Beruflich Dokumente
Kultur Dokumente
A
ELECTROMECHANICAL
METHOD OF STATEMENT
MECHANICAL
WORKS
2009
DUBAI
CONTENTS
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT – M 01
1.0 Purpose
To define the method of installation of underground pipe work.
2.0 Scope
This method is applicable for drainage pipe work below ground.
3.0 Method
3.1.1 Check the trench route to be made to ensure that the pipes
to be installed are as indicated on approved construction
drawings.
3.1.7 Lay the pipes as per the invert levels & slope mentioned in
the approved layout with proper supports, using the water
level & measuring tape with respect to the benchmark level.
3.1.10 Inspect the pipe work for leakage by gravity leakage test.
(by Consultant)
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
3.1.11 Make bedding up to the bottom level of the pipe with aggregate and
compact properly.
3.1.12 Cover the pipe (up to top level) with aggregate as per the
standards.
6.0 Safety
6.1.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves,
Goggles when necessary etc) to be worn all the times.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT –M 02
1.0 Purpose
This method of statement is to define the installation of Pipe work at high level.
2.0 Scope
This method of statement is applicable for installation of Pipe works at high level
for drainage pipe works.
3.1.2 Mark out the location of hanger thread rods for pipe installation
as per the approved construction drawing.
3.1.3 Drill the marked position for hangers and supports by using the drill bit
of appropriate size.
3.1.4 Fix the unfix anchor at drilled position by gentle and uniformly
hammering.
3.1.5 Fix the threaded rod of 6mm diameter appropriate size & length in the
anchor by twisting by turning.
3.1.6 After fixing the threaded rod, insert a 6mm diameter washer of
appropriate size in to the rod.
3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this
will improve the strength and load bearing capacity of threaded rod.
3.1.8 After cutting the pipes in the required length, both ends should be
chamfered properly to remove the unevenness and surface is made
rough using sand paper for length of 3 cm (approx) for good adhesive
surface preperations.
3.1.9 Install the pipe in position as per the approved layout and make the
end connection of pipes as standard specification for each service.
3.1.10 After completion of pipe end connection, fix / tight the support clamps
properly to make the pipe straight and level as per the layout.
3.1.11 Check the levels of pipe work with spirit levels and measuring tape.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
3.1.12 Pressure test and final inspection of the pipe work (by Consultant) as
per the testing philosophy ref.
7.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT –M 03
3.0 Purpose
This method of statement is to define the installation of Pipe work at high level.
4.0 Scope
This method of statement is applicable for installation of Pipe works at high level
for water supply pipe works.
3.1.13 Mark out the location of hanger thread rods for pipe installation
as per the approved construction drawing.
3.1.14 Drill the marked position for hangers and supports by using the drill bit
of appropriate size.
3.1.15 Fix the unfix anchor at drilled position by gentle and uniformly
hammering.
3.1.16 Fix the threaded rod of 6mm diameter appropriate size & length in the
anchor by twisting by turning.
3.1.17 After fixing the threaded rod, insert a 6mm diameter washer of
appropriate size in to the rod.
3.1.18 Finally fix the washer near to the slab by tightening a nut over it, this
will improve the strength and load bearing capacity of threaded rod.
3.1.19 After cutting the pipes in the required length, both ends should be
chamfered properly to remove the unevenness and surface is made
rough using sand paper for length of 3 cm (approx) for good adhesive
surface preparations.
3.1.20 Install the pipe in position as per the approved layout and make the
end connection of pipes as standard specification for each service.
3.1.21 After completion of pipe end connection, fix / tight the support clamps
properly to make the pipe straight and level as per the layout.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
3.1.22 Check the levels of pipe work with spirit levels and measuring tape.
3.1.23 Flow and Leakage test and final inspection of the pipe work (by
Consultant) as per the testing philosophy ref.
8.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT –M 04
5.0 Purpose
This method of statement is to define the installation of Pipe work at high level.
6.0 Scope
This method of statement is applicable for installation of Pipe works at high level
for fire fighting pipe works.
3.1.2 Mark out the location of hanger thread rods for pipe installation
as per the approved construction drawing.
3.1.3 Drill the marked position for hangers and supports by using the drill bit
of appropriate size.
3.1.4 Fix the unfix anchor at drilled position by gentle and uniformly
hammering.
3.1.5 Fix the threaded rod of 6mm diameter appropriate size & length in the
anchor by twisting by turning.
3.1.6 After fixing the threaded rod, insert a 6mm diameter washer of
appropriate size in to the rod.
3.1.7 Finally fix the washer near to the slab by tightening a nut over it, this
will improve the strength and load bearing capacity of threaded rod.
3.1.8 After cutting the pipes to the required length, if the diameter of the pipe
is less than 2.5 inch both ends should be threaded by using a
threading machine and for pipe diameter above 2.5 inch the pipes are
groove cut to the required depth as per the installation specification.
3.1.9 The pipes are connected to each other using a grooved coupler
as per the standard pipe installation procedure.
3.1.10 After completion of pipe end connection, fix / tight the support clamps
properly to make the pipe straight and level as per the layout.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
3.1.11 Check the levels of pipe work with spirit levels and measuring tape.
3.1.12 Flow and Leakage test and final inspection of the pipe work (by
Consultant) as per the testing philosophy ref.
9.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT M - 05
INSTALLATION OF DUCTING
1.0 Purpose
To define the method of installation of Ducting.
2.0 Scope
This method is applicable for Ducting.
3.1.2 Mark out the location of hanger thread rods for duct installation as
per the approved construction drawing.
3.1.3 Drill the marked position for hangers and supports by using the drill
bit of appropriate size.
3.1.4 Fix the unfix anchor at drilled position by gentle and uniform
hammering.
3.1.5 Fix the threaded rod of 6mm diameter & length in the anchor by
twisting.
3.1.6 After fixing the threaded rod of 6mm diameter, insert a washer of
appropriate size in to the rod.
3.1.7 Finally fix the washer near to the slab by tightening a nut over it,
this will improve the strength and load bearing capacity of threaded
rod.
3.1.8 Fix all the duct pieces from the mouth of the unit
3.1.9 Joint all the ducts using flanges or cleats and corners.
3.1.12 Dip the canvas cloths in Foster and fostering all the ducts in case of
GI duct
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
4.0 Inspection and Measuring Equipment Used
5.0 Safety
5.1.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves,
Goggles when necessary etc) to be worn all the times.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT M - 06
1.0 Purpose
To define the method of installation of Copper piping
2.0 Scope
This method is applicable for installation of Copper piping and DX-AHU.
3.0 Method
3.3 Fix the Vibration isolators (RIBBED RUBBER PADS) for AHU on
Plinth.
3.6 Install the Copper pipes from AHU to Condenser Units as per the
approved layout using flare nuts as brazing as per the unit specification
and manufacturers recommendation.
3.7 Expansion valve, sight glass Dryer and filter are installed on liquid line
3.8 Control valve and sight glass are installed on suction line.
3.9 Pressure testing and flushing to be carried out prior to vacuum suction.
3.12 Insulation is wrapped around the copper piping and further wrapped with
6oz cloth and Childers.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
4.0 Reference documents
4.2 Pressure Gauge, Brazing set, pipe cutter and pipe bender.
6.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT M - 07
1.0 Purpose
To define the method of installation of Copper piping
2.0 Scope
This method is applicable for installation of Copper piping for decorative wall
mounted unit.
3.0 Method
3.1 Check the plinth for the outdoor unit is of required size.
3.3 Fix the Vibration isolators (RIBBED RUBBER PADS) for outdoor on
Plinth..
3.6 Install the Copper pipes from the Condenser Units as per the
approved layout using flare nuts and brazing as per the unit
specification and manufacturers recommendation.
3.8 Pressure testing and flushing to be carried out prior to vacuum suction.
3.13 Insulation is wrapped around the copper piping and further wrapped with
6oz cloth and Childers.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
4.0 Reference documents
4.3 Pressure Gauge, Brazing set, pipe cutter and pipe bender.
6.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT M - 08
1.0 Purpose
To define the method of installation of Booster pump
2.0 Scope
This method is applicable for installation of Booster pump.
3.0 Method
3.1 Check the plinth for the Booster pump is of required size.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
6.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT M - 09
1.0 Purpose
To define the method of installation of Transfer pump
2.0 Scope
This method is applicable for installation of transfer pump.
3.0 Method
3.1 Check the plinth for the transfer pump is of required size.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
5.0 Inspection and Measuring Equipment Used
6.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT M - 10
1.0 Purpose
To define the method of installation of submersible pump
2.0 Scope
This method is applicable for installation of submersible pump.
3.0 Method
3.1 Check the support for the submersible pump is of proper size.
6.0 Safety
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
6.1Safety equipment (example Hard hats, Safety shoes, Coverall,
Gloves, Goggles when necessary etc) to be worn all the times.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
METHOD STATEMENT –M 11
1.0 Purpose
To define the method of installation and operation of fire hose reel pump.
2.0 Scope
This method is applicable for installation and operation of fire hose reel pump.
3.0 Method
3.2 Check the level of suction pipe line is to be below the level of
pump(suction header)
3.3 Check whether the required piping and valves are installed properly
3.4 Make sure that electrical panel for the pump is given correct power
supply with protection.
3.5 Load the pump on a strong foundation. Use the expansion bolts to the
base frame to the concrete foundation. The surface of the foundation
should be smooth and level. Ensure easy access to the unit from all sides
for maintenance and services.
3.6 Pump set is accurately aligned in the factory before dispatch. However it is
essential to recheck the alignment at site after fixing pump set on the site.
3.7 The pump set should be located near to the suction reservoir.
3.8 Fix the gate valves non return valves vibration protected flexible connector
etc and suction discharge manifolds as shown on the dawning.
3.9 Connect the suction and discharge line to the manifold .check whether all
joints are straight.
3.10 Fix the pressure switch and pressure gauge on the discharge header.
3.11 Fill the water in the pump and suction line through the priming valve and
remove all the air blocks.
3.12 Interconnecting wiring between the panel and motor diesel engine
pressure switches float switches for dry run protection etc should be done.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2
Panel, motors pressure switches and float switches must be grounded
with suitable wires.
3.13 Do the wiring from electrical supply source to the pump control panel.
3.14 Do the necessary piping between the fuel tank and diesel tank.
3.16 Keep starting point of electrical pump slightly higher than the starting point
of diesel pump. Keep starting point of jockey pump is slightly higher than
starting point of electrical pump.
6.0 Safety
6.1 Safety equipment (example Hard hats, Safety shoes, Coverall gloves,
Goggles when necessary etc) to be worn all the times.
A L R E YA M I E L E C T R O M E C H A N I C A L Page 2