NAME OF WORK: PROPOSED CONSTRUCTION OF R.C.C ROOFED RESIDENTIAL BUILDING IN R.

S NO:
9/13B AT 1/32, WEST STREET, PANANGUDI VILLAGE, NAGAPATTINAM TALUK AND DISTRICT.
ABSTACT ESTIMATE
SI.NO DESCRIPTION OF WORK QUANTITY RATE PER AMOUNT
EARTHWORK EXCAVATION OF HARD
1
GRAVEL SOIL 44 350 M3 15400.00
SAND FILLING FOR COLOUMN USING RIVER
2
SAND 28 800 M3 22400.00
P.C.C 1:5:10 USING HBG METAL FOR
3 FOUNDATION CONCRETE AND FLOORING
CONCRETE 17 2000 M3 34000.00
SUPPLYING AND FILLING THE BASEMENT
WITH WELL GRAVEL FILLING IN LAYERS NOT
4
MORE THAN 15CM THICK WELL RAMMED
WATER AND COMPACTED ETC.. 37 500 M3 18500.00
CENTRING FOR SOFFITS OF RCC SLAB OF
PLANE SURFACE LIKE LILNTELS,
5
BEAMS,ETC.., INCLUDING STRUTTING 3M
HIGH USING MILD STEEL 326 240 M2 78240.00
REINFORCED CEMENT CONCRETE 1:1.5:3
USING 20MM GAUGE HAND BROKEN
GRANITE STONES FOR ALL RCC ITEMS OF
WORKS EXCLUDING CENTERING
6 SHUTTERING AND COST OF
REINFORCEMENTS INCLUDING CURING
ETC..,COMPLETE AND ALSO INCLUDING
FIXING FAN CLAMPS AND FIXTURES IN RCC
WORKS WHEREVER NECESSARY. 36 5000 M3 180000.00
SUPPLYING AN11D FABRICATING AND
PLACING IN POSITION MS (OR) R.T.S BAR OF
REINFORCEMENT TO ALL R.C.C WORKS AS
7
PER THE DESIGN GIVEN INCLUDING COST OF
STEEL BINDING WIRE ALSO IN ALL FLOORS A
PER STANDARD SPECIFICATIONS. 3.7 52000 MT 192400.00
BRICK WORK IN C:M 1:5 (ONE CEMENT AND
FIVE SAND) USING II CLASS GROUND
MOULDED BRICKS OF SIZE 9"X43/8"X4"
8 STANDARD SPECIFICATION INCLUDING
FINISHING,CURING,ETC.., COMPLETE AS PER
COMPLYING WITH STANDARD
SPECITICATION. 59 2600 M3 153400.00

Cont’d with page 2


-2 -

WOOD WORK 40MM THICK DEODAR,


WORK FOR DOORS AND WINDOWS
9
COMPLETE IN ALL RESPECTS INCLUDING
FIXING IN POSITION. 20 3200 M2 64000.00
SPECIAL CEILING PLASTERING WITH
CEMENT MORTAR 1:3 (ONE CEMENT AND
THREE SAND) 10MM THICK INCLUDING ALL
10
COST AND COVEYANCE OF ALL MATERIALS
,FINISHING,CURING AND ALL LABOUR
CHARGES ETC.., 61 150 M2 9150.00
PLASTERING WITH CEMENT MORTAR 1:3
MIX (ONE CEMENT AND THREE
11 SAND)12MM THICK IN ALL FLOORS
INCLUDING COST AND CONVEYANCE OF ALL
MATERIALS TO SITE ETC.., 461 120 M2 55320.00
WHITE WSHING TWO COATS WIT FRESHLY
BURNT SHELL LIME WHITE IN ALL FLOORS
12 INCLUDING COSTS OF LIME AND OTHER
MATERIALS BRUSHES SCAFFOLDING
CHARGES ETC.., 461 100 M2 46100.00
PAINTING THREE COATS ON DOORS AND
WINDOWS ETC…, WITH BEST QUALITY
13
APPROVED PAINT AS PER STANDARD
SPECIFICTIONS 20 550 M2 11000.00
DADDOING WITH GLAZED TILES OF SIZE
600MM X 600MMX 6MM SIZE OF
APPROVED MAKE AND QUALITY AND
COLOUR SET IN CEMENT MORTAR 1:2 (ONE
14
CEMENT AND TWO SAND) OVER 10MM
BASE LAYER PLASTERING AND POINTING
WITH WHITE CEMENT NEATLY AS
DIRECTED. 52 1200 M2 62400.00
ELECTRIFICATIONS WORKS USING BEST
15 QUALITY WIRES AND CABLES AND
SWITCHES. …L.S… 90000.00
PLUMBING AND SANITARY FIXING
SUPPLY AND REPAIR OF EXISTING
16
PLUMBING LINE(INCLUDING W.C, WASH
BASIN, WALL MIXER) …L.S… 80000.00
17 MISCELLANEOUS WORKS …L.S… 30000.00
TOTAL 11,42,310.00

(ELEVEN LAKHS FORTY TWO THOUSAND THREE HUNDRED AND TEN ONLY)