CONSTRUCTION
PROJECT CONSTRUCTION/IMPROVEMENT OF DRAINAGE SYSTEM
LOCATION ESPANA BLVD
BILLING # 2
DATE AUG 2 - SEPT 17
AREA 3

ITEM WORK DESCRIPTION QUANTITY UNIT COST TOTAL COST ACCOMPLISHME


PREVIOUS
1 Construction of RCBC
a. Removal of Actual Structure 139.12 lm 65.00 9,042.80 51%
b. Removal of Actual Structure 119.20 sq.m. 260.00 30,992.00 28%
c. Structure Excavation, Common Soil 239 cu.m. 200.00 47,800.00 29%
d. Lean Concrete Class B 12.0 cu.m 2,200.00 26,400.00 24%
e. Reinforcing Steel, Grade 60 7138.85 kgs 5.00 35,684.25 14%
f. Structural Concrete Class A 95.47 cu.m. 5,700.00 544,179.00 16%

2 Construction of Sidewalks

3 Construction of Curbs & Gutter


a. Removal of Actual Structure/ Obstruction 304.26 l.m. 130.00 39,553.80 20%
Curb & Gutter
b. Aggregate Subbase Course 9.0 cu.m. 531.01 4,779.05 0%
c. Concrete Curb & Gutter Type A 256.26 l.m. 600.00 153,756.00 4%
d. Catch Basins 910mm 18.00 pcs 4,800.00 86,400.00 11%
e. Structure excavation, common soil 28.19 cu.m. 195.00 5,497.05 22%
f. Catch Basins with Curb Inlet 9.0 pcs 62,400.00 42%
g. Structure Excavation, Common Soil 187.92 cu.m. 185.00 34765.2 50%

Accomplished Amount
Less : Previous Accomplis
Current Accomplishmen

AMOUNT IN WORDS :One Hundred Ninety Six Thousand One Hundred Sixty Six Pesos and Sixty Five c

Submitted by :

EDUARDO V. QUINTOS IX
ACCOMPLISHMENT AMOUNT
PRESENT TO DATE

15% 66% 6,427.08


10% 38% 117.77
5% 34% 16,252.00
9% 33% 9,466.67
15% 29% 10,348.43
16% 32% 174,137.28

30% 50% 19,776.90

50% 50% 2,389.52


56% 60% 92,253.60
0% 11% 9,504.00
0% 22% 1,209.35
0% 42% 26,208.00
0% 50% 17,382.60

Accomplished Amount 385,473.20


ess : Previous Accomplishment 189,306.55
Current Accomplishment 196,166.65