Afternoon Schedule:
Solution:
Manual mixing of concrete were applied to fill the remaining portion of the
concrete slab and beam.
Name: Marc Ryan B. Dumalag Date: April 9, 2019
DAILY PLAN
COMPLETED
TO DO; YES NO
1. Pouring of concrete beam and column located at the rear
part of the building.
2. Re-construct stair way landing ( including Electrical
materials)
3. Installing of stirrups at the continuous left side portion of
the 2nd floor.
4. Clearing of soil
5. Removing of scaffolding at the first 15 day cured slab
6. Installing of scaffolding at the remaining portion of slab
in the 2nd floor level.