Sie sind auf Seite 1von 2

QINGDAO, CHINA

FABRICATION FACILITY

McDermott Wuchuan

Warehouse Structure Shop


Piping Shop
Module Shop
Blasting & Painting Shop

Qingdao McDermott Wuchuan (QMW) is a joint venture between McDermott


and CSIC Wuchuan to cater to the FPSO/FLNG and Offshore/Onshore Module
construction market, managed by McDermott.

Piping Shop Warehouse


• Physically isolated carbon and exotic steel shop to • Large cover warehouse which include climatic controlled
prevent contamination for critical equipment
• Equipped with pipe cutting,beveling,rotator,manipulator • Goods receiving and issuing are tracked by an online
• The shops are serviced with various overhead and computerized material control system
A-frame cranes • Materials received are segregated by type and project

Structure Shop QMW Quayside Particular


Ѭ4ZY‫ܪ‬YYJI\NYMXYFYJTKYMJFWYFSIHTRUZYJWHTSYWTQQJI Length: 376m
equipment WaterDepth: Up to 10m
• Serviced by various overhead and A-frame cranes Pier: 2 off
• Material feed and off-cut removal handled by a custom
designed heavy duty conveyor system Shipyard Dry Dock Particular(Top Three)
First: 530m×125m×13.1m
Blasting & Painting Shop Second: 480m×115m×13.6m
• Auto-blast/Primer removes mill scale & rust and Third: 480m×96m×14.1m
enhances“build clean”concept
• Equipped with dust collector/vacuum recovery Overall Yard Particular
RFHMNSJFSIIJMZRNIN‫ܪ‬JW Total Yard Area: 4,500,000m2
• VOC emission treatment as well as other Total Quayside Length: 6,000m
gases/particles

Module Shop
• Fully enclosed assembly shop enhances safety, quality
and delivery certainty
• Ability to work 24/7
• 200m(L)×125m(W)×42m(H), 4 bays
• Served by various overhead cranes

26M062018H-16
MCDERMOTT WUCHUAN CAPABILITIES
Drawing on the unique strengths of its parent companies,
PROJECT EXPERIENCE
QMW delivers high quality onshore and offshore modules,
FPSO construction and integration services for clients
YAMAL Project
Client: Technip/JCG/Chiyoda
worldwide. Our capabilities include the following
Project Type: LNG
Durarion: 16 Months
Total Weight: 12,000 MT
Scope of work: Fabrication engineering, procurement
of painting, structure steel and E&I bulk material,
construction, supply and application of PFP and
insulatiom, mechanical completion &
pre-commissioning, load-out
Onshore Modules Offshore Modules MC Project
Client: Marine Contracting
Project Type: Jacket & Bridge
Durarion: 10 Months
Total Weight: 7000 MT
Scope of work: Fabrication engineering, procurement
of painting, structure steel and E&I bulk material,
construction, mechanical completion
Jacket Subsea Structure JORD Project
Client: Jord Oil & Gas
Project Type: Offshore Module
Durarion: 8 Months
Total Weight: 2,000 MT
Scope of work: Fabrication engineering, procurement of
painting, structure steel, piping and E & I bulk material,
construction of process modules, mechanical completion
FPSO Fish Farm & pre-commissioning, Transportation to integration yard

CAMERON Project
SUBModuleSM Advantages
Client: OneSubsea
• Split the complex module to sub-modules to open the work front.
Project Type: Subsea Structure
• Assemble the sub-modules inside the Mega Module Assembly
Durarion: 14 Months
Shop, 24/7 without being affected by weather condition.
Total Weight: 350 MT
• Provide delivery certainty, particularly to fact track projects.
Scope of work: Fabrication engineering, Procurement
• Requires early engagement during detailed engineering phase
of painting and structure steel, fabrication supervision,
construction of subsea structure including small bore
tubing, provide assistance for FAT, EFAT & SIT

TBM Project
Client: McDermott
Project Type: Buoyancy Structure
Durarion: 12 Months
Total Weight: 1,000 MT
Scope of work: Fabrication engineering,
procurement all materials, construction,
Yamal SUBModuleSM Transfer load-out & transportation
Contact
No. 367, Lijiang East Road
Qingdao, Shandong, China
Tel: +86 532 8695 3500
Email: businessdevelopment@mcdermottwuchuan.com
Visit www.mcdermottwuchuan.com

Yamal SUBModuleSM Stacking

Das könnte Ihnen auch gefallen