Sie sind auf Seite 1von 959

This software is based on Standard Data book for analys

Bridge Works

This Software runs on Microsoft Excel

INPUT- Input the usage rates of Plant & Machinery, labour an

SUMMARY - In this sheet summary of all the rates analysized

ANALYSIS- The analysis has been presented in 16 nos. of sp

Worksheet- 1 :

Worksheet- 2 :

Worksheet- 3 :

Worksheet- 4 :

Worksheet- 5 :

Worksheet- 6 :

Worksheet- 7 :

Worksheet- 8 :

Worksheet- 9 :

Worksheet- 10 :

Worksheet- 11 :

Worksheet- 12 :

Worksheet- 13 :

Worksheet- 14 :

Worksheet- 15 :

Worksheet- 16 :

Worksheet- 17 :

Worksheet- 18 :
This software is based on Standard Data book for analysis of Rates for Road and
Bridge Works

This Software runs on Microsoft Excel

INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable

SUMMARY - In this sheet summary of all the rates analysized is presented

ANALYSIS- The analysis has been presented in 16 nos. of spread sheets

CHAPTER-1 CARRIAGE OF MATERIALS

CHAPTER-2 SITE CLEARANCE

CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE

CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS

CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)

CHAPTER-6 CEMENT CONCRETE PAVEMENTS

CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH

CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD


APPURTENANCES

CHAPTER-9 PIPE CULVERTS

CHAPTER-10 MAINTENANCE OF ROADS

CHAPTER-11 HORTICULTURE

CHAPTER-12 FOUNDATIONS

CHAPTER-13 SUB-STRUCTURE

CHAPTER-14 SUPER-STRUCTURE

CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS

CHAPTER-16 REPAIR AND REHABILITATION

CHAPTER-17 MISCELLANEOUS ITEMS OF WORK

CHAPTER-18 NEW TECHNOLOGY


Page-3

CONTENTS

Chapter Item No. Descriptions

PART-A
ROADS WORKS
1 LOADING, UNLOADING & CARRIAGE OF MATERIALS
Preamble
1.1 Loading and unloading of boulder, tone, sand, moorum fly ash etc. by mechanical means
1.2 Loading and Unloading of boulder, tone, sand, moorum fly ash etc. by Manual Means

1.3 Loading and Unloading of Cement or Steel by Manual Means


1.4 Cost of Haulage Excluding Loading and Unloading
2 SITE CLEARANCE
Preamble
2.1 Cutting of Trees, including Cutting of Trunks, Branches and Removal
2.2 Clearing Grass and Removal of Rubbish
2.3 Clearing and Grubbing Road Land
2.4 Dismantling of Structures
2.5 Dismantling of Flexible Pavements
2.6 Dismantling of Cement Concrete Pavement
2.7 Dismantling Guard Rails
2.8 Dismantling Kerb Stone
2.9 Dismantling Kerb Stone channel
2.10 Dismantling Kilometre Stone
2.11 Dismantling of Fencing
2.12 Dismantling of CI Water Pipe Line
2.13 Removal of Cement Concrete Pipe of Sewer Gutter
2.14 Removal of Telephone / Electric Poles and Lines
3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Preamble
3.1 Excavation in Soil by Manual Means
3.2 Excavation in ordinary rock by manual means
3.3 Excavation in Soil with Dozer
3.4 Excavation in Ordinary Rock with Dozer
3.5 Excavation in Hard Rock (requiring blasting)
3.6 Excavation in Soil using Hydraulic Excavator
3.7 Excavation in Ordinary Rock using Hydraulic Excavator
3.8 Excavation in Hard Rock (blasting prohibited)
3.9 Excavation in Hard Rock (controlled blasting)
3.10 Excavation in Marshy Soil
3.11 Removal of Unserviceable Soil
Page-4

3.12 Pre-splitting of Rock Excavation Slopes


3.13 Excavation for Structures
3.14 Scarifying Existing Granular Surface by Manual Means
3.15 Scarifying existing bituminous surface by mechanical means
3.16 Embankment Construction with Material Obtained from Borrow Pits
3.17 Construction of Embankment with Material Deposited from Roadway Cutting
3.18 Construction of Subgrade and Earthen Shoulders
3.19 Compacting Original Ground
Case-I Compacting original ground supporting subgrade
Case-II :Compacting original ground supporting embankment
3.20 Stripping and Storing Top Soil
3.21 Stripping, storing and re-laying top soil from borrow areas in agriculture fields
3.22 Turfing with Sods
3.23 Seeding and Mulching
3.24 Surface Drains in Soil
3.25 Surface Drains in Ordinary Rock
3.26 Surface Drains in Hard Rock
3.27 Sub Surface Drains with Perforated Pipe
3.28 Aggregate Sub- Surface Drains
3.29 Underground Drain at Edge of Pavement
3.31 Construction of Rock fill Embankment
3.32 Excavation in Hill Area in Soil by Mechanical Means
3.33 Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting.
3.34 Excavation in Hilly Areas in Hard Rock Requiring Blasting
3.36 Embankment Construction with Fly ash/Pond ash available from coal or lignite burning
Thermal Plants as waste material
4 SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Preamble
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
4.2 Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2)
4.3 Lime Stabilisation for Improving Subgrade
4.4 Lime Treated Soil for Sub- Base
4.5 Cement Treated Soil Sub Base/ Base
4.6 Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub
base/ Base
4.7 Making 50 mm x 50 mm Furrows
4.8 Inverted Choke
4.9 Water Bound Macadam
4.10 Crushed Cement Concrete Sub-base / Base
Page-5

4.11 Penetration Coat Over Top Layer of Crushed Cement Concrete Base
4.12 Wet Mix Macadam
4.13 Construction of Median and Island with Soil Taken from Roadway Cutting
4.14 Construction of Median and Island with Soil Taken from Borrow Areas
4.15 Construction of Shoulders (A. Earthen Shoulders)
4.16 Footpaths and Separators
4.17 Crusher Run Macadam Base
4.18 Lime, Fly ash stabalised soil sub-base
5 BASES AND SURFACE COURSES (BITUMINOUS)
Preamble
5.1 Prime coat
5.2 Tack coat
5.3 Bituminous Macadam
5.5 Built-Up-Spray Grout
5.6 Dense Graded Bituminous Macadam
5.7 Semi - Dense Bituminous Concrete
5.8 Bituminous Concrete
5.9 Surface Dressing
5.10 Open - Graded Premix Surfacing
5.11 Close Graded Premix Surfacing/Mixed Seal Surfacing
5.12 Seal Coat
5.13 Supply of Stone Aggregates for Pavement Courses
5.14 Mastic Asphalt
5.15 Slurry Seal
5.16 Recycling of Bituminous Pavement with Central Recycling Plant
5.17 Fog Spray
5.18 Bituminous Cold Mix
5.19 Sand Asphalt Base Course
5.20 Modified Binder
5.21 Crack Prevention Courses
6 CEMENT CONCRETE PAVEMENTS
Preamble
6.1 Dry Lean Cement Concrete Sub- base
6.2 Cement Concrete Pavement
6.3 Rolled Cement Concrete Base
6.5 Construction of Base/Sub-base of pavement with lean concrete - fly ash
6.6 Cement - Fly ash concrete pavement
Page-6

7 GEOSYNTHETICS AND REINFORCED EARTH


Preamble
7.1 Sub-Surface Drain with Geotextiles
7.2 Narrow Filter Sub-Surface Drain
7.3 Laying Paving Fabric Beneath a Pavement Overlay
7.4 Laying Boulder Apron in Crates of Synthetic Geogrids
7.5 Reinforced Earth Retaining Wall
7.6 'Sub-Grade Stabilization:
7.7 Wooven Jute Jio Textile
8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Preamble
8.1 Cast in Situ Cement Concrete M20 kerb
8.2 Cast in Situ Cement Concrete M 20 Kerb with Channel
8.3 Printing new letter and figures of any shade
8.4 Retro reflectorised Traffic sign
8.5 Direction and place identification sign upto 0.9sqm size board.
8.6 Direction and place identification sign more than 0.9sqm size board
8.7 Over head sign:
8.8 Painting Two Coats on New Concrete Surfaces
8.9 Painting on Steel Surfaces
8.10 Painting on Wood Surfaces
8.11 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work
8.12 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work
8.13 Laying of hot applied thermoplastic compound including reflectorising glass beads
8.14 Kilo Metre Stone
8.16 Boundary pillar
8.17 G.I Barbed wire Fencing 1.2 metre high
8.18 G.I Barbed wire Fencing 1.8 metre high
8.19 Fencing with welded steel wire Fabric
8.20 Tubular Steel Railing on Medium Weight steel channel
8.21 Tubular Steel Railing on Precast RCC posts,
8.22 Reinforced Cement Concrete Crash Barrier
8.23 Metal Beam Crash Barrier
8.24 Road Traffic Signals electrically operated
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier
8.26 Anti - Glare Devices in Median
8.27 Street Lighting
Page-7

8.28 Lighting on Bridges


8.29 Cable Duct Across the Road
8.34 Traffic Impact Attenuators at Abutments and Piers
8.43 Portable Barricade in Construction Zone
8.44 Permanent Type Barricade in Construction Zone
8.45 Drum Delineator in Construction Zone
8.46 Flagman
8.47 ‘Sparkle Solar Road Studs
8.48 Spring post
8.49 Tree reflector made of heigh intensity grade retro-reflectorised sheeting
8.50 Linear Delineator System with Diamond grade reflective sheeting
8.51 Reflective pavement marker with Micro prismatic lens in both direction
8.52 Traffic cones
8.53 Inter linking chain link for traffic cones.
8.54 Metal tubular delineator
8.55 Erecting of city stud of dimension 220x100x40 mm plastic body
8.56 Erecting city stud with shank of dimension 220x100x40 mm
8.57 Erecting FT Marker
8.58 Providing and erecting Ministar Road studs
8.59 Reflector for Guard rails for large profile metal bracket
8.60 Reflector for Guard rails for all profile metal bracket
8.61 Providing and fixing Reflector for Guard rails for B profile with dimensions
8.62 Acoustic Wildlife Warning Module(WWA)
8.63 Optical Wildlife Warning Reflector(WWR)
8.64 Metal road studs for permanent marking
8.65 Globemarker
8.66 Metal road stud
8.67 Metal road stud with dimensions 100x50x20mm
8.68 Metal road stud with dimensions 149x149x27mm
8.69 Special road stud
8.70 Lane divider with dimensions 220x150x285 mm
8.71 Lane divider with dimensions 220x150x285 mm
8.72 Reflective inserts for road studs with dimensions 112.7x18.25 mm
8.73 Vertical marking with dia.104 mm
8.74 Vertical marking with dia.60 mm
8.75 Median Markers
8.76 Reflectors for concrete barriers with dimensions146x88 mm
Page-8

8.77 Reflectors for concrete barriers with dimensions 128x110 mm


8.78 Signflash A630 solar flashing LED unit
8.79 Swaroline module100 6 LEDs
9 PIPE CULVERTS
Preamble
9.1 PCC 1:3:6 in Foundation

9.2 Labour for laying Reinforced cement concrete pipe NP4/NP3/prestressed concrete pipe for
culverts single line
9.3 Labour for laying Reinforced cement concrete pipe NP4/NP3/prestressed concrete pipe for
culverts for double line
10 MAINTENANCE OF ROADS
Preamble
10.1 Restoration of Rain Cuts
10.2 Maintenance of Earthen Shoulder
10.3 Maintenance of Earth Shoulder
10.4 Filling Pot- holes and Patch Repairs with open - graded Premix surfacing
10.5 Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm
10.6 Crack Filling
10.7 Dusting
10.8 Fog Seal
10.9 Repair of joint Grooves with Epoxy Mortar
10.10 Repair of old Joints Sealant
10.11 Hill Side Drain Clearance
10.12 Land Slide Clearance in soil
10.13 Land slide Clearance in Hard Rock Requiring Blasting
10.14 Snow Clearance on Roads with Dozer
10.15 Snow Clearance on Roads with Snow Blowers
11 HORTICULTURE
Preamble
11.1 Spreading of Sludge Farm Yard Manure or/and good Earth
11.2 Grassing with ' Doobs' Grass
11.3 Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod
11.4 Maintenance of Lawns or Turfing of Slopes
11.5 Turfing Lawns with Fine Grassing including Ploughing, Dressing
11.6 Maintenance of Lawns with Fine Grassing for the First Year
11.7 a) Planting Permanent Hedges including Digging of Trenches
11.8 Flowering Plants and Shrubs in Central Verge
11.9 Planting of Trees and their Maintenance for one Year
11.10 Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil
Page-9

11.14 Half Brick Circular Tree Guard, in 2nd class Brick


11.15 Edging with 2nd class Bricks, laid dry lengthwise
11.16 Making Tree Guard 53 cm dia and 1.3 m high
11.17 Making Tree Guard 53 cm dia and 2 metres high
11.18 Wrought Iron and Mild Steel Welded Work
11.19 Tree Guard with MS Iron
11.20 Tree Guard with MS Angle Iron and Steel Wire
11.21 Compensatory Afforestation
PART-B
BRIDGE WORKS
12 FOUNDATIONS
Preamble
12.1 Excavation for Structures
12.2 Filling Annular Space Around Footing in Rock
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification
12.4 PCC 1:3:6 in Foundation
12.5 Brick masonry work in cement mortar 1:3 in foundation
12.6 Cement mortar works
12.7 Stone masonry work in cement mortar 1:3 in foundation
12.8 Plain/Reinforced cement concrete, in open foundation
(N) Without plasticiser
(P) With plasticiser
12.9 temporary island
12.10 Cutting edge of mild steel
12.11 Plain/Reinforced cement concrete, in well foundation
(N) Without plasticiser
(P) With plasticiser
12.12 Sinking of 6 m external diameter well
12.13 Sinking of 7 m external diameter well
12.14 Sinking of 8 m external diameter well
12.15 Sinking of 9 m external diameter well
12.16 Sinking of 10 m external diameter well
12.17 Sinking of 11 m external diameter well
12.18 Sinking of 12 m external diameter well
12.19 Sinking of Twin D Type well
12.20 Pneumatic sinking of wells
12.21 Sand filling in wells
12.22 steel liner 10 mm thick for curbs
Page-10

12.23 Bored cast-in-situ M35 grade R.C.C. of diameter-750 mm


12.24 Bored cast-in-situ M35 grade R.C.C. of diameter-1000 mm
12.25 Bored cast-in-situ M35 grade R.C.C. of diameter-1200 mm
12.26 Driven cast-in-place vertical M35 grade R.C.C. pile ofe diameter - 750 mm
12.27 Driven cast-in-place vertical M35 grade R.C.C. pile ofe diameter - 1000 mm
12.28A Driven cast-in-place vertical M35 grade R.C.C. pile ofe diameter - 1200 mm
12.37 Pile load test on single vertical pile
12.38 Cement concrete for reinforced concrete in pile cap
(N) Without plasticiser
(P) With plasticiser
12.39 Levelling course for Pile cap
12.40 Reinforcement in Foundation with TMT bar
12.41 Reinforcement in Foundation with TMT bar
13 SUB-STRUCTURE
Preamble
13.1 Brick masonry work in 1:3 in sub-structure
13.2 Pointing with cement mortar (1:3 ) on brick work
13.3 Plastering with cement mortar (1:3 ) on brick work
13.4 Stone masonry work in cement mortar 1:3 for substructure
13.5 Plain/Reinforced cement concrete, in sub structure complete as per drawing and technical
specification and steel shuttering formwork
(N) Without plasticiser
(P) With plasticiser
13.7 Mild steel reinforcement
13.8 Weep holes
13.9 Back filling
13.10 Filter media with granular materials/stone crushed aggregates
13.11 Cast steel rocker bearing
13.12 Forged steel roller bearing
13.13 Sliding plate bearing
13.14 Elastomeric bearing
13.15 Sliding plate bearing
13.16 POT-PTFE bearing
14 SUPER-STRUCTURE
Preamble
14.1 Reinforced/Prestressed cement concrete in super-structure
(N) Without Plasticiser
(P) WithPlasticiser
Page-11

14.2 Reinforcement in Super Structure with TMT bar


14.3 High tensile steel wires/strands
14.4 Cement concrete wearing coat M-30 grade
14.5 Mastic Asphalt
14.6 precast RCC railing of M30 Grade
14.7 RCC railing of M30 Grade
14.8 Mild steel railing
14.9 Drainage Spouts
14.10 PCC M15 Grade leveling course below approach slab
14.11 Reinforced cement concrete approach slab
14.12 Anti-corrosive treatment to HYSD/TMT reinforcement
14.13 Precast - pretensioned Girders
14.16 Painting on concrete surface
14.17 Burried Joint
14.18 Filler joint
14.19 Asphaltic Plug joint
14.20 Elastomeric Slab Steel Expansion Joint
14.21 Compression Seal Joint
14.22 Strip Seal Expansion Joint
14.23 Modular Strip / Box Seal Joint
14.24 Modular Strip / Box Seal Joint
14.25 Extra for providing water proofing compound
14.26 Extra for providing water proofing compound
15 RIVER TRAINING AND PROTECTION WORKS
Preamble
15.1 boulders apron on river bed
15.2 Boulder apron laid in wire crates
15.3 Cement concrete blocks
15.4 Pitching on slopes
15.5 Filter material
15.8 Flooring
15.9 Dry rubble Flooring
15.10 Curtain wall
15.11 Flexible Apron
15.12 Gabian Structure for Retaining Earth
15.13 Gabian Structure for Erosion Control, River Training Works and Protection works

16 REPAIR AND REHABILITATION


Page-12

Preamble
16.1 Removal of existing cement concrete wearing coat
16.2 Removal of existing asphaltic wearing coat
16.3 Guniting concrete surface with cement mortar
16.4 Inserting nipples for grouting
16.5 Sealing of cracks/porous concrete
16.6 Patching of damaged concrete surface with polymer concrete
16.7 Sealing of crack / porous concrete with Epoxy Grout
16.8 Epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel
reinforcement
16.9 Shotcrete mixture mechanically with compressed air
16.10 Pre-packed cement based polymer mortar
16.11 Eproxy bonding of new concrete to old concrete
16.12 External prestressing of span 25m
16.13 External prestressing of span 50m
16.14 External prestressing of span 100m
16.15 Labour for replacement of Bearings
16.16 Labour for Lifting of superstructure
16.17 Replacement of Expansion Joints
16.18 Replacement of damaged concrete railing.
16.19 Replacement of crash barrier.
16.20 Replacement of damaged mild steel railing
16.21 Repair of crash barrier
16.22 Repair of RCC Railing
16.23 Repair of steel Railing
16.24 Chipping of deteriorated concrete
16.25 Replacement of corroded reinforcement
16.26 Anticorrosive treatment
16.28 Bonding between old and new concret surfaces
16.29 Plastering the surface with high rich polymer modified mortar
16.30 Concreting of the structure with nonshrink cementitious microconcrete with Mastergrout
16.31 Concreting of the structure with free flow nonshrink cementitious microconcrete with
Rendorec RG of Fosroc
16.32 Laying Zinc anode unit Galvashield XP of Fosroc make
16.33 Structural Strengthening with carbon Fibre:
16.34 Grouting with slurry of neat cement & chloride free expanding grout Mastergrout CPG-1
16.35 Low viscous Epoxy grout with Mastergrout EP 150
16.36 Recron3S
Page-13

16.37 Anti-carbonation - a protective coating Techguard 103


16.38 Antiwash, non-shrink, cementatious, high strength Renderoc UW
16.39 Drilling 14 mm dia holes on the concrete surface

16.40 Fabrication and fixing of steel pedestal support for bearing


16.41 Foundation bolts for steel pedestals.
16.42 Steel plates for placing of bearings
16.43 Non-destuctive testing with Ultrasonic Pulse Velocity Meter
16.44 Non-destuctive testing with Profometer 5 Scanlog or equivalent
16.45 Non-destuctive testing with Permeability Tester
16.46 Conducting PH tests on concrete stucture
16.47 Conducting Carbonation tests on concrete stucture
16.48 Conducting suitable tests on concrete stucture
16.49 Conducting Concrete Core tests
16.50 Evaluation of Loss of pre-stress in superstructure PSC girders
16.51 Stressing operation and grouting
16.52 Load testing of existng foundation
16.53 Chemical rebar fastners
17 MISCELLANEOUS ITEMS OF WORK
Preamble
17.1 Cold weather Bamboo Bridge
17.2 Construction of Temporary Bamboo Bridge.
17.3 Bamboo Foot Bridge
17.4 Driving Sal Piles 25cm to 30cm dia
17.5 Driving Non Sal Piles 25cm to 30cm dia
17.6 Sal wood Work
17.7 Non Sal wood Work
17.8 Timber Beam and Bearing Beam
17.9 Sal Wood Log Beam
17.10 Non Sal Timber Beam and Bearing Beam
17.11 Labour for Scarfing and joining Piles
17.12 Labour for taking out old Piles
17.13 Labour for Dismentalling all members of Timber Bridge
17.14 Labour for Driving Piles
17.15 Labour for fitting and fixing RSJ beam,C.I.Saddle etc.
17.16 Labour for fitting and fixing RSJ beam, Old C.I.Saddle etc.
17.17 Labour for making and fixing MS FI straps and cleats.
17.18 Supplying Fitting and fixing "U' shaped flat iron strap
Page-14

17.19 Labour for fitting Woodwork


17.20 Labour for fitting and fixing log Beam
17.21 Labour for taking out old woodwork of Bridge and refitting
17.22 Labour for taking out old logbeam of Bridge and refitting
17.23 Single Bamboo spur and Palasiding with 2nd class Bamboo.
17.24 Single Bamboo spur and Palasiding with 1st class Bamboo.
17.25 Bamboo spur'A" Type
17.26 Bamboo spur'"A"Type with 1st class Bamboo
17.27 Close Bamboo Toe walling
17.28 Double Timber spur with two rows
17.29 Filling up hollows of Timber Spur
17.30 Split Bamboo wooven lining
17.31 Supplying fitting and fixing bamboo pegs in hollows of spur
17.32 R.C.C. Guard post
17.33 Kilometer Post
17.34 Pile Shoes
17.35 Earthwork in filling in Guide Bundh
17.36 Labour for Hauling Boat
17.37 Renewing Rotten planks of Boat
17.38 Making good of cracks in Boat
17.39 Fitting and fixing of Kori.
17.40 Supplying Sal wood Helm
17.41 Supplying Non Sal Helm
17.42 Renewing Oar
17.43 Supplying Koniagosha
17.44 Repairing and providing Free Board
17.45 Refitting Drop Gates upto 6 ton
17.46 Refitting Drop Gates above 6 ton
17.47 Providing Steel Truss of Structural B.U.G.
17.48 Earth work by headload in filling Embankment
17.49 Earthwork in core of Embankment
17.50 Earthwork in subgrade and shoulder
17.51 Labour for laying apron with mansize Boulder
17.52 Stone Masonary work
17.53 Labour for spreading Gravel/Granular Material
17.54 Construction of Temporary Island
17.55 R.C.C.Pipe Delineator
Page-15

17.56 Drum Delineator


17'.57 Paved Shoulder
17.58 Prefabricated Railing
17.59 Crash Barrier
17.60 Construction of Reinforced Earth Retaining wall
17.61 Construction of P.C.C. Strip level Footing
17.62 Providing 600mm drainage bay behind R.E
17.63 Greasing of Bearing
17.64 Providing approved variety of Vetiver
17.65 Closegraded Premix surfacing with cationic Bitumen Emulsion
17.66 Seal coat with Emulsion
17.67 Providing Interlocking Concrete Block Pavement
17.68 Wire rope safety Fence Barrier
17.69 Geo Bags
17.70 Supply and Dumping of Geo Bags in Loose
17.71 Supplying,Laying Non wooven Geo Textile Fabric Sheet
17.72 Supplying and Dumping of Geo Bags in Cages (with Boat)
17.73 Earthwork in Excavation in Key Cage
17.74 Supply and Laying of G-Mat
17.75 Construction Base of Road Pavement by use of Evocrate
17.76 Rope safety Fence Barrier
17.77 Soil Stabilization-Clay Soil in Subgrade using RBI-81
17.78 Excluding Clay Soil in Base course using RBI-81
17.79 With available soil in Base Course using RBI-81
18 NEW TECHNOLOGY
Preamble
18.1 Open - Graded Premix Surfacing (specially for shaded areas)
18.2 Seal coat with Cold mix Binder (specially for shaded areas)With cold mix Binder Ezee PC
(MS)
18.3 Sub-Base/Base with EVOCRETE CCL Soil Modifier (GERMAN) technology
18.4 Bio Enzyme Soil Stabilizer Terrazyme under IRC accredited new Technology
18.5 Soil Stablized subbase/ base using Roadstab
18.6 RBI Grade 81 Treated Base Layer
18.7 Providing, laying, spreading and compacting including in situ mixing of In-Situ 94 % Soil + 4
% PI Reducing Agent with 2 % RBI Grade-81
18.8 Providing, laying, spreading and compacting including in situ mixing of In-Situ 93.5 % Soil + 4
% PI Reducing Agent with 2.5 % RBI Grade-81
18.9 Providing, laying, spreading and compacting including in situ mixing of 98 % In-Situ Soil (PI <
= 10) with 2 % RBI Grade-81
Page-16

18.10 Providing, laying, spreading and compacting including in situ mixing of 97.5 % In-Situ Soil (PI
< = 10) with 2.5 % RBI Grade-81
18.11 Providing, laying, spreading and compacting including in situ mixing of 98 % Selected Soil (PI
< = 10) with 2 % RBI Grade-81
18.12 ZYCOSOIL NANO TECHNOLOGY
18.13 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade) Binder Using
Nanotechnology
18.14 Bitumen (S-90): Seal Coat( with Nanotechnology)
18.15 EVOCRETE TECHNOLOGY
18.16 Cell Filled Concrete Pavement
18.17 TENAX 3D GRID TECHNOLOGY
18.18 Recycling of Bituminous Pavement with Central Recycling Plant
18.19 Protective coatings to the structures, equipments and machine parts with performance
guarantee for 3 years.
Page-17

Page
Page-18
Page-19
Page-20
Page-21
Page-22
Page-23
Page-24
Page-25
Page-26
Page-27
Page-28
Page-29
Page-30
Summary of Rate Analysis

Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-1
CARRIAGE OF MATERIALS
1.1 Loading and unloading by mechanical means (Placing tipper at
loading point, loading with front end loader, dumping, turning for return
trip, excluding time for haulage and return trip)

A Boulders cum 159.00

B Stone aggregates cum 164.00

C Sand/Moorum/flyash cum 154.00


1.2 Loading and Unloading by Manual Means

A Boulders cum 214.00

B Stone aggregates cum 213.00

C Sand/Moorum/flyash cum 184.00


1.3 Loading and Unloading of Cement or Steel by Manual Means and
tonne 575.00
stacking.
1.4 Cost of Haulage Excluding Loading and Unloading

(i) Surfaced Road tonne.km 8.80

cum/km 16.00
(ii) Unsurfaced Gravelled Road tonne.km 11.00

cum/km 20.00
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. tonne.km 17.20

cum/km 31.30

Page 31 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-2

SITE CLEARANCE

2.1 Cutting of Trees, including Cutting of Trunks, Branches and


Removal (Cutting of trees, including cutting of trunks, branches and
201 removal of stumps, roots, stacking of serviceable material with all lifts
and up to a lead of 1000 mtrs and earth filling in the depression/pit.

(i) Girth from 300 mm to 600 mm each 225.00


(ii) Girth from 600 mm to 900 mm each 401.00
(iii) Girth from 900 mm to 1800 mm each 783.00
(iv) Girth above 1800 mm each 1487.00
2.2 Clearing Grass and Removal of Rubbish ( clearing grasss and
201 removal of rubbish upto a distance of 50m outside the periphery of the hectare 15659.00
area.)
2.3 Clearing and Grubbing Road Land .(Clearing and grubbing road land
including uprooting rank vegetation, grass, bushes, shrubs, saplings
and trees girth up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of serviceable
201
materials to beused or auctioned up to lead of 1000metres including
removal and disposal of top organic soil not exceeding 150mm
thickness.

(i) By Manual Means:-

A In area of light jungle hectare 47368.00


B In area of thorny jungle hectare 63418.00
(ii) By Mechanical Means

A In area of light jungle hectare 40291.00


B In area of thorny jungle hectare 48842.00
2.4 Dismantling of Structures (Dismantling of existing structures like
culverts, bridges, retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
202
material,disposal of unserviceable material and stacking the serviceable
material with all lift and lead of 1000 metres)

(i) Lime /Cement Concrete

I By Manual Means

A Lime Concrete, cement concrete grade M-10 and below cum 335.00
B Cement Concrete Grade M-15 & M-20 cum 398.00
C Prestressed / Reinforced cement concrete grade M-20 & above cum 1076.00
II By Mechanical Means for items No. 202( b) & ( c)

A Cement Concrete Grade M-15 & M-20 cum 519.00


B Prestressed / Reinforced cement concrete grade M-20 & above cum 875.00
(ii) Dismantling Brick / Tile work

A In lime mortar cum 210.00


B In cement mortar cum 272.00

Page 32 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

C In mud mortar cum 185.00


D Dry brick pitching or brick soling cum 172.00
(iii) Dismantling Stone Masonry

A Rubble stone masonry in lime mortar cum 235.00


B Rubble stone masonry in cement mortar. cum 272.00
C Rubble Stone Masonry in mud mortar. cum 210.00
D Dry rubble masonry cum 197.00
E Dismantling stone pitching/ dry stone spalls. cum 185.00
F Dismantling boulders laid in wire crates including opening of crates and
stacking dismantled materials. cum 216.00

(iv) Wood work wrought framed and fixed in frames of trusses upto a height
of 5 m above plinth level cum 564.00

(v) Steel work in all types of sections upto a height of 5 m above plinth
level excluding cutting of rivet.
A Including dismembering tonne 1455.00
B Excluding dismembering. tonne 1055.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 11.00
(vi) Scraping of bricks dismantled from brick work including stacking.

A In lime/Cement mortar 1000


1096.00
numbers
B In mud mortar 1000
391.00
numbers
(vii) Scraping of Stone from dismantled stone masonry

A In cement and lime mortar cum 440.00


B In Mud mortar cum 93.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry
sqm 17.00

(ix) Removing all type of hume pipes and stacking within a lead of
1000 metres including earthwork and dismantling of masonry
works.

A Up to 600 mm dia metre 163.00


B Above 600 mm to 900 mm dia metre 220.00
C Above 900 mm metre 377.00
2.5 Dismantling of Flexible Pavements (Dismantling of flexible
pavements and disposal of dismantled materials up to a lead of 1000
202 metres, stacking serviceable and unserviceable materials separately)

I By Manual Means

A Bituminous courses cum 618.00


B Granular courses cum 442.00
II By Mechanical Means

A Bituminous course cum 251.00

Page 33 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

2.6 Dismantling of Cement Concrete Pavement (Dismantling of cement


concrete pavement by mechanical means using pneumatic tools,
breaking to pieces not exceeding 0.02 cum in volume and stock piling at
202 designated locations and disposal of dismantled materials up to a lead cum 1198.00
of 1000metres ,stacking serviceable materials and unserviceable
materials separately.)

2.7 Dismantling Guard Rails (Dismantling guard rails by manual means


and disposal of dismantled material with all lifts and up to a lead of 1000
202 metres, stacking serviceable materials and unserviceable materials metre 67.00
separately.)

2.8 Dismantling Kerb Stone (Dismantling kerb stone by manual means


202 and disposal of dismantled material with all lifts and up to a lead of 1000 metre 13.00
metre)

2.9 Dismantling Kerb Stone channel (Dismantling kerb stone channel by


202 manual means and disposal of dismantled material with all lifts and up metre 19.00
to a lead of 1000 metre)
2.10 Dismantling Kilometre Stone (Dismantling of kilometre stone including
cutting of earth, foundation and disposal of dismantled material with all
202 lifts and lead upto 1000 m and back filling of pit.)

A 5th KM stone each 337.00


B Ordinary KM Stone each 196.00
C Hectometre Stone/200-M stone each 42.00
2.11 Dismantling of Fencing (Dismantling of barbed wire fencing/ wire
mesh fencing including posts, foundation concrete, back filling of pit by
manual means including disposal of dismantled material with all lifts and
202 metre 48.00
up to a lead of 1000 metres, stacking serviceable materials and
unserviceable materials separately.)

2.12 Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line


600 mm dia including disposal with all lifts and lead upto 1000 metres
and stacking of serviceable material and unserviceable material
202 separately under supervision of concerned department.) metre 118.00

2.13 Removal of Cement Concrete Pipe of Sewer Gutter (Removal of


cement concrete pipe of sewer gutter 1500 mm dia under the
supervision of concerned department including disposal with all lifts and
202 up to a lead of 1000 metres and stacking of serviceable and metre 191.00
unserviceable materials separatelyb but excluding earth excavation and
dismantling of masonry works.)

2.14 202 Removal of Telephone / Electric Poles and Lines (Removal of


telephone / Electric poles including excavation and dismantling of
foundation concrete and lines under the supervision of concerned
department, disposal with all lifts and up to a lead of 1000 metres and each 164.00
stacking serviceable materials and unserviceable materials separately.)

Page 34 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-3

EARTH WORK, EROSION CONTROL AND DRAINAGE

3.1 Excavation in Soil by Manual Means. (a)(Excavation for roadway in


soil using manual means including loading in truck for carrying of cut
earth to embankment site with all lifts and lead upto1000 metres.) cum 190.00
301

(b) (Excavation for roadway in soil using manual means using cut earth
to embankment in the immediate vicinity.) cum 117.00

3.2 Excavation in ordinary rock by manual means (a) (Excavation in


ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with in all lifts and cum 255.00
leads upto 1000 metres )
301 (b) (Excavation in ordinary rock using manual means, where there is a
situation where the cross-section is of cut and fill and cut earth is
required to be used in embankment in the immediate vicinity. cum 183.00

3.3 Excavation in Soil with Dozer with lead upto 100 metres (Excavation
for road way in soil by mechanical means including cutting and pushing
the earth to site of embankment upto a distance of 100 metres (average
lead50 metres), including trimming bottom and side slopes in
accordance with requirements of lines,grades and cross sections. cum 132.00

3.4 Excavation in Ordinary Rock with Dozer with lead upto 100 metres
(Excavation for roadway in ordinary rock by deploying a dozer, 80 HP
including cutting and pushing the cut earth to site of embankment upto a
distance of 100 metres ( average lead 50 metres including trimming
301 bottom and side slopes in accordance with requirements of lines,grades cum 223.00
and cross sections.)

3.5 Excavation in Hard Rock (requiring blasting) with disposal upto


1000 metres (Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and side slopes in
301 accordance with requirements of lines, grades and cross cum 251.00
sections,loading and disposal of cut road with in all lifts and leads upto
1000 metres)

3.6 Excavation in Soil using Hydraulic Excavator CK 90 and Tippers


with disposal upto 1000 metres. (Excavation for roadwork in soil with
hydraulic excavator of0.9 cum bucket capacity including cutting and
loading in tippers, trimming bottom and side slopes,in accordance with
301 cum 84.00
requirements of lines, grades and cross sections,loading and disposal of
cut road with in all lifts and leads upto 1000 metres)

3.7 Excavation in Ordinary Rock using Hydraulic ExcavatorCK-90 and


Tippers with disposal upto 1000 metres. (Excavation for roadway in
ordinary rock with hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, transporting to embankment site
301 cum 105.00
within all lift and lead up to 1000metres, trimming of bottom and side
slopes in accordance with requirements of lines, grades and cross
sections.)

Page 35 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

3.8 Excavation in Hard Rock (blasting prohibited) (Excavation for


roadway in hard rock (blasting prohibited) with rock breakers including
breaking rock, loading in tippers and disposal within all lifts and lead
301 upto 1000 metres, trimming of bottom and side slopes in accordance
with requirements of lines, grades and cross sections.)

A Mechanised cum 642.00


B Manual Method cum 967.00
3.9 Excavation in Hard Rock (controlled blasting) with disposal upto
1000 metres (Excavation for roadway in hard rock with controlled
blasting by drilling, blasting and breaking, trimming of bottom and side
slopes in accordance with requirements of lines, grades and cross
301 sections,loading and disposal of cut road with in all lifts and leads upto cum 332.00
1000 metres)

3.10 Excavation in Marshy Soil (Excavation for roadway in marshy soil with
hydraulic excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto 1000
301 metres, trimming of bottom and side slopes in accordance with cum 93.00
requirements of lines, grades and cross sections.)

3.11 Removal of Unserviceable Soil with Disposal upto 1000 metres


(Removal of unserviceable soil including excavation, loading and
301 disposal upto 1000 metres lead but excluding replacement by suitable cum 86.00
soil which shall be paid separately as per clause 305.)

3.12 Pre-splitting of Rock Excavation Slopes (Carrying out excavation in


hard rock to achieve a specified slope of the rock face by controlled use
of explosives and blasting accessories in properly aligned and spaced
drill holes, collection of the excavated rock by a 80 HP Dozer, loading in
303 sqm 159.00
a tipper by a front enf loader and disposing of material with all lift and
lead up to 1000metres all in specified as cl. no. 303.

3.13 Excavation for Structures (Earth work in excavation of foundation of


structures as per drawing and technical specification, including setting
out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom,backfilling the
304 excavated earth to the extent required and utilising theremaining earth
locally for road work.)

(i) Ordinary soil

A Manual Means (Depth upto 3 m)( Without dewatering ) cum 251.00


Manual Means (Depth upto 3 m)( With dewatering ) cum 273.00
B Mechanical Means (Depth upto 3 m))( Without dewatering ) cum 53.00
Mechanical Means (Depth upto 3 m))( With dewatering ) cum 55.00
(ii) Ordinary rock (not requiring blasting)

A Manual Means (Depth upto 3 m)( Without dewatering ) cum 313.00


Manual Means (Depth upto 3 m)( With dewatering ) cum 342.00
B Mechanical Means (Depth upto 3 m))( Without dewatering ) cum 70.00
Mechanical Means (Depth upto 3 m))( With dewatering ) cum 74.00

Page 36 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(iii) Hard rock ( requiring blasting )

A Manual Means ( Without dewatering ) cum 522.00


Manual Means ( With dewatering ) 562.00
(iv) Hard rock ( blasting prohibited )

A Mechanical Means ( Without dewatering ) cum 683.00


Mechanical Means ( With dewatering ) cum 714.00
(v) Marshy soil

A Manual means ( upto 3 m depth)(without dewatering) cum 517.00


Manual means ( upto 3 m depth)(with dewatering) cum 603.00
B Mechanical means ( upto 3 m depth)(without dewatering) cum 247.00
Mechanical means ( upto 3 m depth)(with dewatering) cum 264.00
3.14 Scarifying Existing Granular Surface to a Depth of 50 mm by
Manual Means (Scarifying the existing granular road surface to a depth
305.4.3 of 50 mm and disposal of scarified material within all lifts and leads upto sqm 22.00
1000 metres. )

3.15 Scarifying existing bituminous surface to a depth of 50 mm by


mechanical means (Scarifying the existing bituminous road surface to
305.4.3 a depth of 50 mm and disposal of scarified material with in all lifts and sqm 11.00
lead upto 1000 metres.)
3.16 Embankment Construction with Material Obtained from Borrow
Pits (Construction of embankment with approved material obtained from
borrow pits with all lifts and leads, transporting to site, spreading,
grading to required slope and compacting to meet requirment of table
300-2 ( Including cost of testing of materials at site and laboratory as
directed by the deptt.)
305

(a) from private land cum 238.00


(b) from Govt land cum 238.00
Extra lead beyond initial lead of 3.0 Km. cum/km 7.74
3.17 Construction of Embankment with Material Deposited from
Roadway Cutting (Construction of embankment with approved
305 materials deposited at site from roadway cutting and excavation from cum 103.00
drain and foundation of other structures graded and compacted to meet
requirement of table 300-2 )

3.18 Construction of Subgrade and Earthen Shoulders (Construction of


subgrade and earthen shoulders with approved material obtained from
borrow pits with all lifts & leads, transporting to site, spreading, grading
to required slope and compacted to meet requirement of table (300-2)
(a), ( Including cost of testing of materials at site and laboratory as
directed by the deptt.)

305

(a) from private land cum 290.00


(b) from Govt land cum 290.00
Extra lead beyond initial lead of 3.0 Km. cum/km 8.46
3.19 305.3.4 Compacting Original Ground

Page 37 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case-I Compacting original ground supporting subgrade (Loosening of the


ground upto a level of500 mm below the subgrade level, watered,
graded and compacted in layers to meet requirement of table 300-2 for cum 75.00
subgrade construction.)

Case-II :Compacting original ground supporting embankment cum 38.00


3.20 Stripping and Storing Top Soil (Stripping, storing of top soil by road
side at 15 m internal and re-application on embankment slopes, cut
slopes and other areas in localities where the available embankment
305 material is not conducive to plant growth) cum 195.00

3.21 Stripping, storing and re-laying top soil from borrow areas in
agriculture fields. (Stripping of top soil from borrow areas located in
agriculture fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of agricultural cum 115.00
field,finishing it to the reqd. levels and satisfaction of the farmer.)

3.22 Turfing with Sods (Furnishing and laying of the live sods of perennial
turf forming grass on embankment slope, verges or other locations
shown on the drawing or as directed by the engineer including
307 preparation of ground, fetching of rods and watering) sqm 31.00

3.23 Seeding and Mulching (Preparation of seed bed on previously laid top
soil, furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of0.23 litres per sqm and sqm 127.00
laying and fixing jute netting, including watering)

3.24 Surface Drains in Soil (Construction of unlined surface drains of


average cross sectional area 0.40 sqm in soil to specified lines, grades,
309 levels and dimensions to the requirement of clause 301 and 309.
Excavated material to be used in embankment within a lead of 50m
( Average lead 25m )

A Mechanical means metre 81.00


B Manual Means metre 63.00
3.25 Surface Drains in Ordinary Rock (Construction of unlined surface
drain of average cross sectional area 0.4 sqm in ordinary rock to
309 specified lines, grades, levels and dimensions as per approved design
and to the requirement of clause 301 to 309. Excavated to be used in
embankment at site.)

A Mechanical Means metre 165.00


B Manual Means metre 94.00
3.26 Surface Drains in Hard Rock (Rate per metre may be worked out
309 based on quantity of hard rock as per design.) metre

3.27 Sub Surface Drains with Perforated Pipe (Construction of subsurface


drain with perforated pipe of 100 mm internal diameter of metal/
asbestos cement/ cement concrete/PVC, closely jointed, perforations
ranging from 3 mm to 6 mm depending upon size of material
309 surrounding the pipe,with 150mm bedding below the pipe and 300mm metre 470.00
cushion above the pipe,cross section of excavation 450mmx550mm.
excavated material to be utilised in road way at site.)

3.28 Aggregate Sub- Surface Drains (Construction of aggregate sub


309 surface drain 300 mm x 450 mm with aggregates conforming to table metre 211.00
300-4, excavated material to be utilised in roadway )

Page 38 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

3.29 Underground Drain at Edge of Pavement (Construction of an


underground drain 1 m x 1 m (inside dimensions) lined with RCC-20 cm
309 thick and covered with RCC slab10 cm in thickness on urban roads) metre 4546.00

3.31 Construction of Rock fill Embankment (Construction of rock fill


embankment with broken hard rock fragments of size not exceeding 300
313 mm laid in layers not exceeding 500 mm thick including filling of surface cum 62.00
voids with stone spalls, blinding top layer with vibratory road
roller,complete as per cl. 313.)

3.32 Excavation in Hill Area in Soil by Mechanical Means (Excavation in


soil in hilly area by mechanical means including cutting and trimming of
side slopes

301
(a) Disposing of excavated earth with all lifts and lead upto 1000
metres) cum 181.00

(b) Disposing of excavated earth on the barren valley side.) cum 96.00
3.33 Excavation in Hilly Area in Ordinary Rock by Mechanical Means not
Requiring Blasting. (Excavation in hilly area in ordinary rock not
requiring ballasting by mechanical means including cutting and trimming cum 260.00
301 of slopes
(a) Disposal of cut material with all lift and lead up to
1000m.)
(b) Disposal of cut material on the barren valley side. cum 151.00
3.34 Excavation in Hilly Areas in Hard Rock Requiring Blasting
(Excavation in hilly areas in hard rock requiring blasting, by mechanical
means including trimming of slopes
(a) disposal of cut material with all lifts and lead cum 339.00
301
upto 1000 metres.)

(b) Disposal of cut material on the barren valley side. cum 209.00
3.36 Embankment Construction with Fly ash/Pond ash available from
coal or lignite burning Thermal Plants as waste material.
(Construction of embankment with fly ash conforming to table 1 of IRC:
SP: 58 - 2001 obtained from coal or lignite burning thermal power
stations as waste materials,spread and compacted in layers of 200mm cum 202.00
thickness each at OMC,as specified in IRC:SP:58-2001 and as per
approved plans ( with an initial lead of 5 Km.)

Page 39 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-4

SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS

4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)


401

A Plant Mix Method (Construction of granular sub-base by providing


close graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in uniform layers
with motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density,complete as
per cl. 401( Including cost of testing of materials at site and
laboratory as directed by the deptt.)

(i) for grading- I Material cum 1926.00


(ii) for grading- II Material cum 1849.00
(iii) for grading-III Material cum 1773.00
B By Mix in Place Method (Construction of granular sub-base by
providing close graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with vibratory roller to
achieve the desired density,complete as per cl. 401( Including cost
of testing of materials at site and laboratory as directed by the
deptt.)

(i) for grading- I Material cum 1648.00


(ii) for grading- II Material cum 1570.00
(iii) for grading-III Material cum 1495.00
4.2 Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2)
(Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at
401 OMC,and compacting with vibratory roller to achieve the desired
density,complete as per cl. 401

(i) for grading- I Material cum 1699.00


(ii) for grading- II Material cum 1650.00
(iii) for grading-III Material cum 1593.00
4.3 Lime Stabilisation for Improving Subgrade (Laying and spreading
available soil in the subgrade on a prepared surface, pulverising,
mixing the spread soil in place with rotavator with 3 % slaked lime
having minimum content of 70% of CaO, grading with motor grader
402 and compacting with road roller at OMC to achieve the desired
density to form a layer of improved sub grade

A By Mechanical Means cum 521.00


B By Manual Means cum 525.00

Page 40 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

4.4 Lime Treated Soil for Sub- Base (Providing, laying and spreading
soil on a prepared sub grade, pulverising, mixing the spread soil in
place with rotavator with 3 % slaked lime with minimum content of
70% of CaO, grading with motor grader and compacting with road
402 at OMC to achieve at least 98% of the maximum dry density to cum 644.00
form a layer of sub base .

4.5 Cement Treated Soil Sub Base/ Base (Providing, laying and spreading
soil on a prepared sub grade, pulverising, adding the designed quantity
of cement to the spread soil, mixing in place with rotavator, grading with
the motor grader and compacting with the road roller at OMC to
403 achieve the desired unconfined compressive strength and to form a cum 842.00
layer of sub base / base.)

4.6 Cement Treated Crushed Rock or combination as per clause 403.2


and table 400.4in Sub base/ Base (Providing, laying and spreading
Material on a prepared sub grade, adding the designed quantity of
cement to the spread Material, mixing in place with rotavator grading
with motor grader and compacting with road roller at OMC to achieve
desired unconfined compressive strength and to form a layer of sub
base / base.)

(i) For Sub-Base course cum 2550.00


(ii) For Base course cum 2169.00
4.7 Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows,
25mm deep, 450 to the center line of the road and at one metre interval
in the existing thin bituminous wearing coarse including sweeping and
404.3.1 disposal of excavated material within 1000 metres lead.) sqm 7.00

4.8 Inverted Choke (Construction of inverted choke by providing, laying,


spreading and compacting screening B type/ coarse sand of specified
404.3.2 grade in uniform layer on a prepared surface with motor grader and cum 1465.00
compacting with power roller etc)

4.9 Water Bound Macadam (Providing, laying, spreading and compacting


stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing,
rolling with vibratory roller 8-10 tonnes in stages to proper grade and
404 camber, applying and brooming requisite type of screening/binding
material to fillup the interstices of coarse aggregate,watering and
compacting to the reqd. density ( with an initial lead of 5.0 km. )

A By Manual Means

(I) Grading I

(a) Using Screening Crushable type such as Moorum or Gravel cum 2749.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2717.00
(ii) Grading- II

(a) Using Screening Crushable type such as Moorum or Gravel cum 2770.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2724.00
(c) Using Screening Type-B (11.2mm Agg.) cum 2780.00
(iii) Grading- III

Page 41 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(a) Using Screening Crushable type such as Moorum or Gravel cum 2935.00
(b) Using Screening Type-B (11.2mm Agg.) cum 2945.00
B By Mechanical Means:

(i) Grading- I

(a) Using Screening Crushable type such as Moorum or Gravel cum 2523.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2565.00
(ii) Grading- II

(a) Using Screening Crushable type such as Moorum or Gravel cum 2619.00
(b) Using Screening Type-A (13.2mm Agg.) cum 2574.00
(c) Using Screening Type-B (11.2mm Agg.) cum 2629.00
(iii) Grading- III

(a) Using Screening Crushable type such as Moorum or Gravel cum 2785.00
(b) Using Screening Type-B (11.2mm Agg.) cum 2795.00
4.10 Crushed Cement Concrete Sub-base / Base (Breaking and crushing
of material obtained by breaking damaged cement concrete slabs to
size range not exceeding 75 mm as specified in table 400.7 transporting
the aggregates obtained from breaking of cement concre slabs at a lead
405 of 10km,laying and compacting the same as sub base/base cum 319.00
course,constructed as WBM to cl. 404 except the use of screening or
binding material

4.11 Penetration Coat Over Top Layer of Crushed Cement Concrete


Base (Spraying of bitumen over cleaned dry surface of crushed cement
concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure
405.2 distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm 39.00
sqm by a mechanical gritter and rolling the surface as per 506.3.8

4.12 Wet Mix Macadam (Providing, laying, spreading and compacting


graded stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC in mechanical
mix plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sb-base/base course on well prepared
406 surface and compacting with vibratory roller to achieve the desired cum 2429.00
density (including carriage of mixed materials up to 10.0 Km initial
lead from mixing plant )

4.13 Construction of Median and Island with Soil Taken from Roadway
Cutting (Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
407 excavation for drain and foundation of other structures, spread, graded cum 206.00
and compacted as per cl. 407.0

4.14 Construction of Median and Island with Soil Taken from Borrow
Areas (Construction of median and Island above road level with
407 approved material brought from borrow pits, spread, sloped and cum 264.00
compacted as per clause 407)

4.15 Construction of Shoulders (A. Earthen Shoulders)

Page 42 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

4.16 Footpaths and Separators (Construction of footpath/separator by


providing a 150 mm compacted granular sub base as per clause 401
and 25 mm thick cement concrete grade M15, over laid with precast sqm 1285.00
concrete tiles in cement mortar 1:3 including provision of all drainage
arrangement.

4.17 Crusher Run Macadam Base (Providing crushed stone aggregate,


depositing on a prepared surface by hauling vehicles, spreading and
mixing with a motor grader, watering and compacting with a vibratory
410 roller to clause 410 to form a layer of sub-base/Base)

A By Mix in Place Method

(i) For 53 mm maximum size cum 2271.00


(ii) For 45 mm maximum size cum 2196.00
B By Mixing Plant :

(i) For 53 mm maximum size cum 2550.00


(ii) For 45 mm maximum size cum 1550.00
4.18 Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using
lime - fly ash admixture with granular soil, free from organic matter/
deleterious material or clayey silts and low plasticity clays having PI
between 5 and 20 and liquid limit less than 25 and commercial dry
lime,slaked at site or pre slaked with CaO content not less than 50%,fly
ash to conform to gradation as per cl. 4.3 of IRC:88-1984,lime + fly ash
content ranging between 10 to 30%,the minimum unconfined cum 619.00
compressive strength and CBR value after 28 days curing and 4 days
soaking to be 7.5 kg per sq.cm. and 25% respectively all as specified in
IRC:88-1984.

Page 43 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-5

BASES AND SURFACE COURSES (BITUMINOUS)With cold mix


Binder ( as per IRC:SP:100-2014)

5.1 A Prime coat (Providing and applying primer coat with bitumen emulsion
on prepared surface of granular Base including clearing of road surface
502 and spraying primer at the rate of 0.60 kg/sqm using mechanical
means.)( Including cost of testing of materials at site and laboratory as
directed by the deptt.)

(i) With bitumen emulsion-CSS-1h sqm 30.00


(ii) With bitumen emulsion-CSS-1 ( IS-8887-2004 ) sqm 29.00
5.1 B Prime coat (Providing and applying primer coat with bitumen emulsion
on prepared surface of granular Base including clearing of road surface
and spraying primer at the rate of 1.00 kg/sqm using mechanical
means.)( Including cost of testing of materials at site and laboratory as
directed by the deptt.)

(i) With bitumen emulsion-CSS-1h sqm 48.00


(ii) With bitumen emulsion-CSS-1 ( IS-8887-2004 ) sqm 47.00
5.2 503 Tack coat

Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom.( Including
cost of testing of materials at site and laboratory as directed by the
deptt.)

(I)With Bitumen emulsion CSS-1h

(a) Normal bituminous surface sqm 11.00


(b) dry & hungry bituminous surface sqm 13.00
(c) Granular surfaces treated with primer sqm 13.00
(II)With Bitumen emulsion CSS-1 (IS:8887-2004)

(a) Normal bituminous surface sqm 11.00


(b) dry & hungry bituminous surface sqm 13.00
(c) Granular surfaces treated with primer sqm 13.00
(III)With Bitumen emulsion CRS-1

(a) Normal bituminous surface sqm 9.00


(b) dry & hungry bituminous surface sqm 10.00
(c) Granular surfaces treated with primer sqm 10.00
5.3 Bituminous Macadam (Providing and laying bituminous macadam
with 100-120 TPH hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid over a
504 pr(including carriage of mixed materials up to 10.0 Km initial lead
from mixing plant ) ( Including cost of testing of materials at site
and laboratory as directed by the deptt.)

A (a) Without anti stripping agent

(I)with 60/70 or VG-30 grade paved bitumen

Page 44 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(i) for Grading I ( 40 mm nominal size ) cum 6837.00


(ii) for GradingII(19 mm nominal size) cum 6747.00
5.3 B (ii)with Polymer modified bitumen 70

(i) for Grading I ( 40 mm nominal size ) cum 6894.00


(ii) for GradingII(19 mm nominal size) cum 6804.00
B (b) With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
'(i)with 60/70 or VG-30 grade paved bitumen

(i) for Grading I ( 40 mm nominal size ) cum 7047.00


(ii) for GradingII(19 mm nominal size) cum 6957.00
5.3 B (ii)'with Polymer modified bitumen 70

(i) for Grading I ( 40 mm nominal size ) cum 7104.00


(ii) for GradingII(19 mm nominal size) cum 6841.00
5.5 Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray
grout layer over prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using motor
grader for aggregates. key stone chips spreader may be used with
application of bituminous binder( paving bitumen 60/70 ) after each
layer,and with key agreegates placed on the top of the second layer to
506 serve as a base conforming to the line,grades and cross section
specified,the compacted layer thickness being 75mm ( including
carriage up to initial lead of 5.0 km from quarry) ( Including cost of
testing of materials at site and laboratory as directed by the deptt.)

(a) Without anti stripping agent sqm 419.00


'(b) With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification) sqm 429.00

5.6 Dense Graded Bituminous Macadam (Providing and laying dense


bituminous macadam with 100-120 TPH batch type HMP producing
an average output of 75 tonnes per hour using crushed aggregates
of specified grading, premixed with bituminous binder @ 4.0 to
4.5% by weight of total mix and filler transporting the hot miox to
work site,laying with a hydrostatic paver finisher with sensor
control to the reqd. grade, lavel and alignment,rolling with smooth
wheeled,vibratory and tandem rollers to achieve the desired
507 compaction as per MoSRT&H cl. no. 507. complete in all respect.
(including carriage of mixed materials up to 10.0 Km initial lead
from mixing plant )( Including cost of testing of materials at site
and laboratory as directed by the deptt.)

(a) With hydrated lime/cement as filler ( refer table 500-9 of


MoSRT&H specification)

(A) (I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 40 mm nominal size ) cum 7667.00


(ii) for GradingII(19 mm nominal size) cum 7749.00
(B) (ii)'with Polymer modified bitumen 70

Page 45 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(i) for Grading I ( 40 mm nominal size ) cum 7744.00


(ii) for GradingII(19 mm nominal size) cum 7827.00
(b) With rock dust as filler ( refer table 500-9 of MoSRT&H
specification)

(A) (I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 40 mm nominal size ) cum 7397.00


(ii) for GradingII(19 mm nominal size) cum 7479.00
(B) (ii)'with Polymer modified bitumen 70

(i) for Grading I ( 40 mm nominal size ) cum 7474.00


(ii) for GradingII(19 mm nominal size) cum 7557.00
(a) With hydrated lime / cement as filler ( refer table 500-9 of MoSRT&H
specification) & anti stripping agent as per IS:14982( Refer Appendix-5
of MoSRT&H specification)

(A) (I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 40 mm nominal size ) cum 7682.00


(ii) for GradingII(19 mm nominal size) cum 7764.00
(B) (ii)'with Polymer modified bitumen 70

(i) for Grading I ( 40 mm nominal size ) cum 7759.00


(ii) for GradingII(19 mm nominal size) cum 7841.00
5.7 Semi - Dense Bituminous Concrete (Providing and laying semi
dense bituminous concrete with 100-120 TPH batch type HMP
producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder
@ 4.5 to 5% of mix and filler transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to the
reqd. grade, lavel and alignment,rolling with smooth
508 wheeled,vibratory and tandem rollers to achieve the desired
compaction as per MoSRT&H cl. no.508. complete in all respect.
(including carriage of mixed materials up to 10.0
Km initial lead from mixing plant )( Including cost of testing of
materials at site and laboratory as directed by the deptt.)

A (a) With hydrated lime/cement as filler ( refer table 500-9 of


MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 13 mm nominal size ) cum 7832.00


(ii) for GradingII(10 mm nominal size) cum 8236.00
(ii)with Polymer modified bitumen 70

(i) for Grading I ( 13 mm nominal size ) cum 7914.00


(ii) for GradingII(10 mm nominal size) cum 8328.00
(iii)with CRMB 55

(i) for Grading I ( 13 mm nominal size ) cum 7747.00


(ii) for GradingII(10 mm nominal size) cum 8142.00

Page 46 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(b) With rockdustas filler ( refer table 500-9 of MoSRT&H


specification)
(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 13 mm nominal size ) cum 7562.00


(ii) for GradingII(10 mm nominal size) cum 7966.00
(ii)with Polymer modified bitumen 70

(i) for Grading I ( 13 mm nominal size ) cum 7644.00


(ii) for GradingII(10 mm nominal size) cum 8058.00
(iii)with CRMB 55

(i) for Grading I ( 13 mm nominal size ) cum 7477.00


(ii) for GradingII(10 mm nominal size) cum 7872.00
B (a) With hydrated lime / cement as filler (refer table 500-9 of MoSRT&H
specification) & anti stripping agent as per IS:14982 (Refer Appendix-5
of MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 13 mm nominal size ) cum 8134.00


(ii) for GradingII(10 mm nominal size) cum 8572.00
(II)with Polymer modified bitumen 70

(i) for Grading I ( 13 mm nominal size ) cum 8216.00


(ii) for GradingII(10 mm nominal size) cum 8663.00
(III)with CRMB 55

(i) for Grading I ( 13 mm nominal size ) cum 8049.00


(ii) for GradingII(10 mm nominal size) cum 8477.00
C (a) With rock dust as filler ( refer table 500-9 of MoSRT&H specification)
& anti stripping agent as per IS:14982( Refer Appendix-5 of MoSRT&H
specification)

(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading I ( 13 mm nominal size ) cum 7864.00


(ii) for GradingII(10 mm nominal size) cum 8301.00
(ii)with Polymer modified bitumen 70

(i) for Grading I ( 13 mm nominal size ) cum 7946.00


(ii) for GradingII(10 mm nominal size) cum 8393.00
(iii)with CRMB 55

(i) for Grading I ( 13 mm nominal size ) cum 7812.00


(ii) for GradingII(10 mm nominal size) cum 8207.00
D (i)Using cold mix Binder SS-2 ( as per IRC:SP:100-2014)

(i) for Grading I ( 13 mm nominal size ) cum 8698.00


(ii) for GradingII(10 mm nominal size) cum 8651.00

Page 47 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

5.8 Bituminous Concrete (Providing and laying bituminous concrete


with 100-120 TPH batch type hot mix plant producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 5.4 to 5.6 %
of mix and filler transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the reqd. grade,
lavel and alignment,rolling with smooth wheeled,vibratory and
509 tandem rollers to achieve the desired compaction as per MoSRT&H
cl. no.509. complete in all respect. (including carriage of mixed
materials up to 10.0 Km initial lead from mixing plant )( Including
cost of testing of materials at site and laboratory as directed by the
deptt.)

A (a) With hydrated lime/cement as filler ( refer table 500-9 of


MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading-I ( 19 mm nominal size ) cum 8579.00


(ii) for Grading-II(13 mm nominal size) cum 8465.00
(ii)with Polymer modified bitumen 70

(i) for Grading-I ( 19 mm nominal size ) cum 8778.00


(ii) for Grading-II(13 mm nominal size) cum 8664.00
(a) With rock dust as filler ( refer table 500-9 of MoSRT&H
B specification)

(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading-I ( 19 mm nominal size ) cum 8303.00


(ii) for Grading-II(13 mm nominal size) cum 8190.00
(ii)with Polymer modified bitumen 70

(i) for Grading-I ( 19 mm nominal size ) cum 8502.00


(ii) for Grading-II(13 mm nominal size) cum 8389.00
(a) With hydrated lime / cement as filler ( refer table 500-9 of MoSRT&H
specification) & anti stripping agent as per IS:14982( Refer Appendix-5
C of MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading-I ( 19 mm nominal size ) cum 8917.00


(ii) for Grading-II(13 mm nominal size) cum 8803.00
(ii)with Polymer modified bitumen 70

(i) for Grading-I ( 19 mm nominal size ) cum 9116.00


(ii) for Grading-II(13 mm nominal size) cum 9002.00
(a) With rock dust as filler ( refer table 500-9 of MoSRT&H specification)
D & anti stripping agent as per IS:14982( Refer Appendix-5 of MoSRT&H
specification)
(I)'with 60/70 or VG-30 grade bitumen

(i) for Grading-I ( 19 mm nominal size ) cum 8641.00


(ii) for Grading-II(13 mm nominal size) cum 8528.00

Page 48 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(ii)with Polymer modified bitumen 70

(i) for Grading-I ( 19 mm nominal size ) cum 8840.00


(ii) for Grading-II(13 mm nominal size) cum 8727.00
5.9 Surface Dressing (Providing and laying surface dressing as wearing
course in single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and rolling with
8-10 tonne smooth wheeled steel roller)( including carriage up to initial
510 lead of 5.0 km) ( The penetration grade bitumen shall have kinematic
viscisity lying in the range 1x104 to 7x105 centistokes)( Including cost of
testing of materials at site and laboratory as directed by the deptt.)

(a) Without anti stripping agent

(A) (I)' Paving bitumen 60/70 or VG-30 grade

Case -1 :-19 mm nominal chipping size sqm 86.00


Case - II 13 mm nominal size chipping sqm 69.00
(B) (ii)with bitumen emulsion( CRS-2)

Case -1 :-19 mm nominal chipping size sqm 86.00


Case - II 13 mm nominal size chipping sqm 65.00
(b)With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)

(A) (I)' Paving bitumen 60/70 or VG-30 grade

Case -1 :-19 mm nominal chipping size sqm 89.00


Case - II 13 mm nominal size chipping sqm 68.00
5.10 Open - Graded Premix Surfacing (Providing, laying and rolling of
open - graded premix surfacing of 20 mm thickness composed of
13.2 mm to 5.6 mm aggregates either using penetration grade
bitumen to required line, grade and level to serve as
wearingcoarse on a previously prepared base, including mixing in
511 a suitable plant laying and rolling with a smooth wheeled roller 8-
10 T capacity to yhe reqd. level and grade. (including carriage of
mixed materials up to 10.0 Km initial lead from mixing plant )
( Including cost of testing of materials at site and laboratory as
directed by the deptt.)

A Without anti stripping agent

(i) Mechanical method using Penetration grade Bitumen ( 60/70 or VG-30


grade) and HMP of appropriate capacity not less than 75 tonnes / hour . sqm 137.00

(ii) Mechanical method using CRMB 55 and HMP of appropriate capacity


not less than 75 tonnes / hour . sqm 140.00

(iii) Mechanical method using PMB and HMP of appropriate capacity not
less than 75 tonnes / hour . sqm 140.00

(iv). Open-Graded Premix Surfacing using cold mix Binder( as per


IRC:SP:100:2014cationic Bitumen Emulsion CMS)
sqm 141.00

B With anti stripping agent as per IS:14982( Refer Appendix-5 of


MoSRT&H specification)

Page 49 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(i) Mechanical method using Penetration grade Bitumen (60/70 or VG-


30Garde)and HMP of appropriate capacity not less than 75 tonnes /
sqm 137.00
hour .

(ii) Mechanical method using crumb rubber modified bitumen (CRMB) 55


and HMP of appropriate capacity not less than 75 tonnes / hour .
sqm 136.00

(iii) Mechanical method using polymer modified bitumen (PMB) and HMP
sqm 138.00
of appropriate capacity not less than 75 tonnes / hour .
5.11 Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical
means using HMP of appropriate capacity not less than 75
tonnes/hour. Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of 11.2 mm to
0.09 mm ( Type-A ) or 13.2mm to 0.09mm ( Type-B) aggregate using
penetration grade bitumen ( 60/70 or VG-30 grade) to required line,
grade and level to serve as wearing coarse on a previously
prepared base, including mixing in a suitable plant laying and
512 rolling with a smooth wheeled roller 8-10 T capacity to yhe reqd.
level and grade. (including carriage of mixed materials up to 10.0
Km initial lead from mixing plant )( Including cost of testing of
materials at site and laboratory as directed by the deptt.)

(a)Without anti stripping agent

(ii) ( Type-A ) sqm 161.00


(i) Type-B sqm 152.00
(b)With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
(ii) ( Type-A ) sqm 160.00
(i) Type-B 156.00
5.12 Seal Coat (Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and cross fall
using Type A and B seal coats) ( Including cost of testing of
513 materials at site and laboratory as directed by the deptt.)

(a) Without anti stripping agent

(i) Case - I : Type A (Providing and laying liquid seal coat comprising of a
layer of bituminous binder ( paving bitumen 60/70 or VG-30 grade,
followed by a cover of crushed stone chipping of specified grade.
sqm 65.00

(ii) Case - II : Type B (Providing and laying of premix seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using crushed stone
chipping 6.7 mm size and penetration bitumen of 60/70 or VG-30
grade.) sqm 48.00

Page 50 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

5.13 Supply of Stone Aggregates for Pavement Courses (Supply of stone


aggregates from approved sources confirming to the physical
requirement, specified in the respective specified clauses, including cum
royalties, fees rents, collection, transportation, stacking

(b) With anti stripping agent as per IS:14982( Refer Appendix-5 of


MoSRT&H specification)

(i) Case - I : Type A (Providing and laying liquid seal coat comprising of a
layer of bituminous binder ( paving bitumen 60/70 or VG-30 grade,
followed by a cover of crushed stone chipping of specified grade. sqm 64.00

(ii) Case - II : Type B (Providing and laying of premix seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using crushed stone
chipping 6.7 mm size and penetration bitumen of 60/70 or VG-30
grade.) sqm 48.00

5.14 Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt


wearing course with paving grade bitumen meeting the requirements
given in table 500-29( binder having penetration as (15+/- 5) at 25 deg.
centrigrade), prepared by using mastic cooker and laid to required level
and slope after cleaning the surface, including providing anti skid
surface with bitumen pre coated fine grained hard stone ships of
13.2mm nominal size at the rate of .005cum per 10 sqm. and at an
approximate spacing of 10 cm center tpo center in both direction ,
515 sqm 1366.00
pressed into surface when the temperature of surfaces not less than
1000C, protuding 1mm to 4mm over mastic surface , all complete as per
clause 515.

5.15 Slurry Seal Providing and laying slurry seal consisting of a mixture of
fine aggregates, portland cement filler, bituminous emulsion(CSS-2) and
water on a road surface including cleaning of surface, mixing of slurry
516 seal in a suitable mobile plant, laying and compacting to provide even
riding surface.

(i) 5 mm thickness sqm 73.00


(ii) 3 mm thickness sqm 48.00
(iii) 1.5 mm thickness sqm 30.00
5.16 Recycling of Bituminous Pavement with Central Recycling Plant
(Recycling pavement by cold milling of exiting bituminous layers,
planning the surface after cold milling, reclaiming excavated material to
the extent of 30 % of the required quantity, hauling and stockpilling the
reclamed material near the central recycling plnt after carryingput
necessary checks and evaluation, adding fresh materials includind
517 rejuvenators as required, mixing in a hot mix plant, tranporting and cum 6426.00
laying at site and compacting to the required grade, level and thickness,
all as specified in clause 517

5.17 Fog Spray Providing and applying low viscosity bitumen emulsion
(CSS-1/CSS-1h) for sealing crack less than 3mm wide on incipient
518 frepping for dis integration in existing surfacing.

Page 51 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(I)With Bitumen emulsion CSS-1 (IS:8887-2004)

(I) without blinding sqm 35.00


(ii)'Extra for blinding the fox spray sqm 5.00
(II) With bitumen emulsion-CSS-1h

(I) without blinding sqm 37.00


(ii)'Extra for blinding the fox spray sqm 6.00
5.18 Bituminous Cold Mix ( Including Gravel Emulsion)with cold mix
Binder(Tailor made as per IRC:SP:100-2014. (Providing, laying and
rolling of bituminous cold mix on prepared base consisting of a
mixture of unheated mineral aggregate and emulsified
bitumen( CSS-1/CSS-1h), including mixing in a plant of suitable
type and capacity,transporting,laying,compacting and finishing to
519 specified grades and levels.(including carriage of mixed materials
up to 10.0 Km initial lead from mixing plant )( Including cost of
testing of materials at site and laboratory as directed by the deptt.)

(I)With Bitumen emulsion CSS-1 (IS:8887-2004)

(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size


aggregate cum 10853.00

(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate


cum 10610.00

(II) With bitumen emulsion-CSS-1h

(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size


aggregate cum 8239.00

(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate


cum 7934.00

5.19 Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt
base course composed of sand, mineral filler and bituminous binder
( paving bitumen of 60/70 or VG-30 grade) on a prepared sub-grade or
sub-base to the lines, levels, grades and cross sections as per the
drawings including mixing in a plant of suitable type and
520 capacity,transporting,laying and compacting and finishing.)( Including cum 7257.00
cost of testing of materials at site and laboratory as directed by the
deptt.)

5.21 522 Crack Prevention Courses

(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm


(Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width below 6 mm after cleaning with a
mechanical broom, using modified binder( PMB-70) complying with
clause 521 sprayed @ 9kg per 10 sqm spreading 5.6mm crushed stone
agreegate @ 0.11 cum per 10 sqm. with hydraulic chipps grader
sweeping the surface for uniform spread of agreegates and surface sqm 62.00
finished to conform to cl. no. 902.( Including cost of testing of materials
at site and laboratory as directed by the deptt.)

Page 52 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm


(Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width 6 to 9 mm after cleaning with a
mechanical broom, using modified binder( PMB-70) complying with
clause 521 sprayed @ 11kg per 10 sqm and spreading 11.5mm crushed
stone agreegate @ 0.12 cum per 10 sqm. sweeping the surface for
uniform spread of agreegates and surface finished to conform to cl. no. sqm 71.00
902.( Including cost of testing of materials at site and laboratory as
directed by the deptt.)

(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm and


cracked area above 50 % (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width above 9mm
and cracked area above 50% after cleaning with a mechanical broom,
using modified binder( PMB-70) complying with clause 521 sprayed @
15kg per 10 sqm spreading 11.2mm crushed stone agreegate @ 0.12
cum per 10 sqm. with hydraulic chipps grader sweeping the surface for
sqm 92.00
uniform spread of agreegates and surface finished to conform to cl. no.
902.( Including cost of testing of materials at site and laboratory as
directed by the deptt.)

Page 53 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-6

CEMENT CONCRETE PAVEMENTS

6.1 Dry Lean Cement Concrete Sub- base (Construction of dry lean
cement concrete Sub- base over a prepared sub-grade with coarse and
fine aggregate conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed 15:1,
aggregate gradation after blending to be as per table 600:1 , cement
concrete not to be less than 150kg/cum, optimum moisture content to
be determined during the trial length construction, concrete strength not
601 to be less than 10Mpa at 7 days, mixed in a batching plant, transported cum 3952.00
to the site, laid with a paver with electronic sensor, compacting with 8-10
tonnes vibratory roller, finishing and curing.) (Including carriage of
mixed materials up to 10.0 Km initial lead from mixing plant.)

6.2 A Cement Concrete Pavement (Construction of un-reinforced, dowel


jointed, plain cement concrete pavement over a prepared sub base with
43 grade cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not exceeding
25 mm, mixed in a batching and mixing plant as per approved mixed
design, transported to the site, laid with a fixed form or slip form paver,
spread , compacted and finished in a continuous operation includuing
provision of contraction, expansion, construction and longitudinal joints,
602 joint filler, seperation membrane, sealent primer, sealent joint , cum 8306.00
debonding strips dowel bar, tie rod, admixured as approved, curing
compopund, finishing to lines and grades as per drawing. (Including
carriage of mixed materials up to 10.0 Km initial lead from mixing plant.)

'6.2 B Cement Concrete Pavement (Construction of un-reinforced, dowel


jointed, plain cement concrete pavement over a prepared sub base with
43 grade cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not exceeding
25 mm, mixed with Recron 3S fibre of Reliance Industries Ltd. or its
equivalent @ 0.125 Kg. per bag of cement mixed in a batching and
mixing plant as per approved mixed design, transported to the site, laid
with a fixed form or slip form paver, spread , compacted and finished in
a continuous operation includuing provision of contraction, expansion,
construction and longitudinal joints, joint filler, seperation membrane,
cum 8595.00
sealent primer, sealent joint , debonding strips dowel bar, tie rod,
admixured as approved, curing compopund, finishing to lines and
grades as per drawing. (Including carriage of mixed materials up to 10.0
Km initial lead from mixing plant.) as diected by the Department
complete at all levels.

6.3A Rolled Cement Concrete Base (Construction of rolled cement


concrete base course with coarse and fine aggregate conforming to
IS:383, the size of coarse aggregate not exceeding 25 mm with
minimum, aggregate cement ratio15:1 and minimum cement content of
200 Kgs/cum, aggregate gradation as per table 600-4 after blending,
mixing in a batching plant at optimum moisture content, transporting to
603 site, laying with a paver with electronic sensor, compacting with 8-10 cum 4389.00
tonnes smooth wheeled vibratory roller to achive the designed flexure
strength, finishing and curing.

Page 54 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

6.3B Construction of rolled cement concrete base course with coarse and
fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and
minimum cement content of 200 Kgs/cum, aggregate gradation as per
table 600-4 after blending,mixed with Recron 3S fibre of Reliance
Industries Ltd. or its equivalent @ 0.125 Kg. per bag of cement mixing
in a batching plant at optimum moisture content, transporting to site,
cum 4467.00
laying with a paver with electronic sensor, compacting with 8-10 tonnes
smooth wheeled vibratory roller to achive the designed flexure strength,
finishing and curing as diected by the Department complete at all
levels.

6.4 Construction of Base/Sub-base of pavement with lean concrete -


fly ash. (Construction of Base/sub-base using cement, sand, fly ash
and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and
with water content ratio, slump and compressive strength as defined in
the said table , mix prepared in a batching and mixing plant and
compacted with a vibratory roller 8-10 tonnes capacity within the time cum 3620.00
limit laid down vide clause 7.6.3 of IRC: 74-1979, construction joints
properly formed at the end of the day's work, cured for 14 days, all as
specified in IRC:74-1979 and as per approved plans.

6.5 Cement - Fly ash concrete pavement. (Construction reinforced-


reinforced, dowel jointed, plain cement concrete pavement over a
prepared sub base with 43 grade cement, coarse and fine aggregate cum 8922.00
conforming to IS 383, maximum size of coarse aggregate not exceeding
25 mm, replacing cement by fly ash.....)

Page 55 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-7

GEOSYNTHETICS AND REINFORCED EARTH

7.1 'Sub-Surface Drain with Geotextiles :Construction of sub surface


drain 200 mm dia using geotextiles treated with carbon black with
physical properties as given in clause 702.2.3 formed in to a stable
network and a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil all as per clause 702 and approved metre 1353.00
drawing including excavation and back filling.

7.2 Narrow Filter Sub-Surface Drain :'Construction of a narrow filter sub-


surface drain consisting of porous or perforated pipe laid in narrow
trench surrounded by a geotextile filter fabric, with a minimum of 450 metre 1065.00
mm overlap of fabric and installed as per clause 702.3 and 309.3.5
including excavation and backfilling .

7.3 'Laying Paving Fabric Beneath a Pavement Overlay : Providing and


laying paving fabric with physical requirements as per table 704-2 over
a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate
of 1 kg per sqm over thoroughly cleaned and repaired surface to provide
a water resistant membrane and crack retarding layer. Paving fabric to
be free of wrinkling and folding and to be laid before cooling of tack sqm 442.00
coat, brooming and rolling of surfaces with pneumatic roller to maximise
paving fabrics contact with pavement surfaces.

7.4 Laying Boulder Apron in Crates of Synthetic Geogrids :'Providing,


preparing and laying of geogrid crated apron 1 m x 5 m, 600 mm thick
including excavation and backfilling with baffles at 1 metre interval,
made with geogrids having characteristics as per clause 704.2, joining
sides with connectors/ring staple, top corners to be tie tensioned ,
placing of suitable crioss interval ties in layers of 300 mm connecting
opposite side with lateral braces and tied with polymer braids to avoid
bulging , constructed as per clause 704.3 filled with stone with minimum
size of 200mm and specific gravity not less than 2.65, packed witkh
stone spalls, keyed to the foundation recess in case of sloping ground cum 1247.00
and laid over a layer of Geotextile to prevent migration of fines , all as
per clause 704 and laid as per clause 2503.3 and approved design.

7.5 Reinforced Earth Retaining Wall (Reinforced earth retaining walls


have four main components as under: a) Excavation for foundation,
foundation concrete and cement concrete grooved seating in the
foundation for facing elements (facia material). b) Facia material and
its placement. 'c) Assembling, joining with facing elements and laying
of the reinforcing elements.'d) Earth fill with granular material which
is to be retained by the wall.

I Facing elements of RCC sqm 2280.00


II Assembling, joining and laying of reinforcing elements.

A With reinforcing element of steel / Aluminium strips / polymeric


strips.
Type 1 1.Galvanised carbon steel strips metre 324.00
Type 2 2.Copper Strips metre 1463.00

Page 56 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Type 3 3.Aluminium Strips metre 634.00

Type 4 4.Stainless steel strips


metre 865.00

Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric


strips metre 865.00

B With reinforcing elements of synthetic geogrids sqm 503.00


7.6 'Sub-Grade Stabilization:

(A) Providing and laying one layer of Non-Woven geotextile of


minimum mass per unit area of 280gms/sqm.having minimum roll width
of 5.0m treated with carbon black with physical properties as given in
clause no 702.2.3. over 25mm thick compacted sand layer on a
prepared subgrade as a filter media with necessary overlaps as per sqm 161.00
drawing and technical specification and as directed by the Engineer in
charge complete.

(B) Providing and laying one layer of Biaxial P.V.C.Knitted coated


polyster Geogrid of unit roll width of 5.0m having minimum tensile
strength of 40KN/m in both direction at a maximum elongation of 15% in
th direction of the length of the roll and satisfying all requirements of IS
Code/BIS code of practice and tests prescribed in ASTM or British
standards or ISO on prepared subgrade as a seperator cum sqm 236.00
reinforceing agent with necessary overlaps as per drawing and technical
specification and as directed by the Executive Engineer in charge
complete.

7.7 Wooven Jute Geo Textile for Road Construction and slope
management purpose
(a) Supplying,testing and installation of 100cm wide woven jute
geotextiles(JGT) 724 gm/sq.m posseing tensile strength of
25kn/m(+10%,-5% tolerance) with a porometry around 150 to 400
microns and thickness 2 mm for application on road sub grades and
embankments.. Jute fabric to be laid with overlaps of 100mm crosswise
and 300 mm longitudinally duly secured to subgrade by U shaped m.s
staples(11 gauge)/round head country nail of 150mm length at an sqm 104.00
interval of 750mm as per direction of the engineer-in-charge.

(b) Supplying,testing and installation of 100cm wide woven jute


geotextiles(JGT) 627gm/sqm posseing tensile strength of
25kn/m(+10%,-5% tolerance) with a porometry around 150 to 400
microns and thickness 2 mm for application on road sub grades and
embankments.. Jute fabric to be laid with overlaps of 100mm crosswise
and 300 mm longitudinally duly secured to subgrade by U shaped m.s sqm 122.00
staples(11 gauge)/round head country nail of 150mm length at an
interval of 750mm as per direction of the engineer-in-charge.

(c) Supplying,testing and installation of 100cm wide woven jute


geotextiles(JGT) 500gm/sqm posseing tensile strength of
25kn/m(+10%,-5% tolerance) with a porometry around 150 to 400
microns and thickness 2 mm for application on road sub grades and
embankments.. Jute fabric to be laid with overlaps of 100mm crosswise
and 300 mm longitudinally duly secured to subgrade by U shaped m.s sqm 48.00
staples(11 gauge)/round head country nail of 150mm length at an
interval of 750mm as per direction of the engineer-in-charge.

Page 57 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-8

TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES

8.1 Cast in Situ Cement Concrete M20 kerb (Construction of cement


concrete kerb with top and bottom width 115 and 165 mm respectively,
250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm
thick, foundation having 50 mm projection beyond kerb stone, kerb
408 stone laid with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408.

A Using Concrete Mixer metre 345.00


B Using Concrete Batching and Mixing Plant metre 350.00
8.2 Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction
of cement concrete kerb with channel with top and bottom width 115
and 165 mm respectively, 250 mm high in M 20 grade PCC on M10
grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm
408 thick in PCC M20 grade , sloped towards the kerb, kerb stone with
channel laid with kerb laying machine,foundation concrete manually all
complete as per clause 408.)

A Using Concrete Mixer metre 651.00


B Using Concrete Batching and Mixing Plant metre 660.00
8.3 Printing new letter and figures of any shade (Printing new letter and
figures of any shade with synthetic enamel paint black or any other
801 approved colour to give an even shade)

(i) Hindi ( Matras commas and the like not to be measured and paid for cm height
1.00
Half letter shall be counted as half ) per letter
(ii) English and Roman
cm height
0.67
per letter

8.4 Retro reflectorised Traffic sign:


Providing and erecting of Retro-Reflectrorised cautionary, mandatory &
informatory sign as per IRC: 67 made of high intensity encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick fixed on an angle iron of 25x25x4mm supported on
a mild steel angle iron post 75mm x 75mm x 6mm firmly fixed to the
ground by means of properly design foundation with M-15 grade
Cement concrete 45cm x 45cm x 60cm, 60cm below ground level as
per approved drawing and sign. ( All the Steel work must be Tata/Sail/or
any other approved brand)

(i) 90cm equilateral traingle each 6106.00

(ii) 60cm equilateral traingle each 4052.00

(iii) 60cm circular each 5397.00

(iv) 80cmm x 60 cm rectangular each 7483.00

(v) 60cmm x 45 cm rectangular each 5259.00

(vi) 60cmm x 60 cm square each 6212.00

Page 58 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(vii) 90cm high octagon each 9515.00


8.5 Direction and place identification sign upto 0.9sqm size board.

Providing and erecting direction and place identification retro-


Reflectrorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide clause 801.3 fixed over aluminium sheeting,
2mm thick with area not exceeding 0.9sqm fixed on an angle iron of
25x25x4mm supported on a mild steel angle iron post 75mm x 75mm x
801 6mm firmly fixed to the ground by means of properly design foundation sqm 13243.00
with M-15 grade Cement concrete 45cm x 45cm x 60cm, 60cm below
ground level as per approved drawing and sign. ( All the Steel work
must be Tata/Sail/or any other approved brand)

8.6 'Direction and place identification sign more than 0.9sqm size
board.

Providing and erecting direction and place identification retro-


Reflectrorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide clause 801.3 fixed over aluminium sheeting,
2mm thick with area exceeding 0.9sqm fixed on an angle iron of
801 sqm 13740.00
25x25x4mm supported on a mild steel angle iron post 75mm x 75mm x
6mm, 2 nos. firmly fixed to the ground by means of properly design
foundation with M-15 grade Cement concrete 45cm x 45cm x 60cm,
60cm below ground level as per approved drawing and sign. . ( All the
Steel work must be Tata/Sail/or any other approved brand)

8.7 'Over head sign:


A Providing and erecting overhead signs of anti-corrosive steel tubular
framed structure (all the steel work must be TATA/ SAIL/ any other
approved brand) for retro reflective signage boards made of high
intensity grade encapsulated lens type retro Reflective sheeting
conforming to ASTMD4956 type B III specifications and having
approved pattern over its entire surface bonded on to 2.00 mm thick
aluminium sheet with back supporting angle iron frame of 35x35x4mm
angle iron duly riveted with solid MS & aluminum rivets. The entire face
of the sign shall be covered & bounded with yellow/ white/ red/ blue high
intensity encapsulated lens reflective sheeting with distinctive hoed
pattern on front side (no plain surface) with heat lamp vacuum
applicator machine only. The yellow/ white/ red/ blue portion of the
board shall be screen printed on the high intensity shed base including tonne 86623.00
fixing the board on portal/ support/ wall/ dowel rod etc., with contractors
clamps/ cleats/ bolts/ rivets/ wells including all contractors materials,
labour, tools, lead & lifts etc. complete and all other incidental charges
necessary for successful completion of work as per specifications and
as directed. (Retro Reflective sheeting conforming to ASTMD4956 type
B III specifications and Foundation Works shall be measured and paid
separately)

B. Providing retro reflective sign board of high intensity grade reflective


sheeting conforming to ASTMD4956 B-III specifications having
approved pattern over its entire surface bonded on to 2 mm thick
aluminium sheeting, the entire face of the sign shall be covered &
sqm 666.00
bounded with yellow/ white/ red/ blue high intensity grade with
distinctive nod pattern on front side with heat lamp vacuum applicator
machine only.

Page 59 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

C. Foundation work comprises earth work in foundation trenches, Plain/


Reinforced cement concrete open foundation. ###

i) Plain /Reinforced cement in open foundation complete as per drawing &


technicla specifications as MoSRT&H, 1500, 1700, 2100 PCC grade cum 6128.00
M20

ii) Plain /Reinforced cement in open foundation complete as per drawing &
technicla specifications as MoSRT&H, 1500, 1700, 2100 RCC grade cum 6128.00
M20 using concrete mixure

iii) Earth work in excavation in foundation of structures as per drawing &


techniclal specifications including setting out, construction of soring and
bracing, removal of stumps and other deletarious matter, dressing of
sides and bottom and backfilling with approved material as MoSRT&H cum 120.00
304 inordinary soil by manual means (without dewatring: upto 3M depth)

8.8 Painting Two Coats on New Concrete Surfaces'


803 Painting two sqm 88.00
coats after filling the surface with synthetic enamel paint in all shades on
new plastered concrete surfaces
8.9 Painting on Steel Surfaces (Providing and applying two coats of ready
mix paint of approved brand on steel surface after through cleaning of
803 sqm 77.00
surface to give an even shade)

8.10 Painting on Wood Surfaces (Providing and applying two coats of


ready mix paint of approved brand on wood surface after through
803 sqm 86.00
cleaning of surface to give an even shade)

8.11 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New
Work (Painting lines, dashes, arrows etc on roads in two coats on new
work with ready mixed road marking paint conforming to IS:164 on
803 bituminous surface, including cleaning the surface of all dirts, dusts and
other foreign matter, demarcation at site and traffic control.)

(i) Over 10 cm in width sqm 95.00


(ii) Up to 10 cm in width sqm 78.00
8.12 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old
Work (Painting lines, dashes, arrows etc on roads in two coats on old
work with ready mixed road marking paint confirming to IS: 164 on
803 bituminous surface, including cleaning the surface of all dirts, dusts and
other foreign matter, demarcation at site and traffic control.)

(i) Over 10 cm in width sqm 65.00


(ii) Up to 10 cm in width sqm 72.00
8.13 803 Providing and laying of hot applied thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5
mm is exclusive of surface applied glass beads as per IRC:35 .The finished sqm 876.00
surface to be level, uniform and free from streaks and holes and conforming to
the MoSrt&H specifications
8.14 Kilo Metre Stone (Reinforced cement concrete M15grade kilometre
stone of standard design as per IRC:8-1980, fixing in position including
804
painting and printing etc)

(i) 5th kilometre stone (precast) each 4171.00

Page 60 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(ii) Ordinary Kilometer stone (Precast) each 2592.00


(iii) Hectometer stone (Precast) each 688.00
(iv) 200th meter stone (Precast) as per IRC:26-1967. each 688.00
8.16 Boundary pillar (Reinforced cement concrete M15 grade boundary
pillars of standard design as per IRC:25-1967, fixed in position including
806 finishing and lettering but excluding painting) each 707.00

8.17 G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2
metres high GI barbed wire fencing with 1.8 m angle iron posts 40 mm x
40 mm x 6 mm placed every 3 metres center to center founded in M15
grade cement concrete, 0.6 metre below ground level, every 15th piost,
last but one end post and corner post shall be strutted on both sides
807 and end post on one side only and provided with 9 horizontal lines and metre 330.00
2 digonals interwoven with horizontal wiers, fixed with GI staples, turn
buckles etc complete as per clause 807.

8.18 G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8
metres high GI barbed wire fencing with 2.4 m angle iron posts 50 mm x
50 mm x 6 mm placed every 3 metres center to center founded in M15
grade cement concrete, 0.6 metre below ground level,every 15th piost,
last but one end post and corner post shall be strutted on both sides
807 and end post on one side only and provided with 12 horizontal lines and metre 547.00
2 digonals interwoven with horizontal wiers, fixed with GI staples, turn
buckles etc complete as per clause 807.

8.19 Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive)


(Providing 1.20 metre high fencing with angle iron posts 50 mm x 50
mm x 6 mm at 3 metre center to center with 0.40 metre embedded in
M15 grade cement concrete, corner, end and every 10th post to be
strutted , provided with welded steel wire fabrics of 75mmX50mm mesh
metre 660.00
or 75mmx25mm mesh and fixed to iron posts by flat iron 50mmX5mm
and bolts etc. complete in all respects.)

8.20 Tubular Steel Railing on Medium Weight steel channel ( ISMC


series) 100 mm x 50 mm (Providing, fixing and erecting 50 mm dia
steel pipe railing in 3 rows duly painted on medium weight steel
808 channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above metre 2731.00
ground, 2m center to center, complete as per approved drawings.

8.21 Tubular Steel Railing on Precast RCC posts, 1.2 m high above
ground level (Providing, fencing and erecting 50 mm dia painted steel
pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed
808 metre 1360.00
2meters center to center, complete as per approved drawing.

Page 61 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

8.22 Reinforced Cement Concrete Crash Barrier (Provision of an


Reinforced cement concrete crash barrier at the edges of the road,
approaches to bridge structures and medians, constructed with M-20
grade concrete with HYSD reinforcement conforming to IRC:21 and
dowel bar 25mm dia, 450mm long at expansion joints filled with pre
moulded asphalt filler board, keyed to the structure on which it is built
809 and installed as per design given in the enclouser to MOST circular No.
RW/NH - 33022/1/94-DO III dated June 1994 as per dimension in the
approved drawing and at locations directed by the engineer, all as
specified.

(i) M 20 grade concrete metre 4781.00


8.23 810 Metal Beam Crash Barrier

A Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a


"W" metal beam crash barrier comprising of 3 mm thick corrugated
sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2m center to
center, 1.8 m high, 1.1m below ground/road level, all steel parts and
fitments to be galvanized by hot dip process, all fitting to conform to metre 3691.00
IS:1367 and IS:1364, metal beam rail to be fixedon the vertical post with
a spacer of channel section 150mmX75mmX5mm, 330mm long
complete as per clause 810.)

B Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and


erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 85 cm above road/ground level, fixed
on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2m
center to center, 12 m high, 1.15m below ground level, all steel parts
and fitments to be galvanized by hot dip process, all fitting to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post metre 5286.00
with a spacer of channel section 150mmX75mmX5mm, 546mm long
complete as per clause 810.)

8.24 Road Traffic Signals electrically operated (Since it is a ready made


item commercially produced and erected by specialised firm in the
electrical and electronic field, rate may be taken based on market
enquiry from firms specialised in this field and ISI certified for the
approved design and drawing.

8.25 Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and
erecting a wire rope safety barrier with vertical posts of medium weight
RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85
m above ground and 0.65 m below ground level, split at the bottom for
better grip , embeded in M-15 grade cement concrete
450mmX450mmX450mm, 1.50m center to center with 4 horizantal steel
wier rope 40mm dia and anchored at terminal posts 15m apart. Terminal
posts to be embeded in M15 grade cement concrete foundation
2400X450X900mm(Depth), strengthed by a strut of Rs joists metre 2847.00
100X75mm. 2m long at 450 inclination and a tie 100 X 8mm, 1.50m
long at the bottom, all embeded in foundation concrete as per approved
design and drawing rate excluding excavation and cement concrete.)

8.26 Anti - Glare Devices in Median

Page 62 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

B Anti - Glare Screen with 25 mm steel pipe framework fixed with


circular and rectangular vans (Providing and erecting an anti - glare
screen with 25 mm dia vertical pipes fabricated and framed in the form
of panels of one metre length and 1.75 mtr height fixed with circular
vane 250mm dia at top and rectangular vane 600mmX300mm at the
middle, made out of steel sheet of 3 mm thickness, end vertical pipes of
the panel made larger for embedding in foundation concrete, applying 2 metre 2324.00
coats of paints on all exopsed surfaces, all as per approved design and
drawings.

C Anti - Glare Screen with Rectangular Vane of MS sheet (Providing


and erecting anti - glare screen with rectangular vanes of size 750 x 500
mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x
6 mm at an angle of 450 to the direction of flow traffic, 1.5m center to
center, top edge of the screen 1.75m above th ground level, vertical
posts firmly embeded in cement concrete foundation 0.60 m below metre 1083.00
ground level, applying two coats of paints on the exposed faces, all
complete as per approved drawing and designs.)

8.27 Street Lighting (Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street lighting, 9 m
high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the
median and on one side if fixed on the footh path , fixed with sodium
vapour lamp and fixed on the concrete foundation.

(i) For Fixing in Median each 34769.00


(ii) For fixing in Footpath each 24650.00
8.28 Lighting on Bridges (Providing and fixing lighting on bridges, mounted
on steel hollow circular poles of standard specifications, 5 m high fixed
on parapets with cement concrete, 20 m apart and fitted with sodium each 19260.00
vapour lamp)

8.29 Cable Duct Across the Road (Providing and laying of a reinforced
cement concrete pipe duct, 300 mm dia, across the road (new
construction), extending from drain to drain in cuts and toe of slope to
toe of slope in fills, constructing head walls at both ends, providing a
minimum fill of granular material over top and sides of RCC pipe as per
IRC:98-1997, bedded on a 0.3 mm thick layer of gtranular material free
of rock pieces, outer to outer distance of pipe at least half dia of pipe
subject to minimum 450mm in case of double and triple row ducts, joint
to be made leak proof , invert level of duct to be above higher than
ground level to prevent entry of water and dirt, all as per IRC: 98-1997
and approved drawings.

(i) Single Row for one utility service metre 4171.00


(ii) Double Row for two utility services metre 8096.00
(iii) Triple Row for three utility services metre 12040.00
8.34 Traffic Impact Attenuators at Abutments and Piers

Page 63 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

A With Scrap Tyres (Provision and installation of traffic attenuators at


abutment/pier of flyovers bridges using scrap tyres of size 100 x 20
retrieved from trucks laid in 2 rows and 4 tiers, one above the other and
tied with 20 mm wire rope as per approved design and drawing. sqm 1655.00

B Using Plastic/Steel Barrel, Filled with Sand (Provision and installation


of traffic impact attenuator at abutment/pier of flyovers bridges using
plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in
three rows and tied with 20 mm steel wire rope as per approved design sqm 895.00
and drawings.)

8.43 Portable Barricade in Construction Zone (Installation of a steel


portable barricade with horizontal rail 300 mm wide, 2.5 m in length
fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m
in height, horizontal rail painted (2 coats) with yellow and white stripes ,
150mmin width at an angle of 450, 'A' frame painted with 2 coats of each 3617.00
yellow paint, complete as per IRC:SP:55-2001.

8.44 Permanent Type Barricade in Construction Zone

A With Steel Components (Construction of a permanent type barricade


made of steel components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron
vertical support, painted with yellow and white strips 150mm in width at each 5735.00
an angle of 450, complete as per IRC:SP:55-2001.

B With Wooden Components (Construction of a permanent type


barricade made of wooden components, 1.5 m high from road level,
fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white striups, each 8277.00
150mm in width at an angle of 450, complete as per IRC:SP:55-2001.

C With Bricks (Construction of a permanent type barricade made with


brick work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and white strips) each 20765.00

8.45 Drum Delineator in Construction Zone (Provision of metal


drum/empty bitumen drum delineator, 300 mm in diameter, 800 mm
high, filled with earth for stability, painted in circumferential strips of
alternate black and white 100 mm wide fitted with reflector 3 Nos of 7.5 each 457.00
cm dia, all as per IRC:SP:55-2001.

8.46 Flagman (Positioning of a smart flagman with a yellow vest and a


yellow cap and a red flag 600 x 600 mm securely fastened to a staff 1 m
each 399.00
in length for guiding the traffic)

Page 64 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

8.47 Providing ‘Sparkle Solar Road Studs, manufactured by Tata B.P. Solar
India Ltd. Of size (125mm x 125mm), 90mm height (from bottom of
shank to the top of stud) with detachable battery, m6LEDs-three on
each side for Bi-directional studs/ 3 LEDs on one side for unidirectional
studs, ultra bright LED in amber and red colour, weight per stud 700+25
gms, flash rate of 50-65 times per minute completely water resistant and
weather proof with replacement warranty and free maintenance fro one
year from the date of installation of stud on road-(installation should be
made using adhesives and procedures recommended by manufacturer
under the supervision of their competent technician).

a) Bi-directional Stud- each 3199.00


b) Uni-directional Stud- each 3100.00
8.48 Providing spring post of 750mm height, 80mm dia with round base of
200mm dia made of poly urethane with 3 white reflective bands made of
HIG retro-reflectorised sheeting and fixing to the ground as per each 1300.00
specifications of manufacturers

8.49 Tree reflector made of heigh intensity grade retro-reflectorised sheeting


fixed over aluminium sheeting of 2mm/0.28mm thick firmly fixed with
necessary galvanized nail.

a)100mm dia/100mmx100mm. each 78.00


b)150mm dia/150mmx150mm. each 110.00

8.50 Providing Linear Delineator System with Diamond grade reflective


sheeting of size 80cmx10cm, fixing over thin gauge crimped aluminium
sheeting with single colour panels of Yellow/Red/White and fixing to the each 420.00
object as per specification of the manufacturer.

8.51 Providing reflective pavement marker with Micro prismatic lens in both
direction having thermoplastic body adhering to the specification and
guidelines of MoSRT&H’s fixed to the road surface using the adhesives
and the procedures recommended by the manufacturers with three each 249.00
months replacement warranty and free maintenance.

8.52 Traffic cones: With rubber base and reflective of 7 inch sleeve, height=
each 660.00
750mm, bottom square: 385mm and weight 4.00 kg
8.53 Inter linking chain link for traffic cones. Rm 39.00
8.54 Providing metal tubular delineator (50mm dia and 1.25mm thick) with
15cm reflector made of heigh intensity grade retro reflectorised sheeting
around the pipe at top covered with wire mesh of 20cm length with two
nos of similar reflective bands and bottom fastener M.S. angle including
firmly fixing the delineator to the ground by means of CC(M-15)
foundation of size-(25cmx25cmx25cm), 25cm below ground to the true
line and level as directed by the deptt. With six months replacement
warranty and free maintenance.

a a) 1000mm height. each 480.00


b b) 750mm height. each 400.00
8.55 Providing and erecting of city stud of dimension 220x100x40 mm
plastic body with

a a) One- way reflective- with 1x179 glass element Each 1150.00


b b) Two- way reflective- with 2x179 glass element Each 1345.00

Page 65 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

8.56 Providing and erecting city stud with shank of dimension 220x100x40
mm

a a) One- way reflective- with 1x179 glass element and 2 anchoring Each 1092.00
shanks
b b) Two- way reflective- with 2x179 glass element and 2 anchoring Each 1850.00
shanks

8.57 Providing and erecting FT Marker with dimensions

a a) One- way reflective- with dimensions: Dia 100mm x 19 mm, shank Each 437.00
length 50 mm, dia of shank 24 mm plastic body with 1 x 5 glass
elements and plastic shank
b b) Two- way reflective- with dimensions 100mm x 19 mm, shank Each 587.00
length 50 mm, dia of shank 24 mm plastic body with 2 x 5 glass
elements and plastic shank.
8.58 Providing and erecting Ministar Road studs

a a) One- way reflective(with butyl adhesive) with dimensions :68 x Each 234.00
34x9.8mm Plastic body with 1x8 glass elements.
b b) Two- way reflective(with butyl adhesive) with dimensions : 68 x Each 320.00
34x9.8mm Plastic body with 2x8 glass elements.
8.59 Providing and fixing Reflector for Guard rails for large profile metal
bracket with dimensions:

a a) One- way reflective with 1x213 glass elements. Each 480.00

b b) Two- way reflective with 2x213 glass elements. Each 575.00

8.60 Providing and fixing Reflector for Guard rails for all profile metal bracket
with dimensions:
a a) One- way reflective with 1x166 glass elements. Each 480.00

b b) Two- way reflective with 2x166 glass elements. Each 550.00

8.61 Providing and fixing Reflector for Guard rails for B profile with
dimensions
a a) One- way reflective with 1x166 glass elements.. Each 480.00
b b) Two- way reflective with 2x166 glass elements. Each 550.00
8.62 Providing and fixing Acoustic Wildlife Warning Module(WWA) on Each 1550.00
alternate roadside posts,facing away from the road, with screws and
installation can be made on existing wooden, plastic or metal road side
posts above the optical wildlife warning reflector.Dimension : Height 125
mm, width 81 mm

8.63 Providing and fixing Optical Wildlife Warning Reflector(WWR) with Each 1800.00
colour white or red Dimensions: height 184 mm, width 81mm

8.64 Providing and fixing metal road studs for permanent marking comply Each 480.00
with standard EN1463 and BS 873(Part:IV) according to the CIL
requirements to ASTM D 4280 standard.

8.65 Providing and fixing Globemarker with dimensions120x60x16.5


a a) One- way reflective with 1x39 glass elements. Each 412.00

b (b) Two- way reflective with 2x39 glass elements. Each 560.00

8.66 Providing and fixing metal road stud with dimensions 100x100x19.8 mm
Length anchoring shank:50 mm Aluminum body with

a a) One- way reflective with 1x43 glass elements Each 460.00

Page 66 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b b) Two- way reflective with 2x43 glass elements Each 560.00


8.67 Providing and fixing metal road stud with dimensions 100x50x20mm
Length anchoring shank:60.4 mm Aluminum body with

a a) One- way reflective with 1x43 glass elements. Each 371.00

b b) Two- way reflective with 2x43 glass elements.. Each 504.00

8.68 Providing and fixing metal road stud with dimensions 149x149x27mm
Length anchoring shank:80 mm Aluminum body with.

a a) One- way reflective with 1x28 glass elements Each 490.00

b b) Two- way reflective with 2x28 glass elements Each 555.00

8.69 Providing and fixing Special road stud with dimensions 220x100x40 mm
two anchoring shank plastic body with

a a) One- way reflective with 1x179 glass elements Each 630.00

b b) Two- way reflective with 2x179 glass elements. Each 820.00

8.70 Providing and fixing lane divider with dimensions 220x150x285 mm Each 975.00
base plate 25 mm high Two- way reflective with 1 or 2x128 glass
elements rubber flag with 2 round glass reflectors

8.71 Providing and fixing lane divider with dimensions 220x150x285 mm Each 975.00
base plate 25 mm high Two- way reflective with 1 or 2x128 glass
elements rubber flag with 2 round glass reflectors

8.72 Providing and fixing reflective inserts for road studs with dimensions Each 445.00
112.7x18.25 mm with 76 pieces of glass elements

8.73 Providing and fixing vertical marking with dia.104 mm 256 glass Each 435.00
elements, distance between the two holes are 56 mm.

8.74 Providing and fixing vertical marking with dia.60 mm 80 glass Each 243.00
elements, with central hole.
8.75 Providing and erecting Median Markers which shall be made of tough, each 720.00
high impact resistant, injection-moulded, thermoplastic body with an
isosceles trapezoid structure of length, width and height not less than
15cm, 10cm and 10cm respectively and thickness shall not be less than
1.8 mm. The palstic used for moulding the Median Marker shall have a
minimum notched izod impact strength value 600 J/m at room
temparature, when tested in accordance with ASTM D256 shall retain
70% of this value when sujected to accelerated weathering for 1000
hours as per ASTM G 155. The logo of the manufacturer shall be
embossed on either side of the body in the injection molding process.
The median marker shall have fluroscent yellow color retro-reflective
sheeting of size not les than 8.5cmX8.5cm and with fully reflective
microprismatic cube corners as its retro-reflective elements and meets
ASTM D 4956 type IX specification. The retro-reflective sheeting shall
be on both sides of the median marker and shall be edge protected with
no exposed edges which will prevent edge lifting, vandalism, sheeting
damage etc. The median marker shall by a combination of epoxy
adhesive and grouting as per manufacturers' recommendation
completed as directed by engineer. The material should be
accompanied with pre-quanlification warranty from the manufacturer.

8.76 Providing and fixing reflectors for concrete barriers with dimensions
(Wallflex Top) 146x88 mm mounting with

a a)One- way reflective with 1x188 glass elements Each 97.00

Page 67 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b b) Two- way reflective with 2x188 glass elements. Each 125.00

8.77 Providing and fixing reflectors for concrete barriers with dimensions
(Wallflex Side) 128x110 mm mounting with
a a) One- way reflective with 1x346 glass elements. Each 92.00

b b) Two- way reflective with 2x346 glass elements Each 108.00

8.78 Providing and fixing signflash A630 solar flashing LED unit width 630 Each 2080.00
mm. integrated control unit and battery.(warning system for pedestrian
crossing)

8.79 Providing and fixing swaroline module100 6 LEDs per side one or two Each 2350.00
way with dimensions 100x105x19 mm.

Page 68 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-9
PIPE CULVERTS

9.1 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with
crushed stone aggregate 40 mm nominal size mechanically mixed,
408 placed in foundation and compacted by vibration including curing for 14 cum 5228.00
days.)
9.2 Labour for laying Reinforced cement concrete pipe
NP4/NP3/prestressed concrete pipe for culverts on first class bedding of
granular material /cc M-15 in single row including fixing collar with
cement mortar 1:2,and cost of granular bedding but excluding
2900 excavation, protection works, backfilling, concrete and masonry work in
head wall and parapet,cost of pipe and cost of CC bedding.

(I) With 1st class bedding of granular material

A 1000 mm dia metre 468.00


B 1200 mm dia metre 591.00
C 1800 mm dia metre 591.00
(I) With 1st class bedding of cc M-15

A 1000 mm dia metre 164.00


B 1200 mm dia metre 209.00
C 1800 mm dia metre 591.00
9.3 Labour for laying Reinforced cement concrete pipe
NP4/NP3/prestressed concrete pipe for culverts on first class bedding of
granular material /cc M-15 in double row including fixing collar with
cement mortar 1:2,and cost of granular bedding but excluding
2900 excavation, protection works, backfilling, concrete and masonry work in
head wall and parapet,cost of pipe and cost of CC bedding.

(I) With 1st class bedding of granular material

A 1000 mm dia metre 1097.00


B 1200 mm dia metre 1720.00
(I) With 1st class bedding of cc M-15

A 1000 mm dia metre 329.00


B 1200 mm dia metre 779.00

Page 69 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-10

MAINTENANCE OF ROADS

10.1 Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum,
gravel or a mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250 mm and
3002 compacting with plate compactor or power rammer to restore the cum 121.00
original alignments, levels and slopes.

10.2 Maintenance of Earthen Shoulder (filling with fresh soil) (Making up


loss of material/ irregularities on shoulder( Average 150mm filling )to the
3003 design level by adding fresh approved soil and compacting it with sqm 55.00
appropriate equipment.)

10.3 Maintenance of Earth Shoulder (stripping excess soil) (Stripping


excess soil from the shoulder ( Average depth of 75mm )surface to
3003 achieve the approved level and compacting with plate compactor) sqm 18.00

10.4 Filling Pot- holes and Patch Repairs with open - graded Premix
surfacing, 20mm. (Removal of all failed material, trimming of
completed excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat of bitumen emulsion on the sides and base of
excavation as per clause 503, back filling the pot holes with hot
3004.2 bituminous material with paving bitumen 60/70 as per clause 511,
compacting , trimming and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2.

(i)'using Bitumen emulsion CSS-1h as Tack coat sqm 148.00


(ii)'using Bitumen emulsion CSS-1 ( IS:8887-2004) as Tack coat sqm 147.00
(iii)'using Bitumen emulsion RS-1 as Tack coat sqm 144.00
10.5 Filling Pot- holes and Patch Repairs with - Bituminous concrete,
40mm. (Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface, painting
of tack coat on the sides and base of excavation as per clause 503,
backfilling the pot holes with hot bituminous material as per clause 504,
3004.2 compacting , trimming and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2. (including carriage of
mixed materials upto 10.0km. initial lead from mixing plant.)

(i) for grading I Material sqm 325.00


(ii) for grading II Material sqm 335.00
10.6 Crack Filling (Filling of crack using slow - curing bitumen emulsion and
3004.3.3 applying crusher dust in case crack are wider than 3mm.) metre 4.00

10.7 Dusting (Applying crusher dust to areas of road where bleeding of


3004.4 excess bitumen has occurred.) sqm 1.69

10.8 A Fog Seal (ref item 5.17)


3004.3.2 sqm 44.00

B 3004.3.4 Crack Prevention courses. (ref item 5.21)

(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 62.00
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm
sqm 71.00

Page 70 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm and


cracked area above 50 % sqm 92.00

C 3004.5 Slurry Seal (ref item 5.15)

(i) 5 mm thickness sqm 71.00


(ii) 3 mm thickness sqm 49.00
(iii) 1.5 mm thickness sqm 30.00
D 3004.6 Surface Dressing for maintance works. (ref item 5.9)

(i) 19 mm nominal chipping size sqm 86.00


(ii) 13 mm nominal size chipping sqm 65.00
10.9 Repair of joint Grooves with Epoxy Mortar Repair of spalled joint
grooves of contraction joints, longitudinal joints and expansion joints in
3005.1 concrete pavements using epoxy mortar or epoxy concrete) metre 888.00

10.10 Repair of old Joints Sealant (Removal of existing sealant and re


3005.2 sealing of contraction, longitudinal or expansion joints in concrete metre 95.00
pavement with fresh sealant material)

10.11 Hill Side Drain Clearance (Removal of earth from the choked hill side
3000 drain and disposing it on the valley side manually) metre 33.00

10.12 Land Slide Clearance in soil (Clearance of land slides in soil and
ordinary rock by a bull-dozer D 80 A-12, 180 HP and disposal of the
3000 same on the valley side) cum 68.00

10.13 Land slide Clearance in Hard Rock Requiring Blasting (Clearing of


3000 land slide in hard rock requiring blasting for 50% of the boulders and cum 114.00
disposal of the same on the valley side.)

10.14 Snow Clearance on Roads with Dozer (Snow clearance from road
surface by a bull- dozer 165 Hp and disposing it on the valley side) cum 5.00

10.15 Snow Clearance on Roads with Snow Blowers (Snow clearance from
road surface by a snow blower and disposing on the valley side.) cum 2.00

Page 71 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-11

HORTICULTURE

11.1 Spreading of Sludge Farm Yard Manure or/and good Earth


(Spreading of sludge farm yard manure or/ and good earth in required
307 thickness (cost of sludge, farm- yard manure or/and good earth to be cum 21.00
paid for separately))

11.2 Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including
watering and maintenance of the lawn for 30 days or more till the grass
307 forms a thick lawn free from weeds and fit for moving including
supplying good earth if needed)

(i) In rows 15 cm apart in either direction sqm 30.00


(ii) In rows 7.5 cm apart in either direction sqm 55.00
11.3 Making Lawns including Ploughing and Dragging with 'Swagha'
Breaking of Clod (Making lawns including ploughing and breaking of
clod, removal of rubbish, dressing and supplying doobs grass roots
307 and planting at 15 cm apart, including supplying and spreading of farm sqm 42.00
yard manure at rate of 0.18cum per 100 sqm

11.4 Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or


307 Turfing of slopes (rough grassing) for a period of one year including sqm 172.00
watering etc)

11.5 Turfing Lawns with Fine Grassing including Ploughing, Dressing


(Turfing lawns with fine grassing including ploughing, dressing including
breaking of clods, removal of rubbish, dressing and supplying doobs
307 grass roots at 10 cm apart, including supplying and spreading of farm sqm 46.00
yard manure at a rate of 0.60 cum per 100 sqm

11.6 Maintenance of Lawns with Fine Grassing for the First Year
307 Maintenance of lawns sqm 182.00
with fine grassing for the first year including watering etc.
11.7 a) Planting Permanent Hedges including Digging of Trenches
(Planting permanent hedges including digging of trenches, 60 cm wide
and 45 cm deep, refilling the excavated earth mixed with farmyard
307 manure, supplied at the rate of 4.65 cum per 100 metres and supplying metre 155.00
and planting hedge plants at 30cm apart

b). 'Maintenance of Hedge for one year metre 159.00


11.8 307 a) Planting Flowering Plants and Shrubs in Central Verge km 33267.00
b). Maintenance of Flowering Plants and Shrubs in Central Verge for
one Year km 184815.00

11.9 Planting of Trees and their Maintenance for one Year (Planting of
trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep
dug in the ground, mixing the soil with decayed farm yard/sludge
307 mannure, planting the saplings, backfilling the trenches, watering , each 831.00
fixing the tree guatrd and maintaining the plants for one year.

Page 72 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

11.10 Renovation Lawns including, Weeding, Forking the Ground, Top


Dressing with Forked Soil (Renovation lawns including, weeding,
forking the ground, top dressing with forked soil, watering and
maintenance the lawns, for 30 days or more, till the grass forms a thick
lawns, free from weeds, and fit for moving and disposal of rubbish as
308 sqm 14.00
directed, including supplying good earth, if needed but excluding the
cost of well decayed farm yard manure.

11.14 Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre
1.25 metres, and height 1.2 metres, above ground and 0.20 metre
below ground bottom two course laid dry, and top tree courses in
cement mortar 1:6 (1cement 6 sand) and the intermediate coursees
being in dry honey comb masonry, as per design complete. (Half brick
each 2565.00
circular tree guard, in 2nd class brick, internal diametre 1.25 metres,
and height 1.2 meter.)

11.15 Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd
class bricks, laid dry lengthwise, including excavation, refilling,
consolidation, with a hand packing and spreading nearly surplus earth metre 53.00
within a lead of 50 metres)

11.16 Making Tree Guard 53 cm dia and 1.3 m high as per design from
empty bitumen drum (Making tree guard 53 cm dia and 1.3 m high as
per design from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including providing and each 359.00
fixing 2 nos MS sheet rings 50mmX0.5mm with rivets, complete in all
respects.

11.17 Making Tree Guard 53 cm dia and 2 metres high as per design from
empty bitumen drums (Making tree guard 53 cm dia and 2 metres
high as per design from empty bitumen drums, slit suitably to permit
sun and air, ( supplied by the department at stock issue rate.) including
providing and fixing four legs 40 cm long of 30mmx 3mm MS riveted to
tree guard and providing and fixing 2 nos. MS sheet ring 50mm with each 721.00
rivets complete in alll respects.

11.18 Wrought Iron and Mild Steel Welded Work (Wrought iron and mild
steel welded work) (using angles, square bars, tees and channel
grills, grating frames, gates and tree guards of any size and design etc.
including cost of screens and welding rods or bolt and nuts complete
fixed in position but without the cost of excavation and concrete for quintal 9921.00
mixing which will be paid separately.

11.19 Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60
cm dia and 2 metre high above ground level formed of 4 Nos (25 x 6
mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm)
iron rings in two halves, bolted together with 8 mm dia and 30mm long each tree
bolts including painting two coats with paint pf approved brand over a 2470.00
guard
coat of priming , complete in alll respects.

11.20 Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing
tree guard 0.60 metre square, 2.00 metre high fabricated with MS angle
iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire 3 mm dia each tree
3250.00
welded and fabricated as per design in two halves bolted together. guard

Page 73 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

11.21 Compensatory Afforestation (Planting trees as compensatory


afforestation at the rate of 290 trees per hectare at a spacing of 6 m by
grubbing and leveling the ground upto a depth of 150 mm, digging
holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil , hectare 103617.00
planting of sapling 2m high with 25cm dia stem, backfilling the hole and
watering.

Page 74 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-12
FOUNDATIONS
12.1 Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting
out, construction of shoring and bracing, removal of stumps and other
304 deleterious matter, dressing of sides and bottom and backfilling with
approved material.

I Ordinary soil

A Manual Means

(I) Without dewatering

(i) upto 3 m depth cum 120.00


(ii) 3 m to 6 m depth cum 158.00
(iii) Above 6 m depth cum 205.00
(II) With dewatering

(i) upto 3 m depth cum 132.00


(ii) 3 m to 6 m depth cum 177.00
(iii) Above 6 m depth cum 246.00
B Mechanical Means

(I) Without dewatering

(i) Depth upto 3 m cum 72.00


(ii) Depth 3 m to 6 m cum 82.00
(iii) Depth above 6m cum 100.00
(II) With dewatering

(i) Depth upto 3 m cum 76.00


(ii) Depth 3 m to 6 m cum 88.00
(iii) Depth above 6m cum 108.00
II Ordinary rock (not requiring blasting)

A Manual Means

(I) Without dewatering

Depth upto 3 m cum 174.00


(ii)With dewatering

Depth upto 3 m 188.00


B Mechanical Means cum
(I) Without dewatering

Depth upto 3 m cum 92.00


(ii) With dewatering

Depth upto 3 m 100.00


III Hard rock ( requiring blasting )

Page 75 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

A Manual Means

(I) Without dewatering cum 428.00


(ii) With dewatering cum 459.00
IV Hard rock ( blasting prohibited )

A Mechanical Means

(I) Without dewatering cum 515.00


(ii) With dewatering cum 558.00
V Marshy soil

(i) upto 3 m depth

A Manual means

(I) Without dewatering cum 455.00


(ii) With dewatering cum 541.00
B Mechanical Means

(I) Without dewatering cum 160.00


(ii) With dewatering cum 187.00
VI Back Filling in Marshy Foundation Pits cum 313.00
12.2 Filling Annular Space Around Footing in Rock (Lean cement
304 concrete 1:3:6 nominal mix. Rate may be taken as per items 12.4.) cum 5644.00

12.3 Sand Filling in Foundation Trenches as per Drawing & Technical


304 Specification cum 1448.00

12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm nominal size
2100 mechanically mixed, placed in foundation and compacted by vibration cum 5644.00
including curing for 14 days.)

12.5 Brick masonry work in cement mortar 1:3 in foundation complete


1300 excluding pointing and plastering, as per drawing and technical cum 6649.00
specifications

12.6 A Cement mortar1:3 (1cement :3 sand) cum 4904.00


B Cement mortar1:2 (1cement :2 sand) cum 5956.00
C Cement mortar1:4 (1cement :4 sand) cum 4201.00
D Cement mortar1:6 (1cement :6 sand) cum 3578.00
12.7 Stone masonry work in cement mortar 1:3 in foundation complete as
1400 drawing and Technical Specification

(a) Square Rubble Coursed rubble masonry( first sort ) cum 4428.00
(b) 1405.3 Random Rubble Masonry cum 4133.00
12.8 1500,17 Plain/Reinforced cement concrete, in open foundation complete
00 & as per drawing and technical specification including steel
2100 shuttering formwork.

(N) Without plasticiser


A PCC Grade M15 cum 6128.00

Page 76 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

B PCC Grade M20 cum 6893.00


C (I)RCC Grade M20

Case I Using concrete mixer cum 7097.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8127.00
D PCC Grade M25

Case I Using concrete Mixer cum 7422.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8453.00
E RCC Grade M25

Case I Using concrete Mixer cum 7632.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8659.00
F PCC Grade M30

Case I Using Concrete Mixer cum 7463.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8486.00
G RCC Grade M30

Case I Using Concrete Mixer cum 7646.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8673.00
H RCC Grade M35

Case I Using Concrete Mixer cum 7760.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8781.00
(P) With plasticiser ( Masterplast PL-1/SPL-2 or equivalent ), air
1500,17 entraining and water reducing plasticiser ( Masterplast PAE or
00 & equivalent) and accelerating plasticiser ( Masterplast ACPL or
2100 equivalent) conforming to IS-9103-1999.

A PCC Grade M15 cum 6898.00


B PCC Grade M20 cum 7854.00
C (I)RCC Grade M20

Case I Using concrete mixer cum 8067.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9097.00
D PCC Grade M25

Case I Using concrete Mixer cum 8546.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9578.00
E RCC Grade M25

Case I Using concrete Mixer cum 8767.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9794.00
F PCC Grade M30

Case I Using Concrete Mixer cum 8601.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9623.00
G RCC Grade M30

Page 77 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case I Using Concrete Mixer cum 8788.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9815.00
H RCC Grade M35

Case I Using Concrete Mixer cum 8939.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9960.00
12.9 Providing and constructing temporary island 16 m diameter for
1200 construction of well foundation for 8m dia. Well.

A Assuming depth of water 1.0 m and height of island to be 1.25m.


each 52351.00

B Assuming depth of water 4.0 m and height of island 4.5 m. each 748788.00
C Providing and constructing one span service road to reach island
location from one pier location to another pier location metre 3573.00

12.10 1200 & Providing and laying cutting edge of mild steel weighing 40 kg per metre
for well foundation complete as per drawing and technical specification. tonne 109285.00
1900
12.11 1200, Plain/Reinforced cement concrete, in well foundation complete as
1500 & per drawing and technical specification including steel shuttering
1700 formwork.
(N) Without plasticiser
A Well curb

(i) RCC M20 Grade

Case I Using concrete mixer cum 8189.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9407.00
(ii) RCC M25 Grade

Case I Using concrete mixer cum 8828.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10046.00
(iii) RCC M30 Grade

Case I Using concrete mixer cum 8866.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10085.00
(iv) RCC M35 Grade

Case I Using concrete mixer cum 9041.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10261.00
B Well steining

(I) PCC M15 Grade cum 6601.00


(ii) PCC M20 Grade cum 7290.00
(iii) RCC M20 Grade

Case I Using concrete mixer cum 7507.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8623.00
(iv) PCC M25 Grade

Case I Using concrete mixer cum 7870.00

Page 78 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9161.00
(v) RCC M25 Grade

Case I Using concrete mixer cum 8092.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9209.00
(vi) PCC M30 Grade

Case I Using concrete mixer cum 7932.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9046.00
(vii) RCC M30 Grade

Case I Using concrete mixer cum 8127.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9245.00
(viii) RCC M35 Grade

Case I Using concrete mixer cum 8288.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9406.00
(ix) RCC M40 Grade (With Batching Plant, Transit Mixer and Concrete
cum 9462.00
Pump)
C Bottom Plug

(i) PCC Grade M20

Case I Using Concrete Mixer cum 7374.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8348.00
(ii) PCC Grade M25

Case I Using Concrete Mixer cum 7641.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8637.00
(iii) PCC Grade M30

Case I Using Concrete Mixer cum 7727.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8700.00
(iv) PCC Grade M35

Case I Using Concrete Mixer cum 7867.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8837.00
D Intermediate plug

(I) Grade M20 PCC

Case I Using Concrete Mixer cum 7045.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8032.00
(ii) Grade M25 PCC

Case I Using Concrete Mixer cum 7323.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8308.00
(iii) Grade M30 PCC

Case I Using Concrete Mixer cum 7380.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8367.00

Page 79 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

E Top plug

(i) Grade M15 PCC

Case I Using Concrete Mixer cum 6001.00


(ii) Grade M20 PCC

Case I Using Concrete Mixer cum 6628.00


(iii) Grade M25 PCC

Case I Using Concrete Mixer cum 7154.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8328.00
(iv) Grade M30 PCC

Case I Using Concrete Mixer cum 7211.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8224.00
F Well cap

(i) RCC Grade M20

Case I Using concrete Mixer cum 7038.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8066.00
(ii) RCC Grade M25

Case I Using concrete Mixer cum 7632.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8661.00
(iii) RCC Grade M30

Case I Using Concrete Mixer cum 7646.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8672.00
(iv) RCC Grade M35

Case I Using Concrete Mixer cum 7760.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8781.00
(v) RCC M40 Grade cum 8908.00
(P) With plasticiser ( Masterplast PL-1/SPL-2 or equivalent ), air
1200, entraining and water reducing plasticiser ( Masterplast PAE or
1500 & equivalent) and accelerating plasticiser ( Masterplast ACPL or
1700 equivalent) conforming to IS-9103-1999.

A Well curb

(i) RCC M20 Grade

Case I Using concrete mixer cum 9197.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10413.00
(ii) RCC M25 Grade

Case I Using concrete mixer cum 9857.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 11075.00
(iii) RCC M30 Grade

Case I Using concrete mixer cum 9905.00

Page 80 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case II With Batching Plant, Transit Mixer and Concrete Pump cum 11123.00
(iv) RCC M35 Grade

Case I Using concrete mixer cum 10119.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 11338.00
B Well steining

(I) PCC M15 Grade cum 7523.00


(ii) PCC M20 Grade cum 8214.00
(iii) RCC M20 Grade

Case I Using concrete mixer cum 8430.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9545.00
(iv) PCC M25 Grade

Case I Using concrete mixer cum 8803.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9924.00
(v) RCC M25 Grade

Case I Using concrete mixer cum 9036.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10152.00
(vi) PCC M30 Grade

Case I Using concrete mixer cum 8880.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9994.00
(vii) RCC M30 Grade

Case I Using concrete mixer cum 9079.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10196.00
(viii) RCC M35 Grade

Case I Using concrete mixer cum 9275.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10393.00
(ix) RCC M40 Grade cum 10745.00
C Bottom Plug

(i) PCC Grade M20

Case I Using Concrete Mixer cum 8418.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9391.00
(ii) PCC Grade M25

Case I Using Concrete Mixer cum 8805.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9773.00
(iii) PCC Grade M30

Case I Using Concrete Mixer cum 8882.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9855.00
(iv) PCC Grade M35

Page 81 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case I Using Concrete Mixer cum 9061.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 10030.00
D Intermediate plug

(I) Grade M20 PCC

Case I Using Concrete Mixer cum 7825.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8812.00
(ii) Grade M25 PCC

Case I Using Concrete Mixer cum 8172.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9157.00
(iii) Grade M30 PCC

Case I Using Concrete Mixer cum 8242.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9253.00
E Top plug

(i) Grade M15 PCC

Case I Using Concrete Mixer cum 6839.00


(ii) Grade M20 PCC

Case I Using Concrete Mixer cum 7467.00


(iii) Grade M25 PCC

Case I Using Concrete Mixer cum 8003.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9022.00
(iv) Grade M30 PCC

Case I Using Concrete Mixer cum 8073.00


Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9086.00
F Well cap

(i) RCC Grade M20

Case I Using concrete Mixer cum 7991.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9018.00
(ii) RCC Grade M25

Case I Using concrete Mixer cum 8767.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9796.00
(iii) RCC Grade M30

Case I Using Concrete Mixer cum 8788.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9814.00
(iv) RCC Grade M35

Case I Using Concrete Mixer cum 8939.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9960.00

Page 82 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(v) RCC M40 Grade Using Batching Plant, Transit Mixer and Concrete
Pump cum 10124.00

12.12 Sinking of 6 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey
1200 soil and rock as shown against each case, complete as per
drawing and technical specifications. Depth of sinking is
rekonewedfrom bed level.

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 4722.00


(ii) Beyond 3m upto 10m depth metre 6763.00
(iii) Beyond 10m upto 20m metre 8932.00
(iv) Beyond 20m upto 30 m

a For sinking metre 16754.00


b For sinking including kentledge metre 20104.00
(v) Beyond 30m upto 40 m

a For sinking metre 39805.00


b For sinking including kentledge metre 47766.00
B Clayey soil ( 6m dia. Well )

(i) Depth below bed level upto 3.0 M metre 6786.00


(ii) Beyond 3m upto 10m depth metre 14397.00
(iii) Beyond 10 m upto 20 m

a For sinking metre 19015.00


b For sinking including kentledge metre 19966.00
(iv) Beyond 20m upto 30 m

a For sinking metre 35668.00


b For sinking including kentledge metre 44585.00
c For sinking including kentledge & dewatering if required. metre 46814.00
(v) Beyond 30m upto 40 m

a For sinking metre 84741.00


b For sinking including kentledge metre 101690.00
c For sinking including kentledge & dewatering if required. metre 106774.00
C Soft rock (6m dia well )

(i) Depth of soft rock strata upto 3m metre 18836.00


D Hard rock (6m dia well )

(i) Depth of soft rock strata upto 3m metre 20320.00

Page 83 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

12.13 Sinking of 7 m external diameter well ( other than pneumatic method of


sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and
1200 technical specifications. Depth of sinking is rekonewed from bed level.

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 7084.00


(ii) Beyond 3m upto 10m depth metre 9664.00
(iii) Beyond 10m upto 20m metre 12763.00
(iv) Beyond 20m upto 30 m

a For sinking metre 23941.00


b For sinking including kentledge metre 28729.00
(v) Beyond 30m upto 40 m

a For sinking metre 56883.00


b For sinking including kentledge metre 68260.00
B Clayey soil ( 7m dia. Well )

(I) Depth below bed level upto 3.0 M metre 9664.00


(ii) Beyond 3m upto 10m depth metre 14234.00
(iii) Beyond 10 m upto 20 m

(a) For sinking metre 18799.00


b For sinking including dewatering, if required., if required metre 19739.00
(iv) Beyond 20m upto 30 m

a For sinking metre 35261.00


b For sinking including kentledge metre 44077.00
c For sinking including kentledge & dewatering, if required. metre 46280.00
(v) Beyond 30m upto 40 m

a For sinking metre 83775.00


b For sinking including kentledge 100530.00
c For sinking including kentledge & dewatering, if required. metre 105556.00
C Soft rock ( 7m dia well )

(i) Depth of soft rock strata upto 3m metre 16301.00


D Hard rock ( 7m dia well )

(i) Depth upto 3 m metre 23243.00


12.14 Sinking of 8 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and
1200 technical specifications. Depth of sinking is rekonewed from bed level.

A Sandy soil

Page 84 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(i) Depth below bed level upto 3.0 M metre 8803.00


(ii) Beyond 3m upto 10m depth metre 10863.00
(iii) Beyond 10m upto 20m metre 14346.00
(iv) Beyond 20m upto 30 m

a For sinking metre 26910.00


b For sinking including kentledge metre 32292.00
(v) Beyond 30m upto 40 m

a For sinking metre 63936.00


b For sinking including kentledge metre 76723.00
B Clayey soil ( 8m dia. Well )

(i) Depth upto 3.0 M metre 11827.00


(ii) Beyond 3m upto 10m depth metre 14789.00
(iii) Beyond 10 m upto 20 m

a For sinking metre 19532.00


b Adding for dewatering @ 5% of cost, if required. metre 20509.00
(iv) Beyond 20m upto 30 m

a For sinking metre 36639.00


b For sinking including kentledge metre 45798.00
c For sinking including kentledge & dewatering, if required. metre 48088.00
(v) Beyond 30m upto 40 m

a For sinking metre 87049.00


b For sinking including kentledge metre 104459.00
c For sinking including kentledge & dewatering, if required. metre 109682.00
C Soft rock ( 8m dia well )

(i) Depth in soft rock strata upto 3m metre 18210.00


D Hard rock ( 8m dia well )

(i) Depth in hard rock strata upto 3 m metre 23434.00


12.15 Sinking of 9 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and
1200 technical specifications. Depth of sinking is rekonewed from bed level.

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 8902.00


(ii) Beyond 3m upto 10m depth metre 11921.00
(iii) Beyond 10m upto 20m metre 15745.00
(iv) Beyond 20m upto 30 m

Page 85 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

a For sinking metre 29533.00


b Adding 20% of cost for Kentledge including supports, loading
arrangement and Labour . metre 35440.00

(v) Beyond 30m upto 40 m

a For sinking metre 70167.00


b For sinking including kentledge metre 84201.00
B Clayey soil ( 9m dia. Well )

(i) Depth below bed level upto 3.0 M metre 12478.00


(ii) Beyond 3m upto 10m depth metre 15951.00
(iii) Beyond 10 m upto 20 m

a For sinking metre 21066.00


b For sinking including dewatering, if required metre 22119.00
(iv) Beyond 20m upto 30 m

a For sinking metre 39513.00


b For sinking including kentledge metre 49392.00
c For sinking including kentledge & dewatering, if required. metre 51861.00
(v) Beyond 30m upto 40 m

a For sinking metre 93876.00


b For sinking including kentledge metre 112652.00
c For sinking including kentledge & dewatering, if required. metre 118284.00
C Soft rock ( 9m dia well )

(i) Depth upto 3m metre 21958.00


D Hard rock ( 9m dia well )

(i) Depth of hard rock strata upto 3 m metre 26949.00


12.16 Sinking of 10 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and
1200 technical specifications. Depth of sinking is rekonewed from bed level.

A Sandy soil

(i) Depth below bed level upto 3.0 M metre 10722.00


(ii) Beyond 3m upto 10m depth metre 12582.00
(iii) Beyond 10m upto 20m metre 16618.00
(iv) Beyond 20m upto 30 m

a For sinking metre 31170.00


b For sinking including kentledge metre 37404.00
(v) Beyond 30m upto 40 m

a For sinking metre 74054.00

Page 86 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b Adding 20% of cost for Kentledge including supports, loading metre 88865.00
arrangement, and Labour etc.
B Clayey soil (10m dia. Well )

(i) Depth below bed level upto 3.0 M metre 13690.00


(ii) Beyond 3m upto 10m depth metre 15645.00
(iii) Beyond 10 m upto 20 m

a For sinking metre 20662.00


b Adding for dewatering @ 5% of cost, if required. metre 21696.00
(iv) Beyond 20m upto 30 m

a For sinking metre 38759.00


b For sinking including kentledge metre 48448.00
c For sinking including kentledge & dewatering, if required. metre 50871.00
(v) Beyond 30m upto 40 m

a For sinking metre 92087.00


b For sinking including kentledge 110505.00
c For sinking including kentledge & dewatering, if required. metre 116030.00
C Soft rock (10m dia well )

(i) Depth of soft rock strata upto 3m metre 23460.00


D Hard rock (10m dia well )

(i) Depth of hard rock strata upto 3 m metre 30989.00


12.17 Sinking of 11 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and
1200 technical specifications. Depth of sinking is rekonewed from bed level.

A Sandy soil

(i) Depth from bed level upto 3.0 M metre 24743.00


(ii) Beyond 3m upto 10m depth metre 19339.00
(iii) Beyond 10m upto 20m metre 25540.00
(iv) Beyond 20m upto 30 m

a For sinking metre 47908.00


b For sinking including kentledge metre 57489.00
(v) Beyond 30m upto 40 m

a For sinking metre 113824.00


b For sinking including kentledge metre 136589.00
B Clayey soil (11 m dia. Well )

(i) Depth from bed level upto 3.0 M metre 22818.00


(ii) Beyond 3m upto 10m depth metre 32184.00

Page 87 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(iii) Beyond 10 m upto 20 m

a For sinking metre 42505.00


b For sinking including dewatering, if required metre 44630.00
(iv) Beyond 20m upto 30 m

a For sinking metre 79730.00


b For sinking including kentledge metre 99662.00
c For sinking including kentledge & dewatering, if required. metre 104645.00
(v) Beyond 30m upto 40 m

a For sinking metre 189427.00


b For sinking including kentledge metre 227312.00
c For sinking including kentledge & dewatering, if required. metre 238678.00
C Soft rock (11m dia well )

(i) Depth of soft rock strata upto 3m metre 52670.00


D Hard rock (11m dia well )

(i) Depth of hard rock upto 3 m metre 69513.00


12.18 Sinking of 12 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and
1200 technical specifications. Depth of sinking is rekonewed from bed level.

A Sandy soil

(i) I) Depth below bed level upto 3.0 M metre 51031.00


(ii) Beyond 3m upto 10m depth metre 57296.00
(iii) Beyond 10m upto 20m metre 75670.00
(iv) Beyond 20m upto 30 m

a For sinking metre 141937.00


b For sinking including kentledge metre 170325.00
(v) Beyond 30m upto 40 m

a For sinking metre 337223.00


b For sinking including kentledge metre 404668.00
B Clayey soil (12 m dia. Well )

(i) Depth below bed level upto 3.0 M metre 56009.00


(ii) Beyond 3m upto 10m depth metre 81758.00
(iii) Beyond 10 m upto 20 m

a For sinking metre 107976.00


b For sinking including dewatering, if required metre 113375.00
(iv) Beyond 20m upto 30 m

a For sinking metre 202534.00

Page 88 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b For sinking including kentledge metre 253168.00


c For sinking including kentledge & dewatering, if required. metre 265827.00
(v) Beyond 30m upto 40 m

a For sinking metre 481194.00


b For sinking including kentledge metre 577433.00
c For sinking including kentledge & dewatering metre 606305.00
C Soft rock (12m dia well )

(i) Depth of soft rock strata upto 3m metre 124388.00


D Hard rock (12m dia well )

(i) Depth of hard rock strata upto 3 m metre 158596.00


12.19 Sinking of Twin D Type well ( other than pneumatic method of sinking )
through all types of strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing and technical
1200 specifications. Depth of sinking is reckoned from bed level.

A Sandy soil

(i) Depth from bed level upto 3.0 M metre 11558.00


(ii) Beyond 3m upto 10m depth metre 12471.00
(iii) Beyond 10m upto 20m metre 16472.00
(iv) Beyond 20m upto 30 m

a For sinking metre 30898.00


b For sinking including kentledge metre 37078.00
(v) Beyond 30m upto 40 m

a For sinking metre 73410.00


b For sinking including kentledge metre 88091.00
B Clayey soil (Twin D Type Well )

(i) Depth below bed level upto 3.0 M metre 13560.00


(ii) Beyond 3m upto 10m depth metre 17334.00
(iii) Beyond 10 m upto 20 m

a For sinking metre 22891.00


b For sinking including dewatering, if required metre 24036.00
(iv) Beyond 20m upto 30 m

a For sinking metre 42935.00


b For sinking including kentledge metre 53669.00
c For sinking including kentledge & dewatering, if required. metre 56353.00
(v) Beyond 30m upto 40 m

a For sinking metre 102010.00


b For sinking including kentledge metre 122412.00

Page 89 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

c For sinking including kentledge & dewatering, if required. metre 128532.00


C Soft rock (Twin D Type well )

(i) Depth of soft rock strata upto 3m metre 26526.00


D Hard rock (Twin D Type well )

(i) Depth of hard rock strata upto 3 m metre 33516.00


12.20 Pneumatic sinking of wells with equipment of approved design, drawing
and specifications worked by competent and trained personnel and
comprising of compression and decompression chambers, reducers,
two air locks separately for men and plant & materials

12.21 Sand filling in wells complete as per drawing and technical


1207 specifications cum 1448.00

12.22 1200 Providing steel liner 10 mm thick for curbs and 6mm thick for steining of
& wells including fabricating and setting out as per detailed drawing tonne 99335.00
1900
12.23A Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement
1100 complete as per drawing and technical specifications and removal of
& excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 metre 6832.00
1700 mm)

12.23B Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement


complete as per drawing and technical specifications and removal of
excavated earth with all lifts and lead upto 1000 m. including providing
plasticiser (Masterplast PL-1/SPL-2 or equivalent), air entraining and
1101
water reducing plasticiser ( asterplast PAE or equivalent) and
& metre 7244.00
accelerating plasticiser (Masterplast ACPL or equivalent) conforming to
1700
IS-9103-1999 (Pile diameter-750 mm)

12.24A Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement


1100,16 complete as per drawing and technical specifications and removal of
00 & excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 metre 11459.00
1700 mm)

12.24B Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement


complete as per drawing and technical specifications and removal of
excavated earth with all lifts and lead upto 1000 m. including providing
1100,16 plasticiser (Masterplast PL-1/SPL-2 or equivalent ), air entraining and
00 & water reducing plasticiser ( Masterplast PAE or equivalent) and metre 12193.00
1701 accelerating plasticiser ( Masterplast ACPL or equivalent) conforming to
IS-9103-1999) (Pile diameter-1000 mm)

12.25A Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement


1100&1 complete as per drawing and technical specifications and removal of
excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 metre 15123.00
700
mm)

12.25B Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement


complete as per drawing and technical specifications and removal of
excavated earth with all lifts and lead upto 1000 m. including providing
plasticiser (Masterplast PL-1/SPL-2 or equivalent ), air entraining and
1100&1 water reducing plasticiser ( Masterplast PAE or equivalent) and
metre 16180.00
701 accelerating plasticiser ( Masterplast ACPL or equivalent) conforming to
IS-9103-1999 (Pile diameter-1200 mm)

Page 90 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

12.26A Driven cast-in-place vertical M35 grade R.C.C. pile excluding


1100 & reinforcement complete as per drawing and & Technical Specification
metre 4893.00
1700 (Pile diameter - 750 mm)

12.26B Driven cast-in-place vertical M35 grade R.C.C. pile excluding


reinforcement complete as per drawing and & Technical Specification
including providing plasticiser ( Masterplast PL-1/SPL-2 or equivalent ),
1101 & air entraining and water reducing plasticiser ( Masterplast PAE or
metre 5306.00
1700 equivalent) and accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999 (Pile diameter - 750 mm)

12.27A Driven cast-in-place vertical M35 grade R.C.C. piles excluding


1100
reinforcement complete as per drawing and & Technical Specification
& metre 8277.00
(Pile diameter - 1000 mm)
1700

12.27B Driven cast-in-place vertical M35 grade R.C.C. piles excluding


reinforcement complete as per drawing and & Technical Specification
including providing plasticiser ( Masterplast PL-1/SPL-2 or equivalent ),
1100
air entraining and water reducing plasticiser ( Masterplast PAE or
& metre 9011.00
equivalent) and accelerating plasticiser ( Masterplast ACPL or
1700
equivalent) conforming to IS-9103-1999 (Pile diameter - 1000 mm)

12.28A Driven cast-in-place vertical M35 grade R.C.C. piles excluding


1100&1 reinforcement complete as per drawing and & Technical Specification
metre 11998.00
700 (Pile diameter - 1200 mm)

12.28B Driven cast-in-place vertical M35 grade R.C.C. piles excluding


reinforcement complete as per drawing and & Technical Specification
including providing plasticiser ( Masterplast PL-1/SPL-2 or equivalent ),
1100&1 air entraining and water reducing plasticiser ( Masterplast PAE or
metre 13055.00
701 equivalent) and accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999 (Pile diameter - 1200 mm)

12.37 Pile load test on single vertical pile in accordance with


IS:2911(Part-IV).
1100 Ton 330.00
a). Initial and Routine load test.

b) Lateral load test Ton 5500.00


12.38 (I) Cement concrete for reinforced concrete in pile cap complete as
1100, 1500 per drawing and Technical Specification.
& 1700

A RCC Grade M20

(i) Using Concrete Mixer cum 7037.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 6898.00
B RCC Grade M25

(i) Using concrete mixer. cum 7611.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 7486.00
C RCC Grade M30

(i) Using concrete mixer. cum 7683.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 7544.00
D RCC Grade M35

(i) Using concrete mixer. cum 7835.00

Page 91 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 7710.00
12.38 (II) Cement concrete for reinforced concrete in pile cap complete as per
drawing and Technical Specification including providing plasticiser
1100, ( Masterplast PL-1/SPL-2 or equivalent ), air entraining and water
1500 & reducing plasticiser ( Masterplast PAE or equivalent) and accelerating
1700 plasticiser ( Masterplast ACPL or equivalent) conforming to IS-9103-
1999.

A RCC Grade M20

(i) Using Concrete Mixer cum 7786.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 7647.00
B RCC Grade M25

(i) Using concrete mixer. cum 8494.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8370.00
C RCC Grade M30

(i) Using concrete mixer. cum 8583.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8444.00
D RCC Grade M35

(i) Using concrete mixer. cum 8768.00


(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8644.00
12.39 1100 Levelling course for Pile cap
cum 5870.00
&1700
12.40 Reinforcement in Foundation: Supplying, fitting and placing TMT
IS:1786 Fe500 D bar reinforcement in foundation complete as per
1600
drawing and technical specifications

(a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ 78391.00
Jindal panther steel/ Shyam steel or equivalent) tonne

(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved) 72847.00


tonne

12.41 Supplying, fitting and placing un-coated Mild steel (IS: 1786 Fe-250)
reinforcement complete in foundation as per drawing and technical
1600 specification tonne 83652.00

Page 92 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-13
SUB-STRUCTURE
13.1 Brick masonry work in 1:3 in sub-structure complete excluding pointing
1300 & and plastering, as per drawing and technical specifications
cum 7985.00
2200

13.2 1300 & Pointing with cement mortar (1:3 ) on brick work in substructure as per
Technical specifications sqm 68.00
2200
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work in sub-structure as
per Technical specifications sqm 142.00
2200
13.4 1400 & Stone masonry work in cement mortar 1:3 for substructure complete as
2200 per drawing and Technical Specifications

A Random Rubble Masonry cum 4196.00


B Coursed rubble masonry (first sort ) cum 4359.00
C Ashlar masonry ( first sort ) cum 5768.00
13.5 (N) Plain/Reinforced cement concrete, in sub structure complete as per
1500,1700 drawing and technical specification and steel shuttering formwork
& 2200

(N) Without plasticiser


A PCC Grade M15 cum 6601.00
Height upto 5m

B PCC Grade M20 cum 7290.00


Height upto 5m

C PCC Grade M25

a Height upto 5m

Case I Using concrete Mixer cum 7870.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9161.00
b Height 5m to 10m

Case I Using concrete Mixer cum 8156.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9494.00
c Height above 10m

Case I Using concrete Mixer cum 8514.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9910.00
D PCC Grade M30

a Height upto 5m

Case I Using concrete Mixer cum 7932.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9046.00
b Height 5m to 10m

Case I Using concrete Mixer cum 8221.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9375.00
c Height above 10m

Page 93 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case I Using concrete Mixer cum 8581.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9786.00
E RCC Grade M20

a Height upto 5m

Case I Using concrete Mixer cum 7507.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8623.00
b Height 5m to 10m

Case I Using concrete Mixer cum 7780.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8937.00
c Height above 10m

Case I Using concrete Mixer cum 8121.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6527.00
F RCC Grade M25

a Height upto 5m

Case I Using concrete Mixer cum 8092.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9209.00
b Height 5m to 10m

Case I Using concrete Mixer cum 8092.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9209.00
c Height above 10m

Case I Using concrete Mixer cum 8754.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9962.00
G RCC Grade M30

a Height upto 5m

Case I Using concrete Mixer cum 8127.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9245.00
b Height 5m to 10m

Case I Using concrete Mixer cum 8356.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9505.00
c Height above 10m

Case I Using concrete Mixer cum 8755.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9959.00
H RCC Grade M35

a Height upto 5m

Case I Using concrete Mixer cum 8288.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9406.00
b Height 5m to 10m

Page 94 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case I Using concrete Mixer cum 8469.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9611.00
c Height above 10m

Case I Using concrete Mixer cum 8740.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9919.00
(P) With plasticiser ( Masterplast PL-1/SPL-2 or equivalent ), air
entraining and water reducing plasticiser ( Masterplast PAE or
equivalent) and accelerating plasticiser( Masterplast ACPL or
equivalent) conforming to IS-9103-1999

A PCC Grade M15

Height upto 5m cum 7523.00


B PCC Grade M20

Height upto 5m cum 8214.00


C PCC Grade M25

a Height upto 5m

Case I Using concrete Mixer cum 8803.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9924.00
b Height 5m to 10m

Case I Using concrete Mixer cum 9124.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9494.00
c Height above 10m

Case I Using concrete Mixer cum 9524.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10736.00
D PCC Grade M30

a Height upto 5m

Case I Using concrete Mixer cum 8880.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9994.00
b Height 5m to 10m

Case I Using concrete Mixer cum 9203.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10358.00
c Height above 10m

Case I Using concrete Mixer cum 9607.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10812.00
E RCC Grade M20

a Height upto 5m

Case I Using concrete Mixer cum 8430.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9545.00
b Height 5m to 10m

Page 95 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case I Using concrete Mixer cum 8737.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9893.00
c Height above 10m

Case I Using concrete Mixer cum 9120.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10326.00
F RCC Grade M25

a Height upto 5m

Case I Using concrete Mixer cum 9036.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10152.00
b Height 5m to 10m

Case I Using concrete Mixer cum 9332.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10485.00
c Height above 10m

Case I Using concrete Mixer cum 9775.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10983.00
G RCC Grade M30

a Height upto 5m

Case I Using concrete Mixer cum 9079.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10196.00
b Height 5m to 10m

Case I Using concrete Mixer cum 9335.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10483.00
c Height above 10m

Case I Using concrete Mixer cum 9698.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10891.00
H RCC Grade M35

a Height upto 5m

Case I Using concrete Mixer cum 9275.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10393.00
b Height 5m to 10m

Case I Using concrete Mixer cum 9478.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10620.00
c Height above 10m

Case I Using concrete Mixer cum 9781.00


Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10960.00
13.6 Supplying, fitting and placing TMT IS:1786 (Fe 500) bar
reinforcement in sub-structure complete as per drawing and
technical specifications

Page 96 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/
Jindal panther steel/ Shyam steel or equivalent) tonne 78525.00

(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved)


tonne 72981.00

13.7 Supplying, fitting and placing un-coated Mild steel (IS: 1786 Fe-250)
reinforcement complete in sub-structure as per drawing and Technical tonne 81413.00
Specification

13.8 Providing weep holes in Brick masonry/Plain/Reinforced concrete


abutment, wing wall/return wall with 100 mm dia AC pipe, extending
through the full width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical specification. each 199.00

13.9 Back filling behind abutment, wing wall and return wall complete as per
drawing and Technical specification

A Granular material cum 1420.00


B Sandy material cum 1420.00
13.10 Providing and laying of Filter media with granular materials/stone
crushed aggregates satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a thickness of not less than 600
mm with smaller size towards the soil and bigger size toeards the wall
and provided over the entire surfaces behind the abutement, wing wall cum 1896.00
and return wall to the full height compacted to firm condition complete
as per drawing and technical specification.

13.11 Supplying, fitting and fixing in position true to line and level cast steel
rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 tonne
of MoRTH specifications complete including all accessories as per 727.00
capacity
drawing and Technical Specifications.

13.12 Supplying, fitting and fixing in position true to line and level forged steel
roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 tonne
of MoRTH specifications complete including all accessories as per 628.00
capacity
drawing and Technical Specifications.

13.13 Supplying, fitting and fixing in position true to line and level sliding plate
bearing with PTFE surface sliding on stainless steel complete including
all accessories as per drawing and Technical Specifications and BS: tonne
337.00
5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of MORT&H capacity
specification.

13.14 Supplying, fitting and fixing in position true to line and level elastomeric
bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of cubic
MoRTH specifications complete including all accessories as per drawing centimetre 5.13
and Technical Specifications.
13.15 Supplying, fitting and fixing in position true to line and level sliding plate
bearing with stainless steel plate sliding on stainless steel plate with tonne
mild steel matrix complete including all accessories as per drawing and 189.00
capacity
Technical Specifications.
13.16 Supplying, fitting and fixing in position true to line and level POT-PTFE
bearing consisting of a metal piston supported by a disc or unreinforced
elastomer confined within a metal cylinder, sealing rings, dust seals,
PTFE surface sliding against stainlesssteel matting surfaces, complete
assembly to be of cast steel/fabricated structural steel, meatal and
elastomer elements to be as per IRC:83 part-I &II respectively and parts tonne
214.00
conforming to BS:5400, section 9.1 & 9.2 and clause 2006 of capacity
MORTH&S Specification complete as per drawing and approved
technical specification.

Page 97 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-14

SUPER-STRUCTURE

14.1 Furnishing and Placing Reinforced/Prestressed cement concrete in


super-structure as per drawing and Technical Specification'
including steel shuttering formwork.

(N) Without Plasticiser

A RCC Grade M20

Case I Using Concrete Mixer

(i) For solid slab super-structure

a Height upto 5m cum 8120.00


b Height 5m to 10m cum 8459.00
c Height above 10m cum 8797.00
(ii) For T-beam & slab

a Height upto 5m cum 8459.00


b Height 5m to 10m cum 8797.00
c Height above 10m cum 9135.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 9307.00


b Height 5m to 10m cum 9695.00
c Height above 10m cum 10082.00
(ii) For T-beam & slab

a Height upto 5m cum 9695.00


b Height 5m to 10m cum 10082.00
c Height above 10m cum 10470.00
B RCC Grade M25

Case I Using Concrete Mixer

(i) For solid slab super-structure

a Height upto 5m cum 8782.00


b Height 5m to 10m cum 9148.00
c Height above 10m cum 9514.00
(ii) For T-beam & slab

a Height upto 5m cum 9148.00


b Height 5m to 10m cum 9514.00
c Height above 10m cum 9880.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 9977.00

Page 98 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b Height 5m to 10m cum 10393.00


c Height above 10m cum 10809.00
(ii) For T-beam & slab

a Height upto 5m cum 10393.00


b Height 5m to 10m cum 10809.00
c Height above 10m cum 11225.00
C RCC Grade M 30

Case I Using Concrete Mixer

(i) For solid slab super-structure

a Height upto 5m cum 8893.00


b Height 5m to 10m cum 9263.00
c Height above 10m cum 9634.00
(ii) For T-beam & slab

a Height upto 5m cum 9263.00


b Height 5m to 10m cum 9634.00
c Height above 10m cum 10004.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump.

(i) For solid slab super-structure

a Height upto 5m cum 10015.00


b Height 5m to 10m cum 10433.00
c Height above 10m cum 10850.00
(ii) For T-beam & slab

a Height upto 5m cum 10433.00


b Height 5m to 10m cum 10850.00
c Height above 10m cum 11267.00
D RCC/PSC Grade M35

Case 1 Using concrete mixer.

(i) For solid slab super-structure

a Height upto 5m cum 8917.00


b Height 5m to 10m cum 9294.00
c Height above 10m cum 9672.00
(ii) For T-beam & slab

a Height upto 5m cum 9294.00


b Height 5m to 10m cum 9672.00
c Height above 10m cum 10050.00
(iii) For box girder and balanced cantilever
a Height upto 5m cum 10428.00

Page 99 of 959
Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b Height 5m to 10m cum 11183.00


c Height above 10m cum 11939.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 10014.00


b Height 5m to 10m cum 10438.00
c Height above 10m cum 10862.00
(ii) For T-beam & slab

a Height upto 5m cum 10438.00


b Height 5m to 10m cum 10862.00
c Height above 10m cum 11287.00
(iii) For box girder and balanced cantilever
a Height upto 5m cum 11711.00
b Height 5m to 10m cum 12560.00
c Height above 10m cum 13408.00
E PSC Grade M-40

Case 1 Using concrete mixer.

(i) For solid slab super-structure

a Height upto 5m cum 9211.00


b Height 5m to 10m cum 9595.00
c Height above 10m cum 9979.00
(ii) For T-beam & slab

a Height upto 5m cum 9595.00


b Height 5m to 10m cum 9979.00
c Height above 10m cum 10363.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 10110.00


b Height 5m to 10m cum 10538.00
c Height above 10m cum 10967.00
(ii) For T-beam & slab

a Height upto 5m cum 10538.00


b Height 5m to 10m cum 10967.00
c Height above 10m cum 11395.00
(iii) For box girder and balanced cantilever
a Height upto 5m cum 11823.00
b Height 5m to 10m cum 12680.00
c Height above 10m cum 13537.00

Page 100 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

F PSC Grade M-45

(i) For solid slab/voided slab super-structure

a Height upto 5m cum 10324.00


b Height 5m to 10m cum 10769.00
c Height above 10m cum 11214.00
(ii) For I-beam & slab including launching of precast girders by
launching truss upto 40 m span
a Height upto 5m cum 10769.00
b Height 5m to 10m cum 11214.00
c Height above 10m cum 11659.00
(iii) For cast-in-situ box girder, segmental construction and balanced
cantilever
a Height upto 5m cum 12105.00
b Height 5m to 10m cum 12995.00
c Height above 10m cum 13885.00
G PSC Grade M-50

(i) For cast-in-situ box girder, segmental construction and balanced


cantilever
a Height upto 5m cum 12336.00
b Height 5m to 10m cum 13250.00
c Height above 10m cum 14164.00
H PSC Grade M- 55

(i) For cast-in-situ box girder, segmental construction and balanced


cantilever
a Height upto 5m cum 12839.00
b Height 5m to 10m cum 13790.00
c Height above 10m cum 14741.00
(P) With plasticiser ( Masterplast PL-1/SPL-2 or equivalent ), air
entraining and water reducing plasticiser ( Masterplast PAE or
equivalent) and accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999.

A RCC Grade M20

Case I Using Concrete Mixer

(i) For solid slab super-structure

a Height upto 5m cum 9221.00


b Height 5m to 10m cum 9605.00
c Height above 10m cum 9989.00
(ii) For T-beam & slab

a Height upto 5m cum 9605.00


b Height 5m to 10m cum 9989.00
c Height above 10m cum 10373.00

Page 101 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 10301.00


b Height 5m to 10m cum 10730.00
c Height above 10m cum 11159.00
(ii) For T-beam & slab

a Height upto 5m cum 10730.00


b Height 5m to 10m cum 11159.00
c Height above 10m cum 11588.00
B RCC Grade M25

Case I Using Concrete Mixer

(i) For solid slab super-structure

a Height upto 5m cum 10082.00


b Height 5m to 10m cum 10502.00
c Height above 10m cum 10922.00
(ii) For T-beam & slab

a Height upto 5m cum 10502.00


b Height 5m to 10m cum 10922.00
c Height above 10m cum 11342.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 11228.00


b Height 5m to 10m cum 11695.00
c Height above 10m cum 12163.00
(ii) For T-beam & slab

a Height upto 5m cum 11695.00


b Height 5m to 10m cum 12163.00
c Height above 10m cum 12631.00
C RCC Grade M 30

Case I Using Concrete Mixer

(i) For solid slab super-structure

a Height upto 5m cum 10216.00


b Height 5m to 10m cum 10642.00
c Height above 10m cum 11068.00
(ii) For T-beam & slab

a Height upto 5m cum 10642.00


b Height 5m to 10m cum 11068.00

Page 102 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

c Height above 10m cum 11494.00


Case II Using Batching Plant, Transit Mixer and Concrete Pump.

(i) For solid slab super-structure

a Height upto 5m cum 11339.00


b Height 5m to 10m cum 11811.00
c Height above 10m cum 12284.00
(ii) For T-beam & slab

a Height upto 5m cum 11811.00


b Height 5m to 10m cum 12284.00
c Height above 10m cum 12756.00
D RCC/PSC Grade M35

Case 1 Using concrete mixer.

(i) For solid slab super-structure

a Height upto 5m cum 10267.00


b Height 5m to 10m cum 10702.00
c Height above 10m cum 11137.00
(ii) For T-beam & slab

a Height upto 5m cum 10702.00


b Height 5m to 10m cum 11137.00
c Height above 10m cum 11572.00
(iii) For box girder and balanced cantilever

a Height upto 5m cum 12008.00


b Height 5m to 10m cum 12878.00
c Height above 10m cum 13748.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 11365.00


b Height 5m to 10m cum 11846.00
c Height above 10m cum 12328.00
(ii) For T-beam & slab

a Height upto 5m cum 11846.00


b Height 5m to 10m cum 12328.00
c Height above 10m cum 12809.00
(iii) For box girder and balanced cantilever

a Height upto 5m cum 13291.00


b Height 5m to 10m cum 14254.00

Page 103 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

c Height above 10m cum 15217.00


E PSC Grade M-40

Case 1 Using concrete mixer.

(i) For solid slab super-structure

a Height upto 5m cum 10611.00


b Height 5m to 10m cum 11053.00
c Height above 10m cum 11495.00
(ii) For T-beam & slab

a Height upto 5m cum 11053.00


b Height 5m to 10m cum 11495.00
c Height above 10m cum 11937.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

(i) For solid slab super-structure

a Height upto 5m cum 11486.00


b Height 5m to 10m cum 11973.00
c Height above 10m cum 12460.00
(ii) For T-beam & slab

a Height upto 5m cum 11973.00


b Height 5m to 10m cum 12460.00
c Height above 10m cum 12946.00
(iii) For box girder and balanced cantilever

a Height upto 5m cum 13433.00


b Height 5m to 10m cum 14407.00
c Height above 10m cum 15380.00
F PSC Grade M-45

(i) For solid slab/voided slab super-structure


a Height upto 5m cum 11788.00
b Height 5m to 10m cum 12296.00
c Height above 10m cum 12804.00
(ii) For I-beam & slab including launching of precast girders by
launching truss upto 40 m span

a Height upto 5m cum 12296.00


b Height 5m to 10m cum 12804.00
c Height above 10m cum 13312.00
(iii) For cast-in-situ box girder, segmental construction and balanced
cantilever

a Height upto 5m cum 13820.00

Page 104 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

b Height 5m to 10m cum 14836.00


c Height above 10m cum 15852.00
G PSC Grade M-50

(i) For cast-in-situ box girder, segmental construction and balanced


cantilever

a Height upto 5m cum 14131.00


b Height 5m to 10m cum 15177.00
c Height above 10m cum 16224.00
H PSC Grade M- 55

(i) For cast-in-situ box girder, segmental construction and balanced


cantilever

a Height upto 5m cum 14777.00


b Height 5m to 10m cum 15871.00
c Height above 10m cum 16966.00
14.2 Reinforcement in Super Structure: Supplying, fitting and placing TMT
conforming to IS:1786 Fe 500 D reinforcement in super-structure
including splicing complete as per drawing and technical specifications

(a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/
Jindal panther steel/ Shyam steel or equivalent) tonne 80072.00

(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved)


tonne 74297.00

14.3 High tensile steel wires/strands including all accessories for stressing,
stressing operations and grouting complete as per drawing and
tonne 157232.00
Technical Specifications

14.4 Providing and laying Cement concrete wearing coat M-30 grade
including reinforcement complete as per drawing and Technical cum 14559.00
Specifications

14.5 Mastic Asphalt

(A) Providing and laying 12 mm thick mastic asphalt wearing course on top
of deck slab excluding prime coat with paving grade bitumen meeting
the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope aftering cleaning the surface,
including providing antiskid surface with bitumen pre coated fine grained
hard stone shipping of 9.5mm nominal size at the rate of .005 cum per
10sqm and at approximate spaciong of 10cm center to center in both sqm 434.00
directions, pressed into surfaces when temperature of the surfaces not
less than 100 degC. , protuding 1mm to 4mm over mastic surfaces, all
complete as per clause 515.

Page 105 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(B) Providing and laying Bituminous wearing course comprising of tack coat
with bitumen emulsion CSS-1h as per APWD SOR item no 5.2 &
MOSRT&H Specification Nos 503 0.6mm thick mastic asphalt as per
APWD SOR item no 14.5 & MOSRT&H Specification Nos 515 & 2702
and 2 layers of 25 mm thick Asphalt concrete including of close Graded
Premix Surfacing(CGPS) materials with Type -a aggregate as per sqm 546.00
APWD SOR tem no 5.11 & MOSRT&H Specification Nos 512 including
all lead and lift as directed.

14.6 Construction of precast RCC railing of M30 Grade, aggregate size not
exceeding 12 mm, true to line and grade, tolurence of vertical RCC
post not to exceed 1 in 500, centre to centre spacing between vertical
post not to exceed 2000 mm, leaving adequat space between vertical metre 2312.00
posts for expansion, complete as per approved drawings and technical
specifications.

14.7 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal


size aggregate, true to line and grade, tolurence of vertical RCC post
not to exceed 1 in 500, centre to centre spacing between vertical post
not to exceed 2000 mm, leaving adequat space between vertical posts metre 2253.00
for expansion, complete as per approved drawings and technical
specifications.

14.8 Providing, fitting and fixing mild steel railing complete as per drawing
and Technical Specification metre 4450.00

14.9 Drainage Spouts complete as per drawing and Technical specification


Each 8866.00

14.10 PCC M15 Grade leveling course below approach slab complete as per
drawing and Technical specification cum 6001.00

14.11 Reinforced cement concrete approach slab including reinforcement and


formwork complete as per drawing and Technical specification

(a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ cum 13449.00
Jindal panther steel/ Shyam steel or equivalent)
(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved)
cum 13172.00

(c) MS bar-IS 1786 ( Fe-250 ) Secondary Producer


cum 13172.00

14.13 Precast - pretensioned Girders (Providing, precasting, transportation


and placing in position precast pretensioned concrete girders as per cum 24981.00
drawing and technical specifications)

14.14 Structural steel Built-Up-Girder (BUG) (Providing and launching Steel


Truss of Structural steel BUG Super Structure including painting
complete as per as per drawing and technical specifications under MT 158977.00
Section 1900 of MOST.)

14.16 Painting on concrete surface (Providing and applying 2 coats of water


based cement paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and applying paint @
of 1 litre for 2 Sq.m. )

(A) For Plain surface sqm 51.00


(B) For RCC Railing RM 182.00

Page 106 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

14.17 Burried Joint (Providing and laying a burried expansion joint,


expansion gap being 20 mm, covered with 12 mm thick, 200 mm wide
galvanised wieldable structural steel plate as per IS: 2062, placed
symmetrical to centre line of the joint, resting freely over the top
surfaces of the deck concrete, welding of 8mm dia, 100mm long metre 1497.00
galvanized nails spaced 300mm C/C along the center line of the plate ,
all as specified in clause 2604.)

14.18 Filler joint


(i) Providing & fixing 2 mm thick corrugated copper plate in expansion joint
complete as per drawing & Technical Specification.
metre 4298.00

(ii) Providing & fixing 20 mm thick compressible fibre board in expansion


joint complete as per drawing & Technical Specification.
metre 362.00

(iii) Providing and fixing in position 20 mm thick premoulded joint filler in


expansion joint for fixed ends of simply supported spans not exceeding
10 m to cater for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical specification. metre 328.00

(iv) Providing and filling joint sealing compound as per drawings and
technical specifications with coarse sand and 6% bitumen by weight
metre 23.00

14.19 Asphaltic Plug joint (Providing and laying of asphaltic plug joint to
provide for horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width varying from
500 mm to 750 mm (in traffic direction), covered with a closure plate
200mmX 6mm of wiedable structural steel conforming to IS:2062,
asphaltic plug consist of polymer modified bitumen binder, carefully
metre 1276.00
selected singl;e size aggregate of 12.5mm nominal size and heat
resistant foam caulking/backer rod, all as per approved drawing and
specifications.)

14.20 Elastomeric Slab Seal Expansion Joint (Providing and laying of an


elastomeric slab steel expansion joint, catering to right or skew (less
than 20 deg., moderately curved with maximum horizontal movement
upto 50 mm, complete as per approved drawings and standard
specification to be installed by the manufacture/supplier or their metre 24997.00
authorisedrepresentative ensuring compliance to the manufacturers
instructios for installation and clause 2506 of MORTS&H specification of
bridge works.)

14.21 Compression Seal Joint (Providing and laying of compression seal


joint consisting of steel armoured nosing at two edges of the joint gap
suitably anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and fixed into the
metre 13839.00
gap with special adhesive binder to cater for a horizontal movement up
to 40mm and vertical movement of 3mm.)

14.22 Strip Seal Expansion Joint (Providing and laying of a strip seal
expansion joint catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative metre 27761.00
ensuring compliance to the manufacturer's instruction for installation).

Page 107 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

14.23 Modular Strip / Box Seal Joint


(Providing and laying of a modular strip Box steel expansion joint
including anchorage catering to a horizontal movement beyond 70 mm
and upto 140mm, complete as per approved drawings and standard
specifications to be installed by teh manufacture/supplier or their metre 150525.00
authorised representative ensuring compliance to the manufacturer's
instruction for installation.)

14.24 Modular Strip / Box Seal Joint


(Providing and laying of a modular strip box seal expansion joint
catering to a horizontal movement beyond 140mm and upto 210mm,
complete as per approved drawings and standard specifications to be
installed by the manufactu/supplier or their authorised representative metre 228152.00
ensuring compliance to the manufacturer's instruction for installation.)

14.25 Extra for providing water proofing compound

( Providing and applying cement mortar(1 cement 3 sand) with sqm 340.00
STRUCO LATEX or its equivalent as per specification and as directed
by the Department
14.26 Extra for providing water proofing compound

( Cleaning the surface and applying two coats ofARMOURCRETE or its sqm 237.00
equivalent as per specification and as directed by the Department

Page 108 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-15

RIVER TRAINING AND PROTECTION WORKS

15.1 Providing and laying boulders apron on river bed for protection against
scour with stone boulders weighing not less than 40 kg each complete
2403 as per drawing and Technical specification.

A Boulder laid dry without wire crates. cum 1919.00


15.2 Boulder apron laid in wire crates (Providing and laying of boulder
apron laid in wire crates made with 4mm dia GI wire conforming to IS:
280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including
2503 10% extra for laps and joints laid with stone boulders weighting not less cum 2961.00
than 40Kg each.)

15.3 Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying
of apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ
and made with nominal mix of M-15 grade cement concrete with a
2503 cum 6365.00
minimum cement content of 250 kg/cum as per IRC: 21-2000.)

15.4 Providing and laying Pitching on slopes laid over prepared filter media
including boulder apron laid dry in front of toe of embankment complete
2504 as per drawing and Technical specifications

A Stone/Boulder cum 1919.00


B Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement
concrete of Grade M15 cum 6365.00

15.5 Providing and laying Filter material underneath pitching in slopes


2504 complete as per drawing and Technical specification cum 2069.00

15.8 Providing and laying Flooring complete as per drawing and Technical
2505 specifications laid over cement concrete bedding.

A Rubble stone laid in cement mortar 1:3 cum 5938.00


B Cement Concrete blocks Grade M15 cum 9554.00
15.9 Dry rubble Flooring, Construcytion of dry rubbl flooring at cross drainage
2506 cum 2288.00
works for relatively less important works.
15.10 Curtain wall complete as per drawing and Technical specification
2507.2

A Stone masonry in cement mortar (1:3) cum 4428.00


B Cement concrete Grade M15 cum 6128.00
15.11 Flexible Apron :Construction of flexible apron 1 m thick comprising of
loose stone boulders weighing not less than 40 kg beyond curtain wall.
2507.2 cum 1963.00

Page 109 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

15.12 Gabian Structure for Retaining Earth (Providing and construction of a


gabain structure for retaining earth with segments of wire crates of size
7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross
netting, made from 4 mm galvanised steel wire @ 32Kgs per 10Sqm
having minimum tensil strength of 300Mpa conforming to IS:280 and
2503.3 galvanizing coating conforming to IS:4826, woven into meshes with cum 3148.00
double twist, mesh size not exceeding to 100mmX100mm , firred with
boulders at least dimension of 200mm , all loose ends to be tied with
4mm galvenized steel wire.)

15.13 Gabian Structure for Erosion Control, River Training Works and
Protection works (Providing and constructing gabain structures for
erosion control, river training works and protection works with wire
crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by
cross netting, made from 4 mm galvanised steel wire@ 32Kgs per
10Sqm having minimum tensil strength of 300Mpa conforming to IS:280
2503.3 and galvanizing coating conforming to IS:4826, woven into meshes with cum 5002.00
double twist, mesh size not exceeding to 100mmX100mm , firred with
boulders at least dimension of 200mm , all loose ends to be tied with
4mm galvenized steel wire.)

Page 110 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-16

REPAIR AND REHABILITATION

16.1 Removal of existing cement concrete wearing coat including its disposal
complete as per Technical specification without causing any detrimental
effect to any part of the bridge structure and removal of dismantled
2809 material with all lifts and lead upto 1000.(Thickness 75mm.) sqm 114.00

16.2 Removal of existing asphaltic wearing coat comprising of 50 mm thick


asphaltic concrete laid over 12 mm thick mastic asphalt including
2809 disposal with all lift and lead upto 1000m. sqm 86.00

16.3 Guniting concrete surface with cement mortar applied with compressor
after cleaning surface and spraying with epoxy complete as per
2807 Technical specification sqm 1092.00

16.4 Providing and inserting nipples with approved fixing compound after
drilling holes for grouting as per Technical specifications including
subsequent cutting/removal and sealing of the hole as necessary of
2800 nipples after completion of grouting with Cement/Epoxy. each 215.00

16.5 Sealing of cracks/porous concrete by injection process through


2806
nipples/Grouting complete as per Technical specification.
A Cement Grout kg 199.00
B Cement mortar (1:1) Grouting kg 192.00
16.6 Patching of damaged concrete surface with polymer concrete and
curing compounds, initiator and promoter, available in present
2800 formulations, to be applied as per instructions of manufacturer and as sqm 877.00
approved by the Engineer.

16.7 Sealing of crack / porous concrete with Epoxy Grout by injection through
2803 nipples complete as per clause 2803.1. kg 1208.00

16.8 Applying epoxy mortar over leached, honey combed and spalled
concrete surface and exposed steel reinforcement complete as per
2804 Technical specification sqm 795.00

16.9 Removal of defective concrete, cleaning the surface thoroughly,


applying the shotcrete mixture mechanically with compressed air under
pressure, comprising of cement, sand, coarse aggregates, water and
quick setting compound in the proportion as per clause 2807.1. sand
and coarse aggregates conformiong to IS : 383 and table 1 of IS:9012
2807 respectively, water cement ratio ranging from 0.35 to 0.50, density of sqm 359.00
gunite not less than 2000Kg/cum. , strength not less than 25Mpa and
workmanship conforming to to clause no.2807.6

16.10 Applying pre-packed cement based polymer mortar of strength 45 Mpa


2800 sqm 212.00
at 28 days for replacement of spalled concrete
16.11 2805 Eproxy bonding of new concrete to old concrete sqm 206.00
16.12 Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing
and Technical specification(span=25M) tonne 449029.00

Page 111 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

16.13 Providing external prestressing with high tensile steel wires/strands


including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing
and Technical specification(span=50M) tonne 434817.00

16.14 Providing external prestressing with high tensile steel wires/strands


including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing
and Technical specification(span=100M) tonne 397863.00

16.15 Labour for replacement of Bearings complete as per Technical


2808 Specification (Cost of bearing to be paid extra) each 3966.00

16.16 Labour for Lifting of superstructure span by jacking up from below i.e. by
placing the jacks on pier/abutment caps for span length of 30m. (Cost of
2808 bearing to be paid extra) (Rectification of Bearings as per Technical
Specifications)

A Lifting from the pier cap each 64061.00

B Lifting with constructing auxilary structure upto 6M height including


dismentling and removal of same each 400000.00

16.17 Replacement of Expansion Joints complete as per drawings metre 3897.00


16.18 Replacement of damaged concrete railing. metre 213.00
16.19 Replacement of crash barrier. metre 384.00
16.20 Replacement of damaged mild steel railing metre 179.00
16.21 Repair of crash barrier (Repair of concrete crash barrier with cement
concrete of M-30 grade by cutting and trimming the damaged portion to
a regular shape, cleaning the area to be repaired thoroughly, applying
cement concrete after erection of proper f metre 267.00

16.22 Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring
it to the original shape.) metre 235.00

16.23 Repair of steel Railing (Repair of steel railing to bring it to the original
shape) metre 378.00

16.24 Chipping of deteriorated concrete and removal of all loose & friable
materials and fully exposing rusted reinforcement followed by proper
cleaning and removing of rusts and other foreign materials using sand
blasting/ emery cloths/ wire brush etc. including formwork as directed
sqm 238.00
and specified by the department complete

16.25 Replacement of corroded reinforcement by cutting and welding new


reinforcement of minimum 25mm dia. including lapping on both sides to
the specified length as directed and as per relevant IS/IRC codes and
cost of gas ,welding rods,higher charge of welding machines etc. metre 386.00
including formwork as required.(Reinforcement to be measured and
paid seperately)

16.26 Anticorrosive treatment

Page 112 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(A) Supplying and applying two coats of Zinc rich anti-corrosive protective
coating with'Techguard 102' of Choksey Chemicals or euivalent @ 0.50
Lit per Sqm over thoroughly cleaned and prepared steel bars including
formwork as directed and specified by the department complete. sqm 432.00

(B) Spplying and applying one coat of Zinc based epoxy anticorrosive
coating like CONCRESIVE ZRI of Degussa brand or euivalent @ 0.09
Lit per Sqm all over the exposed reinforcement over thoroughly cleaned
and prepared steel bars including formwork as directed and specified sqm 283.00
by the department complete.

16.28 Bonding between old and new concret surfaces

(A) Supplying and applying Epoxy based bonding agent Masterbond EP of


Choksey Chemicals or euivalent @ 0.50 Lit pe sqm after totally
saturating the cleaned concrete surface with clean water for proper
bonding of old and new concrete including formwork as specified and sqm 790.00
directed by the department complete.

(B) Providing and applying coating of the cleaned patches with two part of
polymer based bonding agent Nitobond SBR of Fosroc or equivalent @
0.22 Lit per Sqm prior to application of polymer modified mortar with
brush after totally saturating the cleaned concrete surface with clean
water for proper bonding of old and new concrete including formwork as sqm 448.00
specified and directed by the department complete.

16.29 Plastering the surface with high rich polymer modified mortar 10mm
thick with cement sand mortar in prop. 1:4 mixed with 100% acrylic
polymer Mastercrete M-81 of Chosey chemicals or equivalent @15% by
weight of cement followed by proper curing as specified and directed by sqm 641.00
the department complete including formwork.

16.30 Concreting of the structure with nonshrink cementitious microconcrete


with properly graded 5mm to 12mm slit free aggregate with Mastergrout
CNS250 of Choksey Chemicals or equivalent, (mixing ratio CNS250 -
1part : graded 12mm down aggregate-0.6part and water/powder ratio-
0.16) with water @ 0.16 w/p ratio and poured at a super fluid
consistency only from one side to avoid air entrapment continuously cum 63484.00
without vibration followed by proper curing for minimum 7 days. as
specified and directed by the department complete including formwork.

16.31 Concreting of the structure with free flow nonshrink cementitious


microconcrete with Rendorec RG of Fosroc or equivalent after proper
mixing with cleanwater including formwork followed by proper curing for
28 days as per manufacturer's specifications complete and as directed cum 75913.00
by the Department .

16.32 Providing and laying Zinc anode unit Galvashield XP of Fosroc make or
equivalent, fixed to the reinforcement steel by means of wire ties to
allow attachment in horizontal, vertical and overhead locations with a
spacing of one piece per 0.5m c/c and ensuring good electrical
each 2268.00
continuity as per specification of manufacturer including cost of
labour,copnsumables, tools and tackles and formwork.

Page 113 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

16.33 Structural Strengthening with carbon Fibre:

(A) Patching in depression of concrete surface wherever necessary by


laying epoxy putty , Nitocote VF of Fosroc Chemicals or equivalent @ 1
Lit per sqm after proper surface preparation and proper scraping of
concrete protrusion as specified and directed by the department sqm 2143.00
complete including formwork .

(B) Applying Nitowrap 410 saturant Fosroc Chemicals or equivalent with


wet film thickness @ 250 microns (0.27Lit per sqm) over a coat of
saturant epoxy primer Nitowrap 30 of Fosroc Chemicals or equivalent @
0.11Lit per sqm with brush followed by fixing carbon fibre composite
system Nitowrap EP (CF) of Fosroc Chemicals or equivalent by
pressing on the saturant and impregnate the same by applying a final
coat of Nitowrap 410 saturant Fosroc Chemicals or equivalent as sqm 5574.00
specified and directed by the department complete including formwork.

(C) Applying two coats of UV resistant coating Nitowrap 512 of Fosroc


Chemicals or equivalent over fibre system having wet film thickness of
100 micron @ 0.11Lit per sqm as specified and directed by the sqm 571.00
department complete including formwork.

16.34 Providing & fixing 16mm dia MS nozzles in a grid of 1m c/c up to the
half of the thickness of the concrete structure.A grout slurry of neat
cement & chloride free expanding grout Mastergrout CPG-1 of Choksey
Chemicals or equivalent @ 0.5% by weight of cement water cement
ratio 0.35 to 0.40 and viscosity not more than 1.02 centipoise with
grouting pressure till the refusal of injection grout Mastergrout CPG-1.
The grouting operation pressure shall be 2Kg/sq.cm.Cutting the
Each 840.00
exposed nozzle after the grouting with a good cutter to make the
surface free from the grouting pipes and to seal the gap with plugging
compound Masterplug of Choksey Chemicals as per the specification
and the direction of the department complete including formwork.

16.35 Providing & fixing PVC pipes in a grid of 0.5m c/c throughout the crack
of the concrete structure.A low viscous Epoxy grout with Mastergrout EP
150 of Choksey Chemicals or equivalent should be inserted throughout
the crack to fill the crack.Cutting the exposed nozzle after the grouting
with a good cutter to make the surface free from the grouting pipes and
to seal the gap with the appeared crack with Epoxy putty of Choksey metre 907.00
Chemicals as per the specification and the direction of the department
complete including formwork.

16.36 Extra for fibre reinforcing concrete/mortars by providing and mixing


Recron3S (CT 2024 12mm fibre cut length / CT 2012 6mm fibre cut
length) of Reliance Industries Ltd. @ 125gms per bag (50Kg) of cement
as specified and directed by the Department complete at all levels.

(A) In concrete
(I) In M-20 grade. cum 324.00
(II) In M-25 grade. cum 376.00
(III) In M-30 grade. cum 379.00
(IV) In M-35 grade. cum 393.00

Page 114 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(B) In cement morter Plastering

(I) 1:3 (1 cement: 3 coarse sand) sqm 5.00


(II) 1:4 (1 cement: 4 coarse sand) sqm 4.00
16.37 Applying 2-coats of anti-carbonation - a protective coating Techguard
103 of Choksey Chemicals or equivalent @ 0.275 Lit per sqm with
brush over exposed portion of the concrete structure of the bridge &
other structure works etc. complete as desired to protect the reinforced
concrete by preventing the process of carbonation and directed by the sqm 322.00
department including formwork.

16.38 Applying and placing Antiwash, non-shrink, cementatious, high strength


Renderoc UW of Fosroc Chemicals or equivalent by mixing with clean
water to repair the damaged and deteriorated underwater structural
elements including formwork as per the department's instructions with cum 108504.00
labour, tools complete as specified and directed by the department
including formwork.

16.39 Drilling 14 mm dia holes on the concrete surface to a depth of 75mm


using a rotary cum hammering,drilling machine as per specification and
throughly cleaning the hole using compressed air & water jet and fixing
of shear connectors of 8mm dia and anchoring it with polyester resin
anchor grout Lokfix P of Fosroc india and as per manufacture's each 88.00
specifications.(Cost inclusive of drilling,cleaning,fixing, steel,labour,tools
and tackles)

16.40 Fabrication and fixing of steel pedestal support for bearing MT 18200.00

16.41 Providing and fixing of Foundation bolts for steel pedestals. Each 552.50

16.42 Providing and fixing of Steel plates for placing of bearings MT 58500.00

Non-destuctive testing with Ultrasonic Pulse Velocity Meter with data


storage facility for detection of cracks, voids and other imperfections in
16.43 Reinforced concrete structures and furnishing the findings thereof in Each 500.50
proper comprehensible format , complete as directed by the
department.

Non-destuctive testing with Profometer 5 Scanlog or equivalent


equipment with facility for built-in memory storage and statistical
analysis of data for detection of location and orientation of rebars in
16.44 Sqm 2145.00
Reinforced concrete structures and furnishing the findings thereof in
proper comprehensible format , complete as directed by the
department.

Non-destuctive testing with Permeability Tester, without causing


damages to the structure, for determination the water permeability and
16.45 water absorption into the near surface zone of the concrete structure Each 550.00
and furnishing the findings thereof in proper comprehensible format ,
complete as directed by the department.

Conducting PH tests on concrete stucture, as per stipulated procedures,


for determination the PH (alkalinity) of the concrete structure and
16.46 Each 88.00
furnishing the findings thereof in proper comprehensible format ,
complete as directed by the department.

Conducting Carbonation tests on concrete stucture, as per stipulated


procedures, for determination the depth of carbonation of cover
16.47 Each 88.00
concrete of the structures and furnishing the findings thereof in proper
comprehensible format , complete as directed by the department.

Page 115 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Conducting suitable tests on concrete stucture, including preparation of


samples etc. as per stipulated procedures, for determination the
16.48 chloride and sulphate concentration in the concrete of the structures Each 715.00
and furnishing the findings thereof in proper comprehensible format ,
complete as directed by the department.

Conducting Concrete Core tests of 75mm diacores, on concrete


stucture, as per stipulated procedures, for determination the equivalent
cube compressive strength, concrete of the structures including
16.49 Each 5005.00
preparation and furnishing the report showing the findings thereof in
proper comprehensible format , complete as directed by the
department.

Evaluation of Loss of pre-stress in superstructure PSC girders including


measurement of deflection by suitable instruments and necessary
16.50 calculations for estimation of the probable loss in pre-stress and Each Span 200000.00
furnishing the findings thereof in a proper comprehensible format with all
details, complete as directed by the department.

Stressing operation and grouting complete, including all accessories for


16.51 stressing of dummy cables, as per drawing and technical specifications MT 10861.00
of section 1800 of MORTH Specification of Roads and Bridge Work .

Load testing of existng foundation to ensire no void/ gap/ loose pocket


below the foundation with a total weight of 250MT (in form of sand bags
filling with locally available sand/ soil etc. placed uniformly on top of
well-cap) placed concentric & uniform w.r.t existing well foundation,
16.52 Each 70000.00
including dewatering and making arrangement with atleast 4 nos dial
gauges, for measurement of settlement of foundation during application
and release of the load, all complete as per specification as directed byb
the department.

Providing, placing and fixing in position Chemical rebar fastners (of M/s
Hilti or M/s Sika or approved equivalent conforming to Europian
standard CSTB/ETA and Civil Aid standard) of vaious diameters in
Piers, Pier caps, including drilling holes of specified size and depth,
cleaning holes, placing chemicals inside the holes and fixing reinforcing
16.53
bars as per specifications of the chemical rebar supplier, and under
supervision of the authorized representative of the supplier and
conducting pull-out test of atleast 5% of total nos. of chemical re-ba
fastners (cost of reinforcing bars to be paid seperately) all complete as
per specification as directed byb the department.

a a) 12 mm dia re-bar fastners. Each 500.00

b b) 16 mm dia re-bar fastners. Each 700.00

c c) 20 mm dia re-bar fastners. Each 750.00

d d) 25 mm dia re-bar fastners. Each 800.00

Page 116 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-17

MISCELLONEOUS ITEMS OF WORK

Bamboo Bridge
17.1 Construction of cold weather Bamboo bridge overall width of 3.70m and meter 12709.30
clear road way 3m with jungle wood post 20cm to 25cm dia 5nos. In
each rows and rows being 2.1m. apart except for the navigable span
which should be 3m. Post to be driven at least 180cm. or more below
ground level including providing 20cm to 25cm center to center and
placed over 20 cm dia, jungle wood dham, 15cm dia. jungle wood
bracing collar fixed by bolts and nuts, straps etc. mature bholuka
Bamboo cross groth all closely packed and tied 75cm wide track way
made from 38mm thick 1st class local plank fixed on 75mmx100mm first
class local wood battens 120cm apart and 3 lines of jati bamboo
horizantal railing fixed in bholuka bamboo post placed at 210cm apart
and white washed including all necessary nuts and bolts, coir ropes,
struts, nails etc. complete with a layer of brushwood to exposed portion
out-side trackway with earth topping complete as per direction of the
department.

17.2 Construction of temporary Bamboo bridge of 3.70m clear road way meter 3250.10
with Bholuka or Barua Bamboo post 5nos. in each rows driven at
least180cm. below ground level and rows not more than 150cm apart
from center to center Bholuka or Barua Bamboo dham longitudinal groth
both closely placed and tied with half bamboo 90cm to 120cm apart in
both layers and ttwo layers of jati bamboo chattais ( top layer should be
digonally woven), 70 mm to 100 mm thick brushwood in between
chattias should be tied with half jati bamboo on both ends, bamboo
railing with bholuka or barua bamboo post placed at150cm apart jati or
betua bamboo hand rails of two lines both side of every alternate
rows.All tying must be done with cane or coir string and only mature
bamboo should be used in work.

17.3 Making 120mm wide bamboo foot bridge with 100mm Bholuka or Barua meter 1014.50
bamboo posts driven 120 cm to 180 cm underground 3 Nos. in each
row and rows being 3m apart bholuka or Barua bamboo dham placed
over the posts and tied with cane or wire , Bholuka or barua bamboo
struts in each row both up and down stream, jati bamboo long gorhs
closely packed and tied with dham. Single layer of mat placed over
75mm thick brush wood and tied with bholuka or Barua bamboo rail
stand fixed in one side of the bridge etc. complete.

0 Timber Bridge
17.4 Supplying and driving timber piles of 25cm to 30cm diameter, dressed to
heart wood including making length in every 30 cm interval, coal tarring
two (2) coats with best tar applied hot (Rate inclusive of the cost of the
required quantity of tar.)
A Using Sal Timber
(a) Mechanically with Rod monkey and crab winch
(i) Portion of pile actually driven underground. meter 8363.80
(ii) Portion of pile remaining above rground. meter 8244.80
(b) Manually with labour
(i) Portion of pile actually driven underground. meter 7102.30
(ii) Portion of pile remaining above rground. meter 6993.70
B Using Azar/ Nahar/ Nageswar/ Zarul Timber
(a) Mechanically with Rod monkey and crab winch
(i) Portion of pile actually driven underground. meter 7323.80
(ii) Portion of pile remaining above ground. meter 7204.80

Page 117 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(b) Manually with labour


(i) Portion of pile actually driven underground. meter 6062.30
(ii) Portion of pile remaining above rground. meter 5953.70
17.5 Wood work including supplying , fitting and fixing complete with
necessary M.S. bolts, nuts, nails, screw etc. and coal tarring two (2)
coats with best tar applied hot (Rate is inclusive of the cost of the
required quantity of tar.)

A Using Sal Wood


(a) Underssed in floor planks, collars, bracing, standards, wheel guards, cum 3699.80
struts and railings, runner belts, rail, posts etc.
(b) In track way planks (alternate nailing to be done with decking in a cum 45673.70
seggragate way.)
B Using Azar/ Nahar/ Nageswar/ Zarul Wood
(a) Undressed in floor planks, collars, bracing, standards, wheel guards, cum 31651.90
struts and railings, runner belts, rail, posts etc
(b) In track way planks (alternate nailing to be done with decking in a cum 38380.70
seggragate way.)
17.6 Supplying, fitting and fixing timber beam and bearing beam rectangular
in size fitted with M.S. etc. supplying spikes etc. as necessary and coal
tarring two (2) coats with best tar applied hot as directed (Rate inclusive
of cost of the required quantity of tar)
(a) Using Sal Timber cum 3688.80
(b) Using Azar/ Nahar/ Nageswar/ Zarul Timber cum 31092.80
17.7 Supplying, fitting and fixing 25 cm to 30 cm dia. sal wood log beam
dressed to heartwood including supplying and fixing with 20mm dia M.S.
bolts and nuts etc.including coal tarring two (2) coats with best tar
applied hot as directed (Rate inclusive of cost of the required quantity of
tar)

(a) Using Sal Timber meter 7040.30


(b) Using Azar/ Nahar/ Nageswar/ Zarul Timber meter 6000.30
17.8 Scarfing and joining piles 25 cm to 30 cm diameter, dressed to each Joints 1476.60
heartwood of 90 cm in length includng supplying, fitting and fixing with 2
nos. of 50mm x 10mm MS FI clamps and 16 mm dia MS bolts and nuts
etc. complete as directed. (Timber for piles and coal tarring shall be
measured and paid separately.)

17.9 Labour for taking out old piles of timber bridge with necessary each 1525.70
scaffolding, jati bamboos, jumper ropes etc, complete and stacking
them at suitable places as directed.
17.10 Labour for dismantling all members of the timber bridge (excluding meter 1216.70
piles) with necessary scaffolding, jati bamboos, jumper ropes etc,
complete and stacking them at suitable places as directed (all members
will be under custody of the contractor till taken over by the department)

17.11 Labour for driving timber piles of 25cm to 30cm diameter, dressed to
heartwood marking length in every 30cm interval including coal tarring
two (2) coats with best tar applied hot including providing ncessary
scaffolding or staging (Rate inclusive of cost of the required quantity of
tar)

(a) With Rod monkey and crab winch


(i) Portion of pile actually driven under ground meter 666.30
(ii) Portion of pile remaining over ground meter 503.80
(b) By use of labour
(i) Portion of pile actually driven under ground meter 1012.40
(ii) Portion of pile remaining over ground meter 677.90

Page 118 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.12 Labour for fitting and fixing RSJ beam, CI saddle etc. in position Quintal 829.40
including necessary scaffolding, cutting them to required size, drilling
holes and supplying and fixing ncessary bolts and nuts, painting two
coats complete (Tar-Steel paints to be supplied by the contractor at his
own costs) including all lead and lifts from PWD Godown.

17.13 Labour for fitting and fixing RSJ beam, Old CI saddle etc. in position Quintal 707.40
including necessary scaffolding and fixing necessary bolts and nuts,
painting two coats complete as directed (Tar-Steel paints to be supplied
by the contractor at his own costs)

17.14 Labour for making and fitting MS F.I. Straps and cleats etc. in position Quintal 3106.90
including drilling holes complete with all lead and lifts from PWD
Godown.
17.15 Supplying fitting and fixing "U" shaped flat iron strap making 0.5m x Each 1619.50
0.3m size from 150mm x 12mm size MS flat including providing 10 bolts
holes and fitting with 0.35m long 20mm dia MS bolts including fitting
tightly with bearing beam, pile and RSJ beams etc. complete as
directed.

17.16 Labour for fitting woodwork including sizing, supplying and fixing with
new MS bolts, nuts, nails, spikes etc. and coal tarring with best tar
applied hot as directed (Rate inclusive of cost of the required quantity of
tar) complete with all lead and lifts from PWD Godown.

(a) Applying 2 (two) coats of Coal Tar cu.m. 2782.00


(b) Applying 1 (one) coats of Coal Tar cu.m. 2232.80
17.17 Labour for fitting and fixing 25cm to 30cm diameter Log Beam including
supplying and fixing necessary MS nuts and bolts etc. and coal tarring
with best tar applied hot as directed (Rate inclusive of cost of the
required quantity of tar)

(a) Applying 2 (two) coats of Coal Tar meter 584.00


(b) Applying 1 (one) coats of Coal Tar meter 394.60
17.18 Labour for talking out old woodworks of bridge and the refitting the cum 3578.90
same including supplying and fixing necessary new MS bolts, nuts,
spikes, nail etc. complete and coal tarring with best tar applied hot as
directed (Rate inclusive of cost of the required quantity of tar)

17.19 Labour for talking out old Log Beam of bridge and the refitting the same meter 322.10
including supplying and fixing necessary new MS bolts, nuts, spikes,
nail etc. complete and coal tarring with best tar applied hot as directed
(Rate inclusive of cost of the required quantity of tar)

17.20 Pile shoes : supplying fitting and fixing the pile shoes made of 6mm Each 2187.90
thick mild steel plate with necessary welding joints, size of pile shoe will
be 78.54 cm (circumferential length of at top.) x 50cm(Depth) x 5cm
(circumferential length at bottom) and 25cm inside diameter at top,
including fitting and fixing 3 (Three) nos. M.S. plate of size of 6mm x
50mm, length 45cm at top of the pile shoe with necessary welding and
drilling three nos of holes in each plate including fitting and fixing the
pile shoes at the pile end with necessary patent nails etc. , complete as
directed by the Department .The pile shoe should be camphered to fit
the pile shoe properly with necessary grooving for placing the MS plates
and pile shoe.

0 Spurs & Palasiding Works

Page 119 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.21 Single bamboo spur and palasiding of whole 2nd class bamboo (Jati or
Bethua) 65mm to 75mm dia closely packed & driven, including fitting
and fixing with half bamboo kamis horizantally in three rows with the
cane or tieing wire complete and struts 1500 mm apart longitudinally
and providing brush wood as per drawing and technical specification
clause 1302.5 of MORD

(a) Driven at least 900mm below and 1800 mm above the ground on meter 610.10
average.
(b) Driven at least 900mm below and 900 mm above the ground on meter 497.70
average
17.22 Single bamboo spur and palasiding of whole 1st class bamboo (Bholuka
or Barua) 85mm to 100mm dia closely packed & driven, including fitting
and fixing with half 2nd class bamboo (Jati or Bethua) bamboo kamis
horizantally in three rows with the cane or tieing wire complete and
struts 1500 mm apart longitudinally and providing brush wood as per
drawing and technical specification clause 1302.5 of MORD.

(a) Driven at least 900mm below and 1800 mm above the ground on meter 692.00
average.
(b) Driven at least 900mm below and 900 mm above the ground on meter 423.20
average
(c) Driven at least 900mm below and 1200 mm above the ground on meter 393.80
average
17.23 Bamboo spur 'A' type with whole bamboo placed 230mm center to
center driven 900mm below ground and 1200mm to 1500mm above the
ground tied with 2nd class bamboo (Jati or Bethua) on either side at
450mm apart horizantally with galvanized wire etc. complete as per
drawing and technical specifications.

(a) 2nd class bamboo (Jati or Bethua) 65mm to 75mm dia. meter 644.70
(b) 1st class bamboo (Bholuka or Barua) 85mm to 100mm dia. meter 527.10
17.24 Bamboo single spur 'A' type with 1st class bamboo (Bholuka or Barua) meter 905.10
85mm to 100mm dia, driven closely placed 3m to 4m above the ground
and 1.20m to 1.5m below the ground and tied with cane or coir string,
half 2nd class bamboo (Jati or Bethua) kamis horizontally on both face
placed not more than one meter apart including whole bamboo struts
inside one meter apart and 2nos. of purlin at top and bottom fitted with
vertical struts at 1500mm apart and filling with brushwood or jungle
wood inside the spur complete as per drawing and technical
specifications.

17.25 Close bamboo toe walling with 65mm to 75mm diameter bamboos of meter 728.70
length ranging from 1.2m to 3.0m driven at least 150mm c/c and
provided with three horizontal split bamboo runner fixed with nails
complete including coal tarring as directed (Rate inclusive of cost of the
required quantity of tar)

17.26 Double timber spur with two rows of 1st class local wood (Azar/ Nahar/ meter 25331.30
Nageswar/ Zarul) timber piles of 150mm to 200mm dia driven 800mm
c/c apart upto minimum 2000mm below ground and 3600mm above
ground and average placed at 800mm belt, bracing etc. of 100mm x
75mm size dia bolts and nuts etc. including coal tarring of timber
members and necessary bamboo staging etc. as directed and as per
drawing and technical specifications.

17.27 Supplying and filling up hollows of the timber spur to an average height meter 54.60
of 3600mm above the ground with jungle wood branches as directed
and as per drawing and technical specifications.

Page 120 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.28 Providing split bamboo digonally wooven lining over slope of bridges, sqm 113.40
abutement and road embakement etc. secured to the ground at least
70cm long bamboo pegs and half bamboo horizontally at 100cm center
to center both ways complete as directed.

17.29 Supplying, fitting and fixing whole Bholuka or Barua bamboo pegs
85mm to 100mm dia, closely placed all round the hollows of spur fitted
with necessary nail in the horizontal timber between 90 cm below
ground and 360cm above ground on average (timber works will be paid
for separately).

(a) For 360 cm above ground on average meter 767.60


(b) For 200 cm above ground on average meter 613.20
0 Guard Posts
17.30 Supplying, fitting and fixing RCC guard post 150cm long erected 75cm
above the ground and 75cm below the ground with M-15 grade (nominal
mix 1:2:4 with broken stone aggregate up to 20mm size) of cement
concrete and required reinforcement tied in position with annealed black
wire including centering, moulding the top, curing including painting
concrete surfaces in 23cm strips upto 0.75m from the top alternately in
black and white and having 2 nos. reflective band of desired shade etc.
complete as per design and as directed.

(a) 30 cm dia. RCC guard post with reinforcement of 6nos. 12mm dia TMT Each 2207
main steel bars and 6mm TMT/ MS stirrups at 15cm c/c.
(b) 15 cm dia. RCC guard post with reinforcement of 4nos. 12mm dia TMT Each 1072
main steel bars and 6mm TMT/ MS stirrups at 15cm c/c.
17.31 Supplying, fitting and fixing 20cm to 25cm diameter Jungle Wood Each 499.80
Dressed guard post of 150cm long erected 75cm above the ground and
75cm below the ground, fitted with horizantal struts size 50mm x 50mm
x 550mm long at bottom with necessary nails necessary etc. including
coal tarring one coat below ground and painting surfaces in 23cm strips
upto 0.75m from the top alternately in black and white and having 2 nos.
reflective band of desired shade etc. complete as per design and as
directed.

0 Earthwork by Head Load


17.32 Earthwork in filling in the guide bund by head load up to lead of 60m cum 86.9
with approved quality all leads and lifts ramming and compacting with
rammer weighing not less than 10kg and falling from height of not less
than 90cm and sprinkling with water if necessary. earth is to collected
after removing the 1st 20cm of top soil and should be free from grass,
shrubs and other foreign matter and rate will be including payment of
land compensation.

(a) Extra lead for each 30cm and part thereof beyond 60m up to a lead cum 11.5
200m.
(b) Extra lift for each 1.50m or part thereof beyond the initial lift of 1.50m cum 11.5

17.33 Earth work by head load in filling embankment in layers not exceeding
20cm thick including breaking clods, dressing and sectioning,
cambering and ramming, within a lead up to 30m and lift up to 1.5m
including payment of land conpensation for obtaining earth from private
land or govt. land as required (measurement will be on the bais of
profile or section measurement, 12.5% deduction being made on the
quantity thus arrived for shrinkage allowance.

(i) Sandy soil. cum 86.9


(ii) Ordinary soil, Basti land, Low marshy land. cum 127.7

Page 121 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

(iii) Hard soil mixed with moorum and gravel cum 155.6
(a) Extra lead for each 30m and part thereof beyond initial lead of 30m. cum 11.5

(b) Extra lift for each 1.50 m or part thereof beyond the initial lift of 1.50m cum 11.5

17.34 Earth work in core of embankment by head load with soil of approved cum 206.7
quality with a lead up to 30 m and lift up to 1.5 m in layers not exceeding
20 cm including breaking clods, dressing grading to required shape and
compacting to meet requiremenet of Table 300 - 2 (including payment of
land conpenssation for obtaining earth).

(a) Extra lead for each 30m and part thereof beyond initial lead of 30m. cum 11.5

(b) Extra lift for each 1.50 m or part thereof beyond the initial lift of 1.50m cum 11.5

17.35 Earth work in sub grade and shoulders by head load with selected soil cum 209.8
of approved quality with a lead of 30 m and lift up to 1.5 m spreading
grading to required shape and compacting to meet requirement of Table
300 -2 (including payment of land compensation of obtaining earth).

(a) Extra lead for each 30m and part thereof beyond initial lead of 30m. cum 11.5

(b) Extra lift for each 1.50 m or part thereof beyond the initial lift of 1.50m cum 11.5

0 Miscelleneous Road Pavement Works


17.36 Labour for spreading metal gravel / granular material on the road Cum 185.7
surface as directed including dressing and cambering the formation and
utilizing the loose earth in filling the depression as directed including
carriage of gravel within 30m.
17.37 Close graded Premix Surfacing using cationic Bitumen Emulsion SS-2
or Tailor made as per(IRC:SP:100-2014)
0 Providing, laying and rolling of close-graded premix surfacing material of
20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm
to 0.9 mm (Type-B) aggregates using Bitumen emulsion to required line,
grade and level to serve as wearing course on a previously prepared
base, including mixing in a suitable plant, laying and rolling with a three
wheel 8-10 kN static roller and finishing to required level and grades as
per Technical Specification Clause 509

A Manual Means
(i) Type-A sqm 150
(ii) Type-B sqm 140
0 Seal coat with Emulsion
17.38 Seal coatwith cold mix Binder (as per IRC: SP-100, 2014) Providing
and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels grade and cross fall using Type A,Type B and Type C as
per Technical specification clause 510.

A By manual means
0 Case-I: Type A (11.2mm to2.36mm)
0 Bitumen Emulsion (CRS-2) sqm 61.1
0 Case-II: Type-B (2.36mm to 180 micron)
0 Bitumen Emulsion (CSS-2) sqm 44.9
0 Case III:Type-C (9.5mm to 2.36mm)
0 Bitumen Emulsion (CSS-2) sqm 48.7
B By mechanical means
0 Case-I: Type A (11.2mm to2.36mm)
0 Bitumen Emulsion (CRS-2) sqm 59.6

Page 122 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

0 Case-II: Type-B (2.36mm to 180 micron)


0 Bitumen Emulsion (CSS-2) sqm 47.4
0 Case III:Type-C (9.5mm to 2.36mm)
0 Bitumen Emulsion (CSS-2) sqm 49.6
0 Paved Shoulder & Interlocking Concrete Block Pavement
17.39 Providing brick soling in earthen shoulder with stone/best quality jhama
brick, sand packed and laid to true line and level and in panel after
preparing the subgrade including earthwork in excavation as directed
including all labour and materials and if necessary dewatering,
complete.

(a) Bricks on flat soling, sqm 723.2


(b) Bricks on edge soling, sqm 1062.3
(c) Stone soling of thickness 150mm. sqm 647.5
17.40 Providing and laying Interlocking Concrete Block Pavement (ICBP)
conforming to IS:15658-2006 including all lead and lift complete as per
technical specification and as directed.
(a) 80mm thick interlocking precast blocks having compressive strength of sqm 805.5
40N/sq.mm.
(b) 100mm thick interlocking precast blocks having compressive strength of Sq m 1148.6
50N/sq.mm.
(c) Providing and laying M-40 grade cement concrete Edge block/ Edge cum 9514.2
restraints complete as per Technical specification clause 1504.

0 Miscelleneous Road Appurtenances


17.41 RCC Pipe Delineator Each 3046

Providing of hume pipe delineator, 250 mm in diameter, 1250 mm high,


having 25mm skin thickness filled with earth for stability up to 5 cm from
top and remaining filled with 1:3:6 c.c.in spherical segment to prevent
percolation of water and emeded in c.c. (1:3:6) below ground level up to
a depth of 500mm, 75mm thick cc surrounding the pipe, painted white
as per approved drawing.

17.42 Drum Delineator Each 743

Providing of metal drum/empty bitumen drum delineator, 600 mm in


diameter, 800 mm high, filled with earth for stability up to 5 cm from top
and remaining filled with 1:3:6 c.c. to prevent percolation of water,
painted in circumferential strips of alternate black and white 120 mm
wide all as per IRC:SP:55-2001and drawing.

17.43 Pre fabricated railing :- metre 1385.00


Providing,fitting and erecting pre fabricated railing of STRUCTURA
materials having size of 2.00x0.90M in panels made of
25x25x2.6/40x40x2.6 vertical bars and 40x40x2.6/32x32x2.6 horizontal
bars.The two end posts of each panel are founded with M-15 cement
concrete up to a depth of 200mm with anti corrosive primer and paint
etc. complete as per approved drawing and technical specification as
directed..

Page 123 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.44 Crash Barrier :-


Providing and erecting steel rails crash barrier in selected location with
vertical post of STRUCTURA WRS of size 113.50mm x 113.50mm x
4.80mm of required height above the GL attached to the gusset plate
330mm x 330mm x 25mm with nut and bolts and embeded in cement
concrete (450mm x 450mm x 750mm) in prop. 1:2:4 as per approved
and technical specification, 3.70m center to center for intermediate bay
and 3.00m for end bay, 4 nos. horizantal steel rails of size 113.50mm x
113.50mm x 4.80mm of STRUCTURA WRS to be fixed on the vertical
posts with a spacer channel section of size 113.50mm x 113.50mm x
4.80mm of STR-WRS including all fittings such as Stainless Steel
Hexagonal Head, SS washer & screw head, nylon top hat washer and
galvanized steel washer including transportation & erection etc.
complete as per approved drawing.

I Four rails System


(A) 1.50m heigh above ground level meter 7254.50
(B) 1.25m heigh above ground level meter 7199.90
II Single rail System
(A) 0.60m heigh above ground level meter 3180.50
(B) 0.75m heigh above ground level meter 3224.60
(C) 0.75m heigh above ground level both side meter 6081.60
17.45 Wire rope safety fence Barrier: Providing & erecting 4 rope wire rope meter 4372.20
safety fence barrier consisting of 4 tensioned galvanized factory
prestressed steel wire ropes of 19mm dia. constructed of 3x7 (i.e.7
wires in a strand and three strand in each rope) having tensile strength
of 1370 N/sqm with a minimum break load of 17.7 tons and supported
by 5mm thick galvanized steel posts of 'Z' section with a standard
section of 100mm x 55mm x 5mm. One upper rope is located within a
central slot in the top of the posts and three ropes interwoven along the
adjacent posts. The ropes are joined and tensioned by means of rigging
screws and the ends of the ropes are attached to anchors embeded in
the ground or surface mounted. The top wire shall be 930 +_30 from
ground level to centre of wire and the posts shall be placed maximum
3.2 mtrs c/c including all end rope anchors, terminals, check ropes, tail
ropes, soft eye connecting with D-Shackle complete as per technical
specifications and as directed.

0 Reinforced Earth Retaining Walls


17.46 Construction of Reinforced Earth Retaining Walls with plain finished sqm 2452.80
cruciform shaped precast concrete facing panels in M 35 grade
concrete, 18 cm thick, including High Adherence Structural Reinforcing
40 X 5mm section strips ( hot dip galvanised) with bearing pads, joint
fillers, tie strips, fastener and all accessories and consumable complete
as per technical specification and drawing.

17.47 Earth work including excavation, backfilling, grading and compaction cu.m. 165.90
with selected backfill soil in layers in Reinforced Earth works as per
Technical specification and drawings.
17.48 Construction of PCC strips level footing (35cm X 15cm) in M-15 grade meter 327.60
concrete complete as per technical specification and drawing.

17.49 Providing 600mm drainage bay behind RE wall with compacted granular cum 1256.90
material as per technical specification and drawing.
17.50 Construction of crash barrier, parapet, coping beam with friction slab in meter 1742.60
M-30 grade concrete complete as per technical specification and
drawing.

Page 124 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

0 Miscelleneous Embankment Protection


17.51 Providing approved variety of vetiver plantation certified by The Vetiver
Network International (TVNI) or its affiliate in India including pouching of
tiller with selected soil for agricultural use mixed with farmyard manure
in 8”x 6” poly pouch, maintaining the pouched plants for at least 1(one)
month with application of growth promoter, fertilizer, watering, weeding
etc., dressing of the area of plantation, planting the pouched plants as
per design approved by The Vetiver Network International (TVNI) or its
affiliate in India. (Excluding jungle clearance, earth work in trimming,
cutting, filling etc.) and Maintenance of the vetiver plants by watering,
pruning, weeding, mulching, application of manure, fertilizer, growth
promoter etc. for 4 (four) months after completion of plantation.

0 Part-1 Plantation Part metre 102.90


0 Part-II Maintenance part metre 33.60
17.52 Labour for laying apron with man size boulders by hand packing the cum 1282.60
stone with dry stone masonry template crosswalls to ensure regular and
orderly deposition of the full intended quality of stone in the apron
including labour for buildung these walls about one meter thick and to
the full height of the specific thockness of the apron at interval of 30
meters all along the length of the apron with local carriage of stone
within 60 meters complete.

17.53 Stone masonry work. Uncoursed rubble masonry work in all retaining cum 5537.40
wall, wing wall, abutement etc. in cement mortar 1;6 withoutside face
stone roughly hammer dressed and inside (earthen side ) undressed as
per drawing and technical sopecifications including racking out joints
and curing , supplying and carriage of stone as directed.

0 Soil Stabilization
17.54 Providing, laying, spreading and compacting available clay soil in Sub- cum 4048.80
grade course including in situ mixing 30% Stone Dust, 70% Soil & 4% of
RBI 81 product, spreading in uniform layers with motor grader on a
prepared base including watering and compacting with 8 to 10 tonne
vibratory power roller to achieve the desired density including all
materials, labour, HOM of machinery, etc complete as per
specifications.

17.55 Providing, laying, spreading and compacting available soil (excluding cum 4635.80
clay soil) and aggregate in base course including in situ mixing 30%
Aggregate, 70% Soil & 4% of RBI 81 product, spreading in uniform
layers with motor grader on a prepared base including watering and
compacting with 8 to 10 tonne vibratory power roller to achieve the
desired density including all materials, labour, HOM of machinery, etc
complete as per specifications.

17.56 Providing, laying, spreading and compacting available soil in base cum 4909.80
course including in situ mixing 30% Aggregate, 20% Stone Dust, 50%
Soil & 4% of RBI 81 product, spreading in uniform layers with motor
grader on a prepared base including watering and compacting with 8 to
10 tonne vibratory power roller to achieve the desired density including
all materials, labour, HOM of machinery, etc complete as per
specifications.

0 Miscelleneous Bridge Works


17.57 Providing and constructing temporary island for construction of pile each 55825.40
foundation with depth of water upto 4.0m complete as per technical
specification.

Page 125 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.58 Providing and constructing temporary island for construction of well


foundation complete as per technical specification.
(a) For 6m dia. Well
(i) Depth of water above 1.0 m upto 2.0 m each 114203.30
(ii) Depth of water above 2.0 m upto 3.0 m each 145075.40
(iii) Depth of water above 3.0 m upto 4.0 m each 164178.00
(b) For 7m dia. Well
(i) Depth of water above 1.0 m upto 2.0 m each 124097.40
(ii) Depth of water above 2.0 m upto 3.0 m each 159964.40
(iii) Depth of water above 3.0 m upto 4.0 m each 193706.10
(c) For 8m dia. Well
(i) Depth of water above 1.0 m upto 2.0 m each 133555.80
(ii) Depth of water above 2.0 m upto 3.0 m each 170298.50
(iii) Depth of water above 3.0 m upto 4.0 m each 207321.50
17.59 Greasing of Bearing with ULTRATACK AP3 grease including cleaeing of each 1225.40
bearings with steel brush, removal of dusts and dirt with necessary
scaffolding etc. complete as directed by the department.

0 Geo-Bags
17.60 Supplying, filling and laying in loose with Geo-textile bags of Type-A
(1.30x0.70 M) made of Geo textile non woven fabric sheets of 400 GSM
manufactured from polyster/ polypropylene conforming to relevant ISO
standard filled with specified sand/ silt from flood plain or adjacent char
within a distance of 90 m of the work site including excavation, filling
Geo bags with sand weighing 126.00 kg after filling, stitching the mouth
of the filled bags with polypropylene or polyster complete as per
technical specifications and as directed.

(a) With Boat Bag 313


(b) Without Boat Bag 301
17.61 Supply, Stitching and Laying of Non wooven Geo textile Fabric sheet of Sqm 223
400 gsm
17.62 Supplying, filling and laying in cages with Geo-textile bags of Type-A
(1.30x0.70 M) made of Geo textile non woven fabric sheets of 400 GSM
manufactured from polyster/ polypropylene conforming to relevant ISO
standard filled with specified sand/ silt from flood plain or adjacent char
within a distance of 90 m of the work site including excavation, filling
Geo bags with sand weighing 126.00 kg after filling, stitching the mouth
of the filled bags with polypropylene or polyster thread by power driven
double needle machine, stacking the same in batches of 100, carrying
the same to the dumping site including all handling charges and local
carriage within a distance of 150m and laying properly in cages of PVC
coated G.I.Gabion box of size 1.5m x 1.5m x 0.45m complete as per
technical specifications and as directed.

(a) With Boat Cage 1039


(b) Without Boat Cage 687
17.63 Earthwork in excavation in key cage of size 1.00m x 1.00m x 1.00m for Cum 3641
anchoring geo fabrics mat including supply and filling of geo bags (bags
are filled with sand/silt from flood plain or adjacent char within a
distance of 90 m of the work site), filling geo bags with sand weighing
126kg after filling, stitching mouth with polyster/ polypropylene thread by
power driven double needle machine, carrying the same to the site
including all handling charges and local carriage from a distance of
150m complete as per technical specifications and as directed.

Page 126 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.64 Supplying, laying, fitting and fixing g-mat in doubled layer composite Sqm 2394.00
geo textile fabricated to form a three dimensional mattresses after filling
sand by pump, the upper layer of mattress being heavily woven with
polyproplyne fabric needle punched with a mixture of U.V. stabilized
green fibres and cut tape yarns (Typical value of mass per unit area
ASTM D5261) is 650g/sqm, tensile strength (ASTMD4595)is 45kn/m,
pore size (ASTMD4751) is less than 0.35mm and UV stability (strength
retained per ASTMD4355-92 @ 500hrs is 80%) the lower layer of the
mattress being polypropyline wooven fabric, UV stabilized (Typical value
of mass per unit area (ASTM D 4595) is greater than 80kn/m, pore size
(ASTMD4751) is less than 0.35mm and UV stability (strength retained
per ASTM4355-92 @ 500hrs is 80%). The sewing thread being of high
tenacity polyster, continued parrell stitches positioned 350mm apart with
a stitch length not exeeding 40mm anchoring by cutting trenches of
1.5m x 1m placing the mat filling earth filled cement bags anchorage at
lower end, double locking chain stitch 3 stitch/inch including all charges
complete. (Approved rate of CWC for the FMP scheme under WRD)

0 Repairing of Boat
17.65 Labour for haulding up boat and refloating the same after repair
(a) Mar boat each 3559.50
(b) Single boat each 1772.40
17.66 Renewing rotton planks of boat with 25 mm to 38 mm thick timber
planks including supplying and fitting with necessary nail etc. including
coat tarring two coats applied hot.
(a) With Sal planks sq.m 2618.70
(b) With Cham or Lorul planks sq.m 2163.00
17.67 Making good cracks of the joint boat with necessary jute mixed with metre 31.50
putty of dhuna and flat nails including coaltarring after taking out old
nails, rotten jute etc.
17.68 Supplying, fitting and fixing kori (for boat) of wood of required sizes.

(a) With Sal timber each 2679.60


(b) With cham/sundi/nageswar/gamari timber each 1892.10
17.69 Supplying sal wood helm for marboat 18cm dia 6.10m as per direction each 5989.20
including fixing in position and coal tarring complete as
directed.cham/nageswar wood helm for mar boat 13cm dia. 6.10m long
as per direction including fixing in position and coal and coal tarring as
directed.

17.70 Supplying cham/nageswar wood helm for mar boat 13cm dia. 6.10m each 3390.50
long as per direction including fixing in position and coal and coal tarring
as directed.
17.71 Renewing oars of wood plank complete as directed.
(a) Of Sal wood each 1021.70
(b) Of Cham wood each 836.90
17.72 Supplying fitting and fixing in position koniaghosa of required size of
wood to fit exactly at boat and coal tarring etc. complete as directed.

(a) Sal wood each 294.00


(b) Cham/ Sundi/ Gamari wood each 211.10
17.73 Repariring or providing timber free board line 8cm by 5cm painted white
with two coats of approved paint complete as directed.

(a) With Sal timber metre 231.00


(b) With Cham/ Sundi/ Gamari timber metre 180.60

Page 127 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

17.74 Refitting drop gates with necessary hinges, spikes, bolts and nuts etc. set of two 417.90
complete up to 6 tonne mar boat.
17.75 Refitting drop gates with necessary hinges, spikes, bolts and nuts etc. set of two 587.00
complete above 6 tonne mar boat.

Page 128 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

CHAPTER-18

NEW TECHNOLOGY

18.1 Open - Graded Premix Surfacing (specially for shaded areas)


Providing, laying and rolling of open - graded premix surfacing of 20 mm sqm 177
thickness composed of 13.2 mm to 5.6 mm aggregates either using
Bitumen Emulsion With cold mix Binder Ezee PC (MS) (As per IRC : SP
: 100 -2014) to required line, grade and level to serve as wearing course
on a per Technical Specification and through credible technology
partners duly licensed by CRRI.

18.2 Seal coat with Cold mix Binder (specially for shaded areas) - Providing sqm 34
and laying seal coat sealing the voids in a bituminous surface
laid to the specified levels grade and cross fall using Type
A,Type B and Type C as per Technical specification clause
510.With cold mix Binder Ezee PC (MS) (As per IRC : SP : 100
-2014)and through credible technology partners duly licensed by
CRRI.

18.3 Construction of Sub-Base/Base of road pavement by making use of


EVOCRETE CCL Soil Modifier (GERMAN) technology by re-
using the existing/in-situ soil. Profiling the road to the required
design standard followed by spreading of 7% of O.P.C. 43
Grade cement of stabilized soil (Variable depending upon soil
properties) , then spreading 2 % EVOCRETE additive of 7 %
OPC and pulverising the cement , additive & profiled
soil/pavment material with help of Recycler/Stabilizer including
moisturing to OMC. On completion of pulverisation re-garding,
profiling to required grade/camber with motor grader &
compacting simaltaneously with 14 tonne vibratory roller to
achieve 95% degree of compaction as directed by the Engineer-
in-charge & finally irrigating the stabilized surface for next 48
hours.

I 20.0cm thick Sub-Base & Base with Evocrete and Cement etc. cum 3410
18.4 Bio Enzyme Soil Stabilizer Terrazyme under IRC accredited new
Technology
I Providing of 1st layer of Bioenyme based soil stabilised layer to a cum 1458
required thickness as per manufacture design with a existing soil, by
ripping open the existing road formation and treating it with TerraZyme
in the ratio 1L for 12.6 cum soil spreading in uniform layer with motor
grader on prepared surface , mixing by mix in place method with
rotavator at OMC and compacting with smooth wheel roller to achieve
the desired density complete as per technical specification incl all labour
, equipments etc as per direction of the Engineer -in -charge of the
work. The soil will have PI between 7 and 18% and clay % by
hydrometry should be more than 15% and less than 40%.

Page 129 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

II Providing of 2nd layer of Bioenyme based soil stabilised layer to a cum 1656
required thickness as per manufacture design with local soil
material/gravel/murram, having CBR greater than 8% and treating it with
Terrazyme in the ratio 1L for 15.0 cum soil with 25% 40mm crusher
broken metal in design mix, spreading in uniform layer with tractor
grader on prepared surface, mixing by mix in place method with
rotavator at OMC and compacting with smooth wheel roller to achieve
the desired densiality complete as per technical specification including
all labour, materials like soil and metal, equipments etc. complete as
per direction of the Engineer-in-charge of the work. The soil will have PI
between 7 and 13% and clay % by hydrometry should be more than
15% and less than 30%.

18.5 Soil Stablized subbase/ base using Roadstab


I Providing of soil stabilized subase/base course by providing,laying and cum 3946
spreading ordinary soil on a prepared subgrade,palverising,adding the
designed quantity of Roadstab mixing compound adding 4% cement,
mixing at OMC,with rotavator grading with motor grader and compacting
with the road roller/vibratory roller at OMC to acheive the desired
unconfined compression strength and to form a layer of subbase and
necessary curing

18.6 RBI Grade 81 Treated Base Layer


A For Selected soil having CBR 5% to 6%
I Providing, laying, spreading and compacting Soil conforming to cum 4688
engineering requirement and Aggregate in base layer including in situ
mixing of 30% Aggregatesof size 22.4 mm to 2.56 mm (for WMM as per
page 154 of Assam SOR 2016-17 for rural road & table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 20%
Stone dust+46% in-situ soil (CBR 5% to 6%) + 4% RBI Grade-81 (a soil
stabilizer cum pavement material) , speading in uniform layers with
motor grader on prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the required
density at OMC for preparing the base layer including all cost of
materials , labour, HOM of machinery, etc. complete as per
specifications and EIC directions.

B For Existing In-situ soil having CBR 5% to 6%

Page 130 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Providing, laying, spreading and compacting including mixing of In-situ


Soil (CBR 5% to 6%), Aggregate size 22.4 mm to 2.56 mm (for WMM as
per page 154 of ASSAM SOR 2016-17 for Rural Roads and Table
400.13 & Technocal Specification clause 406 of MORT&H 5th Revision)
and Stone Dust with Soil Stabiliser and Pavement Material RBI Grade
81 (SRSPL), spreading in uniform layers with motor grader on prepared
sub-base / sub-grade including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the desired density for
preparing the Base / Sub-base layer.

Including basic
cost of materials, labour, HOM of machinary, etc. as per
specifications and EIC directions.
The rate mentioned here are
exclusive of carriage charge of Aggregates / Stone Dust /
Selected Soil from quarry to site. The carriage charge will be
added to these rates to arrive at final rate.
Various
combinations of Aggregates, Stone Dust Insitu Soil and RBI
grade 81 percentages have been given. The optimum
combination would depend upon the following factors:

1. In Situ Soil CBR and PI.


2.
Traffic Catagory.
3. Distance of Quarry from Site
For
further increasing the durability of the road, out of the
combinitations as bellow the combination with higher percentage
of RBI Grade-81 should be prepared so long as commercial
I Providing, laying, spreading and compacting Soil conforming to cum 4771
engineering requirements and Aggregate in base layer including in situ
mixing of 30% Aggregate of size 22.4 mm to 2.56 mm ( for WMM as per
page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 30%
Stone Dust + 36% In-Situ Soil (CBR 5 % to 6 %) + 4 % RBI Grade-81 (a
soil stabilizer cum pavement material), spreading in uniform layers with
motor grader on a prepared base including watering and compacting
with 10 to 12 tonne single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as per specifications
and EIC directions

II Providing, laying, spreading and compacting Soil conforming to cum 4688


engineering requirements and Aggregate in base layer including in situ
mixing of 30% Aggregate of size 22.4 mm to 2.56 mm ( for WMM as per
page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 20%
Stone Dust + 46% In-Situ Soil (CBR 5 % to 6 %) + 4 % RBI Grade-81 (a
soil stabilizer cum pavement material), spreading in uniform layers with
motor grader on a prepared base including watering and compacting
with 10 to 12 tonne single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as per specifications
and EIC directions

Page 131 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

III Providing, laying, spreading and compacting Soil conforming to cum 4549
engineering requirements and Aggregate in base layer including in situ
mixing of 30% Aggregate of size 22.4 mm to 2.56 mm ( for WMM as per
page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 30%
Stone Dust + 36.25 % In-Situ Soil (CBR 5 % to 6 %) + 3.75 % RBI
Grade-81 (a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base including watering
and compacting with 10 to 12 tonne single drum vibratory roller to
achieve the required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery, etc complete
as per specifications and EIC directions

IV Providing, laying, spreading and compacting Soil conforming to cum 4466


engineering requirements and Aggregate in base layer including in situ
mixing of 30% Aggregate of size 22.4 mm to 2.56 mm ( for WMM as per
page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 20%
Stone Dust + 46.25% In-Situ Soil (CBR 5 % to 6 %) + 3.75 % RBI
Grade-81 (a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base including watering
and compacting with 10 to 12 tonne single drum vibratory roller to
achieve the required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery, etc complete
as per specifications and EIC directions

V Providing, laying, spreading and compacting Soil conforming to cum 4327


engineering requirements and Aggregate in base layer including in situ
mixing of 30% Aggregate of size 22.4 mm to 2.56 mm ( for WMM as per
page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 30%
Stone Dust + 36.5 % In-Situ Soil (CBR 5 % to 6 %) + 3.5 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading in uniform layers
with motor grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory roller to achieve
the required density at OMC for preparing the base Layer Including all
cost of materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

VI Providing, laying, spreading and compacting Soil conforming to cum 4244


engineering requirements and Aggregate in base layer including in situ
mixing of 30% Aggregate of size 22.4 mm to 2.56 mm ( for WMM as per
page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision) + 20%
Stone Dust + 46.5% In-Situ Soil (CBR 5 % to 6 %) + 3.5 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading in uniform layers
with motor grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory roller to achieve
the required density at OMC for preparing the base Layer Including all
cost of materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

VII RBI GRADE 81 - 2%

Page 132 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

Providing, laying, spreading and compacting Soil conforming to cum 2828


engineering requirements and Aggregate in sub base layer including in
situ mixing of 30% Aggregate of size 22.4 mm to 2.56 mm (for WMM
item in ASSAM SOR 2017-18 for rural roads & Table 400.13 & technical
specification clause 406 of MORTH 5th Revision) + 20% Stone Dust +
48% In-Situ Soil (CBR 5 % to 6 %) + 2 % RBI Grade-81 (a soil stabilizer
cum pavement material), spreading in uniform layers with motor grader
on a prepared base including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the required density at
OMC for preparing the base Layer Including all cost of materials,
labour, HOM of machinery, etc complete as per specifications and EIC
directions

C For Selected Soil Having CBR 7% to 9%


RBI GRADE-81 - 4%
Providing , laying spreading and compacting inncluding in situ mixing of
selected soil (CBR 7% to 9%), Aggregate of size 22.4 mm to 2.56 mm
(for WMM as per page 154 of ASSAM SOR 2016-17 for rural roads &
Table 400.13 & technical specification clause 408 of MORTH 5th
Revision) & Stone Dust with Soil Stabilizer and PavementMaterial RBI
Grade 81 (SRSPL) , spreading in uniform layers with Motor grader on a
prepared subbase including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the desired density for
preparing the base layer including basic cost of materials, labour,HOM
of machinearyetc, complete as per specification and EIC directions.
The rates mentioned here are Exclusive of carriage charges for
Agrregate/ Stone Dust/ Setected Soil from quarry to site . The carriage
charges will be added to these rates to arrive at final rate.
Various combinations of in-situ soil/selected soil, aggregate and RBI
percentages have been given, The optimum combination would depend
upon the following factors:
1. In-situ soil/selected soil (as applicable), CBR, and PI
2. Traffic Category
3. Distance of Quarry from site

I Providing, laying, spreading and compacting Soil conforming to cum 4817


engineering requirements and Aggregate in base course including in
situ mixing of 45 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 51 %
Selected Soil (CBR 7 % to 9 %) + 4 % RBI Grade-81 (a soil stabilizer
cum pavement material), spreading in uniform layers with motor grader
on a prepared base including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the required density at
OMC for preparing the base Layer Including all cost of materials,
labour, HOM of machinery, etc complete as per specifications and EIC
directions

Page 133 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

II Providing, laying, spreading and compacting Soil conforming to cum 4647


engineering requirements and Aggregate in base course including in
situ mixing of 30 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 15 %
Stone Dust + 51 % Selected Soil (CBR 7 % to 9 %) + 4 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading in uniform layers
with motor grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory roller to achieve
the required density at OMC for preparing the base Layer Including all
cost of materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

III Providing, laying, spreading and compacting Soil conforming to cum 4595
engineering requirements and Aggregate in base course including in
situ mixing of 45 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 51.25
% Selected Soil (CBR 7 % to 9 %) + 3.75 % RBI Grade-81 (a soil
stabilizer cum pavement material), spreading in uniform layers with
motor grader on a prepared base including watering and compacting
with 10 to 12 tonne single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as per specifications
and EIC directions

D RBI GRADE-81 - 3.75%


I Providing, laying, spreading and compacting Soil conforming to cum 4426
engineering requirements and Aggregate in base course including in
situ mixing of 30 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 15 %
Stone Dust + 51.25 % Selected Soil (CBR 7 % to 9 %) + 3.75 % RBI
Grade-81 (a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base including watering
and compacting with 10 to 12 tonne single drum vibratory roller to
achieve the required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery, etc complete
as per specifications and EIC directions

II Providing, laying, spreading and compacting Soil conforming to cum 4373


engineering requirements and Aggregate in base course including in
situ mixing of 45 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 51.5 %
Selected Soil (CBR 7 % to 9 %) + 3.5 % RBI Grade-81 (a soil stabilizer
cum pavement material), spreading in uniform layers with motor grader
on a prepared base including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the required density at
OMC for preparing the base Layer Including all cost of materials,
labour, HOM of machinery, etc complete as per specifications and EIC
directions

RBI GRADE-81 - 3.5%

Page 134 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

III Providing, laying, spreading and compacting Soil conforming to cum 4203
engineering requirements and Aggregate in base course including in
situ mixing of 30 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 15 %
Stone Dust + 51.5 % Selected Soil (CBR 7 % to 9 %) + 3.5 % RBI
Grade-81 (a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base including watering
and compacting with 10 to 12 tonne single drum vibratory roller to
achieve the required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery, etc complete
as per specifications and EIC directions

RBI GRADE-81 - 2%
IV Providing, laying, spreading and compacting Soil conforming to cum 2787
engineering requirements and Aggregate in base course including in
situ mixing of 30 % Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural roads & Table 400.13
& technical specification clause 406 of MORTH 5th Revision) + 15 %
Stone Dust + 53 % Selected Soil (CBR 7 % to 9 %) + 2 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading in uniform layers
with motor grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory roller to achieve
the required density at OMC for preparing the base Layer Including all
cost of materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

E 40% AGGREGATE 20MM + SOIL (CBR 7% TO 9%) + RBI GRADE-


81(SRSPL)
Providing,laying,spreading and compacting including in situ mixing of
selected soil aggregate of size 20mm with soil stabiliser and pavemebt
material RBI Grade-81 (SRSPL), spreading in uniform layers with Motor
grader on a prepared sub base icluding watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the desired density
for preparing the base layer. Including basic cost of materials, labour,
HOM machinery,etc complete as per specifications and EIC directions.
The rates mentioned here are exclusive of carriage charges for
aggregate/stone dust/selected soil from quarry site. Various
combinations of in-situ soil/selected soil(as applicable),aggregate and
RBI percentages have been given. The optimum combination would
depend upon the following factors :
1. In situ soil/selected soil (as applicable) CBR and PI
2. Traffic category
3. Distance of quarry from site

I Providing, laying, spreading and compacting Soil conforming to cum 4963


engineering requirements and Aggregate in base course including in
situ mixing of 40% Aggregate (20 mm) + 56% Soil (CBR 7% to 9%) with
4 % RBI Grade-81 (a soil stabilizer cum pavement material), spreading
in uniform layers with motor grader on a prepared base including
watering and compacting with 10 to 12 tonne single drum vibratory roller
to achieve the required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery, etc complete
as per specifications and EIC directions

Page 135 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

II Providing, laying, spreading and compacting Soil conforming to cum 4741


engineering requirements and Aggregate in base course including in
situ mixing of 40% Aggregate (20 mm) + 56.25% Soil (CBR 7% to 9%)
with 3.75 % RBI Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne single drum
vibratory roller to achieve the required density at OMC for preparing the
base Layer Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

III Providing, laying, spreading and compacting Soil conforming to cum 4520
engineering requirements and Aggregate in base course including in
situ mixing of 40% Aggregate (20 mm) + 56.5% Soil (CBR 7% to 9%)
with 3.5 % RBI Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne single drum
vibratory roller to achieve the required density at OMC for preparing the
base Layer Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

IV Providing, laying, spreading and compacting Soil conforming to cum 3104


engineering requirements and Aggregate in sub base layer including in
situ mixing of 40% Aggregate (20 mm) + 58% Soil (CBR 7% to 9%) with
2% RBI Grade-81 (a soil stabilizer cum pavement material), spreading
in uniform layers with motor grader on a prepared base including
watering and compacting with 10 to 12 tonne single drum vibratory roller
to achieve the required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery, etc complete
as per specifications and EIC directions

18.7 Providing, laying, spreading and compacting including in situ mixing of cum 2589
In-Situ 94 % Soil + 4 % PI Reducing Agent with 2 % RBI Grade-81 (a
soil stabilizer cum pavement material), spreading in uniform layers with
motor grader on a prepared including watering and compacting with 10
to 12 tonne single drum vibratory roller to achieve the desired density
for preparing the Sub Base/Subgrade.
Including basic cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions.

18.8 Providing, laying, spreading and compacting including in situ mixing of cum 2969
In-Situ 93.5 % Soil + 4 % PI Reducing Agent with 2.5 % RBI Grade-81
(a soil stabilizer cum pavement material), spreading in uniform layers
with motor grader on a prepared including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the desired density
for preparing the Sub Base/Subgrade.
Including basic cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions.

18.9 Providing, laying, spreading and compacting including in situ mixing of cum 1988
98 % In-Situ Soil (PI < = 10) with 2 % RBI Grade-81 (Soil Stabiliser and
Pavement Material ), spreading in uniform layers with Motor grader on a
prepared surface including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the desired density for preparing
the Subgrade.
Including basic cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions .

Page 136 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

18.10 Providing, laying, spreading and compacting including in situ mixing of cum 2368
97.5 % In-Situ Soil (PI < = 10) with 2.5 % RBI Grade-81 (Soil Stabiliser
and Pavement Material ), spreading in uniform layers with Motor grader
on a prepared surface including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the desired density for
preparing the Subgrade.
Including basic cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions .

18.11 Providing, laying, spreading and compacting including in situ mixing of cum 1988
98 % Selected Soil (PI < = 10) with 2 % RBI Grade-81 (Soil Stabiliser
and Pavement Material ), spreading in uniform layers with Motor grader
on a prepared surface including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the desired density for
preparing the Subgrade.
Including basic cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions .

18.12 ZYCOSOIL NANO TECHNOLOGY


A Water Proofing
I Waterproofing on top compacted ( as per relevant MoRD specification) sqm 15
sub Grade soil base, shoulders with Organosilane Nanotechnology &
nano acrylic co-polymer with water (<1000 ppm TDS) in the ratio of 1 kg
Organosilane Nanotechnology:1 kg nano acrylic co-polymer :200 liter
water spray @ 3 liter /sqm in two spray applications (1.5 liter + 1.5 liter)
as per direction of the Engineer-in-charge.

II Stabilized Sub-base / Base: Providing, Laying, Spreading and cum 2372


Compacting in-situ/borrow area soil of CBR >5% mixed with /
without 30% crushed aggregate / muruum / GSB Grade 1 as per
mix design.
Application:
(1) Rip and loosen soil with excavator / tractor operated ripper
and scarify with tractor operated rotavator upto depth of 200
mm. Mix aggregates as per mix design.
(2) Apply 1 kg /cum organosilane Nanotechnology mixed in
OMC water (<1000 ppm TDS) on loose soil. Scarify the treated
and allow it to dry.
(2) Spread Cement 3% by weight of soil on the silane treated
and dry soil.
(3) Apply 1 kg/cum of nano acrylic Co-Polymer mixed in OMC
water (<1000 ppm TDS), on the above treated soil mixed with
cement. Scarify and grade the soil.
(4) Spread 13.2 and down size aggregates on the graded soil
surface to form 20-25 mm thick soil-aggregate layer.
(5).Compact the stabilized soil-aggregate base with 8 to 10
tonne vibratory roller to achieve stone embedded layer with the
desired density.
(6) Waterproof the top of the compacted stabilized base with
organosilane & nano acrylic Polymer in the ratio of 1 kg
organosilane :1 kg nano acrylic Co-Polymer : 200 liter water
(<1000 ppm TDS) @ 3ltrs/sqm in two spray applications (1.5 ltrs.
+ 1.5 ltrs.).
Rates include all material, labour, hire charges of machinery etc.
as per MoRD specifications & direction of Engineer-in-Charge.

Page 137 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

III Prime Coat (with silane Nanotechnology)


(i) Low porosity
Prime Coat : Preparing and applying of water soluble organo sqm 22
silane nanotechnology (for bitumen emulsion application, IRC
approved) with cationic bitumen emulsion CSS1 and water
(<1000 ppm TDS) in the ratio of 1 kg organo silane : 100 kg
cationic bitumen emulsion CSS1 : 200 liter water . Mixing &
Spraying : Take 1 kg of organo silane nanotechnology and add
in 200 liter water while filling water in tanker/drum and then add
100 kg cationic bitumen emulsion under circulation. Mix the
solution completely. Spray the solution @ 1 liter per sqm on
compacted stone base. Rates including all materials, labour, hire
Charges of machery etc. complete as per MoRD specifications &
direction of Engineer-in-Charge.

18.13 20mm thick Open-Graded Premix Carpet using Bituminous (penetration


grade) Binder Using Nanotechnology.( Providing, laying and rolling
of open-graded premix carpet of 20 mm thickness composed of
13.2 mm to 5.6 mm stone aggregates using S-65 penetration
grade bitumen mixed with silane nanotechnology @ 0.1% by
weight of bitumen S-65 grade @ 14.6 kg/10 sqm to required line,
grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable hot mix plant,
laying and rolling with a three wheel 80-100 kN static roller
capacity, finished to required level and grades to be followed by
seal coat of Type D as per Technical Specification Clause 508
of MoRD and as per direction of Engineer-in-Charge.)

Bitumen (S-90) sqm 140


18.14 Seal Coat( with Nanotechnology) (Providing and laying seal coat
sealing the voids in a bituminous surface laid to the specified
levels, grade and cross fall using Type D as per Technical
Specification Clause 510 of MORD with S-65grade bitumen
mixed with organosilane nanotechnology @ 0.1% by weight of
S-65 bitumen binder laid as per direction of Engineer-in-
Charge.)

A By Mechanical Means
I Case -3 : Type C: Bitumen (S-90) sqm 50
18.15 EVOCRETE TECHNOLOGY
A Stabilization/soil binding of in-situ soil of sub-base/base course using
EvocreteCCL soil stabilizer (Construction of Sub-Base/Base of road
pavement by making use of EVOCRETE CCL Soil Modifier
(GERMAN) technology by re-using the existing/in-situ soil.
Profiling the road to the required design standard followed by
spreading of 7% of O.P.C. 43 Grade cement of stabilized soil
(Variable depending upon soil properties) , then spreading 2 %
EVOCRETE additive of 7 % OPC and pulverising the cement ,
additive & profiled soil/pavment material with help of
Recycler/Stabilizer including moisturing to OMC. On completion
of pulverisation re-garding, profiling to required grade/camber
with motor grader & compacting simaltaneously with 14 tonne
vibratory roller to achieve 95% degree of compaction as directed
by the Engineer-in-charge & finally irrigating the stabilized
surface for next 48 hours)

Page 138 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

I 20.0cm thick Sub-Base & Base with Evocrete and Cement etc. cum 3441
18.16 Cell Filled Concrete Pavement
I Construction of plastic cell filled cement concrete pavement, thickness
100mm (as per design), over a prepared sub base, with 53 grade
Ordinary Portland Cement(OPC) or any other type as per Clause
1501.2.4 M30 (Grade), coarse and fine aggregates conforming to IS :
2386, mixing in a concrete mixer of not less than 0.2 cum capacity and
appropiate weigh batcher using approved mix design (As per IRC:44-
2008), laid in the cells made of high density polythyne sheets of
thickness 0.22mm to about 0.25mm,side 150mm and depth 100mm of
approximate weight of 1250 kg for a road of 3.75m wide and 1.00km ,
putting iron spike of 200mm long at the end corners of the cells and
using nylon threads passing through the cells 10 mm below the top of
the cells, in approved fixed side formwork (steel channe, wedges, steel
plates including levelling the formwork as per drawing),maitaining
camber of about 3 to3.5%, spreading the concrete with sholvels, rakes,
compacted using needle, scareed and plate vibrators and finished in
continuous operation, curing of concrete slabs for 14- days, curing
compound (where specified) and water finishing to lines and grade as
per drawing and Technical Specification of Cell filled Concrete
Pavement Published by NRRDA

a Rate analysis is being carried out for Cell filled concrete pavement of sqm 903
3.75m and 25m in width and length. As per the requirement of DIY on
cell filled concrete block, the following are the requirements for a
pavement of 3.75m and 25m in width and length that can be
constructed in one day:
*200 micron plastic sheet-1 kg=28 meter long of 10cm width-
(1.75 sq.m/kg-53.57 Kg for 3.75mx25m)
*Labour approximately
*Male workers 20
Female workers 7
Mason 4
1 number concrete mixer
Plate or screed vibrator - 1 no.
Mechanical trowelling - 1 no.
Max. 25meter length(of width 3.75meter) can be laid in a day
(about 10 Cum of CC)

18.17 TENAX 3D GRID TECHNOLOGY


I Supplying and laying of Polypropylene extruded Geogrid with a sqm 157
minimum stiffness (modulus) at 0.5% strain according to ISO 10319
should be 350x550 Kn/m with apparaent coefficient of friction
soil/geosynthetics accroding to EN 13738 must be atleast 1.70(us/gsy)
at 10 KPa load and with a min transversal rib thickness of 2.5 mm and
longitudinal rib thickness of 3.6 mm. Aperture of geogrid should be
30mm x 30 mm. Geogrid should not be made of bonding of strands or
punching and stretched sheets

18.18 Recycling of Bituminous Pavement with Central Recycling Plant

Recycling pavement by cold milling of existing bituminous layers, cum 6373


planning the surface after cold milling, reclaiming excavated material to
the extent of 30 per cent of the required quantity, hauling and stock
piling the reclaimed material near the cent

Page 139 of 959


Ref. of Rate
Item No. Descriptions Unit
MoSRT&H (17-18)

18.19 Protective coatings to the structures, equipments and machine


parts with performance guarantee for 3 years.
I Application cost of two part highbuild 100% solid content system of sqm 780
Cyclophat polyamino based KRAYON KI30021 COROGARD to give
protective coating to the substract by giving good bonding to the
intermediate coat of Krayon KI 30031 RUST CONVERTOR coat giving
the cured coat of crosslinked protective coating from rust , corrosion and
weathering effect including cost of material, labour, scafolding, cleaning
over application of one part primer fron three part system and two part
primer from three part system Krayon KI 30031 RUST CONVERTOR
PRIMER and consumable complete as directed by the Engineer-
incharge and conforming quality as per IS / IRC Specifications.

Page 140 of 959


(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine

P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 435.00

Batching and Mixing Plant


P&M-002 Concrete Mixing cum/hour 20 hour 1957.00
(a) 30 cum capacity
Batching and Mixing Plant
P&M-003 Concrete Mixing cum/hour 13 hour 1590.00
(b) 15 - 20 cum capacity

P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 954.00

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 1,590.00

Concrete Paver Finisher with 40 HP


P&M-006 Paving of concrete surface cum / hour 20 hour 2495.00
Motor
Concrete Pump of 45 & 30 cum
P&M-007 Pumping of concrete cum / hour 33 / 22 hour 234.00
capacity

P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 15.00

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 188.00

P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 188.00

P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1136.00

P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 759.00

P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 318.00

300/
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour hour 3194.00
150/250
200/
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour hour 1965.00
120/150

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 717.00

Front End loader 1 cum bucket Soil loading / Aggregate


P&M-017 cum/hour 60 /25 hour 1,341.00
capacity loading

P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 2073.00

P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 514.00

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1140.00

P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 22823.00

P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 16575.00

Hotmix Plant - 60 to 90 TPH


P&M-023 DBM/BM/SDC/ Premix cum/hour 25 hour 16575.00
capacity

Page 1 of 959
Hotmix Plant - 40 to 60 TPH
P&M-024 DBM/BM/SDC/ Premix cum/hour 17 hour 12379.00
capacity

P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2380.00

Hydraulic Excavator of 1 cum Soil Ordinary/Soil Marshy /


P&M-026 60 /60 /60 hour 1836.00
bucket Soil Unsuitable

P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 7220.00

P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 14389.00

P&M-029 Kerb Casting Machine Rm/hour 80 hour 284.00

P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 56.00

P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 337.00

Clearing /Spreading 200/200/50/


P&M-032 Motor Grader 3.35 mtr blade cum/hour hour 2234.00
/GSB /WBM 50

P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 2072.00

Paver Finisher Hydrostatic with Paving of DBM/ BM/SDC/


P&M-034 cum/hour 40 hour 2341.00
sensor control 100 TPH Premix
Paving of WMM /Paving of
P&M-035 Paver Finisher Mechanical 100 TPH cum/hour 40/30 hour 853.00
DLC
0.75 m dia to 1.2 m dia
P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour 4665.00
Boring attachment

P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1137.00

P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 3453.00

P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 884.00

Prestressing Jack with Pump & Stressing of steel


P&M-040 hour 113.00
access wires/stands

P&M-041 Ripper Scarifying cum/hour 60 hour 31.00

P&M-042 Rotavator Scarifying cum/hour 25 hour 22.00

P&M-043 Road marking machine Road marking Sqm/hour 100 hour 192.00

Soil Compaction /BM


P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour 924.00
Compaction

P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1039.00

Transportation of soil, GSB,


P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 850.00
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-047 Tipper - 5 cum Capacity in cum 5.5 60.00
WMM, Hotmix etc. tonne.km

Page 2 of 959
Transportation of soil, GSB,
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 850.00
WMM, Hotmix etc.
Transportation of Concrete
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 828.00
Mix to site
Transportation of Concrete
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 40.00
Mix to site tonne.km
Transportation of Concrete
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 759.00
Mix to site
Transportation of Concrete
P&M-052 Transit Mixer 3.0 cum cum/hour 3 35.00
Mix to site tonne.km

P&M-053 Tractor Pulling capacity in HP 50 hour 323.00

P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 431.00

P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 440.00

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 825.00

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 717.00

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 3.50
tonne.km

P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1687.00

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 440.00

P&M-061 Water Tanker Water Transport capacity in KL 6 km 17.60

P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1149.00

P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 284.00

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per
P&M-064 hour 2000.00
hour

P&M-065 Belt conveyor system hour 2100.00

P&M-066 Boat to carry atleast 20 persons hour 200.00

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 5229.00

P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 4000.00

P&M-069 Cold milling machine @ 20 cum per hour hour 685.00

P&M-070 Crane 5 tonne capacity hour 725.00

P&M-071 Crane 10 tonne capacity hour 750.00

Page 3 of 959
P&M-072 Crane 15 tonne capacity hour 775.00

P&M-073 Crane 20 tonne capacity hour 800.00

P&M-074 Crane 40 T capacity hour 845.00

P&M-075 Crane with grab 0.75 cum capacity hour 1185.00

P&M-076 Compressor with guniting equipment along with accessories hour 400.00

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 1859.00

P&M-078 Epoxy Injection gun hour 300.00

P&M-079 Generator 33 KVA hour 311.00

P&M-080 Generator 100 KVA hour 621.00

P&M-081 Generator 250 KVA hour 1500.00

Induction, deinduction and erection of plant and equipment including all components and
P&M-082 hour input
accessories for pneumatic method of well sinking.

P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 150.00

P&M-084 Jack for Lifting 40 tonne lifting capacity. day 200.00

P&M-084_1 Jack for Lifting 150 tonne lifting capacity. day 1500.00

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 1000.00

P&M-086 Plate compactor hour 218.00

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 1000.00

P&M-088 Texturing machine (for rigid pavement) hour 800.00

P&M-089 Truck Trailor 30 tonne capacity hour 300.00

P&M-090 Welding Machine hour 500.00

P&M-091 Tunnel Boring machine hour input

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 850.00

P&M-093 Wet Mix Plant 100 TPH hour 1672.00

P&M-094 Wet Mix Plant 75 TPH hour 1353.00

Page 4 of 959
(B) Labour
Sl. No. Description of Labour Unit Rate

L-01 Blacksmith (IInd class) day 356.65

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 458.55

L-03 Blaster (Stone cutter) day 356.65

L-04 Carpenter I Class day 458.55

L-05 Chiseller (Head Mazdoor) day 285.32

L-06 Driller (Jumper) day 356.65

L-07 Diver day 356.65

L-08 Fitter day 458.55

L-09 Mali day 356.65

L-10 Mason (IInd class) day 285.32

L-11 Mason (Ist class) day 458.55

L-12 Mate / Supervisor day 356.65

L-13 Mazdoor day 244.56

L-14 Mazdoor/Dresser (Semi Skilled) day 285.32

L-15 Mazdoor/Dresser/Sinker (Skilled) day 356.65

L-16 Medical Officer day 500.00

L-17 Operator(grouting) day 356.65

L-18 Painter I class day 458.55

L-19 Para medical personnel day 356.65

Page 1 of 959
(C) Materials

Sl. No. Description Unit Rate


M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 1055.00

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 898.00

M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 898.00

M-004 Coarse sand at Mixing Plant cum 950.00

M-005 Coarse sand at Site cum 950.00

M-006 Fine sand at Site cum 850.00

M-007 Moorum at Site cum 698.00

M-008 Gravel/Quarry spall at Site Cum 987.00

M-009 Granular Material or hard murrum for GSB works at Site Cum 698.00

M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 698.00

M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 375.00

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 1013.00
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 1119.00

M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1101.00

M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1101.00

M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1084.00

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 1041.50

M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 1041.50

M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 1089.00

M-020 Close graded Granular sub-base Material 2.36 mm cum 698.00

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 698.00

M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 698.00

M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 698.00

M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 1041.50

M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1084.00

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 1089.00

M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1101.00

M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1101.00

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 1124.00

M-030 Aggregates below 5.6 mm cum 1104.00

M-031 Aggregates 22.4 mm to 2.36 mm cum 1440.50

Page 1 of 959
M-032 Aggregates 22.4 mm to 5.6 mm cum 1440.50

M-033 Aggregates 45 mm to 2.8 mm cum 1623.00

M-034 Aggregates 45 mm to 22.4 mm cum 1623.00

M-035 Aggregates 53 mm to 2.8 mm cum 2035.00

M-036 Aggregates 53 mm to 22.4 mm cum 1623.00

M-037 Aggregates 63 mm to 2.8 mm cum 1936.00

M-038 Aggregates 63 mm to 45 mm cum 1510.00

M-039 Aggregates 90 mm to 45 mm cum 1440.50

M-040 Aggregates 10 mm to 5 mm cum 1510.00

M-041 Aggregates 11.2 mm to 0.09 mm cum 1510.00

M-041_1 Aggregates 11.2 mm to 2.36 mm cum 1510.00

M-042 Aggregates 13.2 mm to 0.09 mm cum 1599.50

M-043 Aggregates 13.2 mm to 5.6 mm cum 1599.50

M-044 Aggregates 13.2 mm to 10 mm cum 1599.50

M-045 Aggregates 20 mm to 10 mm cum 1777.00

M-046 Aggregates 25 mm to 10 mm cum 1827.00

M-047 Aggregates 19 mm to 6 mm cum 1104.00

M-048 Aggregates 37.5 mm to 19 mm cum 1619.00

M-049 Aggregates 37.5 mm to 25 mm cum 1619.00

M-050 Aggregates 6 mm nominal size cum 1807.00

M-051 Aggregates 10 mm nominal size cum 1916.00

M-052 Aggregates 13.2/12.5 mm nominal size cum 1510.00

M-053 Aggregates 20 mm nominal size cum 1777.00

M-054 Aggregates 25 mm nominal size cum 1827.00

M-055 Aggregates 40 mm nominal size cum 1500.00

M-056 G.I. pipe 100 mm dia metre 900.00

M-057 Acrylic polymer bonding coat litre 340.00

M-058 Alluminium Paint litre 231.00

M-059 Aluminium alloy plate 2mm Thick sqm 460.00

M-060 Aluminium alloy/galvanised steel tonne 56000.00


Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards
M-061 sqm 8750.00
lettering, cost of angle iron, cost of drilling holes, nuts, bolts etc.and signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 438.00

M-063 Barbed wire kg 78.00

M-064 Bearing (Cost of parts) nos 32300.00

M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 135850.00

Page 2 of 959
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6
M-066 nos 14180.00
nos. internal reinforcing steel laminates by the process of vulcanisation,)
M-067 Bearing (Forged steel roller bearing of 250 tonne) nos 117306.00
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE
M-068 pads providing sliding surfaces against stainless steel mating together with cast steel nos 39560.00
assemblies/fabricated structural steel assemblies duly painted with all comp
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 19760.00

M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 11025.00

M-071 Bentonite kg 12.00

M-072 Binding wire kg 85.00

M-073 Bitumen ( Cationic Emulsion ) ( CSS-1h) tonne 38530.00

M-074 Bitumen ( Cationic Emulsion ) ( CSS-1)(IS:8887-2004) tonne 36950.00

M-074_1 Bitumen ( Cationic Emulsion ) ( CSS-2) tonne 27790.00

M-074_2 Bitumen ( Cationic Emulsion ) ( CSS-1) tonne 36950.00

M-075 Bitumen ( Cationic Emulsion ) ( RS-1) tonne 26260.00

M-075_1 Bitumen ( Cationic Emulsion ) ( RS-2) tonne 26260.00

M-076 Bitumen ( Cationic Emulsion ) ( MS) tonne 27790.00

M-077 Bitumen (60-70 grade OR VG-30) tonne 32627.00

M-078 Bitumen (80-100 grade OR VG-10 ) tonne 31681.00

M-079 Bitumen (CRMB-55 ) tonne 31950.00

M-080 Bitumen( Penetration at 25 deg C=15+/- 5 tonne 40572.00

M-081 Bitumen (Polymer modified graded) PMB tonne 33280.00

M-082 Brick each 8.00

M-083 C.I.shoes for the pile kg 85.00

M-084 Cement tonne 7200.00


TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal steel/ Shyam steel
M-085 tonne 53667.00
or equivalent)
M-085_1 TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved) tonne 49667.00

M-085_2 MS bar-IS 1786 ( Fe-250 ) Secondary Producer tonne 55637.00

M-086 Coller for joints 300 mm dia nos 504.00

M-087 Compressible Fibre Board(20mm thick) sqm 1077.00

M-088 Connectors/ Staples each 75.00

M-089 Copper Plate(12m long x 250mmwide) kg 646.00

M-090 Corrosion resistant Structural steel tonne 66150.00

M-091 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 88.00

Page 3 of 959
M-092 Credit for excavated rock found suitable for use cum 186.00

M-093 Curing compound liter 214.00

M-094 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 0.00

M-095 Earth Cost or compensation for earth taken from private land cum 33.00
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer
M-096 metre 18000.00
for elastomeric slab unit conforming to clause 915.1 of IRC: 83 (part II),
M-097 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 1500.00

M-098 Epoxy resin-hardner mix for prime coat kg 840.00

M-098_1 Epoxy compound with accessories for preparing epoxy mortar kg 605.00

M-098_2 Epoxy mortar kg 422.00

M-098-3 Epoxy primer kg 395.00

M-099 Flag of red color cloth 600 x 600 mm each 11.00

M-100 Flowering Plants each 31.00

M-101 Galvanised MS flat clamp nos 288.00

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in
M-102 sqm 233.00
rolls of required size.

M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 61.00
M-104 Gelatin 80% kg 72.00
M-105 Geo grids(TGB-40) sqm 240.00

M-106 Geomembrane(1.5mm thick) sqm 333.00


M-107 Geonets(Geonet 121) sqm 310.00
M-108 Geotextile(GNW-280) sqm 116.00

M-109 Geotextile filter fabric(GNW-280) sqm 137.00

M-110 GI bolt 10 mm Dia nos 13.00

M-111 Grouting pump with agitator hour 310.00

M-112 Grass (Doob) kg 18.00

M-113 Grass (Fine) kg 27.00

M-114 HDPE pipes 75mm dia metre 111.00

M-115 HDPE pipes 90mm dia metre 160.00

M-116 Hedge plants each 12.00

M-117 Helical pipes 600mm diameter metre 87.00

M-118 Hot applied thermoplastic compound litre 133.00

M-119 HTS strand tonne 114109.00

M-120 Joint Sealant Compound kg 590.00

M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 34.00

M-122 LDO for steam curing litre 34.00

Page 4 of 959
M-123 M.S. Clamps nos 19.00

M-124 M.S. Clamps kg 90.00

M-125 M.S.shoes @ 35 Kg per pile of 15 m kg 42.00

M-126 TMT IS 1786 ( Fe-500)reinforcement bar. tonne 53667.00

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement
M-127 beyond 70 mm and upto 140mm assembly comprising of edge beams, central beam,2 modules metre 114000.00
chloroprene seal, anchorage elements, support and control system, all steel

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and
M-128 upto 210mm box/box seal joint assembly containing 3 modules/cells and comprising of edge metre 172800.00
beams, two central beams, chloroprene seal, anchorage elements, support and

M-129 Nipples 12mm nos 25.00

M-130 Nuts and bolts kg 90.00

M-131 Paint litre 258.00

M-132 Pavement Marking Paint litre 85.00

M-133 Paving Fabric(1.5mmthick) sqm 315.00

M-134 Perforated geosynthetic pipe 150 mm dia metre 470.00

M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 95.00

M-136 Pesticide kg 504.00

M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 552.00

M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 25.00

M-139 Plastic tubes 50 cm dia, 1.2 m high nos 58.00

M-140 Polymer braids metre 25.00

M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 742.00

M-142 Pre-coated stone chips of 13.2 mm nominal size cum 3890.00

M-144 Pre-moulded asphalt filler board sqm 647.00

M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 46.00

M-146 Primer kg 158.00

M-147 Quick setting compound kg 32.00

M-148 Random Rubble Stone cum 470.00

M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 8579.00

M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 10370.00

M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 2592.00

M-152 Reflectorising glass beads kg 102.00

M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 1103.00

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel
M-154 metre 240.00
strips)

Page 5 of 959
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced
M-155 metre 650.00
polymer/fibre reinforced polymer/polymeric strips)

M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 650.00

M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 475.00

M-158 Rivets each 4.50

M-159 Sand bags (Cost of sand and Empty cement bag) nos 16.00

M-160 Sapling 2 m high 25 mm dia each 42.00

M-161 Scrap tyres of size 900 x 20 nos 30.00

M-162 Seeds kg 30.00

M-163 Selected earth cum 165.00

M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 40.00

M-165 Sheathing duct metre 95.00

M-166 Shrubs each 12.00

M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 60.00

M-167_1 Well decayedFarm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 170.00

M-168 Sodium vapour lamp ( 250 Watts ) each 7900.00

M-169 Square Rubble Coursed Stone cum 590.00


Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height
M-170 each 7500.00
above deck level
Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height
M-171 each 11000.00
above road level
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 66.00

M-173 Steel helmet and cushion block on top of pile head during driving. kg 60.00

M-174 Steel pipe 25 mm external dia as per IS:1239 metre 72.00

M-175 Steel pipe 50 mm external dia as per IS:1239 metre 140.00

M-176 Steel wire rope 20 mm kg 155.00

M-177 Steel wire rope 40 mm kg 95.00

M-178 Strip seal expansion join metre 20000.00

M-179 Structural Steel tonne 60000.00

M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 104.00

M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications.(TGU-150) sqm 370.00

M-182 Through and bond stone each 8.50

M-183 Tie rods 20mm diameter nos 55.00

M-184 Tiles size 300 x 300 mm and 25 mm thick each 57.00

Page 6 of 959
M-185 Timber cum 34100.00

M-186 Traffic cones with 150 mm reflective sleeve nos 1300.00

M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 1500.00

M-188 Unsiaked lime tonne 5900.00

M-189 Water KL 45.00

M-189_1 Anti stripping agent Kg 240.00

M-190 Water based cement paint litre 36.00

M-191 Welded steel wire fabric kg 46.00

M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 46.00

M-193 Wooden ballies 2" Dia for bracing each 210.00

M-194 Wooden ballies 8" Dia and 9 m long each 3300.00

M-195 Wooden packing cum 25500.00

M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 60.00

M-0197 Bamboo Bholuka or Barua 55mm to 100mm dia and 6m long each 90.00

M-0198 Bamboo Jati or Bethua 50mm to mm dia and 6m long each 75.00

M-0199 Wood local first class piles 25cm to 30cm metre 4200.00

M-0200 Wood local first class planks 25cm to 38cm thick cum 26500.00

M-0201 Wood local first class small section cum 18700.00

M-0202 Wood local first class scantling up to 15cmx15cm cum 21200.00

M-0203 Wood local first class heavy section above 15cmx15cm cum 24100.00

M-0204 Wood sal piles 25cm to 30cm dia metre 5000.00

M-0205 Wood sal planks 25cm to 38cm dia thick cum 32000.00

M-0206 Wood sal scantling heavy section above 15cm to 15cm cum 27000.00

M-0207 Wood sal scantling upto15x15cm cum 120.00

M-208 Admixture ( Masterplast Pl-1 or equivalent ) Lit 120.00

M-209 Admixture ( Masterplast SPl-2 or equivalent ) Lit 100.00

Air entraining and water reducing plasticiser conforming to IS-9103-1999


M-210 Lit 75.00
( Masterplast PAE or equivalent)
Accelerating plasticiser conforming to IS-9103-1999
M-211 Lit 95.00
( Masterplast APCL or equivalent )

M-212 PVC rain water pipe 100mm Dia RM 90.00

Page 7 of 959
PERCENTAGES & LEAD INPUTS:

Overheads for Road Works 10%

Contractors profit for Road Works 10% for input of Overheads or Contractors
profit please type in collum C as like
Overheads for Bridge Works 20 % below:

Type symble of apostrope(') then input


Overheads for Bridge Works
20% value then one space then symble of
(Rehabilitation)
percentage (%) for example '08 %

Contractors profit for Bridge Works 10%

Lead from Mixing Plant to working site 10 km

Lead for E/W borow area to site 3 km

Lead for fly ash from source to site 5 km

Page 1 of 959
Summary of Rates calculated and used for analysis of rates of other items

Items No. Items of Work Unit Rate


per cm
Item 8.3 Printing new letter and figures of any shade (ii) English Roman height 0.60
per letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 52.00
Item 8.9 Painting angle iron post two coats sqm 73.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 5,959.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 4,904.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 3,448.00

Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 4,428.00

Item 12.7
Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 3,538.00
(Addl) B)

(A) Without plasticiser

Item 12.8 (A)


PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 6,240.00
M15 PC OM

Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 4,546.00
M15 PC OBM by Mixer

Item 12.8 (B) PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,021.00
M20 PC OBM by Mixer

Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,170.00
M20 RC OBM by Mixer

Item 12.8 (C)


RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 8,152.00
M20 RC OB

Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,939.00
M20 RC OBB by Batching Plant

Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,420.00
M25 PC OBM by Mixer

Item 12.8 (D)


PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 8,640.00
M25 PC OB

Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,309.00
M25 PC OBB by Batching Plant

Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,573.00
M25 RC OBM by Mixer

Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,342.00
M25 RC OBB by Batching Plant

Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,463.00
M30 PC OBM by Mixer

Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,230.00
M30 PC OBB by Batching Plant

Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,597.00
M30 RC OBM by Mixer

Page 1 of 959
Items No. Items of Work Unit Rate

Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,367.00
M30 RC OBB by Batching Plant

Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 5,708.00
M35 RC OBM by Mixer

Item 12.8 (H)


RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 8,806.00
M35 RC OB

Item 12.8 (H)


RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 6,671.00
M35 RC OB(e)

Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,478.00
M35 RC OBB by Batching Plant

(B) With Plasticiser

Item 12.8 (A)


PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 7,112.00
M15 PC OM P

Item 12.8 (A)


PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M15 PC OBM cum 5,181.00
by Mixer
P
Item 12.8 (B)
PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M20 PC OBM cum 5,657.00
by Mixer
P
Item 12.8 (C)
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M20 RC OBM cum 5,806.00
by Mixer
P

Item 12.8 (C)


RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 9,024.00
M20 RC OB P

Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,574.00
M20 RC OBB P by Batching Plant

Item 12.8 (D)


PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M25 PC OBM cum 6,063.00
by Mixer
P

Item 12.8 (D)


PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 9,360.00
M25 PC OB P

Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,835.00
M25 PC OBB P by Batching Plant

Item 12.8 (E)


RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M25 RC OBM cum 6,223.00
by Mixer
P

Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,992.00
M25 RC OBB P by Batching Plant

Item 12.8 (F)


PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M30 PC OBM cum 6,116.00
by Mixer
P

Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 6,883.00
M30 PC OBB P by Batching Plant

Page 2 of 959
Items No. Items of Work Unit Rate
Item 12.8 (G)
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M30 RC OBM cum 6,253.00
by Mixer
P

Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 7,022.00
M30 RC OBB P by Batching Plant

Item 12.8 (H)


RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
M35 RC OBM cum 6,388.00
by Mixer
P

Item 12.8 (H)


RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 9,731.00
M35 RC OB P

Item 12.8 (H)


M35 RC OB(e) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 7,372.00
P

Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery
cum 7,158.00
M35 RC OBB P by Batching Plant

(A) Without plasticiser

Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 5,337.00
M20 PC BBM Material & Mechinery by Mixer

Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 6,085.00
M20 PC BBB Material & Mechinery by Batching Plant

Item 12.11 (C) PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 5,548.00
ii M25 PC BBM Material & Mechinery by Mixer

Item 12.11 (C) PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 6,294.00
ii M25 PC BBB Material & Mechinery by Batching Plant

Item 12.11 (C) PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 5,591.00
iii M30 PC BBM Material & Mechinery by Mixer

Item 12.11 (C) PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 6,339.00
iii M30 PC BBB Material & Mechinery by Batching Plant

Item 12.11 (C)


PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
iv M35 PC cum 5,692.00
Material & Mechinery by Mixer
BBM
Item 12.11 (C)
iv M35 PC PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 8,837.00
WBB

Item 12.11 (C) PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 6,438.00
iv M35 PC BBB Material & Mechinery by Batching Plant

Item 12.11 (F)


iv M35 PC PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 8,837.00
WCB
(B) With Plasticiser

Page 3 of 959
Items No. Items of Work Unit Rate

Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 5,928.00
M20 PC BBM P Material & Mechinery by Mixer

Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
cum 6,676.00
M20 PC BBB P Material & Mechinery by Batching Plant

Item 12.11 (C)


PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
ii M25 PC BBM cum 6,191.00
Material & Mechinery by Mixer
P
Item 12.11 (C)
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
ii M25 PC BBB cum 6,937.00
Material & Mechinery by Batching Plant
P
Item 12.11 (C)
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
iii M30 PC BBM cum 6,244.00
Material & Mechinery by Mixer
P
Item 12.11 (C)
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
iii M30 PC BBB cum 7,010.00
Material & Mechinery by Batching Plant
P
Item 12.11 (C)
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
iv M35 PC cum 6,368.00
Material & Mechinery by Mixer
BBM P
Item 12.11 (C)
iv M35 PC PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 9,772.00
WBB P
Item 12.11 (C)
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour,
iv M35 PC BBB cum 7,113.00
Material & Mechinery by Batching Plant
P
Item 12.11 (F)
iv M35 PC PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 9,731.00
WCB P
Item No. 3.13 Excavation for Structures (Manual Means) cum 251.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 53.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 9,465.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 10,135.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 10,314.69
RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching
Item 14.1(C) cum
Plant 7,745.00
RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching
Item 14.1(C) cum
Plant 6,454.00
Supplying ,fitting and placing TMT/HYSD bar reinforcement in super-structure excluding OH
Item 14.2
& CP
TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal steel/ Shyam
(a) tonne 60,520.00
steel or equivalent)
(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved) tonne 56,320.00

Item 13.6 Supplying, fitting and placing HYSD/TMT including OH & CP for sub-structure

Page 4 of 959
Items No. Items of Work Unit Rate
TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal steel/ Shyam
(a) tonne 78,525.00
steel or equivalent)
(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI approved) tonne 72,981.00
Item 5.17 Fog Seal sqm 44.00
Item 5.21 Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than
sqm 62.00
Case-I 6 mm
Item 5.21 Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6
sqm 71.00
Case-II mm to 9 mm
Item 5.21 Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9
sqm 92.00
Case-IV mm and cracked area above 50 %
Item 5.21
Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 198.00
Case-IV
Item 5.15
Slurry Seal Case-I 5 mm thickness sqm 71.00
Case-I
Item 5.15
Slurry Seal Case-II 3 mm thickness sqm 49.00
Case-II
Item 5.15
Slurry Seal Case III 1.5 mm thickness sqm 30.00
Case-III

Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 86.00

Item 5.9 Case-


Surface Dressing Case-II 13 mm nominal size chipping sqm 65.00
II

Page 5 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.1 Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity 13 Min
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 850.00 280.50 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 1341.00 442.53 P&M-017
cum/hour
b) Overheads @ 10% on (a) 72.30
c) Contractors profit @ 10% on (a+b) 79.53
Cost for 5.5 cum = a+b+c 874.87
Rate per cum = (a+b+c)/ 5.5 159.07
Note Unloading will be by tipping. say 159.00
1.4 Cost of Haulage Excluding Loading and Unloading

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100
t.km
1.4(I) Case I Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 850.00 340.00 P&M-048
Time taken for empty return trip. hour 0.290 850.00 246.50 P&M-048
b) Overheads @ 10% on (a) 58.65
c) Contractors profit @ 10% on (a+b) 64.52
cost for 100 t km = a+b+c 709.67
Rate per t.km = (a+b+c)/100 7.10
say 7.10

1.4(II) Case II Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity

Page 6 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Time taken for onward hanlage with load hour 0.500 850.00 425.00 P&M-048
Time taken for empty return trip hour 0.330 850.00 280.50 P&M-048
b) Overheads @ 10% on (a) 70.55
c) Contractors profit @ 10% on (a+b) 77.61
Cost for 100 t .km = a+b+c 853.66
Rate per t.Km = (a+b+c)/100 8.54
say 8.50

1.4(III) Case III Katcha Track and Track in river bed / nallah bed and
choe bed.
Speed with load : 10 km / hour
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 850.00 850.00 P&M-048
Time taken for empty return trip hour 0.670 850.00 569.50 P&M-048
b) Overheads @ 10% on (a) 141.95
c) Contractors profit @ 10% on (a+b) 156.15
Cost for 100 t .km = a+b+c 1717.60
Rate per t.Km = (a+b+c)/100 17.18
say 17.20
1.5 Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 356.65 21.40 L-12
Mazdoor day 1.500 244.56 366.84 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 898.00 987.80 M-002
c) Overheads @ 10% on (a+b) 137.60
d) Contractors profit @ 10% on (a+b+c) 151.36
Rate per cum = a+b+c+d 1665.01
say 1665.00
1.6 Crushing of stone aggregates 13.2 mm nominal size.

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 356.65 271.05 L-12

Page 7 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor Skilled day 2.000 356.65 713.30 L-15
Mazdoor including breaking of any oversize boulder. day 17.000 244.56 4157.52 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 1055.00 844000.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 14389.00 86334.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1341.00 26820.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 850.00 17000.00 P&M-048
d) Overheads @ 10% on (a+b+c) 97929.59
e) Contractors profit @ 10% on (a+b+c+d) 107722.55
Cost for 600 cum = a+b+c+d+e 1184948.01
Rate per cum = (a+b+c+d+e)*0.95/600 1876.17
say 1876.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a by-
product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.7 Crushing of stone aggregates 20 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit : cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 356.65 271.05 L-12
Mazdoor Skilled day 2.000 356.65 713.30 L-15
Mazdoor including breaking of any size boulder. day 17.000 244.56 4157.52 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 1055.00 844000.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 14389.00 86334.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1341.00 26820.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 850.00 17000.00 P&M-048
d) Overheads @ 10% on (a+b+c) 97929.59
e) Contractors profit @ 10% on (a+b+c+d) 107722.55
Cost for 670 cum = a+b+c+d+e 1184948.01
Rate per cum = (a+b+c+d+e)*0.90/670 1591.72
say 1592.00

Page 8 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.8 Crushing of stone aggregates 40 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 356.65 271.05 L-12
Mazdoor Skilled day 2.000 356.65 713.30 L-15
Mazdoor day 17.000 244.56 4157.52 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 1055.00 844000.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 14389.00 86334.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1341.00 26820.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 850.00 17000.00 P&M-048
d) Overheads @ 10% on (a+b+c) 97929.59
e) Contractors profit @ 10% on (a+b+c+d) 107722.55
Cost for 750 cum = (a+b+c+d+e)x0.85 1007205.81
Rate per cum = (a+b+c+d+e)x0.85/750 1342.94
say 1343.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
5.9 510 Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller

Unit = sqm
Taking output = 9000 sqm

Page 9 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor hour 6.000 954.00 5724.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 32627.00 352371.60 M-077
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1777.00 239895.00 M-053
cum per sqm
d) Overheads @ 10% on (a+b+c) 63959.03
e) Contractors profit @ 10% on (a+b+c+d) 70354.93
Cost for 9000 sqm= a+b+c+d+e 773904.22
Rate per sqm = (a+b+c+d+e)/9000 85.99
say 86.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1687.00 10122.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 32627.00 293643.00 M-077

Page 10 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1510.00 135900.00 M-052
cum per sqm
d) Overheads @ 10% on (a+b+c) 48144.47
e) Contractors profit @ 10% on (a+b+c+d) 52958.91
Cost for 9000 sqm= a+b+c+d+e 582548.05
Rate per sqm = (a+b+c+d+e)/9000 64.73
say 65.00
Note 1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
5.15 516 Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Mechanical broom hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Mobile slurry seal equipment hour 6.000 2072.00 12432.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 850.00 5100.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1137.00 6822.00 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 tonne 19.360 40572.00 785473.92 M-080
Fine aggregate 4.75 mm and below 87 % of total cum 102.080 950.00 96976.00 M-005
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5,= 153.12/1.5 = 102.08 cum

Page 11 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Filler @ 2 % of total mix = 80 x 2.2 x 0.02 tonne 3.520 5900.00 20768.00 M-188
Cost of water KL 12.000 45.00 540.00 M-189
d) Overheads @ 10% on (a+b+c) 94322.29
e) Contractors profit @ 10% on (a+b+c+d) 103754.52
Cost for 16000 sqm= a+b+c+d+e 1141299.68
Rate per sqm = (a+b+c+d+e)/16000 71.33
say 71.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery
Mechanical broom hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Mobile slurry seal equipment hour 6.000 2072.00 12432.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 850.00 5100.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13 tonne 17.160 40572.00 696215.52 M-080
Fine aggregate 3 mm and below 85 % of total mix, 60x cum 74.800 950.00 71060.00 M-005
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02 tonne 2.640 5900.00 15576.00 M-188
Cost of water KL 12.000 45.00 540.00 M-189
d) Overheads @ 10% on (a+b+c) 81577.57
e) Contractors profit @ 10% on (a+b+c+d) 89735.32
Cost for 30000 sqm= a+b+c+d+e 987088.54
Rate per sqm = (a+b+c+d+e)/20000 49.35
say 49.00
Case III 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery
Mechanical broom hour 6.000 337.00 2022.00 P&M-031

Page 12 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Mobile slurry seal equipment hour 6.000 2072.00 12432.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 850.00 5100.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 tonne 12.670 40572.00 514047.24 M-080
Fine aggregate 2.36 mm and below,82 % of total cum 43.300 698.00 30223.40 M-022
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5

Filler @ 2 % of total mix = 36x 2.2 x 0.02 tonne 1.580 5900.00 9322.00 M-188
Cost of water KL 12.000 45.00 540.00 M-189
d) Overheads @ 10% on (a+b+c) 58651.68
e) Contractors profit @ 10% on (a+b+c+d) 64516.84
Cost for 24000 sqm= a+b+c+d+e 709685.29
Rate per sqm = (a+b+c+d+e)/24000 29.57
say 30.00
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately

5.17 518 Fog Spray


Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Bitumen emulsion pressure distributor @ 1750 sqm per tonne 6.000 954.00 5724.00 P&M-004
hour
c) Material
Bitumenemulsion @ 0.75 kg per sqm tonne 7.880 40572.00 319707.36 M-080
d) Overheads @ 10% on (a+b+c) 33083.98
e) Contractors profit @ 10% on (a+b+c+d) 36392.38
Cost for 10500 sqm= a+b+c+d+e 400316.20
Rate per sqm = (a+b+c+d+e)/10500 38.13
say 38.00

Page 13 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor for precoating of grit day 4.000 244.56 978.24 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 1041.50 27339.38 M-024
Bitumenemulsion for precoating grit @ 2 % of tonne 0.790 40572.00 32051.88 M-080
grit,39.38 x 0.02
60426.56
5.75
say 6.00
5.21 522 Crack Prevention Courses
Case - I Stress Absorbing Membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Hydraulic Chip spreader hour 6.000 2380.00 14280.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Modified binder tonne 9.450 33280.00 314496.00 M-081
Crushed stone aggregates 5.6 mm size cum 105.000 1807.00 189735.00 M-050
d) Overheads @ 10% on (a+b+c) 53596.40
e) Contractors profit @ 10% on (a+b+c+d) 58956.04
Cost for 10500 sqm= a+b+c+d+e 648516.39
Rate per sqm = (a+b+c+d+e)/10500 61.76
say 62.00
Case - II Stress Absorbing Membrane (SAM) with crack width 6
mm to 9 mm

Page 14 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 1
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 435.00 2610.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Hydraulic Chip spreader hour 6.000 2380.00 14280.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Modified binder tonne 11.550 33280.00 384384.00 M-081
Crushed stone chipping 11.2 mm size cum 105.000 1916.00 201180.00 M-051
d) Overheads @ 10% on (a+b+c) 61729.70
e) Contractors profit @ 10% on (a+b+c+d) 67902.67
Cost for 10500 sqm= a+b+c+d+e 746929.32
Rate per sqm = (a+b+c+d+e)/10500 71.14
say 71.00
Case III Stress Absorbing Membrane (SAM) crack width above
9 mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 435.00 2610.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Hydraulic Chip spreader hour 6.000 2380.00 14280.00 P&M-025

Page 15 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Smooth wheeled road roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Modified binder tonne 15.750 33280.00 524160.00 M-081
Crushed stone aggregates 11.2 mm size cum 126.000 1916.00 241416.00 M-051
d) Overheads @ 10% on (a+b+c) 79802.23
e) Contractors profit @ 10% on (a+b+c+d) 87782.45
Cost for 10500 sqm= a+b+c+d+e 965606.93
Rate per sqm = (a+b+c+d+e)/10500 91.96
say 92.00
Case IV Case - IV : Bitumen Impregnated Geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed t
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 356.65 199.72 L-12
Mazdoor day 12.000 244.56 2934.72 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfem capacity hour 2.800 435.00 1218.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 954.00 1908.00 P&M-004
Pneumatic roller hour 2.000 1137.00 2274.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 31681.00 116586.08 M-078
kg per sqm
Geotextile including 10 % for overlaps sqm 3850.000 116.00 446600.00 M-108
d) Overheads @ 10% on (a+b+c) 57337.74
e) Contractors profit @ 10% on (a+b+c+d) 63071.52
Cost for 10500 sqm= a+b+c+d+e 693786.68
Rate per sqm = (a+b+c+d+e)/3500 198.22
say 198.00
NOTE As bitumen overlay construction shallfollow closely the fabric
placement on the same day, an output of 3500 sqm only
has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bi
8.3 801 Printing new letter and figures of any shade

Page 16 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 357 24.97
Painter Ist class day 1.25 459 573.19
Mazdoor day 0.50 245 122.28
b) Material
Paint Litre 0.50 258 129.00
c) Overheads @ 10% on (a+b) 84.94
d) Contractors profit @ 10% on (a+b+c) 93.44
Cost for 1600 cm = a+b+c+d 1027.81
Rate per cm height per letter = (a+b+c +d)/1600 0.64
say 0.60
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 357 42.80
Painter day 2.00 459 917.10
Mazdoor day 1.00 245 244.56
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.00 85 510.00

Add for scaffolding @ 1% of labour cost where required 5.10

c) Overheads @ 10% on (a+b) 171.96


d) Contractors profit @ 10% on (a+b+c) 189.15
Cost for 40 sqm = a+b+c+d 2080.67
Rate per sqm = (a+b+c+d)/40 52.02
say 52.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm

Page 17 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 10 sqm
a) Labour
Mate day 0.03 357 10.70
Painter day 0.45 459 206.35
Mazdoor day 0.25 245 61.14
b) Material
Paint ready mixed approved brand. Litre 1.25 258 322.50
Add @ 1% on cost of material for scaffolding 3.23
c) Overheads @ 10% on (a+b) 60.39
d) Contractors profit @ 10% on (a+b+c) 66.43
Cost for 10 sqm = a+b+c+d 730.73
Rate per sqm = (a+b+c+d)/10 73.07
say 73.00
12.6 Sub- Cement mortar1:3 (1cement :3 sand)
analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.51 7200.00 3672.00
Sand cum 1.05 950.00 997.50
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) 4904.00

Sub- Cement mortar1:2 (1cement :2 sand)


analysis
(B) Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.67 7200.00 4838.40
Sand cum 0.93 950.00 886.67
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) 5959.00

Sub- Cement mortar1:6 (1cement :6 sand)


analysis
(D) Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.29 7200.00 2073.60
Sand cum 1.20 950.00 1140.00
b) Labour
Mate day 0.04 356.65 14.27

Page 18 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) 3448.00
12.7 1400 Stone masonry work in cement mortar 1:3 in
foundation complete as drawing and Technical
Specification
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 590.00 3245.00 M-169
Through and bond stone each 35.00 8.50 297.50 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 4904.00 7356.00 Item 12.6
analysis) (A)
b) Labour
Mate day 0.66 356.65 235.39 L-12
Mason day 7.50 458.55 3439.13 L-11
Mazdoor day 9.00 244.56 2201.04 L-13
c) Overhead charges @ 20 % on (a+b) 3354.81
d) Contractor's profit @ 10% on (a+b+c) 2012.89
Cost for 5 cum = a+b+c+d 22141.75
Rate per cum (a+b+c+d)/5 4428.35
say 4428.00
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 470.00 2585.00
Through and bond stone Nos 35.00 8.50 297.50
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A) cum 1.55 4904.00 7601.20
b) Labour
Mate day 0.62 356.65 221.12
Mason day 6.00 458.55 2751.30
Mazdoor day 9.00 244.56 2201.04
c) Overheads @ 20 % on (a+b) 3131.43
d) Contractors profit @ 10% on (a+b+c) 1878.86
Cost for 5 cum = a+b+c+d 20667.46
Rate per cum (a+b+c+d)/5 4133.49
say 4133.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.7 1400 Stone masonry work in cement mortar 1:6 in
(Add) foundation complete as drawing and Technical
Specification
Unit = cum

Page 19 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 5 cum
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 470.00 2585.00
Through and bond stone Nos 35.00 8.50 297.50
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D) cum 1.55 3448.00 5344.40
b) Labour
Mate day 0.62 356.65 221.12
Mason day 6.00 458.55 2751.30
Mazdoor day 9.00 244.56 2201.04
c) Overheads @ 20 % on (a+b) 2680.07
d) Contractors profit @ 10% on (a+b+c) 1608.04
Cost for 5 cum = a+b+c+d 17688.48
Rate per cum (a+b+c+d)/5 3537.70
say 3538.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.

12.8 1500, Plain/Reinforced cement concrete in open foundation


1700 & complete as per drawing and technical specifications
2100
(I) Without using Plasticiser
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 4.13 7200.00 29736.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 8.10 1500.00 12150.00
20 mm Aggregate cum 4.05 1777.00 7196.85
10 mm Aggregate cum 1.35 1916.00 2586.60
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 63 KVA hour 6.00 514.00 3084.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4,546.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 2727.19
labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 14181.38
f) Contractors profit @ 10% on (a+b+c+d+e) 8508.83
Cost for 15 cum = a+b+c+d+e+f 93597.08

Page 20 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum (a+b+c+d+e+f)/15 6239.81
say 6240.00
Note Nedle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement MT 5.16 7200.00 37152.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,021.00
12.8 C RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement MT 5.21 7200.00 37512.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,170.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 7200.00 299952.00
Coarse Sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59

Page 21 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 km, L-lead in km T-km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,939.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 28503.52
labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 148218.33
f) Contractors profit @ 10% on (a+b+c+d+e) 88931.00
Cost for 120 cum = a+b+c+d+e+f 978240.97
Rate per cum = ( a+b+c+d+e+f )/120 8152.01
say 8152.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 7200.00 43128.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,420.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 7200.00 345240.00
Coarse sand cum 54.00 950.00 51300.00
40 mm Aggregate cum 43.20 1827.00 78926.40
20 mm Aggregate cum 43.20 1777.00 76766.40
10 mm Aggregate cum 21.60 1916.00 41385.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery

Page 22 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,309.00
d) Formwork @ 3.75% of cost of concrete i.e.cost of 28388.76
material, labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 157084.50
f) Contractors profit @ 10% on (a+b+c+d+e) 94250.70
cost of 120 cum = a+b+c+d+e+f 1036757.67
Rate per cum (a+b+c+d+e+f)/120 8639.65
say 8640.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 7200.00 43560.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,573.00
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 7200.00 348336.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity 1 cum hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00

Page 23 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Transit Mixer 4 cum capacity lead beyond T-Km 3000.00 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,342.00
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 7200.00 43776.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,463.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 7200.00 349920.00
Coarse sand cum 54.00 950.00 51300.00
40 mm Aggregate cum 43.20 1500.00 64800.00
20 mm Aggregate cum 43.20 1777.00 76766.40
10 mm Aggregate cum 21.60 1916.00 41385.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,230.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material

Page 24 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement MT 6.10 7200.00 43920.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,597.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 7200.00 351360.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,367.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 7200.00 45576.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00

Page 25 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,708.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 50.64 7200.00 364608.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,478.00
d) Formwork @ 3% on cost of concrete i.e.cost of material, 23317.32
labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 160112.29
f) Contractors profit @ 10% on (a+b+c+d+e) 96067.37
cost of 120 cum = a+b+c+d+e+f 1056741.10
Rate per cum (a+b+c+d+e+f)/120 8806.18
say 8806.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 6671.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

12.8 1500, Plain/Reinforced cement concrete in open foundation


1700 & complete as per drawing and technical specifications
2100
(II) With Plasticiser
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 4.13 7200.00 29736.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 8.10 1500.00 12150.00
20 mm Aggregate cum 4.05 1777.00 7196.85
10 mm Aggregate cum 1.35 1916.00 2586.60
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.84 120.00 2500.80 4lit/Ton

Page 26 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Air entraining and water reducing plasticiser Lit 15.63 100.00 1563.00 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.94 75.00 5470.50 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 63 KVA hour 6.00 514.00 3084.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,181.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 3108.56
labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 16164.51
f) Contractors profit @ 10% on (a+b+c+d+e) 9698.71
Cost for 15 cum = a+b+c+d+e+f 106685.77
Rate per cum (a+b+c+d+e+f)/15 7112.38
say 7112.00
Note Nedle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement MT 5.16 7200.00 37152.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.84 120.00 2500.80 4lit/Ton
Air entraining and water reducing plasticiser Lit 15.63 100.00 1563.00 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.94 75.00 5470.50 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,657.00
12.8 C RCC Grade M20
Unit = cum
Case I Using concrete mixer

Page 27 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 15 cum
a) Material
Cement MT 5.21 7200.00 37512.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.84 120.00 2500.80 4lit/Ton
Air entraining and water reducing plasticiser Lit 15.63 100.00 1563.00 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.94 75.00 5470.50 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5,806.00
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 7200.00 299952.00
Coarse Sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast Pl-1 or equivalent) Lit 166.64 120.00 19996.80 4lit/Ton
Air entraining and water reducing plasticiser Lit 124.98 100.00 12498.00 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 583.24 75.00 43743.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 km, L-lead in km T-km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,574.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 31553.04
labour and machinery

Page 28 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overheads @ 20 % on (a+b+c+d) 164075.79
f) Contractors profit @ 10% on (a+b+c+d+e) 98445.47
Cost for 120 cum = a+b+c+d+e+f 1082900.22
Rate per cum = ( a+b+c+d+e+f )/120 9024.17
say 9024.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 7200.00 43128.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 29.95 76.40 2288.18 5lit/Ton
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,063.00
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 7200.00 345240.00
Coarse sand cum 54.00 950.00 51300.00
40 mm Aggregate cum 43.20 1500.00 64800.00
20 mm Aggregate cum 43.20 1777.00 76766.40
10 mm Aggregate cum 21.60 1916.00 41385.60
Admixture ( Masterplast SPl-2 or equivalent) Lit 239.75 76.40 18316.90 5lit/Ton
Air entraining and water reducing plasticiser Lit 143.85 59.80 8602.23 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 671.30 75.00 50347.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08

Page 29 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,835.00
d) Formwork @ 3.75% of cost of concrete i.e.cost of 30756.52
material, labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 170186.09
f) Contractors profit @ 10% on (a+b+c+d+e) 102111.66
cost of 120 cum = a+b+c+d+e+f 1123228.22
Rate per cum (a+b+c+d+e+f)/120 9360.24
say 9360.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 7200.00 43560.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.25 76.40 2311.10 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.15 59.80 1085.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 75.00 6352.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,223.00
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 7200.00 348336.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 241.90 76.40 18481.16 5lit/Ton

Page 30 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Air entraining and water reducing plasticiser Lit 145.14 59.80 8679.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.32 75.00 50799.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity 1 cum hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,992.00
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 7200.00 43776.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.40 76.40 2322.56 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.24 59.80 1090.75 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 75.00 6384.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,116.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 7200.00 349920.00
Coarse sand cum 54.00 950.00 51300.00

Page 31 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
40 mm Aggregate cum 43.20 1500.00 64800.00
20 mm Aggregate cum 43.20 1777.00 76766.40
10 mm Aggregate cum 21.60 1916.00 41385.60
Admixture ( Masterplast SPl-2 or equivalent) Lit 243.00 76.40 18565.20 5lit/Ton
Air entraining and water reducing plasticiser Lit 145.80 59.80 8718.84 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.40 75.00 51030.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,883.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.10 7200.00 43920.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.50 76.40 2330.20 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,253.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit = cum
Taking output = 120 cum

Page 32 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Material
Cement MT 48.80 7200.00 351360.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 244.00 76.40 18641.60 5lit/Ton
Air entraining and water reducing plasticiser Lit 146.40 59.80 8754.72 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.20 75.00 51240.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7,022.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 7200.00 45576.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) Lit 31.65 76.40 2418.06 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6,388.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Page 33 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 50.64 7200.00 364608.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 253.20 76.40 19344.48 5lit/Ton
Air entraining and water reducing plasticiser Lit 151.92 59.80 9084.82 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 75.00 53172.00 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond T-Km 300L 40.00 120000.00 L= 10
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7,158.00
d) Formwork @ 3% on cost of concrete i.e.cost of material, 25765.36
labour and machinery
e) Overheads @ 20 % on (a+b+c+d) 176922.15
f) Contractors profit @ 10% on (a+b+c+d+e) 106153.29
cost of 120 cum = a+b+c+d+e+f 1167686.22
Rate per cum (a+b+c+d+e+f)/120 9730.72
say 9731.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 7372.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

12.11 1200, Plain/Reinforced cement concrete, in well foundation


1500 & complete as per drawing and technical specification
1700 (A) Withot plasticiser

C Bottom Plug
Concrete to be placed using tremie pipe
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum

Page 34 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Material
Cement MT 5.55 7200.00 39960.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 318.00 1908.00

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5337.00
Note 10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 7200.00 319680.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 3000.00 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6085.00

(ii) PCC Grade M25

Case I Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.99 7200.00 43128.00
Coarse sand cum 6.75 950.00 6412.50

Page 35 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5548.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.88 7200.00 344736.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6294.00

(iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.08 7200.00 43776.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83

Page 36 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5591.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.64 7200.00 350208.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6339.00
(iv) PCC Grade M35

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.29 7200.00 45288.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe

Page 37 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5692.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.28 7200.00 362016.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6438.00
Add 5% of cost of material and labour towards cost of 30866.42
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..

d) Overheads @ 20 % on (a+b+c) 160666.16


e) Contractors profit @ 10% on (a+b+c+d) 96399.70
cost of 120 cum = a+b+c+d+e 1060396.66
Rate per cum (a+b+c+d+e)/120 8836.64
Say 8837.00
F Well cap
iv) RCC Grade M35
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 7200.00 364608.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00

Page 38 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Generator 100 KVA hour 6.00 621.00 3726.00
Loader(capacity 1 cum) hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6.00 234.00 1404.00
Formwork @ 3% of (a+b+c) 23251.26
d) Overheads @ 20 % on (a+b+c) 159658.68
e) Contractors profit @ 10% on (a+b+c+d) 95795.21
cost of 120 cum = a+b+c+d+e 1053747.26
Rate per cum (a+b+c+d+e)/120 8781.23
Say 8781.00
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

12.11 1200, Plain/Reinforced cement concrete, in well foundation


1500 & complete as per drawing and technical specification
1700 (B) With Plasticiser

C Bottom Plug
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 7200.00 39960.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast Pl-1 or equivalent ) Lit 22.20 92.00 2042.40
Air entraining and water reducing plasticiser Lit 16.65 59.80 995.67
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 77.70 75.00 5827.50
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 318.00 1908.00

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 5928.00

Page 39 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 7200.00 319680.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast Pl-1 or equivalent ) Lit 177.60 92.00 16339.20
Air entraining and water reducing plasticiser Lit 133.20 59.80 7965.36
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 621.60 75.00 46620.00
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6676.00

(ii) PCC Grade M25

Case I Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.99 7200.00 43128.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 29.95 76.40 2288.18
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50
( Masterplast APCL or equivalent)
b) Labour

Page 40 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6191.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.88 7200.00 344736.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 239.40 76.40 18290.16
Air entraining and water reducing plasticiser Lit 143.64 59.80 8589.67
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 670.32 75.00 50274.00
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6937.00

(iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.08 7200.00 43776.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.40 76.40 2322.56

Page 41 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Air entraining and water reducing plasticiser Lit 18.24 59.80 1090.75
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 75.00 6384.00
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6244.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.64 7200.00 350208.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 243.20 76.40 18580.48
Air entraining and water reducing plasticiser Lit 145.92 59.80 8726.02
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 75.00 53172.00
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7010.00
(iv) PCC Grade M35

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material

Page 42 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement MT 6.29 7200.00 45288.00
Coarse sand cum 6.75 950.00 6412.50
40 mm Aggregate cum 5.40 1500.00 8100.00
20 mm Aggregate cum 5.40 1777.00 9595.80
10 mm Aggregate cum 2.70 1916.00 5173.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 31.45 76.40 2402.78
Air entraining and water reducing plasticiser Lit 18.87 59.80 1128.43
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.06 75.00 6604.50
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 6368.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.28 7200.00 362016.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 251.40 76.40 19206.96
Air entraining and water reducing plasticiser Lit 150.84 59.80 9020.23
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 703.92 75.00 52794.00
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 1341.00 8046.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 40.00 120000.00 L= 10
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 7113.00

Page 43 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 5% of cost of material and labour towards cost of 34917.48
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..

d) Overheads @ 20 % on (a+b+c) 177680.61


e) Contractors profit @ 10% on (a+b+c+d) 106608.37
cost of 120 cum = a+b+c+d+e 1172692.03
Rate per cum (a+b+c+d+e)/120 9772.43
Say 9772.00
F Well cap
iv) RCC Grade M35
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 7200.00 364608.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 253.20 76.40 19344.48
Air entraining and water reducing plasticiser Lit 151.92 59.80 9084.82
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 75.00 53172.00
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader(capacity 1 cum) hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6.00 234.00 1404.00
Formwork @ 3% of (a+b+c) 25765.36
d) Overheads @ 20 % on (a+b+c) 176922.15
e) Contractors profit @ 10% on (a+b+c+d) 106153.29
cost of 120 cum = a+b+c+d+e 1167686.22
Rate per cum (a+b+c+d+e)/120 9730.72
Say 9731.00
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

3.13 304 Excavation for Structures

Page 44 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the exc
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
b) Overheads @ 10% on (a) 207.06
c) Contractors profit @ 10% on (a+b) 227.77
Cost for 10 cum = a+b+c 2505.44
Rate per cum = (a+b+c)/10 250.54
say 251.00
Note Cost of dewatering may be added where required upto 10 %
of labour cost Assessment for dewatering shall be made as
per site conditions..

B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 357 114.13
Mazdoor day 8.00 245 1956.48
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836 11016.00
c) Overheads @ 10% on (a+b) 1308.66
d) Contractors profit @ 10% on (a+b+c) 1439.53
Cost for 300 cum = a+b+c+d 15834.80
Rate per cum = (a+b+c+d)/300 52.78
say 53.00
Note Cost of dewatering upto 5% of (a+b) may be added, where
required. Assessment for dewatering shall be made as per
site conditions..

13.6 Section Supplying, fitting and placing HYSD/TMT bar


1600 & reinforcement in sub-structure complete as per
2200 drawing and technical specifications

Page 45 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage MT 1.05 53667.00 56350.35
Binding wire kg 6.00 85.00 510.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26
Blacksmith day 2.00 458.55 917.10
Mazdoor day 6.50 244.56 1589.64
c) Overheads @ 20 % on (a+b) 11897.67
d) Contractors profit @ 10% on (a+b+c) 7138.60
Rate for per MT (a+b+c+d) 78524.62
say 78525.00
14.1 1500 Furnishing and Placing Reinforced/Prestressed
&1600 cement concrete in super-structure as per drawing and
1700 Technical Specification
A RCC Grade M20
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 7200.00 294624.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.25 76.40 2311.10 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.15 59.80 1085.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 75.00 6352.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 717010.00

(i) For solid slab super-structure, 20-30% of (a+b+c)


(p) Height upto 5m

Page 46 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 717010.00
cum
d) Formwork and staging 20 % of (a+b+c) 20.00 143402.00
e) Overheads @ 20 % on (a+b+c+d) 172082.40
f) Contractors profit @ 10% on (a+b+c+d+e) 103249.44
Cost for 15 cum = a+b+c+d+e+f 1135743.84
Rate per cum (a+b+c+d+e+f)/120 9464.53
say 9465.00
B RCC Grade M25

Case II Using Batching Plant, Transit Mixer and Concrete


Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 7200.00 345240.00
Coarse sand cum 54.20 950.00 51490.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.25 76.40 2311.10 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.15 59.80 1085.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 75.00 6352.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 767816.00
For formwork and staging add the following:
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 767816.00
120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 153563.20
e) Overheads @ 20 % on (a+b+c+d) 184275.84
f) Contractors profit @ 10% on (a+b+c+d+e) 110565.50
Cost for 15 cum= a+b+c+d+e+f 1216220.54
Rate per cum (a+b+c+d+e+f)/120 10135.17

Page 47 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 10135.00
C RCC Grade M 30

Case II Using Batching Plant, Transit Mixer and Concrete


Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.79 7200.00 351288.00
Coarse sand cum 54.60 950.00 51870.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.25 76.40 2311.10 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.15 59.80 1085.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 75.00 6352.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 19.00 244.56 4646.64
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 774502.00
For formwork and staging add the following:

(i) For solid slab super-structure, 20-30% of (a+b+c)


(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 774502.00
cum
d) Formwork and staging 20 % of (a+b+c) 20.00 154900.40
e) Overheads @ 20 % on (a+b+c+d) 185880.48
f) Contractors profit @ 10% on (a+b+c+d+e) 111528.29
Cost for 15 cum = a+b+c+d+e+f 1226811.17
Rate per cum (a+b+c+d+e+f)/120 10223.43
say 10223.00
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP) 7745.00
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP) 6454.00

Page 48 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
E PSC Grade M-40
Case 1 Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.45 7200.00 46440.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.25 76.40 2311.10 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.15 59.80 1085.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 75.00 6352.50 14lit/Ton
( Masterplast APCL or equivalent)
Admixture @ 0.4% of cement kg 25.80 104.00 2683.20
b) Labour
Mate day 0.96 356.65 342.38
Mason day 2.00 458.55 917.10
Mazdoor day 22.00 244.56 5380.32
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum 99659.00

Case II Using Batching Plant, Transit Mixer and Concrete


Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 51.60 7200.00 371520.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.25 76.40 2311.10 5lit/Ton
Air entraining and water reducing plasticiser Lit 18.15 59.80 1085.37 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 75.00 6352.50 14lit/Ton
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1957.00 11742.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )

Page 49 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 40.00 120000.00 L= 10
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum 794660.00
For formwork and staging add the following:
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 794660.00
120 cum
d) Formwork and staging 18 % of (a+b+c) 18.00 143038.80
e) Overheads @ 20 % on (a+b+c+d) 187539.76
f) Contractors profit @ 10% on (a+b+c+d+e) 112523.86
Cost for 15 cum= a+b+c+d+e+f 1237762.42
Rate per cum (a+b+c+d+e+f)/120 10314.69
say 10315.00
Note 1.Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exac
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.
14.2 1600 A) Supplying ,fitting and placing TMT/HYSD bar
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
(a) With TATA make TMT CRS (Fe-500 grade) Rebar
a) Material
HYSD bars including 5% for laps and wastage MT 1.05 53667.00 56350.35
Binding wire Kg 8.00 85.00 680.00
b) Labour for cutting, bending, tying and placing in position

Mate day 0.44 356.65 156.93


Blacksmith day 3.00 458.55 1375.65
Mazdoor day 8.00 244.56 1956.48
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 60520.00
(b) With TATA make Rebar

a) Material
HYSD bars including 5% for laps and wastage MT 1.05 49667.00 52150.35

Page 50 of 959
DIRECTORY OF USED ITEMS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Binding wire Kg 8.00 85.00 680.00
b) Labour for cutting, bending, tying and placing in position

Mate day 0.44 356.65 156.93


Blacksmith day 3.00 458.55 1375.65
Mazdoor day 8.00 244.56 1956.48
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 56320.00
(c) With other make ISI marked Rebar
a) Material
HYSD bars including 5% for laps and wastage MT 1.05 55637.00 58418.85
Binding wire Kg 8.00 85.00 680.00
b) Labour for cutting, bending, tying and placing in position

Mate day 0.44 356.65 156.93


Blacksmith day 3.00 458.55 1375.65
Mazdoor day 8.00 244.56 1956.48
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 62588.00

Page 51 of 959
Analysis SOR (Roads) 2017-18
Chapter-1

CHAPTER-1
CARRIAGE OF MATERIALS
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1.1 Loading and Unloading by Mechanical Means cum
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
A Boulders
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 850.00 280.50 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 1341.00 442.53 P&M-017
cum/hour
b) Overhead charges @ 10% on (a) 72.30
c) Contractor's profit @ 10% on (a+b) 79.53
Cost for 5.5 cum = a+b+c 874.87
Rate per cum = (a+b+c)/ 5.5 159.07 80.00
Unloading will be by tipping. say 159.00 98.8%
B Stone aggregate
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.340 850.00 289.00 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.340 1341.00 455.94 P&M-017
cum/hour
b) Overhead charges @ 10% on (a) 74.49
c) Contractor's profit @ 10% on (a+b) 81.94
Cost for 5.5 cum = a+b+c 901.38
Rate per cum = (a+b+c)/ 5.5 163.89 82.00
Unloading will be by tipping. say 164.00 100.0%
C Sand/Moorum/flyash
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour

Page 1 of 959
Analysis SOR (Roads) 2017-18
Chapter-1

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.320 850.00 272.00
Front end-loader 1 cum bucket capacity @ 25 hour 0.320 1341.00 429.12
cum/hour
b) Overhead charges @ 10% on (a) 70.11
c) Contractor's profit @ 10% on (a+b) 77.12
Cost for 5.5 cum = a+b+c 848.36
Rate per cum = (a+b+c)/ 5.5 154.25 78.00
Unloading will be by tipping. say 154.00 97.4%

1.2 Loading and Unloading by Manual Means


A Boulders
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 356.65 39.23 L-12
Mazdoor for loading and unloading day 0.750 244.56 183.42 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.880 850.00 748.00 P&M-048
c) Overhead charges @ 10% on (a+b) 97.07
d) Contractor's profit @ 10% on (a+b+c) 106.77
Cost for5.5 cum = a+b+c+d 1174.49
Rate per cum = (a+b+c+d)/5.5 213.54 88.00
Unloading will be by tipping. say 214.00 143.2%

B Stone aggregate
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 356.65 39.23 L-12
Mazdoor for loading and unloading day 0.850 244.56 207.88 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.850 850.00 722.50 P&M-048
c) Overhead charges @ 10% on (a+b) 96.96
d) Contractor's profit @ 10% on (a+b+c) 106.66
Cost for5.5 cum = a+b+c+d 1173.23
Rate per cum = (a+b+c+d)/5.5 213.31 90.00
Unloading will be by tipping. say 213.00 136.7%

C Sand/Moorum/flyash
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 356.65 39.23 L-12
Mazdoor for loading and unloading day 0.650 244.56 158.96 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 850.00 637.50 P&M-048
c) Overhead charges @ 10% on (a+b) 83.57
d) Contractor's profit @ 10% on (a+b+c) 91.93

Page 2 of 959
Analysis SOR (Roads) 2017-18
Chapter-1

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for5.5 cum = a+b+c+d 1011.19
Rate per cum = (a+b+c+d)/5.5 183.85 86.00
Unloading will be by tipping. say 184.00 114.0%

1.3 Loading and Unloading of Cement or Steel by Manual


Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor for loading and unloading day 2.000 244.56 489.12 L-13
b) Machinery
Truck 10 tonne capacity hour 5.900 717.00 4230.30 P&M-057
c) Overhead charges @ 10% on (a+b) 474.80
d) Contractor's profit @ 10% on (a+b+c) 522.27
Cost for10 tonnes = a+b+c+d 5745.02
Rate per tonnes = (a+b+c+d)/10 574.50 97.00
say 575.00 492.8%
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100
t.km
Surfaced Road
Speed with load : 20 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.500 850.00 425.00 P&M-048
Time taken for empty return trip. hour 0.360 850.00 306.00 P&M-048
b) Overhead charges @ 10% on (a) 73.10
c) Contractor's profit @ 10% on (a+b) 80.41
cost for 100 t km = a+b+c 884.51
Rate per t.km = (a+b+c)/100 8.85 3.50
say 8.80 151.4%
Rate per cum say 16.00
1.4 Unsurfaced Graveled Road
Speed with load: 15 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.670 850.00 569.50 P&M-048
Time taken for empty return trip hour 0.400 850.00 340.00 P&M-048
b) Overhead charges @ 10% on (a) 90.95
c) Contractor's profit @ 10% on (a+b) 100.05
Cost for 100 t .km = a+b+c 1100.50
Rate per t.Km = (a+b+c)/100 11.00 6.36
say 11.00 73.0%
Rate per cum say 20.00

Page 3 of 959
Analysis SOR (Roads) 2017-18
Chapter-1

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1.4 Katcha Track and Track in River Bed/Nallah Bed and
Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 850.00 850.00 P&M-048
Time taken for empty return trip hour 0.670 850.00 569.50 P&M-048
b) Overhead charges @ 10% on (a) 141.95
c) Contractor's profit @ 10% on (a+b) 156.15
Cost for 100 t .km = a+b+c 1717.60
Rate per t.Km = (a+b+c)/100 17.18
say 17.20
Rate per cum say 31.30

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

CHAPTER-2
SITE CLEARANCE
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2.1 Cutting of Trees, including cutting of Trunks, Branches


and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
Unit = Each
Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoors for cutting trees including cutting, refilling, day 0.600 244.56 146.74 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 323.00 32.30 P&M-053
c) Overhead charges @ 10% on (a+b) 18.62
d) Contractor's profit @ 10% on (a+b+c) 20.48
Rate for each tree = a+b+c+d 225.26 113.00
say 225.00 99.1%
2.1 Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoors for cutting trees including cutting, refilling, day 0.900 244.56 220.10 L-13
compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 323.00 96.90 P&M-053
c) Overhead charges @ 10% on (a+b) 33.13
d) Contractor's profit @ 10% on (a+b+c) 36.44
Rate for each tree = a+b+c+d 400.84 229.00
say 401.00 75.1%
2.1 Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoors for cutting trees including cutting, refilling, day 2.000 244.56 489.12 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 323.00 129.20 P&M-053
c) Overhead charges @ 10% on (a+b) 64.69
d) Contractor's profit @ 10% on (a+b+c) 71.15
Rate for each tree = a+b+c+d 782.69 403.00
say 783.00 94.3%
2.1 Girth above 1800 mm
a) Labour
Mate day 0.160 356.65 57.06 L-12

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoors for cutting trees including cutting, refilling, day 4.000 244.56 978.24 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 323.00 193.80 P&M-053
c) Overhead charges @ 10% on (a+b) 122.91
d) Contractor's profit @ 10% on (a+b+c) 135.20
Rate for each tree = a+b+c+d 1487.22 728.00
say 1487.00 104.3%
2.2 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of 50
metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 356.65 713.30 L-12
Mazdoor day 50.000 244.56 12228.00 L-13
b) Overhead charges @ 10% on (a) 1294.13
c) Contractor's profit @ 10% on (a+b) 1423.54
Rate per Hectare = a+b+c 15658.97 6171.00
5297.00 195.620 say 15659.00 153.8%
2.3 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be us
Unit = Hectare
Taking output = 1 Hectare
By Manual Means:-
In area of light jungle
a) Labour
Mate day 6.000 356.65 2139.90 L-12
Mazdoor day 150.000 244.56 36684.00 L-13
b) Machinery
Tractor-trolley hour 1.000 323.00 323.00 P&M-053
c) Overhead charges @ 10% on (a+b) 3914.69
d) Contractor's profit @ 10% on (a+b+c) 4306.16
Rate per Hectare = a+b+c+d 47367.75 18904.00
16204.00 192.323 say 47368.00 150.6%
2.3 (i) In area of thorny jungle
a) Labour
Mate day 8.000 356.65 2853.20 L-12
Mazdoor day 200.000 244.56 48912.00 L-13
b) Machinery
Tractor-trolley hour 2.000 323.00 646.00 P&M-053
c) Overhead charges @ 10% on (a+b) 5241.12
d) Contractor's profit @ 10% on (a+b+c) 5765.23
Rate per Hectare = a+b+c+d 63417.55 15466.00
21814.00 190.722 say 63418.00 310.0%

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2.3 By Mechanical Means


In area of light jungle
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 4.000 244.56 978.24 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 3194.00 31940.00 P&M-014
stumps
Tractor-trolley hour 1.000 323.00 323.00 P&M-053
c) Overhead charges @ 10% on (a+b) 3329.83
d) Contractor's profit @ 10% on (a+b+c) 3662.81
Rate per Hectare = a+b+c+d 40290.95 39532.00
32753.00 23.015 say 40291.00 1.9%
2.3 (ii) In area of thorny jungle
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 12.000 3194.00 38328.00 P&M-014
stumps
Tractor-trolley hour 1.500 323.00 484.50 P&M-053
c) Overhead charges @ 10% on (a+b) 4036.55
d) Contractor's profit @ 10% on (a+b+c) 4440.20
Rate per Hectare = a+b+c+d 48842.20 47704.00
39524.00 23.576 say 48842.00 2.4%
2.4 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of un
Unit = cum
Taking output = 1.25 cum
Lime /Cement Concrete
By Manual Means
Lime Concrete, cement concrete grade M-10 and
below
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor for dismantling and loading day 1.000 244.56 244.56 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 34.60
d) Contractor's profit @ 10% on (a+b+c) 38.06
Cost for 1.25 cum = a+b+c+d 418.70
Rate per cum = (a+b+c+d)/ 1.25 334.96 183.00
152.00 120.395 say 335.00 83.1%

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2.4 (i) Cement Concrete Grade M-15 & M-20


a) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor for dismantling and loading day 1.250 244.56 305.70 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 41.07
d) Contractor's profit @ 10% on (a+b+c) 45.18
Cost for 1.25 cum = a+b+c+d 497.00
Rate per cum = (a+b+c+d)/ 1.25 397.60 208.00
173.00 130.058 say 398.00 91.3%
2.4 (i) Prestressed / Reinforced cement concrete grade M-20
& above
a) Labour
Mate day 0.150 356.65 53.50 L-12
Blacksmith day 0.250 458.55 114.64 L-02
Mazdoor for dismantling, loading and unloading day 3.500 244.56 855.96 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 111.13
d) Contractor's profit @ 10% on (a+b+c) 122.24
Cost for 1.25 cum = a+b+c+d 1344.68
Rate per cum = (a+b+c+d)/ 1.25 1075.74 470.00
401.00 168.329 say 1076.00 128.9%
2.4 By Mechanical Means for items No. 202( b)& ( c)
Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor for loading and unloading day 0.250 244.56 61.14 L-13
Mazdoor with Pneumatic breaker day 0.250 356.65 89.16 L-15
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 0.670 435.00 291.45 P&M-001
breaker @ 1.5 cum per hour
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 53.61
d) Contractor's profit @ 10% on (a+b+c) 58.97
Cost for 1.25 cum = a+b+c+d 648.68
Rate per cum = (a+b+c+d)/ 1.25 518.94 318.00
261.00 98.851 say 519.00 63.2%
2.4 II Prestressed / reinforced cement concrete grade M-20
& above
a) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor with Pneumatic breaker day 0.660 285.32 188.31 L-14
Blacksmith day 0.250 458.55 114.64 L-02
Mazdoor for loading and unloading day 0.250 244.56 61.14 L-13

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 1.000 435.00 435.00 P&M-001
breaker @ 1.00 cum per hour
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 90.41
d) Contractor's profit @ 10% on (a+b+c) 99.45
Cost for 1.25 cum = a+b+c+d 1094.00
Rate per cum = (a+b+c+d)/ 1.25 875.20 491.00
412.00 112.379 say 875.00 78.2%
2.4 Dismantling Brick / Tile work
In lime mortar
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor for dismantling, loading and unloading day 0.500 244.56 122.28 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 21.66
d) Contractor's profit @ 10% on (a+b+c) 23.83
Cost for 1.25 cum = a+b+c+d 262.11
Rate per cum = (a+b+c+d)/ 1.25 209.69 134.00
110.00 90.909 say 210.00 56.7%
2.4 (ii) In cement mortar
a) Labour
Mate day 0.030 356.65 10.70 L-12
Mazdoor for dismantling, loading and unloading day 0.750 244.56 183.42 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 28.13
d) Contractor's profit @ 10% on (a+b+c) 30.95
Cost for 1.25 cum = a+b+c+d 340.41
Rate per cum = (a+b+c+d)/ 1.25 272.33 158.00
131.00 107.634 say 272.00 72.2%
2.4 (ii) In mud mortar
a) Labour
Mate day 0.016 356.65 5.71 L-12
Mazdoor for dismantling and loading day 0.400 244.56 97.82 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 19.07
d) Contractor's profit @ 10% on (a+b+c) 20.98
Cost for 1.25 cum = a+b+c+d 230.80
Rate per cum = (a+b+c+d)/ 1.25 184.64 124.00
101.00 83.168 say 185.00 49.2%
2.4 (ii) Dry brick pitching or brick soling
a) Labour
Mate day 0.014 356.65 4.99 L-12

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoor for Dismantling, loading and unloading day 0.350 244.56 85.60 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 17.78
d) Contractor's profit @ 10% on (a+b+c) 19.56
Cost for 1.25 cum = a+b+c+d 215.14
Rate per cum = (a+b+c+d)/ 1.25 172.11 119.00
97.00 77.320 say 172.00 44.5%
2.4 Dismantling Stone Masonry
Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 356.65 8.56 L-12
Mazdoor for dismantling, loading and unloading. day 0.600 244.56 146.74 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 24.25
d) Contractor's profit @ 10% on (a+b+c) 26.68
Cost for 1.25 cum = a+b+c+d 293.43
Rate per cum = (a+b+c+d)/ 1.25 234.75 144.00
118.00 99.153 say 235.00 63.2%
2.4 (iii) Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 356.65 10.70 L-12
Mazdoor for dismantling, loading and unloading. day 0.750 244.56 183.42 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 28.13
d) Contractor's profit @ 10% on (a+b+c) 30.95
Cost for 1.25 cum = a+b+c+d 340.41
Rate per cum = (a+b+c+d)/ 1.25 272.33 158.00
131.00 107.634 say 272.00 72.2%
2.4 (iii) Rubble Stone Masonry in mud mortar.
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor for dismantling, loading and unloading. day 0.500 244.56 122.28 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 21.66
d) Contractor's profit @ 10% on (a+b+c) 23.83
Cost for 1.25 cum = a+b+c+d 262.11
Rate per cum = (a+b+c+d)/ 1.25 209.69 134.00
110.00 90.909 say 210.00 56.7%

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2.4 (iii) Dry rubble masonry


a) Labour
Mate day 0.018 356.65 6.42 L-12
Mazdoor for dismantling, loading and unloading. day 0.450 244.56 110.05 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 20.37
d) Contractor's profit @ 10% on (a+b+c) 22.40
Cost for 1.25 cum = a+b+c+d 246.45
Rate per cum = (a+b+c+d)/ 1.25 197.16 129.00
106.00 85.849 say 197.00 52.7%
2.4 (iii) Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 356.65 5.71 L-12
Mazdoor for dismantling, loading and unloading. day 0.400 244.56 97.82 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 19.07
d) Contractor's profit @ 10% on (a+b+c) 20.98
Cost for 1.25 cum = a+b+c+d 230.80
Rate per cum = (a+b+c+d)/ 1.25 184.64 124.00
101.00 83.168 say 185.00 49.2%
2.4 (iii) Dismantling boulders laid in wire crates including
opening of crates and stacking dismantled materials.

a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor for dismantling, loading and unloading day 0.500 244.56 122.28 L-13
b) Machinery
Tractor-trolley hour 0.290 323.00 93.67 P&M-053
c) Overhead charges @ 10% on (a+b) 22.31
d) Contractor's profit @ 10% on (a+b+c) 24.54
Cost for 1.25 cum = a+b+c+d 269.93
Rate per cum = (a+b+c+d)/ 1.25 215.94 134.00
110.00 96.364 say 216.00 61.2%
2.4 Wood Work wrought framed and fixed in frames of
trusses upto a height of 5 m above plinth level
a) Labour
Mate day 0.060 356.65 21.40 L-12
Carpenter day 0.500 458.55 229.28 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 244.56 244.56 L-13
b) Machinery
Tractor-trolley hour 0.270 323.00 87.21 P&M-053
c) Overhead charges @ 10% on (a+b) 58.24
d) Contractor's profit @ 10% on (a+b+c) 64.07
Cost for 1.25 cum = a+b+c+d 704.76

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Rate per cum = (a+b+c+d)/ 1.25 563.81 263.00


214.00 163.551 say 564.00 114.4%

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2.4 Steel Work in all types of sections upto a height of 5 m


above plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne
Including dismembering
a) Labour
Mate day 0.140 356.65 49.93 L-12
Blacksmith day 1.000 458.55 458.55 L-02
Mazdoor for dismantling, loading and unloading day 2.500 244.56 611.40 L-13
Add 2.5 per cent of cost of labour for gas cutting, ropes, 28.00
pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 323.00 54.91 P&M-053
c) Overhead charges @ 10% on (a+b) 120.28
d) Contractor's profit @ 10% on (a+b+c) 132.31
Rate per tonne = a+b+c+d 1455.37 587.00
515.00 182.524 say 1455.00 147.9%
2.4 (v) Excluding dismembering.
a) Labour
Mate day 0.220 356.65 78.46 L-12
Mazdoor for dismantling, loading and unloading day 2.000 244.56 489.12 L-13
Blacksmith day 0.500 458.55 229.28 L-02
Add 2.5 per cent of cost of labour for gas cutting, ropes, 19.92
pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 323.00 54.91 P&M-053
c) Overhead charges @ 10% on (a+b) 87.17
d) Contractor's profit @ 10% on (a+b+c) 95.89
Rate per tonne = a+b+c+d 1054.74 440.00
379.00 178.364 say 1055.00 139.8%
2.4 (v) Extra over item No( v ) A and( v ) B for cutting rivets.

Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 356.65 3.57 L-12
Blacksmith day 0.130 458.55 59.61 L-02
Mazdoor day 0.130 244.56 31.79 L-13
b) Overhead charges @ 10% on (a) 9.50
c) Contractor's profit @ 10% on (a+b) 10.45
Cost for 10 rivets = a+b+c 114.91
Rate for each rivet = ( a+b+c)/10 11.49 4.00
4.00 175.000 say 11.00 175.0%
2.4 Scraping of Bricks Dismantled from Brick Work
including Stacking.
Unit = numbers
Taking output = 1000 numbers

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

In lime/Cement mortar
a) Labour
Mate day 0.140 356.65 49.93 L-12
Mazdoor day 3.500 244.56 855.96 L-13
b) Overhead charges @ 10% on (a) 90.59
c) Contractor's profit @ 10% on (a+b) 99.65
Rate per1000 Nos = a+b+c 1096.13 432.00
371.00 195.418 say 1096.00 153.7%
2.4 (iv) In mud mortar
a) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor day 1.250 244.56 305.70 L-13
b) Overhead charges @ 10% on (a) 32.35
c) Contractor's profit @ 10% on (a+b) 35.59
Rate per1000 Nos = a+b+c 391.47 154.00
132.00 196.212 say 391.00 153.9%
2.4 Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
In cement and lime mortar
a) Labour
Mate day 0.060 356.65 21.40 L-12
Mazdoor day 1.400 244.56 342.38 L-13
b) Overhead charges @ 10% on (a) 36.38
c) Contractor's profit @ 10% on (a+b) 40.02
Rate per cum = a+b+c 440.18 173.00
149.00 195.302 say 440.00 154.3%
2.4 In Mud mortar
(vii)
a) Labour
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.300 244.56 73.37 L-13
b) Overhead charges @ 10% on (a) 7.69
c) Contractor's profit @ 10% on (a+b) 8.46
Rate per cum = a+b+c 93.09 37.00
32.00 190.625 say 93.00 151.4%
2.4 Scarping Plaster in Lime or Cement Mortar from Brick/
Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor for scarping and loading day 5.000 244.56 1222.80 L-13
b) Machinery
Tractor-trolley hour 0.320 323.00 103.36 P&M-053
c) Overhead charges @ 10% on (a+b) 138.32

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

d) Contractor's profit @ 10% on (a+b+c) 152.15


Cost for 100 sqm = a+b+c+d 1673.70
Rate per sqm = (a+b+c+d)/100 16.74 6.00
5.00 240.000 say 17.00 183.3%
2.4 Removing all type of Hume Pipes and Stacking within
a lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.
Unit = metre
Taking output = 1 metre
Up to 600 mm dia
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor day 0.520 244.56 127.17 L-13
b) Overhead charges @ 10% on (a) 13.43
c) Contractor's profit @ 10% on (a+b) 14.77
Rate per metre = a+b+c 162.51 64.00
55.00 196.364 say 163.00 154.7%
2.4 (ix) Above 600 mm to 900 mm dia
a) Labour
Mate day 0.030 356.65 10.70 L-12
Mazdoor day 0.700 244.56 171.19 L-13
b) Overhead charges @ 10% on (a) 18.19
c) Contractor's profit @ 10% on (a+b) 20.01
Rate per metre = a+b+c 220.09 87.00
74.00 197.297 say 220.00 152.9%
2.4 (ix) Above 900 mm
a) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor day 1.200 244.56 293.47 L-13
b) Overhead charges @ 10% on (a) 31.13
c) Contractor's profit @ 10% on (a+b) 34.24
Rate per metre = a+b+c 376.68 148.00
127.00 196.850 say 377.00 154.7%
1. The excavation of earth, dismantling of stone masonry
work in head walls and protection works is not included
which is to be measured and paid separately.
2. Credit for retrieved stone from masonry work may be
taken as per actual availability.
2.5 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately
Unit = cum
Taking output = 1 cum
By Manual Means
Bituminous courses
a) Labour

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mate day 0.060 356.65 21.40 L-12


Mazdoor for dismantling, loading and unloading day 1.500 244.56 366.84 L-13
b) Machinery
Tractor-trolley hour 0.380 323.00 122.74 P&M-053
c) Overhead charges @ 10% on (a+b) 51.10
d) Contractor's profit @ 10% on (a+b+c) 56.21
Rate per cum = a+b+c+d 618.28 334.00
278.00 122.302 say 618.00 85.0%
2.5 I Granular courses
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 244.56 244.56 L-13
b) Machinery
Tractor-trolley hour 0.330 323.00 106.59 P&M-053
c) Overhead charges @ 10% on (a+b) 36.54
d) Contractor's profit @ 10% on (a+b+c) 40.20
Rate per cum = a+b+c+d 442.15 252.00
209.00 111.483 say 442.00 75.4%
2.5 By Mechanical Means
Bituminous course
a) Labour
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.300 244.56 73.37 L-13
b) Machinery
Tractor-trolley hour 0.380 323.00 122.74 P&M-053
Farm tractor with ripper @ 60 cum per hour hour 0.017 440.00 7.48 P&M-055
c) Overhead charges @ 10% on (a+b) 20.72
d) Contractor's profit @ 10% on (a+b+c) 22.79
Rate per cum = a+b+c+d 250.66 194.00
156.00 60.897 say 251.00 29.4%
2.6 Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by mechanical
means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials
up to a lead of 1000 metres, stacking serv
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 356.65 10.70 L-12
Semi skilled mazdoor for operating pneumatic tools day 0.500 285.32 142.66 L-14
Mazdoors as helpers including loading and unloading day 0.500 244.56 122.28 L-13

b) Machinery
Air compressor 250 cfm with two leads for pneumatic hour 1.000 435.00 435.00 P&M-001
cutters/ hammers @ 1 cum per hour
Tractor-trolley hour 0.400 323.00 129.20 P&M-053

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Joint Cutting Machine with 2-3 blades hour 1.000 150.00 150.00 P&M-083
c) Overhead charges @ 10% on (a+b) 98.98
d) Contractor's profit @ 10% on (a+b+c) 108.88
Rate per cum = a+b+c+d 1197.71 805.00
#DIV/0! say 1198.00 48.8%
The above analysis is for removal of complete pavement. In
case full depth repair work is required to be done after
dismantling, provision of a concrete cutting and sawing
machine may be added for 0.25 hours.
2.7 Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable materials and unserviceable
materials separately.
Unit = running metre
Taking output = 1 metre
a) Labour
Mate day 0.006 356.65 2.14 L-12
Mazdoor including loading and unloading day 0.150 244.56 36.68 L-13
b) Machinery
Tractor-trolley hour 0.050 323.00 16.15 P&M-053
c) Overhead charges @ 10% on (a+b) 5.50
d) Contractor's profit @ 10% on (a+b+c) 6.05
Rate per metre = a+b+c+d 66.52 38.00
32.00 109.375 say 67.00 76.3%
2.8 Dismantling of Kerb Stone
Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.010 356.65 3.57 L-12
Mazdoor including loading and unloading day 0.150 244.56 36.68 L-13
b) Machinery
Tractor-trolley hour 0.200 323.00 64.60 P&M-053
c) Overhead charges @ 10% on (a+b) 10.49
d) Contractor's profit @ 10% on (a+b+c) 11.53
Cost for 10 m = a+b+c+d 126.87
Rate per metre = (a+b+c+d)/10 12.69 10.00
8.00 62.500 say 13.00 30.0%
2.9 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mate day 0.015 356.65 5.35 L-12


Mazdoor including loading and unloading day 0.225 244.56 55.03 L-13
b) Machinery
Tractor-trolley hour 0.300 323.00 96.90 P&M-053
c) Overhead charges @ 10% on (a+b) 15.73
d) Contractor's profit @ 10% on (a+b+c) 17.30
Cost for 10 m = a+b+c+d 190.30
Rate per metre = (a+b+c+d)/10 19.03 15.00
12.00 58.333 say 19.00 26.7%

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2.10 Dismantling of Kilometre Stone


Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone
5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 356.65 46.36 L-12
Mazdoor day 0.750 244.56 183.42 L-13
b) Machinery
Tractor-trolley hour 0.150 323.00 48.45 P&M-053
c) Overhead charges @ 10% on (a+b) 27.82
d) Contractor's profit @ 10% on (a+b+c) 30.61
Rate for one 5th KM stone = a+b+c+d 336.66 166.00
137.00 145.985 say 337.00 103.0%
Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor day 0.500 244.56 122.28 L-13
b) Machinery
Tractor-trolley hour 0.100 323.00 32.30 P&M-053
c) Overhead charges @ 10% on (a+b) 16.17
d) Contractor's profit @ 10% on (a+b+c) 17.79
Rate for one ordinary KM stone = a+b+c+d 195.67 101.00
84.00 133.333 say 196.00 94.1%
Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 356.65 1.43 L-12
Mazdoor day 0.110 244.56 26.90 L-13
b) Machinery
Tractor-trolley hour 0.020 323.00 6.46 P&M-053
c) Overhead charges @ 10% on (a+b) 3.48
d) Contractor's profit @ 10% on (a+b+c) 3.83
Rate for one Hectometre stone = a+b+c+d 42.09 20.00
17.00 147.059 say 42.00 110.0%
2.11 Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing
including posts, foundation concrete, back filling of pit by
manual means including disposal of dismantled material with
all lifts and up to a lead of 1000 metres, stacking serviceable
material and uns
Unit = running metre
Taking output = 30 metres

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

a) Labour
Mate day 0.150 356.65 53.50 L-12
Mazdoor including loading and unloading day 3.000 244.56 733.68 L-13
Blacksmith day 0.750 458.55 343.91 L-02
b) Machinery
Tractor-trolley hour 0.200 323.00 64.60 P&M-053
c) Overhead charges @ 10% on (a+b) 119.57
d) Contractor's profit @ 10% on (a+b+c) 131.53
Cost for 30 metres = a+b+c+d 1446.78
Rate per metre = (a+b+c+d)/30 48.23 19.00
17.00 182.353 say 48.00 152.6%
2.12 Dismantling of CI Water Pipe Line
Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking
of serviceable material and unserviceable material
separately under supervision of concerned department

Unit = running metre


Taking output = 10 metres
a) Labour
Mate day 0.090 356.65 32.10 L-12
Mazdoor day 2.000 244.56 489.12 L-13
Plumber day 0.250 458.55 114.64 L-02
b) Machinery
Truck 10 tonne capacity hour 0.250 717.00 179.25 P&M-057
Light Crane 3 tonne capacity hour 0.500 318.00 159.00 P&M-013
c) Overhead charges @ 10% on (a+b) 97.41
d) Contractor's profit @ 10% on (a+b+c) 107.15
Cost for 10 metres = a+b+c+d 1178.67
Rate per metre = (a+b+c+d)/10 117.87 58.00
50.00 136.000 say 118.00 103.4%
The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.
2.13 Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm
dia under the supervision of concerned department including
disposal with all lifts and up to a lead of 1000 metres and
stacking of serviceable and unserviceable material
separately but excluding ear
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.100 356.65 35.67 L-12
Mazdoor day 2.500 244.56 611.40 L-13
b) Machinery
Crane 5 tonne capacity hour 0.300 725.00 217.50 P&M-070
Truck flat body 10 tonne hour 1.000 717.00 717.00 P&M-057

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-2

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

c) Overhead charges @ 10% on (a+b) 158.16


d) Contractor's profit @ 10% on (a+b+c) 173.97
Cost for 10 metres = a+b+c+d 1913.69
Rate per metre = (a+b+c+d)/10 191.37 93.00
79.00 141.772 say 191.00 105.4%
The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.
2.14 Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation
and dismantling of foundation concrete and lines under the
supervision of concerned department, disposal with all lifts
and up to a lead of 1000 metres and stacking the
serviceable and unserviceab
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 356.65 171.19 L-12
Mazdoor day 10.200 244.56 2494.51 L-13
Electrician/Lineman day 2.000 458.55 917.10 L-02
b) Machinery
Tractor-trolley hour 1.500 323.00 484.50 P&M-053
c) Overhead charges @ 10% on (a+b) 406.73
d) Contractor's profit @ 10% on (a+b+c) 447.40
Cost for 30 poles = a+b+c+d 4921.44
Rate per pole = (a+b+c+d)/30 164.05
63.00 160.317 say 164.00

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
3.1 Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 356.65 641.97 L-12
Mazdoor day 45.000 244.56 11005.20 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 717.00 7170.00 P&M-057
c) Overhead charges @ 10% on (a+b) 1881.72
d) Contractor's profit @ 10% on (a+b+c) 2069.89
Cost of 120 cum = a+b+c+d 22768.78
Rate per cum = (a+b+c+d)/120 189.74 77.00
say 190.00 146.8%
In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
a) Labour
Mate day 1.800 356.65 641.97 L-12
Mazdoor day 45.000 244.56 11005.20 L-13
b) Machinery
c) Overhead charges @ 10% on (a+b) 1164.72
d) Contractor's profit @ 10% on (a+b+c) 1281.19
Cost of 120 cum = a+b+c+d 14093.08
Rate per cum = (a+b+c+d)/120 117.44 46.00
say 117.00 154.3%
3.2 Excavation in Ordinary Rock by Manual Means
Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 356.65 998.62 L-12
Mazdoor day 70.000 244.56 17119.20 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 717.00 7170.00 P&M-057
c) Overhead charges @ 10% on (a+b) 2528.78
d) Contractor's profit @ 10% on (a+b+c) 2781.66
Cost for 120 cum = a+b+c+d 30598.26
Rate per cum = (a+b+c+d)/120 254.99 102.00
say 255.00 150.0%
In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
a) Labour

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 2.800 356.65 998.62 L-12
Mazdoor day 70.000 244.56 17119.20 L-13
b) Machinery
c) Overhead charges @ 10% on (a+b) 1811.78
d) Contractor's profit @ 10% on (a+b+c) 1992.96
Cost for 120 cum = a+b+c+d 21922.56
Rate per cum = (a+b+c+d)/120 182.69 72.00
say 183.00 154.2%

3.3 Excavation in Soil with Dozer with lead upto 100


metres

Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3194.00 19164.00 P&M-014
c) Overhead charges @ 10% on (a+b) 1968.17
d) Contractor's profit @ 10% on (a+b+c) 2164.98
Cost for 180 cum = a+b+c+d 23814.80
Rate per cum = (a+b+c+d)/180 132.30 130.00
say 132.00 1.5%
3.4 Excavation in Ordinary Rock with Dozer with lead upto
100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirem
Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 3194.00 19164.00 P&M-014
c) Overhead charges @ 10% on (a+b) 1994.05
d) Contractor's profit @ 10% on (a+b+c) 2193.45
Cost for 108 cum = a+b+c+d 24127.98
Rate per cum = (a+b+c+d)/108 223.41 218.00
say 223.00 2.3%
3.5 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts an
Unit = cum
Taking 0utput = 180 cum

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.220 356.65 78.46 L-12
Mazdoor day 3.000 244.56 733.68 L-13
Driller day 2.000 356.65 713.30 L-06
Blaster day 0.250 356.65 89.16 L-03
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 7.500 3194.00 23955.00 P&M-014
Air compressor, 250 cfm with 2 jack hammer hour 6.000 435.00 2610.00 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper10 tonne capacity hour 11.250 850.00 9562.50 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 72.00 4536.00 M-104
Electric Detonators @ 1 detonator for 2 gelatin sticks of each 252.000 15.00 3780.00 M-097 /100
125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 (186.00) (16740.00) M-092
per cent quantity blasted
d) Overhead charges @ 10% on (a+b+c) 3736.41
e) Contractor's profit @ 10% on (a+b+c+d) 4110.05
Cost for 180 cum = a+b+c+d+e 45210.57
Rate per cum = (a+b+c+d+e)/180 251.17 161.00
say 251.00 55.9%
1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
3.6 Excavation in Soil using Hydraulic Excavator CK 90
and Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the emb
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 1836.00 11016.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 850.00 13600.00 P&M-048
c) Overhead charges @ 10% on (a+b) 2513.37
d) Contractor's profit @ 10% on (a+b+c) 2764.70
Cost for 360 cum = a+b+c+d 30411.72
Rate per cum = (a+b+c+d)/360 84.48 51.00
say 84.00 64.7%

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
3.7 Excavation in Ordinary Rock using Hydraulic
Excavator CK-90 and Tippers with Disposal upto 1000
metres.
Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 1836.00 11016.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 850.00 9350.00 P&M-048
c) Overhead charges @ 10% on (a+b) 2088.37
d) Contractor's profit @ 10% on (a+b+c) 2297.20
Cost for 240 cum = a+b+c+d 25269.22
Rate per cum = (a+b+c+d)/240 105.29 66.00
say 105.00 59.1%
3.8 Excavation in Hard Rock (blasting prohibited)
Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines
Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor for trimming slopes including mannul loading day 10.000 244.56 2445.60 L-13
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 7.800 1836.00 14320.80 P&M-026
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 850.00 5525.00 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 18.000 (186.00) (3348.00) M-092
per cent of excavated quantity
c) Overhead charges @ 10% on (a+b) 1908.61
d) Contractor's profit @ 10% on (a+b+c) 2099.47
Cost for 36 cum = a+b+c+d 23094.13
Rate per cum = (a+b+c+d)/36 641.50 313.00
say 642.00 105.1%

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.
3.8 Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 356.65 584.91 L-12
Mazdoor including loading in truck day 16.000 244.56 3912.96 L-13
Chiseller day 24.000 285.32 6847.68 L-05
Blacksmith day 1.000 458.55 458.55 L-02
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 850.00 2465.00 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 8.000 (186.00) (1488.00) M-092
per cent of excavated
c) Overhead charges @ 10% on (a+b) 1278.11
d) Contractor's profit @ 10% on (a+b+c) 1405.92
Cost for 16 cum = a+b+c+d 15465.13
Rate per cum = (a+b+c+d)/16 966.57 418.00
say 967.00 131.3%
1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
3.9 Excavation in Hard Rock (controlled blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 356.65 78.46 L-12
Mazdoor day 3.000 244.56 733.68 L-13
Driller day 2.000 356.65 713.30 L-06
Blaster day 0.500 356.65 178.33 L-03
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 7.500 3194.00 23955.00 P&M-014
Air compressor, 250 cfm with 2 jack hammers hour 6.000 435.00 2610.00 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 850.00 6970.00 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 72.00 4536.00 M-104
Electric Detonators @ 1 detonator for1/2 gelatin stick each 1008.000 15.00 15120.00 M-097 /100
of 125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 (186.00) (16740.00) M-092
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling 3147.04
arrangements to guard against any rock fly off during
blasting
d) Overhead charges @ 10% on (a+b+c) 4934.78
e) Contractor's profit @ 10% on (a+b+c+d) 5428.26
Cost for 180 cum = a+b+c+d+e 59710.85
Rate per cum = (a+b+c+d+e)/180 331.73 184.00
say 332.00 80.4%
1. Credit is considered for 50 per cent of quantity of
blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
3.10 Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 hour 6.000 1836.00 11016.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 850.00 11594.00 P&M-048
c) Overhead charges @ 10% on (a+b) 2312.77
d) Contractor's profit @ 10% on (a+b+c) 2544.04
Cost for 300 cum = a+b+c+d 27984.46
Rate per cum = (a+b+c+d)/300 93.28 57.00
say 93.00 63.2%
3.11 Removal of Unserviceable Soil with Disposal upto
1000 metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour 6.000 1836.00 11016.00 P&M-026
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 850.00 13906.00 P&M-048
c) Overhead charges @ 10% on (a+b) 2543.97
d) Contractor's profit @ 10% on (a+b+c) 2798.36
Cost for 360 cum = a+b+c+d 30781.98
Rate per cum = (a+b+c+d)/360 85.51 51.00
say 86.00 68.6%
This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock
face)
a) Labour
Mate day 0.600 356.65 213.99 L-12
Mazdoor day 15.000 244.56 3668.40 L-13
b) Machinery
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 435.00 2610.00 P&M-001
hour
Dozer, 80 HP hour 7.800 3194.00 24913.20 P&M-014
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
c) Materials
Gelatin 80 per cent kg 42.000 72.00 3024.00 M-104
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 15.00 10080.00 M-097 /100
of 125 gms each
d) Overhead charges @ 10% on (a+b+c) 5255.56
e) Contractor's profit @ 10% on (a+b+c+d) 5781.11
Cost for 400 sqm = a+b+c+d+e 63592.26
Rate per sqm = (a+b+c+d+e)/400 158.98 100.00
say 159.00 59.0%
In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
3.13 Excavation for Structures

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the exca
Ordinary soil
Unit = cum
Taking output = 10 cum
Manual Means (Depth upto 3 m)(Without dewatering)

a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
b) Overhead charges @ 10% on (a) 207.06
c) Contractor's profit @ 10% on (a+b) 227.77
Cost for 10 cum = a+b+c 2505.44
Rate per cum = (a+b+c)/10 250.54 99.00
say 251.00 153.5%
Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
Manual Means (Depth upto 3 m)(With dewatering)
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
Cost of dewatering @ 10 per cent of labour cost 207.06
b) Overhead charges @ 10% on (a) 207.06
c) Contractor's profit @ 10% on (a+b) 248.47
Cost for 10 cum = a+b+c 2733.20
Rate per cum = (a+b+c)/10 273.32 108.00
say 273.00 152.8%
3.13 (i) Mechanical Means (Depth upto 3 m)(Without
dewatering)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1836.00 11016.00 P&M-026
c) Overhead charges @ 10% on (a+b) 1308.66
d) Contractor's profit @ 10% on (a+b+c) 1439.53
Cost for 300 cum = a+b+c+d 15834.80
Rate per cum = (a+b+c+d)/300 52.78 37.00
say 53.00 43.2%

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means (Depth upto 3 m)(Without
dewatering)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1836.00 11016.00 P&M-026
Cost of dewatering @ 5% on (a+b) 654.33
c) Overhead charges @ 10% on (a+b) 1308.66
d) Contractor's profit @ 10% on (a+b+c) 1504.96
Cost for 300 cum = a+b+c+d 16554.56
Rate per cum = (a+b+c+d)/300 55.18 38.00
say 55.00 44.7%
3.13 Ordinary Rock (not requiring blasting)
Manual Means (Depth upto 3 m)(Without dewatering)

Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
b) Overhead charges @ 10% on (a) 258.83
c) Contractor's profit @ 10% on (a+b) 284.71
Cost for 10 cum = a+b+c 3131.79
Rate per cum = (a+b+c)/10 313.18 123.00
say 313.00 154.5%
Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 Manual Means (Depth upto 3 m)(With dewatering)
(ii)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
Cost of dewatering @ 10 per cent of labour cost 258.83
b) Overhead charges @ 10% on (a) 258.83
c) Contractor's profit @ 10% on (a+b) 310.59
Cost for 10 cum = a+b+c 3416.50

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c)/10 341.65 135.00
say 342.00 153.3%
Mechanical Means (Depth upto 3 m)(Without
dewatering)
Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1836.00 11016.00 P&M-026
c) Overhead charges @ 10% on (a+b) 1256.90
d) Contractor's profit @ 10% on (a+b+c) 1382.59
Cost for 216 cum = a+b+c+d 15208.44
Rate per cum = (a+b+c+d)/216 70.41 50.00
say 70.00 40.0%
1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Mechanical Means (Depth upto 3 m)(With dewatering)

Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1836.00 11016.00 P&M-026
Cost of dewatering @ 5% on (a+b) 628.45
c) Overhead charges @ 10% on (a+b) 1256.90
d) Contractor's profit @ 10% on (a+b+c) 1445.43
Cost for 216 cum = a+b+c+d 15899.73
Rate per cum = (a+b+c+d)/216 73.61 52.00
say 74.00 42.3%
3.13 Hard Rock ( requiring blasting )
Manual Means (Without dewatering)
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 356.65 189.02 L-12
ii) Driller day 0.840 356.65 299.59 L-06
iii) Blaster day 0.400 356.65 142.66 L-03
iv) Mazdoor day 12.000 244.56 2934.72 L-13

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 435.00 290.00 P&M-001
per hour
c) Material
Blasting Material kg 3.500 72.00 252.00 M-104
Detonator electric each 14.000 15.00 210.00 M-097 /100

d) Overhead charges @ 10% on (a+b+c) 431.80


e) Contractor's profit @ 10% on (a+b+c+d) 474.98
Cost for 10 cum = a+b+c+d+e 5224.77
Rate per cum = (a+b+c+d+e)/10 522.48 240.00
say 522.00 117.5%
Cost of dewatering @ 10 per cent of labour cost may be
added, where required Assessment for dewatering shall be
made as per site conditions.
Manual Means (Without dewatering)
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 356.65 189.02 L-12
ii) Driller day 0.840 356.65 299.59 L-06
iii) Blaster day 0.400 356.65 142.66 L-03
iv) Mazdoor day 12.000 244.56 2934.72 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 435.00 290.00 P&M-001
per hour
c) Material
Blasting Material kg 3.500 72.00 252.00 M-104
Detonator electric each 14.000 15.00 210.00 M-097 /100

Cost of dewatering @ 10 per cent of labour cost 356.60


d) Overhead charges @ 10% on (a+b+c) 431.80
e) Contractor's profit @ 10% on (a+b+c+d) 510.64
Cost for 10 cum = a+b+c+d+e 5617.03
Rate per cum = (a+b+c+d+e)/10 561.70 255.00
say 562.00 120.4%

3.13 Hard Rock ( blasting prohibited )


Unit = cum
Taking output = 10 cum
A Mechanical Means (Without dewatering)
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 435.00 4350.00 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 10% on (a+b) 564.41
d) Contractor's profit @ 10% on (a+b+c) 620.85
Cost for 10 cum = a+b+c+d 6829.40
Rate per cum = (a+b+c+d)/10 682.94 405.00
say 683.00 68.6%
B Mechanical Means (With dewatering)
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 435.00 4350.00 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 10% on (a+b) 564.41
Cost of dewatering @ 5% on (a+b) 282.21
d) Contractor's profit @ 10% on (a+b+c) 649.07
Cost for 10 cum = a+b+c+d 7139.82
Rate per cum = (a+b+c+d)/10 713.98 510.00
say 714.00 40.0%
1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)(Without dewatering)

a) Labour
Mate/Supervisor day 0.400 356.65 142.66 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Tractor-trolley hour 2.670 323.00 862.41 P&M-053
c) Material
Selected earth for refilling cum 5.000 165.00 825.00 M-163
d) Overhead charges @ 10% on (a+b+c) 427.57
e) Contractor's profit @ 10% on (a+b+c+d) 470.32
Cost for 10 cum = a+b+c+d+e 5173.56
Rate per cum = ( a+b+c+d+e)/ 10 517.36 303.00
say 517.00 70.6%
1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
A Manual means ( upto 3 m depth)(With dewatering)
a) Labour
Mate/Supervisor day 0.400 356.65 142.66 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Tractor-trolley hour 2.670 323.00 862.41 P&M-053
c) Material
Selected earth for refilling cum 5.000 165.00 825.00 M-163
Cost of dewatering @ 30 per cent of labour cost 776.48
d) Overhead charges @ 10% on (a+b+c) 427.57
e) Contractor's profit @ 10% on (a+b+c+d) 547.97
Cost for 10 cum = a+b+c+d+e 6027.69
Rate per cum = ( a+b+c+d+e)/ 10 602.77 337.00
say 603.00 78.9%

3.13 Mechanical Means (Without dewatering)


(v)
a) Labour
i) Mate day 0.080 356.65 28.53 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 1836.00 312.12 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 850.00 382.50 P&M-048
c) Material
Selected earth for refilling cum 5.000 165.00 825.00 M-163
d) Overhead charges @ 10% on (a+b+c) 203.73
e) Contractor's profit @ 10% on (a+b+c+d) 224.10
Cost for 10 cum = a+b+c+d+e 2465.10
Rate per cum = (a+b+c+d+e)/10 246.51 151.00
say 247.00 63.6%
1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
Mechanical Means (With dewatering)
a) Labour
i) Mate day 0.080 356.65 28.53 L-12

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 1836.00 312.12 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 850.00 382.50 P&M-048
c) Material
Selected earth for refilling cum 5.000 165.00 825.00 M-163
Cost of dewatering @ 20% on (a+b) 121.23
d) Overhead charges @ 10% on (a+b+c) 242.45
e) Contractor's profit @ 10% on (a+b+c+d) 240.10
Cost for 10 cum = a+b+c+d+e 2641.05
Rate per cum = (a+b+c+d+e)/10 264.10 158.00
say 264.00 67.1%

3.14 Scarifying Existing Granular Surface to a Depth of 50


mm by Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor including loading and unloading day 5.000 244.56 1222.80 L-13
b) Machinery
Tractor-trolley hour 1.670 323.00 539.41 P&M-053
d) Overhead charges @ 10% on (a+b+c) 183.35
e) Contractor's profit @ 10% on (a+b+c+d) 201.69
Cost for 100 sqm = a+b+c+d 2218.58
Rate per sqm = (a+b+c+d)/100 22.19 13.00
say 22.00 69.2%
In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.15 Scarifying Existing Bituminous Surface to a depth of
50 mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.250 244.56 61.14 L-13
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 440.00 35.20 P&M-055

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.470 1341.00 630.27 P&M-017
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 850.00 195.50 P&M-048
c) Overhead charges @ 10% on (a+b) 92.57
d) Contractor's profit @ 10% on (a+b+c) 101.82
Cost for 100 sqm = a+b+c+d 1120.07
Rate per sqm = (a+b+c+d)/100 11.20 4.00
say 11.00 175.0%
3.16 Construction of Embankment with Material obtained
from Borrowpits( from private land )
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 1836.00 3066.12 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 3.50 1680.00 Lead =160
km & P&M-
058
Cost of loading and unloading cum 100.000 30.00 3000.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3194.00 1597.00 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2234.00 2234.00 P&M-032
Water tanker6 KL capacity hour 4.000 440.00 1760.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1687.00 1687.00 P&M-059
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
Compensation for earth taken from private land cum 100.000 33.00 3300.00 M-095
d) Overhead charges @ 10% on (a+b+c) 1966.29
e) Contractor's profit @ 10% on (a+b+c+d) 2162.92
Cost for 100 cum = a+b+c+d+e 23792.16
Rate per cum = (a+b+c+d+e)/100 237.92 168.00
say 238.00 41.7%
Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be cle

Construction of Embankment with Material obtained


from Borrowpits( from Govt land )

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 1836.00 3066.12 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 3.50 1680.00 Lead =160
km & P&M-
058
Cost of loading and unloading cum 100.000 30.00 3000.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3194.00 1597.00 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2234.00 2234.00 P&M-032
Water tanker6 KL capacity hour 4.000 440.00 1760.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1687.00 1687.00 P&M-059
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
Compensation for earth taken from private land cum 100.000 33.00 3300.00 M-095
d) Overhead charges @ 10% on (a+b+c) 1966.29
e) Contractor's profit @ 10% on (a+b+c+d) 2162.92
Cost for 100 cum = a+b+c+d+e 23792.16
Rate per cum = (a+b+c+d+e)/100 237.92 149.00
say 238.00 59.7%
7.04
Extra lead beyond initial lead of 3 Km 7.74 10.0%
3.17 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor day 0.500 244.56 122.28 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3194.00 1597.00 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2234.00 2234.00 P&M-032
Water tanker6 KL capacity hour 4.000 440.00 1760.00 P&M-060
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1687.00 1687.00 P&M-059

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
d) Overhead charges @ 10% on (a+b+c) 848.74
e) Contractor's profit @ 10% on (a+b+c+d) 933.62
Rate for 100 cum = a+b+c+d+e 10269.77
Rate per cum = (a+b+c+d+e)/100 102.70 87.00
say 103.00 18.4%
In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from r
3.18 Construction of Subgrade and Earthen Shoulders
( Form private land )
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-
2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 1836.00 3066.12 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 175xL 3.50 1837.50 Lead =175
km & P&M-
058
Cost of loading and unloading cum 100.000 45.00 4500.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3194.00 1597.00 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 2234.00 4468.00 P&M-032
Water tanker with 6 km lead hour 4.000 440.00 1760.00 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1687.00 2108.75 P&M-059
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
Compensation for earth taken from private land cum 100.000 33.00 3300.00 M-095
d) Overhead charges @ 10% on (a+b+c) 2397.62
e) Contractor's profit @ 10% on (a+b+c+d) 2637.38
Cost for 100 cum = a+b+c+d+e 29011.20
Rate per cum = (a+b+c+d+e)/100 290.11 201.00
say 290.00 44.3%
Construction of Subgrade and Earthen Shoulders
( Form Govt land )

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-
2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 1836.00 3066.12 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 175xL 3.50 1837.50 Lead =175
km & P&M-
058
Cost of loading and unloading cum 100.000 45.00 4500.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3194.00 1597.00 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 2234.00 4468.00 P&M-032
Water tanker with 6 km lead hour 4.000 440.00 1760.00 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1687.00 2108.75 P&M-059
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
Compensation for earth taken from private land cum 100.000 33.00 3300.00 M-095
d) Overhead charges @ 10% on (a+b+c) 2397.62
e) Contractor's profit @ 10% on (a+b+c+d) 2637.38
Cost for 100 cum = a+b+c+d+e 29011.20
Rate per cum = (a+b+c+d+e)/100 290.11 182.00
say 290.00 59.3%
7.69
Extra lead beyond initial lead of 3 Km 8.46 10.00
3.19 Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 440.00 3960.00 P&M-055
Motor grader for grading hour 7.700 2234.00 17201.80 P&M-032
Water tanker 6 KL capacity hour 4.000 440.00 1760.00 P&M-060
Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1687.00 12652.50 P&M-059

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
d) Overhead charges @ 10% on (a+b+c) 3743.08
e) Contractor's profit @ 10% on (a+b+c+d) 4117.39
Cost for 600 cum = a+b+c+d+e 45291.24
Rate per cum = (a+b+c+d+e)/600 75.49 60.00
say 75.00 25.0%
3.19 :Compacting original ground supporting embankment

Loosening, leveling and Compacting original ground


supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as g
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Tractor with ripper attachment hour 6.000 440.00 2640.00 P&M-055
Vibratory road roller 8-10 tonne capacity hour 7.500 1687.00 12652.50 P&M-059
Water tanker6 KL capacity hour 4.000 440.00 1760.00 P&M-060
c) Material
Cost of water KL 24.000 45.00 1080.00 M-189
d) Overhead charges @ 10% on (a+b+c) 1865.02
e) Contractor's profit @ 10% on (a+b+c+d) 2051.52
Cost for 600 cum = (a+b+c+d+e) 22566.68
Rate per sqm = (a+b+c+d+e)/600 37.61 30.00
say 38.00 26.7%
3.20 Stripping and Storing Top Soil
Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery
Dozer 80 HP @ 100 cum per hour hour 0.100 3194.00 319.40 P&M-014
c) Overhead charges @ 10% on (a+b) 161.35
d) Contractor's profit @ 10% on (a+b+c) 177.49
Cost for 10 cum = (a+b+c+d) 1952.37

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d)/10 195.24 100.00
say 195.00 95.0%
3.21 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Dozer, 80 HP hour 8.800 3194.00 28107.20 P&M-014
c) Overhead charges @ 10% on (a+b) 2862.49
d) Contractor's profit @ 10% on (a+b+c) 3148.73
Cost for 300 cum = (a+b+c+d) 34636.07
Rate per cum = (a+b+c+d)/300 115.45 78.00
say 115.00 47.4%
3.22 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor for preparation of ground and fetching of sods day 3.000 244.56 733.68 L-13

b) Machinery
Water tanker including watering for 3 months hour 2.000 440.00 880.00 P&M-060
Tractor-trolley hour 1.000 323.00 323.00 P&M-053
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 60.00 10.80 M-167
work
Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 253.03
e) Contractor's profit @ 10% on (a+b+c+d) 278.33
Cost for 100 sqm = a+b+c+d+e 3061.64
Rate per 100 sqm = (a+b+c+d+e)/100 30.62 19.00
say 31.00 63.2%
3.23 Seeding and Mulching

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 15.000 440.00 6600.00 P&M-060
months
Tractor-trolley hour 2.400 323.00 775.20 P&M-053
c) Material
Seeds kg 3.600 30.00 108.00 M-162
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 60.00 25.80 M-167
Bitumen Emulsion litre 55.200 40.57 2239.57 M-080
Jute netting, open weave, 2.5 cm square opening sqm 264.000 34.00 8976.00 M-121
Cost of water for 3 months KL 84.000 45.00 3780.00 M-189
d) Overhead charges @ 10% on (a+b+c) 2509.28
e) Contractor's profit @ 10% on (a+b+c+d) 2760.21
Cost for 240 sqm = a+b+c+d+e 30362.33
Rate per sqm = (a+b+c+d+e)/240 126.51 77.00
say 127.00 64.9%
3.24 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (ave
Unit = metre
Taking output = 10 metres
Mechanical means
a) Labour
Mate day 0.010 356.65 3.57 L-12
Mazdoor for dressing of bed and side of drain day 0.250 244.56 61.14 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 1836.00 605.88 P&M-026
metres per hour
c) Overhead charges @ 10% on (a+b) 67.06
d) Contractor's profit @ 10% on (a+b+c) 73.76
Cost for 10 metres = a+b+c+d 811.41
Rate per metre = (a+b+c+d)/10 81.14 58.00
say 81.00 39.7%
3.24 Manual Means

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Overhead charges @ 10% on (a) 51.77
c) Contractor's profit @ 10% on (a+b) 56.94
Cost for 10 metres = a+b+c 626.36
Rate per metre = (a+b+c)/10 62.64 25.00
say 63.00 152.0%
Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
3.25 Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankmen
Unit = metre
Taking output = 10 metres
Mechanical Means
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor for dressing of bed and side of drain day 0.500 244.56 122.28 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 15 hour 0.670 1836.00 1230.12 P&M-026
metres per hour
c) Overhead charges @ 10% on (a+b) 135.95
d) Contractor's profit @ 10% on (a+b+c) 149.55
Cost for 10 metres = a+b+c+d 1645.03
Rate per metre = (a+b+c+d)/10 164.50 118.00
say 165.00 39.8%
3.25 Manual Means
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Overhead charges @ 10% on (a) 77.65
c) Contractor's profit @ 10% on (a+b) 85.41
Cost for 10 metres = a+b+c 939.54
Rate per metre = (a+b+c)/10 93.95 37.00
say 94.00 154.1%
3.26 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
3.27 Sub-Surface Drains with Perforated Pipe
Construction of subsurface drain with perforated pipe of 100
mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bed
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor for excavation and back filling day 2.000 244.56 489.12 L-13
c) Material
Perforated pipe of cement concrete, internal dia 100 metre 10.000 95.00 950.00 M-135
mm
Crushed stone as per table 300-3 cum 2.400 1013.00 2431.20 M-012
d) Overhead charges @ 10% on (a+b+c) 388.46
e) Contractor's profit @ 10% on (a+b+c+d) 427.30
Cost for 10 metres = a+b+c+d+e 4700.35
Rate per metre = (a+b+c+d+e)/10 470.03 290.00
say 470.00 62.1%
Type of pipe may be modified depending upon provision in
design.
3.28 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor for excavation and back filling with day 1.500 244.56 366.84 L-13
aggregates
b) Material
Crushed stone as per table 300-3 cum 1.350 1013.00 1367.55 M-012
c) Overhead charges @ 10% on (a+b) 174.15
d) Contractor's profit @ 10% on (a+b+c) 191.57
Cost for 10 metres = a+b+c+d 2107.24
Rate per metre = (a+b+c+d)/10 210.72 116.00
say 211.00 81.9%
3.29 Underground Drain at Edge of Pavement
Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil cum 1.500 53.00 79.50 Item No.
3.13

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) RCC work M-20 cum 0.495 9024.00 4466.88 Item 12.8
(C) M20
RC OB P
Rate per metre = (a+b) 4546.38 2879.00
Rates for these items may be taken from chapters on earth say 4546.00 57.9%
work and substructures respectively.
3.31 Construction of Rock fill Embankment
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibrat
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.500 244.56 366.84 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3194.00 1597.00 P&M-014
Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1687.00 1687.00 P&M-059

Water tanker 6 KL, one trip per hour hour 2.000 440.00 880.00 P&M-060
c) Material
Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 508.51
e) Contractor's profit @ 10% on (a+b+c+d) 559.36
Cost for 100 cum = a+b+c+d+e 6152.98
Rate per cum = (a+b+c+d+e)/100 61.53 49.00
say 62.00 26.5%
It is assumed that rock is available locally at site from
roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD
3.32 A Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor for trimming slopes and helping in excavation day 6.000 244.56 1467.36 L-13
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3194.00 19164.00 P&M-014
Front end loader hour 6.000 1341.00 8046.00 P&M-017

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 850.00 10200.00 P&M-048
c) Overhead charges @ 10% on (a+b) 3896.30
d) Contractor's profit @ 10% on (a+b+c) 4285.93
Cost for 260 cum = a+b+c+d 47145.18
Rate per cum = (a+b+c+d)/260 181.33 134.00
say 181.00 35.1%
In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.

3.32 B Excavation in Hill Area in Soil by Mechanical Means


Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth on the barren valley side
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor for trimming slopes and helping in excavation day 6.000 244.56 1467.36 L-13
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3194.00 19164.00 P&M-014
c) Overhead charges @ 10% on (a+b) 2071.70
d) Contractor's profit @ 10% on (a+b+c) 2278.87
Cost for 260 cum = a+b+c+d 25067.52
Rate per cum = (a+b+c+d)/260 96.41 92.00
say 96.00 4.3%

3.33 A Excavation in Hilly Area in Ordinary Rock by


Mechanical Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3194.00 19164.00 P&M-014
Front end loader hour 7.000 1341.00 9387.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 850.00 5950.00 P&M-048
c) Overhead charges @ 10% on (a+b) 3657.16
d) Contractor's profit @ 10% on (a+b+c) 4022.88

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 170 cum = a+b+c+d 44251.65
Rate per cum = (a+b+c+d)/170 260.30 197.00
say 260.00 32.0%
In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

3.33 B Excavation in Hilly Area in Ordinary Rock by


Mechanical Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material on the barren valley side.

Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor day 8.000 244.56 1956.48 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3194.00 19164.00 P&M-014
c) Overhead charges @ 10% on (a+b) 2123.46
d) Contractor's profit @ 10% on (a+b+c) 2335.81
Cost for 170 cum = a+b+c+d 25693.88
Rate per cum = (a+b+c+d)/170 151.14 142.00
say 151.00 6.3%
3.34 A Excavation in Hilly Areas in Hard Rock Requiring
Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.

Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 356.65 174.76 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
Driller day 2.000 356.65 713.30 L-06
Blaster day 0.250 356.65 89.16 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.900 3194.00 22038.60 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 435.00 2175.00 P&M-001
cum per hour
Front end loader hour 7.000 1341.00 9387.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 850.00 5950.00 P&M-048
c) Materials
Gelatine 80 per cent kg 35.000 72.00 2520.00 M-104

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 15.00 2100.00 M-097 /100
of 125 gms each
d) Overhead charges @ 10% on (a+b+c) 4759.34
e) Contractor's profit @ 10% on (a+b+c+d) 5235.28
Cost for 170 cum = a+b+c+d+e 57588.04
Rate per cum = (a+b+c+d+e)/170 338.75 239.00
say 339.00 41.8%
In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
3.34 B Excavation in Hilly Areas in Hard Rock Requiring
Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material on the barren valley side
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 356.65 174.76 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
Driller day 2.000 356.65 713.30 L-06
Blaster day 0.250 356.65 89.16 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3194.00 19164.00 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 435.00 2175.00 P&M-001
cum per hour
c) Materials
Gelatine 80 per cent kg 35.000 72.00 2520.00 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 15.00 2100.00 M-097 /100
of 125 gms each
d) Overhead charges @ 10% on (a+b+c) 2938.18
e) Contractor's profit @ 10% on (a+b+c+d) 3232.00
Cost for 170 cum = a+b+c+d+e 35552.00
Rate per cum = (a+b+c+d+e)/170 209.13 184.00
say 209.00 13.6%
3.36 Embankment Construction with Flyash/Pond ash
available from coal or lignite burning Thermal Plants
as waste material.

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-3

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 5
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 4.000 244.56 978.24 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 14.000 1836.00 25704.00 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 3.50 7560.00 #REF!
Add 10 per cent of cost of carriagefor loading and 756.00
unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 3194.00 5749.20 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 2234.00 8042.40 P&M-032
Water tanker6 KL capacity hour 12.000 440.00 5280.00 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 1687.00 6073.20 P&M-059
c) Overhead charges @ 10% on (a+b) 6020.01
d) Contractor's profit @ 10% on (a+b+c) 6622.01
Cost for 360 cum = a+b+c+d 72842.13
Rate per cum = (a+b+c+d)/360 202.34
say 202.00
1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
4.1 Granular Sub-Base with Close Graded Material (Table:-
400-1)
Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power r
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 8.000 244.56 1956.48 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 1672.00 10032.00 P&M-093
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Water tanker 6 KL capacity 5 km lead with one trip per hour 4.500 440.00 1980.00 P&M-060
hour
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover loading and 1575.00
unloading
Motor Grader 110 HP hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8-10 t hour 6.000 1687.00 10122.00 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 144.000 1119.00 161136.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 1041.50 59365.50 M-017
2.36 mm below @ 30 per cent cum 86.400 698.00 60307.20 M-020
Cost of water KL 27.000 45.00 1215.00 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 1101.00 110980.80 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 1041.50 74988.00 M-017
2.36 mm below @ 40 per cent cum 115.200 698.00 80409.60 M-020
Cost of water KL 27.000 45.00 1215.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 100.800 1084.00 109267.20 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 36.000 1041.50 37494.00 M-018
2.36 mm below @ 52.5 per cent cum 151.200 698.00 105537.60 M-020
Cost of water KL 27.000 45.00 1215.00 M-189
4.1A Rate per cum for grading-I Material
d) Overhead charges @ 10% on (a+b+c) 35818.31
e) Contractor's profit @ 10% on (a+b+c+d) 39400.15
Cost for 225 cum = a+b+c+d+e 433401.60
Rate per cum = (a+b+c+d+e)/225 1926.23 1285.00
say 1926.00 49.88
4.1A Rate per cum for grading-II Material

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10% on (a+b+c) 34375.28
e) Contractor's profit @ 10% on (a+b+c+d) 37812.81
Cost for 225 cum = a+b+c+d+e 415940.94
Rate per cum = (a+b+c+d+e)/225 1848.63 1351.00
say 1849.00 36.86
4.1A Rate per cum for grading-III Material
d) Overhead charges @ 10% on (a+b+c) 32967.32
e) Contractor's profit @ 10% on (a+b+c+d) 36264.06
Cost for 225 cum = a+b+c+d+e 398904.62
Rate per cum = (a+b+c+d+e)/225 1772.91 1268.00
say 1773.00 39.83
Any one of the grading for material may be adopted as per
design
4.1 By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired densi
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 356.65 171.19 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor unskilled day 10.000 244.56 2445.60 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1687.00 10122.00 P&M-059
Tractor - Rotavator hour 12.000 431.00 5172.00 P&M-054
Water tanker 6 KL capacity hour 3.000 440.00 1320.00 P&M-060
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 192.000 1119.00 214848.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 76.000 1041.50 79154.00 M-017
2.36 mm below @ 30 per cent cum 115.200 698.00 80409.60 M-020
Cost of water KL 18.000 45.00 810.00 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 134.400 1101.00 147974.40 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 96.000 1041.50 99984.00 M-017
2.36 mm below @ 40 per cent cum 153.600 698.00 107212.80 M-020
Cost of water KL 18.000 45.00 810.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 134.400 1084.00 145689.60 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 48.000 1041.50 49992.00 M-018
2.36 mm below @ 52.5 per cent cum 201.600 698.00 140716.80 M-020

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost of water KL 18.000 45.00 810.00 M-189
4.1B Rate per cum for grading-I Material
d) Overhead charges @ 10% on (a+b+c) 40856.97
e) Contractor's profit @ 10% on (a+b+c+d) 44942.67
Cost for 300 cum = a+b+c+d+e 494369.33
Rate per cum = (a+b+c+d+e)/300 1647.90 1121.00
say 1648.00 47.01
4.1B Rate per cum for grading-II Material
d) Overhead charges @ 10% on (a+b+c) 38932.93
e) Contractor's profit @ 10% on (a+b+c+d) 42826.22
Cost for 300 cum = a+b+c+d+e 471088.44
Rate per cum = (a+b+c+d+e)/300 1570.29 1187.00
say 1570.00 32.27
4.1B Rate per cum for grading-III Material
d) Overhead charges @ 10% on (a+b+c) 37055.65
e) Contractor's profit @ 10% on (a+b+c+d) 40761.21
Cost for 300 cum = a+b+c+d+e 448373.36
Rate per cum = (a+b+c+d+e)/300 1494.58 1104.00
say 1495.00 35.42
Any one of the grading for material may be adopted as per
design
4.2 Granular Sub-Base with Coarse Graded Material (Table:-
400- 2)
Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired dens
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 8.000 244.56 1956.48 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1687.00 10122.00 P&M-059
Water tanker 6 KL capacity hour 3.000 440.00 1320.00 P&M-060
c) Material
For coarse graded Granular sub-base Materials per table 400-
2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 1124.00 151065.60 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 1089.00 188179.20 M-026
2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 698.00 53606.40 M-022
Cost of water KL 18.000 45.00 810.00 M-189

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 1089.00 313632.00 M-026
2.36 mm below @ 25 per cent cum 96.000 698.00 67008.00 M-022
Cost of water KL 18.000 45.00 810.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 66 per cent cum 255.000 1084.00 276420.00 M-025
2.36 mm below @ 34 per cent cum 129.000 698.00 90042.00 M-022
Cost of water KL 18.000 45.00 810.00 M-189
4.2 Rate per cum for grading-I Material
d) Overhead charges @ 10% on (a+b+c) 42131.96
e) Contractor's profit @ 10% on (a+b+c+d) 46345.16
Cost for 300 cum = a+b+c+d+e 509796.76
Rate per cum = (a+b+c+d+e)/300 1699.32 1127.00
say 1699.00 50.75
4.2 Rate per cum for grading-II Material
d) Overhead charges @ 10% on (a+b+c) 40910.84
e) Contractor's profit @ 10% on (a+b+c+d) 45001.93
Cost for 300 cum = a+b+c+d+e 495021.21
Rate per cum = (a+b+c+d+e)/300 1650.07 1158.00
say 1650.00 42.49
4.2 Rate per cum for grading-III Material
d) Overhead charges @ 10% on (a+b+c) 39493.04
e) Contractor's profit @ 10% on (a+b+c+d) 43442.35
Cost for 300 cum = a+b+c+d+e 477865.83
Rate per cum = (a+b+c+d+e)/300 1592.89 1276.00
say 1593.00 24.84
Any one of the grading for material may be adopted as per
design
4.3 Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting w
Unit = cum
Taking output = 300 cum (525 tonne)
By Mechanical Means
a) Labour
Mate day 0.360 356.65 128.39 L-12
Skilled mazdoor for alignment and geometrics day 1.000 356.65 356.65 L-15
Mazdoor for spraying lime day 8.000 244.56 1956.48 L-13
b) Machinery

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tractor with ripper and rotavator attachments @ 60 cum hour 12.000 440.00 5280.00 P&M-055
per hour for ripping and 25 cum per hour for mixing

Motor Grader 110 HP @ 50 cum per hour hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 - 10 tonne capacity hour 6.00x0.65* 1687.00 6579.30 P&M-059
Water tanker 6 KL capacity hour 12.000 440.00 5280.00 P&M-060
c) Material
Lime at site tonne 15.750 5900.00 92925.00 M-188
Cost of water KL 72.000 45.00 3240.00 M-189
d) Overhead charges @ 10% on (a+b+c) 12914.98
e) Contractor's profit @ 10% on (a+b+c+d) 14206.48
Cost for 300 cum= a+b+c+d+e 156271.29
Rate per cum =( a+b+c+d+e)/300 520.90 442.00
say 521.00 17.87
* Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.

4.3 By Manual Means


Unit = cum
Taking output = 150 cum (263 tonnes)
a) Labour
Mate day 1.440 356.65 513.58 L-12
Mazdoor skilled day 1.000 356.65 356.65 L-15
Mazdoor day 35.000 244.56 8559.60 L-13
b) Machinery
Vibratory roller 8 - 10 tonne @ 60 cum per hour hour 2.500 1687.00 4217.50 P&M-059
Water tanker 6 KL capacity hour 6.000 440.00 2640.00 P&M-060
c) Material
Lime at site tonne 8.000 5900.00 47200.00 M-188
Cost of water KL 36.000 45.00 1620.00 M-189
d) Overhead charges @ 10% on (a+b+c) 6510.73
e) Contractor's profit @ 10% on (a+b+c+d) 7161.81
Cost for 150 cum= a+b+c+d+e 78779.86
Rate per cum =( a+b+c+d+e)/150 525.20 403.00
say 525.00 30.27
4.4 Lime Treated Soil for Sub- Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with
3 per cent slaked lime with minimum content of 70 per cent
of CaO, grading with motor grader and compacting with the
road rol
Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate day 0.480 356.65 171.19 L-12

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1836.00 11016.00 P&M-026
Tipper for carriage of soil tonne.km 525 x L 3.50 5512.50 #REF!
Add 10 per cent of cost of carriage to cover cost of 551.25
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1687.00 10122.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 431.00 5172.00 P&M-054
Water tanker 6 KL capacity hour 12.000 440.00 5280.00 P&M-060
c) Material
Lime at site tonne 17.300 5900.00 102070.00 M-188
Cost of water KL 72.000 45.00 3240.00 M-189
d) Overhead charges @ 10% on (a+b+c) 15969.78
e) Contractor's profit @ 10% on (a+b+c+d) 17566.76
Cost for 300 cum = a+b+c+d+e 193234.39
Rate per cum= (a+b+c+d+e)/300 644.11 512.00
say 644.00 25.78
4.5 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the d
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 356.65 171.19 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1836.00 11016.00 P&M-026
Tipper for carriage of soil tonne.km 525 x L 3.50 5512.50 #REF!
Add 10 per cent of cost of carriage to cover cost of 551.25
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1687.00 10122.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 431.00 5172.00 P&M-054
Water tanker 6 KL capacity hour 12.000 440.00 5280.00 P&M-060
c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 7200.00 151200.00 M-084
Cost of water KL 72.000 45.00 3240.00 M-189
d) Overhead charges @ 10% on (a+b+c) 20882.78
e) Contractor's profit @ 10% on (a+b+c+d) 22971.06

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 300 cum = a+b+c+d+e 252681.69
Rate per cum= (a+b+c+d+e)/300 842.27 635.00
say 842.00 32.60
4.6 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desire
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity
of crushed rock by weight.
a) Labour
Mate day 0.480 356.65 171.19 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1687.00 10122.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 431.00 5172.00 P&M-054
Water tanker 6 KL capacity hour 10.000 440.00 4400.00 P&M-060
c) Material
Cement at site @ 4 per cent by weight of crushed tonne 24.000 7200.00 172800.00 M-084
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 1101.00 232531.20 M-014
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 1084.00 83251.20 M-025
4.75 mm to 75 micron @ 25 per cent cum 96.000 1089.00 104544.00 M-019
Cost of water KL 60.000 45.00 2700.00 M-189
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 1101.00 137404.80 M-028
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 1084.00 20812.80 M-025
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 698.00 167520.00 M-023
Cost of water KL 60.000 45.00 2700.00 M-189
4.6 For Sub-Base course
d) Overhead charges @ 10% on (a+b+c) 63225.45
e) Contractor's profit @ 10% on (a+b+c+d) 69547.99
Cost for 300 cum = a+b+c+d+e 765027.94
Rate per cum = (a+b+c+d+e)/300 2550.09 1998.00
say 2550.00 27.63
4.6 For Base course
d) Overhead charges @ 10% on (a+b+c) 53766.57
e) Contractor's profit @ 10% on (a+b+c+d) 59143.23

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 300 cum = a+b+c+d+e 650575.49
Rate per cum = (a+b+c+d+e)/300 2168.58 2060.00
say 2169.00 5.29
Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.7 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
50mm deep furrow cutting
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 4.000 244.56 978.24 L-13
b) Machinery
Tractor-trolley hour 0.400 323.00 129.20 P&M-053
c) Overhead charges @ 10% on (a+b) 116.45
d) Contractor's profit @ 10% on (a+b+c) 128.10
Cost for 210 sqm= a+b+c+d 1409.05
Rate per sqm =(a+b+c+d)/210 6.71 2.00
say 7.00 250.00
4.8 Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 356.65 328.12 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 21.000 244.56 5135.76 L-13
b) Machinery
Motor Grader 110 HP hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 1687.00 10122.00 P&M-059
Water tanker 6 KL capacity hour 18.000 440.00 7920.00 P&M-060
c) Material
Screening type 'B' or coarse sand cum 720.000 950.00 684000.00 M-004
Cost of water KL 108.000 45.00 4860.00 M-189
d) Overhead charges @ 10% on (a+b+c) 72648.32
e) Contractor's profit @ 10% on (a+b+c+d) 79913.15
Cost for 600 cum = a+b+c+d+e 879044.65
Rate per cum = ( a+b+c+d+e)/600 1465.07 792.00
say 1465.00 84.97

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
4.9 Water Bound Macadam
Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grad
By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 356.65 3595.03 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 250.000 244.56 61140.00 L-13
b) Machinery

Vibratory roller 8 - 10 tonne @ 60cum per hour hour 6.000 1687.00 10122.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 12.000
Water tanker 6 KL capacity hour 24.000 440.00 10560.00 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 1440.50 627481.80 M-039
compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 695.00 67554.00 M-052

OR
Crushable type such as Moorum or Gravel for grading-I cum 140.000 698.00 97720.00 M-007
@ 0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 29.800 698.00 20800.40 M-007
material
Cost of water KL 144.000 45.00 6480.00 M-189

say 2749.00 103.18

OR

4.9A (i) Using Scrining Type-A (13.2mm agg.)

d) Overhead charges @ 10% on (a+b+c) 80844.65


e) Contractor's profit @ 10% on (a+b+c+d) 88929.12
Cost for 360 cum = a+b+c+d+e 978220.30
Rate per cum = (a+b+c+d+e)/360 2717.28 1353.00
say 2717.00 100.81

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
4.9A Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 1510.00 657756.00 M-038
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 695.00 40032.00 M-052
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 698.00 73701.82 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 655.00 56592.00 M-051

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 698.00 20102.40 M-007
material
Cost of water KL 144.000 45.00 6480.00 M-189
4.9A Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 10% on (a+b+c) 82406.82
e) Contractor's profit @ 10% on (a+b+c+d) 90647.50
Cost for 360 cum = a+b+c+d+e 997122.46
Rate per cum = (a+b+c+d+e)/360 2769.78 1226.00
say 2770.00 125.94
OR
4.9A Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 10% on (a+b+c) 81050.07
e) Contractor's profit @ 10% on (a+b+c+d) 89155.08
Cost for 360 cum = a+b+c+d+e 980705.89
Rate per cum = (a+b+c+d+e)/360 2724.18 1330.00
say 2724.00 104.81
4.9A Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 10% on (a+b+c) 82706.07
e) Contractor's profit @ 10% on (a+b+c+d) 90976.68
Cost for 360 cum = a+b+c+d+e 1000743.49
Rate per cum = (a+b+c+d+e)/360 2779.84 1427.00
say 2780.00 94.81
4.9A Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 1623.00 706978.80 M-036
for compacted thickness of 75 mm

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 655.00 56592.00 M-051

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 698.00 73701.82 M-007
&III @ 0.22 cum per 10 sqm

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 698.00 20102.40 M-007
material
Cost of water KL 144.000 45.00 6480.00 M-189
4.9A Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 10% on (a+b+c) 87329.10
e) Contractor's profit @ 10% on (a+b+c+d) 96062.00
Cost for 360 cum = a+b+c+d+e 1056682.05
Rate per cum = (a+b+c+d+e)/360 2935.23 1262.00
say 2935.00 132.57
OR
4.9A Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 10% on (a+b+c) 87628.35
e) Contractor's profit @ 10% on (a+b+c+d) 96391.19
Cost for 360 cum = a+b+c+d+e 1060303.07
Rate per cum = (a+b+c+d+e)/360 2945.29 1464.00
say 2945.00 101.16
( Anyone of the aggregate grading, screening and binding
material may be used as per design)
4.9 By Mechanical Means:
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 356.65 242.52 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 15.000 244.56 3668.40 L-13
b) Machinery
Motor grader 110 HP @ 50cum/hr. for spreading hour 7.200 2234.00 16084.80 P&M-032
Vibratory roller 8-10 tonnes @ 60cum/hr. hour 6.000 1687.00 10122.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Water tanker 6 KL capacity hour 24.000 440.00 10560.00 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9B Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 1440.50 627481.80 M-039
compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 695.00 67554.00 M-052

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
OR
Crushable type such as Moorum or Gravel for grading-I cum 108.000 698.00 75384.00 M-007
@ 0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 698.00 20102.40 M-007
material
Cost of water KL 144.000 45.00 6480.00 M-189
4.9B Using Scrining Crushable type such as Moorum or Gravel
(i)
d) Overhead charges @ 10% on (a+b+c) 75073.68
e) Contractor's profit @ 10% on (a+b+c+d) 82581.05
Cost for 360 cum = a+b+c+d+e 908391.55
Rate per cum = (a+b+c+d+e)/360 2523.31 1099.00
say 2523.00 129.57
OR
4.9B Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 10% on (a+b+c) 76300.92
e) Contractor's profit @ 10% on (a+b+c+d) 83931.01
Cost for 360 cum = a+b+c+d+e 923241.16
Rate per cum = (a+b+c+d+e)/360 2564.56 1327.00
say 2565.00 93.29
4.9B Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 1510.00 657756.00 M-038
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 695.00 40032.00 M-052
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 698.00 73701.82 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 655.00 56592.00 M-051

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 698.00 20102.40 M-007
material
Cost of water KL 144.000 45.00 6480.00 M-189
4.9B Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 10% on (a+b+c) 77932.88
e) Contractor's profit @ 10% on (a+b+c+d) 85726.17
Cost for 360 cum = a+b+c+d+e 942987.90
Rate per cum = (a+b+c+d+e)/360 2619.41 1199.00
say 2619.00 118.43

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
OR
4.9B Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 10% on (a+b+c) 76576.14
e) Contractor's profit @ 10% on (a+b+c+d) 84233.76
Cost for 360 cum = a+b+c+d+e 926571.32
Rate per cum = (a+b+c+d+e)/360 2573.81 1304.00
say 2574.00 97.39
4.9B Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 10% on (a+b+c) 78232.14
e) Contractor's profit @ 10% on (a+b+c+d) 86055.36
Cost for 360 cum = a+b+c+d+e 946608.92
Rate per cum = (a+b+c+d+e)/360 2629.47 1401.00
say 2629.00 87.65
4.9B Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 1623.00 706978.80 M-036
for compacted thickness of 75 mm

Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 655.00 56592.00 M-051

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 698.00 73701.82 M-007
&III @ 0.22 cum per 10 sqm

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 698.00 20102.40 M-007
material
Cost of water KL 144.000 45.00 6480.00 M-189
4.9B Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 10% on (a+b+c) 82855.16
e) Contractor's profit @ 10% on (a+b+c+d) 91140.68
Cost for 360 cum = a+b+c+d+e 1002547.49
Rate per cum = (a+b+c+d+e)/360 2784.85 1236.00
say 2785.00 125.32
OR
4.9B Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 10% on (a+b+c) 83154.42
e) Contractor's profit @ 10% on (a+b+c+d) 91469.86
Cost for 360 cum = a+b+c+d+e 1006168.51
Rate per cum = (a+b+c+d+e)/360 2794.91 1437.00
say 2795.00 94.50
As three wheeled smooth rollers are also very commonly
used, the same has been provided as an alternative.

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
4.10 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and c
Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 356.65 1483.66 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor for crushing broken cement concrete day 102.000 244.56 24945.12 L-13
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 1687.00 10122.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 720 x L 3.50 25200.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 2520.00
loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour 12.000 440.00 5280.00 P&M-060
hour
c) Material
Material available from dismantled concrete slab after crushing
/ breaking and only carriage is required to be provided

Cost of water KL 72.000 45.00 3240.00 M-189


d) Overhead charges @ 10% on (a+b+c) 9495.41
e) Contractor's profit @ 10% on (a+b+c+d) 10444.95
Cost for 360 cum = a+b+c+d+e 114894.44
Rate per cum = (a+b+c+d+e)/360 319.15 188.00
say 319.00 69.68
1. It is assumed that dismantling of concrete slab/pavement
has been considered separately. Hence same is not added in
this analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work
site has bee
2. In case of breaking of slabs is done locally without
involvement of transportation, the provision of tipper, front end
loader and loading/unloading charges may be deleted.

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
3. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative.
4.11 Penetration Coat Over Top Layer of Crushed Cement
Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 356.65 199.72 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 12.000 244.56 2934.72 L-13
b) Machinery
Mechanical broom hydraulic @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Hydraulic self propelled chips spreader hour 6.000 2380.00 14280.00 P&M-025
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity hour 6.000 850.00 5100.00 P&M-048
Vibratory roller 8 -10 tonnes @ 30 cum per hour hour 6.00x0.65* 1687.00 6579.30 P&M-059
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 954.00 4083.12 P&M-004
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 1916.00 186810.00 M-051
Bitumen (60-70 grade) tonne 0.250 32627.00 8156.75 M-077
d) Overhead charges @ 10% on (a+b+c) 23892.49
e) Contractor's profit @ 10% on (a+b+c+d) 26281.74
Cost for 7500 sqm = a+b+c+d+e 289099.15
Rate per sqm = (a+b+c+d+e)/7500 38.55 22.00
say 39.00 77.27

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
4.12 Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with pave

Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 356.65 171.19 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 1353.00 8929.80 P&M-094
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum capacity hour 6.000 1341.00 8046.00 P&M-017
Paver finisher hour 6.000 853.00 5118.00 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1687.00 6579.30 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 440.00 1320.00 P&M-060
Tipper tonne.km 495 x L 3.50 17325.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1732.50
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1623.00 144609.30 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 1440.50 171131.40 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 698.00 62191.80 M-022
Cost of water KL 200.000 45.00 9000.00 M-189
d) Overhead charges @ 10% on (a+b+c) 45175.12
e) Contractor's profit @ 10% on (a+b+c+d) 49692.63
Cost for 225 cum = a+b+c+d+e 546618.94
Rate per cum = (a+b+c+d+e)/225 2429.42 1251.00
say 2429.00 94.16
1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
4.13 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 440.00 440.00 P&M-060
Plate compactor @ 3.5 cum per hour hour 6.000 218.00 1308.00 P&M-086
c) Material
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 357.10
e) Contractor's profit @ 10% on (a+b+c+d) 392.81
Cost for 21 cum = a+b+c+d+e 4320.86
Rate per cum = (a+b+c+d+e)/21 205.76 139.00
say 206.00 48.20
This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill
4.14 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 4.000 244.56 978.24 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 440.00 440.00 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 218.00 1308.00 P&M-086
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 1836.00 918.00 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 3.50 551.25 #REF!
Add 10 per cent of cost of transportation to cover cost 55.13
of loading and unloading
c) Material
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 457.77
e) Contractor's profit @ 10% on (a+b+c+d) 503.54

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 21 cum = a+b+c+d+e 5538.99
Rate per cum = (a+b+c+d+e)/ 21 263.76 201.00
say 264.00 31.34
This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish
4.15 Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.
4.16 Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 356.65 485.04 L-12
Mason day 4.000 458.55 1834.20 L-11
Mazdoor day 30.000 244.56 7336.80 L-13
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 1687.00 1265.25 P&M-059
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 440.00 880.00 P&M-060
Concrete mixer 0.4/0.28 cum per hour hour 6.000 188.00 1128.00 P&M-009
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 1124.00 23367.96 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 1089.00 29108.97 M-026
2.36 mm below @ 20 per cent cum 11.880 698.00 8292.24 M-022
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 1510.00 10192.50 M-052
Sand @ 0.45 cum/cum of concrete cum 3.380 950.00 3211.00 M-005
Cement tonne 1.880 7200.00 13536.00 M-084
iii) For cement plaster 1:3
Sand cum 3.840 950.00 3648.00 M-005
Cement tonne 1.830 7200.00 13176.00 M-084
iv) Pre-cast cement concrete tiles

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 57.00 188100.00 M-184
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 552.00 12420.00 M-137
vi) Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 31852.20
e) Contractor's profit @ 10% on (a+b+c+d) 35037.42
Cost for 300 sqm = a+b+c+d+e 385411.58
Rate per sqm = (a+b+c+d+e)/300 1284.71 971.00
say 1285.00 32.34
4.17 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base

Unit = cum
Taking output = 360 cum
By Mix in Place Method
a) Labour
Mate day 0.480 356.65 171.19 L-12
Mazdoor skilled day 2.000 356.65 713.30 L-15
Mazdoor day 10.000 244.56 2445.60 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per hour hour 12.000 431.00 5172.00 P&M-054
Motor grader 110 HP hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 -10 tonnes @ 60 cum per hour hour 6.000 1687.00 10122.00 P&M-059
Water tanker 6 KL capacity hour 6.000 440.00 2640.00 P&M-060
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 157.460 1510.00 237764.60 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 151.060 1440.50 217601.93 M-032
Below 5.6 mm @ 35 per cent cum 166.680 1104.00 184014.72 M-030
Cost of water KL 36.000 45.00 1620.00 M-189
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 24.120 1623.00 39146.76 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 237.600 1440.50 342262.80 M-032
Below 5.6 mm@ 45 per cent cum 213.480 1104.00 235681.92 M-030
Cost of water KL 36.000 45.00 1620.00 M-189
4.17A For 53 mm maximum size
d) Overhead charges @ 10% on (a+b+c) 67566.93
e) Contractor's profit @ 10% on (a+b+c+d) 74323.63
Cost for 360.0cum = a+b+c+d+e 817559.90
Rate per cum = (a+b+c+d+e)/360 2271.00 1456.00

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
or say 2271.00 35.89
4.17A For 45 mm maximum size
d) Overhead charges @ 10% on (a+b+c) 65337.96
e) Contractor's profit @ 10% on (a+b+c+d) 71871.75
Cost for 360.0cum = a+b+c+d+e 790589.28
Rate per cum = (a+b+c+d+e)/360 2196.08 1573.00
say 2196.00 28.37
Any one of the aggregate grading may be adopted
4.17 By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a) Labour
Mate day 0.280 356.65 99.86 L-12
Mazdoor skilled day 1.000 356.65 356.65 L-15
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Wet mix plant @ 75 tonne per hour hour 6.000 1672.00 10032.00 P&M-093
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Motor grader 110 HP hour 6.000 2234.00 13404.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1687.00 10122.00 P&M-059
Water tanker 6 KL capacity hour 3.000 440.00 1320.00 P&M-060
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 98.400 1510.00 148584.00 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 94.410 1440.50 135997.61 M-032
Below 5.6 mm @ 35 per cent cum 104.180 1104.00 115014.72 M-030
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 15.060 1623.00 24442.38 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 1440.50 213914.25 M-032
Below 5.6 mm@ 45 per cent cum 133.430 1104.00 147306.72 M-030
Cost of water KL 18.000 45.00 810.00 M-189
4.17 B For 53 mm maximum size
d) Overhead charges @ 10% on (a+b+c) 47420.72
e) Contractor's profit @ 10% on (a+b+c+d) 52162.79
Cost for 225cum = a+b+c+d+e 573790.71
Rate per cum = (a+b+c+d+e)/225 2550.18 1627.00
say 2550.00 56.73
4.17 B For 45 mm maximum size
d) Overhead charges @ 10% on (a+b+c) 46108.42

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Contractor's profit @ 10% on (a+b+c+d) 50719.26
Cost for 360.0cum = a+b+c+d+e 557911.91
Rate per cum = (a+b+c+d+e)/360 1549.76 1092.00
say 1550.00 41.94
4.18 Lime, Flyash Stabilised Soil Sub-Base

Construction of Sub-base using lime - Flyash admixture with


granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50
t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
Mazdoor (Skilled) day 1.000 356.65 356.65 L-15
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ hour 6.000 1836.00 11016.00 P&M-026
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes tonne.km 576 x L 3.50 6069.00 #REF!
Tipper 10T capacity for carriage of 115 tonnes Flyash tonne.km 115 x L 3.50 2012.50 #REF!
Tipper 10T capacity for carriage of 29 tonnes of lime from hour 3.000 850.00 2550.00 P&M-048
store to work site
Add 10 per cent of cost of carriage to cover cost of 255.00
loading and unloading
Tractor with disc harrows for pulverisation hour 6.000 323.00 1938.00 P&M-053
Motor Grader 110 HP @ 50 cum per hour for mixing in- hour 9.600 2234.00 21446.40 P&M-032
place and grading
Vibratory roller 8 - 10 tonne hour 6.000 1687.00 10122.00 P&M-059
Water tanker 6 KL capacity hour 12.000 440.00 5280.00 P&M-060
c) Material
Slaked Lime tonne 29.000 5900.00 171100.00 M-188
Compensation for earth taken from private source cum 360.000 33.00 11880.00 M-095
d) Overhead charges @ 10% on (a+b+c) 24557.85
e) Contractor's profit @ 10% on (a+b+c+d) 27013.64
Cost for 480 cum = a+b+c+d+e 297149.99
Rate per cum= (a+b+c+d+e)/480 619.06

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-4

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 619.00
1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be c
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.1 Prime Coat
Providing and applying primer coat with bitumen emulsion
on prepared surface of granular Base including clearing of
road surface and spraying primer at the rate of 0.60 kg/sqm
using mechanical means.( Low porosity )( Including cost of
testing of materials at site and laboratory as directed by the
deptt.)
With Bitumen emulsion CSS-1h
Unit = sqm
Taking output = 3500 sqm sqm 3500
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 440.00 440.00 P&M-060
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 38530.00 80913.00 M-073
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 8621.03
e) Contractor's profit @ 10% on (a+b+c+d) 9483.13
Cost for 3500 sqm = a+b+c+d+e 104314.40
Rate per sqm = (a+b+c+d+e)/3500 29.80 23.00
say 30.00 30.43
With Bitumen emulsion CSS-1(IS:8887-2004)
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 440.00 440.00 P&M-060
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 36950.00 77595.00 M-074
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 8289.23
e) Contractor's profit @ 10% on (a+b+c+d) 9118.15
Cost for 3500 sqm = a+b+c+d+e 100299.62
Rate per sqm = (a+b+c+d+e)/3500 28.66 30.00
say 29.00 (3.33)
Providing and applying primer coat with bitumen emulsion
on prepared surface of granular Base including clearing of
road surface and spraying primer at the rate of 1.00 kg/sqm
using mechanical means.( Low porosity )( Including cost of
testing of materials at site and laboratory as directed by the
deptt.)
With Bitumen emulsion CSS-1h
Unit = sqm
Taking output = 3500 sqm

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.080 356.65 28.53
Mazdoor day 2.000 244.56 489.12
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60
Air compressor 250 cfm hour 2.800 435.00 1218.00
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 440.00 440.00
c) Material
Bitumen emulsion @ 1.00 kg per sqm tonne 3.500 38530.00 134855.00 M-073
Cost of water KL 6.000 45.00 270.00
d) Overhead charges @ 10% on (a+b+c) 14015.23
e) Contractor's profit @ 10% on (a+b+c+d) 15416.75
Cost for 3500 sqm = a+b+c+d+e 169584.22 37.00
Rate per sqm = (a+b+c+d+e)/3500 48.45 30.95
say 48.00
With Bitumen emulsion CSS-1(IS:8887-2004)
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53
Mazdoor day 2.000 244.56 489.12
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60
Air compressor 250 cfm hour 2.800 435.00 1218.00
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 440.00 440.00
c) Material
Bitumen emulsion @ 1.0kg per sqm tonne 3.500 36950.00 129325.00 M-074
Cost of water KL 6.000 45.00 270.00
d) Overhead charges @ 10% on (a+b+c) 13462.23
e) Contractor's profit @ 10% on (a+b+c+d) 14808.45
Cost for 3500 sqm = a+b+c+d+e 162892.92 49.00
Rate per sqm = (a+b+c+d+e)/3500 46.54 (5.02)
say 47.00
Bitumen primer has been provided @ 0.60 / 1.00kg per sqm
as per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the Engineer
after the preliminary trials referred to

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.2 Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 kg per
sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.( Including cost of testing of
materials at site and laboratory as directed by the deptt.)

(I) With Bitumen emulsion CSS-1h


(a) Normal bituminous surface
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 38530.00 26971.00 M-073
Per Sqm Basic Cost of Labour, Material & Mechinery (a+b+c) 10.00
d) Overhead charges @ 10% on (a+b+c) 3155.83
e) Contractor's profit @ 10% on (a+b+c+d) 3471.41
Cost for 3500 sqm = a+b+c+d+e 38185.48
Rate per sqm = (a+b+c+d+e)/3500 10.91 8.00
say 11.00 37.50
(b) dry & hungry bituminous surface
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 38530.00 33713.75 M-073
d) Overhead charges @ 10% on (a+b+c) 3830.10
e) Contractor's profit @ 10% on (a+b+c+d) 4213.11
Cost for 3500 sqm = a+b+c+d+e 46344.21
Rate per sqm = (a+b+c+d+e)/3500 13.24 10.00
say 13.00 30.00
(c) Granular surfaces treated with primer
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 38530.00 33713.75 M-073

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10% on (a+b+c) 3830.10
e) Contractor's profit @ 10% on (a+b+c+d) 4213.11
Cost for 3500 sqm = a+b+c+d+e 46344.21
Rate per sqm = (a+b+c+d+e)/3500 13.24 10.00
say 13.00 30.00
With Bitumen emulsion CSS-1(IS:8887-2004)
(a) Normal bituminous surface
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 36950.00 25865.00 M-074
d) Overhead charges @ 10% on (a+b+c) 3045.23
e) Contractor's profit @ 10% on (a+b+c+d) 3349.75
Cost for 3500 sqm = a+b+c+d+e 36847.22
Rate per sqm = (a+b+c+d+e)/3500 10.53 11.00
say 11.00 0.00
(b) dry & hungry bituminous surface
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 36950.00 32331.25 M-074
d) Overhead charges @ 10% on (a+b+c) 3691.85
e) Contractor's profit @ 10% on (a+b+c+d) 4061.04
Cost for 3500 sqm = a+b+c+d+e 44671.39
Rate per sqm = (a+b+c+d+e)/3500 12.76 13.00
say 13.00 0.00
(c) Granular surfaces treated with primer
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 36950.00 32331.25 M-074
d) Overhead charges @ 10% on (a+b+c) 3691.85
e) Contractor's profit @ 10% on (a+b+c+d) 4061.04
Cost for 3500 sqm = a+b+c+d+e 44671.39
Rate per sqm = (a+b+c+d+e)/3500 12.76 13.00

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 13.00 0.00

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

With Bitumen emulsion RS-1


(a) Normal bituminous surface
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.790 26260.00 20745.40 M-075
d) Overhead charges @ 10% on (a+b+c) 2533.27
e) Contractor's profit @ 10% on (a+b+c+d) 2786.59
Cost for 3500 sqm = a+b+c+d+e 30652.51
Rate per sqm = (a+b+c+d+e)/3500 8.76 7.00
say 9.00 28.57
(b) dry & hungry bituminous surface
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 26260.00 22977.50 M-075
d) Overhead charges @ 10% on (a+b+c) 2756.48
e) Contractor's profit @ 10% on (a+b+c+d) 3032.12
Cost for 3500 sqm = a+b+c+d+e 33353.35
Rate per sqm = (a+b+c+d+e)/3500 9.53 9.00
say 10.00 11.11
(c) Granular surfaces treated with primer
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm hour 2.800 435.00 1218.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 954.00 1908.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 26260.00 22977.50 M-075
d) Overhead charges @ 10% on (a+b+c) 2756.48
e) Contractor's profit @ 10% on (a+b+c+d) 3032.12
Cost for 3500 sqm = a+b+c+d+e 33353.35
Rate per sqm = (a+b+c+d+e)/3500 9.53 9.00
say 10.00 11.11

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.3 Bituminous Macadam

Providing and laying bituminous macadam with 100-120


TPH hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid
over a previously prepared su
(a) Without anti stripping agent
(A) with 60/70 or VG-30 grade paved bitumen
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 22823.00 136938.00 P&M-021
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 337.00 741.40 P&M-031
Air compressor 250 cfm hour 2.200 435.00 957.00 P&M-001
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.850 32627.00 484510.95 M-077
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 1619.00 70442.69 M-049
25 - 10 mm 45 per cent cum 130.550 1827.00 238514.85 M-046
10 - 5 mm 25 per cent cum 72.530 1510.00 109520.30 M-040
5 mm and below15 per cent cum 43.510 1104.00 48035.04 M-030
or
GradingII(19 mm nominal size)

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
25 - 10 mm 40 per cent cum 116.040 1827.00 212005.08 M-046
10 - 5 mm 40 per cent cum 116.040 1510.00 175220.40 M-040
5 mm and below 20 per cent cum 58.020 1104.00 64054.08 M-030
* Any one of the alternative may be adopted as per
approved design
for Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 115830.80
e) Contractor's profit @ 10% on (a+b+c+d) 127413.88
Cost for 205 cum = a+b+c+d+e 1401552.71
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 6836.84 4761.00
say 6837.00 43.60
for GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 114307.47
e) Contractor's profit @ 10% on (a+b+c+d) 125738.22
Cost for 205 cum = a+b+c+d+e 1383120.39
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 6746.93 4862.00
say 6747.00 38.77
(B) with Polymer modified bitumen 70
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 22823.00 136938.00 P&M-021
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 337.00 741.40 P&M-031
Air compressor 250 cfm hour 2.200 435.00 957.00 P&M-001
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) P.M. Bitumen@ 3.3 per cent of mix tonne 14.850 33280.00 494208.00 M-081
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 1619.00 70442.69 M-049
25 - 10 mm 45 per cent cum 130.550 1827.00 238514.85 M-046
10 - 5 mm 25 per cent cum 72.530 1510.00 109520.30 M-040
5 mm and below15 per cent cum 43.510 1104.00 48035.04 M-030
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 1827.00 212005.08 M-046
10 - 5 mm 40 per cent cum 116.040 1510.00 175220.40 M-040
5 mm and below 20 per cent cum 58.020 1104.00 64054.08 M-030
* Any one of the alternative may be adopted as per
approved design
for Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 116800.51
e) Contractor's profit @ 10% on (a+b+c+d) 128480.56
Cost for 205 cum = a+b+c+d+e 1413286.14
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 6894.08 5242.00
say 6894.00 31.51
for GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 115277.18
e) Contractor's profit @ 10% on (a+b+c+d) 126804.89
Cost for 205 cum = a+b+c+d+e 1394853.82
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 6804.16 5343.00
say 6804.00 27.34

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
(b) With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
(A) with 60/70 or VG-30 grade paved bitumen
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 22823.00 136938.00
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 337.00 741.40
Air compressor 250 cfm hour 2.200 435.00 957.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10
roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.850 32627.00 484510.95 M-077
Anti stripping agent @ 1% of weight of binder Kg 148.500 240.00 35640.00 M-189_1
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 1619.00 70442.69
25 - 10 mm 45 per cent cum 130.550 1827.00 238514.85
10 - 5 mm 25 per cent cum 72.530 1510.00 109520.30
5 mm and below15 per cent cum 43.510 1104.00 48035.04
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 1827.00 212005.08
10 - 5 mm 40 per cent cum 116.040 1510.00 175220.40
5 mm and below 20 per cent cum 58.020 1104.00 64054.08

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
* Any one of the alternative may be adopted as per
approved design
for Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 119394.80
e) Contractor's profit @ 10% on (a+b+c+d) 131334.28
Cost for 205 cum = a+b+c+d+e 1444677.11
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 7047.21 4936.00
say 7047.00 42.77
for GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 117871.47
e) Contractor's profit @ 10% on (a+b+c+d) 129658.62
Cost for 205 cum = a+b+c+d+e 1426244.79
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 6957.29 5038.00
say 6957.00 38.09
(B) with Polymer modified bitumen 70
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 22823.00 136938.00
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 337.00 741.40
Air compressor 250 cfm hour 2.200 435.00 957.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10
roller.
c) Material
i) P.M. Bitumen@ 3.3 per cent of mix tonne 14.850 33280.00 494208.00 M-081
Anti stripping agent @ 1% of weight of binder Kg 148.500 240.00 35640.00 M-189_1
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 1619.00 70442.69
25 - 10 mm 45 per cent cum 130.550 1827.00 238514.85
10 - 5 mm 25 per cent cum 72.530 1510.00 109520.30
5 mm and below15 per cent cum 43.510 1104.00 48035.04
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 1827.00 212005.08
10 - 5 mm 40 per cent cum 116.040 1510.00 175220.40
5 mm and below 20 per cent cum 58.020 1104.00 64054.08
* Any one of the alternative may be adopted as per
approved design
for Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 120364.51
e) Contractor's profit @ 10% on (a+b+c+d) 132400.96
Cost for 205 cum = a+b+c+d+e 1456410.54
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 7104.44 5417.00
say 7104.00 31.14
for GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 118841.18
e) Contractor's profit @ 10% on (a+b+c+d) 130725.29
Cost for 205 cum = a+b+c+d+e 1402338.22
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 6840.67 5373.00
say 6841.00 27.32
5.4 Bituminous Penetration Macadam
Construction of penetration macadam over prepared Base
by providing a layer of compacted crushed coarse
aggregate using chips spreader with alternate applications
of bituminous binder and key aggregates and rolling with a
smooth wheeled steel roller 8-10 tonne capacity to achieve
the desired degree of compaction
50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
(a) Without anti stripping agent
a) Labour
Mate day 0.320 356.65 114.13 L-12
Mazdoor including for brooming of key aggregates day 6.000 244.56 1467.36 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2380.00 14280.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm = 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour hour 2.570 954.00 2451.78 P&M-004

Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 850.00 8500.00 P&M-048
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1687.00 10122.00 P&M-059

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
c) Material
Bitumen@ 5 kg per sqm tonne 22.500 32627.00 734107.50 M-077
Crushed stone coarse aggregate passing 45 mm and cum 270.000 1623.00 438210.00 M-033
retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8 cum 67.500 1440.50 97233.75 M-031
mm sieve @ 0.015 cum per sqm
d) Overhead charges @ 10% on (a+b+c) 131524.58
e) Contractor's profit @ 10% on (a+b+c+d) 144677.04
Cost for 4500 sqm = a+b+c+d+e 1591447.44
Rate per sqm = (a+b+c+d+e)/4500 353.65 204.00
say 354.00 73.53
2 tippers will be needed to match the capacity of chip
spreader and front end loader.
5.4 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor including for brooming of key aggregates day 8.000 244.56 1956.48 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2380.00 14280.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour hour 2.570 954.00 2451.78 P&M-004

Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 850.00 8500.00 P&M-048
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1687.00 10122.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
c) Material
Bitumen@ 6.8 kg per sqm tonne 30.600 32627.00 998386.20 M-077
Crushed stone coarse aggregate (loose passing 63 cum 405.000 1936.00 784080.00 M-037
mm and retained on 2.8 mm sieve @ 0.09 cum per
sqm
Key aggregates passing 26.5 mm and retained on 2.8 cum 81.000 1089.00 88209.00 M-026
mm sieve @ 0.018 cum per sqm
d) Overhead charges @ 10% on (a+b+c) 191688.74
e) Contractor's profit @ 10% on (a+b+c+d) 210857.62
Cost for 4500 sqm = a+b+c+d+e 2319433.78
Rate per sqm = (a+b+c+d+e)/4500 515.43 211.00
say 515.00 144.08
2 tippers and 2 rollers will be needed to match the capacity
of chip spreader and front end loader.
5.5 Built-up-Spray Grout

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Providing, laying and rolling of built-up-spray grout layer
over prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application
'(a) Without anti stripping agent as per IS:14982( Refer
Appendix-5 of MoSRT&H specification)

Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor including for brooming of key aggregates day 8.000 244.56 1956.48 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2380.00 14280.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Bitumen pressure distributor for 3000 x 2 sqm @ 1750 hour 3.430 954.00 3272.22 P&M-004
sqm per hour
Tipper 5.5 cum capacity hour 10.000 850.00 8500.00 P&M-048
Vibratory roller 8 tonnes hour 6.000 1687.00 10122.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for tonne 10.000 32627.00 326270.00 M-077
each layer
Crushed stone coarse aggregate passing 53 mm and cum 300.000 2035.00 610500.00 M-035
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 39.000 1440.50 56179.50 M-031
mm sieve @ 0.13 cum per 10 sqm
d) Overhead charges @ 10% on (a+b+c) 103998.22
e) Contractor's profit @ 10% on (a+b+c+d) 114398.04
Cost for 3000 sqm = a+b+c+d+e 1258378.41
Rate per sqm = (a+b+c+d+e)/3000 419.46 204.00
say 419.00 105.39
'(b) With anti stripping agent as per IS:14982
( Refer Appendix-5 of MoSRT&H specification)
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 356.65 142.66 L-12
Mazdoor including for brooming of key aggregates day 8.000 244.56 1956.48 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2380.00 14280.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm
Bitumen pressure distributor for 3000 x 2 sqm @ 1750 hour 3.430 954.00 3272.22 P&M-004
sqm per hour
Tipper 5.5 cum capacity hour 10.000 850.00 8500.00 P&M-048
Vibratory roller 8 tonnes hour 6.000 1687.00 10122.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
c) Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for tonne 10.000 32627.00 326270.00 M-077
each layer
Crushed stone coarse aggregate passing 53 mm and cum 300.000 2035.00 610500.00 M-035
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 39.000 1440.50 56179.50 M-031
mm sieve @ 0.13 cum per 10 sqm
Anti stripping agent @ 1% of weight of binder Kg 100.000 240.00 24000.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 106398.22
e) Contractor's profit @ 10% on (a+b+c+d) 117038.04
Cost for 3000 sqm = a+b+c+d+e 1287418.41
Rate per sqm = (a+b+c+d+e)/3000 429.14 211.00
say 429.00 103.32

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

2 tippers will be needed to match the capacity of hydraulic


chip spreader and front end loader.
5.6 Dense Graded Bituminous Macadam(DBM)
Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 4.0 to
4.5 per cent by weight of total

(a) With hydrated lime/cement as filler ( refer table 500-9 of


MoSRT&H specification)
(i)'with 60/70 or VG-30 grade paved bitumen
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Materials
Bitumen @ 4.25 per cent of weight of mix tonne 19.130 32627.00 624154.51 M-077
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1619.00 102304.61 M-049
25 - 10 mm 13 per cent cum 37.340 1827.00 68220.18 M-046
10 -4.75 mm 19 per cent cum 54.580 1510.00 82415.80 M-040
4.75 mm and below 44 per cent cum 126.390 1104.00 139534.56 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1827.00 157414.32 M-046
10 - 5 mm 28 per cent cum 80.430 1510.00 121449.30 M-040
5 mm and below 40 per cent cum 114.900 1104.00 126849.60 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 123558.55
e) Contractor's profit @ 10% on (a+b+c+d) 135914.40
Cost for 205 cum = a+b+c+d+e 1495058.40
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7666.97 5773.00
say 7667.00 32.81
For GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 124882.35
e) Contractor's profit @ 10% on (a+b+c+d) 137370.59
Cost for 205 cum = a+b+c+d+e 1511076.47
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7749.11 5832.00
say 7749.00 32.87

5.6 (ii)with Polymer modified bitumen 70


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Materials
P.M. Bitumen @ 4.25 per cent of weight of mix tonne 19.130 33280.00 636646.40 M-081
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1619.00 102304.61 M-049
25 - 10 mm 13 per cent cum 37.340 1827.00 68220.18 M-046
10 -4.75 mm 19 per cent cum 54.580 1510.00 82415.80 M-040
4.75 mm and below 44 per cent cum 126.390 1104.00 139534.56 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1827.00 157414.32 M-046
10 - 5 mm 28 per cent cum 80.430 1510.00 121449.30 M-040
5 mm and below 40 per cent cum 114.900 1104.00 126849.60 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 124807.73
e) Contractor's profit @ 10% on (a+b+c+d) 137288.51
Cost for 205 cum = a+b+c+d+e 1510173.59
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7744.48 6424.00
say 7744.00 20.55
For GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 126131.54
e) Contractor's profit @ 10% on (a+b+c+d) 138744.70
Cost for 205 cum = a+b+c+d+e 1526191.65
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7826.62 6483.00
say 7827.00 20.73

(b) With rock dust as filler ( refer table 500-9 of MoSRT&H


specification)
(I)'with 60/70 or VG-30 grade paved bitumen
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Materials
Bitumen @ 4.25 per cent of weight of mix tonne 19.130 32627.00 624154.51 M-077
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1619.00 102304.61 M-049
25 - 10 mm 13 per cent cum 37.340 1827.00 68220.18 M-046
10 -4.75 mm 19 per cent cum 54.580 1510.00 82415.80 M-040
4.75 mm and below 44 per cent cum 126.390 1104.00 139534.56 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1827.00 157414.32 M-046
10 - 5 mm 28 per cent cum 80.430 1510.00 121449.30 M-040
5 mm and below 40 per cent cum 114.900 1104.00 126849.60 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 119205.45
e) Contractor's profit @ 10% on (a+b+c+d) 131125.99
Cost for 205 cum = a+b+c+d+e 1442385.89
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7396.85 5533.00
say 7397.00 33.69
For GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 120529.25
e) Contractor's profit @ 10% on (a+b+c+d) 132582.18
Cost for 205 cum = a+b+c+d+e 1458403.96
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7478.99 5592.00
say 7479.00 33.74

5.6 (ii)'with Polymer modified bitumen 70


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Materials
P.M. Bitumen @ 4.25 per cent of weight of mix tonne 19.130 33280.00 636646.40 M-081
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1619.00 102304.61 M-049
25 - 10 mm 13 per cent cum 37.340 1827.00 68220.18 M-046
10 -4.75 mm 19 per cent cum 54.580 1510.00 82415.80 M-040
4.75 mm and below 44 per cent cum 126.390 1104.00 139534.56 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1827.00 157414.32 M-046
10 - 5 mm 28 per cent cum 80.430 1510.00 121449.30 M-040
5 mm and below 40 per cent cum 114.900 1104.00 126849.60 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 120454.63
e) Contractor's profit @ 10% on (a+b+c+d) 132500.10
Cost for 205 cum = a+b+c+d+e 1457501.08
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7474.36 6184.00
say 7474.00 20.86
For GradingII(19 mm nominal size)

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10% on (a+b+c) 121778.44
e) Contractor's profit @ 10% on (a+b+c+d) 133956.29
Cost for 205 cum = a+b+c+d+e 1473519.14
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7556.51 6243.00
say 7557.00 21.05
(a) With hydrated lime / cement as filler ( refer table 500-9 of
MoSRT&H specification) & anti stripping agent as per
IS:14982( Refer Appendix-5 of MoSRT&H specification)

(I)with 60/70 or VG-30 grade paved bitumen


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Materials
Bitumen @ 4.25 per cent of weight of mix tonne 19.130 32627.00 624154.51 M-077
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1619.00 102304.61 M-049
25 - 10 mm 13 per cent cum 37.340 1827.00 68220.18 M-046
10 -4.75 mm 19 per cent cum 54.580 1510.00 82415.80 M-040
4.75 mm and below 44 per cent cum 126.390 1104.00 139534.56 M-030
Anti stripping agent @ 1% of weight of binder Kg 191.300 240.00 45912.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading - II19 mm (Nominal Size)

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
25 - 10 mm 30 per cent cum 86.160 1827.00 157414.32 M-046
10 - 5 mm 28 per cent cum 80.430 1510.00 121449.30 M-040
5 mm and below 40 per cent cum 114.900 1104.00 126849.60 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 191.300 240.00 45912.00 M-189_1
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 123796.65
e) Contractor's profit @ 10% on (a+b+c+d) 136176.31
Cost for 205 cum = a+b+c+d+e 1497939.41
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7681.74 5771.00
say 7682.00 33.11
For GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 125120.45
e) Contractor's profit @ 10% on (a+b+c+d) 137632.50
Cost for 205 cum = a+b+c+d+e 1513957.48
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7763.88 5830.00
say 7764.00 33.17

5.6 (ii)with Polymer modified bitumen 70


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Materials
P.M. Bitumen @ 4.25 per cent of weight of mix tonne 19.130 33280.00 636646.40 M-081
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 1619.00 102304.61 M-049
25 - 10 mm 13 per cent cum 37.340 1827.00 68220.18 M-046
10 -4.75 mm 19 per cent cum 54.580 1510.00 82415.80 M-040
4.75 mm and below 44 per cent cum 126.390 1104.00 139534.56 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 191.300 240.00 45912.00 M-189_1
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1827.00 157414.32 M-046
10 - 5 mm 28 per cent cum 80.430 1510.00 121449.30 M-040
5 mm and below 40 per cent cum 114.900 1104.00 126849.60 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 191.300 240.00 45912.00 M-189_1
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 125045.83
e) Contractor's profit @ 10% on (a+b+c+d) 137550.42
Cost for 205 cum = a+b+c+d+e 1513054.60
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7759.25 6422.00
say 7759.00 20.82
For GradingII(19 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 126369.64
e) Contractor's profit @ 10% on (a+b+c+d) 139006.61
Cost for 205 cum = a+b+c+d+e 1529072.66
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7841.40 6481.00
say 7841.00 20.98

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.7 A Semi-Dense Bituminous Concrete
Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output
of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per
cent of mix and filler, t
(a) With hydrated lime / cement as filler ( refer table 500-9
of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 32627.00 660696.75 M-077
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-077
weight of mix = 450 tonne

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 126221.60
e) Contractor's profit @ 10% on (a+b+c+d) 138843.76
Cost for 205 cum = a+b+c+d+e 1527281.36
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7832.21 6101.00
say 7832.00 28.37
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 132736.52
e) Contractor's profit @ 10% on (a+b+c+d) 146010.17
Cost for 205 cum = a+b+c+d+e 1606111.89
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8236.47 6468.00
say 8236.00 27.33
5.7(B) with Polymer modified bitumen 70
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 33280.00 673920.00 M-081
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-081
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 127543.92
e) Contractor's profit @ 10% on (a+b+c+d) 140298.32
Cost for 205 cum = a+b+c+d+e 1543281.49
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7914.26 6790.00
say 7914.00 16.55
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 134205.77
e) Contractor's profit @ 10% on (a+b+c+d) 147626.35
Cost for 205 cum = a+b+c+d+e 1623889.81
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8327.64 7234.00
say 8328.00 15.12
5.7(C) with CRMB-55
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 31950.00 646987.50 M-079
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 31950.00 718875.00 M-079
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 124850.67
e) Contractor's profit @ 10% on (a+b+c+d) 137335.74
Cost for 205 cum = a+b+c+d+e 1510693.16
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7747.14 6288.00
say 7747.00 23.20

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 131213.27
e) Contractor's profit @ 10% on (a+b+c+d) 144334.60
Cost for 205 cum = a+b+c+d+e 1587680.56
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8141.95 6676.00
say 8142.00 21.96
5.7 (b) With rockdustt as filler ( refer table 500-9 of MoSRT&H
specification)
(I)'with 60/70 or VG-30 grade bitumen
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 32627.00 660696.75 M-077
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-077
weight of mix = 450 tonne

Page 29 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 121868.50
e) Contractor's profit @ 10% on (a+b+c+d) 134055.35
Cost for 205 cum = a+b+c+d+e 1474608.85
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7562.10 5861.00
say 7562.00 29.02
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 128383.42
e) Contractor's profit @ 10% on (a+b+c+d) 141221.76
Cost for 205 cum = a+b+c+d+e 1553439.38
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7966.36 6229.00
say 7966.00 27.89
5.7(B) with Polymer modified bitumen 70
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)

Page 30 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 33280.00 673920.00 M-081
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-081
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 123190.82
e) Contractor's profit @ 10% on (a+b+c+d) 135509.91
Cost for 205 cum = a+b+c+d+e 1490608.98
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7644.15 6550.00
say 7644.00 16.70
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 129852.67
e) Contractor's profit @ 10% on (a+b+c+d) 142837.94
Cost for 205 cum = a+b+c+d+e 1571217.30
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8057.52 6994.00
say 8058.00 15.21

Page 31 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.7(C) with CRMB-55
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 31950.00 646987.50 M-079
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 31950.00 718875.00 M-079
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030

Page 32 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 120497.57
e) Contractor's profit @ 10% on (a+b+c+d) 132547.33
Cost for 205 cum = a+b+c+d+e 1458020.65
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7477.03 6048.00
say 7477.00 23.63
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 126860.17
e) Contractor's profit @ 10% on (a+b+c+d) 139546.19
Cost for 205 cum = a+b+c+d+e 1535008.05
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 7871.84 6437.00
say 7872.00 22.29
(a) With hydrated lime / cement as filler ( refer table 500-9 of
MoSRT&H specification) & anti stripping agent as per
IS:14982( Refer Appendix-5 of MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 32627.00 660696.75 M-077
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum

Page 33 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
Anti stripping agent @ 1% of weight of binder Kg 202.500 240.00 48600.00 M-189_1
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-077
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 131081.60
e) Contractor's profit @ 10% on (a+b+c+d) 144189.76
Cost for 205 cum = a+b+c+d+e 1586087.36
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8133.78 6352.00
say 8134.00 28.05
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 138136.52
e) Contractor's profit @ 10% on (a+b+c+d) 151950.17
Cost for 205 cum = a+b+c+d+e 1671451.89
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8571.55 6748.00
say 8572.00 27.03
5.7(B) with Polymer modified bitumen 70
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour

Page 34 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 33280.00 673920.00 M-081
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
Anti stripping agent @ 1% of weight of binder Kg 202.500 240.00 48600.00 M-189_1
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-081
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 132403.92
e) Contractor's profit @ 10% on (a+b+c+d) 145644.32
Cost for 205 cum = a+b+c+d+e 1602087.49
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8215.83 7041.00
say 8216.00 16.69
5.7 for GradingII(10 mm nominal size)

Page 35 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10% on (a+b+c) 139605.77
e) Contractor's profit @ 10% on (a+b+c+d) 153566.35
Cost for 205 cum = a+b+c+d+e 1689229.81
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8662.72 7513.00
say 8663.00 15.31
5.7(C) with CRMB-55
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) CRMB-55 @ 4.5 per cent of weight of mix tonne 20.250 31950.00 646987.50 M-079
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
Anti stripping agent @ 1% of weight of binder Kg 202.500 240.00 48600.00 M-189_1
or
Grading II: 10 mm (Nominal Size)
CRMB -55 @5 per cent of weight of mix tonne 22.500 31950.00 718875.00 M-079
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes

Page 36 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 129710.67
e) Contractor's profit @ 10% on (a+b+c+d) 142681.74
Cost for 205 cum = a+b+c+d+e 1569499.16
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8048.71 6539.00
say 8049.00 23.09
for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 136613.27
e) Contractor's profit @ 10% on (a+b+c+d) 150274.60
Cost for 205 cum = a+b+c+d+e 1653020.56
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8477.03 6956.00
say 8477.00 21.87
5.7 (a) With rock dust as filler ( refer table 500-9 of MoSRT&H
specification) & anti stripping agent as per IS:14982( Refer
Appendix-5 of MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller

Page 37 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 32627.00 660696.75 M-077
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 202.500 240.00 48600.00 M-189_1
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-077
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 126728.50
e) Contractor's profit @ 10% on (a+b+c+d) 139401.35
Cost for 205 cum = a+b+c+d+e 1533414.85
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7863.67 6112.00
say 7864.00 28.66
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 133783.42
e) Contractor's profit @ 10% on (a+b+c+d) 147161.76
Cost for 205 cum = a+b+c+d+e 1618779.38
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8301.43 6508.00
say 8301.00 27.55
5.7(B) with Polymer modified bitumen 70
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

Page 38 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 33280.00 673920.00 M-081
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 202.500 240.00 48600.00 M-189_1
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-081
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1

Page 39 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 128050.82
e) Contractor's profit @ 10% on (a+b+c+d) 140855.91
Cost for 205 cum = a+b+c+d+e 1549414.98
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7945.72 6801.00
say 7946.00 16.84
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 135252.67
e) Contractor's profit @ 10% on (a+b+c+d) 148777.94
Cost for 205 cum = a+b+c+d+e 1636557.30
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8392.60 7274.00
say 8393.00 15.38
(b) With rockdustt as filler ( refer table 500-9 of MoSRT&H
specification)
5.7(C) with CRMB-55
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 244.56 3912.96 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

Page 40 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) CRMB-55@ 4.5 per cent of weight of mix tonne 20.250 31950.00 646987.50 M-079
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35 M-044
10 - 5 mm 38 per cent cum 108.870 1510.00 164393.70 M-040
5 mm and below 40 per cent cum 114.600 1104.00 126518.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
or
Grading II: 10 mm (Nominal Size)
CRMB-55@5 per cent of weight of mix tonne 22.500 31950.00 718875.00 M-079
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1510.00 245299.50 M-040
4.75 and below@ 41 per cent cum 116.850 1104.00 129002.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 125897.57
e) Contractor's profit @ 10% on (a+b+c+d) 138487.33

Page 41 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 205 cum = a+b+c+d+e 1523360.65
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 7812.11 6328.00
say 7812.00 23.45
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 132260.17
e) Contractor's profit @ 10% on (a+b+c+d) 145486.19
Cost for 205 cum = a+b+c+d+e 1600348.05
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8206.91 6716.00
say 8207.00 22.20

Page 42 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site
for six hours as the hot mix plant and paver will take six
hours for mixing and paving the output of 450 tonnes
considered in this ana
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density
of 1.5 tonne/cum is
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.7 (D) (i)Using cold mix Binder SS-2 ( as per IRC:SP:100-


2014)
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 1.000 356.65 356.65
Mazdoor day 12.000 244.56 2934.72
Skilled mazdoor day 5.000 356.65 1783.25
b) Machinery
Paver finisher electronic with sensor control @ 75 cum hour 6.000 2341.00 14046.00
per hour
Generator 125 KVA hour 6.000 1500.00 9000.00
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00
Add 10 per cent of cost of carriage to cover cost of 1575.00
loading and unloading
Vibratory roller 8 tonnes hour 6.00x0.65* 1687.00 6579.30
Pneumatic Tyred roller hour 6.00x0.65* 1039.00 4052.10
Water tanker 6kl capacity hour 1.000 440.00 440.00
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen Emulsion @85 litre per tonne SS-2 tonne 33.750 27790.00 937912.50
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes

Page 43 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1599.50 91651.35
10 - 5 mm 40 per cent cum 114.600 1510.00 173046.00
5 mm and below 40 per cent cum 114.600 1104.00 126518.40
Fillers etc. @ 2% of aggregates 7824.32
Water Kl 6.000 45.00 270.00
or
Grading II: 10 mm (Nominal Size)
i) Bitumen Emulsion @85 litre per tonne SS-2 tonne 33.750 27790.00 937912.50
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 60 per cent cum 171.000 1510.00 258210.00
4.75 and below@ 40 per cent cum 114.000 1104.00 125856.00
Fillers etc. @ 2% of aggregates 7681.32
Water Kl 6.000 45.00 270.00
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 140178.56
e) Contractor's profit @ 10% on (a+b+c+d) 154196.41
Cost for 205 cum = a+b+c+d+e 1696160.56
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8698.26
say 8698.00
5.7 for GradingII(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 139449.28
e) Contractor's profit @ 10% on (a+b+c+d) 153394.21
Cost for 205 cum = a+b+c+d+e 1686896.34
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8650.75
say 8651.00

5.8 Bituminous Concrete


Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average
output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 per cent of mix and
filler,
(a) With hydrated lime/cement as filler ( refer table 500-9 of
MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen

Page 44 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 140452.86
e) Contractor's profit @ 10% on (a+b+c+d) 154498.15
Cost for 205 cum = a+b+c+d+e 1638537.34
Rate per cum = (a+b+c+d+e)/191 8578.73 6578.00

Page 45 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8579.00 30.42
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 140809.11
e) Contractor's profit @ 10% on (a+b+c+d) 154890.02
Cost for 205 cum = a+b+c+d+e 1616833.17
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8465.10 6678.00
say 8465.00 26.76

(ii)with Polymer modified bitumen 70


Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044

Page 46 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 151552.11
e) Contractor's profit @ 10% on (a+b+c+d) 166707.32
Cost for 205 cum = a+b+c+d+e 1676538.27
Rate per cum = (a+b+c+d+e)/191 8777.69 7645.00
say 8778.00 14.82
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 151908.36
e) Contractor's profit @ 10% on (a+b+c+d) 167099.20
Cost for 205 cum = a+b+c+d+e 1654834.09
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8664.05 7460.00
say 8664.00 16.14

(b) With rock dust as filler ( refer table 500-9 of MoSRT&H


specification)
(I)'with 60/70 or VG-30 grade bitumen
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes

Page 47 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 136127.34
e) Contractor's profit @ 10% on (a+b+c+d) 149740.08
Cost for 205 cum = a+b+c+d+e 1585922.76
Rate per cum = (a+b+c+d+e)/191 8303.26 6322.00
say 8303.00 31.34
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 136483.59
e) Contractor's profit @ 10% on (a+b+c+d) 150131.95
Cost for 205 cum = a+b+c+d+e 1564218.58
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8189.63 6422.00
say 8190.00 27.53

(ii)with Polymer modified bitumen 70


Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading

Page 48 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 147226.59
e) Contractor's profit @ 10% on (a+b+c+d) 161949.25
Cost for 205 cum = a+b+c+d+e 1623923.68
Rate per cum = (a+b+c+d+e)/191 8502.22 7104.00
say 8502.00 19.68
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 147582.84
e) Contractor's profit @ 10% on (a+b+c+d) 162341.13
Cost for 205 cum = a+b+c+d+e 1602219.51
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8388.58 7204.00
say 8389.00 16.45
(a) With hydrated lime / cement as filler ( refer table 500-9 of
MoSRT&H specification) & anti stripping agent as per
IS:14982( Refer Appendix-5 of MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen


Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12

Page 49 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 145492.86
e) Contractor's profit @ 10% on (a+b+c+d) 160042.15
Cost for 205 cum = a+b+c+d+e 1703121.34
Rate per cum = (a+b+c+d+e)/191 8916.87 6863.00
say 8917.00 29.93
for Grading-II(10 mm nominal size)

Page 50 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10% on (a+b+c) 145849.11
e) Contractor's profit @ 10% on (a+b+c+d) 160434.02
Cost for 205 cum = a+b+c+d+e 1681417.17
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8803.23 6963.00
say 8803.00 26.43
(ii)with Polymer modified bitumen 70
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030

Page 51 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5900.00 50858.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 156592.11
e) Contractor's profit @ 10% on (a+b+c+d) 172251.32
Cost for 205 cum = a+b+c+d+e 1741122.27
Rate per cum = (a+b+c+d+e)/191 9115.82 7545.00
say 9116.00 20.82
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 156948.36
e) Contractor's profit @ 10% on (a+b+c+d) 172643.20
Cost for 205 cum = a+b+c+d+e 1719418.09
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 9002.19 7745.00
say 9002.00 16.23

(a) With rock dust as filler ( refer table 500-9 of MoSRT&H


specification) & anti stripping agent as per IS:14982( Refer
Appendix-5 of MoSRT&H specification)

(I)'with 60/70 or VG-30 grade bitumen


Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 32627.00 734107.50 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes

Page 52 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-006
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 141167.34
e) Contractor's profit @ 10% on (a+b+c+d) 155284.08
Cost for 205 cum = a+b+c+d+e 1650506.76
Rate per cum = (a+b+c+d+e)/191 8641.40 6607.00
say 8641.00 30.79
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 141523.59
e) Contractor's profit @ 10% on (a+b+c+d) 155675.95
Cost for 205 cum = a+b+c+d+e 1628802.58
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8527.76 6707.00
say 8528.00 27.15
(a) With hydrated lime/cement as filler ( refer table 500-9 of
MoSRT&H specification)
(ii)with Polymer modified bitumen 70
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 97.00 1552.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 102.00 510.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16575.00 99450.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 2480.00 14880.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 882.00 5292.00 P&M-017

Page 53 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tipper 10 tonne capacity tonne.km 450 x L 3.50 7875.00 Lead =5 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 787.50
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 575.00 2242.50 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1421.00 5541.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1039.00 4052.10 P&M-045
roller.
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 33280.00 748800.00 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 1777.00 177255.75 M-045
10 - 5 mm 23 per cent cum 65.550 1510.00 98980.50 M-040
5 mm and below 40 per cent cum 114.000 1104.00 125856.00 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1599.50 136757.25 M-044
10 - 5 mm 25 per cent cum 71.250 1510.00 107587.50 M-040
5 mm and below43 per cent cum 122.550 1104.00 135295.20 M-030
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
Filler @ 2 per cent of weight of aggregates. tonne 8.620 850.00 7327.00 M-188
*Any one of the alternative may be adopted as per
approved design
for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10% on (a+b+c) 152266.59
e) Contractor's profit @ 10% on (a+b+c+d) 167493.25
Cost for 205 cum = a+b+c+d+e 1688507.68
Rate per cum = (a+b+c+d+e)/191 8840.35 7389.00
say 8840.00 19.64
for Grading-II(10 mm nominal size)
d) Overhead charges @ 10% on (a+b+c) 152622.84
e) Contractor's profit @ 10% on (a+b+c+d) 167885.13
Cost for 205 cum = a+b+c+d+e 1666803.51
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 8726.72 7489.00
say 8727.00 16.53

Page 54 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site
for six hours as the hot mix plant and paver will take six
hours for mixing and paving the output of 450 tonnes
considered in this ana
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density
of 1.5 tonne/cum is
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.9 Surface Dressing


Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller

(a)Without anti stripping agent as per IS:14982( Refer Appendix-5


of MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen
Unit = sqm
Taking output = 9000 sqm
:-19 mm nominal chipping size
a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor hour 6.000 954.00 5724.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 924.00 5544.00 P&M-044
c) Material

Page 55 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Bitumen@ 1.20 kg per sqm tonne 10.800 32627.00 352371.60 M-077
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1777.00 239895.00 M-053
cum per sqm
d) Overhead charges @ 10% on (a+b+c) 62664.92
e) Contractor's profit @ 10% on (a+b+c+d) 68931.41
Cost for 9000 sqm = a+b+c+d+e 771186.60
Rate per sqm = (a+b+c+d+e)/9000 85.69 56.00
say 86.00 53.57
5.9 13 mm nominal size chipping

a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1687.00 10122.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 10.000 32627.00 326270.00 M-077
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1510.00 135900.00 M-052
cum per sqm
d) Overhead charges @ 10% on (a+b+c) 50580.98
e) Contractor's profit @ 10% on (a+b+c+d) 55639.08
Cost for 9000 sqm = a+b+c+d+e 620291.72
Rate per sqm = (a+b+c+d+e)/9000 68.92 48.00
say 69.00 43.75

(ii)with bitumen emulsion( CRS-2)


Unit = sqm
Taking output = 9000 sqm
:-19 mm nominal chipping size
a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour

Page 56 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor hour 6.000 954.00 5724.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 32627.00 352371.60 M-077
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1777.00 239895.00 M-053
cum per sqm
d) Overhead charges @ 10% on (a+b+c) 62664.92
e) Contractor's profit @ 10% on (a+b+c+d) 68931.41
Cost for 9000 sqm = a+b+c+d+e 771186.60
Rate per sqm = (a+b+c+d+e)/9000 85.69 55.00
say 86.00 56.36
5.9 13 mm nominal size chipping

a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1687.00 10122.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 32627.00 293643.00 M-077
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1510.00 135900.00 M-052
cum per sqm
d) Overhead charges @ 10% on (a+b+c) 50580.98
e) Contractor's profit @ 10% on (a+b+c+d) 55639.08
Cost for 9000 sqm = a+b+c+d+e 587664.72
Rate per sqm = (a+b+c+d+e)/9000 65.30 47.00
say 65.00 38.30
(b)With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
(I)'with 60/70 or VG-30 grade bitumen
Unit = sqm
Taking output = 9000 sqm
:-19 mm nominal chipping size
a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13

Page 57 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor hour 6.000 954.00 5724.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 32627.00 352371.60 M-077
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1777.00 239895.00 M-053
cum per sqm
Anti stripping agent @ 1% of weight of binder Kg 108.000 240.00 25920.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 66551.03
e) Contractor's profit @ 10% on (a+b+c+d) 73206.13
Cost for 9000 sqm = a+b+c+d+e 805267.42
Rate per sqm = (a+b+c+d+e)/9000 89.47 59.00
say 89.00 50.85
5.9 13 mm nominal size chipping

a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 9.000 244.56 2201.04 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 337.00 2426.40 P&M-031
Air compressor 250 cfm hour 7.200 435.00 3132.00 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2380.00 14280.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 850.00 5100.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1687.00 10122.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 32627.00 293643.00 M-077
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1510.00 135900.00 M-052
cum per sqm
Anti stripping agent @ 1% of weight of binder Kg 90.000 240.00 21600.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 50304.47
e) Contractor's profit @ 10% on (a+b+c+d) 55334.91
Cost for 9000 sqm = a+b+c+d+e 608684.05
Rate per sqm = (a+b+c+d+e)/9000 67.63 50.00
say 68.00 36.00

Page 58 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.10 Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or
cut-back or emulsion to required line, grade and level to
serve as wearing course on a pr

(a)Without anti stripping agent as per IS:14982( Refer Appendix-5


of MoSRT&H specification)

Unit = sqm
Taking output = 10250 sqm (205 cum)
Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less
than 75 tonnes/hour .
a) Labour

Page 59 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 244.56 3912.96 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
i) Batch type HMP 75 tonne per hour hour 6.000 22823.00 136938.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2341.00 14046.00 P&M-034
iv) Smooth wheeled/tandom roller 8-10 tonnes weight hour 6.000 1039.00 6234.00 P&M-045

c) Material
Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum 276.750 1599.50 442661.63 M-043
cum per 10 sqm
Sub Total= 640246.42
(i) Bitumen 60-70 or VG-30 grade@ 14.60 kg per 10 sqm tonne 15.970 32627.00 521053.19 M-077

d) Overhead charges @ 10% on (a+b+c) 116129.96


e) Contractor's profit @ 10% on (a+b+c+d) 127742.96
Cost for 10250 sqm = a+b+c+d+e 1405172.53
Rate per sqm = (a+b+c+d+e)/10250 137.09 96.00
say 137.00 42.71

(ii) CRMB 55 @ 14.60 kg per 10 sqm tonne 16.970 31950.00 542191.50 M-079
d) Overhead charges @ 10% on (a+b+c) 118243.79
e) Contractor's profit @ 10% on (a+b+c+d) 130068.17
Cost for 10250 sqm = a+b+c+d+e 1430749.88
Rate per sqm = (a+b+c+d+e)/10250 139.59
say 140.00

(iii) CRMB 55 @ 14.60 kg per 10 sqm tonne 16.970 31950.00 542191.50 M-079
d) Overhead charges @ 10% on (a+b+c) 118243.79
e) Contractor's profit @ 10% on (a+b+c+d) 130068.17
Cost for 10250 sqm = a+b+c+d+e 1430749.88
Rate per sqm = (a+b+c+d+e)/10250 139.59
say 140.00

If a premix sand seal coat of 'B' type is proposed, the same


is required to be provided over the open graded premix
carpet immediately on the same day. As the same HMP and
other machines will be used for laying of premix sand seal
coat, out of 6 effective
(iv) Case - IV: Open-Graded Premix Surfacing using
cationic Bitumen Emulsion ( CMS )
Unit = sqm
Taking output = 900 sqm (24.3 cum)

Page 60 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.800 356.65 285.32 L-12
Mazdoor day 18.000 244.56 4402.08 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6.000 188.00 1128.00 P&M-009
Smooth wheeled steel roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm tonne 1.940 27790.00 53912.60 M-073
Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum 24.300 1599.50 38867.85 M-043
cum per 10 sqm
d) Overhead charges @ 10% on (a+b+c) 10485.32
e) Contractor's profit @ 10% on (a+b+c+d) 11533.85
Cost for 900 sqm = a+b+c+d+e 126872.31
Rate per sqm = (a+b+c+d+e)/900 140.97 104.00
say 141.00 35.58
(b)With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
Unit = sqm
Taking output = 10250 sqm (205 cum)
Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less
than 75 tonnes/hour .
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 244.56 3912.96 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
i) Batch type HMP 75 tonne per hour hour 6.000 22823.00 136938.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2341.00 14046.00 P&M-034
iv) Smooth wheeled/tandom roller 8-10 tonnes weight hour 6.000 1039.00 6234.00 P&M-045

c) Material
Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum 276.750 1599.50 442661.63 M-043
cum per 10 sqm
Anti stripping agent @ 1% of weight of binder Kg 149.700 200.00 29940.00
Sub Total = 670186.42
Bitumen 60/70 or VG-30 grade @ 14.60 kg per 10 sqm tonne 14.970 32627.00 488426.19 M-077

d) Overhead charges @ 10% on (a+b+c) 115861.26


e) Contractor's profit @ 10% on (a+b+c+d) 127447.39
Cost for 10250 sqm = a+b+c+d+e 1401921.26

Page 61 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per sqm = (a+b+c+d+e)/10250 136.77 100.00
say 137.00 37.00

(ii) CRMB 55 @ 14.60 kg per 10 sqm tonne 14.970 31950.00 478291.50 M-079
d) Overhead charges @ 10% on (a+b+c) 114847.79
e) Contractor's profit @ 10% on (a+b+c+d) 126332.57
Cost for 10250 sqm = a+b+c+d+e 1389658.28
Rate per sqm = (a+b+c+d+e)/10250 135.58
say 136.00

(iii) PMB @ 14.60 kg per 10 sqm tonne 14.970 33280.00 498201.60 M-081
d) Overhead charges @ 10% on (a+b+c) 116838.80
e) Contractor's profit @ 10% on (a+b+c+d) 128522.68
Cost for 10250 sqm = a+b+c+d+e 1413749.51
Rate per sqm = (a+b+c+d+e)/10250 137.93
say 138.00

Page 62 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.11 Close Graded Premix Surfacing/Mixed Seal Surfacing

Mechanical means using HMP of appropriate capacity not


less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of 11.2
mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b)
aggregates using penetration grade bitumen to the
required line, grade and level to

(a)Without anti stripping agent as per IS:14982( Refer Appendix-5


of MoSRT&H specification)
Using Type - A material
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 244.56 3912.96 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
i) HMP of appropicate capacity. hour 6.000 22823.00 136938.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2341.00 14046.00 P&M-034
iv) Smooth wheeled8-10 tonnes weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm tonne 22.900 32627.00 747158.30 M-077
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum 276.750 1510.00 417892.50 M-041
cum per 10 sqm
Per Sqm Basic Cost of Labour, Material & Mechinery (a+b+c) 133.00
d) Overhead charges @ 10% on (a+b+c) 136194.56
e) Contractor's profit @ 10% on (a+b+c+d) 149814.02
Cost for 10250 sqm = a+b+c+d+e 1647954.17
Rate per sqm = (a+b+c+d+e)/10250 160.78 121.00
say 161.00 33.06
Using Type - B material
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 244.56 3912.96 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
i) HMP of appropicate capacity. hour 6.000 22823.00 136938.00 P&M-021

Page 63 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
ii) Electric Generator Set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2341.00 14046.00 P&M-034
iv) Smooth wheeled8-10 tonnes weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Type - B
Bitumen @ 19 kg per 10 sqm tonne 19.980 32627.00 651887.46 M-077
Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 276.750 1599.50 442661.63 M-042
0.27 cum per 10 sqm
d) Overhead charges @ 10% on (a+b+c) 129144.39
e) Contractor's profit @ 10% on (a+b+c+d) 142058.83
Cost for 10250 sqm = a+b+c+d+e 1562647.10
Rate per sqm = (a+b+c+d+e)/10250 152.45 109.00
say 152.00 39.45
(b)With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
Using Type - A material
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 244.56 3912.96 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
i) HMP of appropicate capacity. hour 6.000 22823.00 136938.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2341.00 14046.00 P&M-034
iv) Smooth wheeled8-10 tonnes weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm tonne 22.500 32627.00 734107.50 M-077
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum 276.750 1510.00 417892.50 M-041
cum per 10 sqm
Anti stripping agent @ 1% of weight of binder Kg 225.000 240.00 54000.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 140289.48
e) Contractor's profit @ 10% on (a+b+c+d) 148918.43
Cost for 10250 sqm = a+b+c+d+e 1638102.70
Rate per sqm = (a+b+c+d+e)/10250 159.81 121.00
say 160.00 32.23
Using Type - B material

Page 64 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 244.56 3912.96 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 356.65 1783.25 L-15
b) Machinery
i) HMP of appropicate capacity. hour 6.000 22823.00 136938.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2341.00 14046.00 P&M-034
iv) Smooth wheeled8-10 tonnes weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Type - B
Bitumen @ 19 kg per 10 sqm tonne 19.480 32627.00 635573.96 M-077
Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 276.750 1599.50 442661.63 M-042
0.27 cum per 10 sqm
Anti stripping agent @ 1% of weight of binder Kg 194.800 240.00 46752.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 132188.24
e) Contractor's profit @ 10% on (a+b+c+d) 145407.06
Cost for 10250 sqm = a+b+c+d+e 1599477.68
Rate per sqm = (a+b+c+d+e)/10250 156.05 114.00
say 156.00 36.84

Page 65 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.12 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
(a) Without anti stripping agent as per IS:14982( Refer Appendix-5
of MoSRT&H specification)
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
Case - I : Type A
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 2380.00 14280.00 P&M-025
Tipper 5.5 cum capacity hour 6.000 850.00 5100.00 P&M-048
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Smooth wheeled roller 8 -10 tonne weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Bitumen@ 9.80 kg per 10 sqm tonne 10.580 32627.00 345193.66 M-077
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 1807.00 166695.75 M-050
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 10% on (a+b+c) 55213.64
e) Contractor's profit @ 10% on (a+b+c+d) 60735.00
Cost for 10250 sqm = a+b+c+d+e 668085.00
Rate per sqm = (a+b+c+d+e)/10250 65.18 45.00
say 65.00 44.44

Since seal coat is provided immediately over the bituminous


layers, mechanical broom for clearing has not been catered.

5.12 Case - II : Type B


Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and penetration
bitumen of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 4.000 244.56 978.24 L-13
b) Machinery
HMP of 75 tonnes/hour. hour 2.000 16575.00 33150.00 P&M-022
Electric Generator Set 250 KVA hour 2.000 1500.00 3000.00 P&M-081
Front end loader 1 cum bucket capacity hour 2.000 1341.00 2682.00 P&M-017
Tipper 10 tonne capacity tonne.km 104 x 'L' 3.50 3640.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 364.00
and unloading

Page 66 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Paver finisher hydrostatic with sensor attachment hour 2.000 2341.00 4682.00 P&M-034
Smooth wheeled 8-10 tonnes capacity hour 2.000 924.00 1848.00 P&M-044
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.340 32627.00 174228.18 M-077
Crushed stone chipping of 6.7 mm size defined as cum 47.160 1807.00 85218.12 M-050
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm
d) Overhead charges @ 10% on (a+b+c) 30984.76
e) Contractor's profit @ 10% on (a+b+c+d) 34083.24
Cost for 7858 sqm = a+b+c+d+e 374915.60
Rate per sqm = (a+b+c+d+e)/7858 47.71 35.00
say 48.00 37.14
(b) With anti stripping agent as per IS:14982( Refer Appendix-5 of
MoSRT&H specification)
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
Case - I : Type A
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 2380.00 14280.00 P&M-025
Tipper 5.5 cum capacity hour 6.000 850.00 5100.00 P&M-048
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Smooth wheeled roller 8 -10 tonne weight hour 6.000 924.00 5544.00 P&M-044
c) Material
Bitumen@ 9.80 kg per 10 sqm tonne 10.050 32627.00 327901.35 M-077
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 1599.50 147553.88 M-042
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
Anti stripping agent @ 1% of weight of binder Kg 100.500 240.00 24120.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 53982.22
e) Contractor's profit @ 10% on (a+b+c+d) 59380.44
Cost for 10250 sqm = a+b+c+d+e 653184.84
Rate per sqm = (a+b+c+d+e)/10250 63.73 47.00
say 64.00 36.17

Since seal coat is provided immediately over the bituminous


layers, mechanical broom for clearing has not been catered.

5.12 Case - II : Type B


Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and penetration
bitumen of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)

Page 67 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 4.000 244.56 978.24 L-13
b) Machinery
HMP of 75 tonnes/hour. hour 2.000 16575.00 33150.00 P&M-022
Electric Generator Set 250 KVA hour 2.000 1500.00 3000.00 P&M-081
Front end loader 1 cum bucket capacity hour 2.000 1341.00 2682.00 P&M-017
Tipper 10 tonne capacity tonne.km 104 x 'L' 3.50 3640.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 364.00
and unloading
Paver finisher hydrostatic with sensor attachment hour 2.000 2341.00 4682.00 P&M-034
Smooth wheeled 8-10 tonnes capacity hour 2.000 924.00 1848.00 P&M-044
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.340 32627.00 174228.18 M-077
Crushed stone chipping of 6.7 mm size defined as cum 47.160 1599.50 75432.42 M-050
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm
Anti stripping agent @ 1% of weight of binder Kg 53.400 240.00 12816.00 M-189_1
d) Overhead charges @ 10% on (a+b+c) 31287.79
e) Contractor's profit @ 10% on (a+b+c+d) 34416.57
Cost for 7858 sqm = a+b+c+d+e 378582.26
Rate per sqm = (a+b+c+d+e)/7858 48.18 37.00
say 48.00 37.14
Since seal coat is required to be provided over the premix
carpet on the same day, out of the 6 working hours of the
HMP, 4.00 hours are proposed to be utilised for the premix
carpet and the balance 2.00 hours for the seal coat. Hence
2.00 hours have been

5.13 Supply of Stone Aggregates for Pavement Courses

Supply of stone aggregates from approved sources


conforming to the rates
Competitive market physical
to berequirement,
as certained.specified in the
Alternatively,
respective
rates specified
for stone clauses,
crushing given including
in chapterroyalties,
1may be fees rents,
adopted,
ifcollection, transportation,
found economical. In case forstacking
supply ofand testingat site
aggregates and
measured
are in cum nearest
not available, as per clause
crusher514
site may be as certained.
Loading and u
5.14 Mastic Asphalt
Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing a
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate day 0.440 356.65 156.93 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
Mazdoor skilled day 1.000 356.65 356.65 L-15
b) Machinery

Page 68 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mechanical broom @ 1250 sqm per hour hour 0.060 337.00 20.22 P&M-031
Air compressor 250 cfm hour 0.060 435.00 26.10 P&M-001
Mastic cooker 1 tonne capacity hour 6.000 56.00 336.00 P&M-030
Bitumen boiler 1500 litres capacity hour 6.000 1590.00 9540.00 P&M-005
Tractor for towing and positioning of mastic cooker and hour 1.000 323.00 323.00 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with
coarse aggregates (based on mix design done by CRRI for
a specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight tonne 0.204 32627.00 6655.91 M-077
of mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on cum 0.390 698.00 272.22 M-021
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less tonne 0.360 5900.00 2124.00 M-188
than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cum 0.550 1599.50 879.73 M-043
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 3890.00 70.02 M-142
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by kg 0.500 32627.00 16313.50 M-077
weight = 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg

d) Overhead charges @ 10% on (a+b+c) 3951.99


e) Contractor's profit @ 10% on (a+b+c+d) 4347.19
Cost for 35.00 sqm = a+b+c+d+e 47819.04
Rate per sqm = (a+b+c+d+e)/35 1366.26 429.00
say 1366.00 218.41
1.The rates for 50 mm & 40 mm thick layers may be worked
out on pro-rata basis.
2.Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
5.15 Slurry Seal
Providing and laying slurry seal consisting of a mixture of
fine aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to
5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)

Page 69 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Mechanical broom hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Mobile slurry seal equipment hour 6.000 2072.00 12432.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 850.00 5100.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1137.00 6822.00 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 40572.00 785473.92 M-080

Fine aggregate 4.75 mm and below 87 per cent of cum 102.080 1104.00 112696.32 M-030
total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5, = 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 tonne 3.520 5900.00 20768.00 M-188
Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 95894.32
e) Contractor's profit @ 10% on (a+b+c+d) 105483.75
Cost for 16000 sqm = a+b+c+d+e 1160321.27
Rate per sqm = (a+b+c+d+e)/16000 72.52 51.00
say 73.00 43.14
5.15 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery
Mechanical broom hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Mobile slurry seal equipment hour 6.000 2072.00 12432.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 850.00 5100.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x tonne 17.160 40572.00 696215.52 M-080
0.13

Page 70 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Fine aggregate 3 mm and below 85 per cent of total cum 74.800 698.00 52210.40 M-022
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 5900.00 15576.00 M-188
Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 79692.61
e) Contractor's profit @ 10% on (a+b+c+d) 87661.87
Cost for 30000 sqm = a+b+c+d+e 964280.52
Rate per sqm = (a+b+c+d+e)/20000 48.21 31.00
say 48.00 54.84
5.15 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 356.65 71.33 L-12
Mazdoor day 5.000 244.56 1222.80 L-13
b) Machinery
Mechanical broom hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Mobile slurry seal equipment hour 6.000 2072.00 12432.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 850.00 5100.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 40572.00 514047.24 M-080

Fine aggregate 2.36 mm and below,82 per cent of cum 43.300 698.00 30223.40 M-022
total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density
1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 5900.00 9322.00 M-188
Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 58651.68
e) Contractor's profit @ 10% on (a+b+c+d) 64516.84
Cost for 24000 sqm = a+b+c+d+e 709685.29
Rate per sqm = (a+b+c+d+e)/24000 29.57 19.00
say 30.00 57.89
1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately
5.16 Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the cent
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour

Page 71 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.480 356.65 171.19 L-12
Mazdoor day 10.000 244.56 2445.60 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 685.00 4110.00 P&M-069
Mechanical broom @ 1250 sqm per hour hour 1.280 337.00 431.36 P&M-031
Air compressor 250 cfm hour 1.280 435.00 556.80 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 954.00 868.14 P&M-004
Hot mix plant 100-120 TPH producing an average of hour 3.000 22823.00 68469.00 P&M-021
75 tonnes per hour
Electric generator set 250 KVA hour 3.000 1500.00 4500.00 P&M-081
Front end loader 1.00 cum bucket capacity hour 3.000 1341.00 4023.00 P&M-017
Tipper 5.5 cum capacity hour 18.000 850.00 15300.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 924.00 1801.80 P&M-044
Vibratory roller 8 tonnes hour 3.00x0.65* 1687.00 3289.65 P&M-059
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 1039.00 2026.05 P&M-045
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 tonne 1.987 32627.00 64836.37 M-077
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 tonne 7.728 32627.00 252141.46 M-077
x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent

Weight of fresh mix = 276 x 0.70 = 193.2 tonne


Weight of fresh aggregate in the mix = 193.2 x 0.96 =
185.47 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440 1619.00 46044.36 M-049
25 - 10 mm @ 15 per cent cum 18.550 1827.00 33890.85 M-046
10- 5 mm @ 20 per cent cum 24.730 1510.00 37342.30 M-040
Below 5 mm @40 per cent cum 49.460 1104.00 54603.84 M-030
Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne 5.520 7200.00 39744.00 M-084
tonne
d) Overhead charges @ 10% on (a+b+c) 63730.91
e) Contractor's profit @ 10% on (a+b+c+d) 70104.00
Cost for 120 cum of DBM = a+b+c+d+e 771143.98
Rate per cum = (a+b+c+d+e)/120 6426.20 1285.00
say 6426.00 400.08

Page 72 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Although the total rolling time is only 4 hours as per norms,
all the three rollers have to be available at site for 3 hours
each to match with the output of re-cycling plant. To cater for
their idling time, these have been multiplied with a factor of
0.6
5.17 Fog Spray

Providing and applying low viscosity bitumen emulsion for


sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
(Without binding)
(I)With Bitumen emulsion CSS-1 (IS:8887-2004)
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Bitumen emulsion pressure distributor @ 1750 sqm tonne 6.000 954.00 5724.00 P&M-004
per hour
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 36950.00 291166.00 M-074
d) Overhead charges @ 10% on (a+b+c) 30229.85
e) Contractor's profit @ 10% on (a+b+c+d) 33252.83
Cost for 10500 sqm = a+b+c+d+e 365781.16
Rate per sqm = (a+b+c+d+e)/10500 34.84 37.00
say 35.00 (5.41)
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor for precoating of grit day 4.000 244.56 978.24 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 1041.50 27339.38 M-024
Bitumen emulsion for precoating grit @ 2 per cent of tonne 0.790 36950.00 29190.50 M-074
grit,39.38 x 0.02
57565.18
5.48 6.00
say 5.00 (16.67)
(II) With bitumen emulsion-CSS-1h
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 1440.50 8643.00 P&M-031

Page 73 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air compressor 250 cfm hour 6.000 1055.00 6330.00 P&M-001
Bitumen emulsion pressure distributor @ 1750 sqm tonne 6.000 950.00 5700.00 P&M-004
per hour
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 38530.00 303616.40 M-073
d) Overhead charges @ 10% on (a+b+c) 32506.59
e) Contractor's profit @ 10% on (a+b+c+d) 35757.25
Cost for 10500 sqm = a+b+c+d+e 393329.71
Rate per sqm = (a+b+c+d+e)/10500 37.46 37.00
say 37.00 0.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor for precoating of grit day 4.000 244.56 978.24 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 1041.50 27339.38 M-024
Bitumen emulsion for precoating grit @ 2 per cent of tonne 0.790 38530.00 30438.70 M-073
grit,39.38 x 0.02
58813.38
5.60 6.00
say 6.00 0.00

5.18 Bituminous Cold Mix ( Including Gravel Emulsion)


Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and
Unit = cum
Taking output = 205 cum (450 tonne)
Using bitumen emulsion CSS-1 (IS:8887-2004) and
9.5 mm or 13.2
Composition mm (450
of mix sizetonne)
aggregate
is assumed to be as
under:-
Bitumen Emulsion 8 per cent By weight of
total mix
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor day 16.000 244.56 3912.96 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Drum mix plant for cold mixes of appropriate capacity hour 6.000 1859.00 11154.00 P&M-077
but not less than 75 tonnes/hour.

Page 74 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Paver finisher hour 6.000 1341.00 8046.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1137.00 4434.30 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1039.00 4052.10 P&M-045
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 36950.00 1330200.00 M-074
Filler (lime)@ 2 per cent tonne 9.000 5900.00 53100.00 M-188
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000 1777.00 133275.00 M-045
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 1510.00 131370.00 M-040
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 1104.00 119232.00 M-030
d) Overhead charges @ 10% on (a+b+c) 183866.82
e) Contractor's profit @ 10% on (a+b+c+d) 202253.50
Cost for 205 cum = a+b+c+d+e 2224788.52
Rate per cum = (a+b+c+d+e)/205 10852.63 10482.00
say 10853.00 3.54
(Applicable to cases I to IV)

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, thei
5.18 Using bitumen emulsion CSS-1 (IS:8887-2004) and
19 mm or 26.5 mm nominal size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor day 16.000 244.56 3912.96 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 1859.00 11154.00 P&M-077
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017

Page 75 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Paver finisher hour 6.000 2341.00 14046.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1137.00 4434.30 P&M-037
Smooth wheeled steel tandom roller 6-8 tonnes hour 6.00x0.65* 1039.00 4052.10 P&M-045
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 36950.00 1330200.00 M-074
Filler (lime)@ 2 per cent tonne 9.000 5900.00 53100.00 M-188
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 1619.00 121425.00 M-048
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 1104.00 99360.00 M-047
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 cum 105.000 1104.00 115920.00 M-030
d) Overhead charges @ 10% on (a+b+c) 179749.62
e) Contractor's profit @ 10% on (a+b+c+d) 197724.58
Cost for 205 cum = a+b+c+d+e 2174970.40
Rate per cum = (a+b+c+d+e)/205 10609.61 10327.00
say 10610.00 2.74
1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, thei
5.18 Using bitumen CSS-1h and 9.5 mm or 13.2 mm
nominal size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Cutback bitumen 5 per cent
Filler (lime) 2 per cent
Total aggregates 93 per cent
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor skilled day 16.000
5.000 244.56
356.65 3912.96
1783.25 L-13
L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 1859.00 11154.00 P&M-077
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Paver finisher hour 6.000 2341.00 14046.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1137.00 4434.30 P&M-037

Page 76 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1039.00 4052.10 P&M-045
c) Material
bitumen CSS-1h@ 5 per cent tonne 22.500 38530.00 866925.00 M-073
Filler (lime)@ 2 per cent tonne 9.000 5900.00 53100.00 M-188
Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5 cum 78.000 1777.00 138606.00 M-045
Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 cum 93.000 1510.00 140430.00 M-040
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 1104.00 119232.00 M-030
d) Overhead charges @ 10% on (a+b+c) 139578.42
e) Contractor's profit @ 10% on (a+b+c+d) 153536.26
Cost for 205 cum = a+b+c+d+e 1688898.88
Rate per cum = (a+b+c+d+e)/205 8238.53 6071.00
say 8239.00 35.71
1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, thei

5.18 Using bitumen CSS-1h and 19 mm or 26.5 mm


nominal size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor day 16.000 244.56 3912.96 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 1859.00 11154.00 P&M-077
producing output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Paver finisher hour 6.000 2341.00 14046.00 P&M-034
Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1137.00 4434.30 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1039.00 4052.10 P&M-045
c) Material
bitumen CSS-1h on @ 5 per cent tonne 22.500 38530.00 866925.00 M-073

Page 77 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Filler (lime)@ 2 per cent tonne 9.000 5900.00 53100.00 M-188
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 1619.00 121425.00 M-048
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 1104.00 99360.00 M-047
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5 cum 114.000 1104.00 125856.00 M-030
d) Overhead charges @ 10% on (a+b+c) 134415.72
e) Contractor's profit @ 10% on (a+b+c+d) 147857.29
Cost for 205 cum = a+b+c+d+e 1626430.21
Rate per cum = (a+b+c+d+e)/205 7933.81 5919.00
say 7934.00 34.04
1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, thei
5.19 Sand Asphalt Base Course
Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a
prepared sub-grade or sub-base to the lines, levels, grades
and cross sections as per the drawings including mixing in a
plant of suitable t
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate day 0.840 356.65 299.59 L-12
Mazdoor day 16.000 244.56 3912.96 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Hot Mix Plant of appropriate capacity but not less than hour 6.000 16575.00 99450.00 P&M-023
75 tonnes/hour
Electric generator set 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Paver finisher hour 6.000 2341.00 14046.00 P&M-034
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65 924.00 3603.60 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65 1687.00 6579.30 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandom hour 6.00x0.65 1039.00 4052.10 P&M-045
rollers.
c) Material
Composition of mix (450 tonne) is assumed to be
as under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent

Page 78 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 32627.00 734107.50 M-077
Filler (lime)@ 2 per cent tonne 9.000 5900.00 53100.00 M-188
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 950.00 274189.00 M-004
d) Overhead charges @ 10% on (a+b+c) 122949.43
e) Contractor's profit @ 10% on (a+b+c+d) 135244.37
Cost for 205 cum = a+b+c+d+e 1487688.10
Rate per cum = (a+b+c+d+e)/205 7257.02 5225.00
say 7257.00 38.89
1. Tack coat will be measured and paid separately
2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site
for six hours as the hot mix plant and paver will take six
hours for mixing and paving the output of 450 tonnes
considered in this anal
5.20 Modified Binder
Supply of modified binder produced by mixing bitumen with
modifier such as natural rubber or crumb rubber or any other
polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of
modifier with bitumen
Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower
Detailed information and inductive dose level on the use of
polymer modified binder is available in IRC : SP-53 / 2002. A
number of proprietary products are now available in the
market. For such proprietary products, test reports and cost
effectiveness sh
The modifier, in the required quantity shall be blended at the
refinery or at central unit with all facilities by proper industrial
process, is essential. If supplied in drums it shall be agitated
in melted condition with suitable device for achieving hom

Proposals to use glass fibre, polypropylene fibres or any


other similar material in a bituminous mixture should be
substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of
incorporating the f
Before agreeing to the use of a fibre, it should have been
proved to be satisfactory in use under circumstances, similar
to the work, elsewhere or it would have under gone
appropriate performance trials. Documented evidence of
use and trials of the fibre,
where information on use of trials is inadequate or lacking,
trials may be required to be under taken before agreeing to
the use of the fibre.
1. The modified binder is usually manufactured by `
specialised firms as a proprietary product. The rate for this
product is required to be as certained from the market.

Page 79 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
2.The specifications for various item of road works using
polymer/rubber modified bitumens are same as those for
3.The other controls
penetration during mixing,
grade bitumen except laying
thoseshall be same
for any as
special
specified
conditionsinwhich
IRC -the
14,manufacturer
29, 94 and 95may
for indicate
open graded premix
carpet, bituminous concrete, DBM and SDBC respectively

4.The temperature of mixing and rolling will be slightly higher


than conventional bituminous mixes as indicated in Table 8
of IRC: SP: 53 - 2002
5.21 Crack Prevention Courses
Stress absorbing membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Hydraulic Chip spreader hour 6.000 2380.00 14280.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Modified binder PMB tonne 9.450 33280.00 314496.00 M-081
Crushed stone aggregates 5.6 mm size cum 105.000 1807.00 189735.00 M-050
d) Overhead charges @ 10% on (a+b+c) 53596.40
e) Contractor's profit @ 10% on (a+b+c+d) 58956.04
Cost for 10500 sqm = a+b+c+d+e 648516.39
Rate per sqm = (a+b+c+d+e)/10500 61.76 49.00
say 62.00 26.53
5.21 Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031

Page 80 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air compressor 250 cfm capacity hour 6.000 435.00 2610.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Hydraulic Chip spreader hour 6.000 2380.00 14280.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Modified binder tonne 11.550 33280.00 384384.00 M-081
Crushed stone chipping 11.2 mm size cum 105.000 1916.00 201180.00 M-051
d) Overhead charges @ 10% on (a+b+c) 61729.70
e) Contractor's profit @ 10% on (a+b+c+d) 67902.67
Cost for 10500 sqm = a+b+c+d+e 746929.32
Rate per sqm = (a+b+c+d+e)/10500 71.14 56.00
say 71.00 26.79
5.21 Stress absorbing membrane (SAM) crack width above
9 mm and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, spraye
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 6.000 356.65 2139.90 L-13
Mazdoor skilled day 2.000 244.56 489.12 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 337.00 2022.00 P&M-031
Air compressor 250 cfm capacity hour 6.000 435.00 2610.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 954.00 5724.00 P&M-004
Hydraulic Chip spreader hour 6.000 2380.00 14280.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 924.00 5544.00 P&M-044
c) Material
Modified binder tonne 15.750 33280.00 524160.00 M-081
Crushed stone aggregates 11.2 mm size cum 126.000 1916.00 241416.00 M-051
d) Overhead charges @ 10% on (a+b+c) 79847.06
e) Contractor's profit @ 10% on (a+b+c+d) 87831.77
Cost for 10500 sqm = a+b+c+d+e 966149.45
Rate per sqm = (a+b+c+d+e)/10500 92.01 73.00
say 92.00 26.03
In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per table 500-47.
5.21 Case - IV : Bitumen impregnated geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to
Unit = sqm

Page 81 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 3500 sqm
a) Labour
Mate day 0.560 356.65 199.72 L-12
Mazdoor day 12.000 244.56 2934.72 L-13
Mazdoor skilled day 2.000 356.65 713.30 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Air compressor 250 cfm capacity hour 2.800 435.00 1218.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 954.00 1908.00 P&M-004
Pneumatic roller hour 2.000 1137.00 2274.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 31681.00 116586.08 M-078
kg per sqm
Geotextile including 10 per cent for overlaps sqm 3850.000 116.00 446600.00 M-108
d) Overhead charges @ 10% on (a+b+c) 57337.74
e) Contractor's profit @ 10% on (a+b+c+d) 63071.52
Cost for 10500 sqm = a+b+c+d+e 693786.68
Rate per sqm = (a+b+c+d+e)/3500 198.22 1285.00
say 198.00 (84.59)
As bitumen overlay construction shall follow closely the
fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will cover a
length of 500 m, of 7 m wide carriagway. This can be
conveniently overlaid by a b
5.22 Recipe Cold Mix
Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing
plant, laid over prepared surface, by paver finisher, rolled
with a pneumatic tyred roller initially and finished with a
smooth steel wheel r
Unit = cum
Taking output = 205 cum (450 tonnes)
75 mm thickness
a) Labour
Mate day 1.000 356.65 356.65 L-12
Mazdoor day 12.000 244.56 2934.72 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 2000.00 12000.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum capacity hour 6.000 1341.00 8046.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Pneumatic tyred roller12-15 tonnes. hour 6.00x0.65* 1137.00 4434.30 P&M-037
Smooth wheeled steel roller6-8 tonnes. hour 6.00x0.65* 924.00 3603.60 P&M-044

Page 82 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Water tanker6 KL capacity hour 1.000 440.00 440.00 P&M-060
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 40572.00 821583.00 M-080
Crushed stone aggregates 40 mm nominal size cum 297.000 1500.00 445500.00 M-055
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 134476.05
e) Contractor's profit @ 10% on (a+b+c+d) 147923.66
Cost for 10500 sqm = a+b+c+d+e 1627160.23
Rate per sqm = (a+b+c+d+e)/205 7937.37 1285.00
say 7937.00 517.67
(Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*4.Both the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.
5.22 40 mm thickness
a) Labour
Mate day 1.000 356.65 356.65 L-12
Mazdoor day 12.000 244.56 2934.72 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Batch type cold mixing plant100-120 TPH capacity hour 6.000 2000.00 12000.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum capacity hour 6.000 1341.00 8046.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1137.00 4434.30 P&M-037
Smooth wheeled steel roller 6-8 tonnes. hour 6.00x0.65* 924.00 3603.60 P&M-044
Water tanker6 KL capacity hour 1.000 440.00 440.00 P&M-060
c) Material
Bitumen emulsion @ 70 litres per tonne tonne 31.500 40572.00 1278018.00 M-080
Crushed stone aggregates 14 mm nominal size cum 287.000 1510.00 433370.00 M-052
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 178906.55
e) Contractor's profit @ 10% on (a+b+c+d) 196797.21
Cost for 10500 sqm = a+b+c+d+e 2164769.28
Rate per sqm = (a+b+c+d+e)/205 10559.85 1285.00
say 10560.00 721.79

Page 83 of 959
Analysisof SOR (Roads) 2017-18
Chapter-5

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
5.22 25 mm thickness
a) Labour
Mate day 1.000 356.65 356.65 L-12
Mazdoor day 12.000 244.56 2934.72 L-13
Mazdoor skilled day 5.000 356.65 1783.25 L-15
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 2000.00 12000.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 2073.00 12438.00 P&M-018
Front end loader 1 cum capacity hour 6.000 1341.00 8046.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2341.00 14046.00 P&M-034
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 3.50 15750.00 #REF!
Add 10 per cent of cost of carriage to cover cost of loading 1575.00
and unloading
Pneumatic tyred roller hour 6.00x0.65* 1137.00 4434.30 P&M-037
Smooth wheeled steel roller hour 6.00x0.65* 924.00 3603.60 P&M-044
Water tanker6 KL capacity hour 1.000 440.00 440.00 P&M-060
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 40572.00 1551879.00 M-080
Crushed stone aggregates 6 mm nominal size cum 270.000 1807.00 487890.00 M-050
Cost of water KL 6.000 45.00 270.00 M-189
d) Overhead charges @ 10% on (a+b+c) 211744.65
e) Contractor's profit @ 10% on (a+b+c+d) 232919.12
Cost for 10500 sqm = a+b+c+d+e 2562110.29
Rate per sqm = (a+b+c+d+e)/205 12498.10 1285.00
say 12498.00 872.61

Page 84 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over
a prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blend

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.12 356.65 399.45
Mazdoor skilled day 6.00 356.65 2139.90
Mazdoor day 22.00 244.56 5380.32
b) Machinery
Front end loader 1 cum bucket capacity hour 6.00 1341.00 8046.00
Cement concrete batch mix plant @ 75 cum per hour 6.00 4000.00 24000.00
hour
Electric generator 100 KVA hour 6.00 621.00 3726.00
Paver with electronic sensor hour 6.00 2341.00 14046.00
Vibratory roller 8-10 t capacity hour 8.00 1687.00 13496.00
Water tanker6 KL capacity hour 8.00 440.00 3520.00
Tipper tonne.km 990 x L 3.50 34650.00
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and cum 405.00 1669.00 675945.00
12.5 mm nominal sizes graded as per table 600-1
@ 0.90 cum/cum of concrete conforming to clause
602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 203.00 950.00 192850.00
concrete
Cement @ 150 kg/cum of concrete tonne 67.50 7200.00 486000.00
Cost of water KL 48.00 45.00 2160.00
d) Overhead charges @ 10% on (a+b+c) 146982.37
e) Contractor's profit @ 10% on (a+b+c+d) 161680.60
Cost for 205 cum = a+b+c+d+e 1778486.64
Rate per cum = (a+b+c+d+e)/450 3952.19
say 3952.00
Note: Quantity provided for aggregate is for estimating
purpose. Exact quantity shall be as per mix design.
6.2A 602 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43
grade cement @ 400 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a b -----------

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 356.65 713.30

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mazdoor skilled day 15.00 356.65 5349.75
Mazdoor day 35.00 244.56 8559.60
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 337.00 943.60
Front end loader 1 cum bucket capacity hour 18.00 1341.00 24138.00
Cement concrete batch mix plant @ 175 cum per hour 6.00 5229.00 31374.00
hour (effective output)
Electric generator 250 KVA hour 6.00 1500.00 9000.00
Slip form paver with electronic sensor hour 6.00 2495.00 14970.00
Water tanker6 KL capacity hour 36.00 440.00 15840.00
Transit truck agitator 5 cum capacity. tonne.km 2415xL 3.50 84525.00
Add 10 per cent of cost of carriage to cover cost of 8452.50
loading and unloading
Concrete joint cutting machine . hour 12.00 150.00 1800.00
Texturing machine . hour 12.00 800.00 9600.00
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.00 1669.00 1577205.00
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause cum 473.00 950.00 449350.00
602.2.4 @ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.00 7200.00 2980800.00
32 mm mild steel dowel bars of grade S 240 tonne 9.45 53667.00 507153.15
16 mm deformed steel tie bars of grade S 415 tonne 1.17 55637.00 65095.29
Separation Membrane of impermeable plastic sqm 3675.00 40.00 147000.00
sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.33 742.00 12116.86
joint.
Joint sealant kg 875.00 590.00 516250.00
Sealant primer kg 116.67 395.00 46084.65
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 25.00 1166.75
Curing compound liter 1850.00 214.00 395900.00
Super plastisizer admixture IS marked as per 9103- kg 2070.00 104.00 215280.00
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.00 45.00 9720.00
Add 1 per cent of material for cost of miscellaneous 69231.22
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel bars,
work bridges for men to approach concrete surface
without walking over it, cutting blades an
d) Overhead charges @ 10% on (a+b+c) 720761.87
e) Contractor's profit @ 10% on (a+b+c+d) 792838.05
Cost for 1050cum = a+b+c+d+e 8721218.59
Rate per cum = (a+b+c+d+e)/1050 8305.92
say 8306.00

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
B Cement Concrete Pavement (Construction of un-reinforced,
dowel jointed, plain cement concrete pavement over a prepared
sub base with 43 grade cement @ 400 kg per cum, coarse and
fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed with Recron 3S fibre of
Reliance Industries Ltd. or its equivalent @ 0.125 Kg. per bag
of cement mixed in a batching and mixing plant as per approved
mixed design, transported to the site, laid with a fixed form or
slip form paver, spread , compacted and finished in a
continuous operation includuing provision of contraction,
expansion, construction and longitudinal joints, joint filler,
seperation membrane, sealent primer, sealent joint , debonding
strips dowel bar, tie rod, admixured as approved, curing
compopund, finishing to lines and grades as per drawing.
(Including carriage up to initial lead of 5Km. from quarry and
carriage of mixed materials up to 10.0 Km initial lead from
mixing plant.) as diected by the Department complete at all
levels.

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 356.65 713.30
Mazdoor skilled day 15.00 356.65 5349.75
Mazdoor day 35.00 244.56 8559.60
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 337.00 943.60
Front end loader 1 cum bucket capacity hour 18.00 1341.00 24138.00
Cement concrete batch mix plant @ 175 cum per hour 6.00 5229.00 31374.00
hour (effective output)
Electric generator 250 KVA hour 6.00 1500.00 9000.00
Slip form paver with electronic sensor hour 6.00 2495.00 14970.00
Water tanker6 KL capacity hour 36.00 440.00 15840.00
Transit truck agitator 5 cum capacity. tonne.km 2415xL 3.50 84525.00
Add 10 per cent of cost of carriage to cover cost of 8452.50
loading and unloading
Concrete joint cutting machine . hour 12.00 150.00 1800.00
Texturing machine . hour 12.00 800.00 9600.00
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.00 1669.00 1577205.00
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause cum 473.00 950.00 449350.00
602.2.4 @ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.00 7200.00 2980800.00
32 mm mild steel dowel bars of grade S 240 tonne 9.45 53667.00 507153.15
16 mm deformed steel tie bars of grade S 415 tonne 1.17 55637.00 65095.29

Separation Membrane of impermeable plastic sqm 3675.00 40.00 147000.00


sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.33 742.00 12116.86
joint.

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Joint sealant kg 875.00 590.00 516250.00
Sealant primer kg 116.67 395.00 46084.65
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 25.00 1166.75
Curing compound liter 1850.00 214.00 395900.00
Super plastisizer admixture IS marked as per 9103- kg 2070.00 104.00 215280.00
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.00 45.00 9720.00
Recron 3S CT 2024 @ 0.125 kg per bag of cement Kg. 1035.00 240.00 248400.00
of Reliance Industries or its equivalent.
Add 1 per cent of material for cost of miscellaneous 71715.22
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel bars,
work bridges for men to approach concrete surface
without walking over it, cutting blades an
d) Overhead charges @ 10% on (a+b+c) 745850.27
e) Contractor's profit @ 10% on (a+b+c+d) 820435.29
Cost for 1050cum = a+b+c+d+e 9024788.23
Rate per cum = (a+b+c+d+e)/1050 8595.04
say 8595.00
Note: The quantities for cement, coarse aggregate and
fine aggregates are for estimating only .The exact
quantities will be as per mix design.
6.3 603 Rolled Cement Concrete Base
A Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size
of coarse aggregate not exceeding 25 mm with minimum,
aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 356.65 427.98
Mazdoor skilled day 7.000 356.65 2496.55
Mazdoor day 23.000 244.56 5624.88
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00
Cement concrete batch mix plant @ 75 cum per hour 6.000 4000.00 24000.00
hour
Electric generator 100 KVA hour 6.000 621.00 3726.00
Paver with electronic sensor @ 75 cum/hr. hour 6.000 2341.00 14046.00
Vibratory roller 8-10 t capacity hour 8.000 1687.00 13496.00
Water tanker with 5 km lead 6 KL capacity hour 8.000 440.00 3520.00
Tipper tonne.km 990xL 3.50 34650.00
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Crushed stone coarse aggregates of 25mm and cum 405.000 1669.00 675945.00
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause cum 203.000 950.00 192850.00
602.2.3 @ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete tonne 90.000 7200.00 648000.00
Cost of water KL 48.000 45.00 2160.00
d) Overhead charges @ 10% on (a+b+c) 163245.34
e) Contractor's profit @ 10% on (a+b+c+d) 179569.88
Cost for 450cum = a+b+c+d+e 1975268.63
Rate per cum = (a+b+c+d+e)/450 4389.49
say 4389.00
Note: The quantities for cement, coarse aggregate and
fine aggregates are for estimating only .The exact
quantities will be as per mix design.
6.3 'Rolled Cement Concrete Base( using Recron 3s )

B Construction of rolled cement concrete base course with coarse


and fine aggregate conforming to IS:383, the size of coarse
aggregate not exceeding 25 mm with minimum, aggregate
cement ratio15:1 and minimum cement content of 200 Kgs/cum,
aggregate gradation as per table 600-4 after blending,mixed
with Recron 3S fibre of Reliance Industries Ltd. or its equivalent
@ 0.125 Kg. per bag of cement mixing in a batching plant at
optimum moisture content, transporting to site, laying with a
paver with electronic sensor, compacting with 8-10 tonnes
smooth wheeled vibratory roller to achive the designed flexure
strength, finishing and curing as diected by the Department
complete at all levels.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 356.65 427.98
Mazdoor skilled day 7.000 356.65 2496.55
Mazdoor day 23.000 244.56 5624.88
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00
Cement concrete batch mix plant @ 75 cum per hour 6.000 4000.00 24000.00
hour
Electric generator 100 KVA hour 6.000 621.00 3726.00
Paver with electronic sensor @ 75 cum/hr. hour 6.000 2341.00 14046.00
Vibratory roller 8-10 t capacity hour 8.000 1687.00 13496.00
Water tanker with 5 km lead 6 KL capacity hour 8.000 440.00 3520.00
Tipper tonne.km 990xL 3.50 34650.00
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Crushed stone coarse aggregates of 25mm and cum 405.000 1669.00 675945.00
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause cum 203.000 950.00 192850.00
602.2.3 @ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete tonne 90.000 7200.00 648000.00
Cost of water KL 48.000 45.00 2160.00
Recron 3S CT 2024 @ 0.125 kg per bag of cement Kg. 120.00 240.00 28800.00
of Reliance Industries or its equivalent.
d) Overhead charges @ 10% on (a+b+c) 166125.34
e) Contractor's profit @ 10% on (a+b+c+d) 182737.88
Cost for 450cum = a+b+c+d+e 2010116.63
Rate per cum = (a+b+c+d+e)/450 4466.93
say 4467.00
6.4 Suggest Construction of Base/Sub-Base of Pavement with
ive Lean Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly
ash and coarse aggregates proportioned as per table 4 of
IRC: 74/1979 and with water content ratio, slump and
compressive strength as defined in the said table, mix
prepared in a batching and mixing pl
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 356.65 399.45
Mazdoor skilled day 6.000 356.65 2139.90
Mazdoor day 22.000 244.56 5380.32
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00
Cement concrete batch mix plant @ 75 cum per hour 6.000 4000.00 24000.00
hour
Electric generator 100 KVA hour 6.000 621.00 3726.00
Paver finisher with electronic sensor hour 6.000 2341.00 14046.00
Vibratory roller 8-10 t capacity hour 8.000 1687.00 13496.00
Water tanker6 KL capacity hour 8.000 440.00 3520.00
Tipper 10 T Capacity tonne.km 990 x L 3.50 34650.00
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material
Crushed stone coarse aggregate of 40 mm nominal cum 405.000 1500.00 607500.00
size @ 0.90 cum/cum of concrete conforming to
table 2 of IRC: 74-1979.
Coarse Sand as per IS: 383 - 1970 cum 110.960 950.00 105412.00
Cement @ 150 kg/cum of concrete tonne 67.500 7200.00 486000.00
Fly ash conforming to IS: 3812 ( Part II ) cum 91.540 375.00 34327.50

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
( Total fine aggregates = 450 x 0.45 = 202.50 cum To be
divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of
IRC: 74-1979).
d) Overhead charges @ 10% on (a+b+c) 134610.82
e) Contractor's profit @ 10% on (a+b+c+d) 148071.90
Cost for 450cum = a+b+c+d+e 1628790.88
Rate per cum = (a+b+c+d+e)/450 3619.54
say 3620.00
Note:
1.Depending upon approved designs, crushed stone
aggregates of nominal size 20mm can also be used as
per gradation given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash and sand has
been assumed to be 0.827.
3.The quantities of materials given in the analyses are for
estimating purposes. Actual quantities shall be as per job
mix formula.
4.Construction procedure as laid down in clause, of IRC:
74-1979 shall be followed.
6.5 Suggest Cement - Flyash Concrete Pavement.
ive
Construction reinforced-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base
with 43 grade cement, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, replacing cement by fly

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 356.65 713.30
Mazdoor skilled day 15.000 356.65 5349.75
Mazdoor day 35.000 244.56 8559.60
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 337.00 943.60
Front end loader 1 cum bucket capacity hour 18.000 1341.00 24138.00
Cement concrete batch mix plant @ 175 cum per hour 6.000 5229.00 31374.00
hour (effective output)
Electric generator 250 KVA hour 6.000 1500.00 9000.00
Slip form paver with electronic sensor hour 6.000 2495.00 14970.00
Water tanker6 KL capacity hour 36.000 440.00 15840.00
Transit truck agitator 5 cum capacity. tonne.km 2415xL 40.00 966000.00
Add 10 per cent of cost of carriage to cover cost of 96600.00
loading and unloading
Concrete joint cutting machine . hour 12.000 150.00 1800.00
Texturing machine . hour 12.000 800.00 9600.00
c) Material

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Crushed stone coarse aggregates of 25mm and cum 945.000 1669.00 1577205.00
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause cum 425.000 950.00 403750.00
602.2.4
Cement 43 grade tonne 357.000 7200.00 2570400.00
Fly ash conforming to IS: 3812-1966 (Part-I) tonne 109.000 375.00 40875.00
32 mm mild steel dowel bars of grade S 240 tonne 9.450 53667.00 507153.15
16 mm deformed steel tie bars of grade S 415 tonne 1.170 55637.00 65095.29
Separation Membrane of impermeable plastic sqm 3675.000 40.00 147000.00
sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.330 742.00 12116.86
joint.
Joint sealant kg 875.000 590.00 516250.00
Sealant primer kg 116.670 395.00 46084.65
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 25.00 1166.75
Curing compound liter 1850.000 214.00 395900.00
Super plastisizer admixture IS marked as per 9103- kg 2070.000 104.00 215280.00
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.000 45.00 9720.00
Add 1 per cent of material for cost of miscellaneous 49307.92
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel bars,
work bridges for men to approach concrete surface
without walking over it, cutting blades an
d) Overhead charges @ 10% on (a+b+c) 774219.29
e) Contractor's profit @ 10% on (a+b+c+d) 851641.22
Cost for 1050cum = a+b+c+d+e 9368053.37
Rate per cum = (a+b+c+d+e)/1050 8921.96
say 8922.00
Note:
1.The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities
will be as per mix design.
2.IRC: 68-1976 may be referred for guidelines on the
design of cement-fly ash concrete for rigid pavement
construction.
*Calculation of cement, sand and fly ash.
Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes.
15 per cent of cement to be replaced by fly ash =
63 tonnes. Balance cement = 357 tonnes. Quantity
of fly ash = 63 x specific gravity of fly ash /specific
gravity of cement = 63 x 2.25/3.15 = 45 tonnes.

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sand @ 0.45 cum / cum of concrete = 1050 x 0.45
= 472.50 x 1.6 = 756 tonnes.10 per cent to be
replaced by flyash. Balance sand = 756 x 0.9 =
680.4 tonnes = 680.4 / 1.6 = 425 cum. Quantity of
flyash = (756-680.4) x specific gravity of fly
ash/specific gr
Fly ash Total fly ash = 45 + 64 = 109 tonnes.

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over
a prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blend

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.12 356.65 399.45 L-12
Mazdoor skilled day 6.00 356.65 2139.90 L-15
Mazdoor day 22.00 244.56 5380.32 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.00 1341.00 8046.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour 6.00 4000.00 24000.00 P&M-068
hour
Electric generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Paver with electronic sensor hour 6.00 2341.00 14046.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.00 1687.00 13496.00 P&M-059
Water tanker6 KL capacity hour 8.00 440.00 3520.00 P&M-060
Tipper tonne.km 990 x L 3.50 34650.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and cum 405.00 1669.00 675945.00 M-052 and
12.5 mm nominal sizes graded as per table 600-1 M-054
@ 0.90 cum/cum of concrete conforming to clause
602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 203.00 950.00 192850.00 M-004
concrete
Cement @ 150 kg/cum of concrete tonne 67.50 7200.00 486000.00 M-084
Cost of water KL 48.00 45.00 2160.00 M-189
d) Overhead charges @ 10% on (a+b+c) 146982.37
e) Contractor's profit @ 10% on (a+b+c+d) 161680.60
Cost for 205 cum = a+b+c+d+e 1778486.64
Rate per cum = (a+b+c+d+e)/450 3952.19 2375.00
say 3952.00 66.40
Note: Quantity provided for aggregate is for estimating
purpose. Exact quantity shall be as per mix design.
6.2A 602 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43
grade cement @ 400 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a b -----------

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 356.65 713.30 L-12

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor skilled day 15.00 356.65 5349.75 L-15
Mazdoor day 35.00 244.56 8559.60 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 337.00 943.60 P&M-031
Front end loader 1 cum bucket capacity hour 18.00 1341.00 24138.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour 6.00 5229.00 31374.00 P&M-067
hour (effective output)
Electric generator 250 KVA hour 6.00 1500.00 9000.00 P&M-081
Slip form paver with electronic sensor hour 6.00 2495.00 14970.00 P&M-006
Water tanker6 KL capacity hour 36.00 440.00 15840.00 P&M-060
Transit truck agitator 5 cum capacity. tonne.km 2415xL 3.50 84525.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 8452.50
loading and unloading
Concrete joint cutting machine . hour 12.00 150.00 1800.00 P&M-083
Texturing machine . hour 12.00 800.00 9600.00 P&M-088
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.00 1669.00 1577205.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause cum 473.00 950.00 449350.00 M-004
602.2.4 @ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.00 7200.00 2980800.00 M-084
32 mm mild steel dowel bars of grade S 240 tonne 9.45 53667.00 507153.15 M-126
16 mm deformed steel tie bars of grade S 415 tonne 1.17 55637.00 65095.29 M-085
Separation Membrane of impermeable plastic sqm 3675.00 40.00 147000.00 M-164
sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.33 742.00 12116.86 M-141
joint.
Joint sealant kg 875.00 590.00 516250.00 M-120
Sealant primer kg 116.67 395.00 46084.65 M-098-3
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 25.00 1166.75 M-138
Curing compound liter 1850.00 214.00 395900.00 M-093
Super plastisizer admixture IS marked as per 9103- kg 2070.00 104.00 215280.00 M-180
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.00 45.00 9720.00 M-189
Add 1 per cent of material for cost of miscellaneous 69231.22
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel bars,
work bridges for men to approach concrete surface
without walking over it, cutting blades an
d) Overhead charges @ 10% on (a+b+c) 720761.87
e) Contractor's profit @ 10% on (a+b+c+d) 792838.05
Cost for 1050cum = a+b+c+d+e 8721218.59
Rate per cum = (a+b+c+d+e)/1050 8305.92 5422.00
say 8306.00 53.19

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
B Cement Concrete Pavement (Construction of un-reinforced,
dowel jointed, plain cement concrete pavement over a prepared
sub base with 43 grade cement @ 400 kg per cum, coarse and
fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed with Recron 3S fibre of
Reliance Industries Ltd. or its equivalent @ 0.125 Kg. per bag
of cement mixed in a batching and mixing plant as per approved
mixed design, transported to the site, laid with a fixed form or
slip form paver, spread , compacted and finished in a
continuous operation includuing provision of contraction,
expansion, construction and longitudinal joints, joint filler,
seperation membrane, sealent primer, sealent joint , debonding
strips dowel bar, tie rod, admixured as approved, curing
compopund, finishing to lines and grades as per drawing.
(Including carriage up to initial lead of 5Km. from quarry and
carriage of mixed materials up to 10.0 Km initial lead from
mixing plant.) as diected by the Department complete at all
levels.

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.00 356.65 713.30 L-12
Mazdoor skilled day 15.00 356.65 5349.75 L-15
Mazdoor day 35.00 244.56 8559.60 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.80 337.00 943.60 P&M-031
Front end loader 1 cum bucket capacity hour 18.00 1341.00 24138.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour 6.00 5229.00 31374.00 P&M-067
hour (effective output)
Electric generator 250 KVA hour 6.00 1500.00 9000.00 P&M-081
Slip form paver with electronic sensor hour 6.00 2495.00 14970.00 P&M-006
Water tanker6 KL capacity hour 36.00 440.00 15840.00 P&M-060
Transit truck agitator 5 cum capacity. tonne.km 2415xL 3.50 84525.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 8452.50
loading and unloading
Concrete joint cutting machine . hour 12.00 150.00 1800.00 P&M-083
Texturing machine . hour 12.00 800.00 9600.00 P&M-088
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.00 1669.00 1577205.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause cum 473.00 950.00 449350.00 M-004
602.2.4 @ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.00 7200.00 2980800.00 M-084
32 mm mild steel dowel bars of grade S 240 tonne 9.45 53667.00 507153.15 M-126
16 mm deformed steel tie bars of grade S 415 tonne 1.17 55637.00 65095.29 M-085

Separation Membrane of impermeable plastic sqm 3675.00 40.00 147000.00 M-164


sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.33 742.00 12116.86 M-141
joint.

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Joint sealant kg 875.00 590.00 516250.00 M-120
Sealant primer kg 116.67 395.00 46084.65 M-098-3
Plastic sheath,1.25 mm thick for dowel bars sqm 46.67 25.00 1166.75 M-138
Curing compound liter 1850.00 214.00 395900.00 M-093
Super plastisizer admixture IS marked as per 9103- kg 2070.00 104.00 215280.00 M-180
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.00 45.00 9720.00 M-189
Recron 3S CT 2024 @ 0.125 kg per bag of cement Kg. 1035.00 240.00 248400.00
of Reliance Industries or its equivalent.
Add 1 per cent of material for cost of miscellaneous 71715.22
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel bars,
work bridges for men to approach concrete surface
without walking over it, cutting blades an
d) Overhead charges @ 10% on (a+b+c) 745850.27
e) Contractor's profit @ 10% on (a+b+c+d) 820435.29
Cost for 1050cum = a+b+c+d+e 9024788.23
Rate per cum = (a+b+c+d+e)/1050 8595.04 5711.00
say 8595.00 50.50
Note: The quantities for cement, coarse aggregate and
fine aggregates are for estimating only .The exact
quantities will be as per mix design.
6.3 603 Rolled Cement Concrete Base
A Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size
of coarse aggregate not exceeding 25 mm with minimum,
aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 356.65 427.98 L-12
Mazdoor skilled day 7.000 356.65 2496.55 L-15
Mazdoor day 23.000 244.56 5624.88 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour 6.000 4000.00 24000.00 P&M-068
hour
Electric generator 100 KVA hour 6.000 621.00 3726.00 P&M-080
Paver with electronic sensor @ 75 cum/hr. hour 6.000 2341.00 14046.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1687.00 13496.00 P&M-059
Water tanker with 5 km lead 6 KL capacity hour 8.000 440.00 3520.00 P&M-060
Tipper tonne.km 990xL 3.50 34650.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Crushed stone coarse aggregates of 25mm and cum 405.000 1669.00 675945.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause cum 203.000 950.00 192850.00 M-004
602.2.3 @ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete tonne 90.000 7200.00 648000.00 M-084
Cost of water KL 48.000 45.00 2160.00 M-189
d) Overhead charges @ 10% on (a+b+c) 163245.34
e) Contractor's profit @ 10% on (a+b+c+d) 179569.88
Cost for 450cum = a+b+c+d+e 1975268.63
Rate per cum = (a+b+c+d+e)/450 4389.49 2691.00
say 4389.00 63.10
Note: The quantities for cement, coarse aggregate and
fine aggregates are for estimating only .The exact
quantities will be as per mix design.
6.3 'Rolled Cement Concrete Base( using Recron 3s )

B Construction of rolled cement concrete base course with coarse


and fine aggregate conforming to IS:383, the size of coarse
aggregate not exceeding 25 mm with minimum, aggregate
cement ratio15:1 and minimum cement content of 200 Kgs/cum,
aggregate gradation as per table 600-4 after blending,mixed
with Recron 3S fibre of Reliance Industries Ltd. or its equivalent
@ 0.125 Kg. per bag of cement mixing in a batching plant at
optimum moisture content, transporting to site, laying with a
paver with electronic sensor, compacting with 8-10 tonnes
smooth wheeled vibratory roller to achive the designed flexure
strength, finishing and curing as diected by the Department
complete at all levels.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 356.65 427.98 L-12
Mazdoor skilled day 7.000 356.65 2496.55 L-15
Mazdoor day 23.000 244.56 5624.88 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour 6.000 4000.00 24000.00 P&M-068
hour
Electric generator 100 KVA hour 6.000 621.00 3726.00 P&M-080
Paver with electronic sensor @ 75 cum/hr. hour 6.000 2341.00 14046.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1687.00 13496.00 P&M-059
Water tanker with 5 km lead 6 KL capacity hour 8.000 440.00 3520.00 P&M-060
Tipper tonne.km 990xL 3.50 34650.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Crushed stone coarse aggregates of 25mm and cum 405.000 1669.00 675945.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause cum 203.000 950.00 192850.00 M-004
602.2.3 @ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete tonne 90.000 7200.00 648000.00 M-084
Cost of water KL 48.000 45.00 2160.00 M-189
Recron 3S CT 2024 @ 0.125 kg per bag of cement Kg. 120.00 240.00 28800.00
of Reliance Industries or its equivalent.
d) Overhead charges @ 10% on (a+b+c) 166125.34
e) Contractor's profit @ 10% on (a+b+c+d) 182737.88
Cost for 450cum = a+b+c+d+e 2010116.63
Rate per cum = (a+b+c+d+e)/450 4466.93 2768.00
say 4467.00 61.38
6.4 Suggest Construction of Base/Sub-Base of Pavement with
ive Lean Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly
ash and coarse aggregates proportioned as per table 4 of
IRC: 74/1979 and with water content ratio, slump and
compressive strength as defined in the said table, mix
prepared in a batching and mixing pl
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 356.65 399.45 L-12
Mazdoor skilled day 6.000 356.65 2139.90 L-15
Mazdoor day 22.000 244.56 5380.32 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1341.00 8046.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour 6.000 4000.00 24000.00 P&M-068
hour
Electric generator 100 KVA hour 6.000 621.00 3726.00 P&M-080
Paver finisher with electronic sensor hour 6.000 2341.00 14046.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1687.00 13496.00 P&M-059
Water tanker6 KL capacity hour 8.000 440.00 3520.00 P&M-060
Tipper 10 T Capacity tonne.km 990 x L 3.50 34650.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 3465.00
loading and unloading
c) Material
Crushed stone coarse aggregate of 40 mm nominal cum 405.000 1500.00 607500.00 M-055
size @ 0.90 cum/cum of concrete conforming to
table 2 of IRC: 74-1979.
Coarse Sand as per IS: 383 - 1970 cum 110.960 950.00 105412.00 M-004
Cement @ 150 kg/cum of concrete tonne 67.500 7200.00 486000.00 M-084
Fly ash conforming to IS: 3812 ( Part II ) cum 91.540 375.00 34327.50 M-011

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
( Total fine aggregates = 450 x 0.45 = 202.50 cum To be
divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of
IRC: 74-1979).
d) Overhead charges @ 10% on (a+b+c) 134610.82
e) Contractor's profit @ 10% on (a+b+c+d) 148071.90
Cost for 450cum = a+b+c+d+e 1628790.88
Rate per cum = (a+b+c+d+e)/450 3619.54 2041.00
say 3620.00 77.36
Note:
1.Depending upon approved designs, crushed stone
aggregates of nominal size 20mm can also be used as
per gradation given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash and sand has
been assumed to be 0.827.
3.The quantities of materials given in the analyses are for
estimating purposes. Actual quantities shall be as per job
mix formula.
4.Construction procedure as laid down in clause, of IRC:
74-1979 shall be followed.
6.5 Suggest Cement - Flyash Concrete Pavement.
ive
Construction reinforced-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base
with 43 grade cement, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, replacing cement by fly

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 356.65 713.30 L-12
Mazdoor skilled day 15.000 356.65 5349.75 L-15
Mazdoor day 35.000 244.56 8559.60 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 337.00 943.60 P&M-031
Front end loader 1 cum bucket capacity hour 18.000 1341.00 24138.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour 6.000 5229.00 31374.00 P&M-067
hour (effective output)
Electric generator 250 KVA hour 6.000 1500.00 9000.00 P&M-081
Slip form paver with electronic sensor hour 6.000 2495.00 14970.00 P&M-006
Water tanker6 KL capacity hour 36.000 440.00 15840.00 P&M-060
Transit truck agitator 5 cum capacity. tonne.km 2415xL 40.00 966000.00 #REF!
Add 10 per cent of cost of carriage to cover cost of 96600.00
loading and unloading
Concrete joint cutting machine . hour 12.000 150.00 1800.00 P&M-083
Texturing machine . hour 12.000 800.00 9600.00 P&M-088
c) Material

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Crushed stone coarse aggregates of 25mm and cum 945.000 1669.00 1577205.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause cum 425.000 950.00 403750.00 M-004
602.2.4
Cement 43 grade tonne 357.000 7200.00 2570400.00 M-084
Fly ash conforming to IS: 3812-1966 (Part-I) tonne 109.000 375.00 40875.00 M-011
32 mm mild steel dowel bars of grade S 240 tonne 9.450 53667.00 507153.15 M-126
16 mm deformed steel tie bars of grade S 415 tonne 1.170 55637.00 65095.29 M-085
Separation Membrane of impermeable plastic sqm 3675.000 40.00 147000.00 M-164
sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.330 742.00 12116.86 M-141
joint.
Joint sealant kg 875.000 590.00 516250.00 M-120
Sealant primer kg 116.670 395.00 46084.65 M-098-3
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 25.00 1166.75 M-138
Curing compound liter 1850.000 214.00 395900.00 M-093
Super plastisizer admixture IS marked as per 9103- kg 2070.000 104.00 215280.00 M-180
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.000 45.00 9720.00 M-189
Add 1 per cent of material for cost of miscellaneous 49307.92
materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel bars,
work bridges for men to approach concrete surface
without walking over it, cutting blades an
d) Overhead charges @ 10% on (a+b+c) 774219.29
e) Contractor's profit @ 10% on (a+b+c+d) 851641.22
Cost for 1050cum = a+b+c+d+e 9368053.37
Rate per cum = (a+b+c+d+e)/1050 8921.96
say 8922.00
Note:
1.The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities
will be as per mix design.
2.IRC: 68-1976 may be referred for guidelines on the
design of cement-fly ash concrete for rigid pavement
construction.
*Calculation of cement, sand and fly ash.
Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes.
15 per cent of cement to be replaced by fly ash =
63 tonnes. Balance cement = 357 tonnes. Quantity
of fly ash = 63 x specific gravity of fly ash /specific
gravity of cement = 63 x 2.25/3.15 = 45 tonnes.

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-6

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sand @ 0.45 cum / cum of concrete = 1050 x 0.45
= 472.50 x 1.6 = 756 tonnes.10 per cent to be
replaced by flyash. Balance sand = 756 x 0.9 =
680.4 tonnes = 680.4 / 1.6 = 425 cum. Quantity of
flyash = (756-680.4) x specific gravity of fly
ash/specific gr
Fly ash Total fly ash = 45 + 64 = 109 tonnes.

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

7.1 Sub-Surface Drain with Geotextiles


Construction of sub surface drain 200 mm dia using Non
geotextiles treated with carbon black with physical Woven
properties as given in clause 702.2.3 formed in to a
stable network and a planar geocomposite structure,
joints wrapped with geotextile to prevent ingress of soil
all as per clause 702 and approved drawing including
excavation and back filling.

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor skilled day 0.250 356.65 89.16 L-15
Mazdoor day 0.500 244.56 122.28 L-13
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain
including wrapping of joints with 160 mm over lapping
with geotextile .
Geonets(Geonet-121) sqm 1.000 310.00 310.00 M-107
Geomembrane1.5mm thick) sqm 1.000 333.00 333.00 M-106
Geotextile(GNW-280) sqm 2.000 116.00 232.00 M-108
Add 2 per cent cost of material for miscellaneous items 17.50
like synthetic cord
c) Overhead charges @ 10% on (a+b) 111.82
d) Contractor's profit @ 10% on (a+b+c) 123.00
Rate per metre = a+b+c+d 1353.03 1037.00
say 1353.00 30.47
Surplus excavated material to be used at site. Hence
seprate cost for disposal not added.
7.2 Narrow Filter Sub-Surface Drain
Construction of a narrow filter sub- surface drain
consisting of porous or perforated pipe laid in narrow
trench surrounded by a geotextile filter fabric, with a
minimum of 450 mm overlap of fabric and installed as
per clause 702.3 and 309.3.5 including excavation and
backfilling .
Unit = Running metre length
Taking output = one metre
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor skilled day 0.250 356.65 89.16 L-15
Mazdoor day 0.500 244.56 122.28 L-13
b) Material
Perforated geosynthetic pipe 150 mm dia metre 1.000 470.00 470.00 M-134
Geotextile filter fabric sqm 1.250 137.00 171.25 M-109
Add 2 per cent cost of material for miscellaneous item 12.83
like synthetic cord
c) Overhead charges @ 10% on (a+b) 87.98
d) Contractor's profit @ 10% on (a+b+c) 96.78
Rate per metre = a+b+c+d 1064.54 743.00
say 1065.00 43.34

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Surplus excavated material to be used at site. Hence


Separate cost for disposal not added.
7.3 Laying Paving Fabric Beneath a Pavement
Overlay
Providing and laying paving fabric with physical
requirements as per table 704-2 over a tack coat of
paving grade Bitumen 80-100 penetration, laid at the
rate of 1 kg per sqm over thoroughly cleaned and
repaired surface to provide a water resistant membrane
and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of
tack coat, brooming and rolling of surfaces with
pneumatic roller to maximise paving fabrics contact with
pavement surfaces.

Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate day 0.800 356.65 285.32 L-12
Mazdoor day 20.000 244.56 4891.20 L-13
b) Machinery
Road sweeper 1250 sqm per hour hour 2.240 337.00 754.88 P&M-031
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1137.00 1591.80 P&M-037
Bitumen pressure distributor 1750 sqm per hour hour 1.680 954.00 1602.72 P&M-004
c) Material
Paving Fabric sqm 2940.000 315.00 926100.00 M-133
Paving Bitumen 80-100 tonne 2.800 31681.00 88706.80 M-078
c) Overhead charges @ 10% on (a+b) 102393.27
d) Contractor's profit @ 10% on (a+b+c) 112632.60
Cost for 2800 sqm = a+b+c+d+e 1238958.59
Rate per sqm =(a+b+c+d+e)/2800 442.49 361.00
say 442.00 22.44
7.4 Laying Boulder Apron in Crates of Synthetic
Geogrids
Providing, preparing and laying of geogrid crated apron
1 m x 5 m, 600 mm thick including excavation and
backfilling with baffles at 1 metre interval, made with
geogrids having characteristics as per clause 704.2,
joining sides with connectors/ring staple, top corners to
be tie tensioned , placing of suitable crioss interval ties
in layers of 300 mm connecting opposite side with
lateral braces and tied with polymer braids to avoid
bulging , constructed as per clause 704.3 filled with
stone with minimum size of 200mm and specific gravity
not less than 2.65, packed witkh stone spalls, keyed to
the foundation recess in case of sloping ground and laid
over a layer of Geotextile to prevent migration of fines ,
all as per clause 704 and laid as per clause 2503.3 and
approved design.

Unit = cum
Taking output = 3.00 cum
a) Labour
Mate day 0.060 356.65 21.40 L-12
Mazdoor skilled day 0.500 356.65 178.33 L-15

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoor day 1.500 244.56 366.84 L-13


b) Material
Geo grids sqm 21.000 240.00 5040.00 M-105
Connectors/ Staples each 50.000 75.00 3750.00 M-088
Polymer braids metre 20.000 25.00 500.00 M-140
Stones with minimum size of 200 mm cum 3.450 898.00 3098.10 M-003
Stones spall for filling voids cum 0.450 987.00 444.15 M-008
c) Overhead charges @ 10% on (a+b) 1339.88
d) Contractor's profit @ 10% on (a+b+c) 1473.87
Cost for 3 cum = a+b+c+d 16212.56
Rate per cum = (a+b+c+d)/ 3 1247.12 927.00
say 1247.00 34.52
7.5 Reinforced Earth Structures
Reinforced earth Structures have four main components
as under:
a) Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for
facing elements (facia material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and
laying of the reinforcing elements.
d) Earth fill with granular material which is to be
retained by the wall.
Each component is analysed separately as under:

considering Average height of wall = 8 m.


7.5 II Assembling, joining and laying of reinforcing
elements.
With reinforcing element of steel / Aluminium
strips / polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 356.65 128.39 L-12
Mazdoor day 6.000 244.56 1467.36 L-13
Mazdoor skilled day 3.000 356.65 1069.95 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as per
clause 3102.
1.Galvanised carbon steel strips metre 450*1.1 240.00 118800.00 M-154
or
2.Copper Strips metre 450*1.1 1103.00 545985.00 M-153
or
3.Aluminium Strips metre 450*1.1 475.00 235125.00 M-157
or
4.Stainless steel strips metre 450*1.1 650.00 321750.00 M-156
or

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

5.Glass reinforced polymer/fibre reinforced metre 450*1.1 650.00 321750.00 M-155


polymer/polymeric strips
@ Any one of the above alternative may be adopted as
per approved design.
Add 10 per cent of the cost of reinforcing strip towards
accessories like tie-strips, nuts and bolts and loops/lugs
for joining reinforcing elements with the facia pannels,
overlaps, heat bonding or extension.
1.Galvanised carbon steel strips
c) Overhead charges @ 10% on (a+b) 12146.57
d) Contractor's profit @ 10% on (a+b+c) 12146.57
Cost of 450 m = a+b+c+d 145758.84
Rate per metre =(a+b+c+d)/450 323.91 266.00
say 324.00 21.80
2.Copper Strips
c) Overhead charges @ 10% on (a+b) 54865.07
d) Contractor's profit @ 10% on (a+b+c) 54865.07
Cost of 450 m = a+b+c+d 658380.84
Rate per metre =(a+b+c+d)/450 1463.07 1190.00
say 1463.00 22.94
3.Aluminium Strips
c) Overhead charges @ 10% on (a+b) 23779.07
d) Contractor's profit @ 10% on (a+b+c) 23779.07
Cost of 450 m = a+b+c+d 285348.84
Rate per metre =(a+b+c+d)/450 634.11 530.00
say 634.00 19.62
4.Stainless steel strips
c) Overhead charges @ 10% on (a+b) 32441.57
d) Contractor's profit @ 10% on (a+b+c) 32441.57
Cost of 450 m = a+b+c+d 389298.84
Rate per metre =(a+b+c+d)/450 865.11 728.00
say 865.00 18.82
5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips
c) Overhead charges @ 10% on (a+b) 32441.57
d) Contractor's profit @ 10% on (a+b+c) 32441.57
Cost of 450 m = a+b+c+d 389298.84
Rate per metre =(a+b+c+d)/450 865.11 728.00
say 865.00 18.82
7.5(i) With reinforcing elements of synthetic geogrids

Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 356.65 128.39 L-12
Mazdoor day 6.000 244.56 1467.36 L-13

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoor skilled day 3.000 356.65 1069.95 L-15


b) Material
Synthetic Geogrids as per clause 3102.8 and sqm 300.000 370.00 111000.00 M-181
approved design and specifications.
Add 10 per cent of the cost of reinforcing 11100.00
elements (synthetic geogrids) for accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels,
overlaps and other protective elements for
synthetic geogrids
c) Overhead charges @ 10% on (a+b) 12476.57
d) Contractor's profit @ 10% on (a+b+c) 13724.23
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 150966.50
Rate per sqm = (a+b+c+d)/ 300 503.22 424.00
say 503.00 18.63
7.5 I Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 356.65 64.20
Mazdoor day 3.000 244.56 733.68
Mazdoor skilled day 1.500 356.65 534.98
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 318.00 1908.00
c) Material
Pre-cast RCC M-35 facing elements of size as per cu.m 13.500 9731.00 131368.50
design and 18 cm thick for 75 sqm. (Refer Item
12.8 (H))
TMT steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 72981.00 27732.78
Add 5 per cent of cost of facia pannels, for all 7955.06
necessary temporary form work, scaffolding and
provision of loops/lugs for lifting of pannels and joining
the reinforcing elements.
d) Overhead charges @ 10% on (a+b) 324.09
e) Contractor's profit @ 10% on (a+b+d) 356.49
Cost for 75 sqm = a+b+c+d+e 170977.77
Rate per sqm = (a+b+c+d+e)/ 75 2279.70 5598.00
say 2280.00 (59.27)
1.The specification and construction details to be
adopted shall be as per section 3100 of MoRTH
Specification.
2.Drainage arrangement shall be made as per approved
design and drawings.
3.The quantity of filler media shall be calculated as per
approved design and specifications and shall be priced
separately.The rate for same to be adopted from
chapter 15.

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

4.Excavation for foundation including foundation


concrete and groove in the foundation for seating of
bottom most facia panel and capping beam to be
calculated as per design and priced separately. The
rates for excavation and foundation concrete shall be
taken from the chapter 12 & 13 of bridge section.
5.The earth fill to be retained is not included in this
analysis. The same is to be worked out and provided
separately complete as per clause 305.
6.For compaction of Earthwork, attention is invited to
clause 3105.5 of MoRTH Specification.

7.Length of reinforcing strips will vary with the height of


wall and will be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall
be as per approved design and specifications.
9.The market rate for supply of reinforcing elements and
their accessories are to be ascertained from reputed
firms in the field of earth reinforcement.
10.The earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-
corrosive, coarse grained with not 10 per cent of
particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies,
mineral oil, fungus and microbes and shall be of
specified PH value.

11.Capping beam is to be priced separately as per


approved design. The rate for cement concrete shall be
taken from the chapter of sub-structure in bridge
section.
12.The cost of reinforced earth retaining wall shall
include following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing
and joining with the facial pannels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form
part of embankment.
7.6 Sub-Grade Stabilization:
(A) Providing and laying one layer of Non-Woven
geotextile of minimum mass per unit area of
280gms/sqm.having minimum roll width of 5.0m treated
with carbon black with physical properties as given in
clause no 702.2.3. over 25mm thick compacted sand
layer on a prepared subgrade as a filter media with
necessary overlaps as per drawing and technical
specification and as directed by the Engineer in charge
complete.

Unit=Sqm
Taking out put = 625sqm.

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

a) Labour
Mazdoor day 12 245 2934.72
Skilled Mazdoor day 4 357 1426.60
Skilled Sticher day 6 459 2751.30
Skilled Asstt. To stitcher day 3 357 1069.95
b) Machinery
Stitching Machine with thread and pins etc. day 1 106 106.00
c) Material
GNW-280 Sqm 663.00 137 90831.00
d) Overhead charges @ 10% on (a+b) 828.86
e) Contractor's profit @ 10% on (a+b+d) 911.74
Cost for 625 sqm = a+b+c+d+e 100860.17
Rate per sqm = (a+b+c+d+e)/ 625 161.38 136.00
say 161.00 18.38
(B) Providing and laying one layer of Biaxial
P.V.C.Knitted coated polyster Geogrid of unit roll width
of 5.0m having minimum tensile strength of 40KN/m in
both direction at a maximum elongation of 15% in th
direction of the length of the roll and satisfying all
requirements of IS Code/BIS code of practice and tests
prescribed in ASTM or British standards or ISO on
prepared subgrade as a seperator cum reinforceing
agent with necessary overlaps as per drawing and
technical specification and as directed by the Executive
Engineer in charge complete.

Unit=Sqm
Taking out put = 525sqm.
a) Labour
Mazdoor day 16 245 3912.96
Skilled Mazdoor day 6 357 2139.90
Anchoring cum stitching expert day 2 459 917.10
Skilled Asstt. To Anchoring cum stitching expert day 12 357 4279.80
b) Machinery
Stitching Machine with thread and pins with other day 1 106 106.00
consumable for machinery.
c) Material
TGB-40. Sqm 557.000 240 133680.00
d) Overhead charges @ 10% on (a+b) 1135.58
e) Contractor's profit @ 10% on (a+b+d) 1249.13
Cost for 525 sqm = a+b+c+d+e 147420.47
Rate per sqm = (a+b+c+d+e)/ 525 235.87
say 236.00
7.7 Wooven Jute Geo Textile for Road Construction
and slope management purpose

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

(a) Supplying,testing and installation of 100cm wide woven


jute geotextiles(JGT) 724 gm/sq.m posseing tensile
strength of 25kn/m(+10%,-5% tolerance) with a
porometry around 150 to 400 microns and thickness 2
mm for application on road sub grades and
embankments.. Jute fabric to be laid with overlaps of
100mm crosswise and 300 mm longitudinally duly
secured to subgrade by U shaped m.s staples(11
gauge)/round head country nail of 150mm length at an
interval of 750mm as per direction of the engineer-in-
charge.

Unit=Rate/sqm.
Woven JGT as per specification including govt. Tax sq.m 1.00 69.71 69.71
(@6.03%) F.O.R Guwahati (65.75 + 3.96)
Extra for lapping @ 10% 6.97
Treatment with ecofriendly natural additive
Cost of nails/staples etc(L.S) sqm 1.00 2.00 2.00
Testing charge @Rs 6000/16000sqm = 0.38 say sqm 1.00 0.40 0.40
Rs0.40/sqm
Labour for laying JGT including preparation of bed and
fixing nails etc.for100sqm
Mazdoor no 0.023 244.56 5.62
Mason no 0.003 285.32 0.86

Overhead charges @ 10% on (a+b) 8.56


Contractor's profit @ 10% on (a+b+d) 9.41
Rate/sqm 103.53
say 104.00
(b) Supplying,testing and installation of 100cm wide woven
jute geotextiles(JGT) 627gm/sqm posseing tensile
strength of 25kn/m(+10%,-5% tolerance) with a
porometry around 150 to 400 microns and thickness 2
mm for application on road sub grades and
embankments.. Jute fabric to be laid with overlaps of
100mm crosswise and 300 mm longitudinally duly
secured to subgrade by U shaped m.s staples(11
gauge)/round head country nail of 150mm length at an
interval of 750mm as per direction of the engineer-in-
charge.

Unit=Rate/sqm.
Woven JGT as per specification including govt. Tax sq.m 1.00 60.97 60.97
(@6.03%) F.O.R Guwahati (57.5 + 3.47)
Extra for lapping @ 10% 6.10
Treatment with ecofriendly natural additive 25.00
Cost of nails/staples etc(L.S) sqm 1.00 2.00 2.00
Testing charge @Rs 6000/16000sqm = 0.38 say sqm 1.00 0.40 0.40
Rs0.40/sqm
Labour for laying JGT including preparation of bed and
fixing nails etc.for100sqm
Mazdoor no 0.023 244.56 5.62

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-7

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mason no 0.003 285.32 0.86

Overhead charges @ 10% on (a+b) 10.09


Contractor's profit @ 10% on (a+b+d) 11.10
Rate/sqm 122.15
say 122.00
(c) Supplying,testing and installation of 100cm wide woven
jute geotextiles(JGT) 627gm/sqm posseing tensile
strength of 25kn/m(+10%,-5% tolerance) with a
porometry around 150 to 400 microns and thickness 2
mm for application on road sub grades and
embankments.. Jute fabric to be laid with overlaps of
100mm crosswise and 300 mm longitudinally duly
secured to subgrade by U shaped m.s staples(11
gauge)/round head country nail of 150mm length at an
interval of 750mm as per direction of the engineer-in-
charge.

Unit=Rate/sqm.
Woven JGT as per specification including govt. Tax sq.m 1.00 28.10 28.10
(@6.03%) F.O.R Guwahati (26.5 + 1.6)
Extra for lapping @ 10% 2.81
Treatment with ecofriendly natural additive
Cost of nails/staples etc(L.S) sqm 1.00 2.00 2.00
Testing charge @Rs 6000/16000sqm = 0.38 say sqm 1.00 0.40 0.40
Rs0.40/sqm
Labour for laying JGT including preparation of bed and
fixing nails etc.for100sqm
Mazdoor no 0.023 244.56 5.62
Mason no 0.003 285.32 0.86

Overhead charges @ 10% on (a+b) 3.98


Contractor's profit @ 10% on (a+b+d) 4.38
Rate/sqm 48.15
say 48.00

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
8.1 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine
Unit = Running metre
Taking output = 360 metre
Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 356.65 256.79 L-12
Mason day 2.000 458.55 917.10 L-11
Mazdoor day 16.000 244.56 3912.96 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 284.00 1704.00 P&M-029
Concrete mixer 0.48/0.28 cum capacity hour 12.000 188.00 2256.00 P&M-009
Water tanker6 KL capacity hour 5.000 440.00 2200.00 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1777.00 38720.83 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 950.00 10355.00 M-005
Cement 11 per cent tonne 5.700 7200.00 41040.00 M-084
Cost of water KL 30.000 45.00 1350.00 M-189
d) Overhead charges @ 10% on (a+b+c) 10271.27
e) Contractor's profit @ 10% on (a+b+c+d) 11298.39
Cost for 360 meter = a+b+c+d+e 124282.34
Rate per metre = (a+b+c+d+e)/360 345.23 204.00
say 345.00 69.12
Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 284.00 1704.00 P&M-029
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1590.00 2544.00 P&M-003
Water tanker6 KL capacity hour 5.000 440.00 2200.00 P&M-060
Tipper 5.5 cum capacity hour 6.000 850.00 5100.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1777.00 38720.83 M-053
cum 21.790
cent

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Coarse sand 30 per cent cum 10.900 950.00 10355.00 M-004
Cement 11 per cent tonne 5.700 7200.00 41040.00 M-084
Cost of water KL 30.000 45.00 1350.00 M-189
d) Overhead charges @ 10% on (a+b+c) 10400.43
e) Contractor's profit @ 10% on (a+b+c+d) 11440.47
Cost for 360 meter = a+b+c+d+e 125845.20
Rate per metre = (a+b+c+d+e)/360 349.57 208.00
say 350.00 68.27
8.2 Cast in Situ Cement Concrete M 20 Kerb with Channel

Construction of cement concrete kerb with channel with top


and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, ke
Using Concrete Mixer
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.720 356.65 256.79 L-12
Mason day 2.000 458.55 917.10 L-11
Mazdoor day 16.000 244.56 3912.96 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 284.00 1704.00 P&M-029
hour 6.000
and channel
Concrete mixer 0.48/0.28 hour 16.000 188.00 3008.00 P&M-009
Water tanker6 KL capacity hour 6.000 440.00 2640.00 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1777.00 65020.43 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 950.00 17385.00 M-005
Cement 10 per cent tonne 9.010 7200.00 64872.00 M-084
Cost of water KL 36.000 45.00 1620.00 M-189
d) Overhead charges @ 10% on (a+b+c) 16133.63
e) Contractor's profit @ 10% on (a+b+c+d) 17746.99
Cost for 360 meter = a+b+c+d+e 195216.90
Rate per metre = (a+b+c+d+e)/300 650.72 382.00
say 651.00 70.42
8.2 Using Concrete Batching and Mixing Plant
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Cement concrete of grade M10 for base = 23.18 cum


Total Concrete = 40.66 cum
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 284.00 1704.00 P&M-029
hour 6.000
and channel
Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 1590.00 4293.00 P&M-003
Water tanker6 KL capacity hour 6.000 440.00 2640.00 P&M-060
Tipper of 5.5 cum capacity hour 6.000 850.00 5100.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1777.00 65020.43 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 950.00 17385.00 M-004
Cement 10 per cent tonne 9.010 7200.00 64872.00 M-084
Cost of water KL 36.000 45.00 1620.00 M-189
d) Overhead charges @ 10% on (a+b+c) 16362.49
e) Contractor's profit @ 10% on (a+b+c+d) 17998.74
Cost for 300 meter = a+b+c+d+e 197986.13
Rate per metre = (a+b+c+d+e)/300 659.95 390.00
say 660.00 69.23
8.3 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
Hindi ( Matras commas and the like not to be measured and
paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.120 356.65 42.80 L-12
Painter day 2.000 458.55 917.10 L-18
Mazdoor day 1.000 244.56 244.56 L-13
b) Material
Paint Litre 0.700 258.00 180.60 M-131
c) Overhead charges @ 10% on (a+b) 138.51
d) Contractor's profit @ 10% on (a+b+c) 152.36
Cost for 1600 cm = a+b+c+d 1675.92
Rate per cm height per letter = (a+b+c+ d)/1600 1.05 0.40
say 1.00 150.00
8.3 English and Roman
Hyphens and the like not to be measured and paid for

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Detail for 100 letters of 16 cm height. i.e.1600 cm


Unit = per cm height per letter
a) Labour
Mate day 0.090 356.65 32.10 L-12
Painter Ist class day 1.240 458.55 568.60 L-18
Mazdoor day 0.500 244.56 122.28 L-13
b) Material
Paint Litre 0.650 258.00 167.70 M-131
c) Overhead charges @ 10% on (a+b) 89.07
d) Contractor's profit @ 10% on (a+b+c) 97.97
Cost for 1600 cm = a+b+c+d 1077.72
Rate per cm height per letter = (a+b+c +d)/1600 0.67 0.20
say 0.67 235.00
8.4 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 7
Unit = Each
Taking output = one traffic sign
i) Excavation for foundation cum 0.216 251.00 54.22 Item No. 3.13
853.44 Item 12.8 (A)
ii) Cement concrete M15 grade cum 0.120 7112.00
M15 PC OM P
iii) Painting angle iron post two coats sqm 0.430 73.00 31.39 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.250 244.56 61.14 L-13
b) Material
Mild steel angle iron 75 x 75 x 6 mm kg 19.000 60.00 1140.00 M-179 /1000
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
90 cm equilateral triangle sqm 0.350 8750.00 3062.50 M-061
or
60 cm equilateral triangle sqm 0.156 8750.00 1365.00 M-061
or
60 cm circular sqm 0.283 8750.00 2476.25 M-061
or
80 mm x 60 mm rectangular sqm 0.480 8750.00 4200.00 M-061
or
60 cm x 45 cm rectangular sqm 0.270 8750.00 2362.50 M-061

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

or
60 cm x 60 cm square sqm 0.360 8750.00 3150.00 M-061
or
90 cm high octagon sqm 0.672 8750.00 5880.00 M-061
c) Machinery
Tractor-trolley hour 0.010 323.00 3.23 P&M-053
90 cm equilateral triangle
d) Overhead charges @ 10% on (a+b+c) 427.04
e) Contractor's profit @ 10% on (a+b+c+d) 469.75
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6106.27 5108.00
say 6106.00 19.54
60 cm equilateral triangle
d) Overhead charges @ 10% on (a+b+c) 257.29
e) Contractor's profit @ 10% on (a+b+c+d) 283.02
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4052.30 2991.00
say 4052.00 35.47
60 cm circular
d) Overhead charges @ 10% on (a+b+c) 368.42
e) Contractor's profit @ 10% on (a+b+c+d) 405.26
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5396.91 4377.00
say 5397.00 23.30
80 mm x 60 mm rectangular
d) Overhead charges @ 10% on (a+b+c) 540.79
e) Contractor's profit @ 10% on (a+b+c+d) 594.87
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 7482.65 6526.00
say 7483.00 14.66
60 cm x 45 cm rectangular
d) Overhead charges @ 10% on (a+b+c) 357.04
e) Contractor's profit @ 10% on (a+b+c+d) 392.75
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5259.27 4235.00
say 5259.00 24.18
60 cm x 60 cm square
d) Overhead charges @ 10% on (a+b+c) 435.79
e) Contractor's profit @ 10% on (a+b+c+d) 479.37
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6212.15 5217.00
say 6212.00 19.07
90 cm high octagon
d) Overhead charges @ 10% on (a+b+c) 708.79
e) Contractor's profit @ 10% on (a+b+c+d) 779.67
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 9515.45 8621.00
say 9515.00 10.37

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

1.Any one area of aluminium sheeting given at (i) to (vii) may


be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters

3. The depth of foundation and quantity of cement concrete


in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

Direction and Place Identification Signs upto 0.9 sqm


8.5
Size Board.
Providing and erecting direction and place identification
retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel s
Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.216 251.00 54.22 Item No. 3.13
7112.00 853.44 Item 12.8 (A)
ii) Cement concrete M15 grade cum 0.120
M15 PC OM P
iii) Painting angle iron post two coats sqm 0.430 73.00 31.39 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.200 244.56 48.91 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 60.00 1140.00 M-179 /1000
kg 19.000
metres long
Aluminium sheeting fixed with encapsulated lens type 8750.00 7875.00 M-061
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 323.00 6.46 P&M-053
d) Overhead charges @ 10% on (a+b+c) 907.39
e) Contractor's profit @ 10% on (a+b+c+d) 998.13
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 11918.51
Rate per sqm (for sign having area upto 0.9 sqm) = 12341.00
13242.79
(I+ii+iii+a+b+c+d+e)/0.90
say 13243.00 7.31
I) Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
8.6
than 0.9 sqm size Board.

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Providing and erecting direction and place identification


retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel ang
Unit = sqm
Taking output = 1.50 sqm
i) Excavation for foundation cum 0.430 251.00 107.93 Item No. 3.13

ii) Cement concrete M15 grade cum 0.240 7112.00 1706.88 Item 12.8 (A)
M15 PC OM P
iii) Painting angle iron post 2 coats sqm 0.860 73.00 62.78 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.300 244.56 73.37 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 60.00 2280.00 M-179 /1000
kg 38.000
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type 8750.00 13125.00 M-061
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 323.00 6.46 P&M-053
d) Overhead charges @ 10% on (a+b+c) 1541.15
e) Contractor's profit @ 10% on (a+b+c+d) 1702.95
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 20610.08
Rate per sqm ( for sign having area more than 0.9 12614.00
13740.06
sqm) = ( i+ii+iii+a+b+c+d+e)/1.50
say 13740.00 8.93
i) Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and
Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 356.65 85.60 L-12
Blacksmith day 2.000 458.55 917.10 L-02
Mazdoor including for handling & fixing at site. day 4.000 244.56 978.24 L-13

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

b) Material
Aluminium alloy/galvanised steel including 5 per cent M-060
tonne 1.050 56000.00 58800.00
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
588.00
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
8908.20
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 318.00 954.00 P&M-013
Truck hour 0.500 717.00 358.50 P&M-057
d) Overhead charges @ 10% on (a+b+c) 7158.96
e) Contractor's profit @ 10% on (a+b+c+d) 7874.86
Rate per tonne = (a+b+c+d+e) 86623.46 51555.00
say 86623.00 68.02
8.7 Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 356.65 7.13 L-12
Blacksmith day 0.100 458.55 45.86 L-02
Mazdoor day 0.150 244.56 36.68 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed with high M-059
sqm 1.000 460.00 460.00
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
0.90
ladders, pulleys, ropes etc
c) Overhead charges @ 10% on (a+b) 55.06
d) Contractor's profit @ 10% on (a+b+c) 60.56
Rate per sqm = (a+b+c+d) 666.19
say 666.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as
per the approved drawing/design and to be included in the
estimate.

2. Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been included separately in this chapter.

8.8 Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

a) Labour
Mate day 0.120 356.65 42.80 L-12
Painter day 2.000 458.55 917.10 L-18
Mazdoor day 1.000 244.56 244.56 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 258.00 1548.00 M-132
Add for scaffolding @ 1 per cent of labour cost where
15.48
required
Add @ 5 per cent cost of labour and materials to 137.62
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 10% on (a+b) 290.56
d) Contractor's profit @ 10% on (a+b+c) 319.61
Cost for 40 sqm = a+b+c+d 3515.73
Rate per sqm = (a+b+c+d)/40 87.89 38.00
say 88.00 131.58
8.9 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 356.65 10.70 L-12
Painter day 0.450 458.55 206.35 L-18
Mazdoor day 0.250 244.56 61.14 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 258.00 322.50 M-131
Add @ 1 per cent on cost of material for scaffolding 3.23
Add @ 5 per cent cost of labour and materials to 30.03
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 10% on (a+b) 63.39
d) Contractor's profit @ 10% on (a+b+c) 69.73
Cost for 10 sqm = a+b+c+d 767.08
Rate per sqm= (a+b+c+d)/10 76.71 33.00
say 77.00 133.33
8.10 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

a) Labour
Mate day 0.030 356.65 10.70 L-12
Painter day 0.500 458.55 229.28 L-18
Mazdoor day 0.200 244.56 48.91 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 258.00 387.00 M-131
Add @ 1 per cent on cost of material for scaffolding 3.87
Add @ 5 per cent cost of labour and materials to 33.79
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 10% on (a+b) 71.36
d) Contractor's profit @ 10% on (a+b+c) 78.49
Cost for 10 sqm = a+b+c+d 863.40
Rate per sqm = (a+b+c+d)/10 86.34 37.00
say 86.00 132.43
Painting Lines, Dashes, Arrows etc on Roads in Two
8.11
Coats on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic
Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 356.65 32.10 L-12
Painter day 0.550 458.55 252.20 L-18
Mazdoor day 1.550 244.56 379.07 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 85.00 125.80 M-132
c) Overhead charges @ 10% on (a+b) 78.92
d) Contractor's profit @ 10% on (a+b+c) 86.81
Cost for 10 sqm = a+b+c+d 954.89
Rate per sqm= (a+b+c+d)/10 95.49 41.00
say 95.00 131.71
8.11 Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 356.65 24.97 L-12
Painter day 0.350 458.55 160.49 L-18
Mazdoor day 1.350 244.56 330.16 L-13

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

b) Material
Road marking paint Litre 1.480 85.00 125.80 M-132
c) Overhead charges @ 10% on (a+b) 64.14
d) Contractor's profit @ 10% on (a+b+c) 70.56
Cost for 10 sqm = a+b+c+d 776.11
Rate per sqm = (a+b+c+d)/10 77.61 35.00
say 78.00 122.86
Painting Lines, Dashes, Arrows etc on Roads in Two
8.12
Coats on Old Work
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffi
Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 356.65 21.40 L-12
Painter Ist class day 0.300 458.55 137.57 L-18
Mazdoor day 1.250 244.56 305.70 L-13
b) Material
Road marking paint Litre 0.900 85.00 76.50 M-132
c) Overhead charges @ 10% on (a+b) 54.12
d) Contractor's profit @ 10% on (a+b+c) 59.53
Cost for 10 sqm = a+b+c+d 654.81
Rate per sqm = (a+b+c+d)/10 65.48 28.00
say 65.00 132.14
8.12 Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 356.65 24.97 L-12
Painter Ist class day 0.350 458.55 160.49 L-18
Mazdoor day 1.350 244.56 330.16 L-13
b) Material
Road marking Paint Litre 0.900 85.00 76.50 M-132
c) Overhead charges @ 10% on (a+b) 59.21
d) Contractor's profit @ 10% on (a+b+c) 65.13
Cost for 10 sqm= a+b+c+d 716.46
Rate per sqm = (a+b+c+d)/10 71.65 30.00
say 72.00 140.00

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Road Marking with Hot Applied Thermoplastic


8.13 Compound with Reflectorising Glass Beads on
Bituminous Surface
Providing and laying of hot applied thermoplastic compound
2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform a
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 356.65 10.70 L-12
Mazdoor day 0.750 244.56 183.42 L-13
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 192.00 1920.00 P&M-043
Tractor-trolley hour 0.500 323.00 161.50 P&M-053
c) Material
Hot applied thermoplastic compound Litre 1500.000 133.00 199500.00 M-118
Reflectorising glass beads kg 150.000 102.00 15300.00 M-152
d) Overhead charges @ 10% on (a+b+c) 21707.56
e) Contractor's profit @ 10% on (a+b+c+d) 23878.32
Cost for 600 sqm = a+b+c+d+e 262661.50
Rate per sqm = a+b+c+d+e)/600 437.77
say 438.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.14 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
a) M-15 grade of concrete cum 2.350 7112.00 16713.20 Item 12.8 (A)
M15 PC OM P
78.53 1733.83 Item 13.6 /1000
b) Steel reinforcement @ 5 kg per sqm kg 22.080

c) Excavation in soil for foundation cum 1.680 251.00 421.68 Item No. 3.13
d) Painting two coats on concrete surface sqm 9.850 52.00 512.20 Item 8.8
e) Lettering on km post (average 30 letters of per cm per 0.60 1080.00 Item 8.3
1800.000
10 cm height each) letter
Transportation and fixing
f) Labour

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mate day 0.260 356.65 92.73 L-12


Mason day 0.600 458.55 275.13 L-11
Mazdoor including loading/unloading day 6.000 244.56 1467.36 L-13
g) Machinery
Tractor-trolley hour 6.000 323.00 1938.00 P&M-053
h) Overhead charges @ 10% on (f+g) 377.32
i) Contractor's profit @ 10% on (f+g+h) 415.05
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 25026.51
Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i ) 2614.00
4171.08
/6
say 4171.00 59.56
8.14 Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
7112.00 26812.24 Item 12.8 (A)
a) M-15 grade of concrete cum 3.770
M15 PC OM P
78.53 2066.78 Item 13.6 /1000
b) Steel reinforcement @ 5 kg per sqm kg 26.320

c) Excavation in soil for foundation cum 2.770 251.00 695.27 Item No. 3.13
d) Painting two coats on concrete surface sqm 11.410 52.00 593.32 Item 8.8
e) Lettering on km post ( average 12 letters of per cm per 0.60 1008.00 Item 8.3
1680.000
10 cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 356.65 114.13 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 7.000 244.56 1711.92 L-13
g) Machinery
Tractor-trolley hour 6.000 323.00 1938.00 P&M-053
h) Overhead charges @ 10% on (f+g) 422.26
i) Contractor's profit @ 10% on (f+g+h) 464.49
Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i)
36284.95
Rate for each ordinary km stone = (a+b+ c 1619.00
2591.78
+d+e+f+g+h+j)/14
say 2592.00 60.10
8.14 Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
7112.00 11236.96 Item 12.8 (A)
a) M-15 grade of concrete cum 1.580
M15 PC OM P
78.53 5182.65 Item 13.6 /1000
b) Steel reinforcement @ 5 kg per sqm kg 66.000

c) Excavation in soil for foundation cum 1.390 251.00 348.89 Item No. 3.13
d) Painting two coats on concrete surface sqm 6.270 52.00 326.04 Item 8.8

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

e) Lettering on km post (average 1 letter of 10 per cm per 0.60 198.00 Item 8.3
330.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 356.65 121.26 L-12
Mason day 1.500 458.55 687.83 L-11
Mazdoor day 7.000 244.56 1711.92 L-13
g) Machinery
Tractor-trolley hour 6.000 323.00 1938.00 P&M-053
h) Overhead charges @ 10% on (f+g) 445.90
i) Contractor's profit @ 10% on (f+g+h) 490.49
Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+
22687.94
g+h+i)
Rate for each Hectometer stone = (a+b +c +d+e+f+
687.51 428.00
g+h+i) / 33
say 688.00 60.75
200 -M stone (precast)
Unit = Nos.
Taking output = 33 Nos.
7112.00 11236.96 Item 12.8 (A)
a) M-15 grade of concrete cum 1.580
M15 PC OM P
78.53 5182.65 Item 13.6 /1000
b) Steel reinforcement @ 5 kg per sqm kg 66.000

c) Excavation in soil for foundation cum 1.390 251.00 348.89 Item No. 3.13
d) Painting two coats on concrete surface sqm 6.270 52.00 326.04 Item 8.8
e) Lettering on km post (average 1 letter of 10 per cm per 0.60 198.00 Item 8.3
330.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 356.65 121.26 L-12
Mason day 1.500 458.55 687.83 L-11
Mazdoor day 7.000 244.56 1711.92 L-13
g) Machinery
Tractor-trolley hour 6.000 323.00 1938.00 P&M-053
h) Overhead charges @ 10% on (f+g) 445.90
i) Contractor's profit @ 10% on (f+g+h) 490.49
Cost for 33 Nos. 200 meter stone = (a+b +c +d+e+f+ g+h+i)
22687.94
Rate for each 200 meter stone = (a+b +c +d+e+f+
687.51 428.00
g+h+i) / 33
say 688.00 60.75
The rate for excavation, cement concrete, steel
reinforcement, painting and lettering may be taken from
respective chapters.

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

8.16 Boundary pillar


Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
7112.00 8890.00 Item 12.8 (A)
a) M-15 grade of the boundary stone cum 1.250
M15 PC OM P
78.53 6266.30 Item 13.6 /1000
b) Steel reinforcement kg 79.800

c) Excavation in soil cum 10.720 251.00 2690.72 Item No. 3.13


0.60 1368.00 Item 8.3
per letter
d) Lettering, each 10 cm high 2280.000
per cm high

Transportation and fixing


e) Labour
Mate day 0.570 356.65 203.29 L-12
Mazdoor day 14.250 244.56 3484.98 L-13
f) Machinery
Tractor-trolley hour 6.000 323.00 1938.00 P&M-053
g) Material
Stone spall cum 11.970 987.00 11814.39 M-008
h) Overhead charges @ 10% on (e+f+g) 1744.07
i) Contractor's profit @ 10% on (e+f+g+h) 1918.47
Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )
40318.21
Rate for each boundary pillar = (a+b+c+d+e+ 386.00
707.34
f+g+h+i)/57
say 707.00 83.16

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

8.17 G.I Barbed Wire Fencing 1.2 Metre High


Providing and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post
Unit = per running metre
Taking output = 30 metres
a) Labour

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mate day 0.090 356.65 32.10 L-12


Blacksmith day 0.250 458.55 114.64 L-02
Mazdoor day 2.000 244.56 489.12 L-13
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 78.00 2450.76 M-063
kg 31.420
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in 60.00 4830.00 M-179 /1000
kg 80.500
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
145.62
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 73.00 154.03 Item 8.9
sqm 2.110
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 10% on (a+b) 806.22
e) Contractor's profit @ 10% on (a+b+d) 886.85
Cost for 30 metres fencing = a+b+c+d+e 9909.33
Rate per metre = (a+b+c+d+e)/30 330.31 180.00
say 330.00 83.33
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
8.18 G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.120 356.65 42.80 L-12
Blacksmith day 0.400 458.55 183.42 L-02
Mazdoor day 2.500 244.56 611.40 L-13
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 78.00 3131.70 M-063
kg 40.150
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in 60.00 9120.00 M-179 /1000
kg 152.000
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
245.03
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 73.00 289.08 Item 8.9
sqm 3.960
angle iron posts
d) Overhead charges @ 10% on (a+b) 1333.44
e) Contractor's profit @ 10% on (a+b+d) 1466.78
Cost for 30 metres fencing = a+b+c+d+e 16423.65

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Rate per metre fencing = (a+b+c +d+e)/30 547.45 302.00


say 547.00 81.13
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.

Fencing With Welded Steel Wire Fabric 75 mm x 50


8.19
mm

Providing 1.20 metre high fencing with angle iron posts 50


mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded
steel wire fabric of 75 mm
Unit = Running metre
Taking output = 30 m
a) Labour
Mate day 0.120 356.65 42.80 L-12
Welder day 1.000 458.55 458.55 L-02
Mazdoor day 2.000 244.56 489.12 L-13
b) Material
i) Angle iron for posts 50 x 50 x 6 mm kg 106.000 60.00 6360.00 M-179 /1000
ii) Runner flat 50 x 5 mm kg 26.000 60.00 1560.00 M-179 /1000
iii) Welded steel wire fabric 75x50 mm mesh @ 4 46.00 6946.00 M-191
kg 151.000
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg 293.000
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley hour 0.100 323.00 32.30 P&M-053
d) Painting
Painting two coats including priming sqm 8.000 73.00 584.00 Item 8.9
e) Overhead charges @ 10% on (a+b+c) 1588.88
f) Contractor's profit @ 10% on (a+b+c+e) 1747.76
Cost for 30 metre = a+b+c+d+e+f 19809.41
Rate per metre = (a+b+c+d+e+f)/30 660.31 442.00
say 660.00 49.32
i) Adopt any one type of welded steel wire fabric 75 x 50 mm
or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
8.20
( ISMC series) 100 mm x 50 mm

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Providing, fixing and erecting 50 mm dia steel pipe railing in


3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2
m centre to centre, complete as per approved drawings

Unit = Running metre


Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 251.00 325.30 Item No. 3.13
cum 1.296
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 7112.00 11379.20 Item 12.8 (A)
cum 1.600
0.6 x 0.3 M15 PC OM P
iii) Painting of pipe sqm 4.710 73.00 343.83 Item 8.9
iv) Painting of channel section 6 nos,1.8 metres 73.00 157.68 Item 8.9
sqm 2.160
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 356.65 3.57 L-12
Mazdoor day 0.250 244.56 61.14 L-13
Plumber day 0.010 458.55 4.59 L-02
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 140.00 4200.00 M-175
Medium weight steel channel (ISMC series) 100 mm x 60.00 5961.60 M-179 /1000
kg 99.360
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels 119.23
c) Machinery
Tractor-trolley hour 0.040 323.00 12.92 P&M-053
d) Overhead charges @ 10% on (a+b+c) 2255.61
e) Contractor's profit @ 10% on (a+b+c+d) 2481.17
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 27305.84
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2730.58 1242.00
say 2731.00 119.89
Tubular Steel Railing on Precast RCC Posts, 1.2 m
8.21
High Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 251.00 325.30 Item No. 3.13
cum 1.296
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 7112.00 4608.58 Item 12.8 (A)
cum 0.648
x 0.6 x 0.3 M15 PC OM P
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 9465.00 3028.80 Item 14.1(A)
cum 0.320
metres each
iv) Painting of pipe sqm 4.710 73.00 343.83 Item 8.9
a) Labour

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mate day 0.014 356.65 4.99 L-12


Mazdoor day 0.350 244.56 85.60 L-13
Plumber day 0.010 458.55 4.59 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 140.00 4200.00 M-175
c) Machinery
Tractor-trolley hour 0.250 323.00 80.75 P&M-053
d) Overhead charges @ 10% on (a+b+c) 437.59
e) Contractor's profit @ 10% on (a+b+c+d) 481.35
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 13601.37
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1360.14 932.00
say 1360.00 45.92
8.22 Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expa
Unit = Linear metre
Taking output = 10 m
a) M 20 grade concrete
M 20 grade concrete cum 3.000 9465.00 28395.00 Item 14.1(A)
b) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 55637.00 15578.36 M-085
Pre-moulded asphalt filler board sqm 0.320 647.00 207.04 M-144
d) Overhead charges @ 10% on (b+c) 1604.42
e) Contractor's profit @ 10% on (b+c+d) 1764.86
Cost for 10 metre = a+b+c+d+e 47808.51
Rate per metre = (a+b+c+d+e)/10 4780.85 2870.00
say 4781.00 66.59
i) Excavation and backfilling are incidental to work and not to
be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
8.23 Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m belo
Unit = Running metre

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Taking output = 4.5 metre length


a) Labour
Mate day 0.060 356.65 21.40 L-12
Blacksmith day 0.500 458.55 229.28 L-02
Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Tractor-trolley hour 0.100 323.00 32.30 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section 60.00 2472.60 M-179 /1000
kg 41.210
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 60.00 5313.60 M-179 /1000
kg 88.560
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 60.00 974.40 M-179 /1000
kg 16.240
16.4 kg per metre
Nuts and bolts kg 20.000 90.00 1800.00 M-130
Add 25 per cent of the cost of material for fabrication, nuts,
2640.15
bolts and washers etc.)
d) Overhead charges @ 10% on (a+b+c) 1372.83
e) Contractor's profit @ 10% on (a+b+c+d) 1510.11
Cost for 4.5 metre = a+b+c+d+e 16611.22
Rate per metre = (a+b+c+d+e)/4.5 3691.38 2112.00
say 3691.00 74.76
8.23 Type - B, "THRIE" : Metal Beam Crash Barrier
Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 356.65 21.40 L-12
Blacksmith day 0.500 458.55 229.28 L-02
Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Tractor-trolley hour 0.100 323.00 32.30 P&M-053
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section 88.00 6418.72 M-091
kg 72.940
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 60.00 5904.00 M-179 /1000
kg 98.400
kg per metre
60.00 1611.60 M-179 /1000
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860

Nuts and bolts kg 30.000 90.00 2700.00 M-130


Add 15 per cent of the cost of material for fabrication, nuts,
2495.15
bolts and washers etc.)

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

d) Overhead charges @ 10% on (a+b+c) 1965.70


e) Contractor's profit @ 10% on (a+b+c+d) 2162.27
Cost for 4.5 metre = a+b+c+d+e 23784.97
Rate per metre= (a+b+c+d+e)/4.5 5285.55 3118.00
say 5286.00 69.53
In the case of median crash barrier, 'W' metal beam or thrie
beam section should be provided on both sides of the
vertical posts fixed in the median. Extra provision for metal
beam railing and spacer is required to be made when fixed
in the median dependi
8.24 Road Traffic Signals electrically operated
Since it is a ready made item commercially produced and
erected by specialised firm in the electrical and electronic
field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawin

8.25 Flexible Crash Barrier, Wire Rope Safety Barrier

Providing and erecting a wire rope safety barrier with vertical


posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and
0.65 m below ground level, split at the bottom for better grip,
embedded in M 15
Unit = Running metre
Taking output = 15 metre
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 2.000 244.56 489.12 L-13
Blacksmith day 1.000 458.55 458.55 L-02
b) Material
60.00 11400.00 M-179 /1000
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg 190.000
ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 60.00 2760.00 M-179 /1000
kg 46.000
x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for 60.00 11304.00 M-179 /1000
kg 188.400
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent 95.00 6175.00 M-177
kg 65.000
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
1581.95
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 73.00 1204.50 Item 8.9
d) Machinery
Tractor-trolley hour 0.250 323.00 80.75 P&M-053
e) Overhead charges @ 10% on (a+b+d) 3429.22
f) Contractor's profit @ 10% on (a+b+d+e) 3772.14
Cost for 15 m = a+b+c+d+e+f 42698.02

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Rate per m = (a+b+c+d+e+f)/15 2846.53 1719.00


say 2847.00 65.62
The items of excavations and cement concrete works will be
measured and included separately as per the approved
designs and drawings.

8.26 Anti-Glare Devices in Median

Plantation
Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chap
Anti-glare screen with 25 mm steel pipe framework
fixed with circular and rectangular vans
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, m
Unit = Running metre
Taking output = one metre
a) Labour
Mate day 0.004 356.65 1.43 L-12
Mazdoor day 0.100 244.56 24.46 L-13
b) Material
i) 25 mm steel pipe metre 16.000 72.00 1152.00 M-174
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, 60.00 259.20 M-179 /1000
kg 4.320
one number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4 60.00 288.00 M-179 /1000
kg 4.800
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
84.96
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface sqm 1.830 73.00 133.59 Item 8.9
d) Overhead charges @ 10% on (a+b) 181.00
e) Contractor's profit @ 10% on (a+b+d) 199.10
Rate per metre = a+b+c+d+e 2323.74 1593.00
say 2324.00 45.89
The items of excavation and cement concrete as per
approved design to be measured and paid separately
8.26 Anti-glare screen with rectangular vane of MS sheet

Providing and erecting anti - glare screen with rectangular


vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 to the direction of flow of traffic, 1.5 m center to center,
top edge of the scre

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Unit = Running metre


Taking output = 1.50 metre
a) Labour
Mate day 0.004 356.65 1.43 L-12
Mazdoor day 0.100 244.56 24.46 L-13
b) Material
i) Angle iron post,50 x 50 x 6 mm, length 2.35 m kg 10.580 60.00 634.80 M-179 /1000
ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000 60.00 540.00 M-179 /1000
Add 5 per cent of cost of material for fabrication, nuts, bolts
58.74
etc
c) Machinery
Tractor-trolley hour 0.100 323.00 32.30 P&M-053
d) Painting
Applying 2 coats of painting sqm 0.850 73.00 62.05 Item 8.9
e) Overhead charges @ 10% on (a+b+c) 129.17
f) Contractor's profit @ 10% on (a+b+c+e) 142.09
Cost for 1.5 m = a+b+c+d+e+f 1625.03
Rate per metre = (a+b+c+d+e+f)/1.50 1083.36 632.00
say 1083.00 71.36

The items of excavation and cement concrete as per


approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.

8.27 Street Lighting

Providing and erecting street light mounted on a steel


circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour light 250 watts and
fixed firmly in concrete foundation as per approved
drawing.The items of excavation and cement concrete
foundation will be measured and included separately

For Fixing in Median


Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 356.65 10.70 L-12
Mazdoor day 0.500 244.56 122.28 L-13
Electrician day 0.250 458.55 114.64 L-02
b) Material
i) Steel circular hollow pole of standard specification for 11000.00 11000.00 M-171
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp 250 watts each 2.000 7900.00 15800.00 M-168

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Add 5 per cent of cost of material for holder, electric cable,


1340.00
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 73.00 419.75 Item 8.9
sqm 5.750
circular hollow pipe with overhang on both sides
For Fixing in Median
d) Overhead charges @ 10% on (a+b) 2838.76
e) Contractor's profit @ 10% on (a+b+d) 3122.64
Rate per light for fixing in Median= a+b+c+d+e 34768.77 30147.00
say 34769.00 15.33
For fixing in Footpath
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 356.65 10.70 L-12
Mazdoor day 0.500 244.56 122.28 L-13
Electrician day 0.250 458.55 114.64 L-02
b) Material
i) Steel circular hollow pole of standard specification for 11000.00 11000.00 M-171
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp 250 watts each 1.000 7900.00 7900.00 M-168
Add 5 per cent of cost of material for holder, electric cable,
945.00
insulation, ladder, scaffolding etc
c) Painting
For fixing in Footpath
Providing two coats of alluminium paint over steel 73.00 337.99 Item 8.9
sqm 4.630
circular hollow pipe with overhang on one side
For Fixing in Median
d) Overhead charges @ 10% on (a+b) 2009.26
e) Contractor's profit @ 10% on (a+b+d) 2210.19
For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 24650.06 21218.00
say 24650.00 16.17

8.28 Lighting on Bridges

Providing and fixing lighting on bridges, mounted on steel


hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 356.65 7.13 L-12

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoor day 0.400 244.56 97.82 L-13


Electrician day 0.200 458.55 91.71 L-02
b) Material
7500.00 7500.00 M-170
i) Steel circular hollow pole of standard specification for
each 1.000
street lighting to mount light at 5 m above deck level

ii) Sodium vapour lamp 250 watt each 1.000 7900.00 7900.00 M-168
Add 1 per cent of cost of material for holder, electric cable,
154.00
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel 73.00 201.48 Item 8.9
sqm 2.760
circular hollow pipe
d) Overhead charges @ 10% on (a+b) 1575.07
e) Contractor's profit @ 10% on (a+b+d) 1732.57
Rate per light = a+b+c+d+e 19259.79 16673.00
say 19260.00 15.52
The items of cement concrete to be measured and paid
separately as per approved design. The rate for painting has
already been analysed in this chapter.

8.29 Cable Duct Across the Road

Providing and laying of a reinforced cement concrete pipe


duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at both ends,
providing a minimum fill
Single row for one utility service
Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in 3538.00 8349.68 Item 12.7
cum 2.360
cement mortar 1:6 for head wall both side (Addl) B)
b) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor day 1.000 244.56 244.56 L-13
Mazdoor skilled day 0.250 356.65 89.16 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 20.000 2592.00 51840.00 M-151
Granular soil with PI less than 6 for bedding and sides 698.00 5025.60 M-009
cum 7.200
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia each 9.000 504.00 4536.00 M-086
Cement mortar 1:2 for joints cum 0.020 5959.00 119.18 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 0.500 323.00 161.50 P&M-053
e) Overhead charges @ 10% on (b+c+d) 6203.38
f) Contractor's profit @ 10% on (b+c+d+e) 6823.72
Cost for 20 metre = a+b+c+d+e+f 83410.62

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Rate per metre = (a+b+c+d+e+f)/20 4170.53 1643.00


say 4171.00 153.86
8.29 Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 3538.00 11923.06 Item 12.7
cum 3.370
mortar 1:6 for head wall both sides. (Addl) B)
b) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor day 2.000 244.56 489.12 L-13
Mazdoor skilled day 0.250 356.65 89.16 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 2592.00 103680.00 M-151
Granular soil with PI less than 6 for bedding and sides 698.00 10051.20 M-009
cum 14.400
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each 18.000 504.00 9072.00 M-086
Cement mortar 1:2 for joints cum 0.040 5959.00 238.36 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 1.000 323.00 323.00 P&M-053
e) Overhead charges @ 10% on (b+c+d) 12396.07
f) Contractor's profit @ 10% on (b+c+d+e) 13635.67
Cost for 20 metre = a+b+c+d+e+f 161915.48
Rate per metre = (a+b+c+d+e+f)/20 8095.77 3149.00
say 8096.00 157.10
8.29 Triple rRow for three utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 3538.00 15496.44 Item 12.7
cum 4.380
mortar 1:6 for head wall both sides. (Addl) B)
b) Labour
Mate day 0.160 356.65 57.06 L-12
Mazdoor day 3.000 244.56 733.68 L-13
Mazdoor skilled day 1.000 356.65 356.65 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 60.000 2592.00 155520.00 M-151
Granular soil with PI less than 6 for bedding and sides 698.00 15076.80 M-009
cum 21.600
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia each 27.000 504.00 13608.00 M-086
Cement mortar 1:2 for joints cum 0.060 5959.00 357.54 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 1.500 323.00 484.50 P&M-053
e) Overhead charges @ 10% on (b+c+d) 18619.42
f) Contractor's profit @ 10% on (b+c+d+e) 20481.37
Cost for 20 metre = a+b+c+d+e+f 240791.46

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Rate per metre = (a+b+c+d+e+f)/20 12039.57 4660.00


say 12040.00 158.37
8.34 Traffic Impact Attenuators at Abutments and Piers

With Scrap Tyres


Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawin
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 1.500 244.56 366.84 L-13
Blacksmith day 0.250 458.55 114.64 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 30.00 2400.00 M-161
20 mm steel wire rope kg 150.000 155.00 23250.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 232.50
c) Machinery
Tractor-trolley hour 3.000 323.00 969.00 P&M-053
d) Overhead charges @ 10% on (a+b+c) 2736.15
e) Contractor's profit @ 10% on (a+b+c+d) 3009.77
Cost for 20 sqm = a+b+c+d+e 33107.43
Rate per sqm = (a+b+c+d+e)/20 1655.37 1273.00
say 1655.00 30.01
8.34 Using Plastic/Steel Barrel, Filled with Sand
Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 356.65 46.36 L-12
Mazdoor day 3.000 244.56 733.68 L-13
Blacksmith day 0.250 458.55 114.64 L-02
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 66.00 3300.00 M-172
Sand cum 8.000 950.00 7600.00 M-004

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

20 mm steel wire rope kg 15.000 155.00 2325.00 M-176


Add 1 per cent of cost of wire rope for clamps etc. 23.25
c) Machinery
Tractor-trolley hour 2.000 323.00 646.00 P&M-053
d) Overhead charges @ 10% on (a+b+c) 1478.89
e) Contractor's profit @ 10% on (a+b+c+d) 1626.78
Cost for 20 sqm = a+b+c+d+e 17894.61
Rate per sqm = (a+b+c+d+e)/20 894.73 577.00
say 895.00 55.11
8.43 Portable Barricade in Construction Zone

Installation of a steel portable barricade with horizontal rail


300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white stripes,
150 mm in wid
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor day 0.250 244.56 61.14 L-13
Painter day 0.500 458.55 229.28 L-18
Welder day 0.250 458.55 114.64 L-02
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 60.00 1500.00 M-179 /1000
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 60.00 900.00 M-179 /1000
Paint litre 0.500 258.00 129.00 M-131
Add 2 per cent of cost of steel for welding consumables,
48.00
nuts & bolts and drilling holes
c) Overhead charges @ 10% on (a+b) 298.92
d) Contractor's profit @ 10% on (a+b+c) 328.81
Rate per barricade = a+b+c+d 3616.91 1978.00
say 3617.00 82.86
8.44 Permanent Type Barricade in Construction Zone

With steel components


Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width a
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 356.65 17.83 L-12

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoor day 0.300 244.56 73.37 L-13


Painter day 0.600 458.55 275.13 L-18
Welder day 0.300 458.55 137.57 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 60.00 900.00 M-179 /1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m 60.00 3000.00 M-179 /1000
kg 50.000
length
Paint litre 1.000 258.00 258.00 M-131
Add 1 per cent of cost of steel for welding consumables,
78.00
nuts & bolts and drilling holes
c) Overhead charges @ 10% on (a+b) 473.99
d) Contractor's profit @ 10% on (a+b+c) 521.39
Rate per barricade = a+b+c+d 5735.27 3175.00
say 5735.00 80.63
8.44 With wooden components
Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 356.65 17.83 L-12
Mazdoor day 0.300 244.56 73.37 L-13
Painter day 0.600 458.55 275.13 L-18
Carpenter day 0.600 458.55 275.13 L-04
b) Material
Timber cum 0.180 34100.00 6138.00 M-185
Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 61.38
c) Overhead charges @ 10% on (a+b) 684.08
d) Contractor's profit @ 10% on (a+b+c) 752.49
Rate per barricade = a+b+c+d 8277.42 6567.00
say 8277.00 26.04
8.44 With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 356.65 85.60 L-12
Mazdoor day 3.000 244.56 733.68 L-13
Painter day 1.000 458.55 458.55 L-18

Page 29 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mason day 2.000 458.55 917.10 L-11


b) Material
Brick each 1800.000 8.00 14400.00 M-082
Cement kg 22.000 7.20 158.40 M-084 /1000
Sand cum 0.090 950.00 85.50 M-005
Paint litre 1.250 258.00 322.50 M-131
c) Overhead charges @ 10% on (a+b) 1716.13
d) Contractor's profit @ 10% on (a+b+c) 1887.75
Rate per barricade = a+b+c+d 20765.20 7663.00
say 20765.00 170.98
8.45 Drum Delineator in Construction Zone

Provision of metal drum/empty bitumen drum delineator, 300


mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 356.65 7.13 L-12
Mazdoor day 0.250 244.56 61.14 L-13
Painter day 0.250 458.55 114.64 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen 66.00 66.00 M-172
each 1.000
drum
Paint litre 0.500 258.00 129.00 M-131
c) Overhead charges @ 10% on (a+b) 37.79
d) Contractor's profit @ 10% on (a+b+c) 41.57
Rate per drum delineator = a+b+c+d 457.27 223.00
say 457.00 104.93
8.46 Flagman

Positioning of a smart flagman with a yellow vest and a


yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 11.00 11.00 M-099
Wooden staff for fastening of flag 25 mm dia, one m 60.00 60.00 M-196
each 1.000
long

Page 30 of 959
Analysisof SOR (Roads) 2017-18
Chapter-8

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

c) Overhead charges @ 10% on (a+b) 32.98


d) Contractor's profit @ 10% on (a+b+c) 36.28
Rate per flagman = a+b+c+d 399.09 194.00
say 399.00 105.67

Page 31 of 959
Analysisof SOR (Roads) 2017-18
Chapter-9

CHAPTER-9
PIPE CULVERTS
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
9.1 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 356.65 228.26 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 15.000 244.56 3668.40 L-13
b) Material
40mm Aggregate at site cum 13.800 1500.00 20700.00 M-055
Sand at site cum 6.900 950.00 6555.00 M-005
Cement at site tonne 3.900 7200.00 28080.00 M-084
Cost of water KL 18.000 45.00 810.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 188.00 1128.00 P&M-009
Generator set 33 KVA hour 6.000 311.00 1866.00 P&M-079
Water tanker6 KL capacity hour 3.000 440.00 1320.00 P&M-060
d) Overhead charges @ 10% on (a+b+c) 6481.42
e) Contractor's profit @ 10% on (a+b+c+d) 7129.56
Cost for 15 cum = a+b+c+d+e 78425.19
Rate per cum = (a+b+c+d+e)/15 5228.35 2911.00
say 5228.00 79.59
Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.2 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Labour for laying Reinforced cement concrete pipe
NP4/NP3/prestressed concrete pipe for culverts on first class
bedding of granular material /cc M-15 in single row
including fixing collar with cement mortar 1:2,and cost of
granular bedding but excluding excavation, protection works,
backfilling, concrete and masonry work in head wall and
parapet,cost of pipe and cost of CC bedding.

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
(I) With 1st class bedding of granular material
A)1000 mm dia
a) Labour
Mate day 0.180 356.65 64.20 L-12
Mason day 0.500 458.55 229.28 L-11
Mazdoor day 4.000 244.56 978.24 L-13
b) Material
Sand at site cum 0.070 950.00 66.50 M-005
Cement at site tonne 0.050 7200.00 360.00 M-084
Granular material passing 5.6 mm sieve for bedding cum 4.500 698.00 3141.00 M-009
c) Overhead charges @ 10% on (a+b) 483.92
d) Contractor's profit @ 10% on (a+b+c) 532.31
Cost for 12.5 metres = a+b+c+d 5855.45
Rate per metre = (a+b+c+d)/12.5 468.44 276.00
say 468.00 69.57

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-9

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec
9.2 B)1200 mm dia
a) Labour
Mate day 0.280 356.65 99.86 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 6.000 244.56 1467.36 L-13
b) Material
Sand at site cum 0.090 950.00 85.50 M-005
Cement at site tonne 0.070 7200.00 504.00 M-084
Granular material passing 5-6 mm sieve for class cum 5.000 698.00 3490.00 M-009
bedding
c) Overhead charges @ 10% on (a+b) 610.53
d) Contractor's profit @ 10% on (a+b+c) 671.58
Cost for 12.5 metres = a+b+c+d 7387.38
Rate per metre= (a+b+c+d)/12.5 590.99 337.00
say 591.00 75.37
(I) With 1st class bedding of cc M-15
A)1000 mm dia
a) Labour
Mate day 0.180 356.65 64.20 L-12
Mason day 0.500 458.55 229.28 L-11
Mazdoor day 4.000 244.56 978.24 L-13
b) Material
Sand at site cum 0.070 950.00 66.50 M-005
Cement at site tonne 0.050 7200.00 360.00 M-084

c) Overhead charges @ 10% on (a+b) 169.82


d) Contractor's profit @ 10% on (a+b+c) 186.80
Cost for 12.5 metres = a+b+c+d 2054.84
Rate per metre = (a+b+c+d)/12.5 164.39 76.00
say 164.00 115.79
1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec
9.2 B)1200 mm dia
a) Labour
Mate day 0.280 356.65 99.86 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 6.000 244.56 1467.36 L-13
b) Material
Sand at site cum 0.090 1440.50 129.65 M-005
Cement at site tonne 0.070 12.00 0.84 M-084
c) Overhead charges @ 10% on (a+b) 215.63
d) Contractor's profit @ 10% on (a+b+c) 237.19
Cost for 12.5 metres = a+b+c+d 2609.07
Rate per metre= (a+b+c+d)/12.5 208.73 80.00

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-9

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 209.00 161.25
1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec
9.3 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Labour for laying Reinforced cement concrete pipe
NP4/NP3/prestressed concrete pipe for culverts on first class
bedding of granular material /cc M-15 in double row
including fixing collar with cement mortar 1:2,and cost of
granular bedding but excluding excavation, protection works,
backfilling, concrete and masonry work in head wall and
parapet,cost of pipe and cost of CC bedding.

Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
(I) With 1st class bedding of granular material
1000 mm dia
a) Labour
Mate day 0.360 356.65 128.39 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 8.000 244.56 1956.48 L-13
b) Material
Sand at site cum 0.140 950.00 133.00 M-005
Cement at site tonne 0.100 7200.00 720.00 M-084
Granular material passing 5-6 mm sieve for class cum 12.500 698.00 8725.00 M-009
bedding
c) Overhead charges @ 10% on (a+b) 339.64
d) Contractor's profit @ 10% on (a+b+c) 1246.11
Cost for 12.5 metres = a+b+c+d 13707.17
Rate per metre = (a+b+c+d)/12.5 1096.57 658.00
1. In case of cement craddle bedding, quantity of PCC M15 say 1097.00 66.72
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec
9.3 1200 mm dia
a) Labour
Mate day 0.560 356.65 199.72 L-12
Mason day 6.000 458.55 2751.30 L-11
Mazdoor day 20.000 244.56 4891.20 L-13
b) Material
Sand at site cum 0.200 950.00 190.00 M-005
Cement at site tonne 0.140 7200.00 1008.00 M-084

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-9

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Granular material passing 5-6 mm sieve for class cum 13.750 698.00 9597.50
bedding
c) Overhead charges @ 10% on (a+b) 904.02
d) Contractor's profit @ 10% on (a+b+c) 1954.17
Cost for 12.5 metres = a+b+c+d 21495.92
Rate per metre= (a+b+c+d)/12.5 1719.67 1665.00
1. In case of cement craddle bedding, quantity of PCC M15 say 1720.00 3.30
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec
(I) With 1st class bedding of cc M-15
1000 mm dia
a) Labour
Mate day 0.360 356.65 128.39 L-12
Mason day 1.000 458.55 458.55 L-11
Mazdoor day 8.000 244.56 1956.48 L-13
b) Material
Sand at site cum 0.140 950.00 133.00 M-005
Cement at site tonne 0.100 7200.00 720.00 M-084
c) Overhead charges @ 10% on (a+b) 339.64
d) Contractor's profit @ 10% on (a+b+c) 373.61
Cost for 12.5 metres = a+b+c+d 4109.67
Rate per metre = (a+b+c+d)/12.5 328.77 152.00
1. In case of cement craddle bedding, quantity of PCC M15 say 329.00 116.45
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec
9.3 1200 mm dia
a) Labour
Mate day 0.560 356.65 199.72 L-12
Mason day 6.000 458.55 2751.30 L-11
Mazdoor day 20.000 244.56 4891.20 L-13
b) Material
Sand at site cum 0.200 950.00 190.00 M-005
Cement at site tonne 0.140 111.00 15.54 M-084
c) Overhead charges @ 10% on (a+b) 804.78
d) Contractor's profit @ 10% on (a+b+c) 885.25
Cost for 12.5 metres = a+b+c+d 9737.79
Rate per metre= (a+b+c+d)/12.5 779.02
1. In case of cement craddle bedding, quantity of PCC M15 say 779.00
is to be calculated as per design and priced separately and
added .

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-9

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respec

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

CHAPTER- 10
MAINTENANCE OF ROADS
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

10.1 Restoration of Rain Cuts


Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.130 1836.00 238.68 P&M-026

Tipper ( L is average lead in km for borrow earth) tonne.km 12 x L 3.50 126.00 Lead =3
km & P&M-
058
Add 10 per cent of cost of carriage towards loading and 12.60
unloading charges.
Plate compactor hour 0.500 218.00 109.00 P&M-086
c) Overhead charges @ 10% on (a+b) 100.39
d) Contractor's profit @ 10% on (a+b+c) 110.43
Cost for 10 cum = a+b+c+d 1214.76
Rate per cum = (a+b+c+d)/10 121.48 76.00
say 121.00 59.21
Only 75 per cent of fresh material has been provided as 25
per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of there in cuts
10.2 Maintenance of Earthen Shoulder (filling with fresh
soil)
Making up loss of material/ irregularities on shoulder
( Average 150mm filling ) to the design level by adding fresh
approved soil and compacting it with appropriate equipment.

Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quantity of fresh material = 15 cum
a) Labour
Mate day 0.180 356.65 64.20 L-12
Mazdoor day 4.500 244.56 1100.52 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.250 1836.00 459.00 P&M-026

Tipper ( L is average lead in km for borrow earth) tonne.km 24xL 3.50 252.00 #REF!
Add 10 per cent of cost of transportation to cover cost of 25.20
loading and unloading
Plate compactor @ 25 sqm per hour hour 12.000 218.00 2616.00 P&M-086
c) Overhead charges @ 10% on (a+b) 451.69

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

d) Contractor's profit @ 10% on (a+b+c) 496.86


Cost for 100 sqm = a+b+c+d 5465.47
Rate per sqm = (a+b+c+d)100 54.65 45.00
say 55.00 22.22
10.3 Maintenance of Earth Shoulder (stripping excess soil)

Stripping excess soil from the shoulder surface to achieve


the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate day 0.100 356.65 35.67 L-12
Mazdoor day 2.500 244.56 611.40 L-13
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 218.00 872.00 P&M-086
c) Overhead charges @ 10% on (a+b) 151.91
d) Contractor's profit @ 10% on (a+b+c) 167.10
Cost for 100 sqm = a+b+c+d 1838.07
Rate per sqm on = (a+b+c+d)100 18.38 14.00
say 18.00 28.57
The earth stripped from earthen shoulders to be dumped on
the side slopes locally for disposal.
10.4 Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as p
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
(i)'using Bitumen emulsion CSS-1h
a) Labour
Mate Day 3.760 356.65 1341.00 L-12
Mazdoor Day 90.000 244.56 22010.40 L-13
Mazdoor skilled Day 4.000 356.65 1426.60 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 22823.00 136938.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 850.00 38250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 924.00 11088.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 1510.00 278595.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 1916.00 176751.00 M-051
Bitumen 60/70 tonne 14.970 32627.00 488426.19 M-077
Bitumen emulsion for tack coat including vertical sides tonne 2.460 38530.00 94783.80 M-073
of pot hole.

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

d) Overhead charges @ 10% on (a+b+c) 125222.00


e) Contractor's profit @ 10% on (a+b+c+d) 137744.20
Cost for 10250 sqm = a+b+c+d+e 1515186.19
Rate per sqm = (a+b+c+d+e)/10250 147.82 103.00
say 148.00 43.69
(ii)'using Bitumen emulsion CSS-1( IS:8887-2004 )
a) Labour
Mate Day 3.760 356.65 1341.00 L-12
Mazdoor Day 90.000 244.56 22010.40 L-13
Mazdoor skilled Day 4.000 356.65 1426.60 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 22823.00 136938.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 850.00 38250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 924.00 11088.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 1510.00 278595.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 1916.00 176751.00 M-051
Bitumen 60/70 tonne 14.970 32627.00 488426.19 M-077
Bitumen emulsion for tack coat including vertical sides tonne 2.460 36950.00 90897.00 M-074
of pot hole.
d) Overhead charges @ 10% on (a+b+c) 124833.32
e) Contractor's profit @ 10% on (a+b+c+d) 137316.65
Cost for 10250 sqm = a+b+c+d+e 1510483.16
Rate per sqm = (a+b+c+d+e)/10250 147.36 106.00
say 147.00 38.68
(iii)'using Bitumen emulsion RS-1
a) Labour
Mate Day 3.760 356.65 1341.00 L-12
Mazdoor Day 90.000 244.56 22010.40 L-13
Mazdoor skilled Day 4.000 356.65 1426.60 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 22823.00 136938.00 P&M-021
Tipper 10 tonnes capacity hour 45.000 850.00 38250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 924.00 11088.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm cum 184.500 1510.00 278595.00 M-052
Crushed stone aggregates nominal size 11.2mm cum 92.250 1916.00 176751.00 M-051
Bitumen 60/70 tonne 14.970 32627.00 488426.19 M-077
Bitumen emulsion for tack coat including vertical sides tonne 2.460 26260.00 64599.60 M-075
of pot hole.
d) Overhead charges @ 10% on (a+b+c) 122203.58

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

e) Contractor's profit @ 10% on (a+b+c+d) 134423.94


Cost for 10250 sqm = a+b+c+d+e 1478663.31
Rate per sqm = (a+b+c+d+e)/10250 144.26 102.00
say 144.00 41.18
10.5 Filling Pot-holes and Patch Repairs with Bituminous
concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as p
Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a) Labour
Mate Day 2.920 356.65 1041.42 L-12
Mazdoor Day 70.000 244.56 17119.20 L-13
Mazdoor skilled Day 3.000 356.65 1069.95 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 435.00 2610.00 P&M-001
HMP 100-110 TPH Capacity hour 6.000 16575.00 99450.00 P&M-022
Tipper 10 tonnes capacity hour 45.000 850.00 38250.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 924.00 11088.00 P&M-044
c) Material
I) Bitumen tonne 22.500 31681.00 712822.50 M-078
ii) Bitumen emulsion for tack coat . tonne 1.180 40572.00 47874.96 M-080
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent cum 99.750 1758.00 175360.50 M-051,M-
052,M-053
and M-054

10-5 mm 23 per cent cum 65.550 1084.00 71056.20 M-025


5mm and below40 per cent cum 114.000 1045.00 119130.00 M-021,M-
022 and
M-024
Add 5 per cent for wastage 18277.34
or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent cum 85.500 1713.00 146461.50 M-051 and
M-052
10-5 mm 25 per cent cum 71.250 1084.00 77235.00 M-025
5 mm and Below43 per cent cum 122.550 1045.00 128064.75 M-021,M-
022 and
M-024
Filler 2 per cent tonne 9.000 5900.00 53100.00 M-188
Add 5 per cent for wastage 20243.06

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Any one of the above alternatives of aggregate i.e. 19mm or


13mm nominal size may be adopted as per approved
design.
10.5 for grading I Material
d) Overhead charges @ 10% on (a+b+c) 131515.01
e) Contractor's profit @ 10% on (a+b+c+d) 144666.51
Cost for 4900 cum = a+b+c+d+e 1591331.58
Rate per cum = (a+b+c+d+e)/4900 324.76 265.00
say 325.00 22.64
10.5 for grading II Material
d) Overhead charges @ 10% on (a+b+c) 135643.03
e) Contractor's profit @ 10% on (a+b+c+d) 149207.34
Cost for 4900 cum = a+b+c+d+e 1641280.71
Rate per cum = (a+b+c+d+e)/4900 334.96 279.00
say 335.00 20.07
For detailed working of quantities of aggregates, refer item
5.8 of chapter 5
10.6 Crack Filling

Filling of crack using slow - curing bitumen emulsion and


applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Material
Slow-curing bitumen emulsion ( CSS-1,IS:8887-2004 ) Kg 33.000 37.00 1221.00 M-080

Stone crusher dust cum 0.020 698.00 13.96 M-021


c) Overhead charges @ 10% on (a+b) 149.38
d) Contractor's profit @ 10% on (a+b+c) 164.32
Cost for 500sqm = a+b+c+d 1807.48
Rate per meter = (a+b+c+d+e)/500 3.61 3.00
say 4.00 33.33
10.7 Dusting
Applying crusher dust to areas of road where bleeding
of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Material

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Stone crusher dust finer than 3mm with not more cum 6.250 698.00 4362.50 M-021
than 10 per cent passing 0.075 sieve.
c) Overhead charges @ 10% on (a+b) 488.02
d) Contractor's profit @ 10% on (a+b+c) 536.82
Cost for 3500sqm = a+b+c+d 5904.98
Rate per meter = (a+b+c+d)/3500 1.69 0.59
say 1.69 186.44
10.8 Fog Seal sqm 44.00 Item 5.17
Crack Prevention courses.
i) Stress Absorbing Membrane (SAM) crack width less than 6 sqm 62.00 Item 5.21
mm Case-I
ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to sqm 71.00 Item 5.21
9 mm Case-II
iii) Stress Absorbing Membrane (SAM) crack width above 9 mm sqm 92.00 Item 5.21
and cracked area above 50 per cent Case-IV
Bitumen Impregnated Geotextile sqm 198.00 Item 5.21
Case-IV
10.8 Slurry Seal
i) 5 mm thickness sqm 71.00 Item 5.15
Case-I
ii) 3 mm thickness sqm 49.00 Item 5.15
Case-II
iii) 1.5 mm thickness sqm 30.00 Item 5.15
Case-III
10.8 Surface Dressing for maintenance works.
19 mm nominal chipping size sqm 86.00 Item 5.9
Case-I
13 mm nominal size chipping sqm 65.00 Item 5.9
Case-II
The above mentioned items have already been included in
chapter 5.
10.9 Repair of Joint Grooves with Epoxy Mortar
Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 0.500 244.56 122.28 L-13
Chiseller day 0.500 285.32 142.66 L-05
b) Material
Epoxy primer kg 2.500 395.00 987.50 M-098-3
Epoxy compound with accessories for preparing epoxy kg 10.000 605.00 6050.00 M-098_1
mortar
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 435.00 21.75 P&M-001
d) Overhead charges @ 10% on (a+b+c) 733.85
e) Contractor's profit @ 10% on (a+b+c+d) 807.23
Cost for 10 metres = a+b+c+d+e 8879.53

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Rate per metre = (a+b+c+d+e)/10 887.95 401.00


say 888.00 121.45
10.10 Repair of old Joints Sealant
Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 0.500 244.56 122.28 L-13
b) Material
Primer kg 0.250 158.00 39.50 M-146
Sealant kg 1.000 590.00 590.00 M-120
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 435.00 21.75 P&M-001
d) Overhead charges @ 10% on (a+b+c) 78.78
e) Contractor's profit @ 10% on (a+b+c+d) 86.66
Cost for 10 metres = a+b+c+d+e 953.23
Rate per metre = (a+b+c+d+e)/10 95.32 75.00
say 95.00 26.67
10.11 Hill Side Drain Clearance
Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Overhead charges @ 10% on (a+b) 27.31
c) Contractor's profit @ 10% on (a+b) 30.04
Cost for 10 metres = a+b+c 330.44
Rate per metre = (a+b+c)/10 33.04 13.00
say 33.00 153.85
10.12 Land Slide Clearance in soil
Clearance of land slides in soil and ordinary rock by a bull-
dozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a) Labour

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mate day 0.040 356.65 14.27 L-12


Mazdoor day 1.000 244.56 244.56 L-13
b) Machinery
Dozer 180 HP @ 60 cum per hour hour 1.670 3194.00 5333.98 P&M-014
c) Overhead charges @ 10% on (a+b) 559.28
d) Contractor's profit @ 10% on (a+b+c) 615.21
Cost for 100 cum = a+b+c+d 6767.30
Rate per cum = (a+b+c+d)/100 67.67 66.00
say 68.00 3.03
Land Slide clearance involves pushing of loose earth slided
on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted h
10.13 Landslide Clearance in Hard Rock Requiring Blasting

Clearing of land slide in hard rock requiring blasting for 50


per cent of the boulders and disposal of the same on the
valley side.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.090 356.65 32.10 L-12
Mazdoor day 1.500 244.56 366.84 L-13
Driller day 0.750 356.65 267.49 L-06
Blaster day 0.070 356.65 24.97 L-03
b) Machinery
Dozer D 80 A-12,180 HP @ 60 cum per hour hour 1.670 3194.00 5333.98 P&M-014
Air compressor 250 cfm with two jack hammer hour 2.500 435.00 1087.50 P&M-001
c) Materials
Gelatine 80 per cent @ 35 kg per 100 cum kg 17.500 72.00 1260.00 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 70.000 15.00 1050.00 M-097 /100
of 125 gms each
c) Overhead charges @ 10% on (a+b) 942.29
d) Contractor's profit @ 10% on (a+b+c) 1036.52
Cost for 100 cum = a+b+c+d+e 11401.67
Rate per cum = (a+b+c+d+e)/100 114.02 100.00
say 114.00 14.00
Credit for the rock if found acceptable as construction
material shall be afforded
10.14 Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-10

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour hour 5.880 3194.00 18780.72 P&M-014
c) Overhead charges @ 10% on (a+b) 1929.84
d) Contractor's profit @ 10% on (a+b+c) 2122.82
Cost for 5000 cum = a+b+c+d 23351.03
Rate per cum = (a+b+c+d)/5000 4.67 5.00
say 5.00 0.00
i) Labour provided will not be cutting the snow. They will be
guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep
10.15 Snow Clearance on Roads with Snow Blowers
Snow clearance from road surface by a snow blower and
disposing on the valley side.
Unit = cum
Taking output = 3600 cum
a) Labour
Mate day 0.080 356.65 28.53 L-12
Mazdoor day 2.000 244.56 489.12 L-13
b) Machinery
Snow blower equipment 140 HP @ 600 cum per hour hour 6.000 1000.00 6000.00 P&M-087

c) Overhead charges @ 10% on (a+b) 651.77


d) Contractor's profit @ 10% on (a+b+c) 716.94
Cost for 3600 cum (a+b+c+d) 7886.36
Rate per cum = (a+b+c+d)/3600 2.19
say 2.00

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

CHAPTER-11
HORTICULTURE
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
11.1 Spreading of Sludge Farm Yard Manure or/and good
Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 356.65 14.27 L-12
Mazdoor day 1.000 244.56 244.56 L-13
b) Overhead charges @ 10% on (a) 25.88
c) Contractor's profit @ 10% on (a+b) 28.47
Cost for 15 cum= a+b+c 313.18
Rate per cum = (a+b+c)/15 20.88 8.00
say 21.00 162.50
11.2 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 356.65 60.63 L-12
Mazdoor for grassing day 0.750 244.56 183.42 L-13
Mazdoor for maintenance for 30 days day 1.000 244.56 244.56 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 440.00 220.00 P&M-060
c) Material
Doob grass kg 100.000 18.00 1800.00 M-112
d) Overhead charges @ 10% on (a+b+c) 250.86
e) Contractor's profit @ 10% on (a+b+c+d) 275.95
Cost for 100 sqm = a+b+c+d+e 3035.42
Rate per sqm= (a+b+c+d+e)/100 30.35 21.00
say 30.00 42.86
11.2 In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 356.65 78.46 L-12
Mazdoor for grassing. day 1.250 244.56 305.70 L-13
for maintenance for 30 days day 1.000 244.56 244.56 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 440.00 330.00 P&M-060
c) Material
Doob grass kg 200.000 18.00 3600.00 M-112
d) Overhead charges @ 10% on (a+b+c) 455.87
e) Contractor's profit @ 10% on (a+b+c+d) 501.46
Cost for 100 sqm = a+b+c+d+e 5516.05
Rate per sqm = (a+b+c+d+e)/100 55.16 40.00
say 55.00 37.50

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
11.3 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.150 356.65 53.50 L-12
Mazdoor for preparation of ground day 0.500 244.56 122.28 L-13
Mali for fetching doobs grass roots and grassing at 15 day 1.000 356.65 356.65 L-09
cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 440.00 220.00 P&M-060
Tractor with tiller hour 0.010 323.00 3.23 P&M-053
c) Material
Supply of farm yard manure at site of work cum 0.180 60.00 10.80 M-167
Fine grass kg 100.000 27.00 2700.00 M-113
d) Overhead charges @ 10% on (a+b+c) 346.65
e) Contractor's profit @ 10% on (a+b+c+d) 381.31
Cost for 100 sqm = a+b+c+d+e 4194.41
Rate per sqm = (a+b+c+d+e)/100 41.94 30.00
say 42.00 40.00
11.4 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 356.65 3566.50 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 440.00 6600.00 P&M-060
c) Material
Cost of water KL 90.000 45.00 4050.00 M-189
d) Overhead charges @ 10% on (a+b+c) 1421.65
e) Contractor's profit @ 10% on (a+b+c+d) 1563.82
Cost for 100 sqm = a+b+c+d+e 17201.97
Rate per sqm = (a+b+c+d+e)/100 172.02 104.00
say 172.00 65.38

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
11.5 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 356.65 89.16 L-12
Mazdoor for preparation of ground day 1.000 244.56 244.56 L-13
Mali for fetching doobs grass roots hedges and day 1.500 356.65 534.98 L-09
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 440.00 220.00 P&M-060
Tractor with tiller hour 0.010 323.00 3.23 P&M-053
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 60.00 36.00 M-167
per 100 sqm
Fine grass kg 100.000 27.00 2700.00 M-113
d) Overhead charges @ 10% on (a+b+c) 382.79
e) Contractor's profit @ 10% on (a+b+c+d) 421.07
Cost for 100 sqm = a+b+c+d+e 4631.79
Rate per sqm = (a+b+c+d+e)/100 46.32 32.00
say 46.00 43.75
11.6 Maintenance of Lawns with Fine Grassing for the First
Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 356.65 3566.50 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 440.00 8800.00 P&M-060
c) Material
Cost of water KL 60.000 45.00 2700.00 M-189
d) Overhead charges @ 10% on (a+b+c) 1506.65
e) Contractor's profit @ 10% on (a+b+c+d) 1657.32
Cost for 100 sqm = a+b+c+d+e 18230.47
Rate per sqm = (a+b+c+d+e)/100 182.30 111.00
say 182.00 63.96

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
11.7 Planting and Maintaining of Permanent Hedges
Planting permanent hedges including digging of
trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100metre
a) Labour
Mate day 1.400 356.65 499.31 L-12
Mazdoor for digging of trench 60 cm wide and 45 cm day 10.000 244.56 2445.60 L-13
deep
Mazdoor for refilling the excavated earth mixed with day 4.000 244.56 978.24 L-13
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position
b) Machinery
Water tanker6 KL capacity hour 0.500 440.00 220.00 P&M-060
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 12.00 8160.00 M-116
Supply of farm yard manure at site of work cum 4.670 60.00 280.20 M-167
Pesticide kg 0.250 504.00 126.00 M-136
Cost of water KL 3.000 45.00 135.00 M-189
d) Overhead charges @ 10% on (a+b+c) 1284.44
e) Contractor's profit @ 10% on (a+b+c+d) 1412.88
Cost for 100 metres = a+b+c+d+e 15541.66
Rate per metre = a+b+c+d+e)/100 155.42 66.00
say 155.00 134.85
Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 3.000 356.65 1069.95 L-12
Mazdoor day 30.000 244.56 7336.80 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 440.00 2200.00 P&M-060
c) Material
Manure sludge/Farm yard manure cum 2.000 60.00 120.00 M-167
Pesticide kg 0.500 504.00 252.00 M-136
Cost of water KL 30.000 45.00 1350.00 M-189
Cost of hedge plants @ 10 per cent casualty each 68.000 12.00 816.00 M-116
d) Overhead charges @ 10% on (a+b+c) 1314.48
e) Contractor's profit @ 10% on (a+b+c+d) 1445.92
Cost for 100 metres = a+b+c+d+e 15905.15
Rate per metre = a+b+c+d+e)/100 159.05 76.00

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 159.00 109.21

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
11.8 Planting and Maintaining of Flowering Plants and
Shrubs
Planting flowering plants and shrubs in central verge

Unit = Running metres 200 plants and 800 shrubs in


two rows in one km length of road where width of
verge is 3m and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 356.65 427.98 L-12
Mazdoor day 12.000 244.56 2934.72 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 440.00 2640.00 P&M-060
c) Material
Plants each 200.000 31.00 6200.00 M-100
Shrubs each 800.000 12.00 9600.00 M-166
Manure sludge/Farm yard manure cum 63.640 60.00 3818.40 M-167
Pesticide kg 0.500 504.00 252.00 M-136
Cost of water KL 36.000 45.00 1620.00 M-189
d) Overhead charges @ 10% on (a+b+c) 2749.31
e) Contractor's profit @ 10% on (a+b+c+d) 3024.24
Rate per Km = (a+b+c+d+e) 33266.65 24866.00
say 33267.00 33.79
11.8 Maintenance of flowering plants and shrubs in central
verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 356.65 12839.40 L-12
Mazdoor day 365.000 244.56 89264.40 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 440.00 39600.00 P&M-060
c) Material
Manure Sludge / farm yard manure at site cum 10.000 60.00 600.00 M-167
Cost of water KL 180.000 45.00 8100.00 M-189
Replacement of casualties @ 10 per cent
Plants each 20.000 31.00 620.00 M-100
Shrubs each 80.000 12.00 960.00 M-166
Pesticides kg 1.500 504.00 756.00 M-136
d) Overhead charges @ 10% on (a+b+c) 15273.98
e) Contractor's profit @ 10% on (a+b+c+d) 16801.38
Rate per Km for one year = (a+b+c+d+e) 184815.16 90647.00
say 184815.00 103.88
11.9 Planting of Trees and their Maintenance for one Year

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the pla
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 356.65 606.31 L-12
Mazdoor for planting day 2.000 244.56 489.12 L-13
Mazdoor for maintenance for one year day 15.000 244.56 3668.40 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 440.00 880.00 P&M-060
c) Material
Sapling 2 m high 25 mm dia each 10.000 42.00 420.00 M-160
Farm yard manure cum 0.940 10.00 9.40 M-167
Pesticide kg 0.500 504.00 252.00 M-136
Cost of water KL 12.000 45.00 540.00 M-189
d) Overhead charges @ 10% on (a+b+c) 686.52
e) Contractor's profit @ 10% on (a+b+c+d) 755.17
Cost for 10 trees = a+b+c+d+e 8306.92
Rate per trees = (a+b+c+d+e)/10 830.69 404.00
say 831.00 105.69
11.10 Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, in
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 356.65 42.80 L-12
Mazdoor day 3.000 244.56 733.68 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 440.00 220.00 P&M-060
c) Material
Cost of water KL 3.000 45.00 135.00 M-189
d) Overhead charges @ 10% on (a+b+c) 113.15
e) Contractor's profit @ 10% on (a+b+c+d) 124.46
Cost for 100 sqm = a+b+c+d+e 1369.09
Rate per sqm = (a+b+c+d+e) 13.69 7.00
say 14.00 100.00
11.14 Half Brick Circular Tree Guard, in 2nd Class Brick,
internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermedi
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 356.65 17.83 L-12
Mason day 0.250 458.55 114.64 L-11
Mazdoor day 0.250 244.56 61.14 L-13
b) Material
Brick 2nd class including carriage each 230.000 8.00 1840.00 M-082
Cement mortar 1:6 cum 0.025 3448.00 86.20 Item 12.6 (D)

c) Overhead charges @ 10% on (a+b) 211.98


d) Contractor's profit @ 10% on (a+b+c) 233.18
Rate per tree Guard = a+b+c+d 2564.97 959.00
say 2565.00 167.47
11.15 Edging with 2nd Class Bricks, Laid Dry Lengthwise
Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres

Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 356.65 0.71 L-12
Mason day 0.050 458.55 22.93 L-11
Mazdoor day 0.050 244.56 12.23 L-13
b) Material
Brick 2nd class including carriage each 50.000 8.00 400.00 M-082
c) Overhead charges @ 10% on (a+b) 43.59
d) Contractor's profit @ 10% on (a+b+c) 47.95
Cost for 10 metre = a+b+c+d 527.40
Rate per metre = (a+b+c+d)/10 52.74 19.00
say 53.00 178.95
11.16 Making Tree Guard 53 cm dia and 1.3 m High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete i
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 356.65 7.13 L-12

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Blacksmith day 0.150 458.55 68.78 L-02
Mazdoor day 0.070 244.56 17.12 L-13
b) Material
Empty bitumen drum each 1.000 66.00 66.00 M-172
MS sheet 50 x 0.5 mm kg 0.650 60.00 39.00 M-179 /1000
Rivets 6 mm dia and 10 mm in length each 22.000 4.50 99.00 M-158
d) Overhead charges @ 10% on (a+b+c) 29.70
e) Contractor's profit @ 10% on (a+b+c+d) 32.67
Rate for each tree guard = a+b+c+d 359.41 188.00
say 359.00 90.96
11.17 Making Tree Guard 53 cm dia and 2 Metre High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted t
Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 356.65 14.27 L-12
Blacksmith day 0.200 458.55 91.71 L-02
Mazdoor 0.200 244.56 48.91 L-13
b) Material
Empty bitumen drum each 1.500 66.00 99.00 M-172
MS sheet50 x 0.5 mm kg 0.650 60.00 39.00 M-179 /1000
Rivets 6 mm dia and 10 mm in length each 50.000 4.50 225.00 M-158
MSplate30 x 3 mm kg 1.300 60.00 78.00 M-179 /1000
c) Overhead charges @ 10% on (a+b) 59.59
d) Contractor's profit @ 10% on (a+b+c) 65.55
Rate for each tree guard = a+b+c+d 721.02 372.00
say 721.00 93.82
11.18 Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but with
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 356.65 160.49 L-12
Blacksmith/ welder for cutting to design and shape and day 2.000 458.55 917.10 L-02
jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 244.56 611.40 L-13
b) Material
Angle, tees, channels etc quintal 1.050 6000.00 6300.00 M-179 /10

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Deduct the cost of scrap quintal 0.050 (2000.00) (100.00) M-179/10/3
Add 5 per cent of cost of material for welding rods and other 310.00
welding accessories
c) Overhead charges @ 10% on (a+b) 819.90
d) Contractor's profit @ 10% on (a+b+c) 901.89
Rate per quintal = a+b+c+d 9920.78 5344.00
say 9921.00 85.65
11.19 Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts i
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 356.65 17.83 L-12
Blacksmith day 0.250 458.55 114.64 L-02
Mazdoor day 0.250 244.56 61.14 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 60.00 1152.00 M-179 /1000
MS iron 25 x 3 mm kg 9.600 60.00 576.00 M-179 /1000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 323.00 12.92 P&M-053
d) Painting
Painting two coats including priming sqm 1.770 73.00 129.21 Item 8.9
e) Overhead charges @ 10% on (a+b+c) 193.45
f) Contractor's profit @ 10% on (a+b+c+e) 212.80
Rate per tree guard =a+b+c+d+e+f 2469.99 1375.00
say 2470.00 79.64
1 The items of excavation and concreting to be measured
and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
11.20 Tree Guard with MS Angle Iron and Steel Wire
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one
a) Labour
Mate day 0.050 356.65 17.83 L-12
Blacksmith day 0.250 458.55 114.64 L-02
Welder day 0.250 458.55 114.64 L-02
Mazdoor day 0.250 244.56 61.14 L-13

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 60.00 810.00 M-179 /1000
MS iron 25 x 3 mm kg 18.000 60.00 1080.00 M-179 /1000
Steel wire 3 mm dia kg 6.000 46.00 276.00 M-192
Add 5 per cent of cost of material for riveting, bolting 108.30
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 323.00 12.92 P&M-053
d) Painting
Painting two coats including priming sqm 1.500 73.00 109.50 Item 8.9
e) Overhead charges @ 10% on (a+b+c) 259.55
f) Contractor's profit @ 10% on (a+b+c+e) 285.50
Rate per tree guard = a+b+c+d+e+f 3250.02 1886.00
say 3250.00 72.32
11.21 Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapl
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 2.500 356.65 891.63 L-12
Mazdoor day 25.000 244.56 6114.00 L-13
ii) For Maintenance for one year
Mate day 5.000 356.65 1783.25 L-12
Mazdoor day 50.000 244.56 12228.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 3194.00 31940.00 P&M-014
Water tanker6 KL capacity (for planting) hour 3.000 440.00 1320.00 P&M-060
Water tanker6 KL capacity (for maintenance) hour 25.000 440.00 11000.00 P&M-060
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 50.00 14500.00 M-160 x 0.8
Add 10 per cent of sapling each 29.000 5.00 145.00 M-160 x 0.8
Decayed farm yard/sludge manure (planting) cum 60.900 60.00 3654.00 M-167
Decayed farm yard/sludge manure (maintenance) cum 4.000 60.00 240.00 M-167
Pesticides for planting kg 0.500 504.00 252.00 M-136
Pesticides for maintenance kg 1.500 504.00 756.00 M-136
Cost of water KL 18.000 45.00 810.00 M-189
d) Overhead charges @ 10% on (a+b+c) 8563.39
e) Contractor's profit @ 10% on (a+b+c+d) 9419.73
Rate per hectare = a+b+c+d+e 103616.99
say 103617.00

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-11

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost of fencing to be provided as per size of plot and
approved design, measured and paid separately

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

CHAPTER-12
FOUNDATIONS
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.1 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(I) Without dewatering
12.1 I A (I) Depth upto 3 m
(i)
a) Labour
Mate day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
b) Overhead charges @ 20 % on (a) 181.18
c) Contractor's profit @ 10% on (a+b) 108.71
Cost for 10 cum = a+b+c 1195.78
Rate per cum = (a+b+c)/10 119.58 47.00
say 120.00 155.32
1. Cost of dewatering may be added where required upto, 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 I A (I) Depth 3 m to 6 m
(ii)
a) Labour
Mate/Supervisor day 0.26 356.65 92.73 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
b) Overhead charges @ 20 % on (a) 238.65
c) Contractor's profit @ 10% on (a+b) 143.19
Cost for 10 cum = a+b+c 1575.09
Rate per cum = (a+b+c)/10 157.51 61.00
say 158.00 159.02
Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
12.1 I A (I) Depth above 6 m
(iii)
a) Labour
Mate/Supervisor day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
b) Overhead charges @ 20 % on (a) 310.59
c) Contractor's profit @ 10% on (a+b) 186.35
Cost for 10 cum = a+b+c 2049.90
Rate per cum = (a+b+c)/10 204.99 81.00
say 205.00 153.09
(II) With dewatering

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.1 I A (II) Depth upto 3 m
(i)
a) Labour
Mate day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
Cost of dewatering @ 10% of labour cost 90.59
b) Overhead charges @ 20 % on (a) 199.30
c) Contractor's profit @ 10% on (a+b) 119.58
Cost for 10 cum = a+b+c 1315.35
Rate per cum = (a+b+c)/10 131.54 52.00
say 132.00 153.85
1. Cost of dewatering may be added where required upto, 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 I A (II) Depth 3 m to 6 m
(ii)
a) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
Cost of dewatering @ 15% of labour cost 174.71
b) Overhead charges @ 20 % on (a) 267.88
c) Contractor's profit @ 10% on (a+b) 160.73
Cost for 10 cum = a+b+c 1768.04
Rate per cum = (a+b+c)/10 176.80 70.00
say 177.00 152.86
Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
12.1 I A (II) Depth above 6 m
(iii)
a) Labour
Mate/Supervisor day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
Cost of dewatering @ 20% of labour cost 310.59
b) Overhead charges @ 20 % on (a) 372.71
c) Contractor's profit @ 10% on (a+b) 223.63
Cost for 10 cum = a+b+c 2459.88
Rate per cum = (a+b+c)/10 245.99 97.00
say 246.00 153.61

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
B Mechanical Means
(I) Without dewatering
12.1 I B (I) Depth upto 3 m
(i)
Unit = cum
Taking output = 240 cum
a) Labour

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
c) Overhead charges @ 20 % on (a+b) 2617.32
d) Contractor's profit @ 10% on (a+b+c) 1570.39
Cost for 240 cum = a+b+c+d 17274.32
Rate per cum = (a+b+c+d)/240 71.98 50.00
say 72.00 44.00
Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
12.1 I B (I) Depth 3 m to 6 m
(ii)
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
c) Overhead charges @ 20 % on (a+b) 2617.32
d) Contractor's profit @ 10% on (a+b+c) 1570.39
Cost for 210 cum = a+b+c+d 17274.32
Rate per cum = (a+b+c+d)/210 82.26 57.00
say 82.00 43.86
Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 I B (I) Depth above 6m
(iii)
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
c) Overhead charges @ 20 % on (a+b) 2720.85
d) Contractor's profit @ 10% on (a+b+c) 1632.51
Cost for 180 cum = a+b+c+d 17957.62
Rate per cum = (a+b+c+d)/180 99.76 68.00
say 100.00 47.06
1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
(II) With dewatering
12.1 I B (II) Depth upto 3 m
(i)
Unit = cum
Taking output = 240 cum

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
Cost of dewatering @ 5% of (a+b) 654.33
c) Overhead charges @ 20 % on (a+b) 2748.19
d) Contractor's profit @ 10% on (a+b+c) 1648.91
Cost for 240 cum = a+b+c+d 18138.04
Rate per cum = (a+b+c+d)/240 75.58 52.00
say 76.00 46.15
Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
12.1 I B (II) Depth 3 m to 6 m
(ii)
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
Cost of dewatering @ 7.5% of (a+b) 981.50
c) Overhead charges @ 20 % on (a+b) 2813.62
d) Contractor's profit @ 10% on (a+b+c) 1688.17
Cost for 210 cum = a+b+c+d 18569.90
Rate per cum = (a+b+c+d)/210 88.43 61.00
say 88.00 44.26
Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 I B (II) Depth above 6m
(iii)
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
Cost of dewatering @ 10% of (a+b) 1360.43
c) Overhead charges @ 20 % on (a+b) 2720.85
d) Contractor's profit @ 10% on (a+b+c) 1768.55
Cost for 180 cum = a+b+c+d 19454.09
Rate per cum = (a+b+c+d)/180 108.08 74.00
say 108.00 45.95
1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.

12.1 II Ordinary Rock (not requiring blasting)


(I) Without dewatering
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.26 356.65 92.73 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
b) Overhead charges @ 20 % on (a) 263.11
c) Contractor's profit @ 10% on (a+b) 157.86
Cost for 10 cum = a+b+c 1736.50
Rate per cum = (a+b+c)/10 173.65 67.00
say 174.00 159.70
(I) With dewatering
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 356.65 71.33 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
Cost of dewatering @ 10% of labour cost 129.41
b) Overhead charges @ 20 % on (a) 284.71
c) Contractor's profit @ 10% on (a+b) 170.83
Cost for 10 cum = a+b+c 1879.08
Rate per cum = (a+b+c)/10 187.91 74.00
say 188.00 154.05
Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) Mechanical Means
(I) Without dewatering
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
c) Overhead charges @ 20 % on (a+b) 2513.79
d) Contractor's profit @ 10% on (a+b+c) 1508.27
Cost for 180 cum = a+b+c+d 16591.02
Rate per cum = (a+b+c+d)/180 92.17 65.00

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 92.00 41.54
(ii) With dewatering
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1836.00 11016.00 P&M-026
Cost of dewatering @ 10% of (a+b) 1256.90
c) Overhead charges @ 20 % on (a+b) 2513.79
d) Contractor's profit @ 10% on (a+b+c) 1633.96
Cost for 180 cum = a+b+c+d 17973.61
Rate per cum = (a+b+c+d)/180 99.85 71.00
say 100.00 40.85

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 Hard Rock ( requiring blasting )
Manual Means
(I) Without dewatering
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 356.65 124.83 L-12
Driller day 0.50 356.65 178.33 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. hour 1.00 435.00 435.00 P&M-001

c) Material
Blasting Material kg 3.50 72.00 252.00 M-104
Detonator electric each 14.00 15.00 210.00 M-097/100
d) Overhead charges @ 20 % on (a+b+c) 649.16
e) Contractor's profit @ 10% on (a+b+c+d) 389.50
Cost for 10 cum = a+b+c+d+e 4284.45
Rate per cum = (a+b+c+d+e)/10 428.44 212.00
say 428.00 101.89
(ii) With dewatering
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 356.65 124.83 L-12
Driller day 0.50 356.65 178.33 L-06
Blaster day 0.25 356.65 89.16 L-03

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. hour 1.00 435.00 435.00 P&M-001

c) Material
Blasting Material kg 3.50 72.00 252.00 M-104
Detonator electric each 14.00 15.00 210.00 M-097/100
Cost of dewatering @ 10% of (a+b) 278.38
d) Overhead charges @ 20 % on (a+b+c) 649.16
e) Contractor's profit @ 10% on (a+b+c+d) 417.33
Cost for 10 cum = a+b+c+d+e 4590.67
Rate per cum = (a+b+c+d+e)/10 459.07 225.00
say 459.00 104.00

Cost of dewatering @ 10 per cent of (a+b) may be


added, where required Assessment for dewatering shall be
made as per site conditions.
12.1 Hard Rock ( blasting prohibited )
(I) Without dewatering
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 356.65 71.33 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 435.00 2610.00 P&M-001
breaker
c) Overhead charges @ 20 % on (a+b) 780.83
d) Contractor's profit @ 10% on (a+b+c) 468.50
Cost for 10 cum = a+b+c+d 5153.45
Rate per cum = (a+b+c+d)/10 515.35 292.00
say 515.00 76.37
(ii) With dewatering
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 356.65 71.33 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 435.00 2610.00 P&M-001
breaker
Cost of dewatering @ 10% of (a+b) 390.41
c) Overhead charges @ 20 % on (a+b) 780.83
d) Contractor's profit @ 10% on (a+b+c) 507.54
Cost for 10 cum = a+b+c+d 5582.91
Rate per cum = (a+b+c+d)/10 558.29 317.00
say 558.00 76.03

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 Marshy Soil
(I) Without dewatering
Unit = cum
Taking output = 10 cum
Depth upto 3 m
Manual means
a) Labour
Mate/Supervisor day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 323.00 862.41 P&M-053
c) Overhead charges @ 20 % on (a+b) 690.13
d) Contractor's profit @ 10% on (a+b+c) 414.08
Cost for 10 cum = a+b+c+d 4554.88
Rate per cum = ( a+b+c+d)/ 10 455.49 248.00
say 455.00 83.47
(ii) With dewatering
Unit = cum
Taking output = 10 cum
Depth upto 3 m
Manual means
a) Labour
Mate/Supervisor day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 323.00 862.41 P&M-053
Cost of dewatering @ 30% of (a) 776.48
c) Overhead charges @ 20 % on (a+b) 690.13
d) Contractor's profit @ 10% on (a+b+c) 491.73
Cost for 10 cum = a+b+c+d 5409.01
Rate per cum = ( a+b+c+d)/ 10 540.90 282.00
say 541.00 91.84

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
12.1 (V) Mechanical Means
(I) Without dewatering
a) Labour
Mate day 0.08 356.65 28.53 L-12

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor for dressing sides, bottom and backfilling day 2.00 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1836.00 312.12 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 850.00 382.50 P&M-048
c) Overhead charges @ 20 % on (a+b) 242.45
d) Contractor's profit @ 10% on (a+b+c) 145.47
Cost for 10 cum = a+b+c+d 1600.20
Rate per cum = (a+b+c+d)/10 160.02 83.00
say 160.00 92.77
(ii) With dewatering
a) Labour
Mate day 0.08 356.65 28.53 L-12
Mazdoor for dressing sides, bottom and backfilling day 2.00 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1836.00 312.12 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 850.00 382.50 P&M-048
Cost of dewatering @ 20% of (a+b) 242.45
c) Overhead charges @ 20 % on (a+b) 242.45
d) Contractor's profit @ 10% on (a+b+c) 169.72
Cost for 10 cum = a+b+c+d 1866.90
Rate per cum = (a+b+c+d)/10 186.69 96.00
say 187.00 94.79
1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 356.65 42.80 L-12
Mazdoor for dressing sides, bottom and backfilling day 3.00 244.56 733.68 L-13
b) Machinery
Tractor-trolley for transportation hour 2.00 323.00 646.00 P&M-053
c) Overhead charges @ 20 % on (a+b) 284.50
d) Contractor's profit @ 10% on (a+b+c) 170.70
Cost for 6 cum = a+b+c+d 1877.67
Rate per cum = (a+b+c+d)/6 312.95 209.00
say 313.00 49.76
12.2 Filling Annular Space Around Footing in Rock Item12.4
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be
taken as per item 12.4.
12.3 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.30 244.56 73.37 L-13
b) Material
Sand (assuming 20 per cent voids) cum 1.20 850.00 1020.00 M-006
c) Overhead charges @ 20 % on (a+b) 219.39
d) Contractor's profit @ 10% on (a+b+c) 131.63
Rate per cum = a+b+c+d 1447.95 864.00
say 1448.00 67.59
12.4 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 356.65 228.26 L-12
Mason day 1.00 458.55 458.55 L-11
Mazdoor day 15.00 244.56 3668.40 L-13
b) Material
40 mm Aggregate cum 13.50 1500.00 20250.00 M-055
coarse Sand cum 6.75 950.00 6412.50 M-005
cement tonne 3.95 7200.00 28440.00 M-084
Cost of water KL 18.00 45.00 810.00 M-189
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Water tanker 6 KL capacity hour 2.00 440.00 880.00 P&M-060
d) Overhead charges @ 20 % on (a+b+c) 12828.34
e) Contractor's profit @ 10% on (a+b+c+d) 7697.00
Cost for 15 cum = a+b+c+d+e 84667.05
Rate per cum = (a+b+c+d+e)/15 5644.47 3193.00
say 5644.00 76.76
Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
12.5 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 8.00 20000.00 M-082
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.20 1020.00 1224.00 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.48 356.65 171.19 L-12

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mason day 4.00 458.55 1834.20 L-11
Mazdoor day 8.00 244.56 1956.48 L-13
c) Overhead charges @ 20 % on (a+b) 5037.17
d) Contractor's profit @ 10% on (a+b+c) 3022.30
Cost for 5 cum = a+b+c+d 33245.35
Rate per cum (a+b+c+d)/5 6649.07 3339.00
say 6649.00 99.13
12.6 Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 7200.00 3672.00 M-084
Sand cum 1.05 950.00 997.50 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 4904.00 3269.00
Cement Mortar1:2 (1cement :2 sand) 50.02

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 7200.00 4838.40 M-084
Sand cum 0.93 950.00 883.50 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 5956.00 4052.00
Cement Mortar1:4 (1cement :4 sand) 46.99
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 7200.00 2903.04 M-084
Sand cum 1.12 950.00 1064.00 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 4201.00 2749.00
Cement Mortar1:6 (1cement :6 sand) 52.82
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 7200.00 2073.60 M-084
Sand cum 1.34 950.00 1270.29 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Total Material and Labour = (a+b) say 3578.00 2258.00
12.7 Stone Masonry Work in Cement Mortar 1:3 in 58.46
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 590.00 3245.00 M-169
Through and bond stone each 35.00 8.50 297.50 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 4904.00 7356.00 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.66 356.65 235.39 L-12
Mason day 7.50 458.55 3439.13 L-11
Mazdoor day 9.00 244.56 2201.04 L-13
c) Overhead charges @ 20 % on (a+b) 3354.81
d) Contractor's profit @ 10% on (a+b+c) 2012.89
Cost for 5 cum = a+b+c+d 22141.75
Rate per cum (a+b+c+d)/5 4428.35 2608.00
say 4428.00 69.79
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 470.00 2585.00 M-148
Through and bond stone each 35.00 8.50 297.50 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.55 4904.00 7601.20 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.62 356.65 221.12 L-12
Mason day 6.00 458.55 2751.30 L-11
Mazdoor day 9.00 244.56 2201.04 L-13
c) Overhead charges @ 20 % on (a+b) 3131.43
d) Contractor's profit @ 10% on (a+b+c) 1878.86
Cost for 5 cum = a+b+c+d 20667.46
Rate per cum (a+b+c+d)/5 4133.49 2441.00
say 4133.00 69.32
The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.8 Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and Technical
Specifications cl. no. 1200,1500 & 1700
PCC Grade M15
Unit = cum
Taking output = 15 cum

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Material
Cement tonne 4.13 7200.00 29736.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 8.10 1500.00 12150.00 M-055
20 mm Aggregate cum 4.05 1777.00 7196.85 M-053
10 mm Aggregate cum 1.35 1916.00 2586.60 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 4465.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2678.47
of material, labour and machinery

e) Overhead charges @ 20 % on (a+b+c+d) 13928.03


f) Contractor's profit @ 10% on (a+b+c+d+e) 8356.82
Cost for 15 cum = a+b+c+d+e+f 91925.01
Rate per cum = (a+b+c+d+e+f)/15 6128.33 #REF!
say 6128.00 #REF!
Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7200.00 37152.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5021.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3012.53
of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 15665.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 9399.09
Cost for 15 cum = a+b+c+d+e+f 103390.02
Rate per cum = (a+b+c+d+e+f)/15 6892.67 #REF!

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 6893.00 #REF!
12.8 RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7200.00 37512.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5170.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3101.77
e) Overhead charges @ 20 % on (a+b+c+d) 16129.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 9677.53
Cost for 15 cum = a+b+c+d+e+f 106452.88
Rate per cum = ( a+b+c+d+e+f )/15 7096.86 #REF!
say 7097.00 #REF!
12.8 C With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7200.00 299952.00 M-084
Coarse Sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 km, L-lead in km tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 5920.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 28415.44
of material, labour and machinery

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Overhead charges @ 20 % on (a+b+c+d) 147760.31
f) Contractor's profit @ 10% on (a+b+c+d+e) 88656.19
Cost for 120 cum = a+b+c+d+e+f 975218.06
Rate per cum = ( a+b+c+d+e+f )/120 8126.82 #REF!
say 8127.00 #REF!
12.8 PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5420.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3048.35
e) Overhead charges @ 20 % on (a+b+c+d) 16867.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 10120.51
Cost for 15 cum = a+b+c+d+e+f 111325.62
Rate per cum = ( a+b+c+d+e+f )/15 7421.71 #REF!
say 7422.00 #REF!
12.8 D With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7200.00 345240.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-005
40 mm Aggregate cum 43.20 1500.00 64800.00 M-055
20 mm Aggregate cum 43.20 1777.00 76766.40 M-053
10 mm Aggregate cum 21.60 1916.00 41385.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer (300L) Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6173.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 27776.45
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 153696.35
f) Contractor's profit @ 10% on (a+b+c+d+e) 92217.81
cost of 120 cum = a+b+c+d+e+f 1014395.93
Rate per cum = (a+b+c+d+e+f)/120 8453.30 #REF!
say 8453.00 #REF!
12.8 RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7200.00 43560.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5573.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 3134.71
e) Overhead charges @ 20 % on (a+b+c+d) 17345.41
f) Contractor's profit @ 10% on (a+b+c+d+e) 10407.25
cost of 15 cum = a+b+c+d+e+f 114479.72
Rate per cum (a+b+c+d+e+f )/15 7631.98 #REF!
say 7632.00 #REF!
12.8 E With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7200.00 348336.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6324.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 28453.88
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 157444.80
f) Contractor's profit @ 10% on (a+b+c+d+e) 94466.88
cost of 120 cum = a+b+c+d+e+f 1039135.67
Rate per cum (a+b+c+d+e+f )/120 8659.46 #REF!
say 8659.00 #REF!
12.8 PCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7200.00 43776.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5463.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 2867.80
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 16961.01
f) Contractor's profit @ 10% on (a+b+c+d+e) 10176.61
cost of 15 cum = a+b+c+d+e+f 111942.66
Rate per cum (a+b+c+d+e+f )/15 7462.84 #REF!
say 7463.00 #REF!
12.8 F Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 7200.00 349920.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
40 mm Aggregate cum 43.20 1500.00 64800.00 M-055
20 mm Aggregate cum 43.20 1777.00 76766.40 M-053
10 mm Aggregate cum 21.60 1916.00 41385.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6212.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 26088.49
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 154294.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 92576.86
cost of 120 cum = a+b+c+d+e+f 1018345.42
Rate per cum (a+b+c+d+e+f )/120 8486.21 #REF!
say 8486.00 #REF!
12.8 RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5597.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 2938.33
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 17378.14
f) Contractor's profit @ 10% on (a+b+c+d+e) 10426.88
cost of 15 cum = a+b+c+d+e+f 114695.69
Rate per cum = (a+b+c+d+e+f)/15 7646.38 #REF!
say 7646.00 #REF!

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.8 G Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7200.00 351360.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6349.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. 26662.79
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 157691.38
f) Contractor's profit @ 10% on (a+b+c+d+e) 94614.83
cost of 120 cum = a+b+c+d+e+f 1040763.12
Rate per cum (a+b+c+d+e+f )/120 8673.03 #REF!
say 8673.00 #REF!
12.8 RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5708.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 2568.25
e) Overhead charges @ 20 % on (a+b+c+d) 17635.32

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10% on (a+b+c+d+e) 10581.19
cost of 15 cum = a+b+c+d+e+f 116393.10
Rate per cum = (a+b+c+d+e+f)/15 7759.54 #REF!
say 7760.00 #REF!
12.8 H Using Batching Plant, Transit Mixer and Concrete
Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7200.00 364608.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6459.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 3% 23251.26
of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 20 % 159658.68
f) Contractor's profit @ 10% on (a+b+c+d+e) 10% 95795.21
cost of 120 cum = a+b+c+d+e+f 1053747.26
Rate per cum = (a+b+c+d+e+f)/120 8781.23 #REF!
say 8781.00 #REF!
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
12.8 Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and Technical
Specifications cl. no. 1200,1500 & 1700 including
providing plasticiser ( Masterplast PL-1/SPL-2 or
equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or equivalent) and
accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999.

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7200.00 29736.00 M-084

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 8.10 1500.00 12150.00 M-055
20 mm Aggregate cum 4.05 1777.00 7196.85 M-053
10 mm Aggregate cum 1.35 1916.00 2586.60 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit per Lit 16.52 120.00 1982.40 M-208
Tonne of cement
Air entraining and water reducing plasticiser Lit 12.39 75.00 929.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 57.82 95.00 5492.90 M-211
( Masterplast APCL or equivalent ) @ 14Lit per Tonne
of cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5025.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3014.65
of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 15676.18
f) Contractor's profit @ 10% on (a+b+c+d+e) 9405.71
Cost for 15 cum = a+b+c+d+e+f 103462.78
Rate per cum = (a+b+c+d+e+f)/15 6897.52 4389.00
say 6898.00 57.17
Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7200.00 37152.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit per Lit 20.64 120.00 2476.80 M-208
Tonne of cement
Air entraining and water reducing plasticiser Lit 15.48 75.00 1161.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.24 95.00 6862.80 M-211
( Masterplast APCL or equivalent ) @ 14Lit per Tonne
of cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5721.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3432.55
of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 17849.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 10709.57
Cost for 15 cum = a+b+c+d+e+f 117805.25
Rate per cum = (a+b+c+d+e+f)/15 7853.68 4369.00
say 7854.00 79.77
12.8 RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7200.00 37512.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit per Lit 20.84 120.00 2500.80 M-208
Tonne of cement
Air entraining and water reducing plasticiser Lit 15.63 75.00 1172.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.94 95.00 6929.30 M-211
( Masterplast APCL or equivalent ) @ 14Lit per Tonne
of cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5877.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3525.87
e) Overhead charges @ 20 % on (a+b+c+d) 18334.51
f) Contractor's profit @ 10% on (a+b+c+d+e) 11000.71
Cost for 15 cum = a+b+c+d+e+f 121007.78
Rate per cum = ( a+b+c+d+e+f )/15 8067.19 5101.00
say 8067.00 58.15
12.8 C With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7200.00 299952.00 M-084
Coarse Sand cum 54.00 950.00 51300.00 M-005

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit per Lit 166.64 120.00 19996.80 M-208
tonne cement
Air entraining and water reducing plasticiser Lit 124.98 75.00 9373.50 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @3Lit per tonne cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 583.24 95.00 55407.80 M-211
( Masterplast APCL or equivalent ) @ 14Lit per tonne
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 km, L-lead in km (300L) tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6627.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 31806.57
of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 165394.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 99236.49
Cost for 120 cum = a+b+c+d+e+f 1091601.44
Rate per cum = ( a+b+c+d+e+f )/120 9096.68 5704.00
say 9097.00 59.48
12.8 PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 29.95 100.00 2995.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 17.97 75.00 1347.75 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 95.00 7966.70 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6240.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3509.95
e) Overhead charges @ 20 % on (a+b+c+d) 19421.73
f) Contractor's profit @ 10% on (a+b+c+d+e) 11653.04
Cost for 15 cum = a+b+c+d+e+f 128183.41
Rate per cum = ( a+b+c+d+e+f )/15 8545.56 #REF!
say 8546.00 #REF!
12.8 D With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7200.00 345240.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
40 mm Aggregate cum 43.20 1500.00 64800.00 M-055
20 mm Aggregate cum 43.20 1777.00 76766.40 M-053
10 mm Aggregate cum 21.60 1916.00 41385.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 239.75 100.00 23975.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 143.85 75.00 10788.75 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 671.30 95.00 63773.50 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer (300L) Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6994.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 31471.60
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 174142.83
f) Contractor's profit @ 10% on (a+b+c+d+e) 104485.70
cost of 120 cum = a+b+c+d+e+f 1149342.69
Rate per cum = (a+b+c+d+e+f)/120 9577.86 6084.00
say 9578.00 57.43

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.8 RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7200.00 43560.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.25 100.00 3025.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.15 75.00 1361.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 95.00 8046.50 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6402.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 3600.94
e) Overhead charges @ 20 % on (a+b+c+d) 19925.21
f) Contractor's profit @ 10% on (a+b+c+d+e) 11955.12
cost of 15 cum = a+b+c+d+e+f 131506.37
Rate per cum (a+b+c+d+e+f )/15 8767.09 5618
say 8767.00 56.05
12.8 E With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7200.00 348336.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 241.90 100.00 24190.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 145.14 75.00 10885.50 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.32 95.00 64345.40 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7152.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 32182.16
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 178074.64
f) Contractor's profit @ 10% on (a+b+c+d+e) 106844.78
cost of 120 cum = a+b+c+d+e+f 1175292.60
Rate per cum (a+b+c+d+e+f )/120 9794.10 6219
say 9794.00 57.49
12.8 PCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7200.00 43776.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.40 100.00 3040.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.24 75.00 1368.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 95.00 8086.40 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6296.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 3305.11
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 19547.35
f) Contractor's profit @ 10% on (a+b+c+d+e) 11728.41
cost of 15 cum = a+b+c+d+e+f 129012.51
Rate per cum (a+b+c+d+e+f )/15 8600.83 5522

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8601.00 55.76
12.8 F Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 7200.00 349920.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
40 mm Aggregate cum 43.20 1500.00 64800.00 M-055
20 mm Aggregate cum 43.20 1777.00 76766.40 M-053
10 mm Aggregate cum 21.60 1916.00 41385.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 243.00 100.00 24300.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 145.80 75.00 10935.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.40 95.00 64638.00 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7044.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 29584.04
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 174968.47
f) Contractor's profit @ 10% on (a+b+c+d+e) 104981.08
cost of 120 cum = a+b+c+d+e+f 1154791.91
Rate per cum (a+b+c+d+e+f )/120 9623.27 6120
say 9623.00 57.24
12.8 RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.50 100.00 3050.00 M-209
per MT cement

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air entraining and water reducing plasticiser Lit 18.30 75.00 1372.50 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 95.00 8113.00 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6433.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 3377.07
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 19972.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 11983.79
cost of 15 cum = a+b+c+d+e+f 131821.69
Rate per cum = (a+b+c+d+e+f)/15 8788.11 5635
say 8788.00 55.95
12.8 G Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7200.00 351360.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 244.00 100.00 24400.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 146.40 75.00 10980.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.20 95.00 64904.00 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Per Cum Basic Cost of Labour, Material & Machinery 7184.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. 30172.73
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 178450.17
f) Contractor's profit @ 10% on (a+b+c+d+e) 107070.10
cost of 120 cum = a+b+c+d+e+f 1177771.12
Rate per cum (a+b+c+d+e+f )/120 9814.76 6236
say 9815.00 57.39
12.8 RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 31.65 100.00 3165.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.99 75.00 1424.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 95.00 8418.90 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6575.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 2958.49
e) Overhead charges @ 20 % on (a+b+c+d) 20315.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 12189.00
cost of 15 cum = a+b+c+d+e+f 134078.99
Rate per cum = (a+b+c+d+e+f)/15 8938.60 5750
say 8939.00 55.46
12.8 H Using Batching Plant, Transit Mixer and Concrete
Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7200.00 364608.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051

Page 29 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 253.20 100.00 25320.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 151.92 75.00 11394.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 95.00 67351.20 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7326.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 26373.22
of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 181096.11
f) Contractor's profit @ 10% on (a+b+c+d+e) 108657.66
cost of 120 cum = a+b+c+d+e+f 1195234.31
Rate per cum = (a+b+c+d+e+f)/120 9960.29 6348
say 9960.00 56.90
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
12.9 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m
dia. Well.
Assuming depth of water 1.0 m and height of island to
be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 33.0 8289.60 M-095
Sand bags each 750.00 16.00 12000.00 M-159
b) Labour
Mate day 0.40 356.65 142.66 L-12
Mazdoor for filling sand bags, stitching and placing day 15.00 244.56 3668.40 L-13
c) Machinery
Crane with grab 1 cum capacity hour 20.00 759.00 15180.00 P&M-012
Consumables @ 2.5 per cent of (c) above 379.50
d) Overhead charges @ 20 % on (a+b+c) 7932.03
e) Contractor's profit @ 10% on (a+b+c+d) 4759.22

Page 30 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per No. (a+b+c+d+e) 52351.41 42695
say 52351.00 22.62
It is assumed that earth will be available within the working
space of crane with grab bucket.
12.9 Assuming depth of water 4.0 m and height of island
4.5 m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 33.00 29842.56 M-095
Sand bags each 6000.00 16.00 96000.00 M-159
Wooden ballies 8" Dia and 9 m long each 95.00 3300.00 313500.00 M-194
Wooden ballies 2" Dia for bracing metre 190.00 210.00 39900.00 M-193
b) Labour
Mate day 5.60 356.65 1997.24 L-12
Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 244.56 4402.08 L-13

Mazdoor for bracing with 2" dia ballies day 12.00 244.56 2934.72 L-13
Mazdoor for filling sand bags, stitching and placing day 110.00 244.56 26901.60 L-13
c) Machinery
Crane with grab 1 cum capacity hour 50.00 759.00 37950.00 P&M-012
Consumables and other arrangements for piling ballies @ 13835.71
2.5 per cent of (a+b+c).
d) Overhead charges @ 20 % on (a+b+c) 113452.78
e) Contractor's profit @ 10% on (a+b+c+d) 68071.67
Rate per No. (a+b+c+d+e) 748788.35 607670
say 748788.00 23.22
For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
12.9 Providing and constructing one span service road to
reach island location from one pier location to another
pier location
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 33.00 14850.00 M-095
Sand bags each 300.00 16.00 4800.00 M-159
b) Labour
Mate day 0.24 356.65 85.60 L-12
Mazdoor for filling sand bags, stitching and placing day 6.00 244.56 1467.36 L-13
c) Machinery
Front end Loader 1 cum capacity hour 27.00 1341.00 36207.00 P&M-017
Tipper 5.5 cum capacity hour 28.00 850.00 23800.00 P&M-048
d) Overhead charges @ 20 % on (a+b+c) 16241.99
e) Contractor's profit @ 10% on (a+b+c+d) 9745.19
Cost for 30 m (a+b+c+d+e) 107197.14
Rate per m (a+b+c+d+e)/30 3573.24 2007

Page 31 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 3573.00 78.03
12.10 Providing and Laying Cutting Edge of Mild Steel
weighing 40 kg per metre for Well Foundation
complete as per Drawing and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 60000.00 63000.00 M-179
cent wastage
Nuts & bolts Kg 20.00 90.00 1800.00 M-130
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 1.32 356.65 470.78 L-12
Fitter day 5.50 356.65 1961.58 L-07
Blacksmith day 5.50 458.55 2522.03 L-02
Welder day 5.50 458.55 2522.03 L-02
Mazdoor day 16.50 244.56 4035.24 L-13
Electrodes, cutting gas and other consumables @ 10 per 6480.00
cent of cost of (a) above
c) Overhead charges @ 20 % on (a+b) 16558.33
d) Contractor's profit @ 10% on (a+b+c) 9935.00
Rate per MT (a+b+c+d) 109284.97 60374
say 109285.00 81.01
12.11 Plain/Reinforced cement concrete, in well foundation
complete as per drawing and technical specification and
steel shuttering formwork.

(A) Without plasticiser

Unit = 1 cum
Taking output = 1 cum
Well curb
RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5170.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1034.00
e) Overhead charges @ 20 % on (a+b+c+d) 1240.80
f) Contractor's profit @ 10% on (a+b+c+d+e) 744.48
Rate perm (a+b+c+d+e+f) 8189.28 5009
say 8189.00 63.49
12.11 A (i) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1187.80
e) Overhead charges @ 20 % on (a+b+c+d) 1425.36
f) Contractor's profit @ 10% on (a+b+c+d+e) 855.22

Page 32 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate perm (a+b+c+d+e+f) 9407.38 5704
say 9407.00 64.92
12.11 A RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5573.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1114.60
e) Overhead charges @ 20 % on (a+b+c+d) 1337.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 802.51
Rate perm (a+b+c+d+e+f) 8827.63 5470
say 8828.00 61.39
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6342.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1268.40
e) Overhead charges @ 20 % on (a+b+c+d) 1522.08
f) Contractor's profit @ 10% on (a+b+c+d+e) 913.25
Rate perm (a+b+c+d+e+f) 10045.73 6165
say 10046.00 62.95
12.11 A RCC M30 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5597.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1119.40
e) Overhead charges @ 20 % on (a+b+c+d) 1343.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 805.97
Rate perm (a+b+c+d+e+f) 8865.65
say 8866.00
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6367.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1273.40
e) Overhead charges @ 20 % on (a+b+c+d) 1528.08
f) Contractor's profit @ 10% on (a+b+c+d+e) 916.85
Rate perm (a+b+c+d+e+f) 10085.33
say 10085.00
12.11 A RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5708.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1141.60

Page 33 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Overhead charges @ 20 % on (a+b+c+d) 1369.92
f) Contractor's profit @ 10% on (a+b+c+d+e) 821.95
Rate perm (a+b+c+d+e+f) 9041.47 5623
say 9041.00 60.79
12.11 A (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6478.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1295.60
e) Overhead charges @ 20 % on (a+b+c+d) 1554.72
f) Contractor's profit @ 10% on (a+b+c+d+e) 932.83
Rate perm (a+b+c+d+e+f) 10261.15 6320
say 10261.00 62.36
If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

12.11 Well steining


PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 4546.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 454.60
e) Overhead charges @ 20 % on (a+b+c+d) 1000.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 600.07
Rate perm (a+b+c+d+e+f) 6600.79 4005
say 6601.00 64.82
12.11 B PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5021.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 502.10
e) Overhead charges @ 20 % on (a+b+c+d) 1104.62
f) Contractor's profit @ 10% on (a+b+c+d+e) 662.77
Rate perm (a+b+c+d+e+f) 7290.49 4458
say 7290.00 63.53
12.11 B RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5170.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 517.00
e) Overhead charges @ 20 % on (a+b+c+d) 1137.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 682.44
Rate perm (a+b+c+d+e+f) 7506.84 4591

Page 34 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 7507.00 63.52
12.11 B (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 593.90
e) Overhead charges @ 20 % on (a+b+c+d) 1306.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 783.95
Rate perm (a+b+c+d+e+f) 8623.43 4943
say 8623.00 74.45
12.11 B PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5420.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 542.00
e) Overhead charges @ 20 % on (a+b+c+d) 1192.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 715.44
Rate perm (a+b+c+d+e+f) 7869.84 5229
say 7870.00 50.51
12.11 B (iv) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 630.90
e) Overhead charges @ 20 % on (a+b+c+d) 1387.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 832.79
Rate perm (a+b+c+d+e+f) 9160.67 4876
say 9161.00 87.88
'12.11 B RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5573.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 557.30
e) Overhead charges @ 20 % on (a+b+c+d) 1226.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 735.64
Rate perm (a+b+c+d+e+f) 8092.00 5014
say 8092.00 61.39
12.11 B (v) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6342.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 634.20
e) Overhead charges @ 20 % on (a+b+c+d) 1395.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 837.14
Rate perm (a+b+c+d+e+f) 9208.58 5651
say 9209.00 62.96

Page 35 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
'12.11 B PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5463.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 546.30
e) Overhead charges @ 20 % on (a+b+c+d) 1201.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 721.12
Rate perm (a+b+c+d+e+f) 7932.28 4921
say 7932.00 61.19
12.11 B (vi) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 623.00
e) Overhead charges @ 20 % on (a+b+c+d) 1370.60
f) Contractor's profit @ 10% on (a+b+c+d+e) 822.36
Rate perm (a+b+c+d+e+f) 9045.96 5558
say 9046.00 62.76
'12.11 B RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5597.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 559.70
e) Overhead charges @ 20 % on (a+b+c+d) 1231.34
f) Contractor's profit @ 10% on (a+b+c+d+e) 738.80
Rate perm (a+b+c+d+e+f) 8126.84 5038
say 8127.00 61.31
12.11 B With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery 6367.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 636.70
e) Overhead charges @ 20 % on (a+b+c+d) 1400.74
f) Contractor's profit @ 10% on (a+b+c+d+e) 840.44
Rate perm (a+b+c+d+e+f) 9244.88 5677
say 9245.00 62.85
'12.11 B RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5708.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 570.80
e) Overhead charges @ 20 % on (a+b+c+d) 1255.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 753.46

Page 36 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate perm (a+b+c+d+e+f) 8288.02 5155
say 8288.00 60.78
12.11 B With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 6478.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 647.80
e) Overhead charges @ 20 % on (a+b+c+d) 1425.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 855.10
Rate perm (a+b+c+d+e+f) 9406.06 5793
say 9406.00 62.37

'12.11 B RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7200.00 371520.00 M-084
Coarse Sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Meson day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 52131.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. 78195.41
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 172029.91
f) Contractor's profit @ 10% on (a+b+c+d+e) 103217.94
cost of 120 cum = a+b+c+d+e+f 1135397.38
Rate per cum = (a+b+c+d+e+f)/120 9461.64 5853
say 9462.00 61.66
12.11 C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum

Page 37 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 15 cum
a) Material
Cement tonne 5.55 7200.00 39960.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 318.00 1908.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 5337.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost 3757.08
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 16760.12


e) Contractor's profit @ 10% on (a+b+c+d) 10056.07
cost of 15 cum = a+b+c+d+e 110616.77
Rate per cum = (a+b+c+d+e)/15 7374.45 4597
say 7374.00 60.41
12.11 C (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 7200.00 319680.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6085.00
(a+b+c)

Page 38 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 5 per cent of cost of material and labour towards cost 28749.62
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 151775.60


e) Contractor's profit @ 10% on (a+b+c+d) 91065.36
cost of 120 cum = a+b+c+d+e 1001718.96
Rate per cum = (a+b+c+d+e)/120 8347.66 4630
say 8348.00 80.30
'12.11 C PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 5548.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 3620.48
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 17366.40


e) Contractor's profit @ 10% on (a+b+c+d) 10419.84
cost of 15 cum = a+b+c+d+e 114618.22
Rate per cum = (a+b+c+d+e)/15 7641.21 4809
say 7641.00 58.89
12.11 C (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7200.00 344736.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12

Page 39 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6294.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 30002.42
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 157037.36


e) Contractor's profit @ 10% on (a+b+c+d) 94222.42
cost of 120 cum = a+b+c+d+e 1036446.58
Rate per cum = (a+b+c+d+e)/120 8637.05 5312
say 8637.00 62.59
'12.11 C PCC Grade M30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7200.00 43776.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 5591.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 3947.88
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 17561.48


e) Contractor's profit @ 10% on (a+b+c+d) 10536.89
cost of 15 cum = a+b+c+d+e 115905.75
Rate per cum = (a+b+c+d+e)/15 7727.05 4852
say 7727.00 59.25

Page 40 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.11 C (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7200.00 350208.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6339.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 30276.02
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 158186.48


e) Contractor's profit @ 10% on (a+b+c+d) 94911.89
cost of 120 cum = a+b+c+d+e 1044030.77
Rate per cum = (a+b+c+d+e)/120 8700.26 5358
say 8700.00 62.37
'12.11 C PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7200.00 45288.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079

Page 41 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 5692.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4023.48
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 17879.00


e) Contractor's profit @ 10% on (a+b+c+d) 10727.40
cost of 15 cum = a+b+c+d+e 118001.38
Rate per cum = (a+b+c+d+e)/15 7866.76 4953
say 7867.00 58.83
12.11 C (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7200.00 362016.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6438.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 30866.42
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 160666.16


e) Contractor's profit @ 10% on (a+b+c+d) 96399.70
cost of 120 cum = a+b+c+d+e 1060396.66
Rate per cum = (a+b+c+d+e)/120 8836.64 5456
say 8837.00 61.97
12.11 Intermediate plug
Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5337.00
(a+b+c)

Page 42 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 20 % on (a+b+c) 1067.40
e) Contractor's profit @ 10% on (a+b+c+d) 640.44
Rate per cum = (a+b+c+d+e) 7044.84 4400
say 7045.00 60.11
12.11 D (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6085.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1217.00
e) Contractor's profit @ 10% on (a+b+c+d) 730.20
Rate per cum = (a+b+c+d+e) 8032.20 4909
say 8032.00 63.62
'12.11 D Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5548.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1109.60
e) Contractor's profit @ 10% on (a+b+c+d) 665.76
Rate per cum = (a+b+c+d+e) 7323.36 4602
say 7323.00 59.13
12.11 D (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6294.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1258.80
e) Contractor's profit @ 10% on (a+b+c+d) 755.28
Rate per cum = (a+b+c+d+e) 8308.08 5108
say 8308.00 62.65
'12.11 D Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5591.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1118.20
e) Contractor's profit @ 10% on (a+b+c+d) 670.92
Rate per cum = (a+b+c+d+e) 7380.12 4642
say 7380.00 58.98
12.11 D (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6339.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1267.80
e) Contractor's profit @ 10% on (a+b+c+d) 760.68
Rate per cum = (a+b+c+d+e) 8367.48 5152
say 8367.00 62.40
12.11 Top plug
Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Using Concrete Mixer

Page 43 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Per Cum Basic Cost of Labour, Material & Machinery 4546.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 909.20
e) Contractor's profit @ 10% on (a+b+c+d) 545.52
Rate per cum = (a+b+c+d+e) 6000.72 3641
say 6001.00 64.82
'12.11 E Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5021.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1004.20
e) Contractor's profit @ 10% on (a+b+c+d) 602.52
Rate per cum = (a+b+c+d+e) 6627.72 4052
say 6628.00 63.57
'12.11 E Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5420.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1084.00
e) Contractor's profit @ 10% on (a+b+c+d) 650.40
Rate per cum = (a+b+c+d+e) 7154.40 4433
say 7154.00 61.38
12.11 E (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6309.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1261.80
e) Contractor's profit @ 10% on (a+b+c+d) 757.08
Rate per cum = (a+b+c+d+e) 8327.88 5015
say 8328.00 66.06
'12.11 E Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5463.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1092.60
e) Contractor's profit @ 10% on (a+b+c+d) 655.56
Rate per cum = (a+b+c+d+e) 7211.16 4473
say 7211.00 61.21
12.11 E (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6230.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1246.00
e) Contractor's profit @ 10% on (a+b+c+d) 747.60
Rate per cum = (a+b+c+d+e) 8223.60 5053
say 8224.00 62.75
12.11 Well cap
RCC Grade M20

Page 44 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7200.00 36864.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 4 per cent of a+b+c 3075.85
d) Overhead charges @ 20 % on (a+b+c) 15994.44
e) Contractor's profit @ 10% on (a+b+c+d) 9596.66
cost of 15 cum = a+b+c+d+e 105563.30
Rate per cum = (a+b+c+d+e)/15 7037.55 4297
say 7038.00 63.79
12.11 F (i) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7200.00 294624.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 4 per cent of (a+b+c) 28202.32
d) Overhead charges @ 20 % on (a+b+c) 146652.09
e) Contractor's profit @ 10% on (a+b+c+d) 87991.25
cost of 120 cum = a+b+c+d+e 967903.78
Rate per cum = (a+b+c+d+e)/120 8065.86 4898

Page 45 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8066.00 64.68
12.11 F RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7200.00 43560.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 3.75 per cent of a+b+c 3134.71
d) Overhead charges @ 20 % on (a+b+c) 17345.41
e) Contractor's profit @ 10% on (a+b+c+d) 10407.25
cost of 15 cum = a+b+c+d+e 114479.72
Rate per cum = (a+b+c+d+e)/15 7631.98 4728
say 7632.00 61.42
12.11 F (ii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7200.00 348480.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.75 per cent of ( a+b+c) 28459.28
d) Overhead charges @ 20 % on (a+b+c) 157474.68
e) Contractor's profit @ 10% on (a+b+c+d) 94484.81

Page 46 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
cost of 120 cum = a+b+c+d+e 1039332.88
Rate per cum = (a+b+c+d+e)/120 8661.11 5330
say 8661.00 62.50
12.11 F RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3.5 per cent of (a+b+c) 2938.33
d) Overhead charges @ 20 % on (a+b+c) 17378.14
e) Contractor's profit @ 10% on (a+b+c+d) 10426.88
cost of 15 cum = a+b+c+d+e 114695.69
Rate per cum = (a+b+c+d+e)/15 7646.38 4740
say 7646.00 61.31
12.11 F (iii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7200.00 351288.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.5 per cent of (a+b+c) 26660.27

Page 47 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 20 % on (a+b+c) 157676.48
e) Contractor's profit @ 10% on (a+b+c+d) 94605.89
cost of 120 cum = a+b+c+d+e 1040664.75
Rate per cum = (a+b+c+d+e)/120 8672.21 4341
say 8672.00 99.77
12.11 F RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3 per cent of (a+b+c) 2568.25
d) Overhead charges @ 20 % on (a+b+c) 17635.32
e) Contractor's profit @ 10% on (a+b+c+d) 10581.19
cost of 15 cum = a+b+c+d+e 116393.10
Rate per cum = (a+b+c+d+e)/15 7759.54 4826
say 7760.00 60.80
12.11 F (iv) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7200.00 364608.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km

Page 48 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent of (a+b+c) 23251.26
d) Overhead charges @ 20 % on (a+b+c) 159658.68
e) Contractor's profit @ 10% on (a+b+c+d) 95795.21
cost of 120 cum = a+b+c+d+e 1053747.26
Rate per cum = (a+b+c+d+e)/120 8781.23 5424
say 8781.00 61.89
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7200.00 375840.00 M-084
Coarse Sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent on cost of concrete i.e. cost of 23588.22
material, labour and machinery
d) Overhead charges @ 20 % on (a+b+c) 161972.47
e) Contractor's profit @ 10% on (a+b+c+d) 97183.48
cost of 120 cum = a+b+c+d+e 1069018.29
Rate per cum = (a+b+c+d+e)/120 8908.49 5516
say 8908.00 61.49
12.11 Plain/Reinforced cement concrete, in well foundation
complete as per drawing and technical specification
including providing plasticiser ( Masterplast PL-1/SPL-2 or
equivalent ), air entraining and water reducing plasticiser
( Masterplast PAE or equivalent) and accelerating plasticiser
( Masterplast ACPL or equivalent) conforming to IS-9103-
1999.and steel shuttering formwork.

Unit = 1 cum
Taking output = 1 cum
Well curb

Page 49 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5806.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1161.20
e) Overhead charges @ 20 % on (a+b+c+d) 1393.44
f) Contractor's profit @ 10% on (a+b+c+d+e) 836.06
Rate perm (a+b+c+d+e+f) 9196.70 5886
say 9197.00 56.25
12.11 A (i) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1314.80
e) Overhead charges @ 20 % on (a+b+c+d) 1577.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 946.66
Rate perm (a+b+c+d+e+f) 10413.22 6582
say 10413.00 58.20
12.11 A RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6223.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1244.60
e) Overhead charges @ 20 % on (a+b+c+d) 1493.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 896.11
Rate perm (a+b+c+d+e+f) 9857.23 6499
say 9857.00 51.67
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6992.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1398.40
e) Overhead charges @ 20 % on (a+b+c+d) 1678.08
f) Contractor's profit @ 10% on (a+b+c+d+e) 1006.85
Rate perm (a+b+c+d+e+f) 11075.33 7399
say 11075.00 49.68
12.11 A RCC M30 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1250.60
e) Overhead charges @ 20 % on (a+b+c+d) 1500.72
f) Contractor's profit @ 10% on (a+b+c+d+e) 900.43

Page 50 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate perm (a+b+c+d+e+f) 9904.75
say 9905.00
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7022.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1404.40
e) Overhead charges @ 20 % on (a+b+c+d) 1685.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 1011.17
Rate perm (a+b+c+d+e+f) 11122.85
say 11123.00
12.11 A RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6388.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1277.60
e) Overhead charges @ 20 % on (a+b+c+d) 1533.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 919.87
Rate perm (a+b+c+d+e+f) 10118.59 6700
say 10119.00 51.03
12.11 A (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1431.60
e) Overhead charges @ 20 % on (a+b+c+d) 1717.92
f) Contractor's profit @ 10% on (a+b+c+d+e) 1030.75
Rate perm (a+b+c+d+e+f) 11338.27 7397
say 11338.00 53.28
If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

12.11 Well steining


PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5181.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 518.10
e) Overhead charges @ 20 % on (a+b+c+d) 1139.82
f) Contractor's profit @ 10% on (a+b+c+d+e) 683.89
Rate perm (a+b+c+d+e+f) 7522.81 4809
say 7523.00 56.44
12.11 B PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Page 51 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5657.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 565.70
e) Overhead charges @ 20 % on (a+b+c+d) 1244.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 746.72
Rate perm (a+b+c+d+e+f) 8213.96 5264
say 8214.00 56.04
12.11 B RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5806.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 580.60
e) Overhead charges @ 20 % on (a+b+c+d) 1277.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 766.39
Rate perm (a+b+c+d+e+f) 8430.31 5396
say 8430.00 56.23
12.11 B (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 657.40
e) Overhead charges @ 20 % on (a+b+c+d) 1446.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 867.77
Rate perm (a+b+c+d+e+f) 9545.45 6033
say 9545.00 58.21
12.11 B PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6063.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 606.30
e) Overhead charges @ 20 % on (a+b+c+d) 1333.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 800.32
Rate perm (a+b+c+d+e+f) 8803.48 5811
say 8803.00 51.49
12.11 B (iv) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6835.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 683.50
e) Overhead charges @ 20 % on (a+b+c+d) 1503.70
f) Contractor's profit @ 10% on (a+b+c+d+e) 902.22
Rate perm (a+b+c+d+e+f) 9924.42 6451
say 9924.00 53.84
'12.11 B RCC M25 Grade

Page 52 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6223.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 622.30
e) Overhead charges @ 20 % on (a+b+c+d) 1369.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 821.44
Rate perm (a+b+c+d+e+f) 9035.80 5958
say 9036.00 51.66
12.11 B (v) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6992.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 699.20
e) Overhead charges @ 20 % on (a+b+c+d) 1538.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 922.94
Rate perm (a+b+c+d+e+f) 10152.38 6782
say 10152.00 49.69
'12.11 B PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6116.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 611.60
e) Overhead charges @ 20 % on (a+b+c+d) 1345.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 807.31
Rate perm (a+b+c+d+e+f) 8880.43 5869
say 8880.00 51.30
12.11 B (vi) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 688.30
e) Overhead charges @ 20 % on (a+b+c+d) 1514.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 908.56
Rate perm (a+b+c+d+e+f) 9994.12 6505
say 9994.00 53.64
'12.11 B RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 625.30
e) Overhead charges @ 20 % on (a+b+c+d) 1375.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 825.40
Rate perm (a+b+c+d+e+f) 9079.36 5990

Page 53 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 9079.00 51.57
12.11 B With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery 7022.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 702.20
e) Overhead charges @ 20 % on (a+b+c+d) 1544.84
f) Contractor's profit @ 10% on (a+b+c+d+e) 926.90
Rate perm (a+b+c+d+e+f) 10195.94 6628
say 10196.00 53.83
'12.11 B RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6388.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 638.80
e) Overhead charges @ 20 % on (a+b+c+d) 1405.36
f) Contractor's profit @ 10% on (a+b+c+d+e) 843.22
Rate perm (a+b+c+d+e+f) 9275.38 6142
say 9275.00 51.01
12.11 B With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 7158.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 715.80
e) Overhead charges @ 20 % on (a+b+c+d) 1574.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 944.86
Rate perm (a+b+c+d+e+f) 10393.42 6781
say 10393.00 53.27
'12.11 B RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7200.00 371520.00 M-084
Coarse Sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 258.00 100.00 25800.00 M-209
Air entraining and water reducing plasticiser Lit 154.80 75.00 11610.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 722.40 95.00 68628.00 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59 L-12
Meson day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery

Page 54 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Batching Plant hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 59200.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. 88799.21
cost of material, labour and machinery
e) Overhead charges @ 20 % on (a+b+c+d) 195358.27
f) Contractor's profit @ 10% on (a+b+c+d+e) 117214.96
cost of 120 cum = a+b+c+d+e+f 1289364.55
Rate per cum = (a+b+c+d+e+f)/120 10744.70 6859
say 10745.00 56.66
12.11 C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 7200.00 39960.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 22.20 120.00 2664.00 M-208
Air entraining and water reducing plasticiser Lit 16.65 75.00 1248.75 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 77.70 95.00 7381.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 318.00 1908.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 6090.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4321.79
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 19131.91

Page 55 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Contractor's profit @ 10% on (a+b+c+d) 11479.15
cost of 15 cum = a+b+c+d+e 126270.60
Rate per cum = (a+b+c+d+e)/15 8418.04 5416
say 8418.00 55.43
12.11 C (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 7200.00 319680.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 177.60 120.00 21312.00 M-208
Air entraining and water reducing plasticiser Lit 133.20 75.00 9990.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 621.60 95.00 59052.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6838.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 33267.32
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 170749.94


e) Contractor's profit @ 10% on (a+b+c+d) 102449.96
cost of 120 cum = a+b+c+d+e 1126949.61
Rate per cum = (a+b+c+d+e)/120 9391.25 5922
say 9391.00 58.58
'12.11 C PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053

Page 56 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 29.95 100.00 2995.00 M-209
Air entraining and water reducing plasticiser Lit 17.97 75.00 1347.75 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 95.00 7966.70 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6369.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4530.95
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 20010.38


e) Contractor's profit @ 10% on (a+b+c+d) 12006.23
cost of 15 cum = a+b+c+d+e 132068.52
Rate per cum = (a+b+c+d+e)/15 8804.57 5700
say 8805.00 54.47
12.11 C (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7200.00 344736.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 239.40 100.00 23940.00 M-209
Air entraining and water reducing plasticiser Lit 143.64 75.00 10773.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 670.32 95.00 63680.40 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049

Page 57 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7114.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34922.09
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 177699.97


e) Contractor's profit @ 10% on (a+b+c+d) 106619.98
cost of 120 cum = a+b+c+d+e 1172819.83
Rate per cum = (a+b+c+d+e)/120 9773.50 6203
say 9773.00 57.55
'12.11 C PCC Grade M30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7200.00 43776.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.40 100.00 3040.00 M-209
Air entraining and water reducing plasticiser Lit 18.24 75.00 1368.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 95.00 8086.40 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6424.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4572.60
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 20185.30


e) Contractor's profit @ 10% on (a+b+c+d) 12111.18
cost of 15 cum = a+b+c+d+e 133222.99
Rate per cum = (a+b+c+d+e)/15 8881.53 5757
say 8882.00 54.28
12.11 C (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump

Page 58 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7200.00 350208.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 243.20 100.00 24320.00 M-209
Air entraining and water reducing plasticiser Lit 145.92 75.00 10944.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.96 95.00 64691.20 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7172.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 35273.78
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 179177.07


e) Contractor's profit @ 10% on (a+b+c+d) 107506.24
cost of 120 cum = a+b+c+d+e 1182568.68
Rate per cum = (a+b+c+d+e)/120 9854.74 6263
say 9855.00 57.35
'12.11 C PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7200.00 45288.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm Aggregate cum 5.40 1500.00 8100.00 M-055
20 mm Aggregate cum 5.40 1777.00 9595.80 M-053
10 mm Aggregate cum 2.70 1916.00 5173.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 31.45 100.00 3145.00 M-209
Air entraining and water reducing plasticiser Lit 18.87 75.00 1415.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)

Page 59 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.06 95.00 8365.70 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6554.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4669.77
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 20593.45


e) Contractor's profit @ 10% on (a+b+c+d) 12356.07
cost of 15 cum = a+b+c+d+e 135916.75
Rate per cum = (a+b+c+d+e)/15 9061.12 5889
say 9061.00 53.86
12.11 C (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7200.00 362016.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 251.40 100.00 25140.00 M-209
Air entraining and water reducing plasticiser Lit 150.84 75.00 11313.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 703.92 95.00 66872.40 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 40.00 120000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7299.00
(a+b+c)

Page 60 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 5 per cent of cost of material and labour towards cost 36032.69
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 20 % on (a+b+c) 182364.49


e) Contractor's profit @ 10% on (a+b+c+d) 109418.70
cost of 120 cum = a+b+c+d+e 1203605.66
Rate per cum = (a+b+c+d+e)/120 10030.05 6392
say 10030.00 56.91
12.11 Intermediate plug
Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5928.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1185.60
e) Contractor's profit @ 10% on (a+b+c+d) 711.36
Rate per cum = (a+b+c+d+e) 7824.96 5180
say 7825.00 51.06
12.11 D (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6676.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1335.20
e) Contractor's profit @ 10% on (a+b+c+d) 801.12
Rate per cum = (a+b+c+d+e) 8812.32 5689
say 8812.00 54.90
'12.11 D Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6191.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1238.20
e) Contractor's profit @ 10% on (a+b+c+d) 742.92
Rate per cum = (a+b+c+d+e) 8172.12 5450
say 8172.00 49.94
12.11 D (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6937.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1387.40
e) Contractor's profit @ 10% on (a+b+c+d) 832.44
Rate per cum = (a+b+c+d+e) 9156.84 5957
say 9157.00 53.72
'12.11 D Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6244.00
(a+b+c)

Page 61 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 20 % on (a+b+c) 1248.80
e) Contractor's profit @ 10% on (a+b+c+d) 749.28
Rate per cum = (a+b+c+d+e) 8242.08 5504
say 8242.00 49.75
12.11 D (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 7010.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1402.00
e) Contractor's profit @ 10% on (a+b+c+d) 841.20
Rate per cum = (a+b+c+d+e) 9253.20 6038
say 9253.00 53.25
12.11 Top plug
Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5181.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1036.20
e) Contractor's profit @ 10% on (a+b+c+d) 621.72
Rate per cum = (a+b+c+d+e) 6838.92 4372
say 6839.00 56.43
'12.11 E Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5657.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1131.40
e) Contractor's profit @ 10% on (a+b+c+d) 678.84
Rate per cum = (a+b+c+d+e) 7467.24 4785
say 7467.00 56.05
'12.11 E Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6063.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1212.60
e) Contractor's profit @ 10% on (a+b+c+d) 727.56
Rate per cum = (a+b+c+d+e) 8003.16 5283
say 8003.00 51.49
12.11 E (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6835.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1367.00
e) Contractor's profit @ 10% on (a+b+c+d) 820.20
Rate per cum = (a+b+c+d+e) 9022.20 5865
say 9022.00 53.83
'12.11 E Grade M30 PCC
Same as Item 12.8(f) excluding formwork

Page 62 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6116.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1223.20
e) Contractor's profit @ 10% on (a+b+c+d) 733.92
Rate per cum = (a+b+c+d+e) 8073.12 5335
say 8073.00 51.32
12.11 E (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6883.00
(a+b+c)
d) Overhead charges @ 20 % on (a+b+c) 1376.60
e) Contractor's profit @ 10% on (a+b+c+d) 825.96
Rate per cum = (a+b+c+d+e) 9085.56 5914
say 9086.00 53.64
12.11 Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7200.00 36864.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 120.00 2457.60 M-208
Air entraining and water reducing plasticiser Lit 15.36 75.00 1152.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 95.00 6809.60 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 4 per cent of a+b+c 3492.62
d) Overhead charges @ 20 % on (a+b+c) 18161.63
e) Contractor's profit @ 10% on (a+b+c+d) 10896.98
cost of 15 cum = a+b+c+d+e 119866.78
Rate per cum = (a+b+c+d+e)/15 7991.12 5045
say 7991.00 58.39
12.11 F (i) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7200.00 294624.00 M-084

Page 63 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 163.68 120.00 19641.60 M-208
Air entraining and water reducing plasticiser Lit 122.76 75.00 9207.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 572.88 95.00 54423.60 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 4 per cent of (a+b+c) 31533.21
d) Overhead charges @ 20 % on (a+b+c) 163972.71
e) Contractor's profit @ 10% on (a+b+c+d) 98383.62
cost of 120 cum = a+b+c+d+e 1082219.86
Rate per cum = (a+b+c+d+e)/120 9018.50 5646
say 9018.00 59.72
12.11 F RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7200.00 43560.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.25 100.00 3025.00 M-209
Air entraining and water reducing plasticiser Lit 18.15 75.00 1361.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 95.00 8046.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079

Page 64 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Form Work @ 3.75 per cent of a+b+c 3600.94
d) Overhead charges @ 20 % on (a+b+c) 19925.21
e) Contractor's profit @ 10% on (a+b+c+d) 11955.12
cost of 15 cum = a+b+c+d+e 131506.37
Rate per cum = (a+b+c+d+e)/15 8767.09 5618
say 8767.00 56.05
12.11 F (ii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7200.00 348480.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 242.00 100.00 24200.00 M-209
Air entraining and water reducing plasticiser Lit 145.20 75.00 10890.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.60 95.00 64372.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.75 per cent of ( a+b+c) 32189.10
d) Overhead charges @ 20 % on (a+b+c) 178113.04
e) Contractor's profit @ 10% on (a+b+c+d) 106867.83
cost of 120 cum = a+b+c+d+e 1175546.09
Rate per cum = (a+b+c+d+e)/120 9796.22 6220
say 9796.00 57.49
12.11 F RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051

Page 65 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 100.00 3050.00 M-209
Air entraining and water reducing plasticiser Lit 18.30 75.00 1372.50 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 95.00 8113.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3.5 per cent of (a+b+c) 3377.07
d) Overhead charges @ 20 % on (a+b+c) 19972.98
e) Contractor's profit @ 10% on (a+b+c+d) 11983.79
cost of 15 cum = a+b+c+d+e 131821.69
Rate per cum = (a+b+c+d+e)/15 8788.11 5635
say 8788.00 55.95
12.11 F (iii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7200.00 351288.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 243.95 100.00 24395.00 M-209
Air entraining and water reducing plasticiser Lit 146.37 75.00 10977.75 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.06 95.00 64890.70 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.5 per cent of (a+b+c) 30169.49
d) Overhead charges @ 20 % on (a+b+c) 178431.01
e) Contractor's profit @ 10% on (a+b+c+d) 107058.61

Page 66 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
cost of 120 cum = a+b+c+d+e 1177644.68
Rate per cum = (a+b+c+d+e)/120 9813.71 6236
say 9814.00 57.38
12.11 F RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 100.00 3165.00 M-209
Air entraining and water reducing plasticiser Lit 18.99 75.00 1424.25 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 95.00 8418.90 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3 per cent of (a+b+c) 2958.49
d) Overhead charges @ 20 % on (a+b+c) 20315.00
e) Contractor's profit @ 10% on (a+b+c+d) 12189.00
cost of 15 cum = a+b+c+d+e 134078.99
Rate per cum = (a+b+c+d+e)/15 8938.60 5750
say 8939.00 55.46
12.11 F (iv) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7200.00 364608.00 M-084
Coarse sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 253.20 100.00 25320.00 M-209
Air entraining and water reducing plasticiser Lit 151.92 75.00 11394.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 95.00 67351.20 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13

Page 67 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent of (a+b+c) 26373.22
d) Overhead charges @ 20 % on (a+b+c) 181096.11
e) Contractor's profit @ 10% on (a+b+c+d) 108657.66
cost of 120 cum = a+b+c+d+e 1195234.31
Rate per cum = (a+b+c+d+e)/120 9960.29 6348
say 9960.00 56.90
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7200.00 375840.00 M-084
Coarse Sand cum 54.00 950.00 51300.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 261.00 100.00 26100.00 M-209
Air entraining and water reducing plasticiser Lit 156.60 75.00 11745.00 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 730.80 95.00 69426.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 1341.00 8046.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 40.00 120000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent on cost of concrete i.e. cost of 26806.35
material, labour and machinery
d) Overhead charges @ 20 % on (a+b+c) 184070.29
e) Contractor's profit @ 10% on (a+b+c+d) 110442.18

Page 68 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
cost of 120 cum = a+b+c+d+e 1214863.94
Rate per cum = (a+b+c+d+e)/120 10123.87 6469
say 10124.00 56.50
12.12 Sinking of 6 m external diameter well (other than
pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reckon

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 6 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 356.65 42.80 L-12
Sinker ( skilled ) day 1.00 356.65 356.65 L-15
Sinking helper ( semi-skilled ) day 2.00 285.32 570.64 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 1185.00 2370.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 237.00
c) Overhead charges @ 20 % on (a+b) 715.42
d) Contractor's profit @ 10% on (a+b+c) 429.25
Rate per metre = (a+b+c+d) 4721.76 3857
say 4722.00 22.43
12.12 A Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 356.65 53.50 L-12
Sinker day 1.25 356.65 445.81 L-15
Sinking helper ( semi-skilled ) day 2.50 285.32 713.30 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1185.00 3555.00 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 355.50
c) Overhead charges @ 20 % on (a+b) 1024.62
d) Contractor's profit @ 10% on (a+b+c) 614.77
Rate per metre = (a+b+c+d) 6762.51 5682
say 6763.00 19.02
12.12 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 7101.00
12th m 5% 7456.00
13th m 5% 7829.00
14th m 5% 8220.00
15th m 5% 8631.00
16th m 5% 9063.00

Page 69 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
17th m 5% 9516.00
18th m 5% 9992.00
19th m 5% 10492.00
20th m 5% 11017.00
Total Cost from 10m upto 20m 89317.00 7504.00
Avg Rate per metre 8932.00 19.03
12.12 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 11843.00 14212.00 1.08


22nd m 7.5% 12731.00 15277.00
23rd m 7.5% 13686.00 16423.00
24th m 7.5% 14712.00 17654.00
25th m 7.5% 15815.00 18978.00
26th m 7.5% 17001.00 20401.00
27th m 7.5% 18276.00 21931.00
28th m 7.5% 19647.00 23576.00
29th m 7.5% 21121.00 25345.00
30th m 7.5% 22705.00 27246.00
Total Cost from 20m upto 30m 167537.00 201043.00 14076.00 16891
Avg Rate per metre 16754.00 20104.00 19.03 19.02
12.12 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

31st m 10% 24976.00 29971.00


32nd 10% 27474.00 32969.00
33rd m 10% 30221.00 36265.00
34th m 10% 33243.00 39892.00
35th m 10% 36567.00 43880.00
36th m 10% 40224.00 48269.00
37th m 10% 44246.00 53095.00
38th m 10% 48671.00 58405.00
39th m 10% 53538.00 64246.00
40th m 10% 58892.00 70670.00
Total Cost from 30m upto 40m 398052.00 477662.00 33442.00 40130.00
Avg Rate per metre 39805.00 47766.00 19.03 19.03
12.12 Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 356.65 53.50 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15

Page 70 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Sinking helper ( semi-skilled ) day 2.25 285.32 641.97 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1185.00 3555.00 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 355.50
c) Overhead charges @ 20 % on (a+b) 1028.19
d) Contractor's profit @ 10% on (a+b+c) 616.91
Rate per metre = (a+b+c+d) 6786.04 5683
say 6786.00 19.41
12.12 B Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 356.65 107.00 L-12
Sinker day 3.00 356.65 1069.95 L-15
Sinking helper ( semi-skilled ) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 284.00 568.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 767.80
c) Overhead charges @ 20 % on (a+b) 2181.34
d) Contractor's profit @ 10% on (a+b+c) 1308.80
Rate per metre = (a+b+c+d) 14396.82 12190
say 14397.00 18.11
12.12 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 15117.00 15873.00


12th m 5% 15873.00 16667.00
13th m 5% 16667.00 17500.00
14th m 5% 17500.00 18375.00
15th m 5% 18375.00 19294.00
16th m 5% 19294.00 20259.00
17th m 5% 20259.00 21272.00
18th m 5% 21272.00 22336.00
19th m 5% 22336.00 23453.00
20th m 5% 23453.00 24626.00
Total Cost from 10m upto 20m 190146.00 199655.00 16030.00 16906.00
Avg Rate per metre 19015.00 19966.00 18.62 18.10
12.12 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering of the cost, if required

Page 71 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 25212.00 31515.00 33091.00
22nd m 7.5% 27103.00 33879.00 35573.00
23rd m 7.5% 29136.00 36420.00 38241.00
24th m 7.5% 31321.00 39151.00 41109.00
25th m 7.5% 33670.00 42088.00 44192.00
26th m 7.5% 36195.00 45244.00 47506.00
27th m 7.5% 38910.00 48638.00 51070.00
28th m 7.5% 41828.00 52285.00 54899.00
29th m 7.5% 44965.00 56206.00 59016.00
30th m 7.5% 48337.00 60421.00 63442.00
Total Cost from 20m upto 30m 356677.00 445847.00 468139.00
Avg Rate per metre 35668.00 44585.00 46814.00
30201.00 37751.00 39639.00
18.1% 18.1% 18.1%
12.12 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 53171.00 63805.00 66995.00
32nd 10% 58488.00 70186.00 73695.00
33rd m 10% 64337.00 77204.00 81064.00
34th m 10% 70771.00 84925.00 89171.00
35th m 10% 77848.00 93418.00 98089.00
36th m 10% 85633.00 102760.00 107898.00
37th m 10% 94196.00 113035.00 118687.00
38th m 10% 103616.00 124339.00 130556.00
39th m 10% 113978.00 136774.00 143613.00
40th m 10% 125376.00 150451.00 157974.00
Total Cost from 30m upto 40m 847414.00 1016897.00 1067742.00
Avg Rate per metre 84741.00 101690.00 106774.00
71752.00 86103.00 90408.00
18.1% 18.1% 18.1%
12.12 Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 356.65 328.12 L-12
Sinker ( skilled ) day 3.00 356.65 1069.95 L-15
Sinking helper ( semi-skilled ) day 20.00 285.32 5706.40 L-14
Diver day 0.50 356.65 178.33 L-07

Page 72 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1185.00 4740.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 284.00 994.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 573.40
Add for dewatering @ of 5 per cent of (a+b), if 679.51
required
c) Overhead charges @ 20 % on (a+b) 2853.94
d) Contractor's profit @ 10% on (a+b+c) 1712.36
Rate per metre = (a+b+c+d) 18836.01 12174
say 18836.00 54.72%
12.12 Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 72.00 288.00 M-104
Electric Detonators each 18.00 15.00 270.00 M-097/100
b) Labour
Mate day 1.56 356.65 556.37 L-12
Driller day 2.00 356.65 713.30 L-07
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 12.00 244.56 2934.72 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 284.00 568.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 669.91
Consumables in sinking @ 10 per cent of cost of (b). 767.80
d) Overhead charges @ 20 % on (a+b+c) 3078.77
e) Contractor's profit @ 10% on (a+b+c+d) 1847.26
Rate per metre = (a+b+c+d+e) 20319.90 15114
say 20320.00 34.44%
12.13 Sinking of 7 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 356.65 53.50 L-12

Page 73 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Sinker ( skilled ) day 1.25 356.65 445.81 L-15
Sinking helper ( semi-skilled ) day 2.50 285.32 713.30 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 1185.00 3851.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 385.13
c) Overhead charges @ 20 % on (a+b) 1089.80
d) Contractor's profit @ 10% on (a+b+c) 544.90
Rate per metre = (a+b+c+d) 7083.68 6019
say 7084.00 17.69%
12.13 A Beyond 3m upto 10m depth
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 356.65 64.20 L-12
Sinker day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1185.00 5332.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 533.25
c) Overhead charges @ 20 % on (a+b) 1464.18
d) Contractor's profit @ 10% on (a+b+c) 878.51
Rate per metre = (a+b+c+d) 9663.56 8366
say 9664.00 15.52%
12.13 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 10147.00
12th m 5% 10654.00
13th m 5% 11187.00
14th m 5% 11746.00
15th m 5% 12333.00
16th m 5% 12950.00
17th m 5% 13598.00
18th m 5% 14278.00
19th m 5% 14992.00
20th m 5% 15742.00
Total Cost from 10m upto 20m 127627.00 11049.00
Avg Rate per metre 12763.00 15.28
12.13 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge

21st m 7.5% 16923.00 20308.00


22nd m 7.5% 18192.00 21830.00
23rd m 7.5% 19556.00 23467.00
24th m 7.5% 21023.00 25228.00
25th m 7.5% 22600.00 27120.00

Page 74 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
26th m 7.5% 24295.00 29154.00
27th m 7.5% 26117.00 31340.00
28th m 7.5% 28076.00 33691.00
29th m 7.5% 30182.00 36218.00
30th m 7.5% 32446.00 38935.00
Total Cost from 20m upto 30m 239410.00 287291.00 20726.00 24871.00
Avg Rate per metre 23941.00 28729.00 15.51 15.51
12.13 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 35691.00 42829.00


32nd 10% 39260.00 47112.00
33rd m 10% 43186.00 51823.00
34th m 10% 47505.00 57006.00
35th m 10% 52256.00 62707.00
36th m 10% 57482.00 68978.00
37th m 10% 63230.00 75876.00
38th m 10% 69553.00 83464.00
39th m 10% 76508.00 91810.00
40th m 10% 84159.00 100991.00
Total Cost from 30m upto 40m 568830.00 682596.00 49243.00 59092.00
Avg Rate per metre 56883.00 68260.00 15.51 15.51
12.13 Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 356.65 64.20 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1185.00 5332.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 533.25
d) Overhead charges @ 20 % on (a+b) 1464.18
e) Contractor's profit @ 10% on (a+b+c) 878.51
Rate per metre = (a+b+c+d) 9663.56 8366.00
say 9664.00 15.52
12.13 B Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 356.65 92.73 L-12
Sinker day 2.00 356.65 713.30 L-15
Sinking helper ( semi-skilled ) day 4.00 285.32 1141.28 L-14
b) Machinery

Page 75 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 284.00 923.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 803.30
c) Overhead charges @ 20 % on (a+b) 2156.72
d) Contractor's profit @ 10% on (a+b+c) 1294.03
Rate per metre = (a+b+c+d) 14234.36 12191.00
say 14234.00 16.76
12.13 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 14946.00 15693.00


12th m 5% 15693.00 16478.00
13th m 5% 16478.00 17302.00
14th m 5% 17302.00 18167.00
15th m 5% 18167.00 19075.00
16th m 5% 19075.00 20029.00
17th m 5% 20029.00 21030.00
18th m 5% 21030.00 22082.00
19th m 5% 22082.00 23186.00
20th m 5% 23186.00 24345.00
Total Cost from 10m upto 20m 187988.00 197387.00 16101.00 16907.00
Avg Rate per metre 18799.00 19739.00 16.76 16.75
12.13 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 24925.00 31156.00 32714.00
32nd 7.5% 26794.00 33493.00 35168.00
33rd m 7.5% 28804.00 36005.00 37805.00
34th m 7.5% 30964.00 38705.00 40640.00
35th m 7.5% 33286.00 41608.00 43688.00
36th m 7.5% 35782.00 44728.00 46964.00
37th m 7.5% 38466.00 48083.00 50487.00
38th m 7.5% 41351.00 51689.00 54273.00
39th m 7.5% 44452.00 55565.00 58343.00
40th m 7.5% 47786.00 59733.00 62720.00
Total Cost from 30m upto 40m 352610.00 440765.00 462802.00
Avg Rate per metre 35261.00 44077.00 46280.00
30203.00 37754.00 39641.00

Page 76 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.75 16.75 16.75
12.13 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 52565.00 63078.00 66232.00
32nd 10% 57822.00 69386.00 72855.00
33rd m 10% 63604.00 76325.00 80141.00
34th m 10% 69964.00 83957.00 88155.00
35th m 10% 76960.00 92352.00 96970.00
36th m 10% 84656.00 101587.00 106666.00
37th m 10% 93122.00 111746.00 117333.00
38th m 10% 102434.00 122921.00 129067.00
39th m 10% 112677.00 135212.00 141973.00
40th m 10% 123945.00 148734.00 156171.00
Total Cost from 30m upto 40m 837749.00 1005298.00 1055563.00
Avg Rate per metre 83775.00 100530.00 105556.00
71757.00 86108.00 90414.00
16.75 16.75 16.75
12.13 Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 356.65 206.86 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 10.00 285.32 2853.20 L-14
Diver day 0.75 356.65 267.49 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1185.00 5332.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 284.00 1065.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 639.75
Add for dewatering @ of 5 per cent of (a+b), if 557.58
required
c) Overhead charges @ 20 % on (a+b) 2469.80
d) Contractor's profit @ 10% on (a+b+c) 1481.88
Rate per metre = (a+b+c+d) 16300.65 11905.00
say 16301.00 36.93%
12.13 Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material

Page 77 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Gelatine 80 per cent Kg 7.00 72.00 504.00 M-104
Electric Detonators each 30.00 15.00 450.00 M-097/100
b) Labour
Mate day 1.60 356.65 570.64 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 18.00 244.56 4402.08 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
Diver day 0.50 356.65 178.33 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 284.00 568.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 752.91
Consumables in sinking @ 10 per cent of cost of (b). 843.09
d) Overhead charges @ 20 % on (a+b+c) 3521.62
e) Contractor's profit @ 10% on (a+b+c+d) 2112.97
Rate per metre = (a+b+c+d+e) 23242.70 16551.00
say 23243.00 40.43%
12.14 Sinking of 8 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 356.65 64.20 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1185.00 4740.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 474.00
c) Overhead charges @ 20 % on (a+b) 1333.83
d) Contractor's profit @ 10% on (a+b+c) 800.30
Rate per metre = (a+b+c+d) 8803.25 7506.00
say 8803.00 17.28%
12.14 A Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 356.65 89.16 L-12
Sinker day 1.75 356.65 624.14 L-15
Sinking helper ( semi-skilled ) day 3.50 285.32 998.62 L-14

Page 78 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1185.00 5925.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 592.50
c) Overhead charges @ 20 % on (a+b) 1645.88
d) Contractor's profit @ 10% on (a+b+c) 987.53
Rate per metre = (a+b+c+d) 10862.83 9337.00
say 10863.00 16.34%
12.14 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 11406.00
12th m 5% 11976.00
13th m 5% 12575.00
14th m 5% 13204.00
15th m 5% 13864.00
16th m 5% 14557.00
17th m 5% 15285.00
18th m 5% 16049.00
19th m 5% 16851.00
20th m 5% 17694.00
Total Cost from 10m upto 20m 143461.00 12331.00
Avg Rate per metre 14346.00 16.34%
12.14 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 19021.00 22825.00


22nd m 7.5% 20448.00 24538.00
23rd m 7.5% 21982.00 26378.00
24th m 7.5% 23631.00 28357.00
25th m 7.5% 25403.00 30484.00
26th m 7.5% 27308.00 32770.00
27th m 7.5% 29356.00 35227.00
28th m 7.5% 31558.00 37870.00
29th m 7.5% 33925.00 40710.00
30th m 7.5% 36469.00 43763.00
Total Cost from 20m upto 30m 269101.00 322922.00 23130.00 27756.00
Avg Rate per metre 26910.00 32292.00 16.34 16.34
12.14 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 40116.00 48139.00


32nd 10% 44128.00 52954.00
33rd m 10% 48541.00 58249.00

Page 79 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
34th m 10% 53395.00 64074.00
35th m 10% 58735.00 70482.00
36th m 10% 64609.00 77531.00
37th m 10% 71070.00 85284.00
38th m 10% 78177.00 93812.00
39th m 10% 85995.00 103194.00
40th m 10% 94595.00 113514.00
Total Cost from 30m upto 40m 639361.00 767233.00 54952.00 65942.00
Avg Rate per metre 63936.00 76723.00 16.35 16.35

12.14 Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 356.65 78.46 L-12
Sinker ( skilled ) day 2.00 356.65 713.30 L-15
Sinking helper ( semi-skilled ) hour 3.50 285.32 998.62 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1185.00 6517.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 651.75
c) Overhead charges @ 20 % on (a+b) 1791.93
d) Contractor's profit @ 10% on (a+b+c) 1075.16
Rate per metre = (a+b+c+d) 11826.72 10226.00
say 11827.00 15.66
12.14 B Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 356.65 114.13 L-12
Sinker day 2.50 356.65 891.63 L-15
Sinking helper ( semi-skilled ) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 284.00 994.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 810.40
c) Overhead charges @ 20 % on (a+b) 2240.82
d) Contractor's profit @ 10% on (a+b+c) 1344.49
Rate per metre = (a+b+c+d) 14789.40 12744.00
say 14789.00 16.05
12.14 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 80 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 15529.00 16305.00


12th m 5% 16305.00 17120.00
13th m 5% 17120.00 17976.00
14th m 5% 17976.00 18875.00
15th m 5% 18875.00 19819.00
16th m 5% 19819.00 20810.00
17th m 5% 20810.00 21851.00
18th m 5% 21851.00 22944.00
19th m 5% 22944.00 24091.00
20th m 5% 24091.00 25296.00
Total Cost from 10m upto 20m 195320.00 205087.00 16833.00 17674.00
Avg Rate per metre 19532.00 20509.00 16.03 16.04
12.14 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 25898.00 32373.00 33992.00
32nd 7.5% 27840.00 34800.00 36540.00
33rd m 7.5% 29928.00 37410.00 39281.00
34th m 7.5% 32173.00 40216.00 42227.00
35th m 7.5% 34586.00 43233.00 45395.00
36th m 7.5% 37180.00 46475.00 48799.00
37th m 7.5% 39969.00 49961.00 52459.00
38th m 7.5% 42967.00 53709.00 56394.00
39th m 7.5% 46190.00 57738.00 60625.00
40th m 7.5% 49654.00 62068.00 65171.00
Total Cost from 30m upto 40m 366385.00 457983.00 480883.00
Avg Rate per metre 36639.00 45798.00 48088.00
31574.00 39467.00 41441.00
16.04 16.04 16.04
12.14 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 54619.00 65543.00 68820.00
32nd 10% 60081.00 72097.00 75702.00
33rd m 10% 66089.00 79307.00 83272.00

Page 81 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
34th m 10% 72698.00 87238.00 91600.00
35th m 10% 79968.00 95962.00 100760.00
36th m 10% 87965.00 105558.00 110836.00
37th m 10% 96762.00 116114.00 121920.00
38th m 10% 106438.00 127726.00 134112.00
39th m 10% 117082.00 140498.00 147523.00
40th m 10% 128790.00 154548.00 162275.00
Total Cost from 30m upto 40m 870492.00 1044591.00 1096820.00
Avg Rate per metre 87049.00 104459.00 109682.00
75013.00 90015.00 94516.00
16.05% 16.05% 16.05%
12.14 Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 356.65 242.52 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 12.00 285.32 3423.84 L-14
Diver day 1.00 356.65 356.65 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1185.00 5925.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 284.00 1065.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 699.00
Add for dewatering @ of 5 per cent of (a+b), if 656.93
required
c) Overhead charges @ 20 % on (a+b) 2759.11
d) Contractor's profit @ 10% on (a+b+c) 1655.47
Rate per metre = (a+b+c+d) 18210.12 13195.00
say 18210.00 38.01%
12.14 Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 72.00 576.00 M-104
Electric Detonators each 32.00 15.00 480.00 M-097/100
b) Labour
Mate day 1.09 356.65 388.75 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 20.00 244.56 4891.20 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.

Page 82 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire & running charges of compressor with pneumatic hour 2.00 284.00 568.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 759.35
Consumables in sinking @ 10 per cent of cost of (b). 750.90
d) Overhead charges @ 20 % on (a+b+c) 3550.65
e) Contractor's profit @ 10% on (a+b+c+d) 2130.39
Rate per metre = (a+b+c+d+e) 23434.31 16053.00
say 23434.00 45.98%
12.15 Sinking of 9 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 356.65 67.76 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.25 285.32 927.29 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1185.00 4740.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 474.00
c) Overhead charges @ 20 % on (a+b) 1348.81
d) Contractor's profit @ 10% on (a+b+c) 809.28
Rate per metre = (a+b+c+d) 8902.12 7541.00
say 8902.00 18.05%
12.15 A Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 356.65 96.30 L-12
Sinker day 1.75 356.65 624.14 L-15
Sinking helper ( semi-skilled ) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1185.00 6517.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 651.75
c) Overhead charges @ 20 % on (a+b) 1806.19
d) Contractor's profit @ 10% on (a+b+c) 1083.72
Rate per metre = (a+b+c+d) 11920.87 10266.00
say 11921.00 16.12%
12.15 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12517.00

Page 83 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12th m 5% 13143.00
13th m 5% 13800.00
14th m 5% 14490.00
15th m 5% 15215.00
16th m 5% 15976.00
17th m 5% 16775.00
18th m 5% 17614.00
19th m 5% 18495.00
20th m 5% 19420.00
Total Cost from 10m upto 20m 157445.00 13559.00
Avg Rate per metre 15745.00 16.12%
12.15 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 20876.50 25052.00


22nd m 7.5% 22442.00 26930.00
23rd m 7.5% 24125.00 28950.00
24th m 7.5% 25934.00 31121.00
25th m 7.5% 27879.00 33455.00
26th m 7.5% 29970.00 35964.00
27th m 7.5% 32218.00 38662.00
28th m 7.5% 34634.00 41561.00
29th m 7.5% 37232.00 44678.00
30th m 7.5% 40024.00 48029.00
Total Cost from 20m upto 30m 295334.50 354402.00 25430.00 30516.00
Avg Rate per metre 29533.00 35440.00 16.13% 16.14%
12.15 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 44026.40 52832.00


32nd 10% 48429.00 58115.00
33rd m 10% 53272.00 63926.00
34th m 10% 58599.00 70319.00
35th m 10% 64459.00 77351.00
36th m 10% 70905.00 85086.00
37th m 10% 77996.00 93595.00
38th m 10% 85796.00 102955.00
39th m 10% 94376.00 113251.00
40th m 10% 103814.00 124577.00
Total Cost from 30m upto 40m 701672.40 842007.00 60417.00 72501.00
Avg Rate per metre 70167.00 84201.00 16.14% 16.14%
12.15 Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum

Page 84 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 356.65 85.60 L-12
Sinker ( skilled ) day 2.25 356.65 802.46 L-15
Sinking helper ( semi-skilled ) day 3.75 285.32 1069.95 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1185.00 6813.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 681.38
c) Overhead charges @ 20 % on (a+b) 1890.63
d) Contractor's profit @ 10% on (a+b+c) 1134.38
Rate per metre = (a+b+c+d) 12478.14 10726.00
say 12478.00 16.33%
12.15 B Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 356.65 121.26 L-12
Sinker day 2.50 356.65 891.63 L-15
Sinking helper ( semi-skilled ) day 5.00 285.32 1426.60 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1185.00 7702.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 284.00 1065.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 876.75
c) Overhead charges @ 20 % on (a+b) 2416.75
d) Contractor's profit @ 10% on (a+b+c) 1450.05
Rate per metre = (a+b+c+d) 15950.53 13777.00
say 15951.00 15.78%
12.15 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 16749.00 17586.00


12th m 5% 17586.00 18465.00
13th m 5% 18465.00 19388.00
14th m 5% 19388.00 20357.00
15th m 5% 20357.00 21375.00
16th m 5% 21375.00 22444.00
17th m 5% 22444.00 23566.00
18th m 5% 23566.00 24744.00
19th m 5% 24744.00 25981.00
20th m 5% 25981.00 27280.00
Total Cost from 10m upto 20m 210655.00 221186.00 18194.00 19104.00
Avg Rate per metre 21066.00 22119.00 15.79% 15.78%

Page 85 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.15 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 27930.00 34913.00 36659.00
32nd 7.5% 30025.00 37531.00 39408.00
33rd m 7.5% 32277.00 40346.00 42363.00
34th m 7.5% 34698.00 43373.00 45542.00
35th m 7.5% 37300.00 46625.00 48956.00
36th m 7.5% 40098.00 50123.00 52629.00
37th m 7.5% 43105.00 53881.00 56575.00
38th m 7.5% 46338.00 57923.00 60819.00
39th m 7.5% 49813.00 62266.00 65379.00
40th m 7.5% 53549.00 66936.00 70283.00
Total Cost from 30m upto 40m 395133.00 493917.00 518613.00
Avg Rate per metre 39513.00 49392.00 51861.00
34127.00 42659.00 44792.00
15.78% 15.78% 15.78%
12.15 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 58904.00 70685.00 74219.00
32nd 10% 64794.00 77753.00 81641.00
33rd m 10% 71273.00 85528.00 89804.00
34th m 10% 78400.00 94080.00 98784.00
35th m 10% 86240.00 103488.00 108662.00
36th m 10% 94864.00 113837.00 119529.00
37th m 10% 104350.00 125220.00 131481.00
38th m 10% 114785.00 137742.00 144629.00
39th m 10% 126264.00 151517.00 159093.00
40th m 10% 138890.00 166668.00 175001.00
Total Cost from 30m upto 40m 938764.00 1126518.00 1182843.00
Avg Rate per metre 93876.00 112652.00 118284.00
81083.00 97299.00 102165.00
15.78% 15.78% 15.78%
12.15 Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour

Page 86 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.76 356.65 271.05 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 14.00 285.32 3994.48 L-14
Diver day 1.20 356.65 427.98 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1185.00 7702.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 284.00 1136.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 883.85
Add for dewatering @ of 5 per cent of (a+b), if 792.12
required
c) Overhead charges @ 20 % on (a+b) 3326.92
d) Contractor's profit @ 10% on (a+b+c) 1996.15
Rate per metre = (a+b+c+d) 21957.66 17121.00
say 21958.00 28.25%
12.15 Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 72.00 720.00 M-104
Electric Detonators each 40.00 15.00 600.00 M-097/100
b) Labour
Mate day 1.17 356.65 417.28 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 22.00 244.56 5380.32 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
Diver day 1.00 356.65 356.65 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1185.00 8295.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 284.00 710.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 869.42
Consumables in sinking @ 10 per cent of cost of (b). 838.33
d) Overhead charges @ 20 % on (a+b+c) 4083.21
e) Contractor's profit @ 10% on (a+b+c+d) 2449.93
Rate per metre = (a+b+c+d+e) 26949.20 18731.00
say 26949.00 43.87%
12.16 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 1 m

Page 87 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Diameter of well - 10 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 356.65 71.33 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.50 285.32 998.62 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1185.00 5925.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 592.50
c) Overhead charges @ 20 % on (a+b) 1624.49
d) Contractor's profit @ 10% on (a+b+c) 974.69
Rate per metre = (a+b+c+d) 10721.60 9295.00
say 10722.00 15.35%
12.16 A Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 356.65 110.56 L-12
Sinker day 2.00 356.65 713.30 L-15
Sinking helper ( semi-skilled ) day 4.25 285.32 1212.61 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1185.00 6813.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 681.38
c) Overhead charges @ 20 % on (a+b) 1906.32
d) Contractor's profit @ 10% on (a+b+c) 1143.79
Rate per metre = (a+b+c+d) 12581.71 10769.00
say 12582.00 16.84%
12.16 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 13211.00
12th m 5% 13872.00
13th m 5% 14566.00
14th m 5% 15294.00
15th m 5% 16059.00
16th m 5% 16862.00
17th m 5% 17705.00
18th m 5% 18590.00
19th m 5% 19520.00
20th m 5% 20496.00
Total Cost from 10m upto 20m 166175.00 14223.00
Avg Rate per metre 16618.00 16.84%
12.16 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 88 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 22033.00 26440.00


22nd m 7.5% 23685.00 28422.00
23rd m 7.5% 25461.00 30553.00
24th m 7.5% 27371.00 32845.00
25th m 7.5% 29424.00 35309.00
26th m 7.5% 31631.00 37957.00
27th m 7.5% 34003.00 40804.00
28th m 7.5% 36553.00 43864.00
29th m 7.5% 39294.00 47153.00
30th m 7.5% 42241.00 50689.00
Total Cost from 20m upto 30m 311696.00 374036.00 26678.00 32014.00
Avg Rate per metre 31170.00 37404.00 16.84% 16.84%
12.16 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 46465.00 55758.00


32nd 10% 51112.00 61334.00
33rd m 10% 56223.00 67468.00
34th m 10% 61845.00 74214.00
35th m 10% 68030.00 81636.00
36th m 10% 74833.00 89800.00
37th m 10% 82316.00 98779.00
38th m 10% 90548.00 108658.00
39th m 10% 99603.00 119524.00
40th m 10% 109563.00 131476.00
Total Cost from 30m upto 40m 740538.00 888647.00 63382.00 76059.00
Avg Rate per metre 74054.00 88865.00 16.84% 16.84%
12.16 Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 356.65 89.16 L-12
Sinker ( skilled ) day 2.50 356.65 891.63 L-15
Sinking helper ( semi-skilled ) day 5.50 285.32 1569.26 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 711.00
c) Overhead charges @ 20 % on (a+b) 2074.21
d) Contractor's profit @ 10% on (a+b+c) 1244.53
Rate per metre = (a+b+c+d) 13689.78 11420.00
say 13690.00 19.88%

Page 89 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.16 B Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 356.65 142.66 L-12
Sinker day 3.00 356.65 1069.95 L-15
Sinking helper ( semi-skilled ) day 5.50 285.32 1569.26 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 284.00 1136.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 824.60
c) Overhead charges @ 20 % on (a+b) 2370.49
d) Contractor's profit @ 10% on (a+b+c) 1422.30
Rate per metre = (a+b+c+d) 15645.26 13162.00
say 15645.00 18.86%
12.16 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 16428.00 17249.00


12th m 5% 17249.00 18111.00
13th m 5% 18111.00 19017.00
14th m 5% 19017.00 19968.00
15th m 5% 19968.00 20966.00
16th m 5% 20966.00 22014.00
17th m 5% 22014.00 23115.00
18th m 5% 23115.00 24271.00
19th m 5% 24271.00 25485.00
20th m 5% 25485.00 26759.00
Total Cost from 10m upto 20m 206624.00 216955.00 17383.00 18252.00
Avg Rate per metre 20662.00 21696.00 18.86% 18.87%
12.16 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 27396.00 34245.00 35957.00
32nd 7.5% 29451.00 36814.00 38655.00
33rd m 7.5% 31660.00 39575.00 41554.00
34th m 7.5% 34035.00 42544.00 44671.00
35th m 7.5% 36588.00 45735.00 48022.00
36th m 7.5% 39332.00 49165.00 51623.00

Page 90 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
37th m 7.5% 42282.00 52853.00 55496.00
38th m 7.5% 45453.00 56816.00 59657.00
39th m 7.5% 48862.00 61078.00 64132.00
40th m 7.5% 52527.00 65659.00 68942.00
Total Cost from 30m upto 40m 387586.00 484484.00 508709.00
Avg Rate per metre 38759.00 48448.00 50871.00
Previous SOR Rate 32607.00 40759.00 42797.00
% variation 18.87% 18.86% 18.87%
12.16 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 57780.00 69336.00 72803.00
32nd 10% 63558.00 76270.00 80084.00
33rd m 10% 69914.00 83897.00 88091.85
34th m 10% 76905.00 92286.00 96900.30
35th m 10% 84596.00 101515.00 106590.75
36th m 10% 93056.00 111667.00 117250.35
37th m 10% 102362.00 122834.00 128975.70
38th m 10% 112598.00 135118.00 141873.90
39th m 10% 123858.00 148630.00 156061.50
40th m 10% 136244.00 163493.00 171667.65
Total Cost from 30m upto 40m 920871.00 1105046.00 1160299.00
Avg Rate per metre 92087.00 110505.00 116030.00
Previous SOR Rate 77474.00 97614.00 92965.00
% variation 18.86% 13.21% 24.81%
12.16 Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 356.65 306.72 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 16.00 285.32 4565.12 L-14
Diver day 1.40 356.65 499.31 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1185.00 8295.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 284.00 1207.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 950.20
Add for dewatering @ 5 per cent of cost, if required 522.61
c) Overhead charges @ 20 % on (a+b) 3554.51
d) Contractor's profit @ 10% on (a+b+c) 2132.71
Rate per metre = (a+b+c+d) 23459.78 17535.00

Page 91 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 23460.00 33.79%
12.16 Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 72.00 792.00 M-104
Electric Detonators each. 44.00 15.00 660.00 M-097/100
b) Labour
Mate day 1.27 356.65 452.95 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 24.00 244.56 5869.44 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1185.00 10072.50 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 284.00 852.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 546.23
Consumables in sinking @ 10 per cent of cost of 2002.22
(b+c).
d) Overhead charges @ 20 % on (a+b+c) 4695.28
e) Contractor's profit @ 10% on (a+b+c+d) 2817.17
Rate per metre = (a+b+c+d+e) 30988.84 22931.00
say 30989.00 35.14%
12.17 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 356.65 74.90 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper (semi-skilled) day 3.30 285.32 941.56 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 711.00
d) Overhead charges @ 20 % on (a+b+c) 1874.49
e) Contractor's profit @ 10% on (a+b+c+d) 1124.69
Cost for 0.5m = a+b+c+d 12371.60

Page 92 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per metre = (a+b+c+d)/0.50 24743.21 21983.00
say 24743.00 12.56%
12.17 A Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 356.65 114.13 L-12
Sinker day 2.00 356.65 713.30 L-15
Sinking helper (semi-skilled) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1185.00 4740.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 474.00
c) Overhead charges @ 20 % on (a+b+c) 1465.07
d) Contractor's profit @ 10% on (a+b+c+d) 879.04
Cost for 0.5m = a+b+c+d 9669.49
Rate per metre = (a+b+c+d)/0.50 19338.97 15585.00
say 19339.00 24.09%
12.17 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 20306.00
12th m 5% 21321.00
13th m 5% 22387.00
14th m 5% 23506.00
15th m 5% 24681.00
16th m 5% 25915.00
17th m 5% 27211.00
18th m 5% 28572.00
19th m 5% 30001.00
20th m 5% 31501.00
Total Cost from 10m upto 20m 255401.00 20583.00
Avg Rate per metre 25540.00 24.08%
12.17 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 33864.00 40637.00


22nd m 7.5% 36404.00 43685.00
23rd m 7.5% 39134.00 46961.00
24th m 7.5% 42069.00 50483.00
25th m 7.5% 45224.00 54269.00
26th m 7.5% 48616.00 58339.00
27th m 7.5% 52262.00 62714.00
28th m 7.5% 56182.00 67418.00
29th m 7.5% 60396.00 72475.00
30th m 7.5% 64926.00 77911.00
Total Cost from 20m upto 30m 479077.00 574892.00 38608.00 46330.00

Page 93 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Avg Rate per metre 47908.00 57489.00 24.09% 24.09%
12.17 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 71419.00 85703.00


32nd 10% 78561.00 94273.00
33rd m 10% 86417.00 103700.00
34th m 10% 95059.00 114071.00
35th m 10% 104565.00 125478.00
36th m 10% 115022.00 138026.00
37th m 10% 126524.00 151829.00
38th m 10% 139176.00 167011.00
39th m 10% 153094.00 183713.00
40th m 10% 168403.00 202084.00
Total Cost from 30m upto 40m 1138240.00 1365888.00 91725.00 110071.00
Avg Rate per metre 113824.00 136589.00 24.09% 24.09%
12.17 Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 356.65 92.73 L-12
Sinker ( skilled ) day 2.50 356.65 891.63 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1185.00 5925.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 592.50
c) Overhead charges @ 20 % on (a+b) 1728.63
d) Contractor's profit @ 10% on (a+b+c) 1037.18
Cost for 0.5m = a+b+c+d 11408.94
Rate per metre = (a+b+c+d)/0.50 22817.87 19011.00
say 22818.00 20.03%
12.17 B Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 356.65 153.36 L-12
Sinker day 3.50 356.65 1248.28 L-15
Sinking helper (semi-skilled) day 5.75 285.32 1640.59 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 284.00 1207.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 831.70
c) Overhead charges @ 20 % on (a+b) 2438.18

Page 94 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Contractor's profit @ 10% on (a+b+c) 1462.91
Cost for 0.5m = a+b+c+d 16092.02
Rate per metre = (a+b+c+d)/0.50 32184.04 26740.00
say 32184.00 20.36%
12.17 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 33793.00 35483.00


12th m 5% 35483.00 37257.00
13th m 5% 37257.00 39120.00
14th m 5% 39120.00 41076.00
15th m 5% 41076.00 43130.00
16th m 5% 43130.00 45287.00
17th m 5% 45287.00 47551.00
18th m 5% 47551.00 49929.00
19th m 5% 49929.00 52425.00
20th m 5% 52425.00 55046.00
Total Cost from 10m upto 20m 425051.00 446304.00 35315.00 37081.00
Avg Rate per metre 42505.00 44630.00 20.36% 20.36%
12.17 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 56357.00 70446.00 73968.00
32nd 7.5% 60584.00 75730.00 79517.00
33rd m 7.5% 65128.00 81410.00 85481.00
34th m 7.5% 70013.00 87516.00 91892.00
35th m 7.5% 75264.00 94080.00 98784.00
36th m 7.5% 80909.00 101136.00 106193.00
37th m 7.5% 86977.00 108721.00 114157.00
38th m 7.5% 93500.00 116875.00 122719.00
39th m 7.5% 100513.00 125641.00 131923.00
40th m 7.5% 108051.00 135064.00 141817.00
Total Cost from 30m upto 40m 797296.00 996619.00 1046450.00
Avg Rate per metre 79730.00 99662.00 104645.00
Previous SOR Rate 66242.00 82802.00 86942.00
% variation 20.36% 20.36% 20.36%
12.17 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Page 95 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 118856.00 142627.00 149758.00
32nd 10% 130742.00 156890.00 164735.00
33rd m 10% 143816.00 172579.00 181208.00
34th m 10% 158198.00 189838.00 199330.00
35th m 10% 174018.00 208822.00 219263.00
36th m 10% 191420.00 229704.00 241189.00
37th m 10% 210562.00 252674.00 265308.00
38th m 10% 231618.00 277942.00 291839.00
39th m 10% 254780.00 305736.00 321023.00
40th m 10% 280258.00 336310.00 353126.00
Total Cost from 30m upto 40m 1894268 2273122 2386779
Avg Rate per metre 189427.00 227312.00 238678.00
Previous SOR Rate 157381.00 188857.00 198300.00
% variation 20.36% 20.36% 20.36%
12.17 Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 356.65 338.82 L-12
Sinker ( skilled ) day 4.25 356.65 1515.76 L-15
Sinking helper (semi-skilled) day 18.00 285.32 5135.76 L-14
Diver day 1.50 356.65 534.98 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1185.00 9480.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 284.00 1278.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 1075.80
Add for dewatering @ 5 per cent of cost, if required 591.69
c) Overhead charges @ 20 % on (a+b) 3990.16
d) Contractor's profit @ 10% on (a+b+c) 2394.10
Cost for 0.5m = a+b+c+d 26335.06
Rate per metre = (a+b+c+d)/0.50 52670.13 39560.00
say 52670.00 33.14%
12.17 Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 72.00 864.00 M-104
Electric Detonators each. 48.00 15.00 720.00 M-097/100
b) Labour
Mate day 1.35 356.65 481.48 L-12

Page 96 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 26.00 244.56 6358.56 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1185.00 11850.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 284.00 994.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 642.20
Consumables in sinking @ 10 per cent of cost of 2191.31
(b+c).
d) Overhead charges @ 20 % on (a+b+c) 5266.12
e) Contractor's profit @ 10% on (a+b+c+d) 3159.67
Cost for 0.5m = a+b+c+d 34756.41
Rate per metre = (a+b+c+d)/0.50 69512.81 52440.00
say 69513.00 32.56%
12.18 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
Sandy Soil
I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 356.65 78.46 L-12
Sinker ( skilled ) day 1.75 356.65 624.14 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1185.00 7110.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 711.00
c) Overhead charges @ 20 % on (a+b) 1932.98
d) Contractor's profit @ 10% on (a+b+c) 1159.79
Cost for 0.25m = a+b+c+d 12757.64
Rate per metre = (a+b+c+d)/0.25 51030.57 44473.00
say 51031.00 14.75%
12.18 A Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 356.65 131.96 L-12
Sinker day 2.50 356.65 891.63 L-15
Sinking helper (semi-skilled) day 4.75 285.32 1355.27 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1185.00 7702.50 P&M-075
0.75 cum capacity and accessories.

Page 97 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Consumables in sinking @10 per cent of (b) 770.25
c) Overhead charges @ 20 % on (a+b) 2170.32
d) Contractor's profit @ 10% on (a+b+c) 1302.19
Cost for 0.25m = a+b+c+d 14324.12
Rate per metre = (a+b+c+d)/0.25 57296.48 48810.00
say 57296.00 17.39%
12.18 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 60161.00
12th m 5% 63169.00
13th m 5% 66327.45
14th m 5% 69643.82
15th m 5% 73126.01
16th m 5% 76782.31
17th m 5% 80621.43
18th m 5% 84652.50
19th m 5% 88885.13
20th m 5% 93329.38
Total Cost from 10m upto 20m 756698.04 64463.00
Avg Rate per metre 75670.00 17.39%
12.18 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 100329.00 120395.00


22nd m 7.5% 107854.00 129425.00
23rd m 7.5% 115943.00 139132.00
24th m 7.5% 124639.00 149567.00
25th m 7.5% 133987.00 160784.00
26th m 7.5% 144036.00 172843.00
27th m 7.5% 154839.00 185807.00
28th m 7.5% 166452.00 199742.00
29th m 7.5% 178936.00 214723.00
30th m 7.5% 192356.00 230827.00
Total Cost from 20m upto 30m 1419371.00 1703245.00 120917.00 145100.00
Avg Rate per metre 141937.00 170325.00 17.38% 17.38%
12.18 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 211592.00 253910.00


32nd 10% 232751.00 279301.00
33rd m 10% 256026.00 307231.00
34th m 10% 281629.00 337955.00
35th m 10% 309792.00 371750.00

Page 98 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
36th m 10% 340771.00 408925.00
37th m 10% 374848.00 449818.00
38th m 10% 412333.00 494800.00
39th m 10% 453566.00 544279.00
40th m 10% 498923.00 598708.00
Total Cost from 30m upto 40m 3372231 4046677 287281.00 344738.00
Avg Rate per metre 337223.00 404668.00 17.38% 17.38%
12.18 Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 356.65 107.00 L-12
Sinker ( skilled ) day 3.00 356.65 1069.95 L-15
Sinking helper (semi-skilled) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1185.00 7406.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 740.63
c) Overhead charges @ 20 % on (a+b) 2121.55
d) Contractor's profit @ 10% on (a+b+c) 1272.93
Cost for 0.25m = a+b+c+d 14002.24
Rate per metre = (a+b+c+d)/0.25 56008.97 47181.00
say 56009.00 18.71%
12.18 B Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 356.65 171.19 L-12
Sinker day 3.75 356.65 1337.44 L-15
Sinking helper (semi-skilled) day 6.00 285.32 1711.92 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1185.00 9871.05 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 284.00 1278.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1114.91
c) Overhead charges @ 20 % on (a+b) 3096.90
d) Contractor's profit @ 10% on (a+b+c) 1858.14
Cost for 0.25m = a+b+c+d 20439.55
Rate per metre = (a+b+c+d)/0.25 81758.18 70226.00
say 81758.00 16.42%
12.18 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

Page 99 of 959
Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
11th m 5% 85846.00 90138.00
12th m 5% 90138.00 94645.00
13th m 5% 94645.00 99377.00
14th m 5% 99377.00 104346.00
15th m 5% 104346.00 109563.00
16th m 5% 109563.00 115041.00
17th m 5% 115041.00 120793.00
18th m 5% 120793.00 126833.00
19th m 5% 126833.00 133175.00
20th m 5% 133175.00 139834.00
Total Cost from 10m upto 20m 1079757.00 1133745.00 92747.00 97384.00
Avg Rate per metre 107976.00 113375.00 16.42% 16.42%
12.18 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 143163.00 178954.00 187902.00
32nd 7.5% 153900.00 192375.00 201994.00
33rd m 7.5% 165443.00 206804.00 217144.00
34th m 7.5% 177851.00 222314.00 233430.00
35th m 7.5% 191190.00 238988.00 250937.00
36th m 7.5% 205529.00 256911.00 269757.00
37th m 7.5% 220944.00 276180.00 289989.00
38th m 7.5% 237515.00 296894.00 311739.00
39th m 7.5% 255329.00 319161.00 335119.00
40th m 7.5% 274479.00 343099.00 360254.00
Total Cost from 30m upto 40m 2025343 2531680 2658265
Avg Rate per metre 202534.00 253168.00 265827.00
Previous SOR Rate 173969.00 217462.00 228335.00
% variation 16.42% 16.42% 16.42%
12.18 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 301927.00 362312.00 380428.00
32nd 10% 332120.00 398544.00 418471.00
33rd m 10% 365332.00 438398.00 460318.00
34th m 10% 401865.00 482238.00 506350.00
35th m 10% 442052.00 530462.00 556985.00
36th m 10% 486257.00 583508.00 612683.00
37th m 10% 534883.00 641860.00 673953.00

Page 100 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
38th m 10% 588371.00 706045.00 741347.00
39th m 10% 647208.00 776650.00 815483.00
40th m 10% 711929.00 854315.00 897031.00
Total Cost from 30m upto 40m 4811944 5774332 6063049
Avg Rate per metre 481194.00 577433.00 606305.00
Previous SOR Rate 413328.00 495994.00 520794.00
% variation 16.42% 16.42% 16.42%
12.18 Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 356.65 378.05 L-12
Sinker ( skilled ) day 4.50 356.65 1604.93 L-15
Sinking helper (semi-skilled) day 20.00 285.32 5706.40 L-14
Diver day 1.75 356.65 624.14 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1185.00 11850.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 284.00 1349.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1319.90
Add for dewatering @ 5 per cent, if required 725.95
c) Overhead charges @ 20 % on (a+b) 4711.67
d) Contractor's profit @ 10% on (a+b+c) 2827.00
Cost for 0.25m = a+b+c+d 31097.03
Rate per metre = (a+b+c+d)/0.25 124388.12 95456.00
say 124388.00 30.31%
12.18 Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 72.00 1008.00 M-104
Electric detonator each. 56.00 15.00 840.00 M-097/100
b) Labour
Mate day 1.44 356.65 513.58 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 28.00 244.56 6847.68 L-13
Mazdoor (Skilled) day 4.50 356.65 1604.93 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1185.00 14812.50 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 284.00 1136.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 797.43

Page 101 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Consumables in sinking @ 10 per cent of (c). 1674.59
d) Overhead charges @ 20 % on (a+b+c) 6007.43
e) Contractor's profit @ 10% on (a+b+c+d) 3604.46
Cost for 0.25m = a+b+c+d+e 39649.05
Rate per metre = (a+b+c+d+e)/0.25 158596.21 124920.00
say 158596.00 26.96%
12.19 Sinking of Twin D Type well (other than pneumatic
method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from be

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 356.65 71.33 L-12
Sinker ( skilled ) day 1.25 356.65 445.81 L-15
Sinking helper (semi-skilled) day 3.75 285.32 1069.95 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1185.00 6517.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 651.75
c) Overhead charges @ 20 % on (a+b) 1751.27
d) Contractor's profit @ 10% on (a+b+c) 1050.76
Rate per metre = (a+b+c+d) 11558.37 10155.00
say 11558.00 13.82%
12.19 A Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 356.65 107.00 L-12
Sinker day 1.50 356.65 534.98 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 1185.00 6967.80 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 696.78
c) Overhead charges @ 20 % on (a+b) 1889.57
d) Contractor's profit @ 10% on (a+b+c) 1133.74
Rate per metre = (a+b+c+d) 12471.14 10891.00
say 12471.00 14.51%
12.19 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 13095.00

Page 102 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12th m 5% 13750.00
13th m 5% 14438.00
14th m 5% 15160.00
15th m 5% 15918.00
16th m 5% 16714.00
17th m 5% 17550.00
18th m 5% 18428.00
19th m 5% 19349.00
20th m 5% 20316.00
Total Cost from 10m upto 20m 164718.00 14384.00
Avg Rate per metre 16472.00 14.52%
12.19 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 21840.00 26208.00


22nd m 7.5% 23478.00 28174.00
23rd m 7.5% 25239.00 30287.00
24th m 7.5% 27132.00 32558.00
25th m 7.5% 29167.00 35000.00
26th m 7.5% 31355.00 37626.00
27th m 7.5% 33707.00 40448.00
28th m 7.5% 36235.00 43482.00
29th m 7.5% 38953.00 46744.00
30th m 7.5% 41874.00 50249.00
Total Cost from 20m upto 30m 308980.00 370776.00 26981.00 32378.00
Avg Rate per metre 30898.00 37078.00 14.52% 14.52%
12.19 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 46061.00 55273.00


32nd 10% 50667.00 60800.00
33rd m 10% 55734.00 66881.00
34th m 10% 61307.00 73568.00
35th m 10% 67438.00 80926.00
36th m 10% 74182.00 89018.00
37th m 10% 81600.00 97920.00
38th m 10% 89760.00 107712.00
39th m 10% 98736.00 118483.00
40th m 10% 108610.00 130332.00
Total Cost from 30m upto 40m 734095.00 880913.00 64105.00 76927.00
Avg Rate per metre 73410.00 88091.00 14.52% 14.51%
12.19 Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter

Page 103 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 356.65 92.73 L-12
Sinker ( skilled ) day 2.50 356.65 891.63 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1185.00 7406.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 740.63
c) Overhead charges @ 20 % on (a+b) 2054.50
d) Contractor's profit @ 10% on (a+b+c) 1232.70
Rate per metre = (a+b+c+d) 13559.71 11656.00
say 13560.00 16.33%
12.19 B Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 356.65 160.49 L-12
Sinker day 3.25 356.65 1159.11 L-15
Sinking helper (semi-skilled) day 6.00 285.32 1711.92 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1185.00 7903.95 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 284.00 1278.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 918.20
c) Overhead charges @ 20 % on (a+b) 2626.33
d) Contractor's profit @ 10% on (a+b+c) 1575.80
Rate per metre = (a+b+c+d) 17333.80 14628.00
say 17334.00 18.50%
12.19 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 18200.00 19110.00


12th m 5% 19110.00 20066.00
13th m 5% 20066.00 21069.00
14th m 5% 21069.00 22122.00
15th m 5% 22122.00 23228.00
16th m 5% 23228.00 24389.00
17th m 5% 24389.00 25608.00
18th m 5% 25608.00 26888.00
19th m 5% 26888.00 28232.00
20th m 5% 28232.00 29644.00
Total Cost from 10m upto 20m 228912.00 240356.00 19320.00 20286.00
Avg Rate per metre 22891.00 24036.00 18.48% 18.49%

Page 104 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
12.19 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 30349.00 37936.00 39833.00
32nd 7.5% 32625.00 40781.00 42820.00
33rd m 7.5% 35072.00 43840.00 46032.00
34th m 7.5% 37702.00 47128.00 49484.00
35th m 7.5% 40530.00 50663.00 53196.00
36th m 7.5% 43570.00 54463.00 57186.00
37th m 7.5% 46838.00 58548.00 61475.00
38th m 7.5% 50351.00 62939.00 66086.00
39th m 7.5% 54127.00 67659.00 71042.00
40th m 7.5% 58187.00 72734.00 76371.00
Total Cost from 30m upto 40m 429351.00 536691.00 563525.00
Avg Rate per metre 42935.00 53669.00 56353.00
Previous SOR Rate 36239.00 45299.00 47563.00
% variation 18.48% 18.48% 18.48%
12.19 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 64006.00 76807.00 80647.00
32nd 10% 70407.00 84488.00 88712.00
33rd m 10% 77448.00 92938.00 97585.00
34th m 10% 85193.00 102232.00 107344.00
35th m 10% 93712.00 112454.00 118077.00
36th m 10% 103083.00 123700.00 129885.00
37th m 10% 113391.00 136069.00 142872.00
38th m 10% 124730.00 149676.00 157160.00
39th m 10% 137203.00 164644.00 172876.00
40th m 10% 150923.00 181108.00 190163.00
Total Cost from 30m upto 40m 1020096.00 1224116.00 1285321.00
Avg Rate per metre 102010.00 122412.00 128532.00
Previous SOR Rate 86096.00 103315.00 108481.00
% variation 18.48% 18.48% 18.48%
12.19 Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour

Page 105 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.86 356.65 306.72 L-12
Sinker ( skilled ) day 4.50 356.65 1604.93 L-15
Sinking helper (semi-skilled) day 15.00 285.32 4279.80 L-14
Diver day 1.50 356.65 534.98 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1185.00 9871.05 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 284.00 1704.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 1157.51
Add for dewatering @ 5 per cent, if required 636.63
c) Overhead charges @ 20 % on (a+b) 4019.12
d) Contractor's profit @ 10% on (a+b+c) 2411.47
Rate per metre = (a+b+c+d) 26526.19 20652.00
say 26526.00 28.44%
12.19 Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 72.00 720.00 M-104
Electric detonators each. 40.00 15.00 600.00 M-097/100
b) Labour
Mate day 1.34 356.65 477.91 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 25.00 244.56 6114.00 L-13
Mazdoor (Skilled) day 4.25 356.65 1515.76 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1185.00 11850.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 284.00 852.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 1080.61
Consumables in sinking @ 10 per cent of (b). 1378.26
d) Overhead charges @ 20 % on (a+b+c) 5078.20
e) Contractor's profit @ 10% on (a+b+c+d) 3046.92
Rate per metre = (a+b+c+d+e) 33516.12 25485.00
say 33516.00 31.51%
12.21 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 850.00 1020.00 M-006
b) Labour
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.30 244.56 73.37 L-13

Page 106 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Overhead charges @ 20 % on (a+b) 219.39
d) Contractor's profit @ 10% on (a+b+c) 131.63
Rate per cum (a+b+c+d) 1447.95 515.00
say 1448.00 181.17%
12.22 Providing Steel Liner 10 mm thick for Curbs and 6 mm
thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 60000.00 63000.00 M-179
b) Labour
Mate day 1.24 356.65 442.25 L-12
Fitter day 6.00 356.65 2139.90 L-07
Blacksmith day 5.00 356.65 1783.25 L-01
Welder day 5.00 458.55 2292.75 L-02
Mazdoor day 10.00 244.56 2445.60 L-13
Electrodes, cutting gas and other consumables @ 5 3150.00
per cent on cost a (a) above.
c) Overhead charges @ 20 % on (a+b) 15050.75
d) Contractor's profit @ 10% on (a+b+c) 9030.45
Rate for per MT (a+b+c+d) 99334.94 55457.00
say 99335.00 79.12%
12.23 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 6.62 8837.00 58500.94 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 1341.00 402.30 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 850.00 255.00 P&M-048
bore hole
Bentonite kg 300.00 12.00 3600.00 M-071
c) Labour

Page 107 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate/Supervisor day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
d) Overhead charges @ 20 % on (b+c) 6662.44
e) Contractor's profit @ 10% on (b+c+d) 3997.46
Cost for 15 m = a+b+c+d+d+e 102473.03
Rate per metre (a+b+c+d+e)/15 6831.54 5171.00
say 6832.00 32.12%
(A) With plasticiser
a) Materials
PCC Grade M35 cum 6.62 9772.00 64690.64 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 1341.00 402.30 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 850.00 255.00 P&M-048
bore hole
Bentonite kg 300.00 12.00 3600.00 M-071
c) Labour
Mate/Supervisor day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
d) Overhead charges @ 20 % on (b+c) 6662.44
e) Contractor's profit @ 10% on (b+c+d) 3997.46
Cost for 15 m = a+b+c+d+d+e 108662.73
Rate per metre (a+b+c+d+e)/15 7244.18 5584.00
say 7244.00 29.73%
12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications cl. no. 1100,1600 & 1700and removal of
excavated earth with all lifts and lead upto 1000 m.

Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 7.85 8837.00 69370.45 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )

Page 108 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 1341.00 536.40 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 850.00 340.00 P&M-048
bore hole
Bentonite kg 350.00 12.00 4200.00 M-071
c) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
d) Overhead charges @ 20 % on (b+c) 6852.14
e) Contractor's profit @ 10% on (b+c+d) 4111.28
Cost for 10 m = a+b+c+d+d+e 114594.58
Rate per metre (a+b+c+d+e)/10 11459.46 8505.00
say 11459.00 34.73%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 7.85 9772.00 76710.20 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 1341.00 536.40 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 850.00 340.00 P&M-048
bore hole
Bentonite kg 350.00 12.00 4200.00 M-071
c) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
d) Overhead charges @ 20 % on (b+c) 6852.14
e) Contractor's profit @ 10% on (b+c+d) 4111.28
Cost for 10 m = a+b+c+d+d+e 121934.33
Rate per metre (a+b+c+d+e)/10 12193.43 8900.00
say 12193.00 37.00%
12.25 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter

Page 109 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 9 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 10.17 8837.00 89872.29 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 1341.00 670.50 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 850.00 425.00 P&M-048
bore hole
Bentonite kg 385.00 12.00 4620.00 M-071
c) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
d) Overhead charges @ 20 % on (b+c) 7005.84
e) Contractor's profit @ 10% on (b+c+d) 4203.51
Cost for 9 m = a+b+c+d+d+e 136110.86
Rate per metre (a+b+c+d+e)/9 15123.43 10924.00
say 15123.00 38.44%
(A) With plasticiser
a) Materials
PCC Grade M35 cum 10.17 9772.00 99381.24 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 1341.00 670.50 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 850.00 425.00 P&M-048
bore hole
Bentonite kg 385.00 12.00 4620.00 M-071
c) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
d) Overhead charges @ 20 % on (b+c) 7005.84

Page 110 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Contractor's profit @ 10% on (b+c+d) 4203.51
Cost for 9 m = a+b+c+d+d+e 145619.81
Rate per metre (a+b+c+d+e)/9 16179.98 11981.00
say 16180.00 35.05%
12.26 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 17.66 8837.00 156061.42 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 85.00 13600.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 60.00 3000.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1000.00 6000.00 P&M-085
acting pile driving hammer complete with power unit
and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 356.65 42.80 L-12
Mazdoor day 3.00 244.56 733.68 L-13
e) Overhead charges @ 20 % on (b+c+d) 6007.80
f) Contractor's profit @ 10% on (b+c+d+e) 3604.68
Cost for 40 m = a+b+c+d+e 195712.87
Rate per metre (a+b+c+d+e)/40 4892.82 2995.00
say 4893.00 63.37%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 17.66 9772.00 172573.52 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 85.00 13600.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 60.00 3000.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1000.00 6000.00 P&M-085
acting pile driving hammer complete with power unit
and accessories..

Page 111 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 356.65 42.80 L-12
Mazdoor day 3.00 244.56 733.68 L-13
e) Overhead charges @ 20 % on (b+c+d) 6007.80
f) Contractor's profit @ 10% on (b+c+d+e) 3604.68
Cost for 40 m = a+b+c+d+e 212224.97
Rate per metre (a+b+c+d+e)/40 5305.62 3186.00
say 5306.00 66.54%
1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
12.27 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 23.55 8837.00 208111.35 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 85.00 13600.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 60.00 3000.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1000.00 6000.00 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
e) Overhead charges @ 20 % on (b+c+d) 6091.36
f) Contractor's profit @ 10% on (b+c+d+e) 3654.82
Cost for 30 m = a+b+c+d+e 248314.33
Rate per metre (a+b+c+d+e)/30 8277.14 3186.00

Page 112 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8277.00 159.79%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 23.55 9772.00 230130.60 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 85.00 13600.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 60.00 3000.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1000.00 6000.00 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
e) Overhead charges @ 20 % on (b+c+d) 6091.36
f) Contractor's profit @ 10% on (b+c+d+e) 3654.82
Cost for 30 m = a+b+c+d+e 270333.58
Rate per metre (a+b+c+d+e)/30 9011.12 5076.00
say 9011.00 77.52%
1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
12.28 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 22.61 8837.00 199804.57 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 85.00 13600.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124

Page 113 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
iii) Steel helmet on top of casing head during driving Kg 50.00 60.00 3000.00 M-173
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1000.00 6000.00 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
e) Overhead charges @ 20 % on (b+c+d) 6085.44
f) Contractor's profit @ 10% on (b+c+d+e) 3651.27
Cost for 20 m = a+b+c+d+e 239968.50
Rate per metre (a+b+c+d+e)/20 11998.42 5811.00
say 11998.00 106.47%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 22.61 9772.00 220944.92 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 85.00 13600.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet on top of casing head during driving Kg 50.00 60.00 3000.00 M-173
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1000.00 6000.00 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
e) Overhead charges @ 20 % on (b+c+d) 6085.44
f) Contractor's profit @ 10% on (b+c+d+e) 3651.27
Cost for 20 m = a+b+c+d+e 261108.85
Rate per metre (a+b+c+d+e)/20 13055.44 7351.00
say 13055.00 77.59%
1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
12.37 Pile Load Test on single Vertical Pile in accordance
with IS:2911(Part-IV)
Unit = 1 MT

Page 114 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 330.00 330.00 300.00
b) Lateral load test tonne 1.00 5500.00 5500.00 5000.00
Although, this item is incidental to work and is not required to
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
12.38 Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.12 7200.00 36864.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3075.81
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 15994.23
e) Contractor's profit @ 10% on (a+b+c+d) 9596.54
Cost for 15 cum = a+b+c+d+e 105561.90
Rate per metre (a+b+c+d+e)/15 7037.46 4305.00
say 7037.00 63.46%
12.38A Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.12 7200.00 36864.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080

Page 115 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3015.06
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 15678.30
e) Contractor's profit @ 10% on (a+b+c+d) 9406.98
Cost for 15 cum = a+b+c+d+e 103476.78
Rate per metre (a+b+c+d+e)/15 6898.45 4922.00
say 6898.00 40.15%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 RCC Grade M25
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3326.37
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17297.14
e) Contractor's profit @ 10% on (a+b+c+d) 10378.28
Cost for 15 cum = a+b+c+d+e 114161.12
Rate per metre (a+b+c+d+e)/15 7610.74 4719.00
say 7611.00 61.28%
12.38B Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10

Page 116 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3271.98
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17014.28
e) Contractor's profit @ 10% on (a+b+c+d) 10208.57
Cost for 15 cum = a+b+c+d+e 112294.28
Rate per metre (a+b+c+d+e)/15 7486.29 5350.00
say 7486.00 39.93%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 RCC Grade M30
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3358.05
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17461.88
e) Contractor's profit @ 10% on (a+b+c+d) 10477.13
Cost for 15 cum = a+b+c+d+e 115248.38
Rate per metre (a+b+c+d+e)/15 7683.23 4771.00
say 7683.00 61.04%
'12.38C Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084

Page 117 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3297.30
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17145.95
e) Contractor's profit @ 10% on (a+b+c+d) 10287.57
Cost for 15 cum = a+b+c+d+e 113163.26
Rate per metre (a+b+c+d+e)/15 7544.22 5388.00
say 7544.00 40.01%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3424.29
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17806.32
e) Contractor's profit @ 10% on (a+b+c+d) 10683.79
Cost for 15 cum = a+b+c+d+e 117521.74

Page 118 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per metre (a+b+c+d+e)/15 7834.78 4880.00
say 7835.00 60.55%
'12.38D Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3369.90
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17523.47
e) Contractor's profit @ 10% on (a+b+c+d) 10514.08
Cost for 15 cum = a+b+c+d+e 115654.89
Rate per metre (a+b+c+d+e)/15 7710.33 5512.00
say 7710.00 39.88%
12.38 Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification
including providing plasticiser ( Masterplast PL-1/SPl-2
0r its equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or its equivalent ) and
accelerating plasticiser ( Masterplast APCL or its
equuivalent)

RCC Grade M20


Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.12 7200.00 36864.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 92.00 1884.16 4lit/Ton
Air entraining and water reducing plasticiser Lit 15.36 59.80 918.53 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)

Page 119 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 75.00 5376.00 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3402.96
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17695.39
e) Contractor's profit @ 10% on (a+b+c+d) 10617.24
Cost for 15 cum = a+b+c+d+e 116789.61
Rate per metre (a+b+c+d+e)/15 7785.97 5053.00
say 7786.00 54.09%
12.38A Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.12 7200.00 36864.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 92.00 1884.16 4lit/Ton
Air entraining and water reducing plasticiser Lit 15.36 59.80 918.53 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 75.00 5376.00 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3342.21
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 17379.47
e) Contractor's profit @ 10% on (a+b+c+d) 10427.68
Cost for 15 cum = a+b+c+d+e 114704.49

Page 120 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per metre (a+b+c+d+e)/15 7646.97 5670.00
say 7647.00 34.87%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 RCC Grade M25
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 29.95 76.40 2288.18 M-209
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3712.46
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 19304.82
e) Contractor's profit @ 10% on (a+b+c+d) 11582.89
Cost for 15 cum = a+b+c+d+e 127411.78
Rate per metre (a+b+c+d+e)/15 8494.12 5602.00
say 8494.00 51.62%
12.38B Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.99 7200.00 43128.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 29.95 76.40 2288.18 M-209
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10

Page 121 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3658.07
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 19021.96
e) Contractor's profit @ 10% on (a+b+c+d) 11413.18
Cost for 15 cum = a+b+c+d+e 125544.94
Rate per metre (a+b+c+d+e)/15 8369.66 6234.00
say 8370.00 34.26%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 RCC Grade M30
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 76.40 2330.20 M-209
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3751.23
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 19506.42
e) Contractor's profit @ 10% on (a+b+c+d) 11703.85
Cost for 15 cum = a+b+c+d+e 128742.37
Rate per metre (a+b+c+d+e)/15 8582.82 5671.00

Page 122 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8583.00 51.35%
'12.38C Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.10 7200.00 43920.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 76.40 2330.20 M-209
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3690.48
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 19190.49
e) Contractor's profit @ 10% on (a+b+c+d) 11514.30
Cost for 15 cum = a+b+c+d+e 126657.25
Rate per metre (a+b+c+d+e)/15 8443.82 6288.00
say 8444.00 34.29%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 76.40 2418.06 M-209
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)

Page 123 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 3832.30
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 19927.96
e) Contractor's profit @ 10% on (a+b+c+d) 11956.77
Cost for 15 cum = a+b+c+d+e 131524.52
Rate per metre (a+b+c+d+e)/15 8768.30 5818.00
say 8768.00 50.70%
'12.38D Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.33 7200.00 45576.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-004
20 mm Aggregate cum 8.10 790.00 6399.00 M-053
10 mm Aggregate cum 5.40 960.00 5184.00 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 76.40 2418.06 M-209
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 244.56 244.56 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 1341.00 1005.75 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 40.00 15000.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 3777.90
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 20 % on (a+b+c) 19645.10
e) Contractor's profit @ 10% on (a+b+c+d) 11787.06
Cost for 15 cum = a+b+c+d+e 129657.68

Page 124 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per metre (a+b+c+d+e)/15 8643.85 6445.00
say 8644.00 34.12%
12.39 Levelling Course for Pile cap

Providing and laying of PCC M15 levelling course


100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
(A) Without plasticiser
a) Material
Cement tonne 4.13 7200.00 29736.00 M-084
Coarse sand cum 6.75 950.00 6412.50 M-005
40 mm aggregate cum 8.10 1500.00 12150.00 M-055
20 mm Aggregate cum 4.05 1777.00 7196.85 M-053
10 mm Aggregate cum 1.35 1916.00 2586.60 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
d) Overhead charges @ 20 % on (a+b+c) 13340.37
e) Contractor's profit @ 10% on (a+b+c+d) 8004.22
Cost for 15 cum = a+b+c+d+e 88046.44
Rate per metre (a+b+c+d+e)/15 5869.76 4206.00
say 5870.00 39.56%
12.40 Supplying, Fitting and Placing un-coated TMT bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.

Unit = 1 MT
Taking output = 1 MT
(A) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/
SAIL/ Esser Steel/ Jindal steel/ Shyam steel or
equivalent)
a) Material
TMT bars including5 per cent overlaps and wastage tonne 1.05 53667.00 56350.35 M-085
Binding wire Kg 6.00 85.00 510.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.00 244.56 1467.36 L-13
11877.49
7126.50
78391.46 46725.00
say 78391.00 67.77%
(B) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI
approved)
a) Material

Page 125 of 959


Analysisof SOR (Roads) 2017-18
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
TMT bars including5 per cent overlaps and wastage tonne 1.05 49667.00 52150.35 M-085_1

Binding wire Kg 6.00 85.00 510.00 M-072


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.00 244.56 1467.36 L-13
11037.49
6622.50
72847.46 42978.00
say 72847.00 69.50%
12.41 Supplying, fitting and placing un-coated Mild steel (IS:
1786 Fe-250) reinforcement complete in foundation as
per drawing and technical specification

Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.08 55637.00 60087.96 M-126
Binding wire Kg 6.00 85.00 510.00 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.43 356.65 153.36 L-12
Blacksmith day 2.25 458.55 1031.74 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 20 % on (a+b) 12674.54
d) Contractor's profit @ 10% on (a+b+c) 7604.72
Rate for per MT (a+b+c+d) 83651.96 42440.00
say 83652.00 97.11%

Page 126 of 959


Analysisof SOR (Roads) 2017-18
Chapter-13

CHAPTER-13
SUB-STRUCTURE

Sr No Description Unit Quantity Rate Rs Cost Rs

13.1 Brick masonry work in 1:3 in sub-structure complete


excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 8.00 4000.00
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 4904.00 1176.96
analysis)
b) Labour
Mate day 0.06 356.65 21.40
Mason day 0.80 458.55 366.84
Mazdoor day 0.80 244.56 195.65
Add for scaffolding @ 5 per cent of cost of material 288.04
and labour
c) Overhead charges @ 20 % on (a+b) 1209.78
d) Contractor's profit @ 10% on (a+b+c) 725.87
Rate per cum (a+b+c+d) 7984.53
say 7985.00
13.2 Pointing with cement mortar (1:3 ) on brick work in
substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 4904.00 147.12

b) Labour
Mate day 0.04 356.65 14.27
Mason day 0.50 458.55 229.28
Mazdoor day 0.50 244.56 122.28
c) Overhead charges @ 20 % on (a+b) 102.59
d) Contractor's profit @ 10% on (a+b+c) 61.55
Rate per 10 sqm (a+b+c+d) 677.08
Rate per sqm (a+b+c+d)/10 say 68.00
Scaffolding is already included in item 13.1 288.04
say 288.00
13.3 Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 4904.00 706.18
b) Labour
Mate day 0.04 356.65 14.27
Mason day 0.50 458.55 229.28
Mazdoor day 0.50 244.56 122.28
c) Overhead charges @ 20 % on (a+b) 214.40
d) Contractor's profit @ 10% on (a+b+c) 128.64
Rate per 10 sqm (a+b+c+d) 1415.04
Rate per sqm (a+b+c+d)/10 say 142.00

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

1.Scaffolding is already included in item no. 13.1 288.04


say 288.00
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.4 Stone masonry work in cement mortar 1:3 for
substructure complete as per drawing and Technical
Specifications
13.4 A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 470.00 470.00
Through and bond stone No 7.00 8.50 59.50
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 4904.00 1618.32
b) Labour
Mate day 0.10 356.65 35.67
Mason day 1.20 458.55 550.26
Mazdoor day 1.20 244.56 293.47
Add for scaffolding @ 5 per cent of cost of a) 151.36
Material and b) Labour
c) Overhead charges @ 20 % on (a+b) 635.72
d) Contractor's profit @ 10% on (a+b+c) 381.43
Rate per cum (a+b+c+d) 4195.72
say 4196.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 470.00 517.00
Through and bond stone each 7.00 8.50 59.50
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 4904.00 1471.20
b) Labour
Mate day 0.12 356.65 42.80
Mason day 1.50 458.55 687.83
Mazdoor day 1.50 244.56 366.84
Add for scaffolding @ 5 per cent of cost of material 157.26
and labour
c) Overhead charges @ 20 % on (a+b) 660.48
d) Contractor's profit @ 10% on (a+b+c) 396.29
Rate per cum (a+b+c+d) 4359.20
say 4359.00
13.4 C Ashlar masonry ( first sort )

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 590.00 654.90
Through and bond stone each 7.00 8.50 59.50
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 4904.00 1618.32
b) Labour for masonry work
Mate day 0.20 356.65 71.33
Mason day 2.50 458.55 1146.38
Mazdoor day 2.50 244.56 611.40
Add for scaffolding @ 5 per cent of cost of a) 208.09
Material and b) Labour
c) Overhead charges @ 20 % on (a+b) 873.98
d) Contractor's profit @ 10% on (a+b+c) 524.39
Rate per cum (a+b+c+d) 5768.29
say 5768.00
The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
13.5 Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

(N) Without Plasticiser


Unit = cum
Taking output = 1 cum
13.5 (N) A PCC Grade M15
Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 4546.00
(a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 454.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1000.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 600.07
Rate perm (a+b+c+d+e+f) 6600.79
say 6601.00
13.5 (N) B PCC Grade M20
Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 5021.00


(a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 502.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1104.62
f) Contractor's profit @ 10% on (a+b+c+d+e) 662.77
Rate perm (a+b+c+d+e+f) 7290.49
say 7290.00
13.5 (N) C PCC Grade M25
a Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5420.00


(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 542.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1192.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 715.44
Rate perm (a+b+c+d+e+f) 7869.84
say 7870.00
case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00


(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 630.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1387.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 832.79
Rate perm (a+b+c+d+e+f) 9160.67
13.5 (N) C say 9161.00
b Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5420.00


(a+b+c) of Item 12.8 (D) Case I
d) formwork

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 12 per cent of cost of material, labour and 12.00 650.40


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 108.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1235.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 741.46
Rate perm (a+b+c+d+e+f) 8156.02
say 8156.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00


(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 757.08
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 126.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1438.45
f) Contractor's profit @ 10% on (a+b+c+d+e) 863.07
Rate perm (a+b+c+d+e+f) 9493.78
13.5 (N) C say 9494.00
c Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5420.00


(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 813.00
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 216.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1289.96
f) Contractor's profit @ 10% on (a+b+c+d+e) 773.98
Rate perm (a+b+c+d+e+f) 8513.74
say 8514.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00


(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 946.35
machinery (a+b+c) for Formwork

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 4 per cent of cost of material, Labour and 4.00 252.36


machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1501.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 900.93
Rate perm (a+b+c+d+e+f) 9910.18
say 9910.00
13.5 (N) D PCC Grade M30
a Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5463.00


(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10% 546.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1201.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 721.12
Rate perm (a+b+c+d+e+f) 7932.28
say 7932.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00


(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 623.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1370.60
f) Contractor's profit @ 10% on (a+b+c+d+e) 822.36
Rate perm (a+b+c+d+e+f) 9045.96
13.5 (N) D say 9046.00
b Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5463.00


(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 655.56
machinery (a+b+c) for Formwork

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 2 per cent of cost of material, Labour and 2.00 109.26


machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1245.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 747.34
Rate perm (a+b+c+d+e+f) 8220.72
say 8221.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00


(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 747.60
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 124.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1420.44
f) Contractor's profit @ 10% on (a+b+c+d+e) 852.26
Rate perm (a+b+c+d+e+f) 9374.90
13.5 (N) D say 9375.00
c Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
mater
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5463.00


(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 819.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 218.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1300.19
f) Contractor's profit @ 10% on (a+b+c+d+e) 780.12
Rate perm (a+b+c+d+e+f) 8581.28
say 8581.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00


(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 934.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 249.20
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1482.74

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

f) Contractor's profit @ 10% on (a+b+c+d+e) 889.64


Rate perm (a+b+c+d+e+f) 9786.08
say 9786.00
13.5 (N) E RCC Grade M20
a Height upto 5m
Case I Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5170.00


(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 517.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1137.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 682.44
Rate perm (a+b+c+d+e+f) 7506.84
say 7507.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00


(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 593.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1306.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 783.95
Rate perm (a+b+c+d+e+f) 8623.43
13.5 (N) E say 8623.00
b Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5170.00


(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 620.40
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 103.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1178.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 707.26
Rate perm (a+b+c+d+e+f) 7779.82

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

say 7780.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00


(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 712.68
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 118.78
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1354.09
f) Contractor's profit @ 10% on (a+b+c+d+e) 812.46
Rate perm (a+b+c+d+e+f) 8937.01
13.5 (N) E say 8937.00
c Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material,
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5170.00


(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 775.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 206.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1230.46
f) Contractor's profit @ 10% on (a+b+c+d+e) 738.28
Rate perm (a+b+c+d+e+f) 8121.04
say 8121.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00


(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 890.85
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 237.56
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1413.48
f) Contractor's profit @ 10% on (a+b+c+d+e) 848.09
Rate perm (a+b+c+d+e+f) 9328.98
say 6527.00
13.5 (N) F RCC Grade M25
a Height upto 5m

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Same as Item 12.8 (E) upto 5m height, excluding formwork.


For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5573.00


(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 557.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1226.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 735.64
Rate perm (a+b+c+d+e+f) 8092.00
say 8092.00
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6342.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 634.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1395.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 837.14
Rate perm (a+b+c+d+e+f) 9208.58
13.5 (N) F say 9209.00
b Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5573.00


(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 657.61
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 100.31
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1266.19
f) Contractor's profit @ 10% on (a+b+c+d+e) 759.71
Rate perm (a+b+c+d+e+f) 8356.82
say 8357.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6342.00


(a+b+c) of Item 12.8 (E) Case II
d) formwork

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 11.8 per cent of cost of material, labour and 11.80 748.36
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 114.16
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1440.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 864.54
Rate perm (a+b+c+d+e+f) 9509.96
13.5 (N) F say 9510.00
c Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5573.00


(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 835.95
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 222.92
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1326.37
f) Contractor's profit @ 10% on (a+b+c+d+e) 795.82
Rate perm (a+b+c+d+e+f) 8754.07
say 8754.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6342.00


(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 951.30
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 253.68
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1509.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 905.64
Rate perm (a+b+c+d+e+f) 9962.01
say 9962.00
13.5 (N) G RCC Grade M30
a Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5597.00


(a+b+c) of Item 12.8 (G) Case I
d) formwork

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 10 per cent of cost of material, labour and 10.00 559.70


machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1231.34
f) Contractor's profit @ 10% on (a+b+c+d+e) 738.80
Rate perm (a+b+c+d+e+f) 8126.84
say 8127.00
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6367.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 636.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1400.74
f) Contractor's profit @ 10% on (a+b+c+d+e) 840.44
Rate perm (a+b+c+d+e+f) 9244.88
13.5 (N) G say 9245.00
b Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5597.00


(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 643.66
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 89.55
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1266.04
f) Contractor's profit @ 10% on (a+b+c+d+e) 759.62
Rate perm (a+b+c+d+e+f) 8355.87
say 8356.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6367.00


(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 732.21
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 101.87
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1440.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 864.13
Rate perm (a+b+c+d+e+f) 9505.42
13.5 (N) G say 9505.00

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

c Height above 10m


For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5597.00


(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 839.55
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 195.90
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1326.49
f) Contractor's profit @ 10% on (a+b+c+d+e) 795.89
Rate perm (a+b+c+d+e+f) 8754.83
say 8755.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6367.00


(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 955.05
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 222.85
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1508.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 905.39
Rate perm (a+b+c+d+e+f) 9959.26
say 9959.00

13.5 (N) H RCC Grade M35


a Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5708.00


(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 570.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1255.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 753.46
Rate perm (a+b+c+d+e+f) 8288.02
say 8288.00

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6478.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 647.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1425.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 855.10
Rate perm (a+b+c+d+e+f) 9406.06
13.5 (N) H say 9406.00
b Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5708.00


(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 627.88
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 79.91
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1283.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 769.90
Rate perm (a+b+c+d+e+f) 8468.85
say 8469.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6478.00


(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 712.58
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 90.69
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1456.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 873.75
Rate perm (a+b+c+d+e+f) 9611.28
13.5 (N) H say 9611.00
c Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 5708.00


(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 742.04
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 171.24
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1324.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 794.55
Rate perm (a+b+c+d+e+f) 8740.09
say 8740.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6478.00


(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 842.14
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 194.34
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1502.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 901.74
Rate perm (a+b+c+d+e+f) 9919.11
say 9919.00
The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percent
(P) With plasticiser ( Masterplast PL-1 ), air entraining and
water reducing plasticiser ( Masterplast PAE )
conforming to IS: 1903-1999
Unit = cum
Taking output = 1 cum
13.5 (P) A PCC Grade M15
Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 5181.00
(a+b+c) of Item 12.8 (A)

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

d) formwork
Add 10 per cent of cost of material, labour and 10.00 518.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1139.82
f) Contractor's profit @ 10% on (a+b+c+d+e) 683.89
Rate perm (a+b+c+d+e+f) 7522.81
say 7523.00
13.5 (P) B PCC Grade M20
Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 5657.00
(a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 565.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1244.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 746.72
Rate perm (a+b+c+d+e+f) 8213.96
say 8214.00
13.5 (P) C PCC Grade M25
a Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6063.00


(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 606.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1333.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 800.32
Rate perm (a+b+c+d+e+f) 8803.48
say 8803.00
case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6835.00


(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 683.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1503.70
f) Contractor's profit @ 10% on (a+b+c+d+e) 902.22

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate perm (a+b+c+d+e+f) 9924.42


13.5 (P) C say 9924.00
b Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6063.00


(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 727.56
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 121.26
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1382.36
f) Contractor's profit @ 10% on (a+b+c+d+e) 829.42
Rate perm (a+b+c+d+e+f) 9123.60
say 9124.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00


(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 757.08
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 126.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1438.45
f) Contractor's profit @ 10% on (a+b+c+d+e) 863.07
Rate perm (a+b+c+d+e+f) 9493.78
13.5 (P) C say 9494.00
c Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6063.00


(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 909.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 242.52
machinery excluding formwork to cater for extra lift

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

e) Overhead charges @ 20 % on (a+b+c+d) 1442.99


f) Contractor's profit @ 10% on (a+b+c+d+e) 865.80
Rate perm (a+b+c+d+e+f) 9523.76
say 9524.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6835.00


(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 1025.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 273.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1626.73
f) Contractor's profit @ 10% on (a+b+c+d+e) 976.04
Rate perm (a+b+c+d+e+f) 10736.42
say 10736.00
13.5 (P) D PCC Grade M30
a Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6116.00


(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10% 611.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1345.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 807.31
Rate perm (a+b+c+d+e+f) 8880.43
say 8880.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00


(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 688.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1514.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 908.56
Rate perm (a+b+c+d+e+f) 9994.12
13.5 (P) D say 9994.00
b Height 5m to 10m

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6116.00


(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 733.92
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 122.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1394.45
f) Contractor's profit @ 10% on (a+b+c+d+e) 836.67
Rate perm (a+b+c+d+e+f) 9203.36
say 9203.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00


(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 825.96
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 137.66
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1569.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 941.59
Rate perm (a+b+c+d+e+f) 10357.54
13.5 (P) D say 10358.00
c Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
mater
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6116.00


(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 917.40
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 244.64
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1455.61
f) Contractor's profit @ 10% on (a+b+c+d+e) 873.36
Rate perm (a+b+c+d+e+f) 9607.01

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

say 9607.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00


(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 1032.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 275.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1638.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 982.89
Rate perm (a+b+c+d+e+f) 10811.82
say 10812.00
13.5 (P) E RCC Grade M20
a Height upto 5m
Case I Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5806.00


(a+b+c) of Item 12.8 (C) Case I

d) formwork
Add 10 per cent of cost of material, labour and 10.00 580.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1277.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 766.39
Rate perm (a+b+c+d+e+f) 8430.31
say 8430.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00


(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 657.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1446.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 867.77
Rate perm (a+b+c+d+e+f) 9545.45
13.5 (P) E say 9545.00
b Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5806.00


(a+b+c) of Item 12.8 (C) Case I

d) formwork
Add 12 per cent of cost of material, labour and 12.00 696.72
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 116.12
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1323.77
f) Contractor's profit @ 10% on (a+b+c+d+e) 794.26
Rate perm (a+b+c+d+e+f) 8736.87
say 8737.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00


(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 788.88
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 131.48
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1498.87
f) Contractor's profit @ 10% on (a+b+c+d+e) 899.32
Rate perm (a+b+c+d+e+f) 9892.56
13.5 (P) E say 9893.00
c Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material,
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5806.00


(a+b+c) of Item 12.8 (C) Case I

d) formwork
Add 15 per cent of cost of material, labour and 15.00 870.90
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 232.24
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1381.83
f) Contractor's profit @ 10% on (a+b+c+d+e) 829.10
Rate perm (a+b+c+d+e+f) 9120.06
say 9120.00

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00


(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 986.10
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 262.96
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1564.61
f) Contractor's profit @ 10% on (a+b+c+d+e) 938.77
Rate perm (a+b+c+d+e+f) 10326.44
say 10326.00
13.5 (P) F RCC Grade M25
a Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6223.00


(a+b+c) of Item 12.8 (E) Case I

d) formwork
Add 10 per cent of cost of material, labour and 10.00 622.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1369.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 821.44
Rate perm (a+b+c+d+e+f) 9035.80
say 9036.00
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6992.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 699.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1538.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 922.94
Rate perm (a+b+c+d+e+f) 10152.38
13.5 (P) F say 10152.00
b Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 6223.00


(a+b+c) of Item 12.8 (E) Case I

d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 734.31
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 112.01
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1413.87
f) Contractor's profit @ 10% on (a+b+c+d+e) 848.32
Rate perm (a+b+c+d+e+f) 9331.51
say 9332.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6992.00


(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 825.06
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 125.86
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1588.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 953.15
Rate perm (a+b+c+d+e+f) 10484.64
13.5 (P) F say 10485.00
c Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6223.00


(a+b+c) of Item 12.8 (E) Case I

d) formwork
Add 15 per cent of cost of material, labour and 15.00 933.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 248.92
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1481.07
f) Contractor's profit @ 10% on (a+b+c+d+e) 888.64
Rate perm (a+b+c+d+e+f) 9775.09
say 9775.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6992.00


(a+b+c) of Item 12.8 (E) Case II
d) formwork

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 15 per cent of cost of material, labour and 15.00 1048.80


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 279.68
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1664.10
f) Contractor's profit @ 10% on (a+b+c+d+e) 998.46
Rate perm (a+b+c+d+e+f) 10983.03
say 10983.00
13.5 (P) G RCC Grade M30
a Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6253.00


(a+b+c) of Item 12.8 (G) Case I

d) formwork
Add 10 per cent of cost of material, labour and 10.00 625.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1375.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 825.40
Rate perm (a+b+c+d+e+f) 9079.36
say 9079.00
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 7022.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 702.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1544.84
f) Contractor's profit @ 10% on (a+b+c+d+e) 926.90
Rate perm (a+b+c+d+e+f) 10195.94
13.5 (P) G say 10196.00
b Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6253.00


(a+b+c) of Item 12.8 (G) Case I

d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 719.10
machinery (a+b+c) for Formwork

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 1.6 per cent of cost of material, Labour and 1.60 100.05
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1414.43
f) Contractor's profit @ 10% on (a+b+c+d+e) 848.66
Rate perm (a+b+c+d+e+f) 9335.23
say 9335.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7022.00


(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 807.53
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 112.35
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1588.38
f) Contractor's profit @ 10% on (a+b+c+d+e) 953.03
Rate perm (a+b+c+d+e+f) 10483.28
13.5 (P) G say 10483.00
c Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6253.00


(a+b+c) of Item 12.8 (G) Case I

d) formwork
Add 14 per cent of cost of material, labour and 14.00 875.42
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 218.86
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1469.46
f) Contractor's profit @ 10% on (a+b+c+d+e) 881.67
Rate perm (a+b+c+d+e+f) 9698.40
say 9698.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7022.00


(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 983.08
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 245.77
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1650.17
f) Contractor's profit @ 10% on (a+b+c+d+e) 990.10

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate perm (a+b+c+d+e+f) 10891.12


say 10891.00
RCC Grade M35
Height upto 5m
13.5 (P) H Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
a Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6388.00


(a+b+c) of Item 12.8 (H) Case I

Case I d) formwork
Add 10 per cent of cost of material, labour and 10.00 638.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1405.36
f) Contractor's profit @ 10% on (a+b+c+d+e) 843.22
Rate perm (a+b+c+d+e+f) 9275.38
say 9275.00
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00


(a+b+c) of Item 12.8 (H) Case II
d) formwork
Case II Add 10 per cent of cost of material, labour and 10.00 715.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1574.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 944.86
Rate perm (a+b+c+d+e+f) 10393.42
say 10393.00
Height 5m to 10m
13.5 (P) H For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
b Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6388.00


(a+b+c) of Item 12.8 (H) Case I

Case I d) formwork
Add 11 per cent of cost of material, labour and 11.00 702.68
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 89.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1436.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 861.61
Rate perm (a+b+c+d+e+f) 9477.75
say 9478.00

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00


(a+b+c) of Item 12.8 (H) Case II
Case II d) formwork
Add 11 per cent of cost of material, labour and 11.00 787.38
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 100.21
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1609.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 965.47
Rate perm (a+b+c+d+e+f) 10620.18
say 10620.00
Height above 10m
13.5 (P) H For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
c Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6388.00


(a+b+c) of Item 12.8 (H) Case I

Case I d) formwork
Add 13 per cent of cost of material, labour and 13.00 830.44
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 191.64
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1482.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 889.21
Rate perm (a+b+c+d+e+f) 9781.31
say 9781.00
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00


(a+b+c) of Item 12.8 (H) Case II
Case II d) formwork
Add 13 per cent of cost of material, labour and 13.00 930.54
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 214.74
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1660.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 996.39
Rate perm (a+b+c+d+e+f) 10960.33
say 10960.00
The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percent
13.6 (a)Supplying, fitting and placing TMT bar
reinforcement in sub-structure complete as per
drawing and Technical Specifications
Output: MT
Taking output = 1 MT
(a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/
SAIL/ Esser Steel/ Jindal steel/ Shyam steel or
equivalent)

a) Material
TMT CRS bars including 5 per cent overlaps and tonne 1.05 53667.00 56350.35
wastage
Binding wire kg 6.00 85.00 510.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26
Blacksmith day 2.00 458.55 917.10
Mazdoor day 6.50 244.56 1589.64
c) Overhead charges @ 20 % on (a+b) 11897.67
d) Contractor's profit @ 10% on (a+b+c) 7138.60
Rate for per MT (a+b+c+d) 78524.62
say 78525.00
Output: MT
Taking output = 1 MT
(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI
approved)
a) Material
TMT bars including 5 per cent overlaps and wastage tonne 1.05 49667.00 52150.35
With TATA rebar

Binding wire kg 6.00 85.00 510.00


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26
Blacksmith day 2.00 458.55 917.10
Mazdoor day 6.50 244.56 1589.64
c) Overhead charges @ 20 % on (a+b) 11057.67
d) Contractor's profit @ 10% on (a+b+c) 6634.60

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate for per MT (a+b+c+d) 72980.62


say 72981.00

13.7 Supplying, fitting and placing un-coated Mild steel (IS:


1786 Fe-250) reinforcement complete in sub-structure
as per drawing and Technical Specification

Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.10 53667.00 59033.70
Binding wire kg 6.00 85.00 510.00
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.28 356.65 99.86
Blacksmith day 1.50 458.55 687.83
Mazdoor day 5.50 244.56 1345.08
c) Overhead charges @ 20 % on (a+b) 12335.29
d) Contractor's profit @ 10% on (a+b+c) 7401.18
Rate for per MT (a+b+c+d) 81412.94
say 81413.00
13.8 Providing weep holes in Brick masonry/Plain/
Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical

Unit = Nos.
Taking output = 30 Nos.
a) Material
PVC rain water pipe 100 mm dia. (including wastage @ metre 31.50 90.00 2835.00
5 per cent )
Average length of weep hole is taken as one metre for the
purpose of estimating.
MS clamp each. 30.00 19.00 570.00
Joint for pipe (average) taking 10% of above pipe rate each. 10.00 9.00 90.00

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.15 4904.00 735.60
b) Labour
Mate day 0.03 356.65 10.70
Mason day 0.50 458.55 229.28
Mazdoor day 0.25 244.56 61.14
c) Overhead charges @ 20 % on (a+b) 906.34
d) Contractor's profit @ 10% on (a+b+c) 543.81
Cost for 30 m = a+b+c+d 5981.86
Rate per m (a+b+c+d)/30 199.40

Page 29 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

say 199.00
1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work
and shall not be paid separately.
13.9 Back filling behind abutment, wing wall and return wall
complete as per drawing and Technical Specification

Unit = cum
Taking output = 10 cum
Granular material
a) Labour
Mate day 0.28 356.65 99.86
Mazdoor day 7.00 244.56 1711.92
b) Material
Granular material cum 12.00 698.00 8376.00
c) Machinery
Plate compactor/power rammer hour 2.50 218.00 545.00
Water Tanker hour 0.05 440.00 22.00
d) Overhead charges @ 20 % on (a+b+c) 2150.96
e) Contractor's profit @ 10% on (a+b+c+d) 1290.57
Cost for 10 cum of granular backfill = a+b+c+d+e 14196.31
Rate per cum = (a+b+c+d+e)/10 1419.63
say 1420.00
13.9 Sandy material
a) Labour
Mate day 0.28 356.65 99.86
Mazdoor for filling, watering, ramming etc. day 7.00 244.56 1711.92
b) Material
Sand cum 12.00 698.00 8376.00
c) Machinery
Plate compactor/power rammer hour 2.50 218.00 545.00
Water Tanker hour 0.06 440.00 26.40
d) Overhead charges @ 20 % on (a+b+c) 2151.84
e) Contractor's profit @ 10% on (a+b+c+d) 1291.10
Cost for 10 cum of sandy backfill = a+b+c+d+e 14202.12
Rate per cum = (a+b+c+d+e)/10 1420.21
say 1420.00

Page 30 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

13.10 Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger si

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 356.65 114.13
Mazdoor for filling, watering, ramming etc. day 7.00 244.56 1711.92
Mazdoor (Skilled) day 1.00 356.65 356.65
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1013.00 12156.00
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 440.00 26.40
d) Overhead charges @ 20 % on (a+b+c) 2873.02
e) Contractor's profit @ 10% on (a+b+c+d) 1723.81
cost for 10 cum of Fiter Media = a+b+c+d+e 18961.93
Rate per cum = (a+b+c+d+e)/10 1896.19
say 1896.00
13.11 Supplying, fitting and fixing in position true to line and
level cast steel rocker bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor (Skilled) day 0.50 356.65 178.33
Mazdoor day 1.00 244.56 244.56
b) Material
Cast steel rocker bearing assembly of 250 tonne each. 1.00 135850.00 135850.00
design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 1358.50
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 20 % on (a+b) 27530.56
d) Contractor's profit @ 10% on (a+b+c) 16518.33
cost for 250 tonnes capacity bearing = a+b+c+d 181701.67
Rate per tonne capacity = (a+b+c+d)/250 726.81
say 727.00

Page 31 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

13.12 Supplying, fitting and fixing in position true to line and


level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
Forged steel roller bearing of 250 tonne design load each. 1.00 117306.00 117306.00
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 1173.06
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 20 % on (a+b) 23784.67
d) Contractor's profit @ 10% on (a+b+c) 14270.80
cost for 250 tonnes capacity bearing = a+b+c+d 156978.81
Rate per tonne capacity = (a+b+c+d)/250 627.92
say 628.00
13.13 Supplying, fitting and fixing in position true to line and
level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as
per drawing and Technical Specifications and BS:
5400, section 9.1 & 9.2 (for PTFE)

Unit: one tonne capacity


Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
PTFE sliding plate bearing assembly of 80 tonnes each. 1.00 19760.00 19760.00
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and 197.60
consumables.
c) Overhead charges @ 20 % on (a+b) 4080.38
d) Contractor's profit @ 10% on (a+b+c) 2448.23
cost for 80 tonnes capacity bearing = a+b+c+d 26930.49
Rate per tonne capacity = (a+b+c+d)/80 336.63
say 337.00

Page 32 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

13.14 Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655
cu.cm.xRs4.4/cucm=Rs64482/-
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
Elastomeric bearing assembly consisting of 7 layers of each. 1.14 64482.00 73509.48
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 735.09
foundation anchorage bolts and consumables.
c) Overhead charges @ 20 % on (a+b) 14937.77
d) Contractor's profit @ 10% on (a+b+c) 8962.66
cost for 19200cc of elastomeric bearing = a+b+c+d 98589.29
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 5.13

say 5.13
13.15 Supplying, fitting and fixing in position true to line and
level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.75 244.56 183.42
Mazdoor (Skilled) day 0.35 356.65 124.83
b) Material
Supply of sliding plate bearing of 80 tonne design each. 1.00 11025.00 11025.00
capacity complete as per drawings and Technical
Specifications.

Page 33 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 1 per cent of cost of bearing assembly for 110.25


foundation anchorage bolts and consumables.
c) Overhead charges @ 20 % on (a+b) 2291.55
d) Contractor's profit @ 10% on (a+b+c) 1374.93
cost for 80 tonnes of capacity bearing = a+b+c+d 15124.25
189.05
say 189.00
13.16 Supplying, fitting and fixing in position true to line and
level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against stainles

Unit: one tonne capacity 387.20


Considering a Pot bearing assembly of 250 tonne capacity
for this analysis.
a) Labour
Mate day 0.08 356.65 28.53
Mazdoor day 1.50 244.56 366.84
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
Pot type bearing assembly consisting of a metal piston each. 1.00 39560.00 39560.00
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as
Add 1 per cent of cost of bearing assembly for 395.60
foundation anchorage bolts and consumables.
c) Overhead charges @ 20 % on (a+b) 8105.86
d) Contractor's profit @ 10% on (a+b+c) 4863.52
cost for 250 tonnes capacity bearing = a+b+c+d 53498.67
Rate per tonne capacity = (a+b+c+d)/250 213.99
say 214.00

Page 34 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

CHAPTER-13
SUB-STRUCTURE
Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

13.1 Brick masonry work in 1:3 in sub-structure complete


excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 8.00 4000.00 M-082
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 4904.00 1176.96 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.06 356.65 21.40 L-12
Mason day 0.80 458.55 366.84 L-11
Mazdoor day 0.80 244.56 195.65 L-13
Add for scaffolding @ 5 per cent of cost of material 288.04
and labour
c) Overhead charges @ 20 % on (a+b) 1209.78
d) Contractor's profit @ 10% on (a+b+c) 725.87
Rate per cum (a+b+c+d) 7984.53 3392.00
say 7985.00 135.41%
13.2 Pointing with cement mortar (1:3 ) on brick work in
substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 4904.00 147.12 Item 12.6 (A)

b) Labour
Mate day 0.04 356.65 14.27 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor day 0.50 244.56 122.28 L-13
c) Overhead charges @ 20 % on (a+b) 102.59
d) Contractor's profit @ 10% on (a+b+c) 61.55
Rate per 10 sqm (a+b+c+d) 677.08 30.00
Rate per sqm (a+b+c+d)/10 say 68.00 126.67%
Scaffolding is already included in item 13.1 288.04
say 288.00
13.3 Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 4904.00 706.18 Item 12.6 (A)
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor day 0.50 244.56 122.28 L-13
c) Overhead charges @ 20 % on (a+b) 214.40
d) Contractor's profit @ 10% on (a+b+c) 128.64
Rate per 10 sqm (a+b+c+d) 1415.04 72.00
Rate per sqm (a+b+c+d)/10 say 142.00 97.22%

Page 35 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

1.Scaffolding is already included in item no. 13.1 288.04


say 288.00
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.4 Stone masonry work in cement mortar 1:3 for
substructure complete as per drawing and Technical
Specifications
13.4 A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 470.00 470.00 M-148
Through and bond stone No 7.00 8.50 59.50 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 4904.00 1618.32 Item 12.6 (A)
b) Labour
Mate day 0.10 356.65 35.67 L-12
Mason day 1.20 458.55 550.26 L-11
Mazdoor day 1.20 244.56 293.47 L-13
Add for scaffolding @ 5 per cent of cost of a) 151.36
Material and b) Labour
c) Overhead charges @ 20 % on (a+b) 635.72
d) Contractor's profit @ 10% on (a+b+c) 381.43
Rate per cum (a+b+c+d) 4195.72 2514.00
say 4196.00 66.91%
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 470.00 517.00 M-148
Through and bond stone each 7.00 8.50 59.50 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 4904.00 1471.20 Item 12.6 (A)
b) Labour
Mate day 0.12 356.65 42.80 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 1.50 244.56 366.84 L-13
Add for scaffolding @ 5 per cent of cost of material 157.26
and labour
c) Overhead charges @ 20 % on (a+b) 660.48
d) Contractor's profit @ 10% on (a+b+c) 396.29
Rate per cum (a+b+c+d) 4359.20 2544.00
say 4359.00 71.34%
13.4 C Ashlar masonry ( first sort )

Page 36 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 590.00 654.90 M-169
Through and bond stone each 7.00 8.50 59.50 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 4904.00 1618.32 Item 12.6 (A)
b) Labour for masonry work
Mate day 0.20 356.65 71.33 L-12
Mason day 2.50 458.55 1146.38 L-11
Mazdoor day 2.50 244.56 611.40 L-13
Add for scaffolding @ 5 per cent of cost of a) 208.09
Material and b) Labour
c) Overhead charges @ 20 % on (a+b) 873.98
d) Contractor's profit @ 10% on (a+b+c) 524.39
Rate per cum (a+b+c+d) 5768.29 3209.00
say 5768.00 79.74%
The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
13.5 Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

(N) Without Plasticiser


Unit = cum
Taking output = 1 cum
13.5 (N) A PCC Grade M15
Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 4546.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A) M15 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 454.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1000.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 600.07
Rate perm (a+b+c+d+e+f) 6600.79 4005.00
say 6601.00 64.82%
13.5 (N) B PCC Grade M20
Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.

Page 37 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Per Cum Basic Cost of Labour, Material & Machinery 5021.00 Item 12.8 (B)
(a+b+c) of Item 12.8 (B) M20 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 502.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1104.62
f) Contractor's profit @ 10% on (a+b+c+d+e) 662.77
Rate perm (a+b+c+d+e+f) 7290.49 4458.00
say 7290.00 63.53%
13.5 (N) C PCC Grade M25
a Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5420.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 542.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1192.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 715.44
Rate perm (a+b+c+d+e+f) 7869.84 4875.00
say 7870.00 61.44%
case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 630.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1387.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 832.79
Rate perm (a+b+c+d+e+f) 9160.67 5516.00
13.5 (N) C say 9161.00 66.08%
b Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5420.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM
d) formwork

Page 38 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 12 per cent of cost of material, labour and 12.00 650.40


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 108.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1235.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 741.46
Rate perm (a+b+c+d+e+f) 8156.02 5053.00
say 8156.00 61.41%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB
d) formwork
Add 12 per cent of cost of material, labour and 12.00 757.08
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 126.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1438.45
f) Contractor's profit @ 10% on (a+b+c+d+e) 863.07
Rate perm (a+b+c+d+e+f) 9493.78 5717.00
13.5 (N) C say 9494.00 66.07%
c Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5420.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 813.00
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 216.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1289.96
f) Contractor's profit @ 10% on (a+b+c+d+e) 773.98
Rate perm (a+b+c+d+e+f) 8513.74 5275.00
say 8514.00 61.40%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 946.35
machinery (a+b+c) for Formwork

Page 39 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 4 per cent of cost of material, Labour and 4.00 252.36


machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1501.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 900.93
Rate perm (a+b+c+d+e+f) 9910.18 5967.00
say 9910.00 66.08%
13.5 (N) D PCC Grade M30
a Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5463.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10% 546.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1201.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 721.12
Rate perm (a+b+c+d+e+f) 7932.28 4912.00
say 7932.00 61.48%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 623.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1370.60
f) Contractor's profit @ 10% on (a+b+c+d+e) 822.36
Rate perm (a+b+c+d+e+f) 9045.96 5558.00
13.5 (N) D say 9046.00 62.76%
b Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5463.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM
d) formwork
Add 12 per cent of cost of material, labour and 12.00 655.56
machinery (a+b+c) for Formwork

Page 40 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 2 per cent of cost of material, Labour and 2.00 109.26


machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1245.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 747.34
Rate perm (a+b+c+d+e+f) 8220.72 5100.00
say 8221.00 61.20%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB
d) formwork
Add 12 per cent of cost of material, labour and 12.00 747.60
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 124.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1420.44
f) Contractor's profit @ 10% on (a+b+c+d+e) 852.26
Rate perm (a+b+c+d+e+f) 9374.90 5760.00
13.5 (N) D say 9375.00 62.76%
c Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
mater
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5463.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 819.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 218.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1300.19
f) Contractor's profit @ 10% on (a+b+c+d+e) 780.12
Rate perm (a+b+c+d+e+f) 8581.28 5323.00
say 8581.00 61.21%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6230.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 934.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 249.20
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1482.74

Page 41 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

f) Contractor's profit @ 10% on (a+b+c+d+e) 889.64


Rate perm (a+b+c+d+e+f) 9786.08 6013.00
say 9786.00 62.75%
13.5 (N) E RCC Grade M20
a Height upto 5m
Case I Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5170.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 517.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1137.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 682.44
Rate perm (a+b+c+d+e+f) 7506.84 4591.00
say 7507.00 63.52%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 593.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1306.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 783.95
Rate perm (a+b+c+d+e+f) 8623.43 5229.00
13.5 (N) E say 8623.00 64.91%
b Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5170.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM
d) formwork
Add 12 per cent of cost of material, labour and 12.00 620.40
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 103.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1178.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 707.26
Rate perm (a+b+c+d+e+f) 7779.82 4758.00

Page 42 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

say 7780.00 63.51%


Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB
d) formwork
Add 12 per cent of cost of material, labour and 12.00 712.68
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 118.78
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1354.09
f) Contractor's profit @ 10% on (a+b+c+d+e) 812.46
Rate perm (a+b+c+d+e+f) 8937.01 5419.00
13.5 (N) E say 8937.00 64.92%
c Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material,
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5170.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 775.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 206.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1230.46
f) Contractor's profit @ 10% on (a+b+c+d+e) 738.28
Rate perm (a+b+c+d+e+f) 8121.04 4967.00
say 8121.00 63.50%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5939.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 890.85
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 237.56
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1413.48
f) Contractor's profit @ 10% on (a+b+c+d+e) 848.09
Rate perm (a+b+c+d+e+f) 9328.98 5881.00
say 6527.00 10.98%
13.5 (N) F RCC Grade M25
a Height upto 5m

Page 43 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Same as Item 12.8 (E) upto 5m height, excluding formwork.


For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5573.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 557.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1226.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 735.64
Rate perm (a+b+c+d+e+f) 8092.00 5014.00
say 8092.00 61.39%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6342.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 634.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1395.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 837.14
Rate perm (a+b+c+d+e+f) 9208.58 5651.00
13.5 (N) F say 9209.00 62.96%
b Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5573.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 657.61
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 100.31
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1266.19
f) Contractor's profit @ 10% on (a+b+c+d+e) 759.71
Rate perm (a+b+c+d+e+f) 8356.82 5178.00
say 8357.00 61.39%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6342.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB
d) formwork

Page 44 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 11.8 per cent of cost of material, labour and 11.80 748.36
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 114.16
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1440.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 864.54
Rate perm (a+b+c+d+e+f) 9509.96 5836.00
13.5 (N) F say 9510.00 62.95%
c Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5573.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 835.95
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 222.92
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1326.37
f) Contractor's profit @ 10% on (a+b+c+d+e) 795.82
Rate perm (a+b+c+d+e+f) 8754.07 5424.00
say 8754.00 61.39%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6342.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 951.30
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 253.68
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1509.40
f) Contractor's profit @ 10% on (a+b+c+d+e) 905.64
Rate perm (a+b+c+d+e+f) 9962.01 6114.00
say 9962.00 62.94%
13.5 (N) G RCC Grade M30
a Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5597.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM
d) formwork

Page 45 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 10 per cent of cost of material, labour and 10.00 559.70


machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1231.34
f) Contractor's profit @ 10% on (a+b+c+d+e) 738.80
Rate perm (a+b+c+d+e+f) 8126.84 5038.00
say 8127.00 61.31%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6367.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 636.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1400.74
f) Contractor's profit @ 10% on (a+b+c+d+e) 840.44
Rate perm (a+b+c+d+e+f) 9244.88 5677.00
13.5 (N) G say 9245.00 62.85%
b Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5597.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 643.66
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 89.55
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1266.04
f) Contractor's profit @ 10% on (a+b+c+d+e) 759.62
Rate perm (a+b+c+d+e+f) 8355.87 5180.00
say 8356.00 61.31%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6367.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 732.21
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 101.87
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1440.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 864.13
Rate perm (a+b+c+d+e+f) 9505.42 5837.00
13.5 (N) G say 9505.00 62.84%

Page 46 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

c Height above 10m


For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5597.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 839.55
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 195.90
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1326.49
f) Contractor's profit @ 10% on (a+b+c+d+e) 795.89
Rate perm (a+b+c+d+e+f) 8754.83 5382.00
say 8755.00 62.67%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6367.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 955.05
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 222.85
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1508.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 905.39
Rate perm (a+b+c+d+e+f) 9959.26 6064.00
say 9959.00 64.23%

13.5 (N) H RCC Grade M35


a Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5708.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 570.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1255.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 753.46
Rate perm (a+b+c+d+e+f) 8288.02 5155.00
say 8288.00 60.78%

Page 47 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6478.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 647.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1425.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 855.10
Rate perm (a+b+c+d+e+f) 9406.06 5793.00
13.5 (N) H say 9406.00 62.37%
b Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5708.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM
d) formwork
Add 11 per cent of cost of material, labour and 11.00 627.88
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 79.91
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1283.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 769.90
Rate perm (a+b+c+d+e+f) 8468.85 5267.00
say 8469.00 60.79%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6478.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB
d) formwork
Add 11 per cent of cost of material, labour and 11.00 712.58
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 90.69
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1456.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 873.75
Rate perm (a+b+c+d+e+f) 9611.28 5920.00
13.5 (N) H say 9611.00 62.35%
c Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Page 48 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Per Cum Basic Cost of Labour, Material & Machinery 5708.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM
d) formwork
Add 13 per cent of cost of material, labour and 13.00 742.04
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 171.24
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1324.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 794.55
Rate perm (a+b+c+d+e+f) 8740.09 5436.00
say 8740.00 60.78%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6478.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB
d) formwork
Add 13 per cent of cost of material, labour and 13.00 842.14
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 194.34
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1502.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 901.74
Rate perm (a+b+c+d+e+f) 9919.11 6109.00
say 9919.00 62.37%
The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percent
(P) With plasticiser ( Masterplast PL-1 ), air entraining and
water reducing plasticiser ( Masterplast PAE )
conforming to IS: 1903-1999
Unit = cum
Taking output = 1 cum
13.5 (P) A PCC Grade M15
Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 5181.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A) M15 PC OBM P

Page 49 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

d) formwork
Add 10 per cent of cost of material, labour and 10.00 518.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1139.82
f) Contractor's profit @ 10% on (a+b+c+d+e) 683.89
Rate perm (a+b+c+d+e+f) 7522.81 4809.00
say 7523.00 56.44%
13.5 (P) B PCC Grade M20
Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 5657.00 Item 12.8 (B)
(a+b+c) of Item 12.8 (B) M20 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 565.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1244.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 746.72
Rate perm (a+b+c+d+e+f) 8213.96 5264.00
say 8214.00 56.04%
13.5 (P) C PCC Grade M25
a Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6063.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 606.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1333.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 800.32
Rate perm (a+b+c+d+e+f) 8803.48 5811.00
say 8803.00 51.49%
case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6835.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 683.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1503.70
f) Contractor's profit @ 10% on (a+b+c+d+e) 902.22

Page 50 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Rate perm (a+b+c+d+e+f) 9924.42 6451.00


13.5 (P) C say 9924.00 53.84%
b Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6063.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 727.56
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 121.26
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1382.36
f) Contractor's profit @ 10% on (a+b+c+d+e) 829.42
Rate perm (a+b+c+d+e+f) 9123.60 6022.00
say 9124.00 51.51%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6309.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 757.08
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 126.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1438.45
f) Contractor's profit @ 10% on (a+b+c+d+e) 863.07
Rate perm (a+b+c+d+e+f) 9493.78 6686.00
13.5 (P) C say 9494.00 42.00%
c Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6063.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 909.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 242.52
machinery excluding formwork to cater for extra lift

Page 51 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

e) Overhead charges @ 20 % on (a+b+c+d) 1442.99


f) Contractor's profit @ 10% on (a+b+c+d+e) 865.80
Rate perm (a+b+c+d+e+f) 9523.76 6286.00
say 9524.00 51.51%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6835.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 1025.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 273.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1626.73
f) Contractor's profit @ 10% on (a+b+c+d+e) 976.04
Rate perm (a+b+c+d+e+f) 10736.42 6979.00
say 10736.00 53.83%
13.5 (P) D PCC Grade M30
a Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6116.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10% 611.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1345.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 807.31
Rate perm (a+b+c+d+e+f) 8880.43 5869.00
say 8880.00 51.30%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 688.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1514.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 908.56
Rate perm (a+b+c+d+e+f) 9994.12 6505.00
13.5 (P) D say 9994.00 53.64%
b Height 5m to 10m

Page 52 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6116.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 733.92
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 122.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1394.45
f) Contractor's profit @ 10% on (a+b+c+d+e) 836.67
Rate perm (a+b+c+d+e+f) 9203.36 6082.00
say 9203.00 51.32%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 825.96
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 137.66
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1569.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 941.59
Rate perm (a+b+c+d+e+f) 10357.54 6742.00
13.5 (P) D say 10358.00 53.63%
c Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
mater
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6116.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 917.40
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 244.64
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1455.61
f) Contractor's profit @ 10% on (a+b+c+d+e) 873.36
Rate perm (a+b+c+d+e+f) 9607.01 6349.00

Page 53 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

say 9607.00 51.32%


Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6883.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 1032.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 275.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1638.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 982.89
Rate perm (a+b+c+d+e+f) 10811.82 7037.00
say 10812.00 53.65%
13.5 (P) E RCC Grade M20
a Height upto 5m
Case I Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5806.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM P

d) formwork
Add 10 per cent of cost of material, labour and 10.00 580.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1277.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 766.39
Rate perm (a+b+c+d+e+f) 8430.31 5396.00
say 8430.00 56.23%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 657.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1446.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 867.77
Rate perm (a+b+c+d+e+f) 9545.45 6033.00
13.5 (P) E say 9545.00 58.21%
b Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Page 54 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5806.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM P

d) formwork
Add 12 per cent of cost of material, labour and 12.00 696.72
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 116.12
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1323.77
f) Contractor's profit @ 10% on (a+b+c+d+e) 794.26
Rate perm (a+b+c+d+e+f) 8736.87 5592.00
say 8737.00 56.24%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 788.88
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 131.48
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1498.87
f) Contractor's profit @ 10% on (a+b+c+d+e) 899.32
Rate perm (a+b+c+d+e+f) 9892.56 6252.00
13.5 (P) E say 9893.00 58.24%
c Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material,
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5806.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM P

d) formwork
Add 15 per cent of cost of material, labour and 15.00 870.90
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 232.24
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1381.83
f) Contractor's profit @ 10% on (a+b+c+d+e) 829.10
Rate perm (a+b+c+d+e+f) 9120.06 5837.00
say 9120.00 56.24%

Page 55 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6574.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 986.10
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 262.96
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1564.61
f) Contractor's profit @ 10% on (a+b+c+d+e) 938.77
Rate perm (a+b+c+d+e+f) 10326.44 6527.00
say 10326.00 58.20%
13.5 (P) F RCC Grade M25
a Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6223.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM P

d) formwork
Add 10 per cent of cost of material, labour and 10.00 622.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1369.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 821.44
Rate perm (a+b+c+d+e+f) 9035.80 5958.00
say 9036.00 51.66%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6992.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 699.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1538.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 922.94
Rate perm (a+b+c+d+e+f) 10152.38 6782.00
13.5 (P) F say 10152.00 49.69%
b Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Page 56 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Per Cum Basic Cost of Labour, Material & Machinery 6223.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM P

d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 734.31
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 112.01
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1413.87
f) Contractor's profit @ 10% on (a+b+c+d+e) 848.32
Rate perm (a+b+c+d+e+f) 9331.51 6153.00
say 9332.00 51.67%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6992.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB P
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 825.06
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 125.86
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1588.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 953.15
Rate perm (a+b+c+d+e+f) 10484.64 7004.00
13.5 (P) F say 10485.00 49.70%
c Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6223.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM P

d) formwork
Add 15 per cent of cost of material, labour and 15.00 933.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 248.92
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1481.07
f) Contractor's profit @ 10% on (a+b+c+d+e) 888.64
Rate perm (a+b+c+d+e+f) 9775.09 6445.00
say 9775.00 51.67%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6992.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB P
d) formwork

Page 57 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 15 per cent of cost of material, labour and 15.00 1048.80


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 279.68
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1664.10
f) Contractor's profit @ 10% on (a+b+c+d+e) 998.46
Rate perm (a+b+c+d+e+f) 10983.03 7337.00
say 10983.00 49.69%
13.5 (P) G RCC Grade M30
a Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6253.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM P

d) formwork
Add 10 per cent of cost of material, labour and 10.00 625.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1375.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 825.40
Rate perm (a+b+c+d+e+f) 9079.36 5990.00
say 9079.00 51.57%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 7022.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 702.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1544.84
f) Contractor's profit @ 10% on (a+b+c+d+e) 926.90
Rate perm (a+b+c+d+e+f) 10195.94 6628.00
13.5 (P) G say 10196.00 53.83%
b Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6253.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM P

d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 719.10
machinery (a+b+c) for Formwork

Page 58 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 1.6 per cent of cost of material, Labour and 1.60 100.05
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1414.43
f) Contractor's profit @ 10% on (a+b+c+d+e) 848.66
Rate perm (a+b+c+d+e+f) 9335.23 6158.00
say 9335.00 51.59%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7022.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB P
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 807.53
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 112.35
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1588.38
f) Contractor's profit @ 10% on (a+b+c+d+e) 953.03
Rate perm (a+b+c+d+e+f) 10483.28 6615.00
13.5 (P) G say 10483.00 58.47%
c Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6253.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM P

d) formwork
Add 14 per cent of cost of material, labour and 14.00 875.42
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 218.86
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1469.46
f) Contractor's profit @ 10% on (a+b+c+d+e) 881.67
Rate perm (a+b+c+d+e+f) 9698.40 6398.00
say 9698.00 51.58%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7022.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB P
d) formwork
Add 14 per cent of cost of material, labour and 14.00 983.08
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 245.77
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1650.17
f) Contractor's profit @ 10% on (a+b+c+d+e) 990.10

Page 59 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Rate perm (a+b+c+d+e+f) 10891.12 7080.00


say 10891.00 53.83%
RCC Grade M35
Height upto 5m
13.5 (P) H Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
a Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6388.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM P

Case I d) formwork
Add 10 per cent of cost of material, labour and 10.00 638.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1405.36
f) Contractor's profit @ 10% on (a+b+c+d+e) 843.22
Rate perm (a+b+c+d+e+f) 9275.38 6142.00
say 9275.00 51.01%
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB P
d) formwork
Case II Add 10 per cent of cost of material, labour and 10.00 715.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 20 % on (a+b+c+d) 1574.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 944.86
Rate perm (a+b+c+d+e+f) 10393.42 6781.00
say 10393.00 53.27%
Height 5m to 10m
13.5 (P) H For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
b Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6388.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM P

Case I d) formwork
Add 11 per cent of cost of material, labour and 11.00 702.68
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 89.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1436.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 861.61
Rate perm (a+b+c+d+e+f) 9477.75 6276.00
say 9478.00 51.02%

Page 60 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB P
Case II d) formwork
Add 11 per cent of cost of material, labour and 11.00 787.38
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 100.21
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1609.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 965.47
Rate perm (a+b+c+d+e+f) 10620.18 6929.00
say 10620.00 53.27%
Height above 10m
13.5 (P) H For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
c Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6388.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM P

Case I d) formwork
Add 13 per cent of cost of material, labour and 13.00 830.44
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 191.64
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1482.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 889.21
Rate perm (a+b+c+d+e+f) 9781.31 6477.00
say 9781.00 51.01%
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 7158.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB P
Case II d) formwork
Add 13 per cent of cost of material, labour and 13.00 930.54
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 214.74
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20 % on (a+b+c+d) 1660.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 996.39
Rate perm (a+b+c+d+e+f) 10960.33 7151.00
say 10960.00 53.27%
The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

Page 61 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percent
13.6 (a)Supplying, fitting and placing TMT bar
reinforcement in sub-structure complete as per
drawing and Technical Specifications
Output: MT
Taking output = 1 MT
(a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/
SAIL/ Esser Steel/ Jindal steel/ Shyam steel or
equivalent)

a) Material
TMT CRS bars including 5 per cent overlaps and tonne 1.05 53667.00 56350.35 M-085
wastage
Binding wire kg 6.00 85.00 510.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 20 % on (a+b) 11897.67
d) Contractor's profit @ 10% on (a+b+c) 7138.60
Rate for per MT (a+b+c+d) 78524.62 46779.00
say 78525.00 67.86%
Output: MT
Taking output = 1 MT
(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer (ISI
approved)
a) Material
TMT bars including 5 per cent overlaps and wastage tonne 1.05 49667.00 52150.35 M-085_1
With TATA rebar

Binding wire kg 6.00 85.00 510.00 M-072


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 20 % on (a+b) 11057.67
d) Contractor's profit @ 10% on (a+b+c) 6634.60

Page 62 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Rate for per MT (a+b+c+d) 72980.62 43032.00


say 72981.00 69.60%

13.7 Supplying, fitting and placing un-coated Mild steel (IS:


1786 Fe-250) reinforcement complete in sub-structure
as per drawing and Technical Specification

Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.10 53667.00 59033.70 M-126
Binding wire kg 6.00 85.00 510.00 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.28 356.65 99.86 L-12
Blacksmith day 1.50 458.55 687.83 L-02
Mazdoor day 5.50 244.56 1345.08 L-13
c) Overhead charges @ 20 % on (a+b) 12335.29
d) Contractor's profit @ 10% on (a+b+c) 7401.18
Rate for per MT (a+b+c+d) 81412.94 42128.00
say 81413.00 93.25%
13.8 Providing weep holes in Brick masonry/Plain/
Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical

Unit = Nos.
Taking output = 30 Nos.
a) Material
PVC rain water pipe 100 mm dia. (including wastage @ metre 31.50 90.00 2835.00 M-212
5 per cent )
Average length of weep hole is taken as one metre for the
purpose of estimating.
MS clamp each. 30.00 19.00 570.00 M-123
Joint for pipe (average) taking 10% of above pipe rate each. 10.00 9.00 90.00 M-212/10

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.15 4904.00 735.60 Item 12.6 (A)
b) Labour
Mate day 0.03 356.65 10.70 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor day 0.25 244.56 61.14 L-13
c) Overhead charges @ 20 % on (a+b) 906.34
d) Contractor's profit @ 10% on (a+b+c) 543.81
Cost for 30 m = a+b+c+d 5981.86
Rate per m (a+b+c+d)/30 199.40 90.00

Page 63 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

say 199.00 121.11%


1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work
and shall not be paid separately.
13.9 Back filling behind abutment, wing wall and return wall
complete as per drawing and Technical Specification

Unit = cum
Taking output = 10 cum
Granular material
a) Labour
Mate day 0.28 356.65 99.86 L-12
Mazdoor day 7.00 244.56 1711.92 L-13
b) Material
Granular material cum 12.00 698.00 8376.00 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 218.00 545.00 P&M-086
Water Tanker hour 0.05 440.00 22.00 P&M-060
d) Overhead charges @ 20 % on (a+b+c) 2150.96
e) Contractor's profit @ 10% on (a+b+c+d) 1290.57
Cost for 10 cum of granular backfill = a+b+c+d+e 14196.31
Rate per cum = (a+b+c+d+e)/10 1419.63 897.00
say 1420.00 58.31%
13.9 Sandy material
a) Labour
Mate day 0.28 356.65 99.86 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 244.56 1711.92 L-13
b) Material
Sand cum 12.00 698.00 8376.00 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 218.00 545.00 P&M-086
Water Tanker hour 0.06 440.00 26.40 P&M-060
d) Overhead charges @ 20 % on (a+b+c) 2151.84
e) Contractor's profit @ 10% on (a+b+c+d) 1291.10
Cost for 10 cum of sandy backfill = a+b+c+d+e 14202.12
Rate per cum = (a+b+c+d+e)/10 1420.21 992.00
say 1420.00 43.15%

Page 64 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

13.10 Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger si

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 244.56 1711.92 L-13
Mazdoor (Skilled) day 1.00 356.65 356.65 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1013.00 12156.00 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 440.00 26.40 P&M-060
d) Overhead charges @ 20 % on (a+b+c) 2873.02
e) Contractor's profit @ 10% on (a+b+c+d) 1723.81
cost for 10 cum of Fiter Media = a+b+c+d+e 18961.93
Rate per cum = (a+b+c+d+e)/10 1896.19 1061.00
say 1896.00 78.70%
13.11 Supplying, fitting and fixing in position true to line and
level cast steel rocker bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
Mazdoor day 1.00 244.56 244.56 L-13
b) Material
Cast steel rocker bearing assembly of 250 tonne each. 1.00 135850.00 135850.00 M-065
design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 1358.50
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 20 % on (a+b) 27530.56
d) Contractor's profit @ 10% on (a+b+c) 16518.33
cost for 250 tonnes capacity bearing = a+b+c+d 181701.67
Rate per tonne capacity = (a+b+c+d)/250 726.81 587.00
say 727.00 23.85%

Page 65 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

13.12 Supplying, fitting and fixing in position true to line and


level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Forged steel roller bearing of 250 tonne design load each. 1.00 117306.00 117306.00 M-067
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 1173.06
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 20 % on (a+b) 23784.67
d) Contractor's profit @ 10% on (a+b+c) 14270.80
cost for 250 tonnes capacity bearing = a+b+c+d 156978.81
Rate per tonne capacity = (a+b+c+d)/250 627.92 507.00
say 628.00 23.87%
13.13 Supplying, fitting and fixing in position true to line and
level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as
per drawing and Technical Specifications and BS:
5400, section 9.1 & 9.2 (for PTFE)

Unit: one tonne capacity


Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
PTFE sliding plate bearing assembly of 80 tonnes each. 1.00 19760.00 19760.00 M-069
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and 197.60
consumables.
c) Overhead charges @ 20 % on (a+b) 4080.38
d) Contractor's profit @ 10% on (a+b+c) 2448.23
cost for 80 tonnes capacity bearing = a+b+c+d 26930.49
Rate per tonne capacity = (a+b+c+d)/80 336.63 269.00
say 337.00 25.28%

Page 66 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

13.14 Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655
cu.cm.xRs4.4/cucm=Rs64482/-
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Elastomeric bearing assembly consisting of 7 layers of each. 1.14 64482.00 73509.48 M-066
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 735.09
foundation anchorage bolts and consumables.
c) Overhead charges @ 20 % on (a+b) 14937.77
d) Contractor's profit @ 10% on (a+b+c) 8962.66
cost for 19200cc of elastomeric bearing = a+b+c+d 98589.29
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 5.13 0.82

say 5.13 525.61%


13.15 Supplying, fitting and fixing in position true to line and
level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.75 244.56 183.42 L-13
Mazdoor (Skilled) day 0.35 356.65 124.83 L-15
b) Material
Supply of sliding plate bearing of 80 tonne design each. 1.00 11025.00 11025.00 M-070
capacity complete as per drawings and Technical
Specifications.

Page 67 of 959
Analysisof SOR (Roads) 2017-18
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.

Add 1 per cent of cost of bearing assembly for 110.25


foundation anchorage bolts and consumables.
c) Overhead charges @ 20 % on (a+b) 2291.55
d) Contractor's profit @ 10% on (a+b+c) 1374.93
cost for 80 tonnes of capacity bearing = a+b+c+d 15124.25
189.05 152.00
say 189.00 24.34%
13.16 Supplying, fitting and fixing in position true to line and
level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against stainles

Unit: one tonne capacity 387.20


Considering a Pot bearing assembly of 250 tonne capacity
for this analysis.
a) Labour
Mate day 0.08 356.65 28.53 L-12
Mazdoor day 1.50 244.56 366.84 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Pot type bearing assembly consisting of a metal piston each. 1.00 39560.00 39560.00 M-068
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as
Add 1 per cent of cost of bearing assembly for 395.60
foundation anchorage bolts and consumables.
c) Overhead charges @ 20 % on (a+b) 8105.86
d) Contractor's profit @ 10% on (a+b+c) 4863.52
cost for 250 tonnes capacity bearing = a+b+c+d 53498.67
Rate per tonne capacity = (a+b+c+d)/250 213.99 172.00
say 214.00 24.42%

Page 68 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

CHAPTER-14
SUPER-STRUCTURE

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1 Furnishing and Placing Reinforced/ Prestressed
cement concrete in super-structure as per
drawing and Technical Specification

(N) Without Plasticiser


A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7200.00 36864.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 76897.00
(a+b+c) for 15 cum
14.1 (N) For formwork and staging add the following:
Case I (i) For solid slab super-structure, 20-30 per cent
of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 76897.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 15379.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 18455.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 11073.17

Cost for 15 cum = a+b+c+d+e+f 121804.85


Rate per cum = (a+b+c+d+e+f)/15 8120.32
say 8120.00
14.1A (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 76897.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19224.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 19224.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 11534.55

Cost for 15 cum = a+b+c+d+e+f 126880.05


Rate per cum = (a+b+c+d+e+f)/15 8458.67
say 8459.00

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1A (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 76897.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 23069.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 19993.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 11995.93

Cost for 15 cum = a+b+c+d+e+f 131955.25


Rate per cum = (a+b+c+d+e+f)/15 8797.02
say 8797.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 76897.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19224.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 19224.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 11534.55

Cost for 15 cum = a+b+c+d+e+f 126880.05


Rate per cum = (a+b+c+d+e+f)/15 8458.67
say 8459.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 76897.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 23069.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 19993.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 11995.93

Cost for 15 cum = a+b+c+d+e+f 131955.25


Rate per cum = (a+b+c+d+e+f)/15 8797.02
say 8797.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 76897.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 26913.95
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 20762.19
f) Contractor's profit @ 10% on (a+b+c+d+e) 12457.31

Cost for 15 cum = a+b+c+d+e+f 137030.45


Rate per cum = (a+b+c+d+e+f)/15 9135.36
say 9135.00
14.1A Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Taking output = 120 cum
a) Material
Cement tonne 40.92 7200.00 294624.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 705059.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 705059.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 141011.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 169214.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 101528.50

Cost for 120 cum = a+b+c+d+e+f 1116813.46


Rate per cum = (a+b+c+d+e+f)/120 9306.78
say 9307.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 705059.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 176264.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 176264.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 105758.85

Cost for 120 cum = a+b+c+d+e+f 1163347.35


Rate per cum = (a+b+c+d+e+f)/120 9694.56
say 9695.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 705059.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 211517.70
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 183315.34

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 109989.20

Cost for 120 cum = a+b+c+d+e+f 1209881.24


Rate per cum = (a+b+c+d+e+f)/120 10082.34
say 10082.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 705059.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 176264.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 176264.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 105758.85

Cost for 120 cum = a+b+c+d+e+f 1163347.35


Rate per cum = (a+b+c+d+e+f)/120 9694.56
say 9695.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 705059.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 211517.70
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 183315.34
f) Contractor's profit @ 10% on (a+b+c+d+e) 109989.20

Cost for 120 cum = a+b+c+d+e+f 1209881.24


Rate per cum = (a+b+c+d+e+f)/120 10082.34
say 10082.00
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 705059.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 246770.65
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 190365.93
f) Contractor's profit @ 10% on (a+b+c+d+e) 114219.56

Cost for 120 cum = a+b+c+d+e+f 1256415.14


Rate per cum = (a+b+c+d+e+f)/120 10470.13
say 10470.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7200.00 43128.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40

b) Labour

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 83161.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 83161.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 16632.20
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 19958.64
f) Contractor's profit @ 10% on (a+b+c+d+e) 11975.18

Cost for 15 cum = a+b+c+d+e+f 131727.02


Rate per cum = (a+b+c+d+e+f)/15 8781.80
say 8782.00
14.1B (b) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 83161.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 20790.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 20790.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 12474.15

Cost for 15 cum = a+b+c+d+e+f 137215.65


Rate per cum = (a+b+c+d+e+f)/15 9147.71
say 9148.00
14.1B (b) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 83161.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 24948.30
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21621.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 12973.12

Cost for 15 cum = a+b+c+d+e+f 142704.28


Rate per cum = (a+b+c+d+e+f)/15 9513.62
say 9514.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 83161.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 20790.25
(a+b+c)

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


e) Overhead charges @ 20 % on (a+b+c+d) 20790.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 12474.15

Cost for 15 cum = a+b+c+d+e+f 137215.65


Rate per cum = (a+b+c+d+e+f)/15 9147.71
say 9148.00
14.1B (b) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 83161.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 24948.30
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21621.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 12973.12

Cost for 15 cum = a+b+c+d+e+f 142704.28


Rate per cum = (a+b+c+d+e+f)/15 9513.62
say 9514.00
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 83161.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 29106.35
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22453.47
f) Contractor's profit @ 10% on (a+b+c+d+e) 13472.08

Cost for 15 cum = a+b+c+d+e+f 148192.90


Rate per cum = (a+b+c+d+e+f)/15 9879.53
say 9880.00
14.1B Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 7200.00 345240.00
Coarse sand cum 54.20 950.00 51490.00
20 mm Aggregate cum 64.80 1777.00 115149.60
10 mm Aggregate cum 43.20 1916.00 82771.20
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 755865.00
(a+b+c) for 120 cum

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 755865.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 151173.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 181407.60
f) Contractor's profit @ 10% on (a+b+c+d+e) 108844.56

Cost for 120 cum = a+b+c+d+e+f 1197290.16


Rate per cum = (a+b+c+d+e+f)/120 9977.42
say 9977.00
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 755865.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 188966.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 188966.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 113379.75

Cost for 120 cum = a+b+c+d+e+f 1247177.25


Rate per cum = (a+b+c+d+e+f)/120 10393.14
say 10393.00
14.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 755865.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 226759.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 196524.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 117914.94

Cost for 120 cum = a+b+c+d+e+f 1297064.34


Rate per cum = (a+b+c+d+e+f)/120 10808.87
say 10809.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 755865.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 188966.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 188966.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 113379.75

Cost for 120 cum = a+b+c+d+e+f 1247177.25


Rate per cum = (a+b+c+d+e+f)/120 10393.14
say 10393.00

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 755865.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 226759.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 196524.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 117914.94

Cost for 120 cum = a+b+c+d+e+f 1297064.34


Rate per cum = (a+b+c+d+e+f)/120 10808.87
say 10809.00
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 755865.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 264552.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 204083.55
f) Contractor's profit @ 10% on (a+b+c+d+e) 122450.13

Cost for 120 cum = a+b+c+d+e+f 1346951.43


Rate per cum = (a+b+c+d+e+f)/120 11224.60
say 11225.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7200.00 43920.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 21.00 244.56 5135.76
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 84212.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 84212.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 16842.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 20210.88
f) Contractor's profit @ 10% on (a+b+c+d+e) 12126.53

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Cost for 15 cum = a+b+c+d+e+f 133391.81
Rate per cum = (a+b+c+d+e+f)/15 8892.79
say 8893.00
14.1C (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 84212.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21053.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21053.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 12631.80

Cost for 15 cum = a+b+c+d+e+f 138949.80


Rate per cum = (a+b+c+d+e+f)/15 9263.32
say 9263.00
14.1C (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 84212.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 25263.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21895.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 13137.07

Cost for 15 cum = a+b+c+d+e+f 144507.79


Rate per cum = (a+b+c+d+e+f)/15 9633.85
say 9634.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 84212.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21053.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21053.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 12631.80

Cost for 15 cum = a+b+c+d+e+f 138949.80


Rate per cum = (a+b+c+d+e+f)/15 9263.32
say 9263.00
14.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 84212.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 25263.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21895.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 13137.07

Cost for 15 cum = a+b+c+d+e+f 144507.79


Rate per cum = (a+b+c+d+e+f)/15 9633.85
say 9634.00

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 84212.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 29474.20
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22737.24
f) Contractor's profit @ 10% on (a+b+c+d+e) 13642.34

Cost for 15 cum = a+b+c+d+e+f 150065.78


Rate per cum = (a+b+c+d+e+f)/15 10004.39
say 10004.00
14.1C Case II Using Batching Plant, Transit Mixer and
Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7200.00 351288.00
Coarse sand cum 54.60 950.00 51870.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 19.00 244.56 4646.64
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 758728.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 758728.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 151745.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 182094.72
f) Contractor's profit @ 10% on (a+b+c+d+e) 109256.83

Cost for 120 cum = a+b+c+d+e+f 1201825.15


Rate per cum = (a+b+c+d+e+f)/120 10015.21
say 10015.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 758728.00
for 120 cum

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 25 per cent of 25.00 189682.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 189682.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 113809.20

Cost for 120 cum = a+b+c+d+e+f 1251901.20


Rate per cum = (a+b+c+d+e+f)/120 10432.51
say 10433.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 758728.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 227618.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 197269.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 118361.57

Cost for 120 cum = a+b+c+d+e+f 1301977.25


Rate per cum = (a+b+c+d+e+f)/120 10849.81
say 10850.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 758728.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 189682.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 189682.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 113809.20

Cost for 120 cum = a+b+c+d+e+f 1251901.20


Rate per cum = (a+b+c+d+e+f)/120 10432.51
say 10433.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 758728.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 227618.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 197269.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 118361.57

Cost for 120 cum = a+b+c+d+e+f 1301977.25


Rate per cum = (a+b+c+d+e+f)/120 10849.81
say 10850.00
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 758728.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 265554.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 204856.56

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 122913.94

Cost for 120 cum = a+b+c+d+e+f 1352053.30


Rate per cum = (a+b+c+d+e+f)/120 11267.11
say 11267.00
D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7200.00 45576.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 21.00 244.56 5135.76
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 85868.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 18 per cent of 18.00 15456.24
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 20264.85
f) Contractor's profit @ 10% on (a+b+c+d+e) 12158.91

Cost for 15 cum = a+b+c+d+e+f 133748.00


Rate per cum = (a+b+c+d+e+f)/15 8916.53
say 8917.00
14.1D (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 19749.64
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21123.53
f) Contractor's profit @ 10% on (a+b+c+d+e) 12674.12

Cost for 15 cum = a+b+c+d+e+f 139415.28


Rate per cum = (a+b+c+d+e+f)/15 9294.35
say 9294.00
14.1D (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 28 per cent of 28.00 24043.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21982.21
f) Contractor's profit @ 10% on (a+b+c+d+e) 13189.32

Cost for 15 cum = a+b+c+d+e+f 145082.57


Rate per cum = (a+b+c+d+e+f)/15 9672.17
say 9672.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 19749.64
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21123.53
f) Contractor's profit @ 10% on (a+b+c+d+e) 12674.12

Cost for 15 cum = a+b+c+d+e+f 139415.28


Rate per cum = (a+b+c+d+e+f)/15 9294.35
say 9294.00
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 28 per cent of 28.00 24043.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21982.21
f) Contractor's profit @ 10% on (a+b+c+d+e) 13189.32

Cost for 15 cum = a+b+c+d+e+f 145082.57


Rate per cum = (a+b+c+d+e+f)/15 9672.17
say 9672.00
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 33 per cent of 33.00 28336.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22840.89
f) Contractor's profit @ 10% on (a+b+c+d+e) 13704.53

Cost for 15 cum = a+b+c+d+e+f 150749.86


Rate per cum = (a+b+c+d+e+f)/15 10049.99
say 10050.00
14.1D (iii) For box girder and balanced cantilever, 38-58
Case I per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 38 per cent of 38.00 32629.84
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23699.57

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 14219.74

Cost for 15 cum = a+b+c+d+e+f 156417.15


Rate per cum = (a+b+c+d+e+f)/15 10427.81
say 10428.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 48 per cent of 48.00 41216.64
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25416.93
f) Contractor's profit @ 10% on (a+b+c+d+e) 15250.16

Cost for 15 cum = a+b+c+d+e+f 167751.72


Rate per cum = (a+b+c+d+e+f)/15 11183.45
say 11183.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 85868.00
for 15 cum
d) Formwork and staging 58 per cent of 58.00 49803.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 27134.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 16280.57

Cost for 15 cum = a+b+c+d+e+f 179086.30


Rate per cum = (a+b+c+d+e+f)/15 11939.09
say 11939.00
Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7200.00 364608.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 19.00 244.56 4646.64
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 771478.00
(a+b+c) for 120 cum
For formwork and staging add the following:

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1D (i) For solid slab super-structure, 18-28 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 138866.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 182068.81
f) Contractor's profit @ 10% on (a+b+c+d+e) 109241.28

Cost for 120 cum = a+b+c+d+e+f 1201654.13


Rate per cum = (a+b+c+d+e+f)/120 10013.78
say 10014.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 177439.94
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 189783.59
f) Contractor's profit @ 10% on (a+b+c+d+e) 113870.15

Cost for 120 cum = a+b+c+d+e+f 1252571.68


Rate per cum = (a+b+c+d+e+f)/120 10438.10
say 10438.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 216013.84
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 197498.37
f) Contractor's profit @ 10% on (a+b+c+d+e) 118499.02

Cost for 120 cum = a+b+c+d+e+f 1303489.23


Rate per cum = (a+b+c+d+e+f)/120 10862.41
say 10862.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 177439.94
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 189783.59
f) Contractor's profit @ 10% on (a+b+c+d+e) 113870.15

Cost for 120 cum = a+b+c+d+e+f 1252571.68


Rate per cum = (a+b+c+d+e+f)/120 10438.10
say 10438.00
14.1D (q) Height 5m to 10m
Case II
(ii)

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 216013.84
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 197498.37
f) Contractor's profit @ 10% on (a+b+c+d+e) 118499.02

Cost for 120 cum = a+b+c+d+e+f 1303489.23


Rate per cum = (a+b+c+d+e+f)/120 10862.41
say 10862.00
14.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 254587.74
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 205213.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 123127.89

Cost for 120 cum = a+b+c+d+e+f 1354406.78


Rate per cum = (a+b+c+d+e+f)/120 11286.72
say 11287.00
14.1D (iii) For box girder and balanced cantilever, 38-58
Case II per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 293161.64
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 212927.93
f) Contractor's profit @ 10% on (a+b+c+d+e) 127756.76

Cost for 120 cum = a+b+c+d+e+f 1405324.32


Rate per cum = (a+b+c+d+e+f)/120 11711.04
say 11711.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 370309.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 228357.49
f) Contractor's profit @ 10% on (a+b+c+d+e) 137014.49

Cost for 120 cum = a+b+c+d+e+f 1507159.42


Rate per cum = (a+b+c+d+e+f)/120 12559.66
say 12560.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 771478.00
for 120 cum

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 58 per cent of 58.00 447457.24
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 243787.05
f) Contractor's profit @ 10% on (a+b+c+d+e) 146272.23

Cost for 120 cum = a+b+c+d+e+f 1608994.52


Rate per cum = (a+b+c+d+e+f)/120 13408.29
say 13408.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 7200.00 46440.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40

b) Labour
Mate day 0.96 356.65 342.38
Mason day 2.00 458.55 917.10
Mazdoor day 22.00 244.56 5380.32
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 87227.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 87227.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 17445.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 20934.48
f) Contractor's profit @ 10% on (a+b+c+d+e) 12560.69

Cost for 15 cum = a+b+c+d+e+f 138167.57


Rate per cum = (a+b+c+d+e+f)/15 9211.17
say 9211.00
14.1E (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 87227.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21806.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21806.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 13084.05

Cost for 15 cum = a+b+c+d+e+f 143924.55


Rate per cum = (a+b+c+d+e+f)/15 9594.97
say 9595.00

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1E (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 87227.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26168.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22679.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 13607.41

Cost for 15 cum = a+b+c+d+e+f 149681.53


Rate per cum = (a+b+c+d+e+f)/15 9978.77
say 9979.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 87227.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21806.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21806.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 13084.05

Cost for 15 cum = a+b+c+d+e+f 143924.55


Rate per cum = (a+b+c+d+e+f)/15 9594.97
say 9595.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 87227.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26168.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22679.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 13607.41

Cost for 15 cum = a+b+c+d+e+f 149681.53


Rate per cum = (a+b+c+d+e+f)/15 9978.77
say 9979.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 87227.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 30529.45
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23551.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 14130.77

Cost for 15 cum = a+b+c+d+e+f 155438.51


Rate per cum = (a+b+c+d+e+f)/15 10362.57
say 10363.00
14.1E Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Taking output = 120 cum
a) Material
Cement tonne 51.60 7200.00 371520.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 778885.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per
Case II cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 140199.30
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 183816.86
f) Contractor's profit @ 10% on (a+b+c+d+e) 110290.12

Cost for 15 cum = a+b+c+d+e+f 1213191.28


Rate per cum = (a+b+c+d+e+f)/120 10109.93
say 10110.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 179143.55
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 191605.71
f) Contractor's profit @ 10% on (a+b+c+d+e) 114963.43

Cost for 120 cum = a+b+c+d+e+f 1264597.69


Rate per cum = (a+b+c+d+e+f)/120 10538.31
say 10538.00
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 218087.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 199394.56

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 119636.74

Cost for 120 cum = a+b+c+d+e+f 1316004.10


Rate per cum = (a+b+c+d+e+f)/120 10966.70
say 10967.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 179143.55
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 191605.71
f) Contractor's profit @ 10% on (a+b+c+d+e) 114963.43

Cost for 120 cum = a+b+c+d+e+f 1264597.69


Rate per cum = (a+b+c+d+e+f)/120 10538.31
say 10538.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 218087.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 199394.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 119636.74

Cost for 120 cum = a+b+c+d+e+f 1316004.10


Rate per cum = (a+b+c+d+e+f)/120 10966.70
say 10967.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 257032.05
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 207183.41
f) Contractor's profit @ 10% on (a+b+c+d+e) 124310.05

Cost for 120 cum = a+b+c+d+e+f 1367410.51


Rate per cum = (a+b+c+d+e+f)/120 11395.09
say 11395.00
14.1E (iii) For cast-in-situ box girder, segment
Case II construction and balanced cantilever, 38-58 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 295976.30
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 214972.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 128983.36

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Cost for 120 cum = a+b+c+d+e+f 1418816.92
Rate per cum = (a+b+c+d+e+f)/120 11823.47
say 11823.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 373864.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 230549.96
f) Contractor's profit @ 10% on (a+b+c+d+e) 138329.98

Cost for 120 cum = a+b+c+d+e+f 1521629.74


Rate per cum = (a+b+c+d+e+f)/120 12680.25
say 12680.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 778885.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 451753.30
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 246127.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 147676.60

Cost for 120 cum = a+b+c+d+e+f 1624442.56


Rate per cum = (a+b+c+d+e+f)/120 13537.02
say 13537.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 7200.00 401760.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 809125.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-
26 per cent of cost of concrete (a+b+c)
(p) Height upto 5m

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 16 per cent of 16.00 129460.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 187717.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 112630.20

Cost for 120 cum = a+b+c+d+e+f 1238932.20


Rate per cum = (a+b+c+d+e+f)/120 10324.44
say 10324.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 169916.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 195808.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 117484.95

Cost for 120 cum = a+b+c+d+e+f 1292334.45


Rate per cum = (a+b+c+d+e+f)/120 10769.45
say 10769.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 210372.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 203899.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 122339.70

Cost for 120 cum = a+b+c+d+e+f 1345736.70


Rate per cum = (a+b+c+d+e+f)/120 11214.47
say 11214.00
14.1F (ii) For T-beam & slab including launching of
precast girders by launching truss upto 40 m
span, 21-31 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 169916.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 195808.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 117484.95

Cost for 120 cum = a+b+c+d+e+f 1292334.45


Rate per cum = (a+b+c+d+e+f)/120 10769.45
say 10769.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 210372.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 203899.50

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 122339.70

Cost for 120 cum = a+b+c+d+e+f 1345736.70


Rate per cum = (a+b+c+d+e+f)/120 11214.47
say 11214.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 31 per cent of 31.00 250828.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 211990.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 127194.45

Cost for 120 cum = a+b+c+d+e+f 1399138.95


Rate per cum = (a+b+c+d+e+f)/120 11659.49
say 11659.00
14.1F (iii) For cast-in-situ box girder, segmental
construction and balanced cantilever, 36-56 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 36 per cent of 36.00 291285.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 220082.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 132049.20

Cost for 120 cum = a+b+c+d+e+f 1452541.20


Rate per cum = (a+b+c+d+e+f)/120 12104.51
say 12105.00
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 46 per cent of 46.00 372197.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 236264.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 141758.70

Cost for 120 cum = a+b+c+d+e+f 1559345.70


Rate per cum = (a+b+c+d+e+f)/120 12994.55
say 12995.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 809125.00
for 120 cum
d) Formwork and staging 56 per cent of 56.00 453110.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 252447.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 151468.20

Cost for 120 cum = a+b+c+d+e+f 1666150.20


Rate per cum = (a+b+c+d+e+f)/120 13884.59
say 13885.00

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 7200.00 423360.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 830725.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 830725.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 290753.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 224295.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 134577.45

Cost for 120 cum = a+b+c+d+e+f 1480351.95


Rate per cum = (a+b+c+d+e+f)/120 12336.27
say 12336.00
14.1G (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 830725.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 373826.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 240910.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 144546.15

Cost for 120 cum = a+b+c+d+e+f 1590007.65


Rate per cum = (a+b+c+d+e+f)/120 13250.06
say 13250.00
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 830725.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 456898.75
(a+b+c)

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


e) Overhead charges @ 20 % on (a+b+c+d) 257524.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 154514.85

Cost for 120 cum = a+b+c+d+e+f 1699663.35


Rate per cum = (a+b+c+d+e+f)/120 14163.86
say 14164.00
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 7200.00 457200.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 864565.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 864565.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 302597.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 233432.55
f) Contractor's profit @ 10% on (a+b+c+d+e) 140059.53

Cost for 120 cum = a+b+c+d+e+f 1540654.83


Rate per cum = (a+b+c+d+e+f)/120 12838.79
say 12839.00
14.1H (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 864565.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 389054.25
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 250723.85
f) Contractor's profit @ 10% on (a+b+c+d+e) 150434.31

Cost for 120 cum = a+b+c+d+e+f 1654777.41


Rate per cum = (a+b+c+d+e+f)/120 13789.81
say 13790.00

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1H (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 864565.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 475510.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 268015.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 160809.09

Cost for 120 cum = a+b+c+d+e+f 1768899.99


Rate per cum = (a+b+c+d+e+f)/120 14740.83
say 14741.00
Note 1.Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving desired slump of
concrete.
2. Cement provided for various components of the
super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix
design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact

3. The items like needle and surface vibrators are


part of minor T & P which is already covered under
the overhead charges. As such these items have not
been added separately in the rate analysis.

(P) With plasticiser ( Masterplast PL-1/SPL-2 or


equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or equivalent) and
accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999.

A RCC Grade M20


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7200.00 36864.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast Pl-1 or equivalent ) @ Lit 20.48 120.00 2457.60
4Lit per MT cement
Air entraining and water reducing plasticiser Lit 15.36 75.00 1152.00
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per MT cement
Accelerating plasticiser conforming to IS-9103- Lit 71.68 95.00 6809.60
1999 ( Masterplast APCL or equivalent ) @
14Li per MT cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 87316.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 87316.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 17463.20
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 20955.84
f) Contractor's profit @ 10% on (a+b+c+d+e) 12573.50

Cost for 15 cum = a+b+c+d+e+f 138308.54


Rate per cum = (a+b+c+d+e+f)/15 9220.57
say 9221.00
14.1A (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 87316.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21829.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21829.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 13097.40

Cost for 15 cum = a+b+c+d+e+f 144071.40


Rate per cum = (a+b+c+d+e+f)/15 9604.76
say 9605.00
14.1A (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 87316.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26194.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22702.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 13621.30

Cost for 15 cum = a+b+c+d+e+f 149834.26


Rate per cum = (a+b+c+d+e+f)/15 9988.95
say 9989.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 87316.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21829.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 21829.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 13097.40

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Cost for 15 cum = a+b+c+d+e+f 144071.40
Rate per cum = (a+b+c+d+e+f)/15 9604.76
say 9605.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 87316.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26194.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22702.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 13621.30

Cost for 15 cum = a+b+c+d+e+f 149834.26


Rate per cum = (a+b+c+d+e+f)/15 9988.95
say 9989.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 87316.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 30560.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23575.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 14145.19

Cost for 15 cum = a+b+c+d+e+f 155597.11


Rate per cum = (a+b+c+d+e+f)/15 10373.14
say 10373.00
14.1A Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7200.00 294624.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast Pl-1 or equivalent ) @ Lit 163.68 120.00 19641.60
4Lit per MT cement
Air entraining and water reducing plasticiser Lit 122.76 75.00 9207.00
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per MT cement
Accelerating plasticiser conforming to IS-9103- Lit 572.88 95.00 54423.60
1999 ( Masterplast APCL or equivalent ) @
14Li per MT cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 898.00 5388.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 780356.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 780356.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 156071.20
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 187285.44
f) Contractor's profit @ 10% on (a+b+c+d+e) 112371.26

Cost for 120 cum = a+b+c+d+e+f 1236083.90


Rate per cum = (a+b+c+d+e+f)/120 10300.70
say 10301.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 780356.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 195089.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 195089.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 117053.40

Cost for 120 cum = a+b+c+d+e+f 1287587.40


Rate per cum = (a+b+c+d+e+f)/120 10729.90
say 10730.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 780356.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 234106.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 202892.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 121735.54

Cost for 120 cum = a+b+c+d+e+f 1339090.90


Rate per cum = (a+b+c+d+e+f)/120 11159.09
say 11159.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 780356.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 195089.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 195089.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 117053.40

Page 29 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Cost for 120 cum = a+b+c+d+e+f 1287587.40
Rate per cum = (a+b+c+d+e+f)/120 10729.90
say 10730.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 780356.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 234106.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 202892.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 121735.54

Cost for 120 cum = a+b+c+d+e+f 1339090.90


Rate per cum = (a+b+c+d+e+f)/120 11159.09
say 11159.00
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 780356.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 273124.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 210696.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 126417.67

Cost for 120 cum = a+b+c+d+e+f 1390594.39


Rate per cum = (a+b+c+d+e+f)/120 11588.29
say 11588.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7200.00 43128.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 29.95 100.00 2995.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 17.97 75.00 1347.75
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 83.86 95.00 7966.70
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 95470.00
(a+b+c) for 15 cum

Page 30 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 95470.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 19094.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 22912.80
f) Contractor's profit @ 10% on (a+b+c+d+e) 13747.68

Cost for 15 cum = a+b+c+d+e+f 151224.48


Rate per cum = (a+b+c+d+e+f)/15 10081.63
say 10082.00
14.1B (b) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 95470.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 23867.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23867.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 14320.50

Cost for 15 cum = a+b+c+d+e+f 157525.50


Rate per cum = (a+b+c+d+e+f)/15 10501.70
say 10502.00
14.1B (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 95470.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 28641.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24822.20
f) Contractor's profit @ 10% on (a+b+c+d+e) 14893.32

Cost for 15 cum = a+b+c+d+e+f 163826.52


Rate per cum = (a+b+c+d+e+f)/15 10921.77
say 10922.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 95470.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 23867.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23867.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 14320.50

Cost for 15 cum = a+b+c+d+e+f 157525.50


Rate per cum = (a+b+c+d+e+f)/15 10501.70
say 10502.00

Page 31 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1B (b) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 95470.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 28641.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24822.20
f) Contractor's profit @ 10% on (a+b+c+d+e) 14893.32

Cost for 15 cum = a+b+c+d+e+f 163826.52


Rate per cum = (a+b+c+d+e+f)/15 10921.77
say 10922.00
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 95470.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 33414.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25776.90
f) Contractor's profit @ 10% on (a+b+c+d+e) 15466.14

Cost for 15 cum = a+b+c+d+e+f 170127.54


Rate per cum = (a+b+c+d+e+f)/15 11341.84
say 11342.00
14.1B Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 7200.00 345240.00
Coarse sand cum 54.20 950.00 51490.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 239.75 100.00 23975.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 143.85 75.00 10788.75
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 671.30 95.00 63773.50
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00

Page 32 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Basic Cost of Labour, Material & Machinery 850579.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 850579.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 170115.80
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 204138.96
f) Contractor's profit @ 10% on (a+b+c+d+e) 122483.38

Cost for 120 cum = a+b+c+d+e+f 1347317.14


Rate per cum = (a+b+c+d+e+f)/120 11227.64
say 11228.00
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 850579.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 212644.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 212644.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 127586.85

Cost for 120 cum = a+b+c+d+e+f 1403455.35


Rate per cum = (a+b+c+d+e+f)/120 11695.46
say 11695.00
14.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 850579.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 255173.70
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 221150.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 132690.32

Cost for 120 cum = a+b+c+d+e+f 1459593.56


Rate per cum = (a+b+c+d+e+f)/120 12163.28
say 12163.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 850579.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 212644.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 212644.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 127586.85

Cost for 120 cum = a+b+c+d+e+f 1403455.35


Rate per cum = (a+b+c+d+e+f)/120 11695.46
say 11695.00

Page 33 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 850579.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 255173.70
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 221150.54
f) Contractor's profit @ 10% on (a+b+c+d+e) 132690.32

Cost for 120 cum = a+b+c+d+e+f 1459593.56


Rate per cum = (a+b+c+d+e+f)/120 12163.28
say 12163.00
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 850579.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 297702.65
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 229656.33
f) Contractor's profit @ 10% on (a+b+c+d+e) 137793.80

Cost for 120 cum = a+b+c+d+e+f 1515731.78


Rate per cum = (a+b+c+d+e+f)/120 12631.10
say 12631.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7200.00 43920.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 30.50 100.00 3050.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 18.30 75.00 1372.50
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 85.40 95.00 8113.00
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 21.00 244.56 5135.76
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 96747.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)

Page 34 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 96747.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 19349.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23219.28
f) Contractor's profit @ 10% on (a+b+c+d+e) 13931.57

Cost for 15 cum = a+b+c+d+e+f 153247.25


Rate per cum = (a+b+c+d+e+f)/15 10216.48
say 10216.00
14.1C (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 96747.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 24186.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24186.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 14512.05

Cost for 15 cum = a+b+c+d+e+f 159632.55


Rate per cum = (a+b+c+d+e+f)/15 10642.17
say 10642.00
14.1C (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 96747.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 29024.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25154.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 15092.53

Cost for 15 cum = a+b+c+d+e+f 166017.85


Rate per cum = (a+b+c+d+e+f)/15 11067.86
say 11068.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 96747.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 24186.75
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24186.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 14512.05

Cost for 15 cum = a+b+c+d+e+f 159632.55


Rate per cum = (a+b+c+d+e+f)/15 10642.17
say 10642.00
14.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 96747.00
for 15 cum

Page 35 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 30 per cent of 30.00 29024.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25154.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 15092.53

Cost for 15 cum = a+b+c+d+e+f 166017.85


Rate per cum = (a+b+c+d+e+f)/15 11067.86
say 11068.00
14.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 96747.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 33861.45
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 26121.69
f) Contractor's profit @ 10% on (a+b+c+d+e) 15673.01

Cost for 15 cum = a+b+c+d+e+f 172403.15


Rate per cum = (a+b+c+d+e+f)/15 11493.54
say 11494.00
14.1C Case II Using Batching Plant, Transit Mixer and
Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7200.00 351288.00
Coarse sand cum 54.60 950.00 51870.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 243.95 100.00 24395.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 146.37 75.00 10977.75
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 683.06 95.00 64890.70
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 19.00 244.56 4646.64
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 858992.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)

Page 36 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 858992.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 171798.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 206158.08
f) Contractor's profit @ 10% on (a+b+c+d+e) 123694.85

Cost for 120 cum = a+b+c+d+e+f 1360643.33


Rate per cum = (a+b+c+d+e+f)/120 11338.69
say 11339.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 858992.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 214748.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 214748.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 128848.80

Cost for 120 cum = a+b+c+d+e+f 1417336.80


Rate per cum = (a+b+c+d+e+f)/120 11811.14
say 11811.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 858992.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 257697.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 223337.92
f) Contractor's profit @ 10% on (a+b+c+d+e) 134002.75

Cost for 120 cum = a+b+c+d+e+f 1474030.27


Rate per cum = (a+b+c+d+e+f)/120 12283.59
say 12284.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 858992.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 214748.00
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 214748.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 128848.80

Cost for 120 cum = a+b+c+d+e+f 1417336.80


Rate per cum = (a+b+c+d+e+f)/120 11811.14
say 11811.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 858992.00
for 120 cum

Page 37 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 30 per cent of 30.00 257697.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 223337.92
f) Contractor's profit @ 10% on (a+b+c+d+e) 134002.75

Cost for 120 cum = a+b+c+d+e+f 1474030.27


Rate per cum = (a+b+c+d+e+f)/120 12283.59
say 12284.00
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 858992.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 300647.20
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 231927.84
f) Contractor's profit @ 10% on (a+b+c+d+e) 139156.70

Cost for 120 cum = a+b+c+d+e+f 1530723.74


Rate per cum = (a+b+c+d+e+f)/120 12756.03
say 12756.00
14.1 Furnishing and Placing Reinforced/ Prestressed
cement concrete in super-structure as per drawing
and Technical Specification including providing
plasticiser ( Masterplast SPl-2 or equivalent )
D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7200.00 45576.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 31.65 100.00 3165.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 18.99 75.00 1424.25
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 88.62 95.00 8418.90
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 21.00 244.56 5135.76
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 98876.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case I of (a+b+c)
(p) Height upto 5m

Page 38 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 18 per cent of 18.00 17797.68
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 23334.74
f) Contractor's profit @ 10% on (a+b+c+d+e) 14000.84

Cost for 15 cum = a+b+c+d+e+f 154009.26


Rate per cum = (a+b+c+d+e+f)/15 10267.28
say 10267.00
14.1D (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 22741.48
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24323.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 14594.10

Cost for 15 cum = a+b+c+d+e+f 160535.07


Rate per cum = (a+b+c+d+e+f)/15 10702.34
say 10702.00
14.1D (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 28 per cent of 28.00 27685.28
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25312.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 15187.35

Cost for 15 cum = a+b+c+d+e+f 167060.89


Rate per cum = (a+b+c+d+e+f)/15 11137.39
say 11137.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 22741.48
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24323.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 14594.10

Cost for 15 cum = a+b+c+d+e+f 160535.07


Rate per cum = (a+b+c+d+e+f)/15 10702.34
say 10702.00
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum

Page 39 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 28 per cent of 28.00 27685.28
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25312.26
f) Contractor's profit @ 10% on (a+b+c+d+e) 15187.35

Cost for 15 cum = a+b+c+d+e+f 167060.89


Rate per cum = (a+b+c+d+e+f)/15 11137.39
say 11137.00
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 33 per cent of 33.00 32629.08
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 26301.02
f) Contractor's profit @ 10% on (a+b+c+d+e) 15780.61

Cost for 15 cum = a+b+c+d+e+f 173586.71


Rate per cum = (a+b+c+d+e+f)/15 11572.45
say 11572.00
14.1D (iii) For box girder and balanced cantilever, 38-58
Case I per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 38 per cent of 38.00 37572.88
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 27289.78
f) Contractor's profit @ 10% on (a+b+c+d+e) 16373.87

Cost for 15 cum = a+b+c+d+e+f 180112.52


Rate per cum = (a+b+c+d+e+f)/15 12007.50
say 12008.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 48 per cent of 48.00 47460.48
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 29267.30
f) Contractor's profit @ 10% on (a+b+c+d+e) 17560.38

Cost for 15 cum = a+b+c+d+e+f 193164.15


Rate per cum = (a+b+c+d+e+f)/15 12877.61
say 12878.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 98876.00
for 15 cum
d) Formwork and staging 58 per cent of 58.00 57348.08
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 31244.82

Page 40 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 18746.89

Cost for 15 cum = a+b+c+d+e+f 206215.79


Rate per cum = (a+b+c+d+e+f)/15 13747.72
say 13748.00
Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7200.00 364608.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 253.20 100.00 25320.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 151.92 75.00 11394.00
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 708.96 95.00 67351.20
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 19.00 244.56 4646.64
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 875543.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 157597.74
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 206628.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 123976.89

Cost for 120 cum = a+b+c+d+e+f 1363745.78


Rate per cum = (a+b+c+d+e+f)/120 11364.55
say 11365.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum

Page 41 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 23 per cent of 23.00 201374.89
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 215383.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 129230.15

Cost for 120 cum = a+b+c+d+e+f 1421531.61


Rate per cum = (a+b+c+d+e+f)/120 11846.10
say 11846.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 245152.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 224139.01
f) Contractor's profit @ 10% on (a+b+c+d+e) 134483.40

Cost for 120 cum = a+b+c+d+e+f 1479317.45


Rate per cum = (a+b+c+d+e+f)/120 12327.65
say 12328.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 201374.89
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 215383.58
f) Contractor's profit @ 10% on (a+b+c+d+e) 129230.15

Cost for 120 cum = a+b+c+d+e+f 1421531.61


Rate per cum = (a+b+c+d+e+f)/120 11846.10
say 11846.00
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 245152.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 224139.01
f) Contractor's profit @ 10% on (a+b+c+d+e) 134483.40

Cost for 120 cum = a+b+c+d+e+f 1479317.45


Rate per cum = (a+b+c+d+e+f)/120 12327.65
say 12328.00
14.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 288929.19
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 232894.44

Page 42 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


f) Contractor's profit @ 10% on (a+b+c+d+e) 139736.66

Cost for 120 cum = a+b+c+d+e+f 1537103.29


Rate per cum = (a+b+c+d+e+f)/120 12809.19
say 12809.00
14.1D (iii) For box girder and balanced cantilever, 38-58
Case II per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 332706.34
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 241649.87
f) Contractor's profit @ 10% on (a+b+c+d+e) 144989.92

Cost for 120 cum = a+b+c+d+e+f 1594889.13


Rate per cum = (a+b+c+d+e+f)/120 13290.74
say 13291.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 420260.64
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 259160.73
f) Contractor's profit @ 10% on (a+b+c+d+e) 155496.44

Cost for 120 cum = a+b+c+d+e+f 1710460.80


Rate per cum = (a+b+c+d+e+f)/120 14253.84
say 14254.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 875543.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 507814.94
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 276671.59
f) Contractor's profit @ 10% on (a+b+c+d+e) 166002.95

Cost for 120 cum = a+b+c+d+e+f 1826032.48


Rate per cum = (a+b+c+d+e+f)/120 15216.94
say 15217.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 7200.00 46440.00
Coarse sand cum 6.75 950.00 6412.50
20 mm Aggregate cum 8.10 1777.00 14393.70
10 mm Aggregate cum 5.40 1916.00 10346.40
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 32.25 100.00 3225.00
5Lit per Tonne cement

Page 43 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Air entraining and water reducing plasticiser Lit 19.35 75.00 1451.25
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 90.30 95.00 8578.50
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement

b) Labour
Mate day 0.96 356.65 342.38
Mason day 2.00 458.55 917.10
Mazdoor day 22.00 244.56 5380.32
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Basic Cost of Labour, Material & Machinery 100482.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 100482.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 20096.40
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 24115.68
f) Contractor's profit @ 10% on (a+b+c+d+e) 14469.41

Cost for 15 cum = a+b+c+d+e+f 159163.49


Rate per cum = (a+b+c+d+e+f)/15 10610.90
say 10611.00
14.1E (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 100482.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 25120.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25120.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 15072.30

Cost for 15 cum = a+b+c+d+e+f 165795.30


Rate per cum = (a+b+c+d+e+f)/15 11053.02
say 11053.00
14.1E (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 100482.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 30144.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 26125.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 15675.19

Cost for 15 cum = a+b+c+d+e+f 172427.11


Rate per cum = (a+b+c+d+e+f)/15 11495.14

Page 44 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


say 11495.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 100482.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 25120.50
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 25120.50
f) Contractor's profit @ 10% on (a+b+c+d+e) 15072.30

Cost for 15 cum = a+b+c+d+e+f 165795.30


Rate per cum = (a+b+c+d+e+f)/15 11053.02
say 11053.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 100482.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 30144.60
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 26125.32
f) Contractor's profit @ 10% on (a+b+c+d+e) 15675.19

Cost for 15 cum = a+b+c+d+e+f 172427.11


Rate per cum = (a+b+c+d+e+f)/15 11495.14
say 11495.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 100482.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 35168.70
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 27130.14
f) Contractor's profit @ 10% on (a+b+c+d+e) 16278.08

Cost for 15 cum = a+b+c+d+e+f 179058.92


Rate per cum = (a+b+c+d+e+f)/15 11937.26
say 11937.00
14.1E Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7200.00 371520.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 258.00 100.00 25800.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 154.80 75.00 11610.00
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement

Page 45 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Accelerating plasticiser conforming to IS-9103- Lit 722.40 95.00 68628.00
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 884923.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per
Case II cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 159286.14
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 208841.83
f) Contractor's profit @ 10% on (a+b+c+d+e) 125305.10

Cost for 15 cum = a+b+c+d+e+f 1378356.06


Rate per cum = (a+b+c+d+e+f)/120 11486.30
say 11486.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 203532.29
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 217691.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 130614.63

Cost for 120 cum = a+b+c+d+e+f 1436760.98


Rate per cum = (a+b+c+d+e+f)/120 11973.01
say 11973.00
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 247778.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 226540.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 135924.17

Cost for 120 cum = a+b+c+d+e+f 1495165.90

Page 46 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Rate per cum = (a+b+c+d+e+f)/120 12459.72
say 12460.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 203532.29
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 217691.06
f) Contractor's profit @ 10% on (a+b+c+d+e) 130614.63

Cost for 120 cum = a+b+c+d+e+f 1436760.98


Rate per cum = (a+b+c+d+e+f)/120 11973.01
say 11973.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 247778.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 226540.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 135924.17

Cost for 120 cum = a+b+c+d+e+f 1495165.90


Rate per cum = (a+b+c+d+e+f)/120 12459.72
say 12460.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 292024.59
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 235389.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 141233.71

Cost for 120 cum = a+b+c+d+e+f 1553570.82


Rate per cum = (a+b+c+d+e+f)/120 12946.42
say 12946.00
14.1E (iii) For cast-in-situ box girder, segment
Case II construction and balanced cantilever, 38-58 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 336270.74
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 244238.75
f) Contractor's profit @ 10% on (a+b+c+d+e) 146543.25

Cost for 120 cum = a+b+c+d+e+f 1611975.74


Rate per cum = (a+b+c+d+e+f)/120 13433.13
say 13433.00

Page 47 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 424763.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 261937.21
f) Contractor's profit @ 10% on (a+b+c+d+e) 157162.32

Cost for 120 cum = a+b+c+d+e+f 1728785.57


Rate per cum = (a+b+c+d+e+f)/120 14406.55
say 14407.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 884923.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 513255.34
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 279635.67
f) Contractor's profit @ 10% on (a+b+c+d+e) 167781.40

Cost for 120 cum = a+b+c+d+e+f 1845595.41


Rate per cum = (a+b+c+d+e+f)/120 15379.96
say 15380.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 7200.00 401760.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 279.00 100.00 27900.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 167.40 75.00 12555.00
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 781.20 95.00 74214.00
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00

Page 48 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Basic Cost of Labour, Material & Machinery 923794.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-
26 per cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 16 per cent of 16.00 147807.04
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 214320.21
f) Contractor's profit @ 10% on (a+b+c+d+e) 128592.12

Cost for 120 cum = a+b+c+d+e+f 1414513.37


Rate per cum = (a+b+c+d+e+f)/120 11787.61
say 11788.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 193996.74
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 223558.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 134134.89

Cost for 120 cum = a+b+c+d+e+f 1475483.78


Rate per cum = (a+b+c+d+e+f)/120 12295.70
say 12296.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 240186.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 232796.09
f) Contractor's profit @ 10% on (a+b+c+d+e) 139677.65

Cost for 120 cum = a+b+c+d+e+f 1536454.18


Rate per cum = (a+b+c+d+e+f)/120 12803.78
say 12804.00
14.1F (ii) For T-beam & slab including launching of
precast girders by launching truss upto 40 m
span, 21-31 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 193996.74
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 223558.15
f) Contractor's profit @ 10% on (a+b+c+d+e) 134134.89

Cost for 120 cum = a+b+c+d+e+f 1475483.78


Rate per cum = (a+b+c+d+e+f)/120 12295.70
say 12296.00

Page 49 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 240186.44
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 232796.09
f) Contractor's profit @ 10% on (a+b+c+d+e) 139677.65

Cost for 120 cum = a+b+c+d+e+f 1536454.18


Rate per cum = (a+b+c+d+e+f)/120 12803.78
say 12804.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 31 per cent of 31.00 286376.14
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 242034.03
f) Contractor's profit @ 10% on (a+b+c+d+e) 145220.42

Cost for 120 cum = a+b+c+d+e+f 1597424.58


Rate per cum = (a+b+c+d+e+f)/120 13311.87
say 13312.00
14.1F (iii) For cast-in-situ box girder, segmental
construction and balanced cantilever, 36-56 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 36 per cent of 36.00 332565.84
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 251271.97
f) Contractor's profit @ 10% on (a+b+c+d+e) 150763.18

Cost for 120 cum = a+b+c+d+e+f 1658394.99


Rate per cum = (a+b+c+d+e+f)/120 13819.96
say 13820.00
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum
d) Formwork and staging 46 per cent of 46.00 424945.24
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 269747.85
f) Contractor's profit @ 10% on (a+b+c+d+e) 161848.71

Cost for 120 cum = a+b+c+d+e+f 1780335.80


Rate per cum = (a+b+c+d+e+f)/120 14836.13
say 14836.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 923794.00
for 120 cum

Page 50 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


d) Formwork and staging 56 per cent of 56.00 517324.64
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 288223.73
f) Contractor's profit @ 10% on (a+b+c+d+e) 172934.24

Cost for 120 cum = a+b+c+d+e+f 1902276.60


Rate per cum = (a+b+c+d+e+f)/120 15852.31
say 15852.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 7200.00 423360.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 294.00 100.00 29400.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 176.40 75.00 13230.00
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 823.20 95.00 78204.00
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 951559.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 951559.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 333045.65
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 256920.93
f) Contractor's profit @ 10% on (a+b+c+d+e) 154152.56

Cost for 120 cum = a+b+c+d+e+f 1695678.14


Rate per cum = (a+b+c+d+e+f)/120 14130.65
say 14131.00
14.1G (q) Height 5m to 10m
(i)

Page 51 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Basic Cost of Labour, Material & Machinery (a+b+c) 951559.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 428201.55
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 275952.11
f) Contractor's profit @ 10% on (a+b+c+d+e) 165571.27

Cost for 120 cum = a+b+c+d+e+f 1821283.93


Rate per cum = (a+b+c+d+e+f)/120 15177.37
say 15177.00
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 951559.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 523357.45
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 294983.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 176989.97

Cost for 120 cum = a+b+c+d+e+f 1946889.71


Rate per cum = (a+b+c+d+e+f)/120 16224.08
say 16224.00
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 7200.00 457200.00
Coarse sand cum 54.00 950.00 51300.00
20 mm Aggregate cum 64.80 1916.00 124156.80
10 mm Aggregate cum 43.20 1619.00 69940.80
Admixture ( Masterplast SPl-2 or equivalent) @ Lit 317.50 100.00 31750.00
5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 190.50 75.00 14287.50
conforming to IS-9103-1999( Masterplast PAE
or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS-9103- Lit 889.00 95.00 84455.00
1999 ( Masterplast APCL or equivalent ) @
14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25
Mason day 3.50 458.55 1604.93
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader hour 6.00 1341.00 8046.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 40.00 120000.00
Concrete Pump hour 6.00 234.00 1404.00
Basic Cost of Labour, Material & Machinery 995058.00
(a+b+c) for 120 cum
For formwork and staging add the following:

Page 52 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.1H (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 995058.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 348270.30
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 268665.66
f) Contractor's profit @ 10% on (a+b+c+d+e) 161199.40

Cost for 120 cum = a+b+c+d+e+f 1773193.36


Rate per cum = (a+b+c+d+e+f)/120 14776.61
say 14777.00
14.1H (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 995058.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 447776.10
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 288566.82
f) Contractor's profit @ 10% on (a+b+c+d+e) 173140.09

Cost for 120 cum = a+b+c+d+e+f 1904541.01


Rate per cum = (a+b+c+d+e+f)/120 15871.18
say 15871.00
14.1H (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 995058.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 547281.90
(a+b+c)
e) Overhead charges @ 20 % on (a+b+c+d) 308467.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 185080.79

Cost for 120 cum = a+b+c+d+e+f 2035888.67


Rate per cum = (a+b+c+d+e+f)/120 16965.74
say 16966.00
Note 1.Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving desired slump of
concrete.
2. Cement provided for various components of the
super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix
design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact

3. The items like needle and surface vibrators are


part of minor T & P which is already covered under
the overhead charges. As such these items have not
been added separately in the rate analysis.

Page 53 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.2 Supplying, fitting and placing TMT bar
reinforcement in super-structure including
splicing complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
(a) TMT-IS 1786 ( Fe-500 D) Primary Producer
(TATA/ SAIL/ Esser Steel/ Jindal steel/ Shyam
steel or equivalent)
a) Material
TMT bars including 5 per cent for laps and tonne 1.05 53667.00 56350.35
wastage
Binding wire Kg 8.00 85.00 680.00
b) Labour for cutting, bending, tying and
placing in position
Mate day 0.44 100.00 44.00
Blacksmith day 3.00 120.00 360.00
Mazdoor day 8.00 100.00 800.00
Basic Cost of Labour & Material (a+b) 58235.00
c) Overhead charges @ 20 % on (a+b) 14558.59
d) Contractor's profit @ 10% on (a+b+c) 7279.29
Rate per MT = a+b+c+d 80072.23
say 80072.00
Unit = 1 MT
Taking output = 1 MT
(b) TMT-IS 1786 ( Fe-500 D) Secondary Producer
(ISI approved)
a) Material
TMT bars including 5 per cent for laps and tonne 1.05 49667.00 52150.35
wastage
Binding wire Kg 8.00 85.00 680.00
b) Labour for cutting, bending, tying and
placing in position
Mate day 0.44 100.00 44.00
Blacksmith day 3.00 120.00 360.00
Mazdoor day 8.00 100.00 800.00
Basic Cost of Labour & Material (a+b) 54035.00
c) Overhead charges @ 20 % on (a+b) 13508.59
d) Contractor's profit @ 10% on (a+b+c) 6754.29
Rate per MT = a+b+c+d 74297.23
say 74297.00
14.3 High tensile steel wires/strands including all
accessories for stressing, stressing operations
and grouting complete as per drawing and
Technical Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable
(weight = 0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent tonne 0.39 114109.00 43931.97
for wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent metre 42.00 95.00 3990.00
extra length 40 x 1.05 = 42 m.

Page 54 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Tube anchorage set complete with bearing each 2.00 1500.00 3000.00
plate, permanent wedges etc
Cement for grouting including 3 per cent tonne 0.125 7200.00 900.00
wastage @ 3.00 kg/m = 3 x 1.03 x 40 = 123.60
kg (say, = 125 kg)
Add 0.50 per cent cost of material for Spacers, 2591.10
Insulation tape and miscellaneous items

b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 356.65 57.06
Blacksmith day 1.00 458.55 458.55
Mazdoor day 3.00 244.56 733.68
ii) For prestressing
Mate/Supervisor day 0.05 356.65 17.83
Prestressing operator / Fitter day 0.25 458.55 114.64
Mazdoor day 1.00 244.56 244.56
iii) For grouting
Mate/Supervisor day 0.05 356.65 17.83
Mason day 0.25 458.55 114.64
Mazdoor day 1.00 244.56 244.56
c) Machinery
Stressing jack with pump hour 2.50 113.00 282.50
Grouting pump with agitator hour 1.00 310.00 310.00
Generator 33 KVA. hour 3.50 311.00 1088.50
d) Overhead charges @ 20 % on (a+b+c) 736.87
e) Contractor's profit @ 10% on (a+b+c+d) 442.12
Cost for 0.377 MT (a+b+c+d+e) 59276.41
Rate per MT = (a+b+c+d+e)/0.377 157231.86
say 157232.00
Note Cost of HT steel has been taken for delivery at site.
Hence carriage has not been considered.
14.4 Providing and laying Cement concrete wearing
coat M-30 grade including reinforcement
complete as per drawing and Technical
Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant cum 1.00 6454.00 6454.00
item of concrete in Item 14.1 excluding
formwork
TMT bar reinforcement Rate as per item No tonne 0.075 60520.00 4539.00
14.2(Excluding OH & CP)
b) Labour
Mazdoor for cleaning deck slab concrete day 0.15 244.56 36.68
surface.
c) Overhead charges @ 20 % on (a+b) 2205.94
d) Contractor's profit @ 10% on (a+b+c) 1323.56
Rate per cum (a+b+c+d) 14559.18
say 14559.00
14.5 Mastic Asphalt

Page 55 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


(A) Providing and laying 12 mm thick mastic
asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen
meeting the requirements given in table 500-29,
prepared by using mastic cooker and laid to
required level and slope after cl

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869
cum) assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 356.65 174.76
Mazdoor day 11.00 244.56 2690.16
Mazdoor (Skilled) day 1.25 356.65 445.81
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 337.00 20.22
Air compressor 250 cfm hour 0.06 435.00 26.10
Mastic cooker 1 tonne capacity hour 6.00 56.00 336.00
Bitumen boiler 1500 litres capacity hour 6.00 1590.00 9540.00
Tractor for towing and positioning of mastic hour 1.00 323.00 323.00
cooker and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per
cent .
Proportion of material required for mastic asphalt
with coarse aggregates (based on mix design done
by CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 tonne 0.204 32627.00 6655.91
per cent by weight of mix. 2 x 10.2/100 = 0.204

ii) Crusher stone dust @ 31.9 per cent by cum 0.39 698.00 272.22
weight of mix = 2 x 31.9/100 = 0.638 tonnes =
0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate tonne 0.36 5900.00 2124.00
content not less than 80 per cent by weight @
17.92 per cent by weight of mix = 2 x
17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size cum 0.55 1916.00 1053.80
@ 40 per cent by weight of mix = 2 x 40/100 =
0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal cum 0.036 3890.00 140.04
size for skid resistance = 72.46x0.005/10 =
0.036
vi) Bitumen for coating of chips @ 2 per cent kg 1.05 32.63 34.26
by weight = 0.036 x 1.456 x 2/100 =
0.001048MT = 1.05kg
Per Sqm Basic Cost of Labour, Material & Mechinery (a+b+c) 142.00
d) Overhead charges @ 20 % on (a+b+c) 4767.26
e) Contractor's profit @ 10% on (a+b+c+d) 2860.35
Cost for 72.46 sqm = a+b+c+d+e 31463.89
Rate per sqm = (a+b+c+d+e)/72.46 434.22
say 434.00

Page 56 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Note 1.The rates for 6 mm or any other thickness may be
worked out on pro-rata basis.
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are
for estimating purpose. Exact quantities shall be as
per mix design.
4.This rate analysis is based on design made by
CRRI for a specific case and is meant for estimating
purposes only. Actual design is required to be done
for each case.
5.The quantity of bitumen works out 17 per cent of
the mastic asphalt blocks without aggregates and
falls within the standards laid down by MoRTH
Specifications.
(B) Providing Bituminous wearing course
comprising of tack coat with bitumen emulsion
CSS-1h as per APWD SOR item no 5.2 &
MOSRT&H Specification Nos 503 0.6mm thick
mastic asphalt as per APWD SOR item no
14.5& MOSRT&H Specification Nos 515& 2702
and 2 layers of 25 mm thick Asphalt concrete
including of close Graded Premix
Surfacing(CGPS) materials with Type -a
aggregate as per APWD SOR tem no 5.11 &
MOSRT&H Specification Nos 512 including all
lead and lift as directed.

Unit = sqm
Taking output = 1 sqm
Take coat: (I)With Bitumen emulsion CSS-1h 10.00
Per Sqm Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 5.2 (I)
2x25 mm thick open graded premix sufacing 332.50
Per Sqm Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 5.11 (a) (I) @ 2x25/20
6 mm thick Mastic Asphalt wearing coarse 71.00
Per Sqm Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 14.5(A) @ 0.5
d) Overhead charges @ 20 % on (a+b+c) 82.70
e) Contractor's profit @ 10% on (a+b+c+d) 49.62
Cost for 1 sqm = a+b+c+d+e 545.82
Rate per sqm = (a+b+c+d+e)/72.46 545.82
say 546.00
Note 1.The rates for 6 mm or any other thickness may be
worked out on pro-rata basis.
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are
for estimating purpose. Exact quantities shall be as
per mix design.

Page 57 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


4.This rate analysis is based on design made by
CRRI for a specific case and is meant for estimating
purposes only. Actual design is required to be done
for each case.
5.The quantity of bitumen works out 17 per cent of
the mastic asphalt blocks without aggregates and
falls within the standards laid down by MoRTH
Specifications.
14.6 Construction of precast RCC railing of M30
Grade, aggregate size not exceeding 12 mm,
true to line and grade, tolerance of vertical RCC
post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed
2000 mm, leaving adequate spa
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant cum 4.09 6454.00 26409.77
item of concrete in Item 14.1(C) by using
batching plant, excluding formwork i.e. per cum
basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos.,
External area of vertical post 0.25x0.275 =
0.069sqm, Concrete in Vertical posts = 0.069 x
28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 =
72 m, External area = 0.170 x 0.175 = 0.03
sqm, Concrete in hand rails
Add 5 per cent of above cost for form work for 1320.49
casting in casting yard.
HYSD bar reinforcement Rate as per item No tonne 0.87 60520.00 52349.80
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing 4004.00
of precast panels in position
b) Overhead charges @ 20 % on (a) 16816.81
c) Contractor's profit @ 10% on (a+b) 10090.09
Rate for 48 m (a+b+c) 110990.96
Rate per metre (a+b+c)/48 2312.31
say 2312.00
Note 1.Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.

2.48 m length is the total linear length adding both


sides of 24 m span.
14.7 Construction of RCC railing of M30 Grade in-
situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm,
leaving adequate space
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material

Page 58 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Cement concreteM30 Grade Refer relevant cum 4.092 6454.00 26409.77
item of concrete in Item 14.1(C) by using
batching plant, excluding formwork i.e. per cum
basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos.,
External area of vertical post 0.25x0.275 =
0.069sqm, Concrete in vehicle posts = 0.069 x
28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 =
72 m, External area = 0.170 x 0.175 = 0.03
sqm, Concrete in hand rails =
Add 12 per cent of above cost for form work. 3169.17
HYSD bar reinforcement Rate as per item No tonne 0.87 60520.00 52349.80
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b) Overhead charges @ 20 % on (a) 16385.75
c) Contractor's profit @ 10% on (a+b) 9831.45
Rate for 48 m (a+b+c) 108145.94
Rate per metre (a+b+c)/48 2253.04
say 2253.00
Note 1. Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.

2. 48 m length is the total linear length adding both


sides of 24 m span.
14.8 Providing, fitting and fixing mild steel railing
complete as per drawing and Technical
Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 3.50 60000.00 210000.00
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 60000.00 60720.00
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 60000.00 10800.00
4) MS bolts, nuts and washers tonne 0.15 90000.00 13500.00
Add @ 5 per cent of cost of material for 14751.00
painting one shop coat with red oxide primer
and three coats of synthetic enamel paint and
consumables to safeguard against weathering
and corrosion.
Add for cost of concrete for fixing vertical posts 2950.20
in the performed recess @ 1 per cent of cost
of material.
Add for electricity charges, welding and drilling 2950.20
equipment, electrodes and other consumables
@ 1 per cent of cost of material.
b) Labour
Mate day 2.80 356.65 998.62
Mazdoor (Skilled) day 30.00 356.65 10699.50
Mazdoor day 40.00 244.56 9782.40
c) Overhead charges @ 20 % on (a+b) 67430.38
d) Contractor's profit @ 10% on (a+b+c) 40458.23
Cost for 100 m steel railing = a+b+c+d 445040.53
Rate per metre (a+b+c+d)/100 4450.41
say 4450.00

Page 59 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


14.9 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 Kg 4.00 66.15 264.60
per cent wastage
GI pipe 100mm dia metre 6.00 900.00 5400.00
GI bolt 10 mm Dia each 6.00 13.00 78.00
Galvanised MS flat clamp each 2.00 288.00 576.00
b) Labour
For fabrication
Mate day 0.02 356.65 7.13
Skilled (Blacksmith, welder etc.) day 0.02 458.55 9.17
Mazdoor day 0.02 244.56 4.89
For fixing in position
Mate day 0.01 356.65 3.57
Mason day 0.01 458.55 4.59
Mazdoor day 0.20 244.56 48.91
Add @ 5 per cent of cost of material and 319.84
labour for electrodes, cutting gas, sealant, anti-
corrosive bituminous paint, mild steel grating
etc.
c) Overhead charges @ 20 % on (a+b) 1343.34
d) Contractor's profit @ 10% on (a+b+c) 806.00
Rate per metre (a+b+c+d) 8866.05
say 8866.00
Note 1. In case of viaducts in urban areas, the drainage
spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains
provided at ground level.
2. In case of bridges, sufficient length of G.I Pipe
shall be provided to ensure that there is no splashing
of water from the drainage spout on the structure.

14.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) cum 1.00 6001.00 6001.00
excluding formworks

Rate per cum say 6001.00


14.11 Reinforced cement concrete approach slab
including reinforcement and formwork complete
as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
a) Material

Page 60 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Cement concreteM30 Grade Refer relevant cum 1.00 7022.00 7022.00
item of concrete in item 12.8(G)by using
batching plant, excluding formwork i.e. per cum
basic cost (a+b+c) (Excluding OH & CP)
( Refer relevant item of concrete in item No. 140.44
13.8 (G) except that form work may be added
at the rate of 2 per cent of cost against 3.5 per
cent provided in the foundation concrete.
Unit rate 7162.44
(a) With TATA make TMT (Fe-500) grade rebar
TMT bar reinforcement Rate as per item No tonne 0.05 60520.00 3026.00
14.2(Excluding OH & CP)
b) Overhead charges @ 20 % on (a) 2037.69
c) Contractor's profit @ 10% on(a+b) 1222.61
Rate per cum (a+b+c) 13448.74
say 13449.00
(b) With TATA make TMT grade rebar
TMTbar reinforcement Rate as per item No tonne 0.05 56320.00 2816.00
14.2(Excluding OH & CP)
b) Overhead charges @ 20 % on (a) 1995.69
c) Contractor's profit @ 10% on(a+b) 1197.41
Rate per cum (a+b+c) 13171.54
say 13172.00
(c) With TATA make TMT grade rebar
TMT bar reinforcement Rate as per item No tonne 0.05 56320.00 2816.00
14.2(Excluding OH & CP)
b) Overhead charges @ 20 % on (a) 1995.69
c) Contractor's profit @ 10% on(a+b) 1197.41
Rate per cum (a+b+c) 13171.54
say 13172.00
Note The grade of reinforced cement concrete may be
adopted as M30 for severe conditions and M25 for
moderate conditions.
14.13 Precast - pretensioned Girders
Providing, precasting, transportation and
placing in position precast pretensioned
concrete girders as per drawing and technical
specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Cement tonne 0.47 7200.00 3384.00
Coarse sand cum 0.45 950.00 427.50
20 mm Aggregate cum 0.54 1916.00 1034.64
10 mm Aggregate cum 0.36 1619.00 582.84
Admixture @ 0.4 per cent of cement Kg 1.88 104.00 195.52
TMT steel . (TATA CRS Fe-500) tonne 0.10 53667.00 5366.70
HT strand with 5 per cent as wastage and tonne 0.06 53667.00 3220.02
extra length for anchoring
LDO for steam curing Litre 37.00 34.00 1258.00
Add consumables such as binding wire, foam, 2.25
packing tape, shuttering oil, HDPE pipe for
unbonding of strand, bolt & nuts etc @ 1 per
cent of material cost

Page 61 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


b) Labour
(i) Cutting, bending, making reinforcement
cage, placing in position, binding etc. complete

Taking quantity of steel 100 Kg/cum of concrete


including laps and wastage
Mate day 0.06 356.65 21.40
Mazdoor (Skilled) day 0.35 356.65 124.83
Mazdoor day 1.40 244.56 342.38
(ii) Cable cutting and threading in position
including binding by insulation tape with HDPE
pipes etc., prestessing and cutting of extra
length of HT strand after de-stressing.
Taking quantity of HT strand 60 Kg/cum
Mate day 0.02 356.65 7.13
Mazdoor (Skilled) day 0.14 356.65 49.93
Mazdoor day 0.50 244.56 122.28
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete

Mate day 0.12 356.65 42.80


Mazdoor (Skilled) day 1.00 356.65 356.65
Mazdoor day 2.00 244.56 489.12
(iv) Concreting by Batching plant and stationary
concrete pump
Mate day 0.03 356.65 10.70
Mazdoor (Skilled) day 0.05 356.65 17.83
Mazdoor day 0.60 244.56 146.74
(v) Steam curing and manual curing
Mate day 0.01 356.65 3.57
Mazdoor day 0.35 244.56 85.60
(vi) Handling of precast girder, stacking in
stockyard and again loading in trailor
Mate day 0.01 356.65 3.57
Mazdoor day 0.25 244.56 61.14
(vii) Placement of girders in position over pier
caps including placement of sand jacks,
channel, levelling etc.
Mate day 0.01 356.65 3.57
Mazdoor (Skilled) day 0.06 356.65 21.40
Mazdoor day 0.24 244.56 58.69
c) Machinery
i) At casting yard
Generator 100 KVA hour 0.05 621.00 31.05
Batching Plant @ 20 cum/hour hour 0.05 1590.00 79.50
Transit Mixer 4 cum capacity hour 0.10 828.00 82.80
Concrete Pump stationary hour 0.05 234.00 11.70
Crane 35 tonne capacity hour 0.10 759.00 75.90
Trailor 30 tonne capacity hour 0.10 300.00 30.00
Loader hour 0.05 1341.00 67.05
ii) For transportation and placement at site
Crane 35 tonne capacity hour 0.15 759.00 113.85
Trailer 30 tonne capacity for transporting to site. tonne.km 2.5xL 2.25 56.25

Page 62 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.15 300.00 45.00
Cost of formwork, steam curing arrangement, 890.94
pretensioning arrangement etc @ 5 per cent of
cost material, labour and machinery
d) Overhead charges @ 20 % on (a+b+c) 3784.97
e) Contractor's profit @ 10% on (a+b+c+d) 2270.98
Rate per cum = (a+b+c+d+e) 24980.77
say 24981.00

14.14 Structural steel Built-Up-Girder (BUG)


Providing and launching Steel Truss of
Structural steel Built-Up-Girder (BUG) Super
Structure including painting complete as per as
per drawing and technical specifications under
Section 1900 of MOST.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structrual steel tonne 1.00 66150.00 66150.00
Add 1% of Structural steel for Electrodes and L/s 661.50
other consumables
Nuts and Bolts Kg 25.00 90.00 2250.00
Add 5% for cost of painting 1 shop coat of 3453.08
Aluminium paint including surface preparation
b) Labour
(i) Assembling of BUG
Fitter day 25.00 458.55 11463.75
Blacksmith (IInd class) day 14.00 356.65 4993.10
Mazdoor day 24.00 244.56 5869.44
Welder day 14.00 458.55 6419.70
(ii) Handling of BUG, stacking in stockyard and
again loading in trailor
Mate day 2.00 356.65 713.30
Mazdoor day 12.00 244.56 2934.72
(iii) Placement of BUG in position over pier
caps including placement of sand jacks,
channel, levelling etc.
Mate day 1.00 356.65 356.65
Mazdoor (Skilled) day 3.00 356.65 1069.95
Mazdoor day 12.00 244.56 2934.72
c) Machinery
i) At yard
Welding Machine hour 4.00 500.00 2000.00
ii) For transportation and placement at site
Crane 35 tonne capacity hour 7.20 759.00 5464.80
Trailer 30 tonne capacity for transporting to site. tonne.km 1xL 2.25 225.00

(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 1.80 300.00 540.00
Cost of staging arrangement etc @ 3 per cent 3524.99
of cost material, labour and machinery
d) Overhead charges @ 20 % on (a+b+c) 23499.94
e) Contractor's profit @ 10% on (a+b+c+d) 14452.46

Page 63 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Rate per cum = (a+b+c+d+e) 158977.10
say 158977.00

14.16 Painting on concrete surface


Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1
litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
(A) On Plain surface
a) Labour
Mate day 0.01 356.65 3.57
Painter day 0.25 458.55 114.64
Mazdoor (Skilled) day 0.25 356.65 89.16
b) Material
Water based paint of approved quality for Litres 5.00 36.00 180.00
cement concrete surface
c) Overhead charges @ 20 % on (a+b) 77.47
d) Contractor's profit @ 10% on (a+b+c) 46.48
Cost for 10 sqm (a+b+c+d) 511.32
Rate per sqm (a+b+c+d)/10 51.13
say 51.00
(B) On RCC Brdge Railing @ 3.56 times over Item 3.56 182.03
No 14.16 (A)
Rate per RM 182.03
say 182.00
14.17 Burried Joint
Providing and laying a burried expansion joint,
expansion gap being 20 mm, covered with 12
mm thick, 200 mm wide galvanised weldable
structural steel plate as per IS: 2062, placed
symmetrical to centre line of the joint, resting
freely over the top surfac
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.02 356.65 7.13
Mazdoor day 0.40 244.56 97.82
Mazdoor (Skilled) day 0.20 356.65 71.33
b) Material
Galvanised M.S plate 200 mm wide,12 mm kg 237.50 56.00 13300.00
thick @ 94.20 kg/sqm including 5 per cent
wastage
Add 1 per cent of cost of steel plate cutting, 133.00
welding consumables and galvanised nails.
c) Overhead charges @ 20 % on (a+b) 2721.86
d) Contractor's profit @ 10% on (a+b+c) 1633.11
Cost for 12 m = (a+b+c+d) 17964.26
Rate per m = (a+b+c+d)/12 1497.02
say 1497.00

Page 64 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Note Guidelines laid down vide the MoRTH circular No.
RW/NH-34059/1/96-S&R dated 30.11.2000 and
subsequent corrigendum dated 25.01.2001 may be
reffered for expansion joints.
14.18 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper
plate in expansion joint complete as per
drawing & Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 356.65 14.27
Mazdoor day 0.50 244.56 122.28
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
Copper plate - 12m long x 250 mm wide kg 60.00 646.00 38760.00
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
c) Overhead charges @ 20 % on (a+b) 7814.97
d) Contractor's profit @ 10% on (a+b+c) 4688.98
Cost for 12 m = (a+b+c+d) 51578.83
Rate per m = (a+b+c+d)/12 4298.24
say 4298.00
14.18 (ii) Providing & fixing 20 mm thick compressible
fibre board in expansion joint complete as per
drawing & Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 356.65 2.85
Mazdoor day 0.10 244.56 24.46
Mazdoor (Skilled) day 0.10 356.65 35.67
b) Material
20 mm thick compressible fibre board 12 m sqm 3.00 1077.00 3231.00
long x 25 cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 20 % on (a+b) 658.79
d) Contractor's profit @ 10% on (a+b+c) 395.28
Cost for 12 m = (a+b+c+d) 4348.05
Rate per m = (a+b+c+d)/12 362.34
say 362.00
14.18 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for
fixed ends of simply supported spans not
exceeding 10 m to cater for a horizontal
movement upto 20 mm, covered with sealant
complete as per drawing and technical s
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.01 356.65 3.57

Page 65 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Mazdoor day 0.20 244.56 48.91
Mazdoor (Skilled) day 0.10 356.65 35.67
b) Material
Premoulded joint filler 12 m long,20 mm thick sqm 3.90 742.00 2893.80
and 300 mm deep.
c) Overhead charges @ 20 % on (a+b) 596.39
d) Contractor's profit @ 10% on (a+b+c) 357.83
Cost for 12 m = (a+b+c+d) 3936.17
Rate per m = (a+b+c+d)/12 328.01
say 328.00
14.18 (iv) Providing and filling joint sealing compound as
per drawings and technical specifications with
coarse sand and 6 per cent bitumen by weight

Unit = Running meter


Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a) Labour
Mate day 0.02 356.65 7.13
Mazdoor day 0.50 244.56 122.28
Mazdoor (Skilled) day 0.10 356.65 35.67
b) Material
Sand cum 0.012 950.00 11.40
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 32627.00 32.63
16.8 x 0.06 = 1 kg
c) Overhead charges @ 20 % on (a+b) 41.82
d) Contractor's profit @ 10% on (a+b+c) 25.09
Cost for 12 m = (a+b+c+d) 276.02
Rate per m = (a+b+c+d)/12 23.00
say 23.00
Note For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added
14.19 Asphaltic Plug joint
Providing and laying of asphaltic plug joint to
provide for horizontal movement of 25 mm and
vertical movement of 2 mm, depth of joint
varying from 75 mm to 100 mm, width varying
from 500 mm to 750 mm (in traffic direction),
covered with a closure plate o
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.052 356.65 18.55
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.30 356.65 107.00
b) Material
Crushed stone aggregate 12.5 mm nominal cum 0.75 1510.00 1132.50
size
Polymer modified bitumen kg 77.50 33.28 2579.20

Page 66 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


2.4 Galvanised structural steel plate 200 mm kg 113.00 61.00 6893.00
wide,6 mm thick, 12 m long (2.4 sqm) @ 47.10
kg/sqm including 5 per cent wastage
Add 1 per cent for welding and foam 109.75
caulking/backer rod and other incidentals.
c) Machinery
Mastic cooker 1 tonne capacity hour 1.00 56.00 56.00
Smooth 3-wheeled steel roller 8-10 capacity hour 0.50 924.00 462.00
d) Overhead charges @ 20 % on (a+b+c) 2320.51
e) Contractor's profit @ 10% on (a+b+c+d) 1392.31
Cost for 12 m asphalt plug joint = (a+b+c+d+e) 15315.36
Rate per m = (a+b+c+d+e)/12 1276.28
say 1276.00
Note The nominal size of aggregates shall be 12.5 mm for
depth of joint upto 75 mm and 20 mm for joints of
depth more than 75 mm.
14.20 Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab
steel expansion joint, catering to right or skew
(less than 20 deg., moderately curved with
maximum horizontal movement upto 50 mm,
complete as per approved drawings and
standard specifications to be installed b
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
Supply of elastomeric slab seal expansion joint metre 12.00 18000.00 216000.00
assembly manufactured by using chloroprene,
elastomer for elastomeric slab unit conforming
to clause 915.1 of IRC: 83 (part II), complete as
per approved drawings and standard
specification conforming to cla
Add 5 per cent of cost of material for 10800.00
anchorage reinforcement, welding and other
incidentals.
c) Overhead charges @ 20 % on (a+b) 45448.86
d) Contractor's profit @ 10% on (a+b+c) 27269.31
Cost for 12 m = (a+b+c+d) 299962.45
Rate per m = (a+b+c+d)/12 24996.87
say 24997.00
14.21 Compression Seal Joint
Providing and laying of compression seal joint
consisting of steel armoured nosing at two
edges of the joint gap suitably anchored to the
deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer
compressed and fixed into the jo
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.036 356.65 12.84

Page 67 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Mazdoor day 0.60 244.56 146.74
Mazdoor (Skilled) day 0.30 356.65 107.00
b) Material
1. Galvanised angle sections 100mm x 100mm kg 446.00 61.00 27206.00
of 12mm thickness weldable structural steel as
per IS: 2062, 2 nos. of 12 m length each @
17.7 kg/m and 5 per cent wastage.
Add 5 per cent of cost of above for structural 1373.63
steel for anchorage, welding and other
incidentals.
Preformed continuous chloroprene elastomer metre 12.00 8000.00 96000.00
or closed cell foam sealing element with high
tear strength, vulcanised in a single operation
for the full length of a joint to ensure water
tightness.
Add 1 per cent of cost of sealing element for 960.00
lubricant-cum-adhesive and other
consumables.
c) Overhead charges @ 20 % on (a+b) 25161.24
d) Contractor's profit @ 10% on (a+b+c) 15096.74
Cost for 12 m = (a+b+c+d) 166064.18
Rate per m = (a+b+c+d)/12 13838.68
say 13839.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
14.22 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement
upto 70 mm, complete as per approved
drawings and standard specifications to be
installed by the manufacturer/supplier or their
authorised representative ensuring

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.05 356.65 17.83
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.25 356.65 89.16
b) Material
Supply of complete assembly of strip seal metre 12.00 20000.00 240000.00
expansion joint comprising of edge beams,
anchorage, strip seal element and complete
accessories as per approved specifications and
drawings.

Page 68 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Add 5 per cent of cost of material for 12017.58
anchorage reinforcement, welding and other
incidentals.
c) Overhead charges @ 20 % on (a+b) 50473.83
d) Contractor's profit @ 10% on (a+b+c) 30284.30
Cost for 12 m = (a+b+c+d) 333127.26
Rate per m = (a+b+c+d)/12 27760.60
say 27761.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
14.23 Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to
a horizontal movement beyond 70 mm and upto
140mm, complete as per approved drawings
and standard specifications to be installed by
the manufacturer/supplier

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.056 356.65 19.97
Mazdoor day 1.00 244.56 244.56
Mazdoor (Skilled) day 0.40 356.65 142.66
b) Material
Supply of a modular strip/box seal joint metre 12.00 114000.00 1368000.00
assembly comprising of edge beams, central
beam,2 modules chloroprene seal, anchorage
elements, support and control system, all steel
sections protected against corrosion and
installed by the manufacturer or his au

c) Overhead charges @ 20 % on (a+b) 273681.44


d) Contractor's profit @ 10% on (a+b+c) 164208.86
Cost for 12 m Modular strip/box seal joint = 1806297.49
(a+b+c+d)
Rate per m = (a+b+c+d)/12 150524.79
say 150525.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
14.24 Modular Strip / Box Seal Joint

Page 69 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Providing and laying of a modular strip box seal
expansion joint catering to a horizontal
movement beyond 140mm and upto 210mm,
complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.07 356.65 24.97
Mazdoor day 1.25 244.56 305.70
Mazdoor (Skilled) day 0.50 356.65 178.33
b) Material
Supply of a modular box/box seal joint metre 12.00 172800.00 2073600.00
assembly containing 3 modules/cells and
comprising of edge beams, two central beams,
chloroprene seal, anchorage elements, support
and control system, all steel sections protected
against corrosion and installed by t

c) Overhead charges @ 20 % on (a+b) 414821.80


d) Contractor's profit @ 10% on (a+b+c) 248893.08
Cost for 12 m Modular strip/box seal joint = 2737823.87
(a+b+c+d)
Rate per m = (a+b+c+d)/12 228151.99
say 228152.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
14.25 Extra for providing water proofing compound
( Providing and applying cement
mortar(1 cement 3 sand) with STRUCO LATEX or its
equivalent as per specification and as directed by the
Department
Unit = Per suare mtere
Taking output = 100(One hundred) square
metre.
a) Labour
Mazdoor day 22 97 2134.00
Mazdoor(Skilled) day 11 102 1122.00
b) Material
Cement tonne 0.6500 7200.00 4680.00
Sand cum 17.500 950.00 16625.00
STRUCO LATEX Kg 15 82 1230.00
c) Overhead charges @ 20 % on (a+b) 5158.20
d) Contractor's profit @ 10% on (a+b+c) 3094.92
Cost of providing 100 sqm of waterproofing 34044.12
=(a+b+c+d)

Page 70 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Sr No Description Unit Quantity Rate Rs Cost Rs


Rate per m2 = (a+b+c+d)/100 340.44
say 340.00
14.26 Extra item for providing water proofing
compound
( clean the surfaces and applying two coats of
ARMOURCRETE as per specification or its
equivalent as per specification and as directed by the
Department
Unit = Per suare mtere
Taking output = 1 (One) square meter
a) Labour & Scafolding 40.00
b) Tools & tackles 12.00
c) Material
Cement tonne 0.0080 7200.00 57.60
ARMOURCRETE Kg 0.500 193.00 96.50
d) Profit & Overlays @ 15% on (a+b+c) 30.92
237.02
say 237.00

Page 71 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

CHAPTER-14
SUPER-STRUCTURE
Remarks/
Input ref.

M-084
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

Page 72 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 73 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 74 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-005
M-053
M-051

Page 75 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
L-12
L-11
L-13

P&M-009
P&M-079

Page 76 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 77 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 78 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

Page 79 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 80 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 81 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 82 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

Page 83 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 84 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 85 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 86 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 87 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-005
M-053
M-051

L-12
L-11
L-13

P&M-009
P&M-079

Page 88 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 89 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 90 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 91 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 92 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 93 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Page 94 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 95 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-004
M-053
M-051

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 96 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-084
M-005
M-053
M-051
M-208

M-210

M-211

L-12
L-11
L-13

Page 97 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

P&M-009
P&M-079

5821.00
58.41%

6064.00
58.39%

6307.00
58.38%

Page 98 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

6064.00
58.39%

6307.00
58.38%

6549.00
58.39%

M-084
M-004
M-053
M-051
M-208

M-210

M-211

L-12
L-11
L-13

P&M-003
P&M-080
P&M-017

Page 99 of 959
Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
P&M-049
#REF!
P&M-007

6515.00
58.11%

6786.00
58.12%

7058.00
58.10%

Page 100 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

6786.00
58.12%

7058.00
58.10%

7329.00
58.11%

M-084
M-005
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-009
P&M-079

Page 101 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

6455.00
56.19%

6724.00
56.19%

6993.00
56.18%

6724.00
56.19%

Page 102 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

6993.00
56.18%

7262.00
56.18%

M-084
M-004
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 103 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7156.00
56.90%

7454.00
56.90%

7752.00
56.90%

7454.00
56.90%

Page 104 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7752.00
56.90%

8050.00
56.91%

M-084
M-005
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-009
P&M-079

Page 105 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

6545.00
56.09%

6817.00
56.11%

7090.00
56.11%

6817.00
56.11%

Page 106 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7090.00
56.11%

7363.00
56.10%

M-084
M-004
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 107 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7235.00
56.72%

7537.00
56.71%

7838.00
56.72%

7537.00
56.71%

Page 108 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7838.00
56.72%

8140.00
56.71%

M-084
M-005
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-009
P&M-079

Page 109 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

6598.00
55.61%

6878.00
55.60%

7157.00
55.61%

6878.00
55.60%

Page 110 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7157.00
55.61%

7437.00
55.60%

7717.00
55.60%

8276.00
55.61%

Page 111 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

8835.00
55.61%

M-084
M-004
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

7274.00
56.24%

Page 112 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7582.00
56.24%

7891.00
56.23%

7582.00
56.24%

7891.00
56.23%

Page 113 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

8199.00
56.23%

8507.00
56.24%

9124.00
56.23%

9740.00
56.23%

M-084
M-005
M-053
M-051
M-209

Page 114 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
M-210

M-211

L-12
L-11
L-13

P&M-009
P&M-079

6816.00
55.68%

7100.00
55.68%

7384.00

Page 115 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
55.67%

7100.00
55.68%

7384.00
55.67%

7668.00
55.67%

M-084
M-004
M-053
M-051
M-209

M-210

Page 116 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

7361.00
56.04%

7673.00
56.04%

Page 117 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
7985.00
56.04%

7673.00
56.04%

7985.00
56.04%

8297.00
56.03%

8609.00
56.03%

Page 118 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

9233.00
56.04%

9857.00
56.03%

M-084
M-004
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 119 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

7602.00
55.06%

7929.00
55.08%

8257.00
55.07%

7929.00
55.08%

Page 120 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

8257.00
55.07%

8585.00
55.06%

8912.00
55.07%

9568.00
55.06%

Page 121 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

10223.00
55.06%

M-084
M-004
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

9150.00
54.44%

Page 122 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

9828.00
54.43%

10506.00
54.43%

M-084
M-004
M-053
M-051
M-209

M-210

M-211

L-12
L-11
L-13

P&M-002
P&M-080
P&M-017

P&M-049
#REF!
P&M-007

Page 123 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

9626.00
53.51%

10339.00
53.51%

11052.74
53.50%

Page 124 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-085

M-072

L-12
L-02
L-13

48991.00
63.44%

M-085_1

M-072

L-12
L-02
L-13

45087.00
64.79%

M-119

M-165

Page 125 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
M-187

M-084

L-12
L-02
L-13

L-12
L-08
L-13

L-12
L-11
L-13

P&M-040
M-111
P&M-079

122271.00
28.59%

Item 14.1(C)

Item 14.2

L-13

8841.00
64.68%

Page 126 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

L-12
L-13
L-15

P&M-031
P&M-001
P&M-030
P&M-005
P&M-053

M-077

M-021

M-188

M-051

M-142

M-077/1000

196.00
121.43%

Page 127 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Item No 5.2
(I)

Item No 5.11
(a) (I)

Item No 14.5
(A)

Page 128 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

Item 14.1(C)

Item 14.2

1391.00
66.21%

Page 129 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
Item 14.1(C)

Item 14.2

1356.00
66.15%

M-179
M-179
M-179
M-130*1000

L-12
L-15
L-13

2248.00
97.95%

Page 130 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

M-090/1000

M-056
M-110
M-101

L-12
L-02
L-13

L-12
L-11
L-13

6445.00
37.56%

Item 12.8 (A)


M15 PC
OBM
4372.00
37.26%

Page 131 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
Item 12.8
(G) M30 RC
OBB P

Item 14.2
(a)

8513.00
57.98%

Item 14.2
(b)

Item 14.2
(c)

M-084
M-004
M-053
M-051
M-180
M-085
M-119

M-122

Page 132 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

L-12
L-15
L-13

L-12
L-15
L-13

L-12
L-15
L-13

L-12
L-15
L-13

L-12
L-13

L-12
L-13

L-12
L-15
L-13

P&M-080
P&M-002
P&M-049
P&M-007
P&M-012
P&M-089
P&M-017

P&M-012
Lead =10 km
& P&M-090

Page 133 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

P&M-089

15214.00
64.20%

M-090

M-130

L-08
L-01
L-13
L-02

L-12
L-13

L-12
L-15
L-13

P&M-080

P&M-012
Lead =10 km
& P&M-090

P&M-089

Page 134 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

L-12
L-18
L-15

M-190

28.00
82.14%

L-12
L-13
L-15

M-060/1000

1194.00
25.38%

Page 135 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

L-12
L-13
L-15

M-089

949.00
352.90%

L-12
L-13
L-15

M-087

266.00
36.09%

L-12

Page 136 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
L-13
L-15

M-141

241.00
36.10%

L-12
L-13
L-15

M-005

M-077

10.00
130.00%

L-12
L-13
L-15

M-052

M-081/ 1000

Page 137 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
M-103

P&M-030
P&M-044

953.00
33.89%

L-12
L-13
L-15

M-096

12664.00
97.39%

L-12

Page 138 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
L-13
L-15

M-103

#REF!

12994.00
6.50%

L-12
L-13
L-15

M-178

Page 139 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

11103.00
150.03%

L-12
L-13
L-15

M-127

137296.00
9.64%

Page 140 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.

L-12
L-13
L-15

M-128

221120.00
3.18%

M-084
M-005

Page 141 of 959


Analysisof SOR (Roads) 2017-18
Chapter-14

Remarks/
Input ref.
159.00
113.84%

M-084

176.00
34.66%

Page 142 of 959


Analysisof SOR (Roads) 2017-18
Chapter-15

CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

15.1 Providing and laying boulders apron on river bed for


protection against scour with stone boulders
weighing not less than 40 kg each complete as per
drawing and Technical specification.
Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 898.00 898.00 M-003
Stone Spalls cum 0.20 987.00 197.40 M-008
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mason day 0.35 458.55 160.49 L-11
Mazdoor * day 0.75 244.56 183.42 L-13
c) Overhead charges @ 20 % on (a+b) 290.72
d) Contractor's profit @ 10% on (a+b+c) 174.43
Rate per cum = (a+b+c+d) 1918.72
say 1919.00
Including excavation for trimming for preparation of bed.
Nominal excavation required for preparation of bed has
been taken into account while making provision for labour.

15.2 Boulder Apron Laid in Wire Crates


Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 &
IS:4826 in 100mm x 100mm mesh (weaved diagonally)
including 10 per cent extra for laps and joints laid with
stone boulders weighing not less than
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x sqm 22.00 233.00 5126.00 M-102
100 mm.
Stone cum 5.63 898.00 5055.74 M-003
Stone Spalls cum 1.13 987.00 1115.31 M-008
b) Labour
Mate day 0.18 356.65 64.20 L-12
Mazdoor (Skilled) day 1.50 356.65 534.98 L-15
Mazdoor day *3.00 244.56 733.7 L-13
c) Overhead charges @ 20 % on (a+b) 2526.0
d) Contractor's profit @ 10% on (a+b+c) 1515.59
Cost for 5.63 cum = a+b+c+d 16671.47
Rate per cum = (a+b+c+d)/5.63 2961.18
say 2961.00
Including excavation for trimming for preparation of bed.
Readymade woven wire crate rolls have been considered
in the rate analysis. In case readymade rolls are not
available, GI wire 4mm dia. @ 32 kg per 10 sqm may be
provided. In that case 2 per cent of the cost of GI wire
may be added for weaving the wire c
15.3 Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)

Page 1 of 959
Analysisof SOR (Roads) 2017-18
Chapter-15

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Providing and laying of apron with cement concrete blocks


of size 0.5x0.5x0.5 m cast in-situ and made with nominal
mix of M-15 grade cement concrete with a minimum
cement content of 250 kg/cum as per IRC: 21-2000.

Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 6240.00 6240.00 Item 12.8
including OH & CP (A) M15 PC
OM P
Add 2 per cent of cost to account for excavation for 124.80
preparation of bed, nominal surface reinforcement
and filling of granular material in recesses between
blocks.
Rate per cum 6364.80
say 6365.00
15.4 Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry
in front of toe of embankment complete as per
drawing and Technical specifications
Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 898.00 898.00 M-003
Stone spalls of minimum 25 mm size cum 0.20 987.00 197.40 M-008
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mason day 0.35 458.55 160.49 L-11
Mazdoor day 0.75 244.56 183.42 L-13
c) Overhead charges @ 20 % on (a+b) 290.72
d) Contractor's profit @ 10% on (a+b+c) 174.43
Rate per cum = (a+b+c+d) 1918.72
say 1919.00
15.4 Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast
in cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 6240.00 6240.00 Item 12.8
(A) M15 PC
OM P
Add 2 per cent of cost to account for nominal surface 124.80
reinforcement and filling of granular material in
recesses between blocks.
Rate per cum 6364.80
say 6365.00
15.5 Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
Technical specification
Unit = cum
Taking output = 1 cum
a) Material

Page 2 of 959
Analysisof SOR (Roads) 2017-18
Chapter-15

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Graded stone aggregate of required size cum 1.20 1013.00 1215.60 M-012
b) Labour
Mate day 0.05 356.65 17.83 L-12
Mazdoor (Skilled) day 0.25 356.65 89.16 L-15
Mazdoor * day 1.00 244.56 244.56 L-13
c) Overhead charges @ 20 % on (a+b) 313.43
d) Contractor's profit @ 10% on (a+b+c) 188.06
Rate per cum = (a+b+c+d) 2068.64
say 2069.00
Includes Mazdoor required for trimming of slope to proper
profile and preparation of bed.
15.6 Geotextile Filter

Laying of a geotextile filter between pitching and


embankment slopes on which pitching is laid to prevent
escape of the embankment material through the voids of
the stone pitching/cement concrete blocks as well as to
allow free movement of water without c
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 356.65 7.13 L-12
Mazdoor day 0.30 244.56 73.37 L-13
Mazdoor (Skilled) day 0.10 356.65 35.67 L-15
b) Material
Permeable synthetic geotextile including 5 per cent sqm 11.00 370.00 4070.00
for overlap and wastage M-181
c) Overhead charges @ 20 % on (a+b) 837.23
d) Contractor's profit @ 10% on (a+b+c) 502.34
Cost for 10 sqm = a+b+c+d 5525.74
Rate per sqm = (a+b+c+d)/10 552.57
say 553.00
15.7 Toe protection
A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal mix
if cement concert block have been used for pitching .
Rates for toe wall can be ado
15.8 Providing and laying Flooring complete as per
drawing and Technical specifications laid over
cement concert bedding.
Rubble stone laid in cement mortar 1:3
Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item 12.6 sub- cum 0.33 4904.00 1618.32 Item 12.6
analysis) excluding OH & CP (A)

Page 3 of 959
Analysisof SOR (Roads) 2017-18
Chapter-15

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

b) cum 0.33 4546.00 1500.18


Add for cement concrete bedding (M15 Nominal mix) vide
Item 12.8 (A) excluding OH & CP . Quantity shall be
adopted as per design ( Assume Rubble stone Flooring Item 12.8
thickness 300mm and cement concrete bedding thickness (A) M15 PC
100mm) OBM P
Add 1 per cent of cost to account for excavation for 31.19
preparation of bed.
c) Material
Stone cum 1.00 898.00 898.00 M-003
Stone Spalls cum 0.20 987.00 197.40 M-008
d) Labour
Mate day 0.08 356.65 28.53 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor (for laying stones, filling of quarry spalls) day 1.50 244.56 366.84 L-13
e) Overhead charges @ 20 % on (a+c+d) 667.67
f) Contractor's profit @ 10% on (a+c+d+e) 400.60
Rate per cum = (a+b+c+d+e+f) 5938.01
say 5938.00
Includes cement mortar for laying and filling of joints.
15.8 Cement Concrete blocks Grade M15
Concrete Grade M15 block. (Rate as per item No. cum 1.00 7112.00 7112.00 Item 12.8
12.8 (A) including OH & CP. (A) M15 PC
OM P
Add for cement concrete bedding (M15 Nominal mix) cum 0.33 7112.00 2346.96
vide Item 12.8 (A) including OH & CP. Quantity shall
be adopted as per design ( Assume Cement Item 12.8
Concrete blocks thickness 300mm and cement (A) M15 PC
concrete bedding thickness 100mm) OM P
Add 1 per cent of cost to account for excavation for 94.59
preparation of bed.
Rate per cum 9553.55
say 9554.00
15.9 Dry Rubble Flooring
Construction of dry rubble flooring at cross drainage works
for relatively less important works.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 898.00 898.00 M-003
Stone Spalls cum 0.20 987.00 197.40 M-008
b) Labour
Mate day 0.10 356.65 35.67 L-12
Mason day 0.50 458.55 229.28 L-11
mazdoor day 1.50 244.56 366.84 L-13
Add 1 per cent of (b) for trimming and preparation of 6.32
base.
c) Overhead charges @ 20 % on (a+b) 346.70

Page 4 of 959
Analysisof SOR (Roads) 2017-18
Chapter-15

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

d) Contractor's profit @ 10% on (a+b+c) 208.02


Rate per cum = (a+b+c+d) 2288.22
say 2288.00
15.10 Curtain wall complete as per drawing and Technical
specification
Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 4428.00 4428.00 Item 12.7 (A
)
Rate same as per item No. 12.7 (A) including OH & CP

Rate per cum say 4428.00


or
15.10 Cement concrete Grade M15
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 6128.00 6128.00 Item 12.8
including OH & CP (A) M15 PC
OM P
Rate per cum say 6128.00
Other items like excavation for foundation, filling behind
wall, filter media, weep holes etc. shall be added
separately as per approved design.
15.11 Flexible Apron :Construction of flexible apron 1 m
thick comprising of loose stone boulders weighing
not less than 40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 898.00 898.00 M-003
Stone Spalls cum 0.20 987.00 197.40 M-008
b) Labour
Mate day 0.05 356.65 17.83 L-12
Mason day 0.25 458.55 114.64 L-11
Mazdoor day 1.00 244.56 244.56 L-13
Add 1 per cent of cost of (a+b) for trimming and 14.72
preparation of bed.
c) Overhead charges @ 20 % on (a+b) 297.43
d) Contractor's profit @ 10% on (a+b+c) 178.46
Rate per cum = (a+b+c+d) 1963.04
say 1963.00
15.12 Gabian Structure for Retaining Earth
Providing and construction of a gabian structure for
retaining earth with segments of wire crates of size 7 m x 3
m x 0.6 m each divided into 1.5 m compartments by cross
netting, made from 4 mm galvanised steel wire @ 32 kg
per 10 sqm having minimum tensi
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 356.65 99.86 L-12

Page 5 of 959
Analysisof SOR (Roads) 2017-18
Chapter-15

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

Mazdoor day 5.00 244.56 1222.80 L-13


Mazdoor (Skilled) day 2.00 356.65 713.30 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x sqm 61.00 233.00 14213.00
100 mm woven with 4mm dia. GI wire in rolls of
required size. M-102
Stone boulders with least dimension of 200 mm cum 12.60 898.00 11314.80 M-003
Stone spalls of minimum size 25 mm cum 2.52 987.00 2487.24 M-008
c) Overhead charges @ 20 % on (a+b) 6010.20
d) Contractor's profit @ 10% on (a+b+c) 3606.12
Cost for 12.60 cum (a+b+c+d) 39667.32
Rate per cum (a+b+c+d)/12.60 3148.20
say 3148.00
Readymade woven wire crate rolls have been considered
in the rate analysis. In case readymade rolls are not
available, GI wire 4mm dia. @ 32 kg per 10 sqm may be
provided. In that case 2 per cent of the cost of GI wire
may be added for weaving the wire c
15.13 Gabian Structure for Erosion Control, River Training
Works and Protection works
Providing and constructing gabian structures for erosion
control, river training works and protection works with wire
crates of size 2 m x 1 m x 0.3 m each divided into 1m
compartments by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.14 356.65 49.93 L-12
Mazdoor day 2.50 244.56 611.40 L-13
Mazdoor (Skilled) day 1.00 356.65 356.65 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x sqm 65.00 233.00 15145.00
100 mm woven with 4mm dia. GI wire in rolls of
required size to cover 6.00 cum. M-102
Stone boulders with least dimension of 200 mm cum 6.00 898.00 5388.00 M-003
Stone spalls of minimum size 25 mm cum 1.20 987.00 1184.40 M-008
c) Overhead charges @ 20 % on (a+b) 4547.08
d) Contractor's profit @ 10% on (a+b+c) 2728.25
Cost for 6.00 cum (a+b+c+d) 30010.70
Rate per cum (a+b+c+d)/6.00 5001.78
say 5002.00
Readymade woven wire crate rolls have been considered
in the rate analysis. In case readymade rolls are not
available, GI wire 4mm dia. @ 32 kg per 10 sqm may be
provided. In that case 2 per cent of the cost of GI wire
may be added for weaving the wire c

Page 6 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

CHAPTER-16
REPAIR AND REHABILITATION
Sr No Description Unit Quantity Rate Rs Cost Rs

16.1 Removal of existing cement concrete wearing coat


including its disposal complete as per Technical
Specification without causing any detrimental effect
to any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000
m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor day 1.00 244.56 244.56
b) Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hour 1.00 435.00 435.00
hammer along with accessories.
Tractor-trolley. hour 0.50 323.00 161.50
c) Overhead charges @ 20 % on (a+b) 172.49
d) Contractor's profit @ 10% on (a+b+c) 103.50
Cost for 10 sqm = (a+d+c+d) 1138.45
Rate per sqm = (a+b+c+d)/10 113.84
say 114.00
16.2 Removal of existing asphaltic wearing coat
comprising of 50 mm thick asphaltic concert laid
over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.03 356.65 10.70
Mazdoor day 0.75 244.56 183.42
b) Machinery
Air Compressor 250 cfm with pneumatic breaker. hour 0.75 435.00 326.25
Tractor-trolley. hour 0.40 323.00 129.20
c) Overhead charges @ 20 % on (a+b) 129.91
d) Contractor's profit @ 10% on (a+b+c) 77.95
Cost for 10 sqm = (a+d+c+d) 857.43
Rate per sqm = (a+b+c+d)/10 85.74
say 86.00
16.3 Guniting concrete surface with cement mortar
applied with compressor after cleaning surface and
spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 7.20 115.20
Graded sand cum 0.04 950.00 38.00
Wire mesh 50mm x 50mm size of 3mm wire kg 2.00 46.00 92.00
Epoxy kg 0.67 605.00 405.35
Accelerator compound for guniting @ 4 per cent of kg 0.64 104.00 66.56
weight of cement
Add 2 per cent of cost of material for miscellaneous 14.34
consumables like nozzles, wire brush, cotton waste etc.

Page 7 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Labour
Mate day 0.01 356.65 3.57
Mason day 0.04 458.55 18.34
Mazdoor day 0.14 244.56 34.24
c) Machinery
Compressor with guniting equipment along with hour 0.10 400.00 40.00
accessories
d) Overhead charges @ 20 % on (a+b+c) 165.52
e) Contractor's profit @ 10% on (a+b+c+d) 99.31
Rate per sqm = (a+b+c+d+e) 1092.43
say 1092.00
16.4 Providing and inserting nipples with approved fixing
compound after drilling holes for grouting as per
Technical Specifications including subsequent
cutting/removal and sealing of the hole as
necessary of nipples after completion of grouting
with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 25.00 25.00
Cement, fixing compound and consumables @ 15 per 3.75
cent of cost of nipple
b) Labour
Mate day 0.01 356.65 3.57
Mazdoor (Skilled) labour for drilling day 0.08 356.65 28.53
Mazdoor (Skilled) labour for fixing nipple and sealing day 0.08 356.65 28.53
inlets
Mazdoor for cutting and removing of nipples day 0.04 244.56 9.78
Add 10 per cent of labour cost for drilling holes etc 7.04
c) Machinery
C)Machine for grouting
a) Drill Bit Machine No. 1.00 9.38 9.38
Considering 1000 points& 25% depreciation
(25000/1000x1.5x25%)
b) Drill Bit No. 1.00 39.00 39.00
Considering 75 holes per drill bit (1950/75x1.5)
c) Grant Machine No. 1.00 8.25 8.25

Considering
c) 3000 charges
Overhead points per@m/c(16500/3000x1.5)
20 % on (a+b) 32.57
d) Contractor's profit @ 10% on (a+b+c) 19.54
Rate per No. = (a+b+c+d) 214.93
say 215.00
16.5 Sealing of cracks/porous concrete by injection
process through nipples/Grouting complete as per
Technical Specification.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 7.20 7.92

Page 8 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Admixtures (anti shrinkage compound) @ 20 per cent 1.58


of cost of cement
b) Labour
Mate day 0.08 356.65 28.53
Mazdoor (Skilled) day 0.10 356.65 35.67
Mazdoor day 0.10 244.56 24.46
c) Machinery
Grout pump with agitator and accessories hour 0.10 310.00 31.00
Formwork @ 20% of(a+b+c) 25.83
d) Overhead charges @ 20 % on (a+b+c) 25.83
e) Contractor's profit @ 10% on (a+b+c+d) 18.08
Rate per kg = (a+b+c+d+e) 198.90
say 199.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.55 7.20 3.96
Sand including 10 per cent wastage kg 0.55 0.63 0.35
Admixtures (anti shrinkage compound) @ 20 per cent 0.79
of cost of cement
b) Labour
Mate day 0.08 356.65 28.53
Mazdoor (Skilled) day 0.10 356.65 35.67
Mazdoor day 0.10 244.56 24.46
c) Machinery
Grout pump with agitator and accessories hour 0.10 310.00 31.00
Formwork @ 20% of(a+b+c) 24.95
d) Overhead charges @ 20 % on (a+b+c) 24.95
e) Contractor's profit @ 10% on (a+b+c+d) 17.47
Rate per kg = (a+b+c+d+e) 192.12
say 192.00
16.6 Patching of damaged concrete surface with polymer
concrete and curing compounds, initiator and
promoter, available in present formulations, to be
applied as per instructions of manufacturer and as
approved by the Engineer.

Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour
Mate day 0.06 356.65 21.40
Mazdoor (Skilled) day 0.75 356.65 267.49
Mazdoor day 0.75 244.56 183.42
b) Material

Page 9 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Pre-packed polymer concrete based on epoxy system kg 100.00 46.00 4600.00


complete with curing compound, intiator and promoter
including 5 per cent wastage.
c) Machinery
Grout pump with agitator and accessories hour 2.00 310.00 620.00
Formwork @ 20% of(a+b+c) 1138.46
d) Overhead charges @ 20 % on (a+b+c) 1138.46
e) Contractor's profit @ 10% on (a+b+c+d) 796.92
Cost for 10 sqm = a+b+c+d+e 8766.15
Rate per sqm = (a+b+c+d+e)/10 876.62
say 877.00
Note This item is a proprietory item available in market as pre-
packed polymer concrete and is required to be applied as
per instructions of the manufacturer.
16.7 Sealing of crack / porous concrete with Epoxy Grout
by injection through nipples complete as per clause
2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.10 605.00 665.50
b) Labour
Mate day 0.08 356.65 28.53
Mazdoor (Skilled) day 0.10 356.65 35.67
Mazdoor day 0.10 244.56 24.46
c) Machinery
Epoxy Injection gun hour 0.10 300.00 30.00
Formwork @ 20% of(a+b+c) 156.83
d) Overhead charges @ 20 % on (a+b+c) 156.83
e) Contractor's profit @ 10% on (a+b+c+d) 109.78
Rate per kg = (a+b+c+d+e) 1207.60
say 1208.00
16.8 Applying epoxy mortar over leached, honey combed
and spalled concrete surface and exposed steel
reinforcement complete as per Technical
Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.50 840.00 2100.00
Epoxy mortar kg 2.20 422.00 928.40
Epoxy resin -hardener mix for seal coat. kg 2.00 840.00 1680.00
Add 3 per cent cost of material for other consumables 141.25
like acetone etc and to cover wastage.
b) Labour
Mate day 0.04 356.65 14.27

Page 10 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Mazdoor (Skilled) day 0.50 356.65 178.33


Mazdoor day 0.50 244.56 122.28
Formwork @ 20% of(a+b) 1032.90
c) Overhead charges @ 20 % on (a+b) 1032.90
d) Contractor's profit @ 10% on (a+b+c) 723.03
Cost for 10 sqm = a+b+c+d 7953.37
Rate per sqm = (a+b+c+d)/10 795.34
say 795.00
16.9 Removal of defective concrete, cleaning the surface
thoroughly, applying the shotcrete mixture
mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates,
water and quick setting compound in the proportion
as per clause 2807.1., sand and coarse aggregates
conforming to IS: 383 and table 1 of IS: 9012
respectively, water cement ratio ranging from 0.35
to 0.50, density of gunite not less than 2000
kg/cum, strength not less than 25 Mpa and
workmanship conforming to clause 2807.6.

unit: sqm
Taking output = 10 sqm, 40 mm average thickness.

a) Material
Cement kg 120.00 7.20 864.00
Sand cum 0.15 950.00 142.50
Coarse aggregate of size 4.75mm cum 0.15 1041.50 156.23
Quick setting compound kg 2.50 32.00 80.00
Water KL 0.10 45.00 4.50
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.50 244.56 122.28
Mazdoor (Skilled) day 0.50 356.65 178.33
c) Machinery
Air compressor 250 cfm hour 1.00 435.00 435.00
Shotcreteing equipment hour 1.00 400.00 400.00
water tanker 6 KL capacity hour 0.02 440.00 8.80
Formwork @ 20% of(a+b) 312.42
d) Overhead charges @ 20 % on (a+b+c) 543.66
e) Contractor's profit @ 10% on (a+b+c+d) 326.20
Cost for 10 sqm = a+b+c+d+e 3588.18
Rate per sqm = (a+b+c+d+e)/10 358.82
say 359.00
16.10 Applying pre-packed cement based polymer mortar
of strength 45 Mpa at 28 days for replacement of
spalled concrete
Unit = sqm
Taking output = 10 sqm

Page 11 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 340.00 476.00
pre-packed cement based polymer mortar of strength 45 kg 12.00 46.00 552.00
Mpa at 28 days
Add 3 per cent of (a ) above for wastage. 30.84
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor (Skilled) day 0.50 356.65 178.33
Mazdoor day 0.50 244.56 122.28
Formwork @ 20% of(a+b) 274.74
c) Overhead charges @ 20 % on (a+b) 274.74
d) Contractor's profit @ 10% on (a+b+c) 192.32
Cost for 10 sqm = a+b+c+d 2115.51
Rate per sqm = (a+b+c+d)/10 211.55
say 212.00
16.11 Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes Kg 2.00 605.00 1210.00
and satisfying testing as per clause 2803.9
Add 3 per cent of (a ) above for wastage. 36.30
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor (Skilled) day 0.50 356.65 178.33
Mazdoor day 0.50 244.56 122.28
c) Overhead charges @ 20 % on (a+b) 312.23
d) Contractor's profit @ 10% on (a+b+c) 187.34
Cost for 10 sqm = a+b+c+d 2060.75
Rate per sqm = (a+b+c+d)/10 206.07
say 206.00
16.12 Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification

Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-
9.42 kg/m of cable.
a) Material

Page 12 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

HTS strand including 5 per cent wastage and extra tonne 1.05 114109.00 119814.45
length for jacking
HDPE pipes 75mm dia including 5 per cent wastage metre 112.00 111.00 12432.00
Cement for grouting kg 400.00 7.20 2880.00
Tube anchorage set complete with bearing plate, each 8.00 1500.00 12000.00
permanent wedges etc
Epoxy kg 6.00 605.00 3630.00
MS plates for deviator (where deviator blocks are not tonne 2.10 60000.00 126000.00
provided)
Add 20 per cent cost of material for other materials like 55351.29
lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.24 356.65 85.60
Mazdoor Semi-skilled) day 3.00 285.32 855.96
Mazdoor day 3.00 244.56 733.68
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 0.44 356.65 156.93
Blacksmith day 3.00 458.55 1375.65
Mazdoor day 8.00 244.56 1956.48
iii) For prestressing
Mate/Supervisor day 0.13 356.65 46.36
Fitter day 0.70 458.55 320.99
Mazdoor day 2.65 244.56 648.08
iv) For grouting
Mate/Supervisor day 0.13 356.65 46.36
Mason day 0.70 458.55 320.99
Mazdoor day 2.65 244.56 648.08
c) Machinery
Stressing jack with pump hour 4.00 113.00 452.00
Grouting pump with agitator hour 1.35 310.00 418.50
d) Overhead charges @ 20 % on (a+b+c) 68034.68
e) Contractor's profit @ 10% on (a+b+c+d) 40820.81
Rate per MT = (a+b+c+d+e) 449028.89
say 449029.00
16.13 Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification

Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT

Page 13 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Assume 12.7mm dia. Strand in 19T13 system. Weight-


14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 3.10 114109.00 353737.90
length for jacking
HDPE pipes 90mm dia including 5 per cent wastage metre 224.00 160.00 35840.00
Cement for grouting tonne 1.01 7200.00 7272.00
Tube anchorage set complete with bearing plate, each 8.00 1500.00 12000.00
permanent wedges etc
Epoxy kg 10.00 605.00 6050.00
MS plates for deviator (where deviator blocks are not tonne 7.00 60000.00 420000.00
provided)
Add 20 per cent cost of material for other materials like 166979.98
lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.08 356.65 28.53
Mazdoor Semi-skilled) day 8.00 285.32 2282.56
Mazdoor day 8.00 244.56 1956.48
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 1.28 356.65 456.51
Blacksmith day 7.00 458.55 3209.85
Mazdoor day 25.00 244.56 6114.00
iii) For prestressing
Mate/Supervisor day 0.20 356.65 71.33
Fitter day 1.00 458.55 458.55
Mazdoor day 4.00 244.56 978.24
iv) For grouting
Mate/Supervisor day 0.26 356.65 92.73
Mason day 1.50 458.55 687.83
Mazdoor day 5.00 244.56 1222.80
c) Machinery
Stressing jack with pump hour 7.00 113.00 791.00
Grouting pump with agitator hour 3.00 310.00 930.00
d) Overhead charges @ 20 % on (a+b+c) 204232.06
e) Contractor's profit @ 10% on (a+b+c+d) 122539.23
Cost for 3.10 MT = a+b+c+d+e 1347931.58
Rate per MT = (a+b+c+d+e)/3.10 434816.64
say 434817.00
16.14 Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification

Span assumed: 100 m


No. of cables: 6 no.

Page 14 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

No. of anchorages : 12 no.


Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-
14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra tonne 9.28 114109.00 1058931.52
length for jacking
HDPE pipes 90 mm dia including 5 per cent wastage metre 672.00 160.00 107520.00
Cement for grouting tonne 3.04 7200.00 21888.00
Tube anchorage set complete with bearing plate, each 12.00 1500.00 18000.00
permanent wedges etc
Epoxy kg 14.00 605.00 8470.00
MS plates for deviator (where deviator blocks are not tonne 20.00 60000.00 1200000.00
provided)
Add 20 per cent cost of material for other materials like 482961.90
lead sheet, sleeves, deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 1.72 356.65 613.44
Mazdoor Semi-skilled) day 18.00 285.32 5135.76
Mazdoor day 25.00 244.56 6114.00
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 4.00 356.65 1426.60
Blacksmith day 20.00 458.55 9171.00
Mazdoor day 80.00 244.56 19564.80
iii) For prestressing
Mate/Supervisor day 0.30 356.65 107.00
Fitter day 1.50 458.55 687.83
Mazdoor day 6.00 244.56 1467.36
iv) For grouting
Mate/Supervisor day 1.00 356.65 356.65
Mason day 5.00 458.55 2292.75
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Stressing jack with pump hour 10.00 113.00 1130.00
Grouting pump with agitator hour 10.00 310.00 3100.00
d) Overhead charges @ 20 % on (a+b+c) 590765.96
e) Contractor's profit @ 10% on (a+b+c+d) 354459.58
Cost for 9.28 MT = a+b+c+d+e 3899055.34
Rate per MT = (a+b+c+d+e)/9.28 397862.79
say 397863.00
16.15 Labour for replacement of Bearings complete as
per Technical Specification (Cost of bearing to be
paid extra)
Unit = No

Page 15 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Taking output = 3 No.


Lifting of superstructure span by jacking up from below
i.e. by placing the jacks on pier/abutment caps for span
length of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. Day 3.00 200.00 600.00
Mate day 0.64 356.65 228.26
Mazdoor (Skilled) day 4.00 356.65 1426.60
Mazdoor day 12.00 244.56 2934.72
v) Wooden packing cum 0.15 25500.00 3825.00
c) Overhead charges @ 20 % on (a+b) 1802.92
d) Contractor's profit @ 10% on (a+b+c) 1081.75
Cost of repair of 3 bearings = a+b+c+d 11899.24
Rate of repair per bearing = (a+b+c+d)/3 3966.41
say 3966.00
The work entails replacement of all the bearings on one
side of the span.
16.16 Labour for Lifting of superstructure span by jacking
up from below i.e. by placing the jacks on
pier/abutment caps for span length of 30m. (Cost of
bearing to be paid extra) (Rectification of Bearings
as per Technical Specifications)
A Lifting from the pier cap
Unit = 1 No
Taking output = 1 No.
lfting operation period= 4 days
i) Hire charges for jack of 150 tonne lifting capacity for 4 each 4.00 1500.00 24000.00
days
ii) Jack Operator day 1.00 458.55 1834.20
iii) Mate day 1.00 356.65 1426.60
iv) Mazdoor (Skilled) day 4.00 356.65 5706.40
v) Mazdoor day 12.00 244.56 11738.88
vi) Wooden packing cum 0.15 25500.00 3825.00
c) Overhead charges @ 20 % on (a+b) 9706.22
d) Contractor's profit @ 10% on (a+b+c) 5823.73
Cost of repair of 3 bearings = a+b+c+d 64061.03
Rate of repair per bearing = (a+b+c+d)/3 64061.03
say 64061.00
Note The rectification of 3 bearings included in this analysis
are on the same side of the span.
B Lifting with constructing auxilary structure upto 6M Say 400000.00
height including dismentling and removal of same

16.17 Replacement of Expansion Joints complete as per


drawings
Unit -1 RM
Taking output = 12 RM
a) Material

Page 16 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Epoxy for bonding new concrete to old concrete @ 0.8 kg 9.60 605.00 5808.00
kg/sqm
M-30 grade cement concrete excluding OH & CP (Rate cum 3.60 7745.00 27882.00
as per items 14.1 C (i)
b) Labour
Removal of old expansion joint including breaking of
concrete, cutting of lugs and shifting of broken material
etc.
Mate day 0.26 356.65 92.73
Mazdoor day 6.00 244.56 1467.36
Mazdoor (Skilled) day 0.50 356.65 178.33
c) Overhead charges @ 20 % on (a+b) 7085.68
d) Contractor's profit @ 10% on (a+b+c) 4251.41
Cost for replacement of 12 RM = a+b+c+d 46765.51
Rate per RM = (a+b+c+d)/12 3897.13
say 3897.00
Note The rate for the installation of new expansion joints may
be taken from the chapter on superstructure. Broken
concrete will have to be replaced which has been
included in this analysis.
16.18 Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.20 356.65 71.33
Mazdoor day 5.00 244.56 1222.80
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 323.00 323.00
c) Overhead charges @ 20 % on (a+b) 323.43
d) Contractor's profit @ 10% on (a+b+c) 194.06
Cost for 10 m = a+b+c+d 2134.61
Rate per metre = (a+b+c+d)/10 213.46
say 213.00
Note The rate for the provision of new railing may be adopted
from the chapter on superstructure.
16.19 Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.40 356.65 142.66
Mazdoor day 10.00 244.56 2445.60
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 323.00 323.00
c) Overhead charges @ 20 % on (a+b) 582.25

Page 17 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Contractor's profit @ 10% on (a+b+c) 349.35


Cost for 10 m = a+b+c+d 3842.86
Rate per metre = (a+b+c+d)/10 384.29
say 384.00
Note The rate for the construction of new crash barrier may be
adopted from chapter 8 on Traffic and Transportation.

16.20 Replacement of Damaged Mild Steel Railing


Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.16 356.65 57.06
Mazdoor day 4.00 244.56 978.24
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 323.00 323.00
c) Overhead charges @ 20 % on (a+b) 271.66
d) Contractor's profit @ 10% on (a+b+c) 163.00
Cost for 10 m = a+b+c+d 1792.96
Rate per metre = (a+b+c+d)/10 179.30
say 179.00
16.21 Repair of Crash Barrier
Repair of concrete crash barrier with cement concert of
M-30 grade by cutting and trimming the damaged portion
to a regular shape, cleaning the area to be repaired
thoroughly, applying cement concert after erection of
proper form work.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent
of the volume of concrete .This will require 0.30 cum of
concrete.
a) Manpower*
Mate day 0.04 356.65 14.27
Mazdoor day 1.00 244.56 244.56
* For dismantling and trimming the surface to a regular
shape and removal of damaged material.
b) Material
M-30 grade cement concrete excluding OH & CP (Rate cum 0.30 7745.00 2323.50
as per items 14.1 C (i)
This may be priced based on the rate given the chapter
of superstructure.
c) Overhead charges @ 20 % on (a) 51.77
d) Contractor's profit @ 10% on (a+c) 31.06
Cost for 10 m = a+b+c+d 2665.15
Rate per m = (a+b+c+d)/10 266.52
say 267.00

Page 18 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

16.22 Repair of RCC Railing


Carrying out repair of RCC M30 railing to bring it to the
original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent
.
a) Material
M-30 grade cement concrete excluding OH & CP (Rate cum 0.20 7745.00 1549.00
as per items 14.1 C (i)
TMT bar reinforcement Rate as per item No tonne 0.01 56320.00 732.16
14.2(Excluding OH & CP)
b) Labour*
Mate day 0.016 356.65 5.71
mazdoor day 0.20 244.56 48.91
* For dismantling and trimming the surface to a regular
shape and removal of damaged material.
c) Overhead charges @ 20 % on (b) 10.92
d) Contractor's profit @ 10% on (b+c) 6.55
Cost for 10 m = a+b+c+d 2353.26
Rate per m = (a+b+c+d)/10 235.33
say 235.00
16.23 Repair of Steel Railing
Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the
extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series kg 32.00 60.00 1920.00
Flat iron kg 10.00 60.00 600.00
MS Bolt and nuts kg 1.00 90.00 90.00
Add 5 per cent of cost of material for painting. 130.50
b) Labour
Mate day 0.016 356.65 5.71
Mazdoor (Skilled) day 0.20 356.65 71.33
Mazdoor day 0.20 244.56 48.91
c) Overhead charges @ 20 % on (a+b) 573.29
d) Contractor's profit @ 10% on (a+b+c) 343.97
Cost of repair for10m = a+b+c+d 3783.71
Cost of meter = (a+b+c+d)/10 378.37
say 378.00

Page 19 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

16.24 Chipping of deteriorated concrete and removal of all


loose & friable materials and fully exposing rusted
reinforcement followed by proper cleaning and removing
of rusts and other foreign materials using sand blasting/
emery cloths/ wire brush etc. including formwork as
directed and specified by the department complete

Unit =Sqm
Taking output = 1sqm
A) Labour
Skilled labour day 0.3 356.65 107.00
Ordinary labour day 0.3 244.56 73.37
C)Overhead charges@ 20% on (A+B) 36.07
D)Contractor's Profit @ 10% on (A+B+C) 21.64
Cost of 1 Sqm (A+B+C+D) 238.08
Rate per Cum say 238.00
16.25 Replacement of corroded reinforcement by cutting
and welding new reinforcement of minimum 25mm dia.
including lapping on both sides to the specified length as
directed and as per relevant IS/IRC codes and cost of
gas ,welding rods,higher charge of welding machines etc.
including formwork as required.(Reinforcement to be
measured and paid seperately)

Unit = Running metre


Taking output = 1RM
(A)Machinery
Welding Charge @ 3.853Kg/m Kg 3.853 15 57.80
B) labour
Welder day 0.25 458.55 114.64
Skilled labour day 0.2 356.65 71.33
C) Formwork & staging @ 20% on (A+B) 48.75
D)Overhead charges@ 20% on (A+B+C) 58.50
E)Contractor's Profit @ 10% on (A+B+C+D) 35.10
Cost of 1 metre (A+B+C+D) 386.12
Rate per RM say 386.00
16.26 Anticorrosive treatment
(A) Supplying and applying two coats of Zinc rich anti-
corrosive protective coating with'Techguard 102' of
Choksey Chemicals or euivalent @ 0.50 Lit per Sqm over
thoroughly cleaned and prepared steel bars including
formwork as directed and specified by the department
complete.
Unit =Sqm
Taking output = 1sqm
A)Material
Techguard 102 ( Two coats) @ 0.50lit/sqm Lit 0.5 362.00 181.00
B) labour
Technician day 0.2 458.55 91.71
C) Formwork & staging @ 20% on (A+B) 54.54
D)Overhead charges@ 20% on (A+B+C) 65.4504
E)Contractor's Profit @ 10% on (A+B+C+D) 39.27
Cost of 1 metre (A+B+C+D) 431.97
Rate per Sqm say 432.00

Page 20 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

(B) Spplying and applying one coat of Zinc based epoxy


anticorrosive coating like CONCRESIVE ZRI of
Degussa brand or euivalent @ 0.09 Lit per Sqm all over
the exposed reinforcement over thoroughly cleaned and
prepared steel bars including formwork as directed and
specified by the department complete.
Unit =Sqm
Taking output = 1sqm
A)Material
CONCRESIVE ZRI Lit 0.09 964.80 86.83
B) labour
Technician day 0.2 458.55 91.71
C) Formwork & staging @ 20% on (A+B) 35.71
D)Overhead charges@ 20% on (A+B) 42.85
E)Contractor's Profit @ 10% on (A+B+C) 25.71
Cost of 1 metre (A+B+C+D) 282.81
Rate per Sqm say 283.00
16.28 Bonding between old and new concret surfaces
(A) Supplying and applying Epoxy based bonding agent
Masterbond EP of Choksey Chemicals or euivalent
@ 0.50 Lit pe sqm after totally saturating the cleaned
concrete surface with clean water for proper bonding of
old and new concrete including formwork as specified
and directed by the department complete.
Unit =Sqm
Taking output = 1sqm
A)Material
Masterbond EP ( Two coats) @ 0.50lit/sqm Lit 0.5 672.00 336.00
B) Labour
Mason day 0.2 458.55 91.71
Skilled labour day 0.2 356.65 71.33
C) Formwork & staging @ 20% on (A+B) 99.81
D)Overhead charges@ 20% on (A+B+C) 119.77
E)Contractor's Profit @ 10% on (A+B+C+D) 71.86
Cost of 1 Sqm (A+B+C+D) 790.48
Rate per Sqm say 790.00
(B) Providing and applying coating of the cleaned patches
with two part of polymer based bonding agent Nitobond
SBR of Fosroc or equivalent @ 0.22 Lit per Sqm prior to
application of polymer modified mortar with brush after
totally saturating the cleaned concrete surface with clean
water for proper bonding of old and new concrete
including formwork as specified and directed by the
department complete.

Unit =Sqm
Taking output = 1sqm
A)Material
Nitobond SBR ( Two coats) Lit 0.22 538.00 119.56
B) labour
Mason day 0.2 458.55 91.71
Skilled labour day 0.2 356.65 71.33

C) Add 20% for formwork on (A+B) 56.52


D)Overhead charges@ 20% on (A+B+C) 67.82
E)Contractor's Profit @ 10% on (A+B+C+D) 40.69

Page 21 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Cost of 1 Sqm (A+B+C+D) 447.63


Rate per Sqm say 448.00
16.29 Plastering the surface with high rich polymer modified
mortar 10mm thick with cement sand mortar in prop. 1:4
mixed with 100% acrylic polymer Mastercrete M-81 of
Chosey chemicals or equivalent @15% by weight of
cement followed by proper curing as specified and
directed by the department complete including formwork.

Unit =Sqm
Cost Analysis for : 1Sqm
A)Material
Cement @7.60bags/cum (1sqmx0.01m=0.01cum) Kg 4.00 7.20 28.80
Fine sand @0.035cum/bag (0.035x0.01=0.003cum) Cum 0.012 850.00 10.20
Mastercrete M-81@ 7.5lits/ 50Kg of cement Lit 0.60 270.00 162.00
B) labour
Mason day 0.25 458.55 114.64
Skilled labour day 0.25 356.65 89.16
C) Formwork @20% on (A+B) 80.96
D)Overhead charges@ 20% on (A+B+C) 97.15
E)Contractor's Profit @ 10% on (A+B+C+D) 58.29
Cost of 1 Sqm (A+B+C+D) 641.20
Rate per Sqm say 641.00
16.30 Concreting of the structure with nonshrink
cementitious microconcrete with properly graded 5mm
to 12mm slit free aggregate with Mastergrout CNS250 of
Choksey Chemicals or equivalent, (mixing ratio CNS250
- 1part : graded 12mm down aggregate-0.6part and
water/powder ratio-0.16) with water @ 0.16 w/p ratio and
poured at a super fluid consistency only from one side to
avoid air entrapment continuously without vibration
followed by proper curing for minimum 7 days. as
specified and directed by the department complete
including formwork.

Unit =cum
Cost Analysis for : 1Cum
A)Material
Mastergrout CNS250 @ 2300kg/cum Kg 2300 15.37 35351.00
12mm down aggregates Cum 0.6 1510.00 906.00
B) labour
Mason day 3 458.55 1375.65
Skilled labour day 10 244.56 2445.60
C) Formwork @20% on (A+B) 8015.65
D)Overhead charges@ 20% on (A+B+C) 9618.78
E)Contractor's Profit @ 10% on (A+B+C+D) 5771.27
Cost of 1 cum (A+B+C+D) 63483.95
Rate per cum say 63484.00
16.31 Concreting of the structure with free flow nonshrink
cementitious microconcrete with Rendorec RG of
Fosroc or equivalent after proper mixing with cleanwater
including formwork followed by proper curing for 28 days
as per manufacturer's specifications complete and as
directed by the Department .
Unit =cum
Cost Analysis for : 1Cum

Page 22 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

A)Material
Rendorec RG @ 2150kg/cum Kg 2150 19.50 41925.00
B) labour
Cost of Application Cum 1 6500 6000.00
C) Formwork @20% on (A+B) 9585.00
D)Overhead charges@ 20% on (A+B+C) 11502.00
E)Contractor's Profit @ 10% on (A+B+C+D) 6901.20
Cost of 1 cum (A+B+C+D) 75913.20
Rate per cum say 75913.00
16.32 Providing and laying Zinc anode unit Galvashield XP
of Fosroc make or equivalent, fixed to the reinforcement
steel by means of wire ties to allow attachment in
horizontal, vertical and overhead locations with a spacing
of one piece per 0.5m c/c and ensuring good electrical
continuity as per specification of manufacturer including
cost of labour,copnsumables, tools and tackles and
formwork.

Unit =Each
Cost Analysis for : 1 No
A) Material
Galvashield XP No 1 1030.12 1030.12
B) Labour
Technician day 0.2 458.55 91.71
Skillled labour day 0.2 356.65 71.33
C) Formwork @20% on (A+B) 238.63
D)Overhead charges@ 20% on (A+B+C) 286.36
E)Contractor's Profit @ 10% on (A+B+C+D) 343.63
Cost of 1 cum (A+B+C+D) 206.18
Rate per no say 2267.96
2268.00
16.33 Structural Strengthening with carbon Fibre:
(A) Patching in depression of concrete surface wherever
necessary by laying epoxy putty , Nitocote VF of
Fosroc Chemicals or equivalent @ 1 Lit per sqm after
proper surface preparation and proper scraping of
concrete protrusion as specified and directed by the
department complete including formwork .
Unit =cum
Cost Analysis for : 1Sqm
A)Material
Nitocote VF Lit 1.00 1067.27 1067.27
B) labour
Technician day 0.35 458.55 160.49
Skilled labour day 0.35 356.65 124.83
C) Formwork @20% on (A+B) 270.52
D)Overhead charges@ 20% on (A+B+C) 324.62
E)Contractor's Profit @ 10% on (A+B+C+D) 194.77
Cost of 1 sqm (A+B+C+D) 2142.50
Rate per Sqm say 2143.00

Page 23 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

(B) Applying Nitowrap 410 saturant Fosroc Chemicals or


equivalent with wet film thickness @ 250 microns (0.27Lit
per sqm) over a coat of saturant epoxy primer Nitowrap
30 of Fosroc Chemicals or equivalent @ 0.11Lit per
sqm with brush followed by fixing carbon fibre composite
system Nitowrap EP (CF) of Fosroc Chemicals or
equivalent by pressing on the saturant and impregnate
the same by applying a final coat of Nitowrap 410
saturant Fosroc Chemicals or equivalent as specified
and directed by the department complete including
formwork.

Unit =Sum
Cost Analysis for : 1Sqm
A)Material
Nitowrap 30 Lit 0.11 1035.00 115.00
Nitowrap 410 Lit 0.27 637.50 170.00
Nitowrap EP (CF) Sqm 1.00 2500.00 2500.00
B) labour
Technician day 0.9 458.55 412.70
Skilled labour day 0.9 356.65 320.99
C) Formwork @20% on (A+B) 703.74
D)Overhead charges@ 20% on (A+B+C) 844.48
E)Contractor's Profit @ 10% on (A+B+C+D) 506.69
Cost of 1 sqm (A+B+C+D) 5573.59
Rate per Sqm say 5574.00

(C) Applying two coats of UV resistant coating Nitowrap 512


of Fosroc Chemicals or equivalent over fibre system
having wet film thickness of 100 micron @ 0.11Lit per
sqm as specified and directed by the department
complete including formwork.
Unit =Sum
Cost Analysis for : 1Sqm
A)Material
Nitowrap 512 Lit 0.11 1800.00 200.00
B)Labour
Technician day 0.35 458.55 160.49
C) Formwork @20% on (A+B) 72.10
D)Overhead charges@ 20% on (A+B+C) 86.52
E)Contractor's Profit @ 10% on (A+B+C+D) 51.91
Cost of 1 sqm (A+B+C+D) 571.02
Rate per Sqm say 571.00

Page 24 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

16.34 Providing & fixing 16mm dia MS nozzles in a grid of


1m c/c up to the half of the thickness of the concrete
structure.A grout slurry of neat cement & chloride free
expanding grout Mastergrout CPG-1 of Choksey
Chemicals or equivalent @ 0.5% by weight of cement
water cement ratio 0.35 to 0.40 and viscosity not more
than 1.02 centipoise with grouting pressure till the refusal
of injection grout Mastergrout CPG-1. The grouting
operation pressure shall be 2Kg/sq.cm.Cutting the
exposed nozzle after the grouting with a good cutter to
make the surface free from the grouting pipes and to
seal the gap with plugging compound Masterplug of
Choksey Chemicals as per the specification and the
direction of the department complete including formwork.

Cost Analysis for : Each


No. of points per Sqm=1
A)Material
Cost of nozzle(MS) No. 1.00 25.00 25.00
Cost of Masterplug for fixing of nozzle No. 1.00 9.00 9.00
Cost of cement (considering 25kg of cement/hole) Kg 25.00 7.20 180.00
Mastergrout CPG-1 (considering 50gms by weight Kg 1.25 52.00 65.00
of cement of 25kg/hole) of cement/hole)
C)Labour
Technician for drilling & fixing of nozzle No. 0.05 356.65 17.83
Mate for drilling & fixing of nozzle No. 0.10 356.65 35.67
Technician for grouting No. 0.10 356.65 35.67
Mate for grouting No. 0.20 356.65 71.33
B)Machine
a) Depreciation cost of 25mm Drill Bit (Considering No. 1.00 78.00 78.00
25 holes/Drill Bit and cost of Drill Bit
b) Depreciation cost of 25mm Drill Bit Machine No. 1.00 20.00 20.00
(Considering 40% depression & 500 points in a
year and Machine value
c) Depreciation cost of Grant Machine (Considering No. 1.00 11.00 11.00
1500 points/Machine cost of dia form and cost of
Machine
D) Formwork @20% on (A+B+C) 87.90
E)Overhead charges@ 20% on (A+B+C+D) 127.28
F)Contractor's Profit @ 10% on (A+B+C+D+E) 76.37
Cost of each no (A+B+C+D) 840.04
Rate for each say 840.00
16.35 Providing & fixing PVC pipes in a grid of 0.5m c/c
throughout the crack of the concrete structure.A low
viscous Epoxy grout with Mastergrout EP 150 of
Choksey Chemicals or equivalent should be inserted
throughout the crack to fill the crack.Cutting the exposed
nozzle after the grouting with a good cutter to make the
surface free from the grouting pipes and to seal the gap
with the appeared crack with Epoxy putty of Choksey
Chemicals as per the specification and the direction of
the department complete including formwork.

Cost Analysis for : 1Rm


No. of points per Rm=2

Page 25 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

A)Material
Cost of nozzle(MS) No. 1.00 10.00 10.00
Cost of Masterplug for fixing of nozzle No. 1.00 9.00 9.00
Cost of Epoxy putty (considering 100gms/hole ) Kg 0.10 200.00 20.00
Mastergrout EP 150 (considering 500ml per hole ) Lit 0.50 598.00 299.00

C)Labour
Technician for drilling & fixing of nozzle No. 0.05 356.65 17.83
Mate for drilling & fixing of nozzle No. 0.10 356.65 35.67
Technician for grouting No. 0.10 356.65 35.67
Mate for grouting No. 0.20 356.65 71.33
B)Machine
a) Depreciation cost of 10mm Drill Bit (Considering No. 1.00 70.00 70.00
20 holes/Drill Bit and cost of Drill Bit=Rs.1400
(1400/20)
b) Depreciation cost of 105mm Drill Bit Machine No. 1.00 8.00 8.00
(Considering 40% depression & 500 points in a
year and Machine value=Rs.10000
(10000/500x40%)
c) Depreciation cost of Grant Machine No. 1.00 11.00 11.00
D) Formwork @20% on (A+B+C) 99.70
E)Overhead charges@ 20% on (A+B+C+D) 137.44
F)Contractor's Profit @ 10% on (A+B+C+D+E) 82.46
Rate per Rm 907.09
Rate per RM say 907.00
16.36 Extra for fibre reinforcing concrete/mortars by
providing and mixing Recron3S (CT 2024 12mm fibre
cut length / CT 2012 6mm fibre cut length) of Reliance
Industries Ltd. @ 125gms per bag (50Kg) of cement as
specified and directed by the Department complete at all
levels.
(A) In concrete
Unit=cum
Cost Analysis for : 1cum
(I) In M-20 grade.
A)Material
Recron3S of Reliance Industries Ltd. @ 125gms gms 868.75 0.27 233.52
per bag of cement
Wastage @ 5% 43.44 0.27 11.68
B)Overhead charges@ 20% on (A) 49.04
C)Contractor's Profit @ 10% on (A+B) 29.42
Cost per cum 323.66
Rate per Cum say 324.00
(II) In M-25 grade.
A)Material
Recron3S of Reliance Industries Ltd. @ 125gms gms 1008.75 0.27 271.15
per bag of cement
Wastage @ 5% 50.44 0.27 13.56
B)Overhead charges@ 20% on (A) 56.94
C)Contractor's Profit @ 10% on (A+B) 34.17
Cost per cum 375.82
Rate per Cum say 376.00
(III) In M-30 grade.
A)Material

Page 26 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

Recron3S of Reliance Industries Ltd. @ 125gms gms 1016.25 0.27 273.17


per bag of cement
Wastage @ 5% 50.81 0.27 13.66
B)Overhead charges@ 20% on (A) 57.37
C)Contractor's Profit @ 10% on (A+B) 34.42
Cost per cum 378.61
Rate per Cum say 379.00
(IV) In M-35 grade.
A)Material
Recron3S of Reliance Industries Ltd. @ 125gms gms 1055.00 0.27 283.58
per bag of cement
Wastage @ 5% 52.75 0.27 14.18
B)Overhead charges@ 20% on (A) 59.55
C)Contractor's Profit @ 10% on (A+B) 35.73
Cost per cum 393.05
Rate per Cum say 393.00
(B) In cement morter Plastering
Unit=Sqm
Cost Analysis for : 1 sqm
(I) 1:3 (1 cement: 3 coarse sand)
Considering 10 mm thick plaster
A)Material
Recron3S of Reliance Industries Ltd. @ 125gms gms 12.75 0.27 3.43
per bag of cement
Wastage @ 5% 0.64 0.27 0.17
B)Overhead charges@ 20% on (A) 0.72
C)Contractor's Profit @ 10% on (A+B) 0.43
Cost per sqm 4.75
Rate per sqm say 5.00
(II) 1:4 (1 cement: 4 coarse sand)
Considering 10 mm thick plaster
A)Material
Recron3S of Reliance Industries Ltd. @ 125gms gms 10.13 0.27 2.72
per bag of cement
Wastage @ 5% 0.51 0.27 0.14
B)Overhead charges@ 20% on (A) 0.57
C)Contractor's Profit @ 10% on (A+B) 0.34
Cost per sqm 3.77
Rate per sqm say 4.00
16.37 Applying 2-coats of anti-carbonation - a protective
coating Techguard 103 of Choksey Chemicals or
equivalent @ 0.275 Lit per sqm with brush over exposed
portion of the concrete structure of the bridge & other
structure works etc. complete as desired to protect the
reinforced concrete by preventing the process of
carbonation and directed by the department including
formwork.

Unit=Sqm
Cost Analysis for : 1Sqm
Taking output = 1 sqm
A)Material
Techguard 103 @ 0.275ltr/sqm Lit 0.275 480.76 132.21
B)Labour
Technician day 0.20 356.65 71.33
C) Formwork @20% on (A+B) 40.71

Page 27 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

D)Overhead charges@ 20% on (A+B) 48.85


E)Contractor's Profit @ 10% on (A+B+C+D) 29.31
Cost per sqm 322.41
Rate per Sqm say 322.00
16.38 Under water repairing
A Applying and placing Antiwash, non-shrink,
cementatious, high strength Renderoc UW of
Fosroc Chemicals or equivalent by mixing with clean
water to repair the damaged and deteriorated
underwater structural elements including formwork as
per the department's instructions with labour, tools
complete as specified and directed by the department
including formwork.

Unit=cum
Cost Analysis for : 1cum
Taking output = 1 Cum
A) Material
Renderoc UW @ 2100kg/cum kg 2100.000 32.00 67200.00
B) Cost of application cum 15000.00
C)Overhead charges@ 20% on (A+B) 16440.00
D)Contractor's Profit @ 10% on (A+B+C) 9864.00
Cost per cum 108504.00
Rate per Cum say 108504.00
16.39 Drilling 14 mm dia holes on the concrete surface to a
depth of 75mm using a rotary cum hammering,drilling
machine as per specification and throughly cleaning the
hole using compressed air & water jet and fixing of shear
connectors of 8mm dia and anchoring it with polyester
resin anchor grout Lokfix P of Fosroc india and as per
manufacture's specifications.(Cost inclusive of
drilling,cleaning,fixing, steel,labour,tools and tackles)

Unit= Each
Cost Analysis for : 1Hole
Taking output = 1 hole
A) Material
Lokfix P @10ml/hole Lit 0.01 1680.00 16.80
B)Cost of application 50.00
C)Overhead charges @ 20% on (A+B) 13.36
D)Contractor's Profit @ 10% on (A+B+C) 8.02
Cost of each hole 88.18
Rate of each say 88.00
16.40 Fabrication and fixing of steel pedestal support for MT Say 18200.00
bearing
16.41 Providing and fixing of Foundation bolts for steel Each Say 552.50
pedestals.
16.42 Providing and fixing of Steel plates for placing of MT Say 58500.00
bearings
16.43 Non-destuctive testing with Ultrasonic Pulse Velocity
Meter with data storage facility for detection of cracks,
voids and other imperfections in Reinforced concrete
structures and furnishing the findings thereof in proper Each Say 500.50
comprehensible format , complete as directed by the
department.

Page 28 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

16.44 Non-destuctive testing with Profometer 5 Scanlog or


equivalent equipment with facility for built-in memory
storage and statistical analysis of data for detection of
location and orientation of rebars in Reinforced Sqm say 2145.00
concrete structures and furnishing the findings thereof in
proper comprehensible format , complete as directed by
the department.

16.45 Non-destuctive testing with Permeability Tester,


without causing damages to the structure, for
determination the water permeability and water
absorption into the near surface zone of the concrete Each say 550.00
structure and furnishing the findings thereof in proper
comprehensible format , complete as directed by the
department.

16.46 Conducting PH tests on concrete stucture, as per


stipulated procedures, for determination the PH
(alkalinity) of the concrete structure and furnishing the Each say 88.00
findings thereof in proper comprehensible format ,
complete as directed by the department.
16.47 Conducting Carbonation tests on concrete stucture, as
per stipulated procedures, for determination the depth of
carbonation of cover concrete of the structures and
furnishing the findings thereof in proper comprehensible Each say 88.00
format , complete as directed by the department.

16.48 Conducting suitable tests on concrete stucture, including


preparation of samples etc. as per stipulated procedures,
for determination the chloride and sulphate
concentration in the concrete of the structures and Each say 715.00
furnishing the findings thereof in proper comprehensible
format , complete as directed by the department.

16.49 Conducting Concrete Core tests of 75mm diacores, on


concrete stucture, as per stipulated procedures, for
determination the equivalent cube compressive
strength, concrete of the structures including Each say 5005.00
preparation and furnishing the report showing the
findings thereof in proper comprehensible format ,
complete as directed by the department.

16.50 Evaluation of Loss of pre-stress in superstructure


PSC girders including measurement of deflection by
suitable instruments and necessary calculations for
estimation of the probable loss in pre-stress and Each Span say 200000.00
furnishing the findings thereof in a proper
comprehensible format with all details, complete as
directed by the department.

16.51 Stressing operation and grouting complete, including all


accessories for stressing of dummy cables, as per
MT say 10861.00
drawing and technical specifications of section 1800 of
MORTH Specification of Roads and Bridge Work .

Page 29 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Sr No Description Unit Quantity Rate Rs Cost Rs

16.52 Load testing of existng foundation to ensire no void/ gap/


loose pocket below the foundation with a total weight of
250MT (in form of sand bags filling with locally available
sand/ soil etc. placed uniformly on top of well-cap) placed
concentric & uniform w.r.t existing well foundation,
including dewatering and making arrangement with Each say 70000.00
atleast 4 nos dial gauges, for measurement of settlement
of foundation during application and release of the load,
all complete as per specification as directed byb the
department.

16.53 Providing, placing and fixing in position Chemical rebar


fastners (of M/s Hilti or M/s Sika or approved equivalent
conforming to Europian standard CSTB/ETA and Civil Aid
standard) of vaious diameters in Piers, Pier caps,
including drilling holes of specified size and depth,
cleaning holes, placing chemicals inside the holes and
fixing reinforcing bars as per specifications of the
chemical rebar supplier, and under supervision of the
authorized representative of the supplier and conducting
pull-out test of atleast 5% of total nos. of chemical re-ba
fastners (cost of reinforcing bars to be paid seperately) all
complete as per specification as directed byb the
department.

a a) 12 mm dia re-bar fastners. Each say 500.00


b b) 16 mm dia re-bar fastners. Each say 700.00
c c) 20 mm dia re-bar fastners. Each say 750.00
d d) 25 mm dia re-bar fastners. Each say 800.00

Page 30 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

L-12
L-13

P&M-001
P&M-053

105.00
8.57%

L-12
L-13

P&M-001
P&M-053

85.00
1.18%

M-084/1000
M-005
M-192
M-098_1
M-180

Page 31 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

L-12
L-11
L-13

P&M-076

1020.00
7.06%

M-129

L-12
L-15
L-15

L-13

136.00
58.09%

M-084/1000

Page 32 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

L-12
L-15
L-13

M-111

61.00
226.23%

M-084/1000
M-005/1500

L-12
L-15
L-13

M-111

56.00
242.86%

L-12
L-15
L-13

Page 33 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

M-145

M-111

612.00
43.30%

M-098_1

L-12
L-15
L-13

P&M-078

878.00
37.59%

M-098
M-098_2
M-098

L-12

Page 34 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.
L-15
L-13

629.00
26.39%

M-084/1000
M-005
M-116
M-147
M-189

L-12
L-13
L-15

P&M-001
P&M-076
P&M-060

296.00
21.28%

Page 35 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

M-057

M-145

L-12
L-15
L-13

129.00
64.34%

M-098_1

L-12
L-15
L-13

92.00
123.91%

Page 36 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.
M-119

M-114
M-084/1000

M-187

M-098_1

M-179

L-12
L-14
L-13

L-12
L-02
L-13

L-12
L-08
L-13

L-12
L-11
L-13

P&M-040
M-111

Page 37 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

M-119

M-115
M-084

M-187

M-098_1

M-179

L-12
L-14
L-13

L-12
L-02
L-13

L-12
L-08
L-13

L-12
L-11
L-13

P&M-040
M-111

Page 38 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

M-119

M-115
M-084

M-187

M-098_1

M-179

L-12
L-14
L-13

L-12
L-02
L-13

L-12
L-08
L-13

L-12
L-11
L-13

P&M-040
M-111

Page 39 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

P&M-084
L-12
L-15
L-13
M-195

2469.00
60.63%

P&M-084_1

L-02
L-12
L-15
L-13
M-195

Page 40 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.
M-098_1

Item 14.1(C)

L-12
L-13
L-15

2300.00
69.43%

L-12
L-13

P&M-053

110.00
93.64%

L-12
L-13

P&M-053

Page 41 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

189.00
103.17%

L-12
L-13

P&M-053

108.00
65.74%

L-12
L-13

Item 14.1(C)

165.00
61.82%

Page 42 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

Item 14.1(C)

Item 14.2 (b)

L-12
L-13

88.00
167.05%

M-179/1000
M-179/1000
M-130

L-12
L-15
L-13

202.00
87.13%

Page 43 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

95.00
150.53%

157.00
145.86%

322.00
34.16%

Page 44 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

174.00
62.64%

536.00
47.39%

Page 45 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.
265.00
69.06%

356.00
80.06%

M-040

73715.00
-13.88%

Page 46 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

104861.00
-27.61%

1299.00
74.60%

1709.00
25.39%

Page 47 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

4785.00
16.49%

406.00
40.64%

Page 48 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

M-129

571.00
47.11%

Page 49 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

3097.00
-70.71%

333.00
-2.70%

341.00
10.26%

Page 50 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

349.00
8.60%

395.00
-0.51%

4.24
17.92%

3.16
26.58%

Page 51 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

238.00
35.29%

156816.00
-30.81%

152.00
-42.11%

Page 52 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

Page 53 of 959
Analysisof SOR (Roads) 2017-18
Chapter-16

Remarks/
Input ref.

Page 54 of 959
Chapter 17
MISCELLONEOUS ITEMS OF WORK
Sr. Ref to Rate Amount
Description Unit Quantity
No. Spec (Rs.) (Rs.)
Bamboo Bridge
17.1 Construction of cold weather Bamboo bridge overall
width of 3.70m and clear road way 3m with jungle wood
post 20cm to 25cm dia 5nos. In each rows and rows
being 2.1m. apart except for the navigable span which
should be 3m. Post to be driven at least 180cm. or
more below ground level including providing 20cm to
25cm center to center and placed over 20 cm dia,
jungle wood dham, 15cm dia. jungle wood bracing
collar fixed by bolts and nuts, straps etc. mature
bholuka Bamboo cross groth all closely packed and tied
75cm wide track way made from 38mm thick 1st class
local plank fixed on 75mmx100mm first class local
wood battens 120cm apart and 3 lines of jati bamboo
horizantal railing fixed in bholuka bamboo post placed
at 210cm apart and white washed including all
necessary nuts and bolts, coir ropes, struts, nails etc.
complete with a layer of brushwood to exposed portion
out-side trackway with earth topping complete as per
direction of the department.

Unit ----- RM
Analysis for 30.00 RM

A. Materials
i Jungle wood post/dham/beam/diognal
bracing/strut/collar. RM 680 150.00 102000.00
ii Bholuka Bamboo for Gorah/cross gorah/rail post no 255 90.00 22950.00
iii Jati Bamboo for rail bar no 32 75.00 2400.00
iv Sal Wood for collarand/batten/tie cum 0.93 27000.00 25110.00
v Trackway Plank cum 1.8 32000.00 57600.00
vi Brushwood bundles 700 100.00 70000.00
viii Cane cap 20 500.00 10000.00
viii Spreading Earth L/S 80.00
ix White washing L/S 100.00
x Patent Nail kg 4 45.00 180.00
xi Bolts & Nuts kg 10 80.00 800.00
xii Nails kg 2 60.00 120.00
B. Labour
i Carpentar nos 10 458.55 4585.50
ii Skilled Labour nos 20 356.65 7133.00
iii Ordinary labour nos 60 244.56 14673.60
TOTAL = (a+b+c) 317732.10
d) Overhead charges @ 10% on (a+b+c) 31773.21
e) Contractor's profit @ 10% on (a+b+c+d) 31773.21
Cost for 30m = a+b+c 381278.52
Rate per Rm = (a+b+c)/30 12709.28
say 12709.30
17.2 Construction of temporary Bamboo bridge of 3.70m
clear road way with Bholuka or Barua Bamboo post
5nos. in each rows driven at least180cm. below ground
level and rows not more than 150cm apart from center
to center Bholuka or Barua Bamboo dham longitudinal
groth both closely placed and tied with half bamboo
90cm to 120cm apart in both layers and ttwo layers of
jati bamboo chattais ( top layer should be digonally
woven), 70 mm to 100 mm thick brushwood in between
chattias should be tied with half jati bamboo on both
ends, bamboo railing with bholuka or barua bamboo
post placed at150cm apart jati or betua bamboo hand
rails of two lines both side of every alternate rows.All
tying must be done with cane or coir string and only
mature bamboo should be used in work.

Unit ----- RM
Analysis for 30.00 RM

A. Materials
i Bholuka Bamboo post Nos 220 90.00 19800.00
ii Jati Bamboo Nos 280 75.00 21000.00
iii Brushwood bundles 300 100.00 30000.00
iv Cane cap 10 500.00 5000.00
B. Labour
i Skilled Labour nos 5 356.65 1783.25
ii Ordinary labour nos 15 244.56 3668.40
C. Sundries L/S 100.00
TOTAL = (a+b+c) 81251.65
d) Overhead charges @ 10% on (a+b+c) 8125.17
e) Contractor's profit @ 10% on (a+b+c+d) 8125.17
Cost for 30m = a+b+c 97501.98
Rate per Rm = (a+b+c)/30 3250.07
say 3250.10

17.3 Making 120mm wide bamboo foot bridge with 100mm


Bholuka or Barua bamboo posts driven 120 cm to 180
cm underground 3 Nos. in each row and rows being 3m
apart bholuka or Barua bamboo dham placed over the
posts and tied with cane or wire , Bholuka or barua
bamboo struts in each row both up and down stream,
jati bamboo long gorhs closely packed and tied with
dham. Single layer of mat placed over 75mm thick
brush wood and tied with bholuka or Barua bamboo rail
stand fixed in one side of the bridge etc. complete.

Unit ----- RM
Analysis for 3.00 RM

A. Materials
i Bholuka Bamboo post/ rail post/ dham/ strut.
(5nos+5nos) no 10 90.00 900.00
ii Jati Bamboo/ long gorah/ mat/ railing no 6 75.00 450.00
iii Galvanised Wire gms 0.5 80.00 40.00
iv Brushwood bundles 3 100.00 300.00
v Misc materials, T&P etc. L/S 50.00
B. Labour
i Skilled Labour nos 1 356.65 356.65
ii Ordinary labour nos 1 244.56 244.56
TOTAL = (a+b+c) 2341.21
d) Overhead charges @ 20 % on (a+b+c) 468.24
e) Contractor's profit @ 10% on (a+b+c+d) 234.12
Cost for 30m = a+b+c 3043.57
Rate per Rm = (a+b+c)/3 1014.52
say 1014.50

Timber Bridge
17.4 Supplying and driving timber piles of 25cm to 30cm
diameter, dressed to heart wood including making
length in every 30 cm interval, coal tarring two (2) coats
with best tar applied hot (Rate inclusive of the cost of
the required quantity of tar.)
A Using Sal Timber
(a) Mechanically with Rod monkey and crab winch
(i) Portion of pile actually driven underground.
Unit ----- RM
Considering 8 Nos of pile of 8RM length

A. Materials
i Sal pile 25 cm to 30 cm dia 8 RM Rm 8 5000.00 40000.00
ii Jati Bamboo for one bridge of 8 Post [= (100x70)/8] Nos 90 75.00 6750.00
iii Coir rope tying wire for plateform kg 10 80.00 800.00
B. Labour
i Carpentar nos 1.87 458.55 857.49
ii Skilled Labour nos 1.87 356.65 666.94
iii Ordinary labour nos 5.5 244.56 1345.08
C. Hire Charge of pile Engine for 2 days L/S 1000.00
D. Sundries L/S 50.00
TOTAL = (a+b+c) 51469.50
d) Overhead charges @ 20 % on (a+b+c) 10293.90
e) Contractor's profit @ 10% on (a+b+c+d) 5146.95
Cost for 8.0m = a+b+c 66910.36
Rate per Rm = (a+b+c)/8 8363.79
say 8363.80

(ii) Portion of pile remaining above rground.


Unit ----- RM
Considering 8 Nos of pile of 8RM length

A. Materials
i Sal pile 25 cm to 30 cm dia 8 RM Rm 8 5000.00 40000.00
ii Jati Bamboo for one bridge of 8 Post [= (100x70)/8] Nos 90 75.00 6750.00
iii Coir rope tying wire for plateform kg 10 80.00 800.00
B. Labour
i Carpentar nos 2.18 458.55 999.64
ii Skilled Labour nos 1.87 356.65 666.94
iii Ordinary labour nos 5.81 244.56 1420.89
C. Sundries L/S 100.00
TOTAL = (a+b+c) 50737.47
d) Overhead charges @ 20 % on (a+b+c) 10147.49
e) Contractor's profit @ 10% on (a+b+c+d) 5073.75
Cost for 8.0m = a+b+c 65958.71
Rate per Rm = (a+b+c)/8 8244.84
say 8244.80
(b) Manually with labour
(i) Portion of pile actually driven underground.
Unit ----- RM
Analysis for 3m pile

A. Materials
i Sal pile 25 cm to 30 cm dia 8 RM Rm 3 5000.00 15000.00
ii Bholuka Bamboo Nos 3 90.00 270.00
iii Coir rope tying wire for plateform kg 1 80.00 80.00
iv Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter for dressing / marking nos 0.75 458.55 343.91
ii Skilled Labour nos 0.125 356.65 44.58
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 20.00
TOTAL = (a+b+c) 16389.89
d) Overhead charges @ 20 % on (a+b+c) 3277.98
e) Contractor's profit @ 10% on (a+b+c+d) 1638.99
Cost for 3.0m = a+b+c 21306.86
Rate per Rm = (a+b+c)/3 7102.29
say 7102.30

(ii) Portion of pile remaining above rground.


Unit ----- RM
Analysis for 2m pile

A. Materials
i Sal pile 25 cm to 30 cm dia 8 RM Rm 2 5000.00 10000.00
ii Jati Bamboo for Machine Nos 2 75.00 150.00
iii Coir rope tying wire for plateform kg 0.75 80.00 60.00
iv Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter for dressing / marking nos 0.5 458.55 229.28
ii Skilled Labour nos 0.1 356.65 35.67
iii Unskilled labour for coal tarring, ranoling nos 1 244.56 244.56
C. Sundries L/S 20.00
TOTAL = (a+b+c) 10759.50
d) Overhead charges @ 20 % on (a+b+c) 2151.90
e) Contractor's profit @ 10% on (a+b+c+d) 1075.95
Cost for 2.0m = a+b+c 13987.35
Rate per Rm = (a+b+c)/2 6993.68
say 6993.70

B Using Azar/ Nahar/ Nageswar/ Zarul Timber


(a) Mechanically with Rod monkey and crab winch
(i) Portion of pile actually driven underground.
Unit ----- RM
Considering 8 Nos of pile of 8RM length

A. Materials
i Azar/ Nahar/ Nageswar/ Zarul pile 25 cm to 30 cm dia
8 RM Rm 8 4200.00 33600.00
ii Jati Bamboo for one bridge of 8 Post [= (100x70)/8] Nos 90 75.00 6750.00
iii Coir rope tying wire for plateform kg 10 80.00 800.00
B. Labour
i Carpentar nos 1.87 458.55 857.49
ii Skilled Labour nos 1.87 356.65 666.94
iii Ordinary labour nos 5.5 244.56 1345.08
C. Hire Charge of pile Engine for 2 days L/S 1000.00
D. Sundries L/S 50.00
TOTAL = (a+b+c) 45069.50
d) Overhead charges @ 20 % on (a+b+c) 9013.90
e) Contractor's profit @ 10% on (a+b+c+d) 4506.95
Cost for 8.0m = a+b+c 58590.36
Rate per Rm = (a+b+c)/8 7323.79
say 7323.80

(ii) Portion of pile remaining above ground.


Unit ----- RM
Considering 8 Nos of pile of 8RM length

A. Materials
i Azar/ Nahar/ Nageswar/ Zarul pile 25 cm to 30 cm dia
8 RM Rm 8 4200.00 33600.00
ii Jati Bamboo for one bridge of 8 Post [= (100x70)/8] Nos 90 75.00 6750.00
iii Coir rope tying wire for plateform kg 10 80.00 800.00
B. Labour
i Carpentar nos 2.18 458.55 999.64
ii Skilled Labour nos 1.87 356.65 666.94
iii Ordinary labour nos 5.81 244.56 1420.89
C. Sundries L/S 100.00
TOTAL = (a+b+c) 44337.47
d) Overhead charges @ 20 % on (a+b+c) 8867.49
e) Contractor's profit @ 10% on (a+b+c+d) 4433.75
Cost for 8.0m = a+b+c 57638.71
Rate per Rm = (a+b+c)/8 7204.84
say 7204.80

(b) Manually with labour


(i) Portion of pile actually driven underground.
Unit ----- RM
Analysis for 3m pile

A. Materials
i Azar/ Nahar/ Nageswar/ Zarul pile 25 cm to 30 cm dia
8 RM Rm 3 4200.00 12600.00
ii Bholuka Bamboo Nos 3 90.00 270.00
iii Coir rope tying wire for plateform kg 1 80.00 80.00
iv Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter for dressing / marking nos 0.75 458.55 343.91
ii Skilled Labour nos 0.125 356.65 44.58
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 20.00
TOTAL = (a+b+c) 13989.89
d) Overhead charges @ 20 % on (a+b+c) 2797.98
e) Contractor's profit @ 10% on (a+b+c+d) 1398.99
Cost for 3.0m = a+b+c 18186.86
Rate per Rm = (a+b+c)/3 6062.29
say 6062.30

(ii) Portion of pile remaining above rground.


Unit ----- RM
Analysis for 2m pile

A. Materials
i Azar/ Nahar/ Nageswar/ Zarul pile 25 cm to 30 cm dia
8 RM Rm 2 4200.00 8400.00
ii Jati Bamboo for Machine Nos 2 75.00 150.00
iii Coir rope tying wire for plateform kg 0.75 80.00 60.00
iv Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter for dressing / marking nos 0.5 458.55 229.28
ii Skilled Labour nos 0.1 356.65 35.67
iii Unskilled labour for coal tarring, ranoling nos 1 244.56 244.56
C. Sundries L/S 20.00
TOTAL = (a+b+c) 9159.50
d) Overhead charges @ 20 % on (a+b+c) 1831.90
e) Contractor's profit @ 10% on (a+b+c+d) 915.95
Cost for 2.0m = a+b+c 11907.35
Rate per Rm = (a+b+c)/2 5953.68
say 5953.70

17.5 Wood work including supplying , fitting and fixing


complete with necessary M.S. bolts, nuts, nails, screw
etc. and coal tarring two (2) coats with best tar applied
hot (Rate is inclusive of the cost of the required quantity
of tar.)
A Using Sal Wood
(a) Underssed in floor planks, collars, bracing, standards,
wheel guards, struts and railings, runner belts, rail,
posts etc.
Unit ----- CuM
Analysis for 1cum

A. Materials
i Sal timber(undressed) cum 1.02 120.00 122.40
ii Coal Tar gms 0.5 40.00 20.00
iii Bolts, nuts, spikes, nails etc. kg 5 80.00 400.00
B. Labour
i Carpenter for dressing / marking nos 2.5 458.55 1146.38
ii Skilled Labour nos 1.25 356.65 445.81
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 100.00
TOTAL = (a+b+c) 2845.99
d) Overhead charges @ 20 % on (a+b+c) 569.20
e) Contractor's profit @ 10% on (a+b+c+d) 284.60
Cost for 1cum = a+b+c 3699.78
Rate per cum = (a+b+c+d+e) 3699.78
say 3699.80

(b) In track way planks (alternate nailing to be done with


decking in a seggragate way.)
Unit ----- CuM
Analysis for 1cum

A. Materials
i Sal Wood planks 25cm to 38cm dia thick cum 1.02 32000.00 32640.00
ii Coal Tar gms 1 40.00 40.00
iii Bolts, nuts, spikes, nails etc. kg 2.5 80.00 200.00
B. Labour
i Carpenter for dressing / marking nos 2.5 458.55 1146.38
ii Skilled Labour nos 1.25 356.65 445.81
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 50.00
TOTAL = (a+b+c) 35133.59
d) Overhead charges @ 20 % on (a+b+c) 7026.72
e) Contractor's profit @ 10% on (a+b+c+d) 3513.36
Cost for 1cum = a+b+c 45673.66
Rate per cum = (a+b+c+d+e) 45673.66
say 45673.70

B Using Azar/ Nahar/ Nageswar/ Zarul Wood


(a) Undressed in floor planks, collars, bracing, standards,
wheel guards, struts and railings, runner belts, rail,
posts etc
Unit ----- CuM
Analysis for 1cum

A. Materials
i Azar/ Nahar…..(Undressed) cum 1.02 21200.00 21624.00
ii Coal Tar gms 0.5 40.00 20.00
iii Bolts, nuts, spikes, nails etc. kg 5 80.00 400.00
B. Labour
i Carpenter for dressing / marking nos 2.5 458.55 1146.38
ii Skilled Labour nos 1.25 356.65 445.81
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 100.00
TOTAL = (a+b+c) 24347.59
d) Overhead charges @ 20 % on (a+b+c) 4869.52
e) Contractor's profit @ 10% on (a+b+c+d) 2434.76
Cost for 1cum = a+b+c 31651.86
Rate per cum = (a+b+c+d+e) 31651.86
say 31651.90

(b) In track way planks (alternate nailing to be done with


decking in a seggragate way.)
Unit ----- CuM
Analysis for 1cum

A. Materials
i Azar/ Nahar….. Wood planks 25cm to 38cm thick cum 1.02 26500.00 27030.00
ii Coal Tar gms 1 40.00 40.00
iii Bolts, nuts, spikes, nails etc. kg 2.5 80.00 200.00
B. Labour
i Carpenter for dressing / marking nos 2.5 458.55 1146.38
ii Skilled Labour nos 1.25 356.65 445.81
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 50.00
TOTAL = (a+b+c) 29523.59
d) Overhead charges @ 20 % on (a+b+c) 5904.72
e) Contractor's profit @ 10% on (a+b+c+d) 2952.36
Cost for 1cum = a+b+c 38380.66
Rate per cum = (a+b+c+d+e) 38380.66
say 38380.70
17.6 Supplying, fitting and fixing timber beam and bearing
beam rectangular in size fitted with M.S. etc. supplying
spikes etc. as necessary and coal tarring two (2) coats
with best tar applied hot as directed (Rate inclusive of
cost of the required quantity of tar)
(a) Using Sal Timber
Unit ----- CuM
Analysis for 1cum

A. Materials
i Sal timber(undressed) cum 1 120.00 120.00
ii Coal Tar gms 1 40.00 40.00
iii Bolts, nuts, spikes, nails etc. kg 1 80.00 80.00
B. Labour
i Carpenter for dressing / marking nos 3.25 458.55 1490.29
ii Skilled Labour nos 1.25 356.65 445.81
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 50.00
TOTAL = (a+b+c) 2837.50
d) Overhead charges @ 20 % on (a+b+c) 567.50
e) Contractor's profit @ 10% on (a+b+c+d) 283.75
Cost for 1cum = a+b+c 3688.75
Rate per cum = (a+b+c+d+e) 3688.75
say 3688.80

(b) Using Azar/ Nahar/ Nageswar/ Zarul Timber


Unit ----- CuM
Analysis for 1cum

A. Materials
i Azar/ Nahar….. timber(undressed) cum 1 21200.00 21200.00
ii Coal Tar gms 1 40.00 40.00
iii Bolts, nuts, spikes, nails etc. kg 1 80.00 80.00
B. Labour
i Carpenter for dressing / marking nos 3.25 458.55 1490.29
ii Skilled Labour nos 1.25 356.65 445.81
iii Unskilled labour for coal tarring, ranoling nos 2.5 244.56 611.40
C. Sundries L/S 50.00
TOTAL = (a+b+c) 23917.50
d) Overhead charges @ 20 % on (a+b+c) 4783.50
e) Contractor's profit @ 10% on (a+b+c+d) 2391.75
Cost for 1cum = a+b+c 31092.75
Rate per cum = (a+b+c+d+e) 31092.75
say 31092.80

17.7 Supplying, fitting and fixing 25 cm to 30 cm dia. sal


wood log beam dressed to heartwood including
supplying and fixing with 20mm dia M.S. bolts and nuts
etc.including coal tarring two (2) coats with best tar
applied hot as directed (Rate inclusive of cost of the
required quantity of tar)
(a) Using Sal Timber
Unit ----- Rm
Analysis for 5.0RM of Log

A. Materials
i Sal timber Log Rm 5 5000.00 25000.00
ii Coal Tar gms 1 40.00 40.00
iii Bolts, nuts, spikes, nails etc. kg 1 80.00 80.00
B. Labour
i Carpenter for dressing / marking nos 1.25 458.55 573.19
ii Skilled Labour nos 1 356.65 356.65
iii Unskilled labour for coal tarring, ranoling nos 4 244.56 978.24
C. Sundries/ T&P L/S 50.00
TOTAL = (a+b+c) 27078.08
d) Overhead charges @ 20 % on (a+b+c) 5415.62
e) Contractor's profit @ 10% on (a+b+c+d) 2707.81
Cost for 5 Rm = a+b+c 35201.50
Rate per Rm = (a+b+c+d+e) 7040.30
say 7040.30

(b) Using Azar/ Nahar/ Nageswar/ Zarul Timber


Unit ----- Rm
Analysis for 5.0RM of Log

A. Materials
i Azar/ Nahar….. timber Log Rm 5 4200.00 21000.00
ii Coal Tar gms 1 40.00 40.00
iii Bolts, nuts, spikes, nails etc. kg 1 80.00 80.00
B. Labour
i Carpenter for dressing / marking nos 1.25 458.55 573.19
ii Skilled Labour nos 1 356.65 356.65
iii Unskilled labour for coal tarring, ranoling nos 4 244.56 978.24
C. Sundries/ T&P L/S 50.00
TOTAL = (a+b+c) 23078.08
d) Overhead charges @ 20 % on (a+b+c) 4615.62
e) Contractor's profit @ 10% on (a+b+c+d) 2307.81
Cost for 5 Rm = a+b+c 30001.50
Rate per Rm = (a+b+c+d+e) 6000.30
say 6000.30

17.8 Scarfing and joining piles 25 cm to 30 cm diameter,


dressed to heartwood of 90 cm in length includng
supplying, fitting and fixing with 2 nos. of 50mm x
10mm MS FI clamps and 16 mm dia MS bolts and nuts
etc. complete as directed. (Timber for piles and coal
tarring shall be measured and paid separately.)
Unit ----- Each
Analysis for 1no. Joint

A. Materials
i 50mm x 10mm MS Flats Kg 7.79 77.84 606.37
ii Bolts, nuts, spikes, nails etc. kg 1 80.00 80.00
B. Labour
i Carpenter nos 0.625 458.55 286.59
ii Unskilled labour nos 0.625 244.56 152.85
C. Sundries/ T&P L/S 10.00
TOTAL = (a+b+c) 1135.82
d) Overhead charges @ 20 % on (a+b+c) 227.16
e) Contractor's profit @ 10% on (a+b+c+d) 113.58
Cost for 1 Jt. = a+b+c 1476.56
Rate per Jt. = (a+b+c+d+e) 1476.56
say 1476.60
17.9 Labour for taking out old piles of timber bridge with
necessary scaffolding, jati bamboos, jumper ropes etc,
complete and stacking them at suitable places as
directed.
Unit ----- Each
Analysis for 8nos. Piles

A. Materials
i Jumper, Ropes etc. Kg 10 60.00 600.00
ii Jati Bamboo nos 20 75.00 1500.00
iii Scaffoldings L/S 100.00
B. Labour
i Carpenter nos 5 458.55 2292.75
ii Unskilled labour nos 20 244.56 4891.20
C. Sundries/ T&P L/S 5.00
TOTAL = (a+b+c) 9388.95
d) Overhead charges @ 20 % on (a+b+c) 1877.79
e) Contractor's profit @ 10% on (a+b+c+d) 938.90
Cost for 8nos. piles = a+b+c 12205.64
Rate for each pile = (a+b+c+d+e)/8 1525.70
say 1525.70

17.10 Labour for dismantling all members of the timber bridge


(excluding piles) with necessary scaffolding, jati
bamboos, jumper ropes etc, complete and stacking
them at suitable places as directed (all members will be
under custody of the contractor till taken over by the
department)
Unit ----- Meter
Analysis for 6 Rm of span

A. Materials
i Jumper, Ropes etc. Kg 10 60.00 600.00
ii Jati Bamboo nos 5 75.00 375.00
iii Scaffoldings L/S 100.00
B. Labour
i Carpenter nos 1.88 458.55 862.07
ii Unskilled labour nos 15 244.56 3668.40
C. Sundries/ T&P L/S 10.00
TOTAL = (a+b+c) 5615.47
d) Overhead charges @ 20 % on (a+b+c) 1123.09
e) Contractor's profit @ 10% on (a+b+c+d) 561.55
Cost for 6m of span = a+b+c 7300.12
Rate per Rm = (a+b+c+d+e)/6 1216.69
say 1216.70

17.11 Labour for driving timber piles of 25cm to 30cm


diameter, dressed to heartwood marking length in every
30cm interval including coal tarring two (2) coats with
best tar applied hot including providing ncessary
scaffolding or staging (Rate inclusive of cost of the
required quantity of tar)
(a) With Rod monkey and crab winch
(i) Portion of pile actually driven under ground
Unit ----- RM
Considering 8 Nos of pile of 8RM length
A. Materials
i Jati Bamboo for one bridge of 8 Post Nos 12.5 75.00 937.50
ii Coir rope tying wire for plateform kg 10 80.00 800.00
B. Labour
i Carpentar nos 1.875 458.55 859.78
ii Ordinary labour nos 1.875 244.56 458.55
C. Hire Charge of pile Engine for 2 days L/S 1000.00
D. Carriage of Piles L/S 2% of A 34.75
E. Sundries L/S 10.00
TOTAL = (a+b+c) 4100.58
d) Overhead charges @ 20 % on (a+b+c) 820.12
e) Contractor's profit @ 10% on (a+b+c+d) 410.06
Cost for 8.0m = a+b+c 5330.76
Rate per Rm = (a+b+c)/8 666.34
say 666.30

(ii) Portion of pile remaining over ground


Unit ----- RM
Considering 8 Nos of pile of 8RM length

A. Materials
i Jati Bamboo for one bridge of 8 Post Nos 12.5 75.00 937.50
ii Coir rope tying wire for plateform kg 10 80.00 800.00
B. Labour
i Carpentar nos 1.875 458.55 859.78
ii Ordinary labour nos 1.875 244.56 458.55
C. Carriage of Piles L/S 2% of A 34.75
D. Sundries L/S 10.00
TOTAL = (a+b+c) 3100.58
d) Overhead charges @ 20 % on (a+b+c) 620.12
e) Contractor's profit @ 10% on (a+b+c+d) 310.06
Cost for 8.0m = a+b+c 4030.76
Rate per Rm = (a+b+c)/8 503.84
say 503.80

(b) By use of labour


(i) Portion of pile actually driven under ground
Unit ----- RM
Analysis for 3m pile

A. Materials
i Jati Bamboo Nos 3 75.00 225.00
ii Coir rope tying wire for plateform kg 3 80.00 240.00
iii Coal Tar gms 1 40.00 40.00
B. Labour
i Carpenter for dressing / marking nos 0.75 458.55 343.91
ii Unskilled labour for coal tarring, ranoling nos 6 244.56 1467.36
C. Carriage of Piles L/S 2% of A 10.10
D. Sundries L/S 10.00
TOTAL = (a+b+c) 2336.37
d) Overhead charges @ 20 % on (a+b+c) 467.27
e) Contractor's profit @ 10% on (a+b+c+d) 233.64
Cost for 3.0m = a+b+c 3037.28
Rate per Rm = (a+b+c)/3 1012.43
say 1012.40

(ii) Portion of pile remaining over ground


Unit ----- RM
Analysis for 2m pile

A. Materials
i Jati Bamboo Nos 3 75.00 225.00
ii Coir rope tying wire for plateform kg 1.5 80.00 120.00
iii Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter for dressing / marking nos 0.75 458.55 343.91
ii Unskilled labour for coal tarring, ranoling nos 1.25 244.56 305.70
C. Carriage of Piles L/S 5% of A 18.25
D. Sundries L/S 10.00
TOTAL = (a+b+c) 1042.86
d) Overhead charges @ 20 % on (a+b+c) 208.57
e) Contractor's profit @ 10% on (a+b+c+d) 104.29
Cost for 2.0m = a+b+c 1355.72
Rate per Rm = (a+b+c)/2 677.86
say 677.90

17.12 Labour for fitting and fixing RSJ beam, CI saddle etc. in
position including necessary scaffolding, cutting them to
required size, drilling holes and supplying and fixing
ncessary bolts and nuts, painting two coats complete
(Tar-Steel paints to be supplied by the contractor at his
own costs) including all lead and lifts from PWD
Godown.

Unit ----- Qntl.


Analysis for 10Qntl.

A. Materials
i Jati Bamboo Nos 20 75.00 1500.00
ii Bolts and nuts kg 5 80.00 400.00
iii Rope gms 1 80.00 80.00
iv Paint Ltrs 4.5 258.00 1161.00
B. Labour
i Carpenter nos 1.25 458.55 573.19
ii Unskilled labour nos 10 244.56 2445.60
C. Carriage (for ave. 25Km) Km 25 8.80 220.00
TOTAL = (a+b+c) 6379.79
d) Overhead charges @ 20 % on (a+b+c) 1275.96
e) Contractor's profit @ 10% on (a+b+c+d) 637.98
Cost for 10Qntl. = a+b+c 8293.72
Rate per Qntl. = (a+b+c)/10 829.37
say 829.40

17.13 Labour for fitting and fixing RSJ beam, Old CI saddle
etc. in position including necessary scaffolding and
fixing necessary bolts and nuts, painting two coats
complete as directed (Tar-Steel paints to be supplied by
the contractor at his own costs)
Unit ----- Qntl.
Analysis for 10Qntl.

A. Materials
i Jati Bamboo Nos 20 75.00 1500.00
ii Bolts and nuts kg 5 80.00 400.00
iii Rope gms 1 80.00 80.00
iv Paint Ltrs 4.5 258.00 1161.00
B. Labour
i Carpenter nos 0.75 458.55 343.91
ii Unskilled labour nos 8 244.56 1956.48
TOTAL = (a+b+c) 5441.39
d) Overhead charges @ 20 % on (a+b+c) 1088.28
e) Contractor's profit @ 10% on (a+b+c+d) 544.14
Cost for 10Qntl. = a+b+c 7073.81
Rate per Qntl. = (a+b+c)/10 707.38
say 707.40

17.14 Labour for making and fitting MS F.I. Straps and cleats
etc. in position including drilling holes complete with all
lead and lifts from PWD Godown.
A. Labour
i Carpenter nos 1.25 458.55 573.19
ii Unskilled labour nos 1.25 244.56 305.70
iii Blacksmith nos 2.75 458.55 1261.01
B. Carriage from godown Km 25 8.80 220.00
C. Wear & Tear of T&P L/S 20.00
D. Sundries L/S 10.00
TOTAL = (a+b+c) 2389.90
d) Overhead charges @ 20 % on (a+b+c) 477.98
e) Contractor's profit @ 10% on (a+b+c+d) 238.99
Cost for 1.0Qntl. = a+b+c 3106.87
Rate per Qntl. = (a+b+c) 3106.87
say 3106.90

17.15 Supplying fitting and fixing "U" shaped flat iron strap
making 0.5m x 0.3m size from 150mm x 12mm size MS
flat including providing 10 bolts holes and fitting with
0.35m long 20mm dia MS bolts including fitting tightly
with bearing beam, pile and RSJ beams etc. complete
as directed.
Unit ----- Each
Analysis for 1no. U shaped strap

A. Materials
i U shape iron strap with hole Nos 10 45.00 450.00
ii Bolts and nuts kg 5 80.00 400.00
B. Labour
i Carpenter nos 0.25 458.55 114.64
ii Unskilled labour nos 0.25 244.56 61.14
C. Carriage (for ave. 25Km) Km 25 8.80 220.00
TOTAL = (a+b+c) 1245.78
d) Overhead charges @ 20 % on (a+b+c) 249.16
e) Contractor's profit @ 10% on (a+b+c+d) 124.58
Cost for 1no. strap = a+b+c 1619.51
Rate per No. = (a+b+c) 1619.51
say 1619.50

17.16 Labour for fitting woodwork including sizing, supplying


and fixing with new MS bolts, nuts, nails, spikes etc.
and coal tarring with best tar applied hot as directed
(Rate inclusive of cost of the required quantity of tar)
complete with all lead and lifts from PWD Godown.
(a) Applying 2 (two) coats of Coal Tar
Unit ----- Cum
Analysis for 1.0Cum

A. Materials
i Bolts and nuts kg 1 80.00 80.00
ii Coal Tar gms 1 40.00 40.00
B. Labour
i Carpenter nos 2.25 458.55 1031.74
ii Unskilled labour nos 4 244.56 978.24
C. Wear & Tear of T&P L/S 10.00
TOTAL = (a+b+c) 2139.98
d) Overhead charges @ 20 % on (a+b+c) 428.00
e) Contractor's profit @ 10% on (a+b+c+d) 214.00
Cost for 1.0cum = a+b+c 2781.97
Rate per cum = (a+b+c) 2781.97
say 2782.00

(b) Applying 1 (one) coats of Coal Tar


Unit ----- Cum
Analysis for 1.0Cum

A. Materials
i Bolts and nuts kg 1 80.00 80.00
ii Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter nos 1.65 458.55 756.61
ii Unskilled labour nos 3.5 244.56 855.96
C. Wear & Tear of T&P L/S 5.00
TOTAL = (a+b+c) 1717.57
d) Overhead charges @ 20 % on (a+b+c) 343.51
e) Contractor's profit @ 10% on (a+b+c+d) 171.76
Cost for 1.0cum = a+b+c 2232.84
Rate per cum = (a+b+c) 2232.84
say 2232.80

17.17 Labour for fitting and fixing 25cm to 30cm diameter Log
Beam including supplying and fixing necessary MS
nuts and bolts etc. and coal tarring with best tar applied
hot as directed (Rate inclusive of cost of the required
quantity of tar)
(a) Applying 2 (two) coats of Coal Tar
Unit ----- Rm
Analysis for 5.0Rm

A. Materials
i Bolts and nuts kg 5 80.00 400.00
ii Coal Tar gms 1 40.00 40.00
B. Labour
i Carpenter nos 1.25 458.55 573.19
ii Unskilled labour nos 5 244.56 1222.80
C. Sundries L/S 10.00
TOTAL = (a+b+c) 2245.99
d) Overhead charges @ 20 % on (a+b+c) 449.20
e) Contractor's profit @ 10% on (a+b+c+d) 224.60
Cost for 5.0Rm = a+b+c 2919.78
Rate per Rm = (a+b+c)/5 583.96
say 584.00
(b) Applying 1 (one) coats of Coal Tar
Unit ----- Rm
Analysis for 5.0Rm

A. Materials
i Bolts and nuts kg 5 80.00 400.00
ii Coal Tar gms 0.5 40.00 20.00
B. Labour
i Carpenter nos 0.65 458.55 298.06
ii Unskilled labour nos 3.25 244.56 794.82
C. Sundries L/S 5.00
TOTAL = (a+b+c) 1517.88
d) Overhead charges @ 20 % on (a+b+c) 303.58
e) Contractor's profit @ 10% on (a+b+c+d) 151.79
Cost for 5.0Rm = a+b+c 1973.24
Rate per Rm = (a+b+c)/5 394.65
say 394.60

17.18 Labour for talking out old woodworks of bridge and the
refitting the same including supplying and fixing
necessary new MS bolts, nuts, spikes, nail etc.
complete and coal tarring with best tar applied hot as
directed (Rate inclusive of cost of the required quantity
of tar)
Unit ----- Cum
Analysis for 1.0Cum

A. Materials
i Bolts and nuts kg 10 80.00 800.00
ii Coal Tar gms 1 40.00 40.00
B. Labour
i Carpenter nos 1.75 458.55 802.46
ii Unskilled labour nos 4.5 244.56 1100.52
C. Wear & Tear of T&P L/S 10.00
TOTAL = (a+b+c) 2752.98
d) Overhead charges @ 20 % on (a+b+c) 550.60
e) Contractor's profit @ 10% on (a+b+c+d) 275.30
Cost for 1.0cum = a+b+c 3578.88
Rate per cum = (a+b+c) 3578.88
say 3578.90

17.19 Labour for talking out old Log Beam of bridge and the
refitting the same including supplying and fixing
necessary new MS bolts, nuts, spikes, nail etc.
complete and coal tarring with best tar applied hot as
directed (Rate inclusive of cost of the required quantity
of tar)
Unit ----- Rm
Analysis for 5.0Rm

Log Beam size: 5m x 0.3 x 0.3 = 0.45cum


Cost as per Item no.17.18 above cum 0.45 3578.90 1610.51
Cost for 5.0Rm (a) 1610.51
Rate per Rm = a/5 322.10
say 322.10
17.20 Pile shoes : supplying fitting and fixing the pile shoes
made of 6mm thick mild steel plate with necessary
welding joints, size of pile shoe will be 78.54 cm
(circumferential length of at top.) x 50cm(Depth) x 5cm
(circumferential length at bottom) and 25cm inside
diameter at top, including fitting and fixing 3 (Three)
nos. M.S. plate of size of 6mm x 50mm, length 45cm at
top of the pile shoe with necessary welding and drilling
three nos of holes in each plate including fitting and
fixing the pile shoes at the pile end with necessary
patent nails etc. , complete as directed by the
Department .The pile shoe should be camphered to fit
the pile shoe properly with necessary grooving for
placing the MS plates and pile shoe.

Unit ----- Each


Analysis for 1.0no. Shoe

A. Materials
i 6mm thick mild steel plate kg 0.92 60.00 55.20
ii Bolts and nuts kg 5 80.00 400.00
B. Labour
i Carpenter nos 0.5 458.55 229.28
ii Unskilled labour nos 1.25 244.56 305.70
iii Blacksmith nos 1.5 458.55 687.83
C. Sundries L/S 5.00
TOTAL = (a+b+c) 1683.00
d) Overhead charges @ 20 % on (a+b+c) 336.60
e) Contractor's profit @ 10% on (a+b+c+d) 168.30
Cost for 1.0no. = a+b+c 2187.90
Rate per no. = (a+b+c) 2187.90
say 2187.90

Spurs & Palasiding Works


17.21 Single bamboo spur and palasiding of whole 2nd class
bamboo (Jati or Bethua) 65mm to 75mm dia closely
packed & driven, including fitting and fixing with half
bamboo kamis horizantally in three rows with the cane
or tieing wire complete and struts 1500 mm apart
longitudinally and providing brush wood as per drawing
and technical specification clause 1302.5 of MORD

(a) Driven at least 900mm below and 1800 mm above the


ground on average. meter 581.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 610.05
say 610.10

(b) Driven at least 900mm below and 900 mm above the


ground on average meter 474.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 497.7
say 497.70
17.22 Single bamboo spur and palasiding of whole 1st class
bamboo (Bholuka or Barua) 85mm to 100mm dia
closely packed & driven, including fitting and fixing with
half 2nd class bamboo (Jati or Bethua) bamboo kamis
horizantally in three rows with the cane or tieing wire
complete and struts 1500 mm apart longitudinally and
providing brush wood as per drawing and technical
specification clause 1302.5 of MORD.

(a) Driven at least 900mm below and 1800 mm above the


ground on average. meter 659.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 691.95
say 692.00

(b) Driven at least 900mm below and 900 mm above the


ground on average meter 403.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 423.15
say 423.20

(c) Driven at least 900mm below and 1200 mm above the


ground on average meter 375.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 393.75
say 393.80

17.23 Bamboo spur 'A' type with whole bamboo placed


230mm center to center driven 900mm below ground
and 1200mm to 1500mm above the ground tied with
2nd class bamboo (Jati or Bethua) on either side at
450mm apart horizantally with galvanized wire etc.
complete as per drawing and technical specifications.
(a) 2nd class bamboo (Jati or Bethua) 65mm to 75mm dia.
meter 614.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 644.7
say 644.70

(b) 1st class bamboo (Bholuka or Barua) 85mm to 100mm


dia. meter 502.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 527.1
say 527.10

17.24 Bamboo single spur 'A' type with 1st class bamboo
(Bholuka or Barua) 85mm to 100mm dia, driven closely
placed 3m to 4m above the ground and 1.20m to 1.5m
below the ground and tied with cane or coir string, half
2nd class bamboo (Jati or Bethua) kamis horizontally
on both face placed not more than one meter apart
including whole bamboo struts inside one meter apart
and 2nos. of purlin at top and bottom fitted with vertical
struts at 1500mm apart and filling with brushwood or
jungle wood inside the spur complete as per drawing
and technical specifications.
meter 862.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 905.1
say 905.10

17.25 Close bamboo toe walling with 65mm to 75mm


diameter bamboos of length ranging from 1.2m to 3.0m
driven at least 150mm c/c and provided with three
horizontal split bamboo runner fixed with nails complete
including coal tarring as directed (Rate inclusive of cost
of the required quantity of tar) meter 694.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 728.7
say 728.70

17.26 Double timber spur with two rows of 1st class local
wood (Azar/ Nahar/ Nageswar/ Zarul) timber piles of
150mm to 200mm dia driven 800mm c/c apart upto
minimum 2000mm below ground and 3600mm above
ground and average placed at 800mm belt, bracing etc.
of 100mm x 75mm size dia bolts and nuts etc. including
coal tarring of timber members and necessary bamboo
staging etc. as directed and as per drawing and
technical specifications.
meter 24125.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 25331.25
say 25331.30

17.27 Supplying and filling up hollows of the timber spur to an


average height of 3600mm above the ground with
jungle wood branches as directed and as per drawing
and technical specifications. meter 52.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 54.6
say 54.60

17.28 Providing split bamboo digonally wooven lining over


slope of bridges, abutement and road embakement etc.
secured to the ground at least 70cm long bamboo pegs
and half bamboo horizontally at 100cm center to center
both ways complete as directed. sqm 108.00
Unit ----- sqm
Add 5% above 2013-14 schedule: 5% 113.4
say 113.40

17.29 Supplying, fitting and fixing whole Bholuka or Barua


bamboo pegs 85mm to 100mm dia, closely placed all
round the hollows of spur fitted with necessary nail in
the horizontal timber between 90 cm below ground and
360cm above ground on average (timber works will be
paid for separately).
(a) For 360 cm above ground on average meter 731.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 767.55
say 767.60

(b) For 200 cm above ground on average meter 584.00


Unit ----- meter
Add 5% above 2013-14 schedule: 5% 613.2
say 613.20
Guard Posts
17.30 Supplying, fitting and fixing RCC guard post 150cm
long erected 75cm above the ground and 75cm below
the ground with M-15 grade (nominal mix 1:2:4 with
broken stone aggregate up to 20mm size) of cement
concrete and required reinforcement tied in position
with annealed black wire including centering, moulding
the top, curing including painting concrete surfaces in
23cm strips upto 0.75m from the top alternately in black
and white and having 2 nos. reflective band of desired
shade etc. complete as per design and as directed.

(a) 30 cm dia. RCC guard post with reinforcement of 6nos.


12mm dia TMT main steel bars and 6mm TMT/ MS
stirrups at 15cm c/c. Each
Unit = Each
Taking output = 50 Nos.
a) M-15 grade of the guard post cum 7.833 7112.00 55706.16
b) Steel reinforcement kg 459.04 78.53 36045.83
c) Excavation in soil cum 7.594 251.00 1906.03
d) Painting sqm 35.343 42.00 1484.41
Transportation and fixing
e) Labour
Mate day 0.650 356.65 231.82
Mazdoor day 30.000 244.56 7336.80
f) Machinery
Tractor-trolley hour 8.000 623.00 4984.00
g) Material

h) Overhead charges @ 10% on (e+f+g) 1255.26


i) Contractor's profit @ 10% on (e+f+g+h) 1380.79
Cost for 50Nos. Guard post = (a+b +c+d +e+ f+g+h+i )
110331.11
Rate for each boundary pillar = (a+b+c+d+e+
2206.62
f+g+h+i)/50
say 2207.00
(b) 15 cm dia. RCC guard post with reinforcement of 4nos.
12mm dia TMT main steel bars and 6mm TMT/ MS
stirrups at 15cm c/c. Each 1041.00
Unit = Each
Taking output = 50 Nos.
a) M-15 grade of the guard post cum 2.450 7112.00 17426.98
b) Steel reinforcement kg 294.43 78.53 23120.47
c) Excavation in soil cum 3.375 251.00 847.13
d) Painting sqm 17.672 42.00 742.20
Transportation and fixing
e) Labour
Mate day 0.650 356.65 231.82
Mazdoor day 20.000 244.56 4891.20
f) Machinery
Tractor-trolley hour 7.000 623.00 4361.00
g) Material

h) Overhead charges @ 10% on (e+f+g) 948.40


i) Contractor's profit @ 10% on (e+f+g+h) 1043.24
Cost for 50Nos. Guard post = (a+b +c+d +e+ f+g+h+i )
53612.45
Rate for each boundary pillar = (a+b+c+d+e+
1072.25
f+g+h+i)/50
say 1072.00
17.31 Supplying, fitting and fixing 20cm to 25cm diameter
Jungle Wood Dressed guard post of 150cm long
erected 75cm above the ground and 75cm below the
ground, fitted with horizantal struts size 50mm x 50mm
x 550mm long at bottom with necessary nails
necessary etc. including coal tarring one coat below
ground and painting surfaces in 23cm strips upto 0.75m
from the top alternately in black and white and having 2
nos. reflective band of desired shade etc. complete as
per design and as directed.
Each 476.00
Unit ----- Each
Add 5% above 2013-14 schedule: 5% 499.8
say 499.80

Earthwork by Head Load


17.32 Earthwork in filling in the guide bund by head load up to
lead of 60m with approved quality all leads and lifts
ramming and compacting with rammer weighing not
less than 10kg and falling from height of not less than
90cm and sprinkling with water if necessary. earth is to
collected after removing the 1st 20cm of top soil and
should be free from grass, shrubs and other foreign
matter and rate will be including payment of land
compensation.
cum 57.00
Unit = cum
Analysis for 3.00cum of loose earth, i.e 2.65cum
finished work (with 12.5% compaction)
a) Labour for cutting earth
i) for cutting earth
Mazdoor day 0.630 244.56 154.07
ii) for carrying/ dressing/ ramming
Mazdoor day 0.130 244.56 31.79
b) Sundries, wear and tear of T&P L/s 5.00
c) Overhead charges @ 10% on (a) 18.59
d) Contractor's profit @ 10% on (a+b+c) 20.95
Cost of 2.65 cum = a+b+c+d 230.40
Rate per cum = (a+b+c+d)/2.65 86.94
say 86.90
(a) Extra lead for each 30cm and part thereof beyond 60m
up to a lead 200m. cum 8.00
Analysis for 30.00cum of loose earth, i.e
26.25cum finished work (with 12.5% compaction)
a) Labour
Mazdoor day 1.000 244.56 244.56
b) Sundries, wear and tear of T&P L/s 5.00
c) Overhead charges @ 10% on (a) 24.46
d) Contractor's profit @ 10% on (a+b+c) 27.40
Cost of 2.65 cum = a+b+c+d 301.42
Rate per cum = (a+b+c+d)/26.25 11.48
say 11.50
(b) Extra lift for each 1.50m or part thereof beyond the
initial lift of 1.50m cum 8.00
Rate per cum same as (a) above 11.50
17.33 Earth work by head load in filling embankment in layers
not exceeding 20cm thick including breaking clods,
dressing and sectioning, cambering and ramming,
within a lead up to 30m and lift up to 1.5m including
payment of land conpensation for obtaining earth from
private land or govt. land as required (measurement will
be on the bais of profile or section measurement,
12.5% deduction being made on the quantity thus
arrived for shrinkage allowance.

(i) Sandy soil.


Unit = cum
Analysis for 3.00cum of loose earth, i.e 2.65cum
finished work (with 12.5% compaction)
a) Labour for cutting earth
i) for cutting earth
Mazdoor day 0.630 244.56 154.07
ii) for carrying/ dressing/ ramming
Mazdoor day 0.130 244.56 31.79
b) Sundries, wear and tear of T&P L/s 5.00
c) Overhead charges @ 10% on (a) 18.59
d) Contractor's profit @ 10% on (a+b+c) 20.95
Cost of 2.65 cum = a+b+c+d 230.40
Rate per cum = (a+b+c+d)/2.65 86.94
say 86.90
(ii) Ordinary soil, Basti land, Low marshy land.
Unit = cum
Analysis for 3.00cum of loose earth, i.e 2.65cum
finished work (with 12.5% compaction)
a) Labour for cutting earth
i) for cutting earth
Mazdoor day 0.750 244.56 183.42
ii) for carrying/ dressing/ ramming
Mazdoor day 0.375 244.56 91.71
b) Sundries, wear and tear of T&P L/s 5.00
c) Overhead charges @ 10% on (a) 27.51
d) Contractor's profit @ 10% on (a+b+c) 30.76
Cost of 2.65 cum = a+b+c+d 338.41
Rate per cum = (a+b+c+d)/2.65 127.70
say 127.70
(iii) Hard soil mixed with moorum and gravel
Unit = cum
Analysis for 3.00cum of loose earth, i.e 2.65cum
finished work (with 12.5% compaction)
a) Labour for cutting earth
i) for cutting earth
Mazdoor day 1.000 244.56 244.56
ii) for carrying/ dressing/ ramming
Mazdoor day 0.375 244.56 91.71
b) Sundries, wear and tear of T&P L/s 5.00
c) Overhead charges @ 10% on (a) 33.63
d) Contractor's profit @ 10% on (a+b+c) 37.49
Cost of 2.65 cum = a+b+c+d 412.39
Rate per cum = (a+b+c+d)/2.65 155.62
say 155.60
(a) Extra lead for each 30m and part thereof beyond initial
lead of 30m. cum 8.00
Unit = cum
Analysis for 30.00cum of loose earth, i.e
26.25cum finished work (with 12.5% compaction)

a) Labour
Mazdoor day 1.000 244.56 244.56
b) Sundries, wear and tear of T&P L/s 5.00
c) Overhead charges @ 10% on (a) 24.46
d) Contractor's profit @ 10% on (a+b+c) 27.40
Cost of 2.65 cum = a+b+c+d 301.42
Rate per cum = (a+b+c+d)/26.25 11.48
say 11.50
(b) Extra lift for each 1.50 m or part thereof beyond the
initial lift of 1.50m
Rate per cum same as (a) above 11.50
17.34 Earth work in core of embankment by head load with
soil of approved quality with a lead up to 30 m and lift
up to 1.5 m in layers not exceeding 20 cm including
breaking clods, dressing grading to required shape and
compacting to meet requiremenet of Table 300 - 2
(including payment of land conpenssation for obtaining
earth).

Unit = cum
Taking output = 220 cum
a) Labour
Mate day 20.000 356.65 7133.00
Mazdoor day 100.000 244.56 24456.00
b) Machinery
Truck 5.5 cum capacity hour 8.000 717.00 5736.00
c) Sundries, wear and tear of T&P L/s 250.00
c) Overhead charges @ 10% on (a+b) 3757.50
d) Contractor's profit @ 10% on (a+b+c) 4133.25
Cost of 220 cum = a+b+c+d 45465.75
Rate per cum = (a+b+c+d)/220 206.66
say 206.70
(a) Extra lead for each 30m and part thereof beyond initial
cum Same as item no.17.33(a) 11.50
lead of 30m.
(b) Extra lift for each 1.50 m or part thereof beyond the
cum Same as item no.17.33(b) 11.50
initial lift of 1.50m
17.35 Earth work in sub grade and shoulders by head load
with selected soil of approved quality with a lead of 30
m and lift up to 1.5 m spreading grading to required
shape and compacting to meet requirement of Table
300 -2 (including payment of land compensation of
obtaining earth).
Unit = cum
Taking output = 150 cum
a) Labour
Mate day 15.000 356.65 5349.75
Mazdoor day 60.000 244.56 14673.60
b) Machinery
Truck 5.5 cum capacity hour 8.000 717.00 5736.00
c) Sundries, wear and tear of T&P L/s 250.00
c) Overhead charges @ 10% on (a+b) 2600.94
d) Contractor's profit @ 10% on (a+b+c) 2861.03
Cost of 150 cum = a+b+c+d 31471.31
Rate per cum = (a+b+c+d)/150 209.81
say 209.80
(a) Extra lead for each 30m and part thereof beyond initial cum Same as item no.17.33(a) 11.50
lead of 30m.
(b) Extra lift for each 1.50 m or part thereof beyond the cum Same as item no.17.33(b) 11.50
initial lift of 1.50m
Miscelleneous Road Pavement Works
17.36 Labour for spreading metal gravel / granular material on
the road surface as directed including dressing and
cambering the formation and utilizing the loose earth in
filling the depression as directed including carriage of
gravel within 30m.
Unit = cum
Analysis for 3.00cum of granular material, i.e
2.40cum finished work (with 20% compaction)
a) Labour for cutting earth
Mate day 0.150 356.65 53.50
Mazdoor day 1.250 244.56 305.70
b) Sundries, wear and tear of T&P L/s 10.00
c) Overhead charges @ 10% on (a) 35.92
d) Contractor's profit @ 10% on (a+b+c) 40.51
Cost of 2.40 cum = a+b+c+d 445.63
Rate per cum = (a+b+c+d)/2.40 185.68
say 185.70
17.37 Close graded Premix Surfacing using cationic Bitumen
Emulsion SS-2 or Tailor made as per(IRC:SP:100-
2014)
Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of
11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm
(Type-B) aggregates using Bitumen emulsion to
required line, grade and level to serve as wearing
course on a previously prepared base, including mixing
in a suitable plant, laying and rolling with a three wheel
8-10 kN static roller and finishing to required level and
grades as per Technical Specification Clause 509

A Manual Means
(i) Type-A
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Material
Bitumen@ 22 kg per 10 sqm tonne 22.9 27790 636391.00
Stone crushed aggregates 11.2 mm to 0.09 @ cum 276.75 1510 417892.50
0.27 cum per 10 sqm
b) Labour
Mate No. 0.84 356.65 299.59
Mazdoor (Unskilled) for HMP, road sweeper, No. 16 356.65 5706.40
paver and roller
Mazdoor (skilled) for checking line & levels No. 5 356.65 1783.25
c) Machinery
i) HMP of appropicate capacity. hour 6 22823.00 136938.00
ii) Electric Generator Set 250 KVA hour 6 2073.00 12438.00
iii) Front end loader 1 cum bucket capacity hour 6 1341.00 8046.00
iv) Tipper 10 tonne capacity tonne. 450 60.00 27000.00
km
Add 10 per cent of cost of carriage to cover cost 2700.00
of loading and unloading
v) Paver finisher hydrostatic with sensor hour 6 2341.00 14046.00
attachment
iv) Smooth wheeled8-10 tonnes weight hour 6 924.00 5544.00
d) Overhead charges @ 10% on (a+b+c) 124649.47
e) Contractor's profit @ 10% on (a+b+c+d) 139343.42
Rate per cum = (a+b+c+d+e)/10250 149.54
say 150.00
(ii) Type-B
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Material
Bitumen@ 22 kg per 10 sqm tonne 19.98 27790 555244.20
Stone crushed aggregates 11.2 mm to 0.09 @ cum 276.75 1510 417892.50
0.27 cum per 10 sqm
b) Labour
Mate No. 0.84 356.65 299.59
Mazdoor (Unskilled) for HMP, road sweeper, No. 16 356.65 5706.40
paver and roller
Mazdoor (skilled) for checking line & levels No. 5 356.65 1783.25
c) Machinery
i) HMP of appropicate capacity. hour 6 22823.00 136938.00
ii) Electric Generator Set 250 KVA hour 6 2073.00 12438.00
iii) Front end loader 1 cum bucket capacity hour 6 1341.00 8046.00
iv) Tipper 10 tonne capacity tonne. 450 60.00 27000.00
km
Add 10 per cent of cost of carriage to cover cost 2700.00
of loading and unloading
v) Paver finisher hydrostatic with sensor hour 6 2341.00 14046.00
attachment
iv) Smooth wheeled8-10 tonnes weight hour 6 924.00 5544.00
d) Overhead charges @ 10% on (a+b+c) 116534.79
e) Contractor's profit @ 10% on (a+b+c+d) 130417.27
Rate per cum = (a+b+c+d+e)/10250 139.96
say 140.00
Seal coat with Emulsion
17.38 Seal coatwith cold mix Binder (as per IRC: SP-100,
2014) Providing and laying seal coat sealing the voids
in a bituminous surface laid to the specified levels
grade and cross fall using Type A,Type B and Type C
as per Technical specification clause 510.
A By manual means
Case-I: Type A (11.2mm to2.36mm)
Bitumen Emulsion (CRS-2) sqm 81.00
Unit = sqm
Taking output = 1100 sqm
a) Material
Bitumen (RS-2) @12 Kg per 10 sqm/All in 1 t 1.3 26260 34138.00
Crushed stone chipping 6.7mm 100 percent cum 9.9 1510 14949.00
passing 11.2mm sieve and retained on 2.36mm
sieveapplied @0.09cum per 10 sqm
b) Labour
Mate day 0.8 356.65 285.32
Emulsion sprayer day 1 244.56 244.56
Mazdoor (Unskilled) day 10 244.56 2445.60
Mazdoor (Semi-Skilled) day 2 285.32 570.64
c) Machinery
Bitumen emulsion pressure distributor hour 0.88 954.00 839.52
Three wheel 80-100 kN static roller hour 2.2 924.00 2032.80
d) Overhead charges @ 10% on (a+b+c) 5550.54
e) Contractor's profit @ 10% on (a+b+c+d) 6105.60
Rate per cum = (a+b+c+d+e)/1100 61.06
say 61.10
Case-II: Type-B (2.36mm to 180 micron)
Bitumen Emulsion (CSS-2) sqm 56.00
Unit = sqm
Taking output = 1250 sqm
a) Material
Bitumen (CSS-2) @12 Kg per 10 sqm/All in 1 t 1.25 27790 34737.50
Crushed sand or grit passing 2.36 mm sieve and cum 7.5 698 5235.00
retained on 180 micron applied @0.06 cum per 10
sqm
b) Labour
Mate day 0.8 356.65 285.32
Emulsion sprayer day 1 244.56 244.56
Mazdoor (Unskilled) day 10 244.56 2445.60
Mazdoor (Semi-Skilled) day 2 285.32 570.64
c) Machinery
Bitumen emulsion pressure distributor hour 0.88 954.00 839.52
Three wheel 80-100 kN static roller hour 2.2 924.00 2032.80
d) Overhead charges @ 10% on (a+b+c) 4639.09
e) Contractor's profit @ 10% on (a+b+c+d) 5103.00
Rate per cum = (a+b+c+d+e)/1250 44.91
say 44.90
Case III:Type-C (9.5mm to 2.36mm)
Bitumen Emulsion (CSS-2) sqm 65.00
Unit = sqm
Taking output = 1100 sqm
a) Material
Bitumen (CSS-2) @12 Kg per 10 sqm/All in 1 t 0.99 27790 27512.10
Crushed stone chipping of 6.7 mm size defined cum 9.9 1041.5 10310.85
as 100% passing 9.5mm sieve and retained on
2.36 mm sieve applied @ 0.09 cum
b) Labour
Mate day 0.8 356.65 285.32
Emulsion sprayer day 1 244.56 244.56
Mazdoor (Unskilled) day 10 244.56 2445.60
Mazdoor (Semi-Skilled) day 2 285.32 570.64
c) Machinery
Bitumen emulsion pressure distributor hour 0.88 954.00 839.52
Three wheel 80-100 kN static roller hour 2.2 924.00 2032.80
d) Overhead charges @ 10% on (a+b+c) 4424.14
e) Contractor's profit @ 10% on (a+b+c+d) 4866.55
Rate per cum = (a+b+c+d+e)/1100 48.67
say 48.70
B By mechanical means
Case-I: Type A (11.2mm to2.36mm)
Bitumen Emulsion (CRS-2) sqm 79.00
Unit = sqm
Taking output = 7500 sqm
a) Material
Bitumen (RS-2) @12 Kg per 10 sqm/All in 1 t 8.3 26260 217958.00
Crushed stone chipping 6.7mm 100 percent cum 67.5 1510 101925.00
passing 11.2mm sieve and retained on 2.36mm
sieveapplied @0.09cum per 10 sqm
b) Labour
Mate day 0.16 356.65 57.06
Emulsion sprayer day 1 244.56 244.56
Mazdoor (Unskilled) day 10 244.56 2445.60
c) Machinery
Hydraulic self vpropelled chip spreader hour 6 2380.00 14280.00
Tipper 5.5 cum capacity hour 6 850.00 5100.00
Front end loader hour 6 1341.00 8046.00
Bitumen emulsion pressure distributor hour 6 954.00 5724.00
Three wheel 80-100 kN static roller hour 15 924.00 13860.00
d) Overhead charges @ 10% on (a+b+c) 36964.02
e) Contractor's profit @ 10% on (a+b+c+d) 40660.42
Rate per cum = (a+b+c+d+e)/7500 59.64
say 59.60
Case-II: Type-B (2.36mm to 180 micron)
Bitumen Emulsion (CSS-2) sqm 59.00
Unit = sqm
Taking output = 7500 sqm
a) Material
Bitumen (CSS-2) @12 Kg per 10 sqm/All in 1 t 7.5 27790 208425.00
Crushed sand or grit passing 2.36 mm sieve and cum 45 698 31410.00
retained on 180 micron applied @0.06 cum per 10
sqm
b) Labour
Mate day 0.16 356.65 57.06
Emulsion sprayer day 1 244.56 244.56
Mazdoor (Unskilled) day 10 244.56 2445.60
c) Machinery
Drum mix plant hour 6 2380.00 14280.00
Tipper 5.5 cum capacity hour 6 850.00 5100.00
Front end loader hour 6 1341.00 8046.00
Bitumen emulsion pressure distributor hour 6 954.00 5724.00
Three wheel 80-100 kN static roller hour 6 924.00 5544.00
Paver hour 6 2341.00 14046.00
d) Overhead charges @ 10% on (a+b+c) 28127.62
e) Contractor's profit @ 10% on (a+b+c+d) 32344.98
Rate per cum = (a+b+c+d+e)/7500 47.44
say 47.40
Case III:Type-C (9.5mm to 2.36mm)
Bitumen Emulsion (CSS-2) sqm 67.00
Unit = sqm
Taking output = 7500 sqm
a) Material
Bitumen (CSS-2) @12 Kg per 10 sqm/All in 1 t 6.75 27790 187582.50
Crushed stone chipping of 6.7 mm size defined cum 67.5 1041.5 70301.25
as 100% passing 9.5mm sieve and retained on
2.36 mm sieve applied @ 0.09 cum
b) Labour
Mate day 0.16 356.65 57.06
Emulsion sprayer day 1 244.56 244.56
Mazdoor (Unskilled) day 10 244.56 2445.60
c) Machinery
Hydraulic self vpropelled chip spreader hour 6 2380.00 14280.00
Tipper 5.5 cum capacity hour 6 850.00 5100.00
Front end loader hour 6 1341.00 8046.00
Bitumen emulsion pressure distributor hour 6 954.00 5724.00
Three wheel 80-100 kN static roller hour 15 924.00 13860.00
d) Overhead charges @ 10% on (a+b+c) 30764.10
e) Contractor's profit @ 10% on (a+b+c+d) 33840.51
Rate per cum = (a+b+c+d+e)/7500 49.63
say 49.60
Paved Shoulder & Interlocking Concrete Block
Pavement
17.39 Providing brick soling in earthen shoulder with
stone/best quality jhama brick, sand packed and laid to
true line and level and in panel after preparing the
subgrade including earthwork in excavation as directed
including all labour and materials and if necessary
dewatering, complete.

(a) Bricks on flat soling, sqm 3333.00


Unit = sqm
Taking output = 100 sqm
A) Sub-grade preparation cum 50 75 3750.00
E/W in Excavation cum 75 190 14250.00
B) Soling
a) Materials
(I) Jhama brick No 3900 8 31200.00
(ii) Sand cum 5 950 4750.00
b) Labour
I) Head Mason day 0.5 458.55 229.28
ii) Semi Skilled labour day 10 285.32 2853.20
(iii) Mazdoor (Unskilled) day 15 244.56 3668.40
c) Machinery
Plate Vibrator hour 6 218.00 1308.00
c) Sundries, small T&P 2% of (a) + (b) + (c) 880.18
d) Overhead charges @ 10% on (a+b+c) 4488.91
e) Contractor's profit @ 10% on (a+b+c+d) 4937.80
Rate per cum = (A + B)/100 723.16
say 723.20
(b) Bricks on edge soling, sqm 3852.00
Unit = sqm
Taking output = 100 sqm
A) Sub-grade preparation cum 50 75 3750.00
E/W in Excavation cum 125 190 23750.00
B) Soling
a) Materials
(I) Jhama brick No 5800 8 46400.00
(ii) Sand cum 6 950 5700.00
b) Labour
I) Head Mason day 0.5 458.55 229.28
ii) Semi Skilled labour day 15 285.32 4279.80
(iii) Mazdoor (Unskilled) day 24 244.56 5869.44
c) Machinery
Plate Vibrator hour 6 218.00 1308.00
c) Sundries, small T&P 2% of (a) + (b) + (c) 1275.73
d) Overhead charges @ 10% on (a+b+c) 6506.22
e) Contractor's profit @ 10% on (a+b+c+d) 7156.85
Rate per cum = (A + B)/100 1062.25
say 1062.30
(c) Stone soling of thickness 150mm. sqm 1166.00
Unit = sqm
Taking output = 100 sqm
A) Sub-grade preparation cum 50 75 3750.00
E/W in Excavation cum 150 190 28500.00
B) Soling
a) Materials
(I) Blasted stone cum 11.2 1055 11816.00
(ii) Sand cum 6 950 5700.00
b) Labour
I) Head Mason day 0.6 458.55 275.13
ii) Semi Skilled labour day 12.5 285.32 3566.50
(iii) Mazdoor (Unskilled) day 15 244.56 3668.40
c) Machinery
Plate Vibrator hour 6 218.00 1308.00
c) Sundries, small T&P 2% of (a) + (b) + (c) 526.68
d) Overhead charges @ 10% on (a+b+c) 2686.07
e) Contractor's profit @ 10% on (a+b+c+d) 2954.68
Rate per cum = (A + B)/100 647.51
say 647.50
17.40 Providing and laying Interlocking Concrete Block
Pavement (ICBP) conforming to IS:15658-2006
including all lead and lift complete as per technical
specification and as directed.
(a) 80mm thick interlocking precast blocks having
compressive strength of 40N/sq.mm. sqm 799.00
Unit = sqm
Taking output for road length 100m with shoulder
width of 2.5m = 250sqm
a) Materials
Inter-locking blocks (size = 0.22 x 0.11 = 0.0253 No 9881.42 15.5 153162.06
sqm plan area)
deduct 5% towards gaps (7658.10)
Sand in bed (30mm, 12.5% compacted) cum 9.375 950 8906.25
Sand in joints (0.008cum/sqm) cum 2.000 950 1900.00
Water for wetting of bedding sand Kl 3.000 45 135.00
b) Labour
Mason (2nd Class) day 9.75 285.32 2781.87
Mate day 1.5 356.65 534.98
Mazdoor (Unskilled) day 21 244.56 5135.76
c) Machinery
Plate Vibrator hour 3 218.00 654.00
Water tanker 6 KI capacity hour 2 440.00 880.00
d) Overhead charges @ 10% on (a+b+c) 16643.18
e) Contractor's profit @ 10% on (a+b+c+d) 18307.50
Rate per cum = (a+b+c+d+e)/250 805.53
say 805.50
(b) 100mm thick interlocking precast blocks having
compressive strength of 50N/sq.mm. sqm 1129.00
Unit = sqm
Taking output for road length 100m with shoulder
width of 2.5m = 250sqm
a) Materials
Inter-locking blocks (size = 0.22 x 0.11 = 0.0253 No 9881.42 23 227272.73
sqm plan area)
deduct 5% towards gaps (11363.64)
Sand in bed (30mm, 12.5% compacted) cum 9.375 950 8906.25
Sand in joints (0.01cum/sqm) cum 2.500 950 2375.00
Water for wetting of bedding sand Kl 3.000 45 135.00
b) Labour
Mason (2nd Class) day 9.75 285.32 2781.87
Mate day 1.5 356.65 534.98
Mazdoor (Unskilled) day 21 244.56 5135.76
c) Machinery
Plate Vibrator hour 3 218.00 654.00
Water tanker 6 KI capacity hour 2 440.00 880.00
d) Overhead charges @ 10% on (a+b+c) 23731.19
e) Contractor's profit @ 10% on (a+b+c+d) 26104.31
Rate per cum = (a+b+c+d+e)/250 1148.59
say 1148.60
(c) Providing and laying M-40 grade cement concrete
Edge block/ Edge restraints complete as per Technical
specification clause 1504. cum 10664.00
Unit = cum
Taking output 1cum
a) Materials
Cement t 0.46 7200 3312.00
Sand cum 0.43 950 408.50
40 mm aggregate cum 0.34 1500 510.00
20 mm aggregate cum 0.34 1777 604.18
10 mm aggregate cum 0.19 1510 286.90
Water for wetting of bedding sand Kl 1.000 45 45.00
b) Labour
Mason (1st Class) day 0.15 458.55 68.78
Mate day 0.1 356.65 35.67
Mazdoor (Unskilled) day 1.75 244.56 427.98
Bhisti day 0.3 285.32 85.60
c) Machinery
Concrete mixer hour 0.4 188.00 75.20
Water tanker 6 KI capacity hour 2 440.00 880.00
c) Formwork 4% of (a) + (b) + (c) 269.59
d) Overhead charges @ 10% on (a+b+c) 673.98
e) Contractor's profit @ 10% on (a+b+c+d) 768.34
Carriage of Blocks tonne.km 125 8.50 1062.50
Rate per cum = (a+b+c+d+e)/1 9514.21
say 9514.20
Miscelleneous Road Appurtenances
17.41 RCC Pipe Delineator

Providing of hume pipe delineator, 250 mm in diameter,


1250 mm high, having 25mm skin thickness filled with
earth for stability up to 5 cm from top and remaining
filled with 1:3:6 c.c.in spherical segment to prevent
percolation of water and emeded in c.c. (1:3:6) below
ground level up to a depth of 500mm, 75mm thick cc
surrounding the pipe, painted white as per approved
drawing. Each 1297.00
Unit = each
Taking output = 1000mm length of 250mm dia hume
pipe.
a) Labour
Mate day 0.020 356.65 7.13
Mazdoor day 0.250 244.56 61.14
Painter day 0.250 458.55 114.64
b) Material
RCC pipe of 250 mm dia 1.00 m high each 1.000 2160.00 2160.00
Paint litre 0.350 258.00 90.30

ii) Earth work in excavation cum 0.021 120.00 2.52


ii) Earth filling with selected soil cum 0.034 238.00 8.09
ii) Cement concrete 1:3:6 cum 0.017 5228.00 90.97
c) Overhead charges @10%on (a+b) 243.32
d) Contractor's profit @10% on (a+b+c) 267.65
Rate per drum delineator = a+b+c+d 3045.76
say 3046.00
17.42 Drum Delineator

Providing of metal drum/empty bitumen drum


delineator, 600 mm in diameter, 800 mm high, filled with
earth for stability up to 5 cm from top and remaining
filled with 1:3:6 c.c. to prevent percolation of water,
painted in circumferential strips of alternate black and
white 120 mm wide all as per IRC:SP:55-2001and
Each 346.00
drawing.
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.015 356.65 5.35
Mazdoor day 0.200 244.56 48.91
Painter day 0.250 458.55 114.64
b) Material
Steel drum 600 mm dia 0.9 m high/empty bitumen
each 1.000 90.00 90.00
drum
Paint litre 0.500 258.00 129.00
ii) Earth work in excavation cum 0.132 120.00 15.84
ii) Earth filling with selected soil cum 0.240 238.00 57.12
ii) Cement concrete 1:3:6 cum 0.0435 5228.00 227.42
c) Overhead charges @10%on (a+b) 25.89
d) Contractor's profit @10% on (a+b+c) 28.48
Rate per drum delineator = a+b+c+d 742.65
say 743.00

17.43 Pre fabricated railing :-


Providing,fitting and erecting pre fabricated railing of
STRUCTURA materials having size of 2.00x0.90M in
panels made of 25x25x2.6/40x40x2.6 vertical bars and
40x40x2.6/32x32x2.6 horizontal bars.The two end
posts of each panel are founded with M-15 cement
concrete up to a depth of 200mm with anti corrosive
primer and paint etc. complete as per approved
drawing and technical specification as directed..
metre 1319.00
Unit ----- metre
Add 5% above 2013-14 schedule: 5% 1384.95
say 1385.00

17.44 Crash Barrier :-

Providing and erecting steel rails crash barrier in


selected location with vertical post of STRUCTURA
WRS of size 113.50mm x 113.50mm x 4.80mm of
required height above the GL attached to the gusset
plate 330mm x 330mm x 25mm with nut and bolts and
embeded in cement concrete (450mm x 450mm x
750mm) in prop. 1:2:4 as per approved and technical
specification, 3.70m center to center for intermediate
bay and 3.00m for end bay, 4 nos. horizantal steel rails
of size 113.50mm x 113.50mm x 4.80mm of
STRUCTURA WRS to be fixed on the vertical posts
with a spacer channel section of size 113.50mm x
113.50mm x 4.80mm of STR-WRS including all fittings
such as Stainless Steel Hexagonal Head, SS washer &
screw head, nylon top hat washer and galvanized steel
washer including transportation & erection etc.
complete as per approved drawing.

I Four rails System


(A) 1.50m heigh above ground level meter 6909.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 7254.45
say 7254.50

(B) 1.25m heigh above ground level meter 6857.00


Unit ----- meter
Add 5% above 2013-14 schedule: 5% 7199.85
say 7199.90

II Single rail System


(A) 0.60m heigh above ground level meter 3029.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 3180.45
say 3180.50

(B) 0.75m heigh above ground level meter 3071.00


Unit ----- meter
Add 5% above 2013-14 schedule: 5% 3224.55
say 3224.60
(C) 0.75m heigh above ground level both side meter 5792.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 6081.6
say 6081.60

17.45 Wire rope safety fence Barrier: Providing & erecting 4


rope wire rope safety fence barrier consisting of 4
tensioned galvanized factory prestressed steel wire
ropes of 19mm dia. constructed of 3x7 (i.e.7 wires in a
strand and three strand in each rope) having tensile
strength of 1370 N/sqm with a minimum break load of
17.7 tons and supported by 5mm thick galvanized steel
posts of 'Z' section with a standard section of 100mm x
55mm x 5mm. One upper rope is located within a
central slot in the top of the posts and three ropes
interwoven along the adjacent posts. The ropes are
joined and tensioned by means of rigging screws and
the ends of the ropes are attached to anchors embeded
in the ground or surface mounted. The top wire shall be
930 +_30 from ground level to centre of wire and the
posts shall be placed maximum 3.2 mtrs c/c including
all end rope anchors, terminals, check ropes, tail ropes,
soft eye connecting with D-Shackle complete as per
technical specifications and as directed.

meter 4164.00
Unit ----- meter
Add 5% above 2013-14 schedule: 5% 4372.2
say 4372.20

Reinforced Earth Retaining Walls


17.46 Construction of Reinforced Earth Retaining Walls with
plain finished cruciform shaped precast concrete facing
panels in M 35 grade concrete, 18 cm thick, including
High Adherence Structural Reinforcing 40 X 5mm
section strips ( hot dip galvanised) with bearing pads,
joint fillers, tie strips, fastener and all accessories and
consumable complete as per technical specification
and drawing.
sqm 2336.00
Unit ----- sqm
Add 5% above 2013-14 schedule: 5% 2452.8
say 2452.80

17.47 Earth work including excavation, backfilling, grading


and compaction with selected backfill soil in layers in
Reinforced Earth works as per Technical specification
and drawings. cu.m. 158.00
Unit ----- cu.m.
Add 5% above 2013-14 schedule: 5% 165.9
say 165.90

17.48 Construction of PCC strips level footing (35cm X 15cm)


in M-15 grade concrete complete as per technical
specification and drawing. meter 327.60
17.49 Providing 600mm drainage bay behind RE wall with
compacted granular material as per technical
specification and drawing. cum 1197.00
Unit ----- cum
Add 5% above 2013-14 schedule: 5% 1256.85
say 1256.90

17.50 Construction of crash barrier, parapet, coping beam


with friction slab in M-30 grade concrete complete as
per technical specification and drawing. meter 1742.60
Miscelleneous Embankment Protection
17.51 Providing approved variety of vetiver plantation certified
by The Vetiver Network International (TVNI) or its
affiliate in India including pouching of tiller with selected
soil for agricultural use mixed with farmyard manure in
8”x 6” poly pouch, maintaining the pouched plants for at
least 1(one) month with application of growth promoter,
fertilizer, watering, weeding etc., dressing of the area of
plantation, planting the pouched plants as per design
approved by The Vetiver Network International (TVNI)
or its affiliate in India. (Excluding jungle clearance, earth
work in trimming, cutting, filling etc.) and Maintenance
of the vetiver plants by watering, pruning, weeding,
mulching, application of manure, fertilizer, growth
promoter etc. for 4 (four) months after completion of
plantation.

Part-1 Plantation Part metre 98.00


Unit ----- metre
Add 5% above 2013-14 schedule: 5% 102.9
say 102.90

Part-II Maintenance part metre 32.00


Unit ----- metre
Add 5% above 2013-14 schedule: 5% 33.6
say 33.60

17.52 Labour for laying apron with man size boulders by hand
packing the stone with dry stone masonry template
crosswalls to ensure regular and orderly deposition of
the full intended quality of stone in the apron including
labour for buildung these walls about one meter thick
and to the full height of the specific thockness of the
apron at interval of 30 meters all along the length of the
apron with local carriage of stone within 60 meters
complete.
cum 1166.00
Unit ----- cum
Add 0.1 above 2013-14 schedule: 10% 1282.6
say 1282.60

17.53 Stone masonry work. Uncoursed rubble masonry work


in all retaining wall, wing wall, abutement etc. in cement
mortar 1;6 withoutside face stone roughly hammer
dressed and inside (earthen side ) undressed as per
drawing and technical sopecifications including racking
out joints and curing , supplying and carriage of stone
as directed. cum 5034.00
Unit ----- cum
Add 0.1 above 2013-14 schedule: 10% 5537.4
say 5537.40
Soil Stabilization
17.54 Providing, laying, spreading and compacting available
clay soil in Sub-grade course including in situ mixing
30% Stone Dust, 70% Soil & 4% of RBI 81 product,
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with
8 to 10 tonne vibratory power roller to achieve the
desired density including all materials, labour, HOM of
machinery, etc complete as per specifications.
cum 3856.00
Unit ----- cum
Add 0.05 above 2013-14 schedule: 5% 4048.8
say 4048.80

17.55 Providing, laying, spreading and compacting available


soil (excluding clay soil) and aggregate in base course
including in situ mixing 30% Aggregate, 70% Soil &
4% of RBI 81 product, spreading in uniform layers with
motor grader on a prepared base including watering
and compacting with 8 to 10 tonne vibratory power
roller to achieve the desired density including all
materials, labour, HOM of machinery, etc complete as
per specifications.
cum 4415.00
Unit ----- cum
Add 0.05 above 2013-14 schedule: 5% 4635.75
say 4635.80

17.56 Providing, laying, spreading and compacting available


soil in base course including in situ mixing 30%
Aggregate, 20% Stone Dust, 50% Soil & 4% of RBI 81
product, spreading in uniform layers with motor grader
on a prepared base including watering and compacting
with 8 to 10 tonne vibratory power roller to achieve the
desired density including all materials, labour, HOM of
machinery, etc complete as per specifications.
cum 4676.00
Unit ----- cum
Add 0.05 above 2013-14 schedule: 5% 4909.8
say 4909.80

Miscelleneous Bridge Works


17.57 Providing and constructing temporary island for
construction of pile foundation with depth of water upto
4.0m complete as per technical specification. each 53167.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 55825.35
say 55825.40

17.58 Providing and constructing temporary island for


construction of well foundation complete as per
technical specification.
(a) For 6m dia. Well
(i) Depth of water above 1.0 m upto 2.0 m each 108765.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 114203.25
say 114203.30
(ii) Depth of water above 2.0 m upto 3.0 m each 138167.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 145075.35
say 145075.40

(iii) Depth of water above 3.0 m upto 4.0 m each 156360.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 164178
say 164178.00

(b) For 7m dia. Well


(i) Depth of water above 1.0 m upto 2.0 m each 118188.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 124097.4
say 124097.40

(ii) Depth of water above 2.0 m upto 3.0 m each 152347.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 159964.35
say 159964.40

(iii) Depth of water above 3.0 m upto 4.0 m each 184482.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 193706.1
say 193706.10

(c) For 8m dia. Well


(i) Depth of water above 1.0 m upto 2.0 m each 127196.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 133555.8
say 133555.80

(ii) Depth of water above 2.0 m upto 3.0 m each 162189.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 170298.45
say 170298.50

(iii) Depth of water above 3.0 m upto 4.0 m each 197449.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 207321.45
say 207321.50

17.59 Greasing of Bearing with ULTRATACK AP3 grease


including cleaeing of bearings with steel brush, removal
of dusts and dirt with necessary scaffolding etc.
complete as directed by the department. each 1167.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 1225.35
say 1225.40

Geo-Bags
17.60 Supplying, filling and laying in loose with Geo-textile
bags of Type-A (1.30x0.70 M) made of Geo textile non
woven fabric sheets of 400 GSM manufactured from
polyster/ polypropylene conforming to relevant ISO
standard filled with specified sand/ silt from flood plain
or adjacent char within a distance of 90 m of the work
site including excavation, filling Geo bags with sand
weighing 126.00 kg after filling, stitching the mouth of
the filled bags with polypropylene or polyster complete
as per technical specifications and as directed.

(a) With Boat Bag 272.00


Unit = each
Taking output = 100 bags
a) Labour

filling Sand/Silt, Stitching and carrying to dumping


site and laying the Bags. (As per sor WRD)

Mate day 3.000 356.65 1069.95


Mazdoor day 16.000 244.56 3912.96
b) Material
Geo textile Bag each 100.000 208.80 20880.00
c) Overhead charges @10%on (a+b) 2586.29
d) Contractor's profit @10% on (a+b+c) 2844.92
Cost of 100bags = a+b+c+d 31294.12
Rate per bag = a+b+c+d/100 312.94
say 313.00

(b) Without Boat Bag 261.00


Unit = each
Taking output = 100 bags
a) Labour

filling Sand/Silt, Stitching and carrying to dumping


site and laying the Bags. (As per sor WRD)

Mate day 3.000 356.65 1069.95


Mazdoor day 12.000 244.56 2934.72
b) Material
Geo textile Bag each 100.000 208.80 20880.00
c) Overhead charges @10%on (a+b) 2488.47
d) Contractor's profit @10% on (a+b+c) 2737.31
Cost of 100bags = a+b+c+d 30110.45
Rate per bag = a+b+c+d/100 301.10
say 301.00

17.61 Supply, Stitching and Laying of Non wooven Geo textile


Fabric sheet of 400 gsm Sqm 199.00
Unit = sqm
Taking output = 100 sqm
a) Labour
Stitching and laying the Bags. (As per sor WRD)
Mazdoor day 8.000 244.56 1956.48
b) Material
Geo textile fabric sheet Sqm 100.000 137.00 13700.00
add 20% on above for stitching fibre etc. 2740.00
c) Overhead charges @10%on (a+b) 1839.65
d) Contractor's profit @10% on (a+b+c) 2023.61
Cost of 100sqm = a+b+c+d 22259.74
Rate per sqm = a+b+c+d/100 222.60
say 223.00

17.62 Supplying, filling and laying in cages with Geo-textile


bags of Type-A (1.30x0.70 M) made of Geo textile non
woven fabric sheets of 400 GSM manufactured from
polyster/ polypropylene conforming to relevant ISO
standard filled with specified sand/ silt from flood plain
or adjacent char within a distance of 90 m of the work
site including excavation, filling Geo bags with sand
weighing 126.00 kg after filling, stitching the mouth of
the filled bags with polypropylene or polyster thread by
power driven double needle machine, stacking the
same in batches of 100, carrying the same to the
dumping site including all handling charges and local
carriage within a distance of 150m and laying properly
in cages of PVC coated G.I.Gabion box of size 1.5m x
1.5m x 0.45m complete as per technical specifications
and as directed.

(a) With Boat Cage 758.00


Unit = each
Taking output = 100 bags
a) Labour

filling Sand/Silt, Stitching and carrying to dumping


site and laying the Bags. (Containing 12 nos sand
filled bags in one cage As per sor WRD)

Mate day 45.000 356.65 16049.25


Mazdoor day 200.000 244.56 48912.00
b) Material
Geo textile Bag each 100.000 208.80 20880.00
c) Overhead charges @10%on (a+b) 8584.13
d) Contractor's profit @10% on (a+b+c) 9442.54
Cost of 100bags = a+b+c+d 103867.91
Rate per bag = a+b+c+d/100 1038.68
say 1039.00

(b) Without Boat Cage 526.00


Unit = each
Taking output = 100 bags
a) Labour
filling Sand/Silt, Stitching and carrying to dumping
site and laying the Bags. (Containing 12 nos sand
filled bags in one cage As per sor WRD)

Mate day 15.000 356.65 5349.75


Mazdoor day 125.000 244.56 30570.00
b) Material
Geo textile Bag each 100.000 208.80 20880.00
c) Overhead charges @10%on (a+b) 5679.98
d) Contractor's profit @10% on (a+b+c) 6247.97
Cost of 100bags = a+b+c+d 68727.70
Rate per bag = a+b+c+d/100 687.28
say 687.00

17.63 Earthwork in excavation in key cage of size 1.00m x


1.00m x 1.00m for anchoring geo fabrics mat including
supply and filling of geo bags (bags are filled with
sand/silt from flood plain or adjacent char within a
distance of 90 m of the work site), filling geo bags with
sand weighing 126kg after filling, stitching mouth with
polyster/ polypropylene thread by power driven double
needle machine, carrying the same to the site including
all handling charges and local carriage from a distance
of 150m complete as per technical specifications and
as directed.
Cum 3217.00
Unit = Cum
Taking output = 1cum
a) Labour
Mazdoor for Excavation day 0.380 244.56 92.93
Mazdoor for filling and laying of Geo Bags day 1.680 244.56 410.86
b) Material
Geo textile Bag (@ 12nos. Per cum) each 12.000 208.80 2505.60
c) Overhead charges @10%on (a+b) 300.94
d) Contractor's profit @10% on (a+b+c) 331.03
Cost of 1cum = a+b+c+d 3641.37
Rate per cum = a+b+c+d 3641.37
say 3641.00
17.64 Supplying, laying, fitting and fixing g-mat in doubled
layer composite geo textile fabricated to form a three
dimensional mattresses after filling sand by pump, the
upper layer of mattress being heavily woven with
polyproplyne fabric needle punched with a mixture of
U.V. stabilized green fibres and cut tape yarns (Typical
value of mass per unit area ASTM D5261) is 650g/sqm,
tensile strength (ASTMD4595)is 45kn/m, pore size
(ASTMD4751) is less than 0.35mm and UV stability
(strength retained per ASTMD4355-92 @ 500hrs is
80%) the lower layer of the mattress being
polypropyline wooven fabric, UV stabilized (Typical
value of mass per unit area (ASTM D 4595) is greater
than 80kn/m, pore size (ASTMD4751) is less than
0.35mm and UV stability (strength retained per
ASTM4355-92 @ 500hrs is 80%). The sewing thread
being of high tenacity polyster, continued parrell
stitches positioned 350mm apart with a stitch length not
exeeding 40mm anchoring by cutting trenches of 1.5m
x 1m placing the mat filling earth filled cement bags
anchorage at lower end, double locking chain stitch 3
stitch/inch including all charges complete. (Approved
rate of CWC for the FMP scheme under WRD)

Sqm 2280.00
Unit ----- Sqm
Add 0.05 above 2013-14 schedule: 5% 2394
say 2394.00

Repairing of Boat
17.65 Labour for haulding up boat and refloating the same
after repair
(a) Mar boat each 3390.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 3559.5
say 3559.50

(b) Single boat each 1688.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 1772.4
say 1772.40

17.66 Renewing rotton planks of boat with 25 mm to 38 mm


thick timber planks including supplying and fitting with
necessary nail etc. including coat tarring two coats
applied hot.
(a) With Sal planks sq.m 2494.00
Unit ----- sq.m
Add 0.05 above 2013-14 schedule: 5% 2618.7
say 2618.70

(b) With Cham or Lorul planks sq.m 2060.00


Unit ----- sq.m
Add 0.05 above 2013-14 schedule: 5% 2163
say 2163.00
17.67 Making good cracks of the joint boat with necessary
jute mixed with putty of dhuna and flat nails including
coaltarring after taking out old nails, rotten jute etc. metre 30.00
Unit ----- metre
Add 0.05 above 2013-14 schedule: 5% 31.5
say 31.50

17.68 Supplying, fitting and fixing kori (for boat) of wood of


required sizes.
(a) With Sal timber each 2552.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 2679.6
say 2679.60

(b) With cham/sundi/nageswar/gamari timber each 1802.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 1892.1
say 1892.10

17.69 Supplying sal wood helm for marboat 18cm dia 6.10m
as per direction including fixing in position and coal
tarring complete as directed.cham/nageswar wood
helm for mar boat 13cm dia. 6.10m long as per
direction including fixing in position and coal and coal
tarring as directed. each 5704.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 5989.2
say 5989.20

17.70 Supplying cham/nageswar wood helm for mar boat


13cm dia. 6.10m long as per direction including fixing in
position and coal and coal tarring as directed. each 3229.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 3390.45
say 3390.50

17.71 Renewing oars of wood plank complete as directed.


(a) Of Sal wood each 973.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 1021.65
say 1021.70

(b) Of Cham wood each 797.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 836.85
say 836.90

17.72 Supplying fitting and fixing in position koniaghosa of


required size of wood to fit exactly at boat and coal
tarring etc. complete as directed.
(a) Sal wood each 280.00
Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 294
say 294.00

(b) Cham/ Sundi/ Gamari wood each 201.00


Unit ----- each
Add 0.05 above 2013-14 schedule: 5% 211.05
say 211.10

17.73 Repariring or providing timber free board line 8cm by


5cm painted white with two coats of approved paint
complete as directed.
(a) With Sal timber metre 220.00
Unit ----- metre
Add 0.05 above 2013-14 schedule: 5% 231
say 231.00

(b) With Cham/ Sundi/ Gamari timber metre 172.00


Unit ----- metre
Add 0.05 above 2013-14 schedule: 5% 180.6
say 180.60

17.74 Refitting drop gates with necessary hinges, spikes,


bolts and nuts etc. complete up to 6 tonne mar boat. set of two 398.00
Unit ----- set of two
Add 0.05 above 2013-14 schedule: 5% 417.9
say 417.90

17.75 Refitting drop gates with necessary hinges, spikes,


bolts and nuts etc. complete above 6 tonne mar boat. set of two 559.00
Unit ----- set of two
Add 0.05 above 2013-14 schedule: 5% 586.95
say 587.00
A. Materials:-

Brush wood L/S 300


B. Labour
C. Sundaries L/S 10
cum

cum
cum

cum
cum

cum
L-12
L-13
L-18

M-131

12.1(A)(i)
3.189(a)
9.1

L-12
L-13
L-18

M-172
M-131
12.1(A)(i)
3.189(a)
9.1
L-12
L-13

M-172

L-12
L-13

M-172
L-13

M-172

L-12
L-13

M-172
L-12
L-13

M-172

L-13
L-13

M-172
Analysisof SOR (Roads) 2017-18
Chapter-18

Chapter 18
NEW TECHNOLOGY
Sr. Ref to Rate
Description Unit Quantity
No. Spec (Rs.)
17.1 Open - Graded Premix Surfacing (specially for
IRC SP: shaded areas)
100:
2014
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using Bitumen Emulsion With cold
mix Binder Ezee PC (MS) (As per IRC : SP : 100 -2014) to
required line, grade and level to serve as wearing course
on a per Technical Specification and through credible
technology partners duly licensed by CRRI.

CRRI- Cold Mix Binder Ezee PC (Medium Setting)


(specially for shaded areas)
Unit = sqm
Taking output = 900 sqm (24.3 cum)
a) Labour
Mate day 0.800 356.65
Mazdoor day 18.000 244.56
Mazdoor skilled day 2.000 356.65
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6.000 188.00
Smooth wheeled steel roller 8-10 tonne hour 6.000 924.00
c) Material
CRRI Cold Mix Binder Ezee PC (MS) Bitumen tonne 1.800 45500.00
Emulsion @ 20.00 kg per 10 sqm
Crushed stone aggregates 13.2 mm to 5.6 mm @ cum 24.300 1599.50
0.27 cum per 10 sqm
TOTAL = (a+b+c)
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Cost for 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
say

17.2 Seal coat with Cold mix Binder (specially for shaded
areas) - Providing and laying seal coat sealing the voids
in a bituminous surface laid to the specified levels grade
and cross fall using Type A,Type B and Type C as per
Technical specification clause 510.With cold mix Binder
Ezee PC (MS) (As per IRC : SP : 100 -2014)and through
IRC SP: credible technology partners duly licensed by CRRI.
100:
2014
CRRI- Cold Mix Binder Ezee PC (Medium Setting)
(specially for shaded areas)
By mechanical means
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate day 1.15 356.65
Bitumen Sprayer day 1 356.65

104 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Mazdoor (Unskilled) day 22 244.56
Mazdoor (Semi-Skilled) day 6 285.32
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6 188.00
Three wheel 80-100 kN static roller hour 2.2 924.00
c) Material
Bitumen emulsion Ezee PC medium setting @ 10.00 kg t 0.11 45500.00
per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent cum 9.9 1510.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm
Total (a+b+c) =
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d)/1100
Say
Note Since seal coat is provided immediately over the bituminous layers, Hydraulic broom for cleaning
has
Sincenotseal
been catered.
coat is required to be provided over the premix carpet on the same day, out of the 6
17.3 _ working
Construction of the
hours of HMP, 4.00 hours
Sub-Base/Base are proposed
of road pavementto by
be utilised for the premix carpet and the
making use of EVOCRETE CCL Soil Modifier
(GERMAN) technology by re-using the existing/in-situ
soil. Profiling the road to the required design standard
followed by spreading of 7% of O.P.C. 43 Grade cement
of stabilized soil (Variable depending upon soil properties) ,
then spreading 2 % EVOCRETE additive of 7 % OPC and
pulverising the cement , additive & profiled soil/pavment
material with help of Recycler/Stabilizer including
moisturing to OMC. On completion of pulverisation re-
garding, profiling to required grade/camber with motor
grader & compacting simaltaneously with 14 tonne
vibratory roller to achieve 95% degree of compaction as
directed by the Engineer-in-charge & finally irrigating the
stabilized surface for next 48 hours.

20.0cm thick Sub-Base & Base with Evocrete and


Cement etc.
Unit = Cum
Taking output = 750 Cum
a) Labour
Mate day 1.000 356.65
Mazdoor day 15.000 244.56
Mazdoor skilled day 15.000 356.65
b) Machinery
Heavy Duty Stabilizer/Recycler with moisture controlling hour 12.500 14405.00
meter@ 60cum/hour
Motor Grader 110 HP @50 cum / hour hour 12.500 2234.00
Vibratory Road Roller @ 100 cum / hour hour 7.500 1687.00

105 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Tandem Road Roller @ 30 cum / hour (considering 50% of hour 12.500 1039.00
thickness )
Water tanker 12 kl capacity hour 17.250 440.00
c) Material
Cement @ 126 kg/ cum tonne 94.500 7200.00
Evocrete at site @ 2.52 kg/ cum Kg 1890.000 630.00
Soil (Extra Lead as per schedule) cum/km
Water (For mixing during stabilization) kl 195.000 45.00
Water (Irrigating during curing) Kl 12.000 45.00
TOTAL = (a+b+c)
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Cost for 750 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/750
say
17.4 Bio Enzyme Soil Stabilizer Terrazyme under IRC
accredited new Technology
I 2503 Providing of 1st layer of Bioenyme based soil stabilised
layer to a required thickness as per manufacture design
with a existing soil, by ripping open the existing road
formation and treating it with TerraZyme in the ratio 1L for
12.6 cum soil spreading in uniform layer with motor grader
on prepared surface , mixing by mix in place method with
rotavator at OMC and compacting with smooth wheel roller
to achieve the desired density complete as per technical
specification incl all labour , equipments etc as per
direction of the Engineer -in -charge of the work. The soil
will have PI between 7 and 18% and clay % by hydrometry
should be more than 15% and less than 40%.

Unit = cum
Taking output = 300 cum
a) Material
Cost Bio Enzyme Litre 24.00 13500.00
Water KL 100.00 45.00
Cost of Soil Cum 0.00 155.00
Cost of Metal 37.5 mm to 22.5 mm Cum 0.00 1619.00
b) Labour
Mate day 0.04 356.65
Mason day 0.35 458.55
Mazdoor * day 0.75 244.56
c) Machinaries
(i) Pre TerraZyme Application
Tractor with a ripper @ 60 cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/ hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 432.00
(ii) Post TerraZyme Application
Tractor mount grader @25 cum/hr hr 12.00 431.00
Vibromax soil compactor 100 cum/hr hr 5.00 1687.00
Tractor with a ripper @ 60 cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/ hr 12.00 431.00

106 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Water tanker 6 Kl capacity hr 5.00 440.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d+e)/300
say
II Providing of 2nd layer of Bioenyme based soil stabilised
layer to a required thickness as per manufacture design
with local soil material/gravel/murram, having CBR greater
than 8% and treating it with Terrazyme in the ratio 1L for
15.0 cum soil with 25% 40mm crusher broken metal in
design mix, spreading in uniform layer with tractor grader
on prepared surface, mixing by mix in place method with
rotavator at OMC and compacting with smooth wheel roller
to achieve the desired densiality complete as per technical
specification including all labour, materials like soil and
metal, equipments etc. complete as per direction of the
Engineer-in-charge of the work. The soil will have PI
between 7 and 13% and clay % by hydrometry should be
more than 15% and less than 30%.

Unit = cum
Taking output = 300 cum
a) Material
Cost Bio Enzyme Litre 15.00 13500.00
Water KL 100.00 45.00
Cost of specified Soil 300*0.75 Cum 225.00 200.00
Cost of Metal 300*0.25 Cum 75.00 1619.00
b) Labour
Mate day 0.48 356.65
Mazdoor (Skilled) day 2.00 356.65
Mazdoor (Unskilled) day 10.00 356.65
c) Machinaries
(i) Pre TerraZyme Application
Tractor mount Grader @ 25 cum/hr hr 0.00 431.00
Vibromax soil compactor 100 cum/hr hr 0.00 1687.00
Tractor with a ripper @ 60 Cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/hr hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 440.00
(ii) Post TerraZyme Application
Tractor mount grader @ 25 cum/hr hr 12.00 431.00
Vibromax soil compactor 100 cum/hr hr 5.00 1687.00
Tractor with a ripper @ 60 cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/hr hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 440.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d+e)/300
say
17.5 Soil Stablized subbase/ base using Roadstab

107 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
I 2503 Providing of soil stabilized subase/base course by
providing,laying and spreading ordinary soil on a prepared
subgrade,palverising,adding the designed quantity of
Roadstab mixing compound adding 4% cement, mixing at
OMC,with rotavator grading with motor grader and
compacting with the road roller/vibratory roller at OMC to
acheive the desired unconfined compression strength and
to form a layer of subbase and necessary curing

Unit = cum
Taking output = 300 cum
a) Material
100% Local soil Cum 300.00 79.00
RoadstaB Q Litre 40.00 18200.00
4% Cement Tonne 24.00 7200.00
Cost of water KL 30.00 45.00
b) Labour
Mate day 9.00 356.65
Mason day 0.00 458.55
Mazdoor * day 0.00 244.56
c) Machinaries
Hydraulic Excavator 0.9/1.0 cum Hrs 4.00 1836.00
Motor Grader Hrs 6.00 2234.00
Tipper 5.5 cum/10 tonne capacity Hrs 18.18 850.00
Tractor with roatavator Hrs 12.00 431.00
Vibratory Roller Hrs 3.90 1687.00
Water Tank 6 kl Capacity (Truck mounted) Hrs 3.00 440.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.6 RBI Grade 81 Treated Base Layer
A For Selected soil having CBR 5% to 6%
I Providing, laying, spreading and compacting Soil
conforming to engineering requirement and Aggregate in
base layer including in situ mixing of 30% Aggregatesof
size 22.4 mm to 2.56 mm (for WMM as per page 154 of
Assam SOR 2016-17 for rural road & table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 20% Stone dust+46% in-situ soil (CBR 5% to 6%) + 4%
RBI Grade-81 (a soil stabilizer cum pavement material) ,
speading in uniform layers with motor grader on prepared
base including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the required
density at OMC for preparing the base layer including all
cost of materials , labour, HOM of machinery, etc. complete
as per specifications and EIC directions.

Composition 30% Aggregate + 20% Stone Dust + 46% Soil (CBR 5%


Unit =Cum
Taking Output =300 Cum
a) Material

108 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Agreegate 22.4 mm to 2.36 mm for WMM as per Cum 108.90 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (20%) Cum 69.00 700.00
In-situ Soil (CBR 5% to 6%) (46%) Cum 172.50 100.00
Quantity of RBI Grade 81 by weight (4%) Cum 25.20 35000.00
b) Labour
Mate day 0.48 356.65
Mazdoor (Skilled) (L-017) day 2.00 356.65
Mazdoor (Unskilled) (L-15) day 10.00 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity Hour 6.00 1836.00
Motor Grader Scarifier & Levelling Hour 6.00 2234.00
Single drum 10-12 tone Vibratory roller Hour 6.00 1687.00
Tractor with Rotavator and blade @ 25 cum per hour Hour 12.00 431.00

Water tanker 6 KL capacity Hour 5.00 440.00


Tipper 5.5 cum /10T , 4 trip per hour Hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
B RBI Grade-81 FOR EXISTING IN-SITU SOIL HAVING
CBR 5% TO 6%
Providing, laying, spreading and compacting including
mixing of In-situ Soil (CBR 5% to 6%), Aggregate size 22.4
mm to 2.56 mm (for WMM as per page 154 of ASSAM
SOR 2016-17 for Rural Roads and Table 400.13 &
Technocal Specification clause 406 of MORT&H 5th
Revision) and Stone Dust with Soil Stabiliser and
Pavement Material RBI Grade 81 (SRSPL), spreading in
uniform layers with motor grader on prepared sub-base /
sub-grade including watering and compacting with 10 to
12 tonne single drum vibratory roller to achieve the desired
density for preparing the Base / Sub-base layer.

Including basic cost of materials,


labour, HOM of machinary, etc. as per specifications and EIC
directions.
The rate mentioned here are exclusive of carriage
charge of Aggregates / Stone Dust / Selected Soil from quarry to
site. The carriage charge will be added to these rates to arrive at
final rate.
Various combinations of Aggregates, Stone
Dust Insitu Soil and RBI grade 81 percentages have been given.
The optimum combination would depend upon the following
factors:
1. In Situ Soil CBR and PI.

2. Traffic Catagory.
3. Distance of
Quarry from Site
For further increasing the durability of the road, out of
the combinitations as bellow the combination with higher
percentage of RBI Grade-81 should be prepared so long as
commercial viability is maintained.

109 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
I Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 30% Stone Dust + 36% In-Situ Soil (CBR 5 % to 6 %) +
4 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition: 30% Aggregate + 30% Stone Dust + 36% Soil


Unit =Cum (CBR 5% to 6%) + 4% RBI Grade 81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per Cum 108.90 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (30%) Cum 103.50 700.00
In-Situ Soil (CBR 5 % to 6 %) (36%) Cum 135.00 100.00
Quantity of RBI Grade-81 by weight (4%) MT 25.20 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2.00 356.65
Mazdoor (Unskilled) ( L-15) day 10.00 356.65
c) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 6.00 1836.00
Motor Grader Scarifier & Levelling hour 6.00 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6.00 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12.00 431.00

Water tanker 6 KL capacity hour 5.00 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

110 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
II Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 20% Stone Dust + 46% In-Situ Soil (CBR 5 % to 6 %) +
4 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition: 30% Aggregate + 20% Stone Dust + 46% Soil (CBR 5%


Unit =Cum
density = 2.1 gm/cc
Taking Output = 300 Cum
630 mt
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.90 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (20%) cum 69.00 700.00
In-Situ Soil (CBR 5 % to 6 %) (46%) cum 172.50 100.00
Quantity of RBI Grade-81 by weight (4%) MT 25.20 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2.00 356.65
Mazdoor (Unskilled) ( L-15) day 10.00 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6.00 1836.00
Motor Grader Scarifier & Levelling hour 6.00 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6.00 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12.00 431.00

Water tanker 6 KL capacity hour 5.00 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

111 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 30% Stone Dust + 36.25 % In-Situ Soil (CBR 5 % to 6
%) + 3.75 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition: 30% Aggregate + 30% Stone Dust + 36.25% Soil (CBR


Unit =Cum
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust(30%) cum 103.50 700.00
In-Situ Soil (CBR 5 % to 6 %) (36.25%) cum 135.94 100.00
Quantity of RBI Grade-81 by weight (3.75%) MT 23.625 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

112 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
IV Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 20% Stone Dust + 46.25% In-Situ Soil (CBR 5 % to 6 %)
+ 3.75 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition: 30% Aggregate + 20% Stone Dust + 46.25% Soil (CBR


Unit =Cum
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust(20%) cum 69.00 700.00
In-Situ Soil (CBR 5 % to 6 %) (46.25%) cum 173.44 100.00
Quantity of RBI Grade-81 by weight (3.75%) MT 23.625 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

113 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
V Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 30% Stone Dust + 36.5 % In-Situ Soil (CBR 5 % to 6 %)
+ 3.5 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 30% Aggregate + 30% Stone Dust + 36.5 % In-Situ Soil


Unit =Cum
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust(30%) cum 103.50 700.00
In-Situ Soil (CBR 5 % to 6 %) (36.5%) cum 136.88 100.00
Quantity of RBI Grade-81 by weight (3.5%) MT 22.05 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

114 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
VI Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 20% Stone Dust + 46.5% In-Situ Soil (CBR 5 % to 6 %)
+ 3.5 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 30% Aggregate + 20% Stone Dust + 46.5% In-Situ Soil


Unit =Cum
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust(20%) cum 69.00 700.00
In-Situ Soil (CBR 5 % to 6 %) (46.5%) cum 174.38 100.00
Quantity of RBI Grade-81 by weight (3.5%) MT 22.05 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
RBI GRADE 81 - 2%

115 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
VII Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
sub base layer including in situ mixing of 30% Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 20% Stone Dust + 48% In-Situ Soil (CBR 5 % to 6 %) +
2 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 30% Aggregate + 20% Stone Dust + 48% In-Situ Soil


Unit =Cum
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.90 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (20%) cum 69 700
In-Situ Soil (CBR 5 % to 6 %) (48%) cum 180 100
Quantity of RBI Grade-81 by weight (2%) MT 12 35000
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
C For Selected Soil Having CBR 7% to 9%
RBI GRADE -81--4%

116 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Providing , laying spreading and compacting inncluding in
situ mixing of selected soil (CBR 7% to 9%), Aggregate of
size 22.4 mm to 2.56 mm (for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 408 of MORTH 5th Revision)
& Stone Dust with Soil Stabilizer and PavementMaterial
RBI Grade 81 (SRSPL) , spreading in uniform layers with
Motor grader on a prepared subbase including watering
and compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the base
layer including basic cost of materials, labour,HOM of
machinearyetc, complete as per specification and EIC
directions.
The rates mentioned here are Exclusive of carriage
charges for Agrregate/ Stone Dust/ Setected Soil from
quarry to site . The carriage charges will be added to these
rates to arrive at final rate.
Various combinations of in-situ soil/selected soil, aggregate
and RBI percentages have been given, The optimum
combination would depend upon the following factors:
1. In-situ soil/selected soil (as applicable), CBR, and PI
2. Traffic Category
3. Distance of Quarry from site

I Providing, laying, spreading and compacting Soil


conforming to engineering requirements and Aggregate in
base course including in situ mixing of 45 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 51 % Selected Soil (CBR 7 % to 9 %) + 4 % RBI
Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with 10
to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 45 % Aggregate + 51 % Selected Soil (CBR 7 % to 9


Unit =Cum %) + 4 % RBI Grade-81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 163.35 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (45%)
Stone Dust (0%) cum 0 700.00
Selected Soil (CBR 7 % to 9 %) (51%) cum 191.25 100.00
Quantity of RBI Grade-81 by weight (4%) MT 25.2 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65

117 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
II Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 30 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 15 % Stone Dust + 51 % Selected Soil (CBR 7 % to 9
%) + 4 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 30% Aggregate+15% stone dust+ 51% Selected


Unit =Cum
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.75 700.00
Selected Soil (CBR 7 % to 9 %) (51%) cum 191.25 100.00
Quantity of RBI Grade-81 by weight (4%) MT 25.20 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)

118 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Rate per cum = (a+b+c+d)/300
say
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 45 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 51.25 % Selected Soil (CBR 7 % to 9 %) + 3.75 % RBI
Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with 10
to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 45% Aggregate+ 51.25% Soil(CBR 7%to 9%)+3.75%


Unit =Cum RBI Grade -81(SRSPL)by weight of Aggregate ,
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 163.35 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (45%)
Stone Dust (0%) cum 0 700.00
Selected Soil (CBR 7 % to 9 %) (51.25%) cum 192.19 100.00
Quantity of RBI Grade-81 by weight(3.75%) MT 23.63 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
D RBI GRADE 81-3.75%

119 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
I Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 30 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 15 % Stone Dust + 51.25 % Selected Soil (CBR 7 % to
9 %) + 3.75 % RBI Grade-81 (a soil stabilizer cum
pavement material), spreading in uniform layers with motor
grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory roller
to achieve the required density at OMC for preparing the
base Layer Including all cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions

Composition 30% Aggregate+15% stone dust +51.25% Soil(CBR


Unit =Cum 7%to 9%)+3.75% RBI Grade -81(SRSPL)by weight of
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.75 700.00
Selected Soil (CBR 7 % to 9 %) (51.25%) cum 192.18 100.00
Quantity of RBI Grade-81 by weight(3.75%) MT 23.63 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

120 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
II Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 45 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 51.5 % Selected Soil (CBR 7 % to 9 %) + 3.5 % RBI
Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with 10
to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 45% Aggregate+ 51.5% Selected soil (CBR7%to 9%)


Unit =Cum +3.5% RBI Grade -81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 163.35 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (45%)
Stone Dust(0%) cum 0 700.00
Selected Soil (CBR 7 % to 9 %)(51.50%) cum 193.13 100.00
Quantity of RBI Grade-81 by weight(3.5%) MT 22.05 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
RBI GRADE 81-3.5%

121 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 30 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 15 % Stone Dust + 51.5 % Selected Soil (CBR 7 % to 9
%) + 3.5 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 30% Aggregate+15% Stone Dust+51.5% Selected


Unit =Cum Soil(CBR 7% to 9%)+3.5% RBI Grade -81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.75 700.00
Selected Soil (CBR 7 % to 9 %) (51.50%) cum 193.13 100.00
Quantity of RBI Grade-81 by weight (3.5%) MT 22.05 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
RB! GRADE 81-2%

122 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
IV Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 30 % Aggregate of
size 22.4 mm to 2.56 mm ( for WMM as per page 154 of
ASSAM SOR 2016-17 for rural roads & Table 400.13 &
technical specification clause 406 of MORTH 5th Revision)
+ 15 % Stone Dust + 53 % Selected Soil (CBR 7 % to 9
%) + 2 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 30% Aggregate+ 15% Stone Dust+53% Soil(CBR7%to


Unit =Cum 9%)+2% RBI Grade -81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as per cum 108.9 1440.50
Table 400.13 & Technical Specification Clause 406 of
MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.75 700.00
Selected Soil (CBR 7 % to 9 %)(53%) cum 198.75 100.00
Quantity of RBI Grade-81 by weight(2%) MT 12 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
E 40% AGGREGATE 20MM + SOIL (CBR 7% TO 9%) + RBI
GRADE-81(SRSPL)

123 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
I Providing,laying,spreading and compacting including in
situ mixing of selected soil aggregate of size 20mm with
soil stabiliser and pavemebt material RBI Grade-81
(SRSPL), spreading in uniform layers with Motor grader on
a prepared sub base icluding watering and compacting
with 10 to 12 tonne single drum vibratory roller to achieve
the desired density for preparing the base layer. Including
basic cost of materials, labour, HOM machinery,etc
complete as per specifications and EIC directions. The
rates mentioned here are exclusive of carriage charges for
aggregate/stone dust/selected soil from quarry site.
Various combinations of in-situ soil/selected soil(as
applicable),aggregate and RBI percentages have been
given. The optimum combination would depend upon the
following factors : 1. In situ soil/selected soil
(as applicable) CBR and PI
2. Traffic category

3. Distance of quarry from site

II Providing, laying, spreading and compacting Soil


conforming to engineering requirements and Aggregate in
base course including in situ mixing of 40% Aggregate (20
mm) + 56% Soil (CBR 7% to 9%) with 4 % RBI Grade-81
(a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required density
at OMC for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

40% Aggregate (20 mm) + 56% Soil


Composition
(CBR 7 % to 9 %) + 4 % RBI Grade-81
Unit =Cum
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum 145.20 1777.00
Soil (CBR 7 % to 9 %) (56%) cum 210.00 155.00
Quantity of RBI Grade-81 by weight(4%) MT 25.20 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

124 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 40% Aggregate (20
mm) + 56.25% Soil (CBR 7% to 9%) with 3.75 % RBI
Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with 10
to 12 tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of machinery,
etc complete as per specifications and EIC directions

Composition 40% aggregate 20 mm + 56.25% selected soil


Unit =Cum
(CBR 7% to 9%) + 3.75% RBI Grade-81 (SRSPL)
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum 145.20 1777.00
Soil (CBR 7 % to 9 %) (56.25%) cum 210.94 155.00
Quantity of RBI Grade-81 by weight (3.75%) MT 23.63 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
IV Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
base course including in situ mixing of 40% Aggregate (20
mm) + 56.5% Soil (CBR 7% to 9%) with 3.5 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required density
at OMC for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

Composition 40% aggregate 20 mm + 56.5% selected soil (CBR 7%


Unit =Cum to 9%) + 3.5% RBI Grade-81 (SRSPL) (by weight of
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum 145.20 1777.00
Soil (CBR 7 % to 9 %)(56.50%) cum 211.88 155.00

125 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Quantity of RBI Grade-81 by weight (3.5%) MT 22.05 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
V Providing, laying, spreading and compacting Soil
conforming to engineering requirements and Aggregate in
sub base layer including in situ mixing of 40% Aggregate
(20 mm) + 58% Soil (CBR 7% to 9%) with 2% RBI Grade-
81 (a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required density
at OMC for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as per
specifications and EIC directions

Composition 40% aggregate 20 mm + 58% selected soil (CBR 7% to


Unit =Cum 9%) + 2% RBI Grade-81 (SRSPL) (by weight of
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum 145.2 1777.00
Soil (CBR 7 % to 9 %)(58.00%) cum 217.5 155.00
Quantity of RBI Grade-81 by weight (2%) MT 12 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

126 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
17.7 Providing, laying, spreading and compacting including in
situ mixing of In-Situ 94 % Soil + 4 % PI Reducing Agent
with 2 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared including watering and compacting with 10 to
12 tonne single drum vibratory roller to achieve the desired
density for preparing the Sub Base/Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions.

Composition 94 % Soil + 4 % PI Reducing Agent + 2 % RBI Grade-


Unit =Cum 81
Taking Output =300 Cum
a) Material
Soil (94%) cum 352.5 155.00
PI Reducing Agent (4%) MT 21.6 7000.00
Quantity of RBI Grade-81 by weight (2%) MT 10.8 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.8 Providing, laying, spreading and compacting including in
situ mixing of In-Situ 93.5 % Soil + 4 % PI Reducing Agent
with 2.5 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor grader on
a prepared including watering and compacting with 10 to
12 tonne single drum vibratory roller to achieve the desired
density for preparing the Sub Base/Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions.

Composition 93.5 % Soil + 4 % PI Reducing Agent + 2.5 % RBI


Unit =Cum Grade-81
Taking Output =300 Cum
a) Material
Soil (93.5%) cum 350.63 155.00
PI Reducing Agent (4%) MT 21.60 7000.00
Quantity of RBI Grade-81 by weight (2.5%) MT 13.50 35000.00
b) Labour

127 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.9 Providing, laying, spreading and compacting including in
situ mixing of 98 % In-Situ Soil (PI < = 10) with 2 % RBI
Grade-81 (Soil Stabiliser and Pavement Material ),
spreading in uniform layers with Motor grader on a
prepared surface including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
desired density for preparing the Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions .

Composition: 98 % In-Situ Soil (PI <= 10) + 2 % RBI Grade-81


Unit =Cum
Taking Output =300 Cum
a) Material
In-Situ Soil (PI <= 10) (98%) cum 367.50 155.00
Quantity of RBI Grade-81 by weight (2%) MT 10.80 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say

128 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
17.10 Providing, laying, spreading and compacting including in
situ mixing of 97.5 % In-Situ Soil (PI < = 10) with 2.5 %
RBI Grade-81 (Soil Stabiliser and Pavement Material ),
spreading in uniform layers with Motor grader on a
prepared surface including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
desired density for preparing the Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions .

Composition: 97.5 % In-Situ Soil (PI <= 10) + 2.5 % RBI Grade-81
Unit =Cum
Taking Output =300 Cum
a) Material
In-Situ Soil (PI <= 10) (97.5%) cum 365.63 155.00
Quantity of RBI Grade-81 by weight (2.5%) MT 13.50 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.11 Providing, laying, spreading and compacting including in
situ mixing of 98 % Selected Soil (PI < = 10) with 2 % RBI
Grade-81 (Soil Stabiliser and Pavement Material ),
spreading in uniform layers with Motor grader on a
prepared surface including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve the
desired density for preparing the Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions .

Composition 98 % Selected Soil (PI <= 10) + 2 % RBI Grade-81


Unit =Cum
Taking Output =300 Cum
a) Material
Selected Soil (PI <= 10) (98%) cum 367.5 155.00
Quantity of RBI Grade-81 by weight (2%) MT 10.8 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 356.65
Mazdoor (Unskilled) ( L-15) day 10 356.65
c) Machinaries

129 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1836.00
Motor Grader Scarifier & Levelling hour 6 2234.00
Single Drum 10-12 tonne Vibratory roller hour 6 1687.00
Tractor with Rotavator and blade @25 cum per hour hour 12 431.00

Water tanker 6 KL capacity hour 5 440.00


Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.12 ZYCOSOIL NANO TECHNOLOGY
A Water Proofing
I Waterproofing on top compacted ( as per relevant MoRD
specification) sub Grade soil base, shoulders with
Organosilane Nanotechnology & nano acrylic co-polymer
with water (<1000 ppm TDS) in the ratio of 1 kg
Organosilane Nanotechnology:1 kg nano acrylic co-
polymer :200 liter water spray @ 3 liter /sqm in two spray
applications (1.5 liter + 1.5 liter) as per direction of the
Engineer-in-charge.

Unit = Sqm
Taking output = 7000 Sqm
a) Material
Organosilane Nanotechnology Kg 105 550.00
Nano acrylic co-polymer Kg 105 180.00
Water kl 21 45.00
b) Labour
mazdoor(Unskilled) day 3 356.65
mazdoor(Skilled) day 2 356.65
c) Machinery
Three wheel 80-100 KN Vibratory compactor hour 2.56 1687.00
Water tanker 6 kl capacity truck mounted (4 trips per hour 7.00 440.00
day)
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/7000
say

130 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
II Stabilized Sub-base / Base: Providing, Laying,
Spreading and Compacting in-situ/borrow area soil of CBR
>5% mixed with / without 30% crushed aggregate /
muruum / GSB Grade 1 as per mix design.
Application:
(1) Rip and loosen soil with excavator / tractor operated
ripper and scarify with tractor operated rotavator upto
depth of 200 mm. Mix aggregates as per mix design.
(2) Apply 1 kg /cum organosilane Nanotechnology mixed
in OMC water (<1000 ppm TDS) on loose soil. Scarify the
treated and allow it to dry.
(2) Spread Cement 3% by weight of soil on the silane
treated and dry soil.
(3) Apply 1 kg/cum of nano acrylic Co-Polymer mixed in
OMC water (<1000 ppm TDS), on the above treated soil
mixed with cement. Scarify and grade the soil.
(4) Spread 13.2 and down size aggregates on the graded
soil surface to form 20-25 mm thick soil-aggregate layer.
(5).Compact the stabilized soil-aggregate base with 8 to 10
tonne vibratory roller to achieve stone embedded layer
with the desired density.
(6) Waterproof the top of the compacted stabilized base
with organosilane & nano acrylic Polymer in the ratio of 1
kg organosilane :1 kg nano acrylic Co-Polymer : 200 liter
water (<1000 ppm TDS) @ 3ltrs/sqm in two spray
applications (1.5 ltrs. + 1.5 ltrs.).
Rates include all material, labour, hire charges of
machinery etc. as per MoRD specifications & direction of
Engineer-in-Charge.

Unit = cum
Taking output = 300 cum
a) Material
Cement % = 3% T 16.65 7200.00
Organosilane Nanotechnology Kg 325.23 550.00
Nano acrylic co- polymer Kg 325.23 180.00
Water kl 160.45 45.00
Soil cum 240 170.00
Aggregate (As per SOR Rate - For 53 mm maximum cum 90 1104.00
size - below 5.6 mm / Muruum / GSB Graded
material /Aggregate - Crushable type such as
moorum or Gravel for Grading I - quantity 30% of
total volume
Graded chips 13.2 mm down (AP SOR Rate of 10 cum 30 1280.00
mm chips)
b) Labour
Mate day 0.48 356.65
Mazdoor (Skilled) day 2 356.65
Mazdoor (Unskilled) day 14.65 356.65
c) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 100 hour 3 1836.00
cum / hour
Tipper 5.5 cum with 10t capacity (4 trips per hour) hour 13.64 850.00

131 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Dozer D-50 / Grader for spreading @ 200 cum per hour 1.5 1965.00
hour
Tractor with Mount Grader @ 25 cum per hour hour 8 440.00
Three wheel 80-100 kN vibratory roller @ 100 cum 3 1687.00
hour
per hour
Water tanker 6 kl capacity truck mounted (4 trip/day, 6.685 440.00
day
Rs 535/hr)
Tractor with Rotavator @ 25 cum per hour hour 12 431.00
Tractor with Ripper @ 60 cum per hour hour 5 440.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
III Prime Coat (with silane Nanotechnology)
(i) Low porosity
Prime Coat : Preparing and applying of water soluble
organo silane nanotechnology (for bitumen emulsion
application, IRC approved) with cationic bitumen emulsion
CSS1 and water (<1000 ppm TDS) in the ratio of 1 kg
organo silane : 100 kg cationic bitumen emulsion CSS1 :
200 liter water . Mixing & Spraying : Take 1 kg of organo
silane nanotechnology and add in 200 liter water while
filling water in tanker/drum and then add 100 kg cationic
bitumen emulsion under circulation. Mix the solution
completely. Spray the solution @ 1 liter per sqm on
compacted stone base. Rates including all materials,
labour, hire Charges of machery etc. complete as per
MoRD specifications & direction of Engineer-in-Charge.

Unit = sqm
Taking output = 1750 sqm
a) Material
Cationic Bitumen emulsion (CSS-1) = 1kg/sqm t 0.583 39183.00
Water kl 1.17 45.00
Organo silane nanotechnology kg 5.833 1200.00
b) Labour
Mate day 0.04 356.65
Mazdoor (Skilled) day 1 356.65
c) Machinery
Hydraulic broom with tractor @ 1250 sqm per hour hour 1.40 337.00

Air compressor 210 cfm hour 1.40 435.00


Bitumen emulsion pressure distributor @ 1750 sqm hour 1.00 717.00
per hour
Water tanker 6 kl capacity truck mounted hour 0.50 440.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/1750
say

132 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
17.13 20mm thick Open-Graded Premix Carpet using
Bituminous (penetration grade) Binder Using
Nanotechnology.( Providing, laying and rolling of open-
graded premix carpet of 20 mm thickness composed of
13.2 mm to 5.6 mm stone aggregates using S-65
penetration grade bitumen mixed with silane
nanotechnology @ 0.1% by weight of bitumen S-65 grade
@ 14.6 kg/10 sqm to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable hot mix plant, laying and
rolling with a three wheel 80-100 kN static roller capacity,
finished to required level and grades to be followed by seal
coat of Type D as per Technical Specification Clause 508
of MoRD and as per direction of Engineer-in-Charge.)

Case -II By Mechanical Means


Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Material
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum 108 1599.5
cum per 10 sqm
Organosilane @ 0.1% by weight of S-90 Bitumen kg 5.84 1350
Bitumen (S-90) @ 14.60 kg per 10 sqm t 5.84 31681
b) Labour
Mate day 0.52 356.65
Mazdoor (Unskilled) day 10 356.65
Mazdoor (Semi-Skilled) day 3 356.65
c) Machinery
HMP 30/40 t per hour hour 6 8287.5
Electric generator set 125 KVA hour 6 2073
Front end loader 1 cum bucket capacity hour 6 1341
Tipper 5.5 10 t capacity hour 3.64 850
Paver finisher hour 6 853
Three wheel 80-100 kN static roller hour 16 924
d) Overhead charges @ 10% on (a+b+c )
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/4000
say
17.14 Seal Coat( with Nanotechnology) (Providing and laying
seal coat sealing the voids in a bituminous surface laid to
the specified levels, grade and cross fall using Type D as
per Technical Specification Clause 510 of MORD with S-
65grade bitumen mixed with organosilane nanotechnology
@ 0.1% by weight of S-65 bitumen binder laid as per
direction of Engineer-in-Charge.)

A By Mechanical Means
I Case -3 : Type C: Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Material
Bitumen (S-90) t 4.88 31681
Organosilane @ 0.1% by weight of S-65 Bitumen kg 4.88 1350

133 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Crushed Stone Chipping 6.7 mm size 100% passing cum 67.5 1510
11.2 mm and retained on 2.36 mm
a) Labour
Mate day 0.2 356.65
Mazdoor (Unskilled) day 5 356.65
c) Machinery
Front end loader 1cum bucket capacity hour 6 1341.00
Hydraulic self propelled chip spreader hour 6 2380.00
Bitumen pressure distributor hour 6 954.00
Three wheel 80-100 kN Static Roller hour 15 924.00
Tipper 5.5 cum/10 ton capacity hour 6 850.00
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/7500
say
17.15 EVOCRETE TECHNOLOGY
A Stabilization/soil binding of in-situ soil of sub-
base/base course using EvocreteCCL soil stabilizer
(Construction of Sub-Base/Base of road pavement by
making use of EVOCRETE CCL Soil Modifier (GERMAN)
technology by re-using the existing/in-situ soil. Profiling the
road to the required design standard followed by spreading
of 7% of O.P.C. 43 Grade cement of stabilized soil
(Variable depending upon soil properties) , then spreading
2 % EVOCRETE additive of 7 % OPC and pulverising the
cement , additive & profiled soil/pavment material with help
of Recycler/Stabilizer including moisturing to OMC. On
completion of pulverisation re-garding, profiling to required
grade/camber with motor grader & compacting
simaltaneously with 14 tonne vibratory roller to achieve
95% degree of compaction as directed by the Engineer-in-
charge & finally irrigating the stabilized surface for next 48
hours)

I 20.0cm thick Sub-Base & Base with Evocrete and


Cement etc.
Unit = cum
Taking output = 750 Cum
a) Material
Cement @ 126 kg/ cum( Density 1800 gm , cement tonne 94.5 7200
7% as per laboratory analysis = 126 kg/cum)
Evocrete at site @ 2.52 kg/ cum (considering 2% Kg 1890 630
quantity of cement, as per laboratory advice &
results)
Water (For mixing during stabilization ) kl 195 45
Water (Irrigating during curing ) kl 12 45
b) Labour
Mate No. 1 356.65
Mazdoor (Unskilled) No. 15 356.65
Mazdoor (skilled) No. 15 356.65
c) Machinery

134 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Heavy Duty Stabilizer/Recycler with moisture hour 12.5 14405.00
controlling meter@ 60cum/hour (for in -situ
stabilization using existing material/soil with evocrete
soil modifier)
Motor Grader 110 HP @50 cum / hour (for cambering hour 12.5 2234.00
and super elevation)
Vibratory Road Roller @ 100 cum / hour (for extreme hour 7.5 1687.00
compaction)
Tandem Road Roller @ 30 cum / hour (considering hour 12.5 1039.00
50% of thickness ) (for achieving smooth surface)

Water tanker 12 kl capacity ( for mixing with soil + hour 17.25 440.00
cement + additive + curing)
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/750
say
17.16 Cell Filled Concrete Pavement
I Construction of plastic cell filled cement concrete
pavement, thickness 100mm (as per design), over a
prepared sub base, with 53 grade Ordinary Portland
Cement(OPC) or any other type as per Clause 1501.2.4
M30 (Grade), coarse and fine aggregates conforming to IS
: 2386, mixing in a concrete mixer of not less than 0.2 cum
capacity and appropiate weigh batcher using approved mix
design (As per IRC:44-2008), laid in the cells made of high
density polythyne sheets of thickness 0.22mm to about
0.25mm,side 150mm and depth 100mm of approximate
weight of 1250 kg for a road of 3.75m wide and 1.00km ,
putting iron spike of 200mm long at the end corners of the
cells and using nylon threads passing through the cells 10
mm below the top of the cells, in approved fixed side
formwork (steel channe, wedges, steel plates including
levelling the formwork as per drawing),maitaining camber
of about 3 to3.5%, spreading the concrete with sholvels,
rakes, compacted using needle, scareed and plate
vibrators and finished in continuous operation, curing of
concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per
drawing and Technical Specification of Cell filled Concrete
Pavement Published by NRRDA

135 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
a Rate analysis is being carried out for Cell filled concrete
pavement of 3.75m and 25m in width and length. As per
the requirement of DIY on cell filled concrete block, the
following are the requirements for a pavement of 3.75m
and 25m in width and length that can be constructed in
one day:
*200 micron plastic sheet-1 kg=28 meter long of 10cm
width-(1.75 sq.m/kg-53.57 Kg for 3.75mx25m)
*Labour approximately
*Male workers 20
Female workers 7
Mason 4
1 number concrete mixer
Plate or screed vibrator - 1 no.
Mechanical trowelling - 1 no.
Max. 25meter length(of width 3.75meter) can be laid in a
day (about 10 Cum of CC)

Taking output =25x3.75= 93.75 sqm


unit=sqm
a) Material
Crushed stone coarse aggregates ( Grading will be cum 8.44 1500.00
as per Clause 1501.2.4.1 (Table 1500.1) of
specifications @ 0.90 cum/cum of concrete (25 mm &
12.5 mm blending))
Sand (As per IS:383 and conforming to Clause cum 4.22 950.00
1500.2.4.2 @ 0.45 cum/cum of concrete)
Cement ( 310 kg/cum of concrete) tonne 2.906 7200.00
Plastic cell (In full surface area ) Sqm 93.75 102.00
Curing compound (0.33 litre per sqm) litre 30.938 214.00
Water for curing Kl 2.4 45.00
b) Labour
Mason (1st class) No 4 458.55
Mazdoor (Unskilled) No 7 356.65
Mazdoor (Skilled) No 20 356.65
c) Machinery
Concrete mixer of one cum capacity (One mixer) with hr 8 188.00
weigh batcher and suitable capacity calibrated water
tank for 8 hrs working period
Plate vibrator hr 3 218.00
Water tanker 6 kl capacity hr 1 440.00
Formwork 3% of (a+b+c)
d) Overhead charges @ 10% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Rate per cum = (a+b+c+d)/93.75
say

17.17 TENAX 3D GRID TECHNOLOGY

136 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
I Supplying and laying of Polypropylene extruded Geogrid
with a minimum stiffness (modulus) at 0.5% strain
according to ISO 10319 should be 350x550 Kn/m with
apparaent coefficient of friction soil/geosynthetics
accroding to EN 13738 must be atleast 1.70(us/gsy) at 10
KPa load and with a min transversal rib thickness of 2.5
mm and longitudinal rib thickness of 3.6 mm. Aperture of
geogrid should be 30mm x 30 mm. Geogrid should not be
made of bonding of strands or punching and stretched
sheets

Output= 1sqm
Unit = Sqm
Tenax 3 D Grid S
a) Material
Ex Italy Vigao Italy sqm 1 67.12
Freight from Italy to India sqm 1 12.96
Indian Custom Duty @30 percent sqm 1 30.02
Freight from Kolkata to Guwahati sqm 1 10.00
Cost of U-pins sqm 1 1.40
b) Labour
Skilled No 0.01 356.65
Unskilled labour No 0.02 244.56
c) Overhead charges @ 10% on (a+b )
d) Contractor's profit @ 10% on (a+b+c)
Rate per cum = (a+b+c)
say
17.18 517 Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the cent
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 356.65
Mazdoor day 10.000 244.56
Mazdoor skilled day 2.000 356.65
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 685.00
Mechanical broom @ 1250 sqm per hour hour 1.280 337.00
Air compressor 250 cfm hour 1.280 435.00
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 954.00
Hot mix plant 100-120 TPH producing an average of hour 3.000 22823.00
75 tonnes per hour
Electric generator set 250 KVA hour 3.000 1500.00
Front end loader 1.00 cum bucket capacity hour 3.000 1341.00
Tipper 5.5 cum capacity hour 18.000 850.00
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 924.00
Vibratory roller 8 tonnes hour 3.00x0.65* 1687.00
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 1039.00
c) Material

137 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and
balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ tonne 1.987 32627.00
60 per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = tonne 7.728 32627.00
193.2 x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 =
185.47 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440 1619.00
25 - 10 mm @ 15 per cent cum 18.550 1827.00
10- 5 mm @ 20 per cent cum 24.730 1510.00
Below 5 mm @40 per cent cum 49.460 1104.00
Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne 5.520 7200.00
tonne
c) Overhead charges @ 10% on (a+b )
d) Contractor's profit @ 10% on (a+b+c)
Cost for 120 cum of DBM = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
say
Although the total rolling time is only 4 hours as per norms,
all the three rollers have to be available at site for 3 hours
each to match with the output of re-cycling plant. To cater
for their idling time, these have been multiplied with a
factor of 0.6
17.19 Protective coatings to the structures,
equipments and machine parts with
performance guarantee for 3 years.
I
Application cost of two part highbuild 100% solid
content system of Cyclophat polyamino based
KRAYON KI30021 COROGARD to give protective
coating to the substract by giving good bonding to the
intermediate coat of Krayon KI 30031 RUST
CONVERTOR coat giving the cured coat of
crosslinked protective coating from rust , corrosion
and weathering effect including cost of material,
labour, scafolding, cleaning over application of one
part primer fron three part system and two part primer
from three part system Krayon KI 30031 RUST
CONVERTOR PRIMER and consumable complete
as directed by the Engineer-incharge and conforming
quality as per IS / IRC Specifications.

Unit = sqm

138 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Sr. Ref to Rate


Description Unit Quantity
No. Spec (Rs.)
Taking output = 10 sqm
a) Labour
Mate day 0.065 356.65
Painter day 0.800 458.55
Mazdoor day 0.450 244.56
b) Material
i) Providing & fixing Scaffolding up to 9.00 m height of
Sqm 10.000 22.00
structure
ii) Consumable and Cleaning of structures Sqm 10.000 40.00
iii) Material cost KI Krayon KI 30031 RUST
Sqm 1.780 390.00
CONVERTOR PRIMER single part
iv) Material cost two parts KI Krayon KI 30031 RUST 590.00
Sqm 2.500
CONVERTOR PRIMER single part
v) Material cost of two part highbuild 100% solid
content system of Cyclophat polyamino based
KRAYON KI30021 COROGARD to give protective
coating to the substrate by giving good bonding to
kg 2.940 820.00
the intermediate coat of Krayon KI 30031 RUST
CONVERTOR coat giving the cured coat of
crosslinked protective coating from rust , corrosion
and weathering effect.
c) Overhead charges @ 10% on (a+b )
d) Contractor's profit @ 10% on (a+b+c)
Cost for 10 sqm = a+b+c
Rate per sqm= (a+b+c)/10
say

139 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Chapter 18
NEW TECHNOLOGY
Amount
(Rs.)

285.32
4402.08
713.30

1128.00
5544.00

81900.00

38867.85

132840.55
13284.06
13284.06
159408.66
177.12
177.00 sqm

410.15
356.65

140 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
5380.32
1711.92

1128.00
2032.80

5005.00

14949.00

30973.84
3097.38
3097.38
37168.61
33.79
34.00 sqm

356.65
3668.40
5349.75

180062.50

27925.00
12652.50

141 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
12987.50

7590.00

680400.00
1190700.00

8775.00
540.00
2131007.30
213100.73
213100.73
2557208.76
3409.61
3410.00 cum

324000.00
4500.00

14.27
160.49
183.42

2200.00
5172.00
2160.00

5172.00
8435.00
2200.00
5172.00

142 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
2200.00
36156.92
39772.61
1458.33
1458.00 cum

202500.00
4500.00
45000.00
121425.00

171.19
713.30
3566.50

0.00
0.00
2200.00
5172.00
2200.00

5172.00
8435.00
2200.00
5172.00
2200.00
41062.70
45168.97
1656.20
1656.00 cum

143 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

23700.00
728000.00
172800.00
1350.00

3209.85
0.00
0.00

7344.00
13404.00
15453.00
5172.00
6579.30
1320.00
97833.22
107616.54
3945.94
3946.00 cum

30% Aggregate + 20% Stone Dust + 46% Soil (CBR 5%

144 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
156870.45

48300.00
17250.00
882000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
116237.94
127861.74
4688.26
4688.00 cum

145 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 30% Stone Dust + 36% Soil


(CBR 5% to 6%) + 4% RBI Grade 81

156870.45

72450.00
13500.00
882000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11590.91
118277.64
130105.40
4770.53
4771.00 cum

146 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 20% Stone Dust + 46% Soil (CBR 5%

156870.45

48300.00
17250.00
882000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11590.91
116237.64
127861.40
4688.25
4688.00 cum

147 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 30% Stone Dust + 36.25% Soil (CBR

156870.45

72450.00
13594.00
826875.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
112774.84
124052.33
4548.59
4549.00 cum

148 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 20% Stone Dust + 46.25% Soil (CBR

156870.45

48300.00
17344.00
826875.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
110734.84
121808.33
4466.31
4466.00 cum

149 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 30% Stone Dust + 36.5 % In-Situ Soil

156870.45

72450.00
13688.00
771750.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
107271.74
117998.92
4326.63
4327.00 cum

150 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 20% Stone Dust + 46.5% In-Situ Soil

156870.45

48300.00
17438.00
771750.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
105231.74
115754.92
4244.35
4244.00 cum

151 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate + 20% Stone Dust + 48% In-Situ Soil

156870.45

48300
18000
420000

171.192
713.3
3566.5

11016
13404
10122
5172

2200
11594
70112.94
77124.24
2827.89
2828.00 cum

152 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

45 % Aggregate + 51 % Selected Soil (CBR 7 % to 9


%) + 4 % RBI Grade-81

235305.68

0
19125
882000

171.192

153 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
713.3
3566.5

11016
13404
10122
5172

2200
11594.00
119438.97
131382.86
4817.37
4817.00 cum

30% Aggregate+15% stone dust+ 51% Selected

156870.45

36225.00
19125.00
882000.00

171.19
713.30
3566.50

11016
13404
10122
5172

2200
11594.00
115217.94
126739.74

154 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
4647.12
4647.00 cum

45% Aggregate+ 51.25% Soil(CBR 7%to 9%)+3.75%


RBI Grade -81(SRSPL)by weight of Aggregate ,

235305.68

0.00
19218.75
826875.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
113935.84
125329.43
4595.41
4595.00 cum

155 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate+15% stone dust +51.25% Soil(CBR


7%to 9%)+3.75% RBI Grade -81(SRSPL)by weight of

156870.45

36225.00
19218.00
827050.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
109732.24
120705.47
4425.87
4426.00 cum

156 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

45% Aggregate+ 51.5% Selected soil (CBR7%to 9%)


+3.5% RBI Grade -81

235305.68

0.00
19312.50
771750.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
108432.72
119275.99
4373.45
4373.00 cum

157 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate+15% Stone Dust+51.5% Selected


Soil(CBR 7% to 9%)+3.5% RBI Grade -81

156870.45

36225.00
19312.50
771750.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
104211.69
114632.86
4203.20
4203.00 cum

158 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

30% Aggregate+ 15% Stone Dust+53% Soil(CBR7%to


9%)+2% RBI Grade -81

156870.45

36225.00
19875.00
420000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
69092.94
76002.24
2786.75
2787.00 cum

159 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

40% Aggregate (20 mm) + 56% Soil


(CBR 7 % to 9 %) + 4 % RBI Grade-81

258020.40
32550.00
882000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
123052.94
135358.23
4963.14
4963.00 cum

160 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

40% aggregate 20 mm + 56.25% selected soil


(CBR 7% to 9%) + 3.75% RBI Grade-81 (SRSPL)

258020.40
32695.31
826875.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
117554.97
129310.47
4741.38
4741.00 cum

40% aggregate 20 mm + 56.5% selected soil (CBR 7%


to 9%) + 3.5% RBI Grade-81 (SRSPL) (by weight of

258020.40
32840.63

161 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
771750.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
112057.00
123262.70
4519.63
4520.00 cum

40% aggregate 20 mm + 58% selected soil (CBR 7% to


9%) + 2% RBI Grade-81 (SRSPL) (by weight of

258020.4
33712.5
420000

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
76969.19
84666.11
3104.42
3104.00 cum

162 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

94 % Soil + 4 % PI Reducing Agent + 2 % RBI Grade-


81

54637.50
151200.00
378000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
64179.65
70597.61
2588.58
2589.00 cum

93.5 % Soil + 4 % PI Reducing Agent + 2.5 % RBI


Grade-81

54346.88
151200.00
472500.00

163 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
73600.59
80960.65
2968.56
2969.00 cum

98 % In-Situ Soil (PI <= 10) + 2 % RBI Grade-81

56962.50
378000.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
49292.15
54221.36
1988.12
1988.00 cum

164 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

97.5 % In-Situ Soil (PI <= 10) + 2.5 % RBI Grade-81

56671.88
472500.00

171.19
713.30
3566.50

11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
58713.09
64584.40
2368.09
2368.00 cum

98 % Selected Soil (PI <= 10) + 2 % RBI Grade-81

56962.50
378000.00

171.19
713.30
3566.50

165 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
11016.00
13404.00
10122.00
5172.00

2200.00
11594.00
49292.15
54221.36
1988.12
1988.00 cum

57750.00
18900.00
945.00

1069.95
713.30

4318.72
3080.00

8677.70
9545.47
15.00
15.00 sqm

166 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

119880.00
178876.50
58541.40
7220.25
40800.00
99360.00

38400.00

171.19
713.30
5224.92

5508.00

11594.00

167 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
2947.50

3520.00
5061.00

2941.40

5172.00
2200.00
58813.15
64694.46
2372.13
2372.00 cum

22843.69
52.65
6999.60

14.27
356.65

471.80

609.00
717.00

220.00
3228.47
3551.31
22.32
22.00 sqm

168 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

172746.00

7884.00
185017.04

185.46
3566.50
1069.95

49725.00
12438.00
8046.00
3094.00
5118.00
14784.00
46367.39
51004.13
140.26
140.00 sqm

154603.28
6588.00

169 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
101925.00

71.33
1783.25

8046.00
14280.00
5724.00
13860.00
5100.00
31198.09
34317.89
50.33
50.00 sqm

680400.00

1190700.00

8775.00
540.00

356.65
5349.75
5349.75

170 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)
180062.50

27925.00

12652.50

12987.50

7590.00

213268.87
234595.75
3440.74
3441.00 cum

171 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

12660.00

4009.00

20923.20
9562.50
6620.73
108.00

1834.20
2496.55
7133.00

1504.00

654.00
440.00
2038.36
6998.35
7698.19
903.25
903.00 sqm

172 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

67.12
12.96
30.02
10.00
1.40

3.57
4.89
13.00
14.30
157.25
157.00 sqm

171.19
2445.60
713.30

4110.00
431.36
556.80
868.14
68469.00

4500.00
4023.00
15300.00
1801.80
3289.65
2026.05

173 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

64836.37

252141.46

46044.36
33890.85
37342.30
54603.84
39744.00

63730.91
63730.91
764770.89
6373.09
6373.00 cum

174 of 959
Analysisof SOR (Roads) 2017-18
Chapter-18

Amount
(Rs.)

23.18
366.84
110.05

220.00
400.00
694.20

1475.00

2410.80

570.01
570.01
7801.99
780.20
780.00 sqm

175 of 959
17 Miscelloneous Item

Preamble
17.1 17.1 Cold weather Bamboo Bridge
17.2 17.2 Construction of Temporary Bamboo Bridge.
17.3 17.3 Bamboo Foot Bridge
17.4 17.4 Driving Sal Piles 25cm to 30cm dia
17.5 17.5 Driving Non Sal Piles 25cm to 30cm dia
17.6 17.6 Sal wood Work
17.7 17.7 Non Sal wood Work
17.8 17.8 Timber Beam and Bearing Beam
17.9 17.9 Sal Wood Log Beam
,17.10 17.10 Non Sal Timber Beam and Bearing Beam
17.11 Guard Post
17.11 17.12 Labour for Scarfing and joining Piles
17.12 17.13 Labour for taking out old Piles
17.13 17.14 Labour for Dismentalling all members of Timber Bridge
17.14 17.15 Labour for Driving Piles
17.15 17.16 Labour for fitting and fixing RSJ beam,C.I.Saddle etc.
17.16 Labour for fitting and fixing RSJ beam, Old C.I.Saddle
17.17 etc.
17.17 17.18 Labour for making and fixing MS FI straps and cleats.
17.18 17.19 Supplying Fitting and fixing "U' shaped flat iron strap
17.19 17.20 Labour for fitting Woodwork
17.20 17.21 Labour for fitting and fixing log Beam
17.21 Labour for taking out old woodwork of Bridge and
17.22 refitting
17.22 17.23 Labour for taking out old logbeam of Bridge and refitting
17.23 Single Bamboo spur and Palasiding with 2nd class
17.24 Bamboo.
17.24 Single Bamboo spur and Palasiding with 1st class
17.25 Bamboo.
17.25 17.26 Bamboo spur'A" Type
17.26 17.27 Bamboo spur'"A"Type with 1st class Bamboo
17.27 17.28 Close Bamboo Toe walling
17.28 17.29 Double Timber spur with two rows
17.29 17.30 Filling up hollows of Timber Spur
,17.30 17.31 Split Bamboo wooven lining
17.31 Supplying fitting and fixing bamboo pegs in hollows of
17.32 spur
17.32 17.33 R.C.C. Guard post
17.34 Jungle Wood Guard post
17.33 17.35 Kilometer Post
17.34 17.36 Pile Shoes
17.35 17.37 Earthwork in filling in Guide Bundh
17.36 17.38 Labour for Hauling Boat
17.37 17.39 Renewing Rotten planks of Boat
17.38 17.40 Making good of cracks in Boat
,17.39 17.41 Fitting and fixing of Kori.
17.40 17.42 Supplying Sal wood Helm
17.41 17.43 Supplying Non Sal Helm
17.42 17.44 Renewing Oar
17.43 17.45 Supplying Koniagosha
17.44 17.46 Repairing and providing Free Board
17.45 17.47 Refitting Drop Gates upto 6 ton
17.46 17.48 Refitting Drop Gates above 6 ton
17.47 17.49 Providing Steel Truss of Structural B.U.G.
17.48 17.50 Earth work by headload in filling Embankment
17.49 17.51 Earthwork in core of Embankment
,17.50 17.52 Earthwork in subgrade and shoulder
17.51 17.53 Labour for laying apron with mansize Boulder
17.52 17.54 Stone Masonary work
17.53 17.55 Labour for spreading Gravel/Granular Material
17.54 17.56 Construction of Temporary Island
17.55 17.57 R.C.C.Pipe Delineator
17.56 17.58 Drum Delineator
17'.57 17.59 Paved Shoulder
17.58 17.60 Prefabricated Railing
17.59 17.61 Crash Barrier
17.60 17.62 Construction of Reinforced Earth Retaining wall
17.61 17.63 Construction of P.C.C. Strip level Footing
17.62 17.64 Providing 600mm drainage bay behind R.E
17.63 17.65 Greasing of Bearing
17.64 17.66 Providing approved variety of Vetiver
17.65 Closegraded Premix surfacing with cationic Bitumen
17.67 Emulsion
17.66 17.68 Seal coat with Emulsion
17.67 17.69 Providing Interlocking Concrete Block Pavement
17.68 17.70 Wire rope safety Fence Barrier
17.69 17.71 Geo Bags
17.70 17.72 Supply and Dumping of Geo Bags in Loose
17.71
17.73 Supplying,Laying Non wooven Geo Textile Fabric Sheet
17.72 Supplying and Dumping of Geo Bags in Cages (with
17.74 Boat)
17.73 17.75 Earthwork in Excavation in Key Cage
17.74 17.76 Supply and Laying of G-Mat

Construction Base of Road Pavement by use of


17.75 17.77 Evocrate

17.76 17.78 Rope safety Fence Barrier


17.77 17.79 Soil Stabilization-Clay Soil in Subgrade using RBI-81
17.78 17.80 Excluding Clay Soil in Base course using RBI-81
17.79 17.81 With available soil in Base Course using RBI-81

Usage Rates of Plants and Machinery


Labour
Materials

18.1 Open - Graded Premix Surfacing (specially for shaded areas)


18.2 Seal coat with Cold mix Binder (specially for shaded areas)With cold mix Binder Ezee PC
18.3 Sub-Base/Base with EVOCRETE CCL Soil Modifier (GERMAN) technology
18.4 Bio Enzyme Soil Stabilizer Terrazyme under IRC accredited new Technology
18.5 Soil Stablized subbase/ base using Roadstab
18.6 RBI Grade 81 Treated Base Layer
18.7 Providing, laying, spreading and compacting including in situ mixing of In-Situ 94 % Soil
18.8 Providing, laying, spreading and compacting including in situ mixing of In-Situ 93.5 % So
18.9 Providing, laying, spreading and compacting including in situ mixing of 98 % In-Situ Soil
18.1 Providing, laying, spreading and compacting including in situ mixing of 97.5 % In-Situ So
18.11 Providing, laying, spreading and compacting including in situ mixing of 98 % Selected So
18.12 ZYCOSOIL NANO TECHNOLOGY
18.13 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade) Binder U
18.14 Bitumen (S-90): Seal Coat( with Nanotechnology)
18.15 EVOCRETE TECHNOLOGY
18.16 Cell Filled Concrete Pavement
18.17 TENAX 3D GRID TECHNOLOGY
18.18 Recycling of Bituminous Pavement with Central Recycling Plant
18.19 Protective coatings to the structures, equipments and machine parts with performance g
as)With cold mix Binder Ezee PC (MS)
RMAN) technology
ted new Technology

situ mixing of In-Situ 94 % Soil + 4 % PI Reducing Agent with 2 % RBI Grade-81


situ mixing of In-Situ 93.5 % Soil + 4 % PI Reducing Agent with 2.5 % RBI Grade-81
situ mixing of 98 % In-Situ Soil (PI < = 10) with 2 % RBI Grade-81
situ mixing of 97.5 % In-Situ Soil (PI < = 10) with 2.5 % RBI Grade-81
situ mixing of 98 % Selected Soil (PI < = 10) with 2 % RBI Grade-81
us (penetration grade) Binder Using Nanotechnology

achine parts with performance guarantee for 3 years.

Das könnte Ihnen auch gefallen