Sie sind auf Seite 1von 3

s e g me n t s / t e c hni c a l

Continuing
innovation
in segmentally
lined tunnels
The last 40 years the tunnelling industry has seen significant changes in the
technologies the industry has adopted and how it now operates. We often reflect on
both the past and the future and the authors thought it would be good to stimulate
industry wide discussion by sharing our views on where we collectively believe our
industry is heading. In a recent publication we discussed some of the emergent
technologies in TBM tunnelling and segmental linings in particular

Anthony Harding Mike King


Anthony Harding is the Global Technology Leader for Tunnels Mike has worked all over the world on a range of projects, and
at CH2M. He has a particular interest in segmental linings is currently Head of Underground Construction on Crossrail

T
he changes the tunnelling industry has witnessed Malcolm Chappell
in the last 40 years have been huge. Some important Malcolm is a consultant and director of Ozengi. He spent 7
examples of these changes are presented in Table years with CH2M as director of tunnelling in the Pacific region
1. Have all these changes been for the better? In the main
yes, but on a personal front the authors miss the hand drive
tunnels, visibility of the ground, and the challenge of a break
up. These tunnels were a great learning ground for young
miners and engineers alike.
The welcome push for safety (which has increased enormously
in recent years) reduces the exposure of younger engineers to
such situations, and one side effect of this improvement may
be that our industry could see these skills lost forever. The loss
of such skills will place increasing demands on technology
to provide the improvements in cost, time (productivity) and
safety that the industry seeks in the years to come.
The changes that we have already seen in the industry
have relied heavily on new technologies. These are, of course,
technologies that are now widely accepted and used. However,
it is easy to forget that there would have been a time when this
was not the case. In particular, the successful implementation
of these technologies could only come about because of the
commitment and diligence of designer, client, and contractor
alike.
This is one thing that has not changed over the years. The
implementation of new technologies still involves overcoming
significant technical challenges, and the attendant risk to the
projects that use them for the first time. Technologies that
have been proposed for use in TBM tunnelling today will be
subject to the same challenges. The remainder of this paper
will, through the presentation of some examples, illustrate
both the technical obstacles to the successful implementation Open face excavation with shield at Stanstead Airport

www.tunnelsonline.info September 2015 | Tunnels | 31


t e c hni c a l / s e g m en t s s e g m en t s / t e c hni c a l

of new solutions, but also some ways ■■ Integral segment protection for conveyance of aggressive direction the energy markets take.
in which these challenges might be fluids The solution to both these problems lies with the supply
overcome. ■■ Resisting internal pressures with single pass solutions chain. Where the raw ingredients are in short supply it is
unlikely that geopolymer will be cost effective due to simple
New technologies for Each of these could probably be discussed in detail economics. Therefore attempting to use geopolymer for the
segmental linings in a single article, but this article focusses on just three first time in such a location is less likely to be successful.
It is easy to build a long list of technologies: geopolymer concrete, single pass pressure Where the supply is sufficient the critical hurdle to overcome is
emergent technologies that may see tunnels, and intelligent segments. achieving consistent quality using a by-product with apparent
widespread use in ten or more year’s negligible quality control. This is an area where the segment
time. Some examples pertaining to Geopolymer concrete precast plant has a significant advantage over other projects: a
segmental linings and TBM tunnelling The manufacture of conventional concrete is responsible for requirement for a high volume of binder delivered consistently
include: over five per cent of the world’s CO2 emissions. Around 90 over a reasonable period of time. Indeed, the authors have
per cent of these emissions come from the production of spoken to two geopolymer specialists who have indicated that
■■ Plain concrete segments Portland Cement (OPC). Geopolymer concrete replaces all the they would be willing to set up the supply chain to ensure
■■ Automated ring erection OPC with industrial by-products like slag and fly ash, and can provision of binder of the required quality. They believe that
■■ Accurate performance monitoring to realistically achieve reductions in CO2 emissions of 70 per this would be a profitable venture given the concrete volumes
feedback into design methods cent for delivered segments. Despite research demonstrating typical of a tunnel project of 5-10km.
■■ Energy recovery segments (ground the applicability of geopolymer for segments (Wimpenny Therefore by engaging specialists in a role where they
source and in-tunnel heat recovery) and Chappell, “Fiber-reinforced geopolymer concrete – an can take the risk (and share in the reward) by being party to Above: A and satisfy the operations criteria.
■■ Improvements in analysis to reduce innovative material for tunnel segments”, RETC June 2013) it is the contract could help overcome the main obstacles to the segmental pipe While there are examples of single
the need for testing still yet to be used within a project context. adoption of geopolymer. in North America pass solutions being used to resist
■■ Hexagonal linings for soft ground While some of the obstacles to its adoption undoubtedly modest internal pressures, there is
tunnels with curves stem from lack of understanding of the product there are some Single pass pressure tunnels Below: The Gold significant interest in extending the
■■ Fixtures/methods that facilitate technical challenges. Firstly, geopolymer does require a slightly The traditional approach to tunnels where the internal Coast de- reach of such solutions to allow their use
internal structures construction and higher quality of cementitious material than conventional pressure exceeds the external restraint is to excavate and salination plant at higher internal pressures (up to 2 bars
tunnel fit-out concrete. This means that suppliers would have to implement provide initial support to the tunnel prior to installing a in Queensland. net pressure and beyond). While special
■■ Geopolymer concrete more stringent quality control to achieve the required quality. secondary lining that resists the internal pressure. Such The first steel bolted-plate joints or post-tensioned
■■ Omitting the bolts with reliance on Uncertainty as to whether this could be achieved in a cost secondary linings may be reinforced concrete, steel, or other fibre reinforced systems can be adopted there are
dowels and segment alignment/ effective manner could create risk to a project, particularly one materials, with selection determined by the agressivity of the concrete tunnel concerns that they can be more difficult
location systems only that uses it for the first time. water/ground, the length of tunnel, and the magnitude of the in Australia to install, which introduces constraints
■■ Real-time comprehensive automated Secondly, the materials typically used for geopolymer internal pressure. on tunnel erection as well as requiring
quality control (slag, fly ash, silica fume) are in short supply in some parts of However, significant savings can be made on both cost additional activities in the tunnel behind
■■ Intelligent segments the world, and its adoption will be highly influenced by the and schedule if a single pass solution can be made to work the TBM. For this reason there has

Table 1. Significant developments in tunnelling


40 years ago Today Benefits
610mm (2ft) wide panelled rings (reflecting solid concrete segments 1.2 to 2.0m wide Fewer segments and longer rings means less
cast iron segments) time spent erecting rings
Shields and simple erectors Tunnel Boring Machines with highly sophisti- Increased safety, speed and accuracy
cated hydraulic systems
Compressed air widely used Compressed air seldom used and avoided if Increased safety
possible
Caulking the joints for waterproofing High quality elastomeric gaskets which can Much drier tunnels
now be cast in
Predominately hand mined. Almost exclusively mechanised Improved safety
Through-the-flange bolts. Curved bolts, Spear bolts, dowels or omitted Improved erection times, more hydraulically
altogether efficient, improved durability.
Plain concrete or conventionally reinforced Steel fibre reinforced segments widely used. Reduced costs and improved durability
segments Some use of macro-synthetic fibres.
Dense, low cover reinforcement for fire Micro-synthetic fibres in segments or spalling Reduced cost and improved durability
protection, or secondary linings protection in a fire
Grouting through ports in the segments Tail shield grouting instantaneous with Reduced settlements and less potential for
advance leakage through grout ports
Alignment control using string lines & plane Lasers, Total-Stations and computerised Improved accuracy
checks sequencing
Straight rings with packers for alignment Tapered linings; Universal rings Improved watertightness
control
Basic concrete mixes Improved mix design from better understand- Higher strength mixes for challenging load
ing of concrete technology cases
Static casting systems with concrete/timber Steel moulds using carrousels and steam Increased production and more accurate
moulds curing segments
Source: Authors

32 | Tunnels | September 2015 www.tunnelsonline.info www.tunnelsonline.info September 2015 | Tunnels | 33


t e c hni c a l / s e g m en t s s e g m en t s / t e c hni c a l

recently been attention on using high owners/maintainers of tunnels.


capacity conventional bolts and dowels This is not a straightforward task
to resist tension, with some projects also across a few projects or owners, but
looking at post tensioned rings. will likely require broader industry
Both bolts and dowels are able to engagement.
resist tension, although the mechanisms The authors believe that tunnel
differ. Bolts resist tension directly, while societies around the world are ideally
dowels transfer tension forces between positioned to take this challenge.
rings, as described in Harding and
Chappell [2015]. However, there are a Conclusions and
number of issues with both bolts and expectations
dowels: The changes in the tunnelling
industry in recent decades, and TBM
■■ Durability tunnelling in particular, have been
■■ Consequences of failure could be substantial. The developments have
significant resulted from new technologies whose
■■ Securing serviceability requirements implementation has often involved the
taking of calculated risks by project
Durability is not a great concern teams. The taking of such risks will
for dowels, for which the steel core is inevitably be a part of the future
usually encapsulated in a thick plastic development of technologies in the
coating. However, for bolts traditional industry.
steel is vulnerable to corrosion and thus The number of potential technologies
durability can be difficult to assure for Above: A typical verified. Where coatings are applied to bolts this could identified in the field of segmental
the 100 year design life often specified panelled include impact and adverse installation tests to verify linings alone is substantial. Many of
for such assets. Plastic coatings exist segment tunnel performance. these technologies have obstacles to
that will provide the required durability almost certainly ■■ The consequences of failure should be carefully examined their application. While obstacles may be
provided they are not damaged upon built by hand; and risk assessed. Where risks remain high a redundant political, time related, or a simple lack
installation, but it is almost impossible no gaskets, no system using bolts and dowels may provide the level of of knowledge, ultimately the technical
to be certain that such damage does not tapers; solid assurance needed. obstacles will see a new technology
occur. block key bar ■■ Careful design of the serviceability state must be stand or fall.
The seriousness of this issue is reinforcement undertaken, considering the possible effects of the joint When one thinks of the risk of
exacerbated by the fact that the opening and gasket relaxation leading to water egress or adopting a new technology, technical
consequences of failure can be severe. water/soil ingress after an internal pressure event. uncertainties combined with unknown
We have experience of over a hundred practical difficulties are invariably the
years of concrete tunnel linings and this All three of the above require braod tunnelling expertise sources of most of the risk.
provides confidence that we understand to be brought to the design process to help identify all This paper has, through three
the modes of failure and can design for the possible risks, and a rigorous quality control process examples examined some ways in which
them. Furthermore, we also understand implemented by the contractor in order to ensure that the these risks could be mitigated, including:
the signs of overstress and would completed tunnel functions effectively.
reasonably expect to pick those signs up 1. Engaging specialists within the
during inspection of the lining. However, Intelligent segments supply chain and allow them to
deterioration of either bolts or dowels The issue of ‘intelligent structures’ that monitor themselves collaboratively demonstrate that they
would not be apparent upon inspection, has been discussed in the construction industry for some time. can secure the benefits to the project.
and a failure could occur at very short In other industries – such as building plant, automotive and If this can be done with a backup
notice. aerospace – the concept is much more mature. Machinery is plan in place then the risk to the
So a higher degree of certainty of equipped with sensors that monitor performance and help project can almost be eliminated.
design is required. The same is true of identify when maintenance is required – and also when it is 2. Bring the right specialists to the table
damage upon installation. not. The problems with such systems are considerable: Above: A in sufficient numbers to ensure that
As well as securing the above Inspection and maintenance of tunnel structures can be segmentally as many of the potential risks as
capacities it is also important to ensure difficult, as outlined in Harding and Chappell [2015], and is ■■ The systems are currently expensive, making the life cycle lined shaft in possible are identified and mitigated.
that serviceability requirements are met. often not implemented by infrastructure maintainers, so the cost difficult to demonstrate. London, UK 3. Recognise existing shortcomings
For a typical dowel a few millimetres benefits of such a technology could be significant. ■■ There is uncertainty over the life span of some systems and of knowledge in the industry and
of movement at least is required to their susceptibility to damage, compared to that of the promote research that fills the gaps.
mobilise the load in the dowels. When design life of a modern tunnel structure. It is crucial that practitioners are
you consider the combined impact of ■■ Obtaining and interpreting data can be relatively expensive involved in this process to ensure that
this displacement with the dowel recess with large upfront costs for equipment research actually addresses the day-
positional tolerance, and the gasket ■■ It is not always clear what aspects of the tunnel would need to-day problems that the industry
groove tolerances, high relaxation of to be monitored to assess good or bad performance. faces.
the gasket can result, and the increased
working ranges can be difficult to design If the first three problems are to be overcome then it will This list is certainly not exhaustive.
for. most likely be through technological developments that have Nevertheless it does show that, as an
These problems require a systematic a wider application than just tunnels, such as developments in industry, we can manage the risks, and
approach: Above: power sources, wi-fi technology and others. However, defining ensure that improvements to segmental
High capacity how structures perform in service, and how we might actually linings continue at the same pace as
■■ The durability must be exhaustively shear dowel monitor this, is a task that requires inputs from designers and they have in recent decades

34 | Tunnels | September 2015 www.tunnelsonline.info www.tunnelsonline.info September 2015 | Tunnels | 35

Das könnte Ihnen auch gefallen