GERBANG PERDANA S B
(RoC No. 469478-X)
For Construction and No. 3, Jalan 222,
46100 Petaling Jaya,
Installation of Manhole Selangor Darul Ehsan
Page No. : 1 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
2.0
Important
The information contained herein is proprietary to Gerbang Perdana Sdn. Bhd. It shall
not be reproduced, copied, revealed, published or distributed in whole or in part
without authorization.
__________________________________________________________
TABLE OF CONTENTS
PAGE
REF DESCRIPTION
NO.
1.0 INTRODUCTION………………………………..………………… 2
2.0 SCOPE OF WORKS…………….………………………………… 2
3.0 WORK SEQUENCE FLOW……………………………………… 3
4.0 METHOD STATEMENT……………………..…………………… 4
5.0 MATERIAL………………….………………….…………………… 5
6.0 MACHINERY……………………………………………………… 5
7.0 MANPOWER……………………………………………………… 6
8.0 SAFETY & ENVIRONMENT………………..…………………… 6
9.0 INSPECTION & TEST PLAN…………………………………… 7
10.0 DIAGRAMS & DRAWINGS…………………..…………………… 7
Page No. : 2 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
1.0 INTRODUCTION
The work is applicable for the Manhole construction and installation for the
installation of HT and LV cables.
Page No. : 3 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
No Yes
Re-Submit as per Approved Issue Purchase order
requirement
No Yes
Re-Submit as per Approved Preparation for installation
requirement
Pre-Inspection
Remedy work
No
Final Inspection
END
Page No. : 4 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
4.1 The pit is excavated to its required depth to receive the concrete
base for the construction of the manhole. The base shall be
adequate is size to receive the external concrete surround to the
manhole. The position of the manhole shall be checked to avoid
misalignment of pipes down and up stream of the manhole.
4.2 Shoring to the pit shall be provided if the pit measured from the top
edge is more than 1.5m.
4.3 Excavate further to desired level manually to achieve the required
level.
4.4 Excavate a sump pit at the bottom of the pit for de-watering.
4.5 Prepare formwork to receive base for the positioning of the manhole
and eventual concrete to the external of the manhole.
4.6 Cast the base and allow the concrete to set for the next day to
position the pre-cast concrete reinforced chamber rings.
4.7 Break or puncture a hole through the chamber ring for the inlets and
prepare the box-outs at the hacked openings prior to the 150mm
concrete surround to the external of the manhole.
4.8 Remove the formwork to the concrete surround the next day and lay
the main drain lines to the openings of the manhole. Prepare to cast
the main drain at the end of the day.
4.9 Remove all formwork in the trench and at the pit of the manhole.
Backfill once the pit and trench is cleared of debris.
4.10 Apply sulphate resistant cement to the internal of the manhole.
Render smooth to gaps between chamber rings.
4.11 Proceed to render the benching with cement mortar and construct
the channels with glazed vitrified half channels accordings to the
numbers of main or branch drain lines.
Page No. : 5 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
4.12 Form up the opening to the manhole with timber and wait for the
commencements of the external finishes work by the builder before
installing the approved type of frame and covers
4.13 Call for Inspection.
5.0 MATERIAL
5.1 Timber for formwork
5.2 Glazed vitrifiel clay half channels of vary sizes.
5.3 Portland cement and plastering sand
5.4 Manhole frame and cover.
5.5 BRC or rebar
5.6 Grade 20 concrete.
6.0 MACHINERY
6.1 Man operated excavator
6.2 Hand held cutter
6.3 Rammer
6.4 Leveling equipments
Page No. : 6 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
7.0 MANPOWER
7.1 Resident Engineer
7.2 Supervisor
7.3 QC Inspector
7.4 Excavator operator
7.5 General workers
8.2 Environment
All workers shall be responsible and ensure that the site works carried
out shall conform with the Employer’s Environment Policy and comply
with the Malaysian Environment Act 1974 and any other Federal and
State Government act. Hence always all workers shall ensure that all
the site workers shall;
Page No. : 7 of 7
Revision No. : 1.0
Issued : 20.06.2004
MS-CIQ06/E/024/R1.0
• CSD/GSB/ICIQ/CIQ/EE/GEN/0051
• CSD/GSB/ICIQ/CIQ/EE/GEN/0052
Trade/Service: HT SYSTEM
Service
Item: Location/Level:
items to be check area
Acceptability
No. Item to be Checked Remarks
Yes No
1 TYPE OF MATERIAL
2 CONCRETE GRADES
3 SIZE & DEPTH OF CHAMBER RINGS
4 SIZE & BASE THICKNESS
5 CONCRETE COVER SURROUND
6 POSITION OF MANHOLE
7 INVERT OF MANHOLE
8 PLASTERING TO INTERNAL WALLS
9 BENCHING & CHANNELS
10 TOP SLAB FOR MANHOLE
11 TYPE OF FRAME & COVER