QUOTATION FOR CONTRACTOR’S ALL RISKS INSURANCE

Name of the Principal The Chief Engineer (Project) Himank, C/O 99 A.P.O.

Address of Principal BRO, The Chiek Engineer Headquarters, Chief Engineer (Project) Himank,
pin-931710, C/o 56 APO.

Contractor-Bridge and Roof Co. (India) ltd.


Principal, All Suppliers,
Sub-contractors any tier and any of their subsidiary companies including
Name of Contractor/Insured any other connected party belonging to them, Directors, officers,
employees of each of the above parties for their respective rights and
interest
Consultants and the Independent Engineer for their onsite activities only

Address of Contactor 4th & 5th Floor, Kankaria Centre, 2/1, Russel Street, Kolkata-700071
KM 150.400 at Darbyuk-Shyok-Daulat Beg Oldie Road, Leh, J&K, within
Location of the Project Indian territory (approximately 320 KM from Leh) under Project Himank
(Chief Engineer, Project Himank, Border Roads Organization, C/O 56 A.P.O.
PIN - 931 710).
Manufacturing, supply, transportation and erection /launching (including
Load testing and commissioning) of 1400 ft. (10 X 140ft. (TDR)) Crib
Description of Project Bearing Broken span Bailey type Portable Steel (Galvanized) Bridge’s of
extra wide carriageway width of 4.25M suitable for IRC load class 70R
loading at 150.400 KM on D-S-DBO road within Indian territory.
Tariff Risk Risk code- 111127, S No.-11
Total Project Value INR 295,426,384

Project Period in Months 15 months including one month load testing period (From 01/08/2018 to
31/10/2019)
Policy Period Cheque date to 31/10/2019
Not Liable Period 01/08/2018 to cheque date
Disc
Description Sum Insured Rate Premium
CAR Basic (Total project cost Including Free Issue INR 295,426,384 11.100
Material if any)

Addons:-
STFI Premium 295,426,384 0.3188
EQ 295,426,384 0.3542
Terrorism 295,426,384 0.3258
Clearance and Removal of Debris 29,542,638 11.1000
Third Party Liability including Cross Liability Cover 29,542,638 16.6500
Owners’ surrounding property with FLEXA risks 29,542,638 12.4875
Escalation @ 10% 29,542,638 5.5500
Extended Maintenance Cover for 12 months 295,426,384 1.0000
DE-4 (Design Defect Cover ) INR 295,426,384 1.6650
Loss minimisation expenses INR 1,000,000 11.1000
Professional Fees INR 1,000,000 11.1000
Testing Period 1 month INR 295,426,384 11.1000
72 hrs. clause
50:50 Clause
Gross Premium -
GST -
Premium Payable -

Clauses Opted
STFI
EQ
Terrorism
Clearance and Removal of Debris
Third Party Liability including Cross Liability Cover
Owners’ surrounding property with FLEXA risks
Escalation @ 10%
Extended Maintenance Cover for 12 months
DE-4 (Design Defect Cover )
Loss minimisation expenses
Professional Fees
Testing Period 1 months
72 hrs. clause
50:50 Clause
Conditions / Warranties
All other conditions, Endorsements, Exclusions as per CAR Tariff
Subject to declaration of 'No Known or Reported Losses (NKORL)' before binding the risk
Compulsory Excess
Excess (Normal):- 5 % of claim amount subject to Minm of Rs. 1,125,000
AOG/Major Perils/ Collapse: 10 % of claim amount subject to Minm of Rs. 3,750,000
Extended Maintenance Cover: 5 % of claim amount subject to Minm of Rs. 3,750,000
Design Defect Claims:5 times of AOG excess

Claim- Nil

Current Status of the Project-As on date, all components for 04 Nos. Bailey Bridges have reached the site along
with Anchor Bolts.