ONE MONTH LOOK AHEAD - MARCH 2019

ID Task Name Duration Start Finish Predecessors Successors Mar '19 Apr '19
24 3 10 17 24 31
1 RIVER OF LIFE 1C1D ‐ EOT PROGRAMME 2 1009 days 1/12/16 18/3/20
3 PRELIMINARIES & GENERAL ITEMS 1009 days 1/12/16 18/3/20
21 CONDITION OF CONTRACT 1002 days 9/12/16 18/3/20
31 As‐Built Drawings 312 days 1/3/19 18/3/20
33 Lorong TAR 6 days 1/3/19 7/3/19 208FF 1295
39 COMBINED RECURRING PRELIM ITEM IN BQ 897 days 1/12/16 1/11/19
67 Preliminaries works / Recurring Activities 1 day 1/3/19 1/3/19
76 PACKAGE 1D 853 days 1/6/17 18/3/20
77 JALAN TAR 683 days 1/6/17 21/8/19 32FF
78 HARDSCAPE WORKS 683 days 1/6/17 21/8/19
144 ELECTRICAL WORKS 25 days 1/3/19 29/3/19
145 Cabling pulling works 21 days 1/3/19 25/3/19
146 Dang Wangi ‐ Lorong TAR 7 3 days 1/3/19 4/3/19 147,154
147 Lorong TAR 7 ‐ Lorong Bunus 6 3 days 5/3/19 7/3/19 146 148,155
148 Lorong Bunus 6 ‐ Lorong TAR 5 3 days 8/3/19 11/3/19 147 149,156
149 Lorong TAR 5 ‐ Coliseum 3 days 12/3/19 14/3/19 148 150,157
150 Coliseum ‐ Lorong TAR 3 3 days 15/3/19 18/3/19 149 151,158
151 Lorong TAR 3 ‐ Jalan Melayu 3 days 19/3/19 21/3/19 150 152,159
152 Jalan Melayu ‐ Jalan Tun Perak 3 days 22/3/19 25/3/19 151 160
153 Installation of electrical pole 20 days 5/3/19 27/3/19
154 Dang Wangi ‐ Lorong TAR 7 2 days 5/3/19 6/3/19 146 162
155 Lorong TAR 7 ‐ Lorong Bunus 6 2 days 8/3/19 9/3/19 147 163
156 Lorong Bunus 6 ‐ Lorong TAR 5 2 days 12/3/19 13/3/19 148 164
157 Lorong TAR 5 ‐ Coliseum 2 days 15/3/19 16/3/19 149 165
158 Coliseum ‐ Lorong TAR 3 2 days 19/3/19 20/3/19 150 166
159 Lorong TAR 3 ‐ Jalan Melayu 2 days 22/3/19 23/3/19 151 167
160 Jalan Melayu ‐ Jalan Tun Perak 2 days 26/3/19 27/3/19 152 168
161 Installation of light fitting 20 days 7/3/19 29/3/19
162 Dang Wangi ‐ Lorong TAR 7 2 days 7/3/19 8/3/19 154 207,184
163 Lorong TAR 7 ‐ Lorong Bunus 6 2 days 11/3/19 12/3/19 155 207,185
164 Lorong Bunus 6 ‐ Lorong TAR 5 2 days 14/3/19 15/3/19 156 207,186
165 Lorong TAR 5 ‐ Coliseum 2 days 18/3/19 19/3/19 157 207,187
166 Coliseum ‐ Lorong TAR 3 2 days 21/3/19 22/3/19 158 207,188
167 Lorong TAR 3 ‐ Jalan Melayu 2 days 25/3/19 26/3/19 159 207,189
168 Jalan Melayu ‐ Jalan Tun Perak 2 days 28/3/19 29/3/19 160 207,190
183 SIGNAGES 19 days 9/3/19 30/3/19
184 Dang Wangi ‐ Lorong TAR 7 1 day 9/3/19 9/3/19 162 207,185
185 Lorong TAR 7 ‐ Lorong Bunus 6 1 day 13/3/19 13/3/19 163,184 207,186
186 Lorong Bunus 6 ‐ Lorong TAR 5 1 day 16/3/19 16/3/19 164,185 207,187
187 Lorong TAR 5 ‐ Coliseum 1 day 20/3/19 20/3/19 165,186 207,188
188 Coliseum ‐ Lorong TAR 3 1 day 23/3/19 23/3/19 166,187 207,189
189 Lorong TAR 3 ‐ Jalan Melayu 1 day 27/3/19 27/3/19 167,188 207,190
190 Jalan Melayu ‐ Jalan Tun Perak 1 day 30/3/19 30/3/19 168,189 207
208 LORONG TAR 547 days 1/6/17 7/3/19 33FF
295 FURNITURE & FIXTURE 6 days 1/3/19 7/3/19
296 Bin Type 02 6 days 1/3/19 7/3/19 257 299
297 Bollard 6 days 1/3/19 7/3/19 257 299
298 SIGNAGES 6 days 1/3/19 7/3/19 257 299
299 Completion of Lorong TAR 0 days 7/3/19 7/3/19 296,297,298,287,282 561 7/3
300 JALAN MASJID INDIA 304 days 28/1/19 8/2/20 34FF
301 HARDSCAPE WORKS 278 days 28/1/19 6/1/20
302 Lorong Bunus 6 ‐ Lorong TAR 5 (80m) 62 days 28/1/19 12/4/19
304 Laying Services Ducting & Piping works (M&E) 24 days 9/2/19 8/3/19 303SS+8 days 305SS+12 days,306FF
305 Kerb construction 24 days 23/2/19 22/3/19 304SS+12 days 306FF+18 days
306 Paving works 30 days 9/3/19 12/4/19 305FF+18 days,303FF,3311FF,334,308
400 JALAN BUNUS 619 days 1/3/18 18/3/20 35FF
401 HARDSCAPE WORKS 597 days 1/3/18 21/2/20
409 Boardwalk 170 days 2/1/19 31/7/19
411 RC slab construction 30 days 31/1/19 9/3/19 410SS+24 days 412SS+24 days,414FF
415 Lorong Bunus 1 128 days 16/1/19 24/6/19
417 Laying Services Ducting & Piping works (M&E) 30 days 31/1/19 9/3/19 416SS+12 days 419SS+24 days,420FF
418 Kerb construction 30 days 31/1/19 9/3/19 416SS+12 days 420FF
419 Slab construction 77 days 4/3/19 4/6/19 417SS+24 days 420FF+6 days
433 ELECTRICAL WORKS 336 days 29/1/19 18/3/20
434 Street lighting footing 313 days 29/1/19 20/2/20
440 Cabling pulling works 304 days 15/2/19 24/2/20
446 Installation of electrical pole 303 days 22/2/19 29/2/20
452 Installation of light fitting 301 days 28/2/19 4/3/20
453 Jalan Medan Bunus 3 days 28/2/19 2/3/19 447 454,462,473
461 SOFTSCAPE 304 days 4/3/19 11/3/20
462 Jalan Medan Bunus 6 days 4/3/19 9/3/19 453 487
472 SIGNAGES 304 days 4/3/19 11/3/20
473 Jalan Medan Bunus 6 days 4/3/19 9/3/19 453 487
488 ANCILLARY BUILDINGS AT PACKAGE 1D 643 days 2/10/17 11/11/19
498 Food Court 474 days 2/10/17 13/4/19
502  Part A ‐ Food Court block 402 days 25/12/17 13/4/19
509  Facade screen installation 24 days 11/3/19 6/4/19 508FS‐16 days 510
511  Part B ‐ Toilet block 393 days 25/12/17 3/4/19
518  Architectural 136 days 26/9/18 9/3/19
519 Toilet 136 days 26/9/18 9/3/19
523  Painting 7 days 2/3/19 9/3/19 522 539
524 Stall 124 days 9/10/18 8/3/19
528 Painting 6 days 2/3/19 8/3/19 527
529  Mechanical & Electrical 143 days 12/10/18 3/4/19
530  Connection to existing utilities 7 days 27/3/19 3/4/19 538,534 539

Page 1
ONE MONTH LOOK AHEAD - MARCH 2019
ID Task Name Duration Start Finish Predecessors Successors Mar '19 Apr '19
24 3 10 17 24 31
531  Electrical 136 days 12/10/18 26/3/19
533  Cabling works 14 days 2/3/19 18/3/19 532,526 534
534  Installation of fixture and fitting 7 days 19/3/19 26/3/19 533 530
535  Water and Sewerage 122 days 12/10/18 9/3/19
538  Installation of fixture and fitting 7 days 2/3/19 9/3/19 537 530
550 Canopy at Jalan Masjid India 164 days 17/12/18 8/7/19
551 Engineering 90 days 17/12/18 8/4/19
562 PACKAGE 1C 651 days 1/9/17 18/10/19
563 DATARAN MERDEKA 559 days 1/9/17 27/6/19 36FF
591 SECTION C 311 days 18/6/18 27/6/19
592 Section C (Zone A) 287 days 18/6/18 28/5/19
593 Hardscape Works 275 days 18/6/18 11/5/19
595 Laying services ducting & piping works (M&E) 30 days 20/11/18 26/3/19 594FS+21 days 596FS‐21 days,641FS‐2
596 Construction of Slab 30 days 2/3/19 5/4/19 595FS‐21 days 597
604 Section C (Zone B) 143 days 22/10/18 12/4/19
605 Hardscape Works 131 days 22/10/18 29/3/19
609 Paving works 24 days 2/3/19 29/3/19 608FF+18 days 611FF,614,615
610 Electrical Works 18 days 23/3/19 12/4/19
611 Street lighting footing 6 days 23/3/19 29/3/19 609FF 612
612 Cable pulling works 6 days 30/3/19 5/4/19 611 613
614 Softscape 10 days 30/3/19 10/4/19 609 677
615 Furniture and fixture 10 days 30/3/19 10/4/19 609 677
616 Section C (Zone C) 139 days 23/11/18 11/5/19
617 Hardscape Works 127 days 23/11/18 26/4/19
620 Construction of Slab 24 days 2/3/19 29/3/19 619 621
621 Paving works 24 days 30/3/19 26/4/19 620 623FF,626,627
628 Section C (Zone D) 169 days 9/11/18 4/6/19
629 Hardscape Works 157 days 9/11/18 18/5/19
631 Laying services ducting & piping works (M&E) 18 days 2/3/19 22/3/19 630 632
632 Construction of Slab 24 days 23/3/19 19/4/19 631 633
640 Water feature ‐ City Library Plaza 168 days 1/12/18 27/6/19
642 RC footing construction 24 days 2/3/19 29/3/19 641 643
643 RC slab construction 18 days 30/3/19 19/4/19 642 644SS+6 days
649 SECTION D 96 days 2/3/19 27/6/19
650 Hardscape Works (Zone A) 54 days 2/3/19 4/5/19
651 Demolition/relocation of existing structure 18 days 2/3/19 22/3/19 652SS+12 days
652 Laying Services Ducting & Piping works (M&E) 18 days 16/3/19 5/4/19 651SS+12 days 653SS+6 days,656SS+12
653 Construction of Slab & Planter Wall 24 days 23/3/19 19/4/19 652SS+6 days 654FF+12 days,666
655 Hardscape Works (Zone B) 48 days 30/3/19 28/5/19
656 Demolition/relocation of existing structure 18 days 30/3/19 19/4/19 652SS+12 days 657SS+12 days
678 JALAN TUN PERAK 608 days 2/10/17 28/9/19 37FF
704 HARDSCAPE WORKS ‐ Left Side 392 days 1/2/18 11/5/19
735 Maybank ‐ 3 Junction Pudu 60 days 2/3/19 11/5/19
736 Demolition/relocation of existing structure 18 days 2/3/19 22/3/19 722,716,734 737SS+6 days,740FF,86
737 Laying Services Ducting & Piping works (M&E) 18 days 9/3/19 29/3/19 736SS+6 days 738SS+12 days,740FF
738 Kerb construction 12 days 23/3/19 5/4/19 737SS+12 days 739,740FF
741 HARDSCAPE WORKS ‐ Right Side 497 days 2/10/17 11/5/19
748 Jalan Melayu ‐ Jalan Melaka 170.4 days 15/8/18 8/3/19
753 Paving works 18 days 6/11/18 8/3/19 749FF,750FF,751FF,752777FF,844
766 Jalan Tun HS Lee ‐ Jalan Raja Chulan 134 days 1/10/18 12/3/19
771 Paving works 18 days 28/11/18 12/3/19 767FF,768FF,769FF,770777FF,847,781
772 Jalan Raja Chulan‐ 3 Junction Pudu 60 days 2/3/19 11/5/19
773 Demolition/relocation of existing structure 18 days 2/3/19 22/3/19 747 774SS+6 days,777FF
774 Laying Services Ducting & Piping works (M&E) 18 days 9/3/19 29/3/19 773SS+6 days 775SS+12 days,777FF
775 Kerb construction 12 days 23/3/19 5/4/19 774SS+12 days 776,777FF
778 ELECTRICAL WORKS 82 days 30/11/18 12/3/19
824 Installation of feeder pillar 9 days 2/3/19 12/3/19
825 Cable Pulling 3 days 2/3/19 5/3/19 786 826
826 Installation of Feeder pillar 6 days 6/3/19 12/3/19 825 878
827 SOFTSCAPE 428 days 25/12/17 15/5/19
835 Left Side 323 days 26/4/18 15/5/19
837 Jalan Melayu ‐ Jalan Melaka 3 days 2/3/19 5/3/19 716 878
838 Jalan Melaka ‐ Leboh Ampang 3 days 2/3/19 5/3/19 722 878
842 Right Side 428 days 25/12/17 15/5/19
844 Jalan Melayu ‐ Jalan Melaka 3 days 8/3/19 12/3/19 753 878
845 Jalan Melaka ‐ Leboh Ampang 3 days 2/3/19 5/3/19 759 878
847 Jalan Tun HS Lee ‐ Jalan Raja Chulan 3 days 13/3/19 15/3/19 771 878
849 FURNITURE & FIXTURE 271 days 25/9/18 21/8/19
851 Fence 30 days 2/3/19 5/4/19 816FF,823FF 878
852 Tree Grate 30 days 2/3/19 5/4/19 816FF,823FF 878
853 Bollard 30 days 2/3/19 5/4/19 816FF,823FF 878
879 JALAN TUN TAN CHIN LOCK 444 days 1/5/18 18/10/19 38FF
880 HARDSCAPE ‐ LEFT SIDE OF TTCL 397 days 1/5/18 21/8/19 983FS‐20 days
893 Jalan Petaling ‐ Jalan Tun HS Lee 122 days 1/11/18 29/3/19
897 Slab construction 24 days 24/12/18 15/3/19 896SS+18 days 898FF+12 days,1003,10
898 Paving works 24 days 2/3/19 29/3/19 894FF,895FF,896FF,897904FF,946
899 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 91 days 11/12/18 2/4/19
903 Slab construction 18 days 2/2/19 12/3/19 902SS+18 days 904
904 Paving works 18 days 13/3/19 2/4/19 900FF,901FF,902FF,903910FF,947,906
911 HARDSCAPE ‐ RIGHT SIDE OF TTCL 422 days 21/5/18 12/10/19 989FS‐20 days
924 Jalan Petaling ‐ Jalan Tun HS Lee 136 days 13/11/18 26/4/19
928 Slab construction 24 days 2/3/19 29/3/19 927SS+18 days 929
929 Paving works 24 days 30/3/19 26/4/19 925FF,926FF,927FF,928935FF,966
930 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 104 days 20/12/18 26/4/19
934 Slab construction 18 days 2/3/19 22/3/19 933SS+18 days 935

Page 2
ONE MONTH LOOK AHEAD - MARCH 2019
ID Task Name Duration Start Finish Predecessors Successors Mar '19 Apr '19
24 3 10 17 24 31
942 ELECTRICAL WORKS ‐ LEFT SIDE OF TTCL 229 days 27/11/18 6/9/19
943 Cable Pulling 221 days 27/11/18 26/8/19
945 Jalan Tun Tan Siew Sin ‐ Jalan Petaling  4 days 2/3/19 6/3/19 892,944 951,946
949 Installation of pole 149 days 2/3/19 30/8/19
950 Jalan Pudu ‐ Jalan Tun Tan Siew Sin 4 days 2/3/19 6/3/19 944 951,956
951 Jalan Tun Tan Siew Sin ‐ Jalan Petaling  4 days 7/3/19 11/3/19 945,950 952,957
955 Installation of light fitting 149 days 7/3/19 6/9/19
956 Jalan Pudu ‐ Jalan Tun Tan Siew Sin 4 days 7/3/19 11/3/19 950 957
957 Jalan Tun Tan Siew Sin ‐ Jalan Petaling  4 days 12/3/19 15/3/19 951,956 958
962 ELECTRICAL WORKS ‐ RIGHT SIDE OF TTCL 276 days 13/11/18 18/10/19
963 Cable Pulling 268 days 13/11/18 9/10/19
964 3 Junction Jalan Pudu ‐ Jalan Tun Tan Siew Sin 4 days 2/3/19 6/3/19 917 970
969 Installation of pole 267 days 19/11/18 14/10/19
970 3 Junction Jalan Pudu ‐ Jalan Tun Tan Siew Sin 4 days 7/3/19 11/3/19 964 976
975 Installation of light fitting 267 days 23/11/18 18/10/19
976 3 Junction Jalan Pudu ‐ Jalan Tun Tan Siew Sin 4 days 12/3/19 15/3/19 970 1019
1002 ROAD RAMP CROSSING 42 days 16/3/19 4/5/19
1003 Petaling Street entrance 30 days 16/3/19 19/4/19 897 1004
1005 ROAD RESURFACING WORKS 50 days 16/3/19 14/5/19
1006 Left side of road 25 days 16/3/19 13/4/19
1007 Jalan Pudu ‐ Jalan Tun Tan Siew Sin 5 days 16/3/19 21/3/19 897 1008
1008 Jalan Tun Tan Siew Sin ‐ Jalan Petaling  5 days 22/3/19 27/3/19 1007 1009
1009 Jalan Petaling ‐ Jalan Tun HS Lee 5 days 28/3/19 2/4/19 1008 1010
1020 ANCILLARY BUILDINGS AT PACKAGE 1C 430 days 2/4/18 30/8/19
1021  Cafe at Jalan Tun Perak 345 days 2/4/18 16/5/19
1030 Architectural works 139 days 27/11/18 15/5/19
1033 Ceiling installation 7 days 2/3/19 9/3/19 1032 1034
1034 Installation of internal cladding 14 days 11/3/19 26/3/19 1033 1035
1035 Installation of glass wall 14 days 27/3/19 11/4/19 1034 1036
1039 Mechanical & Electrical 125 days 13/12/18 15/5/19
1040 Electrical works 125 days 13/12/18 15/5/19
1042 Installation of distribution board & meter 21 days 2/3/19 26/3/19 1041 1043
1043 Installation of light fitting 21 days 27/3/19 19/4/19 1042 1044
1045 Mechanical works 90 days 13/12/18 3/4/19
1046 Air Cooled Packaged Unit System 28 days 2/3/19 3/4/19
1047 Installation of ducting 14 days 2/3/19 18/3/19 1031 1048
1048 Installation of air cooled package unit system 7 days 19/3/19 26/3/19 1047 1049
1049 Conduit, Cabling and trunking works 7 days 27/3/19 3/4/19 1048 1064
1050 Water Reticulation & Sewerage Works 75 days 13/12/18 16/3/19
1052 Water storage  2 days 2/3/19 4/3/19 1051 1053
1053 Connection to water meter 2 days 5/3/19 6/3/19 1052 1054
1054 Marking, painting & labelling 2 days 7/3/19 8/3/19 1053 1055
1055 Testing and commisioning 7 days 9/3/19 16/3/19 1054 1064
1056 Sewerage works 66 days 13/12/18 6/3/19
1060 Installation of sanitary ware 3 days 2/3/19 5/3/19 1059 1061
1061 Testing and commisioning 1 day 6/3/19 6/3/19 1060 1064
1084 Bus Stop & Taxi stand at Jalan T.Tan Cheng Lock 430 days 2/4/18 30/8/19
1085 Bus Stop infront Kota Raya 302 days 2/4/18 26/3/19
1092  Installation of rail and bench 7 days 2/3/19 9/3/19 1091 1093
1093  Installation of boxup wall 14 days 11/3/19 26/3/19 1092
1094 Taxi stand ‐ 99 Speedmart 97 days 27/11/18 26/3/19
1101  Installation of rail and bench 7 days 2/3/19 9/3/19 1100 1102
1102  Installation of boxup wall 14 days 11/3/19 26/3/19 1101
1112 Kiosk at pocket park 73 days 2/3/19 29/5/19
1113 Excavation works 6 days 2/3/19 8/3/19 917 1114
1114 Construction of RC footing 18 days 9/3/19 29/3/19 1113 1115
1115 Installation of baseplate & steel column 12 days 30/3/19 12/4/19 1114 1116
1122 CONSTRUCTION OF INTERCEPTOR 914 days 5/1/17 28/12/19
1123 PRELIMINARIES 841 days 5/1/17 1/10/19
1129 Environmental Management Plan 505 days 1/2/18 1/10/19
1131 Monthly Monitoring Data 481 days 1/3/18 1/10/19
1144 Monthly Monitoring Data 13 1 day 1/3/19 1/3/19
1153 SULLAGE WATER TREATMENT PLANT 600 days 1/1/18 21/12/19
1176  Sub‐Structure 268 days 16/10/18 10/9/19
1177 Zone A (P1‐P72) 72 points 214 days 16/10/18 4/7/19
1179 Micropile for foundation 42 days 23/1/19 15/3/19 1178SS+7 days 1180,1183SS,1184
1182 Zone B (P72‐P117) 45 points 167 days 23/1/19 16/8/19
1184 Micropile for foundation  27 days 16/3/19 16/4/19 1183SS+7 days,1179 1185,1188
1241 PUMP SUMP 438 days 2/5/18 12/10/19
1242 Structure 231 days 1/10/18 9/7/19
1259 Piping Works 382 days 2/5/18 5/8/19