over 30 mm in diameter. Most of the tamping should be
directed at a slight angle and towards the side of the hole to assure maximum
compaction and bond. Water shall not be used to facilitate finishing.
Filling material used in repair of surfaces which will be exposed after completion of
the project shall be made with cement from the same sources as that used in
concrete and blended with a sufficient amount of white Portland cement to produce
the same colour as in the adjoining concrete. Patched surfaced shall be given a final
treatment as required to make the texture of the patch match that of the surrounding
material.
Immediately after patching is completed, the patched area shall be covered with an
approved non-staining, water-saturated material which shall be kept wet and
protected against sun and wind for a period of 12 hours. Thereafter, the patched
area shall be kept continuously wet by a fine spray or sprinkling of water for not less
than 10 days as required under section 9.1 and 11.1 of this specification. The layers
of gunite may be reinforced with steel mesh if directed by the Engineer-in-Charge.
All materials, procedures and operations used in the repair of concrete and also the
finished work shall be subject to the approval of the Engineer-in-Charge. All fillings
shall be tightly bonded to the concrete and shall be sound, free from shrinkage
cracks, or dummy areas after the fillings have been cured and dried.
The extent of repair shall be decided upon by the Engineer-in-Charge. The cost of
repairs of defective areas shall be borne by the contractor. The Engineer-in-Charge
may adopt at his discretion any other method of repairing like grouting with cement
grout, epoxy grouts or guniting etc., which will be carried out by the contractor at his
cost as per the specifications supplied by the Engineer-in-Charge.
Stone plums shall not be used unless specified on the drawings. When used the size
of stone plums may be from 150 to 300 mm. The maximum dimension of these
stones or plums shall not exceed 1/3rd the least dimension of the members.
All plums shall be hard, durable, clean and free from soft materials or loose piece or
deleterious substance in them and shall not have sharp corners.
During concreting the first layer of concrete of the specified mix shall be laid to a
thickness of at least two and a half times the thickness of the maximum size of plums
to be used. The plums shall then be laid while the top portion of this concrete is still
green but sufficiently stiff to prevent complete submergence of the plums under their
own weight. These plums shall be about half embedded in the concrete and the
343
remaining part exposed so as to form a key with the next layer of concrete. No plums
shall be used for concrete laid under water.
While placing the plums, care shall be taken to see that the clear distance between
any two plums is not less than either the width or thickness of either of the plums.
The distance from plums to the outer surface or from any steel reinforcement shall be
equal to greatest width of the plum.
If plums of stratified stone are used, they shall be laid on their natural bed. Stones
with concave faces shall be laid with the concave upwards.
The thickness of the next and successive layers of concrete shall be at least twice
that of the largest plums.
The total volume of plums shall not exceed 15% of the volume of the finished
concrete.
16.0 SCOPE
The scope for concrete works shall include the cost of all materials, labour, tools and
plant required for mixing, placing in position, vibrating and compacting, including
staging, shuttering, form work, finishing as per directions of the Engineer-in-Charge,
curing and all other incidental expenses for producing concrete of specified strength
to complete the structure or its components as shown on the drawings and according
to these specifications. The quoted rate shall also include the cost of making, fixing
and removing of all centres and forms required for the work.
17.0 STEELREINFORCEMENT
The contractor shall make bar bending schedules and submit the same for the
Engineer’s approval at no extra cost. Approval by the Engineer-in-Charge does not
relieve the contractor of his responsibility to ensure correctness in respect of details /
placing.
Bars shall be bent cold to the specified shape and dimensions or as directed by the
Engineer-in-Charge using a proper bar bender, operated by hand or power to attain
proper radii of bends. Bars shall not be bent or straightened in a manner that will
injure the material.
Bars bent during transport or handling shall be straightened before being used on
work; they shall not be heated to facilitate bending.
Unless otherwise specified, a U type hook at the end of each bar shall invariably be
provided. The radius of the bend shall not be less than twice the diameter of the
344
round bar for mild steel plain bars and not less than four times the diameter for high
strength deformed bars. In case of bars with diameters greater than 25 mm, the
minimum radius should be three times the diameter for mild steel bars and six times
the diameter for high strength deformed bars. The length of the straight part of the
bar beyond the end of the curve shall be at least four times the diameter of the bar.
In the case of bars which are not round, and in the case of deformed bars, the
diameter shall be taken as the diameter of a circle having an equivalent effective
area. The hook shall be suitably encased to prevent any splitting of the concrete.
All reinforcing bars shall be accurately placed in the exact position shown on the
drawings, and shall be securely held in position during placing of concrete by
annealed binding wire not less than 1 mm in size and conforming to IS: 280, and by
using stays, blocks or metal chairs, spacers, metal hangers, supporting wires or other
approved devices at sufficiently close intervals. Bars will not be allowed to sag
between supports nor displaced during concreting or any other operation over the
work. All devices used for positioning shall be of non-corrodible material. Wooden
and metal supports will not extend to the surface of concrete, except where shown on
the drawings. Placing bars on layers of freshly laid concrete as the work progresses
for adjusting bar spacing will not be allowed. Pieces of broken stone, brick or
wooden blocks shall not be used. Layers of bars shall be separated by spacer bars,
precast mortar blocks or other approved devices.
In the case of columns and walls, vertical bars shall be kept in normal position with
timber templates having slots accurately cut in for bar position. Such templates shall
be removed after the concreting has progressed up to a level just below them.
Bars crossing each other, where required, shall be secured by annealed binding wire
of size not less than 1 mm and conforming to IS:280 in such a manner that they do
not slip over each other at the time of fixing and concreting.
As far as possible, bars of full length shall be used. In case this is not possible,
overlapping of bars shall be done as directed by the Engineer-in-Charge. When
practicable, overlapping bars shall not touch each other, but be kept apart by 25 mm
or 1.25 times the maximum size of the coarse aggregate in the concrete between
them, whichever is greater. Where this is not feasible, overlapping bars shall be
bound with annealed steel wire, not less than 1 mm thickness twisted tight. The
overlaps shall be staggered for different bars and located at points along the span
where neither shear nor bending moment is maximum.
345
located at points where the reinforcement steel will not be subject to more than 75
percent of the maximum permissible stresses and the welded joints should be
staggered such that, at any one section, not more than 33 percent of the bars are
welded. Only electric arc welding using a process which excludes air from the
molten metal and conforms to any or all other special provisions for the work will be
accepted. Suitable means shall be provided for holding the bars securely in position
during welding. It must be ensured that no voids are left in welding and when
welding is done in 2 or 3 stages, the previous surfaces shall be cleaned properly.
Ends of the bars shall be cleaned of all loose scale, rust, grease, paint and other
foreign matter before welding. Only competent welders shall be employed on the
work.
The M.S electrodes used for welding shall conform to IS: 814. Welded pieces of
reinforcement shall be tested. Specimens shall be taken from the actual site and
their number and the frequency of tests shall be as directed by the Engineer-in-
Charge.
17.4 Scope
Scope for reinforcement shall include cost of all steel at works spot and its bending,
placing, binding and fixing in position as shown on the drawings and as directed by
the Engineer-in-Charge. It shall also include cost of all devices for keeping
reinforcement in approved position, cost of jointing as per approved method, and all
wastage, overlaps and spacer bars etc., complete.
As soon as practicable after the acceptance of his tender the contractor shall submit
a scheme showing the order of the procedure and methods by which he proposes to
carry out the work together with such details as are necessary to demonstrate the
adequacy, stability and safety of the methods which the contractor proposes to
adopt. The approval to this general scheme of centering as well as design criteria
and loading shall be obtained in good time to facilitate all preparatory work. Any
delay on this account shall be the responsibility of the contractor.
After approval of the general scheme the contractor will prepare detailed designs and
drawings for execution of the work, centering and temporary works. These shall also
be forwarded for approval. No work shall be carried out without prior approval of the
Engineer-in-Charge.
Not withstanding the approval given to design criteria and loading and the general
scheme for the centering, the entire responsibility for the satisfactory execution of the
centering and all temporary works shall rest with the contractor and he shall be liable
to pay all claims and compensations arising from any loss or damage to life and
property due to any deficiency, failure or malfunctioning of the centering or any of the
temporary works.
346
18.1 Re-use of Forms,etc.
18.2.1 Before placing concrete the surface of all forms shall be coated with
suitable non-staining form releasing agents such as raw linseed oil so
as to prevent adhesion of concrete and to facilitate removal of forms.
18.2.2 The form releasing agent shall cover the forms fully and evenly without
excess over drip. Care shall be taken to prevent form releasing agents
from getting on the surface of the construction joints and on
reinforcement bars. Special care shall be taken to thoroughly cover
form strips for narrow grooves, so as to prevent swelling of the forms
and the consequent damage to concrete prior to or during removal of
forms.
18.2.3 Immediately before concrete is placed care shall be taken to see that
all forms are in proper alignment and the supports and fixtures are
properly secured and tightened.
18.2.4 Where forms for continuous surfaces are placed in successive units,
the forms shall lap and fit tightly over the completed surface so as to
prevent leakage of cement slurry from the fresh concrete and to
maintain accurate alignment of the surface.
18.2.5 Forms shall be left in place until their removal is authorized and shall
then be removed with care so as to avoid injury to concrete.
Note:
Time shall be measured from last batch concreted in respect to the structural
member under consideration.
In no case shall forms be removed until there is an assurance that removal can be
accomplished without damaging the concrete surface. Heavy loads shall not be
permitted until after the concrete has reached its design strength. The forms shall be
removed with great caution and without jerking the structure.
347
18.3 Settlement of Formwork and Camber
Due to various reasons such as closure of form joints, shrinkage of timber, dead load
deflections, elastic shortening of form members or formwork deflections, settlement
may occur. The contractor shall take precautions, including using adequately rigid
formwork, in order to prevent excessive settlement/deflection; the usual acceptable
limit being 1 / 500 of the spans of the formwork.
In the absence of any specified camber on the drawings, soffit of all beams more
than 5 m. in span and other than prestressed concrete beams shall be laid to a
camber, the amount of which at mid span shall not be less than 1 / 500 of the span of
the structure. The profile of soffit shall be parabolic.
18.4 Mock-ups
The method for pouring difficult zones of concrete will be pre-studied on mock-ups.
Mock-ups will be particularly necessary for the following:
Work involved in mock-up pours will not be paid to the contractor. Sampling and
testing of all samples will be done by the Contractor. Unsuccessful mock-ups may
have to be repeated in full or in part as required by the Engineer.
19.0 TOLERANCE
All works will be carried out true to the lines, levels and grades shown on the
drawings and within the tolerances specified below. The contractor shall establish,
erect and maintain in an undisturbed condition until final completion and acceptance
of the project control, points and bench marks necessary and adequate to establish
these tolerances.
348
Variation in slab thickness : - 3 mm, + 6mm
349
CIVIL SPECIFICATIONS - 5
1.0 SCOPE
2.0 GENERAL
The provisions of the latest Indian Standards listed below, but not restricted to, form
part of these specifications:
IS: 814- Covered electrodes for metal are welding of structural steel (Part I
&II).
IS: 816- Code of practice for use of metal are welding for general
construction in mild steel.
IS: 817- Code of practice for training and testing of metal are
IS: 823- Code of procedure for manual metal is welding of mild steel.
350
IS: 961- Structural steel (high tensile).
IS:1148- Hot rolled steel rivet bars (up to 40mm diameters)for structural
purposes.
IS: 1477- Part I, Code of practice for painting of ferrous metals in buildings-
pretreatment.
IS: 1599- Method for bend test for steel products other than sheets, strip,
wire and tube.
IS: 1731- Dimensions for steel flats for structural and general engineering
purposes.
IS: 2074- Ready Mixed paint, air drying red-oxide-zinc chrome, and
IS: 4000- Code of practice for assembly of structural joints using high tensile
friction grip fasteners.
Other I.S. Codes and I.R.C. codes pertaining to the items of structural steel not
specifically listed shall also be deemed to come under the purview of this clause.
Pin Material
Rolled steel pins and rollers, including those made from slabs shall comply with the
requirements of IS: 226 - Specification and structural steel and IS: 2062 -
Specification for structural steel (fusion welding quality) or IS: 961 - Specification for
high tensile structural steel.
351
Pin Holes
Pin holes shall be bored true to gauge, smooth, straight, at right angle with the axis of
the member and parallel with each other, unless otherwise required, in built up
members the boring shall be done after the members have been welded. The
specified diameter of pin shall be its minimum diameter. Hole diameter can be
maximum + 0.5 mm more than pin diameter.
Pins
The pins shall be parallel throughout and shall have a smooth surface free from
flaws. At ends of pins there shall be slot to facilitate in driving the pin.
Pins more than 175 mm in length or diameter shall be forged and annealed. Coffer
pins shall be provided on both sides of the pin.
10 FABRICATION
All supplies of structural steel and other materials specified shall be supported by
manufacturers test certificates showing that the materials meet the requirements of
these specifications.
The Engineer-in-Charge may require to get further samples tested and all the cost of
taking samples and testing the same by the approved agency shall be borne by the
Contractor.
2.6 Workmanship
a. No dragging of steel shall be permitted. All steel shall be stored 30 cm above ground
on suitable packing to avoid damage during the monsoons. Steel shall be stored in
the order of erection with erection marks visible. Storage areas shall be prepared and
maintained by the Contractor. Any steel stored
352
near excavations shall be removed immediately to a safe distance to avoid
burial under debris.
ii. Applying one coat zinc phosphate grey primer paint and two coats
of finishing paint as specified in schedule to all surfaces which will
be inaccessible after erection, except surfaces coming in contact
with concrete. It should be noted that all steel work such as
Trusses, Purlins etc., are considered inaccessible.
iii. After steel has been erected, all burrs and abraded spots scratched
surfaces, field welds, bolt heads and nuts shall receive one coat of
primer paint. Before the paint is applied the surface shall be dry and
free from dust, dirt, scale and grease. No paint shall be applied to
bolt or field welds until these bolts or field welds have been
approved by the Engineer.
iv. All steel material except surfaces coming in contact with concrete
shall receive one coat of primer paint after erection after having
been thoroughly cleansed of dust and foreign matter. No paint shall
be applied when humidity is such as to cause condensation on the
surfaces to be painted. Paint shall be stirred frequently to keep the
pigment in suspension.
d. All the external structural steel works shall be painted with two coats of approved
anti-corrosive paint with two coats of compatible primer.
All the materials shall be of the best quality from and approved manufacturer.
The Contractor shall obtain prior approval of the Engineer-in-Charge for the
brand of manufacture and the colour / shade prior to procurement for usage in
the works.
Primer and finish paints shall be compatible with each other to avoid cracking
and wrinkling and shall be from the same manufacturer for each painting
system.
e. Final Paint
353
5.0 ERECTION
5.1 Preliminaries
a) The Contractor shall complete all preliminary works at site, well before the
arrival of structural steel, such as keeping in readiness electrical winches,
mobile cranes, gin poles, compressors, all tools and tackles, rivet guns,
welding sets, torque wrenches etc. and work that may be necessary so as to
start erection immediately after the arrival of steel at site.
b) The Contractor shall furnish at his own expenses, the necessary non-
inflammable staging and hoisting or equipment required for the erection work
and shall remove and take them away after the completion of the job. The
contractor shall also provide necessary passage ways, fences, safe belts,
helmets, lights and other fittings to the satisfaction of the Engineer and for
protection of his men and materials.
All structures shall be erected as shown on drawings. The contractor shall carry out
all erection work in the sequence required by the Engineer-in-Charge. The method
of erection and complete erection scheme shall be subject to the approval of the
Engineer-in-Charge and shall be modified as required by the Engineer-in-Charge.
This, however, will not relieve the contractor of the responsibility for safe and
expeditious completion of the work, its quality and accuracy.
5.3 Workmanship
a. Unless specified herein, all erection work will be carried out in accordance
with the latest edition of Indian Standard code of practice for use of structural
steel in General Building Construction IS: 800 and AISC code wherever
applicable.
b. Drifts should be used only for drawing the work into position and must not be
used to such an extent so as to destroy the holes. Drifts of a larger size than
the nominal diameter of the holes or burrs must be rectified to the satisfaction
of the Engineer-in-Charge.
354
d. As erection progresses, the work shall be securely bolted to take care of all
dead load, wind and erection stresses. No final welding or bolting shall be
done until the structure has been properly aligned and approved by the
Engineer-in-Charge.
f. The contractor shall protect all existing plants, embedded parts, all piping,
conduits, equipment and facilities against damage during erection. The
contractor shall perform his work in a manner which in no way endangers the
operations of any existing plant or structures or hinders other construction
activities.
h. In case of any faulty erection, all such dismantling and re-erection required
will be at Contractor’s cost.
i. Shim stock of mild steel plates required for erection will be set, levelled and
prepared for grouting. Where flat bearing beams occur, bearing plates shall
be set, levelled and prepared for grouting.
5.4 Tolerance
The erection shall be carried out to the requirements stated in Section 7 (h) of AISC
Code Standard practice.. Column splices and other compression joints which
depend upon contact bearing, upon completion, shall bear with respect to the
centroid of the contact area.
At least 65% of the entire contact area shall be in full bearing and the separation of
any remaining portion shall not exceed 0.5 mm except locally at toes of flanges
where a 50% greater separation is permissible. Otherwise corrective measures as
specified by the Engineer shall be taken.
5.5 Connections
5.5.1 H.S.F.G.Bolts
The Contractor shall obtain the prior written approval of the Engineer-in-
Charge for the method proposed to be adopted for tightening the High
Strength Friction Grip bolts. For preliminary assembly and before use of these
bolts he shall use his own erection bolts.
In general bolts and rivets will conform to the relevant Indian Standards. The
methods of establishing connections use of equipment, etc., shall be as
approved by the Engineer-in-Charge.
355
5.5.3 Welding
Welding where specified shall be performed by the shielded electric arc, gas
or other approved methods, using coated electrodes and / or low hydrogen
electrode conforming to IS: 814. The welding process and the qualification of
the welding operators shall conform to IS: 817 and IS: 823 and shall be got
approved before commencement of any work of welding.
All field assembly and welding shall be executed in accordance with the
requirements for shop fabrications excepting which manifestly apply to shop
conditions only. Where the steel has been delivered, painted, the paint shall
be removed before field welding for a distance of at least 50 mm on either
side of the joints. All welds should be free from defects like blow holes, lack
of penetration, slag intrusion etc. All welds shall be cleaned of slag or flux
and shall show uniform smoothness of weld metal, feather edges without
overlap and free from porosity. Where a thick weld is required the weld metal
shall be deposited in successive layers. Each layer except the last, shall be
preened moderately before the next layer is applied. The contractor shall be
responsible for the quality of the work performed by his welding group.
If required, the engineer may test the welds by non-destructive tests. Any
defective welds shall be made good by the Contractor at no extra cost and
the cost of non-destructive testing for such defective welds shall be borne by
the Contractor.
6.0 SCOPE
The scope under this item shall including cost of all materials, labour, supervision,
tools and plant, apparatus, conveying equipment, incidental expenses, painting as
specified, nuts, bolts and washers etc., complete.
356
CIVIL SPECIFICATIONS - 6
1.0 SCOPE
These specifications cover the use of Brick Masonry for the structural purposes.
2.0 GENERAL
The provision of the latest Indian Standards listed below form part of these
specifications:
IS: 1725 Specifications for solid cement blocks used in general building
construction.
IS:3952 Specification for burnt clay hollow blocks for walls and
partitions.
357
IS: 4139 Specification for sand lime bricks
IS: 4441 Code of practice for use of silicate type chemical resistant
mortars.
IS: 4442 Code of practice for use of sulphur type chemical resistant
mortars.
Other I.S. Codes not specifically mentioned here but pertaining to the use of bricks
for structural purposes forms part of these specifications.
3.0 MATERIALS
3.1 Bricks
The contractor should use the fly ash bricks wherever available. Bricks shall be of
regular and uniform size, shape and colour, uniformly well burnt throughout but not
over burnt. They shall have plane rectangular faces with parallel sides and sharp
straight and right angled edges. They shall be free from cracks or other flaws. They
shall have a frog of 10 mm. depth on one of their flat faces.
They shall give a clear metallic ringing sound when struck. They shall show a fine
grained, uniform homogeneous and dense texture on fracture and be free from lumps
of lime, laminations, cracks, air holes, soluble salts causing efflorescence or other
defects which may in any way impair their strength, durability, appearance or
usefulness for the purpose intended. They shall not have any parts under-burnt.
They shall not break when thrown on the ground on their flat face in a saturated
condition from a height of 60cm.
Size of bricks
3.1.1 The size of the conventional bricks may vary from 8 3/4" x 4.3/16" x
2.5/8" to 9" x 4 1/4" x 3". Only bricks of one standard size, shall be
used on one work unless specially permitted by the Engineer. The
following tolerances are permitted in the standard conventional size
adopted on a particular work:
3.1.2 When metric bricks are used they shall comply with I.S: 1077 -1976.
Concrete Block
The size of the concrete block (solid block) shall be 400 mm x 200 mm x 200 mm
only be used for construction.
Absorption
After immersion in water, absorption by weight shall not exceed 20% of the dry
weight of the brick when tested according to IS:1077-1976
358
Crushing strength
The load to crush the brick when dry shall not be less than 50 kg/sq.cm. and when
thoroughly soaked, shall not be less than 35 kg/sq.cm.
The load to crush the concrete block when dry shall not be less that 50 kg/sq.cm.
3.3 Mortars
Cement and sand shall be mixed in specified proportions given on the drawings.
cement shall be proportioned only by weight, by taking its unit weight as 1440 kg per
cubic metre and the sand shall be proportioned by volume after making due
allowance for bulking. The required quantity of water shall then be added and the
mortar mixed to produce workable consistency.
4 CONSTRUCTION
Bricks shall be soaked in water for a minimum period of one hour before use so that
they will be saturated and will not absorb water from the mortar. When bricks are
soaked they shall be removed from the tank sufficiently in advance so that at the time
of laying they are skin-dry. Such soaked bricks shall be stacked on a clean place
where they are not spoil by dirt, earth, etc.
All brick work shall be laid in English bond, even and true to line, plumb, level and all
joints accurately kept. The bricks used on the face shall be selected whole ones of
uniform size and with true rectangular face. Brick shall be laid with frogs up, if any,
onafullbedofmortar.Whenlaying,bricksshallbeslightlypressedsothatthe
359
mortar gets into all the surface pores of bricks to ensure proper adhesion. All joints
shall be properly flushed and packed with mortar so that no hollow spaces are left.
Before laying bricks in foundation, a layer of not less than 12 mm of mortar shall be
spread to make the surface on which the brick work will be laid even. Immediately
thereafter, the first course of bricks shall be laid.
The brick work shall be built in uniform layers, corners and other advanced work hall
be raked back. Brick work shall be done true to plumb or in specified batter. No part
of it, during construction, shall rise more than one meter above the general
construction level, to avoid unequal settlement and improper jointing.
Toothing may be done where future extension is contemplated but shall be used as
an alternative to raking back.
4.3 Joints
The thickness of joints shall not exceed 10 mm and this thickness shall be uniform
throughout.
4.5 Curing
Green work shall be protected from rain by suitable covering. Masonry work in
cement or composite mortar shall be kept constantly moist on all faces for a minimum
period of seven days. The top of the masonry work shall be left flooded with water at
the close of the day. During hot weather all finished or partly completed work shall be
covered or wetted in such manner as will prevent rapid drying of the brick work.
4.6 Scaffolding
The scaffolding shall be sound and strong to withstand all loads likely to come upon it
and will be double or single as is warranted for the particular work. The holes which
provide resting space for horizontal members shall not be left in masonry under one
metre in width or immediately near the skew backs of arches. The holes left in the
masonry work for supporting the scaffolding shall be filled and made good with 1:4:8
cement concrete.
All equipment used for mixing or transporting mortar and bricks shall be clean and
free from set mortar, dirt or other injurious foreign substances.
360
joints shall be well brushed to remove dust and loose particles and the surface shall
be thoroughly washed with water, cleaned and wetted.
5.0 WEEPHOLES
In case of abutment retaining walls and wing walls, weep holes as shown on the
drawings or directed by the Engineer shall be provided in the masonry to drain
moisture from the backfilling. Weep holes shall be 8 cm wide, 15 cm high and shall
extend through the full width of the masonry with slope of about 1 vertical to 20
horizontal towards the draining face.
The spacing of weep holes shall be as shown on the drawings with the lowest one at
about 15 cm above the low water level or ground level whichever is higher or as
directed by the Engineer.
5 The scope under this item shall include the cost of all labour, materials, tools and plant,
scaffolding and other expenses incidental to the satisfactory completion of the work as
described herein above and as shown on the drawings and including the following.
j. dewatering required for completing this item and till the mortar of masonry
pointing & plastering is properly set
361
CIVIL SPECIFICATIONS - 7
1.0 SCOPE
The Contractor shall furnish all labour, materials, and equipment required for the
construction of all stone masonry work required.
2.0 MATERIALS
Building stones shall be obtained from the quarries to be approved by the Engineer-
in-Charge and shall conform to IS: 1597 (Part-I).
Stones shall be of uniform colour and texture, hard, durable tough and the best
quality of its respective kind. These shall be free from decay, sand holes, veins,
flaws, cracks and other defects. These shall be carried in such a way as to be most
suitable for the particular class of work for which these are required. Stone not suited
for the particular class of work defined shall be rejected and rejected stone shall be at
once removed from the site, by the contractor.
3.0 LAYING
Stratified stones shall be laid on their natural bed i.e., with the strata perpendicular to
the pressure. The courses shall be built perpendicular to the pressure.
Where there is to be variation in the depth of the course, larger stones are to be
placed in the lower courses, the thickness of courses decreasing gradually towards
the top the wall.
To give sufficient lateral bond, a stone in any course should overlap the stone in the
course below i.e., joints parallel to the pressure in two adjoining courses should not
lie too closely in the same vertical line.
To give sufficient transverse bond the prescribed number of headers must extend
from front to back of thin walls or from outside to the interior of thick walls.
At all angle junctions of walls the stones at each alternative course shall be so
carried into each of the respective walls as to unite the work thoroughly.
Where breaks are unavoidable in carrying out the work continuously in horizontal
courses, sufficient long steps shall be left to join the old and new work.
The practice of building two thin faces tied with occasional through stones and filling
up the middle with small stuff or even dry packing is strictly prohibited.
If it is necessary to move a stone after it has been placed on the mortar bed, it should
be lifted clear and rest and not made to slide over stones already laid.
362
4.0 WATERING
To prevent absorption of water from the mortar, the stones shall be sufficiently well
wetted before laying.
All masonry shall be kept watered for three weeks from the date of building in place
unless otherwise instructed by the Engineer.
At the close of the day’s work or for other period of cessation of work, the top of all
unfinished masonry is to be kept well flooded.
Should the mortar perish i.e., become dry, white or powdery through neglect of
watering, the work shall be pulled down and rebuilt at the Contractor’s expense.
The mortar to be used for each class of masonry shall conform to the particular
standard specification for that class of mortar and the standard specifications for the
materials used therein.
Care shall be taken to see that holes for passage of water wherever necessary as
from terraces, bath rooms, recesses for downfall pipes, etc., are provided during
construction and neatly finished off by pointing or plastering as ordered. Well
seasoned wooden plugs of sizes and quality approved by the Engineer are to be built
in as work proceeds for fixing door and window shutter appliances, hangers, picture
rails, and for any other purpose decided necessary by the Engineer. Holes are also
to be cut in the sill-stones to receive the uprights of door-frames, in cases where
there is no threshold plate to the frame. No extra payment will be made to the
contractor for the supply and fixing of the wooden plugs forming holes, etc., as
described in this clause, for any class of masonry.
363
CIVIL SPECIFICATIONS - 8
1.0 SCOPE
These specifications cover the use of plastering for masonry and RCC work, pointing
for brick and stone masonry work.
The provision of the latest revisions of the following IS codes shall form a part of this
specification to the extent they are relevant.
IS:269 Specification for ordinary rapid hardening and low heat Portland
cement
IS: 1630 Mason's Tools for Plaster work and pointing work.
Other I.S. Codes, not specifically mentioned here, but pertaining to plastering work,
form part of these specifications.
3.0 GENERAL
Cement mortar shall have the proportion of cement to sand as specified and shall
comply with relevant clauses of concrete specifications.
3.2 Scaffolding
Scaffolding will be double and shall be erected with steel sections or pipes of
adequate strength so as to be safe for construction operations. The contractor shall
take all measures to ensure the safety of the work and working people. Any
instructions of the Engineer in this respect shall also be complied with. The
contractor shall be entirely responsible for any damage to properly or injury to
persons resulting from ill erected scaffolding, defective ladders and materials or
otherwise arising out of his default in this respect. Proper scaffolding shall be
provided to allow easy approach to every part of the work. Overhead work shall not
be allowed.
364
3.3 Tools and Accessories
Tools and accessories used in plaster work shall conform to IS: 1630. All tools shall
be cleaned by scrapping and washing at the end of each day's work or after use.
Metal tools shall be cleaned after each operation. All tools shall be examined to see
that they are thoroughly cleaned before plastering is begun.
The programme of other building operations before, during and after plastering shall
be according to the instructions contained in clause 9 of IS: 1661.
All general precautions as specified in IS: 1661, Clause 9, shall be taken and
preparation of the background shall be done as laid down in IS: 1661, Clause 13.
Care shall be taken to see that other parts of the work or adjacent works are not
damaged while plastering.
All joints in the face work that is to be plastered shall be raked out to depth equal to
not less than the width of the joints or as directed by the Engineer. The raking shall
be done taking care not to allow by chipping of masonry. In new work the raking out
shall be done when the mortar in the joints is still green. Smooth surfaces of
concrete, old plaster, etc. must be suitably roughened to provide necessary bond for
the plaster. All dirt, soot, oil paint or any other material that might interfere with
satisfactory bond shall be removed. In the case of stone masonry, scrubbing on the
walls to receive the plaster shall not be more than 12 mm ( 1/2"). The surface to be
plastered shall be cleaned and scrubbed with fresh water and kept wet for 6 hours
prior to plastering. It shall be kept damp during the progress of the work. The
plastering shall not be commenced unless the preparatory work is passed in writing
by the Engineer.
3.7 Gauges
3.8 Workmanship
Plastering:
In all plaster work the mortar shall be firmly applied with somewhat more than the
required thickness and well pressed into the joints and on the surface and rubbed
and levelled with a flat wooden rule to give required thickness. Long straight edges
shall be freely used to give perfectly plane and even surface. All corners must be
finished to their true angles or rounded as directed by the Engineer. The surface
shall be finished to plane or curved surface as shown on the plan or directed by the
Engineer, and shall present a neat appearance. The mortar shall adhere to the
masonry surface intimately when set and there should be no hollow sound when
struck. Cement plastering should be done in squares or strips as directed.
Plastering shall be done from top downward.
365
First or Backing Coat
The first coat of the specified thickness shall be applied as described above. The
subsequent coat shall be applied after this cost has been allowed to set for 3 to 5
days depending upon weather conditions. The surface shall not be allowed to dry
during this period.
Projecting burrs of mortar formed due to the gaps at joints in shuttering shall be
removed. The surface shall be scrubbed clean with wire brushes. In addition
concrete surface shall be poke marked with a pointed tool at spacing of not more
than 50 mm centres, the pokes being made not less than 3 mm deep, to ensure a
proper key for the plaster. The mortar shall be washed off and surface cleaned of all
oil, grease etc., and well wetted before the plaster is applied.
5.2 Basecoat:
The base coat plaster shall be of cement mortar 1:4. Waterproofing compound of
approved make like Sika, Accoproof shall be added according to the makers'
instructions to make the mortar water-proof.
The plaster with this mortar shall be laid as specified above with a thickness of not
more than 12 mm for brick work and concrete surfaces, and 15mm for rubble stone
masonry. Keys shall be formed on the surface by thoroughly combing it with wavy
horizontal lines about 12 mm apart and about 3 m deep when the mortar is still
plastic. The base coat shall be cured for not less than 2 days.
The cement mortar for sand faced plaster shall have washed Kharasalis or similar
type of approved sand with slightly larger proportion of coarse material. The
proportion of cement to sand shall be 1:3. The water is added gradually to make the
mixture homogeneous. The thickness of finishing coat shall not exceed 7 mm. After
application, the surface should be finished with a wooden flat, lined with cork and
tapped gently to retain a coarse surface texture. When the finishing coat has
hardened, the surface shall be kept moist continuously for 14 days.
The first coat of plaster shall be of cement mortar of 1:4 mix and applied according to
the relevant provisions of IS: 1661 Clause 14.1. The finished thickness of the first
coat shall be 12 mm for brick masonry or concrete surface and 15 mm for rubble
stone masonry. The plaster shall be laid by throwing the mortar (by using a strong
whipping motion) on the prepared surface with a trowel in a uniform layer, and
pressed to form a good bond. The surface shall be roughened.
366
6.2 Second Coat
The second coat shall be the rough coat mixture consisting of aggregate which may
vary in size from 5 to 8 mm and may consist of specially graded mixture mixed with
fine sand and cement. The proportion of cement to sand and aggregate shall be
1:1½:3. It shall be flung upon the first coat with large trowels to form an even
protective coat. The second coat must be applied while the first coat is still soft and
plastic. The work shall generally conform to clause 16.5 of IS: 166. The thickness of
the coat shall be about 12 mm.
7 NEERUFINISH
7.1 Materials
Cement, sand and other materials shall generally conform to relevant clauses of
concrete specifications and Neeru shall conform to clause c (i.e pure fat lime) of IS:
712. All sand shall pass through IS sieve no. 60.
Lime shall be slaked and mixed with sufficient water to form a thick paste. It shall be
reduced to a fine paste by grinding. It shall then be passed through a fine sieve (3
mm mesh) to remove all unslaked particles and foreign matter and allowed to mellow
under water for at least 10 days in large slaking tanks. The surplus water on the top
shall be allowed to run off. The slaked lime paste thus formed shall be used for
preparing Neeru.
The Neeru shall be prepared by mixing together 4 parts of this lime paste and 1 part
of fine sieved sand by volume. Jute fiber finely chopped shall be added to the above
mortar at the rate of 4 kg of jute to every cu. meter of lime-sand mixture. The mixture
shall then be properly ground to a fine paste between two stones or a mill. The Neeru
thus prepared shall be kept moist until used and no more than what can be
consumed in 15 days shall be prepared at a time.
The plaster surfaces shall be combed lightly with wire brushes or nails before it is
completely set to form hey for Neeru. The undercoat shall be only damped evenly
but not soaked before the application of Neeru.
7.4 Application
Neeru shall be applied to the prepared and partially set but somewhat plastic
surfaces with steel trowel to a thickness slightly exceeding 1.5 mm and rubbed down
to 1.5mm thickness and polished to a perfectly smooth and even finish working from
top to bottom. While trowelling is going on, soap stone power contained in thin
muslin bags shall be dusted over the surface and worked in. Moistening shall be
commenced as soon as the plaster has hardened sufficiently and is not susceptible
to injury. Soaking of wall shall be avoided and only as much water as can be readily
absorbed shall be used. The surface shall be kept sprinkled with water for 14 days.
The finished surface shall be true and even and present a uniform texture throughout
and all jointing marks shall be eliminated.
367
8 .0 POINTING
8.1 General
When the type of pointing is not mentioned in the item, sunk pointing is described
below shall be carried out.
Where the joints have not been raked out when the mortar is green, the joint shall be
chipped (without damaging the masonry) to such a depth that the minimum depth of
new mortar measured from either the sunk surface of the finished surface of the
finished pointing or from the edge of the brick shall not be less than 12 mm,
thoroughly cleaned off all loose particles with a stiff brush and thoroughly wetted.
8.3 Pointing
The mortar shall be pressed into the raked out joints with a pointing trowel. The
mortar shall not spread over the corners, edges or the surface of the masonry. With
a pointing tool, the mortar shall be neatly pressed back to about 3 mm or as directed.
The vertical joints shall be pressed back similarly to match the horizontal joints. The
surface of masonry shall be cleaned of all mortar.
8.4 Curing
The pointed face shall be kept continuously wet for 7 days suitably protected from all
damage.
9.0 SCOPE
The scope under this item shall include erecting and removal of scaffolding all labour,
materials, equipment, plants, tools and all incidental expenses to complete plastering
pointing rubbing out joints, cleaning, wetting, filling with cement mortar, trowelling etc.
and making of drip moulds, grooves, etc.
368
CIVIL SPECIFICATIONS - 9
1.0 SCOPE
These specifications cover the use of paints for the plastered and concrete surfaces.
It also includes the painting of wood and metal surfaces.
2.0 GENERAL
The provisions of the latest revisions of the following IS: Codes shall form a part of
this specification.
IS:63 Whiting for Paints Ready mixed paint, brushing, grey filler, for
Enamels, for use over primers.
IS: 2338 Code of practice for finishing of wood and wood based materials
Part I Operations and workmanship for finishing.
IS: 2338 Code of practice for finishing of wood and wood based materials,
Part II: Schedule
IS: 2395 Code of practice for painting concrete masonry and plaster
Part I: surfaces. Operation &workmanship
IS: 2395 Code of practice for painting concrete, masonry and plaster
Part II: surfaces. Schedule
369
Other IS Codes not specifically mentioned here, but pertaining to painting form part
of these specifications.
3.0 MATERIALS
8 PLASTERED OR CONCRETESURFACES
4.1 General
Preparation of surfaces
The surface shall be thoroughly cleaned off all dirt, dust, mortar dropping and other
foreign matter, before paint is to be applied. New plaster surfaces shall be allowed to
dry for at least 2 months, before applying paint. All unnecessary nails shall be
removed. Pitting in plaster shall be made good with putty. The surface shall then be
rubbed down again with a fine grade sand paper and made smooth.
The surface shall be allowed to dry thoroughly before the regular coat of paint is
allowed.
The surface affected by moulds moss, fungi, algae licnens, efflorescence shall be
treated in accordance with IS 2395 (Part I) before applying paint.
Preparation of Surfaces
Any unevenness shall be made good by applying putty, made of plaster of Paris
mixed with water on the entire surface including filling up the undulation and then
sand papering the same after it is dry.
Primer Coat
The primer where used as on undercoated surfaces shall be alkali resistance primer
or distemper primer as specified in the item. These shall be of the same
manufacture as of oil bound distemper. If the wall surface plaster has not dried
completely alkali resistance primer shall be applied before distempering the walls.
But if the distempering is done after the wall surface is dried completely, distemper
primer shall be applied.
Application
Primer shall be applied with a brush on the clean dry and smooth surface. Horizontal
strokes shall be given first and vertical strokes shall be applied immediately
afterwards. This entire operation will constitute one coat. The surface shall be
370
Finished as uniformly as possible leaving no brush marks. It shall be allowed to dry
for at least 48 hours, before oil bound distemper or paint is applied.
The distemper shall be diluted with water or any other prescribed thinner in a manner
recommended by the manufacturer. Only sufficient quantity of distemper required for
days work shall be prepared.
After the primer coat has dried for at least 48 hours, the surface shall be lightly sand
papered to make it smooth for receiving the distemper, taking care not to rub out the
priming coat. All loose particles shall be dusted off after rubbing. Minimum two coats
of distemper shall be applied with brushes in horizontal strokes followed to
immediately by vertical which together shall constitute one coat. The subsequent
coats shall be applied after a time interval of at least 24 hours between consecutive
coats to permit the proper drying of the preceding coat.
The finished surface shall be even and uniform without patches, brush marks,
distemper, drops, etc.
Sufficient quantity of distemper shall be mixed to finish one room at a time. The
application of a coat in each room shall be finished in one operation and no work
shall be started in any room, which cannot be completed the same day.
15 cm. double bristled distemper brushes shall be used. After each days work,
brushes shall be thoroughly washed in hot water with soap solution and hung down
to dry. Old brushes which are dirty and caked with distemper shall not be used on the
work.
Plastic emulsion paint and primer of approved brand manufacture and shade shall be
used.
Applications
The priming and the number of coats to be applied shall be as specified in the bill of
quantities and shall be as per the manufacturers specification. The surface on
finishing shall present a flat velvety smooth finish.
Precautions
A) Old brushes if they are to be used with emulsion paints, should be completely
dried of turpentine or oil paints by washing in warm soap water. Brushes should be
quickly washed in water immediately after use and kept immersed in water during
break periods to prevent the paint from hardening on the brush.
B) In the preparation of walls for plastic emulsion painting, no oil base putties shall
be used in filling cracks, holes,etc.
C) Splashes on floors etc, shall be cleaned out without delay as they will be difficult
to remove after hardening.
371
4.3 Water Proof Cement Paint
Preparation of Surfaces
The surfaces shall be thoroughly wetted with clean water before the water proof
cement paint is applied.
Preparation of Paint
Portland cement paints are made readily by adding paint powder to water and stirring
to obtain a thick paste which shall then be diluted to a brushable consistency.
Generally equal volumes of paint powder and water make a satisfactory paint. In all
cases the manufacturer’s instructions shall be followed. The paint shall be mixed in
such quantities as can be used up within an hour of mixing as otherwise the mixture
will set and thicken, affecting flow and finish.
The lids of cement paint drums shall be kept tightly closed when not in use, as by
exposure to atmosphere the cement paint rapidly becomes air set due to its
hydroscopic qualities.
Application of Paint
When weather conditions are such as to cause the paint to dry rapidly, work shall be
carried out in the shed as far as possible. This helps the proper hardening of the
paint film by keeping the surface moist for a longer period.
To maintain a uniform mixture and to prevent segregation the paint shall be stirred
frequently in the bucket.
For undecorated surfaces, the surface shall be treated with minimum two coats of
water-proof cement paint. Not less than 24 hours shall be allowed between two
coats and the second or subsequent coat shall not be started until the preceding coat
has become sufficiently hard to resist marking by the brush being used. In hot dry
weather the preceding coat shall be slightly moistured before applying the
subsequent coat.
The finished surface shall be even and uniform in shade without patches, brush
marks, paint drops, etc.
Cement paints shall be applied with a brush with relatively short stiff hog or fiber
bristles. The paint shall be brushed in uniform thickness and shall be free of
excessively heavy brush marks. The laps shall be well brushed out.
Curing
Painted surfaces shall be sprinkled with water two or three times a day. This shall
done between coats and for at least two days following the final coat. The curing
shall be started as soon as the paint has hardened so as not to be damaged by the
sprinkling of water say about 12 hours after its application.
372
9 PAINTING OF WOOD AND METALSURFACES
The materials required for the execution of painting work shall be obtained directly
from approved manufacturers and brought to the site in maker's drums, with seals
unbroken. All paints shall not be inferior to relevant Indian Standards as mentioned
under sub-head "Material".
All materials not in actual use shall be kept properly protected. Lids of containers
shall be kept closed and surface of paint in open or partially open containers covered
with a thin layer turpentine to prevent formation of skin. Materials which have
become stale or fat due to improper and long storage shall not be used. The paint
shall be stirred thoroughly in its container before pouring into small containers. While
applying also, the paint shall be continuously stirred in the smaller container. No left
over paint shall be put back into stock tins. When not in use, the containers shall be
kept properly closed.
If for any reason thinning is necessary, in case of ready mixed paint, the brand of
thinner recommended by manufacturer shall be used.
Painting except the priming coat shall generally be taken in hand after all other
builder's work is practically finished. The rooms shall be thoroughly swept out and
the entire building cleaned up at least one day in advance of the paint work being
started. The surface to be painted shall be thoroughly cleaned and dusted. All rust,
dirt scales, smoke and grease shall be thoroughly removed before painting is started.
No painting on exterior or other exposed parts of the work shall be carried out in wet,
humid or otherwise unfavourable weather and all the surfaces must be thoroughly dry
before painting work is started.
Brushing of Paint
The brushing operations are to be adjusted to the spreading capacity advised by the
manufacturers of the particular paint. The painting shall be applied evenly and
smoothly by means of crossing and laying off, the later in the direction of the grain of
wood. The crossing and laying off consists of covering the area over with paint,
brushing the surface hard for the first time over and then brushing alternatively in the
opposite directions two or three times and then finally brushing lightly in a direction at
right angles to the same. In this process, no brush marks shall be left after the laying
off is finished. The full process of crossing and laying off will constitute one coat.
During painting, every time after the paint has been worked out of the brush bristles
or after the brush has been unloaded, the bristles of the brush (which are down
together due to the high surface tension) shall be opened up by striking the brush
against a portion of the unpainted surface with the end of the bristles held at right
angles to the surface, so that bristles thereafter will collect the correct amount of
paint when dipped again into the paint container.
Spraying
Where so stipulated, the painting shall be done with spray. Spray machine used may
be (a) high pressure (small air aperture) type or (b) a low pressure (large air gap)
type, depending on the nature and location of work to be carried out. Skilled and
373
experienced workmen shall be employed for this class of work. Paints used shall be
brought to the requisite consistency by adding a suitable thinner.
Spraying should be done only when dry conditions prevails. During spraying the
spray gun shall be held perpendicular to the surface to be coated and shall be
passed over the surface in a uniform sweeping motion. Different air pressures and
fan adjustment shall be tried so as to obtain the best application with the minimum
wastage of paint. The air pressure shall not be kept too high as otherwise the paint
will log up and will be wasted.
At the end of the job, the spray-gun shall be cleaned thoroughly so as to be free from
dirt. Incorrect adjustments shall be set right, as otherwise they will result in variable
spray patterns, runs, sags and uneven coats.
Each coat shall be allowed to dry completely and lightly rubbed with very fine grade
of sand paper and loose particles brushed off before next cast is applied. Each coat
shall vary slightly in shade and shall be got approved from the Engineer-in-Charge
before next coat is started.
Each coat except the last coat, shall be lightly rubbed down with sand paper or fine
pumice stone and cleaned off dust before the next coat is applied.
No hair marks from the brush or clogging of paint puddles in the corner panels,
angles of moulding, etc. shall be left on the works. In painting doors and windows,
the putty round the glass panes shall also be painted but care shall be taken to see
that no paint stains etc. are left on the glass. Tops of shutters and surfaces in similar
hidden locations shall not be left out in painting.
In painting steel work, special care shall be taken while painting over bolts, nuts,
rivets, overlaps etc.
The additional specifications for primer and other coats of paints shall be according
to the detailed specifications under the respective headings.
After work, the brushes shall be completely cleaned off paint and linseed oil by
rinsing with turpentine. After cleaning, the brushes are wrapped in heavy paper or
water proof paper for storage. It is to be used the next day; it shall be hung in a
thinner or linseed oil in a container. On no account shall brushes be made to stand
on bristles. A brush in which paint has dried up is ruined and shall on no account be
used for painting work. The containers, when not in use, shall be kept closed and
free from air so that paint does not thicken and also shall be kept guarded from dust.
When the paint has been used, the containers shall be washed with turpentine and
wiped dry with soft clean cloth, before they can be used again.
Preparation of Surfaces
The surface before painting shall be cleaned of all rust, scale, dirt and other foreign
matter sticking to it with wire brushes, steel wool, scrappers, sand papers etc. The
surfaces shall then be wiped finally with mineral turpentine which shall also remove
grease and perspiration of hand marks. The surface shall then be allowed to dry.
374
Preparation of Surfaces
The surface shall be treated with Mordant Solution (5 litres for about 190 sq.m) by
rubbing the solution generously, with a brush or bundle of rags on a stick. After
about half an hour, the surface will turn grey and parts remaining bright shall be
retouched and the extra surface washed down thoroughly with clean cold water and
allowed to dry.
After preparation of the surface, the priming coat shall be applied immediately. The
specifications for application shall conform to Para 5.1 above.
All the external steel works shall be painted with two coats of approved anti-corrosive
paint with two coats of compatible primer.
All the materials shall be of the best quality from and approved manufacturer. The
Contractor shall obtain prior approval of the Employer’s Representative for the brand
of manufacture and the colour/shade prior to procurement for usage in the works.
Primer and finish paints shall be compatible with each other to avoid cracking and
wrinkling and shall be from the same manufacturer for each painting system.
Preparation of Surface
All wood work shall be dry and free from any foreign matter, incidental to building
operation. Nails shall be punched well below the surface to provide a firm key for
stopping. Moulding shall be carefully smoothened with abrasive paper and projecting
fibres shall be removed. Flat portions shall be smoothened off with abrasive paper
used across the grain prior to painting. Any knots, resinous, streaks or bluish sap
wood that are large not enough to justify cutting out shall be treated with two coats of
pure shellac knotting, applied thinly and extended about 25 mm beyond the actual
area requiring treatment.
Hard Boards
The surface shall be dusted off and painted with a coat of plastic emulsion paint
thinned with water or with a coat of shellac varnish as specified. The surface shall
then be rubbed down with fine grade abrasive paper and followed with required
under coating and finishing coat as for soiled wood.
375
Particle Board
The surface shall be filled with a thin brushable filler and finished as for solid wood.
Insulation Boards
Priming Coat
The dirt or any other extraneous material shall be removed from the surface to be
painted. In case the surface is already finished with primer coat but unsatisfactory, it
shall be rubbed down to bare wood and surface reprimed. Primer shall be applied by
brushing.
The filler shall be applied with brush or rag in such a way that it fills up all the pores
and indentations and levels up the surface. It shall be allowed to dry for 24 hours
and it shall then be cut and rubbed with emery paper so that the surface of the wood
is laid bare, with the filler only in the pores and crevices of the wood.
Stopping
All holes, cracks, crevices, etc. shall be stopped carefully to true and level surface
with putty before the main undercoat is applied and after the application of the
priming coat, stopping shall be prepared as below:
Bees wax, resin and lac (orange in colour) in the proportion of 1:1:16 by weight shall
be melted down together in a suitable pot using slow heat, the mix being kept well
stirred. Colouring materials to produce the required shade shall be added into
molten mixture and stirred. Stopping shall on cooling be rolled into stick forms for
use.
Application of Paints
The preservatives of specified quality shall be applied in two coats. On new wood
work, it shall be applied liberally with a stout brush and not doubled with rags or
cotton waste. The first coat shall be allowed at least 24 hours to soak in before the
second coat is applied. The excess of preservative which does not soak into the
wood shall be wiped off with a clean dry piece of cloth.
10 WHITEWASHING
6.1 General
The item refers to white-washing over old and new concrete, stone masonry brick
plastered surfaces and asbestos cement sheets.
376
White wash shall be prepared from fresh burnt white stone lime or shell lime. This
lime shall be of class C type as per IS: 712. Surkhi lime or lime of equivalent quality
may be used. The lime shall be dissolved in a tub with sufficient quality of water
(about 4.5 litres/Kg. of lime) and the whole shall be thoroughly mixed and stirred until
it attains the consistency of thin cream. The wash shall be taken out in small
quantities and strained through a clear course cloth. Alternatively with IS: 63 may
also be used. Clean gum dissolved in hot water shall then be added in suitable
proportion of 2 gm of gum arabic to a litre of lime or whiting to prevent the white-wash
coming off easily when rubbed. Rice may be used instead of gum.
6.2 Scaffolding
This may be double or single according to requirements. If ladders are used, pieces
of old gunny bags or cloth rags shall be tied on their tops to avoid damage or
scratches to the wall. Proper stage scaffolding shall be created when white-washing
ceiling. The contractor shall be responsible for accidents if any taken place.
The surface shall be prepared by removing all mortar dropping and foreign matter
and thoroughly cleaned with wire or fiber brush or other means as may be ordered by
the Engineer to produce an approved clean and even surface. All loose pieces and
the scales shall be scraped off and holes stopped with mortar. In case where the
surface have been previously coloured-washed, the old colour wash must be entirely
removed before the white-wash is applied. In the case of surface which have once
been white-washed, the old loose white-wash shall be broomed down. In case, the
loose white-wash cannot be removed by brooming, the Engineer may order scraping
of the surface.
After cleaning the surface as specified above, the unwanted nails shall be removed
and all nail holes, cracks and crevices stopped with mortar similar in composition to
the surface to be stopped. The mortar should be cured.
On the surface so prepared, the white-wash shall be laid. Each coat shall be laid on
with a brush. The first stroke of the brush shall be from the top downwards, another
from bottom upwards over the first stroke, and similarly, one stroke from the right and
another from the left over the first brush before it dries. This will form one coat. Each
coat must be allowed to dry and shall be subject to inspection before the next coat is
applied. When dry, the surface shall show no signs of cracking. It shall present a
smooth and uniform finish free from brush marks and it should not come off easily
when rubbed with a finger.
No portion in the surface shall be left out initially, to be patched up later on.
For new work, the white washed surface shall present a smooth and uniform finish.
For old work, patches and repairs shall be white washed first. Thereafter, the whole
surface shall be white washed with the required number of coats.
Doors, windows, floors and other articles of furniture, etc., shall be protected from
being splashed upon. Splashing and droppings, if any, shall be removed and the
surfaces cleaned.
377
Preparing the surface for white wash including the scaffolding.
Applying the white wash in required number of coats as specified above and prior
white washing of repaired patched.
378
CIVIL SPECIFICATIONS - 10
1.0 Scope
The Contractor shall furnish all labour, material and equipment required for supply,
transportation and fixing in position, all aluminium doors including glass required.
Before starting fabrication of all metal doors, windows etc., the Contractor shall
submit detailed fabrication drawings to Engineer-in-Charge for approval. Only after
approval of drawings, the fabrication work shall be started.
5.0 Workmanship
Workmanship shall be of best quality, free from any flaws and defects. Approval of
the Engineer shall be taken for the samples of each type of work after submitting the
same, before starting the bulk manufacture.
6.0 Transporting
Packing, dispatching, loading and unloading from wagons/ trucks shall be done by
the Contractor with all care to ensure safe arrival of materials at site in undamaged
condition.
B. ROLLING SHUTTERS
1.0 The rolling steel shutters shall conform to the size indicated in drawings and shall be
of quality specified in the schedule of quantities. The rolling slats shall be in one
piece and be made of heavy gauge steel sheets minimum 18 Swg. in thickness. A
cylindrical hood shall be provided on the top to enclose the shutter when it is open.
The rolling shutters shall be provided with suitable locking arrangements and deep
channelguides.Incasegalvanizedrollingshuttersarespecifiedtherollingshutter
379
shall be made of hot dip galvanized slats, hood, deep channel guides all preferably in
one piece.
2.0 In case of hard operated pull and push type rolling shutters of sizes larger than 10
Sqm in area and in case of very large gear operated and / or as directed by the
Engineer, rolling shutters shall be provided with ball bearings for smooth and efficient
operation. In case of large rolling shutters and depending upon local wind conditions,
the rolling shutters should be provided with special locking type of wider channel
guides or it shall be provided with central moveable channel supports to take up the
design wind pressures in the area.
Rates quoted shall also include cost of lever lock and erection. Fixing lugs to be
provided to guide channel to suit actual site conditions or as directed by the Engineer
at no extra cost.
C. SANITARY APPLIANCES
1.0 Scope
The Contractor shall furnish all labour, materials and equipment required for supply
and installation of various sanitary appliances required for complete construction of the
Power Station Building and other miscellaneous buildings as per drawings and
specifications.
Wash basins shall be of white vitreous china of standard size 558.8 mm x 406.4 mm
with flat back. Wash basin shall be one piece construction including a combined
overflow and a soap holder. Wash basins shall be provided with approved quality
chromium plated pillar taps (15 mm) dia (hot and cold) along with chain and plug stop
cocks, brackets, complete. The wash basins shall in all respects conform to IS: 2556
(Part-IV), and shall be provided with a looking glass, liquid soap dispenser and towel
rail. Wash basins shall be provided with 31.75 mm dia CP bottle trap and waist, 76.2
mm CI Nahani floor trap and connecting pipes.
The urinals shall be with flat back and lipped in front. These shall be of white vitreous
china. The urinals shall be of one piece construction. Each urinal shall be provided with
not less than two fixing holes of minimum dia of 6.5 mm on each side. Each urinal shall
have an integral flushing rim and inlet or supply horn for connecting the flush pipe. The
flushing rim and inlet shall be of the self draining type. It shall have a weep hole at the
flushing inlet of the urinal. At the bottom of the urinal, an outlet for connecting to an
outlet pipe shall be provided. The exterior of the horn shall not be glazed and the
surface shall be provided with grooves at right angles to the axis of the outlet to
facilitate fixing to the outlet pipe. The inside surface of the urinal shall be smooth
throughout to ensure efficient flushing. The bottom of the pan shall have sufficient
slope from the front towards the outlet such that there is efficient draining of the urinal.
For every urinal there shall be one (1) number of automatic cast iron flushing cistern
conforming to IS: 774, stop cocks, connecting pipe, flush pipe etc. complete for proper
functioning of the urinals. A vitreous china screen shall be provided after every urinal.
380
4.1 Indian type
Indian type WC shall be of Orissa pattern of size 584.2 mm. Each pan shall have an
integral flushing rim of suitable type. It shall also have an inlet or supply horn for
connecting the flush pipe. The flushing rim and inlet shall be of the self draining type.
It shall have weep hole at the flushing inlet of the pan. The flushing inlet shall be in the
front unless otherwise specified or as ordered by the Engineer. The inside of the
bottom of the pan shall have sufficient slope from the front towards the outlet and the
surface shall be uniform and smooth to enable easy and quick disposal while flushing.
In all cases a pan shall be provided with a 110 mm „P‟ trap with approximately 50 mm
effective water seal and 50 mm diameter vent horn, where required by the Engineer.
Each pan shall be provided with a cast iron flushing cistern of (15 litres capacity)
approved manufacture and quality along with telescopic flush pipe, stop cocks, taps,
floor traps, connection pipe etc., complete for proper functioning of the pan and shall
conform to IS: 2556(Part-III).
European type water closet pan shall be of white vitreous china and shall be of wash
down type. The closet shall be of one piece construction. Each water closet shall
have four (4) holes having a minimum diameter of 6.5 mm for fixing to floor and shall
have an integral flushing rim of suitable type. Each water closet shall have an integral
„P‟ trap outlet with at least 50 mm water seal. Where required the water closet shall
have an antisiphonage 50 mm diameter vent horn on the outlet side of the trap. The
water closet when sealed at the bottom of the trap in line with the back plate shall be
capable of holding not less than 15 litres of water between the normal water level and
the highest possible water level of the water closet as installed. Each water closet
shall be provided with a standard low level cistern of approved quality and
manufacture, telescopic flush pipe, connection pipe, stop cock taps, floor traps etc.,
complete for proper function of the water closet. European type water closet shall
conform to IS: 2556 (Part-II).
381
PART H - INSTRUMENTATION SYSTEM STANDARD SPECIFICATION
A) PLC CONTROLSYSTEM
PLC Hardware.
Spare Philosophy.
PLC Panels.
PLC Communication Network
SCADA
Earthlings
Documentations
Cables
1.0 PLC
PLC shall be of the latest state of art based on 32 - bit processor. PLC and I / O
module shall be of the same family and well proven for the proposed applications.
Control system should be designed keeping in the mind having individual PLC at
different locations. The number of PLC shall be depending upon me / O distribution
and to minimize the cabling and control philosophy.
Each PLC must have RS: 485 with MODBUS protocol built in to communicate with
various instruments transmitters, power monitors etc.
1.2 CPU
Central Processing Unit (CPU) must be multi tasking unit based on 32 - bit processor
capable of real time process application.
382
CPU shall have built in Ethernet port 10 / 100 MB for communication between the
CPU and SCADA system.
CPU shall have extensive diagnostic facility and watch dog timer to identify even up
to I / O channel level faults.
CPU shall have real time clock capable to accept time synchronization pulse and
adjust its internal clock with the pulse.
1.3 Memory
Memory unit shall comprise of highly reliable as per industry standards, and shall be
expandable if required to take care future expansion. Minimum 50% of spare
memory shall be made available as spare.
1.4 I / O Modules
Standard rack mounted plug in I / O modules shall be provided. Field wiring shall be
terminated in screwed terminal blocks.
20% extra modules of installed capacity for each type of module shall be provided as
pre wired installed spare.
Digital I / O
Inter posing relays wherever necessary, shall be of reputed make. Relay should be
of 2 C / O with minimum contact ratings 5amp.
383
Analog I / O Modules
I / O module shall consist of an isolation unit, signal conditioning unit and an analogue to
digital converter, in addition, the following features shall be provided;
Note:
Power supply to all PLC, instruments, and computers shall be provided by UPS with one
hour battery backup time.
All power supply should be redundant. Field interrogation power supply shall be preferably
24V DC.
A common engineering station has to be provided for SCADA and PLC programming.
1 number Laptop has to be provided with loaded PLC programming software package.
PLC programming package must support all the 5 language as per IEC standard, i.e.
Ladder, Instruction List, Structured Text, Graced, Function and instruction.
It shall be possible to introduce the comments in the programmed, and on line programmed
monitoring should differentiate the on / off status of the I / O.
Sufficient diagnostic shall be provided for system diagnostic, diagnostic function blocks, and
display system of fault messages.
It shall be possible to monitor / programmed from remote location on Ethernet bus or through
modem.
384
All diagnostic messages shall have time and date stamped.
It shall be possible to create user configurable diagnostic blocks to meet the specific
requirements of their application.
All PLC panel shall be provided with local colour graphic screen HMI having the following as
a minimum;
10.4” TFT, 256 colours, with minimum 640 x 480 pixels screen
Communication monitoring LED
1 keypad with tactile feedback, LEDs associated with services and alphanumeric
keys
Minimum of 32 MB dynamic RAM memory
At least 16 real time curves
Capable of maximum 300 application pages, for application, alarm, help,etc.
Communication on RS: 485 MODBUS or Ethernet
Built in real time clock
Facility to connect printer
20% of used modules of each type shall be available with fully wired and usable condition.
PLC system shall be capable of expanding at least 20% of used modules of each type in
future.
5 years of recommended spares with a minimum of one module of each type, and
commissioning spares shall be provided.
PLC panel must be of standard make of standard design of at least IP: 44 protections with
proper cooling fan.
Each panel shall have its own isolation transformer and shall generate all necessary
voltages required for PLC.
All wires used for internal wiring shall be of copper with minimum of 1 sq.mm for analogue
and 1.5 sq.mm for digital I / O with proper colour code. All wires used must have at least
660 / 1100V PVC insulated standard tinned copper conductor and twisted pair with at least
one twist per 30 mm approximately.
No component shall be mounted at the side of the panel. Field cable entry shall be from
bottom.
385
There shall be separate earth for electrical and electronics as per safety standards.
Panel shall have internal light with door switch and at least two switches and sockets for
connecting instruments and computers etc.
No double decker terminals shall be used. All out put terminals must be fused terminals and
input terminals as normal type of reputed make.
2. Wherever communication cable goes from one building to another building, fiber
optic communication media shall be used.
Transmitters with 4 - 20 m Amp signals will be used for connecting to indicating instrument
mounted on the dynamic MIMIC Panel at control room, while MODBUS will be used for
interfacing with PLC.
5.0 SCADA
Offered system shall have 2 Nos. SCADA station at each location having latest PC with at
least 17” Monitor. One number alarm laser jet printer and one number laser jet printer for
report generation etc.
One number of development plus run time and one number of run time SCADA software
package capable of handling at least 2000/- tags should be provided.
SCADA package shall have all latest features for graphic pages, alarm, bar graph, trend
curves, data logging, and historical data facility shall be provided.
SCADA packages shall be user friendly, shall control the plant, screen update shall be less
than 2 - 3 seconds.
6.0 Earthings
A solid earth for electrical system and a separate earth for electronic / instrument earth shall
be provided.
386
Electrical earth shall have the resistance of 10 ohms, while electronic earth resistance shall
be less than 5 ohms.
B) PROCESSINSTRUMENTATION
1.0 General
Instrumentation system shall be designed, manufactured, installed and tested to ensure the
high standards of operational reliability. All electronic components shall be adequately rated
and circuits shall be designed so that change of component characteristics shall not affect
plant operation. All instrumentation equipment shall be new, of proven design, reputed
make, and shall be suitable for continuous operation. Unless otherwise specified, all
instruments shall be tropicalised. The outdoor equipments shall be designed to withstand
tropical rain. Wherever necessary space heaters, dust and water proof cabinets shall be
provided. Instruments offered shall be complete with all the necessary mounting
accessories.
Electronic instruments shall utilize solid state electronic components, integrated circuits,
microprocessors, etc., and shall be of proven design.
Unless otherwise specified, the normal working range of all indicating instruments shall be
between 30% and 80% of the full scale range.
On resumption of the supply following a power failure the instruments and associated
equipment shall start working automatically.
The instruments shall be designed to permit maximum interchangeability of parts and ease
of access during inspection and maintenance.
The field instruments i.e., the instruments mounted outside the control panel shall be
mounted at a convenient height of approximately 1.2 meters above grade platform.
Unless otherwise stated, field mounted electrical and electronic instruments shall be
weatherproof to IP: 65.
Lockable enclosures shall be provided for all the field mounted instruments.
All field instruments, and cabinets / panel mounted instruments shall have tag plates / name
plates permanently attached to them. Details of proposed inscriptions shall be submitted to
the Client / Consultant for approval before any labels are manufactured.
All coated parts of sensors shall be made out of non corrosive material capable of working
with chlorine content of 5.0 mg/l.
387
For all instruments installed in the field, surge protection devices (SPDs) shall be provided at
both ends of the connecting cable for protection against static discharges / lightning and
electromagnetic interference.
Individual pair screened overall screened, armoured cables shall be used for analogue
signals and armoured overall screened cables shall be used for digital signal cables.
Flow measuring systems shall consist of flow sensors / transducers, flow computer and flow
transmitter.
Flow transducers shall be rugged in construction and shall be suitable for continuous
operation. Flow transducers shall have waterproof construction and shall be suitable for
installation in underground / above ground pipelines.
To avoid the effects of disturbances in the velocity profile, a straight and uninterrupted run,
upstream as well as downstream from the location of the flow sensor shall be provided in
accordance with the requirements of the flow meter manufacturer.
The flow transmitter shall be suitable for field or panel mounting and shall accept an input
from the flow sensor. It shall process the input signal and provide 4 - 20 mA DC output
proportional to flow rate. The flow range shall be adjustable.
A zero span adjustment facility shall be provided for flow transmitter and indicator. Flow
measurement shall not be affected by physical properties of sewage viz., pH, temperature,
pressure, viscosity, density, etc., within given limits. Contractor shall provide compensating
electronic circuits if required. The overall accuracy of flow measuring systems shall be at
least ± 1.0% of the measured value unless otherwise stated.
2.1 Electromagnetic Flow meter
Full bore electromagnetic flow meter shall consist of flow sensors (i.e. flow tube), transmitter
and remote flow indicator cum integrator.
The flow meter shall have flanged connections and shall be installed at locations as
specified elsewhere in the document.
The flow computer / transmitter shall be microprocessor based and shall have diagnosis
facility.
Remote flow indicator cum integrator shall be provided on the control panel.
To ensure full electromagnetic compatibility the flow tube flanges and transmitter housing
shall be connected to instrumentation earth.
Ultrasonic level measuring devices applied for liquid level measurement shall comprise a
transducer, control unit and remote indicator.
The transducer shall be suitable for flange or bracket mounting as required and shall be
environmentally protected to IP: 65. It shall have ambient temperature compensation,
388
Adjustable datum setting facility and be BASEEFA / CENEFLEC approved for intrinsically
safe operation when required by the installation.
The design and application of ultrasonic level meters shall take into account the vessel or
channel construction, the material, size, shape, environment, process fluid or material, the
presence of foam, granules, size etc.
The installation shall avoid any degradation of performance from spurious reflections,
absorption, sound velocity variations, sensor detection area, temperature fluctuations,
specific gravity changes and condensation. For applications where spurious reflections are
unavoidable the control unit shall be provided with facilities for spurious reflection rejection.
If turbulence exists, shielding, stilling tubes or other measures shall be provided to avoid
effects of measurement.
The electrodes used for conductivity level switches shall be stainless steel. Single electrode
systems (one electrode per holder) shall be used (except where their use is impractical) with
insulted electrodes such that only the tip of each electrode is exposed to the liquid at the
operating level.
Relay or control units operating with level electrodes shall have adjustable sensitivity.
Electrodes for use in fluids of low or variable conductivity shall be fitted with conductivity
discs.
Where relay or control units are not mounted in control panels, they shall be provided with
surface mounting enclosures with a degree of protection to IP: 52 for indoor locations or IP:
65 for outdoor locations.
The ultrasonic type differential level measuring system shall consist of ultrasonic type level
sensors on upstream and downstream of screens differential level computer / transmitter
and indicator.
The flow computer transducer shall be suitable for flange or bracket mounting as required
and shall have facility for programming (i.e. adjustment of set points).
The ultrasonic transducer shall be suitable for flange or bracket mounting as required and
shall be environmentally protected as per IP: 65. It shall have ambient temperature
compensation and adjustable datum setting facilities.
389
Pressure measuring systems shall be rugged in construction. They shall be designed for
operation over 130% of full range, and be capable of withstanding surge pressures likely to
occur in the monitored system.
Pressure transmitters shall be suitable for field mounting. They shall provide a 420 mA
output proportional to pressure.
Pressure gauges shall comply with relevant IS standards. Snubber shall be provided where
the gauge is subjected to pressure pulsations and / or vibrations. The parts of pressure
gauge shall be of stainless steel material. In chlorine applications the diaphragm shall be
silver or tantalum, for other fluids an appropriate diaphragm material shall be used. The
pressure gauge shall be provided with diaphragm seal arrangement.
The minimum diameter for round pressure gauges shall be 150 mm unless specified
otherwise or where the gauge forms part of a standard item of equipment.
The accuracy of pressure gauges shall be ±1% over the operating range. Where
compensation of more than 2% of instrument span is needed for the difference in level
between the instrument and tapping point, the reading shall be suitably adjusted and the
amount of compensation shall be marked on the dial.
The zero and span of pressure gauges shall not change by more than ±0.1% of the span per
o
C changes in ambient temperature.
Surge protection devices (SPD's) shall be suitable for withstanding the surge arising of high
energy static discharge / lightning strikes and protect the instrument to which it is connected
against damage. SPD's shall provide protection through the use of quick acting
semiconductors like Tranzorb, Zener diodes, varistors and an automatic disconnect and
reset circuit. ASPD's shall be passive and shall require negligible power for operation.
During the occurrence of a surge it shall clamp on the allowable voltage and pass the excess
voltage to the ground. The SPD shall be self resetting to minimize the down time of
measurement loop.
SPD's shall be provided to protect devices transmitting and receiving analogue and digital
signals derived from field devices located outdoors.
The surge protection device shall be rated for surge rating of 10 KA.
Wall mounted cabinets shall be provided for enclosing transducer units and associated
accessories which are mounted outside the main control panel. The cabinet shall be of die-
cast aluminium, rated to provide not less than IP: 55 protection and shall be lockable. The
cabinet shall have facilities for earthing. A steel plate shall be provided inside the cabinet for
mounting instrument and accessories.
Alarms shall be initiated by the opening or closing of volt-free contacts which shall remain
unchanged throughout the periods in which the alarm conditions exist. Alarm circuits shall
be capable of conversion from open-healthy to open-alarm conditions exist. Alarm circuits
390
shall be capable of conversion from open-healthy to open-alarm or vice versa by a simple
modification after installation requiring no additional parts of special equipment.
Each alarm shall initiate the operation of both visual and audible devices.
The sound intensity of each audible device shall be suitable for the maximum sound level of
its environment.
Audible devices in the same room or area shall have distinguishable sounds and adjustable
sound levels.
The alarm annunciator shall be microprocessor based, modular, split type unit with alarm
windows mounted on the front door and electronic modules inside the panel. The weather
protection class for alarm annunciator shall be IP: 54 of lS: 13947, Part-I.
Each alarm shall initiate a visible and audible indication of the specified condition. Unless
otherwise specified, alarm indicators shall be grouped together in annunciator units each
having at least 200% spare ways. Alarm indicators shalI be of similar design to indicator
lamps (Cluster LED type) and shall have transparent screens engraved with legends
approved by Client / Consultant. The legend area of each indication shall not exceed 40 mm
high and 75 mm wide.
When any alarm condition occurs, an audible device common to an alarm annunciator
system shall sound and the appropriate indicator shall flash on and off. The flashing rate
shall not be less than 2 Hz and shall not exceed 5 Hz. On pressing an accept pushbutton
the audible device shall be silenced and the flashing light shall become steady. The alarm
indicator shall remain illuminated until the alarm condition ceases and a rest pushbutton has
been operated.
The operation or acceptance of one alarm shall not inhibit the operation of the audible device
or the flashing of the appropriate alarm indicator if a further alarm condition occurs. At
unmanned locations alarms operated on two or more annunciators require acceptance at
each annunciator.
Alarms shall be accepted automatically and the appropriate audible device silenced after an
adjustable period of 1 to 5 minutes.
An integral “test” pushbutton shall be provided to illuminate each lamp in the appropriate
group and to operate the audible device but shall not cause a spurious alarm condition on
any other annunciator.
Alarm circuitry shall be arranged so that spurious or transient alarm states persisting for less
than 0.5 seconds do not initiate any action.
Alarm annunciator / indicator legends or labels shall be arranged with three lines of texts as
follows;
391
- Sumps
- Level
- High
The UPS shall be floor mounted, self contained and metal clad and shall be suitable for
supplying a non linear load.
It shall be possible to open the enclosure front door when the unit is in use without exposing
any live contacts to touch.
The UPS shall be an online type incorporating a six pulse rectifier and pulse width
modulation inverter technology with microprocessor control. It shall incorporate a static
bypass switch which shall operate in the event of UPS failure, overload or manual initiation
in order to transfer the output supply to mains without disturbance to the output supply.
The UPS shall incorporate a DC under-voltage trip circuit to electronically trip the UPSoutput
in order to protect the batteries.
The noise level of the unit shall not exceed 60 dB (A) at 1 m from the UPS cabinet.
The output of the inverter shall be a sine wave having less than 2% THD for linear loads and
less than 4% for 50% non linear load. It shall be suitable load power factor 0.7 lag and 0.9
lead.
The unit shall have a dynamic response such that a 100% step load causes an output
voltage transient of less than ± 1% with recovery time of less than 4 ms.
For three phase output units the output voltage shall not vary by more than ± 1% for an
unbalance of 10%.
The load crest factor shall not be less than 3:1. The efficiency at full load and 0.8 power
factor shall be greater than 88%.
Indicators to indicate;
UPS Status
UPS Alarm Conditions
The UPS shall have an overload capacity of 150% for 30 seconds and shall be protected in
the event of a short circuit of the output.
The batteries shall be housed either within the UPS enclosure or within a separate matching
battery cubicle suitable for location adjacent to UPS.
The batteries shall be maintenance free lead acid type sealed for life.
392
Batteries shall be contained within translucent impact resistant flame retardant
polypropylene cases. They shall have life in service of at least 10years.
Terminals shall be shrouded to prevent accidental contact. The battery enclosure shall be
corrosion resistant and ventilated to prevent the buildup of gases.
Warning notices shall be provided for wall mounting to warn of the presence of change
gases.
The batter supply to the UPS shall be via a fused load break switch disconnector circuit
breaker.
The battery recharge time to 90% of full charge shall be approximately ten times the
discharge time at full load.
393
LIST OF MANUFACTURERS FOR DIFFERENT MATERIALS FOR
REFERENCE.
( It is the responsibility of the contractor to select a proven vendor for trouble free
operation of the scheme)
1. M.S. PIPES
6. M/s. Steel Authority of India Ltd., No.8, VISL Building, J.C. Road, Bangalore – 560002.
7. M/s. Welspun, Trade World, `B' Wing, 9th Floor, Kamala Mills Compound, Senapati Bapat
Marg, Lower Parel, Mumbai- 400013
8. M/s. PSL Holdings, 22, Vaijavoor Village, Malai Vaiyavoor P.O., Mahuranthakam Taluk,
Kancheepuram Dist- 603308.
9. M/s Tata Steel Limited, Tata Steel tubes Division, PO Burmamines, Jamshedpur-831 007,
Jharkhand.
2. D.I. Pipes
6. M/s. Electrosteel Casting Ltd., 30, B.T. Road, Kharda, P.O. Sukhchar, Dist. 24,
Paraganas(N)- 700 115 – WestBengal
7. M/s.Jindal Saw Ltd., Samaghogha Village, Mundra Taluk, Dist. Kutch, Gujarat-392415
8. M/s.Lanco Industries Ltd., Rachagunneri-517 641 Sri Kalahasti, Chittor,A.P.
9. Tata Metallics DI PipesLtd.
10. M/s Electrotherm India ltd-Plot no 206-207,Shop no-1, Kunal-II, sector-21 Nerul ( E) Navi
Mumbai-400706 (Maharashtra)
3. H.D.P.E. PIPES
9. M/s. Jain Irrigation Systems Ltd., Jain Plastic Park, P.O. Box: 72, N.H. No. 6, Bambhori,
Jalagaon- 425 001
10. M/s. Duraline India Pvt. Ltd., Plot No. L-24, 25, Phase II A, Verna Electronic City, Verna,
Salcete, Goa- 403722
11. M/s. Pioneer Polyfab, Plot No. 12, Site IV, Industrial Area, Sahibabad Dist.,Ghaziabad.
12. M/s. Pennwalt Agro Plastics Ltd., Plot No. 272/A, Savli GIDC Village, Manjusar- 391 775.
Gujarat.
13. M/s. Reliance Industries, Surath, Hazira Manufacturing Fa Village, Botha Taluq, Surath,
Gujarat.
14. M/s Rishi Polymach Pvt. Ltd., 16-A belagola indutrial area metagalli,K.R. Road, Mysore– 570
017
15. M/s.Supreme Industries Ltd., 612, Raheja Chambers, Nariman Point, Mumbai- 400021.
16. M/s Time technoplast Ltd -C-Wing, 2nd Floor, Opp - HDFC Bank, Off. Saki Naka, Chandivali
Road, Andheri - (E)- Mumbai –400072
1. M/s.The Mysore Stoneware pipe & Potteries Ltd., Soladevanahalli Chickbanavar P.O.,
Bangalore-90
3. M/s Indian Hume pipe Co. Ltd., Venkatala Village, Yelahanka Pos,Bangalore – 560064
4. M/s Aradhya Concrete Products, No. 301, Hebbal Industrial Area, Mysore-570016
395
6. G.I. PIPES FOR PLUMBING WORKS
5. M/s. Tata Iron & Steel Co. Ltd., No.45, Jubilee Building, II Floor `A' Wing, Museum Road,
Bangalore- 560001
6. M/s Surya Roshni Limited, Prakash Nagar, Delhi-Rohtak Road, Bahadurgarh-124
507, Haryana
7. M/s Jindal Pipes Ltd- Plot no 30, Institutional sector-44 Gurgoan-122002-Haryana
8. M/s Jindal Industries ltd -Delhi Road, Model Town,Hisar
7. CI D/F PIPES
4. M/s. NECO Castings Ltd., 65/2, Nildoh/Digdoh, MIDC Industrial area, Nagpur- 440016
5. M/s. Upadhaya Valves Mfg, Pvt Ltd., NH-6, VIII, Jangalpur, Andul Mogri Road,Howrah
6. M/s Electrosteel Casting Ltd., 30, B.T. Road, Kharda, P.O. Sukhchar, Dist. 24,
Paraganas(N)- 700 115 – WestBengal
8. DI SPECIALS
5. M/s. Kiswok Industries Pvt. Ltd, Bipranna Para, Via-Begri, Domjur, Howrah-711411
6. M/s. Electrosteel Casting Ltd., 30, B.T. Road, Kharda, P.O. Sukhchar, Dist. 24,
Paraganas(N)- 700 115 – WestBengal
7. M/s. Kejriwal Castings, P-200, Benaras Road, Netajigarh, Howrah – 711108
8. M/s Jindal Saw Ltd-Jindal Centre, 12 Bhikaiji Cama Place-New Delhi110066
9. CI SPECIALS
10. M/s. Indo Precast Industries, C-5, IDA, Uppal, Hyderabad- 500039
11. M/s. Tanvi Cement Products, No. 128, Lakkenahalli, Bhadrapura Road, Solar Hobli, Magadi
Taluk, Bangalore RuralDist.
12. M/s Southern Concrete Industries, Plot No.22, C, KIADB Industrial Area, Doddaballapur,
Bangalore Rural District.
13. M/s S.S.V. Precast Industries, 4/8, B, IDA Nacharam, Hyderabad – 500076.
14. S.S. Polytech Concrete Products,No.32/4, Bukkasagara Village, Jigani Hobli, Anekal Taluk,
Bangalore
15. M/s Rajvaibhav Enterprises (P) Ltd., No.18, KIADB Industrial Area, Hoskote, Bangalore
Urban Dist.
16. M/s Swamy Concrete Products Pvt Ltd.,Plot No. 35, KIADB, Hirehally Industrial Area,
Hirehalli,Tumkur – 572168
17. M/s Mahesh Precast Industries, D-5-6, Industrial Estate, M.S.K. Mill Road, Gulbarga-585102
18. M/s Juneja Metal WorksVillage Variana, P.O. Nagra, Kapurthala Road,Jalandhar – 13.(DI
Manhole Cover)
396
8. M/s. Kirloskar Brothers Ltd., Gate No. 252/253, Village Kondhapuri, Shirur Dist.Pune
9. M/s. Fouress Engg. (I) Ltd., Plot No. 324, Wagale Industrial Estate, Road No. 21, Thane (W)-
400608
1. M/s. Indian Valves Pvt Ltd., H.O.- 53, Industrial Estate, Satpur, Nashik- 422 007
3. M/s Indian Valves Pvt Ltd., H.O.- 53, Industrial Estate, Satpur, Nashik- 422007
4. M/s.JashEngg.Ltd.,31,Sector`C‟,IndustrialArea,SanwerRoad,Indore-452015
397
19. FOOT VALVES
20. CEMENT
12. M/s.Vasavadatta, Cement, Prop.Kesoram Industries Ltd., Post Sedam- 585 222, Gulbarga,
Karnataka
13. M/s.Penna Cement Industries Ltd., Talaricheruvu Village, Tadpatri Mandal, Ananthapur Dist.
A.P.
14. M/s.Madras Cement, Flat No.100-100/1, M-Floor, Eden Park, No.20, Vittal Mallya Road,
Bangalore- 560001
15. Birla Cement
16. Ultratech
17. ACC
18. Zuari Cement
19. Ambuja Cement, Elegant Business Park, MIDC Cross Road „B‟ Off Andheri-Kurla Road,
Andheri (E) Mumbai400059
20. Chettinad Cement, House of chettinad “Rani Seethai Hall” 5th Floor # 603, Anna Salai,
Chennai 600006 PNo. 044 –28292727
21. Ramco Cement , The Ramco Cements Limited (Formerly Madras Cements Ltd), Auras
Corporate Centre, 98-A Dr.Radhakrishnan Salai Mylapore, Chennai - 600 004, PNo.044
- 28478666
22. Coromandal Cement, Coromandel Towers, 93, Santhome High Road,Karpagam Avenue,
R.A.Puram,Chennai600028.
1. M/s. Krohne Marshell, A34/35, MIDC Estate, H block, Pimpri, Pune- 411018
2. M/s Endress Hauser Flowtec (India) Pvt. Ltd., M-174/175 MIDC Waluj, Aurangabad–
431 436.
3. M/s. Siemens, 130, Pandurang Budhkar marg, worli, Mumbai400018
4. M/s. Krohne Marshell, A34/35, MIDC Estate, H block, Pimpri, Pune- 411018.
5. M/s Endress Hauser Flowtec (India) Pvt. Ltd., M-174/175 MIDC Waluj, Aurangabad– 431
436.
6. M/s ABB, Prestige Palladium Bayan, Greams Ln, Thousand Lights West, Thousand
Lights, Chennai, Tamil Nadu600006.
7. M/s Yokogawa, 115, Mahatama Gandhi road, 2nd floor, Kothari, buildings,
Nugambakkam, Chennai, Tamilnadu, India,600034.
6. M/s. Sree Rayalaseema Hi-Strength Hypo Ltd., (Bleaching powder) Gondiparla, Kurnool-
518 004
7. M/s. Sriram Vinyl and Chemicals Industries, (PAC powder) Kota Nagar, Kota- 324004
8. M/s. Grasim Industries Ltd., (Bleaching & PAC powder) Chemical Division, Birlagram, Nagda
(M.P)- 456331
9. M/s Gujarat Alkalies & Chemical Ltd., (PAC Powder), P.O. Petro Chemicals- 391 346,
Vadodara.
10. M/s Kanoria Chemicals & Industries Ltd., (Bleaching Powder), Renukot, Sonebhadra, Uttar
Pradesh
398
23. RUBBER RINGS & RUBBER GASKETS
6. M/s.Durable Polymer Products Pvt Ltd., Boai, 2nd Lane, P.O.Jugberia, Kolkata- 700110
7. M/s. Prabhat Elastomers Pvt. Ltd., A1/413-415, GIDC Road, No. 4, Sarigam Gujarat- 396155
8. M/s.Amalgamated Synthetic Moulders,44/14, K.B.Sarani(Mall Road),Kolkatta- 700080
9. M/s. J.D.Rubber Industries, Survey No. 580/A, Ghatkesar (M) R.R. Dist(A.P.)
10. M/s Andhra Polymers Pvt. Ltd., Plot No.2, Phase – 5, IDA, Jeedimetla, Hyderabad – 560055
4. M/s. K.G.M. Exports, Plot No. 1 & 2, Sector 59, H.S.I.D.C. Indl. Estate,Faridabad
5. M/s. TV Plastics Ltd., 488, Kamakshipalya New Extension, Bangalore- 560079
6. M/s. Rajvaibhav Enterprises Pvt Ltd., No. 18, KIADB, Industrial Area, Chintamani Road,
Hosakote- 14,Bangalore
6. M/s. STP Ltd., Mirgadih, Dimna Road, P.O. MGM Medical College, Jamshedpur- 831 018,
Jharkhand
7. M/s Shalimar Tar products- 404,Lloyds Chamber,Block no-2, Mangalwar Peth-Pune-411011
8. M/s MP Tar Products- Plot No 69 and 70 Light Industrial area Bhilai dist- Durg(C.G)
9. M/s A.R. Laminators -497/2, G.I.D.C-Makarpura, Vadodara-390 010-Gujarat,India
10. M/s IWL India ltd-W360, North Main Road-Anna Nagar West-Chennai -600 101-Tamilnadu
3. M/s.JashEngineeringLtd.,31,Sector`C‟,IndustrialArea,SanwerRoad,Indore-452015
4. M/s. Indian Valves Pvt Ltd., H.O.- 53, Industrial Estate, Satpur, Nashik- 422007
10. M/s. Fair Banks Morse, 28 A, Site IV, Industrial Area, Sahibabad, Ghaziabad(U.P)
11. M/s. Kirloskar Brothers, Stategic Business Unit-1, Kirloskar Brothers, Kirloskar Wadi, Pune –
416 308
12. M/s. Jyothi Ltd., Nanubai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
13. M/s. Worthington Pvt. India Ltd., (WPIL), 22, Ferry Fund Road, Panihati-743 176, 24,
Parganas(N), WestBengal.
14. M/s. Worthington Pvt. India Ltd., (WPIL), Macneill & Major Industrial Estate, A-5, Section
XXII, Meerut Road, Ghaziabad- 201 002, UttaraPradesh.
15. M/s. Mather & Platt Pumps Ltd., P.O. Box No.7, Pune-Mumbai Road, Chinchwad, Pune- 411
019.
16. M/s. Voltas Ltd., Pumps & Projects, Business Dvn. 2nd Pokran Road, Thane-400601.
17. M/s.Flowmore Pvt. Ltd., 9th Mile Stone, G.T.Road, P.O. Mohan Nagar, Ghaziabad,U.P.
399
18. M/s Grundfoss Pumps India Pvt Ltd., 118, Old Mahabalipuram Road, Thorappakkam,
Chennai-600097
9. M/s.Kirloskar Brothers Ltd., Ujjain Road, Opp. Railway Station, Dewas(MP)- 455001
10. M/s.Beacon Weir Ltd., 28, Industrial Estate (North), Ambattur, Chennai- 600098.
11. M/s. Kirloskar Brothers, Stategic Business Unit-1, Kirloskar Brothers, Kirloskar Wadi, Pune
416308
12. M/s. Flowmore Pvt.Limited, A-292, Mahipalpur Extn., N.H- 8, New Delhi-110037
13. M/s. Jyothi Ltd., Nanubai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
14. M/s. Worthington Pvt. India Ltd., (WPIL), Macneill & Major Industrial Estate, A-5, Section
XXII, Meerat Road, Ghaziabad- 201 002(U.P.)
15. M/s. Mather & Platt Pumps Ltd., P.B. No.7, Mumbai–Pune Road, Chinchwad, Pune– 411019
16. M/s Grundfoss Pumps India Pvt Ltd., 118, Old Mahabalipuram Road, Thorappakkam,
Chennai-600 097(including boosterpump)
8. M/s. Kirloskar Brothers Ltd., Ujjain Road, Opp. Railway Station, Dewas (MP)- 455001
9. M/s. KSB Pumps Ltd., Mumbai – Pune Road, Pimpri, Pune – 411018.
10. M/s. Grundfoss Pumps India Pvt Ltd., 118, Old Mahabalipuram Road, Thorappakkam,
Chennai-600097
11. M/s Aqua pumps and Machinersi pvtltd
12. M/s. Kishore Pumps Pvt. ltd., Enviro Pumps Dvn., 675/2, Pune-Nasik Highway, Kuruli
(Chakan), Pune- 410501.
13. M/s. M.B.H. Pumps Pvt. Ltd., Plot No. 14, GIDC Naroda Industrial Estate,Ahmedabad-
14. M/s Xylem Water Solutions India Pvt ltd--Ground & First Floor,- Vishnu Shivam Mall-Thakur
Village, Kandivali (E)- Mumbai – 400101
8. M/s. M.B.H. Pumps Pvt. Ltd., Plot No. 14, GIDC Naroda Industrial Estate, Ahmedabad- 382
330
9. M/s. Arihant Pumps Pvt. ltd., Nr. Ladbhi Nala, Deesa Highway, Palanpur, Banaskantha- 385
001
10. M/s. Jyothi Ltd., Nambai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
11. M/s. Unnati Industrial Corporation, Near Uttar Gujrat Industrial Estate, Opp. Forge & Blower,
Naroda Road, Ahmedabad- 380025
12. M/s Cheran Industries,Coimbatore
13. M/s Waterman Industries Pvt Ltd., 407, Opp New Intas Pharma, Sarkhej Baavla Highweay,
Moraiya, Changodar, Ahmedabad-382213
14. M/s. Mather & Platt Pumps Ltd., P.B. No.7, Mumbai–Pune Road, Chinchwad, Pune– 411019
400
33. MOTOR
4. M/s. Jyothi Ltd., Nanubai, Amin Marg, P.O. Chemical Industries, Vadodara- 390002
5. M/s.Crompton Greaves Ltd., Pumps Division, Plot No.A/28, MIDC, Ahmednagar-414111.
6. M/s. SIEMENS Ltd., Thane Belapur Road, Kalwa, Thane- 400601.
DESCRIPTION MAKES
HT SIDE:
COMPACT SUB-STATON ABB / SCHIENDER
RING MAIN UNITS ABB / SCHIENDER / SIEMENS
PLCs ABB / SIEMENS / ALLEN BRADLEY / HONEYWELL
VCB ABB / SCHIENDER / SIEMENS
HT PANELS ABB / SIEMENS / LOTUS POWER GEAR
11kV HT XLPE CABLES UNISTAR / POLYCAB / CCI / KEI
HT CABLE TERMINATION KIT RAYCHEM / BIRLA-3M
OIL FILLED TRANSFORMER UNIVERSAL/ KIRLOSKAR/ VOLT AMP
DRY TYPE TRANSFORMER ABB / VOLT AMP
CHANGE OVER SWITCH ABB / HPL / C&S /INDOASIAN
CURRENT TRANSFORMER KAPPA / AE / PRAGATHI
VOLTAGE TRANSFORMER KAPPA / AE / PRAGATHI
LT SIDE:
BUS DUCT ( AIR INSULATED TYPE) ZETA / ANITA ELECTRICALS / TRICOLITE
BUS DUCT ( SANDWITCHED
CONSTRUCTION) SCHNEIDER ELECTRIC / GODREJ / EMFORM
ACB / MCCB ABB / SCHNEIDER / SIEMENS / L&T
PRAGATHI CONTROLS / LOTUS POWER GEAR /
LT PANELS / AMF POWER CONTROL EQUIPMENTS/ LOAD
CONTROLS
DG SETS CUMMINS / CATERPILLAR
BATTERIES EXIDE / AMCO / AMARON
UPS DELTA / LIEBERT / EMERSON
1.1kV LT CABLES POLYCAB / CCI / SBEE
CABLE GLANDS USHA / CROMPTON / COMET
CABLE LUGS DOWELL/3D
LT CABLE TERMINATION KIT RAYCHEM / SAFE KIT
MCB / MCCB - DBs FOR LIGHTING /
ABB / MDS LEXIC / SCHNEIDER
POWER / EMERGENCY / UPS
BELUK (GERMANY) / ENERCON SYS. PVT.LTD /
APFCR (NUMERIC TYPE)
ALSTOM
CABLE TRAYS PROFAB / INDIANA / OBO BUTTERMAN
RACE WAYS / CABLE MANAGEMENT
SCHNEIDER / LEGRAND / OBO BUTTERMAN
SYSTEM
TELEPHONE CABLE ( INDOOR) DOORAVANI / DELTON / FINOLEX
TELEPHONE CABLE OUTDOOR (JELLY
FINOLEX / KARNATAKA TELECABLES / VINDHYA
FILLED)
TELEVISION CABLE RR KABELS/FINOLEX
INDUSTRIAL TYPE PLUG & TOP
SOCKETS & WEATHER PROOF HENSEL/ LEGRAND
ENCLOSURES
401
DESCRIPTION MAKES
ADVANCED LIGHTNING PROTECTION
ERICO / INDELEC / OBO BUTTERMAN
SYSTEM
METERS / SWITCHES / RELAYS:
STARTERS ABB / SIEMENS / TELEMECHANIC/L&T
TIMERS ABB / LEGRAND / TELEMECHANIC
CAPACITORS UNIVERSAL / MEHER / EPCOS
SELECTOR SWITCHES SIEMENS / L&T / KAYCEE
INDICATING METERS CONZERV
ENERGY METER CONZERV / AE / SECURE
PUSH BUTTONS SIEMENS / L&T / TEKNIC
INDICATING LAMPS SIEMENS / ALSTOM / VAISHNO / BINAY
PROTECTIVE RELAYS ABB / SIEMENS / ALSTOM / EASUN
LIGHT FIXTURES / CONDUITS
LIGHT FIXTURES PHILIPS / HAVELS / BAJAJ
STREET LIGHT POLES SHUBHAM / PIPE CORPORATION / KESELEC
CEILING / EXHAUST FANS GE / KHAITAN / ANCHOR/CG
FRLS PVC CONDUITS VIP / PRECISION / UNIVERSAL
METAL CONDUITS TATA / BHARATH / GB
FRLS WIRES-1100V GRADE RR KABELS / ANCHOR / FINOLEX
LIGHT SWITCHES ANCHOR ROMA / ABB / LEGRAND
6. M/s. Hitech Systems and Services, White House, 119, Park Street, Kolkata- 700016
7. M/s. Nivo Controls Pvt Ltd., 104-115, Electronic Complex, Indore- 452010.
8. M/s. Gujarat Electronics and Controls, (Water level controllers & Water level guards) 7,
Adavani Market, Out side Delhi Gate, Ahamedabad- 380004.
9. M/s. Pune Techtrol, S-18, MIDC Bhosari, Pune - 411026(INDIA).
10. M/s. SBEM, 39, Electronic Co-Operative Estate, Pune Satara Road, Pune – 411009(India).
4. M/s Al Aziz Plastics Pvt Ltd., No. Plot No.5-14, Achhad Industrial Estate, Achhad,
Tal:Talasari, Dist: Thane(Maharastra)-401606
5. M/s.Glynwed Pipe Systems India Private Ltd., A-208, Kailash Complex, Park Site, Vikhroli-
Hiranandani Link Road, Vikhroli (W), Mumbai -400079.
6. M/s.George Fischer Piping System, Plot No.9-B, 1st Floor, Kopri Village, Above China
Valley, Powai, Mumbai- 400076.
7. M/s.Sujana Metal Products Ltd., Survey No.296/7/9, IDA Bollaram, Jinnaram Mandal, Medak
Dist., A.P. India (TMTBars)
8. M/s.SRMB Srijan Ltd., SRMB House, 7 Khetra Das Lane, Kolkata- 700 002. India (TMTBars)
9. M/s.Shyam Steel Industries, Shyam Towers, EN-32, Sector V, Salt Lake, Kolkata- 700 091
(TMT re-bars, CRS TMRre-bars)
10. SAIL, Steel Authority of India limited, Ispat Bhawan, Lodi Road, New Delhi – 110003 PNo.
011 -24300100
11. TATA, Tata Steel Limited Registered Office Bombay House, 24, Homi Mody Street, Mumbai
- 400 001Ph: 91 02266658282
12. Rashtriya Ispat Nigam Limited, Visakhapatnam Steel Plant, Visakhapatnam,AP.
402
38. Ultrasonic Level transmitter & Pressure Transmitter
6. M/s ABB, Prestige Palladium Bayan, Greams Ln, Thousand Lights West, Thousand Lights,
Chennai, Tamil Nadu600006.
7. M/s Siemens, 130, Pandurang Budhkar marg, worli, Mumbai400018.
8. M/s E&H, M-174/175 MIDC Waluj, Aurangabad– 431436.
9. M/s Yokogawa, 115, Mahatama Gandhi road, 2nd floor, Kothari, buildings, Nugambakkam,
Chennai, Tamilnadu, India,600034.
10. M/s Honey well, Mohamadpur Pace City-2, Sector-36, Gurgaon Ho, Gurgaon –122001.
5. M/s Siemens Siemens Limited, Registered & Corporate Office, 130, Pandurang
Budhkar Marg,Worli,Mumbai 400018.
6. M/s Schneider - Schneider Electric India Pvt. Ltd., 9th Floor, DLF Building
No. 10, Tower C,DLF Cyber City,Phase II,Gurgaon-122002.Haryana,India
403