Beruflich Dokumente
Kultur Dokumente
DECISION
On issuing Vietnam Standard 104: 2007 "Urban Road – Specification for Design"
CONSTRUCTION MINISTER
Pursuant to Decree No. 36/2003/NĐ-CP dated April 4, 2003 of the Government on stipulating
functions, duties, competences and organizing structure of Ministry of Construction;
DECIDES
Article 2. This Decision takes into effects after 15 days since the date of the government
Official Gazette.
Article 3. Chief of Ministry Office, General Director of Science and Technology Dept, and
Heads of relevant agencies take responsibility for the enforcement of this Decision./.
PP. MINISTER
Receivers: VICE MINISTER
- As in Article 3
- The Government Website Signed
- Official Gazette
- Judicary Ministry Nguyen Van Lien
- Ministry of Science & Technology
- Legislation Dept.
- Office Archive, Science & Tech Dept.
1
TCXDVN 104 : :2007
TCXDVN VIETNAM CONSTRUCTION STANDARD
URBAN ROAD
Hanoi – 2007
2
TCXDVN 104 : :2007
PREFACE
TCXDVN 104: 2007 “Urban road-Specifications for Design” is composed to replace TCXD 104: 1983
“Specifications for Urban road, Square”.
TCXDVN 104: 2007 “Urban road – Specifications for Design” is to regulate the specifications for
planning, design, new construction, improvement and upgrading of urban road and enclosed by the
issuing of Decision No.22/2007 /QĐ-BXD dated June 30, 2007.
3
TCXDVN 104 : :2007
1.1. This standard sets out requirements for the planning – design, new construction,
improvement and upgrading of urban road, street.
1.2. In the case of urban road design involving other works such as railway, irrigation work,
water supply and drainage, lighting and ect… the design must be in compliance with the in-force
regulations of the State and integrated with the concerned agencies.
1.3. This standard takes the place of Vietnam Standard 20TCXD 104 – 1983: Specifications for
Urban road, Square
3. General Regulations
3.1. Urban road network must be in line with the approved construction plan of different
infrastructures to avoid wastes of construction and overlapped administration.
3.2. The urban transport system design plan must be placed in the urban spatial comprehension
including center area (inner city) and subregion (suburban, outskirt, satellite urban….); be in line
with the urban road design plan as its right functions and specifications.
3
TCXDVN 104 : :2007
3.3. In addition to complying with the regulations of this standard, the urban road design could
be referred to specifications for highway design, expressway design and other in-force
specifications and guidelines.
3.4. When designing the urban road, investment phasing needs to be considered, and the
phasing alternative is based on the future option. Investment phase could be made for sub-grade,
pavement, drainage, intersection and other traffic facilities on the principle of non-reducing
technical grade, utilizing existing facilities, construction landmark and red landmark management.
The selected alternative will be the one which have higher advantages in the economic and
technical aspects than others.
4. Interpretation of Terms
In this specification for design, the terms are interpreted as follows:
Urban: comprises of city, town and small town authorized to establish by the state agency.
Urban Category: is categorized into 6 classes: special class, Class I, II, III, IV and V.
Urban area: is the territory including the boudary of core-urban, influenced area such as
suburban, outskirt, sattelite urban and ect...
Infrastructure system: includes transport system, communication system, energy supply, public
lighting system, water supply and drainage, waste treatment and other facilities.
Socio-infrastructure system: includes housing works, health-care facilities, cultural and
eductional facilities, sport and trading facilities, public service, gree trees, parks, water surface
and other other facilities.
Construction planning: is the organization of urban space and rural residential areas,
infrastructure system and socio-infrastructure system; to formulate a desirable living-environment
for local people in order to ensure the harmonization between national interest and public interest,
to satisfy the socio-economic development target, national defense, security, environment
protection. The construction planning is shown by the construction planning design including map,
drawing, model and presentation.
Urban Construction Master Plan ( the comprehensive plan on urban construction): is the
organization of urban space, infrastructures and socio-infrastructures, in accordance with the
socio-economic development master plan, setoral plan to ensure national security and defense of
the entire region and the country in each period of time.
The detail urban construction plan: is the specification of the gernal construction plan, as legal
base for the management of construction works, information supply, provision for construction
license, land allocation, land rental to develop the construction projects.
Urban Design: is the specification of the general plan, detail plan on urban construction in terms
of urban architecture, landscape of functional zone, streets and other urban public spaces.
Urban road (or street): is road in urban, including streets, ordinary highways and other dedicated
roads.
Street: is urban road with most of civil works constructed along the roadside.
Highway (in urban): is urban road with none or few of housing along the roadside. Highway is
mainly for transport (expressway, national highway, connective road between factories,
warehouses and terminals....)
Sidewalk: is dedicatedly designed for pedestrian or a part of border line.
4
TCXDVN 104 : :2007
Red Landmark: is the line identified on the planning map and on the field, to define between the
land for construction and the land for traffic or other facilities, public space.
Construction landmark: is the line that limits the construction works.
5
TCXDVN 104 : :2007
Dimension Overhang
WB2
WB3
Type of Design Vehicle
T
Length (L)
Height (h)
Width (w)
Front (f)
Symbol
Rear (r)
Car PCU 1.3 2.1 5.8 0.9 1.5 3.4 7.3
Single bus BUS 4.1 2.6 12.1 2.1 2.4 7.6 12.8
Bus with trailer A-BUS 3.2 2.6 18.3 2.6 2.9 5.5 1.2 6.1 11.6
Truck with one trailer WB-12 4.1 2.6 15.2 1.2 1.8 4.0 8.2 12.2
Truck with 2 trailers WB-35 4.1 2.6 35.9 0.6 0.6 6.7 12.2 0.6 18 13.4 18.3
Note :
- WB1, WB2 is effective distance between the front axle and rear axle.
L
W r WB f
W
h
6
TCXDVN 104 : :2007
5,8
1,5 3,4 0,9
2,1
xe thiÕt kÕ p
12,1 18,3
2,4 7,6 2,1 2,9 5,2 2,1 5,5 2,6
2,6
2,6
xe thiÕt kÕ BUS xe thiÕt kÕ a-BUS
9,1 16,7
1,8 6,1 1,2 0,6 9,1 6,1 0,9
2,6
2,6
xe thiÕt kÕ SU xe thiÕt kÕ WB-15
21
1,5 18,3
0,9 12,8 6,1 1,2
2,6
xe thiÕt kÕ WB-19
22,5
2,6 12,6 6,1
0,9 20,4 1,2
2,6
xe thiÕt kÕ WB-20
35,9
13,4 1,5 12,2 6,7
0,6 34,7 0,6
2,6
xe thiÕt kÕ WB-35
7
TCXDVN 104 : :2007
8
TCXDVN 104 : :2007
traffic possibility. It is able to apply foreign conditions for computing and as in Table 3.
Table 3. Highest numberic values of traffic possibility (Unit: car/h).
Highest numberic value of
Type of urban road Unit
Traffic Possibility
Note:
(*)
: The minimum value is applied when center lane is used to be through lane, left- turn lane, U-turn
lane.; The maximum value is applied when organizing lane offset (1 direction-2lanes, 1direction-1
lane)
Computed Traffic Possibility (Ptt) is the traffic possibility defined under common condition of
designed road. Computed traffic possibility is determined by reducing the highest traffic possibility
according to the Common adjustment coefficient and the unattainable design parameters.
Main concerned parameters are: Width of a lane, level of roadside obstacles, components of the
vehicle flow. Preliminarily, Ptt = (0,7 ÷ 0,9)Pln
Computed Traffic Possibility is used to estimate number of lanes and level of service of designed
urban road.
5.4.2. Level of Service (Abbreviated: MPV).
Level of Service is a measure of the quality of traffic flows, which drivers and passengers is
recognizable.
Level of service is divided into 6 different levels, symbolized as A,B,C,D,E,F. A Level means the
best quality- F Level means the poorest quality. Traffic Possibility Factor is one of the criteria
attached to level of service in one road section. (Refer to Article 5.4.3).
Different levels of service:
- A – Free flow, high speed, using traffic possibility factor Z < 0,35.
- B – Partially free flow, high speed, using Z=0,35÷0,50.
- C – Stable flow, however drivers are influenced if freely selecting expected speed, using
Z=0,50÷0,75.
- D – Initially unstable flow, drivers have few choices of speed selection, using Z=
0,75÷0,90.
- E –Unstable flow, any challenge can cause to congestion, using Z=0,90÷1,00.
- F – Fully unstable flow, vehicle congestion.
When designing, a level of service for a route or a section must be given to operate effectively
and in right function.
5.4.3. Traffic Possiblity Factor (Symbolized: Z)
Traffic Possiblity Factor (Z) is a ratio between design vehicle volume (N) and Computed traffic
possibility (Ptt). Traffic possibility factor is a figure to specify level of service of designed road.
9
TCXDVN 104 : :2007
The higher quality of vehicle flow is, the lower Z factor is. On contrary, if Z increases, the average
speed of vehicle flows decreases and at a certain value, vehicle congestion will occur (Z~1).
Design level of service and Z factor is used in urban road design in Table 7.
6. Urban road classification and hierarchy
Urban road is classified and hierarchized by purpose
6.1. Urban road classification by function
Classification by function is a basic framework and a tool for urban construction plan. Urban road
is classified by 2 funtions: traffic function and spatial function.
6.1.1. Traffic function is performed by traffic quality and traffic indicators such as speed, density
and factor of traffic possibility. The traffic funtion is shown by two contrary sub-functions: mobility
and accessibility.
- High mobility of road requires high speed of vehicles. This is for superior road with high
traffic volume, a vast length and low traffic density.
- High accessibility of road requires no high speed of vehicles but this kind of road must be
advantageous to accessibility (Origin – Destination).
According to the traffic function, urban road is divided into 4 types with specifications as can be
seen from Table 4.
10
TCXDVN 104 : :2007
Table 4. Urban road Classification
Trafic nature Prioritirized
No Function Urban road (*) Vehicle flow Proposed volume branch to
Type Nature of flow Speed
component (**) residental area
1 Urban expressway High mobility traffic
To serve express and constant traffic. To satisfy high traffic
volume and traffic possibility. To provide the connectivity Expressway All cars and 50000
Uninterrupted, High and super
between big cities, urban centers and industrial centers, Main urban street motocycles - Unallowed
no interchange high
ports, terminals, satellite urban and so on. Transport road (limited) 70000
To serve regional traffic as in bid residential areas and district Main urban road 10000
a-Regional road areas Access urban road Moderate All vehicles - Allowed
Internal road 20000
To be collector road for cargo transport in concentrated Expressway
b-Transport road industrial zones, providing connectivity to ports, stations and Main urban road Access urban Discontinued Truck and
Moderate - Unallowed
trunk lines. road traffic bus only
To be road of large scope, functioning traffic and spatial Main urban road All vehicles
Low and
c-Avenue balance but satisfying spatial function at high level. Access urban road (except - Allowed
moderate
Internal road truck)
4 Internal road High accessibility traffic
To be connectivity in precincts, residential areas, industrial Access urban road Car, 2 wheel
Low Low
a-Internal road zones, public facilities or trading facilities… Internal road Interrupted car
b-Sidewalk To be dedicated roads providing connectivity in internal Internal road traffic - Pedestrian - Priortirized
c-Road for bicycle quarters, roads parallel to main street and access road Low Bike -
Note: (*): Urban road connectivity relation in Figure 2.
(**): Values of traffic volume are references only. Unit: vehicle/day.night per automobile
11
TCXDVN 104 : :2007
Urban cao
®−êng expressway
tèc ®« thÞ Access
®−êng road
phè gom Interchange
nót giao th«ng kh¸c møc
®−êng
Main phè chÝnh ®« thÞ ®−êng phè néi bé kh¸c møc kh«ng liªn th«ng
urban street Internal Road Grade-Unseparated
Hình 2. Road network map by function
6.1.2. Urban ring roads are classified into urban expressway and main urban street
6.1.3. Spatial function of road is illustrated by scope of width of landmark. In this scope, each part of
cross section clearly shows its spatial function
such as landscape architecture, environment, allocation of ground and underground facilities....
6.1.4. In the urban road network plan, road density by type could be reviewed through road length
by type, and shares of road by type are as follows:
Table 5. Road length by function and traffic volume
%
Road system by function
Traffic volume Road length
Primary urban road system 40 - 65 5 - 10
Main urban road system 65 - 80 15 - 25
(Primary and secondary)
Access road system 5 -10 5 - 10
Internal road system 10 - 30 65 - 80
6.2. Technical Classification of Urban Road.
6.2.1. Urban roads are categorized into technical classes matching to given indicators. Technical
class is named after speed design 20, 40, 60….(km/h) and used for street design.
6.2.2. Technical classification is defined by function of urban road, construction condition,
alignment condition, urban classification. Reffer to Table 6
12
TCXDVN 104 : :2007
Table 6. Selection of technical class by road type, urban type, topographical condition and
construction condition
Urban Category Special urban, Class II, III Class IV Class V
Class I
Topography (*) Plain Mountain Plain Mountain Plain Mountain Plain Mountain
Urban 100, 80 70, 60 - - - - - -
expressway
Main Primary 80,70 70,60 80,70 70,60 - - - -
urban Secondary 70,60 60,50 70,60 60,50 70,60 60,50 - -
road
Access urban 60,50 50,40 60,50 50,40 60,50 50,40 60,50 50,40
road
Internal road 40,30,20 30,20 40,30,20 30,20 40,30,20 30,20 40,30,20 30,20
Remark:
1. Selection of urban road class is in line with road design duration but it must be attached to the
long term urban development plan (30-40years)
2. High value is applied to construction condition- Class I,II; low value is applied to construction
condition-Class II, III (**).
3. As for internal road, it must be from lower to higher speed
4. Road for bicycle is designated at 20km/h or higher if highway is planed to improve.
Note:
(*)
: Topographical condition is classified by horinzontal gradient (i), specify:
- Plain i≤10%.
- Moutainous i>30%
- Hilly:
Slope hill (i=10-20%) applied by plain topography,
High hill (i=20-30%) applied by moutainous topograhy
(**)
: Classification of construction condition
- Class I: less influenced by ground clearance problem, houses and other sentitive issues.
- Class II:An intermediate between Class I and III..
- Class III: facing difficulties in terms of ground clearance, housing and other sentitive issue.
6.2.3. Urban road design and planning by function must be sticked to levels and factor of traffic
possibility as in Table 7.
13
TCXDVN 104 : :2007
Table 7. Level and Traffic Possibility Factor of Designed Urban Road
Technical class Design Speed Factor of Traffic
Type of road Level
(km/h) Posibility
100 100 0.6-0.7
Urban expressway 80 80 C 0,7-0,8
70 70 0,7-0,8
80 80 0,7-0,8
70 70 0,7-0,8
Main urban road C
60 60 0,8
50 50 0,8
60 60 0,8
Access road 50 50 D 0,8-0,9
40 40 0,8-0,9
40 40 D 0,8-0,9
Internal road 30 30 0,9
E
20 20 0,9
6.2.4. Urban road sections must be in the same class in the same minium length. At class of 60 up
to, the minium length is 1km. The design speed difference of continuous sections in the same route
must be less than 10km/h.
6.2.5. Distance between intersections is short and visibility is limited. Therefore, the selection of
relevant design speed is to avoid wastes and non-standardized technical criteria, particularly sight-
distance.
14
TCXDVN 104 : :2007
Table 8 Control of Access by Road Type
Urban road by type
Design
Technical Access
Speed Urban Main urban Internal
class urban
(km/h) Expressway road road
road
100 100 FC - - -
80 80 FC FC, PC - -
70 70 FC, PC PC - -
60 60 - PC PC -
50 50 - PC NC -
40 40 - - NC NC
30 30 - - - NC
20 20 - - - NC
Note:
- FC = Full Control of Access
- PC = Partial Control of Access
- NC = No Control of Access
6.4.5. Other cases, not under Article 6.4.2, 6.4.3, considered as no control of access.
6.4.6. The land-use planning must comply with the principle of road connectivity and control of
access
15
TCXDVN 104 : :2007
1A. kiÓm so¸t nghiªm ngÆt lèi ra vμo.
1B. kiÓm so¸t nghiªm ngÆt lèi ra vμo, cã sö dông ®−êng song song
3 2
2. kiÓm so¸t mét phÇn lèi ra vμo, cã sö dông ph©n c¸ch ngoμi
4 4
3A. kh«ng kiÓm so¸t lèi ra vμo, giao c¾t kh¸c møc t¹i mét sè nót giao chÝnh
4
16
TCXDVN 104 : :2007
7. Square
Square, a large area of land with opening space, an outstanding point of the urban while combing
between architecture works and transport system; surrounded by large streets and large-scale
construction works with different functions. Traffic speed in square area is not so high.
17
TCXDVN 104 : :2007
advised to organize the traffic flows in one direction and rotation. Islands are only advised to use
with marking and only when necessary, channelization by fencing or mobile seaparator will be
applied.
8. Cross section
In which: n is a number of lanes (including separated or non-separate lane for motorised and non-
motorised vehicles)
bi is the width of lane no.i
Note : - If non-separated lane, all vehicles are converted to car : B=n.b
-If separated lane, carriageway is organized into dedicated lanes, carriageway is a set of
accommodation lanes.
8.2.2. Number of lanes
Number of lanes on the cross-section is integral, number of lane is determined by type of planned
N yc
road and use the formula as follow: nlx = to calculate the construction phase and check traffic
Z .Ptt
possibility.
In which :
- nlx : required lanes
- Nyc : designed volumen of vehicle by hour in accounted year according to the article 5.2.3
- Z : Traffic posibility factor, Article 6.2.3
- Ptt : Calculated traffic posibility of one lane (vehicle/h, PCU/h) in article 5.4.1
Note:
- Z.Ptt : service volume : means vehicle volume matching with given level of service while
designing.
18
TCXDVN 104 : :2007
- As for accommodation lanes, for example lane for bus, vehicle volume and traffic possibility
are indentified by bus.
8.2.3. A lane width ( see Table 10)
In urban, width of lane varies from 2.75 to 3.75m, 0.25m is multiple relating to type of road, speed
design and traffic organization using carriageway.
Table 10. Lane width, and a minimum number of lane
8.2.5. Crossfall
Pavement’s Crossfall with two-side sloping is needed in the cases:
19
TCXDVN 104 : :2007
- Both direction road, without separator, 2 lanes up to, the highest point is in the centre of
carriageway.
- On-way road, 4 lanes up to, the highest point is in the centre of carriageway or border point of
lanes upon lane-using traffic organization design.
- Road with wide separator, 4 lanes up to for each direction, the highest point is in the centre of or
carriageway or border point of lanes upon lane-using traffic organization design.
- Other cases, cross slope (single pitch) will be used
Table 12. Crossfall of carriageway
8.3. Shoulder
8.3.1. Function
Shoulder is structured border with carriageway to protect pavement structure, improve sight
distance, intensify traffic possibility, safety, drainage, emergency parking strip and place materials
when maintaining…
8.3.2. Structure.
Width of shoulder must function as its design, Table 13 definesthe minimum width of shoulder, from
margin of carriageway to margin of curb.
Minimum width of shoulder must include safe line (speed >= 40km/h) and side ditch (if any).
Safe line is a narrow line , close to the margin of carriageway to protect pavement, safety guide (see
8.4.1). Shoulder close to carriageway is marked by paint according to “ road signal regulations
22TCN-273”.
Table 13. Minimum width of Shoulder and safe line, m
8.3.3. Structure and slope of shoulder are designed the same as those of carriageway. As for other
roads, present road specification for design of transport sector will be applied.
20
TCXDVN 104 : :2007
8.4. Separation section
8.4.1. Function and clasification
Separation section includes:
- Median separation section: to separate reverse traffic directions
- Side separation section: to separate high speed freeway from local traffic, motorized from non-
motorized vehicles, and accommodation vehicles from others.
Separation section could include (figure 4): separator and safety line. Safe line is formed if design
speed ≥50km/h, according to the requirements in article 8.3.2.
PhÇn xe ch¹y
Carriageway PhÇn ph©n
Separation c¸ch
section PhÇn xe ch¹y
Carriageway
D¶i
D¶i an
Safe toμn
line Separator Safe
D¶i line
an toμn
ph©n c¸ch
21
TCXDVN 104 : :2007
Table 14. Minimum width and type of separator
Internal street - - - -
Note:
Note:
1. Specifications for the boulevard’s separator are also applied to main urban road but it is
impossible to use simple separator.
2. ( ) is the expected minimum value which can meet any functions (such as scenery structure,
land reservation, and street traffic…)
3. Side separator can be applied by width numeric data at low level in construction condition III.
Note :
1. Classification of construction condition in section 6.2
2.Types of separator in figure 5.
22
TCXDVN 104 : :2007
a) Ph©n c¸ch ®¬n gi¶n
phÇn ph©n c¸ch
w
v¹ch s¬n
lo¹i a lo¹i b
d¶i ph©n c¸ch bo bã vØa vμ ®−îc phñ mÆt d¶i ph©n c¸ch bo bã vØa vμ trång c©y, th¶m cá, thu n−íc 2 bªn
lo¹i c
d¶i ph©n c¸ch bo bã vØa vμ trång c©y, th¶m cá, thu n−íc ë gi÷a
lo¹i d d¶i ph©n c¸ch phñ mÆt ngang b»ng kÕt hîp víi barie phßng hé.
lo¹i e d¶i ph©n c¸ch phñ mÆt ngang - h¹ thÊp thu n−íc, trång c©y th¶m cá
Note:
1. When 2 side separator is designed in special cases, it is necessary to avoid being
misunderstood by drivers that each side is separate side.
2. The minimum width of paint line seperator is 0.5m.
Figure 5. Types of separator.
I II III
Urban expressway - - -
Note:
1. Requirement about boulevard border area is applied as main urban roads.
2. Width in the table is applied for ordinary roads. In urban area, commercial streets,
sidewalk must be wider, convenient and better scenery.
3. Classification of construction condition in section 6.2
8.5.3. As for border area sections used for expansion (bus stop, bus parking…), border area width
must be wider than 2m.
8.6. Sidewalk
8.6.1. Sidewalk is for pedestrians. Sidewalk is an indispensable part on the urban road layout.
In some cases, sidewalk is separated from border area such as: parallel to carriageway or
sidewalks in residential and commercial areas, parks, path along rivers and lakes, woods, cultural-
historical structures...Sidewalk with two lines of tree are so-called avenue. Sidewalk is geometrically
structured the same as carriageway.
8.6.2. In residential, industrial, culture-sport areas , it is necessary to arrange specific sidewalk; as
for main urban roads, regid separator is needed to separate continuous traffic and local traffic,
sidewalk should be placed close to the lane for local traffic or separated from express traffic by
buffer line (range of trees or barrier...).
8.6.3. Sidewalk must be covered by rigid materials or designed for convinience and better
drainage.
8.6.4. Sidewalk width is defined as pedestrianized traffic.
Formula: Bwalking = nwalking . bwalking
In which:
24
TCXDVN 104 : :2007
N tk
- Number of walker lane: ndibo =
Ptk
- Ptt: one walker lane’s continuous capacity (people/lane.hour).
- b: one walker lane’s width, normally b = 0,75 – 0,8m (1 suitcase in hand); at railway station,
b = 1 – 1,2m (2 suitcases in hand).
8.6.5. Sidewalk slope:
- Advised to be less than 40%, with slope length less than 200m.
- If slope length, longitudinal grade are larger than the above-mentioned, a terrace road is
needed. It at least must have 3 steps, shorter than 15cm and wider than 40cm for each, and
the longitudinal grade must be less than. Every 10-15 steps , there must have a rested mat,
wider than 2m. In such sections, sidewalk for chilren and disables must be designed
separately.
- Facility ultilisation (up –down way...) should be installed for elders, disables and sightless.
8.6.6. Cross slope of sidewalk can be from 1% - 3%, depending on width and sidewalk materials.
8.7. Tree belt
8.7.1. Tree belt can be placed on the pavement, separator or tree land on the both side. Tree belt
normally includes others facilities (electric post, transformer post, signals system and underground
work…). The allocation of these facilities is not allowed to make negative influences on the vehicle
and pedestrian traffic.
8.7.2. Width of tree belt
Width of tree belt on the cross section are applied as in Table 16
Table 16. Width of tree belt
2,0
Shade tree: in 1 line.
5,0
Shade tree: in 2 lines.
1,0
Shrup plot, grassplot.
2,0
Orchard in front of 1 floor building.
6,0
Orchard in front of more than 2 floor building.
Note:
1. If we do not use all spit to plant tree, we can plant tree in area which have different size and form. It
is also applied to sections which have specific structure.
2. We should plant continuous planted spit in full control of access and partial control of access.
8.7.3. The distance from tree belt to other structures can be referred in table 17.
25
TCXDVN 104 : :2007
Table 17. The minimum distance from tree belt to other structures
8.7.4. The distance between trees is identified by type of tree or specific position on roads. Note
that trees should be planted in front of barred wall between 2 houses, not placing in the center or
straight of the house gate in which street width is < 5m.
8.7.5. Refer to section 17.1 for regulations on green trees
8.8. Curb.
8.8.1. Curb is used to transit elevation of road parts. Curb is installed in the outer of pavement,
separator and traffic island…
8.8.2. Curb, with traffic function, is divided into 3 types:
- Type 1: impassable for vehicles: straight surface and high.
- Type 2: intermediary: slight slope and passable for vehicles when necessary.
- Type 3: passable and sloping, easy for vehicles to pass.
Curb is structured by different types can be combined with drainage ditch to the local, sectoral
specification, but it needs an agreed model for a route.
Materials to make curbs are concrete cement or high compacted stone (250daN/cm2)
8.8.3. The elevation of top curb of pavement, traffic island must be at least 12.5m higher than the
shoulder, if separator, it must be 30cm.
8.8.4. At feeder roads to office buildings, residential houses where motorized vehicles are < 10
vehicles/h, or temporary parking place, cars are =< 25, it is not allowed to expanded to roadbed as
intersection design, only enable to partially reduce the pavement elevation. In this case, structures
must be desirable both pedestrians and vehicles.
8.9. Bicycle track
8.9.1. General regulation
Traffic organization of Bicycle (and other non-motorized vehicles if allowed by the urban
management agencies) can be as follows:
26
TCXDVN 104 : :2007
a). Using the carriageway of the furthest lane (on the right side) with motorize vehicles. This method
is only applied for low-level road or lane for local traffic.
b). Using apart of pavement or shoulder create lanes for bicycle by road marking. This method is
possibly applied to urban roads by all types, except urban road with speed >= 70 km/h.
c). Separate bicycle track from carriageway and shoulder; some protective solutions: different
elevation, barrier, tree belt…
d). Track for bicycle is an independent and accommodate lane.
Note:
- Case 1, 2 is Bicycle Path
- Case 3, 4 is Bicycle Track
8.9.2. Width of Bicycle track
Number of bycicle lanes in one direction is defined as formula:
N
n= , lane.
P
In which: N is number of bicycles in peak hour (unit/ h)
P is number of bicycles in one lane, it may be 1500vehicles/hour. lane.
With of Bicycle track in one direction is:
B = 1,0 x n + 0,5 , m.
For bicycle track design, minimum width should be 3.0m, to enable cars to enter if necessary or it
will be more economic when reorganizing traffic.
8.9.3. Specification for design of bicycle track
- Geometric design for bicycles is required flat, cross sloping, super-elevation equivalent to the
car lane (as for bicycle path) and other technical figures is similar to urban roads-20km/h (as
for bicycle track).
- Pavement structure is designed for small cars and service cars when necessary.
8.10. Crosswalk
8.10.1. Cross the urban road
Crosswalk is formed by 3 types: At grade , grade-separated ( overpass or undergound). It depends
on numbers of walkers, design speed – traffic volume on road, control of access, traffic possibility,
intersection and other conditions such as schools, offices, trading centers, cultural areas......... To
select relevant crosswalk, refer to Table 18.
27
TCXDVN 104 : :2007
Table 18. Selection of crosswalk by traffic volume
Traffic volume
Number of walkers at
(one direction) at rush- Forms
rush- hour, people/h
hour, PCU/h
<50 <1000 At-grade crosswalk
50-100 100 – 2000 At-grade crosswalk with traffic color
>100 >2000 Grade separated
8.11. Clearance
8.11.1. Clearance is defined as a safe distance as for above-mentioned space. In the clearance
areas, no obstacles, even road facilities such as signals, lighting poles, ect is allowed to be placed.
8.11.2. The minimum clearance is 4.75m from the highest part of carriageway, excluding space
reservation for enhancing roadbed and special cases. In the case that tunnel crosswalk has
limitations, the clearance numeric value applied to improved road or internal road can be 4.50m.
8.11.3. If Bicycle traffic (or crosswalk) is separated from the carriageway, the minimum clearance of
bicycle track and crosswalk are 2.5m in height and 1.5m in width.
9. Sight Distance
9.1. General Regulations
9.1.1. Sight distance is one of the important elements to help drivers have safe operation
corresponding to determined design speed.
9.1.2. In the field of vision, sight distance must be unhidden (removing obstacles …). Only in
advantageous case, traffic organization solutions (speed restriction, instruction sign, marking or
overtaking restriction….) will be applied. Sight distance at intersections and small radii curvature
must be examined. Obstacles must be removed under 0.30 m for driver’s sight distance.
9.1.3. When estimating the length of sight distance and the field of vision, the height of driver’s
sight is 1.20m from the carriageway’s surface, 1.5m from the margin of the right-side carriageway.
Stipulations on challenging object: if it is inactive object, the elevation will be 0.01m from the surface,
if it is opposing vehicle, the elevation will be 1.20m from the surface.
9.2. Regulations on Minimum Sight Distance
Minimum values of stopping sight distance, opposing sight-distance and overtaking sight-distance
are stipulated in Table 19.
Table 19.Minimum Sight Distance (m)
Design Speed Minimum stopping-sight Minimum Opposing Minimum overtaking
(km/h) distance sight-distance sight-distance
100 150 - -
80 100 200 550
70 85 175 450
60 75 150 350
50 55 115 275
40 40 80 200
30 30 60 150
20 20 20 100
10. Horizontal alignment
10.1. General regulations
28
TCXDVN 104 : :2007
10.1.1. Major regulations on horizontal alignment design:
a) To follow the approved urban planning, especially master plan on the urban transportation
network system.
b) To consider all components and construction of road when planning and designing such as:
auxiliary lane, crossing structure, separator openness… to ensure construction landmark, redline
landmark of long-term planning.
c) To ensure the outer line to be designed and combined harmoniously: with terrain, geography,
urban scenery architecture, simultaneously ensures interior line combination design: combine
among horizontal alignment, cross section, longitudinal section.
d) Control points must be considered when designing alignment: crossing, railway crossing, big
bridge position…, suggested and compulsory point to avoid: cultural and historical monument,
crowded residential zone, important works…
e) To have the urban road route position projects on horizontal alignment: elevation or low, large or
small scale…to compare technology economy and other targets. Selected project must meet
technology, economy and traffic, architecture functions and urban planning management.
g) When urban road planning and design encounter disadvantageous construction conditions, there
should have a solution attached to the selection of traffic organization model of designed roads and
the consideration on related areas to ensure a smooth traffic system operation as usual.
10.1.2. Urban road alignment includes: common route alignment (specify: position, elevation,
dimension…); intersection alignment (designed to be a separated item, in the case that it is a low
classified road or simple intersection, a separated design is unnecessary).
10.2. Tangent
The length of the tangent is based on the planning roadmap, features of urban area, distance to
urban centers and road density. Minimum distance must secure vehicle technical operation on that
section. In addition, it must have a strict control on the connectivity principle as mentioned in Article
6 of this standard
10.3. Curve (Horizontal Curve)
10.3.1. It is advised to select the curves close to terrain, construction condition to reduce land
acquisition but still ensuring technical criteria. It is encouraged to utilize the minimum radius of
horizontal curve
10.3.2. With the angle less than 0030’, it is not necessary to place horizontal curves. Where radius of
horizontal curve is small and large turning angle, it should be planed to be an intersection.
10.3.3. Specifications for circular curves are given in Table 20.
Table 20. Specifications for Horizontal Curve
- No need superelevation, m 4000 2500 2000 1500 1000 600 350 250
29
TCXDVN 104 : :2007
7.0m 6.5m 6.0m
Radius Design Speed Design Speed (km/h) Design Speed
(m) 50 60 70 80 90 100 50 60 70 80 90 100 50 60 70 80 90 100
1500 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.2 0.3 0.3 0.4 0.3 0.4 0.4 0.4 0.4 0.5
1000 0.0 0.0 0.1 0.1 0.1 0.1 0.3 0.3 0.3 0.4 0.4 0.4 0.4 0.4 0.4 0.5 0.5 0.5
750 0.0 0.0 0.1 0.1 0.1 0.2 0.3 0.3 0.3 0.4 0.5 0.5 0.6 0.6 0.7 0.7 0.7 0.8
500 0.2 0.3 0.3 0.4 0.4 0.5 0.5 0.6 0.6 0.7 0.7 0.8 0.8 0.9 0.9 1.0 1.0 1.1
400 0.3 0.3 0.4 0.4 0.4 0.5 0.6 0.6 0.7 0.7 0.8 0.8 0.9 0.9 1.0 1.0 1.1 1.1
300 0.3 0.4 0.4 0.5 0.5 0.6 0.7 0.7 0.8 0.8 0.9 1.0 1.0 1.1 1.1
250 0.4 0.5 0.5 0.6 0.7 0.8 0.8 0.9 1.0 1.1 1.1 1.2
200 0.6 0.7 0.6 0.9 1.0 1.1 1.2 1.3 1.3 1.4
150 0.7 0.8 1.0 1.1 1.3 1.4
Note:
- Values are used below the deep outline in Table. Values are less than 0.6m can be omitted.
- 3-lane road multiplied by 1.5.
- 4-lane road multiplied by 2.0.
- If volume of semi-trailer truck is high (WB15), values in Table 21 will be multiplied by 0.2 as
for the curve with radius from 110 – 175 m and 0.3 as for the curve with radius less than
110m.
10.4.2. Widening part is apart of carriageway and it is placed at the sage of curve. When necessary,
it will be placed on crest or both sides. Widening section is placed along superelevation-runoffs. Full
widening is structured in the area of curve.
10.4.3. Without transition curve and super elevation runoff, widening section is placed as follows:
- Length of widened tapering section has scale of 1:10 – 1:20 depending on construction
conditions and tapering by the fist rule.
- Length of widening section is a half on the curve and a half on the tangent. Super elevation –
Superelevation Run-off – Transition Curve
10.4.4. Superelevation is one-side crossfall of traveled way grading toward the sag dise of the
curve. When traveled way is separated by separator or pavement, superelevation is designed for
separated parts.
10.4.5. Superelevation of shouder and safe line (edge line) is structured the same as of
carriageway.
10.4.6. If design speed of urban road is ≥60km/h, there must have superelevations placed
coincidently with transition curves. Without transition curve, the superevelavtion run-off will be half
on the curve and half on the tangent.
30
TCXDVN 104 : :2007
10.4.7. On the superelevation run-off, superelevation shall be done by revoling the carriageway on
the crest side of the curve about centerline profile to the cross slope of carriageway, and then
continue revolving about the centerline profile to the full rate of superelevation. In case of divided
highway, superelevation is attained by revolving about the inside and outside edges of pavement.
10.4.8. Transition curve is normally a clothoid curvature, third-degree parabolic curvature or
compound circular curves (difference of continuous radii is not bigger than 2 times).
10.4.9. Superelevation rate and tangent runout (maximum value of tangent runout (if available) and
length of transition curve (if avaible)) depend on design speed and horizontal curve as stipulated in
Table 22.
31
TCXDVN 104 : :2007
Table 22. Superelevation (isc) and Length of tagent runout (L)
32
TCXDVN 104 : :2007
side rail (bordering with highway traffic).
11.1.2. Design elevation of red line must comply with controlled elevation:
- Elevation was identified in the general urban construction plan, the detail urban construction
plan approved by the competence agency.
- Clearance controlled elevation or underground works.
- Other requirements on economic and technical aspect, urban landscape and architecture and
urban and relevant request of urban management agency….
11.2. Longitudinal grade
11.2.1. Maximum longitudinal grade
Maximum longitudinal grade is reviewed basing on design speed, type of road, vehicle components
and traffic volume. Maximum longitudinal grade with different design speed could be referred from
Table 24.
Table 24. Maximum longitudinal slope
Maximum longitudinal
4 5 5 6 6 7 8 9
slope, %
Refer to the followings for the selection:
- On residential road or various bicylcle road, maximum longitudinal grade is 4%
- On gradient of 3% or less than, car will be affected to a very small degree and truck is only
influenced onlong grades.
- On gradient of 5% or more than, in general it causes fewer difficulties to the operation
effectiveness of car, but trucks will experience significant loss of speed and may have
difficulty when roadways are wet, consequently the traffic possibility will also be affected.
- If the bus is the traffic dominant, it needs analysis and Table 24 should be utilized relevantly
for economic-technical aspect and traffic safety.
- If it is devided road or devided pavement, independent profile for each roadway, the
maximum values for downgrades can be exceed by up to 2% more than imax. In mountainous
terrain, the maximum values for grades can be increased by 2% but are never to exceed
10%.
- If it is urban railroad crossing, the longitudinal grade must be less than 4%, in the railway
right of way, the maximum longitudinal grade must be less than 2.5% (excluding gap
between two rails).
11.2.2. Minimum grade
Standard minimum grades for urban road are given in Table 25.
Table 25 Minimum Grades
Grades, ‰
Design elements
Desirable minimum Minimum grade
On roadways with curbs, drainage is generally adjacent to the curb and parallel to road grades. In
special cases hydraulic analysis shall be made to determine where water might spead onto adjacent
travel lane.
In plain terrain, if minimum pavement’s grade can not desire, it needs to design saw-tooth shaped
33
TCXDVN 104 : :2007
grade along the gutter basing on the planning drawing on urban height by constantly varying the
gutter grades and pavement crossfall within 1-1.5m from the gutter edge.
11.2.3. Length of grade changing
In urban area, there shoud have a close coordination between grades, length of grade changing and
drainage (position of inlet well).
a) Length of longitudinal grades can not exceed stipulated length in table 26.
Bảng 26. Maximum length of grade section
11.2.4. On the curve radius of 50m or less than, the maximum grade must reduced as shown in
Table 28.
Table 28. Reduction on maximum grade
34
TCXDVN 104 : :2007
Tabel 29. Minimum Radius and Length of Vertical Curvature
Standardized Minimum Desirable Minimum Standard minimum
Design Speed
Type of Curve Radius of Vertical Radius of Vertical length of Vertical Curve
km/h
Curve (mm) Curve (mm) (m)
Convex 6500 10000 85
100
Concave 3000 4500
Convex 3000 4500 70
80
Concave 2000 3000
Convex 2000 3000 60
70
Concave 1500 2000
Convex 1400 2000 50
60
Concave 1000 1500
Convex 800 1200 40
50
Concave 700 1000
Convex 450 700 35
40
Concave 450 700
Convex 250 400 25
30
Concave 250 400
Convex 100 200 20
20
Concave 100 200
35
TCXDVN 104 : :2007
12. Intersection
12.1. General
12.1.1. The intersection design aims at solving traffic conflicts to get the followings:
- Level of intersection traffic possibility at given level of service.
- The highest safety level by reducing conflict points and level of conflicts, controlling speed…
- Socio-economic effectiveness
- Ensure environment and scenery.
12.1.2. Intersection planning and design must comply with the current standards related to 22TCN
273 – 01. In this standard, only some basic contents of intersection are mentioned.
12.1.3. General Provisions
a) Elements should be counted in the planning and design as follows:
- Traffic elements: including specifications at intersection: traffic volume, present and future
vehicle flow, design speed, traffic control and organization, traffic possibility…
- Geometric elements (physical): including functional access road to intersection,
specifications, design of lanes, geometric formation, slection of intersection model, land-use
planning…
- Economic elements: including land-use cost, construction cost, operation cost, construction
phasing…Estimation on economic targets and interests.
- Social and human element: including convinience for drivers and traffic participants such as:
clear instruction of direction, satisfying expected values, benefiting pedestrians and disables;
harmonizing to area landscape and facililties.
b) Intersection planning and design must be in line with the land-use planning and urban
construction plan. The intersection planning and design is at the same time with the planning
formulation and the road design. The duration for traffic organization and traffic revision under
operation is 3 years or 5 years.
c) Intersection legs contrary to the planning principle are not allowed to open. The existing
intersection legs contrary to the planning principle need to be redesigned and reorganized too
ensure traffic safety at intersection and reduce the traffic obstacles in the main way.
d) The planning and geometric design of intersections must be in line with traffic organization design
not only within scope of intersection but also needs considerations on traffic organization in directly-
related intersections and sections.
e) The planning and geometric design of intersections must be in line with the planning of drainage,
lighting, and santination environment. A need is to design and plan intersection height to create the
traffic convenient at maximum level, surface drainage and urban structure.
Each of the following traffic controls and organizations must be sticked to the intersection design-
planning alternative and the intersection traffic possibility calculating method.
- Intersection non-control: there is no equipment, instruction (marking, sign, and color) at
intersection.
- Sign, stop-marking control at intersection (*)
- Island roundabout traffic control: is the way that an island will be placed in the center of
intersection to instruct vehicles roundabout the island in the anticlockwise direction. (**)
36
TCXDVN 104 : :2007
- Color traffic control at intersection.
Note:
(*)
: Traffic is controlled by combining between markings, danger sign, and restricted sign.
(**)
: Central island is diversified by many types, but 2 main types: island roundabout traffic control or
priority traffic control at the entrance of intersection.
12.3. Intersection by design
It is divided in to 6 intersections as follows:
12.3.1. Simple intersection: is an intersection with the same width of intersection legs, tapering the
crossing angle by simple curvatures. Such intersection is advised to use for sections with low vehicle
flow and limited land acquisition; low volume of right-turn or left-turn vehicles, same level of feeders
and low speed.
12.3.2. Open Throat Intersection: is an intersection at which carriageway is expanded by various
forms such as: widening carriageway in the curvature, arrage the auxialary lanes to accelerate of
reduce speed at the intersection access to serve right-turn vehicles or left-turn vehicles with
separated lane, waiting lane. Expanded lane and its design depend on using-purpose, demand and
layout.
12.3.3. Channellized intersection: is an intersection in which vehicle flows are divided to use
separated chanel and lane. While division, island is used to hide empty space on the road. Island is
structured by its functions, vehicle flow orbit, including Triangle Island, Central Island and ect…
12.3.4. Rotary intersection: is an intersection with a central island or additional lane-separated
islands at the merge. The central island differs from lane-separated islands in shape and size so that
traffic organization and control are also different. That could be considered as chanellized
intersection
12.3.5. Signalized Intersection: is an intersection to settle fully or partially conflict by orgainzing
signals controlled by time.
12.3.6. Interchange: is to handle traffic conflicts by using separated elevations such as: viaduct,
overpass or tunnel (*)
Note:
(*)
: 2 main types:
- Interchange is grade-separated intersection with assigned legs for vehicle to change the
direction
- Direct interchange (Grade-separation) is an interchange without transitted legs.
12.4. Intersection in the urban road network
12.4.1. Urban roads in at-graded intersection
- Urban roads should be crossed at the angle of 90% and try to avoid the angle of 600, if the
angle of 600, it is advised to improve the alignment for better cross-angle.
- On the plan, it should be a straight alignment at intersection, limiting intersections on the
horizontal curvature, particularly curvature with radii smaller than the ordinary minimum
numeric value of corresponding road class.
- At-graded intersections should be placed in advantageous locations for transport and
drainage such as flat areas or gently sloping areas
12.4.2. Distance between intersections
- Large distance between intersections makes convenient operation of vehicles.
- Minimum distance must be higher than the following numeric values (if designed):
37
TCXDVN 104 : :2007
o Length of weaving section
o Length of vehicle line in front of intersection
o Length of right - turn lane, acceleration and decelaration lane
o Visual limitation of drivers.
Note:
1) In the above table, signs indicate as follows
a - At-grade intersection
b- grade-separated intersections
c- Grade-separated intersection with access relation control
d- Grade-separated intersection without relation (no turning movement).
e- Following problems normally occur upon using at-grade intersection, intersection with signals
or grade-separated intersections:
+ Slower traffic
+ Greater number of serious accidents.
+ Construction cost for at-grade intersection is higher than that for grade-separated
intersection.
f) Connection is allowed only in special cases. In such cases, arrange entering volume with
acceleration and deceleration lanes, not causing cutting conflicts with main movement.
g) Simple and expanded at-grade intersections can only use signals when justified.
2) It needs to consider building grade-separated intersections if topographical condition is
favorable and in line with approved general plan of the road
12.5.2. Engineering and planning concept is subject to traffic system and future road network plan
approved. Initial intersection option should be based on complete future engineering plan so as to
take use of existing facilities and facilitate management of land use for construction, enforcement of
road development policies without breaking principles provided in Article 12.1.2 and 12.5.1.
38
TCXDVN 104 : :2007
12.7. At-grade intersection
12.7.1. Designed speed
Designed speed for the road section in the intersection (VTK) is taken from designed speed of the
road section outside the corresponding intersection. This speed is used for measuring visibility,
vertical slope, and width of roadway. In some special cases, the intersection located in curving
section or with traffic island or combined type, it is recommended to use designed capacity ≤ (0.6 ÷
0.7) comparing to designed capacity of the section outside the intersection.
Designed speed for turning directions (left and right) is selected by taking into account: construction
condition, existing and operational conditions of the intersection in use, traffic, etc. In all cases, it is
not recommended to take more than 0.7 of designed speed of the road section outside the
intersection and not smaller than 15km/h to secure general movement of the whole intersection.
12.7.2. Curving radius
For the sake of traffic safety for intersections from hamlets to road and streets, local road should
have designed capacity of 20km/h with curving radius not big. I is possible to make the curve have
radius of 3-10m or equaling width of the pavement.
Main urban road, turning radius identified by designed turning speed.
In remaining cases (local urban roads with V> 20km/h), minimum curving radius is 7.5 m. For
dedicated roads where vehicles are not conventional cars, it is needed to review section 5.1 to
decide design specifications which are subject to bigger than specification of the minimum turning
radius.
12.7.3. Internal visibility
Plan and design of an intersection should secure visibility for drivers to respond safely to situations.
The most basic drawing for identification of visibility, right of way from a corner of the intersection is
the drawing for one-way visibility from two lanes (see Figure 9)
VËt c¶n
tÇm nh×n
db
Vb
Tia
nh
×n
Va
®−êng phè da
®−êng phè
tr−êng nh×n
i
h¶
Ïp
nr
¹
®o
¶i
ph
rÏ
¹n
d¹ng song song
®o
lμn gi¶m tèc
lμn rÏ ph¶i cã ®o¹n chuyÓn tèc lμn rÏ ph¶i cã ®o¹n chuyÓn tèc lμn rÏ ph¶i kh«ng cã ®o¹n chuyÓn tèc
d¹ng song song d¹ng vuèt d¹ng nèi trùc tiÕp
b. Geometrical design:
40
TCXDVN 104 : :2007
lμn xe rÏ tr¸i
lμn xe rÏ tr¸i
§O¹N chuyÓn lμn - L V ®o¹n chê rÏ tr¸i - LX
§O¹N chuyÓn lμn - L V ®o¹n chê rÏ tr¸i - LX
cÊu t¹o lμn rÏ tr¸i cã c¸ch li cÊu t¹o lμn rÏ tr¸i kh«ng c¸ch li
41
TCXDVN 104 : :2007
12.8.1. When planning and designing grade-separated intersections, it should select type, number
of grades structural design by taking into account following factors: general plan of the network, type
of road, road grade at the intersection, topography, construction condition, urban land use, traffic
condition (volume, speed, circulation capacity, composition of traffic and traffic safety), economic,
environmental social and urban beauty aspects..
12.8.2. Analyzing to select grade-separated facilities, which road to be upper and which road is
lower by taking into account following factors:
- Economic factor is measured in the design so as to fit existing topographical conditions. Then,
it is to consider various intersecting options so as to compare and decide to use flyovers or viaduct.
- Viaduct makes it easier for drivers to realize grade-separated intersections and pay attention to
relations inside the intersection.
- When direction-changing volume is significant, the flyover will be favorable for arranging
connection branches in the intersection.
- Flyover will be better in terms of landscape.
- Preference as to viaduct or flyover should be based on the option providing better visibility for
the main road.
- Flyover option is suitable for phased constructions, for both road and other structures with
minimum initial investment cost.
- When main road is upper without changing speed of the crossing road, it is marginal to change
drainage and sewerage system of the area.
- When taking into account operation of oversized vehicles, the upper option will produce no
restriction in terms of vertical clearance.
- It is suitable if using flyover with a new road crossing an existing road with big traffic volume.
- Road with biggest traffic volume should be arranged in the direction with smallest number of
bridges to secure good operation and reduce obstructions in cases of repair, maintenance or
rebuilding.
- In some cases, it is needed to build roads with bigger traffic volumes on the grade lower than
the road with smaller volumes so as to abate noise.
12.8.3. Geometrical design for connection branch should take into account following factors:
- Type of connection branch: left turning or right turning;
- Type of connection: Direct, semi-direct, indirect;
- Handling conflict: at-grade intersecting cordner, etc.
- Designing geometrical structure of connection branch includes:
1) Identifying designed speed for the connection branch, see more in Table 32.
42
TCXDVN 104 : :2007
Table 32 Identifying designed speed on connection branch
VTK on the Designed speed on connection branch (km/h)
intersecting road
High Medium low
(km/h)
100 80-70 60 50
70 70 55 45
80 70-60 50 40
60 50 40 30
50 40 30 25
Note:
- Right turning connection branch is normally applicable with medium or high speed
- Indirect connection branch is normally applied with low speed
- Semi-direct connection branch is applied with medium or high speed
- If length of connection branch is short, one lane, it is possible to take <= 60km/h
2) Designing components of a connection branch: top section, central section and ending section of
connection branch.
3) Identifying cross-section of connection branch
- 1 lane, 1 direction with overtaking reserve or without overtaking reserve.
- 2 lanes, either one direction or two directions
Cross-section of the connection branch includes roadway, sidewalk and median (if any). See in the
Table 33.
Table 33 Cross-section of connection branch
One-way, one-lane road Two-way, two-lane road
- Roadway width, m 4.0 (straight) 7,0 (straight)
- Expanded on curve of R<100m
- Sidewalk, m 50/R 2x50/R
+ embanked roadsides on Right
and left 2.0 1.0
+ Roadsides without embankment - 1.0
on right - 0.75
And left 1.0 0.75
Note:
If connection branch is on the flyover or viaduct, sidewalk width is taken as equal to embanked
sidewalk as earlier stated.
4) Designing …and examining conditions for deployment of connection branch (slope, length,
clearance and number of lane).
43
TCXDVN 104 : :2007
place.
13.1.3. Road foundation in weak land area follow 22TCN 262. Road foundation in areas with
complicated geological conditions follows 22TCN 171. Road foundation in earthquake-prone area
follows 22TCN 211 in place.
44
TCXDVN 104 : :2007
Table 34 Required compactness of the road foundation (following 22TCN 333 - 05)
Type of structure Depth from Compactness k
bottom of the Main urban road Local urban
pavement, cm Feeder urban road
road
Embanked Thickness of upper pavement 30 ≥0,98 ≥0,95
foundation 60cm
Thickness of lower pavement 50 ≥0,98 ≥0,95
60cm
Below Newly ≥0,95 ≥0,93
mentioned embanked soil
depth Natural Up to 80cm ≥0,93 ≥0,90
foundation
Excavated foundation and original foundation 30 ≥0,98 ≥0,95
30-80 ≥0,93 ≥0,90
Note:
Body of the foundation is affected by inundation or ground water therefore subject to minimum
compactness of 0.95
13.5.2. After compacting, it must secure that affected area of the foundation meets following
requirements:
- 30 cm of the top layer can tolerate the minimum load CBR of 8 for main urban road, feeder
road and 6 for local roads.
- The next 50 cm must tolerate minimum load of CBR of 5 for main urban road, feeder roads
and 5 for local roads
In which: CBR is the rate for load tolerance identified in laboratory with sample soil compacted at
standard level and left submerged for four days, following 22TCN332
13.6.1. Embanked road slope depends on the geological conditions and the slope height (refer to
Table 35).
45
TCXDVN 104 : :2007
Table 35. Slope of Embanked Road
Slope Elevation
Soil Type and Condition
≤6.0m >6.0m
- Soft soil or medium to loose soil 1:1.0 1:1.25
- Loose soil 1:1.50 1:1.75
- Light-weathered stiff rock 1:0.3 1:0.50
- Strong-weathered stiff rock 1:1.0 1:1.25
- Light-weathered soft rock 1:0.75 1:1.00
- Strong-weathered soft rock 1:1.00 1:1.25
Note:
1. The slope height of the excavated soil foundation shall not exceed 12 m. For soft stone foundation
the designed slope is equally to the slope of the rock layer if the grade inclined toward the outside area
and is over 250.
2. When the slope runs through different rock and soil layers the relevant slope shall be designed for
each foundation condition properly.
3. When the slope elevation is high the terraces shall be designed at the interval of 5 – 6 meter.
Note: the terrace is – 3 m wide, 5 – 10% gradient toward the inside gutter. The gutter in rectangle or
triangle shape shall be built to ensure water discharge from the higher slope terrace.
13.6.2. Slope of the embanked road depends on the filled materials and the height of the slope
(refer to Table 36).
46
TCXDVN 104 : :2007
Table 36. Slope of Embanked Road
Slope height
Rock/soil type
<6m 6 - 12m
- Light weathered rock 1:1 ÷ 1: 1.3 1:1.3 ÷ 1: 1.5
- Large-dimension rock (25 cm) 1 : 0.75 1: 1.10
- Gravel, pebble, gravel-mixed sand, slag 1: 1.3 1:1.3 ÷ 1: 1.5
- Rough to medium sand, sandy clay, weathered rock 1 : 1.5 1:1.75
- Dust and fine sand 1:1.75 ÷ 1: 2 1:1.75 ÷ 1: 2
Note:
1. In the flooding areas, the slope of embanked road shall be increase to 1: 2 or the slope shall be
strengthened.
2. If the slope is high the terraces shall be designed at the interval of 5 – 6 m.
3. The height of the embanked road slope shall not exceed 12 m.
13.6.3. High slope elevation is not recommended in urban areas. The slope in urban areas shall be
covered by grass, brush tree, pre-casted concrete block, etc. to protect the urban environment and
landscape as well as to prevent land erosion.
13.6.4. The slope foundation shall be strengthened if the slope height exceeds 12 m or in other
cases (heavy load, weak foundation, etc.) .
13.6.5. TCVN 4054 and other approved construction plans shall be enforced when designing crown-
and foot-gutters.
14. Pavement
47
TCXDVN 104 : :2007
Table 37. Pavement Surface Sub-layer
Calculated Accumulated
Category Road Type Material and structure period Vehicle No.
(Year) (PCU/lane)
High - Access road - Concrete or reinforce concrete ≥20 >1*106
standard A1 - Collector street - Fine to medium asphalt concrete for
the upper sub-layer or rough to medium ≥10
asphalt concrete for the underneath
sub-layer (1)
High - Collector street - Cool asphalt concrete, asphalt coated. 8 >2*106
standard A2 - Local street - Bituminous seal 5-8 >1*106
- Bituminous seal (gravel, standardized 4-7 >0.1*106
gravel, bituminous-coated consolidated
soil) (2)
Low - Collector street - Gravel road, macadam, or Natural 3-4 <0.1*106
standard B1 (initial phase) Gravel with protective cover or fine
- Local street gravel cover
- Temporary road
Low - Collector street - Consolidated soil 2-3 <0.1*106
standard B2 (initial phase) - Local soil, rock, industrial waste
- Temporary road material
Note
1. (1): total minimum thickness of the asphalt concrete sub-layers is 12 – 18 cm in case of arterial
urban road and avenue; that of local road is 7 to 12 cm.
2. (2): collector street: multi-asphalt layers coated; local street: one or multi-asphalt layers coasted.
3. Accumulated vehicle number in the calculated period is a reference.
4. Based on the economic conditions the local street could be paved by cement concrete or asphalt
concrete but the load shall be equivalent to high standard pavement A2.
5. Bituminous material or bituminous seal, B1, B2 pavements are not recommended in densely
populated urban areas.
14.3.3. Selection of foundation material for A1 Pavement
Processed Soil, rock or sand shall be used to build the foundation layer. Regarding to non-reinforced
concrete pavement (arterial road or avenue) the minimum thickness of consolidated foundation layer
shall be 15 cm.
For asphalt concrete pavement gravel or void asphalt concrete could be used to develop upper
foundation layer and gravel class II, 22TCN334, macadam or natural pebble could be used to
construct lower foundation layer.
The foundation layer width shall be 20 cm larger than that of the surface layer.
14.3.4. Bottom foundation layer (bottom pavement layer)
For A1 category soil or proper materials (pebble, cement consolidated soil) layer shall be at least 30
cm thick to meet the requirement on k compactness and CBR indicator of the roadbed as defined in
Provisions 15.5.1, 15.5.2. The bottom foundation layer width shall be 15 cm wider than that of other
foundation layers in each side.
14.3.5. Thickness of Layers of Pavement Structure
The minimum thickness shall be 1.5 times of the largest material particle dimension. The compacted
thickness of asphalt concrete shall not exceed 8 to 10 cm; the thickness of other materials shall not
exceed 15 cm (strengthened materials) or 15 cm (non-strengthened materials).
14.4. Road Pavement Designing
48
TCXDVN 104 : :2007
Road pavement shall be designed in complying with 22TCN-211 – Soft pavement and 22TCN-223-
stiff pavement. Other methods could be referred upon the investor agreement.
15. Drainage and Height Planning
15.1. General Provision of the Surface Water Discharge System
15.1.1. Planning and designing of the drainage system is a component of the urban road designing,
which shall be in complying with the approved drainage system and the outside drainage network
designing standard.
15.1.2. The urban drainage system shall meet the following requirements:
- Quickly collect and discharge water on the street and surrounding area, preventing flooding
in the locality.
- Transfer water to culvert system to discharge into the general drainage system.
15.1.3. Drainage components and facilities include: longitudinal grade and cross fall – gutter, gutter
inlet and catch basins, culverts, flow regulation, pumping station, etc.
15.1.4. Type and structure of drainage culvert are as follows:
- Combined drainage system or separate local drainage system linking to the general drainage
system
- Drainage culvert could be open-culvert, close-culvert or mix; round, rectangle or trapezium
shape; underground or elevated culvert, etc.
The type and structure shall be selected depending on the approved construction plan, local
conditions and in complying with the sectoral specific standards.
Note:
1. The separate drainage system is designed only for discharging of rainwater and clean
wastewater (road/vehicle cleaning wastewater or clean production wastewater). The
combined drainage system is designed to discharge all wastewaters.
2. Close drainage system is the culvert system (including longitudinal gutter) while open
drainage system is the cover or non-cover canal/ditch system.
15.1.5. Completed urban drainage system shall be designed to operate properly following the below
process: gutter => gutter inlet => collecting culvert => secondary culvert => primary culvert =>
(wastewater treatment) => discharging. In developing urban areas the system is simpler: gutter =>
culvert => discharge but the environment sanitation requirement shall be secured.
15.2. Crossfall
15.2.1. Crossfall of roadbed and roadside shall be designed properly to meet requirements of water
discharge and safety vehicle operation.
15.2.2. The typical crossfall of the road surface could be selected in complying with the above
provisions and Table 12. In the elevation planning the crossfall cold be smaller that the value in this
table.
15.3. Gutter
15.3.1. Gutter (longitudinal gutter) shall be designed on both sides of the roads or on the road
depending on the designed cross-section. The street gutter is usually made from concrete block or
curbed structure.
15.3.2. Normally the longitudinal gutter is parallel to vertical alignment of the road (the depth of the
gutter is constant). However, in case where the longitudinal grade of the slope is below 0.1% the
gutter depth shall be varied from 0.3 to 0.5%.
49
TCXDVN 104 : :2007
15.3.3. For conventional automobile road, the gutter is designed in complying with TCVN4054. In
urban area, the gutter shall be consolidated and covered.
15.4. Culvert (round, rectangle or trapezium shape)
15.4.1. Culvert system could be classified into three categories as follows:
- Primary culvert: large-size culvert, discharging water from large basin to reservoir or the
planned receiving areas. (*)
- Secondary culvert: medium-size culvert, collecting water of small areas in the sub-zones and
housing blocks or in unplanned area to the primary culvert. (**)
- Branch culvert: small-size culvert, collecting water from longitudinal gutter and roadside
through the gutter inlet to discharge into the primary/secondary culvert.
Note:
(*)
: This category is usually built along arterial streets and avenues. Inclining direction and the
primary culvert map shall be in complying with the specific drainage plan.
(**)
: This category is usually developed along local streets. The inclining direction shall be based on
the spatial plan and the drainage plan in the locality to minimize the culvert length.
15.4.2. The culvert could be in round, rectangle, trapezium shape; close or open; and mix. Water
and power supply and telecommunication systems could be combined with the culvert system but
the specific pipe is required (see Article 8.4 – Underground facilities).
15.4.3. In low building to land ratio open culvert (canal and ditch) could be introduced. When the
construction and the discharging basin are small the cover shall be designed to improve the safety
and urban environment landscape.
15.4.4. The minimum dimension or diameter of the culvert shall be designed in accordance with the
existing specific standard and shall meet the following requirements:
- d ≥750mm along arterial roads and avenues.
- d ≥500mm along local streets.
Note: The minimum dimension is related to the maintenance and repairing works during the
operation stage. The large-size culvert shall be built in case where the upper structure is large.
15.5. Gutter Inlet
15.5.1. Gutter inlet shall be designed to collect rainwater from the gutter to the drainage system.
15.5.2. The gutter inlet shall be located on the water-flowed place and shall be designed on long
slope section. The distance between two consecutive gutters is 30 to 80 m (refer to Table 38).
Table 38. Average Distance between Gutters
Street slope (%0) Conventional distance (m)
<5 50
5-6 60
6 - 10 70
10-30 80
>30 90
Noe:
1. If width of single-slope road width is over 14 m and that of double-slope width is over 24 m the
distance shall not exceed 60 m.
2. If the road is the water basin median or the road is narrow the distance could be 100 m to 200
m.
15.5.3. The inlet shape shall be quadrant or rectangle to collect and discharge wastewater..
50
TCXDVN 104 : :2007
15.5.4. Depth of the inlet bed shall be suitable to the minimum selected depth in order to secure
proper connection of the culvert. The minimum selected depth shall ensure that the culvert joint
could bear the load of the bulldozer during the road surface construction process. Garbage storage
hole shall be equipped, having the minimum depth of 30 cm.
15.5.5. The inlet structure could be as follows:
- Horizontal inlet: It is usually made from cast iron to ensure vehicle operation, comprising
screen to separate the garbage. This type is usually applied when the culvert is located
under the road carriage or the road curb is low.
- Vertical inlet: it is usually made from reinforce concrete, equipped with screen and xyphon to
separate garbage and to prevent odor dispersion.
51
TCXDVN 104 : :2007
15.8.2. Road and crossing embankment level must be in line with the levels identified in previous
plans. It is encouraged to plan road and crossing embankment level in all design stages. Road and
crossing embankment level planning is compulsory in the following cases:
- During engineering drawing preparation, for main urban roads, avenues; during engineering
design stages for all crossings of these roads when longitudinal grade is ≤0.5%.
- During engineering drawing preparation for local roads with longitudinal grade of ≤0,5% and
for all crossings of the roads
15.8.3. Embankment level drawing, to support drainage planning, needs to show design contour
line; for the case of construction work and load calculation, even the black (existing) contour line is
needed. Two adjacent red contour lines show a difference of 5-20cm, depending on the drawing
scale (1/200, 1/500, 1/1000) and on required details and grade.
15.8.4. Major principles for identification of road and crossing embankment level
a) For roads:
- Embankment level must comply with the control red line and approved elevation.
- Close coordination is required with drainage system to prevent water pooling in roadway.
- It is important not to create great cross fall, which is dangerous for traffic flows.
b) For crossings:
- For the case of crossings among roads of the same class, longitudinal grades are retained,
while only cross falls are modified in the range that cross drainage is ensured.
- For the case of crossings among roads of different class, higher-class road is prioritized, and
grades are modified only for lower-class roads.
- To facilitate drainage, it is necessary to provide an outward ditch. In case of concave terrain,
all incoming collectors must be provided with underground culvert and gutter inlets
- In any cases, it is imperial to avoid water pooling in crossings, or water flowing across road
crossings and pedestrian crossings.
52
TCXDVN 104 : :2007
16.2. Provisions of Underground Facilities/Utilities
16.2.1. Technical solutions for underground structure must follow existing sectoral technical
guidance and standards.
16.2.2. Regulations on locations of a number of underground facilities are shown in tables of
40,41,42.
Table 40. Minimum Depth for Underground Structure.
Minimum Depth for the underground
Type of Underground Facilties
facilities, from top of covered structure (m)
Water pipe under sidewalk 0.5
Water pipe under carriageway:
Pipe diameter ≤ 300mm 0.8
Pipe diameter ≥ 300mm 1.0
Cable under sidewalk 0.7
Cable under carriageway 1.0
Table 41. Minimum distance from edge of underground facilities to others (m)
Underground Water Supply Water drainage Utility lines, cables
Others Pipe pipe
53
TCXDVN 104 : :2007
Table 42. Minimum distance between outer edges of underground facilities (m)
Facilities Water supply Water drainage Power cable Utility line
pipe pipe
Water supply pipe 1.5 - 0.5 0.5
Water drainage pipe - 0.4 0.5 0.5
Power cable 0.5 0.5 0.1-0.5 0.5
Utility line 0.5 0.5 0.5 -
Note:
1. When network elevation in comparison to building foundation in earlier table shows a big
differential, the distance must be reconsidered, taking into account natural rest angle of
foundation soil.
2. If it is hard to place the network, the distance can be reduced while case structure
strengthened.
3. When water supply pipe is placed in parallel to drainage pipe, the distance between them
must not be less than 1.5m if the water supply pipe is smaller than 200mm in diameter, and
must not be less than 3.0m if the diameter is bigger than 200 mm. In this case, the supply
pipe must be metal.
4. Distance between electricity cable and water supply pipe is 1m in minimum in parallel
configuration. If a ditch contains two pipes or more, the minimum distance of clearance
among them is as follows:
- For pipes with diameter less than 300mm, it must not be less than 0.4m.
- For pipes with diameter more than 300mm, it must not be less than 0.5m.
16.2.3. Vertical and horizontal distance when there is a transverse of underground network, water
supply pipe with roads and other pipes:
- The distance between water supply pie or cable lines with roadway (pavement to pipetop),
surface of power line is 1.0m.
- The distance between water supply pipe with cables, including power lines and utility lines, is
0.5m
- The distance between walls of pipes of the same functions (except for drainage crossing
water supply and other pipes with toxic liquids, organic ordor) is 0.2m
- The distance between domestic water supply network and drainage network when water
supply pipe is place above drainage pipe is 0.15m.
- The distance between 2 water supply pipe is 0.15m.
Note:
1. For installation of cased metal water supply pipe, it is to calculate the distance to sides of the
cased sections of each crossings:
- In clay, not less than 5m
- In watery soil, not less than 10m
2. If at the crossings, water drainage pipe is placed above cased metal water supply pipe, for
the length of the cased section, the distance to sides is:
- In clay, not less than 5m
54
TCXDVN 104 : :2007
- In watery soil, not less than 10m
a) Selection of types and plantation methods must take into account purposes, cross section, road
class, local identities, local climate and soil suitablity, features of townscape, traffic safety, urban
environment and sanitation, risks for nagative impacts on on-ground, underground and elevated
facilities.
b) It is not advisable to mix too many types of trees on a single midblock section. It is best to plant
one or two types of trees on a midblock section of less than 2km, while three types can be accepted
on a section longer than 2km, depending on particular cases .
c) For median with width less than 2m, only grass, low bushes and vased trees are planted. For
medians wider than 2m, higher and bigger trees can be planted but their branches must not be
obstacles to traffic, and they are planted away from ends of the median, enough to provide sufficient
sighting and traffic safety.
d) At a number of artificial structure such as bridge piers, vidaducts, walls, slopes etc. creepers are
encouraged to apply more greenery patches to urban townscapes using suitable string materials to
protect, as well, the structure. At important road crossings, apart from regulations for traffic safety
protection, grass, bushes and flowers are also to improve greenery patches and urban townscape.
e) Deployment of green trees must be rationale and trimming of branches for ensured traffic sighting
is a must, especially at road crossings and during rainy/stormy seasons.
17.1.5. Planted green trees must be at least 3.0m high with respective trunk diameter of 6cm.
17.1.6. Other regulations are based on local regulations (if any) and provisions in 7.7.
17.2. Lighting
17.2.1. Roadside lighting is a part of urban infrastructure system, including voltage transformation
station, control boxes, electricity cables, wires, poles and lamps.
17.2.2. Calculation and detail design are described in TCXDVN 259 – “the Standards for Design of
Artificial Lighting System for Urban Roads and Square” with horizontal distance requirements shown
in Table 39.
Table 39. Minimum horizontal distance from edge of roadway to light pole, m
55
TCXDVN 104 : :2007
Roads Expected minimum value Absolute minimum value
Urban expressway 2.0 1.0
Urban main road 1.0 0.75
Collectors 0.75 0.5
Local roads 0.5 0.5
MÐp lÒ ®−êng
a 15.0 b
bÕn lÊy kh¸ch
56
TCXDVN 104 : :2007
Note: Consider expanding area of bus stop to provide multipe loading and unloading at the same
time if number of bus is big.
17.3.3. Scope of bus top use.
a. Turnout bus stops:
- On urban highways (if possible), on key urban arterial roads with designed speed of 80km/h
in the periperal areas is necessary to provide Turnout bus stops in isolation form. Pedestrian
crossing should be grade-separated.
- On key streets in urban core area, if area is enough, it is encouraged to provide isolation bus
stops.
- On key streets (except earlier mentioned cases), boulevards, local roads and internal roads
with high traffic of busses (headway of five minutes) is necessary to provide turnout bus stop
of stop and bypass.
b. Simple bus stop:
- It is only used in cases not earlier regulated.
17.3.4. Placement of bus stop.
- Location of bus stop is provided on the right side of operating direction, from 300 to 700
apart. It is banned to provide on curving sections with curving radius smaller than
conventional horizontal curve.
- Except the case median is provided, bus stop on two roadsides should not be symetric.
Starting point should be at least 10 meters apart.
- Stop point can be provided on the nearside or farside of the traffic intersection. Distance
from the intersection should take into account the acceleration section, observation time (if
placing before the intersection), deceleration (if placing after the intersection) and influence
of each stop on operating capacity of the intersection. When stopping after the intersection,
the bus stop must be at least 50 meters from the center of the intersection. When stopping
before the intersection, it should be at least 40 meters from the road with Vtt = 60km/h; 60m,
or with road of Vtt >60km/h.
- If intersection is provided with pedestrian markings, bus stop should be at least 10 meters
from the marking.
17.3.5. On bus shelter, seats, shelter should be provided to secure amenities and aestheticic
purposes.
57
TCXDVN 104 : :2007
17.4.3. Parking space: in urban areas, if possible, roadside and curb can be used for parking
purposes, but it is best to widen given section for exclusive parking lots.
17.4.4. In case of parallel parking, minimum width of parking lane is 2.5m, but not bigger than 3.5m.
17.4.5. Parking spaces should be marked for identification; parking is not allowed at certain
locations, such as fire hydrants, bus stops, etc. ....
17.4.6. It is not adviable to design parking lanes near road crossings. This situation should be
eliminated by establishing a transition section of at least 6m from the road crossing (see Figure 14)
2.5
6.0m
6.0 7.5 7.5 6.0 7.5 6.0 7.5 6.0
18.1. Other road devices are under provisions in TCVN 4054 “Highway Design Standard” and
other existing design standards.
18.2. On-road traffic safety facilities include signboards, road markings, road markers, fences etc.
are stipulated by TCVN 4053 and 22TCN 237 “Road Sign Code” and other existing codes.
58
TCXDVN 104 : :2007
18.3. Other type of service areas are stipulated in TCVN 4054.
---------------------------------------
59