Project ID Contract Title Responsible Manager

Replacement Works at Jabel Haffet Pumping


N-15063 & N-16297 Adil
Station

Consultancy services for water transmission


N-16307 Adil
scheme of unit III and unit V pumping station

Replacement Works at UAN-B, TAW A2


N-11547 & N-14510.1 Pumping Station & Submarine Pipelines Adil
Crossing UAN and Maqta Channel

MDEC Compliant Installations at the


Connection and Interface Points in Al Ain
N-14244.1 Adil
Region
N-15603 Consultancy Services
Award Date: 21.01.2018
Contract Amount: AED 4,799,322.00
Consultant: ARCADIS Consulting Middle East

N-16297 Construction Contract


01.08.2018 - BL approved by TC
Tender Floated on 14.02.2019
Closing Date 17.03.2019
Closing Date extended to 24.04.2019
Supply negotiated discount for the offered tenders
29.04.2019 Technical Bid opening
Currently the tender is under Technical Evaluation

N-11547 Consultancy Services


Award Date: 11.04.2013
Contract Amount: AED 9,771,613.00
Consultant: AECOM Middle East Limited
VO1 (Cost impact) AED 22,618.48
Revised Contract Value AED 9,998,231.48

N-16297 Construction Contract


04.04.2018 - BL approved by TC
Tender Floated on 09.12.2018
Closing Date 06.01.2019
Closing Date extended to 27.01.2019
2nd Closing Date Extension to 10-02-2019
3rd Closing Date Extension to 20-02-2019
4th Closing Date Extension to 27-02-2019
5th Closing Date Extension to 31-03-2019
Bid closed on 31.03.2018 with only (1) Bid recieved
TC approved case study to proceed with one bidder on 17.04.2019
Technical offere opened on 22-04-2019
Currently the tender is under Technical Evaluation

LOA was issued on 22 Feb 2018


The Project was handed over officially to WPMD on 08.03.2008.
Execution under progress
Progressing as scheduled
Slightly behind schedule
waiting for Liwa NOC work
Outstation issue with ADDC resolved
SIM cards issue with SEWA & FEWA to be resolved
Project in delay
18.03.2018: Published in March Newspaper advertisement. EOI sent to bidders, closing date is Sunday 25.03.2018.
04-04-2018 BL approved by TC.
03.05.2018: AECOM wants confirmation on the additinal cost before submitting the tender documents. Therefore, Supply a
04.07.2018: Waiting for site visit findings.
18.07.2018: As per Projects letter to Consultant, scope needs some deletion.
05.08.2018: MOM for consultant additional cost is signed, waiting for tender documents.
06.09.2018: As per the meeting with AECOM, tender document will be ready in less than 2 weeks.
Consultant did not complete submission of the tender documents to projects yet (expected by second week of october)
29.10.2018 Final Tender docs recived from consultant and it is under review
30.10.2018 Reviewed and comments sent to user department.
01.11.2018 All comments are passed to consultants. Waiting for final Document
25.11.2018 Projects approved TD and sent to Supply for floating
09.12.2018: Tender floated. Closing date is 06.01.2019.
18-12-2018 Pre-bid Meeting done, only 2 companies attended
20-12-2018 Received PTC 1
24-12-2018 Response to PTC 1
24-12-2018 Received PTC 2
26-12-2018 Received PTC 3
26-12-2018 PTC 1 forwarded to all bidders
27-12-2018 EU approved time extension for 3 weeks from 06-01-2019 and site visits to be rescheduled
27-12-2018 Request to extend forwarded to HOC for approval
27-12-2018 HOC approved, revised bid closing date on 27-01-2019
23-01-2019 Bid closing date extended to 10-02-2019
30&31-01-2019 Site visit done by bidders
07-02-2019 bid closing date extended to 20-02-2019
19-02-2019 bid closing date extended to 27-02-2019
20-02-2019 Addendum No.1 sent to all bidders, changed the SOW, deleted 2 BOQ Lines and attached Drawings