EBWPC Status Date: 21-Feb-14

BURGOS WIND POWER PROJECT (29 x V90/3MW)


Printed: 21-Feb-14 / 19:50
VESTAS SERVICES PHILIPPINES, INC. REVISED PROJECT SCHEDULE
FIRST BALFOUR
(REV.T)

DETAILED

Activity Name Rem Start Finish TF Issues/Constraints 2014


Dur JJJJJ JJ

BURGOS WIND FARM WF (29x 90/3MW) REVISED PROJECT SCHEDULE [REV.T] 205 28-May-13 A 13-Sep-14 0

MILESTONES 205 18-Jun-13 A 13-Sep-14 0

PROJECT MILESTONES 154 18-Jun-13 A 01-Aug-14 15


Contract Signature 0 18-Jun-13 A
Notice to Proceed 0 04-Jul-13 A
Mobilization & Start of Construction - BOP 0 22-Jul-13 A
Readiness of Storage Yard - Laydown Area 0 03-Jan-14 A
Completion - First Tower Foundation (Pedestal Concrete Poured) 0 09-Jan-14 A
Commencement for WTG Delivery to Site (By Others) 0 13-Feb-14 A
Start Delivery to Site of Electrical & FO Cable Materials 0 28-Feb-14 0
Completion - Last Tower Foundation (Pedestal Concrete Poured) 0 09-Mar-14 159
BOP Completion 0 01-Aug-14* 15
SECTIONAL MILESTONES 41 21-Jun-14 01-Aug-14 11
Section 1 Completion 0 21-Jun-14* 9
Section 2 Completion 0 09-Jul-14* 26
Section 3 Completion 0 20-Jul-14* 22
Section 4 Completion 0 01-Aug-14* 11
CLOSEOUT DOCUMENTATIONS 0 13-Sep-14 13-Sep-14 0
As-Built Documentation - Electrical 0 13-Sep-14* 0
As-Built Documentation - Civil/Structural 0 13-Sep-14* 0
WORK ITEMS COMPLETION 116 21-Feb-14 17-Jun-14 11
POWER SUBSTATION (BY OTHERS) 54 05-Apr-14 29-May-14 -16
Substation: Cable Termination & Testing Complete (SS to YPBS) 0 05-Apr-14 38
Substation: Ready for Energization (By Others) 0 15-Apr-14* 0
Substation: Final Commissioning & Switching (By Others) 0 15-Apr-14 20
Substation: Cable Termination & Testing Complete (SS to RMU's/WTG's) 0 29-May-14 -16
POWERHOUSE (YPBS) 7 07-May-14 14-May-14 -1
Powerhouse: Yaw Power Backup System (YPBS) Complete 0 07-May-14 6
Powerhouse: Cable Termination & Testing Complete (YPBS to SS) 0 14-May-14 -1
RING MAIN UNITS (RMU'S) 19 08-May-14 29-May-14 -15
RMU D: Cable Termination & Testing Complete (RMU to SS/WTG's) 0 08-May-14 4
RMU A: Cable Termination & Testing Complete (RMU to SS/WTG's) 0 11-May-14 1
RMU B: Cable Termination & Testing Complete (RMU to SS/WTG's) 0 29-May-14 -15
SECTION 01 76 21-Feb-14 07-May-14 9
CIVIL / STRUCTURAL / ELECTRICAL 61 21-Feb-14 22-Apr-14 9
Section 01: Roads/Site Tracks Complete 0 21-Feb-14 70
Section 01: Hardstands Complete 0 12-Mar-14 35
Section 01: WTG's Foundation to Bafilling Complete 0 12-Mar-14 50
Section 01: Drainage/Slope Stabilization Complete 0 13-Apr-14 18
Section 01: WTG's Electrical Trenching & Cabling Complete 0 20-Apr-14 11
Section 01: WTG's Switchgear Terminations Complete 0 22-Apr-14 9
FINISHING & PUNCHLISTING COMMENCEMENT 26 11-Apr-14 07-May-14 9
Section 01: Start Hardstand Finishing / Punchlisting 0 11-Apr-14 35

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 1 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Section 01: Start Foundation Finishing / Punchlisting 0 27-Apr-14 19


Section 01: Start Site Tracks/Roads/Drainage Finishing / Punchlisting 0 29-Apr-14 18
Section 01: Start Electrical Finishing / Punchlisting 0 07-May-14 9
SECTION 02 94 21-Feb-14 26-May-14 26
CIVIL / STRUCTURAL / ELECTRICAL 79 21-Feb-14 10-May-14 26
Section 02: Roads/Site Tracks Complete 0 21-Feb-14 105
Section 02: Hardstands Complete 0 07-Mar-14 75
Section 02: WTG's Foundation to Bafilling Complete 0 07-Mar-14 90
Section 02: WTG's Electrical Trenching & Cabling Complete 0 02-May-14 35
Section 02: WTG's Switchgear Terminations Complete 0 07-May-14 29
Section 02: Drainage/Slope Stabilization Complete 0 10-May-14 26
FINISHING & PUNCHLISTING COMMENCEMENT 49 06-Apr-14 26-May-14 26
Section 02: Start Hardstand Finishing / Punchlisting 0 06-Apr-14 75
Section 02: Start Foundation Finishing / Punchlisting 0 28-Apr-14 53
Section 02: Start Electrical Finishing / Punchlisting 0 25-May-14 27
Section 02: Start Site Tracks/Roads/Drainage Finishing / Punchlisting 0 26-May-14 26
SECTION 3A (WEST) 96 21-Feb-14 27-May-14 31
CIVIL / STRUCTURAL / ELECTRICAL 77 21-Feb-14 08-May-14 35
Section 3A: Hardstands Complete 0 21-Feb-14 97
Section 3A: WTG's Foundation to Bafilling Complete 0 21-Feb-14 112
Section 3A: Roads/Site Tracks Complete 0 21-Feb-14 112
Section 3A: WTG's Electrical Trenching & Cabling Complete 0 10-Apr-14 64
Section 3A: WTG's Switchgear Terminations Complete 0 12-Apr-14 62
Section 3A: Drainage/Slope Stabilization Complete 0 08-May-14 35
FINISHING & PUNCHLISTING COMMENCEMENT 66 23-Mar-14 27-May-14 31
Section 3A: Start Hardstand Finishing / Punchlisting 0 23-Mar-14 97
Section 3A: Start Foundation Finishing / Punchlisting 0 29-Apr-14 59
Section 3A: Start Site Tracks/Roads/Drainage Finishing / Punchlisting 0 23-May-14 35
Section 3A: Start Electrical Finishing / Punchlisting 0 27-May-14 31
SECTION 3B (WEST) 82 15-Mar-14 06-Jun-14 22
CIVIL / STRUCTURAL / ELECTRICAL 67 15-Mar-14 21-May-14 22
Section 3B: Roads/Site Tracks Complete 0 15-Mar-14 89
Section 3B: Hardstands Complete 0 16-Mar-14 73
Section 3B: WTG's Foundation to Bafilling Complete 0 16-Mar-14 88
Section 3B: WTG's Electrical Trenching & Cabling Complete 0 01-May-14 42
Section 3B: WTG's Switchgear Terminations Complete 0 07-May-14 37
Section 3B: Drainage/Slope Stabilization Complete 0 21-May-14 22
FINISHING & PUNCHLISTING COMMENCEMENT 51 15-Apr-14 06-Jun-14 22
Section 3B: Start Hardstand Finishing / Punchlisting 0 15-Apr-14 73
Section 3B: Start Foundation Finishing / Punchlisting 0 02-May-14 56
Section 3B: Start Electrical Finishing / Punchlisting 0 27-May-14 31
Section 3B: Start Site Tracks/Roads/Drainage Finishing / Punchlisting 0 06-Jun-14 22
SECTION 04 95 14-Mar-14 17-Jun-14 11
CIVIL / STRUCTURAL / ELECTRICAL 75 14-Mar-14 28-May-14 15
Section 04: Hardstands Complete 0 14-Mar-14 75
Section 04: WTG's Foundation to Bafilling Complete 0 14-Mar-14 90
Section 04: Roads/Site Tracks Complete 0 14-Mar-14 90
Section 04: WTG's Electrical Trenching & Cabling Complete 0 25-May-14 19
Section 04: WTG's Switchgear Terminations Complete 0 27-May-14 16
Section 04: Drainage/Slope Stabilization Complete 0 28-May-14 15
FINISHING & PUNCHLISTING COMMENCEMENT 65 13-Apr-14 17-Jun-14 11
Section 04: Start Hardstand Finishing / Punchlisting 0 13-Apr-14 75

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 2 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Section 04: Start Foundation Finishing / Punchlisting 0 25-Apr-14 63


Section 04: Start Site Tracks/Roads/Drainage Finishing / Punchlisting 0 13-Jun-14 15
Section 04: Start Electrical Finishing / Punchlisting 0 17-Jun-14 11
CONSTRAINTS 46 08-Oct-13 A 29-Apr-14 8

POWERHOUSE (YPBS) (BY OTHERS) 0 25-Jan-14 A 07-Feb-14 A


Powerhouse: Access to Generators House Construction (By Others) 0 25-Jan-14 A Access for Construction of Generators House.
Powerhouse: Work Suspension at Generators House (By Others) 0 30-Jan-14 A Work Suspended due to Design issue.
Powerhouse: Work Resumption at Generators House (By Others) 0 07-Feb-14 A Work Resumed 07Feb14.
POWER SUBSTATION (BY OTHERS) 15 14-Mar-14 28-Mar-14 40
Substation: Access for Cable Trenching at Powerhouse to Substation (By Others) 0 14-Mar-14 32
Substation: Access for Cable Pulling & Terminations (By Others) 0 27-Mar-14 15
Substation: Switchgears Installed (By Others) ready for Cable Terminations 0 28-Mar-14 29
RING MAIN UNITS (RMU'S) (BY OTHERS) 35 19-Mar-14 29-Apr-14 -10
RMU A: Access for Concrete Pad Construction (By Others) 0 19-Mar-14 0
RMU D: Access for Concrete Pad Construction (By Others) 0 24-Mar-14 0
RMU B: Access for Concrete Pad Construction (By Others) 0 29-Apr-14 -10
SECTION 01 0 08-Oct-13 A 20-Dec-13 A
TREE CUTTING PERMIT (BY OTHERS) 0 08-Oct-13 A 20-Dec-13 A
C22: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C07: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C03: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C01: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C06: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C44: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C15: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C08: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C34: TCP (EDWC Scope) at WTG location (By Others) 0 20-Dec-13 A TCP issued 20Dec13
Section 01 C08-C03: TCP (EDWC Scope) Site Tracks (By Others) 0 20-Dec-13 A TCP issued 20Dec13
SECTION 02 0 20-Dec-13 A 20-Dec-13 A
TREE CUTTING PERMIT (BY OTHERS) 0 20-Dec-13 A 20-Dec-13 A
C37: TCP (EDWC Scope) at WTG location (By Others) 0 20-Dec-13 A TCP issued 20Dec13
C45: TCP (EDWC Scope) at WTG location (By Others) 0 20-Dec-13 A TCP issued 20Dec13
C29: TCP (EDWC Scope) at WTG location (By Others) 0 20-Dec-13 A TCP issued 20Dec13
C42: TCP (EDWC Scope) at WTG location (By Others) 0 20-Dec-13 A TCP issued 20Dec13
C25: TCP (EDWC Scope) at WTG location (By Others) 0 20-Dec-13 A TCP issued 20Dec13
Section 02: TCP (EDWC Scope) Site Tracks (By Others) 0 20-Dec-13 A TCP issued 20Dec13
SECTION 3A (WEST) 0 08-Oct-13 A 08-Oct-13 A
TREE CUTTING PERMIT (BY OTHERS) 0 08-Oct-13 A 08-Oct-13 A
C09: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C16: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C17: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C04: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C14: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
SECTION 3B (EAST) 0 08-Oct-13 A 08-Oct-13 A
TREE CUTTING PERMIT (BY OTHERS) 0 08-Oct-13 A 08-Oct-13 A
C02: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C13: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C43: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C05: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C18: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
SECTION 04 0 08-Oct-13 A 08-Oct-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 3 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

TREE CUTTING PERMIT (BY OTHERS) 0 08-Oct-13 A 08-Oct-13 A


C48: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C19: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C35: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C12: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
C50: TCP (EDWC Scope) at WTG location (By Others) 0 08-Oct-13 A TCP issued 08Oct13
Section 04: TCP (EDWC Scope) Site Tracks (By Others) 0 08-Oct-13 A TCP issued 08Oct13
INTERFACE 138 08-Oct-13 A 09-Jul-14 0

SECTION 01 105 08-Feb-14 A 06-Jun-14 -15


HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR WTG COMPONENTS SITE DELIVERY 15 08-Feb-14 A 12-Mar-14 12
C03: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 08-Feb-14 A TCP Required 30Aug13 / Issued 08Oct13.
C22: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 12-Feb-14 A TCP Required 30Aug13 / Issued 08Oct13.
C06: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 13-Feb-14 A TCP Required 30Aug13 / Issued 08Oct13.
C01: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 15-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. Change of Road Allignment.
C07: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 15-Feb-14 A TCP Required 30Aug13 / Issued 08Oct13.
C08: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 26-Feb-14 11 Geotechnical.
C44: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 28-Feb-14 18 TCP Required 30Aug13 / Issued 08Oct13. Geotechnical.
C34: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 09-Mar-14 8 TCP Required 30Aug13 / Issued 19Dec13. Geotechnical.
C15: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 12-Mar-14 6 TCP Required 30Aug13 / Issued 08Oct13. Geotechnical.
WTG TOWER COMPONENTS SITE DELIVERY (BY OTHERS) 21 19-Feb-14 A 13-Mar-14 16
C22: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 19-Feb-14 A TCP Required 30Aug13 / Issued 08Oct13.
C03: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 18 TCP Required 30Aug13 / Issued 08Oct13.
C07: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 24 TCP Required 30Aug13 / Issued 08Oct13.
C06: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 26 TCP Required 30Aug13 / Issued 08Oct13.
C01: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 19 TCP Required 29Sep13 / Issued 08Oct13. Change of Road Allignment.
C08: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 26-Feb-14 11 Geotechnical.
C44: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 01-Mar-14 20 TCP Required 30Aug13 / Issued 08Oct13. Geotechnical (Current).
C34: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 10-Mar-14 8 TCP Required 30Aug13 / Issued 19Dec13. Geotechnical.
C15: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 13-Mar-14 7 TCP Required 30Aug13 / Issued 08Oct13. Geotechnical.
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR BASE / MID TOWER ERECTION 14 11-Mar-14 25-Mar-14 0
C03: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 11-Mar-14* 0
C01: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 11-Mar-14* 0
C08: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 11-Mar-14* 0
C07: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 15-Mar-14* 0
C44: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 19-Mar-14* 0
C06: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 19-Mar-14* 0
C34: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 19-Mar-14* 0
C15: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 19-Mar-14* 0
C22: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 25-Mar-14* 0
WTG FIELD SWITCHGEARS INSTALLATION (BY OTHERS) 21 30-Mar-14 20-Apr-14 9
C22: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 30-Mar-14 20
C08: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 02-Apr-14 19
C01: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 03-Apr-14 19
C03: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 04-Apr-14 19
C07: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 06-Apr-14 19
C06: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 12-Apr-14 13
C34: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 13-Apr-14 13
C15: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 15-Apr-14 12
C44: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 20-Apr-14 9
WTG BASE & MID TOWER ERECTION (BY OTHERS) 18 13-Mar-14 31-Mar-14 0
C08: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 13-Mar-14* 0

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 4 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C03: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 14-Mar-14* 0
C01: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 15-Mar-14* 0
C07: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 20-Mar-14* 0
C34: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 21-Mar-14* 0
C06: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 22-Mar-14* 0
C15: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 24-Mar-14* 0
C44: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 25-Mar-14* 0
C22: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 31-Mar-14* 0
WTG TOWER BASE GROUTING & SEALANT 18 15-Mar-14 02-Apr-14 21
C08: Commence WTG Tower Base Grouting & Sealing 0 15-Mar-14 28
C03: Commence WTG Tower Base Grouting & Sealing 0 16-Mar-14 35
C01: Commence WTG Tower Base Grouting & Sealing 0 17-Mar-14 29
C07: Commence WTG Tower Base Grouting & Sealing 0 22-Mar-14 31
C34: Commence WTG Tower Base Grouting & Sealing 0 23-Mar-14 31
C06: Commence WTG Tower Base Grouting & Sealing 0 24-Mar-14 30
C15: Commence WTG Tower Base Grouting & Sealing 0 26-Mar-14 28
C44: Commence WTG Tower Base Grouting & Sealing 0 27-Mar-14 27
C22: Commence WTG Tower Base Grouting & Sealing 0 02-Apr-14 6
WTG FIELD SWITCHGEAR TERMINATION 21 01-Apr-14 21-Apr-14 9
C22: Start Field Switchgear Termination 0 01-Apr-14 20 May take place before or after B & M tower erection.
C08: Start Field Switchgear Termination 0 03-Apr-14 19 May take place before or after B & M tower erection.
C01: Start Field Switchgear Termination 0 04-Apr-14 19 May take place before or after B & M tower erection.
C03: Start Field Switchgear Termination 0 05-Apr-14 19 May take place before or after B & M tower erection.
C07: Start Field Switchgear Termination 0 07-Apr-14 19 May take place before or after B & M tower erection.
C06: Start Field Switchgear Termination 0 13-Apr-14 13 May take place before or after B & M tower erection.
C34: Start Field Switchgear Termination 0 14-Apr-14 13 May take place before or after B & M tower erection.
C15: Start Field Switchgear Termination 0 16-Apr-14 12 May take place before or after B & M tower erection.
C44: Start Field Switchgear Termination 0 21-Apr-14 9 May take place before or after B & M tower erection.
WTG TOP TOWERS / NACELLE / HUB / BLADES ERECTION & MECHANICAL INSTALLATION (BY OTHERS) 19 22-Mar-14 10-Apr-14 29
C08: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 22-Mar-14 31
C03: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 23-Mar-14 35
C01: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 24-Mar-14 32
C07: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 31-Mar-14 29
C34: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 01-Apr-14 33
C06: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 02-Apr-14 30
C15: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 04-Apr-14 32
C44: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 05-Apr-14 34
C22: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 10-Apr-14 9
WTG PRE-COMMISSIONING (BY OTHERS) 19 21-Apr-14 10-May-14 9
C22: Start Pre-Commissioning (By Others) 0 21-Apr-14 8
C08: Start Pre-Commissioning (By Others) 0 23-Apr-14 9
C01: Start Pre-Commissioning (By Others) 0 25-Apr-14 10
C03: Start Pre-Commissioning (By Others) 0 28-Apr-14 9
C07: Start Pre-Commissioning (By Others) 0 30-Apr-14 9
C06: Start Pre-Commissioning (By Others) 0 03-May-14 9
C34: Start Pre-Commissioning (By Others) 0 06-May-14 8
C15: Start Pre-Commissioning (By Others) 0 08-May-14 8
C44: Start Pre-Commissioning (By Others) 0 10-May-14 9
WTG STARTUP TURBINE / COMMISSIONIG (BY OTHERS) 8 29-May-14 06-Jun-14 -15
C22: Start Turbine Start-Up / Commissioning (By Others) 0 29-May-14 -16
C08: Start Turbine Start-Up / Commissioning (By Others) 0 30-May-14 -16
C01: Start Turbine Start-Up / Commissioning (By Others) 0 31-May-14 -16

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 5 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C03: Start Turbine Start-Up / Commissioning (By Others) 0 01-Jun-14 -16


C07: Start Turbine Start-Up / Commissioning (By Others) 0 02-Jun-14 -15
C06: Start Turbine Start-Up / Commissioning (By Others) 0 03-Jun-14 -15
C34: Start Turbine Start-Up / Commissioning (By Others) 0 04-Jun-14 -15
C15: Start Turbine Start-Up / Commissioning (By Others) 0 05-Jun-14 -15
C44: Start Turbine Start-Up / Commissioning (By Others) 0 06-Jun-14 -15
SECTION 02 102 15-Feb-14 A 03-Jun-14 -5
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR WTG COMPONENTS SITE DELIVERY 12 15-Feb-14 A 07-Mar-14 17
C45: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 15-Feb-14 A TCP Required 14Sep13 / Issued 19Dec13.
C29: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 17-Feb-14 A TCP Required 14Sep13 / Issued 19Dec13. Geotechnical.
C37: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 23-Feb-14 29 TCP Required 14Sep13 / Issued 19Dec13. Design Issue (Current).
C42: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 05-Mar-14 2 TCP Required 14Sep13 / Issued 19Dec13. Geotechnical.
C25: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 07-Mar-14 1 TCP Required 14Sep13 / Issued 19Dec13. Geotechnical (Affected By C08 Relocation).
WTG TOWER COMPONENTS SITE DELIVERY (BY OTHERS) 16 21-Feb-14 08-Mar-14 20
C45: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 12 TCP Required 14Sep13 / Issued 19Dec13.
C29: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 14 TCP Required 14Sep13 / Issued 19Dec13. Geotechnical.
C37: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 23-Feb-14 33 TCP Required 14Sep13 / Issued 19Dec13. Design Issue (Current).
C42: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 06-Mar-14 2 TCP Required 14Sep13 / Issued 19Dec13. Geotechnical.
C25: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 08-Mar-14 1 TCP Required 14Sep13 / Issued 19Dec13. Geotechnical (Affected By C08 Relocation).
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR BASE / MID TOWER ERECTION 19 06-Mar-14 25-Mar-14 0
C29: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 06-Mar-14* 0
C45: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 06-Mar-14* 0
C42: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 10-Mar-14* -1
C25: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 11-Mar-14* -1
C37: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 25-Mar-14* 0
WTG FIELD SWITCHGEARS INSTALLATION (BY OTHERS) 11 23-Apr-14 04-May-14 15
C45: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 23-Apr-14 18
C37: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 01-May-14 13
C29: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 02-May-14 15
C42: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 03-May-14 15
C25: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 04-May-14 15
WTG BASE & MID TOWER ERECTION (BY OTHERS) 24 08-Mar-14 01-Apr-14 0
C45: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 08-Mar-14* 0
C29: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 10-Mar-14* 0
C42: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 11-Mar-14* 0
C25: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 13-Mar-14* -1
C37: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 01-Apr-14* 0
WTG TOWER BASE GROUTING & SEALANT 24 10-Mar-14 03-Apr-14 33
C45: Commence WTG Tower Base Grouting & Sealing 0 10-Mar-14 48
C29: Commence WTG Tower Base Grouting & Sealing 0 12-Mar-14 52
C42: Commence WTG Tower Base Grouting & Sealing 0 13-Mar-14 53
C25: Commence WTG Tower Base Grouting & Sealing 0 15-Mar-14 52
C37: Commence WTG Tower Base Grouting & Sealing 0 03-Apr-14 26
WTG FIELD SWITCHGEAR TERMINATION 11 24-Apr-14 05-May-14 15
C45: Start Field Switchgear Termination 0 24-Apr-14 18 May take place before or after B & M tower erection.
C37: Start Field Switchgear Termination 0 02-May-14 13 May take place before or after B & M tower erection.
C29: Start Field Switchgear Termination 0 03-May-14 15 May take place before or after B & M tower erection.
C42: Start Field Switchgear Termination 0 04-May-14 15 May take place before or after B & M tower erection.
C25: Start Field Switchgear Termination 0 05-May-14 15 May take place before or after B & M tower erection.
RING MAIN UNIT (RMU) - D (BY OTHERS) 0 12-Apr-14 12-Apr-14 0
RMU D: Equipments & Accessories Installed (By Others) ready for Cable Termination 0 12-Apr-14* 0
WTG TOP TOWERS / NACELLE / HUB / BLADES ERECTION & MECHANICAL INSTALLATION (BY OTHERS) 25 17-Mar-14 11-Apr-14 33

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 6 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C45: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 17-Mar-14 49
C29: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 19-Mar-14 52
C42: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 20-Mar-14 53
C25: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 23-Mar-14 53
C37: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 11-Apr-14 26
WTG PRE-COMMISSIONING (BY OTHERS) 15 26-Apr-14 12-May-14 12
C45: Start Pre-Commissioning (By Others) 0 26-Apr-14 18
C37: Start Pre-Commissioning (By Others) 0 05-May-14 12
C29: Start Pre-Commissioning (By Others) 0 07-May-14 13
C42: Start Pre-Commissioning (By Others) 0 09-May-14 13
C25: Start Pre-Commissioning (By Others) 0 12-May-14 12
WTG STARTUP TURBINE / COMMISSIONIG (BY OTHERS) 5 29-May-14 03-Jun-14 -5
C45: Start Turbine Start-Up / Commissioning (By Others) 0 29-May-14 -6
C37: Start Turbine Start-Up / Commissioning (By Others) 0 30-May-14 -6
C29: Start Turbine Start-Up / Commissioning (By Others) 0 31-May-14 -5
C42: Start Turbine Start-Up / Commissioning (By Others) 0 02-Jun-14 -5
C25: Start Turbine Start-Up / Commissioning (By Others) 0 03-Jun-14 -5
SECTION 03 (EAST & WEST) 0 08-Oct-13 A 08-Apr-14 0
Section 03: TCP (EDWC Scope) Site Tracks (By Others) 0 08-Oct-13 A TCP issued 08Oct13
RING MAIN UNIT (RMU) - A (BY OTHERS) 0 08-Apr-14 08-Apr-14 0
RMU A: Equipments & Accessories Installed (By Others) ready for Cable Termination 0 08-Apr-14* 0
SECTION 3A (WEST) 126 02-Feb-14 A 27-Jun-14 0
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR WTG COMPONENTS SITE DELIVERY 0 02-Feb-14 A 08-Feb-14 A
C04: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 02-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. GPR.
C16: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 03-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C14: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 05-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. GPR.
C17: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 06-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C09: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 08-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. Relocation & Geotechnical.
WTG TOWER COMPONENTS SITE DELIVERY (BY OTHERS) 0 13-Feb-14 A 21-Feb-14 37
C16: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 13-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C04: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 14-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. GPR.
C14: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 14-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. GPR.
C09: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 16-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. Relocation & Geotechnical.
C17: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 21-Feb-14 37 TCP Required 29Sep13 / Issued 08Oct13.
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR BASE / MID TOWER ERECTION 24 01-Mar-14 25-Mar-14 0
C16: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 01-Mar-14* 0
C14: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 01-Mar-14* 0
C09: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 01-Mar-14* 0
C04: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 01-Mar-14* 0
C17: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 25-Mar-14* 0
WTG FIELD SWITCHGEARS INSTALLATION (BY OTHERS) 5 05-Apr-14 10-Apr-14 62
C17: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 05-Apr-14 62
C16: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 06-Apr-14 62
C04: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 07-Apr-14 62
C14: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 08-Apr-14 62
C09: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 10-Apr-14 62
WTG BASE & MID TOWER ERECTION (BY OTHERS) 30 03-Mar-14 02-Apr-14 0
C16: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 03-Mar-14* 0
C04: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 04-Mar-14* 0
C14: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 05-Mar-14* 0
C09: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 06-Mar-14* 0
C17: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 02-Apr-14* 0

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 7 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

WTG TOWER BASE GROUTING & SEALANT 30 05-Mar-14 04-Apr-14 62


C16: Commence WTG Tower Base Grouting & Sealing 0 05-Mar-14 86
C04: Commence WTG Tower Base Grouting & Sealing 0 06-Mar-14 87
C14: Commence WTG Tower Base Grouting & Sealing 0 07-Mar-14 88
C09: Commence WTG Tower Base Grouting & Sealing 0 08-Mar-14 89
C17: Commence WTG Tower Base Grouting & Sealing 0 04-Apr-14 53
WTG FIELD SWITCHGEAR TERMINATION 5 06-Apr-14 11-Apr-14 62
C17: Start Field Switchgear Termination 0 06-Apr-14 62 May take place before or after B & M tower erection.
C16: Start Field Switchgear Termination 0 07-Apr-14 62 May take place before or after B & M tower erection.
C04: Start Field Switchgear Termination 0 08-Apr-14 62 May take place before or after B & M tower erection.
C14: Start Field Switchgear Termination 0 09-Apr-14 62 May take place before or after B & M tower erection.
C09: Start Field Switchgear Termination 0 11-Apr-14 62 May take place before or after B & M tower erection.
WTG TOP TOWERS / NACELLE / HUB / BLADES ERECTION & MECHANICAL INSTALLATION (BY OTHERS) 31 12-Mar-14 12-Apr-14 63
C16: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 12-Mar-14 86
C04: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 13-Mar-14 87
C14: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 14-Mar-14 88
C09: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 15-Mar-14 91
C17: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 12-Apr-14 52
WTG PRE-COMMISSIONING (BY OTHERS) 9 21-Apr-14 30-Apr-14 54
C17: Start Pre-Commissioning (By Others) 0 21-Apr-14 52
C16: Start Pre-Commissioning (By Others) 0 23-Apr-14 53
C04: Start Pre-Commissioning (By Others) 0 25-Apr-14 53
C14: Start Pre-Commissioning (By Others) 0 28-Apr-14 52
C09: Start Pre-Commissioning (By Others) 0 30-Apr-14 54
WTG STARTUP TURBINE / COMMISSIONIG (BY OTHERS) 4 23-Jun-14 27-Jun-14 0
C17: Start Turbine Start-Up / Commissioning (By Others) 0 23-Jun-14 0
C16: Start Turbine Start-Up / Commissioning (By Others) 0 24-Jun-14 0
C04: Start Turbine Start-Up / Commissioning (By Others) 0 25-Jun-14 0
C14: Start Turbine Start-Up / Commissioning (By Others) 0 26-Jun-14 0
C09: Start Turbine Start-Up / Commissioning (By Others) 0 27-Jun-14 0
SECTION 3B (EAST) 110 09-Feb-14 A 03-Jul-14 0
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR WTG COMPONENTS SITE DELIVERY 0 09-Feb-14 A 16-Mar-14 8
C18: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 09-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C13: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 10-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C43: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 11-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C05: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 18-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. Geotechnical.
C02: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 16-Mar-14 8 TCP Required 29Sep13 / Issued 08Oct13. Geotechnical.
WTG TOWER COMPONENTS SITE DELIVERY (BY OTHERS) 0 16-Feb-14 A 17-Mar-14 15
C43: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 16-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C13: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 17-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C18: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 18-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C05: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 19-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13. Geotechnical.
C02: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 17-Mar-14 14 TCP Required 29Sep13 / Issued 08Oct13. Geotechnical.
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR BASE / MID TOWER ERECTION 10 15-Mar-14 25-Mar-14 0
C18: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 15-Mar-14* 0
C13: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 15-Mar-14* 0
C43: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 15-Mar-14* 0
C02: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 25-Mar-14* 0
C05: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 25-Mar-14* 0
WTG FIELD SWITCHGEARS INSTALLATION (BY OTHERS) 13 21-Apr-14 04-May-14 37
C05: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 21-Apr-14 46
C43: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 01-May-14 37

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 8 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C02: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 02-May-14 37
C13: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 03-May-14 37
C18: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 04-May-14 37
WTG BASE & MID TOWER ERECTION (BY OTHERS) 18 17-Mar-14 04-Apr-14 0
C13: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 17-Mar-14* 0
C18: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 18-Mar-14* 0
C43: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 19-Mar-14* 0
C05: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 03-Apr-14* 0
C02: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 04-Apr-14* 0
WTG TOWER BASE GROUTING & SEALANT 18 19-Mar-14 06-Apr-14 60
C13: Commence WTG Tower Base Grouting & Sealing 0 19-Mar-14 35
C18: Commence WTG Tower Base Grouting & Sealing 0 20-Mar-14 77
C43: Commence WTG Tower Base Grouting & Sealing 0 21-Mar-14 76
C05: Commence WTG Tower Base Grouting & Sealing 0 05-Apr-14 58
C02: Commence WTG Tower Base Grouting & Sealing 0 06-Apr-14 60
WTG FIELD SWITCHGEAR TERMINATION 13 22-Apr-14 05-May-14 37
C05: Start Field Switchgear Termination 0 22-Apr-14 46 May take place before or after B & M tower erection.
C43: Start Field Switchgear Termination 0 02-May-14 37 May take place before or after B & M tower erection.
C02: Start Field Switchgear Termination 0 03-May-14 37 May take place before or after B & M tower erection.
C13: Start Field Switchgear Termination 0 04-May-14 37 May take place before or after B & M tower erection.
C18: Start Field Switchgear Termination 0 05-May-14 37 May take place before or after B & M tower erection.
WTG TOP TOWERS / NACELLE / HUB / BLADES ERECTION & MECHANICAL INSTALLATION (BY OTHERS) 19 26-Mar-14 14-Apr-14 67
C13: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 26-Mar-14 83
C18: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 27-Mar-14 85
C43: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 30-Mar-14 75
C05: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 13-Apr-14 57
C02: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 14-Apr-14 62
WTG PRE-COMMISSIONING (BY OTHERS) 18 24-Apr-14 12-May-14 49
C05: Start Pre-Commissioning (By Others) 0 24-Apr-14 56
C43: Start Pre-Commissioning (By Others) 0 05-May-14 49
C02: Start Pre-Commissioning (By Others) 0 07-May-14 49
C13: Start Pre-Commissioning (By Others) 0 09-May-14 49
C18: Start Pre-Commissioning (By Others) 0 12-May-14 49
WTG STARTUP TURBINE / COMMISSIONIG (BY OTHERS) 5 28-Jun-14 03-Jul-14 0
C05: Start Turbine Start-Up / Commissioning (By Others) 0 28-Jun-14 0
C43: Start Turbine Start-Up / Commissioning (By Others) 0 30-Jun-14 0
C02: Start Turbine Start-Up / Commissioning (By Others) 0 01-Jul-14 0
C13: Start Turbine Start-Up / Commissioning (By Others) 0 02-Jul-14 0
C18: Start Turbine Start-Up / Commissioning (By Others) 0 03-Jul-14 0
SECTION 04 130 02-Feb-14 A 09-Jul-14 0
HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR WTG COMPONENTS SITE DELIVERY 7 02-Feb-14 A 14-Mar-14 7
C48: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 02-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C50: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 07-Mar-14 14
C12: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 11-Mar-14 10
C19: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 14-Mar-14 7
C35: Handover Road, Hardstand & Foundation for WTG Component Delivery 0 14-Mar-14 7
WTG TOWER COMPONENTS SITE DELIVERY (BY OTHERS) 7 16-Feb-14 A 15-Mar-14 10
C48: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 16-Feb-14 A TCP Required 29Sep13 / Issued 08Oct13.
C50: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 08-Mar-14 17
C12: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 12-Mar-14 12
C19: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 15-Mar-14 7
C35: Start Deliver WTG Components (Tower, Nacelle, Hub & Blades) (By Others) 0 15-Mar-14 8

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 9 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

HANDOVER ROADS / FOUNDATIONS / HARDSTANDS FOR BASE / MID TOWER ERECTION 21 01-Mar-14 22-Mar-14 0
C48: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 01-Mar-14* 0
C50: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 22-Mar-14* 0
C12: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 22-Mar-14* 0
C35: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 22-Mar-14* 0
C19: Handover Road, Hardstand & Foundation for B&M Tower Erection 0 22-Mar-14* 0
WTG FIELD SWITCHGEARS INSTALLATION (BY OTHERS) 9 16-May-14 25-May-14 16
C19: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 16-May-14 20
C35: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 17-May-14 20
C12: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 18-May-14 20
C50: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 23-May-14 16
C48: WTG MV Switchgear Installed (By Others) ready for Cable Termination 0 25-May-14 16
WTG BASE & MID TOWER ERECTION (BY OTHERS) 22 07-Mar-14 29-Mar-14 0
C48: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 07-Mar-14* 0
C19: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 26-Mar-14* 0
C35: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 27-Mar-14* 0
C12: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 28-Mar-14* 0
C50: Complete B&M Tower Erection (By Others) Prior to Grouting & Sealing 0 29-Mar-14* 0
WTG TOWER BASE GROUTING & SEALANT 22 09-Mar-14 31-Mar-14 66
C48: Commence WTG Tower Base Grouting & Sealing 0 09-Mar-14 88
C19: Commence WTG Tower Base Grouting & Sealing 0 30-Mar-14 67
C35: Commence WTG Tower Base Grouting & Sealing 0 30-Mar-14 67
C12: Commence WTG Tower Base Grouting & Sealing 0 30-Mar-14 67
C50: Commence WTG Tower Base Grouting & Sealing 0 31-Mar-14 66
WTG FIELD SWITCHGEAR TERMINATION 9 17-May-14 26-May-14 16
C19: Start Field Switchgear Termination 0 17-May-14 20 May take place before or after B & M tower erection.
C35: Start Field Switchgear Termination 0 18-May-14 20 May take place before or after B & M tower erection.
C12: Start Field Switchgear Termination 0 19-May-14 20 May take place before or after B & M tower erection.
C50: Start Field Switchgear Termination 0 24-May-14 16 May take place before or after B & M tower erection.
C48: Start Field Switchgear Termination 0 26-May-14 16 May take place before or after B & M tower erection.
RING MAIN UNIT (RMU) - B (BY OTHERS) 0 19-May-14 19-May-14 -9
RMU B: Equipments & Accessories Installed (By Others) ready for Cable Termination 0 19-May-14* -9
WTG TOP TOWERS / NACELLE / HUB / BLADES ERECTION & MECHANICAL INSTALLATION (BY OTHERS) 22 16-Mar-14 07-Apr-14 79
C48: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 16-Mar-14 101
C19: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 06-Apr-14 71
C35: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 06-Apr-14 73
C12: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 06-Apr-14 78
C50: Anchor Stud Tensioning & Start Erect Top Tower/Nacelle/Hub/Blades/Mech. Installation (By Others) 0 07-Apr-14 75
WTG PRE-COMMISSIONING (BY OTHERS) 13 19-May-14 02-Jun-14 33
C19: Start Pre-Commissioning (By Others) 0 19-May-14 37
C35: Start Pre-Commissioning (By Others) 0 21-May-14 37
C50: Start Pre-Commissioning (By Others) 0 28-May-14 34
C12: Start Pre-Commissioning (By Others) 0 30-May-14 34
C48: Start Pre-Commissioning (By Others) 0 02-Jun-14 33
WTG STARTUP TURBINE / COMMISSIONIG (BY OTHERS) 5 04-Jul-14 09-Jul-14 0
C19: Start Turbine Start-Up / Commissioning (By Others) 0 04-Jul-14 0
C35: Start Turbine Start-Up / Commissioning (By Others) 0 05-Jul-14 0
C50: Start Turbine Start-Up / Commissioning (By Others) 0 07-Jul-14 0
C12: Start Turbine Start-Up / Commissioning (By Others) 0 08-Jul-14 0
C48: Start Turbine Start-Up / Commissioning (By Others) 0 09-Jul-14 0
DESIGN SUBMITTAL / REVIEW / APPROVAL 0 15-Jan-14 A 01-Feb-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 10 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

GENERAL 0 15-Jan-14 A 01-Feb-14 A


POWERHOUSE (YPBS) 0 15-Jan-14 A 01-Feb-14 A
CIVIL / STRUCTURAL 0 15-Jan-14 A 01-Feb-14 A
GENERATOR SETS / FUEL DAY TANKS HOUSE 0 15-Jan-14 A 01-Feb-14 A
Powerhouse: Structural Design Submittal 0 15-Jan-14 A
Powerhouse: Structural Design Review (By Others) 0 16-Jan-14 A 01-Feb-14 A
Powerhouse: Structural Design Approval (By Others) 0 01-Feb-14 A
ELECTRO-MECHANICAL 0 01-Feb-14 A 01-Feb-14 A
Powerhouse: Design Approval of Generator Sets, Transformer & Shunt Reactors (By Others) 0 01-Feb-14 A
PROCUREMENT & SITE DELIVERIES 85 08-Jan-14 A 16-May-14 21

GENERAL 60 22-Jan-14 A 21-Apr-14 1


POWERHOUSE (YPBS) 60 22-Jan-14 A 21-Apr-14 1
GENERATORS HOUSE 6 22-Jan-14 A 11-Mar-14 0
SUBCONTRACTOR'S CONTRACT AWARD 0 22-Jan-14 A 31-Jan-14 A
Gensets House: Pre-Engineered Structures Sub-Contract Award Complete 0 22-Jan-14 A
Gensets House: Building Roof Insulation, Roofing, Doors & Louvers Sub-Contract Award Complete 0 24-Jan-14 A
Gensets House: Building Wall & Ceiling System Sub-Contract Award Complete 0 28-Jan-14 A
Gensets House: Foundation Sub-Contract Award Complete 0 31-Jan-14 A
MATERIALS REQUIRED ON SITE 6 09-Feb-14 A 11-Mar-14 0
Gensets House: Foundation Rebars Required on Site 0 09-Feb-14 A
Gensets House: Pre-Engineered Structures / Building Steel Frames Required on Site 0 04-Mar-14 0
Gensets House: Roof Insulation, Roofing & Doors Required on Site 0 06-Mar-14 0
Gensets House: Building Wall & Ceiling System Required on Site 0 11-Mar-14 0
FUEL TANKS (DAY & STORAGE TANKS) 34 01-Feb-14 A 26-Mar-14 26
FABRICATION 16 01-Feb-14 A 08-Mar-14 31
Fuel Day Tanks: Fabrication (2 - 900 Gallons) 12 01-Feb-14 A 04-Mar-14 13
Fuel Storage Tank: Fabrication (1 - 4,800 Gallons) 12 01-Feb-14 A 04-Mar-14 34
Fuel Storage Tank: Foundation Rebars Fabrication 7 01-Mar-14 08-Mar-14 26
SITE DELIVERY 18 08-Mar-14 26-Mar-14 26
Fuel Storage Tank: Foundation Rebars Required on Site 0 08-Mar-14 26
Fuel Day Tanks: Tanks & Accessories Required on Site 0 18-Mar-14 0
Fuel Storage Tank: Tank & Accessories Required on Site 0 26-Mar-14 26
ELECTRO-MECHANICAL 60 01-Feb-14 A 21-Apr-14 1
FABRICATION 12 01-Feb-14 A 04-Mar-14 45
Fabrication of Residential Muffler 12 01-Feb-14 A 04-Mar-14 45
Fabrication of Sync Panel w/ ComAp Controller 12 01-Feb-14 A 04-Mar-14 32
Fabrication of Fuel Transfer Pump Duplex Controller 8 21-Feb-14 28-Feb-14 45
Fabrication of Exhaust Pipe Hangers & Supports 7 22-Feb-14 28-Feb-14 47
Fabrication of Radiator Duct 7 22-Feb-14 28-Feb-14 47
Fabrication of Radiator Duct Hangers & Supports 7 22-Feb-14 28-Feb-14 47
FACTORY ACCEPTANCE TESTING PROCESS 9 05-Mar-14 13-Mar-14 32
Deliver Sync Panel w/ ComAp Controller to Monark's Yard 1 05-Mar-14 05-Mar-14 32
Temporary Control Connection for Factory Test Sync Panel w/ ComAp Controller 1 06-Mar-14 06-Mar-14 32
Programming & Control Wire Verification (Sync Panel, Genset & Client SCADA) 2 07-Mar-14 08-Mar-14 32
Elec-Mtion of Testing including Load Bank & SCADA Testing (Prior to Customers Witness) 3 09-Mar-14 11-Mar-14 32
Factory Testing including Load Bank & SCADA Testing (Customers to Witness) 1 12-Mar-14 12-Mar-14 32
Dismantling Temporay Control Wires (Sync Panel & Gensets) 1 13-Mar-14 13-Mar-14 32
SITE DELIVERY / LEAD TIME 60 01-Feb-14 A 21-Apr-14 1
Generator Set & Accessories (2 Units CAT3512-1250 KW) Lead Time 23 01-Feb-14 A 15-Mar-14 1
Transformer (TX) & Accessories (4MVA 0.48V/34.5KV) Lead Time 50 01-Feb-14 A 11-Apr-14 11
Shunt Reactors, Insulators & Accessories (3400KVAR) Lead Time 60 01-Feb-14 A 21-Apr-14 0

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 11 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

SITE DELIVERY / REQUIRED ON SITE 39 14-Mar-14 21-Apr-14 1


Site Delivery Sync Panel w/ ComAp & Fuel Transfer Pump Duplex Controller 2 14-Mar-14 15-Mar-14 32
Site Delivery Exhaust Tail & Fuel Pipe, Radiator Duct, Fuel Transfer Pump, Hangers & Supports 4 16-Mar-14 19-Mar-14 32
Generator Set & Accessories (2 Units CAT3512-1250 KW) Required on Site 0 17-Mar-14 0
Transformer (TX) & Accessories (4MVA 0.48V/34.5KV) Required on Site 0 14-Apr-14 9
Shunt Reactors, Insulators & Accessories (3400KVAR) Requir ed on Site 0 21-Apr-14 0
SECTION 01 27 27-Jan-14 A 30-Mar-14 20
CIVIL / STRUCTURAL 0 27-Jan-14 A 15-Mar-14 24
Section 1: Road Base Course Required on Site 0 27-Jan-14 A
Section 1: WTG Tower Base Grout / Sealant Required on Site 0 15-Mar-14 24
ELECTRICAL 27 03-Mar-14 30-Mar-14 20
Section 1: MV & FO Cables Required On Site 0 03-Mar-14* 0
Section 1: Certified Terminators Required On Site 0 24-Mar-14 20
Section 1: Cable Termination Kits & Accessories Required On Site 0 30-Mar-14 20
SECTION 02 45 01-Feb-14 A 23-Apr-14 18
CIVIL / STRUCTURAL 0 01-Feb-14 A 10-Mar-14 48
Section 2: Road Base Course Required on Site 0 01-Feb-14 A
Section 2: WTG Tower Base Grout / Sealant Required on Site 0 10-Mar-14 48
ELECTRICAL 35 19-Mar-14 23-Apr-14 18
Section 2: MV & FO Cables Required On Site 0 19-Mar-14* 0
Section 2: Certified Terminators Required On Site 0 17-Apr-14 18
Section 2: Cable Termination Kits & Accessories Required On Site 0 23-Apr-14 18
SECTION 3A (WEST) 36 26-Jan-14 A 05-Apr-14 62
CIVIL / STRUCTURAL 0 26-Jan-14 A 05-Mar-14 83
Section 3A: Road Base Course Required on Site 0 26-Jan-14 A
Section 3A: WTG Tower Base Grout / Sealant Required on Site 0 05-Mar-14 83
ELECTRICAL 36 28-Feb-14 05-Apr-14 62
Section 3A: MV & FO Cables Required On Site 0 28-Feb-14* 0
Section 3A: Certified Terminators Required On Site 0 30-Mar-14 62
Section 3A: Cable Termination Kits & Accessories Required On Site 0 05-Apr-14 62
SECTION 3B (EAST) 34 08-Jan-14 A 22-Apr-14 46
CIVIL / STRUCTURAL 0 08-Jan-14 A 19-Mar-14 35
Section 3B: Road Base Course Required on Site 0 08-Jan-14 A
Section 3B: WTG Tower Base Grout / Sealant Required on Site 0 19-Mar-14 35
ELECTRICAL 17 05-Apr-14 22-Apr-14 46
Section 3B: MV & FO Cables Required On Site 0 05-Apr-14* -16
Section 3B: Certified Terminators Required On Site 0 15-Apr-14 46
Section 3B: Cable Termination Kits & Accessories Required On Site 0 22-Apr-14 46
SECTION 04 69 15-Feb-14 A 16-May-14 20
CIVIL / STRUCTURAL 0 15-Feb-14 A 09-Mar-14 88
Section 4: Road Base Course Required on Site 0 15-Feb-14 A
Section 4: WTG Tower Base Grout / Sealant Required on Site 0 09-Mar-14 88
ELECTRICAL 20 26-Apr-14 16-May-14 20
Section 4: MV & FO Cables Required On Site 0 26-Apr-14* -16
Section 4: Certified Terminators Required On Site 0 10-May-14 20
Section 4: Cable Termination Kits & Accessories Required On Site 0 16-May-14 20
CONSTRUCTION 139 28-May-13 A 09-Jul-14 66

TEMPORARY FACILITIES 0 04-Jul-13 A 31-Oct-13 A


BATCHING PLANT (60 CU.M & 30 CU.M) 0 28-May-13 A 18-Nov-13 A
JETTY 0 19-Oct-13 A 31-Dec-13 A
ACCESS ROAD 0 19-Oct-13 A 28-Dec-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 12 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

PIER 0 29-Oct-13 A 31-Dec-13 A


LAYDOWN AREAS 1 & 2 0 21-Sep-13 A 03-Jan-14 A
LAYDOWN AREA 1 0 21-Sep-13 A 15-Oct-13 A
LAYDOWN AREA 2 0 20-Dec-13 A 03-Jan-14 A
HARDSTANDS 24 25-Sep-13 A 16-Mar-14 8
SECTION 01 19 25-Sep-13 A 12-Mar-14 12
HS C08 4 16-Jan-14 A 26-Feb-14 11
HS C08: Survey Layout 0 16-Jan-14 A 17-Jan-14 A
HS C08: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 18-Jan-14 A 19-Jan-14 A
HS C08: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 01-Feb-14 A 07-Feb-14 A
HS C08: Blade, Tower, Nacelle & Hub Hardstands 2 08-Feb-14 A 22-Feb-14 11
HS C08: Crane Pad & Crane Movement Area (PLT) 2 23-Feb-14 26-Feb-14 11
HS C03 0 26-Sep-13 A 05-Feb-14 A
HS C03: Survey Layout 0 26-Sep-13 A 26-Sep-13 A
HS C03: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 30-Sep-13 A 22-Oct-13 A
HS C03: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 05-Dec-13 A 19-Dec-13 A
HS C03: Blade, Tower, Nacelle & Hub Hardstands 0 10-Jan-14 A 12-Jan-14 A
HS C03: Crane Pad & Crane Movement Area (PLT) 0 01-Feb-14 A 05-Feb-14 A
HS C01 0 26-Sep-13 A 03-Feb-14 A
HS C01: Survey Layout 0 26-Sep-13 A 26-Sep-13 A
HS C01: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 29-Sep-13 A 25-Oct-13 A
HS C01: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 12-Nov-13 A 01-Dec-13 A
HS C01: Blade, Tower, Nacelle & Hub Hardstands 0 11-Jan-14 A 13-Jan-14 A
HS C01: Crane Pad & Crane Movement Area (PLT) 0 01-Feb-14 A 03-Feb-14 A
HS C07 0 26-Sep-13 A 06-Feb-14 A
HS C07: Survey Layout 0 26-Sep-13 A 26-Sep-13 A
HS C07: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 28-Sep-13 A 18-Oct-13 A
HS C07: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 25-Oct-13 A 31-Oct-13 A
HS C07: Blade, Tower, Nacelle & Hub Hardstands 0 11-Jan-14 A 12-Jan-14 A
HS C07: Crane Pad & Crane Movement Area (PLT) 0 13-Jan-14 A 06-Feb-14 A
HS C34 4 22-Oct-13 A 09-Mar-14 8
HS C34: Survey Layout 0 22-Oct-13 A 23-Oct-13 A TCP issued 20Dec13
HS C34: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 22-Dec-13 A 23-Dec-13 A
HS C34: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 05-Jan-14 A 18-Feb-14 A
HS C34: Blade, Tower, Nacelle & Hub Hardstands 2 05-Mar-14 07-Mar-14 8
HS C34: Crane Pad & Crane Movement Area (PLT) 2 07-Mar-14 09-Mar-14 8
HS C06 0 26-Sep-13 A 12-Feb-14 A
HS C06: Survey Layout 0 26-Sep-13 A 26-Sep-13 A
HS C06: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 08-Nov-13 A 09-Nov-13 A
HS C06: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 01-Dec-13 A 04-Dec-13 A
HS C06: Blade, Tower, Nacelle & Hub Hardstands 0 14-Jan-14 A 16-Jan-14 A
HS C06: Crane Pad & Crane Movement Area (PLT) 0 10-Feb-14 A 12-Feb-14 A
HS C15 4 22-Oct-13 A 12-Mar-14 6
HS C15: Survey Layout 0 22-Oct-13 A 22-Oct-13 A Pending Design Issue
HS C15: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 29-Dec-13 A 03-Jan-14 A
HS C15: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 01-Feb-14 A 08-Feb-14 A
HS C15: Blade, Tower, Nacelle & Hub Hardstands 2 09-Mar-14 10-Mar-14 6
HS C15: Crane Pad & Crane Movement Area (PLT) 2 11-Mar-14 12-Mar-14 6
HS C44 4 22-Oct-13 A 28-Feb-14 18
HS C44: Survey Layout 0 22-Oct-13 A 22-Oct-13 A Pending Design Issue
HS C44: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 17-Nov-13 A 18-Nov-13 A
HS C44: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 10-Dec-13 A 16-Dec-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 13 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

HS C44: Blade, Tower, Nacelle & Hub Hardstands 2 24-Feb-14 26-Feb-14 18


HS C44: Crane Pad & Crane Movement Area (PLT) 2 27-Feb-14 28-Feb-14 18
HS C22 0 25-Sep-13 A 10-Feb-14 A
HS C22: Survey Layout 0 25-Sep-13 A 25-Sep-13 A
HS C22: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 26-Sep-13 A 15-Oct-13 A
HS C22: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 27-Sep-13 A 18-Oct-13 A
HS C22: Blade, Tower, Nacelle & Hub Hardstands 0 15-Nov-13 A 13-Jan-14 A
HS C22: Crane Pad & Crane Movement Area (PLT) 0 17-Jan-14 A 10-Feb-14 A
SECTION 02 14 20-Dec-13 A 07-Mar-14 17
HS C45 0 05-Jan-14 A 15-Feb-14 A
HS C45: Survey Layout 0 05-Jan-14 A 05-Jan-14 A TCP issued 20Dec13
HS C45: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 06-Jan-14 A 08-Jan-14 A
HS C45: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 11-Jan-14 A 10-Feb-14 A
HS C45: Blade, Tower, Nacelle & Hub Hardstands 0 11-Feb-14 A 13-Feb-14 A
HS C45: Crane Pad & Crane Movement Area (PLT) 0 14-Feb-14 A 15-Feb-14 A
HS C29 0 11-Jan-14 A 17-Feb-14 A
HS C29: Survey Layout 0 11-Jan-14 A 12-Jan-14 A TCP issued 20Dec13
HS C29: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 15-Jan-14 A 17-Jan-14 A
HS C29: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 26-Jan-14 A 11-Feb-14 A
HS C29: Blade, Tower, Nacelle & Hub Hardstands 0 11-Feb-14 A 14-Feb-14 A
HS C29: Crane Pad & Crane Movement Area (PLT) 0 14-Feb-14 A 17-Feb-14 A
HS C42 11 20-Jan-14 A 05-Mar-14 2
HS C42: Survey Layout 0 20-Jan-14 A 20-Jan-14 A TCP issued 20Dec13
HS C42: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 21-Jan-14 A 22-Jan-14 A
HS C42: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 7 18-Feb-14 A 28-Feb-14 2
HS C42: Blade, Tower, Nacelle & Hub Hardstands 2 01-Mar-14 03-Mar-14 2
HS C42: Crane Pad & Crane Movement Area (PLT) 2 03-Mar-14 05-Mar-14 2
HS C25 14 20-Dec-13 A 07-Mar-14 1
HS C25: Survey Layout 0 20-Dec-13 A 21-Dec-13 A TCP issued 20Dec13
HS C25: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 22-Jan-14 A 23-Jan-14 A
HS C25: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 7 21-Feb-14 28-Feb-14 4
HS C25: Blade, Tower, Nacelle & Hub Hardstands 2 04-Mar-14 05-Mar-14 1
HS C25: Crane Pad & Crane Movement Area (PLT) 2 06-Mar-14 07-Mar-14 1
HS C37 0 27-Dec-13 A 15-Feb-14 A
HS C37: Survey Layout 0 27-Dec-13 A 27-Dec-13 A TCP issued 20Dec13
HS C37: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 28-Dec-13 A 02-Jan-14 A
HS C37: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 01-Feb-14 A 07-Feb-14 A
HS C37: Blade, Tower, Nacelle & Hub Hardstands 0 08-Feb-14 A 11-Feb-14 A
HS C37: Crane Pad & Crane Movement Area (PLT) 0 12-Feb-14 A 15-Feb-14 A
SECTION 3A / WEST 0 04-Nov-13 A 08-Feb-14 A
HS C16 0 04-Nov-13 A 28-Jan-14 A
HS C16: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C16: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 18-Nov-13 A 19-Nov-13 A
HS C16: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 01-Dec-13 A 04-Dec-13 A
HS C16: Blade, Tower, Nacelle & Hub Hardstands 0 11-Jan-14 A 13-Jan-14 A
HS C16: Crane Pad & Crane Movement Area (PLT) 0 28-Jan-14 A 28-Jan-14 A
HS C04 0 04-Nov-13 A 31-Jan-14 A
HS C04: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C04: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 17-Nov-13 A 18-Nov-13 A
HS C04: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 16-Dec-13 A 19-Dec-13 A
HS C04: Blade, Tower, Nacelle & Hub Hardstands 0 12-Jan-14 A 14-Jan-14 A
HS C04: Crane Pad & Crane Movement Area (PLT) 0 29-Jan-14 A 31-Jan-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 14 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

HS C14 0 04-Nov-13 A 02-Feb-14 A


HS C14: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C14: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 11-Nov-13 A 12-Nov-13 A
HS C14: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 16-Dec-13 A 19-Dec-13 A
HS C14: Blade, Tower, Nacelle & Hub Hardstands 0 13-Jan-14 A 15-Jan-14 A
HS C14: Crane Pad & Crane Movement Area (PLT) 0 31-Jan-14 A 02-Feb-14 A
HS C09 0 07-Nov-13 A 08-Feb-14 A
HS C09: Survey Layout 0 07-Nov-13 A 08-Nov-13 A
HS C09: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 09-Nov-13 A 10-Nov-13 A
HS C09: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 05-Jan-14 A 09-Jan-14 A
HS C09: Blade, Tower, Nacelle & Hub Hardstands 0 01-Feb-14 A 03-Feb-14 A
HS C09: Crane Pad & Crane Movement Area (PLT) 0 04-Feb-14 A 08-Feb-14 A
HS C17 0 04-Nov-13 A 03-Feb-14 A
HS C17: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C17: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 18-Nov-13 A 20-Nov-13 A
HS C17: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 01-Dec-13 A 04-Dec-13 A
HS C17: Blade, Tower, Nacelle & Hub Hardstands 0 04-Jan-14 A 06-Jan-14 A
HS C17: Crane Pad & Crane Movement Area (PLT) 0 05-Jan-14 A 03-Feb-14 A
SECTION 3B / EAST 24 04-Nov-13 A 16-Mar-14 8
HS C13 0 04-Nov-13 A 08-Feb-14 A
HS C13: Survey Layout 0 04-Nov-13 A 05-Nov-13 A
HS C13: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 05-Nov-13 A 06-Nov-13 A
HS C13: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 27-Nov-13 A 04-Dec-13 A
HS C13: Blade, Tower, Nacelle & Hub Hardstands 0 12-Jan-14 A 15-Jan-14 A
HS C13: Crane Pad & Crane Movement Area (PLT) 0 06-Feb-14 A 08-Feb-14 A
HS C18 0 04-Nov-13 A 09-Feb-14 A
HS C18: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C18: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 13-Nov-13 A 14-Nov-13 A
HS C18: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 09-Dec-13 A 14-Jan-14 A
HS C18: Blade, Tower, Nacelle & Hub Hardstands 0 14-Jan-14 A 16-Jan-14 A
HS C18: Crane Pad & Crane Movement Area (PLT) 0 07-Feb-14 A 09-Feb-14 A
HS C43 0 04-Nov-13 A 07-Feb-14 A
HS C43: Survey Layout 0 04-Nov-13 A 05-Nov-13 A
HS C43: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 05-Nov-13 A 06-Nov-13 A
HS C43: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 28-Dec-13 A 29-Dec-13 A
HS C43: Blade, Tower, Nacelle & Hub Hardstands 0 09-Jan-14 A 11-Jan-14 A
HS C43: Crane Pad & Crane Movement Area (PLT) 0 12-Jan-14 A 07-Feb-14 A
HS C05 0 04-Nov-13 A 18-Feb-14 A
HS C05: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C05: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 11-Nov-13 A 12-Nov-13 A
HS C05: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 02-Jan-14 A 05-Jan-14 A
HS C05: Blade, Tower, Nacelle & Hub Hardstands 0 15-Feb-14 A 16-Feb-14 A
HS C05: Crane Pad & Crane Movement Area (PLT) 0 17-Feb-14 A 18-Feb-14 A
HS C02 23 08-Jan-14 A 16-Mar-14 8
HS C02: Survey Layout 0 08-Jan-14 A 08-Jan-14 A
HS C02: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 01-Feb-14 A 02-Feb-14 A
HS C02: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 7 21-Feb-14 28-Feb-14 20
HS C02: Blade, Tower, Nacelle & Hub Hardstands 2 13-Mar-14 14-Mar-14 8
HS C02: Crane Pad & Crane Movement Area (PLT) 2 15-Mar-14 16-Mar-14 8
SECTION 04 19 28-Oct-13 A 14-Mar-14 7
HS C48 0 28-Oct-13 A 02-Feb-14 A
HS C48: Survey Layout 0 28-Oct-13 A 29-Oct-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 15 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

HS C48: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 29-Oct-13 A 31-Oct-13 A


HS C48: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 20-Dec-13 A 23-Dec-13 A
HS C48: Blade, Tower, Nacelle & Hub Hardstands 0 09-Jan-14 A 01-Feb-14 A
HS C48: Crane Pad & Crane Movement Area (PLT) 0 12-Jan-14 A 02-Feb-14 A
HS C50 4 04-Nov-13 A 28-Feb-14 22
HS C50: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C50: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 23-Dec-13 A 27-Dec-13 A
HS C50: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 13-Jan-14 A 07-Feb-14 A
HS C50: Blade, Tower, Nacelle & Hub Hardstands 2 23-Feb-14 24-Feb-14 22
HS C50: Crane Pad & Crane Movement Area (PLT) 2 26-Feb-14 28-Feb-14 22
HS C19 2 04-Nov-13 A 26-Feb-14 24
HS C19: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C19: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 06-Jan-14 A 08-Jan-14 A
HS C19: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 14-Jan-14 A 20-Jan-14 A
HS C19: Blade, Tower, Nacelle & Hub Hardstands 0 19-Feb-14 A 20-Feb-14 A
HS C19: Crane Pad & Crane Movement Area (PLT) 2 23-Feb-14 26-Feb-14 24
HS C35 4 04-Nov-13 A 14-Mar-14 7
HS C35: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C35: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 09-Jan-14 A 11-Jan-14 A
HS C35: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 10-Jan-14 A 07-Feb-14 A
HS C35: Blade, Tower, Nacelle & Hub Hardstands 2 11-Mar-14 12-Mar-14 7
HS C35: Crane Pad & Crane Movement Area (PLT) 2 13-Mar-14 14-Mar-14 7
HS C12 0 04-Nov-13 A 10-Feb-14 A
HS C12: Survey Layout 0 04-Nov-13 A 04-Nov-13 A
HS C12: Cutting/Grading/Stripping/Excavation/Clearing to enable Foundation Survey 0 12-Jan-14 A 15-Jan-14 A
HS C12: Cutting/Grading/Stripping/Excavation/Clearing/Leveling 0 18-Jan-14 A 04-Feb-14 A
HS C12: Blade, Tower, Nacelle & Hub Hardstands 0 07-Feb-14 A 08-Feb-14 A
HS C12: Crane Pad & Crane Movement Area (PLT) 0 09-Feb-14 A 10-Feb-14 A
WTG FOUNDATIONS 46 01-Oct-13 A 07-Apr-14 159
WTG FOOTINGS (BACKFILLING COMPLETE) 24 01-Oct-13 A 16-Mar-14 181
SECTION 01 20 01-Oct-13 A 12-Mar-14 12
WTG FOOTING C22 0 01-Oct-13 A 22-Jan-14 A
Footing C22: Survey Layout 0 01-Oct-13 A 01-Oct-13 A
Footing C22: Clearing / Excavation for Foundation Including Access Ramp 0 17-Oct-13 A 26-Oct-13 A
Footing C22: Trench Excavation, Encasement Construction and Conduit Layout 0 28-Oct-13 A 29-Oct-13 A
Footing C22: Lean Concrete Pouring 0 30-Oct-13 A 30-Oct-13 A
Footing C22: Anchor Cage & Shim Plate (Assembly & Installation) 0 04-Nov-13 A 13-Nov-13 A
Footing C22: Rebar Works Inc. Grounding Wires & Rod Inst. 0 13-Nov-13 A 04-Dec-13 A
Footing C22: Install Forms 0 13-Nov-13 A 04-Dec-13 A
Footing C22: Footing Concrete Pouring 0 09-Dec-13 A 09-Dec-13 A
Footing C22: Curing before removing Formwork 0 10-Dec-13 A 10-Dec-13 A
Footing C22: Curing Before Pedestal Concreting 0 10-Dec-13 A 16-Dec-13 A
Footing C22: Remove Forms 0 12-Dec-13 A 12-Dec-13 A
Footing C22: Pedestal Concrete Pouring 0 09-Jan-14 A 09-Jan-14 A
Footing C22: Backfill, Compaction & FDT (Initial @ 1.3M) 0 11-Jan-14 A 14-Jan-14 A
Footing C22: Backfill, Compaction & FDT (Final to FGL) 0 20-Jan-14 A 22-Jan-14 A
WTG FOOTING C07 0 14-Oct-13 A 15-Feb-14 A
Footing C07: Survey Layout 0 14-Oct-13 A 15-Oct-13 A
Footing C07: Clearing / Excavation for Foundation Including Access Ramp 0 19-Oct-13 A 24-Oct-13 A
Footing C07: Trench Excavation, Encasement Construction and Conduit Layout 0 29-Oct-13 A 30-Oct-13 A
Footing C07: Lean Concrete Pouring 0 04-Nov-13 A 05-Nov-13 A
Footing C07: Anchor Cage & Shim Plate (Assembly & Installation) 0 13-Nov-13 A 14-Nov-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 16 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C07: Install Forms 0 18-Nov-13 A 22-Nov-13 A


Footing C07: Rebar Works Inc. Grounding Wires & Rod Inst. 0 22-Nov-13 A 29-Nov-13 A
Footing C07: Footing Concrete Pouring 0 11-Dec-13 A 11-Dec-13 A
Footing 02 (C07): Curing before removing formwork 0 12-Dec-13 A 12-Dec-13 A
Footing C07: Curing Before Pedestal Concreting 0 12-Dec-13 A 18-Dec-13 A
Footing C07: Remove Forms 0 14-Dec-13 A 14-Dec-13 A
Footing C07: Pedestal Concrete Pouring 0 15-Jan-14 A 15-Jan-14 A
Footing C07: Backfill, Compaction & FDT (Initial @ 1.3M) 0 13-Feb-14 A 14-Feb-14 A
Footing C07: Backfill, Compaction & FDT (Final to FGL) 0 14-Feb-14 A 15-Feb-14 A
WTG FOOTING C03 0 14-Oct-13 A 30-Jan-14 A
Footing C03: Survey Layout 0 14-Oct-13 A 15-Oct-13 A
Footing C03: Clearing / Excavation for Foundation Including Access Ramp 0 24-Oct-13 A 05-Nov-13 A
Footing C03: Trench Excavation, Encasement Construction and Conduit Layout 0 06-Nov-13 A 09-Nov-13 A
Footing C03: Lean Concrete Pouring 0 10-Nov-13 A 10-Nov-13 A
Footing C03: Anchor Cage & Shim Plate (Assembly & Installation) 0 18-Nov-13 A 21-Nov-13 A
Footing C03: Rebar Works Inc. Grounding Wires & Rod Inst. 0 29-Nov-13 A 05-Dec-13 A
Footing C03: Footing Concrete Pouring 0 15-Dec-13 A 15-Dec-13 A
Footing C03: Install Forms 0 15-Dec-13 A 21-Dec-13 A
Footing C03: Curing before removing formwork 0 16-Dec-13 A 16-Dec-13 A
Footing C03: Curing Before Pedestal Concreting 0 16-Dec-13 A 22-Dec-13 A
Footing C03: Remove Forms 0 18-Dec-13 A 18-Dec-13 A
Footing C03: Pedestal Concrete Pouring 0 09-Jan-14 A 09-Jan-14 A
Footing C03: Backfill, Compaction & FDT (Initial @ 1.3M) 0 14-Jan-14 A 16-Jan-14 A
Footing C03: Backfill, Compaction & FDT (Final to FGL) 0 29-Jan-14 A 30-Jan-14 A
WTG FOOTING C01 0 14-Oct-13 A 06-Feb-14 A
Footing C01: Survey Layout 0 14-Oct-13 A 15-Oct-13 A
Footing C01: Clearing / Excavation for Foundation Including Access Ramp 0 26-Oct-13 A 06-Nov-13 A
Footing C01: Trench Excavation, Encasement Construction and Conduit Layout 0 07-Nov-13 A 11-Nov-13 A
Footing C01: Lean Concrete Pouring 0 12-Nov-13 A 12-Nov-13 A
Footing C01: Anchor Cage & Shim Plate (Assembly & Installation) 0 25-Nov-13 A 27-Nov-13 A
Footing C01: Install Forms 0 13-Dec-13 A 16-Dec-13 A
Footing C01: Footing Concrete Pouring 0 17-Dec-13 A 17-Dec-13 A
Footing C01: Curing before removing formwork 0 18-Dec-13 A 18-Dec-13 A
Footing C01: Curing Before Pedestal Concreting 0 18-Dec-13 A 26-Dec-13 A
Footing C01: Remove Forms 0 21-Dec-13 A 21-Dec-13 A
Footing C01: Rebar Works Inc. Grounding Wires & Rod Inst. 0 21-Dec-13 A 29-Dec-13 A
Footing C01: Pedestal Concrete Pouring 0 15-Jan-14 A 15-Jan-14 A
Footing C01: Backfill, Compaction & FDT (Initial @ 1.3M) 0 04-Feb-14 A 05-Feb-14 A
Footing C01: Backfill, Compaction & FDT (Final to FGL) 0 06-Feb-14 A 06-Feb-14 A
WTG FOOTING C06 0 16-Oct-13 A 09-Feb-14 A
Footing C06: Clearing / Excavation for Foundation Including Access Ramp 0 16-Oct-13 A 22-Oct-13 A
Footing C06: Survey Layout 0 09-Nov-13 A 09-Nov-13 A
Footing C06: Trench Excavation, Encasement Construction and Conduit Layout 0 22-Dec-13 A 26-Dec-13 A
Footing C06: Lean Concrete Pouring 0 27-Dec-13 A 27-Dec-13 A
Footing C06: Anchor Cage & Shim Plate (Assembly & Installation) 0 28-Dec-13 A 02-Jan-14 A
Footing C06: Rebar Works Inc. Grounding Wires & Rod Inst. 0 03-Jan-14 A 08-Jan-14 A
Footing C06: Install Forms 0 06-Jan-14 A 09-Jan-14 A
Footing C06: Footing Concrete Pouring 0 10-Jan-14 A 10-Jan-14 A
Footing C06: Curing Before Pedestal Concreting 0 11-Jan-14 A 16-Jan-14 A
Footing C06: Curing before removing formwork 0 11-Jan-14 A 11-Jan-14 A
Footing C06: Remove Forms 0 18-Jan-14 A 18-Jan-14 A
Footing C06: Pedestal Concrete Pouring 0 18-Jan-14 A 18-Jan-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 17 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C06: Backfill, Compaction & FDT (Initial @ 1.3M) 0 07-Feb-14 A 08-Feb-14 A
Footing C06: Backfill, Compaction & FDT (Final to FGL) 0 08-Feb-14 A 09-Feb-14 A
WTG FOOTING C08 2 20-Jan-14 A 26-Feb-14 11
Footing C08: Survey Layout 0 20-Jan-14 A 21-Jan-14 A
Footing C08: Clearing / Excavation for Foundation Including Access Ramp 0 22-Jan-14 A 29-Jan-14 A
Footing C08: Trench Excavation, Encasement Construction and Conduit Layout 0 01-Feb-14 A 02-Feb-14 A
Footing C08: Lean Concrete Pouring 0 03-Feb-14 A 03-Feb-14 A
Footing C08: Anchor Cage & Shim Plate (Assembly & Installation) 0 04-Feb-14 A 05-Feb-14 A
Footing C08: Rebar Works Inc. Grounding Wires & Rod Inst. 0 06-Feb-14 A 10-Feb-14 A
Footing C08: Install Forms 0 07-Feb-14 A 10-Feb-14 A
Footing C08: Curing before removing formwork 0 12-Feb-14 A 13-Feb-14 A
Footing C08: Curing Before Pedestal Concreting 0 12-Feb-14 A 16-Feb-14 A
Footing C08: Footing Concrete Pouring 0 14-Feb-14 A 14-Feb-14 A
Footing C08: Remove Forms 0 15-Feb-14 A 15-Feb-14 A
Footing C08: Pedestal Concrete Pouring 0 16-Feb-14 A 17-Feb-14 A
Footing C08: Backfill, Compaction & FDT (Initial @ 1.3M) 1 24-Feb-14 25-Feb-14 11
Footing C08: Backfill, Compaction & FDT (Final to FGL) 1 25-Feb-14 26-Feb-14 11
WTG FOOTING C34 16 23-Dec-13 A 09-Mar-14 7
Footing C34: Survey Layout 0 23-Dec-13 A 26-Dec-13 A TCP issued 19Dec13
Footing C34: Clearing / Excavation for Foundation Including Access Ramp 0 03-Feb-14 A 10-Feb-14 A
Footing C34: Trench Excavation, Encasement Construction and Conduit Layout 0 10-Feb-14 A 12-Feb-14 A
Footing C34: Lean Concrete Pouring 0 12-Feb-14 A 13-Feb-14 A
Footing C34: Anchor Cage & Shim Plate (Assembly & Installation) 0 13-Feb-14 A 16-Feb-14 A
Footing C34: Rebar Works Inc. Grounding Wires & Rod Inst. 3 16-Feb-14 A 23-Feb-14 1
Footing C34: Install Forms 3 21-Feb-14 23-Feb-14 1
Footing C34: Footing Concrete Pouring 1 23-Feb-14 24-Feb-14 1
Footing C34: Curing Before Pedestal Concreting 6 23-Feb-14 01-Mar-14 2
Footing C34: Curing before removing formwork 1 24-Feb-14 25-Feb-14 13
Footing C34: Remove Forms 1 01-Mar-14 02-Mar-14 13
Footing C34: Pedestal Concrete Pouring 1 06-Mar-14 07-Mar-14 2
Footing C34: Backfill, Compaction & FDT (Initial @ 1.3M) 1 07-Mar-14 08-Mar-14 7
Footing C34: Backfill, Compaction & FDT (Final to FGL) 1 08-Mar-14 09-Mar-14 7
WTG FOOTING C15 20 04-Jan-14 A 12-Mar-14 6
Footing C15: Survey Layout 0 04-Jan-14 A 05-Jan-14 A
Footing C15: Clearing / Excavation for Foundation Including Access Ramp 0 06-Jan-14 A 07-Feb-14 A
Footing C15: Trench Excavation, Encasement Construction and Conduit Layout 0 08-Feb-14 A 18-Feb-14 A
Footing C15: Lean Concrete Pouring 0 19-Feb-14 A 19-Feb-14 A
Footing C15: Anchor Cage & Shim Plate (Assembly & Installation) 1 20-Feb-14 A 21-Feb-14 0
Footing C15: Rebar Works Inc. Grounding Wires & Rod Inst. 3 22-Feb-14 24-Feb-14 0
Footing C15: Install Forms 3 22-Feb-14 24-Feb-14 0
Footing C15: Footing Concrete Pouring 1 24-Feb-14 25-Feb-14 1
Footing C15: Curing Before Pedestal Concreting 7 24-Feb-14 03-Mar-14 4
Footing C15: Curing before removing formwork 1 25-Feb-14 26-Feb-14 14
Footing C15: Remove Forms 1 02-Mar-14 03-Mar-14 14
Footing C15: Pedestal Concrete Pouring 1 04-Mar-14 04-Mar-14 4
Footing C15: Backfill, Compaction & FDT (Initial @ 1.3M) 1 10-Mar-14 11-Mar-14 6
Footing C15: Backfill, Compaction & FDT (Final to FGL) 1 11-Mar-14 12-Mar-14 6
WTG FOOTING C44 8 19-Nov-13 A 28-Feb-14 18
Footing C44: Survey Layout 0 19-Nov-13 A 20-Nov-13 A
Footing C44: Clearing / Excavation for Foundation Including Access Ramp 0 21-Jan-14 A 27-Jan-14 A
Footing C44: Trench Excavation, Encasement Construction and Conduit Layout 0 01-Feb-14 A 06-Feb-14 A
Footing C44: Lean Concrete Pouring 0 07-Feb-14 A 07-Feb-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 18 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C44: Anchor Cage & Shim Plate (Assembly & Installation) 0 08-Feb-14 A 11-Feb-14 A
Footing C44: Rebar Works Inc. Grounding Wires & Rod Inst. 0 12-Feb-14 A 17-Feb-14 A
Footing C44: Install Forms 0 15-Feb-14 A 18-Feb-14 A
Footing C44: Footing Concrete Pouring 0 19-Feb-14 A 19-Feb-14 A
Footing C44: Curing before removing formwork 0 20-Feb-14 A 20-Feb-14 A
Footing C44: Curing Before Pedestal Concreting 4 21-Feb-14 24-Feb-14 11
Footing C44: Remove Forms 1 21-Feb-14 21-Feb-14 22
Footing C44: Pedestal Concrete Pouring 1 26-Feb-14 26-Feb-14 10
Footing C44: Backfill, Compaction & FDT (Initial @ 1.3M) 1 26-Feb-14 27-Feb-14 18
Footing C44: Backfill, Compaction & FDT (Final to FGL) 1 27-Feb-14 28-Feb-14 18
SECTION 02 15 03-Jan-14 A 07-Mar-14 17
WTG FOOTING C37 2 03-Jan-14 A 22-Feb-14 30
Footing C37: Survey Layout 0 03-Jan-14 A 04-Jan-14 A TCP issued 20Dec13
Footing C37: Clearing / Excavation for Foundation Including Access Ramp 0 05-Jan-14 A 12-Jan-14 A
Footing C37: Trench Excavation, Encasement Construction and Conduit Layout 0 13-Jan-14 A 14-Jan-14 A
Footing C37: Lean Concrete Pouring 0 15-Jan-14 A 15-Jan-14 A
Footing C37: Anchor Cage & Shim Plate (Assembly & Installation) 0 15-Jan-14 A 17-Jan-14 A
Footing C37: Rebar Works Inc. Grounding Wires & Rod Inst. 0 18-Jan-14 A 21-Jan-14 A
Footing C37: Install Forms 0 18-Jan-14 A 21-Jan-14 A
Footing C37: Footing Concrete Pouring 0 23-Jan-14 A 23-Jan-14 A
Footing C37: Curing before removing formwork 0 24-Jan-14 A 24-Jan-14 A
Footing C37: Curing Before Pedestal Concreting 0 24-Jan-14 A 30-Jan-14 A
Footing C37: Remove Forms 0 31-Jan-14 A 31-Jan-14 A
Footing C37: Pedestal Concrete Pouring 0 31-Jan-14 A 31-Jan-14 A
Footing C37: Backfill, Compaction & FDT (Initial @ 1.3M) 1 21-Feb-14 21-Feb-14 30
Footing C37: Backfill, Compaction & FDT (Final to FGL) 1 22-Feb-14 22-Feb-14 30
WTG FOOTING C45 0 09-Jan-14 A 15-Feb-14 A
Footing C45: Survey Layout 0 09-Jan-14 A 10-Jan-14 A TCP issued 20Dec13
Footing C45: Clearing / Excavation for Foundation Including Access Ramp 0 13-Jan-14 A 18-Jan-14 A
Footing C45: Trench Excavation, Encasement Construction and Conduit Layout 0 19-Jan-14 A 22-Jan-14 A
Footing C45: Lean Concrete Pouring 0 23-Jan-14 A 23-Jan-14 A
Footing C45: Anchor Cage & Shim Plate (Assembly & Installation) 0 24-Jan-14 A 26-Jan-14 A
Footing C45: Rebar Works Inc. Grounding Wires & Rod Inst. 0 29-Jan-14 A 05-Feb-14 A
Footing C45: Install Forms 0 02-Feb-14 A 05-Feb-14 A
Footing C45: Footing Concrete Pouring 0 06-Feb-14 A 07-Feb-14 A
Footing C45: Curing Before Pedestal Concreting 0 06-Feb-14 A 12-Feb-14 A
Footing C45: Curing before removing formwork 0 07-Feb-14 A 08-Feb-14 A
Footing C45: Remove Forms 0 09-Feb-14 A 10-Feb-14 A
Footing C45: Pedestal Concrete Pouring 0 12-Feb-14 A 13-Feb-14 A
Footing C45: Backfill, Compaction & FDT (Initial @ 1.3M) 0 14-Feb-14 A 14-Feb-14 A
Footing C45: Backfill, Compaction & FDT (Final to FGL) 0 14-Feb-14 A 15-Feb-14 A
WTG FOOTING C29 0 18-Jan-14 A 17-Feb-14 A
Footing C29: Survey Layout 0 18-Jan-14 A 18-Jan-14 A TCP issued 20Dec13.
Footing C29: Clearing / Excavation for Foundation Including Access Ramp 0 19-Jan-14 A 23-Jan-14 A
Footing C29: Trench Excavation, Encasement Construction and Conduit Layout 0 24-Jan-14 A 25-Jan-14 A
Footing C29: Lean Concrete Pouring 0 26-Jan-14 A 26-Jan-14 A
Footing C29: Anchor Cage & Shim Plate (Assembly & Installation) 0 27-Jan-14 A 02-Feb-14 A
Footing C29: Rebar Works Inc. Grounding Wires & Rod Inst. 0 03-Feb-14 A 07-Feb-14 A
Footing C29: Install Forms 0 04-Feb-14 A 07-Feb-14 A
Footing C29: Footing Concrete Pouring 0 09-Feb-14 A 10-Feb-14 A
Footing C29: Curing Before Pedestal Concreting 0 09-Feb-14 A 13-Feb-14 A
Footing C29: Curing before removing formwork 0 10-Feb-14 A 10-Feb-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 19 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C29: Remove Forms 0 11-Feb-14 A 11-Feb-14 A


Footing C29: Pedestal Concrete Pouring 0 13-Feb-14 A 14-Feb-14 A
Footing C29: Backfill, Compaction & FDT (Initial @ 1.3M) 0 15-Feb-14 A 16-Feb-14 A
Footing C29: Backfill, Compaction & FDT (Final to FGL) 0 16-Feb-14 A 17-Feb-14 A
WTG FOOTING C25 14 24-Jan-14 A 07-Mar-14 1
Footing C25: Survey Layout 0 24-Jan-14 A 24-Jan-14 A TCP issued 20Dec13. Relocation Issue
Footing C25: Clearing / Excavation for Foundation Including Access Ramp 0 01-Feb-14 A 07-Feb-14 A
Footing C25: Trench Excavation, Encasement Construction and Conduit Layout 0 08-Feb-14 A 09-Feb-14 A
Footing C25: Lean Concrete Pouring 0 10-Feb-14 A 10-Feb-14 A
Footing C25: Anchor Cage & Shim Plate (Assembly & Installation) 0 11-Feb-14 A 12-Feb-14 A
Footing C25: Rebar Works Inc. Grounding Wires & Rod Inst. 0 13-Feb-14 A 20-Feb-14 A
Footing C25: Install Forms 0 15-Feb-14 A 20-Feb-14 A
Footing C25: Footing Concrete Pouring 1 22-Feb-14 22-Feb-14 -1
Footing C25: Curing Before Pedestal Concreting 7 22-Feb-14 28-Feb-14 -1
Footing C25: Curing before removing formwork 1 22-Feb-14 23-Feb-14 8
Footing C25: Remove Forms 1 23-Feb-14 24-Feb-14 7
Footing C25: Pedestal Concrete Pouring 1 01-Mar-14 01-Mar-14 -1
Footing C25: Backfill, Compaction & FDT (Initial @ 1.3M) 1 05-Mar-14 06-Mar-14 1
Footing C25: Backfill, Compaction & FDT (Final to FGL) 1 06-Mar-14 07-Mar-14 1
WTG FOOTING C42 12 22-Jan-14 A 05-Mar-14 2
Footing C42: Survey Layout 0 22-Jan-14 A 22-Jan-14 A TCP issued 20Dec13.
Footing C42: Clearing / Excavation for Foundation Including Access Ramp 0 28-Jan-14 A 08-Feb-14 A
Footing C42: Trench Excavation, Encasement Construction and Conduit Layout 0 09-Feb-14 A 18-Feb-14 A
Footing C42: Lean Concrete Pouring 0 20-Feb-14 A 20-Feb-14 A
Footing C42: Anchor Cage & Shim Plate (Assembly & Installation) 2 21-Feb-14 22-Feb-14 0
Footing C42: Rebar Works Inc. Grounding Wires & Rod Inst. 4 23-Feb-14 27-Feb-14 0
Footing C42: Install Forms 3 24-Feb-14 27-Feb-14 0
Footing C42: Footing Concrete Pouring 1 28-Feb-14 01-Mar-14 -1
Footing C42: Curing Before Pedestal Concreting 1 28-Feb-14 01-Mar-14 -1
Footing C42: Curing before removing formwork 1 01-Mar-14 02-Mar-14 2
Footing C42: Pedestal Concrete Pouring 1 01-Mar-14 02-Mar-14 -1
Footing C42: Remove Forms 1 02-Mar-14 03-Mar-14 2
Footing C42: Backfill, Compaction & FDT (Initial @ 1.3M) 1 03-Mar-14 04-Mar-14 2
Footing C42: Backfill, Compaction & FDT (Final to FGL) 1 04-Mar-14 05-Mar-14 2
SECTION 3A / WEST 0 11-Nov-13 A 08-Feb-14 A
WTG FOOTING C16 0 20-Nov-13 A 27-Jan-14 A
Footing C16: Survey Layout 0 20-Nov-13 A 21-Nov-13 A
Footing C16: Clearing / Excavation for Foundation Including Access Ramp 0 22-Nov-13 A 26-Nov-13 A
Footing C16: Trench Excavation, Encasement Construction and Conduit Layout 0 30-Nov-13 A 01-Dec-13 A
Footing C16: Lean Concrete Pouring 0 02-Dec-13 A 02-Dec-13 A
Footing C16: Anchor Cage & Shim Plate (Assembly & Installation) 0 15-Dec-13 A 17-Dec-13 A
Footing C16: Rebar Works Inc. Grounding Wires & Rod Inst. 0 18-Dec-13 A 23-Dec-13 A
Footing C16: Install Forms 0 21-Dec-13 A 26-Dec-13 A
Footing C16: Footing Concrete Pouring 0 27-Dec-13 A 27-Dec-13 A
Footing C16: Curing before removing formwork 0 28-Dec-13 A 28-Dec-13 A
Footing C16: Curing Before Pedestal Concreting 0 28-Dec-13 A 06-Jan-14 A
Footing C16: Remove Forms 0 08-Jan-14 A 08-Jan-14 A
Footing C16: Pedestal Concrete Pouring 0 12-Jan-14 A 12-Jan-14 A
Footing C16: Backfill, Compaction & FDT (Initial @ 1.3M) 0 16-Jan-14 A 26-Jan-14 A
Footing C16: Backfill, Compaction & FDT (Final to FGL) 0 27-Jan-14 A 27-Jan-14 A
WTG FOOTING C17 0 20-Nov-13 A 06-Feb-14 A
Footing C17: Survey Layout 0 20-Nov-13 A 21-Nov-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 20 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C17: Clearing / Excavation for Foundation Including Access Ramp 0 21-Nov-13 A 26-Nov-13 A
Footing C17: Trench Excavation, Encasement Construction and Conduit Layout 0 14-Dec-13 A 15-Dec-13 A
Footing C17: Lean Concrete Pouring 0 16-Dec-13 A 16-Dec-13 A
Footing C17: Anchor Cage & Shim Plate (Assembly & Installation) 0 17-Dec-13 A 19-Dec-13 A
Footing C17: Rebar Works Inc. Grounding Wires & Rod Inst. 0 20-Dec-13 A 27-Dec-13 A
Footing C17: Install Forms 0 23-Dec-13 A 28-Dec-13 A
Footing C17: Footing Concrete Pouring 0 29-Dec-13 A 29-Dec-13 A
Footing C17: Curing before removing formwork 0 02-Jan-14 A 02-Jan-14 A
Footing C17: Curing Before Pedestal Concreting 0 02-Jan-14 A 08-Jan-14 A
Footing C17: Remove Forms 0 07-Jan-14 A 08-Jan-14 A
Footing C17: Pedestal Concrete Pouring 0 12-Jan-14 A 12-Jan-14 A
Footing C17: Backfill, Compaction & FDT (Initial @ 1.3M) 0 20-Jan-14 A 05-Feb-14 A
Footing C17: Backfill, Compaction & FDT (Final to FGL) 0 05-Feb-14 A 06-Feb-14 A
WTG FOOTING C04 0 19-Nov-13 A 01-Feb-14 A
Footing C04: Survey Layout 0 19-Nov-13 A 19-Nov-13 A
Footing C04: Clearing / Excavation for Foundation Inc. Access Ramp, Add Exc. & Inspect 0 20-Nov-13 A 04-Dec-13 A
Footing C04: Trench Excavation, Encasement Construction and Conduit Layout 0 03-Jan-14 A 04-Jan-14 A
Footing C04: Lean Concrete Pouring 0 05-Jan-14 A 05-Jan-14 A
Footing C04: Anchor Cage & Shim Plate (Assembly & Installation) 0 06-Jan-14 A 08-Jan-14 A
Footing C04: Install Forms 0 12-Jan-14 A 17-Jan-14 A
Footing C04: Rebar Works Inc. Grounding Wires & Rod Inst. 0 13-Jan-14 A 17-Jan-14 A
Footing C04: Footing Concrete Pouring 0 18-Jan-14 A 18-Jan-14 A
Footing C04: Curing before removing formwork 0 19-Jan-14 A 19-Jan-14 A
Footing C04: Curing Before Pedestal Concreting 0 19-Jan-14 A 26-Jan-14 A
Footing C04: Remove Forms 0 29-Jan-14 A 29-Jan-14 A
Footing C04: Backfill, Compaction & FDT (Initial @ 1.3M) 0 30-Jan-14 A 31-Jan-14 A
Footing C04: Pedestal Concrete Pouring 0 30-Jan-14 A 30-Jan-14 A
Footing C04: Backfill, Compaction & FDT (Final to FGL) 0 31-Jan-14 A 01-Feb-14 A
WTG FOOTING C14 0 13-Nov-13 A 05-Feb-14 A
Footing C14: Survey Layout 0 13-Nov-13 A 13-Nov-13 A
Footing C14: Clearing / Excavation for Foundation Inc. Access Ramp, Add Exc. & Inspect 0 24-Nov-13 A 29-Nov-13 A
Footing C14: Trench Excavation, Encasement Construction and Conduit Layout 0 07-Jan-14 A 08-Jan-14 A
Footing C14: Lean Concrete Pouring 0 16-Jan-14 A 16-Jan-14 A
Footing C14: Anchor Cage & Shim Plate (Assembly & Installation) 0 17-Jan-14 A 18-Jan-14 A
Footing C14: Rebar Works Inc. Grounding Wires & Rod Inst. 0 18-Jan-14 A 26-Jan-14 A
Footing C14: Install Forms 0 19-Jan-14 A 26-Jan-14 A
Footing C14: Footing Concrete Pouring 0 27-Jan-14 A 27-Jan-14 A
Footing C14: Curing Before Pedestal Concreting 0 28-Jan-14 A 29-Jan-14 A
Footing C14: Curing before removing formwork 0 28-Jan-14 A 29-Jan-14 A
Footing C14: Remove Forms 0 30-Jan-14 A 30-Jan-14 A
Footing C14: Backfill, Compaction & FDT (Initial @ 1.3M) 0 03-Feb-14 A 04-Feb-14 A
Footing C14: Pedestal Concrete Pouring 0 04-Feb-14 A 04-Feb-14 A
Footing C14: Backfill, Compaction & FDT (Final to FGL) 0 04-Feb-14 A 05-Feb-14 A
WTG FOOTING C09 0 11-Nov-13 A 08-Feb-14 A
Footing C09: Survey Layout 0 11-Nov-13 A 12-Nov-13 A
Footing C09: Clearing / Excavation for Foundation Including Access Ramp 0 28-Dec-13 A 05-Jan-14 A
Footing C09: Trench Excavation, Encasement Construction and Conduit Layout 0 06-Jan-14 A 07-Jan-14 A
Footing C09: Lean Concrete Pouring 0 08-Jan-14 A 08-Jan-14 A
Footing C09: Anchor Cage & Shim Plate (Assembly & Installation) 0 20-Jan-14 A 23-Jan-14 A
Footing C09: Rebar Works Inc. Grounding Wires & Rod Inst. 0 24-Jan-14 A 28-Jan-14 A
Footing C09: Install Forms 0 24-Jan-14 A 28-Jan-14 A
Footing C09: Footing Concrete Pouring 0 29-Jan-14 A 29-Jan-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 21 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C09: Curing before removing formwork 0 30-Jan-14 A 30-Jan-14 A


Footing C09: Curing Before Pedestal Concreting 0 01-Feb-14 A 04-Feb-14 A
Footing C09: Remove Forms 0 03-Feb-14 A 04-Feb-14 A
Footing C09: Backfill, Compaction & FDT (Initial @ 1.3M) 0 06-Feb-14 A 07-Feb-14 A
Footing C09: Backfill, Compaction & FDT (Final to FGL) 0 07-Feb-14 A 08-Feb-14 A
Footing C09: Pedestal Concrete Pouring 0 08-Feb-14 A 08-Feb-14 A
SECTION 3B / EAST 24 04-Nov-13 A 16-Mar-14 8
WTG FOOTING C13 0 06-Nov-13 A 07-Feb-14 A
Footing C13: Survey Layout 0 06-Nov-13 A 06-Nov-13 A
Footing C13: Clearing / Excavation for Foundation Including Access Ramp 0 08-Nov-13 A 16-Nov-13 A
Footing C13: Trench Excavation, Encasement Construction and Conduit Layout 0 20-Nov-13 A 21-Nov-13 A
Footing C13: Lean Concrete Pouring 0 25-Nov-13 A 26-Nov-13 A
Footing C13: Anchor Cage & Shim Plate (Assembly & Installation) 0 08-Dec-13 A 11-Dec-13 A
Footing C13: Rebar Works Inc. Grounding Wires & Rod Inst. 0 12-Dec-13 A 17-Dec-13 A
Footing C13: Install Forms 0 15-Dec-13 A 18-Dec-13 A
Footing C13: Footing Concrete Pouring 0 19-Dec-13 A 19-Dec-13 A
Footing C13: Curing before removing formwork 0 20-Dec-13 A 20-Dec-13 A
Footing C13: Curing Before Pedestal Concreting 0 20-Dec-13 A 28-Dec-13 A
Footing C13: Remove Forms 0 02-Jan-14 A 02-Jan-14 A
Footing C13: Pedestal Concrete Pouring 0 16-Jan-14 A 16-Jan-14 A
Footing C13: Backfill, Compaction & FDT (Initial @ 1.3M) 0 06-Feb-14 A 06-Feb-14 A
Footing C13: Backfill, Compaction & FDT (Final to FGL) 0 07-Feb-14 A 07-Feb-14 A
WTG FOOTING C43 0 04-Nov-13 A 11-Feb-14 A
Footing C43: Survey Layout 0 04-Nov-13 A 05-Nov-13 A
Footing C43: Clearing / Excavation for Foundation Including Access Ramp 0 09-Nov-13 A 14-Nov-13 A
Footing C43: Trench Excavation, Encasement Construction and Conduit Layout 0 14-Nov-13 A 15-Nov-13 A
Footing C43: Lean Concrete Pouring 0 15-Nov-13 A 16-Nov-13 A
Footing C43: Anchor Cage & Shim Plate (Assembly & Installation) 0 11-Dec-13 A 13-Dec-13 A
Footing C43: Rebar Works Inc. Grounding Wires & Rod Inst. 0 14-Dec-13 A 19-Dec-13 A
Footing C43: Install Forms 0 17-Dec-13 A 20-Dec-13 A
Footing C43: Footing Concrete Pouring 0 21-Dec-13 A 21-Dec-13 A
Footing C43: Curing before removing formwork 0 22-Dec-13 A 22-Dec-13 A
Footing C43: Curing Before Pedestal Concreting 0 22-Dec-13 A 02-Jan-14 A
Footing C43: Remove Forms 0 04-Jan-14 A 04-Jan-14 A
Footing C43: Pedestal Concrete Pouring 0 16-Jan-14 A 16-Jan-14 A
Footing C43: Backfill, Compaction & FDT (Initial @ 1.3M) 0 09-Feb-14 A 10-Feb-14 A
Footing C43: Backfill, Compaction & FDT (Final to FGL) 0 10-Feb-14 A 11-Feb-14 A
WTG FOOTING C18 0 15-Nov-13 A 09-Feb-14 A
Footing C18: Survey Layout 0 15-Nov-13 A 15-Nov-13 A
Footing C18: Clearing / Excavation for Foundation Including Access Ramp 0 24-Nov-13 A 29-Nov-13 A
Footing C18: Trench Excavation, Encasement Construction and Conduit Layout 0 28-Dec-13 A 29-Dec-13 A
Footing C18: Lean Concrete Pouring 0 02-Jan-14 A 02-Jan-14 A
Footing C18: Anchor Cage & Shim Plate (Assembly & Installation) 0 03-Jan-14 A 05-Jan-14 A
Footing C18: Install Forms 0 05-Jan-14 A 12-Jan-14 A
Footing C18: Rebar Works Inc. Grounding Wires & Rod Inst. 0 06-Jan-14 A 12-Jan-14 A
Footing C18: Footing Concrete Pouring 0 13-Jan-14 A 13-Jan-14 A
Footing C18: Curing before removing formwork 0 14-Jan-14 A 15-Jan-14 A
Footing C18: Curing Before Pedestal Concreting 0 15-Jan-14 A 21-Jan-14 A
Footing C18: Pedestal Concrete Pouring 0 21-Jan-14 A 21-Jan-14 A
Footing C18: Remove Forms 0 01-Feb-14 A 01-Feb-14 A
Footing C18: Backfill, Compaction & FDT (Initial @ 1.3M) 0 07-Feb-14 A 08-Feb-14 A
Footing C18: Backfill, Compaction & FDT (Final to FGL) 0 08-Feb-14 A 09-Feb-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 22 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

WTG FOOTING C05 0 13-Nov-13 A 13-Feb-14 A


Footing C05: Survey Layout 0 13-Nov-13 A 14-Nov-13 A
Footing C05: Clearing / Excavation for Foundation Including Access Ramp 0 24-Nov-13 A 29-Nov-13 A
Footing C05: Trench Excavation, Encasement Construction and Conduit Layout 0 04-Jan-14 A 05-Jan-14 A
Footing C05: Lean Concrete Pouring 0 06-Jan-14 A 06-Jan-14 A
Footing C05: Anchor Cage & Shim Plate (Assembly & Installation) 0 25-Jan-14 A 27-Jan-14 A
Footing C05: Rebar Works Inc. Grounding Wires & Rod Inst. 0 28-Jan-14 A 05-Feb-14 A
Footing C05: Install Forms 0 30-Jan-14 A 05-Feb-14 A
Footing C05: Footing Concrete Pouring 0 06-Feb-14 A 06-Feb-14 A
Footing C05: Curing Before Pedestal Concreting 0 07-Feb-14 A 07-Feb-14 A
Footing C05: Curing before removing formwork 0 07-Feb-14 A 07-Feb-14 A
Footing C05: Pedestal Concrete Pouring 0 08-Feb-14 A 08-Feb-14 A
Footing C05: Remove Forms 0 10-Feb-14 A 10-Feb-14 A
Footing C05: Backfill, Compaction & FDT (Initial @ 1.3M) 0 11-Feb-14 A 12-Feb-14 A
Footing C05: Backfill, Compaction & FDT (Final to FGL) 0 13-Feb-14 A 13-Feb-14 A
WTG FOOTING C02 24 17-Feb-14 A 16-Mar-14 8
Footing C02: Survey Layout 0 17-Feb-14 A 17-Feb-14 A
Footing C02: Clearing / Excavation for Foundation Including Access Ramp 0 17-Feb-14 A 20-Feb-14 A
Footing C02: Trench Excavation, Encasement Construction and Conduit Layout 1 21-Feb-14 21-Feb-14 5
Footing C02: Lean Concrete Pouring 1 22-Feb-14 22-Feb-14 5
Footing C02: Anchor Cage & Shim Plate (Assembly & Installation) 2 23-Feb-14 24-Feb-14 5
Footing C02: Rebar Works Inc. Grounding Wires & Rod Inst. 4 26-Feb-14 01-Mar-14 5
Footing C02: Install Forms 3 27-Feb-14 01-Mar-14 5
Footing C02: Footing Concrete Pouring 1 01-Mar-14 02-Mar-14 5
Footing C02: Curing Before Pedestal Concreting 7 01-Mar-14 08-Mar-14 5
Footing C02: Curing before removing formwork 1 02-Mar-14 03-Mar-14 15
Footing C02: Remove Forms 1 07-Mar-14 08-Mar-14 15
Footing C02: Pedestal Concrete Pouring 1 09-Mar-14 09-Mar-14 5
Footing C02: Backfill, Compaction & FDT (Initial @ 1.3M) 1 14-Mar-14 15-Mar-14 8
Footing C02: Backfill, Compaction & FDT (Final to FGL) 1 15-Mar-14 16-Mar-14 8
SECTION 04 22 28-Oct-13 A 14-Mar-14 183
WTG FOOTING C48 0 28-Oct-13 A 01-Feb-14 A
Footing C48: Survey Layout 0 28-Oct-13 A 29-Oct-13 A
Footing C48: Clearing / Excavation for Foundation Including Access Ramp 0 28-Oct-13 A 10-Nov-13 A
Footing C48: Lean Concrete Pouring 0 03-Nov-13 A 03-Nov-13 A
Footing C48: Trench Excavation, Encasement Construction and Conduit Layout 0 11-Nov-13 A 12-Nov-13 A
Footing C48: Anchor Cage & Shim Plate (Assembly & Installation) 0 21-Nov-13 A 22-Nov-13 A
Footing C48: Rebar Works Inc. Grounding Wires & Rod Inst. 0 04-Dec-13 A 09-Dec-13 A
Footing C48: Install Forms 0 10-Dec-13 A 12-Dec-13 A
Footing C48: Footing Concrete Pouring 0 13-Dec-13 A 13-Dec-13 A
Footing C48: Curing before removing formwork 0 14-Dec-13 A 14-Dec-13 A
Footing C48: Curing Before Pedestal Concreting 0 14-Dec-13 A 20-Dec-13 A
Footing C48: Remove Forms 0 16-Dec-13 A 16-Dec-13 A
Footing C48: Pedestal Concrete Pouring 0 18-Jan-14 A 18-Jan-14 A
Footing C48: Backfill, Compaction & FDT (Initial @ 1.3M) 0 31-Jan-14 A 31-Jan-14 A
Footing C48: Backfill, Compaction & FDT (Final to FGL) 0 31-Jan-14 A 01-Feb-14 A
WTG FOOTING C12 0 12-Jan-14 A 10-Feb-14 A
Footing C12: Survey Layout 0 12-Jan-14 A 13-Jan-14 A
Footing C12: Clearing / Excavation for Foundation Including Access Ramp 0 16-Jan-14 A 21-Jan-14 A
Footing C12: Trench Excavation, Encasement Construction and Conduit Layout 0 21-Jan-14 A 22-Jan-14 A
Footing C12: Lean Concrete Pouring 0 23-Jan-14 A 23-Jan-14 A
Footing C12: Anchor Cage & Shim Plate (Assembly & Installation) 0 24-Jan-14 A 25-Jan-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 23 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C12: Rebar Works Inc. Grounding Wires & Rod Inst. 0 26-Jan-14 A 31-Jan-14 A
Footing C12: Install Forms 0 26-Jan-14 A 31-Jan-14 A
Footing C12: Curing before removing formwork 0 01-Feb-14 A 01-Feb-14 A
Footing C12: Curing Before Pedestal Concreting 0 01-Feb-14 A 05-Feb-14 A
Footing C12: Footing Concrete Pouring 0 01-Feb-14 A 02-Feb-14 A
Footing C12: Remove Forms 0 02-Feb-14 A 03-Feb-14 A
Footing C12: Pedestal Concrete Pouring 0 05-Feb-14 A 06-Feb-14 A
Footing C12: Backfill, Compaction & FDT (Initial @ 1.3M) 0 08-Feb-14 A 09-Feb-14 A
Footing C12: Backfill, Compaction & FDT (Final to FGL) 0 09-Feb-14 A 10-Feb-14 A
WTG FOOTING C19 5 22-Dec-13 A 25-Feb-14 24
Footing C19: Trench Excavation, Encasement Construction and Conduit Layout 0 22-Dec-13 A 23-Jan-14 A
Footing C19: Survey Layout 0 09-Jan-14 A 10-Jan-14 A
Footing C19: Clearing / Excavation for Foundation Including Access Ramp 0 13-Jan-14 A 21-Jan-14 A
Footing C19: Lean Concrete Pouring 0 04-Feb-14 A 04-Feb-14 A
Footing C19: Anchor Cage & Shim Plate (Assembly & Installation) 0 05-Feb-14 A 09-Feb-14 A
Footing C19: Rebar Works Inc. Grounding Wires & Rod Inst. 0 10-Feb-14 A 15-Feb-14 A
Footing C19: Install Forms 0 13-Feb-14 A 16-Feb-14 A
Footing C19: Footing Concrete Pouring 0 17-Feb-14 A 17-Feb-14 A
Footing C19: Curing before removing formwork 0 18-Feb-14 A 18-Feb-14 A
Footing C19: Curing Before Pedestal Concreting 1 18-Feb-14 A 21-Feb-14 17
Footing C19: Remove Forms 1 21-Feb-14 21-Feb-14 24
Footing C19: Pedestal Concrete Pouring 1 22-Feb-14 22-Feb-14 16
Footing C19: Backfill, Compaction & FDT (Initial @ 1.3M) 1 23-Feb-14 24-Feb-14 24
Footing C19: Backfill, Compaction & FDT (Final to FGL) 1 24-Feb-14 25-Feb-14 24
WTG FOOTING C50 1 03-Jan-14 A 21-Feb-14 22
Footing C50: Survey Layout 0 03-Jan-14 A 04-Jan-14 A
Footing C50: Clearing / Excavation for Foundation Including Access Ramp 0 05-Jan-14 A 20-Jan-14 A
Footing C50: Trench Excavation, Encasement Construction and Conduit Layout 0 21-Jan-14 A 23-Jan-14 A
Footing C50: Lean Concrete Pouring 0 03-Feb-14 A 03-Feb-14 A
Footing C50: Anchor Cage & Shim Plate (Assembly & Installation) 0 04-Feb-14 A 05-Feb-14 A
Footing C50: Rebar Works Inc. Grounding Wires & Rod Inst. 0 06-Feb-14 A 10-Feb-14 A
Footing C50: Install Forms 0 09-Feb-14 A 11-Feb-14 A
Footing C50: Footing Concrete Pouring 0 12-Feb-14 A 12-Feb-14 A
Footing C50: Curing before removing formwork 0 13-Feb-14 A 13-Feb-14 A
Footing C50: Curing Before Pedestal Concreting 0 13-Feb-14 A 16-Feb-14 A
Footing C50: Pedestal Concrete Pouring 0 17-Feb-14 A 17-Feb-14 A
Footing C50: Remove Forms 0 20-Feb-14 A 20-Feb-14 A
Footing C50: Backfill, Compaction & FDT (Initial @ 1.3M) 0 20-Feb-14 A 20-Feb-14 A
Footing C50: Backfill, Compaction & FDT (Final to FGL) 1 21-Feb-14 21-Feb-14 22
WTG FOOTING C35 22 12-Jan-14 A 14-Mar-14 7
Footing C35: Survey Layout 0 12-Jan-14 A 13-Jan-14 A
Footing C35: Clearing / Excavation for Foundation Including Access Ramp 0 14-Jan-14 A 17-Feb-14 A
Footing C35: Trench Excavation, Encasement Construction and Conduit Layout 0 18-Feb-14 A 19-Feb-14 A
Footing C35: Lean Concrete Pouring 0 20-Feb-14 A 20-Feb-14 A
Footing C35: Anchor Cage & Shim Plate (Assembly & Installation) 2 21-Feb-14 22-Feb-14 -1
Footing C35: Rebar Works Inc. Grounding Wires & Rod Inst. 3 23-Feb-14 26-Feb-14 -1
Footing C35: Install Forms 2 24-Feb-14 26-Feb-14 -1
Footing C35: Footing Concrete Pouring 1 26-Feb-14 27-Feb-14 -1
Footing C35: Curing Before Pedestal Concreting 7 26-Feb-14 05-Mar-14 5
Footing C35: Curing before removing formwork 1 27-Feb-14 28-Feb-14 15
Footing C35: Remove Forms 1 02-Mar-14 02-Mar-14 15
Footing C35: Pedestal Concrete Pouring 1 06-Mar-14 06-Mar-14 5

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 24 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C35: Backfill, Compaction & FDT (Initial @ 1.3M) 1 12-Mar-14 13-Mar-14 7
Footing C35: Backfill, Compaction & FDT (Final to FGL) 1 13-Mar-14 14-Mar-14 7
WTG FOOTINGS CONCRETE CURING (PRIOR TO BASE / MID TOWER ERECTION & TURBINE STARTUP) 46 10-Jan-14 A 07-Apr-14 77
SECTION 01 44 10-Jan-14 A 05-Apr-14 41
WTG FOOTING C22 1 10-Jan-14 A 23-Mar-14 50
Footing C22: Concrete Curing Prior to B & M Tower Erection 0 10-Jan-14 A 16-Jan-14 A
Footing C22: Concrete Curing Prior to Turbine Startup 0 10-Jan-14 A 06-Feb-14 A
Footing C22: Pedestal Cleaning/Certified for Tower Base Grouting 1 23-Mar-14 23-Mar-14 0
WTG FOOTING C07 1 16-Jan-14 A 13-Mar-14 58
Footing C07: Concrete Curing Prior to Turbine Startup 0 16-Jan-14 A 12-Feb-14 A
Footing C07: Concrete Curing Prior to B & M Tower Erection 0 16-Jan-14 A 22-Jan-14 A
Footing C07: Pedestal Cleaning/Certified for Tower Base Grouting 1 13-Mar-14 13-Mar-14 0
WTG FOOTING C03 1 10-Jan-14 A 09-Mar-14 67
Footing C03: Concrete Curing Prior to B & M Tower Erection 0 10-Jan-14 A 16-Jan-14 A
Footing C03: Concrete Curing Prior to Turbine Startup 0 10-Jan-14 A 06-Feb-14 A
Footing C03: Pedestal Cleaning/Certified for Tower Base Grouting 1 09-Mar-14 09-Mar-14 0
WTG FOOTING C01 1 16-Jan-14 A 09-Mar-14 61
Footing C01: Concrete Curing Prior to B & M Tower Erection 0 16-Jan-14 A 22-Jan-14 A
Footing C01: Concrete Curing Prior to Turbine Startup 0 16-Jan-14 A 12-Feb-14 A
Footing C01: Pedestal Cleaning/Certified for Tower Base Grouting 1 09-Mar-14 09-Mar-14 0
WTG FOOTING C06 1 19-Jan-14 A 17-Mar-14 51
Footing C06: Concrete Curing Prior to B & M Tower Erection 0 19-Jan-14 A 25-Jan-14 A
Footing C06: Concrete Curing Prior to Turbine Startup 0 19-Jan-14 A 15-Feb-14 A
Footing C06: Pedestal Cleaning/Certified for Tower Base Grouting 1 17-Mar-14 17-Mar-14 0
WTG FOOTING C08 25 18-Feb-14 A 17-Mar-14 45
Footing C08: Concrete Curing Prior to B & M Tower Erection 4 18-Feb-14 A 24-Feb-14 12
Footing C08: Concrete Curing Prior to Turbine Startup 25 18-Feb-14 A 17-Mar-14 45
Footing C08: Pedestal Cleaning/Certified for Tower Base Grouting 1 09-Mar-14 09-Mar-14 0
WTG FOOTING C34 28 08-Mar-14 05-Apr-14 27
Footing C34: Concrete Curing Prior to B & M Tower Erection 7 08-Mar-14 15-Mar-14 2
Footing C34: Concrete Curing Prior to Turbine Startup 28 08-Mar-14 05-Apr-14 27
Footing C34: Pedestal Cleaning/Certified for Tower Base Grouting 1 17-Mar-14 17-Mar-14 0
WTG FOOTING C15 28 05-Mar-14 02-Apr-14 29
Footing C15: Concrete Curing Prior to B & M Tower Erection 7 05-Mar-14 12-Mar-14 4
Footing C15: Concrete Curing Prior to Turbine Startup 28 05-Mar-14 02-Apr-14 29
Footing C15: Pedestal Cleaning/Certified for Tower Base Grouting 1 17-Mar-14 17-Mar-14 0
WTG FOOTING C44 28 27-Feb-14 27-Mar-14 35
Footing C44: Concrete Curing Prior to B & M Tower Erection 7 27-Feb-14 06-Mar-14 10
Footing C44: Concrete Curing Prior to Turbine Startup 28 27-Feb-14 27-Mar-14 35
Footing C44: Pedestal Cleaning/Certified for Tower Base Grouting 1 17-Mar-14 17-Mar-14 0
SECTION 02 38 01-Feb-14 A 31-Mar-14 59
WTG FOOTING C37 31 01-Feb-14 A 23-Mar-14 61
Footing C37: Concrete Curing Prior to B & M Tower Erection 0 01-Feb-14 A 07-Feb-14 A
Footing C37: Concrete Curing Prior to Turbine Startup 8 01-Feb-14 A 28-Feb-14 84
Footing C37: Pedestal Cleaning/Certified for Tower Base Grouting 1 23-Mar-14 23-Mar-14 0
WTG FOOTING C45 21 14-Feb-14 A 13-Mar-14 70
Footing C45: Concrete Curing Prior to B & M Tower Erection 0 14-Feb-14 A 20-Feb-14 A
Footing C45: Concrete Curing Prior to Turbine Startup 21 14-Feb-14 A 13-Mar-14 70
Footing C45: Pedestal Cleaning/Certified for Tower Base Grouting 1 04-Mar-14 04-Mar-14 0
WTG FOOTING C29 22 15-Feb-14 A 14-Mar-14 72
Footing C29: Concrete Curing Prior to B & M Tower Erection 1 15-Feb-14 A 21-Feb-14 10
Footing C29: Concrete Curing Prior to Turbine Startup 22 15-Feb-14 A 14-Mar-14 72

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 25 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Footing C29: Pedestal Cleaning/Certified for Tower Base Grouting 1 04-Mar-14 04-Mar-14 0
WTG FOOTING C42 29 02-Mar-14 31-Mar-14 58
Footing C42: Concrete Curing Prior to B & M Tower Erection 7 02-Mar-14 09-Mar-14 -1
Footing C42: Concrete Curing Prior to Turbine Startup 28 03-Mar-14 31-Mar-14 58
Footing C42: Pedestal Cleaning/Certified for Tower Base Grouting 1 09-Mar-14 10-Mar-14 -1
WTG FOOTING C25 28 02-Mar-14 30-Mar-14 59
Footing C25: Concrete Curing Prior to B & M Tower Erection 7 02-Mar-14 09-Mar-14 -1
Footing C25: Concrete Curing Prior to Turbine Startup 28 02-Mar-14 30-Mar-14 59
Footing C25: Pedestal Cleaning/Certified for Tower Base Grouting 1 09-Mar-14 10-Mar-14 -1
SECTION 3A / WEST 31 13-Jan-14 A 23-Mar-14 92
WTG FOOTING C16 1 13-Jan-14 A 27-Feb-14 116
Footing C16: Concrete Curing Prior to B & M Tower Erection 0 13-Jan-14 A 19-Jan-14 A
Footing C16: Concrete Curing Prior to Turbine Startup 0 13-Jan-14 A 09-Feb-14 A
Footing C16: Pedestal Cleaning/Certified for Tower Base Grouting 1 27-Feb-14 27-Feb-14 0
WTG FOOTING C17 31 13-Jan-14 A 23-Mar-14 81
Footing C17: Concrete Curing Prior to B & M Tower Erection 0 13-Jan-14 A 19-Jan-14 A
Footing C17: Concrete Curing Prior to Turbine Startup 9 13-Jan-14 A 01-Mar-14 103
Footing C17: Pedestal Cleaning/Certified for Tower Base Grouting 1 23-Mar-14 23-Mar-14 0
WTG FOOTING C04 7 31-Jan-14 A 27-Feb-14 105
Footing C04: Concrete Curing Prior to B & M Tower Erection 0 31-Jan-14 A 06-Feb-14 A
Footing C04: Concrete Curing Prior to Turbine Startup 7 31-Jan-14 A 27-Feb-14 105
Footing C04: Pedestal Cleaning/Certified for Tower Base Grouting 1 27-Feb-14 27-Feb-14 0
WTG FOOTING C14 12 05-Feb-14 A 04-Mar-14 100
Footing C14: Concrete Curing Prior to B & M Tower Erection 0 05-Feb-14 A 11-Feb-14 A
Footing C14: Concrete Curing Prior to Turbine Startup 12 05-Feb-14 A 04-Mar-14 100
Footing C14: Pedestal Cleaning/Certified for Tower Base Grouting 1 27-Feb-14 27-Feb-14 0
WTG FOOTING C09 16 09-Feb-14 A 08-Mar-14 96
Footing C09: Concrete Curing Prior to B & M Tower Erection 0 09-Feb-14 A 15-Feb-14 A
Footing C09: Concrete Curing Prior to Turbine Startup 16 09-Feb-14 A 08-Mar-14 96
Footing C09: Pedestal Cleaning/Certified for Tower Base Grouting 1 27-Feb-14 27-Feb-14 0
SECTION 3B / EAST 46 17-Jan-14 A 07-Apr-14 74
WTG FOOTING C13 1 17-Jan-14 A 13-Mar-14 56
Footing C13: Concrete Curing Prior to B & M Tower Erection 0 17-Jan-14 A 23-Jan-14 A
Footing C13: Concrete Curing Prior to Turbine Startup 0 17-Jan-14 A 13-Feb-14 A
Footing C13: Pedestal Cleaning/Certified for Tower Base Grouting 1 13-Mar-14 13-Mar-14 0
WTG FOOTING C43 1 17-Jan-14 A 13-Mar-14 99
Footing C43: Concrete Curing Prior to B & M Tower Erection 0 17-Jan-14 A 23-Jan-14 A
Footing C43: Concrete Curing Prior to Turbine Startup 0 17-Jan-14 A 13-Feb-14 A
Footing C43: Pedestal Cleaning/Certified for Tower Base Grouting 1 13-Mar-14 13-Mar-14 0
WTG FOOTING C18 21 22-Jan-14 A 13-Mar-14 91
Footing C18: Concrete Curing Prior to B & M Tower Erection 0 22-Jan-14 A 28-Jan-14 A
Footing C18: Concrete Curing Prior to Turbine Startup 18 22-Jan-14 A 10-Mar-14 94
Footing C18: Pedestal Cleaning/Certified for Tower Base Grouting 1 13-Mar-14 13-Mar-14 0
WTG FOOTING C05 31 09-Feb-14 A 23-Mar-14 81
Footing C05: Concrete Curing Prior to B & M Tower Erection 0 09-Feb-14 A 15-Feb-14 A
Footing C05: Concrete Curing Prior to Turbine Startup 16 09-Feb-14 A 08-Mar-14 96
Footing C05: Pedestal Cleaning/Certified for Tower Base Grouting 1 23-Mar-14 23-Mar-14 0
WTG FOOTING C02 28 10-Mar-14 07-Apr-14 66
Footing C02: Concrete Curing Prior to B & M Tower Erection 7 10-Mar-14 17-Mar-14 5
Footing C02: Concrete Curing Prior to Turbine Startup 28 10-Mar-14 07-Apr-14 66
Footing C02: Pedestal Cleaning/Certified for Tower Base Grouting 1 23-Mar-14 23-Mar-14 0
SECTION 04 43 19-Jan-14 A 04-Apr-14 75

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 26 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

WTG FOOTING C48 1 19-Jan-14 A 27-Feb-14 111


Footing C48: Concrete Curing Prior to B & M Tower Erection 0 19-Jan-14 A 25-Jan-14 A
Footing C48: Concrete Curing Prior to Turbine Startup 0 19-Jan-14 A 15-Feb-14 A
Footing C48: Pedestal Cleaning/Certified for Tower Base Grouting 1 27-Feb-14 27-Feb-14 0
WTG FOOTING C12 28 07-Feb-14 A 20-Mar-14 84
Footing C12: Concrete Curing Prior to B & M Tower Erection 0 07-Feb-14 A 13-Feb-14 A
Footing C12: Concrete Curing Prior to Turbine Startup 14 07-Feb-14 A 06-Mar-14 98
Footing C12: Pedestal Cleaning/Certified for Tower Base Grouting 1 20-Mar-14 20-Mar-14 0
WTG FOOTING C19 28 23-Feb-14 23-Mar-14 81
Footing C19: Concrete Curing Prior to B & M Tower Erection 7 23-Feb-14 02-Mar-14 17
Footing C19: Concrete Curing Prior to Turbine Startup 28 23-Feb-14 23-Mar-14 81
Footing C19: Pedestal Cleaning/Certified for Tower Base Grouting 1 20-Mar-14 20-Mar-14 0
WTG FOOTING C50 28 18-Feb-14 A 20-Mar-14 84
Footing C50: Concrete Curing Prior to B & M Tower Erection 4 18-Feb-14 A 24-Feb-14 23
Footing C50: Concrete Curing Prior to Turbine Startup 25 18-Feb-14 A 17-Mar-14 87
Footing C50: Pedestal Cleaning/Certified for Tower Base Grouting 1 20-Mar-14 20-Mar-14 0
WTG FOOTING C35 28 07-Mar-14 04-Apr-14 69
Footing C35: Concrete Curing Prior to B & M Tower Erection 7 07-Mar-14 14-Mar-14 5
Footing C35: Concrete Curing Prior to Turbine Startup 28 07-Mar-14 04-Apr-14 69
Footing C35: Pedestal Cleaning/Certified for Tower Base Grouting 1 20-Mar-14 20-Mar-14 0
ROADS / SITE TRACKS / DRAINAGE / SLOPE STABILIZATION 97 05-Sep-13 A 28-May-14 15
ROADS / SITE TRACKS 23 05-Sep-13 A 15-Mar-14 9
SECTION 01 0 05-Sep-13 A 16-Feb-14 A
C44-OCEAN DRIVE: ROADS / SITE TRACKS 0 12-Sep-13 A 16-Feb-14 A
Track.8A (C44-OD): Survey & Layout 0 12-Sep-13 A 13-Sep-13 A
Track.8A (C44-OD): Clearing, Grubbing, Tree Cutting, Piloting 0 03-Nov-13 A 10-Nov-13 A
Track.8A (C44-OD): Subgrade / Cut & Fill 0 07-Dec-13 A 11-Dec-13 A
Track.8A (C44-OD): Sub-Base Spreading & Compaction 0 13-Jan-14 A 15-Jan-14 A
C44-OD: Road Base Course Spreading & Compaction 0 11-Feb-14 A 16-Feb-14 A
C15-C44: ROADS / SITE TRACKS 0 08-Sep-13 A 15-Feb-14 A
Track.08 (C15-C44): Survey & Layout 0 08-Sep-13 A 09-Sep-13 A
Track.08 (C15-C44): Clearing, Grubbing, Tree Cutting, Piloting 0 29-Oct-13 A 11-Nov-13 A
Track.08 (C15-C44): Subgrade / Cut & Fill 0 02-Dec-13 A 04-Dec-13 A
Track.08 (C15-C44): Sub-Base Spreading & Compaction 0 11-Jan-14 A 12-Jan-14 A
C15-C44: Road Base Course Spreading & Compaction 0 12-Feb-14 A 15-Feb-14 A
C34-C15: ROADS / SITE TRACKS 0 08-Sep-13 A 15-Feb-14 A
Track.07 (C34-C15): Survey & Layout 0 08-Sep-13 A 09-Sep-13 A
Track.07 (C34-C15): Clearing, Grubbing, Tree Cutting, Piloting 0 19-Oct-13 A 23-Oct-13 A
Track.07 (C34-C15/ED): Subgrade / Cut & Fill 0 02-Dec-13 A 04-Dec-13 A
Track.07 (C34-C15): Sub-Base Spreading & Compaction 0 12-Jan-14 A 13-Jan-14 A
C34-C15: Road Base Course Spreading & Compaction 0 12-Feb-14 A 15-Feb-14 A
C07-C34: ROADS / SITE TRACKS 0 07-Sep-13 A 15-Feb-14 A
Track.06 (C07-C34): Survey & Layout 0 07-Sep-13 A 08-Sep-13 A
Track.06 (C07-C34): Clearing, Grubbing, Tree Cutting, Piloting 0 14-Oct-13 A 18-Oct-13 A
Track.06 (C07-C34/ED): Subgrade / Cut & Fill 0 04-Nov-13 A 09-Nov-13 A
Track.06 (C07-C34): Sub-Base Spreading & Compaction 0 09-Jan-14 A 11-Jan-14 A
C07-C34: Road Base Course Spreading & Compaction 0 13-Feb-14 A 15-Feb-14 A
C03-C07: ROADS / SITE TRACKS 0 07-Sep-13 A 15-Feb-14 A
Track.05 (C03-C07): Survey & Layout 0 07-Sep-13 A 08-Sep-13 A
Track.05 (C03-C07): Clearing, Grubbing, Tree Cutting, Piloting 0 26-Sep-13 A 30-Sep-13 A
Track.05 (C03-C07/ED): Subgrade / Cut & Fill 0 04-Nov-13 A 04-Dec-13 A
Track.05 (C03-C07): Sub-Base Spreading & Compaction 0 01-Dec-13 A 08-Jan-14 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 27 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C03-C07: Road Base Course Spreading & Compaction 0 09-Feb-14 A 15-Feb-14 A


C08-C03: ROADS / SITE TRACKS 0 06-Sep-13 A 08-Feb-14 A
Track.03 (C08-C03): Survey & Layout 0 06-Sep-13 A 07-Sep-13 A TCP issued 20Dec13
Track.03 (C08-C03/ED): Clearing, Grubbing, Tree Cutting, Piloting 0 26-Sep-13 A 13-Jan-14 A
Track.03 (C08-C03): Subgrade / Cut & Fill 0 26-Sep-13 A 17-Jan-14 A
Track.03 (C08-C03): Sub-Base Spreading & Compaction 0 02-Feb-14 A 04-Feb-14 A
C08-C03: Road Base Course Spreading & Compaction 0 05-Feb-14 A 08-Feb-14 A
C22-C08: ROADS / SITE TRACKS 0 05-Sep-13 A 08-Feb-14 A
Track.02 (C22-C08): Survey & Layout 0 05-Sep-13 A 06-Sep-13 A
Track.02 (C22-C08): Clearing, Grubbing, Tree Cutting, Piloting 0 26-Sep-13 A 27-Sep-13 A
Track.02 (C22-C08): Subgrade / Cut & Fill 0 27-Sep-13 A 11-Nov-13 A
Track.02 (C22-C08): Sub-Base Spreading & Compaction 0 05-Jan-14 A 08-Jan-14 A
C22-C08: Road Base Course Spreading & Compaction 0 05-Feb-14 A 08-Feb-14 A
C03-C01: ROADS / SITE TRACKS 0 06-Sep-13 A 15-Feb-14 A
Track.04 (C03-C01): Survey & Layout 0 06-Sep-13 A 07-Sep-13 A
Track.04 (C03-C01): Clearing, Grubbing, Tree Cutting, Piloting 0 26-Sep-13 A 30-Sep-13 A
Track.04 (C03-C01/R18): Subgrade / Cut & Fill 0 22-Oct-13 A 04-Dec-13 A
Track.04 (C03-C01): Sub-Base Spreading & Compaction 0 10-Feb-14 A 12-Feb-14 A
C03-C01: Road Base Course Spreading & Compaction 0 13-Feb-14 A 15-Feb-14 A
EAST DRIVE-C06: ROADS / SITE TRACKS 0 09-Sep-13 A 13-Feb-14 A
Track.09 (ED-C06): Survey & Layout 0 09-Sep-13 A 10-Sep-13 A
Track.09 (ED-C06): Clearing, Grubbing, Tree Cutting, Piloting 0 26-Oct-13 A 30-Oct-13 A
Track.09 (ED-C06): Subgrade / Cut & Fill 0 10-Jan-14 A 14-Jan-14 A
Track.09 (ED-C06): Sub-Base Spreading & Compaction 0 08-Feb-14 A 10-Feb-14 A
ED-C06: Road Base Course Spreading & Compaction 0 11-Feb-14 A 13-Feb-14 A
SECTION 02 0 05-Sep-13 A 15-Feb-14 A
NATIONAL HUGHWAY-C22: ROADS / SITE TRACKS 0 05-Sep-13 A 12-Feb-14 A
Track.01 (N.HWay-C22): Survey & Layout 0 05-Sep-13 A 06-Sep-13 A TCP issued 20Dec13
Track.01 (N.HWay-C22/ED): Clearing, Grubbing, Tree Cutting, Piloting 0 26-Sep-13 A 30-Sep-13 A
Track.01 (N.HWay-C22): Subgrade / Cut & Fill 0 26-Sep-13 A 09-Jan-14 A
Track.01 (N.HWay-C22): Sub-Base Spreading & Compaction 0 08-Jan-14 A 11-Jan-14 A
N.HWay-C22: Road Base Course Spreading & Compaction 0 01-Feb-14 A 12-Feb-14 A
EAST DRIVE-C37: ROADS / SITE TRACKS 0 09-Sep-13 A 11-Feb-14 A
Track.10 (ED-C37/R22): Survey & Layout 0 09-Sep-13 A 10-Sep-13 A TCP issued 20Dec13
Track.10 (ED-C37/R22): Clearing, Grubbing, Tree Cutting, Piloting 0 20-Dec-13 A 26-Dec-13 A
Track.10 (ED-C37): Subgrade / Cut & Fill 0 01-Feb-14 A 03-Feb-14 A
Track.10 (ED-C37): Sub-Base Spreading & Compaction 0 04-Feb-14 A 06-Feb-14 A
ED-C37: Road Base Course Spreading & Compaction 0 09-Feb-14 A 11-Feb-14 A
C37-C45: ROADS / SITE TRACKS 0 11-Sep-13 A 11-Feb-14 A
C37-C45/R22: Survey & Layout 0 11-Sep-13 A 13-Sep-13 A TCP issued 20Dec13
C37-C45/R22: Clearing, Grubbing, Tree Cutting, Piloting 0 27-Dec-13 A 03-Jan-14 A
C37-C45/R22: Subgrade / Cut & Fill 0 06-Feb-14 A 07-Feb-14 A
C37-C45/R22: Sub-Base Spreading & Compaction 0 08-Feb-14 A 09-Feb-14 A
C37-C45/R22: Road Base Course Spreading & Compaction 0 10-Feb-14 A 11-Feb-14 A
EAST DRIVE-C29: ROADS / SITE TRACKS 0 12-Sep-13 A 08-Feb-14 A
Track.12 (ED-C29): Survey & Layout 0 12-Sep-13 A 13-Sep-13 A TCP issued 20Dec13
Track.12 (ED-C29/R23): Clearing, Grubbing, Tree Cutting, Piloting 0 11-Jan-14 A 18-Jan-14 A
Track.12 (ED-C29): Subgrade / Cut & Fill 0 25-Jan-14 A 01-Feb-14 A
Track.12 (ED-C29): Sub-Base Spreading & Compaction 0 03-Feb-14 A 05-Feb-14 A
ED-C29: Road Base Course Spreading & Compaction 0 06-Feb-14 A 08-Feb-14 A
EAST DRIVE-C25: ROADS / SITE TRACKS 0 13-Sep-13 A 15-Feb-14 A
Track.13 (ED-C25): Survey & Layout 0 13-Sep-13 A 14-Sep-13 A TCP issued 20Dec13

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 28 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Track.13 (ED-C25/R21): Clearing, Grubbing, Tree Cutting, Piloting 0 13-Jan-14 A 19-Jan-14 A


Track.13 (ED-C25): Subgrade / Cut & Fill 0 15-Jan-14 A 10-Feb-14 A
Track.13 (ED-C25): Sub-Base Spreading & Compaction 0 12-Feb-14 A 12-Feb-14 A
ED-C25: Road Base Course Spreading & Compaction 0 14-Feb-14 A 15-Feb-14 A
C25-C42: ROADS / SITE TRACKS 0 14-Sep-13 A 15-Feb-14 A
Track.14 (C25-C42): Survey & Layout 0 14-Sep-13 A 15-Sep-13 A TCP issued 20Dec13
Track.14 (C25-C42): Subgrade / Cut & Fill 0 15-Jan-14 A 10-Feb-14 A
Track.14 (C25-C42/R21): Clearing, Grubbing, Tree Cutting, Piloting 0 15-Jan-14 A 18-Jan-14 A
Track.14 (C25-C42): Sub-Base Spreading & Compaction 0 12-Feb-14 A 13-Feb-14 A
C25-C42: Road Base Course Spreading & Compaction 0 14-Feb-14 A 15-Feb-14 A
SECTION 3A / WEST 0 15-Sep-13 A 04-Feb-14 A
OCEAN DRIVE-C14: ROADS / SITE TRACKS 0 16-Sep-13 A 31-Jan-14 A
Track.16 (OD-C14/WD): Survey & Layout 0 16-Sep-13 A 17-Sep-13 A
Track.16 (OD-C14/WD): Clearing, Grubbing, Tree Cutting, Piloting 0 16-Oct-13 A 06-Nov-13 A
Track.16 (OD-C14/WD): Subgrade / Cut & Fill 0 04-Nov-13 A 01-Dec-13 A
Track.16 (OD-C14/WD): Sub-Base Spreading & Compaction 0 27-Dec-13 A 25-Jan-14 A
OD-C14/WD: Road Base Course Spreading & Compaction 0 26-Jan-14 A 31-Jan-14 A
C16-C17: ROADS / SITE TRACKS 0 19-Sep-13 A 31-Jan-14 A
Track.19 (C16-C17): Survey & Layout 0 19-Sep-13 A 20-Sep-13 A
Track.19 (C16-C17): Clearing, Grubbing, Tree Cutting, Piloting 0 17-Nov-13 A 19-Nov-13 A
Track.19 (C16-C17): Subgrade / Cut & Fill 0 25-Nov-13 A 17-Dec-13 A
Track.19 (C16-C17): Sub-Base Spreading & Compaction 0 18-Dec-13 A 26-Dec-13 A
C16-C17: Road Base Course Spreading & Compaction 0 27-Jan-14 A 31-Jan-14 A
C16-C14: ROADS / SITE TRACKS 0 18-Sep-13 A 30-Jan-14 A
Track.18 (C16-C14/WD): Survey & Layout 0 18-Sep-13 A 19-Sep-13 A
Track.18 (C16-C14/WD): Clearing, Grubbing, Tree Cutting, Piloting 0 13-Nov-13 A 16-Nov-13 A
Track.18 (C16-C14/WD): Subgrade / Cut & Fill 0 14-Nov-13 A 21-Dec-13 A
Track.18 (C16-C14/WD): Sub-Base Spreading & Compaction 0 07-Jan-14 A 11-Jan-14 A
C16-C14/WD: Road Base Course Spreading & Compaction 0 29-Jan-14 A 30-Jan-14 A
C14-C04: ROADS / SITE TRACKS 0 17-Sep-13 A 02-Feb-14 A
Track.17 (C14-C04): Survey & Layout 0 17-Sep-13 A 18-Sep-13 A
Track.17 (C14-C04): Grubbing, Tree Cutting, Piloting 0 07-Nov-13 A 08-Nov-13 A
Track.17 (C14-C04/R7): Subgrade / Cut & Fill 0 28-Nov-13 A 19-Dec-13 A
Track.17 (C14-C04/R7): Sub-Base Spreading & Compaction 0 29-Jan-14 A 31-Jan-14 A
C14-C04/R7: Road Base Course Spreading & Compaction 0 31-Jan-14 A 02-Feb-14 A
WEST DRIVE-C09: ROADS / SITE TRACKS 0 15-Sep-13 A 04-Feb-14 A
Track.15 (WD-C09): Survey & Layout 0 15-Sep-13 A 16-Oct-13 A
Track.15 (WD-C09): Clearing, Grubbing, Tree Cutting, Piloting 0 25-Oct-13 A 30-Oct-13 A
Track.15 (WD-C09/R5): Subgrade / Cut & Fill 0 10-Dec-13 A 22-Dec-13 A
Track.15 (WD-C09/R5): Sub-Base Spreading & Compaction 0 31-Jan-14 A 01-Feb-14 A
WD-C09/R5: Road Base Course Spreading & Compaction 0 02-Feb-14 A 04-Feb-14 A
SECTION 3B / EAST 6 20-Sep-13 A 15-Mar-14 9
OCEAN DRIVE-C18: ROADS / SITE TRACKS 0 20-Sep-13 A 28-Jan-14 A
Track.20 (OD-C18): Survey & Layout 0 20-Sep-13 A 21-Sep-13 A
Track.20 (OD-C18): Clearing, Grubbing, Tree Cutting, Piloting 0 18-Nov-13 A 20-Nov-13 A
Track.20 (OD-C18): Subgrade / Cut & Fill 0 10-Dec-13 A 22-Dec-13 A
Track.20 (OD-C18): Sub-Base Spreading & Compaction 0 23-Dec-13 A 25-Jan-14 A
OD-C18: Road Base Course Spreading & Compaction 0 26-Jan-14 A 28-Jan-14 A
C18-C13: ROADS / SITE TRACKS 0 21-Sep-13 A 10-Feb-14 A
Track.21 (C18-C13): Survey & Layout 0 21-Sep-13 A 22-Sep-13 A
Track.21 (C18-C13): Clearing, Grubbing, Tree Cutting, Piloting 0 15-Nov-13 A 17-Nov-13 A
Track.21 (C18-C13): Subgrade / Cut & Fill 0 14-Dec-13 A 18-Dec-13 A

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 29 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Track.21 (C18-C13): Sub-Base Spreading & Compaction 0 19-Dec-13 A 21-Dec-13 A


C18-C13: Road Base Course Spreading & Compaction 0 09-Feb-14 A 10-Feb-14 A
OCEAN DRIVE-C43: ROADS / SITE TRACKS 0 23-Sep-13 A 11-Jan-14 A
Track.23 (OD-C43): Survey & Layout 0 23-Sep-13 A 24-Sep-13 A
Track.23 (OD-C43): Clearing, Grubbing, Tree Cutting, Piloting 0 28-Oct-13 A 31-Oct-13 A
Track.23 (OD-C43/R1A): Subgrade / Cut & Fill 0 02-Dec-13 A 06-Dec-13 A
Track.23 (OD-C43): Sub-Base Spreading & Compaction 0 04-Jan-14 A 07-Jan-14 A
OD-C43: Road Base Course Spreading & Compaction 0 08-Jan-14 A 11-Jan-14 A
OCEAN DRIVE-C05: ROADS / SITE TRACKS 0 24-Sep-13 A 18-Feb-14 A
Track.24 (OD-C05): Survey & Layout 0 24-Sep-13 A 25-Sep-13 A
Track.24 (OD-C05): Clearing, Grubbing, Tree Cutting, Piloting 0 13-Nov-13 A 18-Nov-13 A
Track.24 OD-C05): Subgrade / Cut & Fill 0 13-Nov-13 A 17-Jan-14 A
Track.24 (OD-C05): Sub-Base Spreading & Compaction 0 01-Feb-14 A 02-Feb-14 A
OD-C05: Road Base Course Spreading & Compaction 0 17-Feb-14 A 18-Feb-14 A
C13-C02: ROADS / SITE TRACKS 6 22-Sep-13 A 15-Mar-14 0
C13-C02: Survey & Layout 0 22-Sep-13 A 23-Sep-13 A
C13-C02: Clearing, Grubbing, Tree Cutting, Piloting 0 14-Nov-13 A 17-Nov-13 A
C13-C02: Subgrade / Cut & Fill 2 10-Mar-14 11-Mar-14 0
C13-C02: Sub-Base Spreading & Compaction 2 12-Mar-14 13-Mar-14 0
C13-C02: Road Base Course Spreading & Compaction 2 14-Mar-14 15-Mar-14 0
SECTION 04 21 20-Oct-13 A 14-Mar-14 7
OCEAN DRIVE-C48: ROADS / SITE TRACKS 0 20-Oct-13 A 02-Feb-14 A
Track.29 (OD-C48): Survey & Layout 0 20-Oct-13 A 22-Oct-13 A
Track.29 (OD-C48): Clearing, Grubbing, Tree Cutting, Piloting 0 24-Oct-13 A 26-Oct-13 A
Track.29 (OD-C48/R3): Subgrade / Cut & Fill 0 04-Nov-13 A 25-Nov-13 A
Track.29 (OD-C48): Sub-Base Spreading & Compaction 0 28-Jan-14 A 29-Jan-14 A
OD-C48: Road Base Course Spreading & Compaction 0 30-Jan-14 A 02-Feb-14 A
OCEAN DRIVE-C50: ROADS / SITE TRACKS 14 20-Oct-13 A 07-Mar-14 10
Track.25 (OD-C50): Survey & Layout 0 20-Oct-13 A 22-Oct-13 A
Track.25 (OD-C50/SD): Clearing, Grubbing, Tree Cutting, Piloting 0 23-Oct-13 A 11-Nov-13 A
Track.25 (OD-C50): Subgrade / Cut & Fill 0 15-Nov-13 A 19-Jan-14 A
Track.25 (OD-C50): Sub-Base Spreading & Compaction 7 15-Dec-13 A 28-Feb-14 10
OD-C50: Road Base Course Spreading & Compaction 7 01-Mar-14 07-Mar-14 10
C50-C12: ROADS / SITE TRACKS 18 20-Oct-13 A 11-Mar-14 10
Track.26 (C50-C12): Survey & Layout 0 20-Oct-13 A 22-Oct-13 A
Track.26 (C50-C12/SD): Clearing, Grubbing, Tree Cutting, Piloting 0 12-Nov-13 A 22-Nov-13 A
Track.26 (C50-C12): Subgrade / Cut & Fill 0 20-Dec-13 A 07-Feb-14 A
Track.26 (C50-C12): Sub-Base Spreading & Compaction 4 21-Feb-14 24-Feb-14 20
C50-C12: Road Base Course Spreading & Compaction 4 08-Mar-14 11-Mar-14 10
C50-C19: ROADS / SITE TRACKS 21 20-Oct-13 A 14-Mar-14 0
Track.28 (C50-C19): Survey & Layout 0 20-Oct-13 A 22-Oct-13 A
Track.28 (C50-C19): Clearing, Grubbing, Tree Cutting, Piloting 0 12-Nov-13 A 18-Nov-13 A
Track.28 (C50-C19): Subgrade / Cut & Fill 13 28-Nov-13 A 06-Mar-14 0
Track.28 (C50-C19): Sub-Base Spreading & Compaction 4 07-Mar-14 10-Mar-14 0
C50-C19: Road Base Course Spreading & Compaction 4 11-Mar-14 14-Mar-14 0
SOUTH DRIVE-C35: ROADS / SITE TRACKS 4 20-Oct-13 A 14-Mar-14 0
Track.27 (SD-C35): Survey & Layout 0 20-Oct-13 A 22-Oct-13 A
Track.27 (SD-C35): Clearing, Grubbing, Tree Cutting, Piloting 0 13-Nov-13 A 10-Jan-14 A
Track.27 (SD-C35): Subgrade / Cut & Fill 0 12-Jan-14 A 09-Feb-14 A
Track.27 (SD-C35): Sub-Base Spreading & Compaction 2 11-Mar-14 12-Mar-14 0
SD-C35: Road Base Course Spreading & Compaction 2 13-Mar-14 14-Mar-14 0
DRAINAGE & SLOPE STABILIZATION 97 23-Dec-13 A 28-May-14 15

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 30 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

SECTION 01 52 09-Jan-14 A 13-Apr-14 18


C44-OCEAN DRIVE: CROSS DRAINS (1 RCBC / 4 RCPC) / DRAINAGE / SLOPE STABILIZATION 46 09-Jan-14 A 07-Apr-14 24
Track.8A (C44-OD): RCBC (1 Units) 0 09-Jan-14 A 20-Feb-14 A
C44-OD: RCPC (3 Units) 8 30-Jan-14 A 28-Feb-14 18
C44-OD: Construct Head/Wing Walls/Apron (4 Pairs including RCBC) 46 21-Feb-14 07-Apr-14 24
C44-OD: Drainage 3 01-Mar-14 03-Mar-14 28
C44-OD: Slope Stabilization 3 04-Mar-14 06-Mar-14 56
C15-C44: CROSS DRAINS (3 UNITS) / DRAINAGE / SLOPE STABILIZATION 10 01-Mar-14 11-Mar-14 52
C15-C44: RCPC including C44 spur Road (1 Units) 4 01-Mar-14 04-Mar-14 18
C15-C44: Drainage 3 05-Mar-14 08-Mar-14 27
C15-C44: Construct Head/Wing Walls/Apron (1 Pairs) 4 05-Mar-14 08-Mar-14 18
C15-C44: Slope Stabilization 3 08-Mar-14 11-Mar-14 52
C34-C15: CROSS DRAINS (2 UNITS) / DRAINAGE / SLOPE STABILIZATION 28 21-Feb-14 20-Mar-14 42
C34-C15: RCPC (4 Units) (Including C06 approach) 16 21-Feb-14 08-Mar-14 15
C34-C15: Drainage 3 09-Mar-14 11-Mar-14 26
C34-C15: Construct Head/Wing Walls/Apron (4 Pairs) 12 09-Mar-14 20-Mar-14 18
C34-C15: Slope Stabilization 3 12-Mar-14 14-Mar-14 48
C07-C34: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 13 01-Feb-14 A 24-Mar-14 38
C07-C34: RCPC (1 Unit) 0 01-Feb-14 A 04-Feb-14 A
C07-C34: Drainage 3 12-Mar-14 14-Mar-14 26
C07-C34: Slope Stabilization 3 15-Mar-14 17-Mar-14 45
C07-C34: Construct Head/Wing Walls/Apron (1 Pair) 4 21-Mar-14 24-Mar-14 18
C03-C07: CROSS DRAINS (4 UNITS) / DRAINAGE / SLOPE STABILIZATION 22 23-Jan-14 A 05-Apr-14 26
C03-C07: RCPC (2 Units) 0 23-Jan-14 A 31-Jan-14 A
C03-C07: Drainage 5 15-Mar-14 19-Mar-14 26
C03-C07: Slope Stabilization 5 20-Mar-14 24-Mar-14 38
C03-C07: Construct Head/Wing Walls/Apron (4 Pairs) 12 25-Mar-14 05-Apr-14 18
C08-C03: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 21 10-Jan-14 A 09-Apr-14 22
C08-C03: RCPC (1 Unit) 0 10-Jan-14 A 22-Jan-14 A
C08-C03: Drainage 3 20-Mar-14 22-Mar-14 26
C08-C03: Slope Stabilization 3 23-Mar-14 25-Mar-14 37
C08-C03: Construct Head/Wing Walls/Apron (1 Pair) 4 06-Apr-14 09-Apr-14 18
C22-C08: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 36 09-Mar-14 13-Apr-14 18
C22-C08: RCPC (1 Unit) 4 09-Mar-14 12-Mar-14 15
C22-C08: Drainage 3 23-Mar-14 25-Mar-14 26
C22-C08: Slope Stabilization 3 26-Mar-14 28-Mar-14 34
C22-C08: Construct Head/Wing Walls/Apron (1 Pair) 4 10-Apr-14 13-Apr-14 18
C03-C01: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 6 26-Mar-14 31-Mar-14 31
C03-C01: Drainage 3 26-Mar-14 28-Mar-14 26
C03-C01: Slope Stabilization 3 29-Mar-14 31-Mar-14 31
EAST DRIVE-C06: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 6 29-Mar-14 03-Apr-14 28
ED-C06: Drainage 3 29-Mar-14 31-Mar-14 26
ED-C06: Slope Stabilization 3 01-Apr-14 03-Apr-14 28
SECTION 02 59 12-Jan-14 A 10-May-14 26
NATIONAL HIGHWAY-C22: CROSS DRAINS (7 UNITS) / DRAINAGE / SLOPE STABILIZATION 43 12-Jan-14 A 24-Apr-14 26
N.HWay-C22: Install RCPC (4 Units) 4 12-Jan-14 A 16-Mar-14 15
N.HWay-C22: Construct Head/Wing Walls/Apron (4 Pairs) 16 17-Mar-14 01-Apr-14 31
N.HWay-C22: Drainage 14 01-Apr-14 14-Apr-14 26
N.HWay-C22: Slope Stabilization 10 15-Apr-14 24-Apr-14 26
EAST DRIVE-C37: CROSS DRAINS (2 UNITS) / DRAINAGE / SLOPE STABILIZATION 26 16-Jan-14 A 27-Apr-14 26
ED-C37: Install RCPC (2 Units) 0 16-Jan-14 A 22-Jan-14 A
ED-C37: Construct Head/Wing Walls/Apron (2 Pairs) 8 02-Apr-14 09-Apr-14 31

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 31 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

ED-C37: Drainage 3 15-Apr-14 17-Apr-14 32


ED-C37: Slope Stabilization 3 25-Apr-14 27-Apr-14 26
C37-C45: CROSS DRAINS (2 UNITS) / DRAINAGE / SLOPE STABILIZATION 13 18-Apr-14 30-Apr-14 26
ED-C45: Drainage 3 18-Apr-14 20-Apr-14 32
ED-C45: Slope Stabilization 3 28-Apr-14 30-Apr-14 26
EAST DRIVE-C29: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 49 17-Mar-14 04-May-14 26
ED-C29: Install RCPC (1 Unit) 4 17-Mar-14 20-Mar-14 15
ED-C29: Construct Head/Wing Walls/Apron (1 Pair) 4 10-Apr-14 13-Apr-14 31
ED-C29: Drainage 4 21-Apr-14 24-Apr-14 32
ED-C29: Slope Stabilization 4 01-May-14 04-May-14 26
EAST DRIVE-C25: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 24 13-Feb-14 A 07-May-14 26
ED-C25: Install RCPC (1 Unit) 0 13-Feb-14 A 17-Feb-14 A
ED-C25: Construct Head/Wing Walls/Apron (1 Pair) 4 14-Apr-14 17-Apr-14 31
ED-C25: Drainage 3 25-Apr-14 27-Apr-14 33
ED-C25: Slope Stabilization 3 05-May-14 07-May-14 26
C25-C42: CROSS DRAINS (3 UNITS) / DRAINAGE / SLOPE STABILIZATION 51 21-Mar-14 10-May-14 26
C25-C42: Install RCPC (3 Units) 12 21-Mar-14 01-Apr-14 15
C25-C42: Construct Head/Wing Walls/Apron (2 Pairs) 8 18-Apr-14 25-Apr-14 31
C25-C42: Drainage 3 28-Apr-14 30-Apr-14 33
C25-C42: Slope Stabilization 3 08-May-14 10-May-14 26
SECTION 3A / WEST 37 29-Dec-13 A 08-May-14 35
OCEAN DRIVE-C14: CROSS DRAINS (3 UNITS) / DRAINAGE / SLOPE STABILIZATION 20 29-Dec-13 A 21-Apr-14 35
OD-C14: Install RCPC (5 Units) 4 29-Dec-13 A 05-Apr-14 15
OD-C14/WD: Drainage 8 06-Apr-14 13-Apr-14 22
OD-C14: Construct Head/Wing Walls/Apron (4 Pairs) 16 06-Apr-14 21-Apr-14 35
OD-C14/WD: Slope Stabilization 8 14-Apr-14 21-Apr-14 35
C16-C17: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 15 29-Dec-13 A 29-Apr-14 32
C16-C17: Install RCPC (1 Unit) 0 29-Dec-13 A 23-Jan-14 A
C16-C17: Drainage 4 14-Apr-14 17-Apr-14 22
C16-C17: Slope Stabilization 4 22-Apr-14 25-Apr-14 35
C16-C17: Construct Head/Wing Walls/Apron (1 Pair) 3 26-Apr-14 29-Apr-14 31
C16-C14: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 12 18-Apr-14 29-Apr-14 35
C16-C14/WD: Drainage 4 18-Apr-14 21-Apr-14 22
C16-C14/WD: Slope Stabilization 4 26-Apr-14 29-Apr-14 35
C14-C04: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 13 22-Apr-14 04-May-14 35
C14-C04: Drainage 5 22-Apr-14 26-Apr-14 22
C14-C04: Slope Stabilization 5 30-Apr-14 04-May-14 35
WEST DRIVE-C09: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 12 26-Apr-14 08-May-14 35
WD-C09: Drainage 4 26-Apr-14 30-Apr-14 22
WD-C09: Slope Stabilization 4 04-May-14 08-May-14 35
SECTION 3B (EAST) DRAINAGE / SLOPE STABILIZATION 46 23-Dec-13 A 21-May-14 22
OCEAN DRIVE-C18: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 10 23-Dec-13 A 08-May-14 35
OD-C18: Install RCPC (1 Unit) 0 23-Dec-13 A 28-Dec-13 A
OD-C18: Construct Head/Wing Walls/Apron (1 Pair) 3 29-Apr-14 02-May-14 31
OD-C18: Drainage 4 30-Apr-14 04-May-14 22
OD-C18: Slope Stabilization 4 04-May-14 08-May-14 35
C18-C13: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 38 06-Apr-14 14-May-14 30
C18-C13: Install RCPC (1 Unit) 4 06-Apr-14 09-Apr-14 15
C18-C13: Construct Head/Wing Walls/Apron (1 Pair) 3 02-May-14 05-May-14 31
C18-C13: Drainage 5 04-May-14 09-May-14 22
C18-C13: Slope Stabilization 5 09-May-14 14-May-14 30
OCEAN DRIVE-C43: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 36 10-Apr-14 15-May-14 28

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 32 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

OD-C43: Install RCPC (2 Unit) 4 10-Apr-14 13-Apr-14 15


OD-C43: Construct Head/Wing Walls/Apron (1 Pair) 3 05-May-14 08-May-14 31
OD-C43: Drainage 3 09-May-14 12-May-14 22
OD-C43: Slope Stabilization 3 12-May-14 15-May-14 28
OCEAN DRIVE-C05: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 6 12-May-14 19-May-14 25
OD-C05: Drainage 3 12-May-14 15-May-14 22
OD-C05: Slope Stabilization 3 16-May-14 19-May-14 25
C13-C02: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 38 14-Apr-14 21-May-14 22
C13-C02: Install RCPC (1 Unit) 4 14-Apr-14 17-Apr-14 15
C13-C02: Construct Head/Wing Walls/Apron (1 Pair) 4 08-May-14 12-May-14 31
C13-C02: Drainage 3 16-May-14 18-May-14 22
C13-C02: Slope Stabilization 3 19-May-14 21-May-14 22
SECTION 04 41 18-Apr-14 28-May-14 15
OCEAN DRIVE-C48: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 14 18-Apr-14 01-May-14 25
OD-C48: Install RCPC (1 Unit) 4 18-Apr-14 21-Apr-14 15
OD-C48: Construct Head/Wing Walls/Apron (1 Pair) 4 22-Apr-14 25-Apr-14 20
OD-C48: Drainage 3 26-Apr-14 28-Apr-14 20
OD-C48: Slope Stabilization 3 29-Apr-14 01-May-14 25
OCEAN DRIVE-C50: CROSS DRAINS (4 UNITS) / DRAINAGE / SLOPE STABILIZATION 28 22-Apr-14 19-May-14 20
OD-C50: Install RCPC (4 Units) 12 22-Apr-14 03-May-14 15
OD-C50: Construct Head/Wing Walls/Apron (4 Pairs) 12 26-Apr-14 07-May-14 32
OD-C50: Drainage 8 04-May-14 11-May-14 15
OD-C50: Slope Stabilization 8 12-May-14 19-May-14 15
C50-C12: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 19 04-May-14 22-May-14 21
C50-C12/C19: Install RCPC (2 Unit) 8 04-May-14 11-May-14 19
C50-C12: Drainage 3 12-May-14 14-May-14 19
C50-C12/C19: Construct Head/Wing Walls/Apron (2 Pair) 4 12-May-14 15-May-14 28
C50-C12: Slope Stabilization 3 20-May-14 22-May-14 15
C50-C19: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 12 15-May-14 26-May-14 15
C50-C19: Drainage 4 15-May-14 18-May-14 19
C50-C19: Slope Stabilization 4 23-May-14 26-May-14 15
SOUTH DRIVE-C35: CROSS DRAIN (1 UNIT) / DRAINAGE / SLOPE STABILIZATION 10 19-May-14 28-May-14 15
SD-C35: Drainage 2 19-May-14 20-May-14 21
SD-C35: Slope Stabilization 2 27-May-14 28-May-14 15
MECHANICAL / ELECTRICAL / PLUMBING (MEP) 116 09-Jan-14 A 17-Jun-14 11
WTG'S UNDERGROUND TRENCHING & CABLING 93 09-Jan-14 A 25-May-14 15
SECTION 01 58 30-Jan-14 A 20-Apr-14 9
CABLING C01-C03 23 22-Feb-14 16-Mar-14 36
C01-C03: Survey Layout 1 22-Feb-14* 22-Feb-14 0
C01-C03: Cable Trenching/Temporary Backfilling 3 22-Feb-14 25-Feb-14 10
C01-C03: Remove Temporary Backfill/Sand Bedding for MV Cables 2 03-Mar-14 04-Mar-14 9
C01-C03: Laying of MV/FO Cables & Testing 4 04-Mar-14 08-Mar-14 9
C01-C03: Sand Bedding for Earthing Cables 2 08-Mar-14 10-Mar-14 36
C01-C03: Laying Earthing Cables 1 10-Mar-14 11-Mar-14 36
C01-C03: Sand Bedding (3rd Layer) 2 11-Mar-14 12-Mar-14 36
C01-C03: Warning Tape 1 12-Mar-14 13-Mar-14 36
C01-C03: Final Backfilling 2 13-Mar-14 15-Mar-14 36
C01-C03: Cable Pulling & Testing 2 15-Mar-14 16-Mar-14 36
CABLING C03-C07 32 08-Feb-14 A 29-Mar-14 27
C03-C07: Survey Layout 0 08-Feb-14 A 08-Feb-14 A
C03-C07: Cable Trenching/Temporary Backfilling 8 08-Feb-14 A 05-Mar-14 10
C03-C07: Remove Temporary Backfill/Sand Bedding for MV Cables 2 06-Mar-14 08-Mar-14 9

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 33 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C03-C07: Laying of MV/FO Cables & Testing 10 08-Mar-14 18-Mar-14 9


C03-C07: Sand Bedding for Earthing Cables 2 18-Mar-14 20-Mar-14 27
C03-C07: Laying Earthing Cables 2 20-Mar-14 22-Mar-14 27
C03-C07: Sand Bedding (3rd Layer) 2 22-Mar-14 24-Mar-14 27
C03-C07: PC Tiles / S-Bedding / Warning Tape 1 24-Mar-14 25-Mar-14 27
C03-C07: Final Backfilling 2 25-Mar-14 27-Mar-14 27
C03-C07: Cable Pulling & Testing 2 27-Mar-14 29-Mar-14 27
CABLING C22-C08 23 08-Feb-14 A 28-Mar-14 23
C22-C08: Survey Layout 0 08-Feb-14 A 08-Feb-14 A
C22-C08: Cable Trenching/Temporary Backfilling 3 08-Feb-14 A 08-Mar-14 17
C22-C08: Remove Temporary Backfill/Sand Bedding for MV Cables 2 17-Mar-14 18-Mar-14 9
C22-C08: Laying of MV/FO Cables & Testing 4 18-Mar-14 22-Mar-14 9
C22-C08: Sand Bedding for Earthing Cables 1 22-Mar-14 23-Mar-14 23
C22-C08: Laying Earthing Cables 1 23-Mar-14 24-Mar-14 23
C22-C08: Sand Bedding (3rd Layer) 1 24-Mar-14 25-Mar-14 23
C22-C08: Warning Tape 1 25-Mar-14 26-Mar-14 23
C22-C08: Final Backfilling 1 26-Mar-14 26-Mar-14 23
C22-C08: Cable Pulling & Testing 2 26-Mar-14 28-Mar-14 23
CABLING C08-C03 25 16-Feb-14 A 02-Apr-14 19
C08-C03: Survey Layout 0 16-Feb-14 A 16-Feb-14 A
C08-C03: Cable Trenching/Temporary Backfilling 3 16-Feb-14 A 11-Mar-14 17
C08-C03: Remove Temporary Backfill/Sand Bedding for MV Cables 2 21-Mar-14 22-Mar-14 9
C08-C03: Laying of MV/FO Cables & Testing 3 22-Mar-14 25-Mar-14 9
C08-C03: Sand Bedding for Earthing Cables 1 25-Mar-14 26-Mar-14 19
C08-C03: Laying Earthing Cables 1 26-Mar-14 27-Mar-14 19
C08-C03: Sand Bedding (3rd Layer) 2 27-Mar-14 29-Mar-14 19
C08-C03: Warning Tape 1 29-Mar-14 30-Mar-14 19
C08-C03: Final Backfilling 2 30-Mar-14 31-Mar-14 19
C08-C03: Cable Pulling & Testing 2 31-Mar-14 02-Apr-14 19
CABLING C07-C15 26 12-Feb-14 A 06-Apr-14 21
C07-C15: Survey Layout 0 12-Feb-14 A 12-Feb-14 A
C07-C15: Cable Trenching/Temporary Backfilling 4 12-Feb-14 A 15-Mar-14 17
C07-C15: Remove Temporary Backfill/Sand Bedding for MV Cables 2 24-Mar-14 25-Mar-14 9
C07-C15: Laying of MV/FO Cables & Testing 4 25-Mar-14 29-Mar-14 9
C07-C15: Sand Bedding for Earthing Cables 2 29-Mar-14 31-Mar-14 21
C07-C15: Laying Earthing Cables 1 31-Mar-14 01-Apr-14 21
C07-C15: Sand Bedding (3rd Layer) 2 01-Apr-14 02-Apr-14 21
C07-C15: PC Tiles / S-Bedding / Warning Tape 1 02-Apr-14 03-Apr-14 21
C07-C15: Final Backfilling 2 03-Apr-14 05-Apr-14 21
C07-C15: Cable Pulling & Testing 2 05-Apr-14 06-Apr-14 21
CABLING C34-C15 25 17-Feb-14 A 10-Apr-14 17
C34-C15: Survey Layout 0 17-Feb-14 A 17-Feb-14 A
C34-C15: Cable Trenching/Temporary Backfilling 4 17-Feb-14 A 19-Mar-14 17
C34-C15: Remove Temporary Backfill/Sand Bedding for MV Cables 2 28-Mar-14 29-Mar-14 9
C34-C15: Laying of MV/FO Cables & Testing 3 29-Mar-14 02-Apr-14 9
C34-C15: Sand Bedding for Earthing Cables 2 02-Apr-14 03-Apr-14 17
C34-C15: Laying Earthing Cables 1 03-Apr-14 04-Apr-14 17
C34-C15: Sand Bedding (3rd Layer) 2 04-Apr-14 06-Apr-14 17
C34-C15: Warning Tape 1 06-Apr-14 06-Apr-14 17
C34-C15: Final Backfilling 2 06-Apr-14 08-Apr-14 17
C34-C15: Cable Pulling & Testing 2 08-Apr-14 10-Apr-14 17
CABLING C06-C34 25 14-Feb-14 A 13-Apr-14 13

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 34 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C06-C34: Survey Layout 0 14-Feb-14 A 14-Feb-14 A


C06-C34: Cable Trenching/Temporary Backfilling 3 14-Feb-14 A 22-Mar-14 17
C06-C34: Remove Temporary Backfill/Sand Bedding for MV Cables 2 31-Mar-14 02-Apr-14 9
C06-C34: Laying of MV/FO Cables & Testing 3 02-Apr-14 05-Apr-14 9
C06-C34: Sand Bedding for Earthing Cables 2 05-Apr-14 06-Apr-14 13
C06-C34: Laying Earthing Cables 1 06-Apr-14 07-Apr-14 13
C06-C34: Sand Bedding (3rd Layer) 2 07-Apr-14 09-Apr-14 13
C06-C34: Warning Tape 1 09-Apr-14 09-Apr-14 13
C06-C34: Final Backfilling 2 09-Apr-14 11-Apr-14 13
C06-C34: Cable Pulling & Testing 2 11-Apr-14 13-Apr-14 13
CABLING C15-C44 25 19-Feb-14 A 16-Apr-14 12
C15-C44: Survey Layout 0 19-Feb-14 A 19-Feb-14 A
C15-C44: Cable Trenching/Temporary Backfilling 3 19-Feb-14 A 25-Mar-14 17
C15-C44: Remove Temporary Backfill/Sand Bedding for MV Cables 2 03-Apr-14 05-Apr-14 9
C15-C44: Laying of MV/FO Cables & Testing 3 05-Apr-14 08-Apr-14 9
C15-C44: Sand Bedding for Earthing Cables 2 08-Apr-14 09-Apr-14 12
C15-C44: Laying Earthing Cables 1 09-Apr-14 10-Apr-14 12
C15-C44: Sand Bedding (3rd Layer) 2 10-Apr-14 12-Apr-14 12
C15-C44: Warning Tape 1 12-Apr-14 12-Apr-14 12
C15-C44: Final Backfilling 2 12-Apr-14 14-Apr-14 12
C15-C44: Cable Pulling & Testing 2 14-Apr-14 16-Apr-14 12
CABLING C44-SUBSTATION 26 30-Jan-14 A 20-Apr-14 9
C44-SS: Survey Layout 0 30-Jan-14 A 30-Jan-14 A
C44-SS: Cable Trenching/Temporary Backfilling 4 30-Jan-14 A 29-Mar-14 17
C44-SS: Remove Temporary Backfill/Sand Bedding for MV Cables 2 06-Apr-14 08-Apr-14 9
C44-SS: Laying of MV/FO Cables & Testing 4 08-Apr-14 12-Apr-14 9
C44-SS: Sand Bedding for Earthing Cables 2 12-Apr-14 13-Apr-14 9
C44-SS: Laying Earthing Cables 1 13-Apr-14 14-Apr-14 9
C44-SS: Sand Bedding (3rd Layer) 2 14-Apr-14 16-Apr-14 9
C44-SS: PC Tiles / S-Bedding / Warning Tape 1 16-Apr-14 16-Apr-14 9
C44-SS: Final Backfilling 2 16-Apr-14 18-Apr-14 9
C44-SS: Cable Pulling & Testing 2 18-Apr-14 20-Apr-14 9 Requires Access at Substatation
SECTION 02 46 17-Mar-14 02-May-14 16
CABLING EAST C25-SUBSTATION 28 17-Mar-14 13-Apr-14 25
C25-RMU.D: Survey Layout 1 17-Mar-14* 17-Mar-14 0
C25-RMU.D: Cable Trenching/Temporary Backfilling 2 17-Mar-14 19-Mar-14 9
C25-RMU.D: Remove Temporary Backfill/Sand Bedding for MV Cables 1 20-Mar-14 20-Mar-14 8
C25-RMU.D: Laying of MV/FO Cables & Testing 14 20-Mar-14 03-Apr-14 8
C25-RMU.D: Sand Bedding for Earthing Cables 1 03-Apr-14 04-Apr-14 25
C25-RMU.D: Laying Earthing Cables 2 04-Apr-14 07-Apr-14 25
C25-RMU.D: Sand Bedding (3rd Layer) 1 07-Apr-14 08-Apr-14 25
C25-RMU.D: PC Tiles / S-Bedding / Warning Tape 2 08-Apr-14 09-Apr-14 25
C25-RMU.D: Final Backfilling 2 09-Apr-14 12-Apr-14 25
C25-RMU.D: Cable Pulling & Testing 2 12-Apr-14 13-Apr-14 25 Requires Access at Substatation
CABLING C42-C25 26 19-Mar-14 14-Apr-14 34
C42-C25: Survey Layout 1 19-Mar-14 19-Mar-14 14
C42-C25: Cable Trenching/Temporary Backfilling 4 19-Mar-14 23-Mar-14 14
C42-C25: Remove Temporary Backfill/Sand Bedding for MV Cables 2 02-Apr-14 03-Apr-14 8
C42-C25: Laying of MV/FO Cables & Testing 3 03-Apr-14 06-Apr-14 8
C42-C25: Sand Bedding for Earthing Cables 2 06-Apr-14 08-Apr-14 34
C42-C25: Laying Earthing Cables 1 08-Apr-14 09-Apr-14 34
C42-C25: Sand Bedding (3rd Layer) 2 09-Apr-14 10-Apr-14 34

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 35 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C42-C25: Warning Tape 1 10-Apr-14 11-Apr-14 34


C42-C25: Final Backfilling 1 11-Apr-14 12-Apr-14 34
C42-C25: Cable Pulling & Testing 2 12-Apr-14 14-Apr-14 34
CABLING C29-C25 30 23-Mar-14 21-Apr-14 25
C29-C25: Survey Layout 1 23-Mar-14 23-Mar-14 14
C29-C25: Cable Trenching/Temporary Backfilling 5 23-Mar-14 28-Mar-14 14
C29-C25: Remove Temporary Backfill/Sand Bedding for MV Cables 2 06-Apr-14 07-Apr-14 8
C29-C25: Laying of MV/FO Cables & Testing 6 07-Apr-14 13-Apr-14 8
C29-C25: Sand Bedding for Earthing Cables 2 13-Apr-14 15-Apr-14 25
C29-C25: Laying Earthing Cables 1 15-Apr-14 16-Apr-14 25
C29-C25: Sand Bedding (3rd Layer) 2 16-Apr-14 17-Apr-14 25
C29-C25: PC Tiles / S-Bedding / Warning Tape 1 17-Apr-14 18-Apr-14 25
C29-C25: Final Backfilling 2 18-Apr-14 20-Apr-14 25
C29-C25: Cable Pulling & Testing 2 20-Apr-14 21-Apr-14 25
CABLING C45-C37 27 28-Mar-14 24-Apr-14 18
C45-C37: Survey Layout 1 28-Mar-14 28-Mar-14 14
C45-C37: Cable Trenching/Temporary Backfilling 4 28-Mar-14 01-Apr-14 14
C45-C37: Remove Temporary Backfill/Sand Bedding for MV Cables 2 12-Apr-14 13-Apr-14 8
C45-C37: Laying of MV/FO Cables & Testing 3 13-Apr-14 16-Apr-14 8
C45-C37: Sand Bedding for Earthing Cables 2 16-Apr-14 18-Apr-14 18
C45-C37: Laying Earthing Cables 1 18-Apr-14 19-Apr-14 18
C45-C37: Sand Bedding (3rd Layer) 2 19-Apr-14 20-Apr-14 18
C45-C37: Warning Tape 1 20-Apr-14 21-Apr-14 18
C45-C37: Final Backfilling 1 21-Apr-14 22-Apr-14 18
C45-C37: Cable Pulling & Testing 2 22-Apr-14 24-Apr-14 18
CABLING C37-C29 31 01-Apr-14 01-May-14 13
C37-C29: Survey Layout 1 01-Apr-14 01-Apr-14 14
C37-C29: Cable Trenching/Temporary Backfilling 8 01-Apr-14 09-Apr-14 14
C37-C29: Remove Temporary Backfill/Sand Bedding for MV Cables 2 15-Apr-14 16-Apr-14 8
C37-C29: Laying of MV/FO Cables & Testing 6 16-Apr-14 22-Apr-14 8
C37-C29: Sand Bedding for Earthing Cables 2 22-Apr-14 24-Apr-14 13
C37-C29: Laying Earthing Cables 2 24-Apr-14 26-Apr-14 13
C37-C29: Sand Bedding (3rd Layer) 2 26-Apr-14 27-Apr-14 13
C37-C29: PC Tiles / S-Bedding / Warning Tape 1 27-Apr-14 28-Apr-14 13
C37-C29: Final Backfilling 2 28-Apr-14 30-Apr-14 13
C37-C29: Cable Pulling & Testing 2 30-Apr-14 01-May-14 13
CABLING RMU.D-SS 23 09-Apr-14 02-May-14 8
RMU.D-SS: Survey Layout 1 09-Apr-14 09-Apr-14 17
RMU.D-SS: Cable Trenching/Temporary Backfilling 3 09-Apr-14 12-Apr-14 17
RMU.D-SS: Remove Temporary Backfill/Sand Bedding for MV Cables 2 21-Apr-14 22-Apr-14 8
RMU.D-SS: Laying of MV/FO Cables & Testing 2 22-Apr-14 24-Apr-14 8
RMU.D-SS: Sand Bedding for Earthing Cables 2 24-Apr-14 26-Apr-14 8
RMU.D-SS: Laying Earthing Cables 1 26-Apr-14 27-Apr-14 8
RMU.D-SS: Sand Bedding (3rd Layer) 2 27-Apr-14 28-Apr-14 8
RMU.D-SS: Warning Tape 1 28-Apr-14 29-Apr-14 8
RMU.D-SS: Final Backfilling 1 29-Apr-14 30-Apr-14 8
RMU.D-SS: Cable Pulling & Testing 2 30-Apr-14 02-May-14 8
SECTION 3A / WEST 48 09-Jan-14 A 10-Apr-14 59
CABLING C04-C14 20 30-Jan-14 A 12-Mar-14 87
C04-C14: Survey Layout 0 30-Jan-14 A 30-Jan-14 A
C04-C14: Cable Trenching/Temporary Backfilling 3 30-Jan-14 A 23-Feb-14 -16
C04-C14: Remove Temporary Backfill/Sand Bedding for MV Cables 2 28-Feb-14 01-Mar-14 30

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 36 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C04-C14: Laying of MV/FO Cables & Testing 4 01-Mar-14 05-Mar-14 30


C04-C14: Sand Bedding for Earthing Cables 2 05-Mar-14 07-Mar-14 87
C04-C14: Laying Earthing Cables 1 07-Mar-14 07-Mar-14 87
C04-C14: Sand Bedding (3rd Layer) 2 08-Mar-14 09-Mar-14 87
C04-C14: Warning Tape 1 09-Mar-14 10-Mar-14 87
C04-C14: Final Backfilling 1 10-Mar-14 11-Mar-14 87
C04-C14: Cable Pulling & Testing 2 11-Mar-14 12-Mar-14 87
CABLING C16-C14 24 09-Jan-14 A 19-Mar-14 79
C16-C14: Cable Trenching/Temporary Backfilling 3 09-Jan-14 A 26-Feb-14 -16
C16-C14: Survey Layout 0 09-Jan-14 A 10-Jan-14 A
C16-C14: Remove Temporary Backfill/Sand Bedding for MV Cables 2 04-Mar-14 06-Mar-14 30
C16-C14: Laying of MV/FO Cables & Testing 6 06-Mar-14 12-Mar-14 30
C16-C14: Sand Bedding for Earthing Cables 2 12-Mar-14 14-Mar-14 79
C16-C14: Laying Earthing Cables 1 14-Mar-14 14-Mar-14 79
C16-C14: Sand Bedding (3rd Layer) 2 15-Mar-14 16-Mar-14 79
C16-C14: PC Tiles / S-Bedding / Warning Tape 1 16-Mar-14 17-Mar-14 79
C16-C14: Final Backfilling 1 17-Mar-14 18-Mar-14 79
C16-C14: Cable Pulling & Testing 2 18-Mar-14 19-Mar-14 79
CABLING C17-C16 26 30-Jan-14 A 24-Mar-14 73
C17-C16: Survey Layout 0 30-Jan-14 A 30-Jan-14 A
C17-C16: Cable Trenching/Temporary Backfilling 2 30-Jan-14 A 28-Feb-14 -16
C17-C16: Remove Temporary Backfill/Sand Bedding for MV Cables 2 12-Mar-14 13-Mar-14 30
C17-C16: Laying of MV/FO Cables & Testing 4 13-Mar-14 17-Mar-14 30
C17-C16: Sand Bedding for Earthing Cables 2 17-Mar-14 19-Mar-14 73
C17-C16: Laying Earthing Cables 1 19-Mar-14 19-Mar-14 73
C17-C16: Sand Bedding (3rd Layer) 2 20-Mar-14 21-Mar-14 73
C17-C16: Warning Tape 1 21-Mar-14 22-Mar-14 73
C17-C16: Final Backfilling 1 22-Mar-14 23-Mar-14 73
C17-C16: Cable Pulling & Testing 2 23-Mar-14 24-Mar-14 73
CABLING C09-RMU.A 40 05-Feb-14 A 10-Apr-14 30
C09-RMU.A: Survey Layout 0 05-Feb-14 A 05-Feb-14 A
C09-RMU.A: Cable Trenching/Temporary Backfilling 12 05-Feb-14 A 12-Mar-14 -16
C09-RMU.A: Remove Temporary Backfill/Sand Bedding for MV Cables 2 17-Mar-14 18-Mar-14 30
C09-RMU.A: Laying of MV/FO Cables & Testing 6 18-Mar-14 24-Mar-14 30
C09-RMU.A: Sand Bedding for Earthing Cables 2 24-Mar-14 26-Mar-14 39
C09-RMU.A: Laying Earthing Cables 1 26-Mar-14 26-Mar-14 39
C09-RMU.A: Sand Bedding (3rd Layer) 2 27-Mar-14 28-Mar-14 39
C09-RMU.A: PC Tiles / S-Bedding / Warning Tape 1 28-Mar-14 29-Mar-14 39
C09-RMU.A: Final Backfilling 2 29-Mar-14 30-Mar-14 39
C09-RMU.A: Cable Pulling & Testing 2 08-Apr-14 10-Apr-14 30 Requires RMU installed (By others)
CABLING C14-C09 27 17-Jan-14 A 08-Apr-14 30
C14-C09: Survey Layout 0 17-Jan-14 A 19-Jan-14 A
C14-C09: Cable Trenching/Temporary Backfilling 10 13-Mar-14 22-Mar-14 -16
C14-C09: Remove Temporary Backfill/Sand Bedding for MV Cables 2 24-Mar-14 25-Mar-14 30
C14-C09: Laying of MV/FO Cables & Testing 6 25-Mar-14 31-Mar-14 30
C14-C09: Sand Bedding for Earthing Cables 2 31-Mar-14 02-Apr-14 30
C14-C09: Laying Earthing Cables 1 02-Apr-14 02-Apr-14 30
C14-C09: Sand Bedding (3rd Layer) 2 03-Apr-14 04-Apr-14 30
C14-C09: Warning Tape 1 04-Apr-14 05-Apr-14 30
C14-C09: Final Backfilling 2 05-Apr-14 06-Apr-14 30
C14-C09: Cable Pulling & Testing 2 07-Apr-14 08-Apr-14 30
SECTION 3B / EAST 40 22-Mar-14 01-May-14 39

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 37 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

CABLING C18-RMU.A 26 22-Mar-14 16-Apr-14 24


C18-RMU.A: Survey Layout 1 22-Mar-14 22-Mar-14 -16
C18-RMU.A: Cable Trenching/Temporary Backfilling 4 23-Mar-14 26-Mar-14 -16
C18-RMU.A: Remove Temporary Backfill/Sand Bedding for MV Cables 2 05-Apr-14 06-Apr-14 -16
C18-RMU.A: Laying of MV/FO Cables & Testing 3 06-Apr-14 09-Apr-14 -16
C18-RMU.A: Sand Bedding for Earthing Cables 2 09-Apr-14 11-Apr-14 24
C18-RMU.A: Laying Earthing Cables 1 11-Apr-14 11-Apr-14 24
C18-RMU.A: Sand Bedding (3rd Layer) 2 12-Apr-14 13-Apr-14 24
C18-RMU.A: PC Tiles / S-Bedding / Warning Tape 1 13-Apr-14 14-Apr-14 24
C18-RMU.A: Final Backfilling 1 14-Apr-14 15-Apr-14 24
C18-RMU.A: Cable Pulling & Testing 2 15-Apr-14 16-Apr-14 24
CABLING C05-C43 26 26-Mar-14 21-Apr-14 46
C05-C43: Survey Layout 1 26-Mar-14 26-Mar-14 -16
C05-C43: Cable Trenching/Temporary Backfilling 3 27-Mar-14 29-Mar-14 -16
C05-C43: Remove Temporary Backfill/Sand Bedding for MV Cables 2 09-Apr-14 10-Apr-14 -16
C05-C43: Laying of MV/FO Cables & Testing 3 10-Apr-14 13-Apr-14 -16
C05-C43: Sand Bedding for Earthing Cables 2 13-Apr-14 15-Apr-14 46
C05-C43: Laying Earthing Cables 1 15-Apr-14 15-Apr-14 46
C05-C43: Sand Bedding (3rd Layer) 2 16-Apr-14 17-Apr-14 46
C05-C43: Warning Tape 1 17-Apr-14 18-Apr-14 46
C05-C43: Final Backfilling 2 18-Apr-14 19-Apr-14 46
C05-C43: Cable Pulling & Testing 2 20-Apr-14 21-Apr-14 46
CABLING C13-C18 26 29-Mar-14 23-Apr-14 46
C13-C18: Survey Layout 1 29-Mar-14 29-Mar-14 -16
C13-C18: Cable Trenching/Temporary Backfilling 3 30-Mar-14 01-Apr-14 -16
C13-C18: Remove Temporary Backfill/Sand Bedding for MV Cables 2 12-Apr-14 13-Apr-14 -16
C13-C18: Laying of MV/FO Cables & Testing 3 13-Apr-14 16-Apr-14 -16
C13-C18: Sand Bedding for Earthing Cables 2 16-Apr-14 18-Apr-14 46
C13-C18: Laying Earthing Cables 1 18-Apr-14 18-Apr-14 46
C13-C18: Sand Bedding (3rd Layer) 2 19-Apr-14 20-Apr-14 46
C13-C18: PC Tiles / S-Bedding / Warning Tape 1 20-Apr-14 21-Apr-14 46
C13-C18: Final Backfilling 1 21-Apr-14 22-Apr-14 46
C13-C18: Cable Pulling & Testing 2 22-Apr-14 23-Apr-14 46
CABLING C02-C13 26 01-Apr-14 26-Apr-14 42
C02-C13: Survey Layout 1 01-Apr-14 01-Apr-14 -16
C02-C13: Cable Trenching/Temporary Backfilling 3 02-Apr-14 04-Apr-14 -16
C02-C13: Remove Temporary Backfill/Sand Bedding for MV Cables 2 15-Apr-14 16-Apr-14 -16
C02-C13: Laying of MV/FO Cables & Testing 3 16-Apr-14 19-Apr-14 -16
C02-C13: Sand Bedding for Earthing Cables 2 19-Apr-14 21-Apr-14 42
C02-C13: Laying Earthing Cables 1 21-Apr-14 21-Apr-14 42
C02-C13: Sand Bedding (3rd Layer) 2 22-Apr-14 23-Apr-14 42
C02-C13: Warning Tape 1 23-Apr-14 24-Apr-14 42
C02-C13: Final Backfilling 1 24-Apr-14 25-Apr-14 42
C02-C13: Cable Pulling & Testing 2 25-Apr-14 26-Apr-14 42
CABLING C43-C18 27 04-Apr-14 01-May-14 37
C43-C18: Survey Layout 1 04-Apr-14 04-Apr-14 -16
C43-C18: Cable Trenching/Temporary Backfilling 4 05-Apr-14 08-Apr-14 -16
C43-C18: Remove Temporary Backfill/Sand Bedding for MV Cables 2 18-Apr-14 19-Apr-14 -16
C43-C18: Laying of MV/FO Cables & Testing 4 19-Apr-14 23-Apr-14 -16
C43-C18: Sand Bedding for Earthing Cables 2 23-Apr-14 25-Apr-14 37
C43-C18: Laying Earthing Cables 1 25-Apr-14 25-Apr-14 37
C43-C18: Sand Bedding (3rd Layer) 2 26-Apr-14 27-Apr-14 37

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 38 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C43-C18: PC Tiles / S-Bedding / Warning Tape 1 27-Apr-14 28-Apr-14 37


C43-C18: Final Backfilling 2 28-Apr-14 29-Apr-14 37
C43-C18: Cable Pulling & Testing 2 30-Apr-14 01-May-14 37
CABLING RMU.A-SS (SECTION 03) 26 08-Apr-14 04-May-14 4
RMU.A-SS: Survey Layout 1 08-Apr-14 08-Apr-14 -16
RMU.A-SS: Cable Tr enching/Temporary Backfilling 3 09-Apr-14 11-Apr-14 -16
RMU.A-SS: Remove Temporary Backfill/Sand Bedding for MV Cables 2 22-Apr-14 23-Apr-14 -16
RMU.A-SS: Laying of MV/FO Cables & Testing 3 23-Apr-14 26-Apr-14 -16
RMU.A-SS: Sand Bedding for Earthing Cables 2 26-Apr-14 28-Apr-14 4
RMU.A-SS: Laying Earthing Cables 1 28-Apr-14 28-Apr-14 4
RMU.A-SS: Sand Bedding (3rd Layer) 2 29-Apr-14 30-Apr-14 4
RMU.A-SS: Warning Tape 1 30-Apr-14 01-May-14 4
RMU.A-SS: Final Backfilling 1 01-May-14 02-May-14 4
RMU.A-SS: Cable Pulling & Testing 2 02-May-14 04-May-14 4 Requires Access at Substation
SECTION 04 44 11-Apr-14 25-May-14 14
CABLING C12-C50 28 11-Apr-14 09-May-14 30
C12-C50: Survey Layout 1 11-Apr-14 11-Apr-14 -16
C12-C50: Cable Trenching/Temporary Backfilling 4 12-Apr-14 15-Apr-14 -16
C12-C50: Remove Temporary Backfill/Sand Bedding for MV Cables 2 26-Apr-14 27-Apr-14 -16
C12-C50: Laying of MV/FO Cables & Testing 4 27-Apr-14 01-May-14 -16
C12-C50: Sand Bedding for Earthing Cables 2 01-May-14 03-May-14 30
C12-C50: Laying Earthing Cables 1 03-May-14 03-May-14 30
C12-C50: Sand Bedding (3rd Layer) 2 04-May-14 05-May-14 30
C12-C50: Warning Tape 1 05-May-14 06-May-14 30
C12-C50: Final Backfilling 2 06-May-14 07-May-14 30
C12-C50: Cable Pulling & Testing 2 08-May-14 09-May-14 30
CABLING C35-C50 28 15-Apr-14 13-May-14 25
C35-C50: Survey Layout 1 15-Apr-14 15-Apr-14 -16
C35-C50: Cable Trenching/Temporary Backfilling 4 16-Apr-14 19-Apr-14 -16
C35-C50: Remove Temporary Backfill/Sand Bedding for MV Cables 2 30-Apr-14 01-May-14 -16
C35-C50: Laying of MV/FO Cables & Testing 4 01-May-14 05-May-14 -16
C35-C50: Sand Bedding for Earthing Cables 2 05-May-14 07-May-14 25
C35-C50: Laying Earthing Cables 1 07-May-14 07-May-14 25
C35-C50: Sand Bedding (3rd Layer) 2 08-May-14 09-May-14 25
C35-C50: PC Tiles / S-Bedding / Warning Tape 1 09-May-14 10-May-14 25
C35-C50: Final Backfilling 2 10-May-14 11-May-14 25
C35-C50: Cable Pulling & Testing 2 12-May-14 13-May-14 25
CABLING C19-C35 28 19-Apr-14 16-May-14 20
C19-C35: Survey Layout 1 19-Apr-14 19-Apr-14 -16
C19-C35: Cable Trenching/Temporary Backfilling 3 20-Apr-14 22-Apr-14 -16
C19-C35: Remove Temporary Backfill/Sand Bedding for MV Cables 1 04-May-14 05-May-14 -16
C19-C35: Laying of MV/FO Cables & Testing 4 05-May-14 09-May-14 -16
C19-C35: Sand Bedding for Earthing Cables 2 09-May-14 11-May-14 20
C19-C35: Laying Earthing Cables 1 11-May-14 11-May-14 20
C19-C35: Sand Bedding (3rd Layer) 2 12-May-14 13-May-14 20
C19-C35: Warning Tape 1 13-May-14 14-May-14 20
C19-C35: Final Backfilling 1 14-May-14 15-May-14 20
C19-C35: Cable Pulling & Testing 2 15-May-14 16-May-14 20
CABLING C48-RMU.B 29 22-Apr-14 20-May-14 -10
C48-RMU.B: Survey Layout 1 22-Apr-14 22-Apr-14 -16
C48-RMU.B: Cable Trenching/Temporary Backfilling 5 23-Apr-14 27-Apr-14 -16
C48-RMU.B: Remove Temporary Backfill/Sand Bedding for MV Cables 2 08-May-14 09-May-14 -16

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 39 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C48-RMU.B: Laying of MV/FO Cables & Testing 4 09-May-14 13-May-14 -16


C48-RMU.B: Sand Bedding for Earthing Cables 1 13-May-14 14-May-14 -10
C48-RMU.B: Laying Earthing Cables 1 14-May-14 15-May-14 -10
C48-RMU.B: Sand Bedding (3rd Layer) 2 15-May-14 16-May-14 -10
C48-RMU.B: PC Tiles / S-Bedding / Warning Tape 1 16-May-14 17-May-14 -10
C48-RMU.B: Final Backfilling 2 17-May-14 19-May-14 -10
C48-RMU.B: Cable Pulling & Testing 2 19-May-14 20-May-14 -10
CABLING C50-RMU.B 27 27-Apr-14 23-May-14 -13
C50-RMU.B: Survey Layout 1 27-Apr-14 27-Apr-14 -16
C50-RMU.B: Cable Trenching/Temporary Backfilling 12 28-Apr-14 09-May-14 -16
C50-RMU.B: Remove Temporary Backfill/Sand Bedding for MV Cables 3 10-May-14 13-May-14 -16
C50-RMU.B: Laying of MV/FO Cables & Testing 3 13-May-14 16-May-14 -16
C50-RMU.B: Sand Bedding for Earthing Cables 2 16-May-14 18-May-14 -13
C50-RMU.B: Laying Earthing Cables 1 18-May-14 18-May-14 -13
C50-RMU.B: Sand Bedding (3rd Layer) 1 19-May-14 19-May-14 -13
C50-RMU.B: PC Tiles / S-Bedding / Warning Tape 1 19-May-14 20-May-14 -13
C50-RMU.B: Final Backfilling 2 20-May-14 22-May-14 -13
C50-RMU.B: Cable Pulling & Testing 2 22-May-14 23-May-14 -13
CABLING RMU.B-SS 16 09-May-14 25-May-14 -16
RMU.B-SS: Survey Layout 1 09-May-14 09-May-14 -14
RMU.B-SS: Cable Tr enching/Temporary Backfilling 3 10-May-14 12-May-14 -14
RMU.B-SS: Remove Temporary Backfill/Sand Bedding for MV Cables 2 15-May-14 16-May-14 -16
RMU.B-SS: Laying of MV/FO Cables & Testing 3 16-May-14 19-May-14 -16
RMU.B-SS: Sand Bedding for Earthing Cables 1 19-May-14 20-May-14 -16
RMU.B-SS: Laying Earthing Cables 1 20-May-14 21-May-14 -16
RMU.B-SS: Sand Bedding (3rd Layer) 1 21-May-14 22-May-14 -16
RMU.B-SS: Warning Tape 1 22-May-14 22-May-14 -16
RMU.B-SS: Final Backfilling 1 23-May-14 23-May-14 -16
RMU.B-SS: Cable Pulling & Testing 2 23-May-14 25-May-14 -16 Requires Access at Substation
POWERHOUSE (YPBS) 82 26-Jan-14 A 14-May-14 -1
GENERATORS & FUEL DAY TANKS 75 26-Jan-14 A 07-May-14 0
CIVIL / STRUCTURAL 38 26-Jan-14 A 30-Mar-14 36
BUILDING FOOTING / PEDESTAL 8 26-Jan-14 A 28-Feb-14 4
Gensets House: Survey & Layout 0 26-Jan-14 A 26-Jan-14 A
Gensets House: Clearing/Grubbing/Grading 0 26-Jan-14 A 27-Jan-14 A
Gensets House: Excavate/Prepare Footing Subgrade 0 27-Jan-14 A 08-Feb-14 A
Gensets House: Pour Concrete for Blinding 0 09-Feb-14 A 09-Feb-14 A
Gensets House: Install Footing/Pedestal Rebars & Footing Forms 0 10-Feb-14 A 12-Feb-14 A
Gensets House: Pour Concrete for Footing 0 13-Feb-14 A 13-Feb-14 A
Gensets House: Install Pedestal Forms & Anchor Bolts for Building Frame 0 14-Feb-14 A 14-Feb-14 A
Gensets House: Pour Concrete for Pedestal 1 21-Feb-14 21-Feb-14 0
Gensets House: Pedestal Concrete Curing 7 21-Feb-14 28-Feb-14 4
BUILDING GROUND / TIE BEAMS 1 15-Feb-14 A 21-Feb-14 0
Gensets House: Excavate/Prepare Ground Beams Subgrade 0 15-Feb-14 A 16-Feb-14 A
Gensets House: Install Ground Beams Rebars/Forms 0 17-Feb-14 A 19-Feb-14 A
Gensets House: Pour Concrete for Ground Beams 1 21-Feb-14 21-Feb-14 0
UNDERGROUND CABLE VAULT 4 21-Feb-14 25-Feb-14 0
Gensets House: Construct 400mmX600mm Cable Vault (Gensets House to TX) 4 21-Feb-14 25-Feb-14 0
BUILDING CONCRETE SLAB / RAMP 24 21-Feb-14 18-Mar-14 0
Gensets House: Prepare Concrete Slab Subgrade 4 21-Feb-14 25-Feb-14 0
Gensets House: Install Slab Rebars/Forms 3 25-Feb-14 28-Feb-14 0
Gensets House: Slab Concrete Pouring 1 01-Mar-14 01-Mar-14 0

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 40 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

Gensets House: Install CHB Walls 2 01-Mar-14 03-Mar-14 1


Gensets House: Construct Concrete Ramp 3 15-Mar-14 18-Mar-14 0
GENERATOR PADS/PLINTHS (2 UNITS) 10 01-Mar-14 11-Mar-14 6
Generator Pads: Install Rebars/Anchor Bolts/Forms 2 01-Mar-14 03-Mar-14 0
Generator Pads: Concrete Pouring 1 03-Mar-14 04-Mar-14 0
Generator Pads: Concrete Curing prior to Gensets Installation 7 04-Mar-14 11-Mar-14 6
FUEL DAY TANKS PAD & CONTAINMENT 26 01-Mar-14 28-Mar-14 36
Fuel Day Tanks Pad: Install Rebars/Anchor Bolts/Forms 2 01-Mar-14 03-Mar-14 0
Fuel Day Tanks Pad: Concrete Pouring 1 03-Mar-14 04-Mar-14 0
Fuel Day Tanks Pad: Concrete Curing prior to Tank Installation 7 04-Mar-14 11-Mar-14 6
Fuel Day Tanks Containment: Install CHB Walls 2 26-Mar-14 28-Mar-14 36
BUILDING STRUCTURAL STEEL FRAMING SYSTEM 3 04-Mar-14 07-Mar-14 0
Gensets House: Erection of Building Steel Frames (Steel Coulumns, Walls & Roof Framing System) 3 04-Mar-14 07-Mar-14 0
BUILDING ENVELOP & FINISHING 23 08-Mar-14 30-Mar-14 36
Gensets House: Install Roof Panels including Insulation System 3 08-Mar-14 11-Mar-14 0
Gensets House: Install Wall & Ceiling Panels including Insulation System & Doors 7 11-Mar-14 18-Mar-14 0
Gensets House: Floor Finishing (If Required) 2 28-Mar-14 30-Mar-14 36
FUEL TRANSFER PUMP PADS (2 UNITS) 10 18-Mar-14 28-Mar-14 31
Fuel Transfer Pumps: Construct Pads (2 Units) 3 18-Mar-14 21-Mar-14 31
Fuel Transfer Pumps: Concrete Curing prior to Pumps Installation 7 21-Mar-14 28-Mar-14 31
ELECTRO-MECHANICAL 50 18-Mar-14 07-May-14 0
BUILDING ELECTRICAL SYSTEM 10 18-Mar-14 30-Mar-14 31
Gensets House: Electrical & Lighting Fixtures Installations 10 18-Mar-14 30-Mar-14 31
FUEL DAY TANKS (2-900 GALLONS) 3 18-Mar-14 21-Mar-14 0
Fuel Day Tanks: Install Tank & Accessories 3 18-Mar-14 21-Mar-14 0
GENERATOR SETS (2 UNITS) 8 18-Mar-14 26-Mar-14 0
Generator Sets: Install w/ Vibro Isolator Gensets, Sync Panel w/ ComAp & Fuel Transfer Pump Duplex Controller 8 18-Mar-14 26-Mar-14 0
FUEL TRANSFER PUMPS (2 UNITS) 7 02-Apr-14 09-Apr-14 26
Fuel Transfer Pumps: Install Fuel Transfer Pump, Pipings & Accessories 7 02-Apr-14 09-Apr-14 26
MEP INSTALLATIONS 21 18-Mar-14 08-Apr-14 27
MEP: Roof Deck Framing (Exhaust Pipe & Muffler Supports) 2 18-Mar-14 20-Mar-14 32
MEP: Install Power Supply for Battery Charger 2 24-Mar-14 26-Mar-14 0
MEP: Install Exhaust Tail Pipe (BI Pipe) 3 25-Mar-14 28-Mar-14 27
MEP: Exhaust Pipe & Muffler Installation, Insulation & Aluminum Cladding 3 28-Mar-14 31-Mar-14 27
MEP: Install Exhaust Residential Muffler Bracket Support w/ Spring Hanger, Expansion Bellows & Y Adapter 2 31-Mar-14 02-Apr-14 31
MEP: Install Radiator Duct w/ Braces, Stiffeners & Supports 6 31-Mar-14 06-Apr-14 27
MEP: Install Louvers for Radiator Ducts 2 06-Apr-14 08-Apr-14 27
TERMINATIONS / TESTING / COMMISSIONING 42 26-Mar-14 07-May-14 0
Install & Terminate Power Cables & Control Wires 40 26-Mar-14 05-May-14 0
Testing & Commissioning Power Equipments 20 17-Apr-14 07-May-14 0
FUEL STORAGE TANK (4,800 GALLONS) 30 03-Mar-14 02-Apr-14 26
CIVIL / STRUCTURAL 23 03-Mar-14 26-Mar-14 26
CONCRETE PAD & CONTAINMENT (4,800 GALLONS) 23 03-Mar-14 26-Mar-14 26
Fuel Storage Tank Pad: Survey & Layout 1 03-Mar-14 04-Mar-14 26
Fuel Storage Tank Pad: Clearing/Grubbing/Grading 1 04-Mar-14 05-Mar-14 26
Fuel Storage Tank Pad: Excavate Foundations 1 05-Mar-14 06-Mar-14 26
Fuel Storage Tank Pad: Prepare Subgrade 1 06-Mar-14 07-Mar-14 26
Fuel Storage Tank Pad: Concrete Blinding/Lean Concrete 1 07-Mar-14 08-Mar-14 26
Fuel Storage Tank Pad: Install Rebars/Anchor Bolts/Forms 3 08-Mar-14 11-Mar-14 26
Fuel Storage Tank Pad: Concrete Pouring 1 11-Mar-14 12-Mar-14 26
Fuel Storage Tank Contaiment: Install CHB Walls 2 12-Mar-14 14-Mar-14 38
Fuel Storage Tank Pad: Concrete Curing prior to Tank Installation 14 12-Mar-14 26-Mar-14 26

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 41 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

ELECTRO-MECHANICAL 7 26-Mar-14 02-Apr-14 26


TANK & ACCESSORIES (4,800 GALLONS) 7 26-Mar-14 02-Apr-14 26
Fuel Storage Tank: Install Tank & Accessories 7 26-Mar-14 02-Apr-14 26
TRANSFORMER (TX) (1-4MVA 0.48V/34.5KV) 37 18-Mar-14 24-Apr-14 9
CIVIL / STRUCTURAL 28 18-Mar-14 15-Apr-14 9
UNDERGROUND CABLE TRENCH (EXITS TO GENSETS/SUBSTATION) 10 18-Mar-14 28-Mar-14 9
TX Cable Trench: Layout/Excavate/Grading 2 18-Mar-14 20-Mar-14 9
TX Cable Trench: Excavate Trenches (Exits to Gensets/SS) 1 20-Mar-14 21-Mar-14 9
TX Cable Trench: Construct Cable Trenches (Exits to Gensets/SS) 7 21-Mar-14 28-Mar-14 9
CONCRETE PAD 18 28-Mar-14 15-Apr-14 9
TX Pad: Prepare Subgrade 1 28-Mar-14 29-Mar-14 9
TX Pad: Blinding/Lean Concrete 1 29-Mar-14 30-Mar-14 9
TX Pad: Construct Pad 2 30-Mar-14 01-Apr-14 9
TX Pad: Concrete Curing Pad 14 01-Apr-14 15-Apr-14 9
ENCLOSURE (CYCLONE WIRE FENCE) 5 01-Apr-14 06-Apr-14 16
TX Fence: Construct Cyclone Wire Fence (Including Gate) 5 01-Apr-14 06-Apr-14 16
SITE DEVELOPMENT 2 06-Apr-14 08-Apr-14 16
TX Site Development: Prepare Subgrade for Gravel Fill (Including Ramp) 1 06-Apr-14 07-Apr-14 16
TX Site Development: Gravel Filling 1 07-Apr-14 08-Apr-14 16
ELECTRO-MECHANICAL 9 15-Apr-14 24-Apr-14 9
EQUIPMENT & ACCESSORIES (1-4MVA 0.48V/34.5KV) 9 15-Apr-14 24-Apr-14 9
TX Equipment: Install TX & Accessories 9 15-Apr-14 24-Apr-14 9
SHUNT REACTORS / INSULATORS (SRX) (12-3400KVAR) 50 14-Mar-14 02-May-14 0
CIVIL / STRUCTURAL 40 14-Mar-14 22-Apr-14 0
UNDERGROUND CABLE TRENCH (EXITS TO GENSETS/SUBSTATION) 16 14-Mar-14 30-Mar-14 8
SRX's & Insulators Cable Trench: Site Layout/Cleaing/Grubbing 2 14-Mar-14 16-Mar-14 8
SRX's & Insulators Cable Trench: Site Excavation/Grading 4 16-Mar-14 20-Mar-14 8
SRX's & Insulators Cable Trench: Layout & Excavate 500mmX500mm Cable Trenches 2 20-Mar-14 22-Mar-14 8
SRX's & Insulators Cable Trench: Construct 500mmX500mm Cable Trenches 8 22-Mar-14 30-Mar-14 8
CONCRETE PADS 16 07-Apr-14 22-Apr-14 0
SRX's & Insulators Pads: Layout & Prepare Subgrade 4 07-Apr-14 10-Apr-14 0
SRX's & Insulators Pads: Blinding/Lean Concrete 1 11-Apr-14 11-Apr-14 0
SRX's & Insulators Pads: Construct Pads 4 12-Apr-14 15-Apr-14 0
SRX's & Insulators Pads: Concrete Curing Pads prior to Equipments Installation 7 16-Apr-14 22-Apr-14 0
ENCLOSURE (CYCLONE WIRE FENCE) 7 10-Apr-14 16-Apr-14 0
SRX's & Insulators Fence: Construct Cyclone/Barb Wire Fence (Including Gate) 7 10-Apr-14 16-Apr-14 0
SITE DEVELOPMENT 6 17-Apr-14 22-Apr-14 0
SRX's & Insulators Site Development: Prepare Subgrade for Gravel Fill (Including Ramp) 4 17-Apr-14 20-Apr-14 0
SRX's & Insulators Site Development: Gravel Filling 2 21-Apr-14 22-Apr-14 0
ELECTRO-MECHANICAL 10 23-Apr-14 02-May-14 0
EQUIPMENT & ACCESSORIES (12-3400KVAR) 10 23-Apr-14 02-May-14 0
SRX's & Insulators Equipment: Install Shunt Reactors, Insulators & Accessories 10 23-Apr-14 02-May-14 0
POWER CABLING / TERMINATIONS / TESTING (YPBS TO SUBSTATION) 13 29-Apr-14 14-May-14 0
POWER CABLING (YPBS TO SUBSTATION) 10 29-Apr-14 10-May-14 3
YPBS : Install Grounding System 10 29-Apr-14 10-May-14 3
YPBS: Gensets-TX: Cable Pulling & Testing 3 07-May-14 10-May-14 0
POWER TERMINATIONS / TESTING (YPBS TO SUBSTATION) 6 07-May-14 14-May-14 0
YPBS : TX-SS: Cable Termination & Testing 3 07-May-14 10-May-14 3
YPBS : SRX-SS: Cable Termination & Testing 3 07-May-14 10-May-14 3
YPBS : Gensets-TX: Cable Termination & Testing 3 10-May-14 14-May-14 0
POWER SUBSTATION (EQUIPMENTS & ACCESSORIES BY OTHERS) 76 14-Mar-14 29-May-14 -16
ELECTRO-MECHANICAL 76 14-Mar-14 29-May-14 -16

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 42 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

POWER CABLING (SS TO YPBS) (CABLE PULLING TO FOLLOW ACCESS AT SS BY OTHERS) 18 14-Mar-14 01-Apr-14 38
Substation TX-SS: Cable Trench Layout & Excavation 2 14-Mar-14 16-Mar-14 38
Substation TX-SS: Cable Laying / Backfilling 7 16-Mar-14 23-Mar-14 38
Substation SRX-SS: Cable Trench Layout & Excavation 2 21-Mar-14 23-Mar-14 38
Substation SRX-SS: Cable Laying / Backfilling 7 23-Mar-14 30-Mar-14 38
Substation TX-SS: Cable Pulling & Testing 2 28-Mar-14 30-Mar-14 38 Requires access at Substation
Substation SRX-SS: Cable Pulling & Testing 2 30-Mar-14 01-Apr-14 38 Requires access at Substation
POWER TERMINATIONS / TESTING (TO FOLLOW ACCESS AT SS BY OTHERS) 60 30-Mar-14 29-May-14 -16
Substation: SS-TX: Cable Termination & Testing 4 30-Mar-14 03-Apr-14 40 Requires Substation Switchgears installed (By others)
Substation: SS-SRX: Cable Termination & Testing 4 01-Apr-14 05-Apr-14 38 Requires Substation Switchgears installed (By others)
Substation: RMU.D-SS: Cable Termination & Testing 4 13-Apr-14 17-Apr-14 25 Requires Substation Switchgears installed (By others)
Substation: C44-SS: Cable Termination & Testing 4 20-Apr-14 24-Apr-14 18 Requires Substation Switchgears installed (By others)
Substation: RMU.A-SS: Cable Termination & Testing 4 04-May-14 08-May-14 4 Requires RMU & Substation Switchgears installed (By others)
Substation: RMU.B-SS: Cable Termination & Testing 4 25-May-14 29-May-14 -16 Requires RMU & Substation Switchgears installed (By others)
RING MAIN UNIT - D (RMU & ACCESSORIES BY OTHERS) 46 24-Mar-14 10-May-14 27
SECTION 02 46 24-Mar-14 10-May-14 27
CIVIL / STRUCTURAL 46 24-Mar-14 10-May-14 27
RMU D: Survey, Clearing & Grading 2 24-Mar-14 26-Mar-14 0 Requires access at RMU-A Location (By others)
RMU D: Construct Equipment Pad (Includes Concrete Curing) 12 26-Mar-14 07-Apr-14 0
RMU D: Perimeter Fencing (If Required) 6 04-May-14 10-May-14 27
ELECTRICAL 21 13-Apr-14 04-May-14 8
RMU D: C25-RMU D: Cable Termination & Testing 2 13-Apr-14 16-Apr-14 27 Requires RMU installed (By others)
RMU D: RMU D-SS: Cable Termination & Testing 2 02-May-14 04-May-14 8 Requires RMU & Substation Switchgears installed (By others)
RING MAIN UNIT - A (RMU & ACCESSORIES BY OTHERS) 54 20-Mar-14 12-May-14 31
SECTION 03 (EAST & WEST) 54 20-Mar-14 12-May-14 31
CIVIL / STRUCTURAL 54 20-Mar-14 12-May-14 31
RMU A: Survey, Clearing & Grading 2 20-Mar-14 21-Mar-14 0 Requires access at RMU-A Location (By others)
RMU A: Construct Equipment Pad (Includes Concrete Curing) 12 21-Mar-14 02-Apr-14 0
RMU A: Perimeter Fencing (If Required) 6 07-May-14 12-May-14 31
ELECTRICAL 27 10-Apr-14 06-May-14 6
RMU A: RMU A-C09: Cable Termination & Testing 2 10-Apr-14 12-Apr-14 30 Requires Access at Substation
RMU A: RMU A-C18: Cable Termination & Testing 2 16-Apr-14 19-Apr-14 24 Requires RMU installed (By others)
RMU A: RMU A-SS: Cable Termination & Testing 2 04-May-14 06-May-14 6 Requires RMU & Substation Switchgears installed (By others)
RING MAIN UNIT - B (RMU & ACCESSORIES BY OTHERS) 33 30-Apr-14 02-Jun-14 11
SECTION 04 33 30-Apr-14 02-Jun-14 11
CIVIL / STRUCTURAL 33 30-Apr-14 02-Jun-14 11
RMU B: Survey, Clearing & Grading 2 30-Apr-14 02-May-14 -10 Requires access at RMU-B Location (By others)
RMU B: Construct Equipment Pad (Includes Concrete Curing) 12 02-May-14 14-May-14 -10
RMU B: Perimeter Fencing (If Required) 6 27-May-14 02-Jun-14 11
ELECTRICAL 7 20-May-14 27-May-14 -15
RMU B: RMU B-C48: Cable Termination & Testing 2 20-May-14 23-May-14 -10 Requires Access at Substation
RMU B: RMU B-C50: Cable Termination & Testing 2 23-May-14 26-May-14 -13 Requires Access at Substation
RMU B: RMU B-SS: Cable Termination & Testing 2 25-May-14 27-May-14 -15 Requires RMU & Substation Switchgears installed (By others)
FIELD SWITCHGEARS TERMINATION (TO FOLLOW SWITCHGEAR INSTALLATION BY OTHERS) 57 01-Apr-14 27-May-14 16
SECTION 01 22 01-Apr-14 22-Apr-14 9
C22: Terminate to Field Switchgear & Testing (RMU) 1 01-Apr-14 01-Apr-14 20 To follow WTG Cabling by FB & Switchgear Installed by others
C08: Terminate to Field Switchgear & Testing (RMU) 1 03-Apr-14 04-Apr-14 19 To follow WTG Cabling by FB & Switchgear Installed by others
C01: Terminate to Field Switchgear & Testing (RMU) 1 04-Apr-14 05-Apr-14 19 To follow WTG Cabling by FB & Switchgear Installed by others
C03: Terminate to Field Switchgear & Testing (RMU) 2 05-Apr-14 07-Apr-14 19 To follow WTG Cabling by FB & Switchgear Installed by others
C07: Terminate to Field Switchgear & Testing (RMU) 1 07-Apr-14 08-Apr-14 19 To follow WTG Cabling by FB & Switchgear Installed by others
C06: Terminate to Field Switchgear & Testing (RMU) 1 13-Apr-14 14-Apr-14 13 To follow WTG Cabling by FB & Switchgear Installed by others
C34: Terminate to Field Switchgear & Testing (RMU) 1 14-Apr-14 15-Apr-14 13 To follow WTG Cabling by FB & Switchgear Installed by others

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 43 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C15: Terminate to Field Switchgear & Testing (RMU) 2 16-Apr-14 18-Apr-14 12 To follow WTG Cabling by FB & Switchgear Installed by others
C44: Terminate to Field Switchgear & Testing (RMU) 1 21-Apr-14 22-Apr-14 9 To follow WTG Cabling by FB & Switchgear Installed by others
SECTION 02 13 24-Apr-14 07-May-14 15
C45: Terminate to Field Switchgear & Testing (RMU) 1 24-Apr-14 25-Apr-14 18 To follow WTG Cabling by FB & Switchgear Installed by others
C37: Terminate to Field Switchgear & Testing (RMU) 1 02-May-14 03-May-14 13 To follow WTG Cabling by FB & Switchgear Installed by others
C29: Terminate to Field Switchgear & Testing (RMU) 1 03-May-14 04-May-14 15 To follow WTG Cabling by FB & Switchgear Installed by others
C42: Terminate to Field Switchgear & Testing (RMU) 1 04-May-14 05-May-14 15 To follow WTG Cabling by FB & Switchgear Installed by others
C25: Terminate to Field Switchgear & Testing (RMU) 2 05-May-14 07-May-14 15 To follow WTG Cabling by FB & Switchgear Installed by others
SECTION 3A (WEST) 6 06-Apr-14 12-Apr-14 62
C17: Terminate to Field Switchgear & Testing (RMU) 1 06-Apr-14 07-Apr-14 62 To follow WTG Cabling by FB & Switchgear Installed by others
C16: Terminate to Field Switchgear & Testing (RMU) 1 07-Apr-14 08-Apr-14 62 To follow WTG Cabling by FB & Switchgear Installed by others
C04: Terminate to Field Switchgear & Testing (RMU) 1 08-Apr-14 09-Apr-14 62 To follow WTG Cabling by FB & Switchgear Installed by others
C14: Terminate to Field Switchgear & Testing (RMU) 2 09-Apr-14 11-Apr-14 62 To follow WTG Cabling by FB & Switchgear Installed by others
C09: Terminate to Field Switchgear & Testing (RMU) 1 11-Apr-14 12-Apr-14 62 To follow WTG Cabling by FB & Switchgear Installed by others
SECTION 3B (EAST) 15 22-Apr-14 07-May-14 37
C05: Terminate to Field Switchgear & Testing (RMU) 1 22-Apr-14 23-Apr-14 46 To follow WTG Cabling by FB & Switchgear Installed by others
C43: Terminate to Field Switchgear & Testing (RMU) 1 02-May-14 03-May-14 37 To follow WTG Cabling by FB & Switchgear Installed by others
C02: Terminate to Field Switchgear & Testing (RMU) 1 03-May-14 04-May-14 37 To follow WTG Cabling by FB & Switchgear Installed by others
C13: Terminate to Field Switchgear & Testing (RMU) 1 04-May-14 05-May-14 37 To follow WTG Cabling by FB & Switchgear Installed by others
C18: Terminate to Field Switchgear & Testing (RMU) 2 05-May-14 07-May-14 37 To follow WTG Cabling by FB & Switchgear Installed by others
SECTION 04 10 17-May-14 27-May-14 16
C19: Terminate to Field Switchgear & Testing (RMU) 1 17-May-14 18-May-14 20 To follow WTG Cabling by FB & Switchgear Installed by others
C35: Terminate to Field Switchgear & Testing (RMU) 1 18-May-14 19-May-14 20 To follow WTG Cabling by FB & Switchgear Installed by others
C12: Terminate to Field Switchgear & Testing (RMU) 1 19-May-14 20-May-14 20 To follow WTG Cabling by FB & Switchgear Installed by others
C50: Terminate to Field Switchgear & Testing (RMU) 2 24-May-14 26-May-14 16 To follow WTG Cabling by FB & Switchgear Installed by others
C48: Terminate to Field Switchgear & Testing (RMU) 1 26-May-14 27-May-14 16 To follow WTG Cabling by FB & Switchgear Installed by others
BOP COMPONENT TESTING & REPORT SUBMISSION 42 06-May-14 17-Jun-14 11
Section 01: BOP Component Testing & Report Submission - Section 01 (9 turbines) 1 06-May-14 07-May-14 5
Section 02: BOP Component Testing & Report Submission - Section 02 (5 turbines) 1 24-May-14 25-May-14 -2
Section 3A: BOP Component Testing & Report Submission - Section 03 (5 turbines) 1 26-May-14 27-May-14 26
Section 3B: BOP Component Testing & Report Submission - Section 03 (5 turbines) 1 26-May-14 27-May-14 31
Section 04: BOP Component Testing & Report Submission - Section 04 (5 turbines) 1 16-Jun-14 17-Jun-14 11
WTG TOWER BASE GROUTING (TO FOLLOW BASE & MID TOWER ERECTION BY OTHERS) 37 05-Mar-14 13-Apr-14 54
SECTION 01 23 15-Mar-14 08-Apr-14 17
WTG C08 TOWER BASE GROUTING 7 15-Mar-14 21-Mar-14 26
C08: WTG Tower Base Grouting 1 15-Mar-14 15-Mar-14 25 To Follow WTG B & M Tower Erection (By Others)
C08: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 16-Mar-14 19-Mar-14 28
C08: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 16-Mar-14 21-Mar-14 25
WTG C03 TOWER BASE GROUTING 7 16-Mar-14 22-Mar-14 30
C03: WTG Tower Base Grouting 1 16-Mar-14 16-Mar-14 29 To Follow WTG B & M Tower Erection (By Others)
C03: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 17-Mar-14 20-Mar-14 32
C03: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 17-Mar-14 22-Mar-14 29
WTG C01 TOWER BASE GROUTING 7 17-Mar-14 23-Mar-14 27
C01: WTG Tower Base Grouting 1 17-Mar-14 17-Mar-14 26 To Follow WTG B & M Tower Erection (By Others)
C01: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 18-Mar-14 21-Mar-14 29
C01: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 18-Mar-14 23-Mar-14 26
WTG C07 TOWER BASE GROUTING 7 22-Mar-14 30-Mar-14 26
C07: WTG Tower Base Grouting 1 22-Mar-14 22-Mar-14 25 To Follow WTG B & M Tower Erection (By Others)
C07: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 23-Mar-14 26-Mar-14 28
C07: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 23-Mar-14 30-Mar-14 25
WTG C34 TOWER BASE GROUTING 7 23-Mar-14 31-Mar-14 25
C34: WTG Tower Base Grouting 1 23-Mar-14 23-Mar-14 25 To Follow WTG B & M Tower Erection (By Others)

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 44 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

C34: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 24-Mar-14 27-Mar-14 27
C34: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 24-Mar-14 31-Mar-14 25
WTG C06 TOWER BASE GROUTING 7 24-Mar-14 01-Apr-14 24
C06: WTG Tower Base Grouting 1 24-Mar-14 24-Mar-14 24 To Follow WTG B & M Tower Erection (By Others)
C06: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 25-Mar-14 30-Mar-14 26
C06: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 25-Mar-14 01-Apr-14 24
WTG C15 TOWER BASE GROUTING 7 26-Mar-14 03-Apr-14 22
C15: WTG Tower Base Grouting 1 26-Mar-14 26-Mar-14 22 To Follow WTG B & M Tower Erection (By Others)
C15: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 27-Mar-14 01-Apr-14 24
C15: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 27-Mar-14 03-Apr-14 22
WTG C44 TOWER BASE GROUTING 7 27-Mar-14 04-Apr-14 21
C44: WTG Tower Base Grouting 1 27-Mar-14 27-Mar-14 21 To Follow WTG B & M Tower Erection (By Others)
C44: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 30-Mar-14 02-Apr-14 23
C44: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 30-Mar-14 04-Apr-14 21
WTG C22 TOWER BASE GROUTING 7 02-Apr-14 08-Apr-14 7
C22: WTG Tower Base Grouting 1 02-Apr-14 02-Apr-14 6 To Follow WTG B & M Tower Erection (By Others)
C22: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 03-Apr-14 06-Apr-14 9
C22: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 03-Apr-14 08-Apr-14 6
SECTION 02 29 10-Mar-14 10-Apr-14 29
WTG C45 TOWER BASE GROUTING 7 10-Mar-14 16-Mar-14 43
C45: WTG Tower Base Grouting 1 10-Mar-14 10-Mar-14 42 To Follow WTG B & M Tower Erection (By Others)
C45: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 11-Mar-14 14-Mar-14 45
C45: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 11-Mar-14 16-Mar-14 42
WTG C29 TOWER BASE GROUTING 7 12-Mar-14 18-Mar-14 46
C29: WTG Tower Base Grouting 1 12-Mar-14 12-Mar-14 45 To Follow WTG B & M Tower Erection (By Others)
C29: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 13-Mar-14 16-Mar-14 48
C29: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 13-Mar-14 18-Mar-14 45
WTG C42 TOWER BASE GROUTING 7 13-Mar-14 19-Mar-14 47
C42: WTG Tower Base Grouting 1 13-Mar-14 13-Mar-14 46 To Follow WTG B & M Tower Erection (By Others)
C42: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 14-Mar-14 17-Mar-14 49
C42: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 14-Mar-14 19-Mar-14 46
WTG C25 TOWER BASE GROUTING 7 15-Mar-14 22-Mar-14 46
C25: WTG Tower Base Grouting 1 15-Mar-14 16-Mar-14 45 To Follow WTG B & M Tower Erection (By Others)
C25: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 16-Mar-14 20-Mar-14 48
C25: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 16-Mar-14 22-Mar-14 45
WTG C37 TOWER BASE GROUTING 7 03-Apr-14 10-Apr-14 23
C37: WTG Tower Base Grouting 1 03-Apr-14 03-Apr-14 22 To Follow WTG B & M Tower Erection (By Others)
C37: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 04-Apr-14 07-Apr-14 25
C37: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 04-Apr-14 10-Apr-14 22
SECTION 3A (WEST) 35 05-Mar-14 11-Apr-14 56
WTG C16 TOWER BASE GROUTING 7 05-Mar-14 11-Mar-14 79
C16: WTG Tower Base Grouting 1 05-Mar-14 05-Mar-14 78 To Follow WTG B & M Tower Erection (By Others)
C16: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 06-Mar-14 09-Mar-14 81
C16: WTG WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 06-Mar-14 11-Mar-14 78
WTG C04 TOWER BASE GROUTING 7 06-Mar-14 12-Mar-14 80
C04: WTG Tower Base Grouting 1 06-Mar-14 06-Mar-14 79 To Follow WTG B & M Tower Erection (By Others)
C04: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 07-Mar-14 10-Mar-14 82
C04: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 07-Mar-14 12-Mar-14 79
WTG C14 TOWER BASE GROUTING 7 07-Mar-14 13-Mar-14 81
C14: WTG Tower Base Grouting 1 07-Mar-14 07-Mar-14 80 To Follow WTG B & M Tower Erection (By Others)
C14: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 08-Mar-14 11-Mar-14 83
C14: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 08-Mar-14 13-Mar-14 80

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 45 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

WTG C09 TOWER BASE GROUTING 7 08-Mar-14 14-Mar-14 81


C09: WTG Tower Base Grouting 1 08-Mar-14 08-Mar-14 81 To Follow WTG B & M Tower Erection (By Others)
C09: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 09-Mar-14 12-Mar-14 83
C09: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 09-Mar-14 14-Mar-14 81
WTG C17 TOWER BASE GROUTING 7 04-Apr-14 11-Apr-14 48
C17: WTG Tower Base Grouting 1 04-Apr-14 04-Apr-14 47 To Follow WTG B & M Tower Erection (By Others)
C17: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 05-Apr-14 08-Apr-14 50
C17: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 05-Apr-14 11-Apr-14 47
SECTION 3B (EAST) 23 19-Mar-14 13-Apr-14 54
WTG C13 TOWER BASE GROUTING 7 19-Mar-14 25-Mar-14 70
C13: WTG Tower Base Grouting 1 19-Mar-14 19-Mar-14 29 To Follow WTG B & M Tower Erection (By Others)
C13: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 20-Mar-14 23-Mar-14 72
C13: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 20-Mar-14 25-Mar-14 29
WTG C18 TOWER BASE GROUTING 7 20-Mar-14 26-Mar-14 69
C18: WTG Tower Base Grouting 1 20-Mar-14 20-Mar-14 69 To Follow WTG B & M Tower Erection (By Others)
C18: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 21-Mar-14 24-Mar-14 71
C18: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 21-Mar-14 26-Mar-14 69
WTG C43 TOWER BASE GROUTING 7 21-Mar-14 27-Mar-14 68
C43: WTG Tower Base Grouting 1 21-Mar-14 21-Mar-14 68 To Follow WTG B & M Tower Erection (By Others)
C43: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 22-Mar-14 25-Mar-14 70
C43: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 22-Mar-14 27-Mar-14 68
WTG C05 TOWER BASE GROUTING 7 05-Apr-14 12-Apr-14 53
C05: WTG Tower Base Grouting 1 05-Apr-14 05-Apr-14 52 To Follow WTG B & M Tower Erection (By Others)
C05: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 06-Apr-14 10-Apr-14 55
C05: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 06-Apr-14 12-Apr-14 52
WTG C02 TOWER BASE GROUTING 7 06-Apr-14 13-Apr-14 54
C02: WTG Tower Base Grouting 1 06-Apr-14 06-Apr-14 54 To Follow WTG B & M Tower Erection (By Others)
C02: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 07-Apr-14 11-Apr-14 56
C02: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 07-Apr-14 13-Apr-14 54
SECTION 04 27 09-Mar-14 06-Apr-14 60
WTG C48 TOWER BASE GROUTING 7 09-Mar-14 15-Mar-14 80
C48: WTG Tower Base Grouting 1 09-Mar-14 09-Mar-14 80 To Follow WTG B & M Tower Erection (By Others)
C48: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 10-Mar-14 13-Mar-14 82
C48: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 10-Mar-14 15-Mar-14 80
WTG C50 TOWER BASE GROUTING 7 31-Mar-14 06-Apr-14 60
C50: WTG Tower Base Grouting 1 31-Mar-14 31-Mar-14 60 To Follow WTG B & M Tower Erection (By Others)
C50: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 01-Apr-14 04-Apr-14 62
C50: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 01-Apr-14 06-Apr-14 60
WTG C19 TOWER BASE GROUTING 7 30-Mar-14 05-Apr-14 61
C19: WTG Tower Base Grouting 1 30-Mar-14 30-Mar-14 61 To Follow WTG B & M Tower Erection (By Others)
C19: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 31-Mar-14 03-Apr-14 63
C19: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 31-Mar-14 05-Apr-14 61
WTG C35 TOWER BASE GROUTING 7 30-Mar-14 05-Apr-14 61
C35: WTG Tower Base Grouting 1 30-Mar-14 30-Mar-14 61 To Follow WTG B & M Tower Erection (By Others)
C35: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 31-Mar-14 03-Apr-14 63
C35: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 31-Mar-14 05-Apr-14 61
WTG C12 TOWER BASE GROUTING 7 30-Mar-14 05-Apr-14 61
C12: WTG Tower Base Grouting 1 30-Mar-14 30-Mar-14 61 To Follow WTG B & M Tower Erection (By Others)
C12: Grout Sealant Application & Curing Prior to Anchor Stud Tensioning 4 31-Mar-14 03-Apr-14 63
C12: WTG Tower Base Grout Curing Prior to Base & Mid Tower Erection (Includes Test Results) 6 31-Mar-14 05-Apr-14 61
PRE-COMMISSIONING & TURBINE STARTUP (BY OTHERS) 80 21-Apr-14 09-Jul-14 0
PRE-COMMISSIONING (TO FOLLOW CABLE TERMINATIONS BY FB & MECHANICAL COMPLETION BY OTHERS) 36 21-Apr-14 03-Jun-14 27

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 46 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone
Activity Name Rem Start Finish TF Issues/Constraints 2014
Dur JJJJJ JJ

SECTION 01 18 21-Apr-14 12-May-14 7


SECTION 02 13 26-Apr-14 13-May-14 11
SECTION 3A (WEST) 10 21-Apr-14 03-May-14 42
SECTION 3B (EAST) 16 24-Apr-14 13-May-14 39
SECTION 04 12 19-May-14 03-Jun-14 27
TURBINE STARTUP / COMMISSIONING (BY OTHERS) 42 29-May-14 09-Jul-14 0
SECTION 01 9 29-May-14 07-Jun-14 -15
SECTION 02 5 29-May-14 04-Jun-14 -4
SECTION 3A (WEST) 5 23-Jun-14 27-Jun-14 0
SECTION 3B (EAST) 5 28-Jun-14 03-Jul-14 0
SECTION 04 5 04-Jul-14 09-Jul-14 0
CLOSEOUT 131 23-Mar-14 01-Aug-14 11

FINISHING / PUNCHLISTING 131 23-Mar-14 01-Aug-14 11


SECTION 01 71 11-Apr-14 21-Jun-14 9
SECTION 02 94 06-Apr-14 09-Jul-14 26
SECTION 3A (WEST) 111 23-Mar-14 11-Jul-14 31
SECTION 3B (EAST) 96 15-Apr-14 20-Jul-14 22
SECTION 04 110 13-Apr-14 01-Aug-14 11

Remaining Level of Effort Actual Work Milestone S...TASK filters: Activity Type, Layout Filter. Date Revision Checked Approved Page
21-Feb-14 Rev.T
Actual Level of Effort Remaining Work Critical Milestone 47 of 47
Critical Level of Effort Critical Remaining Work Actual Milestone

Das könnte Ihnen auch gefallen