Structure Submission / Revised Status Structure is

Volume Submission Date Under


S5201 CIVIL CONSTRUCTION DRAWING 2019-5-6 NESPAK Responded SEPCO III
OF CIRCULATING WATER PIPE - Response From SEPCO
III is awaited
S5319 CIVIL CONSTRUCTION DRAWING 2019-5-12 Under Review by NESPAK
OF FLOCCULATE AND NESPAK
SEDIMENTATION POND
S5322 CIVIL CONSTRUCTION DRAWING 2019-5-12 NESPAK Responded SEPCO III
OF CHEMICAL DOSING ROOM - Response From SEPCO
III is awaited
S5501 CIVIL CONSTRUCTION DRAWING 2019-5-9 Under Review by NESPAK
OF POTABLE WATER, SERVICE NESPAK
WATER AND FIRE-FIGHTING
WATER BASINS
T0211 CONSTRUCTION DRAWING OF 2019-5-11 Under Review by NESPAK
UNDERGROUND FACILITY AND NESPAK
ANCILLARY EQUIPMENT OF MAIN
POWER HOUSE
T0214 FLOORS OF DEAERATOR BAY 2019-5-4 NESPAK Responded SEPCO III
- Response From SEPCO
III is awaited
T0227 CONSTRUCTION DRAWING OF 2019-5-3 NESPAK Responded SEPCO III
BOILER FRONT PLATFORM - Response From SEPCO
STRUCTURE III is awaited
T0305 STEEL FLUE DUCT SUPPORT IN 2019-5-15 Under Review by NESPAK
REAR OF BOILER NESPAK
T0702 STRUCTURAL DRAWING OF 2019-5-7 NESPAK Responded SEPCO III
BOILER MAKE-UP WATER - Response From SEPCO
TREATMENT ROOM III is awaited
T0236 STRUCTURAL DRAWINGS OF 2019-5-3 Already Approved on SEPCO III
BOILER ROOF 13-05-2019
Current Status of 660 MW Lucky Power Plant Project
Overall Status of the Project

Total Submitted Structures = 43

Approved Structures = 34

Under Review Structures = 9 (Please refer to the following table for detailed status)

Pending Structures = 106