1x GT13E2 Equipment Package
TGNV 2007-037
Technical Information
2. Scope of Work
2. Scope of Work
. General Considerations
2.1.1, Scope Overview
2.1.2. Supply Basis
2.1.3. Definition of Quantities and “Percent Duty” Figures
Scope of Supply
2.2.1. Gas Turbine and Auxiliaries
2.2.2. Generator & Generator Equipment
2.2.3, Electrical and Control Equipment
Limits of Supply
2.3.1. Termination Points
. Scope of Services
Customer's Obligations
2.5.1, Customer's Scope of Supply
2.5.2. Customer's Scope of Services
Mandatory and Optional Equipment & Services
2.6.1. Mandatory Scope in Addition to Base Scope
2.6.2. Optional Equipment and Services
Attachements
End of Document
ONNN
oN
12
16
17
17
18
21
21
21
22
221 x GT13E2 Equipment Package Technical Information
TGNV 2007-037 2.1 General Considerations
2.1. General Considerations
2.1.1. Scope Overview
This scope of supply covers the design, manufacturing, delivery (Ex Works) and
supporting services of one (1)GT13E2 Equipment Package, consisting of the
materials and services listed in this section.
This submittal includes:
* One (1) gas turbine generator package, type GT13E2, for outdoor installation and
for operation on Natural Gas only
Auxiliary equipment for the gas turbine as described
Electrical equipment for the gas turbine as described
* Control and instrumentation for the gas turbine as described
+ Delivery (Ex Works) as described
Technical Field Advisory (TFA) and Technical Commissioning Advisory (TCA) as
described
+ Engineering, documentation, training and operation & maintenance manuals as
described
2.1.2. Supply Basis
Gas Turbine Equipment Arrangement
The proposed scope is based on the Alstom standard layout (considering outdoor
arrangement for all equipment supplied by Alstom) for gas turbine equipment
package provided under chapter 3.8.
Equipment Design
This submittal is based on the design basis provided under chapter 3.
Component Type and Origin
This submittal is based on standardised components and pre-selected supplier
material.
Alstom approves only those subcontractors, which have demonstrated to Alstom’s
full satisfaction that they have the requisite technical knowledge and practical ability
to supply such work on key projects. Alstom reserve the right to subcontract any
element of the work at its discretion to any Alstom approved subcontractor or any
company within the Alstom group of companies.
Change of Supply Basis
Any changes to the supply bases as listed above, need to be mutually agreed.
Scope Definitions
In case of any discrepancy between the scope of work described in this chapter 2
and other description of this submittal, the description of this chapter 2 shall prevail.
Page 21 x GT13E2 Equipment Package Technical Information
TGNV 2007-037 2.1 General Considerations
All equipment and services, which are not explicitly listed under Alstom scope in this
chapter 2, are excluded.
2.1.3. Definition of Quantities and “Percent Duty” Figures
Unless specified differently
+ All duty percentage figures (e.g. 1 x 100%) refer to one (1) GT13E2 unit, i.e.
100% is equivalent to the capacity (flow, heat load etc.) required for
one (1) GT13E2 unit
+ All quantities listed in this section refer to one (1) GT13E2 unit.
+ Exceptions to the above statement are mentioned explicitly where applicable with
remarks in italics
Page 3