RfT#201xxxxxxx Section 00 01 10

Project No. <Insert #> TABLE OF CONTENTS


<Insert Project Title> PAGE 1 OF 7

Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract

00 01 01 Title Page
Map
Receipt Confirmation Form
00 01 10 Table of Contents

Refer to UBC Financial Operations or UBC Properties Trust for Division 00 documents.

Division 01 General Requirements

01 00 00 General Requirements ........................................................................................... 1 – 6


01 05 00 Construction Site Security...................................................................................... 1 – 2
01 11 00 Summary of Work .................................................................................................. 1 – 6
01 14 00 Work Restrictions .................................................................................................. 1 – 4
01 21 00 Allowances ........................................................................................................... 1 only
01 26 00 Contract Modification Procedures ........................................................................ 1 only
01 29 00 Payment Procedures ........................................................................................... 1 only
01 31 00 Project Management and Coordination ................................................................. 1 – 3
01 32 16 Construction Progress Schedule ........................................................................... 1 – 3
01 33 00 Submittal Procedures ............................................................................................ 1 – 3
01 35 05 UBC Policies, Work Procedures, and Forms ...................................................... 1 only
01 35 16 Alteration Project Procedures ................................................................................ 1 – 2
01 35 29 Healthy, Safety, and Emergency Response Procedures ....................................... 1 – 3
01 35 43 Environmental Procedures .................................................................................... 1 – 4
01 35 43.13 Environmental Procedures for Hazardous Materials ............................................. 1 – 5
01 41 00 Regulatory Requirements ...................................................................................... 1 – 2
01 45 00 Quality Control ....................................................................................................... 1 – 3
01 51 00 Temporary Facilities and Controls ......................................................................... 1 – 5
01 60 00 Ergonomics Requirements .................................................................................... 1 – 5
01 74 19 Construction Waste Management and Disposal ................................................... 1 – 8
01 77 00 Closeout Procedures ............................................................................................. 1 – 6
01 78 23 Operation and Maintenance Data ........................................................................ 1 – 25
01 78 36 Warranties ........................................................................................................... 1 only
01 78 39 Project Record Documents .................................................................................. 1 – 19
01 78 45 Maintenance Materials ......................................................................................... 1 only
01 79 00 Demonstration and Training .................................................................................. 1 – 5
01 91 00 Commissioning .................................................................................................... 1 – 19
01 92 00 Monitoring Based Commissioning ....................................................................... 1 – 12

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>
RfT#201xxxxxxx Section 00 01 10
Project No. <Insert #> TABLE OF CONTENTS
<Insert Project Title> PAGE 2 OF 7

Division 02 Existing Conditions

02 41 00 Demolition .............................................................................................................. 1 – 3

Division 03 Concrete

03 00 00 Concrete ............................................................................................................. 1 only


03 33 00 Architectural Concrete ......................................................................................... 1 only

Division 04 Masonry

04 05 23 Masonry Accessories ............................................................................................. 1 – 2

Division 05 Metals

05 00 00 Metals .................................................................................................................. 1 only


05 50 00 Metal Fabrications................................................................................................ 1 only

Division 06 Wood, Plastics, and Composites

06 00 10 Wood Structures – General Requirements............................................................ 1 – 2


06 10 00 Rough Carpentry.................................................................................................... 1 – 2
06 40 00 Architectural Woodwork ......................................................................................... 1 – 4

Division 07 Thermal and Moisture Protection

07 00 10 Building Envelope – General Requirements .......................................................... 1 – 3


07 10 00 Dampproofing and Waterproofing ......................................................................... 1 – 3
07 21 00 Thermal Insulation ................................................................................................. 1 – 2
07 25 00 Weather Barriers.................................................................................................... 1 – 3
07 40 00 Cladding ................................................................................................................. 1 – 2
07 50 00 Membrane Roofing ................................................................................................ 1 – 7
07 55 63 Vegetated Protected Membrane Roofing ............................................................ 1 only
07 61 00 Sheet Metal Roofing .............................................................................................. 1 – 2
07 62 00 Sheet Metal Flashing and Trim .............................................................................. 1 – 2
07 72 00 Roof Accessories ................................................................................................. 1 only
07 84 00 Firestopping ........................................................................................................... 1 – 2
07 92 00 Joint Sealants ........................................................................................................ 1 – 2

Division 08 Openings

08 00 10 Openings – General Requirements ....................................................................... 1 – 5


08 11 00 Metal Doors and Frames ....................................................................................... 1 – 2
08 14 00 Wood Doors ........................................................................................................... 1 – 2
08 41 13 Aluminum–Framed Entrances and Storefronts ..................................................... 1 – 4

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>
RfT#201xxxxxxx Section 00 01 10
Project No. <Insert #> TABLE OF CONTENTS
<Insert Project Title> PAGE 3 OF 7

08 44 13 Glazed Aluminum Curtain Walls ............................................................................ 1 – 4


08 50 00 Windows ................................................................................................................ 1 – 3
08 71 00 Door Hardware....................................................................................................... 1 – 7
08 80 00 Glazing ................................................................................................................... 1 – 3

Division 09 Finishes

09 00 10 Finishes – General Requirements ......................................................................... 1 – 4


09 21 16 Gypsum Board Assemblies ................................................................................... 1 – 2
09 22 16 Non–Structural Metal Framing ............................................................................. 1 only
09 30 00 Tiling ...................................................................................................................... 1 – 2
09 51 00 Acoustical Ceilings ................................................................................................. 1 – 2
09 64 00 Wood Flooring ....................................................................................................... 1 – 2
09 65 00 Resilient Flooring ................................................................................................... 1 – 3
09 67 00 Fluid Applied Flooring ............................................................................................ 1 – 2
09 68 00 Carpet .................................................................................................................... 1 – 4
09 69 00 Access Floor ........................................................................................................ 1 only
09 90 00 Painting and Coating .............................................................................................. 1 – 6

Division 10 Specialties

10 00 10 Special Room Requirements ................................................................................. 1 – 8


10 14 00 Room Numbering................................................................................................... 1 – 2
10 14 01 Door Numbering .................................................................................................... 1 – 2
10 14 05 Sign Standards and Guidelines .......................................................................... 1 only
10 20 00 Interior Specialties ................................................................................................. 1 – 2
10 21 13 Toilet Compartments ............................................................................................. 1 – 2
10 28 00 Toilet, Bath, and Laundry Accessories .................................................................. 1 – 3
10 44 00 Fire Protection Specialties ................................................................................... 1 only

Division 11 Equipment

11 53 13 Fume Hoods and Biological Safety Cabinets......................................................... 1 – 5


11 53 33 Emergency Safety Appliances ............................................................................... 1 – 2
11 60 00 Cranes and Hoists ............................................................................................... 1 only
11 81 29 Facility Fall Protection ............................................................................................ 1 – 4
11 82 00 Waste Handling Equipment ................................................................................... 1 – 2

Division 12 Furnishings

12 00 00 Furnishings ............................................................................................................ 1 – 3
12 20 00 Window Coverings and Blinds ............................................................................. 1 only
12 30 00 Fabricated Casework ........................................................................................... 1 only

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>
RfT#201xxxxxxx Section 00 01 10
Project No. <Insert #> TABLE OF CONTENTS
<Insert Project Title> PAGE 4 OF 7

12 35 53 Laboratory Casework ............................................................................................. 1 – 3

Division 14 Conveying Equipment

14 20 00 Elevators .............................................................................................................. 1 – 14
14 40 00 Lifts ...................................................................................................................... 1 only

Division 20 Mechanical – General Requirements

20 00 05 Mechanical – General Requirements .................................................................... 1 – 6


20 00 06 Meters .................................................................................................................. 1 only
20 00 07 Salvage of Existing Mechanical Equipment ......................................................... 1 only
20 00 08 Mechanical Identification........................................................................................ 1 – 4
20 00 30 Indoor Thermal Environment ................................................................................. 1 – 3

Division 21 Fire Suppression

21 05 00 Fire Protection – General Requirements ............................................................... 1 – 6


21 12 00 Fire–Suppression Standpipes ................................................................................ 1 – 2
21 13 13 Sprinkler Systems .................................................................................................. 1 – 2
21 21 00 Carbon–Dioxide Fire–Extinguishing Systems ........................................................ 1 – 3
21 22 00 Total Flooding Discharge Systems ...................................................................... 1 only
21 23 00 Wet–Chemical Fire–Extinguishing Systems .......................................................... 1 – 2
21 24 00 Dry–Chemical Fire–Extinguishing Systems ........................................................... 1 – 2
21 30 00 Fire Pumps ............................................................................................................ 1 – 2

Division 22 Plumbing

22 05 00 Plumbing – General Requirements ........................................................................ 1 – 3


22 11 00 Facility Water Distribution ...................................................................................... 1 – 3
22 11 18 Backflow/Cross Connection Control ...................................................................... 1 – 2
22 13 00 Facility Sanitary Drainage ...................................................................................... 1 – 2
22 14 00 Facility Storm Drainage........................................................................................ 1 only
22 15 00 Compressed Air Systems ...................................................................................... 1 – 2
22 30 00 Domestic Water Heaters ..................................................................................... 1 only
22 35 00 Plumbing Equipment .............................................................................................. 1 – 2
22 40 00 Plumbing Fixtures .................................................................................................. 1 – 4
22 60 00 Specialty Piping Systems ....................................................................................... 1 – 2

Division 23 Heating, Ventilating, and Air Conditioning (HVAC)

23 05 00 HVAC – General Requirements ............................................................................. 1 – 4


23 21 00 Hydronic Systems -Piping and Equipment............................................................. 1 – 5
23 22 00 Steam Systems – Piping, Insulation and Equipment ............................................. 1 – 3

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>
RfT#201xxxxxxx Section 00 01 10
Project No. <Insert #> TABLE OF CONTENTS
<Insert Project Title> PAGE 5 OF 7

23 30 00 Air Systems – Ductwork and Equipment .............................................................. 1 – 3


23 38 00 Fumehood, Lab and Contaminated Exhaust Systems .......................................... 1 – 4
23 60 00 Refrigeration Systems............................................................................................ 1 – 2

Division 25 Building Management Systems

25 05 00 Building Management Systems (BMS) Design Guidelines .................................. 1 - 86

Division 26 Electrical

26 05 00 Electrical – General Requirements ........................................................................ 1 – 2


26 05 01 Design Development Documents .......................................................................... 1 – 2
26 05 02 Installation Methods and Requirements .............................................................. 1 only
26 05 03 Primary Power Systems ....................................................................................... 1 only
26 05 04 Protective Device Coordination and Arc Flash Analysis ...................................... 1 only
26 05 05 High Voltage Cables .............................................................................................. 1 – 3
26 05 06 Standard Drawings ................................................................................................ 1 – 2
26 05 13 Wires and Cables (0–1000V)............................................................................... 1 only
26 05 26 Grounding and Bonding ....................................................................................... 1 only
26 05 48 Vibration and Seismic Controls for Electrical Systems ........................................ 1 only
26 05 53 Labeling ................................................................................................................. 1 – 2
26 08 00 Commissioning of Electrical Systems .................................................................... 1 – 5
26 10 00 Secondary Power Distribution ................................................................................ 1 – 2
26 11 13 Primary Unit Substations ..................................................................................... 1 – 14
26 12 00 Medium–Voltage Transformers ............................................................................. 1 – 5
26 27 13 Metering ................................................................................................................. 1 – 2
26 30 00 Emergency and Standby Power............................................................................. 1 – 4
26 51 00 Interior Building Lighting ........................................................................................ 1 – 5
26 56 00 Exterior Lighting ..................................................................................................... 1 – 2

Division 27 Communications

27 05 00 Communications Overview .................................................................................... 1 – 4


27 05 01 Basic Requirements ............................................................................................... 1 – 4
27 05 02 Administration ........................................................................................................ 1 – 8
27 05 03 Site Requirements ................................................................................................. 1 – 3
27 05 04 Construction Safety.............................................................................................. 1 only
27 05 05 Communication Rooms Design Guidelines ........................................................... 1 – 7
27 05 06 Communications Services ..................................................................................... 1 – 3
27 05 07 Firestopping ........................................................................................................... 1 – 4
27 05 08 Cable Infrastructure Design Guidelines ............................................................... 1 – 13
27 05 09 Warranty ................................................................................................................ 1 – 2
27 05 26 Bonding and Grounding for Communications Systems ......................................... 1 – 4

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>
RfT#201xxxxxxx Section 00 01 10
Project No. <Insert #> TABLE OF CONTENTS
<Insert Project Title> PAGE 6 OF 7

27 05 28 Pathways for Communications Systems ............................................................. 1 – 12


27 05 53 Identification for Communications Systems ........................................................... 1 – 5
27 08 00 Testing of Fibre and Copper Communications Cables .......................................... 1 – 5
27 13 00 Communications Backbone Cabling ...................................................................... 1 – 3
27 15 00 Communications Horizontal Cabling ...................................................................... 1 – 5
27 21 33 Data Communications Wireless Access Points ..................................................... 1 – 6
27 40 00 Audio-Video Infrastructure ..................................................................................... 1 – 5
27 41 16 Integrated Audio–Video Systems and Equipment ................................................. 1 – 3
27 41 16.11 Audio Systems and Equipment ............................................................................ 1 – 13
27 41 16.12 Video Systems and Equipment ............................................................................ 1 – 18
27 41 16.13 Control Systems and Equipment ........................................................................... 1 – 6
27 41 51 Lecture Capture Systems ...................................................................................... 1 – 2
27 41 52 Listening Assist Systems ....................................................................................... 1 – 4
27 53 13 Clock Systems ..................................................................................................... 1 only

Division 28 Electronic Safety and Security

28 05 00 Access Services: General Standards .................................................................... 1 – 7


28 13 00 Access Control ....................................................................................................... 1 – 4
28 16 00 Intrusion Detection ................................................................................................. 1 – 5
28 20 00 Electronic Surveillance........................................................................................... 1 – 3
28 31 00 Fire Detection and Alarm ....................................................................................... 1 – 4

Division 31 Earthwork

31 22 00 Grading ................................................................................................................ 1 only

Division 32 Exterior Improvements

32 00 10 Landscaping Design Requirements ..................................................................... 1 only


32 00 13 Integrated Pest Management .............................................................................. 1 only
32 00 15 Crime Prevention Through Environmental Design (CPTED) ............................... 1 only
32 01 90 Operation and Maintenance of Planting................................................................. 1 – 5
32 01 93.01 Tree and Shrub Preservation ................................................................................. 1 – 5
32 10 00 Bases, Ballasts, and Paving ................................................................................ 1 only
32 14 00 Unit Paving ........................................................................................................... 1 only
32 33 00 Site Furnishings ................................................................................................... 1 only
32 80 00 Irrigation ................................................................................................................. 1 – 7
32 91 00 Planting Preparation .............................................................................................. 1 – 6
32 92 00 Turf and Grasses ................................................................................................... 1 – 7
32 92 23 Sodding .................................................................................................................. 1 – 5
32 93 00 Plants ................................................................................................................... 1 – 11
32 93 05 Relocation of Existing Plant Material ..................................................................... 1 – 6

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>
RfT#201xxxxxxx Section 00 01 10
Project No. <Insert #> TABLE OF CONTENTS
<Insert Project Title> PAGE 7 OF 7

Division 33 Utilities

33 00 10 Underground Utilities Services............................................................................... 1 – 5


33 01 30.41 Cleaning of Sewers .............................................................................................. 1 only
33 10 00 Water Utilities ......................................................................................................... 1 – 7
33 30 00 Sanitary Sewerage Utilities .................................................................................... 1 – 6
33 49 00 Storm Energy Structures........................................................................................ 1 – 6
33 51 00 Natural Gas Distribution ......................................................................................... 1 – 4
33 61 00 District Hot Water Energy Distribution ................................................................. 1 – 19
33 63 00 Steam Energy Distribution ..................................................................................... 1 – 4
33 71 00 Electrical Utility Transmission and Distribution ...................................................... 1 – 2
33 71 19 Electrical Underground Ducts and Manholes ........................................................ 1 – 3
33 82 01 Communications Distribution Inspection.............................................................. 1 only

APPENDICES

Appendix A: UBC HS & E Asbestos Hazard Assessment Memo

LIST OF DRAWINGS (include Revision No.)

The University of British Columbia Date UBC Technical Guidelines Updated: May 2019
Technical Guidelines Date Modified for Project No. <Insert #>:<Insert date>

Das könnte Ihnen auch gefallen