Beruflich Dokumente
Kultur Dokumente
###
#REF!
### ###
### ###
### ###
### : Mechanical & Electrical
Page 1 of 90
#REF!
0
Name of Project #REF!
Location #REF!
Fiscal Year #REF!
#REF! : Mechanical & Electrical
A. CONSTRUCTION COST
The works include supplying and installing main equipment on-site, comply with Technical Specification, Design
Drawings and operate normally good
Note on price:
- Main equipment includes its accessories,
- All instalation incuding accessories and supporting materials.
-
Price including labor, all risk insurance for equipment, wages and the works.
-
Offer price including risks on the project work Offer price including risks on the project work
- Site Documentation, Shop Drawings and As Built Drawings.
- Testing And Commissioning for all system,etc
comply with Technical Specifications, Design Drawings and Standard Operation Procedure
a. Booster Pump
Type : Booster Pump Packaged / Paralel Alternate Packaged 1 5,000,000
Capacity : 2 x 250 L/mnt
Total Head : 30 Meter
Total Power : 3,7 kW
Rotation : 2900 rpm
Caracteristic : 380/415 V , 3 Ph , 50 Hz
Comply with pump control equipment, electrical cable NYY 4 x 4 mm²,
installing, meterials accessories, valve-valve, elbow, tee-way, reducer,
seal, vondation pump K-225, etc
b. Top Recervoir
Capacity : 20 M³ Unit 2 -
Comply with header, pipe installation, accessories,
vondation Top Reservoir K-225, etc
Page 2 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 3 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 4 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
II.3.5 5 Floor
th
Page 5 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
II.3.8 8 Floor
th
Page 6 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 7 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
e. Sprinkler pipings :
Pipe use Black Steel Pipe (BSP), Sch. 40, with zinkchromate and painting :
- Diameter 150 mm M' 4 483,058
- Diameter 100 mm M' 20 276,250
- Diameter 80 mm M' 32 194,242
- Diameter 65 mm M' 42 149,392
- Diameter 50 mm M' 56 93,470
- Diameter 40 mm M' 34 69,918
- Diameter 32 mm M' 24 58,890
- Diameter 25 mm M' 300 43,290
- Diameter 25 mm (drain test pipings to drain riser) M' 62 43,290
f. Sprinkler Piping Supporting Material :
- Gate Valve 16 K, diameter 150 mm Nos 1 55,611,270
- Gate Valve 150 Psi diameter 25 mm (Inspektor Test Valve Sprinkler) Nos 1 10,530,960
- Branch Control Valve, dia. 25 mm (c/w accessoriess, etc) Set 1 5,325,000
- Preassure Gauge scala 10 Kg/cm², c/w Gate Valve 15 mm Nos 1 331,155
- Flow Switch Nos 1 2,687,175
- Dropper pipe, dia. 25 mm c/w fitting, elbow, tee, reducer, etc Nos 120 259,740
- Accessories pipings (fitting, elbow, tee, reducer, etc) Ls 1 13,392,990
- Hanger, clem, bracket/support, etc Ls 1 6,696,495
g. Fire Extinguisher :
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) Nos 2 1,150,000
- Box Fire Extinguisher Nos 2 750,000
Page 8 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
e. Sprinkler pipings :
Pipe use Black Steel Pipe (BSP), Sch. 40, with zinkchromate and painting :
- Diameter 150 mm M' 4 483,058
- Diameter 100 mm M' 11 276,250
- Diameter 80 mm M' 32 194,242
- Diameter 65 mm M' 50 149,392
- Diameter 50 mm M' 34 93,470
- Diameter 40 mm M' 16 69,918
- Diameter 32 mm M' 30 58,890
- Diameter 25 mm M' 310 43,290
- Diameter 25 mm (drain test pipings to drain riser) M' 56 43,290
f. Sprinkler Piping Supporting Material :
- Gate Valve 16 K, diameter 150 mm Nos 1 55,611,270
- Gate Valve 150 Psi diameter 25 mm (Inspektor Test Valve Sprinkler) Nos 1 10,530,960
- Branch Control Valve, dia. 25 mm (c/w accessoriess, etc) Set 1 5,325,000
- Preassure Gauge scala 10 Kg/cm², c/w Gate Valve 15 mm Nos 1 331,155
- Flow Switch Nos 1 2,687,175
- Dropper pipe, dia. 25 mm c/w fitting, elbow, tee, reducer, etc Nos 114 259,740
- Accessories pipings (fitting, elbow, tee, reducer, etc) Ls 1 12,169,144
- Hanger, clem, bracket/support, etc Ls 1 6,084,572
g. Fire Extinguisher :
- Multi Purpose Dry Chemical Fire Extinguisher 3,5 kg (ABC) Nos 2 1,150,000
- Box Fire Extinguisher Nos 2 750,000
Page 9 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 10 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
III.4.9 9 Floor
th
Page 11 of 90
AMOUNT
(Rp)
5,000,000.00
Page 12 of 90
AMOUNT
(Rp)
5,000,000.00
2,500,000.00
2,500,000.00
15,000,000.00
5,387,800.00
28,000,000.00
2,424,510.00
1,077,560.00
28,458,000.00
9,759,420.00
11,465,226.00
5,732,613.00
5,068,800.00
3,015,000.00
2,647,260.00
2,682,765.00
1,609,659.00
11,827,200.00
8,123,750.00
502,500.00
4,987,737.50
2,992,642.50
16,447,225.95
152,209,668.95
1,119,000.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,737,783.00
868,891.50
3,350,000.00
9,759,420.00
550,550.00
2,473,600.00
418,750.00
382,500.00
4,840,071.00
2,420,035.50
39,071,511.00
Page 13 of 90
AMOUNT
(Rp)
1,398,750.00
736,200.00
745,625.00
2,080,375.00
2,279,812.50
2,567,700.00
3,909,600.00
2,172,228.75
1,086,114.38
3,350,000.00
9,759,420.00
550,550.00
2,473,600.00
418,750.00
382,500.00
4,840,071.00
2,420,035.50
41,171,332.13
1,119,000.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,737,783.00
868,891.50
4,187,500.00
12,199,275.00
688,187.50
3,092,000.00
418,750.00
382,500.00
6,050,088.75
3,025,044.38
44,919,930.13
839,250.00
441,720.00
447,375.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,564,948.50
782,474.25
4,187,500.00
12,199,275.00
550,550.00
2,473,600.00
418,750.00
382,500.00
5,823,277.50
2,911,638.75
42,988,309.00
Page 14 of 90
AMOUNT
(Rp)
1,398,750.00
736,200.00
745,625.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,910,617.50
955,308.75
4,187,500.00
12,199,275.00
688,187.50
2,473,600.00
418,750.00
382,500.00
5,864,568.75
2,932,284.38
44,858,616.88
839,250.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,653,858.00
826,929.00
3,350,000.00
12,199,275.00
550,550.00
2,473,600.00
418,750.00
382,500.00
5,572,027.50
2,786,013.75
42,203,663.25
1,398,750.00
736,200.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,865,880.00
932,940.00
5,025,000.00
14,639,130.00
550,550.00
2,473,600.00
418,750.00
382,500.00
6,806,484.00
3,403,242.00
49,194,976.00
Page 15 of 90
AMOUNT
(Rp)
1,678,500.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,905,633.00
952,816.50
3,350,000.00
9,759,420.00
550,550.00
3,092,000.00
418,750.00
382,500.00
5,025,591.00
2,512,795.50
40,779,466.00
1,398,750.00
736,200.00
745,625.00
2,080,375.00
2,279,812.50
2,567,700.00
3,909,600.00
2,172,228.75
1,086,114.38
4,187,500.00
12,199,275.00
688,187.50
3,092,000.00
418,750.00
382,500.00
6,050,088.75
3,025,044.38
47,019,751.25
2,712,500.00
1,996,250.00
15,712,500.00
480,500.00
606,375.00
523,875.00
896,625.00
517,750.00
7,527,843.75
3,226,218.75
34,200,437.50
27,281,760.00
38,372,950.00
45,778,425.00
2,873,475.00
39,001,597.25
16,714,970.25
170,023,177.50
596,431,170.63
763,640,839.58
Page 16 of 90
AMOUNT
(Rp)
70,526,516.67
50,238,066.67
42,267,604.17
18,114,687.50
38,644,666.67
19,322,333.33
5,975,666.67
41,794,875.00
51,053,850.00
1,398,465.00
19,182,800.00
9,591,400.00
368,110,931.67
16,875,000.00
2,091,483.33
5,500,000.00
1,200,000.00
732,019.17
313,722.50
5,040,000.00
7,410,000.00
1,932,233.33
3,315,000.00
10,683,291.67
7,469,583.33
4,112,680.00
1,817,876.67
5,594,550.00
12,554,100.00
2,424,240.00
8,500,000.00
550,000.00
14,000,000.00
331,155.00
2,687,175.00
34,805,160.00
14,971,066.50
7,485,533.25
1,700,000.00
1,500,000.00
175,595,869.75
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,800,000.00
Page 17 of 90
AMOUNT
(Rp)
1,932,233.33
5,525,000.00
6,215,733.33
6,274,450.00
5,234,320.00
2,377,223.33
1,413,360.00
12,987,000.00
2,683,980.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
31,168,800.00
13,392,990.00
6,696,495.00
2,300,000.00
1,500,000.00
232,661,680.00
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,150,000.00
1,932,233.33
3,315,000.00
5,827,250.00
8,067,150.00
2,804,100.00
1,398,366.67
1,590,030.00
13,160,160.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
28,571,400.00
12,155,559.00
6,077,779.50
2,300,000.00
1,500,000.00
223,433,363.50
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,410,000.00
Page 18 of 90
AMOUNT
(Rp)
1,932,233.33
3,038,750.00
6,215,733.33
7,469,583.33
3,177,980.00
1,118,693.33
1,766,700.00
13,419,900.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,610,360.00
12,169,144.00
6,084,572.00
2,300,000.00
1,500,000.00
224,797,984.33
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,410,000.00
1,932,233.33
3,038,750.00
6,215,733.33
7,469,583.33
3,177,980.00
1,118,693.33
1,766,700.00
13,419,900.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,610,360.00
12,169,144.00
6,084,572.00
2,300,000.00
1,500,000.00
224,797,984.33
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,410,000.00
1,932,233.33
3,038,750.00
6,215,733.33
7,469,583.33
3,177,980.00
1,118,693.33
1,766,700.00
13,419,900.00
2,424,240.00
Page 19 of 90
AMOUNT
(Rp)
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,610,360.00
12,169,144.00
6,084,572.00
2,300,000.00
1,500,000.00
224,797,984.33
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,670,000.00
1,932,233.33
3,315,000.00
6,992,700.00
7,469,583.33
2,804,100.00
1,118,693.33
1,766,700.00
13,939,380.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
30,649,320.00
12,528,789.00
6,264,394.50
2,300,000.00
1,500,000.00
227,835,228.50
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
6,435,000.00
1,932,233.33
3,038,750.00
6,409,975.00
7,469,583.33
3,925,740.00
4,265,018.33
1,531,140.00
9,956,700.00
2,077,920.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
25,714,260.00
12,182,118.00
6,091,059.00
2,300,000.00
1,500,000.00
219,989,592.00
Page 20 of 90
AMOUNT
(Rp)
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
4,875,000.00
1,932,233.33
8,840,000.00
3,496,350.00
11,951,333.33
3,364,920.00
1,398,366.67
8,009,040.00
2,813,850.00
-
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
201,538,125.00
259,740.00
12,541,828.00
-
2,300,000.00
385,793,706.33
2,507,814,324.75
376,172,148.71
376,172,148.71
3,252,097,405.13
Page 21 of 90
RECAPITULATION
###
#REF!
### ###
### ###
### ###
### : Mechanical & Electrical
Page 22 of 90
#REF!
#REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! : Mechanical & Electrical
The works include supplying and installing main equipment on-site, comply with Technical Specification, Design
Drawings and operate normally good
Note on price:
- Main equipment includes its accessories,
- All instalation incuding accessories and supporting materials.
-
Price including labor, all risk insurance for equipment, wages and the works.
-
Offer price including risks on the project work Offer price including risks on the project work
- Site Documentation, Shop Drawings and As Built Drawings.
- Testing And Commissioning for all system,etc
comply with Technical Specifications, Design Drawings and Standard Operation Procedure
Page 23 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
b. Top Recervoir
Capacity : 20 M³ Unit 2 48,000,000
Comply with header, pipe installation, accessories,
vondation Top Reservoir K-225, etc
Page 25 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 26 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 27 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Complete Control Panel Standard NFPA-20 and cable wiring to the pump using the FRC, Base Plate
Coupling and Gauge, Diesel Fuel Pumps (automatic and manual) with installation of diesel fuel piping,
Pump Foundation (concrete K 225-U 24), etc.
Complete Control Panel Standard NFPA-20 and cable wiring to the pump using the FRC, Base Plate
Coupling and Gauge, Pump Foundation (concrete K 225-U 24), etc.
Sub Total III.1
Page 29 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 31 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 32 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 33 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 34 of 90
NO. DESCRIPTION UNIT QTY UNIT PRICE (Rp)
Page 35 of 90
AMOUNT
(Rp)
Page 36 of 90
AMOUNT
(Rp)
35,850,000.00
96,000,000.00
31,400,000.00
8,635,500.00
5,895,000.00
177,780,500.00
21,061,400.00
7,371,490.00
9,477,630.00
4,212,280.00
24,588,333.33
6,240,000.00
9,835,333.33
6,147,083.33
28,458,000.00
9,759,420.00
11,465,226.00
5,732,613.00
5,068,800.00
3,015,000.00
2,647,260.00
2,682,765.00
1,609,659.00
11,827,200.00
8,123,750.00
502,500.00
4,987,737.50
2,992,642.50
28,170,918.45
215,977,041.45
Page 37 of 90
AMOUNT
(Rp)
Page 38 of 90
AMOUNT
(Rp)
1,119,000.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,737,783.00
868,891.50
3,350,000.00
9,759,420.00
550,550.00
2,473,600.00
418,750.00
382,500.00
4,840,071.00
2,420,035.50
39,071,511.00
1,398,750.00
736,200.00
745,625.00
2,080,375.00
2,279,812.50
2,567,700.00
3,909,600.00
2,172,228.75
1,086,114.38
3,350,000.00
9,759,420.00
550,550.00
2,473,600.00
418,750.00
382,500.00
4,840,071.00
2,420,035.50
41,171,332.13
1,119,000.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,737,783.00
868,891.50
4,187,500.00
12,199,275.00
688,187.50
3,092,000.00
418,750.00
382,500.00
6,050,088.75
3,025,044.38
44,919,930.13
Page 39 of 90
AMOUNT
(Rp)
839,250.00
441,720.00
447,375.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,564,948.50
782,474.25
4,187,500.00
12,199,275.00
550,550.00
2,473,600.00
418,750.00
382,500.00
5,823,277.50
2,911,638.75
42,988,309.00
1,398,750.00
736,200.00
745,625.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,910,617.50
955,308.75
4,187,500.00
12,199,275.00
688,187.50
2,473,600.00
418,750.00
382,500.00
5,864,568.75
2,932,284.38
44,858,616.88
839,250.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,653,858.00
826,929.00
3,350,000.00
12,199,275.00
550,550.00
2,473,600.00
418,750.00
382,500.00
5,572,027.50
2,786,013.75
42,203,663.25
Page 40 of 90
AMOUNT
(Rp)
1,398,750.00
736,200.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,865,880.00
932,940.00
5,025,000.00
14,639,130.00
550,550.00
2,473,600.00
418,750.00
382,500.00
6,806,484.00
3,403,242.00
49,194,976.00
1,678,500.00
588,960.00
596,500.00
1,664,300.00
1,823,850.00
2,567,700.00
3,909,600.00
1,905,633.00
952,816.50
3,350,000.00
9,759,420.00
550,550.00
3,092,000.00
418,750.00
382,500.00
5,025,591.00
2,512,795.50
40,779,466.00
1,398,750.00
736,200.00
745,625.00
2,080,375.00
2,279,812.50
2,567,700.00
3,909,600.00
2,172,228.75
1,086,114.38
4,187,500.00
12,199,275.00
688,187.50
3,092,000.00
418,750.00
382,500.00
6,050,088.75
3,025,044.38
47,019,751.25
2,712,500.00
1,996,250.00
15,712,500.00
480,500.00
606,375.00
523,875.00
896,625.00
517,750.00
7,527,843.75
3,226,218.75
34,200,437.50
Page 41 of 90
AMOUNT
(Rp)
27,281,760.00
38,372,950.00
45,778,425.00
2,873,475.00
39,001,597.25
16,714,970.25
170,023,177.50
596,431,170.63
185,000,000.00
185,000,000.00
1,175,188,712.08
39,000,000.00
59,500,000.00
8,875,000.00
107,375,000.00
37,665,000.00
5,913,000.00
3,226,500.00
594,000.00
490,050.00
938,250.00
2,808,000.00
13,073,400.00
64,708,200.00
Page 42 of 90
AMOUNT
(Rp)
11,250,000.00
17,557,312.50
1,546,425.00
826,076,225.00
31,668,650.00
8,640,750.00
110,112,600.00
21,300,000.00
145,739,660.00
17,869,830.00
11,199,320.00
1,859,660.00
21,228,720.00
3,414,360.00
36,025,685.00
43,556,625.00
4,806,625.00
2,330,775.00
5,448,465.00
9,106,121.25
4,553,060.63
-
1,335,290,869.38
140,086,916.67
121,247,641.67
91,467,095.42
39,200,183.75
38,644,666.67
19,322,333.33
5,975,666.67
41,794,875.00
51,053,850.00
1,398,465.00
19,182,800.00
9,591,400.00
578,965,894.17
1,914,256,763.54
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,735,000.00
3,640,000.00
1,932,233.33
3,315,000.00
11,266,016.67
5,079,316.67
3,738,800.00
2,097,550.00
4,946,760.00
15,411,240.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
38,181,780.00
15,063,347.00
7,531,673.50
2,300,000.00
1,500,000.00
Page 43 of 90
AMOUNT
(Rp)
251,323,052.17
Page 44 of 90
AMOUNT
(Rp)
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
9,230,000.00
1,932,233.33
3,315,000.00
8,740,875.00
5,228,708.33
4,112,680.00
3,565,835.00
2,767,830.00
15,844,140.00
2,597,400.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
36,883,080.00
14,431,410.50
7,215,705.25
2,300,000.00
1,500,000.00
244,824,992.42
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,475,000.00
1,932,233.33
3,315,000.00
6,604,216.67
7,469,583.33
3,177,980.00
1,118,693.33
706,680.00
14,285,700.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,870,100.00
12,310,298.00
6,155,149.00
2,300,000.00
1,500,000.00
225,804,968.67
Page 45 of 90
AMOUNT
(Rp)
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,475,000.00
1,932,233.33
3,038,750.00
6,215,733.33
7,469,583.33
3,177,980.00
1,118,693.33
706,680.00
14,285,700.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,870,100.00
12,110,878.00
6,055,439.00
2,300,000.00
1,500,000.00
224,841,105.33
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,475,000.00
1,932,233.33
3,315,000.00
6,604,216.67
7,469,583.33
3,177,980.00
1,118,693.33
706,680.00
14,285,700.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,870,100.00
12,310,298.00
6,155,149.00
2,300,000.00
1,500,000.00
225,804,968.67
Page 46 of 90
AMOUNT
(Rp)
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,475,000.00
1,932,233.33
3,038,750.00
6,215,733.33
7,469,583.33
3,177,980.00
1,118,693.33
706,680.00
14,285,700.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,870,100.00
12,110,878.00
6,055,439.00
2,300,000.00
1,500,000.00
224,841,105.33
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
7,475,000.00
1,932,233.33
3,315,000.00
6,604,216.67
7,469,583.33
3,177,980.00
1,118,693.33
706,680.00
14,285,700.00
2,424,240.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
29,870,100.00
12,310,298.00
6,155,149.00
2,300,000.00
1,500,000.00
225,804,968.67
Page 47 of 90
AMOUNT
(Rp)
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
8,515,000.00
4,830,583.33
1,657,500.00
14,179,641.67
5,676,883.33
3,738,800.00
3,076,406.67
471,120.00
13,852,800.00
2,077,920.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
34,025,940.00
14,868,496.50
7,434,248.25
2,300,000.00
1,500,000.00
243,365,434.75
16,875,000.00
2,091,483.33
30,000,000.00
662,310.00
732,019.17
313,722.50
6,500,000.00
1,932,233.33
8,563,750.00
5,050,283.33
5,228,708.33
7,290,660.00
2,936,570.00
765,570.00
9,090,900.00
2,727,270.00
55,611,270.00
10,530,960.00
5,325,000.00
331,155.00
2,687,175.00
25,974,000.00
13,075,783.50
6,537,891.75
2,300,000.00
1,500,000.00
224,633,715.25
2,091,244,311.25
313,686,646.69
313,686,646.69
4,491,270,921.48
Page 48 of 90
RECAPITULATION
ENGINEERING ESTIMATE ( EE )
The Development of Four Higher Education Institution Project ( Improving Access, Quality, Relevance,
and Competitiveness of Higher Education Program )
Name of Project : Perencanaan Pembangunan 2 Gedung Kuliah Bersama Universitas Negeri Malang ( UM )
Location : Malang, East Java
Fiscal Year : 2016
B. SUPPORTING INFRASTRUCTURE
I. WASTE WATER TREATMENT 1,131,541,155.00
II. LANDSCAPE 1,606,519,603.90
III. PEDESTRIAN AND PAVEMENT #REF!
IV. APPROACH ROAD #REF!
V. STORM WATER DRAINAGE #REF!
VI. CAMPUS POWER SUBSTATION 2,928,433,334.50
Main Distribution Cable Medium Voltage (MV) 46,433,334.50
Connection Fees and Security Deposits Subscriptions Connecting
2,802,000,000.00
Cost of 2.335 kVA to PLN ( TM )
Telephone Line Connecting Cost to PT.Telkom (20 Channels) 20,000,000.00
Connection fees to PDAM 60,000,000.00
ROUNDED #REF!
Page 49 of 90
###
#REF!
### #REF!
### #REF!
### #REF!
I PREPARATION WORK
1 Nursery and keet Bamboo & paranet 70% ls 1.00 5,000,000.00 5,000,000.00
2 Site clearing , Clean from debris , existing shrubs, m2 10,150.00 7,500.00 76,125,000.00
weed and others
3 Top soil /fertile soil ± 20cm @ ground fl ± 20 cm fertile soil m3 2,400.00 120,000.00 288,000,000.00
top soil + fertilizer @ planter box 2nd - 9th fl Building A & B (included carrying top soil m3 55.00 250,000.00 13,750,000.00
to planter box at 2nd - 9th floor)
4 Watering months 6.00 5,000,000.00 30,000,000.00
5 Fertilizer / compost bags 300.00 40,000.00 12,000,000.00
SUB TOTAL I 424,875,000.00
II HARDSCAPE
1 Concrete Bench TYPE 1 finishing plaster m3 14.85 3,500,000.00 51,975,000.00
2 Concrete Bench TYPE 2 (50x200x50 cm) finishing plaster m3 15.60 3,500,000.00 54,600,000.00
3 Plaza (200x400 cm) Concrete base 10 cm m3 8.00 2,982,629.65 23,861,037.20
Finishing - Andesit ramdom Ø 30 cm m2 80.00 468,893.87 37,511,509.60
Edging - Andesit 10x20x2 cm m' 80.00 221,643.87 17,731,509.60
III SOFTSCAPE
A TREE
1 Michelia champaca / Cempaka kuning H. 3 m overall , Ø 6 cm tree trunk pcs 8.00 1,087,900.00 8,703,200.00
2 Manilkara kauki / Sawo kecik H. 3 m overall , Ø 6 cm tree trunk pcs 49.00 1,087,900.00 53,307,100.00
3 Spathodea campanulata / Kecrutan H. 4 m overall , Ø 15 cm tree trunk pcs 20.00 708,400.00 14,168,000.00
4 Xanthostemon crysanthus / Xantostemon H. 3 m overall , Ø 6 cm tree trunk pcs 38.00 581,900.00 22,112,200.00
5 Kigelia pinnata / Sausage tree H. 3 m overall , Ø 6 cm tree trunk pcs 14.00 1,087,900.00 15,230,600.00
6 Cinnamomum inners / Kayu manis H. 3 m overall , Ø 6 cm tree trunk pcs 16.00 518,650.00 8,298,400.00
7 Prunus serrulata / Sakura H. 3 m overall , Ø 6 cm tree trunk pcs 20.00 1,404,150.00 28,083,000.00
8 Lagerstroemia speciosa / Bungur ungu H. 3 m overall , Ø 7 cm tree trunk pcs 59.00 581,900.00 34,332,100.00
Livistona rotundifolia / Palm sadeng minyak
9 H. 3 m trunk height pcs 73.00 2,373,600.00 173,272,800.00
daun pendek
10 Washingtonia robusta / Palm Washington H. 3 m trunk height pcs 4.00 3,753,600.00 15,014,400.00
B SHRUBS
1 Ixora sp / Soka king merah H. 40 cm , Ø plant 20 cm nos 1,700.00 21,188.75 36,020,875.00
2 Ixora sp / Soka orange H. 40 cm , Ø plant 20 cm nos 1,090.00 14,863.75 16,201,487.50
3 Hymenocalis sp / Lili bakung daun lebar H. 30 cm , Ø plant 20 cm nos 10,690.00 14,231.25 152,132,062.50
4 Philodendron burlermarx / Burlermarx H. 40 cm , Ø plant 25 cm nos 784.00 24,351.25 19,091,380.00
5 Osmocylon dactilon / Aralea daun kuning H. 25 cm , Ø plant 20 cm nos 2,960.00 14,863.75 43,996,700.00
6 Ophiopogon japonicum / Lili kucai hijau H. 25 cm , Ø plant 15 cm nos 1,325.00 8,538.75 11,313,843.75
C CLIMBER
1 Quisqualis indica / Rangoon creper H. 100 cm , Ø plant 30 cm nos 19.00 195,126.25 3,707,398.75
D GRASS
1 Axonopus compresus dwarf / Rumput gajah mini m2 9,400.00 26,700.00 250,980,000.00
Page 50 of 90
RECAPITULATION
#REF!
#REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Works : Infrastructure
Unit Price Amount
No Description
( Rp. ) ( Rp. )
1 PEDESTRIAN #REF!
2 ACCESS ROAD & PARKING #REF!
3 DRAINAGE WORKS #REF!
4 CUT AND FILL #REF!
5 AMPHITHEATER #REF!
- Structure #REF!
- Architecture #REF!
6 RETAING WALL / TURAP #REF! #REF!
7 MOTORCYCLE PARKING #REF!
- Structure #REF!
- Architecture #REF!
8 CORRIDOR WORKS #REF!
-Covered Walkway #REF!
-Gate Corridoor #REF!
9 TRASH CAN WORKS #REF! #REF!
Page 51 of 90
ENGINEERING ESTIMATE (EE)
#REF! #REF!
#REF! #REF!
#REF! #REF!
Works : Infrastructure
Unit Price Amount
No Description Unit Quantity
Rp Rp.
IV. INFRASTRUCTURE
IV.1 LANDSCAPE
IV.1.2 PEDESTRIAN
Paving Type PV 02
1 Soil Compaction sq.m 541.76 #REF! #REF!
2 Layer stone dust / abu batu t - 5 cm sq.m 541.76 #REF! #REF!
3 Paving Block Pedestrian ( Natural t = 6 cm ) sq.m 541.76 #REF! #REF!
4 Curb Concrete 15 x 20 cm m' 795.38 #REF! #REF!
-
plant trees and grass IV.1.2 #REF!
Page 52 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
IV.1.6 AMPHITHEATER
I STRUCTURE AMPHITHEATER WORKS
I.1 Preparation
1 - Batter board (Bowplank) m' 70.00 #REF! #REF!
Page 53 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
7 Beam - 0.300
- Lean concrete Cu.m 0.07 #REF! #REF!
- Concrete f'c 30 Mpa Cu.m 0.79 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 382.20 #REF! #REF!
- Formwork sq.m 5.28 #REF! #REF!
Beam Type G.1 EL + 0.000
- Concrete f'c 30 Mpa Cu.m 17.42 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 3,757.43 #REF! #REF!
- Formwork sq.m 116.14 #REF! #REF!
Beam Type B.1 EL + 0.000
- Concrete f'c 30 Mpa Cu.m 3.80 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 746.90 #REF! #REF!
- Formwork sq.m 25.32 #REF! #REF!
8 Plate EL + 0.000
- Concrete f'c 30 Mpa Cu.m 16.31 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 3,726.06 #REF! #REF!
- Formwork sq.m 217.52 #REF! #REF!
9 Stair
- Concrete f'c 30 Mpa Cu.m 4.35 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,031.00 #REF! #REF!
- Formwork sq.m 32.34 #REF! #REF!
10 Tribun Plate EL
- Concrete f'c 30 Mpa Cu.m 93.60 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 10,288.48 #REF! #REF!
- Formwork sq.m 374.40 #REF! #REF!
-
Total Structure Amphiteater Tank works #REF!
Page 54 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
II.4 #REF!
Page 55 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
Page 56 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
ARCHITECTURE WORKS
FLOOR EL. - 03.150
#REF!
MISCELANEOUS WORKS
Railing Steel Pipe Dia 3" + 2" Paint Finish h = 1200 mm m' 150.00 #REF! #REF!
II.2 #REF!
TOTAL MOTORCYRCLE PARKING AREA - 03.15 #REF!
TOTAL ARCHITECTURE MOTORCYRCLE PARKING AREA #REF!
Page 57 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
IV.1.9 CORRIDOR
9.1 COVERED WALKWAY WORKS
Page 58 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
Page 59 of 90
Unit Price Amount
No Description Unit Quantity
Rp Rp.
II. Architecture
Red Brick 1 Stone 1PC : 4 Sand sq.m 31.49 #REF! #REF!
Plestering 1PC : 3Sand sq.m 66.18 #REF! #REF!
Exterior wall painting OP sq.m 66.18 #REF! #REF!
Floorhardener sq.m 73.00 #REF! #REF!
Gutter L= 10 cm m' 10.85 50,000.00 542,500.00
Sub Total Architecture #REF!
Page 60 of 90
RECAPITULATION
#REF!
#REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Works : Amphitheater
Unit Price Amount
No Description
( Rp. ) ( Rp. )
I. AMPHITHEATER #VALUE!
Page 61 of 90
#REF!
#REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Works : Amphitheater
HARGA SATUAN JUMLAH HARGA
NO Description UNIT VOLUME
( Rp. ) ( Rp. )
Page 62 of 90
6 Wall
- Concrete f'c 30 Mpa Cu.m 31.20 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 7,369.98 #REF! #REF!
- Formwork sq.m 312.04 #REF! #REF!
7 Beam - 0.300
- Lean concrete Cu.m 0.07 #REF! #REF!
- Concrete f'c 30 Mpa Cu.m 0.79 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 382.20 #REF! #REF!
- Formwork sq.m 5.28 #REF! #REF!
Beam Type G.1 EL + 0.000
- Concrete f'c 30 Mpa Cu.m 17.42 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 3,757.43 #REF! #REF!
- Formwork sq.m 116.14 #REF! #REF!
Beam Type B.1 EL + 0.000
- Concrete f'c 30 Mpa Cu.m 3.80 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 746.90 #REF! #REF!
- Formwork sq.m 25.32 #REF! #REF!
8 Plate EL + 0.000
- Concrete f'c 30 Mpa Cu.m 16.31 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 3,726.06 #REF! #REF!
- Formwork sq.m 217.52 #REF! #REF!
9 Stair
- Concrete f'c 30 Mpa Cu.m 4.35 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,031.00 #REF! #REF!
- Formwork sq.m 32.34 #REF! #REF!
10 Tribun Plate EL
- Concrete f'c 30 Mpa Cu.m 93.60 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 10,288.48 #REF! #REF!
- Formwork sq.m 374.40 #REF! #REF!
-
Total Structure Ground Water Tank works #REF!
Page 63 of 90
#REF!
#REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! : Architecture
Unit Price Amount
No Description
( Rp. ) ( Rp. )
AMPHITHEATER
Page 64 of 90
II. ARCHITECTURE AMPHITEATHER WORKS
II.1 MASONRY WORKS
1 Lightweight Concrete t = 100 mm Semen Instan area Toilet sq.m 57.51 #REF! #REF!
2 Lightweight Concrete t = 100 mm Semen Instan sq.m 148.82 #REF! #REF!
3 Wall Thickening Toilet Area sq.m 7.40 #REF! #REF!
4 Wall plastering 1Pc:3Sand + Aci t = 15 mm sq.m 115.02 #REF! #REF!
5 Plastering concrete 1Pc:3Sand (Colum + Beam) + Aci t = 15 mm sq.m 64.32 #REF! #REF!
6 Wall plastering 1Pc:5Sand + Aci t = 15 mm sq.m 310.34 #REF! #REF!
7 Plastering Rough 1PC:3Sand sq.m 165.65 #REF! #REF!
8 Practical column 10x10 cm m' 49.60 #REF! #REF!
9 Practical beam 10x15 cm m' 60.50 #REF! #REF!
10 Glass Block 20 x 20 cm sq.m 20.21 #REF! #REF!
11 Homogenous tile 30x60 cm (Male and Female Toilet) sq.m 216.38 #REF! #REF!
12 Groove m' 48.50 75,000.00 3,637,500.00
13 Expose Concrete Interior sq.m 48.50 #REF! #REF!
14 Expose Concrete exterior sq.m 216.38 #REF! #REF!
-
II.1 #REF!
II.4 #REF!
Page 65 of 90
II.6 STAIR WORKS
1 Ceramic Tile 30 x 30 Cm sq.m 23.70 #REF! #REF!
2 Step Nosing m' 48.00 #REF! #REF!
3 Stair Railling pipe steel Ø 2" & 1" oil paint finish m' 22.86 #REF! #REF!
4 Plastering concrete sq.m - #REF! #REF!
5 Painting with AEP sq.m - #REF! #REF!
-
- #REF!
Page 66 of 90
RECAPITULATION
#REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Works : Architecture
Unit Price Amount
No Description
( Rp. ) ( Rp. )
1 STRUCTURE #REF!
2 GROUND TANK & POWER HOUSE #REF!
4 ARCHITECTURE #REF!
FLOOR EL. - 03.150 #REF!
POWER HOUSE FLOOR EL. - 00.150 #REF!
POWER HOUSE FLOOR EL. + 5.000 #REF!
FUEL TANK / TANGKI BBM #REF!
Page 67 of 90
#REF!
roject : Perencanaan Pembangunan 2 Gedung Kuliah Bersama Universitas Negeri Malang ( UM )
cation : Malang, East Java
Fiscal Year : 2016
#REF! : Structure
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
III.2 STRUCTURE GROUND WATER TANK and POWER HOUSE WORKS
1 Pile Cap
- Soil Excavation Cu.m 44.42 #REF! #REF!
- Soil back fill & compaction Cu.m 15.59 #REF! #REF!
- Disposal soil around site Cu.m 28.83 #REF! #REF!
- Sand bed & compacting t=10 cm Cu.m 3.39 #REF! #REF!
2 Sloof
- Soil Excavation Cu.m 141.18 #REF! #REF!
- Soil back fill & compaction Cu.m 61.51 #REF! #REF!
- Disposal soil around site Cu.m 79.67 #REF! #REF!
- Sand bed & compacting t=10 cm Cu.m 15.80 #REF! #REF!
3 Floor Plate
- Sand bed & compacting t=10 cm Cu.m 68.13 #REF! #REF!
Page 68 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
9 Wall Type K.1 El - 4.300 ± 0.000
- Concrete f'c 30 Mpa Cu.m 69.09 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 16,009.49 #REF! #REF!
- Formwork sq.m 690.94 #REF! #REF!
10 Wall Type K.1 El ± 0.000 + 5.000
- Concrete f'c 30 Mpa Cu.m 9.65 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 2,296.75 #REF! #REF!
- Formwork sq.m 48.23 #REF! #REF!
11 Beam El + 5.000
Beam Type G.1
- Concrete f'c 30 Mpa Cu.m 16.87 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 3,712.69 #REF! #REF!
- Formwork sq.m 84.37 #REF! #REF!
Beam Type G.2
- Concrete f'c 30 Mpa Cu.m 11.24 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 2,062.63 #REF! #REF!
- Formwork sq.m 56.22 #REF! #REF!
Beam Type G.3
- Concrete f'c 30 Mpa Cu.m 3.22 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 917.97 #REF! #REF!
- Formwork sq.m 21.46 #REF! #REF!
Beam Type G.4
- Concrete f'c 30 Mpa Cu.m 4.58 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,698.00 #REF! #REF!
- Formwork sq.m 30.55 #REF! #REF!
Beam Type BG.3
- Concrete f'c 30 Mpa Cu.m 3.81 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 802.11 #REF! #REF!
- Formwork sq.m 25.43 #REF! #REF!
Beam Type BG.4
- Concrete f'c 30 Mpa Cu.m 6.46 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,461.90 #REF! #REF!
- Formwork sq.m 43.06 #REF! #REF!
Beam Type BG.4A
- Concrete f'c 30 Mpa Cu.m 0.29 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 75.59 #REF! #REF!
- Formwork sq.m 1.93 #REF! #REF!
Beam Type CG.
- Concrete f'c 30 Mpa Cu.m 2.35 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 640.28 #REF! #REF!
- Formwork sq.m 15.64 #REF! #REF!
12 Plate El + 5.000
- Concrete f'c 30 Mpa Cu.m 55.47 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 4,651.40 #REF! #REF!
- Formwork sq.m 369.82 #REF! #REF!
13 Coloum El + 5.000 - 7300
- Concrete f'c 30 Mpa Cu.m 3.45 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 857.27 #REF! #REF!
- Formwork sq.m 27.60 #REF! #REF!
14 Beam Type G4 El + 7.300
- Concrete f'c 30 Mpa Cu.m 1.75 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 595.84 #REF! #REF!
- Formwork sq.m 11.65 #REF! #REF!
15 Plate El +7.300
- Concrete f'c 30 Mpa Cu.m 2.04 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 238.96 #REF! #REF!
- Formwork sq.m 17.00 #REF! #REF!
16 Stair
- Concrete f'c 30 Mpa Cu.m 2.33 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 305.06 #REF! #REF!
- Formwork sq.m 18.29 #REF! #REF!
Page 69 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
17 Equipment Foundation
- Booster Pump Cu.m 0.90 3,026,410.00 2,723,769.00
- Electric Pump Cu.m 0.58 3,026,410.00 1,740,185.75
- Diesel Pump Cu.m 0.75 3,026,410.00 2,269,807.50
- Jocky Pump Cu.m 0.04 3,026,410.00 121,056.40
- Water Pump Cu.m 0.81 3,026,410.00 2,458,958.13
- Pompa Sand Filter (SF) & CF Cu.m 0.16 3,026,410.00 484,225.60
- Genset Building Cu.m 13.75 3,026,410.00 41,613,137.50
-Genset Data Center Cu.m 1.02 3,026,410.00 3,086,938.20
-Panel Genset Cu.m 1.40 3,026,410.00 4,236,974.00
-LVMDP Cu.m 2.48 3,026,410.00 7,490,364.75
-MVDP Cu.m 0.72 3,026,410.00 2,163,883.15
-Capasitor Bank Cu.m 0.99 3,026,410.00 2,996,145.90
- Trafo Cu.m 1.31 3,026,410.00 3,972,163.13
- Roof Tank Cu.m 0.75 3,026,410.00 2,269,807.50
Page 70 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
#REF!
Page 71 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
POWER HOUSE FLOOR EL. - 00.150
1.1 MASONRY WORKS
1 Lightweight Concrete t = 100 mm Semen Instan sq.m 940.63 #REF! #REF!
2 Practical column 11x11 cm m' 355.00 #REF! #REF!
3 Practical beam 11x15 cm m' 294.25 #REF! #REF!
4 Wall Plastering 1PC:5 Sand sq.m 1,551.06 #REF! #REF!
5 Rockwool Density 80 kg / m3 sq.m 128.00 150,000.00 19,200,000.00
-
#REF!
1.7 ROOF
1 Gutter 200 x 50 mm m' 87.00 #REF! #REF!
2 Roof Drain 4" sq.m 6.00 350,000.00 2,100,000.00
3 Waterproofing Membrane sq.m 382.70 #REF! #REF!
4 Screed Protecsi Membrane Waterproofin 40 mm thick sq.m 382.70 #REF! #REF!
-
#REF!
Page 72 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
I. POWER HOUSE FLOOR EL. + 5.000
1.1 MASONRY WORKS
1 Lightweight Concrete t = 100 mm Semen Instan area Toilet sq.m 56.36 #REF! #REF!
2 Practical column 10x10 cm m' 26.40 #REF! #REF!
3 Practical beam 10x15 cm m' 34.10 #REF! #REF!
4 Wall Plastering 1PC:5 Sand sq.m 112.72 #REF! #REF!
-
#REF!
1.7 ROOF
1 Gutter 200 x 50 mm m' 87.00 #REF! #REF!
2 Roof Drain 4" sq.m 6.00 350,000.00 2,100,000.00
3 Waterproofing Membrane sq.m 382.70 #REF! #REF!
4 Screed Protecsi Membrane Waterproofin 40 mm thick sq.m 382.70 #REF! #REF!
-
#REF!
Page 73 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
4 Fondation Tank
- Concrete f'c 30 Mpa Cu.m 8.80 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 2,054.82 #REF! #REF!
- Formwork sq.m 70.40 #REF! #REF!
Column
- Concrete f'c 30 Mpa Cu.m 8.58 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,978.51 #REF! #REF!
- Formwork sq.m 114.41 #REF! #REF!
Wall
- Concrete f'c 30 Mpa Cu.m 58.11 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 9,970.71 #REF! #REF!
- Formwork sq.m 464.87 #REF! #REF!
6 Beam
Beam RB
- Concrete f'c 30 Mpa Cu.m 5.55 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,178.74 #REF! #REF!
- Formwork sq.m 37.02 #REF! #REF!
7 Plate
- Concrete f'c 30 Mpa Cu.m 6.17 #REF! #REF!
- Rebars BJTP24+BJTD40 kg 1,231.76 #REF! #REF!
- Formwork sq.m 51.40 #REF! #REF!
Page 74 of 90
Unit Price Amount
No Description Unit Quantity
( Rp. ) ( Rp. )
II. FUEL TANK / TANGKI BBM
1.1 MASONRY WORKS
1 Exposed Concrete sq.m 227.20 #REF! #REF!
2 Waterproofing Membrane sq.m 227.20 #REF! #REF!
3 Screed Protecsi Membrane Waterproofin 40 mm thick sq.m 227.20 #REF! #REF!
-
#REF!
1.4 ROOF
1 Waterproofing Membrane sq.m 57.00 #REF! #REF!
2 Screed Protecsi Membrane Waterproofin 40 mm thick sq.m 57.00 #REF! #REF!
-
#REF!
Page 75 of 90
RECAPITULATION
ENGINEERING ESTIMATE ( EE )
The Development of Four Higher Education Institution Project ( Improving Access, Quality, Relevance, and Competitiveness
of Higher Education Program )
Name of Project : Perencanaan Pembangunan 2 Gedung Kuliah Bersama Universitas Negeri Malang ( UM )
Location : Malang, East Java
Fiscal Year : 2016
Works : Mechanical & Electrical
UNIT PRICE
NO. DESCRIPTION UNIT QTY
(Rp)
A. CONSTRUCTION COST
The works include supplying and installing main equipment on-site, comply with Technical Specification, Design
Drawings and operate normally good
Note on price:
- Main equipment includes its accessories,
- All instalation incuding accessories and supporting materials.
-
Price including labor, all risk insurance for equipment, wages and the works.
-
Offer price including risks on the project work Offer price including risks on the project work
- Site Documentation, Shop Drawings and As Built Drawings.
- Testing And Commissioning for all system,etc
comply with Technical Specifications, Design Drawings and Standard Operation Procedure
a. Delivery Pump
Type : Centrifugal End Suction Unit 4 187,110,000
Capacity : 750 L/Mn
Total Head : 60 Meter
Total Power : 18,5 kW
Rotation : 2900 rpm
Caracteristic : 380/415 V , 3 Ph , 50 Hz
Comply with pump control equipment, electrical cable NYY 4 x 6 mm²,
installing, meterials accessories, valve-valve, elbow, tee-way, reducer,
seal, vondation pump K-225, etc
c. Sumpit
Type : Submersible Unit 2 22,000,000
Capacity : 120 L/mn
Total Head : 20 M
Total Power : 0.75 Kw
Caracteristic : 380/415 V , 3 Ph , 50 Hz
Comply with pump control equipment, electrical cable NYY 4 x 4 mm²,
installing, meterials accessories, valve-valve, elbow, tee-way, reducer,
seal, vondation pump K-225, etc
Page 77 of 90
UNIT PRICE
NO. DESCRIPTION UNIT QTY
(Rp)
I.1.2 Main Pipe Installation
a. Installation Clean Water in Pump Room :
Pipe Material Galvanized Iron Pipe (GIP), Medium Class,
Complete elbow, reducer, T-Way, etc
- Header Pipe, length 6 M', diameter 250 mm, c/w flange & Accessories Nos 1 7,075,200
- Diameter 150 mm M' 8 529,200
- Diameter 100 mm M' 16 339,700
- Diameter 50 mm M' 20 156,100
Pipe auxiliary equipment, etc
- Gate Valve, diameter 150 mm, 10 K Nos 2 4,185,900
- Gate Valve, diameter 100 mm Nos 2 2,036,000
- Gate Valve, diameter 50 mm Nos 3 632,400
- Check Valve, diameter 50 mm Nos 2 926,700
- Foot Valve, diameter 50 mm Nos 2 1,950,000
- Strainer, diameter 50 mm Nos 2 582,200
- Fleksible Conection, diameter 50 mm Nos 4 250,300
- Water Level Control Nos 1 1,500,000
- Preassure Gauge (scala 25 Kg/cm²) Nos 2 650,000
- Fitting, Elbow, tee, reducer etc Ls 1 3,197,700
- Hanger, klem, bracket/support etc Ls 1 1,918,620
Page 78 of 90
UNIT PRICE
NO. DESCRIPTION UNIT QTY
(Rp)
b. Sumpit (AMPHITEATRE)
Type : Submersible Unit 2 22,000,000
Capacity : 120 L/mn
Total Head : 20 M
Total Power : 0.75 Kw
Caracteristic : 380/415 V , 3 Ph , 50 Hz
Comply with pump control equipment, electrical cable NYY 4 x 4 mm²,
installing, meterials accessories, valve-valve, elbow, tee-way, reducer,
seal, vondation pump K-225, etc
Sub Total III.2.1
Page 79 of 90
UNIT PRICE
NO. DESCRIPTION UNIT QTY
(Rp)
III.3 ELECTRICAL WORK AND LIGHTING
a. Illumination Installation and Receptacle work, complete with
cablel NYM 3 x 2,5 mm² , PVC conduit diameter 20 mm, T-does, accessories etc.
- General Ligthing Installation Nos 66 308,300
- General Purpose Outlet, 1ph,10 Amp Installation Nos 15 577,800
b. Procurement and installation of fixtures and armatures
- Stair Lamp LED 9 Watt Nos 28 508,000
- Recessed Mounted Down Light PL-C 18 Watt Nos 26 225,720
- Surface Mounted Flourescent Light TL5 : 2 x 28 Watt / V-Shape Nos 2 620,000
- Recessed Mounted Down Light PL-C 13 Watt Nos 10 197,820
- Receptacle, 1ph,10 Amp Nos 15 37,500
- Single Switch Nos 5 23,300
- Double Switch Nos 7 34,000
- Cable tray, 300 mm x 50 mm M' 22 329,550
Sub Total III.3
TOTAL - III
Page 80 of 90
UNIT PRICE
NO. DESCRIPTION UNIT QTY
(Rp)
V. FIBER OPTIC NETWORK
Backbone
1 Cabling System
a Fiber Optic SingleMode Burried for Backbone (Main) 144 Core , MH to DC m¹ 145 134,500
b Fiber Optic SingleMode Burried for Backbone (Backup) 144 Core , MH to DC m¹ 145 134,500
c Fiber Optic SingleMode Burried for Backbone (Main) 24 Core , HHex to MH m¹ 270 44,500
d Fiber Optic SingleMode Burried for Backbone (Backup) 24 Core , HHex to MH m¹ 225 44,500
e Joint Closure Burried Capacity 144core ea 2 3,307,500
f Joint Closure Burried Capacity 24core ea 2 1,080,000
g Mainhole with dimension W : 120cm x H : 100 cm x D : 100 cm Lot 1 4,646,336
h Handhole Ex with dimension W : 80cm x H : 80 cm x D : 100 cm Lot 1 2,837,098
j Rack Cabling 19", 42U Depth 1100mm ea 2 18,850,000
j Optical Destination Frame 144 Core include Acc (Casette, SC Adapter, etc) ea 2 14,500,000
k Patchord SC - LC, min 3m length ea 288 628,550
2 Instalation Cost
a Installation, Pulling, Planting HDPE m¹ 640 34,735
b Installation, Pulling Cable Fiber Optic m¹ 785 59,900
c Termination Cable Fiber Optic Backbone Main-Backup core 672 112,000
d Testing Commisioning,Labeling,& Documentation Fiber Optic ( OTDR ) lot 1 1,500,000
ODC-1
1 Cabling System
a Cable 24 Singlemode Fiber direct burried, MH to HH1 (ODC-1) m¹ 30 44,500
b Cable 24 Singlemode Fiber direct burried, Redundant MH to HH1 ODC-1) m¹ 30 44,500
c Handhole with dimension W : 80cm x H : 80 cm x D : 100 cm Lot 1 2,837,098
d Optical Destination Cabinet (outdoor Use) WxHxD = ea 1 3,850,000
e PDU (6 Hole), Arrester,Blower ea 1 1,560,000
f Optic Terminal Box 24 core, include Acc (Casette, SC Adapter, etc) ea 2 2,600,000
g Patchord SC - LC, min 1,2m length ea 24 628,550
2 Instalation Cost
a Installation, Pulling, Planting HDPE m¹ 60 34,735
b Installation, Pulling Cable Fiber Optic m¹ 60 59,900
c Termination Cable Fiber Optic main-backup core 48 112,000
d Testing Commisioning,Labeling,& Documentation Fiber Optic ( OTDR ) lot 1 1,500,000
ODC-2
1 Cabling System
a Cable 24 Singlemode Fiber direct burried, MH to HH2 (ODC-2) m¹ 162 44,500
b Cable 24 Singlemode Fiber direct burried, Redundant MH to HH2 (ODC-2) m¹ 170 44,500
c Handhole with dimension W : 80cm x H : 80 cm x D : 100 cm Lot 1 2,837,098
d Optical Destination Cabinet (outdoor Use) WxHxD = ea 1 3,850,000
e PDU (6 Hole), Arrester,Blower ea 1 1,560,000
f Optic Terminal Box 24 core, include Acc (Casette, SC Adapter, etc) ea 2 2,600,000
g Patchord SC - LC, min 1,2m length ea 24 628,550
2 Instalation Cost
a Installation, Pulling, Planting HDPE m¹ 332 34,735
b Installation, Pulling Cable Fiber Optic m¹ 332 59,900
c Termination Cable Fiber Optic main-backup core 48 112,000
d Testing Commisioning,Labeling,& Documentation Fiber Optic ( OTDR ) lot 1 1,500,000
TOTAL - V.
VI. CAMPUS POWER SUBSTATION
VI.1.1 MAIN DISTRIBUTION CABLE MEDIUM VOLTAGE (MV)
Works Including Supplying, Installing And Operate In Normally Good
c/w Cable Lugs, Cable Gland, Termination, Accessories,
Grounding System (max. 2 Ohm)
Page 81 of 90
AMOUNT
(Rp)
748,440,000.00
47,520,000.00
44,000,000.00
100,000,000.00
25,000,000.00
23,000,000.00
987,960,000.00
Page 82 of 90
AMOUNT
(Rp)
7,075,200.00
4,233,600.00
5,435,200.00
3,122,000.00
8,371,800.00
4,072,000.00
1,897,200.00
1,853,400.00
3,900,000.00
1,164,400.00
1,001,200.00
1,500,000.00
1,300,000.00
3,197,700.00
1,918,620.00
25,473,042.00
1,678,656.00
2,098,320.00
2,517,984.00
2,937,648.00
816,435.00
395,670.00
474,804.00
553,938.00
553,938.00
27,038,400.00
9,000,000.00
20,000,000.00
143,581,155.00
1,131,541,155.00
183,250,000.00
114,250,000.00
88,670,400.00
164,920,000.00
114,800,000.00
119,700,000.00
40,950,000.00
344,160,000.00
1,170,700,400.00
1,170,700,400.00
17,620,000.00
5,670,000.00
6,500,000.00
Page 83 of 90
AMOUNT
(Rp)
29,790,000.00
432,900.00
577,200.00
3,078,400.00
425,000.00
850,000.00
904,000.00
6,267,500.00
778,000.00
778,000.00
389,000.00
7,996,000.00
1,999,000.00
1,199,400.00
13,139,400.00
379,680.00
2,177,160.00
1,236,000.00
100,200.00
3,893,040.00
53,089,940.00
23,000,000.00
44,000,000.00
67,000,000.00
899,400.00
1,986,000.00
1,396,000.00
556,800.00
756,000.00
2,008,000.00
2,817,600.00
1,900,550.00
1,140,330.00
3,926,000.00
1,452,000.00
216,000.00
660,800.00
1,548,000.00
840,000.00
1,600,000.00
1,950,700.00
1,170,420.00
26,824,600.00
93,824,600.00
Page 84 of 90
AMOUNT
(Rp)
20,347,800.00
8,667,000.00
14,224,000.00
5,868,720.00
1,240,000.00
1,978,200.00
562,500.00
116,500.00
238,000.00
7,250,100.00
60,492,820.00
207,407,360.00
750,000.00
7,330,000.00
23,112,000.00
16,040,000.00
238,000.00
47,470,000.00
419,214,600.00
157,437,000.00
81,302,000
9,570,100
144,162,900
86,497,740
37,500,000
52,500,000
5,300,000
32,252,500.00
1,025,736,840.00
1,025,736,840.00
Page 85 of 90
AMOUNT
(Rp)
19,502,500
19,502,500
12,015,000
10,012,500
6,615,000
2,160,000
4,646,336
2,837,098
37,700,000
29,000,000
181,022,400
22,230,400
47,021,500
75,264,000
1,500,000
1,335,000
1,335,000
2,837,098
3,850,000
1,560,000
5,200,000
15,085,200
2,084,100
3,594,000
5,376,000
1,500,000
7,209,000
7,565,000
2,837,098
3,850,000
1,560,000
5,200,000
15,085,200
11,532,020
19,886,800
5,376,000
1,500,000
596,386,751.25
14,785,462.50
13,302,528.00
14,965,344.00
3,380,000.00
46,433,334.50
2,802,000,000.00
20,000,000.00
60,000,000.00
2,882,000,000.00
2,928,433,334.50
5,976,134,685.75
Page 86 of 90
ENGINEERING ESTIMATE ( EE )
The Development of Four Higher Education Institution Project ( Improving Access, Quality, Relevance,
and Competitiveness of Higher Education Program )
Name of Project : Perencanaan Pembangunan 2 Gedung Kuliah Bersama Universitas Negeri Malang ( UM )
Location : Malang, East Java
Fiscal Year : 2016
Works : Data Center
a. Core Switch
Core Switch Bundle (Chassis,2xSUP2E,3xFAB2),NoPowSup ea 1.00 1,215,000,000.00 1,215,000,000.00
Bundle (Chas,2xSUP2E,3xFAB2),NoPwr ea 1.00 146,996,505.00 146,996,505.00
OS Release 6.2 for Core SwitchSeries ea 1.00 - -
6 Slot Chassis 220Gbps/Slot Fabric Module ea 1.00 135,000,000.00 405,000,000.00
6 Slot Chassis 220Gbps/Slot Fabric Module ea 3.00 - -
3.0KW AC Power Supply Module (Cable Included) ea 4.00 47,250,000.00 189,000,000.00
Power Cord, 250Vac 16A, Europe ea 4.00 - -
6 Slot Chassis Air Filter Kit (Front/Side) ea 1.00 47,250,000.00 47,250,000.00
6 Slot Chassis Center Mount Kit ea 1.00 13,500,000.00 13,500,000.00
6 Slot Chassis Front Door Kit ea 1.00 20,250,000.00 40,500,000.00
Module Blank Slot Cover ea 2.00 - -
N7K or N77 Campus Deployment; For Tracking Only ea 1.00 - -
Perpetual Core Switch 6 Slot and Higher ea 1.00 675,000,000.00 675,000,000.00
SWSS UPGRADES C1 Foundation Perpetual Bundle ea 1.00 116,437,500.00 116,437,500.00
DCNM LAN Enterprise License Core Switch ea 1.00 - -
Core SwitchVDC license (4 VDCs per license) ea 1.00 - -
Core SwitchLAN Enterprise License (L3 protocols) ea 1.00 - -
Core SwitchTransport Services License (OTV/LISP) ea 1.00 - -
Core SwitchEnhanced Layer 2 License (FabricPath) ea 1.00 - -
Core Switch- Supervisor 2 Enhanced ea 1.00 - -
Core Switch- Supervisor 2 Enhanced ea 1.00 - -
Core SwitchF3-Series 48 Port 1/10GbE (SFP/SFP+) ea 1.00 594,000,000.00 594,000,000.00
Core SwitchF3-Series 48 Port 1/10GbE (SFP/SFP+) ea 1.00 594,000,000.00 594,000,000.00
d IP PABX (kapasitas minimum 500 ext), dengan rincian: Lot 1 904,471,785.00 904,471,785.00
including of :
IPPBX Svr (M4), Export Restricted SW Unit 1
Power Cord, 250VAC 10A CEE 7/7 Plug, EU Unit 2
Virt. Hypervisor 5.x (2-socket) Unit 1
Software App Version 10.X 11.X Unit 1
Virt. Hypervisor 5.x - SnS Unit 1
300GB 6Gb SAS 10K RPM SFF HDD/hot plug/drive sled mounted Unit 8
8GB DDR4-2133-MHz RDIMM/PC4-17000/single rank/x4/1.2v Unit 6
770W AC Hot-Plug Power Supply for 1U C-Series Rack Server Unit 2
2.40 GHz E5-2630 v3/85W 8C/20MB Cache/DDR4 1866MHz Unit 2
Intel i350 Quad Port 1Gb Adapter Unit 1
Enable RAID 5 Setting Unit 1
12G SAS Modular Raid Controller Unit 1
12Gbps SAS 1GB FBWC Cache module (Raid 0/1/5/6) Unit 1
IPPBX User License Starter Bundle with 35 UWL Pro Licenses Unit 1
Basic User Connect License Users 150
elepresence Room System User Unit 2
Voice Gateway
Voice Bundle, PVDM3-16, UC License PAK, FL-CUBE10 Unit 1
AC Power Supply Users 1
AC Power Cord (Europe), C13, CEE 7, 1.5M Unit 1
Pro Express on Router Flash w/o default config Unit 1
Adapter for use with External RPS Unit 1
Unified Border Element Enterprise License - 5 sessions Unit 2
IP Base License Users 1
512MB DRAM default Unit 1
Unified Communication License Users 1
256MB Compact Flash Users 1
Survivable Remote Site Telephony License Users 1
Communication Manager Express or SRST - 25 seat license Users 1
2-Port 3rd Gen Multiflex Trunk Voice/WAN Int. Card - T1/E1 Unit 1
Four-port Voice Interface Card - FXO (Universal) Unit 3
PVDM3 16-channel to 128-channel factory upgrade Unit 1
e CCTV EQUIPMENT
1 NVR516-128, NVR 128 channel, 16 bay (include HDD capacity 64 TB ) unit 2 129,140,000.00 258,280,000.00
2 Operation center work Station unit 3 17,650,000.00 52,950,000.00
3 43" Display for Wall monitor unit 6 7,529,000.00 45,174,000.00
Page 87 of 90
UNIT PRICE AMOUNT
NO. DESCRIPTION UNIT QTY
(Rp) (Rp)
Page 88 of 90
UNIT PRICE AMOUNT
NO. DESCRIPTION UNIT QTY
(Rp) (Rp)
G CCTV
Lens
Focal length 1.27 mm
Max. Aperture Ratio ,F2.0
Lens Angle AdjustmenRotation ±180°
Angular Field of View Horizontal angle of view: 187°
Vertical angle of view: 168°
Operational
Network storage Support for SD/SDHC/SDXC card
Power supply Power over Ethernet IEEE 802.3af/802.3a Type 1 Class 2 max 4.5 Watt
Audio Built-in mic
Digital zoom 4x
Communication Inter Male RJ45 10BASE-T/100BASE-TX PoE on a 2 m (6.6 ft) network cable
Frequency Range 50/60 Hz
Page 89 of 90
UNIT PRICE AMOUNT
NO. DESCRIPTION UNIT QTY
(Rp) (Rp)
1 PARTITION lot
Including :
Gypsum Partition Fire Rated inside 2 layer, 1 hr m2 72 960,000 69,120,000.00
Metal Stud Frame 7,6mm
Insulation Glasswool, thickness 2 inch
Normal Partition m2 18 390,000 7,020,000.00
Painting (Wall + Gypsum Partition) m2 72 100,000 7,200,000.00
Tempered Glass Partition with support, t=12mm m2 4 2,310,000 8,085,000.00
2 DOORS lot
Including :
Double Steel Fire Door pcs 1 20,770,000 20,770,000.00
Dimension : (30x210)+(90x210) cm
Steel Frame
Accessories
Single Steel Fire Door pcs 1 15,390,000 15,390,000.00
Dimension : (30x210)+(90x210) cm
Frameless
Accessories
3 CEILING lot
Including :
Metal Ceiling m2 32 650,000 20,800,000.00
Perforated Metal Ceiling pcs 4 700,000 2,800,000.00
Normal Ceiling m2 48 470,000 22,560,000.00
Support Material lot 1 5,390,000 5,390,000.00
Page 90 of 90