Sie sind auf Seite 1von 4

Date: April 8, 2019

DAILY ACTIVITY REPORT


Prepared by:

Marc Ryan B. Dumalag


Name: Marc Ryan B. Dumalag Date: April 8, 2019

Duty Time: Monday – Saturday 8:00 am – 5:00 pm

Project Title: Three – Storey Residential Building

Daily Log of Activities


Morning Schedule:

No. of Persons, Time Activities


Duration
5 8:15-12:00 Sacking of Concrete component (Sand, Gravel, and
Cement)
4 8:15-9:05 Preparing of Concrete Mixer
1 8:45-9:05 Curing of Concrete slab and beam
4 9:15-10:15 Pouring and levelling Concrete mix in the slab and
beam in the 2nd floor level
1 9:15-10:15 Dowel Installer and Removal of beam forms
4 10:15-11:30 Manual Pouring and levelling Concrete mix in the
slab and beam in the 2nd floor level

Afternoon Schedule:

No. of Persons, Time Activities


Duration
4 1:00-2:00 Manual Pouring and levelling Concrete mix in the
slab and beam in the 2nd floor level
2 1:00-2:00 Removal of beam forms
2 1:30-5:00 Installing of beam forms
2 2:00-5:00 Clearing of soil in the ground floor level
1 2:00-5:00 Cutting of Bars for stirrups
1 3:00-5:00 Making a concrete Joist
Problem during the session:
 Mixer – lower bolts are loosened and machine disconnection.

Solution:

 Manual mixing of concrete were applied to fill the remaining portion of the
concrete slab and beam.
Name: Marc Ryan B. Dumalag Date: April 9, 2019

Duty Time: Monday – Saturday 8:00 am – 5:00 pm

Project Title: Three – Storey Residential Building

DAILY PLAN
COMPLETED
TO DO; YES NO
1. Pouring of concrete beam and column located at the rear
part of the building.
2. Re-construct stair way landing ( including Electrical
materials)
3. Installing of stirrups at the continuous left side portion of
the 2nd floor.
4. Clearing of soil
5. Removing of scaffolding at the first 15 day cured slab
6. Installing of scaffolding at the remaining portion of slab
in the 2nd floor level.

Das könnte Ihnen auch gefallen