Maintenance check list

Model: Frequency
Factory serial number: 1st
2nd 3rd
maintenance maintenance maintenance
Customer: service service service
Date:
N° Cycles
Service engineer signature
Activity
Clean the sterilization chamber very well □ □ □
Check, clean or evenly change the fill water filter. □ □ □
Verify the quality of feed water (for machines with internal steam generator). □ □ □
Verify the integrity of electrical connections □ □ □
Verify connections in the electric panel: tight the terminals with special attention to the power cable. □ □ □
Verify electrical connections, taking care to the supply tension of every electrical device. □ □ □
Verify the efficiency of all manometers (Pressure gauges). □ □ □
Verify the relationship between pressure gauges and operator panel. □ □ □
Verify the efficiency of the printer. □ □ □
Verify the efficiently and the integrity of the door opening/closing devices (belt included). □ □ □
Verify, clean and evenly replace the steam generator water level probe. □ □ □
Verify the correct functioning of the pumps □ □ □
Verify and the visual level of the steam generator (if it's present). □ □ □
Verify the resistance gaskets integrity of the electric steam generator (if present). □ □ □
Verify current consumption of the resistances of the electric steam generator (if present). □ □ □
If it needed, replace. □ □ □
Control the steam generator chamber (if present). □
if necessary, remove calcium deposits from the □
Verify electric steam generator resistance fuses (if present) □ □ □
if it necessary, replace them. □ □ □
Verify and clean the steam traps. □
If it needed replace them. □
Verify the temperature switch of water saving container (if present). □ □ □
If it needed replace the switch. □ □ □
Verify the temperature switch of the steam generator (if present). □ □ □
If it needed replace the switch. □ □ □
Verify the functioning of the door safety device of the doors. □ □ □
Verify pressure switched. □ □ □
If it needed calibration or substitution. □ □ □
Verify the intervention of opening/closing door micro switches. □ □ □
Verify tri clamp gaskets. □ □ □
Verify the efficiency of check valves. □ □ □
CV 24 □ □ □
If it needed, replace: CV 25 □ □ □
CV 80 □ □ □
Verify the efficiency of pneumatic valves. □ □ □
KV 24 □ □ □
KV 25 □ □ □
KV 31 □ □ □
KV 32 □ □ □
KV 40 □ □ □
KV 52 □ □ □
If it needed, replace:
KV 70 □ □ □
KV 71 □ □ □
KV 74 □ □ □
KV 80 □ □ □
KV90 □ □ □
KV 91 □ □ □
Check no leaks on the safety valves □ □ □
I/O Test □ □ □
Replace air filter. □ □ □
Replace door gaskets. □ □ □
Replace tri clamps gaskets. □
Replace door belt. □
Probes calibration □
Transducer calibration □